Wind Integration
Wind Integration
The challenge of wind integration is to make best use of the variable and uncertain
power source while maintaining the continuous balance between consumption
and generation and high level of reliability in the power system. There is already
experience of operating power systems with large amounts of wind power and
integration studies give estimates on wind power impacts. Power systems are
equipped to handle variability and uncertainty that comes from the electricity
consumption, the load. Short-term wind forecasting is required to manage large
amounts of wind power. The main impacts of wind integration are investments
in grid infrastructure and efficiency losses in power plants when following the
increased variations and uncertainty in the power system. Wind power will lower
emissions while replacing energy produced by fossil fuels and can also replace
some power plant capacity. However, wind’s lower capacity value compared to
conventional power plants is one integration impact of wind power, meaning
higher total installed capacity in power systems with high wind penetration.
Managing options for wind integration impacts includes proper wind power plant
grid-connection rules, increasing transmission capacity and increasing flexibility
that is available from generation plants and demand side. Further development of
models and tools is required to study how entire power systems can be operated
during the hours and days of very high penetration levels covering 60–80% of
load. C 2012 John Wiley & Sons, Ltd.
244
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration
BOX 1: WIND TURBINE CAPABILITIES ARE to areas that are part of larger areas, it is chal-
IMPROVING lenging to simulate possibilities that transmission ca-
pacity to neighboring areas can have in a way that
Wind turbines can provide support the grid. Allowing higher would not under- or overestimate the system flex-
instantaneous penetration levels means that wind power ibility in managing variability.19 Larger area stud-
plant capabilities in providing (part) of the ancillary services ies capture the impacts of wind power taking into
need to be improved. account the possibilities for cross-border trade and
One reliability concern has been that large amounts of wind balancing.20–23
power can trip off the grid because of a short disturbance of Most studies so far have concentrated on the
the grid (voltage drop).24 This problem has been addressed technical costs of integrating wind into the power sys-
by new grid connection rules (grid codes) requiring fault- tem The benefit when adding wind power to power
ride-through (FRT) capability from wind turbines.11,12,25–27 systems is reducing the total operating costs and emis-
The grid codes often require wind turbines to provide re- sions as wind replaces fossil fuels. To set the costs
active power and in some regions also to take part in volt- in scope, integration costs of wind power should be
age and frequency control.8,11,12 It should be noted, how- compared to something, such as the production costs
ever, that when providing frequency (active power) control or market value of wind power, or integration cost
(Figure 2), this will be at the expense of lost production of other generation forms.1 A fair comparison should
from the turbines. Even if wind power would probably be keep system reliability in the same level and some-
the last to provide such services, it is important to have that how take into account any changes in costs and emis-
option in the systems during high penetration events. sion savings. Cost–benefit analysis has been used in
Ireland.18
F I G U R E 2 | Outline of possible active power control functions from wind power plants. The plots show the possible power and the actual
achieved power when different control functions are activated (Reproduced by permission of Jesper Runge Kristoffersen.)
246
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration
F I G U R E 4 | Variability of wind power will smooth out with aggregation of wind power plants. Real data from Germany where the data are
from the same time period and are normalized to the mean output of each group of wind turbines. (Reproduced by permission of ISET.)
F I G U R E 5 | Predictability of wind power is better for shorter time F I G U R E 6 | Decrease of forecast error of prediction for aggregated
horizons and for larger areas/several sites. Example of average wind power production due to spatial smoothing effects. Error
absolute prediction error for a single wind-power plant and four reduction = ratio between root-mean-square error (rmse) of regional
distribute wind power plants when forecasting horizon is from one to prediction and rmse of single site, based on results of measured power
36 h ahead. generation of 40 wind farms in Germany. (Reproduced by permission
of Energy & Meteo Systems).
F I G U R E 7 | Results for the increase in reserve requirement due to wind power, presented as percent of installed wind capacity, for different
wind penetration levels.
