Project Planning and Scheduling: Ishwar Adhikari
Project Planning and Scheduling: Ishwar Adhikari
AND SCHEDULING
ISHWAR ADHIKARI
CONCEPT OF PROJECT
Every product or services what we are acquiring today is the
outcome of our necessity.
For fulfilling the desire or necessity, an idea is generated in a
human mind.
To translate the idea into reality, a single person is not
capable of doing it alone.
A person utilizes the different resources including the human
and non human resources for translating the idea into the
physical form.
The process of converting the idea into reality by utilizing
the different resources is said to be a project.
DEFINITION OF PROJECT
“A project can be defined as an unique task (however large or
small) with defined goal, limited in cost and time and giving
some benefits to the users after its completion”.
“A project is defined as a temporary endeavor undertaken to
create a unique products or services”.
“A project is a collection of limited activities, carried out in an
organized manner with a clearly defined start and finish points,
to achieve some specific results that satisfy the needs of an
organization as derived from the current business plans.”
RESOURCES OF A PROJECT
Generally Denoted by 5 ‘M’
Money
Manpower
Material
Machine
Minute/ Management
Technically feasible
Economically viable
Because projects are
Socially acceptable considered as cutting edge of
Politically suitable & any development
Environmentally friendly
CHARACTERISTICS OF A PROJECT
Any task or job or work can be said as a project if it meets the certain
characteristics.
1. A Defined Goal/ Objective
2. Unique
3. Specific task not routinely performed
4. Temporary (Life Span)
5. Team Work
6. Resource being consumed
7. Risk and Uncertainties
8. Planning and Control
9. Constraints
10. Contracting and subcontracting
11. Progressive Elaboration
12. Life cycle
13. Defined Deliverables
CLASSIFICATION OF PROJECT
(Cont’d…)
Customer sponsorship
• Sponsorship by an individual or a party
Organization
• By firm, company
According to Sponsorship
(Who Sponsors??) Contractor
• To sub contractor
Government Organizations
• Department, office
1. Individual
This sub class of project is one in which one individual (may be
from within the organization or an independent person) is
assigned with the responsibilities to complete it. [2]
An INGO may identify individual from its organizational setup
or independent person.
CLASSIFICATION OF PROJECT
(Cont’d…)
2. Staff
This sub class of project refers to assigning the project activities
to a particular department.
The research and development or engineering department
within a company may be assigned to develop a project on new
product development.
3. Special
This sub class is one in which an independent researcher is
identified and entrusted with the responsibilities to conduct a
research.
This is similar to the individual project but will address a special
issue. Example: national expert on security issue.
CLASSIFICATION OF PROJECT
(Cont’d…)
According to Source of
Funding
1. Indigenous Project
It is based on local thinking, technology, and environment and
carried mostly by local people.
It is mostly the blend of indigenous materials, technology and
resources.
It helps to preserve and protect tradition and culture and help to
expand people friendly market for local products. [3]
CLASSIFICATION OF PROJECT
(Cont’d…)
2. Bilateral Project
All the projects which are carried on under the agreement
of two countries are called bilateral projects.
It involves both technology as well as capital. These projects
are mostly funded through the financial resources of the
donor. They could be in the form of grants. [4]
These projects are governed by an agreement and
memorandum of understanding between two governments.
[2]
Example: JICA, USAID, GTZ, KOICA etc.
CLASSIFICATION OF PROJECT
(Cont’d…)
3. Multilateral Project
All the projects which involves the funding of projects through
the resources directed by the donors through multilateral
agencies are called multilateral projects.[4]
The financial resources are mobilized from the international
financial institutions by way of credit or loans.
Multilateral agencies might be European union (EU), World
bank, Asian Development Bank (ADB), International Finance
Corporation (IFC), World Bank etc.
CLASSIFICATION OF PROJECT
(Cont’d…)
4. Joint Venture Project
Any project undertaken to produce goods and services
through collaboration of foreign and local investors is joint
venture project.
The ownership is proportionally shared in an agreed ratio.
It is associated with transfers of technology, capital, or
managerial skills.
Due to globalization and advancement in information
technology, joint venture business is becoming very popular.
Examples: Maruti-Suzuki in India,
CLASSIFICATION OF PROJECT
(Cont’d…)
According to the Orientation
Product Process
Oriented Oriented
1. Product oriented
The focus is on the technical content of the project. The outcome
of the project is a product which fulfills consumer needs.
Examples – building, road, bridge etc.
2. Process oriented
• No consideration is given to technical context. Examples- person
focused training, repair of cement plant etc.
