Hns Level 4AA

ENDILA, an ICT consultancy, is tasked with planning, designing, and implementing a new network infrastructure for a four-floor building with 27 users, aiming to expand to 36 users. The project includes requirements for file sharing, system security, database management, user control, central administration, and email sharing. The project manager must prepare a detailed project plan, list hardware and software requirements, draw a physical topology diagram, calculate total costs, and develop a maintenance strategy, culminating in a presentation for the management team.

Uploaded by

bekelekolola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
33 views8 pages

Hns Level 4AA

ENDILA, an ICT consultancy, is tasked with planning, designing, and implementing a new network infrastructure for a four-floor building with 27 users, aiming to expand to 36 users. The project includes requirements for file sharing, system security, database management, user control, central administration, and email sharing. The project manager must prepare a detailed project plan, list hardware and software requirements, draw a physical topology diagram, calculate total costs, and develop a maintenance strategy, culminating in a presentation for the management team.

Uploaded by

bekelekolola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

HNS level 4

Hardware network servicing


Project information
Based on the give scenario do the following task.

ENDILA is ICT consultancy, network installation and software Development Company is assigned you
to plan, design and implement network service. ENDILA has one building in its compound. The building
has four floors. Assume that is currently in average there are 27 users and the first floor is data center.
There company has 1MB of the internet connection from the service provider. This ENDILA has planned
to connect these users each floors in building through network and you are assigned as a project manager.
ENDILA now wanted implement new network infrastructure which include the following infrastructure

Requirement in the project are as follow

1. File sharing service between user


2. Needed system security.
3. Database management service is needed.
4. User control management is required.
5. Central administration users are another consideration.
6. To share email, schedule and task.

Project 1: propose and design new network infrastructure

Task 1.1 plan the project based on the following table using micro soft word.

no Phase Activity Start date Duration End date Responsibility body Required
manpower

Up on time, the project needs to grow with additional employees added to reach 36 users

Task 1.2identify and list all hardware and equipment used to implement new network
infrastructure on the following template on MS –word.

no Item Specification Unit Price Remark


1
2
3
4
Task 1.3 identify and list all software to implement new network infrastructure on the following
template on MS –word.

no Item Specification Price Remark


1
2
3
4

Task 1.4 draw the physical diagram or topology of the project that includes all components and
requirement and equipment that are listed on task 2.

 Show appropriate types of the cable can be used.


 Show appropriate types of network device in appropriate place.
 Show types of internet connection needed to build internet infrastructure
 Show server in appropriate place

Task 1.5 calculates the total cost of the project including hardware and software and equipment
and labor expense internet connectivity.

Project 2: plan, organize and assist to develop organizational client support


and determine maintenance strategy
Task 2.1 prepare maintenance and backup strategy for few proposed network system on MS-word
and strategy must be included

Under this task you can perform to propose client support mechanism and maintenance strategy to
minimizing the down time of the network system.

Task 2.2 prepare presentation using MS-power point and present for ENDILA company
management team about the network infrastructure that you are created in project 1.your
presentation must include the following.

1. Title
Under this title you have assign project them.
2. Introduction
Under this you are required to write overview of the project and background of the project
regarding to project arrangement and implementation as well as current status or progress must be
expressed in clear manner.
3. Project implementation plan
Express work plan using chart
4. Hardware requirement
Under this task you list down all hardware requirement used in the project in a table format or list
tabs.
5. Software used in project implementation.
Under this task you list down all application software, system software and utility software
requirement used in the project in a table format or list tabs.
6. Conclusion.
Under this task, you are required to generalize the project life cycle and current status for your
clients and stakeholders
Answer

Task 1.1 plan the project based on the following table using micro soft word. 2hr

no Phase Activity Start date Duratio End date Responsibility body Required
n manpower
1 Planning Prepare work plan 25/8/2013 4days 29/8/2013 Project manager 1
Allocate budget 30/8/2013 3days 2/9/2013 Project manager 1
Determine human 3/9/2013 3days 5/9/2013 Project manager 1
resource
2 Identify Hardware 6/9/2013 10days 15/9/2013 Network technician 3
requirements Software 16/9/2013 5days 20/9/2013 Network technician 3
Purchasing peocurcent 21/9/2013 5days 25/9/2013 Network technician 3
3 Design Visit building site 26/9/2013 2days 27/9//2013 Network admin 2
network Select install design tool 28/9/2013 2days 29/9/2013 Network admin 2
and topology
Design physical and 30/9/2013 6days 5/10/2013 Network admin 2
logical diagram
4 Network Install cabling 6/10/2013 20days 25/10/2013 Labor man & Network 2
installation technician
and device Configure switch, router, 26/10/2013 5days 30/10/2013 Network admin 2
configuration firewall and etc
Configure all server 1/11/2013 5days 5/11/2013 Network admin 2
5 Maintenance Check bandwidth 6/11/2013 2days 7/11/2013 Network technician 2
and testing Test every devices and 8/11/2013 3days 10/11/2013 Network admin 2
network arrangement Network technician
6 Documenting Prepare troubleshooting 11/11/2013 5days 15/11/2013 Network admin 2
&presentation document
Prepare presentation for 16/11/2013 6days 21/11/2013 Project manager 2
acceptance
Total duration in days 86days Total human power 8

