TTI Test
TTI Test
by
Wanda L. Menges
Associate Research Specialist
and
Rebecca R. Haug
Assistant Research Specialist
Sponsored by
HESCO Bastion Ltd.
April 2005
TH EA A UNVRST SYTE
DISCLAIMER
The contents of this report reflect the views of the authors who are solely responsible for
the facts and accuracy of the data, and the opinions, findings and conclusions presented herein.
The contents do not necessarily reflect the official views or policies of the HESCO Bastion Ltd.,
The Texas A&M University System, or Texas Transportation Institute. This report does not
constitute a standard, specification, or regulation. In addition, the above listed agencies assume
no liability for its contents or use thereof. The names of specific products or manufacturers
listed herein does not imply endorsement of those products or manufacturers.
KEY WORDS
Anti-ram; perimeter; crash testing; barriers; gates; bollards; walls; fences; homeland
security.
Technical Renort Documentation Paee
1. Report No. 2. Government Accession No. 3. Recipient's Catalog No.
The objective of this test is to determine if the HESCO Bastion Ltd. C-3315 flood barrier is capable
of arresting a 6810 kg (15,000 lb) truck traveling at 80 km/h (50 mi/h) with 1.0 m (3.3 ft) of vehicle partial
penetration and/or deflection. This criterion is based on Condition Designation K12 as stated in
ST-STD-02.01, Revision A. This condition designation requires the HESCO Bastion Ltd. C-3315 flood
barrier to withstand kinetic energy of 1,695,000 J (1,250,000 ft-lb).
This report presents the construction details of the HESCO Bastion Ltd. C-3315 flood barrier, details
of the vehicle used in the test, details of the test, and the assessment of the test results. Target impact speed
was 75.0 km/h or above (47.0 to 56.9 mi/h), and the actual impact speed was 81.0 km/h (50.3 mi/h). The
1995 International 4700 single-unit flatbed truck impacted the barrier at 90 degrees, with the centerline of the
vehicle aligned with the centerline of the barrier. The HESCO C-3315 barrier brought the vehicle to a
complete stop with minimal penetration of the vehicle. The front of the cargo bed did not penetrate the
inside edge of the barrier and came to rest 0.85 m (2.8 ft) from the inside edge of the barrier.
ST-STD-02. 01, Revision A performance criteria limits penetration of the leading edge of the cargo bed
to 1 m beyond the pre-impact, inside edge of the barrier. As stated above, the cargo bed did not penetrate the
inside edge of the barrier. The actual impact speed was within the permissible range to receive the
designated K12 condition level. According to the results of the full-scale crash test, the HESCO Bastion
C-3315 flood barrier, as constructed in this test configuration, met the requirements for Condition
Designation K12.
*SI is the symbol for the International System of Units. Appropriate rounding should be made to comply with Section 4 of ASTM E380.
(Revised March 2003)
ii
TABLE OF CONTENTS
Section Page
RE F EREN C E S ............................................................................................................................. 21
iii
LIST OF FIGURES
Figure Page
LIST OF TABLES
iv
INTRODUCTION
PROBLEM
BACKGROUND
The procedures set out in SD-STD-02. 01, Revision A were intended to ensure that
perimeter barriers/gates provide a specified level of vehicle impact resistance as recommended
by the DS/PSP/PSD. The assessment criteria are based on the capability of the barrier/gate to
arrest the vehicle such that it does not penetrate or vault over the system. Three levels of
performance are defined based on the amount of vehicular impact kinetic energy the barrier/gate
is capable of arresting. SD-STD-02.01, Revision A also limits the penetration of the leading edge
of the cargo bed to one meter (3.3 ft) beyond the pre-impact, inside edge of the barrier. If the
barrier meets this requirement, a pass rating will be assigned at the appropriate speed
designation.
OBJECTIVES/SCOPE OF RESEARCH
The objective of this test is to determine if the HESCO Bastion Ltd. C-3315 flood barrier
is capable of arresting a 6810 kg (15,000 lb) truck traveling at 80 km/h (50 mi/h) with 1.0 m
(3.3 ft) of vehicle partial penetration and/or deflection. This criterion is based on Condition
Designation K12 as stated in ST-STD-02.01, Revision A. This condition designation requires
the HESCO Bastion Ltd. C-3315 flood barrier to withstand kinetic energy of 1,695,000 J
(1,250,000 ft-lb).
This report presents the construction details of the HESCO Bastion Ltd. C-3315 flood
barrier, details of the vehicle used in the test, details of the test, and the assessment of the test
results.
1
2
TECHNICAL DISCUSSION
TEST PARAMETERS
Test Facility
The test facilities at the Texas Transportation Institute's Proving Ground consist of an
809-hectare (2000-acre) complex of research and training facilities situated 16 km (10 mi)
northwest of the main campus of Texas A&M University. The site, formerly an Air Force base,
has large expanses of concrete runways and parking aprons well suited for experimental research
and testing in the areas of vehicle performance and handling, vehicle-roadway interaction,
durability and efficacy of highway pavements, and evaluation of roadside safety hardware and
perimeter security barriers/gates. The site selected for placing of the HESCO Bastion Ltd.
C-3315 flood barrier was on a wide out-of-service apron. The apron consists of an unreinforced
jointed concrete pavement in 3.8 m x 4.6 m (12.5 ft x 15 ft) blocks nominally 203-305 mm (8-12
in) deep. The apron is about 50 years old and the joints have some displacement, but are
otherwise flat and level.
The total installation length of the HESCO Bastion Ltd. C-3315 flood barrier was
9.14 m (30.0 ft). Width at the base was 1.83 m (6.0 ft) and the height of the bottom tier was 0.91
m (3.0 ft). The top tier was identical to the bottom tier. Overall height of the test installation
was 1.83 m (6.0 ft).
The HESCO Bastion Ltd. C-3315 flood barriers are constructed with welded wire sheets
to form open top cubes that measured 0.91 m ( 3.0 ft) wide by 0.91 m (3.0 ft) tall. The welded
wire was 4mm (0.158 in) diameter and was welded on a 76 mm x 76 mm ( 3.0 in x 3.0 in) grid.
