0% found this document useful (0 votes)
39 views15 pages

General Instrumentation Installation

The document outlines the basic requirements and precautions for instrumentation installation in refineries, emphasizing the importance of proper material, calibration, location, and mounting height. It details various installation types, inspection points, cable laying requirements, and the significance of maintaining separation between power and signal cables. Additionally, it covers specific checks for cable trays, junction boxes, and instrument panels to ensure compliance with industry standards and safety regulations.

Uploaded by

Mansoor Ali Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views15 pages

General Instrumentation Installation

The document outlines the basic requirements and precautions for instrumentation installation in refineries, emphasizing the importance of proper material, calibration, location, and mounting height. It details various installation types, inspection points, cable laying requirements, and the significance of maintaining separation between power and signal cables. Additionally, it covers specific checks for cable trays, junction boxes, and instrument panels to ensure compliance with industry standards and safety regulations.

Uploaded by

Mansoor Ali Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 15

General Instrumentation

Installation Practice in
Refinery
What is Instrument Installation basic requirement for
Instrumentation Engineers? Explain precaution prior and after
installation.

Installation: It is very hard to explain or define Installation all


together at same time but in simple way we can explain standard
instrument hook-up the parameter with process, sub-system or
any system as per approved drawing is called Installation.
Usually there are two types of installation: inline and offline or
remote.

They basic precaution for instrumentation Installation could be


as following:

Material: Ensure that material is as per spec and suitable to


use.

Calibration: Ensure that parameter is functioning fine prior to


take it for site to install.

Location: Ensure the location is as per P&ID and elevation is


per approved Layout: All instrument remote type should be
mounted as close as possible to the process connection,
consistent with required accessibility, operability,
maintainability, visibility and not be subject to vibration, invisible
and obstacle to walkway etc.

Instrument Height: Instrument should be mounted as closer to


grade than 1.2 to 1.5 meter unless specified or approved.
Nozzle orientation: for Gas must be vertical or 45o below
vertical, for Liquid must be horizontal or 45o below horizontal,
for steam must be horizontal or 45 above horizontal in normal
cases for exceptional it may vary upon mutual agreement only.

Instrument: instrument must above tape for Gas, below tape


for liquid and steam.

Instrument Installation: most instruments are susceptible to


damage, abnormal wear, or malfunction if mounted in a location
where the are subject to vibration. If any part of the flow system
or equipment is subject to vibration, the affected instrument
should be provided with vibration free stanchion/support/bracket
etc.

Impulse Line: Tubing for remote devices should be as short as


possible, 3 feet for close-coupled transmitters and preferably not
more than 20 feet (6mtrs). Slope should be at least 1 inch per
foot (12:1) for liquid /steam services towards instrument and for
gas towards process.

Impulse Tubing for Gas service: Instrument and impulse line


for gas service must be free from liquid pocketing and slope
should be towards process since instrument is mounted above
process taping.

Impulse Tubing for Liquid service: Instrument and impulse


line for liquid service must be free from air trapping and slope
should be towards instrument since instrument is mounted
below process taping.

Impulse tubing for Steam service: Instrument and impulse


line for steam service must be provided with Seal-pot
(condensate port) to avoid damage of device by heat and slope
should be towards instrument since instrument is mounted
below process.
Access Field mounted: for maintenance purpose all locally
mounted devices shall be easily accessible, operable,
maintainable, and removable from grade, platform, fixed
walkway or fixed ladder etc.

Local Panel mounted: Where several instruments are installed


within a small area, consideration shall be given to mounting
them on a common local panel / board and sunshade shall be
provided to avoid calibration drift if they are in open area.

Differential type Instrument: Should not be installed in a


service where the measured liquid gravity will vary widely and
often, magnetic, PDmeter or turbine should be used.

Displacer type Instrument: should be always be installed in a


manner to permit removal without disconnecting major process
piping, shall be installed in external chamber with block and
drain valves. Shall never be considered for vessels which are
subject to high vibration.

