As 1851-2012
As 1851-2012
AS 1851—2012
Australian Standard®
FP-008—Fire Pumpsets
FP-009—Fire Hydrants
FP-011—Special Fire Hazards
FP-017—Emergency Management Procedures
FP-019—Passive Fire Systems
ME-062—Ventilation and Airconditioning
Standards Australia wishes to acknowledge the participation of the expert individuals that
contributed to the development of this Standard through their representation on the
Committee and through the public comment period.
Standards may also be withdrawn. It is important that readers assure themselves they are
using a current Standard, which should include any amendments that may have been
published since the Standard was published.
Detailed information about Australian Standards, drafts, amendments and new projects can
be found by visiting www.standards.org.au
Australian Standard®
COPYRIGHT
© Standards Australia Limited
All rights are reserved. No part of this work may be reproduced or copied in any form or by
any means, electronic or mechanical, including photocopying, without the written
permission of the publisher, unless otherwise permitted under the Copyright Act 1968.
Published by SAI Global Limited under licence from Standards Australia Limited, GPO Box
476, Sydney, NSW 2001, Australia
ISBN 978 1 74342 313 4
AS 1851—2012 2
PREFACE
This Standard was prepared by the Standards Australia Committee FP-001, Maintenance of Fire
Protection Systems and Equipment, to supersede AS 1851—2005, Maintenance of fire protection
systems and equipment.
This edition of AS 1851 incorporates a considerable amount of new material and technical changes for
the routine service (maintenance) of fire protection systems and equipment in the light of user
experience and feedback from regulatory bodies.
The scope of this Standard is applicable to the routine service procedures for fire protection systems
and fire equipment. Routine service procedures for pre-engineered fire systems and other building
safety measures such as emergency lighting and exit signs, emergency lifts or standby generator sets
can be found in the relevant system Standard.
This edition retains a uniform structure for routine service (maintenance) requirements. Section 1 sets
out general requirements applying to all systems and equipment. The other Sections contain the
additional requirements specific to particular fire protection systems or equipment.
The following summarizes the major changes made to AS 1851—2005:
(a) Title changed to overcome reported ambiguity but still reflect the concept of inspection, test and
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
preventive maintenance. The term ‘maintenance’ has been replaced by ‘routine service’.
(b) Restructured documentation requirements into service records and reporting to assist regulatory
use.
(c) Defined the relationship between initial installation, routine service and annual regulatory
compliance (see Figure 1.7).
(d) Critically appraised and refined the routine service technical requirements in light of field
experience and studies including, battery load testing, detector sensitivity testing and system
interface testing (examples include change in frequencies and specific application instructions).
(e) Facilitating the implementation of the Standard by the responsible entity and service provider
(e.g. the consolidation of sections and consistency across sections, for the fire alarm, special
hazards and mechanical services).
(f) A thorough overhaul of the general requirements of Section 1 to remove administrative
requirements and avoid regulatory conflict.
(g) Tables in Sections 2 to 14 changed from type based to frequency based, and yearly service
separated from supportive routine service schedules.
(h) Clarified requirements for interface testing.
(i) Clarified role of commissioning and baseline data as part of the approved design.
(j) Deletion of specific competency qualifications.
(k) Distinguished between critical defects, non-critical defects and non-conformances.
(l) Extensively revised records (logbooks, tags, labels and summary records) and reporting
requirements.
(m) Removed ambiguity relating to current design Standards versus the design Standards applicable
at the time of original systems installation, i.e. the approved design.
(n) Sections 6 to 10 of the 2005 edition covering fire detection, alarms, sound systems and intercom
systems have been combined in a new Section 6 with the previous Section 8 (Fire alarm
monitoring) being removed from this revised document.
3 AS 1851—2012
(o) The routine service requirements for the fire detection and control equipment of special hazard
systems and smoke hazard management systems have been relocated from their respective
sections into Section 6.
(p) A new Section 5 has been included, covering water storage tanks for fire protection systems to
address the new design Standard AS 2304, Water storage tanks for fire protection systems.
(q) Sections 11 (Gaseous fire extinguishing systems), 12 (Fixed aerosol systems) and 13 (Water
mist systems) of the 2005 edition have been combined in a new Section 7 (Special hazards).
(r) Several new appendices have been included to expand on Section 1 content— baseline data
(Appendix C) and systems interface testing (Appendix D), with two normative appendices,
battery capacity testing (Appendix F) and fire detector testing (Appendix G). Extensive detail
on mechanical services included in the normative section of the 2005 edition has been relocated
in two appendices, both informative.
The terms ‘normative’ and ‘informative’ have been used in this Standard to define the application of
the appendix to which they apply. A ‘normative’ appendix is an integral part of the Standard, whereas
an ‘informative’ appendix is only for information and guidance.
Notes in this Standard are advisory only.
This Standard incorporates a Commentary on some clauses. The Commentary directly follows the
relevant clause, is designated by ‘C’ preceding the clause number and is printed in italics in a
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
panel. The Commentary is for information only and does not need to be followed for compliance
with the Standard.
AS 1851—2012 4
CONTENTS
Page
FOREWORD ............................................................................................................................................. 7
Page
Page
APPENDICES
A REFERENCED DOCUMENTS .............................................................................................. 168
B ROUTINE SERVICE PROCESS ............................................................................................ 170
C BASELINE DATA.................................................................................................................. 172
D SYSTEMS INTERFACE TESTING ....................................................................................... 178
E YEARLY CONDITION REPORT .......................................................................................... 186
F BATTERY CAPACITY TESTING ......................................................................................... 187
G FIRE DETECTOR TESTING ................................................................................................. 189
H MECHANICAL SERVICES—DOCUMENTATION AND SKILLS...................................... 193
I MECHANICAL SERVICES—GUIDANCE ........................................................................... 196
J OTHER EMERGENCY RESPONSE IN FACILITIES ........................................................... 203
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
7 AS 1851—2012
FOREWORD
The criteria adopted for revising this Standard include reliability, integrity, functionality and
performance of fire protection systems and equipment. Consideration has also been given to the
interfaces between fire protection systems and other building safety systems.
The Standard contains inspection, test, preventive maintenance and survey requirements to
demonstrate that the fire systems and equipment installed in a building are achieving a standard of
performance to which they were designed (the approved design). The Standard may be applied to fire
systems and equipment regardless of building age. The Standard may be applied to demonstrate the
minimum performance standard required by the National Construction Code (NCC) BCA, Volume 1,
for new buildings or it may also be applied to existing buildings constructed to an approved design
prior to the current BCA edition of the NCC. The Standard may also be used to develop specific
routine service requirements for fire systems or equipment that are part of an alternative solution
designed to satisfy the performance requirements of the NCC. Application of the Standard may also
support health and safety acts and regulations.
The scope of this Standard is identified as Stage 2 of the process and procedures diagram in
Figure 1.7. It includes the inspection, test, preventive maintenance and survey, coupled with records
to be kept and reports to be made, culminating in the issue of a yearly condition report.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
The revised inspection, test, preventive maintenance and survey regimes in this Standard address the
functional aspects of installed fire protection systems and equipment on a periodic basis, with the
objective that systems and equipment operate effectively at all times. The regimes aim to ensure that
fire protection systems and equipment are in working order throughout the year or period of interest;
not only at the time of annual inspection and test. A significant objective of this Standard is to provide
reliability of fire protection systems and equipment, linking design, installation, commissioning and
maintenance.
This Standard includes a requirement to annually test all aspects of system interconnection; for
example, detection and alarm systems with atrium smoke exhaust plant, alarm systems with stairwell
pressurization, automatic fire sprinkler systems with mechanical services fire mode operation and
warning facilities. This will require adequate documentation of interconnections between the various
systems as required in the design, installation and commissioning Standards.
Training of personnel to the appropriate levels for inspection, testing, preventive maintenance and
survey of fire protection systems has not been directly addressed in this Standard; however, it is
recognized that effective maintenance programs depend on suitably competent personnel.
This Standard provides a set of requirements to increase the probability that fire protection systems
and equipment will function as intended by the respective design, installation and commissioning
Standards, thus achieving reliability.
Continuous correct functioning is a basic criterion, and the yearly survey requirement also assures that
system performance capability (efficacy) is not degraded by building or occupancy changes, which
could otherwise adversely affect the capability of the system to perform as originally intended.
Routine service (maintenance) is concerned with the principle that a system will continue to perform
to the approved design when routine service is conducted on a pre-determined and regular basis.
Surveys are scripted activities in the routine service schedules as a check for any component
degradation or building changes that may impact on system performance. The survey requirements of
this Standard do not require auditing to AS 4655, Fire safety audits.
AS 1851—2012 8
STANDARDS AUSTRALIA
Australian Standard
Routine service of fire protection systems and equipment
S E C T I O N 1 S C O P E A N D G E N E R A L
1.1 SCOPE
This Standard sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire protection systems and equipment.
1.2 OBJECTIVE
The objective of this Standard is to maintain the reliability of fire protection systems and equipment
such that they continue to meet the requirements of the approved design and are likely to do so until
the next scheduled activity.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.3 APPLICATION
This Standard provides a systematic basis for minimum routine service applicable to fire protection
systems and equipment. It also may be used to develop specific routine service requirements for
systems or equipment that are part of an alternative solution. It requires evidence, in the form of
records and reports of completion of the periodic inspection (including survey), testing and preventive
maintenance activities required by this Standard.
NOTE: The documentary evidence resulting from compliance with this Standard is intended to support the
responsible entity to satisfy regulatory obligations.
1.5 DEFINITIONS
1.5.1 Adverse operating environments
Any environment or condition that may adversely affect the reliability of fire protection systems and
equipment (see Clause 1.13.)
1.5.2 Approved design
The design of fire protection systems and equipment approved by the authority having jurisdiction at
the time of installation or subsequent modification.
1.5.3 Authority having jurisdiction
A minister of the Crown, a government department, or other authority having power to issue
regulations, orders or other instructions having the force of law or, in cases where none of these
apply, the responsible entity.
1.5.4 Baseline data
Data derived from the approved design and commissioning, which serve as a basis for subsequent
comparison with the data derived from inspection, test and survey.
NOTE: Examples of non-critical defects include, local alarm bell not operating, water motor alarm failure
(see Figure 1.5.6).
1.5.7 High-rise
A multistorey building with storeys exceeding an effective height of 25 m.
1.5.8 Inspection
Visual examination of the components of fire protection systems or equipment to establish correct
settings, physical condition or fitness for purpose.
1.5.9 Mechanical services
Air-handling plant and systems dedicated to or arranged for dual duty to control the spread of fire and
smoke in buildings.
1.5.10 Preventive maintenance
A series of actions including lubrication, cleaning, adjustment and replacement of components at a
predetermined frequency, to minimize the incidence of breakdown.
1.5.11 Rectification
The repair or replacement of components found to be defective.
1.5.12 Responsible entity
The entity responsible for the routine service of the fire protection systems and equipment.
NOTE: Typically the building owner, the building occupier or the building owner’s agent.
1.5.13 Routine service
Inspection (including survey), testing and preventive maintenance at specific intervals (see
Figure 1.7).
1.5.14 Service penetrations
Penetrations of fire-resistant building elements by electronic, electrical, plumbing, mechanical
ventilation, airconditioning or other services.
1.5.15 Shall
Indicates a mandatory requirement.
1.5.16 Should
Indicates a recommendation (advisory, not mandatory).
1.5.17 Simulate
Rendering the equipment in a state or condition without necessarily carrying out the action that causes
that state.
1.5.18 Survey
Visual inspection, typically conducted from floor level, to identify if the fire protection system or
equipment has been inappropriately altered, damaged or compromised by changes in the occupancy,
environment or building.
C1.5.18 The goal of the survey is to determine that the approved design of the system is not
compromised. Where an upgrade or modification has resulted in a change of the performance
capability, the system should be appraised against the new baseline data of the approved design.
1.5.19 Systems interface
A connection between two or more systems forming part of the approved design.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.5.20 Testing
Confirmation of correct function or performance of a component or system.
1.5.21 Yearly condition report
A report prepared annually for the responsible entity, which summarizes the routine service activities,
records operational status, notes defects and non-conformances and confirms that the installed fire
protection systems and equipment generally accord with the approved design (see Clause 1.17.2).
1.5.22 Where fitted
A phrase in the service schedule tables to recognize that the absence of elements or components of a
system that were not required as part of the approved design need not be retrofitted and the related
routine service activity is not to be considered a defect or non-conformance if not performed (see also
Clause 1.9).
C1.5.22 This Standard has been written with the objective of providing relevant routine service
activities applicable to fire protection systems and equipment, of any age, that may have been
designed and/or installed to an earlier version of their relevant installation Standard. It is not the
intent of this Standard to require system or equipment to be upgraded to meet current installation
Standards.
R o u ti n e S e r vi c e
Ac tivit y Fa ilu r e
Fa il u r e af fe c t s No
o p e r a ti o n?
Ye s
Fa il u r e
No
r e n d e r s th e sys te m
i n o p e r a t i ve?
Ye s
1.6 ABBREVIATIONS
The following abbreviations are used in this Standard:
ASE Alarm signalling equipment
CIE (c.i.e.) Control and indicating equipment
DBEP Designated building entry point
DSEP Designated site entry point
ECO Emergency control organization
EPC Emergency planning committee
EWS Emergency warning systems
f.b.p Fire brigade panel
FFCP Fire fan control panel
FIP Fire indicator panel (also known as c.i.e.)
FRL Fire resistance level
HVAC Heating, ventilation and airconditioning
ISO International Organization for Standardization
LCS Local control station
MJC Multiple jet control
OHS Occupational health and safety
RTI Response time index (sprinklers)
C1.7.3 Construction of building services does not always finish at the time of handover of the
project, resulting in fire protection systems that have not been fully commissioned. The fire safety
services need to be completed and commissioned in order for the results of inspection and test
work to be meaningful.
Commissioning [1]
S TAG E 1
S y s te m D e s i g n,
I n s t a l l a ti o n a n d
Commissioning
B a s e li n e D at a Es t a b li s h e d [2]
R o u ti n e S e r vi c e S c h e d u l e s [3]
R e c ti f i c a t i o n I d e nti f y a n d R e p o r t Ac tiv i t y
[4] S TAG E 2
o r R e s o l u ti o n Fa il u r e s
AS 18 51
R o u t i n e S e r vi c i n g
Ye a r l y S e r vi c e S c h e d u l e s [5 ]
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
[6]
Ye a r l y C o n di ti o n R e p o r t
S TAG E 3
A n n u a l C o m p li a n c e
[7] Regulation &
S t ate m e nt
A p p l i c a ti o n
NOTE: See Appendix B for explanations of Items 1 to 7.
C1.8 Baseline data may include, for example, water supply details, pump test flow and pressure
data, pressure settings, block plan information, systems interface cause and effect, control and
indicating equipment configuration.
NOTE: Competence may be further defined by the authority having jurisdiction. Governments may have in
place occupational licensing schemes or other means of determining competence. Where this is not the case,
competencies may be demonstrated in accordance with Australian Qualification Framework (AQF).
C1.10 Sections 2 to 14 nominate the routine service required by this Standard. Equipment and
systems have been grouped within these sections simply to comply with normal industry trade
demarcations. It is, however, the intention of this Standard that all required tasks be performed by
the most appropriately qualified, experienced and competent persons, rather than the
trade/discipline normally associated with that particular section of the Standard.
C1.11.1 The initial monthly activity is scheduled for the 20th of the month. Subsequent monthly
activities are required to be carried out within five working days either side of the 20th of the
month.
1.11.2 Change of scheduled date
The scheduled date may be brought forward by agreement between the responsible entity and the
service provider subject to the ongoing frequencies and tolerances applying and the required number
of activities being completed within the prescribed period.
C1.11.2 The initial scheduled date is the 27th of the month. The agreed new scheduled date is the
10th of the month (outside tolerance limits). By agreement, the date may be brought forward by
performing the test on the 27th of the month and again on the 10th of the next month. This may
necessitate an additional test. The new scheduled date would now be the 10th of the month, the
date that will consequently be used for tolerance purposes.
TABLE 1.11(A)
ROUTINE SERVICE FREQUENCIES FOR EACH SECTION
Twenty-five-yearly
Three-monthly
Thirty-yearly
Six-monthly
Five-yearly
Ten-yearly
AS 1851 Section
Monthly
Yearly
2 Automatic fire sprinkler systems
3 Fire pumpsets
4 Fire hydrant systems *
Hydrant valves
5 Water storage tanks for fire protection
systems
6 Fire detection and alarm systems
7 Special hazard systems
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 1.11(B)
FREQUENCY TOLERANCES
Frequency Tolerance (±)
Monthly 5 working days
Three-monthly 10 working days
Six-monthly 1 month
Yearly 2 months
Five-yearly 3 months
Ten-yearly 6 months
Twenty-five-yearly 6 months
Thirty-yearly 6 months
NOTE: The tolerance schedule is not intended to
require additional routine service activities to be
carried out (e.g. six monthly routines carried out at
five or seven monthly intervals).
sprinkler system.