Task 1.2 identify and list all hardware and equipment used to implement new network
infrastructure on the following template on MS –word.

no Item Specification Unit quantity Price Remark


1 Server Dell core i7-7550 CPU 3.00GHz,RAM PCs 2 15000*2
16GB and HDD 1TB
2 Client PCs Dell core i3-7550 CPU 2.4GHz,RAM 4GB PCs 63 5000*63
and HDD 500GB
3 Access switch D-link port 24 PCs 3 20000*3
4 Distribution Core switch port 16 PCs 1 25000*1
switch
5 Cabling UTP cat5 Roll 5 500*5
6 Connector jack RJ-45 and RJ-11 PCs 400 5*400
7 Crimper Standard PCs 3 3*450
8 Tester Standard PCs 2 2*600
9 UPS Uninterruptible power supply PCs 2 2*12000
10 Ventilator fan Datacenter fan PCs 1 1*16000
11 WAP Wireless access point (Wi-Fi) PCs 1 1*400

Task 1.3 identify and list all software to implement new network infrastructure on the following
template on MS –word.

no Item Specification Price Quantity Remark


1 NOS Window server 2008 R2 100 2/DVD
2 Client OS Window 10 500 5/DVD
3 Database software SQL 50 1/DVD
4 Office package Microsoft office 2007 150 3/CD
5 Design software Microsoft office Visio 2007 50 1/CD
6 Utility software Antivirus smadav and avast 100 2/CD
7 Internet software Browser,chrome,firefox Download free 2/CD
8 Driver software Snappy 209 Download 1/32GB USB flash disk
9 Mailing software Mail exchange 50 1/CD

Task 1.4 draw the physical diagram or topology of the project that includes all components and
requirement and equipment that are listed on task 2.
Task 1.5 calculates the total cost of the project including hardware and software and equipment
and labor expense internet connectivity.

Calculate the total cost of the project including hardware and software

• Hardware requirement =

• Software requirement =

• Total cost =

• Internet connectivity = broadband connection

=4000 per month for 4Mb/s speed per month

=5,500 per month ethio telecom

Task 2.1 prepare maintenance and backup strategy for few proposed network system on MS-word
and strategy must be included

Under this task you can perform to propose client support mechanism and maintenance strategy to
minimizing the down time of the network system

Offer client support mechanism

 All users must have account and password.


 Users must use resource as organizational rules and guidelines.
 Report necessary information at a time.
 Help desk support.

Purpose maintenance policy.

Preventive maintenance.
 Install antivirus and scan computer.
 Disk cleaning.
 Disk defragments.
 Cleaning computer
Corrective maintenance.
 Correct hardware damage.
 Correct cable functionally.
 Install and upgrade software corrupted.
Backup and strategy on database and files server
 Bacula backup automatic backup configuration on strategy: 1 times per a day 6:30 PM on
incremental backup.
Task 2.2 prepare presentation using MS-power point and present for ENDILA company
management team about the network infrastructure that you are created in project 1.your
presentation must include the following.

1. Title

Under this title you have assign project them

Example: network implementation by ENDILA.

2. Introduction
Under this you are required to write overview of the project and background of the project
regarding to project arrangement and implementation as well as current status or progress must be
expressed in clear manner.
3. Project implementation plan
Express work plan using chart

NO Phase /activity Month 1 Month 2 Month 3 Month 4


Duration in weeks peer W1 W2 W3 W4 W1 W W3 W4 W1 W2 W3 W4 W1 W2 W3 W4
month 2
1 Planning
2 Identify requirements
3 Design network
4 Network installation
and device
configuration
5 Maintenance and
testing
6 Documenting
&presentation
4. Hardware requirement
Under this task you list down all hardware requirement used in the project in a table format or list
tabs.

no Item Specification
1 Server Dell core i7-7550 CPU 3.00GHz,RAM 16GB and HDD 1TB
2 Client PCs Dell core i3-7550 CPU 2.4GHz,RAM 4GB and HDD 500GB
3 Access switch D-link port 24
4 Distribution switch Core switch port 16
5 Cabling UTP cat5
6 Connector jack RJ-45 and RJ-11
7 Crimper Standard
8 Tester Standard
9 UPS Uninterruptible power supply
10 Ventilator fan Datacenter fan
11 WAP Wireless access point (Wi-Fi)
5. Software used in project implementation.

Under this task you list down all application software, system software and utility software requirement
used in the project in a table format or list tabs

no Item Specification
1 NOS Window server 2008 R2
2 Client OS Window 10
3 Database software SQL
4 Office package Microsoft office 2007
5 Design software Microsoft office Visio 2007
6 Utility software Antivirus smadav and avast
7 Internet software Browser,chrome,firefox
8 Driver software Snappy 209
9 Mailing software Mail exchange

6. Conclusion.
Under this task, you are required to generalize the project life cycle and current status for your
clients and stakeholders

Example: it is clear that one project is successfully completed with agreed time frame or deadline need
higher efforts and higher project management skill. This network implementation project by ENDILA has
been implementing that 86 days according to our agreement as well as work plan. Now it is operational
and the user able to share resource and access internet using newly deployed network based on your
organization policy and deadlines established. At the end, we would like to request you to approve and
accept finalization the project after evaluating current status to fully covered the remaining budget