Indication: Instrument Indicator should always be installed in


front means visible for manual station, obstacles to see
unacceptable.

Cable way: Tray/Conduit: Cable way must be made of adequate


fitting and all standards accessories even site fabricated fitting
and Accessories are acceptable as long as they comply to
standard bending radius and sharp bending must be avoided.

Cabling: Proper segregation must be maintain for power, signal,


control, TC etc cable and slaking, twisting, crossing, and sharp
bending must be avoided and loop shall be provided at the end of
instrument for easy removal of instrument.

Cable dress: Cable must be dress nicely with cable tie (the
approved material)
Transmission: Hydrocarbon or other process fluids should not
be piped to any instruments located in a control room. Standard
industry practice is to convert the process variable to an
electrical or pneumatic signal and transmit the signal to remote
receiving instruments.

Seal / Gland: If cable is being run through conduit then seal


fitting must be provide for Zone 0 and zone 1 area, if Tray is
used then cable should be connected to instrument through
gland.

Wiring: Wiring must be done in such a manner that shrinkable


ferrules shall be provided with from/To address (cross ferruling)
for easy maintenance.

Name plate: Name plate must be provided of Stainless steel as


well as Phenolic with clear alpha-numeric number as per
approved drawing and must be readable.

Purging Sealing : When viscous liquids or pressure of


corrosive, slurry, or freezing process fluids are measured or
when plugging is possible where solid exist, an instrument may
be sealed, purged, or protected by a diaphragm seal or
protector.

Steam Heat tracing: The need for heating depends on the


severity of the winters in the locality to prevent freezing. Since
steam is normally available in the plant process unit, steam
heating has the advantage of being readily accessible steam.
Steam supplies high-density heat from condensation, and large
quantities of heat can be obtained from a single tracer line. On
the other hand, steam delivers heat at a temperature that
corresponds to the saturated steam pressure in the tracer

Electrical Heat Tracing: Electrical heating selection care


must be exercised to ensure that they are not potential source of
ignition. Several types of cables are available (mineral Insulated
MIC, and self limiting)
Insulation/protective covering: The entire tracing system for
impulse lines should be carefully insulated and waterproofed.
Particular care should be used at the point of measurement and
at the entry into insulated enclosure. A durable protective cover
should be used where stainless steel tubing is used, chloride-free
insulation must be specified to prevents stress corrosion
cracking.

If one Pressure Transmitter is installed at site, how many


inspections are related to that one instrument?

 Cable Tray Installation Inspection.


 Cable Laying Inspection.
 Cable IR/Continuity Test Inspection.
 Cable Glanding &Termination Inspection.
 Instrument Tubing Installation Inspection.
 Final Instrument Installation Inspection.

What are the necessary points to be inspected for cable laying?

They shall be as following:

Ø Material inspection as per approved materials specification


and Purchase order

Ø Cable Types and size as per spec and cable schedule

Ø Cable meggering and continuity prior to cable pulling and


recorded in QVD

Ø Updated Cable routing drawing shall be available prior to


cable laying

Ø Completion of cable route (tray, conduit or trench etc.) prior to


cable laying

Ø Segregation and separation shall be maintain after cable


laying (dressing)
Ø Cable bending radius should be as per spec and vendor
recommendation

Ø Proper tools and accessories should be used to avoid cable


damage

Ø Cable dressing shall be done in good workmanship to avoid


slaking, twisting etc.

Ø Cable numbering (tags) shall be provided as per spec and


Drawing.

What is the basic requirement for cabling?

Instrument cable shall be routed separately from electrical


cables, details are below:

separation of signal and power cable on parallel run shall be as


below:

Power Cable Instrument signal / control / power cable etc

125VAC or 10A 250 mm

250VAC or 50A 500 mm

440VAC or 200A 750 mm

3.3KVAC or 500A 1250 mm

11KVAC or 800A 4000 mm

-Separation of signal and power cable for crossover should be


250mm as minimum.
What are the inspection points of cable tray installation
inspection?