CLASSIFICATION OF PROJECT
(Cont’d…)
According to the Scale and Size
1. Mega Project
It is a big size complex project for 10 to 20 years involving huge
investment and high technology, includes multiple public and
private stakeholders and impact millions of people.
These projects required environmental screening like EIA
(Environmental Impact Assessment).
CLASSIFICATION OF PROJECT
(Cont’d…)
2. Major Project
It is smaller in size than mega project. The project requires
relatively large amount of fund, large number of people and more
activities to be performed is known as major project. [5]
3. Medium Project
It is small in size than major project. These project requires IEE
(Initial Environment Examination).
4. Micro Project
It refers to a very small project for short duration. The financial
resources involved is also very small.
CLASSIFICATION OF PROJECT
(Cont’d…)
According to the Time and
Speed
Normal Crash
1. Normal Project
In this category of projects, adequate time is allowed for
Implementation of the project.
All the phases in a project are allowed to take the time they
should normally take. This type of project will require minimum
capital cost and no sacrifice in terms of quality. [6]
CLASSIFICATION OF PROJECT
(Cont’d…)
2. Crash Project
Crashing is the process of shortening the project duration.
When the project duration exceeds the normal completion
time, crashing is encouraged.
Saving in time is achieved by spending extra resources in
terms of money, materials and manpower with
compromising quality. Overlapping or shortening of project
phases is encouraged.
PROJECT LIFE CYCLE AND PHASES
Project is a temporary job. It cannot continue endlessly. The
life span of the project is divided into phases.
This phase involves about 80% of the total project work and
the resources are also extensively used.
Major
Percent Complete
Contracts
Let
Project
“GO”
Decision
Start End
Stage I Stage II Stage III Stage IV
Fig: LIFE CYCLE STAGES [7]
Project life cycle in terms of
resources/risk and time
Resources /Risk
Resources
Risk
Start End
Initiation Planning Engineering and Implementati Termination
design on
PROJECT CASH FLOW (Cont’d…)
Revenue
Time
Commission
Cost Sanction
Investment Return
Fig: Project Cash Flow
CONCEPT OF PROJECT PLANNING
Meaning of General Planning
In the simple sense, planning means thinking ahead of an
operation to be performed.
It is the function of selecting the enterprise objectives and
establishing the policies, procedures, and programs necessary for
achieving them. [7]
Planning includes both assessment of future opportunities and
challenges for an organization and developing strategies to achieve
the organizational goals.
Planning is the intellectual capability of manager who decides
whether or not the act or take up to a particular event or not. [6]
CONCEPT OF PROJECT PLANNING
Meaning of Project Planning
It is concerned with development a project for investment.
It identifies and addresses the tasks required for accomplishment
of project objectives.
It acts as a roadmap for managing the project. It determines how
the project objectives will be accomplished.
It involves detailed design, budgeting, scheduling and allocation of
resources.
It is the process of thinking through and making explicit the
project’s objectives, goals and strategies necessary to bring the
project through its lifecycle to successful termination. [8]
Meaning of Project Planning (Cont’d…)
Steps of project planning: [9]
1. DEFINE : The objective of the project in definite words.
2. ESTABLISH : Goals and stages intermediate to attain the final
target.
3. DEVELOP : Forecast and means of achieving goal, i.e.,
activities.
4. EVALUATE : Organization’s resources – financial, managerial,
and operational to carry out activities and to determine what is
feasible and what is not.
5. DETERMINE : Alternatives – individual courses of action that
will allow to accomplish goal.
Meaning of Project Planning (Cont’d…)
6. TEST : For consistency with company’s policy.
7. CHOOSE : An alternative which is not only consistent with its
goals and concept but also one that can be accomplished with
the evaluated resources.
8. DECIDE : on a plan
1 Foundation
work
2 R.C.C. work
3 Door and
No defined relationship
windows work
4 Interior Finish
5 Sanitary works
6 Electrical works
7 Exterior finish
B
Type 2 Start to Start (SS)
(Activity B should start when Activity A starts )
A
B
LINKED BAR CHART (Cont’d…)
Type 3 Finish to Finish (FF)
(Activity B should be finished when Activity A finishes)
A
B
MILESTONE CHART
It is a modification over the original bar chart.
When a particular activity represented by a bar on a bar chart is
very long, the details lack.
A Chart that graphically depicts key events along a timescale,
usually with triangles representing each event, is called milestone
chart.
Milestones provide a sense of accomplishment and show project
team how the work they’re doing contributes to the overarching
project objective.