A series of 5 cubes came pre-assembled and lined with 2mm (0.8 in) non-woven polypropylene
geotextile fabric. Comers of the HESCO Bastion Ltd. C-3315 flood barriers are formed with
coiled 4 mm (0.158 in) wire. The coils are 32 mm (1.25 in) diameter with a coil pitch of 25 mm
(1.0 in). Pre-assembled units are joined with adjacent units by overlapping wire coils and
placing a 4mm (0.158 in) joining pin in the overlapped section of coils.
The HESCO Bastion Ltd. C-3315 flood barriers were filled with a reddish-tan silty,
clayey sand, designated as select fill from the Kelly Burt pit. The density of the fill material was
1900 kg/cubic meter (118.5 lbs/cubic ft) and was manually tamped by HESCO installers. Details
of the installation are shown in figures 1 and 2. Photographs of the completed installation are
shown in figure 3.
3
I'
\\A
".-T10 "
Figure2.1 Connectin-del o1 f lo d b 1
6
Test Conditions and Evaluation Criteria
According to SD-STD-02.01, Revision A, the test article can be rated according to one of
three designated condition levels as shown in table 1. The test procedures are intended to ensure
that perimeter barriers and gates will provide a specified level of vehicle impact resistance.
Actual vehicle speed must be within a permissible range to receive the condition designation.
ST-STD-02. 01, Revision A performance criteria limits penetration of the leading edge of the
cargo bed to 1 m beyond the pre-impact, inside edge of the barrier. If the barrier meets this
requirement, a pass rating will be assigned at the appropriate speed designation as shown in
table 1. The test vehicle specified is a medium duty truck with diesel engine, tested at a gross
vehicle weight of 6,800 kg (15,000 lb) ±90 kg (200 lb).
The crash test and data analysis procedures were in accordance with guidelines presented
in SD-STD-02.01, Revision A. Appendix A presents brief descriptions of these procedures.
7
8
CRASH TEST 400001-HBL2 (SD-STD-02.01 CONDITION DESIGNATION K12)
Test Vehicle
A 1995 International 4700 single-unit flatbed truck, shown in figures 4 and 5, was used
for the crash test. Test inertia weight of the vehicle was 6867 kg (15,140 lb). The height to the
lower edge of the vehicle front bumper was 514 mm (20.25 inches), and the height to the upper
edge of the front bumper was 800 mm (31.5 inches). Figure 11 in appendix B gives additional
dimensions and information on the vehicle. The vehicle was directed into the installation using
the cable reverse tow and guidance system, and was released to be free-wheeling and
unrestrained just prior to impact.
The crash test was performed the morning of morning of December 17, 2004. Weather
conditions at the time of testing were: Wind Speed: 5 km/h Th. . f
Impact Description
The 1995 International 4700 single-unit flatbed truck, traveling at a speed of 81.0 km/h
(50.3 mi/h), impacted the HESCO Bastion Ltd. C-3315 flood barrier at an impact angle of
90.8 degrees, with the centerline of the vehicle aligned with the centerline of the barrier. Shortly
after impact, the hood of the vehicle separated from the vehicle near the cab. At 0.054 s, the
head rack of the truck bed contacted the rear of the cab. The inside edge of the bottom row of
box units began to move toward the inside of the barrier at 0.060 s, and the top row began to
move toward inside of the barrier at 0.078 s. The strap on the front row of the box units
separated at 0.560 s. At 0.800 s, the vehicle reached maximum penetration of the front of the
truck bed of 1.1 m (3.7 ft) into the barrier (or 0.8 m (2.9 ft) from the impact side of the inside
edge of the barrier). The vehicle subsequently backed up slightly and came to rest with the front
of the cargo bed 0.85 m (2.8 ft) to the impact side of the inside edge of the barrier. The front of
the cargo bed did not reach inside edge of the barrier. Appendix C, figures 12 and 13, show
sequential photographs of the test period.
9
Figure 4. Vehicle/installation geometrics for test 400001-HBL2.
10
Figure 5. Vehicle before test 400001-HBL2.
11
Damage to Test Article
The wire mesh ruptured and the center rows were damaged. Three rows of box units on
each side were intact The ends of the barrier were pulled inward, 150 mm (5.9 inches) on the
right side and 140 mm (5.5 inches) on the left side. Soil was scattered over an area to the inside
of the barrier, 12.2 m (40 ft) long and 9.1 m (30 ft) wide. Damage to the installation is shown in
figures 6 and 7.
Vehicle Damage
Damage to the vehicle is shown in figure 8 and 9. The front of the cargo bed did not
penetrate the inside edge of the barrier, and came to rest 0.85 m (2.8 ft) from the inside edge of
the barrier.
Data from the accelerometer, located at the vehicle center of gravity, were digitized for
evaluation of occupant risk for informational purposes only. In the longitudinal direction, the
occupant impact velocity was 11.9 m/s (39.0 ft/s) at 0.106 s, the highest 0.010-s occupant
ridedown acceleration was -10.6 g's from 0.106 to 0.116 s, and the maximum 0.050-s average
acceleration was -14.4 g's between 0.011 and 0.061 s. In the lateral direction, the occupant
impact velocity was 0.4 m/s (1.3 ft/s) at 0.106 s, the highest 0.010-s occupant ridedown
acceleration was 3.0 g's from 0.113 to 0.123 s, and the maximum 0.050-s average was -1.5 g's
between 0.024 and 0.074 s. These data and other pertinent information from the test are
summarized in figure 10. Vehicle angular displacements and accelerations versus time traces are
presented in appendix D, figures 14 through 19.
12
Figure 6. Vehicle trajectory path after test 400001-HBL2.
13
Figure 7. Installation after test 40000 1-HBL2.
14
Figure 8. Vehicle after test 400001-HBL2.
15
Before test
After test
16
0.000 s I.
0.213 s I.
0.733 s
Dimensions in millimeters
Figure 10. Summary of results for test SD-STD-2.01 test K12 on the HESCO C-3315 flood barrier.
18
SUMMARY AND CONCLUSIONS
Target impact speed was 75.0 km/h or above (47.0 to 56.9 mi/h), and the actual impact
speed was 81.0 km/h (50.3 mi/h). The 1995 International 4700 single-unit flatbed truck
impacted the barrier at 90 degrees, with the centerline of the vehicle aligned with the centerline
of the barrier. The HESCO C-3315 barrier brought the vehicle to a complete stop with minimal
penetration of the vehicle. The front of the cargo bed did not penetrate the inside edge of the
barrier, and came to rest 0.85 m (2.8 ft) from the inside edge of the barrier.