First Required IFC drawing (cable tray lay out diagram).

Check material: aluminum free of cooper or SS316 for classified


areas. Follow the

NEMA VE-2 standard for cable tray installation.

What are the checks you will perform for a cable tray
installation?

Supports prefabrication, Installation & layout as per approved


drawings, Supports & hangers installed properly, Clamps &
fixings properly installed ,

Expansion joints, splice plates and fittings correctly located,


Midspan deflection acceptable, Clearances from other structures
and components, Cable tray without roughness.

Cable tray Inspection Notes

First I will check cable tray routing as per drawing.

I will check support as per standard.

I will check nut bolt as per Steen less steel and proper tight.

I will check bonding jumper as per with 25m

I will check expiation joint with in 20m..

I will check all support tray made steel or iron either hot-dip-
galvanized or zinc electroplated.

I will check tray to tray distance.


Cable Tray Inspection Documents

 Cable laying drawing and IPL or location drawaing.


 The elevation of the bottom of the lowest interior cable
tray shall be a minimum of 2.67 m above the main
substation floor. SAES-P-119 Sec. 6.3.3.
 All cable trays shall have a minimum of 300 mm clear
space above the tray. (NEMA VE 2 Sec. 4) SAES-P-104
Sec. 3.2.
 A minimum of 200 mm of vertical clearance shall be
provided between cable trays. SAES-P-119 Sec. 6.3.2.
 Supports should be located within 2 ft. (600 mm) of
each side of vertical adjustable splice plates. (NEC
110.3, NEMA VE-2 Sec.4.3.3).
 Place horizontal tee supports within 2 ft. (600 mm) of
each of the three openings connected to other cable
tray items for the 12 in.
 All fasteners (i.e., nuts, bolts, washers, etc.) used to
connect and assemble the cable tray system shall be
304 SS. In severe corrosive environments, 316 SS
fasteners shall be used.
 Channel erector system components (Unistrut or
similar) used to support cable tray shall be made of
steel or iron, either hot-dip galvanized (preferably), or
zinc electroplated as supplied by the manufacturer.
 Cables are fastened a minimum of every 18 in. (450
mm) on vertical runs. (NEC 110.3, NEMA VE-2
Sec.5.6) SAES-P-104 Sec. 4.1.
 Cable trays shall not have sharp edges, burrs, or
projections that could damage the insulation or jackets
of the wiring. [NEC 392.5 (B)]
 Minimum thickness of covers shall be 1 mm. SAES-P-
104 Sec. 9.2.
 Cable tray installed outdoors shall have ventilated
covers. SAES-P-104 Sec. 9.1
 Cable trays run vertically in outdoor areas shall have
covers on both sides. SAES-P-104 Sec. 9.1
 Flanged type covers shall be secured with stainless
steel banding, one band per ½ m of cover length, with
a minimum of six bands per cover. SAES-P-104 Sec.
9.1.
What are the inspection points for duct bank inspection?

First we check survey report.

1. Type of conduit material


2. It should be- PVC gray color conduit. Schedule 40 as
per NEMA TC-6/8
3. Size:- 3” to 6”
4. Separation between conduits
5. 50mm or 150mm from the conduit centre to centre.
6. separation between reinforced to conduit
7. 75mm minimum.
8. Separators should be provided every 2.4 meter
9. Bell end to be provide very end point of conduit.
How to check the installation of inst. panels?