Both accuracy and uncertainty of short-term variations seen by the system. The range of results
forecasts, are important information for system oper- for reserve requirement increase due to wind power
ators, when allocating the reserves needed to manage is wide (Figure 7): increased reserve capacity should
the real-time operation. be 1–15% of installed wind power capacity at 10%
penetration and 4–18% of installed wind power ca-
pacity at 20% penetration.1 Timescales used in the
Frequency Control and Reserves estimation explain much of the differences in results
The reserve requirement addresses the more short- as can be seen from German results from 2010 that
term flexibility for power plants that can follow un- calculate the reserve requirement based on either day-
predicted net load variations. Wind power will also ahead, 4 h ahead or hour-ahead uncertainties.32 Ger-
increase the need for flexibility for power plants that man Dena estimates only show the average day-ahead
can follow the scheduled net load. Operational prac- uncertainty (for up and down reserves separately).26
tices, such as markets scheduling on hourly level or In Minnesota33 and California,34 day-ahead uncer-
scheduling at 5–15 min, will also have an impact tainty has been included in the estimate. UK study35
on how much reserves are needed during the op- combines the 4 h ahead variability of wind to load
erating hour. Experience shows that when reaching uncertainty–using wind forecasting would give lower
penetration levels of 5–10%, an increase in the use results.1 For others, the effect of variations during the
of short-term reserves is observed, especially for re- operating hour is considered,36 with Ireland37 and
serves activated on 10–15 min timescale. So far, no Sweden38 including the 4 h ahead uncertainty sepa-
new reserve capacity has been built specifically for rately. All studies show increasing trend of reserve
wind power.8,30 In Portugal and Spain, new pumped requirements as wind penetration increases. Even if
hydro is planned to be built to increase the flexibil- the aggregation benefits of wind power can decrease
ity of the power system, and this is mainly driven by the reserve requirements, in the studies it is often as-
wind power to enable more than 15% penetration sumed that the smoothing effect reaches its maximum
levels.11 In the highest wind penetration countries— already at lower penetration levels, and adding wind
Denmark, Spain, and Portugal—no significant fre- in the same area will no longer decrease the variability
quency impacts have been observed that are the result nor forecast error levels.
of wind-power variation.31 With high wind penetration, it will be beneficial
In wind integration studies, the increase in to allocate reserve requirements dynamically. If allo-
short-term reserve requirement is mostly estimated cation is estimated once a day for the next day instead
by comparing the reliability of the system before and of using same reserve requirement for all days, the low
after the addition of wind. A basic approach is to com- wind days will induce less requirements for the system
bine the variability or forecast errors of wind power and thus the reserve allocation can be increased only
with that of load and in some cases also power plant for days when wind variability and uncertainty are at
outages, and to investigate the increase in the largest highest.15,30
248
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration
Increasing reserve requirement is usually calcu- Increase in balancing costs at wind penetrations
lated for the extreme cases. Even if there is increase in of up to 20% amounted to roughly 1–4 €/MWh of
reserve requirements, this does not necessarily mean wind power produced.1,33,35–37,45,47–51 If intercon-
new investments for reserve capacity, rather genera- nection capacity is allowed to be used also for balanc-
tors that were formerly used to provide energy could ing purposes, the balancing costs are lower compared
now be used to provide reserves.1 to the case where balancing is made only in the area—
increasing area size will have aggregation benefits of
wind power and also add more balancing power. The
Electricity Markets two points for Greennet Germany and Denmark45 at
There is good experience from Denmark, Spain, Ire-
the same wind penetration level reflect that balancing
land, and New Zealand with balancing wind power
costs increase when neighboring countries get more
variations through forecasting and liquid day-ahead
wind52 (Figure 8).