CONCLUSIONS
ST-STD-02. 01, Revision A performance criteria limits penetration of the leading edge of
the cargo bed to 1 m beyond the pre-impact, inside edge of the barrier. As stated above, the
cargo bed did not penetrate the inside edge of the barrier. The actual impact speed was within
the permissible range to receive the designated K12 condition level. According to the results of
the full-scale crash test, the HESCO Bastion C-3315 flood barrier, as constructed in this test
configuration, met the requirements for Condition Designation K12.
19
20
REFERENCES
1. "Test Method for Vehicle Crash Testing of Perimeter Barriers and Gates," SD-STD-02. 01,
Revision A, Physical Security Division, United States Department of State, Washington,
D.C., March 2003.
The crash test and data analysis procedures were in accordance with guidelines presented
in SD-STD-2.01, Revision A. Brief descriptions of these procedures are presented as follows.
The test vehicle was instrumented with three solid-state angular rate transducers to
measure roll, pitch, and yaw rates; a triaxial accelerometer near the vehicle center of gravity
(c.g.) to measure longitudinal, lateral, and vertical acceleration levels; and a backup biaxial
accelerometer in the rear of the vehicle to measure longitudinal and lateral acceleration levels.
These accelerometers were ENDEVCO® Model 2262CA, piezoresistive accelerometers with a
+100 g range.
The accelerometers are strain gage type with a linear millivolt output proportional to
acceleration. Angular rate transducers are solid state, gas flow units designed for high-"g"
service. Signal conditioners and amplifiers in the test vehicle increase the low-level signals to a
+2.5 volt maximum level. The signal conditioners also provide the capability of an R-cal
(resistive calibration) or shunt calibration for the accelerometers and a precision voltage
calibration for the rate transducers. The electronic signals from the accelerometers and rate
transducers are transmitted to a base station by means of a 15-channel, constant-bandwidth,
Inter-Range Instrumentation Group (IRIG), FM/FM telemetry link for recording on magnetic
tape and for display on a real-time strip chart. Calibration signals from the test vehicle are
recorded before the test and immediately afterwards. A crystal-controlled time reference signal
is simultaneously recorded with the data. Wooden dowels actuate pressure-sensitive switches on
the bumper of the impacting vehicle prior to impact by wooden dowels to indicate the elapsed
time over a known distance to provide a measurement of impact velocity. The initial contact
also produces an "event" mark on the data record to establish the instant of contact with the
installation.
The multiplex of data channels, transmitted on one radio frequency, is received and
demultiplexed onto TEAC® instrumentation data recorder. After the test, the data are played
back from the TEAC® recorder and digitized. A proprietary software program (WinDigit)
converts the analog data from each transducer into engineering units using the R-cal and pre-zero
values at 10,000 samples per second, per channel. WinDigit also provides Society of
Automotive Engineers (SAE) J211 class 180 phaseless digital filtering and vehicle impact
velocity.
All accelerometers are calibrated annually according to SAE J211 4.6.1 by means of an
ENDEVCO® 2901, precision primary vibration standard. This device and its support
instruments are returned to the factory annually for a National Institute of Standards Technology
(NIST) traceable calibration. The subsystems of each data channel are also evaluated annually,
using instruments with current NIST traceability, and the results are factored into the accuracy of
the total data channel, per SAE J2 11. Calibrations and evaluations are made any time data are
suspect.
23
The Test Risk Assessment Program (TRAP) uses the data from WinDigit to compute
occupant/compartment impact velocities, time of occupant/compartment impact after vehicle
impact, and the highest 10-millisecond (ms) average ridedown acceleration. WinDigit calculates
change in vehicle velocity at the end of a given impulse period. In addition, maximum average
accelerations over 50-ms intervals in each of the three directions are computed. For reporting
purposes, the data from the vehicle-mounted accelerometers are filtered with a 60-Hz digital
filter, and acceleration versus time curves for the longitudinal, lateral, and vertical directions are
plotted using TRAP.
TRAP uses the data from the yaw, pitch, and roll rate transducers to compute angular
displacement in degrees at 0.0001-s intervals and then plots yaw, pitch, and roll versus time.
These displacements are in reference to the vehicle-fixed coordinate system with the initial
position and orientation of the vehicle-fixed coordinate systems being initial impact.
Photographic coverage of the test included three high-speed cameras: one overhead with
a field of view perpendicular to the ground and directly over the impact point; one placed behind
the installation at an angle; and a third placed to have a field of view parallel to and aligned with
the installation at the downstream end. A flashbulb activated by pressure-sensitive tape switches
was positioned on the impacting vehicle to indicate the instant of contact with the installation
and was visible from each camera. The films from these high-speed cameras were analyzed on a
computer-linked motion analyzer to observe phenomena occurring during the collision and to
obtain time-event, displacement, and angular data. A BetaCam, a VHS-format video camera and
recorder, and still cameras recorded and documented conditions of the test vehicle and
installation before and after the test.
The test vehicle was towed into the test installation using a steel cable guidance and
reverse tow system. A steel cable for guiding the test vehicle was tensioned along the path,
anchored at each end, and threaded through an attachment to the front wheel of the test vehicle.
An additional steel cable was connected to the test vehicle, passed around a pulley near the
impact point, through a pulley on the tow vehicle, and then anchored to the ground such that the
tow vehicle moved away from the test site. A two-to-one speed ratio between the test and tow
vehicle existed with this system. Just prior to impact with the installation, the test vehicle was
released to be free-wheeling and unrestrained. The vehicle remained free-wheeling, i.e., no
steering or braking inputs, until the vehicle cleared the immediate area of the test site.
24
APPENDIX B. TEST VEHICLE PROPERTIES AND INFORMATION
GEOMETRY (cm)
M1 2889 3375
M2 3062 3493
I I
4 4
fl AAO v (1 ~1R c
II1 1 -".%
0.196 s 0.990 s
Figure 12. Sequential photographs for test 40000 1-HBL2
(overhead view).
27
0.000 5
0.049 s
0.098 s
0.196 s
28
0.318 s
0.526s
0.733 s
0.990 s
29
30
XAcceleration at CG
10
U)
0-
0)
Cu
0
0
-10 i I - - - I
-;'I
--
+
,0
-- ,-.
0.1
. .
0.2
. .. .
0.3
. . .
0.4
. .
0.5
. . .
