Module 4 - Assembly Line Balancing
Module 4 - Assembly Line Balancing
In the world of manufacturing, efficiency is the name of the game. Wasted time, resources, and
materials can eat into profits and hinder growth. This is where line balancing comes into play – a
strategic approach that can revolutionize your production line.
Assembly Line Balancing (ALB) optimizes the mass production process by dividing tasks into
workstations and allocating equal processing time to each one without any delay.
The assembly line in which the workstations have equal processing time with less or no ideal
time is said to be a perfect one.
It must be balanced in order to ease the manufacturing process efficiently. Besides, it involves the
apportionment and allocation of the tasks into several workstations. But, the allotment must not
impact the existing precedence relationships.
Therefore, Assembly line balancing is strategically planning, locating, and sequencing the
workstations.
Following are the examples where there is a need to balance the assembly line may arise:
• Manufacturing of Automobiles
• Assembling Aircrafts
• Shipyards, etc
Line balancing or Assembly line balancing was introduced by Henry Ford in the early 19th century.
They created an assembly line which was pulled on a continuous basis where the assemble is
carried out at each stations. Initially in 1913, they took 12hrs and 8mins to assemble the chassis, but
it later in 1914, it took only 93mins to assemble a new Model-T in a moving production line.
Key Terms:
1. Workstation: A workstation is a specific physical area where a task or group is performed in
the assembly line.
2. Task: The task is a minor division of the work that cannot be subdivided further.
3. Precedence Diagram: A precedence diagram is used to represent the assembly line. It depicts
the relationship of the tasks with each other. And it also shows the flow of the production
activities. We prepare a precedence diagram with the help of Nodes and Arrows.
4. Cycle Time: It is basically the rate at which the overall production is taking place. We can
calculate it with the help of the formula given below: CT = Productive Time/Demand per Period
5. Heuristics: Heuristics are the methods to discover a solution that helps in decision making. It
acts as a guideline for solving typical problems.
Following are the two heuristics methods that one can use in ALB: –
A. Ranked Positional Weight (RPW) Method
B. The Computer Method of Sequencing Operations for Assembly Line (COMSOAL)
6. Takt time: The time available to carry out production in relation to the customers’ demand for
that product. Takt Time = Available Time/Customer Request
Objectives: The objective of using ALB is to divide the entire work process into several sub-
stations. But, the division must not affect the precedence relationships of the tasks and must not
exceed the cycle time. Besides these, we perform line balancing for the following reasons:
• Minimization of the cycle time
• Minimizing the number of the workstations
• Maximization of workload and smoothness
• Maximization of work-relatedness
Line balancing isn’t just a manufacturing buzzword; it’s a powerful strategy that can revolutionize
your production processes. By minimizing waste, reducing inventory, adapting to change, and
boosting profits, line balancing can unlock value for your organization. So, take the plunge, analyze
your lines, improve, and reap the rewards of a more efficient production line.
Step 1. Define the tasks: The first step is defining all the steps or tasks in the processes involved in
production or assembly line.
demand.
III. Number of workstation calculation
Step 4. Selection and assigning tasks to the workstation: After identifying the workstations,
select the workstation based on the precedence diagram and workstation tasks group.
Step 5. Understand the efficiency of the line: Based on the current cycle time of the workstation,
calculate the efficiency of the line. We can further improve the efficiency on a later stage based on
demand.
Step 6. Line Rebalancing: The rebalancing can be done for the improved customer demand in
future. The same steps will be continued to rebalance the line for improved customer demand.
Cycle Time of Assembly Line: Cycle time of Assembly Line is the maximum time of individual
work stations.
CL = Maximum (CW1, CW2, CW3, CW4, CW5)
CL = Maximum (80, 60, 70, 70, 70)
CL = 80 Seconds
Balance Delay: Balance delay indicates the ideal time on the assembly line.
Balance Delay (DL) = (nCL – Tp)/ nCL X 100
DL = [(5 X 80) – 350] / [5 X 80] X 100
DL = 12.5%
Production Rate: Assuming Production happens 24 Hrs in 3 shifts each of 8 hrs.
