Project Progress Weightage Formula
Project Progress Weightage Formula
(Duration elapsed × Total remaining amount) + (Remaining amount × Duration elapsed × 100)
Project Progress =
2 × Total remaining amount × Duration × (1 − Percentage of Progress)
However, for a more general progress formula, let's look at two components: earned value and planned
value.
Elapsed time
PV = × Total project budget
Total time
2. Earned Value (EV): This is the value of the work that has actually been completed up to a certain
point. It reflects the progress made on the project. It can be calculated as:
Elapsed time
EV = × Total project budget completed so far
Total time
3. Cost Performance Index (CPI): This measures cost efficiency and is defined as:
EV
CP I =
AC
4. Schedule Performance Index (SPI): This measures schedule efficiency and is defined as:
EV
SP I =
PV
5. Project Progress: Based on the combined view of schedule and cost, the progress can be assessed
as a weighted average of these indices.
In your formula:
Where:
? is a variable that could represent a progress factor, possibly related to the percentage of work
completed or a certain phase of progress.
This formula might be an approximation or a variant of a more standard weighted formula for project
progress, combining elapsed time and remaining work in a non-linear way. The inclusion of 100 could
be an attempt to scale the formula for percentages.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 1/13
3/13/25, 8:38 PM Project Progress Weightage Formula
Given:
Progress = 25.31%
So, the project progress would be approximately 25.31% based on the given inputs.
Conclusion
While the formula you've provided is not a standard or commonly used project progress formula, it
seems to be a customized approach. The derivation we went through suggests that this formula is likely
designed to give a weighted measure of project progress by considering both time elapsed and work
remaining. If you are looking for a more conventional method, Earned Value Management (EVM)
formulas might be more widely applicable in project progress tracking.
Let me know if you'd like a deeper dive into EVM or if you have further questions about the formula!
Let's delve deeper into the formula you provided and its components to understand its behavior and
meaning.
Formula Breakdown
The formula you presented is:
Here, each term likely represents some aspect of project progress. Let's carefully break down the
components of this formula:
1. Duration: This represents the time already elapsed in the project or a specific phase of it.
2. Total Remaining Amount: This could represent the remaining budget, work, cost, or effort that is
yet to be completed.
3. Remaining Amount: This could represent the remaining value of work, budget, or effort within a
specific scope or component of the project.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 2/13
3/13/25, 8:38 PM Project Progress Weightage Formula
4. Total Duration: This represents the total time allocated for the entire project, from start to
completion.
5. ? (Progress Factor): This is likely a factor that adjusts the calculation based on some form of
progress or completion percentage. For example, if the project is 30% completed, this would be 0.3.
1. Numerator:
This term likely represents the amount of remaining work or cost based on the time already spent in the
project. Essentially, it's a way to factor in how much of the remaining work has been completed,
adjusted by the time already used.
If the project has spent a considerable amount of time (long Duration), the remaining amount of
work/cost would be scaled accordingly, reflecting the progress made so far.
This part of the formula seems to account for the overall scope of the project (Remaining Amount)
scaled by the total duration. The multiplication by 100 might serve to adjust this factor into percentage
form. This term might also be used to account for future progress or remaining tasks' scaling, taking
into consideration how much effort is needed over the total duration.
2. Denominator:
This part likely serves as a scaling factor, designed to normalize the calculation of progress across time
and remaining effort. By multiplying by 2, the formula might aim to emphasize both the elapsed and
remaining work in a balanced manner. The use of "2" could be an arbitrary choice or might be there to
reflect some underlying weighting system.
Second Part: (1 - ?)
This term is a progress adjustment factor. The ? variable might represent the percentage of work
completed so far (for instance, 0.5 for 50% progress, or 0.3 for 30%). By subtracting it from 1, you're
factoring in the portion of work that still needs to be done. This essentially adjusts the formula to make
the progress calculation dynamic — as the project advances, the formula shifts to reflect the progress
achieved.
The use of Duration and Total Remaining Amount in the numerator indicates that the formula takes
into account both the time spent on the project and how much effort is required to finish the remaining
tasks. The denominator normalizes this by factoring in the total project scope and time, adjusted by how
much progress has already been made.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 3/13
3/13/25, 8:38 PM Project Progress Weightage Formula
accordingly. The overall effect will be that the formula considers both the work already completed
and the work still pending.
Example:
Remaining Amount = $200,000 (remaining cost for a specific part of the project)
Simplifying:
Progress = 34.71%
Interpretation of Results
This progress reflects a combination of both elapsed time and remaining cost/work. The calculation
doesn’t just focus on one aspect (time or work remaining) but instead tries to weigh them together,
adjusting based on the progress factor ( ? ).
A higher ? (closer to 1) reduces the total progress result, as most of the work is complete.
A lower ? (closer to 0) keeps the focus on the remaining tasks, thus indicating more progress to be
made.
Conclusion
The formula you provided is a customized or derived approach to calculate project progress, accounting
for both time elapsed and remaining work. It provides a weighted, dynamic estimate of project
completion, adjusting based on the remaining scope and how much work has been completed. While
the formula is not standard across all industries, its approach can be useful when you want a quick
estimate of project progress that balances these factors.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 4/13
3/13/25, 8:38 PM Project Progress Weightage Formula
Given Formula:
((Duration of item i) × (Remaining total amount) + (Remaining item i amount) × (Total duration)) × 100
Weightage =
2 × (Remaining total amount) × (Total duration) × (1−?)
Where:
Remaining total amount = The total cost, budget, or work remaining for the entire project.
Remaining item i amount = The remaining cost, budget, or work for a specific item i.