0.6
. . .
0.7
... .
0.8
. .
0.9
. .
1 z>
.0
lime (sec)
10-
0)
I rI I ii
0)
Tes Veice 199 Inentoa 470 Truc
0) 0-
I IiIi
-- -- --- --- --
'mTest Number: 400001-HBL2
Test Article: HESCO 0-3315 Flood Barrier
',Test Vehicle: 1995 International 4700 Truck
-10l II IInertial Mass: 6868 kg
II Gross Mass: 6868 kg
II Impact Speed: 81 km/h
II Impact Angle: 90.8 degrees
iI i
-9r
-2 t. . . . . . . . . . . . . . ... .... ... Ie ... II. . ... .I
0 0.1 0.2 0.13 0.4 0.5 0.6 0.7 0.8 0.9 1.0
lime (sec)
Figure 15. Vehicle lateral accelerometer trace for test 400001 -HBL2
(accelerometer located at center of gravity).
Z Accelerationat CG
Ii.',
CD
I II
i iI
I i
-10-
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Time (sec)
Figure 16. Vehicle vertical accelerometer trace for test 40000 1-HBL2
(accelerometer located at center of gravity).
X Acceleration over RearAxle
.w
*i I I I iI
0.
0
;P
-10-
Figure 17. Vehicle longitudinal accelerometer trace for test 400001 -HBL2
(accelerometer located over rear axle).
Y Acceleration over RearAxle
(A
0
I-
o,
C.,
(U
lime (sec)
4 .. .. . . .I I
(A I
0
-6.
"• - - - --
i- -- -
Test Number: 400001-HBL2
-- - - - Test Article: HESCO C-3315 Flood Barrier
-- -- -- ----------...-.......
>Test Vehicle: 1995 International 4700 Truck
Inertial Mass: 6868 kg
6----- ------- G ross Mass: 6868 kg
Impact Speed: 81 km/h
Impact Angle: 90.8 degrees
88- ....
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
lime (sec)
Texas Transportation Institute, "DOS K12 Crash Test and Evaluation of the
HESCO C-3315 Flood Barrier," April 2005
Engineering
Evaluation of Hesco
Barriers Performance
at Fargo,ND 2009
Prepared for:
Prepared by:
1
ATTACHMENTS
ii
1.0 Introduction
The Fargo, North Dakota area, along with its sister city across the river, Moorhead, Minnesota
was recently faced with massive flooding from the Red River of the North. Due to an unusually
wet fall, followed by a cold, snowy winter, the normally placid Red River was forecasted by the
National Weather Service (NWS) to reach a flood crest elevation of 37 to 39 feet in Fargo by late
March.(') Unfortunately, unusual conditions continued to dominate, forcing the NWS to revise
their forecast up to 41 feet, higher than any flood level on record, and predicted for only 7 to 10
days from then, instead of the originally estimated three weeks. As the river rapidly rose to
nearly 39 feet, new forecasts predicted the river might even go as high as 42 or even 43 feet.
This situation, of course, generated intense concerns, and forced the rapid evaluation and
subsequent use of several different methods of flood protection. To protect the City of Fargo,
temporary clay dikes, which are the most common form of flood protection in the area, were
used to the greatest extent possible to raise existing flood protection to at first 42 feet, but later
raised to 44 feet in response to the revised forecasts. Traditional sandbag dikes were also widely
used, but due to time constraints, reliability, height limitations, and availability of volunteers, the
length of dikes that could be deployed could not meet all the area needs. Therefore, the US
Army Corps of Engineers, who were assisting the City of Fargo, turned to Hesco Bastion, LLC
for help, and to provide the remaining flood barriers. Hesco barriers have been well-tested by
the U.S. Army Corps of Engineers (COE) for use as temporary flood protection, and widely used
in many flood situations around the country, including New Orleans for temporary hurricane
protection.
Footnote: (1) For reference, "normal" flood stage here is considered to be anything over 18 feet. The 1997 flood, called the
"Flood of the Century" and which inundated Grand Forks that year, reached a stage height in Fargo of 39.6 feet. The highest
level on record was 40.1 feet, reached back in 1897.
1-1
U:\2283\01\Hesco Bastion Report~doc
Hesco barriers are able to be installed relatively quickly, and due to this speed of deployment,
approximately 10 miles of barriers were installed over a 4 to 5 day period. Fortunately, the
combination of clay dikes, sandbag dikes, and Hesco barriers, together with the tremendous
efforts by City of Fargo staff, National Guard, and volunteers, worked, and the City of Fargo
largely escaped serious flooding.
In the aftermath of these efforts, various comments surfaced regarding the performance of the
Hesco Barriers. In particular, concerns were raised about the possibility of the Hesco's sliding
laterally over the ground surface due to water pressure, and the increased rate of seepage through
the barriers over expected rates. Also, concerns were raised about two specific locations where
Hesco's had been deployed, and significant leakage had occurred requiring emergency actions to
prevent possible breaching.
Hesco Bastion, concerned about these comments, approached Wenck Associates, Inc. (Wenck)
to provide an independent engineering evaluation of the performance of the Hesco barriers
during the Fargo floodfighting efforts. The scope of this engineering evaluation was agreed to
be as follows:
" Meet with Mr. Dennis Barkemeyer of Hesco Bastion to discuss installation procedures
that were used at the various sites in Fargo.
* Interview City of Fargo/COE staff to discuss product use, problems they encountered
or noted, comparison to other dikes (sand bag and clay), and comments on the products.
* Revisit dike locations where the City/COE indicated they had problems or issues.
• Evaluate product and its uses in Fargo for floodfighting in light of the frozen ground
oftentimes encountered, and the soft clay soils.
" Prepare a letter report or technical memorandum that outlines the findings of the above
work, and provides recommendations for future use in this environment.
1-2
U:\2283\01\Hesco Bastion Report.doc
1.1 PURPOSE OF EVALUATION
This independent engineering evaluation was requested by Hesco Bastion, LLC to
address comments raised after Hesco units were installed in Fargo, North Dakota for
combating flooding by the Red River of the North in March, 2009.
1-3
U:\2283\0 I\Hesco Bastion Report.doc
2.0 City of Fargo Uses of Hesco Barriers
2.2 SIZES
The City of Fargo deployed two types of Hesco units, the standard and flood barriers in
the 3' deep by 3' high by 15' long, and 3' deep by 4' high by 15' long sizes. The standard
barriers have separation fabric dividing each barrier into five equal compartments, 3'
long each. The flood barriers do not utilize the separation fabric between compartments,
so each unit is able to have continuous fill material.
