Scenario Analysis
Scenario Analysis
Risk Analysis
09-Oct-20 1
Methods of Describing Risk
• Scenario Analysis
In scenario analysis, we estimate expected cash
flows and asset value under scenarios, with the
intent of getting a better sense of the effect of
risk on value. Estimation of one or more
factors is done in a favorable (Optimistic)
direction & in an unfavorable (pessimistic)
direction to investigate the effect of these
changes on study results.
09-Oct-20 2
Question: An engineer is evaluating three alternatives for new equipment at
Emerson Electronics. She has made three estimates for the salvage value,
annual operating cost, and life. The estimates are presented on an
alternative-by-alternative basis in Table 18–1. For example, alternative B
has pessimistic estimates of S $500, AOC $4000, and n 2 years. The first
costs are known, so they have the same value. Perform a scenario analysis
and determine the most economical alternative, using AW analysis at a
MARR of 12% per year.
09-Oct-20 3
Solution
For each alternative in Table 18–1, calculate the AW value of
costs. For example, the AW relation for alternative A,
pessimistic estimates, is
AW = - 20,000(AP,12%,3) -11,000 = $-19,327
Table 18–2 presents all AW values.
09-Oct-20 4
Question: From the following information, calculate NPW for
each scenario by assuming I= 1,25,000. MARR=15% & life of
project is 5 years.
09-Oct-20 6
NPW of Most likely case scenario at 15%
=-1,25,000+(2,000*50-2,000*15-10,000)*(P/A,
15%, 5)+40,000(P/F,15%,5)
=-1,25,000+ 60,000*3.352+40,000*0.4972
=96,008 (Profit)
NPW of Best case scenario at 15%
=-1,25,000+(2,400*53-2,400*12-8,000)*(P/A,
15%, 5)+50,000(P/F,15%,5)
=-1,25,000+ 90,400*3.352+50,000*0.4972
=2,02,880 (Profit)
It indicates that there is no risk of investment.
09-Oct-20 7
Thank You
09-Oct-20 8