7 The interface test is not a commissioning test of each system; it is to establish that each interface
operates correctly.
8 Where an interfaced system would be operated more than once during interface testing, it may be
isolated provided at least one complete end to end test of the systems has been carried out and there is an
indication that a signal has been received at the interfaced system for all other tests.
Effect
emergency purposes
HVAC shutdown
Damper closure
Plant shutdown
Smoke curtains
Fuel isolation
Door release
Roof vents
Sprinkler systems • • • • • • • • •
Fire detection and alarm • • • • • • • • • • • • •
systems
Smoke/heat alarm systems • • • • • • • • •
Cause
Gaseous systems • • • • • • •
Aerosol systems • • • • • • •
Water mist systems • • • • • •
Hydrants • •
Hose reels • •
Examples of high usage include frequently used fire and smoke doors in such occupancies as
health care buildings, shopping centres and airport terminals resulting in excessive wear on latch
mechanisms and door leaf closing sequencing.
High defect rates may result from tampering, excessive vibration, frequent tenancy changes,
vandalism or inappropriate occupant activity.
1.14 PRECAUTIONS
Prior to commencing any routine service, the following precautions shall be carried out:
(a) Take all reasonable precautions to not adversely affect the normal operation of any system,
except for those systems to be serviced, or to adversely affect occupants of the building, or to
cause any situation that will result in an unwanted alarm.
(b) Inform the responsible entity or nominated person that routine service is to be carried out,
which may adversely affect the occupants or operations of the building.
(c) Inform the responsible entity or nominated person of the extent and expected duration of the
impairment during the routine service so that alternative safety arrangements can be
implemented.
(d) Notify the monitoring service provider where testing or service may cause signals to be
transmitted.
NOTE: The notification may be by configuring the alarm signalling equipment to test mode and
confirmation that the system has been restored to ‘normal’ by the alarm signalling equipment returning
to ‘normal’.
(e) On completion of any routine service, return all controls to their prior state. When any function
is left impaired, disabled or is not restored to ‘normal’, record in the system logbook and notify
the owner or agent.
(f) If on-site welding is to be carried out, it shall be in accordance with the requirements of
AS 1674 and the hot work procedures applicable to the building.
NOTE: On-site welding should be avoided wherever possible and particularly when sprinkler systems are
inoperative.
NOTES:
1 During periods when the system is inoperative it is recommended that all fire extinguishing appliances
be held in special readiness for immediate use, and that a watchperson be on duty throughout non-
working hours. Where a water supply from a particular source is curtailed for any protracted period, e.g.
as in time of drought, special attention should be given to the routine service of any other water supplies.
2 In the case of multiple installations, each individual installation should be returned to service before
work commences on subsequent installations.
TABLE 1.16.1
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
For all methods of recording, a hardcopy of the service record [paper-based logbooks or printed and
signed paper-based copy of the electronic log (see Clause 1.16.3)] shall be left on site at the
completion of the test. Where tags or labels are permitted, a printed and signed paper-based copy of
the summary record (see Clause 1.16.5) may be provided to the responsible entity within one week
from the date of service.
NOTE: Clause 1.16.6 requires the responsible entity to retain hard copy service records on site.
Where tags or labels are used, the recording of the completed activity shall be as specified in
Clause 1.16.4.1. A service tag or label shall be provided to record the last level of service performed
in accordance with Sections 4, 8, 9, 10, 11 and 12. The tag or label shall be permanently marked with
a number to correspond with the frequencies as set out in Table 1.16.2.
The record of each non-conformance or defect when using the tag or label system shall be captured in
the summary record.
TABLE 1.16.2
SERVICE TAGS OR LABELS—FREQUENCY OF APPLICATION
Frequency
Section Equipment Three- Six- Three- Five- After
Yearly
monthly monthly yearly yearly use
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.16.3 Logbooks
Service records in the form of logbooks (hardcopy or electronic) shall contain the following
information:
(a) Name and address of building or site.
(b) Date and frequency of service performed.
(c) System or equipment identification and location.
(d) Each activity performed, including recorded results if required, and ‘pass’ or ’fail’ as
appropriate.
(e) Details of each non-conformance or defect including its classification, location and any
rectification completed.
(f) Name of responsible entity (owner/occupier).
(g) Name and signature of the service person and date.
(h) Name of the service provider or company.
marked on the label in the space corresponding to the year and month in which the service
was performed, with a figure representing the activity as detailed in Section 12.
(c) Date (month/year).
A service tag or label, as shown in Figure 1.16.4.1, shall be attached to the item serviced. The figures
shall be not less than 3 mm high, and the markings shall be such that the figures are legible.
Where a service tag is used, it shall be attached so that the force necessary to detach the tag is not less
than 200 N.
1.16.4.2 Requirements
Service tags and labels shall—
(a) be made from a durable material (adhesive backed in the case of labels);
(b) have lettering, figures, and lines on the tag printed in black;
(c) have a continuous background colour of approximately Golden Yellow (Y15 of AS 2700);
(d) have the dimensions and show only the information detailed in Figure 1.16.4.1 and the recorded
information specified in this Clause; and
(e) have the previous full year service record transferred from the expired tag or label to the new
tag when a new tag or label is provided.
The label shall be applied adjacent to the completed label so that the previous service history is not
obscured when a new label is provided.
80
DIMENSIONS IN MILLIMETRES
Where tags or labels are used, a supporting hardcopy summary record shall be completed and shall
include a register of the equipment on the premises, a statement of the service performed and details
of missing or defective items as follows:
(a) Name and address of building or site.
(b) Date of service.
(c) Details of equipment on site as listed in the Equipment Register. (See Appendix C.)
(d) Scheduled date of service (see Clause 1.11).
(e) Quantity and type of equipment serviced and frequency of service performed.
(f) Quantity and location of equipment not serviced.
(g) Details of each non-conformance or defect including its classification, location and any
rectification completed.
(h) Name of responsible entity.
(i) Name and signature of the service person and date.
(j) Name of the service provider or company
(k) For fire extinguishers, the date of manufacture or the date of the last pressure test.
(l) For fire hose reels, details of the flow test results for the most hydraulically disadvantaged hose
reel.
(m) Any other applicable comments (e.g. additional activities as a result of adverse operating
environments).
1.16.6 Records retention
The responsible entity shall retain the service records [logbook(s) and summary record(s)] on site,
which shall be available at all times. Service records shall be retained for a minimum period of seven
years.
1.17 REPORTS
1.17.1 Defects, non-conformances and out of tolerance activities
The responsible entity shall be notified of critical defects before leaving site, or where this cannot be
achieved, as soon as possible. Critical defects shall be confirmed in writing within 24 h of the defect
identification and reconfirmed each time the defect is identified.
The responsible entity shall be notified of non-critical defects, non-conformances and out of tolerance
activities within one week.
NOTES:
1 The full report should be submitted as soon as practicable, thereafter.
2 A recommendation should be sent to the responsible entity that critical defects be rectified with the
minimum of delay, non-critical defects and non-conformances be rectified as soon as practicable prior to
the next yearly condition report.
1.17.2 Yearly condition reports
Evidence of compliance with this Standard shall take the form of one or more condition reports.
Condition report(s) shall provide a summary of the service records for the year’s activities and shall
be issued yearly to the responsible entity.
The condition report shall contain details of outstanding defects and non-conformances. If the
outstanding defects result in the fire system or equipment being no longer operational, such non-
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
operational status shall be noted on the report. The yearly condition report shall contain the following:
(a) Name and address of building or site.
(b) Period covered by this report.
(c) System or equipment identification and location.
(d) Applicable approved design Standard.
(e) Defects outstanding.
(f) Non-conformances outstanding.
(g) Summary of the relevant records of service.
(h) Statement of condition.
(i) Name and address of responsible entity.
(j) Name and signature of service provider representative and date.
(k) Name of the service provider or company.
NOTES:
1 It is recognized that different parties may undertake portions of the routine service.
2 An example of a condition report is given in Appendix E.
The condition report shall contain acknowledgment of missed service activities or outstanding defects
and non-conformances. If the outstanding defects report results in the fire system or equipment being
no longer operational, such non-operational status shall be noted on the report.
C1.17.2 It is intended that the yearly condition report be used as supporting evidence for State or
Territory regulatory compliance of fire protection systems and equipment.
S E C T I O N 2 A U T O M A T I C F I R E S P R I N K L E R
SYSTE MS
2.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of automatic fire sprinkler systems.
NOTE: Home sprinkler systems are covered in AS 2118.5.
The following systems are covered in this Section:
(a) Wet pipe systems.
(b) Dry pipe systems.
(c) Deluge and water spray systems.
(d) Pre-action systems.
Routine service of combined sprinklers and hydrant systems shall be carried out in accordance with
the requirements of this Section for automatic fire sprinkler systems and Section 4 for fire hydrant
systems.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
NOTES:
1 For drencher systems (wall wetting) refer to Clause 2.4.1.
2 For pumpsets refer to Section 3.
3 For water storage tanks refer to Section 5.
This Section shall be read in conjunction with Section 1.
C2.2.3 Ensuring that main stop valves, water supply stop valves, underground
key-operated and subsidiary stop valves are in their correct operational position is critical to the
reliability of any automatic sprinkler system. As a minimum, all valves on the critical direct water
flow path to sprinklers should be identified, appropriately labelled and numbered and listed on a
valve list (an example is shown in Appendix C). This includes valves associated with pumpsets
(Section 3) and water supply tanks (Section 5) feeding sprinkler systems. This valve list is part of
required baseline data and may also be used when conducting valve inspections and tests in
accordance with all the tables in this Section.
2.2.4 Service records
Service records of activities and results detailed in Clause 2.4.1 shall be kept in accordance with
Clause 1.16.
2.2.5 Reports
Critical defects, non-critical defects, non-conformances and yearly condition reports shall be prepared
and distributed in accordance with Clause 1.17.
2.3 FREQUENCY
The frequency of routine servicing of sprinkler systems, as set out in Clause 2.1, shall be in
accordance with Clause 2.4 and the following:
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(a) Monthly.
(b) Six-monthly.
(c) Yearly.
(d) Five-yearly.
(e) Ten-yearly.
(f) Twenty-five yearly.
(g) Thirty yearly.
TABLE 2.4.2.1
MONTHLY ROUTINE SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
WET PIPE SYSTEMS
TABLE 2.4.2.2
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
WET PIPE SYSTEMS
(river, lake, etc.) any condition likely to affect its function. Where
strainers/screens blocked, CLEAN the suction inlet strainers or
screens.
TABLE 2.4.2.3
YEARLY ROUTINE SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKER SYSTEMS
WET PIPE SYSTEMS
(ASE)
(a) CHECK the batteries for any condition likely to
(Standalone) or
adversely affects its function
and Test load current
(b) Where the battery has not been replaced in the .......................... A
previous two years, VERIFY the battery Final test voltage
condition by carrying out a battery discharge
test in accordance with Appendix F. .......................... V
3.12 Tank quick fill CONDUCT a water supply test through a flow- Flow ...... L/min @
(reduced measuring device or other appropriate methods that pressure ......... kPa
capacity or the flow corresponds to the required quick fill-rate.
break tank)
3.13 Spray booths INSPECT accumulated spray residue on sprinklers
and ducts and reapply protective medium (petroleum
jelly/paper bags).
NOTE: The required frequency of inspection
depends upon the amount of spraying being done
and could be accomplished at the same time as the
cleaning of booth.
3.14 Kitchen hoods INSPECT all sprinklers inside kitchen hoods and
and ducts ducts and CLEAN if necessary to remove
accumulated grease and any other foreign matter and
verify that the sprinkler head is appropriate for this
application.
3.15 Foam water DRAW a sample and verify condition in accordance
sprinkler with NFPA 11 (pH, specific gravity, sediment,
systems—Foam expansion ratio, 25% drain time).
concentrate
3.16 Foam CHECK and clean foam concentrate strainer (fitted
concentrate upstream of proportioning device).
strainer (where
fitted)
(continued)
guards
3.20 Survey— CHECK for obstructions likely to impede sprinkler
Sprinkler discharge and for adequate clear space below
obstructions sprinklers.
3.21 Survey— (a) CHECK for presence of unprotected areas such
Unprotected as mezzanines, platforms and building
areas extensions.
(b) CHECK for sprinkler spacing and location
relative to wall, bulkhead and partition
alterations and the introduction of fixtures and
fittings shielding sprinkler discharge.
(c) CHECK for the need to install sprinkler guards.
3.22 Survey— CHECK that sprinklers within a compartment are of
Sprinkler similar operating characteristics (e.g. area coverage,
compatibility RTI and temperature rating).
3.23 Survey— CHECK for localized changes in ambient
Sprinkler temperatures, which may require different sprinkler
ambient temperature ratings (e.g. exposure to freezing or high
conditions temperature conditions).
3.24 Survey— CHECK for new building structures, yard storage or
External the like, exposing unprotected openings, non-fire
sprinklers resistant walls that may require the provision for
external sprinklers.
3.25 Survey— CHECK that sprinkler design remains applicable for
Occupancy the occupancy hazard classification and the category
of storage involved.
(continued)
TABLE 2.4.2.4
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 2.4.3.1
MONTHLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DRY PIPE SYSTEMS
level oil.
1.5 Air compressor VERIFY that air compressor operates at specified Cut-in ........... kPa
cut-in and cut-out pressures. Cut-out ......... kPa
1.6 Low air pressure VERIFY:
alarms(s)
(a) Low air pressure alarm operates at ..................... kPa
predetermined levels. ..................... kPa
(b) Low air pressure alarm(s) visual indicator and
sounders are operational.
1.7 Local alarm and SIMULATE operation of dry pipe alarm valve and
fire brigade test OPERATE local and fire brigade alarms through
simulation (in lieu the bypass valve(s). Where the system is
of Item 1.12, monitored, ensure the alarm has activated the
Table 2.4.1.1) alarm signalling equipment. (Refer to
manufacturer’s operating manual.)
NOTE: Where multiple control valve assemblies
are separately identified at an FIP, only one
transmission from the FIP to the monitoring
station is required.
1.8 Air receiver DRAIN condensate from condensate trap.
condensate
TABLE 2.4.3.2
SIX-MONTHLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DRY PIPE SYSTEMS
accelerator or exhauster.
(d) RECORD time(s) to operation of alarms
gong(s) and verify that these do not exceed
180 s. ......................... s
(e) VERIFY correct operation of the fire
brigade alarms from each control assembly
or group of control assemblies. Where the
system is monitored, ensure the alarm has
activated the alarm signalling equipment.
NOTE: Where multiple control valve
assemblies are separately identified at an
FIP, only one transmission from the FIP to
the monitoring station is required.
(f) Where an isolation valve has not been fitted
above the alarm valve, the main stop valve
should be mostly closed, enabling a partial
test of the alarm valve.
NOTE: Consider full testing at the first
opportunity (at which time the isolation
test valve should be installed).
2.3 Installation RESTORE system air pressure and verify the
pressure alarm has reseated.
2.4 FIP/ASE RESTORE FIP/ASE to operational status.
2.5 Pressure gauge (a) RECORD reading from each pressure gauge. Inst……………kPa
readings Below SV….…kPa
(b) VERIFY pressure gauge readings are within
WS1…………..kPa
the ranges indicated on the pressure gauge
WS2…………...kPa
schedule. See Appendix C for guidance.
2.6 Control assemblies RESET and SECURE all valve and alarms cocks
resetting in the open position or the closed position, as
labelled.
TABLE 2.4.3.3
YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DRY PIPE SYSTEMS
TABLE 2.4.3.4
FIVE-YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DRY PIPE SYSTEMS
TABLE 2.4.4.1
MONTHLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DELUGE AND WATER SPRAY SYSTEMS
stop valve
…….………kPa
1.3 Air compressor oil (a) CHECK oil level is correct and visually
level (where fitted) assess condition of oil.
(b) CHECK regulator is locked and set in the
correct position in accordance with the
pressure gauge schedule.
1.4 Electrical detection INSPECT and TEST in accordance with
(where fitted) Section 6.
1.5 Detector sprinkler CHECK detector sprinkler line valves are in the
line (where fitted) correct operating position.
1.6 Air compressor VERIFY that air compressor operates at Cut in……..kPa
(where fitted) specified cut-in and cut-out pressures.
Cut out……kPa
1.7 Solenoid valve(s) TEST solenoid valves for correct operations.
1.8 Low air pressure VERIFY:
alarm(s)
(a) Low air pressure alarm operates at
predetermined levels. …………….kPa
(b) Low pressure alarm(s) visual indicator and
sounders are optional.
1.9 Local alarm and fire (a) GENERATE a test of the alarm signalling
brigade test equipment and local alarm in accordance
simulation in lieu of with the manufacturer’s operating manual.
Item 1.12 in
NOTE: Where fitted, bypass valve may be
Table 2.4.2.1
used for this test.