and balancing markets.39 For West Denmark, the bal-
Not all case studies presented results quantified
ancing cost from the Nordic day-ahead market has
as MW of increase in reserve requirements or mone-
been 1.4–2.6 €/MWh for a 24% wind penetration of
tary values for increase in balancing costs. The Irish
gross demand.1
All Island Grid Study shows that the net benefit for the
There is already some experience on how wind
power systems, going from 2 to 6 GW wind, will be
power impacts the day-ahead electricity market prices
€13/MWh, as the operational costs of the electricity
during hours with a lot of wind, the market prices
system fall compared to the base case.18
are lowered as wind energy displaces power sources
with higher marginal costs.40–42 At high wind penetra-
tions, wind power will increase the volatility in mar-
ket prices as wind energy will not always be available CURTAILMENTS OF WIND POWER
to displace higher marginal cost generators.43 In the GENERATION
long run, however, the average effect of wind energy
Challenging situations seen in system operation so
on wholesale electricity prices is not as clear because
far are from high wind-power generation during low-
the relationships between investment costs, operation
load situations, when wind power penetration lev-
and maintenance costs, and wholesale price signals
els exceed 50%.11 Wind is usually last to be cur-
will begin to influence decisions about the expansion
tailed. However, when all other units are already
of transmission interconnections, conventional gener-
at minimum (and some shut down) system opera-
ator retirement, and the type of new generation that
tors sometimes need to curtail wind power to control
is built.10,40
frequency.8 Denmark has solved part of the curtail-
ments by increasing flexible operation of combined
heat and power plants and by lowering the minimum
BALANCING COSTS OF WIND POWER generation levels used in the thermal plants.1
Balancing costs reflect increased use of reserves and In Ireland, some curtailments have been due to
less efficient scheduling of conventional power plants. concerns of low inertia53 and consequently suscep-
Impact on efficiency of conventional power plants tibility to instability in the system because of high
needs simulations of power system scheduling and instantaneous wind penetration and low system load.
dispatch and they are mostly based on comparing Currently, the issue of low inertia is unique to small
costs of system operation without wind and adding systems such as Ireland and Crete in Greece.3 In Ire-
different amounts of wind. The studies show a signif- land, they are working on solutions to go up to 75%
icant reduction of operational costs (fuel usage and penetration levels.17
costs) due to wind power even at higher penetration
levels so the integration effort will not offset the emis-
sion savings of wind power.44 To capture the integra- Does Wind Integration Need Storage?
tion cost means capturing the difference of full credit Storage is nearly always beneficial to the grid, but this
for operating cost reduction compared with cost for benefit must be weighed against its cost. All variation
system operation with efficiency penalties due to in- and uncertainty in power systems is being handled
creased variability and uncertainty. One way of cap- in power system level. This is because of lower costs
turing cost of variability is by comparing simulations when variability is aggregated before being balanced.
with flat wind energy to varying wind energy.33,45 Storage is most economic when operated to maximize
However, the two simulated cases can also result in the economic benefit for the entire system. Additional
other cost differences than just the variability cost.46 wind generation could increase the value of energy
F I G U R E 8 | Results from estimates for the increase in balancing and operating costs due to wind power for different wind penetration levels.
The currency conversion used here is 1 € = 0.7 £ and 1 € = 1.3 US$. For UK, according to a 2007 study, the average cost is presented here, the
range in the last point for 20% penetration level is from 2.6 to 4.7 €/MWh.35
storage in the grid as a whole, but storage would Wind power is normally not the only driving
continue to provide its services to the grid.2 force for grid investments but it is a major fac-
There are many studies that specifically looked tor (Ireland,59 Germany,60 Europe,61 and the United
at the cost effectiveness of electricity storage to as- States,62 ).24 The cost of grid reinforcements due
sist in integrating wind.54–58 These studies found that to wind power is very dependent on where the
for wind penetration levels up to 30% the cost effec- wind power plants are located relative to load and
tiveness of building new electricity storage is still low grid infrastructure. Portugal reported million 145 €
for other options than hydropower with large reser- (70 €/kW) increase in grid infrastructure investments
voirs and pumped hydro. With higher wind penetra- in the period 2004–2009 for increasing wind pene-
tion levels the extra flexibility that energy storage can tration from 3% (1400 MW) to 13% wind energy
provide will be beneficial for the power system op- penetration (3500 MW).24 In several studies grid re-