2-1
U:\2283\01\Hesco Bastion Report.doc
rising of the Red River had completely saturated these soils, making conditions very
muddy. Dikes then had to built on top of, and using, these saturated clay soils, often
while rains continued. Subgrade conditions were thus far from ideal.
Later in the week prior to the predicted flood crest for the Red River, the weather
changed again to very cold, and the area received nearly one foot of snow. These cold
conditions persisted for awhile, and caused many of the soils to freeze at the surface,
further complicating subgrade conditions on which the Hesco barriers (and all temporary
dikes) were built.
2-2
UA\2283\01\Hesco Bastion Report.doc
3.0 Interviews with City and City
Representatives
Two specific locations of concern were also brought up by the City of Fargo. The first
was on 5th Street South (just south of 1-94), and the second was along the south side of
Drain 27 (just east of 1-29). It was stated that the 5 th Street area had to be buttressed with
material on the back side of the Hesco barriers and a section of sandbag dike, after a
significant leak was found in the transition area from Hesco barrier to sandbag dike. The
second was the Drain 27 area, which had shown settlement in one area where the Hesco
barriers were placed on top of an existing earthen levee.
3-1
U:\2283\01\Hesco Bastion Report.doc
about the issues raised above, and what the engineers observed, as well as about the two
locations of concerns.
The first location of concern, 5th Street South, was thought to be a problem due to a
sandbag dike being butted up directly to a Hesco barrier, with little or no overlap. This
transition area had started to leak, so emergency crews buttressed the back side with clay
to stop the excessive leakage. Field personnel thought the problem was due to the poor
transition, not the Hesco units.
The second location of concern, along the south side of Drain 27, was due to water
pushing through a stormwater structure and discharging rapidly out the top of a manhole.
This water saturated the dike around the structure and caused a section of the dike to
slump (sag), including the Hesco units on top of the dike. Field personnel packed clay
over the top of the manhole, and built a small cofferdam around it to stop the leakage.
Field personnel thought this issue had nothing to do with the Hesco units, only the
stormwater structure.
Field personnel indicated that the amount of dikes constructed with the Hesco barriers in
a short time was instrumental in protecting the city. Building the 10 miles with sandbag
dikes would have been very difficult with the time and volunteers available, plus the
miles already built with sandbags. Additionally, the uniformity of the dikes erected with
Hesco units was thought to be very important, especially relative to sandbag dikes raised
on an emergency basis by volunteers. They also noted that the units adapted to terrain
changes very well. Most thought that seepage under the units was less than what a
sandbag dike would be, even without the poly-sheeting used in most locations. Field
personnel believed that any leaning or apparent sliding of the units was most likely due to
settlement of the units into the saturated clay subsoils, as subgrade locations were often
poor due to the saturated conditions, and then the snow and freezing conditions, rather
than actual sliding.
3-2
U:\2283\01\Hesco Bastion Report.doc
4.0 On Site Evaluations by Wenck Associates,
Inc.
The 5th Street Hesco barriers were difficult to inspect for the concerns that were brought
up by City staff. The area behind the Hesco barriers and sandbag dike had been filled in
with sand after issues were first brought up. During interviews with field personnel it was
determined that this area most likely didn't have the sandbag dike tied in sufficiently to
the Hesco barriers. It was stated that the sandbags butted up directly to the Hesco units,
instead of using a sufficient overlap to adequately protect the transition.
In the Drain 27 area, Hesco barriers were placed on top of an existing earthen levee.
Settlement was noted in a section of the earthen levee just east of 1-29 on the south side
of the drain. Interviews and inspection showed that this appeared to be due to an existing
storm sewer running through the existing earth levee and discharging to the drain. After
installation of the Hesco barriers and noticeable settlement in part of the dike, it became
apparent that a storm sewer structure located within the earthen levee was discharging
water through the top of the structure and onto the earthen levee. This leakage completely
saturated the area and allowed the Hesco barriers to settle into the earthen levee, as well
as causing settlement of the levee itself.
The Fargo Country Club area consisted of Hesco barriers being deployed through the
golf course. Evidence of soft soils were noted from the ruts left by equipment used to
deploy and fill the Hesco barriers.
4-1
U:\2283\01\Hcsco Bastion Rcport.doc
The 40th Avenue south area had Hesco barriers installed on top of an existing earthen
levee. A concern of the barriers leaning was made during interviews. Measurements
showed that the barriers were leaning approximately 3.5" in 4 vertical feet. These barriers
have also settled on the water side approximately a V2", and none on the dry side.
The Timberline area consisted of Hesco barriers that were used for primary temporary
protection. Barriers were placed in residential backyards along a drainage channel. It was
noted that some of the Hesco barriers were leaning. Measurements were made at a few
locations, which showed 6.5" of lean in four feet. Field personnel indicated that the
barriers were leaning during installation because of the lay of the land, and that they had
performed field measurements over a couple of days and determined that the units had
not shown any movement.
4-2
U:\2283\01\Hesco Bastion Report.doc
5.0 Technical Evaluations
This section discusses three different traditional failure mechanisms for retaining
structures such as the Hesco barriers; sliding, overturning/tipping, and seepage, and the
Hesco barriers resistance to them. Within each of this subsections, references to previous
studies are introduced and discussed (if available), followed by an independent review.
5.1 SLIDING
Sliding of a retaining system (i.e., the Hesco barriers) is most simply defined by Equation
1, which relates the resisting and driving forces for sliding to the overall factor of safety
against sliding. For long-term situations (i.e. permanent walls), it is considered good
practice to have a factor of safety (FS) against sliding equal at least 1.5, meaning that the
resisting forces are 50% greater than the driving forces. For short-term situations,
applicable to temporary flood protection dikes, this acceptable factor of safety is 1.3.
Where: Fv = Weight of basket (1' "slice" of basket) minus uplift force (lbs/ft)
6= Interface friction coefficient
c = Cohesion, or undrained shear strength (lbs/ft2 )
L = Length, or basket depth (ft)
Fh = Horizontal force from water (lbs/ft)
5-1
U:\2283\01\Hcsco Bastion Report.doc
sand, coarse sand, and gravel), and different types of surfacing materials (earth, concrete,
and grass).