(b) OBSERVE correct operation of the fire
brigade alarm from each pre-action valve
or group of pre-action valves. Where the
system is monitored, ensure the alarm has
activated the alarm signalling equipment.
NOTE: Where multiple pre-action valve
assemblies are separately identified at the
FIP, only one transmission from the FIP to
the monitoring station is required .
TABLE 2.4.4.2
SIX-MONTHLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DELUGE AND WATER SPRAY SYSTEMS
TABLE 2.4.4.3
YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 2.4.4.4
FIVE-YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
DELUGE AND WATER SPRAY SYSTEMS
by the manufacturer.
4.5 Foam quality GENERATE foam through delivery device
(nozzle, monitor) or test foam maker and check:
(a) Proportioning ratio (using conductivity meter
or refractometer).
(b) 25% drainage time.
(c) Expansion ratio.
1.3 Air compressor oil (a) CHECK oil level is correct and visually
level (where fitted) assess condition of oil.
(b) CHECK regulator is locked and set in the
correct position in accordance with the
pressure gauge schedule.
1.4 Electrical detection INSPECT and TEST in accordance with
Section 6.
1.5 Air compressor VERIFY that air compressor operates at Cut-in ......... kPa
(where fitted) specified cut-in and cut-out pressures.
Cut-out ....... kPa
1.6 Nitrogen supply (a) CHECK cylinder contents per pressure Cylinder
(where fitted) gauge. pressure…….kPa
(b) CHECK regulator is locked and set in
correct position in accordance with the
pressure gauge schedule.
1.7 Solenoid valve(s) TEST solenoid valves for correct operations.
1.8 Low air pressure VERIFY:
alarms(s)
(a) Low air pressure alarm operates at
predetermined levels. ................... kPa
(b) Low air pressure alarm(s) visual indicator
and sounders are optional.
1.9 Local alarm and fire (a) GENERATE a test of the alarm signalling
brigade test equipment and local alarm in accordance
simulation in lieu of with the manufacturer’s operating manual.
Item 1.12 in NOTE: Where fitted, bypass valve may
Table 2.4.2.1 be used for this test.
(b) VERIFY correct operation of the fire
brigade alarm from each pre-action valve or
group of pre-action valves. Where the
system is monitored, ensure the alarm has
activated the alarm signalling equipment.
NOTE: Where multiple pre-action valve
assemblies are separately identified at the
FIP, only one transmission from the FIP to
the monitoring station is required.
TABLE 2.4.5.2
SIX-MONTHLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
PRE ACTION SYSTEMS
TABLE 2.4.5.3
YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
PRE-ACTION SYSTEMS
TABLE 2.4.5.4
FIVE-YEARLY SERVICE SCHEDULE
AUTOMATIC FIRE SPRINKLER SYSTEMS
PRE-ACTION SYSTEMS
Records
Item Action required and Task Task
Item
No. pass/fail requirement completed completed
Yes/No Yes/No
4.1 Monthly, six-monthly COMPLETE all monthly, six-monthly and
and yearly service yearly activities, as listed in Tables 2.4.5.1,
2.4.5.2 and 2.4.5.3.
4.2 Five yearly service COMPLETE all five yearly wet pipe service
activities as listed in Table 2.4.2.4.
4.3 Valve overhaul FIT new pre-action valve seats and seals.
CHECK and CLEAN operating mechanism. FIT
new cover plate gasket.
S E C T I O N 3 F I R E P U M P S E T S
3.1 GENERAL
This Section sets out the requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire pumpsets.
Routine service of pumpsets detailed in this Section shall be carried out in addition to the
requirements of Section 2 for sprinkler systems and Section 4 for hydrant systems.
This Section shall be read in conjunction with the relevant clauses of Section 1.
3.3 FREQUENCY
The frequency of routine servicing of pumpsets shall be in accordance with the following and
Clause 3.4:
(a) Monthly and six-monthly.
(b) Yearly.
(c) Five-yearly.
TABLE 3.4.1
MONTHLY SERVICE SCHEDULE
FIRE PUMPSETS
correctly.
(k) Engine instrumentation is operating. Record Oil pressure
the results. ..................... kPa
Engine temp
....................... °C
Operating
pressure ........ kPa
(l) Flow is evident from the circulation relief
valve when the pump is operating at shut-off
head and ceases at the appropriate pressure.
(m) Exhaust system is leak free.
(n) Cooling water (heat exchanger cooled
engines only) is discharging.
1.15 Electric motor Prior to commencing any test function:
driven
(a) CHECK all safety guards are in place and
pumpset—
secure.
Precautions
(b) CHECK enclosure for corrosion and ingress
of water, dust or insects.
1.16 Pump controller CHECK that the main isolating switch is in the on
status position and secured in position where facilities
are provided and, where fitted, the green power
supply lamps are illuminated and that no red
warning lamps are on. Ensure all lights are
functional by pressing the lamp test button, where
fitted.
1.17 Pump starting (a) START each pumpset by reducing the
devices applied water pressure to the starting device
and run motor continuously for at least
3 minutes.
(b) RESTART each pumpset using the manual
starting device and run motor continuously
for at least 3 minutes.
(continued)
TABLE 3.4.2
SIX-MONTHLY SERVICE SCHEDULE
FIRE PUMPSETS
TABLE 3.4.3
YEARLY SERVICE SCHEDULE
FIRE PUMPSETS
TABLE 3.4.4
FIVE-YEARLY SERVICE SCHEDULE
FIRE PUMPSETS
Records
Item
Item Action required and pass/fail requirement Task completed
No. Comments
Yes/No
4.1 Monthly, six- COMPLETE all monthly, six-monthly and yearly
monthly and activities, as listed in Tables 3.4.1, 3.4.2 and 3.4.3.
yearly service
4.2 Pump REPACK pump glands.
4.3 Relief, engine OVERHAUL the following valves in accordance with
cooling and supplier’s specifications:
pressure
(a) Circulation-relief valves.
regulating
valves (b) Pressure-relief valves.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 3.4.5.1
MONTHLY SERVICE SCHEDULE
HOSE REEL AND PRESSURE MAINTENANCE/JACKING PUMPSETS
Records
Item
Item Action required and pass/fail requirement Task completed
No. Comments
Yes/No
5.1 Pump areas (a) CHECK that pump areas are unobstructed, not
used for storage and lighting is adequate.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 3.4.5.2
SIX-MONTHLY SERVICE SCHEDULE
HOSE REEL AND PRESSURE MAINTENANCE/JACKING PUMPSETS
Records
Item
Item Action required and pass/fail requirement Task completed
No. Comments
Yes/No
6.1 Monthly service COMPLETE all monthly service activities, as listed in
Table 3.4.5.1.
6.2 Hydro- VERIFY that pressure is correct.
pneumatic
accumulator
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 4 F I R E H Y D R A N T S Y S T E MS
4.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire hydrant installations together with fire mains, fire brigade booster
assemblies and other associated equipment. Service requirements for fire pumpsets, water storage
tanks and delivery lay flat fire hose are set out in Sections 3, 5 and 8, respectively.
Routine service of combined hydrant and sprinkler systems shall be carried out in accordance with the
requirements of this section for hydrant systems, Section 2 for automatic fire sprinkler systems,
Section 4 for fire pumps and Section 5 for fire service tanks.
This Section shall be read in conjunction with Section 1.
Hydrant systems shall be surveyed in accordance with the survey requirements specified in
Clauses 4.3 and 4.4.
C4.2.2 A survey is typically conducted visually from floor level to identify changes to the hydrant
system or the building and its environment which could impair the performance of the hydrant
system.
4.2.3 Baseline data
Baseline data shall be in accordance with Clause 1.8 and shall include a water supply valve list
including valve unique number, location and whether monitored or locked. See Appendix C for
guidance and examples.
4.2.4 Service records, tags or labels
Service records of activities and results detailed in Clause 4.4.1 shall be kept in accordance with
Clause 1.17.
4.2.5 Reports
Critical defect, non-critical defects, non-conformances and yearly condition reports shall be prepared
and distributed in accordance with Clause 1.17.
4.3 FREQUENCY
The frequency of routine servicing of hydrants shall be in accordance with Clause 4.4 and the
following:
(a) Monthly (pump-related inspection and test items only).
(b) Six-monthly.
(c) Yearly.
(d) Five-yearly.
TABLE 4.4.1
MONTHLY SERVICE SCHEDULE
FIRE HYDRANT SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Results Pass/Fail Comments
1.1 Monthly service Where pumpsets are fitted complete all pumpset
monthly service activities, as listed in Table 3.4.1.
1.2 Pump-starting devices (a) CHECK that all isolating valves to pump-
starting pressure devices are secured in the
open position.
(b) CHECK that pressure switches are securely
mounted and are protected against the ingress
of water, dust and insects.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.3 Pump-starting devices (a) START each pumpset by reducing the applied
function test— water pressure to the pump-starting device
Compression ignition and run engine, in accordance with Section 3.
engine (diesel)
(b) RESTART the pumpset using the manual
starting device and again run the compression
ignition engine in accordance with Section 3.
Where more than one starting device is
installed, including the manual starting
device, the test may be carried out on a
rotating basis. The period between the
exercising of each starting device is not to
exceed 3 months. Where this would require
the pump to start more than 5 times in
succession, the period may be extended to
6 months (see also Table 3.4.3, Items 3.6 and
3.7).
(c) RECORD the pump cut-in pressures and
………kPa
verify that they are within the ranges indicated
on the pressure gauge schedule. ………kPa
1.4 Pump-starting devices (a) START each pumpset by reducing the applied
function test— water pressure to the starting device and run
Electric motor drivers motor in accordance with Section 3.
(b) RESTART the pumpset using the manual
starting device and again run the motor in
accordance with Section 3.
(c) Where more than one starting device is
installed, including the manual starting
device, the test may be carried out on a
rotating basis. The period between the
exercising of each starting device is not to
exceed 3 months. Where this would require
the pump to start more than 5 times in
………..kPa
succession, the period may be extended to
6 months. ………. kPa
TABLE 4.4.2
SIX-MONTHLY SERVICE SCHEDULE
FIRE HYDRANT SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Results Pass/Fail Comments
2.1 Monthly service COMPLETE all monthly service activities, as
listed in Table 4.4.1.
2.2 Water supply stop OPERATE (two full turns) all water supply stop
valves and isolating valves (including backflow prevention stop valves
valves and underground key-operated valves except where
owned by the water supply authority) and verify
they are fully open, secure in the open position
(relaxed ¼ turn if appropriate) and are correctly
labelled as indicated on the valve list.
NOTES:
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Results Pass/Fail Comments
2.6 Remote pump DEPRESSURIZE the hydrant system(s) at the most
starting hydraulically disadvantaged hydrant and CHECK
that the pump starts.
2.7 Hydrant and booster CHECK that all hydrant and booster connection
connections— points are compatible with local brigade
Compatibility requirements.
2.8 Hydrant hose CHECK all branch pipes, nozzles and hose
(where fitted) couplings are in good condition, compatible with
the hydrant valves and properly stowed.
2.9 Foam concentrate CHECK:
and loose equipment
(a) Equipment provided in the cabinet is in
(where provided)
accordance with the cabinet contents list.
(b) Equipment items are compatible and in good
condition.
(c) Foam concentrate containers are in good
condition, seals are intact and the labels are
legible.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 4.4.3
YEARLY SERVICE SCHEDULE
FIRE HYDRANT SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comment
3.1 Monthly and six- COMPLETE all monthly and six-monthly service
monthly service activities, as listed in Tables 4.4.1 and 4.4.2.
3.2 Hydrant valves OPEN partially all hydrant valves in the system
(above and below and prove the presence of water at each point.
ground)
NOTE: To prevent water damage, it is
recommended that a suitable adapter to limit
water flow be used for this test on internal
hydrants. Each hydrant in the system should be
opened separately.
3.3 Hydrant water supply (a) OPERATE (two full turns) all water supply
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comment
3.6 Pressure-reducing (a) OPERATE all pressure-reducing valves and
station test verify correct operation under flow
conditions.
(b) VERIFY that pressure readings on the low
pressure side of the valves are within the
range stated at the pressure-reducing valve ………….kPa
station.
(c) OPERATE pressure-relief valve and record
operating pressure. If necessary, adjust the
setting to relieve at 50 kPa above the
operating pressure of the pressure-reducing
valve. Replace the tamper seal if necessary.
NOTE: The pressure-relief valve test may be
carried out using a portable test apparatus.
3.7 Water supply proving CONDUCT a water supply proving test for each
test water supply verifying that the system flow and
pressure requirements meet the design criteria,
using either—
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comment
3.10 Water supply (a) CHECK suction inlet strainer(s) or screen(s).
(river, lake, etc.)
(b) Following water supply proving test
Strainers/screens
(Table 4.4.2 Item 2.6), CLEAN suction inlet
strainer(s). Lower raised screen and raise
and clean ‘in-use’ screen.
3.11 Survey—Installation (a) Pipework—CHECK that exposed water
distribution system, including pipework,
pipe supports and valve, appears free from
corrosion and damage, not subject to
external loads and pipework is properly
supported.
(b) Hydrant obstructions—CHECK for
obstructions likely to impede hydrant valve
access.
3.12 Survey—Design (a) Occupancy—CHECK that hydrant design
remains applicable for current building
arrangement or use.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 4.4.4
FIVE-YEARLY SERVICE SCHEDULE
FIRE HYDRANT SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comment
4.1 Six-monthly and COMPLETE all monthly, six monthly and yearly
yearly service service activities, as listed in Tables 4.4.1, 4.4.2
and 4.4.3.
4.2 Booster connection CONDUCT a flow test through booster connection
flow test (where in accordance with AS 2419.1 or to approved
fitted) design Standard.
NOTE: Conduct the flow test after a satisfactory
(pass) hydrostatic test.
4.3 Hydrostatic test Where a booster is fitted CONDUCT a hydrostatic
pressure test on the entire system at 1.5 times the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 5 W A T E R S T O R A G E T A N K S F O R F I R E
P R O T E C T I O N S Y S T E M S
5.1 GENERAL
This Section sets out the requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of water storage tanks for fire protection systems.
This Section shall be read in conjunction with Section 1.
C5.1 Elements of water storage tanks requiring particular attention include the following:
(a) Corrosion of internal and external components such as—
(i) suction inlets;
(ii) vortex inhibitors;
(iii) tie rods in rectangular tanks;
(iv) fittings; and
(v) roof supports.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
5.3 FREQUENCY
5.3.1 General
The frequency of routine servicing of water storage tanks shall be in accordance with Clause 5.4 and
the following:
(a) Monthly and six-monthly.
(b) Yearly.
(c) Ten-yearly (and other frequencies where applicable).
5.3.2 Life of tank liner
An indication of the life remaining in a tank liner shall be estimated at the end of the first 10-year
drain and clean period or at the end of the manufacturer’s warranty period (whichever comes first).
The estimated remaining life of the liner shall determine the subsequent tank drain and inspection
frequency.
TABLE 5.4.1
MONTHLY SERVICE SCHEDULE
WATER STORAGE TANKS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Water level CHECK that the tank is full.
1.2 Water level CHECK for correct operation and reading of
indicator water level indicator.
1.3 Water supply VERIFY:
pressure tank
(a) Gauge glass indicates the correct water level.
(where fitted)
(b) Tank pressure gauge reads within the range Tank pressure
nominated on the pressure schedule. gauge…..kPa
(c) Air pressure switch operates at specified Compressor
compressor cut-in and cut-out pressures. operating
pressure
Cut in…..kPa
Cut-out....kPa
(d) Low tank pressure alarm operates at Low tank
specified pressure. pressure
alarm……..kPa
(e) Air compressor of gas cylinder supply is
operational.
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.10 Vermin CHECK the condition of vermin proofing and
adequacy of the positioning.
3.11 Foreign objects CHECK for internal foreign objects visually
through the top inspection/access hatch.
3.12 Algae CHECK for internal accumulation of algae.
3.13 Vents CHECK the condition and satisfactory operation
of vents and rotary spinners.
3.14 Accessibility CHECK for adequate means to access the tank.
3.15 Signs CHECK for satisfactory condition of all signs.
3.16 Gaskets and seals CHECK the condition of all gaskets and sealants.
3.17 Vortex inhibitor CHECK the condition of the vortex inhibitor
visually from the access hatch if practicable.
3.18 Level indicator LUBRICATE water level indicator, pulleys and
cables.
3.19 Fire authority hard CHECK fittings are compatible with the local fire
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
TANKS WITH LINERS—(B) BELOW THE WATERLINE
2.27 Flexibility CHECK for signs of loss of flexibility.
2.28 Discolouration CHECK to determine the extent of any
discolouration to the tank liner.
2.29 Elongation CHECK for signs of elongation of the liner.
2.30 Bulging CHECK for signs of the liner bulging out from
under the base girder (external).
2.31 Leaks, cuts and CHECK for signs of leaks, cuts and tears of the
tears liner.
