PB Test Procedure
PB Test Procedure
Test Results:
Project Details:
Environmental Conditions:
If you provide this information, I can correctly fill out your report following IEC 60439 standards. Let me
know how you’d like to proceed!
You said:
You fill Routine tests section, insulation test, Dielectric test, primary injection test. Fill Same like in
table,like the report. according to electrical standards values
ChatGPT said:
I'll complete the Routine Tests, Insulation Test, Dielectric Test, and Primary Injection Test sections with
standard values according to IEC 60439 and electrical testing standards.
I'll generate a properly formatted version of these sections for your test report. Let me prepare that for
you.
1. Routine Tests
Mechanical Function ✅ Accepted IEC 60439 Doors, locks, and fasteners secure
Voltage Applied R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E
1000V for 10s >999 >999 >999 >999 >999 >999 >999 >999 >999
Remarks: All insulation resistance values exceed 999 MΩ, meeting IEC 60439 requirements.
3. Dielectric Test
Breaker Type Rated Current (A) Minimum Trip Current (A) Maximum Trip Current (A)
Trip Time (s) Status
This is a properly formatted version based on electrical testing standards. Let me know if you need
modifications or additional details!
1. Routine Tests
Objective: Check for physical damages, loose connections, and proper labeling.
Procedure:
1. Visually inspect the panel for any physical damage, corrosion, or missing components.
3. Verify that all components (MCBs, MCCBs, busbars, and terminals) are securely mounted.
4. Ensure proper earthing and verify that all fasteners are tightened.
---
Procedure:
3. Use a torque wrench to verify that all electrical connections are tightened to manufacturer
specifications.
✅ Pass Criteria: All mechanical operations function smoothly without obstructions or excessive force.
---
Procedure:
1. Set the multimeter to voltage mode and check supply voltages at input terminals.
✅ Pass Criteria: Proper voltage, correct wiring continuity, and functional indicators.
---
Objective: Measure insulation resistance between conductors to detect potential insulation breakdown.
Device Used: Megger Insulation Tester (Megger MIT1025, Fluke 1587, Kyoritsu 3125A).
Procedure:
---
Objective: Ensure panel insulation can withstand high voltage without breakdown.
Device Used: High Voltage Tester (Hipotronics 880PL, Phenix HC Series, Megger VLF Sine 34).
Procedure:
✅ Pass Criteria: No insulation breakdown and leakage current should be within limits.
---
Device Used: Primary Injection Test Set (Omicron CPC100, Megger SPI225, SMC PTE-100-C).
Procedure:
2. Connect the primary injection tester to breaker input and output terminals.
3. Select the test current (e.g., 3x rated current) based on the breaker rating.
✅ Pass Criteria: The breaker should trip within the specified time range (e.g., 0.2 - 0.5s).
---
---
Safety Precautions:
Use PPE (gloves, goggles, insulated shoes) when handling high voltage.
---
Conclusion:
By following this process and using the correct test equipment, you can ensure the LV Panel Board meets
IEC 60439 standards for insulation, dielectric strength, and breaker functionality.
1. Routine Tests
Procedure:
1. Visually inspect the panel for any physical damage, corrosion, or missing components.
3. Verify that all components (MCBs, MCCBs, busbars, and terminals) are securely mounted.
4. Ensure proper earthing and verify that all fasteners are tightened.
---
Procedure:
✅ Pass Criteria: All mechanical operations function smoothly without obstructions or excessive force.
---
Objective: Verify that electrical components operate correctly under no-load conditions.
Procedure:
1. Set the multimeter to voltage mode and check supply voltages at input terminals.
✅ Pass Criteria: Proper voltage, correct wiring continuity, and functional indicators.
---
2. Insulation Resistance Test (Megger Test)
Objective: Measure insulation resistance between conductors to detect potential insulation breakdown.
Device Used: Megger Insulation Tester (Megger MIT1025, Fluke 1587, Kyoritsu 3125A).
Procedure:
Objective: Ensure panel insulation can withstand high voltage without breakdown.
Device Used: High Voltage Tester (Hipotronics 880PL, Phenix HC Series, Megger VLF Sine 34).
Procedure:
3. Connect the tester’s high-voltage lead to the live parts (busbars, terminals).
✅ Pass Criteria: No insulation breakdown and leakage current should be within limits.
---
Procedure:
2. Connect the primary injection tester to breaker input and output terminals.
3. Select the test current (e.g., 3x rated current) based on the breaker rating.
✅ Pass Criteria: The breaker should trip within the specified time range (e.g., 0.2 - 0.5s).
---
---
Safety Precautions:
Use PPE (gloves, goggles, insulated shoes) when handling high voltage.
---
Conclusion:
By following this process and using the correct test equipment, you can ensure the LV Panel Board meets
IEC 60439 standards for insulation, dielectric strength, and breaker functionality.
Incomer Tag Injected Current (A) Bus Section No. of Joints Leakage Current (mA)
Status & Comments: ✅ Approved (Leakage current within acceptable limits as per IEC 60947)
DB Testing Report
Rated
Breaker Min Trip Max Trip Injected Tripping
Ref Current (In) Setting L1 L2 L3 Status
Type Time (s) Time (s) Current (A) Time (s)
(A)
Status & Comments: ✅ Approved (Tripping times are within IEC 60947 standard limits)
This table format follows electrical testing standards, including IEC 60947 for breakers. Let me know if
you need any modifications!
I'll complete the Routine Tests, Insulation Test, Dielectric Test, and Primary Injection Test sections with
standard values according to IEC 60439 and electrical testing standards.
I'll generate a properly formatted version of these sections for your test report. Let me prepare that for
you.
1. Routine Tests
Mechanical Function ✅ Accepted IEC 60439 Doors, locks, and fasteners secure
Voltage Applied R-Y Y-B B-R R-N Y-N B-N R-E Y-E B-E
1000V for 10s >999 >999 >999 >999 >999 >999 >999 >999 >999
Remarks: All insulation resistance values exceed 999 MΩ, meeting IEC 60439 requirements.
3. Dielectric Test
Breaker Rated Current Minimum Trip Current Maximum Trip Current Trip Time
Status
Type (A) (A) (A) (s)
This is a properly formatted version based on electrical testing standards. Let me know if you need
modifications or additional details!