Workshop 1 Solution
Workshop 1 Solution
Workshop 1 Solution
1. Provide a list of tasks which must be conducted in each life cycle phase of the
construction of a complex of townhouses in Sydney.
Solution:
a) Initiation
Project objective development
Conceptual designs
Project Scope identification
Brainstorming
Rough cost and time estimation
Feasibility study
Market analysis and predictions
Stakeholders identification
b) Planning
Detailed construction cost and time
Construction plans and drawings
Getting development approval (DA)
WBS development
Gantt chart development
Project scope statement
c) Execution
Getting construction certificate (CC)
Conducting construction activities
Communications with subcontractors
Site supervision
1
Progress tracking
Ordering materials
Contracting with supplires and contractors
Meetings
e) Closure
Contracts closing
Project closing report preparation
Project evaluation and archiving
Project handing over
2
2. Developing a table, map the project life cycle phases and project management
knowledge areas.
Define Scope
Create WBS
Schedule Plan Schedule Control Schedule
Management
Define Activities
Sequence Activities
Estimate Activity
Resources
Estimate Activities
Durations
Develop Schedule
Cost Plan Cost Control Costs
Management
Estimate Costs
Determine Budget
Quality Plan Quality Perform Quality Control Quality
Management Assurance
Human resources Plan Human Acquire Project
Resource Team
Management
Develop Project
Team
Manage Project
Team
Communications Plan Manage Control
Communications Communications Communications
Management
Risk Plan Risk Control Risks
Management
Identify Risks
Perform Qualitative
Risk analysis
Perform Quantitative
Risk
3
Plan Risk
Responses
Procurement Plan Procurement Conduct Control Close
Management Procurements Procurements Procure
ments
Stakeholder Identify Plan stakeholder Manage Control
stakeholders Management Stakeholder Stakeholder
Engagement Engagement
2 24 8 11 2
4
4. Construction of a small granny flat takes 15 months which includes seven main
construction processes provided in the Gantt chart below. The numbers in the
Gantt chart are project progress (percentage) and activity costs (thousand
dollars), respectively.
A 1,3 2,5
E 8,15 9,15 4, 9
G 2, 4 2, 3 2, 3
3, 2 2, 1 2, 2 1, 1 1, 1
H
Based on the signed contract, client will release the following payments during
construction of the project in the beginning of the outlined months.
5
Solution:
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15
A 1,3 2,5
E 8,15 9,15 4, 9
G 2, 4 2, 3 2, 3
3, 2 2, 1 2, 2 1, 1 1, 1
H
Com% 1 4 3 6 8 9 15 13 13 9 7 4 4 3 1
Cul % 1 5 8 14 22 31 46 59 72 81 88 92 96 99 100
inf low 20 0 0 60 0 0 0 50 0 0 20 0 0 20 0
outflow 3 8 5 10 13 10 24 18 23 15 11 5 5 4 1
Cul 20 20 20 80 80 80 80 130 130 130 150 150 150 170 170
inflow
Cul 3 11 16 26 39 49 73 91 114 129 140 145 150 154 155
outflow
Cash 17 9 4 54 41 31 7 39 16 1 10 5 0 16 15
flow
6
120
100
Cumulative Completion Percentage
80
60
40
20
0
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15
Months
180
160
120
Cumulative outflow
100
80
60
40
20
Cash flow
0
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15
Profit = Final cumulative cash inflow – Final cumulative cash outflow = 170 – 155 =
$15k
7
5. Eight activities shown in the table below must be undertaken in succession to
construct an airport runway.
Solution
a)
OT + 4MT + PT
ET =
6
PT −OT 2
σ2=( )
6
Activity OT MT PT ET σ2
A 38 45 50 44.67 4
B 27 34 40 33.83 4.694
C 50 62 72 61.67 13.444
D 13 16 18 15.83 0.694
E 22 25 27 24.83 0.694
F 30 32 35 32.17 0.694
G 45 54 62 53.83 8.028
H 8 9 12 9.33 0.444
8
b)
Using Table 2, the probability of project completion on or before 285 days = 0.9389
(93.89%) (interpolation is required)
So, the probability of completing project after 285 days is 1 – 0.9389 = 0.0611
(6.11%)
c)
Using Table 2, the probability of project completion on or before 280 days = 0.7492
(74.92%) (interpolation is required)
Probability of finishing project between 275 and 280 days is 0.7492 – 0.4195 =
0.3297 (32.97%)
d)
X = 277.61
This project will be completed in less than 277.61 days with the chance of 60%.