2.32 Drain clean and DRAIN and CLEAN the tank leaving a minimum
refill of 50 mm of water to prevent liner movement;
(Only required after and—
the first year of
(a) Remove all sludge and debris without using
service and then
sharp tools or shovels to prevent tearing and
every 10 years)
puncturing of the liner.
(b) Clean all internal surfaces, excluding the
roof, with low pressure spray using
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
PRESSURE TANKS
2.36 Pressure tanks (a) INSPECT externally for structural integrity,
freedom from corrosion, and acceptable
condition in accordance with AS/NZS 3788.
(b) VERIFY low water level alarm switch Alarm level
operates at predetermined level ……..………m
TABLE 5.4.4
TEN-YEARLY AND OTHER SERVICE SCHEDULE
WATER STORAGE TANKS
Item Records
Item Action required and pass/fail requirement
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
(c) REFILL the tank as soon as practicable.
NOTES:
1 For water conservation measures when
tanks need to be drained, see AS 2304.
2 Ensure the liner is in the correct position
prior to refilling; this includes the
positioning of the neoprene mat (where
fitted) under the vortex inhibitor bottom
support and strainer.
3 A diver or other underwater inspection
technique may be used in lieu of draining
the tank in consultation with the tank
manufacturer (to satisfy warranty
requirements).
PRESSURE TANKS
4.4 Water supply Conduct a six-yearly inspection by a qualified
tanks—Pressure pressure vessel inspector.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 6 F I R E D E T E C T I O N A N D A L A R M
SYSTE MS
6.1 GENERAL
This Section sets out the requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire detection and alarm systems.
Where smoke alarms and heat alarms are connected to a fire detection system, the procedures for the
smoke and heat alarms shall be in accordance with Clause 6.4.2.
The requirements for routine service of emergency warning systems and emergency intercom systems
shall be in accordance with Clauses 6.4.3 and 6.4.4, respectively.
This Section shall be read in conjunction with Section 1.
6.3 FREQUENCY
The frequency of routine servicing of detection systems shall be in accordance with the following and
Clause 6.4.
(a) Monthly.
(b) Six-monthly.
(c) Yearly.
(d) Five-yearly.
6.4.1.1 General
Routine service of fire detection and alarm systems, special hazards systems and smoke hazard
management, shall be carried out in accordance with Tables 6.4.1.2 to 6.4.1.5.
TABLE 6.4.1.2
MONTHLY ROUTINE SERVICE SCHEDULE
FIRE DETECTION AND ALARM SYSTEM, SPECIAL HAZARD SYSTEMS AND
SMOKE HAZARD MANAGEMENT SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 External alarm INSPECT the external alarm (bell or strobe light)
to ensure it clearly indicates the designated
building entry point.
Inspect to ensure the external alarm label is
legible with the word ‘FIRE’ in characters not
less than 25 mm in height.
1.2 Control and INSPECT the following as applicable:
indicating
Fire indicator panel (FIP), sub-indicator panel
equipment (CIE)
(SIP), repeater panel, fire brigade panel (FBP),
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.7 Filament visual TEST the operation of each filament type visual
indicators indicators.
1.8 Zone block plan INSPECT zone block plans to ensure that they
are securely mounted and legible and
supplementary zone drawings, where required,
are available and legible.
1.9 Baseline data CHECK that baseline data is available and
documentation legible.
TABLE 6.4.1.3
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE DETECTION, ALARMS AND CONTROLS FOR SPECIAL HAZARD SYSTEMS
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Monthly service Complete all monthly service activities, as listed
in Table 6.4.1.2.
2.2 Local control (a) Ensure that they are clearly visible readily
station (LCS) accessible and free from dust and
contaminants.
(b) Check that the door is correctly labelled.
2.3 Visual warning INSPECT all visual warning devices, including:
devices
• DO NOT ENTER
•
EVACUATE
•
FIRE ALARM
•
SYSTEM INOPERATIVE
for any condition or damage that is likely to
adversely affect their function.
2.4 Local control TEST the operation of each inhibit or auto/manual
station (LCS) switch and confirm that:
discharge inhibit
(a) It prevents the automatic discharge of
switch
suppression system.
(b) Stops and resets the normal system
discharge sequence.
(c) Causes the illumination of a visual indicator
at the LCS and the system FIP.
(d) Causes an audible indication.
(e) Does not override the operation of the
manual discharge switch.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.5 Local control TEST the operation of the manual initiate switch
station (LCS) and confirm normal system discharge sequence,
manual initiate including fire and evacuation alarms, time delays
switch equipment shutdowns, and that it overrides the
LCS discharge inhibit switch.
2.6 System inoperative CONFIRM the system inoperative VWD operates
visual warning for:
device (VWD)
(a) Operation of a service switch (discharge
initiating circuit electrical isolation).
(b) Fault in the discharge actuator circuit.
(c) Operation of a lock-off valve (where fitted).
(d) Operation of a manual inhibit switch (where
fitted).
(e) Isolation or fault in any part of the fire
detection or control system that prevents the
automatic or electrical manual discharge of
the suppression system.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
2.7 System operation TEST the system logic (e.g. dual detector
and logic operation or dependency on more than one alarm)
and confirm that the operation of—
• VWDs
•
audible alarms
•
directional valve signal/output
•
equipment fire mode signal/output
•
HVAC fire mode signal/output
•
system discharge actuator
•
door and damper release and
•
ancillary controls
is in accordance with the approved design.
2.8 Actuator circuit TEST each supervised actuator circuit to ensure a
faults fault is registered at the FIP.
2.9 Actuator TEST the function of each actuator and ensure
that each actuator operates correctly.
Ensure that each actuator has been mechanically
isolated or temporarily removed from the
suppressant supply to prevent unintended
discharge.
For non-resettable actuators (e.g. pyrotechnic
types) substitute the actuator with a load of
equivalent value and CONFIRM the operating
current is in accordance with baseline data.
NOTE: Take precautions to prevent the discharge of the system during these tests.
TABLE 6.4.1.4
YEARLY ROUTINE SERVICE SCHEDULE
FIRE DETECTION AND ALARM SYSTEM, SPECIAL HAZARD SYSTEMS AND
SMOKE HAZARD SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Monthly and six- COMPLETE all monthly and six-monthly
monthly service service activities, as listed in Table 6.4.1.2 and
6.4.1.3.
3.2 Manual call points CHECK all manual call points are free of
conditions likely to adversely affect their
function.
3.3 Manual call points TEST the operation of each manual call point.
3.4 Other warning Where other warning devices are used as the
devices alarm-indicating devices, INSPECT all devices
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.10 Occupant warning MEASURE and record the sound pressure level Location of
system sound from at least one reference point for each reference
pressure level amplifier used and ensure at each reference points……….
point the measured value is consistent with the Baseline SPL
baseline sound pressure level at each reference …………...dBA
point (see AS 1670.1).
Measured test
SPL
…………...dBA
3.13 Batteries condition When the battery has not been replaced in the Date last
previous two years, verify the battery condition replaced or;
by carrying out a battery discharge test in Test load
accordance with Appendix F. current……..A
Final test
voltage……..V
3.14 Smoke alarms and Refer to Clause 6.4.2.
heat alarms
3.15 Service life Inspect detectors, equipment or other items
having a defined service life and report where
the service life is exceeded or will be exceeded
before the next scheduled service.
3.16 Baseline data CONFIRM the baseline data is accurate.
3.17 Protected areas SURVEY all areas of the building from floor
survey level and check—
(a) that the fire detection and alarm system
has not been altered from the approved
design, damaged or compromised;
(b) detection device and remote indicators are
appropriate for the current use;
(c) for any condition that may cause a
nuisance alarm or the unintentional
operation of a suppression system;
(d) all exposed cabling, conduits, junction
boxes and the like for any condition that
may impact on the performance of the
system and is labelled in accordance with
approved design; and
(e) all CIE to ensure all components are
appropriately mounted and secure.
3.18 Interfaced system Simulate alarm(s) to verify that each interface
initiation transmission path initiates the corresponding
interfaced system(s) in accordance with the
approved design.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
SMOKE HAZARD MANAGEMENT SYSTEMS—ADDITIONAL ACTIVITIES
CAUTION: TAKE PRECAUTIONS TO PREVENT UNACCEPTABLE VENTILATION SYSTEM CHANGES
3.19 FFCP latching and CHECK that after initiation by a signal from
reset the FIP, the FFCP remains operating in the fire
mode until reset by the reset switch on the
FFCP.
3.20 Manual override CHECK that manual override ON-AUTO-OFF
controls control operates.
NOTE: Manual override should function in
normal mode and fire mode.
3.21 Airflow fault CHECK the operation of the airflow fault
indicator indicator
3.22 Open-circuit fault CHECK the operation of the air-handling
indicator equipment interconnecting cable open-circuit
fault indicator.
3.23 Closed-circuit CHECK the operation of the air-handling
fault indicator equipment interconnecting cable closed-circuit
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
fault indicator.
3.24 Electrical CHECK the operation of the electricity phase-
fail fault indicator.
3.25 Fan-running CHECK the operation of the fan-running
indicator indicator.
3.26 Fan-stopped CHECK the operation of the fan-stopped
indicator indicator.
3.27 Fan fault indicator CHECK the operation of the fan-fault indicator.
SPECIAL HAZARD SYSTEMS—ADDITIONAL ACTIVITIES
CAUTION: TAKE PRECAUTIONS TO PREVENT THE DISCHARGE OF THE SYSTEM DURING THESE
TESTS
3.28 Status monitoring TEST the each suppression system status
monitored function (e.g. container level,
pressure switches, pump controllers, isolation
valves) and CHECK each monitored function
indicates at the suppression system control
panel.
3.29 Suppression SIMULATE the system operation and confirm
system directional that each electrical directional valve operates
valves according to the approved design.
3.30 Discharge time TEST and RECORD the system discharge
delay sequence and confirm the time delay period is
in accordance with the approved design.
3.31 Agent release TEST the agent release detection device
indication (e.g. pressure switch) and confirm the operation
of the agent release is indicated at the FIP.
TABLE 6.4.1.5
FIVE-YEARLY ROUTINE SERVICE SCHEDULE
FIRE DETECTION AND ALARM SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.1 Monthly, six- Complete all monthly, six-monthly and yearly
monthly and service activities, as listed in Tables 6.4.1.2,
yearly service 6.4.1.3 and 6.4.1.4.
4.2 Supervised circuits TEST each input and output supervised circuit for
any condition that prevents the transmission of the
required signal and ensure a fault is registered at
the FIP.
4.3 Fault SIMULATE a circuit fault condition at the FIP and
confirm that all required common or general visual
and audible indications operate. Where such faults
are monitored, ensure the fault has activated the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 6.4.2.2
SIX-MONTHLY SERVICE SCHEDULE
SMOKE ALARMS AND HEAT ALARMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Smoke alarms and INSPECT all alarms for any condition that is likely
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 6.4.2.3
YEARLY SERVICE SCHEDULE
SMOKE ALARMS AND HEAT ALARMS
TABLE 6.4.3.1
MONTHLY SERVICE SCHEDULE
EMERGENCY WARNING SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Baseline data INSPECT that baseline data is available and legible.
1.2 Zone Block plan INSPECT zone block plans to ensure that they are
securely mounted and legible and supplementary
zone drawings, if provided, are available and legible.
1.3 Control and INSPECT the warning system panel, and—
indicating
(a) ensure that it is clearly visible, readily
equipment
accessible and free from dust and
contaminants;
(b) where a panel is obscured by a door, CHECK
that the door is correctly labelled; and
(c) where manual call points use replaceable
frangible elements, ENSURE that at least one
replacement element and a tool is available for
replacing the element where required.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.4 Battery Where vented batteries are used, INSPECT the
enclosure battery enclosure for evidence of corrosion.
1.5 Emergency SIMULATE an alarm condition and confirm that the
warning system required warning signal(s) operate.
test
NOTE: It is recommended that the warden
intercom system is used by the floor wardens to
confirm the operation of the warning signals.
TABLE 6.4.3.2
YEARLY SERVICE SCHEDULE
EMERGENCY WARNING SYSTEM
Item Records
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.11 Aural indicators TEST or confirm the operation of the aural
indicators as required.
2.12 Panel switches and TEST the operation of each control.
keypads
2.13 Fault SIMULATE a fault between the fire system and the
warning system and confirm the fault condition is
indicated at the EWP and the FIP.
2.14 Visual indicators TEST the operation of each visual indicator and
alphanumeric displays.
2.15 Nominal battery MEASURE system quiescent and alarm currents. Quiescent
capacity Calculate the required battery capacity and current I Q …..A
CHECK the installed battery’s nominal capacity is
Alarm current
no less than the required capacity. See Appendix F
I A …………..A
for calculating the required battery capacity.
Battery
capacity…...Ah
2.16 Ancillary controls TEST the operation of ancillary control functions
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 6.4.3.3
FIVE YEARLY SERVICE SCHEDULE
EMERGENCY WARNING SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Monthly and Complete all monthly and yearly service
yearly Service activities, as listed in Tables 6.4.3.1 and 6.4.3.2.
3.2 Speech UNDERTAKE tests to ensure intelligibility in all Location….…
intelligibility areas of the building where required to meet the Reference….CIS
requirements of the approved design. Recorded…..CIS
3.3 Sound pressure MEASURE and record the sound pressure level Location of
level from at least one reference point for each reference point
amplifier used and ensure at each recorded point ………………..
the measured value is consistent with the Reference SPL
reference sound pressure level. ……………dBA
Measured test
SPL……….dBA
3.4 Emergency MEASURE and record the impedance of each Baseline….…
warning system loud speaker circuit and check that it has not
Impedance per
speaker circuits changed by more than 15% from the last test nor
circuit……….
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 6.4.4.1
YEARLY SERVICE SCHEDULE
EMERGENCY INTERCOM SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Baseline data INSPECT that baseline data is available and
legible.
1.2 Emergency INSPECT the intercom panel to ensure that it is
intercom clearly visible, readily accessible and free from
equipment dust and contaminants. Where the panel is
obscured by a door, check that the door is
correctly labelled.
1.3 Visual indicators TEST the operation of visual indicators and
alphanumeric displays.
1.4 Aural indicators TEST the operation of the aural indicators.
1.5 Panel switches TEST the operation of each required control
and keypads (e.g. secondary emergency control panels).
1.6 Fault SIMULATE a WIP circuit fault condition and
confirm the fault condition is indicated at the
intercom panel.
1.7 Reset TEST the operation of the reset function.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.8 Warden indicator CHECK the operation of each warden indicator
and controls and controls.
1.9 Warden intercom INSPECT all WIPs to ensure they are clearly
points (WIPs) visible and readily accessible. Where the WIP is
obscured by a door, check that the door is
correctly labelled.
1.10 WIP INSPECT all WIPs to ensure there is no
mechanical damage.
1.11 Stand-alone Where vented batteries are used, INSPECT the
intercom system battery enclosure for evidence of corrosion.
(battery enclosure)
1.12 Outgoing WIPs INITIATE a call from each WIP and confirm that
function test each WIP is indicating correctly and that clear
communication is possible with the intercom
panel operator.
1.13 Incoming WIPs INITIATE a call to each WIP and phone and
function test confirm that each WIP is indicating correctly and
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 7 S P E C I A L H A Z A R D S Y S T E M S
7.1 GENERAL
This Section sets out the requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of gaseous, aerosol and open nozzle water mist special hazard fire
suppression systems.
NOTE: Routine service requirements for some pre-engineered special hazard systems are covered in other
standards; AS 3772 for pre-engineered systems protecting cooking equipment and AS 5062 for pre-
engineered foam spray and dry chemical powder systems fitted to mobile and transportable equipment. Pre-
engineered special hazards systems should be serviced in accordance with either of these specific Standards
or the relevant parts of this Section where other specific standards do not exist.
Special hazard fire suppression systems that incorporate electrical detection and control systems shall
be serviced in accordance with this Section and the requirements of Section 6.
This Section shall be read in conjunction with Section 1.
All special hazard systems shall be subjected to routine service at the intervals specified in
Clause 7.4.
7.2.2 Precautions
Prior to commencing any routine service, the following precautions shall be carried out:
(a) Inform the responsible entity that service is to be carried out.
(b) Where the system may be temporarily impaired, advise the responsible entity of the nature and
expected duration of the impairment.
(c) Advise the monitoring service provider where service activities may cause a signal to be
transmitted.
NOTE: Advice may be by configuring the alarm signalling equipment into a test mode.
(d) Disable the system to ensure that service activities cannot cause discharge of extinguishing
agent.
(e) Set the detection and alarm system in the appropriate test mode and ensure that ancillary
facilities, systems and air-handling plant (including smoke exhaust and stairwell pressurization
systems, evacuation warning systems, and the like), where they are not to be tested, are isolated
to avoid inadvertent operation.
On completion of any testing or service, return all controls to their prior state. When any function is
left impaired, disabled or is not restored to normal, it shall be recorded in the system logbook and the
owner or agent shall be notified (see Clause 1.17).
NOTE: When any section of an installation is to be isolated, the responsible entity should be notified.