eration, provided it is economically competitive with inforcement costs roughly vary from 0 €/kW to 270
other forms of flexibility, e.g., from thermal power €/kW reflecting different systems, countries, grid in-
plants and demand side. frastructure, and calculation methodologies.1
A challenge for transmission planning is to re-
solve the scheduling conflict where wind plants can
WIND IMPACTS ON TRANSMISSION
be permitted and constructed in 2–3 years and it
GRID may take 5–10 years to plan, permit, and construct
Grid planning for future wind energy targets brings a transmission line. Some transitional solutions can
needs to reinforce the grid as well as building new allow wind power plants to connect to the existing
lines, both inside the country/region as well as inter- grid even if there will be times when the grid is not
connection to neighboring countries/regions. Trans- strong enough to transmit all generation produced.3
mission is important both for enabling transfer of Dynamic line ratings, taking into account the cooling
the generated electricity to loads but is also required effect of the wind together with ambient temperature
to gain aggregation benefits in variability and uncer- in determining the transmission constraints, can in-
tainty of wind power. To assess the impacts of wind crease transmission capacity and delay the need for
power to the transmission grid involves steady-state network expansion. By curtailing the generation in
load flow and transient stability simulations of the critical situations, grid equipment such as overhead
network for specific snapshots situations. Network lines or transformers can be protected from over-
contingency situations are studied to meet the criteria loads. As wind power will produce most of the time
of power system operation and safety established by at part load, the critical situations often result in only
the system operator. small production losses and in these cases it can be
250
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration
F I G U R E 9 | Capacity credit of wind power, results from eight studies.1,26,33,66,67 The Ireland estimates were made for two power system
configurations, with 5 GW and 6.5 GW peak load.
cost effective to curtail and thus lower the connection some capacity to be relied upon during peak loads.
costs.63 However, these transitional solutions are in- Ensuring power adequacy is typically done using reli-
sufficient for large amounts of wind power and can ability analysis, which is based on loss of load proba-
result in high curtailments, such as in Texas with 17% bility (LOLP) or loss of load expectation (LOLE). The
of all potential wind energy generation curtailed in use of these approaches allows the system planner to
2009.64 determine the power adequacy level and also the con-
tribution that each generating plant makes toward
Wind Power Impacts on Stability resource adequacy, called capacity credit or capacity
There will be technical and operational implications value.2,65 The availability of high-quality chronolog-
for the power system at times of high shares of ical synchronized data that captures the correlation
wind power. The power system should sustain dis- with load data is of paramount importance and the
turbances, such as the loss of largest power plant or robustness of the calculations is highly dependent on
line so that the frequency and voltage remain stable. the volume of this data.
Wind power is asynchronous generation that does not So far, wind power has been built as additional
have the same inherent, physical support to the power generation to power systems, and thus no problems
system inertia as synchronous machines. In the small with having adequate power capacity to cover peak
island system of Ireland, the issues to enable more loads have been reported.8
than 30% wind penetration level has been studied.17 The results from studies estimating the capac-
The issues that could be mitigated were power bal- ity value for wind power range from 5% to 40%
ancing with instantaneous reserves, voltage stability, of wind-rated capacity (Figure 9). The wide range of
transient, and small-signal stability. The fundamen- capacity credit assigned to wind reflects the differ-
tal issues regarding frequency stability when losing ences in the timing of wind energy delivery (when the
a large unit or power line as well as large amounts wind blows) relative to system peak loads.66 Aggre-
of wind power tripping during network faults need gating larger areas benefits the capacity credit of wind
further analyses. power.1,67
In some reports the term ‘capacity cost’ is used.
The meaning of this is the cost for the difference
between lower capacity credit for wind power and
CAPACITY VALUE OF WIND POWER higher capacity credit for a conventional power plant.
Power system planning includes determining genera- It is not straightforward to calculate how a ‘re-
tion capacity needs for the future. Wind power is often duced value’ transforms to a cost for wind power.
considered as an energy source, but it can also provide It is important to use the lowest investment cost
generating capacity as back-up not to overestimate offset the emission savings of wind power. The capac-
this cost.68 ity value of wind power is less than for conventional
power plants and will reduce at higher penetration
levels.