In the above example we could clearly understand that with proper arrangement and allocation of
activities and tasks to individual workstations in assembly, we could increase production by 14%. In
the manufacturing industry it is always necessary to re-arrange the activities based on individual
workstations so that the total processing time can be optimized and the effort – well balanced,
leading to optimum level of production.
In the next step, we need to calculate the Cycle Time. But first, we will convert the productive time
from Hours to Seconds because tasks time is given in Seconds.
6-Hours = 21600 seconds
CT = Productive Time/Demand per Period
So, CT = 21600/216 = 100 Sec
Therefore, 1 unit must be produced after every 100 seconds in an assembly line.
Now, will we find the least number of workstations needed for the production. For this, we will
divide the Total Task Time by Cycle Time.
Total Task Time = 400 Sec
Cycle Time = 100 Sec
So, Minimum Number of Stations = 400/100 = 4 Stations
Thus, we need 4 workstations to produce a unit every 100 seconds.
Now, we will assign the tasks in these workstations using the Longer-Operation-Time-Integer
heuristic.
=270/90 = 3stations
Thus the manager need 3 stations to produce a unit in every 90secs.
D. Workstation assignment
The longer operation time integer heuristic method to assign tasks to workstation. The Table
1, shows the workstations and their tasks after balancing the assembly line for a takt of
90secs.
Table 2: Cycle time of individual tasks in workstations
E. Identify the flow
The cycle time for individual workstations are plotted in Table 2., to get an understanding on how
the cycle time is balanced with respect to target takt time.
F. The final assembly line
The graph shows how the assembly line is balanced with respect to the takt time. The final
assembly line will be as shown in the figure 3, below.
In the next step, we need to calculate the Cycle Time. But first, we will convert the productive time
from Hours to Seconds because tasks time is given in Seconds.
6-Hours = 21600 seconds
CT = Productive Time/Demand per Period
So, CT = 21600/216 = 100 Sec
Therefore, 1 unit must be produced after every 100 seconds in an assembly line.
Now, will we find the least number of workstations needed for the production. For this, we will
divide the Total Task Time by Cycle Time.
Total Task Time = 400 Sec
Cycle Time = 100 Sec
So, Minimum Number of Stations = 400/100 = 4 Stations
Thus, we need 4 workstations to produce a unit every 100 seconds.
Now, we will assign the tasks in these workstations using the Longer-Operation-Time-Integer
heuristic.
Conclusion
In conclusion, ALB is the optimization of the mass manufacturing process. This optimization occurs
by reducing the ideal and cycle time by creating workstations.
Line balancing results in the greatest use of resources. It also increases the efficiency of the overall
production process.
The business becomes less agile due The business becomes more agile due
Business Agility to the longer movement across to the shorter movement across
different departmental regions different departmental regions
Inter-
Effective communication within each
departmental Communication gaps are observed
cell
Communication
FAQs
1. What is the Cellular Manufacturing Definition?
Cellular manufacturing meaning is a system of production in which a large manufacturing system is
divided into smaller subsystems called “Cells” to reduce the material handling time and cost and
improve productivity.
2. What are Cellular Production Examples?
Apple and Toyota are the most popular and successful cellular manufacturing examples. Apple
produces different gadgets such as the iPhone, iPad, and iPod, with a shared set of circuits and
functionalities. Similarly, Toyota manufactures different models of vehicles with common
components.
3. Which Industries Benefit from Cellular Manufacturing System?
Various industries from automotive, aerospace, and electronics manufacturing, to medical device
manufacturing benefit from the Cellular Manufacturing System. Modern-day manufacturing
businesses have increasingly adopted the cellular manufacturing process to optimize their
production process.
4. How Does Cellular Manufacturing System Bring Down Manufacturing Costs?
A Cellular Manufacturing System reduces the amount of manufacturing waste, and the time being
spent on each manufacturing process. It also eliminates the need for additional labor and machinery.
All of these collectively result in significant cost savings.
5. How is Cellular Manufacturing Different than Traditional Layouts?
While the Traditional Layout focuses on building standardized products, the Cellular Manufacturing
System emphasizes building products with variations. It does so by dedicating every cell to building
a single subassembly that will be used in the final product.