7.2.3 System isolation
All stored pressure container discharge valves shall be mechanically isolated prior to undertaking the
tests referred to in Tables 7.4.1 to 7.4.2. This mechanical isolation may involve removing the actuator
from the discharge valve or fitting a locking pin. Electrical isolation only does not satisfy this
requirement.
Fixed aerosol fire extinguisher system actuation means shall be isolated by means of the maintenance
isolate switch as defined in AS/NZS 4487 prior to undertaking the tests set out in Table 7.4.2. Where
there is no maintenance isolate switch, aerosol fire extinguisher units shall be removed from the
protected areas prior to testing.
7.2.4 Baseline data
Baseline data shall in accordance with Clause 1.8 and shall include a systems interface diagram. See
Clause 1.12 and Appendix C.
7.2.5 Service records
Records of activities and results detailed in Clause 7.4 shall be kept in accordance with Clause 1.16.
7.2.6 Reports
Critical defects and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
7.3 FREQUENCY
The frequency of routine servicing of special hazard systems shall be in accordance with Clause 7.4
and the following:
(a) Monthly.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(b) Six-monthly.
(c) Yearly.
(d) Ten-yearly.
TABLE 7.4.2
MONTHLY ROUTINE SERVICE SCHEDULE
SPECIAL HAZARD SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Electrical Perform routine service in accordance with
detection and Section 6.
control systems
1.2 Warning signs CHECK that all warning signs are readily visible
(printed signs and and legible.
labels)
1.3 Storage container CHECK the storage container enclosure is
enclosure accessible, adequately illuminated, ventilated and
secured against unauthorized entry.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.4 Storage containers (a) CHECK that all containers are secure,
accessible, free from damage and mounted to
allow free passage of air around the base.
(b) CHECK each container pressure indicator and
verify that any loss in pressure is not greater
than 10% of the nominal charge pressure.
Where there is no container pressure indicator,
check that the system discharge indicator has
not operated (see Note 2).
1.5 Mechanical (a) CHECK that all release anti-tamper seals/pull
release devices pins are in place and secure.
(b) CHECK that all release mechanisms, including
gas container valves, actuators and drop
weights, are undamaged, accessible and
unimpeded.
1.6 Lock-off valve CHECK that the lock-off valve is correctly labelled
(where fitted) and accessible.
(see Note 1)
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.7 Protected area INSPECT the protected area to check that the risk
has not changed from the approved design
(e.g. volume, fuel type, change of use).
AEROSOL SYSTEMS—ADDITIONAL ACTIVITIES
1.8 Aerosol generators CHECK that all aerosol generators have not been
discharged and are secure.
1.9 Aerosol generator CHECK that all aerosol generator moisture seals
moisture seal are secure.
WATER MIST SYSTEMS—ADDITIONAL ACTIVITIES
1.10 Pressure regulator CHECK for damage and correct setting.
1.11 Pumps and water CHECK in accordance with the requirements of
supplies Section 3.
1.12 Pumps and TEST operational function of pumps and associated
associated equipment in accordance with the requirements of
equipment Section 3.
1.13 Air compressor Where air receivers form part of a water mist
system, TEST compressor cut-in/cut-out pressures.
NOTES:
1 It is recommended that lock-off valves be retrofitted to gaseous fire extinguishing systems which may result in unsafe
concentrations of extinguishing agent developing in occupiable areas (for example CO 2 systems).
The installation of a lock-off valve introduces the possibility of trapping agent in the pipework. As a result, additional
safety devices, including means of indicating trapped pressure, means of manually venting trapped pressure and a means
of automatic pressure relief, should be installed in conjunction with the lock-off valve. (See AS ISO 14520.1).
2 Cylinder contents for non-liquefied agents may be directly determined from the container pressure gauge without the
need for weighing the cylinder.
TABLE 7.4.3
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
SPECIAL HAZARD SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Monthly Service COMPLETE all monthly service activities as listed
in Table 7.4.2.
2.2 Electrical Perform routine service in accordance with
detection and Section 6.
control systems
2.3 Detection devices CHECK all mechanical and pneumatic detection
(mechanical) devices for any condition that is likely to adversely
affect their function.
2.4 Detection systems TEST operation of automatic mechanical detection
(mechanical), e.g. systems and confirm the alarm activates the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
WATER MIST SYSTEMS—ADDITIONAL ACTIVITIES
2.14 Cycling system TEST cycling system through a complete discharge
cycle.
2.15 Pumps Perform routine service in accordance with
Section 3.
2.16 Water valves Perform routine service in accordance with
(release/isolating Section 2.
and control)
NOTES:
1 It is recommended that lock-off valves be retrofitted to gaseous fire extinguishing systems, which may result in unsafe
concentrations of extinguishing agent developing in occupiable areas (for example CO 2 systems). The installation of a
lock-off valve introduces the possibility of trapping agent in the pipework. As a result, additional safety devices,
including means of indicating trapped pressure, means of manually venting trapped pressure and a means of automatic
pressure relief, should be installed in conjunction with the lock-off valve (see AS ISO 14520.1).
2 Cylinder contents for non-liquefied agents may be directly determined from the container pressure gauge without the
need for weighing the cylinder.
Routine service of special hazards systems on a yearly basis shall be carried out in accordance with
Table 7.4.4.
TABLE 7.4.4
YEARLY ROUTINE SERVICE SCHEDULE
SPECIAL HAZARD SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Monthly and six- COMPLETE all monthly and six-monthly
monthly service service activities, as listed in Tables 7.4.2
and 7.4.3.
3.2 Electrical Perform routine service in accordance with
detection and Section 6.
control systems
3.3 Gas storage Record last pressure test or inspection date of
containers gas storage containers. Report to owner if
ten-yearly pressure test or inspection will be
due in the next year. See Table 7.4.5
Items 4.3 and 4.4.
3.4 Mechanical CHECK operation and lubricate as necessary.
actuator
3.4 Mechanical CHECK operation and lubricate as necessary.
release system
3.5 Detection system CHECK operation and lubricate as necessary.
(mechanical)
3.6 Detection device REPLACE any detection device or sensing
(mechanical) element that will exceed its listed service life
prior to the next scheduled routine service.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.7 Detection device CHECK that all mechanical and pneumatic
location detection devices are spaced and located in
accordance with the approved design.
3.8 Pyrotechnic REPLACE any actuator that will exceed its
actuator listed service life prior to the next scheduled
routine service.
3.9 Nozzles CLEAN nozzles that have been subjected to
the deposit of contaminants.
3.10 Dampers CLEAN dampers that have been subjected to
the deposit of contaminants.
3.11 Unintentional CHECK for any condition that could cause
discharge inadvertent discharge of the extinguishing
agent.
3.12 Type of hazard VERIFY fuel class and type match baseline
data.
3.13 Enclosure volume VERIFY volumes (gross and net) match the
(total flooding baseline data.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
systems)
3.14 Design VERIFY design concentration or application
concentration or density matches baseline data.
application
density
3.15 Dimensions of VERIFY dimensions match the baseline data.
protected objects
(local application
systems)
3.16 Enclosure COMPLETE an enclosure integrity test for Equivalent
integrity (total total flooding systems in accordance with leakage area
flooding systems) AS ISO 14520.1 for gaseous systems, and …………….m 2
CONFIRM that the results satisfy the
Retention time
requirements of the approved design.
……min
NOTE: Where an integrity test cannot be (gaseous
conducted due to factors such as physical systems only)
dimensional constraints, or large
unclosable openings, confirm enclosure
integrity conforms with the approved
design by visual inspection.
3.17 Pressure-relief TEST and record the pressure at which
vent (where pressure-relief vent operates.
fitted) ............... Pa
3.18 Adjacent areas INSPECT all areas adjacent to the protected
area to ensure that migration of extinguishing
agent does not create a hazard to personnel.
3.19 Ventilation Test operation of automatically operated HVAC ………
dampers ventilation dampers.
Power or fuel
3.20 NOTE: For special hazard system shut-off
interfaces with HVAC systems, see ………..EWS
Clause 1.12 and Section 10.
3.21 Post-discharge TEST the operation of the post-discharge
ventilation ventilation system.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.22 Directional SIMULATE a system operation and confirm
valves that directional valves operate in accordance
with the approved design.
3.23 System interface (a) CONDUCT a functional system test with
test (see other interfaced fire systems (e.g.
Clause 1.12.2) HVAC, EWS).
(b) VERIFY that the interface functions in
accordance with the building’s systems
interface diagram.
NOTE: It is recommended that the
responsible entity coordinate testing the
interfaced fire protection systems.
AEROSOL SYSTEMS—ADDITIONAL ACTIVITIES
3.24 Aerosol REPLACE any generator that will exceed its
generators listed service life prior to the next scheduled
routine service.
WATER MIST SYSTEMS—ADDITIONAL ACTIVITIES
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 7.4.5
TEN-YEARLY ROUTINE SERVICE SCHEDULE
SPECIAL HAZARD SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.1 Monthly, six- COMPLETE all monthly, six-monthly and yearly
monthly and service activities, as listed in Tables 7.4.2, 7.4.3
yearly service and 7.4.4.
4.2 Pipework and TEST for free and unobstructed flow from each
nozzles nozzle, using a continuous flow of nitrogen or
suitable alternative.
4.3 Gas storage Hydrostatically pressure TEST cylinders that have
container exceeded 10 years since the last test in accordance
(transport type with the procedure in AS 2030.1 (see Note 1).
e.g. cylinders)
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 8 D E L IV E R Y L A Y F L A T F I R E H O S E
8.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of delivery lay flat fire hose manufactured in accordance with AS 2792.
Hose not manufactured to comply with AS 2792 shall be maintained in accordance with this Section,
except that the maximum periodic test pressure shall be assumed to be as for Class L hose (see
Item 1.4 of Table 8.4).
This Section shall be read in conjunction with Section 1.
NOTE: Delivery lay flat fire hose is generally referred to in this Standard as ‘the hose’ or ‘a hose’.
8.2.8 Reports
Critical defect and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
8.3 FREQUENCY
Lay flat hose shall be serviced—
(a) yearly;
(b) after usage; and
(c) when defects are suspected.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 8.4
YEARLY ROUTINE SERVICE AND RECORDS SCHEDULE
DELIVERY LAY FLAT HOSE
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Hose jacket CHECK hose when laid out, preferably straight and
on a flat clean surface, for obvious defects such as
cuts, abrasion, burns or contamination.
NOTE: The hose should be free of dirt, abrasives
and contaminants prior to inspection.
1.2 Couplings INSPECT hose couplings for damage or distortion
to threads, lugs or gaskets.
1.3 Storage CHECK that the hose is stored as follows:
(a) Its folds do not recur in the same position.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.6 Drying DRY the wet hose prior to storage unless it is an
extruded type.
NOTE: Where the hose is dried by heating:
(a) The hose temperature should not exceed 40°C.
(b) The heating should be accompanied by a
natural or forced air draught through the hose.
(c) The hose should not be exposed to the drying
temperature for more than 12 h.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 9 F I R E H O S E R E E L S
9.1 GENERAL
This Section sets out the requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire hose reels manufactured to comply with AS/NZS 1221 and installed
in accordance with AS 2441 or the relevant statutory requirements.
This Section shall be read in conjunction with Section 1.
NOTE: A fire hose reel is generally referred to in this Standard as ‘a hose reel’ or ‘the hose reel’.
Any label applied to the hose reel by a service provider after servicing shall not exceed
90 mm × 50 mm in size and shall not be applied over any manufacturers’ labels or instructions, or on
the service tag or label.
9.2.4 Isolation valves and backflow prevention devices
Where, for routine service purposes, a system isolation valve that can isolate flow in the hose reel
water supply main is installed, it shall be restored to its open position and padlocked open, or have its
operating handle removed, at the completion of or after any service. Backflow prevention devices
fitted to any hose reel water supply shall be locked open.
9.2.5 Pumps
Where a pumpset is installed to supply the required water pressure to the fire hose reel system, it shall
comply with AS 2941, and shall be checked for start-up and serviced in accordance with Section 3 of
this Standard.
9.2.6 ‘After-use’ procedure
After the use of any hose reel, or on completion of any service routines on a hose reel, the following
actions shall be taken to restore its ‘ready for use’ status:
(a) Rewind the hose onto the reel in even layers while it is still pressurized (i.e. stop valve open,
nozzle closed).
(b) Re-engage the nozzle in the nozzle interlock, then close the stop valve (Notes 1 and 2).
(c) De-pressurize the hose by opening the nozzle while it is directed downwards (catching spillage
in a suitable container), then closing the nozzle.
NOTES:
1 Hose reels manufactured prior to 1989 may not be fitted with a nozzle interlock.
2 Automatic hose reels do not have a manual stop valve or nozzle interlock.
9.2.7 Systems interface
Where fire hose reels interface with other systems, all interface functions shall be tested in
conjunction with the other systems to ensure that the interconnections to other systems function as
intended.
NOTE: A typical interface diagram is shown in Figure 1.12.
Critical defect and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
9.3 FREQUENCY
Fire hose reels shall be serviced—
(a) six monthly; and
(b) yearly.
TABLE 9.4.1
SIX-MONTHLY SERVICE SCHEDULE
FIRE HOSE REELS
1.1 Accessibility CHECK that the hose reel is readily accessible with
no obstacles restricting its access. Where a hose
reel is installed in a recess or cabinet, CHECK that
the clearances around the hose reel comply with the
requirements of AS 2441.
1.2 Signage Where a location sign is required by AS 2441,
CHECK that it is correctly located and visible.
1.3 Operating CHECK that the operating instructions are legible.
instructions
(continued)
TABLE 9.4.2
YEARLY SERVICE SCHEDULE
FIRE HOSE REELS
2.6 Flow rate With the stop valve and nozzle fully opened,
MEASURE the water flow rate from the most
disadvantaged hose reel.
Minimum acceptable flow rates:
(a) 0.33 L/s for reels with 19 mm hose.
(b) 0.41 L/s for reels with 25 mm hose.
2.7 Hose CHECK hose for kinking, excessive damage or
wear, or collapse.
2.8 Ancillary CHECK that any foam branch pipe or other
equipment equipment is in good repair and maintained in
accordance with the manufacturer’s instructions.
2.9 Fire hazard CHECK that the hose reel is appropriate protection
for the fire hazard/risk.
2.10 Obstructions CHECK that no alterations have been made to the
building, which impede access to the hose reel or
restrict the running out of the hose, and that the hose
can reach the fire hazard/risk in accordance with
AS 2441.
S E C T I O N 1 0 P O R T A B L E A N D W H E E L E D F I R E
E X T I N G U I S H E R S
10.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of portable and wheeled fire extinguishers, that, at the time of manufacture,
complied with the contemporary edition of the relevant Standard listed in Table 10.1 or AS 4265, and
were installed in accordance with AS 2444 or the relevant statutory requirement.
This Section shall be read in conjunction with Section 1.
NOTES:
1 For extinguishers used regularly for demonstration and training, service should be more frequent than
specified due to the increased potential for wear and damage.
2 A portable or wheeled fire extinguisher is generally referred to in this Standard as ‘an extinguisher’ or
‘the extinguisher’.
TABLE 10.1
AUSTRALIAN STANDARDS FOR PORTABLE
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
FIRE EXTINGUISHERS
Expellant method
Extinguisher type
Gas container Stored pressure
Water AS/NZS 1841.2 AS/NZS 1841.2
(AS 1841.2) (AS 1841.2)
(AS 1841) (AS 1842)
(AS A31.2) (AS A31.3)
Wet chemical AS/NZS 1841.3
— (AS 1841.3)
(AS 1842)
Foam AS/NZS 1841.4 AS/NZS 1841.4
(AS 1841.4) (AS 1841.4)
(AS 1844) (AS 1845)
(AS A32.2) (AS A32.3)
Powder AS/NZS 1841.5 AS/NZS 1841.5
(AS 1841.5) (AS 1841.5)
(AS 1846) (AS 1846)
(AS A137) (AS A137)
Carbon dioxide AS/NZS 1841.6
(AS 1841.6)
—
(AS 1847)
(AS A138)
Vaporizing liquid (Halon) AS/NZS 1841.7
(AS 1841.7)
—
(AS 1848)
(AS A163) (see Note 2)
NOTES:
1 Australian Standard numbers shown in parenthesis refer to superseded Standards.
2 Halon 1211 and Halon 1301.
treated cylinders shall be used, or a corrosion inhibitor shall be added to each charge in the
extinguisher. Extinguishers used in these areas shall be supplied with the appropriate treatment in
accordance with the extinguisher manufacturer’s recommendations.
Where the water quality is in doubt, an inhibitor should be added. Failure to do so may result in rapid
deterioration of the extinguisher, leading to leakage or failure to operate.
Routine service shall be undertaken more regularly where—
(a) water quality has proved to be a problem, or is likely to be a problem;
(b) salts are deposited in extinguishers; or
(c) hard water is used.