Reaching high wind penetration levels chal-
CONCLUSION AND OUTLOOK
lenges generation owners and transmission operators
The natural variability of wind power makes it dif- to better utilize technology and existing assets to pro-
ferent from other generating technologies. This raises vide flexibility. More flexibility from the nonwind
questions about how wind power can be successfully generation fleet would include reduced minimum gen-
integrated into the grid. Power systems are equipped eration levels, greater ramp rates, quicker start times,
to handle variability and uncertainty that comes from and designs that allow frequent cycling without in-
the load. There is already a lot of experience of op- creasing material fatigue or reducing component life-
erating power systems with large amounts of wind times. This will require incentives or requirements and
power and integration studies have also offered valu- markets and tariffs also need to be designed to reward
able insights into how high wind penetrations can be increased flexibility. Integrating wind power genera-
successfully achieved. Model and tool development is tion into power systems can be aided by enlarging
still required to study how entire power systems can balancing areas and moving to subhourly scheduling,
be operated with occasionally high penetration levels which enable grid operators to access a deeper stack
at 60–80% of load. of generating resources and to take advantage of the
Wind integration means investments in grid in- smoothing of wind power output due to geographic
frastructure and increased use of balancing power diversity. The on-going developments on smart grids,
that can lead to efficiency losses in power plants. demand response, and plug-in hybrids as well as con-
There will be significant reduction of operational tinued improvements in new conventional-generation
costs (fuel usage and costs) due to wind power even at technologies will give new opportunities for wind in-
higher penetration levels so integration effort will not tegration.
ACKNOWLEDGMENTS
This work is part of International Energy Agency Implementing Agreement for Wind Energy
(IEAWIND) research collaboration Task 25 Design and Operation of Power Systems with Large
Amounts of Wind Power http://www.ieawind.org/AnnexXXV.html. All participating members
are greatly acknowledged for providing information on wind integration studies and experience.
Juha Kiviluoma is acknowledged for his comments on the text.
REFERENCES
1. Holttinen H, Meibom P, Orths A, van Hulle F, Power M, et al. Integration of RE into electric power
Lange B, O’Malley M, Pierik J, Ummels B, Tande JO, systems. In: Edenhofer O, Pichs-Madruga R, Sokona
Estanqueiro A, et al. Design and operation of power Y, Seyboth K, Matschoss P, Kadner S, Zwickel T,
systems with large amounts of wind power. Final re- Eickemeier P, Hansen G, Schlömer S, et al., eds. Spe-
port, IEA WIND Task 25. VTT Tiedotteita—Research cial Report on Renewable Energy Sources and Climate
Notes 2493. Phase one 2006–2008. Espoo, VTT; Change Mitigation. Cambridge/New York, NY: Cam-
2009. 200 p. + app. 29 p. Available at: http://www. bridge University Press; 2011, p. 1075.
vtt.fi/inf/pdf/tiedotteet/2009/T2493.pdf. (Accessed 4. Lundsager P, Baring-Gould I. Isolated systems with
May 14, 2012). wind power. In: Ackermann T, ed. Wind Power in
2. Milligan M, Porter K, DeMeo E, Denholm P, Holt- Power Systems. Chichester, England: John Wiley &
tinen H, Kirby B, Miller N, Mills A, O’Malley Sons; 2005, Ch. 14.
M, Schuerger M, et al. Wind power myths de- 5. Caralis G, Zervos A. Analysis of the combined use
bunked. IEEE Power Energy Mag 2009, 7:89–99. of wind and pumped storage systems in autonomous
DOI: 10.1109/MPE.2009.934268. Greek islands. Renew Power Gener 2007, 1:49–60.
