Schedule Levels From Level 1 To 5

The document outlines the five levels of project schedules, from Level 1 (Executive Summary) to Level 5 (Detail Schedule), detailing their purpose, development, and audience. Level 1 provides a high-level overview of project milestones, while Level 5 focuses on detailed daily tasks for workforce coordination. Each level serves a specific role in project management, ensuring effective planning and execution throughout the project lifecycle.

Uploaded by

Allan Ssemujju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views3 pages

Schedule Levels From Level 1 To 5

The document outlines the five levels of project schedules, from Level 1 (Executive Summary) to Level 5 (Detail Schedule), detailing their purpose, development, and audience. Level 1 provides a high-level overview of project milestones, while Level 5 focuses on detailed daily tasks for workforce coordination. Each level serves a specific role in project management, ensuring effective planning and execution throughout the project lifecycle.

Uploaded by

Allan Ssemujju
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Compiled By Dev M

What Are Schedule Levels From Level 1 to 5

Schedules are typically developed from the top down, but are then maintained from ‘Level
4’ up. Level 5 schedules are temporary documents based on the ‘Look-ahead’ schedule and
used to coordinate work in an area.

Level 1 Schedule:
Executive Summary, also called a Project Master Schedule (PMS). This is a major milestone
type of schedule; usually only one page, it highlights major project activities, milestones, and
key deliverables for the whole project. It is used to summarise the project schedule in reports
and other documents when a more detailed schedule is not required. Frequently developed
by the ‘client’ as part of its initial feasibility studies for the project and then maintained by the
contractor; may be used to assist in the decision making process (go/no-go, prioritization and
determining the criticality of projects). Can be used to integrate multiple contractors /
multiple project schedules into an overall program schedule. Audiences for this schedule
Level include, but are not limited to client, senior executives and general managers. If
included with a bid and/or the Contract, demonstrates conformance to contractual and other
milestones.

Level 2 Schedule:
Management Summary, also called a Summary Master Schedule (SMS). Maintained as a
summarisation of the Level 3 Project Coordination Schedule(s). It depicts the overall project
broken down into its major components by area and is used for higher-level management
reporting. Frequently developed by the ‘client’ as part of its commitment planning for the
project and then maintained by the contractor. Can be used to integrate multiple contractors
/ multiple project schedules for the overall control of a program. It will include the Level 1
information expanded to show activities by area or major item of capital equipment. Should
demonstrate the driving path for structures and major process systems at the CSI Division
Level (e.g., Earthwork, Foundations, Framing, Enclosure, MEP Services and Process
Equipment), based on the project method statement. Audiences for this type of schedule
include, but are not limited to general managers, sponsors, and program or project managers.

Level 3 Schedule:
Project Coordination Schedule (PCS) also called a Publication Schedule. Initially developed as
an integrated CPM overview of the project, the Level 3 schedule is then maintained as an
integrated rollup or summary of the Level 4 schedule activities for reporting status to senior
Page 1 of 3
https://t.me/Constructionplanningmanager
Compiled By Dev M

management and to report monthly status to major clients, etc. The schedule consists of a
set of integrated Level 4 schedules based on Critical Path Methodology (CPM) and is
developed with detailed input from the project management team. Usually developed by the
‘main contractor’ as part of its tendering process for the project or by the project team during
the initial phases of planning. The Level 3 schedule spans the whole of the project and is used
to support the monthly report. It includes all major milestones, major elements of design,
engineering, procurement, construction, testing, commissioning and/or start-up. If the Level
4 schedules are primarily developed by trade/sub-contractors, during the initial phases of the
project the Level 3 schedule provides the schedule framework and constraints used by the
subcontractors to develop their tenders. During the execution phase of the project this
schedule defines the overall critical path and is the primary coordination tool for the overall
project. Audiences for this type of schedule include, but are not limited to program or project
managers, CMs or owner’s representatives, superintendents, and general foremen.

Level 4 Schedule:
Execution Schedule, also called a Project Working Level Schedule. Level 4 is the detailed
working level schedule, where each schedule is an expansion of part of a Level 3 schedule,
and is established within the integrated project schedule. This is the key working level CPM
schedule displaying the activities to be accomplished by the project workforce and is required
for every project. The dates generated by the schedule activities represent the anticipated
start and completion of work required to complete the project. If there is no ‘Level 3’
schedule, activities in future months/years may be summary in nature but still provide
approximate start and completion dates for major pieces of work (this is called ‘rolling wave
scheduling’). Developed by the ‘contractor’, ‘subcontractor’ (trade contractor), or the project
team prior to commencing work on the project execution, or work in a phase or area of the
project. The Level 4 schedule may be for the whole of the project or a part of the project
depending on the size of the project and complexity of the work. A critical factor is keeping
each ‘Level 4’ schedule to a sensible size that can be easily managed, updated, validated, etc.
‘Level 4’ schedules may be for major sections of the work or for discrete processes such as a
‘Design Schedule’, ‘Procurement schedule’ and/or a ‘Commissioning Schedule’. Generally, the
‘Level 4’ schedule represents the area of authority of a section manager or engineer, so one
manager is responsible for all of the work in the schedule. Activities are generally over a week
in duration (depending on the nature of the project) and should be resource loaded at least
in the near term and include detailed crew movements and other means and methods to
ensure viability. Where used, short term ‘look ahead’ are produced from this level; typically
‘Three Week Look-ahead’ schedules are updated every two weeks. Audiences for this type of
schedule include but are not limited to project managers, superintendents, and general
foremen.

Page 2 of 3
https://t.me/Constructionplanningmanager
Compiled By Dev M

Level 5 Schedule:
Detail Schedule. The further breakdown of the activities of a Level 4 Schedule. A short term
schedule used to map out the detailed tasks needed to coordinate day to day work in a
specific areas. Level 5 schedules are developed by workforce supervisors to plan and
coordinate their work at the detail level; Workarounds and critical areas can be exploded
here. Typically Bar Charts (Gantt Charts), the schedules are replaced every 1, 2 or 4 weeks
depending on the complexity of the work, typically schedules extend for 1 or 2 weeks beyond
the date when the replacement is due (eg a ‘weekly schedule’ will extend for 2 weeks and be
updated/replaced each week), this encourages continuity of working. Audiences for this type
of schedule include but are not limited to superintendents, team leaders, crew leaders,
general foremen, foremen and sub-foremen.

General Notes:
• Where available, the WBS is used as a basis for the development of the schedule
structure
• Level 1 and 2 schedules are normally developed as part of the pre-feasibility
studies to determine the viability of the project.
• Only Mega projects will have a fully maintained Level 1 and Level 2 schedule.
Smaller project typically only have a Level 2 schedule.
• The Level 3 schedule is initially developed as a high level CPM overview of the
project. If the project is relatively small, the Level 3 schedule is expanded into a
Level 4 schedule for coordinating the execution of the works. On larger projects
with multiple Level 4 schedules the Level 3 schedule is maintained as the project’s
overall, integrated CPM schedule.
• Every project requires a Level 4 schedule for day to day coordination of the
project’s work. However, the overall size of this schedule needs to be
‘manageable’ and focused on the work in one management area. The Level 3
schedule becomes critical for the overall coordination of the project as soon as
more than one Level 4 schedule is in use.

Page 3 of 3