CHAPTER 2 - Project Life Cycle and Integration Management
CHAPTER 2 - Project Life Cycle and Integration Management
1
CHAPTER 2
Project life cycle
And
Project Integration Management
2
By the end of this chapter, you should be able to
❑ Explain how the project life cycle differs from the product life cycle
4
Characteristics of the project life cycle
▪ Cost and staffing levels are low at the start, increase as the work is carried out, and drop
rapidly as the project draws to a close.
▪ Risk is greatest at the start of the project. These factors decrease over the life cycle of the
project as decisions are reached and as deliverables are accepted.
▪ The cost of making changes and correcting errors typically increases substantially as the
project approaches completion.
5
Characteristics of the project life cycle
▪ Cost and staffing levels are low at the start, increase as the work is carried out, and drop
rapidly as the project draws to a close.
▪ Risk is greatest at the start of the project. These factors decrease over the life cycle of the
project as decisions are reached and as deliverables are accepted.
▪ The cost of making changes and correcting errors typically increases substantially as the
project approaches completion.
6
Characteristics of the project life cycle (cont’d)
STARTING ORGANISING CLOSING
CARRYING OUT THE WORK
THE PROJECT & PREPARING THE PROJECT
Resources
Utilized
TIME
PROJECT Project Archived
MGT Project Accepted
Management Project
OUTPUTS Charter Deliverables
Plan Documents
7
Characteristics of the project life cycle
▪ Cost and staffing levels are low at the start, increase as the work is carried out, and drop
rapidly as the project draws to a close.
▪ Risk is greatest at the start of the project. These factors decrease over the life cycle of the
project as decisions are reached and as deliverables are accepted.
▪ The cost of making changes and correcting errors typically increases substantially as the
project approaches completion.
8
Characteristics of the project life cycle (cont’d)
STARTING ORGANISING
CARRYING OUT THE WORK CLOSING
THE PROJECT & PREPARING
THE PROJECT
High
Low
TIME
9
Characteristics of the project life cycle
▪ Cost and staffing levels are low at the start, increase as the work is carried out, and drop
rapidly as the project draws to a close.
▪ Risk is greatest at the start of the project. These factors decrease over the life cycle of the
project as decisions are reached and as deliverables are accepted.
▪ The cost of making changes and correcting errors typically increases substantially as the
project approaches completion.
10
Characteristics of the project life cycle (cont’d)
STARTING ORGANISING
CARRYING OUT THE WORK CLOSING
THE PROJECT & PREPARING
THE PROJECT
High
Cost of change
Low
TIME
11
Project & Product life cycle
12
Project Phases
▪ The number of phases, the need for phases, and the degree of control applied
▪ Project phases typically are completed sequentially, but can overlap in some project
situations
13
Project Phases (cont’d)
Sequential
relationship
14
Project Phases: example
Sequential
relationship
15
Project Phases
Overlapping
relationship
16
Project Phases: example
Overlapping
relationship
17
Project Phases: example
18
Milestones & Deliverables
19
Project Management Process Groups
Project management is composed of five process groups:
▪ Initiating Process Group
▪ Planning Process Group
▪ Executing Process Group
▪ Monitoring and Controlling Process Group
▪ Closing Process Group
20
Project Management Process Groups
Describe the interactions between project process groups and project management knowledge areas
Knowledge Areas Project Management Process Groups
Initiating Process Group Planning Process Group Executing Process Group Monitoring and Controlling Process Closing Process Group
Group
Project Integration - Develop Project Charter - Develop Project Management Plan - Direct and Manage Project Work - Monitor and Control Project Work - Close Project or Phase
Management - Perform Integrated Change Control
Project Scope - Plan Scope Management - Validate Scope
Management - Collect Requirements - Control Scope
- Define Scope
- Create WBS
Project Time - Plan Schedule Management - Control Schedule
Management - Define Activities
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
Project Procurement - Plan Procurement Management - Conduct Procurements - Control Procurements - Close Procurements
Management
Project Stakeholder - Identify Stakeholders - Plan Stakeholder Management - Manage Stakeholder Engagement - Control Stakeholder Engagement
Management 21
Project Management Process Groups : Example
Number Questions Answers
1 If you want to begin to “Collect Requirements”, which process
or processes should you complete before doing that?
2 “Validate Scope” is part of what Process Group?
3 I am starting “Estimate Activity Durations”. What process should I
have completed?
4 The “Direct and Manage Project Work” process is in what
Knowledge Area?
5 After completing the “Identify Risks” process, which process
should follow?
6 In what Process Group would you perform the “Conduct
Procurement” process
22
Project Integration
Management
23
Project Integration Management
24
Project Integration Management processes
Inputs Processes Outputs
Deliverables
Project management plan Direct and Manage Project
Change requests
Approved change requests Work
Work performance data
25
Project Charter
▪Developing the project charter involves working with stakeholders to create the
document that formally authorizes a project —the charter.
▪A project charter is a document that formally recognizes the existence of a project and
provides direction on the project’s objectives and management.
26
Project Charter (cont’d)
27
Project Charter (cont’d)
28
Project Charter (cont’d)
29
Project Charter (cont’d)
30
Project management plan
▪ Developing the project management plan involves coordinating all planning efforts to
create a consistent and coherent document—the project management plan.
▪ A project management plan is the document that describes how the project will be
executed, monitored, and controlled.
▪ Plans created in the other knowledge areas are subsidiary parts of the overall project
management plan.
31
Project management plan (cont’d)
32
Project Integration Management
▪ Better control over the project in terms of time, budget and any deviation from
the scope
33