3. O’Malley M, Flynn D, Holttinen H, Outhred H, van 6. International Energy Agency. Empowering variable
Hulle F, Bazilian M, Denny E, Infield D, Keane A, renewables. options for flexible electricity systems;
252
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration
2008. Available at: http://www.iea.org/g8/2008/ 18. All Island Grid Study. Workstream 4: Analysis of Im-
Empowering_Variable_Renewables.pdf. (Accessed pacts and Benefits. Dublin, Ireland: Department of
May 14, 2012). Communications, Energy and Natural Resources and
7. International Energy Agency. Harnessing Variable Re- UK Department of Enterprise, Trade and Investment;
newables: a Guide to the Balancing Challenge. Paris, 2008, 82.
France: OECD/IEA; 2011. Available at: www.iea.org. 19. Holttinen H. Overview of integration studies—
(Accessed May 14, 2012). methodologies and results. In: Ackermann T,
8. Söder L, Hofmann L, Orths A, Holttinen H, Wan ed. Wind Power in Power Systems. 2nd Ed.
Y.-H, Tuohy A. Experience from wind integration in John Wiley & Sons; 2011 (In press). Available
some high penetration areas. IEEE Trans Energy Con- at: http://www.windpowerinpowersystems.info. (Ac-
vers 2007, 22:4–12. cessed May 14, 2012).
9. EirGrid, Annual renewable report: powering a sus- 20. EWIS European Wind Integration Study. Towards
tainable future. Dublin, Ireland: Eirgrid; 2010, 32. a successful integration of wind power in European
Available at: http://www.eirgrid.com/media/Annual electricity grids. Final Report TREN/07/FP6EN/
%20Renewable%20Report%202010.pdf. (Accessed S07.70123/038509, 2010, 182. Available at: http://
May 14, 2012). www.wind-integration.eu/downloads/library/EWIS_
10. Wiser R, O’Malley M, Infield D, Smith JC, Holttinen Final_Report.pdf. (Accessed May 14, 2012).
H. Near-term grid integration issues. In: IPCC Spe- 21. van Hulle F, Tande JO, Uhlen K, Warland L,
cial Report on Renewables (SRREN). Cambridge/New Korpås M, Meibom P, Sörensen P, Morthorst PE,
York, NY: Cambridge University Press. 2011, Cutululis N, Giebel G, et al. Tradewind Integrat-
Ch. 7.5. ing Wind, Developing Europe’s Power Market for
11. Estanqueiro A, Mateus CB, Pestana R. Operational the Large Scale Integration of Wind. Brussels, Bel-
experience of extreme wind penetrations. In: Pro- gium: Tradewind; 2009. Available at: http://www
ceedings of the 9th International Workshop on .trade-wind.eu/fileadmin/documents/publications/Final
Large-Scale Integration of Wind Power into Power _Report.pdf. (Accessed May 14, 2012).
Systems as well as on Transmission Networks 22. EWITS (Eastern Wind Integration and Transmis-
for Offshore Wind Power Plants. Québec City, sion Study). Prepared for the National Renewable
Canada: Energynautics; 2010, 34–39. Available at: Energy Laboratory by EnerNex, 2011, 242. Avail-
www.windintegrationworkshop.org. (Accessed May able at: http://www.nrel.gov/docs/fy11osti/47078.pdf.
14, 2012). (Accessed May 14, 2012).
12. Morales A, Robe X, Sala M, Prats P, Aguerri C, Tor- 23. Western Wind and Solar Integration Study. Prepared
res E, Advanced grid requirements for the integration for NREL by GE Energy. Golden, CO: National Re-
of wind farms into the Spanish transmission system, newable Energy Laboratory; 2010, 536 . Available
Renew Power Gener 2008, 2:47–59. at: http://www.nrel.gov/wind/systemsintegration/wwsis
13. Smith JC, Milligan M, DeMeo E, Parsons B. Utility .html. (Accessed May 14, 2012).
wind integration and operating impact state of the art. 24. Smith JC, Osborn D, Zavadil R, Lasher W, Gómez-
IEEE Trans Power Syst 2007, 22:900–908. Lázaro E, La Mancha C, Trötscher T, Tande
14. Söder L, Holttinen H. On methodology for modelling JO, Korpås M, Van Hulle F, et al. Transmission
power system impact on power systems. Int J Global planning for wind energy: status and prospects.