It only identify the scheduled start or completion of major
deliverables and key external interfaces. [4]
MILESTONE CHART (Cont’d…)
A B
i j k
4 Dummy activity
CRITICAL PATH METHOD (CPM)
TERMINOLOGIES (Cont’d…)
Grammatical purpose:
It is used to prevent two arrows having common beginning and
end nodes for two or more activities.
For example, consider the arrows of activities A and B; both
starts from node 1 and end at node 2.
Due to this an inconvenience results when the network is used for
computation, i.e., uniqueness in the identification is lost. This
inconvenience frequently leads to mistake. [7]
CRITICAL PATH METHOD (CPM)
TERMINOLOGIES (Cont’d…)
Logical purpose
Dummies are also used to give logical clear representation in a
network having an activity common to two sets of operations
running parallel to each other.
Here, Activity D cannot be
started until Activity A is
completed. The inter
dependency or logical
relation between two
activities are clearly
known.
CRITICAL PATH METHOD (CPM)
TERMINOLOGIES (Cont’d…)
Graphical Representation of activities and events
1. Activity on Arrow (AOA) system
In this system, an activity is represented by an arrow with circles
at both ends drawn from left hand side to the right hand side.
The tail end of the arrow represents the start of an activity and
head of arrow represents completion of activity.
Excavation
1 2
CRITICAL PATH METHOD (CPM)
TERMINOLOGIES (Cont’d…)
2. Activity on Node (AON) system
In this system, activities are represented by nodes or circles.
Arrow only shows the dependence of activities on each other.
No dummy activity is required to represent the inter dependency
between succeeding and preceding activity.
It is also called precedence diagramming method (PDM)
ES EF ES EF
ACTIVITY A ACTIVITY B
LS LF LS LF
CRITICAL PATH METHOD (CPM)
TERMINOLOGIES (Cont’d…)
5. Earliest start time (EST)
It is the earliest possible time that the activity can start.
6. Earliest finish time (EFT)
It is the earliest possible time for completion of an activity or
operation without delaying the project completion time.
It can be computed by adding activity duration by EST.
In a network diagram, the path along which the project takes the
maximum time from start to finish is called critical path.
It is the longest path of the network and gives the total time
taken to complete the project. Any delay along this path delays
the project.
Critical Path (Cont’d….)
Implement Termination
Initiation Planning Design
ation
Source: [5]
Earned Value Analysis (Cont’d….)
Some Derived Metrics in EVA (parameters in EVA)
1. Variances Formula Interpretation
Cost CV = If CV is +ve, cost under run (actual budget expense is
Variance BCWP - ACWP less than planned)
If CV is -ve, cost overrun (actual budget expense is
greater than planned)
If CV is 0 No cost variance (actual expense is equal to
planned)
Schedule SV = If SV is +ve, Schedule under run (actual schedule is
Variance BCWP - BCWS ahead of planned)
If SV is -ve, Schedule overrun (actual schedule is
behind of planned)
If SV is 0 No Schedule variance (actual Schedule is
equal to planned)
Earned Value Analysis (Cont’d….)
2. Variances expressed in percentage
CV % Over budget or under budget expresses in % , by what %
does the cost under run or over run
3. Indices
Cost CPI = If CPI ≥ 1, Better Performance for Cost, less
performance BCWP / ACWP budget
index If CPI < 1, Poor Performance for Cost,
more budget
Schedule SPI = If SPI ≥ 1, Better Performance in Schedule,
Performance BCWP / BCWS ahead of schedule
Index If SPI < 1, Poor Performance in Schedule,
behind of schedule
Earned Value Analysis (Cont’d….)
11. When two or more activities merge into a node than the smallest
value should be taken as the latest occurrence time of that
particular node in
a) Forward pass calculation
b) Backward pass calculation
c) Middle pass calculation
d) Both (a) and (b)
12. If the duration and the earliest finish time of preceding activity is 2 days
and 5 days respectively and the earliest start time of the succeeding activity
is 7 days then the free float of preceding activity is
(a) -2 (b) 2 (c) -3 (d) 3
13. If the planned value, actual value and the earned value of an activity is Rs
7,000, Rs. 8000 and Rs. 6000 respectively, then the cost variance will be
a) - 2000 b) 2000 c) -1000 d) 1000
14. If the optimistic time is 2 days, pessimistic time is 10 days and the most
likely time is 3 days, then the most expected time of an activity will be
a) 2 days
b) 3 days
c) 4 days
d) 5 days