 The complete assembly shall be checked to ensure


alignment and level after the tightening the bolts.
 The instrument shall be checked against identifying
labels d and tags are installed as per the layout
drawing.
 Earthling of the panel shall be checked to ensure it is
as per detailed drawing.
 The installation shall be rigid.
 Panel doors and detachable cover shall be checked to
ensure proper closure and sealing .
Connections at Field Junction Boxes:

 First I will check all instrument cable entries to field


junction boxes shall be through the bottom.
 The outer jacket Twisted, multi-pair/triad cables shall
be cut to the appropriate length to minimize looping
and flexing of the cable within the junction box.
 The outer jacket of shielded twisted single pair/triad
cables shall be left intact up to the point of
termination. (Approximately three to four inches from
terminal blocks).
The shield drain wire shall be insulated from jacket
end to terminal. Approximately, one inch of heat shrink
tubing shall be applied over the jacket end.
 Drain wires and Mylar shields on shielded cables shall
be cut and insulated with heat shrink sleeve.
 Spare pairs/triads in multi-pair/triad cables shall be
labeled “Spare” in addition to the destination and
source terminal numbers.
 For individually shielded twisted multi-pair/triad
cables each pair/triad shall be heat shrink sleeve
insulated from the cable-jacket-end up to the point-of-
termination to keep the foil shielding intact and free
from accidental grounds. The shield drain wire shall be
insulated from foil end to terminal. Approximately, two
inches of heat shrink tubing shall be applied over the
jacket end.
 All wiring shall be tagged at each end. Each wire tag
shall have two labels. The first label (closest to the end
of the wire) shall identify the terminal number to
which the wire is physically connected. The other label
shall be the terminal number of the connection of the
opposite end of the wire.
 Wire tag information shall be permanently marked in
block alpha numeric or typed on tubular, heat-
shrinkable, slip-on sleeves. Wrap-around, snap-on or
self-adhesive wire markers shall not be used.
Handwritten wire tags are not acceptable.
 A clear heat shrink sleeve shall be installed over the
wire tag for all instruments that use rust preventive
grease on its threaded wiring access cover.
Cable Tagging Inspection:

 All cables shall be tagged, at each end, with a cable-


tag.
 Homerun cables shall be tagged with the assigned “IC”
cable number.
 Cable tags outside junction boxes and marshaling
cabinets shall be 316 SS with permanently marked
alphanumeric characters i.e., raised or stamped
characters.
 Outside junction box The cable tag shall be securely
attached to the cable with stainless-steel cable ties.
Terminal Reference: Each row of terminals shall be
uniquely identified alphanumerically, e.g., TS-101, TS-
102, etc.
 The terminals in each row shall be sequentially
numbered starting at number one (1). The number of
conduit entries shall be kept to a minimum.
 All unused entry ports shall be fitted with approved
plugs.
 How to check the instrument installation?
 Check the identification tag)
 Check the elevation if it is above or below the process
tapping point
 The support shall be rigid
 The instrument shall be accessible.
What are the checks you will perform for installation of JB?

Fabrication of JB Support as per drawing, support earthed. JB


location as per approved drawing. JB shall be free of damage.
Type 316 stainless steel Body, door and hardware. Continuously
welded seams, finished smooth. Stainless steel captive clamps.
Data/Print pocket on inside of door. Ground stud for terminating
A/C safety ground wire. A gasket shall be secured with adhesive.
Junction boxes having an internal volume exceeding 2,000 cm³
shall be provided with Type 300 Series stainless steel breather
and drain fittings, or a combination breather and drain fitting. JB
shall conform to all applicable requirements, standards, and
specifications. A coding system to indicate the degrees of
protection provided by an enclosure against access to hazardous
parts, ingress of solid foreign objects, ingress of water and to
give additional information in connection with such protection. A
designation of the degree of protection provided by an enclosure
is indicated by the IP Code arranged. . (IEC 60529 sec. 3.4 and
4). Locations where chlorine or other corrosive chemicals are
being handled are also corrosive environments. In these
locations, enclosures must be resistant to the chemicals
present.In hazardous (classified) areas, General Box that are
required by the National Electrical Code (NEC) to be approved)
shall be labelled or listed or certified by any of the agencies,

What are inspection points for field instruments with impulse


tubing?