Numerator:
(Duration of item i) × (Remaining total amount) + (Remaining item i amount) × (Total duration) × 100
The first term (Duration of item i) × (Remaining total amount) suggests that the time allocated
to an item is weighted by the remaining total project effort.
The second term (Remaining item i amount) × (Total duration) suggests that the remaining
effort of an item is scaled relative to the total project duration.
Denominator:
The term (1−?) likely represents the remaining portion of the project to be completed (where ?
represents the completed percentage).
The denominator ensures that the weightage accounts for the entire remaining project work and
duration.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 5/13
3/13/25, 8:38 PM Project Progress Weightage Formula
2. Avoid unnecessary scaling: If the formula works without multiplication by constants like 2 or 100, it
should be simplified.
3. Reflect an intuitive meaning: The formula should clearly indicate why it is structured the way it is.
Possible refinements:
The term 2 × (Remaining total amount) × (Total duration) in the denominator seems arbitrary.
The factor of 2 may not always be needed unless it is part of an empirical adjustment.
The 100 multiplier is only for percentage conversion. If working with fractions, we could omit it.
(Duration of item i) × (Remaining total amount) + (Remaining item i amount) × (Total duration)
Weightage =
(Remaining total amount) × (Total duration) × (1−?)
(Duration of item i) × (Remaining total amount) + (Remaining item i amount) × (Total duration)
Weightage = × 10
(Remaining total amount) × (Total duration) × (1−?)
The formula helps assess the contribution of a specific task to the remaining work, allowing
prioritization.
By comparing the weightage values across different tasks, project managers can decide how
much focus or resources to allocate to each.
The formula can be used to adjust schedules dynamically based on remaining work and time
constraints.
Final Conclusion
The original formula is logically structured but contains unnecessary constants (factor of 2) that do
not necessarily add clarity.
This formula is not a standard project progress formula but can be useful for prioritizing tasks in
the context of resource and cost allocation.
Would you like an example calculation with real values to illustrate its use?
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 6/13
3/13/25, 8:38 PM Project Progress Weightage Formula
Where:
This formula is commonly used for physical progress tracking in construction projects, where work units
(e.g., cubic meters of concrete poured, meters of retaining wall installed) define progress.
Where:
Where:
AC (Actual Cost) = The actual cost incurred for the work performed.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 7/13
3/13/25, 8:38 PM Project Progress Weightage Formula
n
Work Completed for Task i
Total Progress (%) = ∑ ( × Weight of Task i)
Total Work for Task i
i=1
Where:
This is useful when work is evenly distributed over time but does not consider variations in actual work
completion.
Example Calculation
Project Data:
Calculate:
1. Schedule Progress
400, 000
Schedule Progress = ( ) × 100 = 80%
500, 000
2. Cost Progress
400, 000
Cost Progress = ( ) × 100 = 88.89%
450, 000
3. Time-Based Progress
6
Time Progress = ( ) × 100 = 50%
12
Since schedule progress is 80% but time progress is 50%, the project is ahead of schedule.
Conclusion
If you want to track physical work completed, use percentage of work completed.
If you want financial and schedule tracking, use Earned Value Analysis.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 8/13
3/13/25, 8:38 PM Project Progress Weightage Formula
If you want overall project progress based on multiple tasks, use Weighted Progress.
If you want a simple estimation based on time spent, use Time-Based Progress.
Would you like a custom progress tracking method suited for shoring construction projects?
Yes, please.
(Weights should sum to 100% and can be adjusted based on project-specific priorities.)
Excavated so far = 7m
Total Worki
i=1
Example Calculation
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 9/13
3/13/25, 8:38 PM Project Progress Weightage Formula
Finalization 20% 0%
Total Progress = (5% × 100) + (20% × 52.24) + (15% × 40) + (15% × 30) + (25% × 10) + (20% × 0)
= 28.45%
Time-Based Progress
Elapsed Days
Time Progress = ( ) × 100
Total Project Duration
If:
40
Time Progress = ( ) × 100 = 33.33%
120
Interpretation: Since the project progress (28.45%) is lower than time progress (33.33%), the project
is slightly behind schedule.
If:
450, 000
Cost Progress = ( ) × 100 = 90%
500, 000
Interpretation: Since Cost Progress (90%) is higher than Work Progress (28.45%), cost expenditure is
ahead of actual work done—suggesting possible inefficiencies or cost overruns.
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 10/13
3/13/25, 8:38 PM Project Progress Weightage Formula
If Work Progress < Time Progress, accelerate work or adjust the schedule.
If Cost Progress > Work Progress, check cost overruns due to delays, wastage, or inefficiencies.
If any critical activity lags, shift resources, manpower, or extend working hours.
Conclusion
This custom progress tracking method: ✅ Uses weighted activities to reflect real project status.
✅ Compares time, work, and cost progress for better decision-making.
✅ Helps in identifying delays & inefficiencies early.
Would you like a progress tracking template (Excel or software-based)? 🚀
Excel based.
I'll create an Excel-based progress tracking template for your shoring construction project. The
template will include:
I have created the Excel-based progress tracking template for your shoring construction project. You
can download it here:
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 11/13
3/13/25, 8:38 PM Project Progress Weightage Formula
Example: Excavation
13.4
Duration = = 8.93 ≈ 9 days
1.5
Total Work
Duration =
Crew Productivity per Day × No. of Crews
50
Duration = = 6.25 ≈ 7 days
4×2
Total Work
Duration =
Machine Output per Day
800
Duration = = 8 days
100
https://chatgpt.com/c/67d2da3d-e500-8001-af29-2165b6ec24ed 13/13