Lecture 4
Lecture 4
WHAT IS CONTRACT?
A contract is a legally binding agreement which recognizes and governs the rights
and duties of the parties to the agreement. A contract is legally enforceable because
it meets the requirements and approval of the law. An agreement typically involves
the exchange of goods, services, money, or promises of any of those. In the event of
breach of contract, the law awards the injured party access to legal remedies such as
damages and cancellation.
A construction contract provides a legal binding agreement, for both the owner and
the builder, that the executed job will receive the specific amount of compensation
or how the compensation will be distributed. There are several types of construction
contracts used in the industry, but there are certain types of construction contracts
preferred by construction professionals.
Construction contract types are usually defined by the way the disbursement is going
to be made and details other specific terms, like duration, quality, specifications, and
several other items. These major contract types can have many variations and can be
customized to meet the specific needs of the product or the project.
There are several factors which have to be taken into consideration in making the
choice of contractual arrangement. This may include the following:
Since there are many arrangements to choose from, the choice of any one
arrangement will therefore mean the elimination of the others when you come to the
place of deciding the contractor.
TYPES OF CONTRACT
This type of contract involves a total fixed price for all construction related activities.
This can include incentives or benefits for early termination, or can also have
penalties, called liquidated damages, for a late termination. These contracts are
preferred when a clear scope and a defined schedule has been reviewed and agreed
upon.
This contract is used when the risk needs to be transferred to the builder and the
owner wants to avoid change orders for unspecified work. However, a contractor
must also include some percentage cost associated with carrying that risk. These
costs will be hidden in the fixed price.
In lump sum contract the complete work as per plan and specifications is carried out
by contractor for certain fixed amount as per agreement. The owner provides
required information and contractor charges certain amount. This contract is suitable
when the number of items is limited or when it is possible to work out exact
quantities of work to be executed. The detailed specifications of all items of work,
plans and detail drawings, security deposit, penalty, progress and other condition of
contract are included in agreement. Though it is lump sum contract, contractor will
be paid at regular interval of 2-3 months as per progress of work on the basis of
certificate of payment issued by engineer in charge.
Under a lump sum contract, a “fixed price” for the work to be done is agreed upon
by the client and contractor before the work begins. This contract can also be applied
to both home building and commercial contracts. It can be more of a risk to the
contractor as there are fewer mechanisms to allow them to vary their price.
Advantages of Lump-sum Contract
• Early project starts not possible due to need to complete design prior to bidding.
• Contractor free to choose lowest cost means, methods, and materials consistent
with the specifications. Only minimum specifications will be provided.
• Contractor may include high contingency within each Schedule of Value item.
• Unit Pricing Contracts
Unit pricing contracts is probably another type of fixed price contract commonly
used by builders and in federal agencies. Unit prices can also be set during the
bidding process as the owner requests specific quantities and pricing for a pre-
determined number of unitized items.
By providing unit prices, the owner can easily verify that he's being charged with
un-inflated prices for goods or services being acquired.
• Final cost not known at outset since bills of quantities at bid time are only estimates
• Additional site staff needed to measure, control, and report on units completed.
• Unit price contracts tend to draw unbalanced bidding
In this process the owner selects one contractor to both design and build the project.
It is primarily intended to save time. It is not necessary to prepare drawings in great
detail if the builder already understands what needs to be done. It works very well
when using standard designs that have been built repeatedly. It is absolutely critical
that the owner and builder have the same clear picture of the final project before
construction begins.
Design-Build is not a good method for most projects for the following reasons:
• When the designers work for the builder, rather than the owner, the checks and
balances that exist in other methods are lost.
Saving time is the main advantage of design-build, but that should not be as critical
an issue for a project as cost and construction quality.
To some extent, all variable price contracts must contain fixed prices (or elements
or agreements on prices or other considerations).
Time and material contracts are usually preferred if the project scope is not clear, or
has not been defined. The owner and the contractor must establish an agreed hourly
or daily rate, including additional expenses that could arise in the construction
process. The costs must be classified as direct, indirect, markup, and overhead and
should be included in the contract. Sometimes the owner might want to establish a
cap or specific project duration to the contractor that must be met, in order to have
the owner’s risk minimized. These contracts are useful for small scopes like
maintenance work or when you can make a realistic guess on how long it will take
to complete the scope.
• The Pros of Time and Materials Contract: You only pay when your contractor
works.
• The Cons of Time and Materials Contract: Your contractor will tend to work very
slowly.
• Cost-plus-percentage
Cost-plus-percentage is used particularly for emergency work where time does not
permit the use of other forms of contract. The contractor is paid for actual
expenditures plus an agreed percentage to cover overhead and profits.
• Cost-plus-fixed fees
• Man-hour basis
The price for labor is agreed and the cost is measured as the product of the agreed
rate and the man-hour used in performing the contract.
• Professional briefs
SUB CONTRACTS
A sub contract is a contract in which a party agrees to perform part of the work that
was originally arranged with the signer of a previous contract.
TYPES OF SUB-CONTRACTORS
NOMINATED SUBCONTRACTOR
Certain contracts permit the architect or supervising officer to reserve the right of
the final selection and approval of subcontractors. The main contractor is permitted
to make a profit from the use of nominated subcontractors on site, but must provide
"attendance" (usually the provision of water, power, restrooms, and other services
to enable the nominated subcontractor to do his job). In effect the appointment of
nominated subcontractors establishes a direct contractual relationship between the
client and the subcontractor.
CONTRACT DOCUMENTS
• Cover/Title page
• Cost of lubricants
• Cost of freight
• Drawings
• Specifications: the following specifications are normally included in
the contract documents:
• General specifications
• Detailed specifications
• The agreement: which is the actual deed of the contract. It is a registered legal
document and has all the other contract documents annexed.
• Consensus
• Contractual capacity
• Certain performance
• Possibility of performance
OFFER EXPIRATION
• Rejection of offer
• Time lapse
• Counter offer
ACCEPTANCE
•Unconditional
Contractual capacity
TERMINATION OF CONTRACTS
• By agreement: the parties agree to terminate the contract either by one waiving
his right or by releasing the other from his obligation or a new contract substituted
for the old one.
• By breach: one party fails in its obligation and the other then has the right to cancel
the contract and sue for damages.
• By impossibility: this may be due to a cause which has arisen since the making of
the contract.
Whenever a breach of contract occurs, a right of action exists in the court to remedy
the matter. The remedies generally available are as follows:
i. Claim of damages: Damages consist of a sum of money which will as far as it
is practicable place the aggrieved party in the same position as it would have been
if the contract had not been performed. The parties, when entering into agreement
may agree that a certain sum, known as ‘liquidated damages’ shall be payable if
a breach occurs.
iii. Specific performance: The term refers to an order of the court directing a
party to a contract to perform its part of the agreement. It is now only applied by
the courts on mere occasions when damages may be an inadequate remedy but
specific performance constitute a fair and reasonable remedy and is capable of
effective supervision by the court. This remedy may not be given if it requires
the constant supervision of the court.
Disputes may arise between contractor and the Owner/Client because of several
factors. The dispute can be settled through litigation in a court of law or where
the contract permits through arbitration.
TRANSFER OF OBLIGATIONS
•Cession: the person in the right gives up the right to another. The consent of
the other party is required