Energy Issues 2008, 29:181–198. In: Proceedings of the 9th International Workshop
15. Milligan M, Ela E, Lew D, Corbus D, Wan Y. Ad- on Large-Scale Integration of Wind Power into
vancing wind integration study methodologies: impli- Power Systems as well as on Transmission Net-
cations of higher levels of wind. In: Presented at Wind- works for Offshore Wind Power Plants. Québec City,
Power. Dallas, TX; 2010. Available as NREL/CP- Canada: Energynautics; 2010, 371–382. Available at:
550-48944, 46 p. Available at: http://www.nrel.gov/ www.windintegrationworkshop.org. (Accessed May
docs/fy10osti/48944.pdf. (Accessed May 14, 2012). 14, 2012).
16. Corbus D, Schuerger M, Roose L, Strickler J, 25. Tsili M, Papathanassiou S. A review of grid code
Surles T, Manz D, Burlingame D, Woodford D. technical requirements for wind farms. Renew Power
Oahu wind integration and transmission study: sum- Gener 2009, 3:308–332.
mary report, 2010. NREL/TP-5500-48632. Available 26. Dena. Planning of the grid integration of wind
at: http://www.nrel.gov/docs/fy11osti/48632.pdf. (Ac- energy in Germany onshore and offshore up to
cessed May 14, 2012). the year 2020 (Dena Grid study), 2005 Deutsche
17. EirGrid. All island TSO facilitation of renewables Energie-Agentur Dena, March 2005. English sum-
studies, prepared for Eirgrid by Ecofys. Dublin, mary and full German version. Available at: http://
Ireland: Eirgrid; 2010, 77 pp. Available at: http://www. www.dena.de/fileadmin/user_upload/Publikationen/
eirgrid.com/renewables/facilitationofrenewables/. (Ac- Energiedienstleistungen/Dokumente/dena-grid_study
cessed May 14, 2012). _summary.pdf. (Accessed May 14, 2012).
27. FERC Federal Energy Regulatory Commission, US. 36. Holttinen H. The impact of large scale wind power pro-
Order 661-A. Available at: http://www.ferc.gov/ duction on the Nordic electricity system. PhD disserta-
industries/electric/indus-act/gi/wind.asp. (Accessed De- tion. VTT Publications 554. Espoo, Finland; VTT Pro-
cember 12, 2005). cesses, 2004, 82 p. + app. 111 p. Available at: http://
28. Giebel G, Brownsword R, Kariniotakis G, Dernhard www.vtt.fi/inf/pdf/publications/2004/P554.pdf. (Ac-
M, Draxl C. The state of the art in short-term cessed May 14, 2012).
prediction of wind power: a literature overview. 37. ILEX, UCD, QUD, UMIST. Operating reserve require-
Deliverable D-1.2 of Anemos.plus, 2011. Avail- ments as wind power penetration increases in the Irish
able at: http://www.prediktor.dk/publ/GGiebelEtAl- electricity system. Dublin, Ireland: Sustainable Energy
StateOfTheArtInShortTermPrediction_ANEMOSplus_ Ireland; 2004.
2011.pdf. (Accessed May 14, 2012). 38. Axelsson U, Murray R, Neimane V. 4000 MW wind
29. Lange M, Focken U, Meyer R, Denhardt M, Ernst B, power in Sweden—impact on regulation and reserve
Berster F. Optimal combination of different numerical requirements. Elforsk Report 05:19, Stockholm; 2005.
weather models for improved wind power predictions. Available at: http://www.elforsk.se. (Accessed May 14,
In: Sixth International Workshop on Large-Scale Inte- 2012).
gration of Wind Power and Transmission Networks 39. Ackermann T, Ancell G, Diness Borup L, Børre Eriksen
for Offshore Wind Farms. Delft, The Netherlands; P, Ernst B, Groome F, Lange M, Möhrlen C, Orths AG,
2006. O’Sullivan J, et al. Where the wind blows. IEEE Power
30. Gil A, de la Torre M, Dominguez T, Rivas R. Influence Energy Mag 2009, 72009:65–75.
of wind energy forecast in deterministic and proba- 40. Sensfuß F, Ragwitz M, Genoese M. The merit-order
bilistic sizing of reserves. In: Proceedings of the 9th effect: a detailed analysis of the price effect of renew-
International Workshop on Large-Scale Integration of able electricity generation on spot market prices in Ger-
Wind Power into Power Systems as well as on Trans- many. Energy Policy 36:3076–3084.
mission Networks for Offshore Wind Power Plants.