NOTE: The presence of salts in water that is used to fill extinguishers can clog the pressure indicator filter,
bind the actuation mechanism, inhibit the removal of the operating head or lead to the corrosion of
extinguisher components. Typical areas affected by water of this type include Adelaide and Perth.
10.2.6 Corrosion
Where an extinguisher is pitted or otherwise damaged by corrosion and it cannot be determined if the
damage is within the limits as detailed in AS 2337.1, then the cylinder shall be condemned.
10.2.7 Exceptions
Portable fire extinguishers designed for ‘one-off’ use, such as aerosol and non-rechargeable types,
shall undergo all inspection and test requirements contained in Clause 10.4 except for those requiring
the depressurizing of the cylinder, removal of the operating head, inspection of the contents, and
inspection of the interior of the extinguisher.
10.2.8 Pressure test marking
Portable carbon dioxide type extinguishers and all wheeled extinguishers that have passed the
hydrostatic pressure test (see Items 3.7 and 3.8 of Table 10.4.3) shall be marked in accordance with
the requirements of AS 2030.1.
All other portable extinguishers that have passed the hydrostatic test shall have the month and year of
the pressure test clearly identified on the extinguisher by one of the following means:
(a) Permanent marking (by stamping, embossing or engraving) on the skirt or neck ring of the
cylinder, provided that it is not applied to part of the pressure retaining portion of the cylinder.
(b) Recording on a durable label affixed to the cylinder. The label shall be self-destructive when
removal from the cylinder is attempted.
(c) A plastic indicator ring retained under the valve such that it can only be installed/removed from
the extinguisher by fully removing the valve from the extinguisher.
10.2.9 Service provider labels
Any label applied to the extinguisher by a service provider after servicing shall not exceed
90 mm × 50 mm in size and shall not be applied on the coloured identification band, over any
manufacturer’s labels or instructions, or on the service tag or label.
10.2.10 Defects
Defects, including faulty or defective components advised by public notices or manufacturers’ service
bulletins, shall be replaced, exchanged or repaired.
Defects that can be repaired on site shall be repaired immediately, or reported to the responsible entity
(see Clause 1.17.1).
Defective extinguishers that cannot be rectified on site shall be removed from site for repair, or
reported to the responsible entity (see Clause 1.17.1).
A replacement unit of the same type and size or a similar rating shall be left in place of the unit
removed from site.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Extinguishers with defects that cannot be repaired shall be condemned, and labelled accordingly. The
label shall have black letters, not less than 10 mm high, on a yellow background as follows:
Evidence of the service level shall not be applied to the service tag or label. The inspection and the
outcome shall be entered in the service records.
Such unsuitable equipment shall be returned to the owner with a ‘defective component’ report and an
‘action required’ report.
Actions taken shall be entered in the service record.
NOTES:
1 The owner’s permission should be obtained to destroy any extinguisher or component that is unsuitable
for re-use.
2 The need for prompt action to recharge and return extinguishers to service, or to replace them, should be
emphasized to the responsible entity.
10.2.11 Recharging agent
Recommendations and instructions for the recharging of fire extinguishers shall be included on the
extinguisher label as supplied by the manufacturer. These instructions shall include the quantity and
type of extinguishing agent to be used.
Where an internal inspection of the extinguisher and its components is required, but a discharge test is
not specified, the extinguishing agent [with the exception of vaporizing liquid type extinguishers (see
Clause 10.2.13)] may be either recovered for re-use in the extinguisher being maintained (provided
that the extinguishing agent is not due for mandatory replacement), or discarded.
10.2.17 Reports
Critical defect and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
10.3 FREQUENCY
Fire extinguishers shall be serviced—
(a) six-monthly;
(b) yearly; and
(c) five-yearly.
Upon installation and after any usage, a six-monthly service shall be carried out. The starting date for
five-yearly service shall be either the date of manufacture of the extinguisher or the date of last
pressure test, whichever is the later. If the date of manufacture or last pressure test cannot be reliably
established, a five-yearly service procedure shall be carried out on the extinguisher.
NOTE: Where an extinguisher has been discharged after the fourth year of the five-year period, a pressure
test should be carried out to allow the extinguisher to begin a new five-year cycle.
Six-monthly routine service of portable and wheeled fire extinguishers shall be completed in
accordance with Table 10.4.1.
NOTE: The following fire extinguishers are referred to as ‘All extinguisher types’ in Tables 10.4.1, 10.4.2
and 10.4.3:
(a) Water (gas container) type.
(b) Water (stored pressure) type.
(c) Wet chemical type.
(d) Foam (gas container) type.
(e) Foam (stored pressure) type.
(f) Powder (gas container) type.
(g) Powder (stored pressure) type.
(h) Carbon dioxide type.
(i) Vaporizing liquid type.
TABLE 10.4.1
SIX-MONTHLY SERVICE SCHEDULE
FIRE EXTINGUISHERS
Item
Item Action required and pass/fail requirement
No.
1.1 Accessibility CHECK the extinguisher is conspicuous,
readily accessible and in its assigned location.
All extinguishers types
1.2 Anti-tamper CHECK that the anti-tamper device is intact.
device
All extinguishers types
1.3 Exterior and CHECK that the extinguisher is clean and the
operating operating instructions are legible.
instructions All extinguishers types
1.4 Service tag or CHECK that the service tag or label is firmly
label attached to the extinguisher.
All extinguishers types
1.5 External CHECK that the extinguisher, including any
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(continued)
Item
Item Action required and pass/fail requirement
No.
1.13 Discharge CHECK that the discharge nozzle is not
nozzle and blocked and that the control valve is
control valve functional.
All wheeled extinguishers
1.14 Carriage CHECK that the carriage assembly is
assembly functional and free from corrosion.
All wheeled extinguishers
1.15 Powder— INVERT the extinguisher and ensure that the
Portable powder remains free flowing.
extinguishers
Powder (stored pressure), powder (gas
container)
1.16 Compressed DETERMINE that the compressed gas
gas container container is the correct size and type, in good
condition, fully charged, and subjected to
service as per AS 2030.5.
All gas container extinguishers
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 10.4.2
YEARLY SERVICE SCHEDULE
FIRE EXTINGUISHERS
Item
Item Action required and pass/fail requirement
No.
Item
Item Action required and pass/fail requirement
No.
TABLE 10.4.3
FIVE-YEARLY SERVICE SCHEDULE
FIRE EXTINGUISHERS
Item
Item Action required and pass/fail requirement
No.
Item
Item Action required and pass/fail requirement
No.
Item
Item Action required and pass/fail requirement
No.
3.11 Seals and RENEW all seals and gaskets fitted to the
gaskets actuating device, operating head, or cap.
All extinguisher types
3.12 Leak detection CHECK if there are any leaks at the joints and
seals that were renewed or disturbed during
recharging.
Water (stored pressure), wet chemical, foam
(stored pressure), powder (stored pressure),
carbon dioxide, vaporizing liquid
3.13 Hose Assembly (a) SUBJECT the hose assembly to a
hydrostatic pressure test of 10 MPa.
All CO 2 type wheeled extinguishers
(b) SUBJECT the hose assembly to a
hydrostatic pressure test of 1.5 times the
extinguisher working pressure, or 2 MPa,
whichever is the greater.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 1 1 F I R E B L A N K E T S
11.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing, preventive
maintenance and survey) of fire blankets manufactured to comply with AS/NZS 3504 and installed in
accordance with AS 2444.
This Section shall be read in conjunction with Section 1.
Fire blankets are located and installed, with the appropriate location signs, in accordance with
AS 2444.
11.2.4 ‘After use’ procedures
Fire blankets shall be discarded after they have been used on a fire.
11.2.5 Service provider labels
Any service label applied to the fire blanket container by a service provider after servicing shall not
exceed 90 mm × 50 mm in size and shall not be applied over any manufacturer’s labels or
instructions, or on the service tag or label. Labels shall not be applied to the fire blanket.
11.2.6 Identification
Fire blankets shall bear a permanently fixed, unique site identification mark, suitable for cross-
referencing with the service records. The mark shall consist of at least one of the following:
(a) Written numbers, letters or a combination of both.
(b) A barcode.
(c) A magnetic or electronic strip or similar (e.g. a smart chip).
11.2.7 Service records
Service records of activities and results detailed in Clause 11.4 shall be kept in accordance with
Clause 1.16.
11.2.8 Reports
Yearly condition reports shall be prepared and distributed in accordance with Clause 1.17.
11.3 FREQUENCY
The frequency of routine servicing of fire blankets shall be in accordance with Clause 11.4 and the
following:
(a) At intervals not exceeding 6 months.
(b) When defects are suspected.
TABLE 11.4
SIX-MONTHLY SERVICE SCHEDULE
FIRE BLANKETS
Item
Item Action required and pass/fail requirement
No.
1.1 Accessibility CHECK that the fire blanket is:
(a) Conspicuous.
(b) In its assigned location.
(c) Readily accessible.
(d) Installed in accordance with AS 2444.
1.2 Signage CHECK that the location sign is visible and
correct.
1.3 Blanket CHECK that the fire blanket container:
container
(a) Is securely and correctly supported.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 1 2 P A S S I V E F I R E A N D S M O K E
SYSTE MS
12.1 GENERAL
This Section sets out requirements for the routine servicing (inspection, testing and preventive
maintenance) of passive fire and smoke systems comprising vertical and horizontal fire and smoke
compartment barriers together with any openings, fire doors and fire shutters, or any service
penetrations and control joints.
The basis of inspection, test and routine servicing of compartment integrity is to identify the
respective vertical and horizontal barriers and their respective fire-resistance level (FRL) or smoke
requirements and to ensure all openings or service penetrations and control joints in these barriers do
not compromise the performance of the fire and smoke compartmentation.
Required passive fire and smoke systems include, but are not limited to the following:
(a) Fire and smoke elements—vertical and horizontal—including walls, floors, ceilings, access
panels and hatches (see Clause 12.4.1).
(b) Structural fire-resistant elements—beams, columns, girders, trusses, etc. (see Clause 12.4.2).
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(c) Fire-resistant doorsets—hinged and pivoted and horizontal sliding (see Clause 12.4.3).
(d) Smoke doors—hinged and pivoted (see Clause 12.4.4).
(e) Fire shutters (see Clause 12.4.5).
(f) Fire-rated glazing (see Clause 12.4.6).
(g) Ducts and dampers (see Clause 12.4.7).
NOTE: The basis of inspection, test and routine servicing of structural elements that have passive fire
protection applied is to identify any degradation to the intended performance.
For the purpose of this Section, accessibility refers to any passive fire and smoke elements that can be
readily inspected without the de-construction (demolition) of any building elements. Elements that are
inaccessible may be excluded from the service routine.
NOTES:
1 This exclusion does not apply to roof space or void inspections where an access hatch exists or areas are
otherwise accessible (e.g. suspended ceilings or raised floors with removable floor tiles).
2 The responsible entity should consider performing an inspection of a representative sample of all non-
accessible areas and elements and keep a register of all systems that have been inspected.
This Section shall be read in conjunction with Section 1.
12.2.2 Application
The requirements for fire rated° ducts are included in this Section; however, fire dampers as part of a
duct assembly, fire rated or otherwise, are covered in Section 13.
NOTE: The responsible entity should consider arranging random inspections of non-accessible areas.
Passive fire and smoke systems are illustrated in Figure 12.1.
1
2
7
9
3
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
6
5
1
9 ( T hi n li n e of s e a l a nt)
LEGEND:
1 Fire and smoke elements
2 Structural fire-resistant elements–beams, columns, trusses
3 Fire-resistant doorsets
4 Smoke doors
5 Fire-resistant shutters
6 Fire-resistant glazing
7 Access panels and hatches
8 Ducts and dampers (see Clause 12.4.4 for dampers)
9 Fire stopping of service penetration and control joints (metal/plastic pipes, electrical cables/conduits/cable tray,
construction/control joints and deflection heads)
FIGURE 12.1 EXAMPLE OF A FIRE AND SMOKE COMPARTMENT SHOWING PASSIVE FIRE
AND SMOKE PROTECTION SYSTEMS
or modified and to determine whether there are any areas that may require repair.
12.2.4.2 Structural fire inspection
An inspection shall be conducted, using the structural drawings or appropriately marked general
drawings and any associated schedules, to identify or locate all structural elements to determine
whether there are any areas that may require repair to an existing fire protective covering.
NOTE: Typically, many structural elements may be inaccessible (see Clause 12.1).
12.2.5 Baseline data
Baseline data shall be in accordance with Clause 1.8 (see Note 1) and shall include but not be limited
to the following:
(a) Fire and smoke compartmentation drawings detailing the bounding construction and FRL of
each fire and smoke compartment.
(b) Fire door data comprising a schedule or record (asset list) detailing type, location and FRL.
(c) Penetrations in fire and smoke compartmentation schedule detail (see Note 2).
NOTES:
1 For guidance and examples of baseline data, see Appendix C.
2 See Table C3, Appendix C.
3 Fire doorsets are required by AS 1905.1 to be tagged.
4 Smoke doors, where required by the NCC or by specific designs, should be tagged or labelled in a
similar manner to that of fire doors. The tags or labels should be numbered to coincide with the key used
on any compartmentation integrity or appropriately marked up general drawings and any associated
schedules.
12.2.6 Marking, labelling and schedule
Passive fire and smoke system components, including penetrations, shall be labelled.
NOTE: If the responsible entity and service provider agree, multiple services may be identified on a single
label.
When a new service label is provided, the label shall be applied adjacent to the completed label so
that the previous service history is not obscured.
80
ID
DIMENSIONS IN MILLIMETRES
12.3 FREQUENCY
The frequency of routine servicing of passive fire and smoke systems shall be in accordance with the
following and Clause 12.4.
(a) Three-monthly (sliding fire doors only).
(b) Six-monthly (fire doors and smoke doors).
(c) Yearly.
TABLE 12.4.1.1
YEARLY SERVICE SCHEDULE FIRE AND SMOKE BARRIERS WALLS,
SERVICE PENETRATIONS AND CONTROL JOINTS
Records
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Wall types, INSPECT against drawings (see Clause 12.2.5) that no
locations fire and/or smoke walls have been added, removed or
modified.
1.2 Service (a) INSPECT against drawings and associated
penetration penetration schedules that no penetrations have
and control been added, removed or modified.
joint
(b) CHECK that reference drawings and penetration
inspection
schedules correctly represent the installed
penetrations.
(c) IDENTIFY any penetration and control joints work
that is unprotected, damaged or incorrectly
installed.
1.3 Walls, where (a) INSPECT that walls continue up to the next
accessible horizontal fire-resistant barrier or to the underside
of the roof above.
(b) INSPECT for any damage that will cause loss of
fire resistance.
TABLE 12.4.1.2
YEARLY SERVICE SCHEDULE
FIRE AND SMOKE BARRIERS FLOORS, SERVICE PENETRATIONS
AND CONTROL JOINTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Fire rated floors INSPECT against drawings (see Clause 12.2.5) that
no fire-rated floors, including resistance to incipient
spread of fire, have been added, removed or modified.
2.2 Service (a) INSPECT against drawings and associated
penetration and penetration schedules that no penetrations have
control joint been added, removed or modified.
inspection
(b) CHECK that reference drawings and penetration
schedules correctly represent the installed
penetrations.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.1.3
YEARLY SERVICE SCHEDULE
FIRE AND SMOKE BARRIERS CEILINGS, SERVICE PENETRATIONS
AND CONTROL JOINTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Ceiling types, INSPECT against drawings (see Clause 12.2.5) that no
locations fire-rated ceilings, including resistance to incipient
spread of fire, have been added, removed or modified.
3.2 Service (a) INSPECT against drawings and associated
penetration and penetration schedules that no penetrations have
control joint been added, removed or modified.
inspection
NOTE: All light fittings and access
panels/ceiling hatches should be inspected.
(b) CHECK that reference drawings and penetration
schedules represent as-installed penetrations.
(c) IDENTIFY any penetration and control joints
work that is unprotected, damaged or incorrectly
installed.
TABLE 12.4.1.4
YEARLY SERVICE SCHEDULE
FIRE AND SMOKE BARRIERS FIRE AND
SMOKE RATED ACCESS PANELS AND HATCHES
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.1 Access panel INSPECT against drawings (see Clause 12.2.5) that
label access panels or hatches, including resistance to
incipient spread of fire, have been added, removed or
modified.
4.2 Access panel or (a) INSPECT panel to ensure it is free of any visible
leaf delamination, and other damage.
(b) INSPECT that the any perimeter seal is in good
condition and not damaged.
4.3 Frame (a) INSPECT access panel frame is adequately
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.2
YEARLY SERVICE SCHEDULE
FIRE-PROTECTED STRUCTURAL MEMBERS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Structural INSPECT against drawings (see Clause 12.2.5) that no
members structural steel members have been added, removed or
modified.
2.2 Inspection (a) CHECK condition of fire protection system or
coating.
(b) CHECK for mechanical damage.