Table 1 of the referenced report, shown below, gives the interface coefficients of friction
for the fill soils and surfacing materials.
Using the above information, the authors of the referenced report compiled factors of
safety against sliding for 30 different load cases, considering various structure heights,
flood heights, fill types, and surfacing materials. This information is provided in
Attachment B, but most of the cases are shown again (albeit in a different order) in Table
2 below. Information not included in Table 2 are the cases where the flood height was
higher than the structure height, and also cases where the fill material was gravel
(because site observations in Fargo noted that only sand was used to fill the Hesco
Concertainers).
Table 2. Factor of safety against sliding for various load cases organized by flood
height'
Structure Surface
Fill Type
FS (full FS (no
Case Flood Height
Hei2ht Tvoe ulift) uplift)
4 3 3 Concrete Fine sand
5 3 3 Concrete Coarse sand
1 3 3 Earth Fine sand
2 3 3 Earth Coarse sand
7 3 3 Grass Fine sand
8 3 3 Grass Coarse sand
This table indicates that the authors found acceptable or marginally acceptable factors of
safety against sliding are achievable for many of the cases analyzed, including all of the
cases where the flood height was 3 feet, the containers were 4 feet high, and the
containers were placed on earth.
An analysis was also completed for a two layer Hesco system (consider a double
container base and a single container top) using the same theories as used to develop
Table 2 (i.e., forces acting on a one-foot cross-section of barrier). This information is
provided in Table 3, below.
5-3
U:\2283\01\Hesco Bastion Rcport.doc
Table 3. Factor of safety against sliding for various load cases organized by flood
height" 2
Red highlighting means the factor of safety is not acceptable (at or below 1.0).
Yellow highlight means that the factor of safety is only marginally acceptable (between 1.0 and 1.3).
Blue highlighting means that the factor of safety is acceptable (greater than 1.3) for short-term
conditions.
(2) Overall system is set up as 2 containers on the bottom and one on top.
This table shows that careful engineering is needed before installing such a two-tier
system, as acceptable factors of safety are achievable for much fewer cases than the
single tier system. These relatively low calculated factors, together with some concerns
about the single tier system, especially with flood height equal to barrier height, showed
that some actual field testing of the barriers should be done. This was largely due to
actual field experience not squaring well with theory.
5-4
U:\2283\01\Hesco Bastion Report.doc
memo to Hesco Bastion LLC, dated April 30, 2009. Tests on 3' deep by 3' wide by 4'
high sections were conducted with the filled units placed on various base surfaces. The
total amount of force required to move the unit was recorded, along with the volume and
weight of the filled unit. This allowed the actual friction coefficient and factor of safety
to be computed in a real-life environment. An independent soils laboratory performed
soil analyses on submitted fill samples, and gave a unit weight and gradation of the fill
sand for both uncompacted and medium compacted samples (see Tables 4, 5 and 6).
[Note: The field tests did not consider overturning, bearing capacity of the underlying
soils, or seepage rates of the units.]
Grass -
Muddy 2 44.0 3300 3956 4488 0.83 0.74
Grass -
Muddy/
Saturated 3 51.4 3400 4621 5243 0.74 0.65
PCC
Street 4 46.7 2700 4198 4763 0.64 0.57
PCC
Street 5 49.8 2600 4477 5080 0.58 0.51
Notes: Weights of sand are from laboratory tests on samples obtained during field testing - 89.5 PCF is average
uncompacted, and 102.0 PCF is average of compacted samples to approximately 88% Standard Proctor.
PCF = Pounds per Cubic Foot
PCC = Portland Concrete Cement
5-5
U:\2283\01\Hcsco Bastion Report.doc
Table 5: Summary of Factor of Safety Calculations for Water 3' High Against 3' x 3' x 4'
High Baskets
Force
Causing
Forces Resisting Slidin Sliding
Basket Fuplift Fw
Weight (y. x H x (y. x H x Factor of
Test Surface (,s x -VA w2/2) 1, FR w)/2 Safety
(Ibs) (Ibs) (Ibs) (Ibs)
Grass 4387 842 0.58 2056 842 2.44
Grass - Muddy 3956 842 0.78 2429 842 2.88
Grass -
Muddy/Saturated 4621 842 0.70 2645 842 3.14
PCC Street 4338 842 0.58 2028 842 2.40
Table 6: Summary of Factor of Safety Calculations for Water 4' High Against 3' x 3' x 4'
High Baskets
Force
Causing
Forces Resisting Sliding Sliding
Basket Fuplift Fw
Weight (y, x H x (yw x H x Factor of
Test Surface (ys X _Nq W 2/2) • FR w)/2 Safety
(Ibs) (Ibs) (Ibs) (Ibs)
Grass 4387 1123 0.58 1893 1497 1.26
Grass - Muddy 3956 1123 0.78 2209 1497 1.47
Grass -
Muddy/Saturated 4621 1123 0.70 2449 1497 1.63
PCC Street 4338 1123 0.58 1865 1497 1.24
5-6
U:\2283\01\Hcsco Bastion Report.doc
1) Summary of Calculated Friction Coefficient Data
Friction coefficients were calculated for each of the field tests performed.
The field data showed significantly higher friction coefficients than the original
engineering calculations, which used published friction coefficients for the different
base materials. This is believed to be due to the deformation of the bottom edge of the
basket, which was observed as it began to slide. This deformation cannot be
discounted, however, as it would occur in the event that the lateral loads applied to
the basket were enough to cause lateral movement. Therefore, the field measured
friction coefficients are believed to be valid for the specific situations in which the
baskets were tested.
These higher friction coefficients, in turn, show that the actual performance of the
Hesco units in resisting sliding is highýr than the calculated resistance using
published friction coefficients, as shown by the factors of safety calculated in Tables
5 and 6.
5-7
U:\2283\01\Hesco Bastion Report.doc
5.2 OVERTURNING/TIPPING
Traditional methods of overturning analysis are not truly applicable for this type of
container because of the general deformability of the system, plus the possibility that
uplift pore-water pressures can often be dissipated
through the sandy infill material. Even if a layer
of sand is frozen at the base of the Hesco -- .0
RESISTING DRIVNG
Therefore, the overturning and tipping will most BLOCK BLOCK
likely be related to either 1) installation issues (where infill material is placed in a manner
such that initial container tilt occurs), or 2) thaw of the subsoil on only one side of the
container occurs, such that some differential settlement occurs (e.g., rising water on one
side of barrier thaws the soil beneath one side).