Ans: Materials inspection as per approved spec material, type


and size, Installation as per Hook-up, check line route to avoid
any obstruction, check tube bending, and check tube support,
compression fitting or ferrules, and then pressure test
(hydrostatic test) shall be done.

1.I will check taping point as per P&ID. Or high or low as per
P&ID

2. I will check slope


3.I will check tubing support should be spaced not more then 4
feet.

What are the checks you will perform for a field Instruments
with impulse tubing?

Fabrication of Stand as per drawing, Instrument location as per


IPL Drawing, Access is unobstructed and clear for maintenance,
Stand earthed, Instrument mounted in accordance with hook up
drawing, Check instrument is correct in accordance with ISS / P
& ID, impulse tubing material used according to specification,
Isolation and equalization valves / manifold installed, Vent and
drain / manifold installed, Verify Tubing connection to HP & LP
sides, Impulse tubing length, tubing slope, Elevation correct
relative to process tapping.

For Gas and Vapor Service- For gas and vapour service,
transmitters shall be mounted above and as close to pressure
taps as possible while still maintaining accessibility. Impulse
lines shall slope continuously downward from transmitter to root
valve such that they are self-draining (minimum one inch per
foot).
For Liquid or Condensing Service- For liquid or condensing
service, transmitters shall be mounted below the pressure taps.
Impulse lines shall slope continuously upward from transmitter
to root valve such that they are self-venting (minimum one inch
per foot).

For steam service, the transmitter may be mounted above the


pressure taps with a siphon or pigtail or below the taps with
correction for static head in the process tap lines.

Leak Test done, Pressure Test of impulse tubing.

What are the checks you will perform for a conduit inspection?

Conduit installation as per approved drawings, Supports


installation &support distance, Correct type & size, Conduit
bending radius, Internal surface smooth & free of sharp edges,
Alignment and straightness, Clearances from other objects,
Bodies, fittings, unions, nipples and other components installed
properly, low point drain installation, Bushings installation
(where applicable), Grounding connection (when applicable)

What are the checks you will perform in a material receiving


inspection of received cable?

Review Quality Documentation for Material Receiving- Purchase


Order and specification sheet criteria shall be confirmed and
compared with stainless steel tags / labels and nameplates, and
shipment checked for damage, prior to acceptance of the
shipment Cable materials supplied shall be third-party listed as
meeting the requirements of UL standards (UL 13, 1277, 1709,
2250, NEC Article727, and NEC Article 725 as applicable, or
approved equal standards). (NFPA 70 NEC) – cable materials
shall be new and unused-Free of Damage-

What are the checks you will perform for installation of


instruments?

1.Instrument location as per IPL Drawing


2. Instrument mounted in accordance with P&ID hook up
drawing,
3. Check instrument is correct Elevation
4. Access is unobstructed and clear for maintenance,
5. Fabrication of Stand as per drawing
6. Stand earthed,
7. Instrument Calibrated prior to installation and
documentation checked,
8. I will check instrument securely installed
The most important activities for pre-loop checking inspection
are:

 Check the hook-up and installation of instruments is


correct.
 Check that impulse lines are pressure tested.
 Check the cable continuity and resistance test are
completed.
 Check that all the instruments involved in the loop are
calibrated.
 Check the correct wiring and tagging of
instrumentation cable point to point from marshalling
cabinet to instrument at field side, in accordance to
wiring diagram loop. All of them
What are inspection points for a cable laying?

Ans: Material inspection as per approved materials, types and


size, meggering, cable routing drawing, completion of cable
route ( tray, conduit or trench etc ) and cable numbering (Tag),
cable bending, use or proper tools and equipment for cable
pulling.

First I will check cable laying as per IPL(instrument point and


line ) or location drawing,

1. I will check cable schedule


2. I will check specification marking cable outer jacket
3. I will check cable tag ss both side installed
Document required cable laying RFI
IPL(instrument point and line ) or location drawing, cable
schedule.

You might also like