2.3 Fire-protection (a) INSPECT visually for areas of deterioration
system or coating against vermiculite, cement, mineral fibre and
plaster (or combinations of) spray’s loss of
adhesion.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.3.1
SIX-MONTHLY SERVICE SCHEDULE
HINGED AND PIVOTED FIRE-RESISTANT DOORSETS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Location INSPECT to determine if the fire-resistant doorset has
been modified since the previous routine service.
1.2 Marking—Tags (a) INSPECT door leaves and door frames are tagged in
and signage accordance with AS 1905.1.
(b) INSPECT to ensure relevant statutory signage has
been applied and that the location of the signage is
in accordance with regulatory requirements.
1.3 Clearances in the (a) CHECK that gaps between the edge of the door leaf
closed position and the door frame are in accordance with
AS 1905.1 or the relevant test report.
(b) CHECK that the gap between the bottom edge of
the door leaf and the finished floor level is in
accordance with AS 1905.1 or the relevant test
report.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.8 Door leaves (a) CHECK doors for any visible delamination,
buckling, warping, bowing, twisting or significant
damage.
(b) CHECK door edges are in good condition and free
from any splitting or damage on all sides.
1.9 Door frames (a) CHECK door stop dimensions are approved for the
proprietary door type and FRL.
(b) CHECK steel door frames are back-filled as
required for the proprietary door type and FRL.
NOTE: See AS 1905.1.
(c) CHECK door frame is free from excessive
distortion at any point along frame sections.
(d) CHECK to ensure doorframe incorporates a door
striker plate.
(e) CHECK condition of frame.
1.10 Vision panels (a) CHECK proprietary door type is approved for use
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.3.2
THREE-MONTHLY AND SIX-MONTHLY SERVICE SCHEDULE
HORIZONTAL SLIDING DOORS FIRE-RESISTANT DOORSETS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
THREE-MONTHLY
2.1 Frictional forces, SIMULATE a full operational test (mechanically and
operation and electronically) as appropriate to ensure correct
self-closing automatic closing of the door is achieved.
ability
CHECK operation to ensure the door fully closes from
the fully open position and from one intermediary
position.
SIX-MONTHLY
2.2 Location INSPECT against drawings and all schedules (see
Clause 12.2.5) to ensure that no fire doors has been
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
Automatic (d) REPLACE all fusible links every 25 years from the
operations (cont) date of manufacture.
NOTE: In lieu of replacing all fusible links, a
representative sample may be tested as per
Section 2.
(e) PERFORM a full operational test (mechanically
and electrically) as appropriate to ensure correct
automatic closing of the door is achieved.
(f) CHECK operation to ensure the door fully closes
from one intermediary position.
(g) TEST operation of illuminated sliding doors,
warning signs, sounders and release delays, as
appropriate.
2.9 Door guides, INSPECT floor and/or track and/or wall-mounted guides
stops and and stops and all travel-limiting devices at door open
restraints and close locations are adequate and soundly mounted.
2.10 Other fittings and (a) CHECK arrows indicating opening direction are
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.4
SIX-MONTHLY SERVICE SCHEDULE
HINGED AND PIVOTED SMOKE DOORS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.1 Location INSPECT against drawings and all schedules (see
Clause 12.2.5) that no smoke doors have been added,
removed or modified.
4.2 Door type and (a) CHECK that the smoke door complies to
signage appropriate door design specification, is at least
35 mm thick solid core door or in accordance
with the requirement of the ‘building approval’.
(b) CHECK that doors are self closing.
(c) INSPECT to ensure relevant statutory signage
has been applied and that the location of the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.8 Frictional forces VERIFY the opening and closing forces are such that
and self-closing the doors can be easily opened and closed in normal
and self-latching conditions and in fire mode, taking into account any
function pressurization systems within the building.
4.9 Door closers and (a) CHECK the door closer (body and arm) is free
pivots from obstructions by walls or fixtures and is
operating freely throughout its swing.
(b) CHECK any closer free from oil leakages.
(c) CHECK screw fixing and mounting
arrangements for door closer are secured to the
door leaf and door frame.
4.10 Hinges (a) CHECK hinges are free from any undue wear
and tear and are correctly aligned and operating
smoothly and freely.
(b) CHECK hinges are securely fixed to the door
leaf and frame.
4.11 Door leaves (a) INSPECT that door is free from any visible
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 12.4.5
YEARLY SERVICE SCHEDULE
FIRE SHUTTERS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
5.1 Location INSPECT against drawings and all schedules (see
Clause 12.2.5) that no fire shutters have been added,
removed or modified.
5.2 Marking—Tags CHECK fire shutters and frames are tagged in
and signage accordance with AS 1905.2.
5.3 Bracket fixings (a) CHECK brackets are securely fixed to the walls.
and barrel
(b) CHECK barrel assembly is mounted so that the
assembly
rolled-up curtain on the barrel sits higher than
the top level of the guide tracks.
5.4 Guide track (a) CHECK guide tracks are securely fixed to the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
fixings walls.
(b) CHECK guide tracks are mounted such that the
curtain overlaps equally the jamb on each side of
the opening.
(c) CHECK the gap between the end of the slats,
including end clips and the guide track, is no
more that 10 mm.
(d) CHECK that the shutter moves freely in the
guide tracks without jamming under normal
operation.
5.5 Threshold INSPECT that the threshold is of concrete or similar
approved material deemed non-combustible.
5.6 Fusible link (a) INSPECT that the fire shutter is fitted with a
fusible link (if applicable) of not greater than
80ºC (57ºC in the case of a drenched fire shutter)
and the fusible link is in good and operational
condition.
(b) REPLACE all fusible links every 25 years from
the date of manufacture.
NOTE: In lieu of replacing all fusible links, a
representative sample may be tested as per
Section 2.
5.7 Operation test (a) TEST that under simulated automatic operation
the fire shutter curtain descends to the threshold
at an average speed of between 0.15 m/s and
0.3 m/s.
(b) TEST that under simulated automatic operation
the curtain does not rebound creating a gap
greater than 25 mm between the bottom rail and
the threshold.
(c) CHECK shutter slats, bottom rail and brake
release mechanism, illuminated warning signs,
sounders and release delays (where fitted) are
free from damage and the slats are not binding
on each other when opening and closing.
TABLE 12.4.7
YEARLY SERVICE SCHEDULE
FIRE-PROTECTED AIR DUCTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
7.1 Location INSPECT against drawings and all schedules (see
Clause 12.2.5) that no air duct has been added,
removed or modified.
7.2 Fire-protected (a) INSPECT fire-resistant ducts from drawings,
duct plans and schedule for condition of fire protection
system or coating, including supports.
(b) CHECK for mechanical damage.
7.3 Fire protection (a) INSPECT visually for areas of deterioration,
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 1 3 F I R E A N D S M O K E C O N T R O L
F E A T U R E S O F M E C H A N I C A L S E R V I C E S
( S M O K E H A Z A R D M A N A G E M E N T S Y S T E M S )
13.1 GENERAL
This Section sets out the requirements for routine service of fire and smoke control features of
mechanical services in buildings covered by AS/NZS 1668.1, AS 1668.2, AS 1682.1, AS 1682.2 and
AS 2665. This Section does not apply to air conditioning, mechanical ventilation or natural ventilation
systems that are not required to operate in fire and smoke control mode. For systems required to shut
down in fire mode, it shall be proven they shut down in accordance with Clause 13.2.
This Section shall be read in conjunction with Section 1.
Fire-rated ducts and dampers are illustrated in Figure 13.1.
NOTE: Refer to Appendix H for information relating to documentation, records, reports and skills associated
with routine servicing, and to Appendix I for baseline data, dual duty systems, forms for recording routine
service, and explanation of functionality versus performance and use of smoke control system functionality
test chart.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
D a m p e r- r e t a i ni n g Wa ll
a n g l e s h owi n g c u t- away
Duct Insu
In ull a
ate
te d a s r e q u i r e d
by m a n u fa c tu r e r
Damper
TABLE 13.2.1
APPLICATION OF AS 1851 TO HVAC SYSTEMS
NOTE: Smoke exhaust systems, smoke control systems and exit pressurization
systems are required to be tested at least annually to demonstrate they are
capable of performing to the Standard to which they were installed. In the case
of the following systems, this requires measurement of parameters required by
AS/NZS 1668.1 or the relevant building codes including:
(a) Pressurization systems—Doorway velocities, door opening forces,
restoration times, etc.
(b) Smoke control systems—Differential pressures, etc.
(c) Smoke exhaust systems—Airflow rates.
C13.2.2 A survey is typically conducted visually from floor level, from an accessible platform, or
from an accessible roof by simple observation through vent and fan discharges, and is intended to
identify changes to the mechanical services system, or the building and its environment, that could
affect the performance of the smoke control features of the mechanical services system.
13.2.3 Dual duty systems
Systems or components that have dual duty operation as well as systems that have dedicated fire mode
duty shall be inspected, tested and maintained to the requirements set out in Tables 13.4.1.1 and
13.4.1.2. Dual duty systems are those that operate in day-to-day mechanical services function as well
as in fire modes.
NOTE: For guidance on mechanical services, see Appendix I.
13.2.4 Service records
Service records of activities and results detailed in Clause 13.4 shall be kept in accordance with
Clause 1.16.
13.2.5 Reports
Critical defect and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
13.3 FREQUENCY
The frequency of inspection, testing, maintenance and survey shall be in accordance with the
following:
(a) Monthly (applies to kitchen exhausts and outdoor air intakes only).
(b) Three-monthly.
(c) Six-monthly.
(d) Yearly. (Also includes 5-yearly and 25-yearly items.)
Records shall demonstrate evidence that the procedures in this Standard have been followed (see
Clause 1.15) Routine service, where required, includes removal, repair, replacement, lubrication or
adjustment, as appropriate.
NOTES:
1 In the case of mechanical services used for smoke control, the inspection, testing, preventive
maintenance and survey work should be carried out such that inspection, preventive maintenance and
surveys are applied to components or equipment, and testing is applied to whole systems.
2 Apart from gross failures such as broken belt drives or collapsed bearings, most of the preventive
maintenance work on mechanical services depends on the skill and experience of qualified technicians
recognizing, after inspection, test or survey, that repair, adjustment, etc., of components or replacement
of consumables is necessary. Hence, preventive maintenance work is not specified at prescribed
intervals, rather, it depends on an inspection to ascertain the condition of the plant, followed by
adjustment, correction or even repair where, in the judgment of the experienced technician, such actions
are necessary, and this is the intention of Tables 13.4.1.2 to 13.4.1.18. Where action is taken during
inspection to successfully rectify or repair a component, then ‘pass’ is to be recorded in the ‘Pass/fail’
column and details of the action taken are to be entered in the ‘Comments’ column.
3 Routine service should be completed at the specified intervals and to the Standard required by the
equipment manufacturer and scheduled in the project’s operation and service manuals.
C13.4.1.1 In mechanical services, much of the work is carried out when required; hence,
inspections need to be carried out prior to considering the scheduled maintenance activity. For
example, belt tensioning is carried out when inspection shows it is needed, rather than regular
tightening without assessment, which could do more damage than leaving the belts loose.
13.4.1.2 Fans and motors—Three-monthly
Supply, exhaust and return, pressurization, smoke exhaust or smoke spill fans used in day-to-day
operation, or dedicated fire mode duty only, shall be inspected and subjected to routine service on a
three-monthly basis in accordance with Table 13.4.1.2.
TABLE 13.4.1.2
THREE-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF
MECHANICAL SERVICES—FANS AND MOTORS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Obstructions CHECK there are no physical obstructions likely to
impede performance.
1.2 Noise, CHECK motor and all bearings for noise,
overheating and overheating and excessive vibration.
vibration
1.3 Flexible CHECK flexible connections, where fitted, for
connections leaks, tearing or fraying.
1.4 Fan belts (wear) CHECK fan belts for wear.
1.5 Guards and other CHECK for satisfactory condition.
safety features
1.6 Bearings CHECK lubrication of bearings.
1.7 Fan belts (tension) CHECK for correct tension.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
NOTE: Diagnostic procedures or remote monitoring are an acceptable alternative to sensory inspection such as sight,
touch, hearing or smell. This alternative is particularly applicable where sensory inspection is dangerous or not
practicable.
TABLE 13.4.1.3
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF
MECHANICAL SERVICES—FANS AND MOTORS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Three-monthly COMPLETE all three-monthly service activities
service (see Table 13.4.1.2.)
2.2 Pulley wheels CHECK pulley wheels for alignment and couplings for
and couplings alignment and tightness.
2.3 Casing guards CHECK casing, guards and impeller for corrosion.
and impeller
2.4 Electrical CHECK electrical connections, isolators and terminal
box.
NOTE: Diagnostic procedures or remote monitoring are an acceptable alternative to sensory inspection such as sight,
touch, hearing or smell. This alternative is particularly applicable where sensory inspection is dangerous or not
practicable.
TABLE 13.4.1.4
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
FIRE DAMPERS AND SMOKE DAMPERS
Records
Item No. Item Action required and pass/fail requirement
Result Pass/Fail Comments
MECHANICAL AND INTUMESCENT FIRE DAMPERS
3.1 Obstruction— CHECK and ensure that the fire damper is in place,
Mechanical open and free from obstruction (see Notes 1 and 2).
dampers
3.2 Operation— For mechanical fire dampers, remove or release the
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Records
Item No. Item Action required and pass/fail requirement
Result Pass/Fail Comments
3.11 Corrosion CHECK smoke dampers and casings for corrosion,
accumulation of dust, which may prevent future
operation or affect the overall integrity. The extent of
corrosion shall not impede damper operation or
prevent it remaining in place until the next inspection
(5 years) (see Notes 1, 2 and 5).
3.12 Fail-safe ENSURE damper moves to its fail-safe position on
operation removal of power source.
3.13 Tampering and CHECK for signs of tampering or modifications. The
modifications responsible entity shall confirm that modifications
comply with the manufacturer’s requirements or a
registered testing authority’s confirmation of
operation.
NOTES:
1 Inspect 20% of the fire dampers annually so that all dampers have been inspected by the end of the fifth year.
Tagging, labelling or a logbook is necessary for verification.
2 Where significant numbers of dampers fail or are unable to close, inspect all dampers within the next twelve-month
period. A failure rate in excess of 10% of the 20% tested is regarded as significant.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
3 For intumescent fire dampers, checks for obstruction and corrosion (internal and external) may be carried out by
remote visual inspection, using optical viewing equipment or high-resolution cameras. These techniques may be
applied to minimize access requirements for checking.
4 For intumescent dampers, where testing shows obstructions will not adversely affect their performance in fire
conditions, routine service in accordance with Item 3.3 should be waived by the approval authority. Such testing
should consider—
(a) rubbish that could burn before closure and be transmitted downstream to breach the damper’s integrity;
(b) accumulation of rubbish between slats, to prevent complete closure; or
(c) compromising of a ‘collar style’ fire damper by a lump of timber or cable.
5 Corrosion may adversely affect the operation of the damper or its capability to remain in the fire-resistant structure.
13.4.1.5 Air control dampers—Recycle air, relief air, smoke spill and outdoor air—Six-monthly
Air control dampers for recycle air, relief air, smoke spill and outdoor air shall be inspected and
subjected to a routine service on a six-monthly basis in accordance with Table 13.4.1.5.
NOTE: These dampers are typically used in central plant smoke control systems. They have a single fire
mode function, which corresponds to their failure position. For definitions of recycle air, relief air and
outdoor air damper, as well as tables specifying their operation, see AS/NZS 1668.1.
TABLE 13.4.1.5
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AIR CONTROL DAMPERS—RECYCLE AIR, RELIEF AIR, SMOKE SPILL
AND OUTDOOR AIR
Records
Item No. Item Action required and pass/fail requirement
Result Pass/Fail Comments
4.1 Operation CHECK that the damper is capable of operating from
fully open to fully closed, and is clear of obstructions.
Where the damper is not required to fully open or close,
check that it is capable of operating between maximum
and minimum positions.
NOTE: Increase frequency to three-monthly if dampers
are dedicated to fire mode duty only and are exposed
to the corrosive effects of exterior air.
13.4.1.6 Air control dampers—Recycle air, relief air, smoke spill and outdoor air—Yearly
Air control dampers for recycle air, relief air, smoke spill and outdoor air shall be inspected and
subjected to a routine service on a yearly basis in accordance with Table 13.4.1.6.
NOTE: Air control dampers are typically used in central plant smoke control systems. They have a single
fire mode function, which corresponds to their failure position. For definitions of recycle air, relief air and
outdoor air damper, as well as tables specifying their operation, see AS/NZS 1668.1.
TABLE 13.4.1.6
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AIR CONTROL DAMPERS—RECYCLE AIR, RELIEF AIR, SMOKE SPILL
AND OUTDOOR AIR
Records
Item No. Item Action required and pass/fail requirement
Result Pass/Fail Comments
5.1 Six-monthly COMPLETE all six-monthly service activities as
service listed in Table 13.4.1.5.
5.2 Fire mode ENSURE damper(s) moves to its fire mode position
position upon removal of power source.