41. Munksgaard J, Morthorst PE. Wind power in the Dan-
Québec City, Canada: Energynautics; 2010, 83–
ish liberalized power market—policy measures, price
88. Available at: www.windintegrationworkshop.org.
impact and investor incentives. Energy Policy 2008,
(Accessed May 14, 2012).
36:3940–3947.
31. Eto, Undrill JH, Mackin J, Daschmans P, Williams
42. Clifford E, Clancy M. 2011. Impact of wind gen-
R, Haney B, Hunt B, Ellis R, Illian J, Martinez HC,
eration on wholesale electricity costs in 2011 SEI
et al. Use of frequency response metrics to assess the
and Eirgrid, 2011. Available at http://www.seai.ie/
planning and operating requirements for reliable
Publications/Statistics_Publications/Energy_Modelling
integration of variable renewable generation.
_Group/Impact_of_Wind_Generation_on_Wholesale_
Lawrence Berkeley National Laboratory, LBNL-
Elec_Costs/Impact_of_Wind_Generation_on_Wholesa
4142E, Berkeley, CA; 2010.
le_Electricity_Costs_in_2011.pdf.
32. Dobschinski J, De Pascalis E, Wessel A, von Bremen L,
43. Jónsson T, Pinson P, Madsen H. On the market impact
Lange B, Rohrig K, Saint-Drenan Y-M. The potential
of wind energy forecasts. Energy Econ 2010, 32:313–
of advanced shortest-term forecasts and dynamic pre-
320.
diction intervals for reducing the wind power induced
reserve requirements. In: European Wind Energy Con- 44. UKERC, 2006. The costs and impacts of intermittency:
ference EWEC’2010. Warsaw, Poland; 2010. an assessment of the evidence on the costs and impacts
of intermittent generation on the British electricity net-
33. EnerNex/WindLogics 2006. Minnesota Wind Integra-
work. Imperial College, London: Energy Research Cen-
tion Study Final Report. Vol I. Prepared for Minnesota
tre; 2006. ISBN 1 90314 404 3.
Public Utilities Commission, Nov. 2006. Available
at: http://www.puc.state.mn.us/portal/groups/public/ 45. Meibom P, Weber C, Barth R, Brand H. Operational
documents/pdf_files/000664.pdf. (Accessed May 14, costs induced by fluctuating wind power production in
2012). Germany and Scandinavia. Renew Energy Gener 2009.
3:75–83.
34. Porter K, Intermittency Analysis Project Team. Inter-
mittency Analysis Project: Summary of Final Results. 46. Milligan M, Kirby B. Calculating wind integra-
California Energy Commission, PIER Research Devel- tion costs: separating wind energy value from inte-
opment & Demonstration Program. 2007. CEC-500- gration cost impacts. NREL Technical report TP-
2007-081. Available at: http://www.uwig.org/CEC 550-46275; 2009. Available at: http://www.nrel.gov/
-500-2007-081.pdf. docs/fy09osti/46275.pdf. (Accessed May 14, 2012).
35. Strbac G, Shakoor A, Black M, Pudjianto D, Bopp T. 47. Ilex Energy, Strbac G. Quantifying the system costs of
Impact of wind generation on the operation and de- additional renewables in 2020. DTI 2002.
velopment of the UK electricity systems. Electr Power 48. Zavadil R. Wind integration study for public ser-
Syst Res 77:1143–1238. vice company of Colorado. 2006. Available at:
254
c 2012 John Wiley & Sons, Ltd. Volume 1, November/December 2012
WIREs Energy and Environment Wind integration