3.ELECT. - Method Statement

This Method Statement outlines the procedures and controls for the installation of PVC conduits, GI back boxes, and accessories in electrical works for Project No. 264R15. It details responsibilities, execution methods, inspection and testing protocols, and safety measures to ensure compliance with project specifications. The document also emphasizes the importance of quality assurance and safety practices throughout the installation process.

Uploaded by

waseem hallak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views5 pages

3.ELECT. - Method Statement

This Method Statement outlines the procedures and controls for the installation of PVC conduits, GI back boxes, and accessories in electrical works for Project No. 264R15. It details responsibilities, execution methods, inspection and testing protocols, and safety measures to ensure compliance with project specifications. The document also emphasizes the importance of quality assurance and safety practices throughout the installation process.

Uploaded by

waseem hallak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

METHOD STATEMENT Page 1 of 5

ELECT. WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-ELECT -01 HSE-DOCS-264R15 07.02.2024 00

METHOD STATEMENT FOR ELECT. WORK

Project No: 264R15

REVISION
ISSUE DATE DESCRIPTION REVIEW / STATUS
HISTORY
00 07.02.2024 ELECT. WORK

PREPARED BY: REVIEWED & APPROVED BY:


A.REFAI W.HALLAK

QA QC ENGINEER PROJECT MANGER

HSE Documents-Method Statement for ELECT Work


METHOD STATEMENT Page 2 of 5
ELECT. WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-ELECT -01 HSE-DOCS-264R15 07.02.2024 00

1. Purpose
The purpose of this Method Statement is to describe the details used and controls to
be carried out for the installation of PVC Conduits, GI Back Boxes and Accessories to
ensure that it complies to Project requirements, specifications and standards.
2. Scope
This Method Statement is applicable to all PVC conduits, GI back Boxes and accessories
at (JITHER) electrical works in slab, screed, wall and ceiling serving Lighting, Small
Power, Fire Alarm, Low Current, Intercom and Lightning Protection.
3. Definition
Abbreviation:
PVC - polyvinyl chloride
GI - Galvanized Iron
QAQC - Quality Assurance Quality Control
RFIA - Request for Inspection – Test
ITP - Inspection and Test Plan
TBT - Tool Box Talk
MSDS - Material Safety Data Sheet
A. Approved
Approved means approved in writing by the applicable Engineers Assistant acting
within the scope of their delegate authority.
B. Shop Drawings
means drawings produced where the contract designs drawings require
expressing in more basic form to facilitate construction.
C. Final Inspection
means the inspection of the records of works at completion or at completion
of pre-determined elements to ensure that all previous inspections and tests
have been satisfactorily carried out and properly recorded.
D. Materials
means all items covering the materials or equipments delivered to site that
must be incorporated in the project.
E. Method Statements
Method Statements (MOS) means a technical document to be read in
conjunction with the drawings, specification, standards and codes of practice,
technical data sheets, schedules, work instructions and any other technical
document related to a particular work.
4. Reference Documents – Specifications, Drawings. Etc.
• Project Quality Plan
• Project Specification

HSE Documents-Method Statement for ELECT Work


METHOD STATEMENT Page 3 of 5
ELECT. WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-ELECT -01 HSE-DOCS-264R15 07.02.2024 00

• Approved Shop Drawings


• Manufacturer Instruction
5. Responsibilities
• The Project Manager shall be responsible for the entire construction activities.
• The Construction Manager (CM) Site Engineers, Supervisors and Foremen shall
implement this Method Statement.
• The Material controller shall be accountable for receiving materials on site
warehouse.
• Site Engineer / Supervisor shall check the materials as per manufacture’s
recommendation prior to installation and shall be responsible for the
installation as per approved shop drawings.
6. Method of Execution or Application.
• Ensure that materials PVC Conduits, GI Back Boxes and Accessories – are store
as per manufacturer’s recommendation, procedures and project
specifications.
• Prior to material use, ensure that Materials Inspection Request (MIR) is raised
and approved.
• Ensure that the material is free from damages.
• Install the conduits as per approved Shop Drawings, Coordination Drawings
and Project Specifications. Comply with specifications on support installation
to prevent from sagging. Any changes in the routing shall be RED LINED in
approved Shop Drawings and changes shall be reflected in AS-BUILT
DRAWINGS.
• Approved fittings shall be used for joining PVC Conduits.
• Any bench marks shall be removed from PVC Conduits and painted
immediately after erections.
• Cover all ends of conduits to prevent any debris going inside thus blocking the
conduit.
• Ensure that workmanship is tidy and complying to good construction practices.

7. Inspection and Testing


• After completion of the work, the Site Engineer who perform an activity are
required to raise an RFIA (Request for Inspection and Approval) with complete
information regarding the scope of inspection, including necessary drawings
highlighted to show the scope of inspection. He shall systematically check and
inspect their work. The inspection shall be performed according to typical

HSE Documents-Method Statement for ELECT Work


METHOD STATEMENT Page 4 of 5
ELECT. WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-ELECT -01 HSE-DOCS-264R15 07.02.2024 00

checklist and approved Inspection and Test Plans (ITP) which shall also be
attached to the RFIA.
• After the Site Engineer completed their inspection, RFIA shall be submitted to
QAQC Department who shall process the documents to have completed work
inspected by Supervision Consultant for their approval
8. Tools and Equipments
Tools
• Pipe Cutter
• Pipe Reamer
• Hickey Bender / Bending spring
• Electric drill with wits
• Jigsaw
• Hacksaw
• Open and box type spanners
• Chalk line / marking pen
• Measuring Tape
• Ball Hammer and cold chisel
• Screw Driver set
• Level Bar
9. Manpower
Staff:
• Project Manager
• Site Engineer
• Supervisor
Labor
• Foreman
• Trade workers
• Helpers / Labours
• Drivers
10. Health, Safety and Environment
Safety of all workers and equipment is the highest priority of organization during the
execution of the Works.
Personnel Protective Equipment
• Safety Helmet
• Safety Glasses (during drilling and use of grinders)
• Face shield (during grinding)

HSE Documents-Method Statement for ELECT Work


METHOD STATEMENT Page 5 of 5
ELECT. WORK
Company Doc. No. Contractor Ref. No. Date Revision
HSE DOCS-MST-ELECT -01 HSE-DOCS-264R15 07.02.2024 00

• Safety Footwear (steel toes)


• Safety Gloves (for material handling)
• Coverall (as protective clothing)
• Full Body Harness
• Respiratory Mask (if require)
Tool Box Talk (TBT)
• HSE Tool Box Talk shall be given by the site supervisor every week and/or as
deemed necessary.
• HSE tool Box Talk shall brief the task / subject and shall be given in languages
understandable by multinational workforce.
• HSE Tool Box Talk attendance shall be recorded on a sheet and signed by
attendees.
Material Safety Data Sheet (MSDS)
All materials shall be identified and all MSDS should be read and understood
before use.
Housekeeping
Housekeeping shall be maintained by all personnel working at site.
Housekeeping for fabrication and installation shall be as per project safety plan
and organization Safety Manual.
Signage
All Mandatory safety warning and caution signs shall be displayed at work
locations.
11. QC Approval and Other Documentary Requirements
• Material Technical Submittal Approval
• Shop Drawing Approval
• Material Inspection Report (MIR) approval
• Installation Request for Inspection – Test (RFIA)

HSE Documents-Method Statement for ELECT Work