Chapter 5
Chapter 5
Quản lý Dự án
Dr. TRAN QUYNH LE
Dr. NGUYEN DUC DUY
Industrial Systems Engineering Department
Mechanical Engineering Faculty
Ho Chi Minh City University of Technology (HCMUT)–
VNUHCM
Chapter 5
Estimating Project Times and Costs
2
3
LEARNING OUTCOME
4
Estimating Projects
▪ Estimating
• The process of forecasting or approximating the time and cost of completing
project deliverables.
• The task of balancing the expectations of stakeholders and the need for
control while the project is implemented
▪ Types of Estimates
• Top-down (macro) estimates: analogy, group consensus, or mathematical
relationships
• Bottom-up (micro) estimates: estimates of elements of the work breakdown
structure
5
Why Estimating Time and Cost Are Important
6
Factors Influencing the Quality of Estimates
Planning
Horizon
Quality of
Organization Estimates People
Culture
7
Estimating Guidelines for Times, Costs, and Resources
8
Macro versus Micro Estimating
9
Estimating Projects: Preferred Approach
10
Methods for Estimating Project Times and Costs
11
Methods for Estimating Project Times and Costs (cont’d)
5. Learning curves
➢ also known as improvement curve, experience curve, and industrial progress curve
➢ Each time the output quantity doubles, the unit labor hours are reduced at a
constant rate
12
Learning curves
13
Some examples of
learning curves in
industry.
15
Learning Curves for Estimating
For example, assume that a manufacturer has a new contract for 16 prototype
units and a total of 800 labor hours were required for the first unit.
Past experience has indicated that on similar types of units the improvement
rate has been 80 percent.
This relationship of improvement in labor hours is shown below:
Or: 800*0.4096=328
16
Learning Curves for Estimating
▪ That is, the 16th unit should require close to 328 labor hours, assuming an 80
percent improvement ratio.
▪ Compute the cumulative total labor hours of all units.
▪ The first 16 units, the total labor hours required would be:
800x 8.920=7,136 hours
17
Learning Curves Unit Values
18
Learning Curves Cumulative Values
19
Apportion Method of Allocating Project Costs Using the Work
Breakdown Structure
20
Simplified Basic Function Point Count Process for a Prospective
Project or Deliverable
21
Example: Function Point Count Method
TABLE 5.3
22
Methods for Estimating Project Times and Costs (cont’d)
23
SB45 Support Cost Estimate Worksheet
24
Phase Estimating over Product Life Cycle
25
Top-Down and Bottom-Up Estimates
26
Level of Detail
27
Developing Budgets
▪ Time-Phased Budgets
• A cost estimate is not a budget unless it is time-phased.
➢ Time phasing begins with the time estimate for a project.
➢ Time-phased budgets mirror how the project’s cash needs (costs) will occur or
when cash flows from the project can be expected.
➢ Budget variances occur when actual and forecast events do not coincide.
28
Work Package Estimates
FIGURE 5.4
29
Three Views of Cost
30
Types of Costs
▪ Direct Costs
• Costs that are clearly chargeable to a specific work package.
➢ Labor, materials, equipment, and other
▪ Direct (Project) Overhead Costs
• Costs incurred that are directly tied to an identifiable project deliverable or work
package.
➢ Salary, rents, supplies, specialized machinery
▪ General and Administrative Overhead Costs
• Organization costs indirectly linked to a specific package that are apportioned to
the project
31
Contract Bid Summary Costs
32
Refining Estimates
▪ Reasons for Adjusting Estimates
• Interaction costs are hidden in estimates.
• Normal conditions do not apply.
• Things go wrong on projects.
• Changes in project scope and plans.
▪ Adjusting Estimates
• Time and cost estimates of specific activities are adjusted as the risks, resources,
and situation particulars become more clearly defined.
33
Refining Estimates (cont’d)
34
Creating a Database for Estimating
35
Key Terms
36
This Page Intentionally Left Blank
37