As discussed earlier in this report, some of the units were experiencing some tilt, with
angles nearing 6 or 7 degrees. Based on information obtained during the field work, it is
believed that the units showing some tilt were either installed that way, or settlement of
the units into the base soils occurred.
For a single layer system, a tilt of less than 14 degrees is a reasonable maximum value.
The reason for this is because the system tends to operate as a block. Therefore, at an
angle of 14 degrees or less, there is at least 7 times the mass holding back the container
from tipping. When considering this angle, the resisting mass and the associated moment
arm of the units, based on the resisting and driving forces, a calculated system factor of
safety against overturning is greater than 30. This is shown by Equation 2 below.
Overturning or tipping is not considered to be a significant problem, therefore, unless the
entire subgrade fails.
5-8
U:\2283\01\Hesco Bastion Report.doc
FS = Resisting Forces
Driving Forces
x Density
FS = Resisting Block Area x Resisting Moment Arm
Driving Block Area x Driving Moment Ann x Density (Equation 2)
5.3 SEEPAGE
Field personnel's input on the issue of seepage by the Hesco barriers varied greatly.
Some thought that the seepage was excessive, while others thought it was less than a
traditional sandbag levee would be. Most areas had poly-sheeting placed on the wet side
of the Hesco units. However, an area of Drain 27 did not receive poly-sheeting, and the
field staff thought that the seepage wasn't excessive and was easily managed.
Assessment of actual seepage rates in the field were not part of this report.
5-9
U:\2283\01\•Hesco Bastion Report.doe
6.0 Summary and Recommendations
Overall, the consensus of opinion among users of the Hesco barriers for the Fargo floodfight is
that the barriers are well-designed, and were vital to the success of the effort to contain the
flooding from the Red River of the North. They were appreciative of the speed of deployment
(vital in emergency situations such as this), their ability to adapt to irregular subgrades, and the
uniformity of results compared to sandbag dikes. Some cautions oftentimes repeated were to be
careful with proper filling of the barriers, and to pay particular attention to the subgrade the
barriers are placed on, as this can cause significant problems. Additionally, transitions between
Hesco's and other types of dikes need to be done carefully, allowing an adequate overlap to
prevent a weak spot in the resulting dike. Adequate monitoring of the completed barrier wall
must be done, just as for any temporary dike, throughout the emergency period. Most users,
especially those who used them in the field, declared they would use them again, given the same
situation.
Some useful recommendations were made, however, and should be considered by Hesco
Bastion.
o Consider use of colored hinge pins to join the units together. This would make the
visual inspection of finished units easier and faster, particularly at night (i.e., Were
the baskets properly joined during installation?).
o Additional training. Several users reported receiving only very minimal training in
how to properly install the units. This caused considerable problems and delays in
getting the various installations properly started, especially as new workers arrived to
help.
6-1
UA2283\0 I Hesco Bastion Report.doc
o Preparation of a Guidance Document for communities considering using the Hesco
barriers. Like most products being considered to fight a flood, proper engineering
needs to be done prior to installing them. Such a guidance document could be given
to communities prior to their using Hesco's, recommending the type of engineering
needed, the considerations that need to be made, and procedures to follow for such
things as needed site preparation, height of barriers needed for the predicted flood
elevations and their configuration (e.g., 2-4' barriers with 1-4' stacked over them, or
2-4' with 2 more 4' barriers stacked over them), lessening seepage with plastic
sheeting and how to do it (front face of barrier, back face, how anchored, etc.),
joining Hesco barrier walls to sandbag or clay dikes (necessary overlap, tie-ins, etc.),
and proper installation procedures.
6-2
U:\2283\01\Hesco Bastion Report.doc
Attachment A
1/
I
I- -
1'
N
,&- Add
I-
-l
F-
I1
CrAdd
fA '
I.
r.
'A
I
7
II~~ P
N
N
- I
----~1 N
p.
N
N
N
\ ,. N
-j
SA-My
L-'
RomC-ý Add,.
PORTA-D,..
-I Gnvd Bhm-
- - *XVD 198AFt-p Dý
V.1I'l
Add
I-
IL - -
- 9
'K
Attachment B
ENGINEERING ANALYSIS
The ability of the Concertainer® structure to withstand hydrostatic and uplift forces, as
well as other forces, results primarily from a combination of shape and weight of the
structure and the frictional resistance generated along its base. The linkages between the
units also allows for the load on a single unit to be distributed over several adjacent units.
The structure is compliant and deforms slightly as a response to applied loads. This
particularly important when the structure responds to uplifting forces. The
Concertainer® basket is basically a shell and will experience almost no uplifting forces.
Since the basket is open at the bottom, if the unit is raised the fill material remains in
contact with the ground surface. The uplifting force on the fill will be due to buoyancy
and not from any mechanical force of the basket. Therefore, the conventional analysis of
stability based upon overturning is not applicable to the Concertainer® structure.
However, because the basket and fill could be displaced laterally, the analysis of the
stability of the structure to sliding is appropriate.
The ability of the structure to resist lateral forces it can be theoretically analyzed based
upon the assumption that the structure will respond as a rigid body to hydrodynamic
forces. A general load case is shown in Figure 1.
Fw, Fi -- II II
II w II
II w H"II
h
4II Fh -> II <-Bt3-÷
II
II
II hLA
t 1" +-Rh
Fu Rv
The Figure illustrates that the force per foot of structure on the Concertainer® can result
from several sources:
The formulas for the static forces for the load case shown in Figure 1 and their lines of
action from point A, are as follows:
W= ½/72r, BH @ B/2
Fh =½2yh 2 @h/3
Fu= ½"yBh @ 2/3 B
Rv =W- Fu @ 1/3 B
Rh = Fh with maximum value of Cf Rv
Where:
B = width of the Concertainer®
H = height of the ConcertainerD
yr,11 = unit weight of the fill or S y
= unit weight of water
S specific gravity of the fill
h = height of water above the base of the structure
The resistance to sliding can be expressed as a factor of safety, which is the ratio of the
resisting forces to the applied forces. The horizontal resisting force is the frictional
resistance generated along the base of the structure, given by Cf Rv. The applied
hydrostatic force is Fh. Thus factor of safety against sliding can then be defined by
SF = Cf Rv/Fh = Cf(W-FU)/Fh
The analysis presented is based upon treating the structure as a rigid body, the
Concertainer® is actually deformable and it would affect the impact loads and the
overturning. The Concertainer® is highly resistant to impact loads because the basket
and fill deform when the load is applied, thus lengthening the time over which the
impacting object is stopped, and hence reducing the force. The amount of deformation
would depend upon the where the impact occurred, with more deformation occurring
near the top of the structure.
