Smart Home Technology GanttChart

The document outlines a project plan for a Smart Home Technology solution, starting on November 15, 2024, with various phases including requirements gathering, design, software and hardware development, integration, testing, and pilot deployment. Each phase consists of specific tasks with designated start and end dates, along with progress percentages. The plan emphasizes an Agile approach for software development and includes user feedback at multiple stages to refine the product.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views2 pages

Smart Home Technology GanttChart

The document outlines a project plan for a Smart Home Technology solution, starting on November 15, 2024, with various phases including requirements gathering, design, software and hardware development, integration, testing, and pilot deployment. Each phase consists of specific tasks with designated start and end dates, along with progress percentages. The plan emphasizes an Agile approach for software development and includes user feedback at multiple stages to refine the product.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

SMART HOME TECHNOLOGY SOLUTION PROJECT PLAN

Smart Home Technologies

Project Start Date 11/15/2024 (Friday) Display Week 3 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
Project Lead 25 Nov 2024 2 Dec 2024 9 Dec 2024 16 Dec 2024 23 Dec 2024 30 Dec 2024 6 Jan 2025 13 Jan 2025
25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS
1 Phase 1: Requirements Gathering and Ana - -
Define project scope and
1.1 [Name] Fri 11/15/24 Thu 11/21/24 7 100% 5
objectives
Conduct surveys and
1.2 interviews with potential Fri 11/22/24 Thu 12/05/24 14 60% 10
users

Compile a requirements
1.3 Fri 12/06/24 Thu 12/12/24 7 46% 5
document

Review and finalize


1.4 requirements with Fri 12/13/24 Thu 12/19/24 7 29% 5
stakeholders
2 Phase 2: Design and Prototyping - -
Create initial design
2.1 Fri 12/20/24 Mon 12/23/24 4 0% 2
mockups
Develop Prototype 1 with
2.2 core hardware and Mon 12/23/24 Sun 1/05/25 14 0% 10
software features
Gather feedback on
2.3 Mon 1/06/25 Sun 1/12/25 7 0% 5
Prototype 1 and revise
Build Prototype 2 with
2.4 enhanced features based Thu 1/02/25 Tue 1/07/25 6 0% 4
on feedback
Conduct user testing on
2.5 Wed 1/08/25 Tue 1/14/25 7 0% 5
Prototype 2
3 Phase 3: Software Development (Agile Spr - -
Plan and organize Agile
3.1 sprints for software Wed 1/15/25 Tue 1/21/25 7 0% 5
development

Develop key
functionalities in sprints,
3.2 Wed 1/22/25 Tue 3/04/25 42 0% 30
such as real-time
monitoring and alerts

Conduct sprint reviews


and adjust based on
3.3 Tue 2/11/25 Mon 2/24/25 14 0% 10
feedback (Concurrent
with sprints)

Finalize software after the


3.4 Wed 3/05/25 Mon 3/10/25 6 0% 4
final sprint
4 Phase 4: Hardware Development - -
Procure materials for
4.1 Tue 3/11/25 Mon 3/24/25 14 0% 10
hardware
Assemble and test
4.2 Tue 3/25/25 Mon 4/07/25 14 0% 10
hardware components
Perform integration
4.3 testing with initial Tue 4/08/25 Mon 4/14/25 7 0% 5
software build
Refine and finalize
4.4 Tue 4/15/25 Mon 4/21/25 7 0% 5
hardware components
5 Phase 5: Integration and Testing - -
Integrate hardware and
5.1 Tue 4/22/25 Mon 4/28/25 7 0% 5
software
Perform functional and
5.2 Tue 4/29/25 Mon 5/05/25 7 0% 5
usability testing
Project Start Date 11/15/2024 (Friday) Display Week 3 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10
Project Lead 25 Nov 2024 2 Dec 2024 9 Dec 2024 16 Dec 2024 23 Dec 2024 30 Dec 2024 6 Jan 2025 13 Jan 2025
25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
% WORK
WBS TASK LEAD START END DAYS M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DONE DAYS

Conduct user acceptance


5.3 testing (UAT) with a small Tue 5/06/25 Fri 5/09/25 4 0% 4
group

Make final adjustments


5.4 Sat 5/10/25 Mon 5/12/25 3 0% 1
based on UAT feedback

6 Phase 6: Pilot Deployment and Iteration - -


Deploy the MVP to a pilot
6.1 Tue 5/13/25 Fri 5/16/25 4 0% 4
group (1 week)