0% found this document useful (0 votes)
29 views2 pages

OM Test - 2

The document outlines various operational management tasks including job sequencing based on different priority rules, minimizing total elapsed time for job processing through two machines, projecting sales trends, evaluating plant locations based on costs, determining initial feasible distribution for factories and warehouses, calculating incentive bonuses for production, and assessing a machine shop's layout for potential improvements. Each task presents specific data and requires analytical approaches to derive optimal solutions. The document serves as a test paper for assessing knowledge in operations management principles.

Uploaded by

takercare007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
29 views2 pages

OM Test - 2

The document outlines various operational management tasks including job sequencing based on different priority rules, minimizing total elapsed time for job processing through two machines, projecting sales trends, evaluating plant locations based on costs, determining initial feasible distribution for factories and warehouses, calculating incentive bonuses for production, and assessing a machine shop's layout for potential improvements. Each task presents specific data and requires analytical approaches to derive optimal solutions. The document serves as a test paper for assessing knowledge in operations management principles.

Uploaded by

takercare007
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

OM Test Paper – 2nd

1.

2. Table shows the time remaining (number of days until due date) and the work remaining
(number of day’s still required to finish the work) for 5 jobs which were assigned the
letters A to E as they arrived to the shop. Sequence these jobs by priority rules viz., (a)
FCFS, (b) EDD, (c) LS, (d) SPT and (e) LPT.

Job Number days until due date Number of days of work remaining
A 7 2
B 9 7
C 4 3
D 1 1
E 3 8
3. In a factory, there are six jobs to perform, each of which should go through two machines
A and B, in the order BA. The processing timings (in hours) for the jobs are given here.
You are required to determine the sequence for performing the jobs that would
minimize the total elapsed time, T. What is the value of T?
Job Machine A Machine B
1 7 4
2 1 6
3 6 5
4 8 2
5 4 9
6 2 7
4. With the help of following data project, the trend of sales for the next five years:

Years 2002 2003 2004 2005 2006 2007


Sales (in lakhs) 56 67 88 96 105 120
5. A company planning to manufacture a household cooking range has to decide on the
location of the plant. Three locations are being considered viz., Jaipur, Kota, and Alwar.
The fixed costs of the three location are estimated to be ₹30 lakh, ₹50 lakh, and ₹25 lakh
per annum respectively. The variable costs are ₹400, ₹700 and ₹ 300 per unit
respectively.
The expected sales price of the cooking range is ₹100 per unit Find out:
(i) The range of annual production/sales volume for which each location is most
suitable and (ii) Which one of the three locations is the best location at a
production/sales volume of units.

6. XYZ enterprise has three factories at locations A, B and C which supply three warehouses
located at D, E and F. Monthly factory capacities are 20, 90 and 35 units respectively.
Monthly warehouse requirements are 65, 40 and 60 units respectively. Unit shipping
costs (in ₹) are given in the following table:
Determine the initial feasible distribution using NWC method.
7. An incentive scheme allows proportionate production bonus beyond 100% performance
level. Calculate the amount of (i) Incentive bonus and (ii) Total payment received by an
operator on a particular day during which the following particulars apply:
Operation: Assembling pocket transistor radio set
Work Content: 20 Standard minutes per assembled set
Attended Time: 8 Hours
Time spent on unmeasured work: 1 Hours
Numbers of sets assembled during the day: 25
Wage rate: ₹5 per hour
8. A building contractor is evaluating its machine shops current process layout. The figure
below shows the current layout and the table shows the trip matrix for the facility.
Health and safety regulations require departments E and F to remain at their current
positions.
E B F
A C D
Current Layout
From / To A B C D E F
A 7 4 8 6
B - 5
C - 9 10
D - 2
E - 3
F -
Can layout be improved? Also evaluate using load distance (ld) score.