The Concertainer® structure is well suited to resist impact loads. The structure is
compliant such that it will deform under loads. This property means that a unit will
absorb debris loads and actually experience a lower force from debris than rigid
structures would experience for the same debris. This can be explained because debris
loads resulting from floating objects such as vegetation, logs and lumber are impact
loads. In an impact load the force produced by the impacting object depends upon the
initial momentum of the object, its mass time its velocity, and the time over which the
objects velocity is reduced to zero by the impact; that is its deceleration. The compliancy
of the structure thus extends the time over which the impacting object is stopped. This
results in a reduced deceleration and hence a reduced force on the structure. The
performance of the structure under debris loads would also depend upon the water depth
relative to the top of the structure, the fill in the structure and the shape of the debris
object. Impact tests for specific objects of interest for various fill types would need to be
conducted. The effect of debris loads on the performance of the Concertainer® can be
accounted for by including impact loads in the analysis of the factor of safety against
sliding.
The performance of the Concertainer® on various surfaces will depend both on the type
of surface and the type of fill used in the structure. This is because the same fill will
interact differently with different surface materials. The net effect of the surface/fill
interaction can be expressed through the interface friction coefficient. As shown above,
the friction coefficient directly affects the resistance of the structure to sliding. Other
factors that may need to be considered concerning the surface upon which the structure is
placed are the permeability of the surface and it's bearing capacity. Given the test
conditions described in the solicitation, the bearing capacity and permeability of the test
surfaces should present no problems. However, in actual usage, these issues would need
to be investigated at each field site.
The actual coefficient of friction between different fill materials and the different test
surfaces will depend upon the detailed characteristics each. Since these are not known at
this time, representation values of the friction coefficient can be taken from published
values. The following values were used in the stability analysis:
The coefficients of friction between concrete and for various fill types are taken from the
Shore Protection Manual (Table 7-15 and 7-16). Table 7-16 gives the friction
coefficients for concrete dams on sand and gravel. For freshly graded surfaces, earthen
material is present both in the container and on the surface. The friction resistance will
depend upon the angle of internal friction for the each material. The values used in the
analysis for the various fills on an earthen surface are based upon the angles of internal
friction for firmly packed sediments as given in Table 7-15 of the SPM. For the grass
surface case, the approach taken is that the coefficient of friction will be assumed to be
smaller than for a concrete surface. Thus the concrete values were reduced for gravel,
coarse sand, and fine sand by factor of .67, .77 and .86 respectively.
The performance of the Concertainer® under a particular set of test conditions can be
determined using the formulas presented above. Various load cases were considered
based upon the type of surface at the test site, the height of the floodwater, the size of the
structure and the fill material. The results of these calculations are given in Table 2.
A single load case will be used to illustrate the methodology used in computing the factor
of safety against sliding. The structure will be assumed to be placed on either grass, earth
or concrete. A 3 foot by 3 foot unit will be subject to a 3 foot flood, with no waves or
impact loads. The structure will be fill with either fine sand, coarse sand, or gravel. The
formula for the factor of safety against sliding for a 3 foot Concertainer® unit (b=H=3
feet) as
FS = Cf ( W-Fu)/Fh
or
FS = Cf (HBSy-hBy/2)I(h 2,112) = 2BCf (HS-h/2)/(h2 )
For the various fill materials and surface types the values of Cf and S can be specified.
For example, for an earthen surface and with a fine sand fill, S= 1.60 and Cf = .58. The
computed factor of safety is
This is the result shown in Table 2 for load case 1. For coarse sand S = 1.76 and Cf =
.67, and the resulting factor of safety is 1.69, as shown in Table 2 for load case 2. For
gravel, S = 1.92 and Cf = .78, and the factor of safety is 2.22, as shown in Table 2 as load
case 3.
The other load cases listed in Table 2 were based upon changing the surface types, flood
water depth and unit size. A second set of calculations were performed based upon
increasing the flood water depth to 4 feet, and placing a 2 foot by 2 foot Concertainer®
on top of a 3 foot by 3 foot unit. The factors of safety against sliding for different
surfaces are given in load cases 28, 29 and 30.
Overall the analysis indicates that for the fill types and surface types considered, large
changes in the factor of safety can occur. For example, for a 3 foot by 3 foot unit on a
concrete surface the factor of safety changes from .77 to 1.13, to 1.70 as the fill is
changed from fine sand, to coarse sand and then to gravel.
Table 2. Factor of safety against sliding for various load cases.
1 E 3' 3, FS 1.28
2 E 3, 3' CS 1.69
3 E 3, 3, GR 2.22
4 C 3, 3' FS .77
5 C 3, 3, CS 1.13
6 C 3, 3, GR 1.70
7 G 3, 3, FS .66
8 G 3' 3, CS .88
9 G 3, 3' GR 1.14
10 E 4W 3' FS 2.53
11 E 4, 3' CS 3.30
12 E 4' 3' GR 4.28
13 C 4, 3, FS 1.52
14 C 4, 3, CS 2.22
15 C 4, 3, GR 3.29
16 G 4, 3, FS 1.31
17 G 4' 3, CS 1.72
18 G 4' 3, GR 2.20
19 E 4' 4, FS 1.28
20 E 4' 4, CS 1.69
21 E 4, 4, GR 2.22
22 C 4, 4, FS .77
23 C 4, 4, CS 1.13
24 C 4, 4, GR 1.70
25 G 4, 4, FS .66
26 G 4, 4' CS .88
27 G 4, 4, GR 1.14
28 E 4, 5' FS 1.07
29 E 4, 5, CS 1.41
30 E 4, 5, GR 1.85
The data presented herein by HESCO Bastion USA, LLC from the Rapid
Deployment Flood Wall Testing at Engineering Research and Development Center
(ERDC) Water Experimental Station (WES) in preliminary information from Dr. Joseph
Suhayda.