5.3 Leakage CHECK that there is no excessive leakage past
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.1.7
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AIR CONTROL DAMPERS—SUPPLY, RETURN AND EXHAUST AIR
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
6.1 Operation CHECK that the damper is capable of operating from
fully open to fully closed, and is clear of obstructions.
Where the damper is not required to fully open or
close, check that it is capable of operating between
maximum and minimum positions.
NOTE: Increase frequency to three-monthly if
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.1.8
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AIR CONTROL DAMPERS—SUPPLY, RETURN AND EXHAUST AIR
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
7.1 Six-monthly COMPLETE all six-monthly service activities as
service listed in Table 13.4.1.7.
7.2 Power failure ENSURE damper(s) moves to its required failure
position mode position upon removal of power source.
7.3 Leakage CHECK that there is no excessive leakage past
dampers when in the closed position (only where
dampers are required to close fully).
7.4 Bearings CHECK linkage and damper bearings.
7.5 Corrosion CHECK dampers for corrosion.
NOTE: Corrosion may adversely affect the
operation of the damper.
7.6 Air leaks If motors are pneumatic, CHECK for air leaks in the
air lines and connections.
TABLE 13.4.1.9
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AUTOMATIC SMOKE AND HEAT VENTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
8.1 Control panel CHECK air supply and control panel for signs of
damage.
8.2 Power supply CHECK power supply to control panel.
8.3 Air filter CHECK air filter and drain fluid.
8.4 Air pressure CHECK system air pressure.
8.5 Battery CHECK battery backup supply where power is
required to operate vents.
8.6 Battery function CHECK operation under mains failure condition.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
8.7 Obstruction CHECK and ensure that the vents and all
components such as pulleys, hinges, latches,
cables, etc. are free from obstruction and capable
of operation.
TABLE 13.4.1.10
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
AUTOMATIC SMOKE AND HEAT VENTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
9.1 Six-monthly COMPLETE all six-monthly service activities as
service listed in Table 13.4.1.9.
9.2 Control panel CHECK air supply and control panel for signs of
damage.
9.3 Power supply CHECK power supply to control panel.
9.4 Air filter CHECK air filter and drain fluid.
9.5 Air pressure CHECK system air pressure.
9.6 Battery CHECK battery backup supply where power is
required to operate vents.
9.7 Battery function CHECK operation under mains failure condition
9.8 Obstruction CHECK and ensure that the vents and all
components such as pulleys, hinges, latches,
cables, etc. are free from obstruction and capable
of operation.
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
9.9 Vents CHECK vents for damage, wear or corrosion.
9.10 Drain holes and CHECK drain holes and internal drain channels are
channels clear.
9.11 Dust covers CHECK ram dust covers are in place.
9.12 Operation CHECK manual/automatic operation and operating
time of system.
9.13 Fusible links REPLACE any fusible release links if coated with
paint.
9.14 Fusible links REPLACE all fusible links throughout the building
every 25 years from the date of manufacture.
TABLE 13.4.1.11
SIX MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
FIRE CURTAINS AND SMOKE CURTAINS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
10.1 Operation CHECK there are no physical obstructions likely to
impede operation. RECORD any changes or
additions to the surrounding area.
10.2 Manual CHECK manual deployment of curtain via switch at
operation control panel.
10.3 Curtain fabric CHECK for damage to curtain fabric.
10.4 Guide tracks CHECK for damage and confirm the integrity of
(where fitted) side tracks, to ensure correct operation.
10.5 Electrical (a) CHECK mains power input.
tests—Power
(b) CONFIRM correct display and LED
supply unit
notification.
(PSU)
(c) CHECK the battery charger outputs.
(d) CHECK the control voltage being supplied
from the PSU to the MCU.
(e) CHECK the permanent d.c. power supplied
from the PSU to the MCU (where applicable).
NOTE: Curtains that deploy below 2.5 m from floor level should be checked at least monthly, to ensure that the
area underneath the curtain is clear of obstructions.
TABLE 13.4.1.12
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
FIRE CURTAINS AND SMOKE CURTAINS
Item
Item Action required and pass/fail requirement Records
No.
11.1 Six-monthly COMPLETE all six-monthly service activities, as
service listed in Table 13.4.1.11.
11.2 Top limit (a) CHECK bottom bar and capping (where
applied) positioning in relation to the ceiling.
Adjust where necessary.
(b) CONFIRM that the curtain performs the soft
ascent function (where fitted).
11.3 Bottom limit CHECK that the bottom limit position is closing
to the correct position.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
11.4 Operating CHECK the ascent and descent speeds against the Ascent
speed approved design. RECORD results and adjust if ………..s
necessary. Descent
………..s
11.5 Automatic CHECK automatic deployment of curtain via
operation alarm signal activation.
11.6 Fail-safe CHECK gravity fail-safe or other fail-safe
operation deployment of curtain by disconnecting all power
sources to all controls.
11.7 Battery REPLACE batteries that are more than two years Date last
function old. replaced
11.8 Electrical (a) CHECK mains power input
tests—Motor (where applicable).
control card
(b) CONFIRM correct display and LED
(MCC)
notification.
(c) CHECK the transformer outputs
(where applicable).
(d) CHECK the control voltage being supplied
from the PSU to the MCC.
(e) CHECK the permanent d.c. power supplied
from the PSU to the MCC (where applicable).
(f) CHECK the motor brake voltage.
(g) CHECK the motor drive voltage.
(h) CHECK the motor stall-out function
(where fitted).
11.9 Light warning CHECK that the light warning unit flashes with
(where fitted) the correct intensity when required.
11.10 Audible CHECK that the local audible warning system is
warning distinctly audible in the vicinity of the curtain.
(where fitted)
(continued)
Item
Item Action required and pass/fail requirement Records
No.
11.11 Obstruction CHECK that the obstruction warning system
warning activates the appropriate warning system when the
(where fitted) curtain is obstructed for more than the required
duration.
11.12 Split/dual drop (a) CHECK the half drop height.
delay (where
(b) CHECK the hold time at the half height
fitted)
position.
(c) CHECK that the curtain closes when
activated by the second alarm source (dual
drop only).
11.13 Emergency CHECK that the curtain retracts temporarily when
retract (where the retract button is pressed.
fitted)
11.14 Fusible link REPLACE all fusible links throughout the
(where fitted) building every 25 years from the date of
manufacture.
Motorized relief openings, windows and shutters shall be inspected and subjected to a routine service
on a six-monthly basis in accordance with Table 13.4.1.13.
TABLE 13.4.1.13
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
MOTORIZED RELIEF OPENINGS, WINDOWS AND SHUTTERS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
12.1 Visual CHECK the control centre (and in the case of
inspection pneumatic actuators, the air supply) for signs of
damage.
12.2 Power supply CHECK the power supply indicator is functioning.
12.3 Air filter— DRAIN any fluid that has accumulated in the air
Pneumatic filter.
systems
NOTE: Solvents should not be used.
12.4 System CHECK system pressure against manufacturer’s
pressure— requirements, and RECORD.
Pneumatic
NOTE: The frequency of filter inspection and
systems
service could vary depending on usage and the
quantity of supplied air. Fluid should be drained
from the filter bowl before fluid reaches the filter
element.
12.5 Battery CHECK battery backup supply where power is
required to operate system.
12.6 Battery CHECK operation under mains failure condition.
function
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
12.7 Vents (a) REMOVE any foreign matter from the blades.
(b) REMOVE any debris from the internal rain
channel.
(c) CHECK that the drain holes are clear.
(d) CHECK the vents for signs of damage, wear
and tear or corrosion.
(e) ENSURE cylinder ram dust covers are in place.
12.8 Open/close CHECK the manual function by operating the
switch open/close manual switch.
NOTE: Closing times in excess of 20 s should be
investigated.
12.9 Air filter— CLEAN or REPLACE the filter element. If any
Pneumatic damage or fault is discovered, correct immediately.
systems
Motorized relief openings, windows and shutters shall be inspected and subjected to a routine service
on a yearly basis in accordance with Table 13.4.1.14.
TABLE 13.4.1.14
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
MOTORIZED RELIEF OPENINGS, WINDOWS AND SHUTTERS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
13.1 Six-monthly COMPLETE all six-monthly service activities as
service listed in Table 13.4.1.12.
13.2 Vents and air CHECK all vents and connecting air lines to
lines— ascertain unauthorized alterations, damage or
Pneumatic corrosion.
systems
13.3 Fusible release If equipped, CHECK the fusible release links for
links type and temperature rating and replace release links
that have been coated with paint or similar coatings.
13.4 Control centres CHECK all control centres and supply lines for
and supply damage or deterioration.
lines
13.5 Operation ENSURE all relief openings, windows and shutters
operate open and close in accordance with the
system requirements. (Refer Appendix I.)
13.6 Plans ENSURE installation plans include current
information.
13.7 Fusible release REPLACE all fusible links throughout the building
link (where every 25 years from the date of manufacture.
fitted)
TABLE 13.4.1.15
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
ELECTRIC HEATERS—DUCT OR UNIT MOUNTED
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
14.1 Overheating CHECK the outside surface of the heater casing for
discolouration or any indication of overheating.
14.2 Loose CHECK for loose external connections and fittings.
connections
14.3 Loose CHECK for loose internal thermal insulation.
insulation
14.4 Obstructions CHECK the elements for obstructions and
accumulation of foreign matter.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.1.16
MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
KITCHEN EXHAUST SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
15.1 Filters CHECK grease-arresting filters for excessive grease
accumulation.
15.2 Hood and CHECK hood and its exhaust plenum for excessive
plenum grease accumulation.
15.3 Gutters CHECK grease gutters for excessive grease
accumulation.
15.4 Filter CHECK that grease-arresting filters are secured in
(condition) the correct position and undamaged.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.1.17
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
KITCHEN EXHAUST SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
16.1 Monthly service COMPLETE all monthly service activities as
listed in Table 13.4.1.16.
16.2 Hood and plenum CLEAN hood and its exhaust plenum.
16.3 Filter (replace) CHECK for excessive leaks or damage to
grease-arresting filters, and REPLACE as
necessary.
NOTE: Non-metallic grease filters and other
special types have to be replaced at specific
time intervals whether damaged or not. In
these cases, follow manufacturer’s
instructions.
16.4 Duct CHECK duct for accumulated grease and
CLEAN.
TABLE 13.4.1.18
MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
OUTDOOR INTAKES
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
17.1 Fire hazards REMOVE any combustible material from the
vicinity of the intakes.
NOTE: Removal of combustible material from air intakes on a monthly basis may be carried out by non-technical
personnel who are aware of the fire hazards associated with this type of risk.
TABLE 13.4.1.19
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
OUTDOOR INTAKES
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
18.1 Monthly COMPLETE all monthly service activities as listed
service in Table 13.4.1.18.
18.2 Corrosion CHECK intake louvres for corrosion and damage.
18.3 Insect screens CHECK and clean insect screens, replace if
damaged.
18.4 Oil bath filters CHECK to ensure that the oil bath or adhesive
coating is as specified by the manufacturer.
NOTE: Oil bath filters are now obsolete in new
commercial air-conditioning systems, and
adhesive coated filters are uncommon; however, if
such devices are still in service, the oil bath fluid
or adhesive coating should be checked on an
annual basis to ensure that the material is as
specified by the original filter manufacturer and
has a flashpoint not less than 160ºC.
TABLE 13.4.1.20
THREE-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
VARIABLE FREQUENCY INVERTERS (VFIs)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
19.1 Dust and dirt CHECK for dust and accumulated dirt on vents and
circuit boards and clean where necessary.
Where there is evidence of moisture, inspect on a
monthly basis or replace enclosure with one having
an appropriate IP rating.
19.2 Electrical CHECK electrical connections and tighten where
necessary.
19.3 Cooling fans CHECK the operation of all cooling fans.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
NOTES:
1 VFIs may be used to power mechanical services systems that are used for dual duty or dedicated smoke
control purposes. VFIs are electronic devices and are susceptible to breakdown due to dust, moisture
‘tracking’, corrosion, overheating and physical damage and require service to ensure reliable operation in fire
mode.
2 Inspection and preventive maintenance on switchboards should be carried out by a relevant trade-qualified
technician.
TABLE 13.4.1.21
SIX-MONTHLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
VARIABLE FREQUENCY INVERTERS (VFIs)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
20.1 Three-monthly COMPLETE all three-monthly service activities as
service listed in Table 13.4.1.20.
20.2 Damage and CHECK for evidence of damage or overheating and
overheating clean or repair where necessary.
NOTES:
1 VFIs may be used to power mechanical services systems that are used for dual duty or dedicated smoke
control purposes. VFIs are electronic devices and are susceptible to breakdown due to dust, moisture
‘tracking’, corrosion, overheating and physical damage and require service to ensure reliable operation in fire
mode.
2 Inspection and preventive maintenance on switchboards should be carried out by a relevant trade qualified
technician.
TABLE 13.4.1.22
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
VARIABLE FREQUENCY INVERTERS (VFIs)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
21.1 Six-monthly COMPLETE all six-monthly service activities,
service (see Table 13.4.1.21).
21.2 Calibration CHECK calibration and set point of all adjustable
components, including customer settings and correct
if necessary.
21.3 Fire mode CHECK operation of fire-mode override functions
override and correct if necessary.
NOTES:
1 VFIs may be used to power mechanical services systems that are used for dual duty or dedicated smoke
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
control purposes. VFIs are electronic devices and are susceptible to breakdown due to dust, moisture
‘tracking’, corrosion, overheating and physical damage and require service to ensure reliable operation in fire
mode.
2 Inspection and preventive maintenance on switchboards should be carried out by a relevant trade-qualified
technician.
TABLE 13.4.1.23
THREE-MONTHLY, ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
PNEUMATIC COMPRESSOR/RECEIVER STATION
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
22.1 Pressures CHECK cut-in and cut-out pressures and record.
22.2 Overheating, noise CHECK unit for overheating, undue noise and
and vibration excessive vibration.
22.3 Crankcase oil CHECK crankcase oil level and top up as
necessary.
22.4 Pressure-relief CHECK if pressure-relief valves are operating by
valves manually bleeding.
22.5 Condensate drain CHECK and clean auto condensate drain or
actuate manual drain.
22.6 Filter and breather CHECK air intake filter and crankcase breather.
Clean or replace as necessary.
22.7 Belts CHECK belts for wear (if belt drive); adjust
tension or replace as required.
TABLE 13.4.1.24
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
PNEUMATIC COMPRESSOR/RECEIVER STATION
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
23.1 Three-monthly COMPLETE all three-monthly service activities
service (see Table 13.4.1.23.)
23.1 Sump and oil DRAIN and clean sump and replace sump oil.
23.2 Pulley CHECK pulley alignment (if belt drive). Ensure
alignment pulleys are secure on shaft.
23.3 Compressor CHECK compressor holding-down bolts are secure.
bolts
23.4 Pressure vessel CHECK and open pressure vessel; clean and operate
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.1.25
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
MOTOR CONTROL CENTRES
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
24.1 Busbar CHECK for loose busbar connections and cable
connections terminations.
24.2 Wiring and CHECK general condition of conduits, connectors,
switches switches and wiring for any condition likely to
adversely affect their function.
24.3 Contacts and CHECK, clean or replace, as necessary, any faulty
relays contacts or relays.
24.4 Overload CHECK overload ratings against motor nameplate
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
ratings ratings.
24.5 Fuses CHECK circuit protectors (fuses and circuit
breakers) for correct rating.
24.6 Electrical CHECK connections at motors, switchboards and
connections equipment subject to vibration. Retighten cable
terminations as necessary.
24.7 Interpole INSPECT interpole barriers and shrouds where
barriers fitted.
24.8 Cable CHECK and rectify any damaged or faulty exposed
insulation cable insulation.
24.9 Switchboard INSPECT each switchboard internally to ensure it is
clean and free from rubbish.
24.10 Panel seals CHECK panel seals, and rectify if faulty.
24.11 Wiring CHECK and report where wiring diagram(s) are
diagrams considered to be incorrect.
24.12 Earthing CHECK continuity to earth.
24.13 Neutral current CHECK and record neutral current.
NOTE: Inspection and preventive maintenance on switchboards should be carried out by a relevant trade-qualified
technician.
TABLE 13.4.1.26
YEARLY ROUTINE SERVICE SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
POWER SUPPLIES—MAIN SWITCHBOARDS (LOW VOLTAGE)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
25.1 Busbar CHECK for loose busbar connections and cable
connections terminations and retighten any loose connections.
25.2 Wiring and EXAMINE the general condition of conduits,
switches connectors, switches and wiring.
25.3 Contacts and CHECK, clean or replace, as necessary, contacts or
relays faulty relays.
25.4 Interpole INSPECT interpole barriers and shrouds.
barriers
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
13.4.1.27 Fire fan control panel (FFCP) and fire indicator panel (FIP)
The fire fan control panel (FFCP) and fire indicator panel (FIP) shall be subjected to routine service
in accordance with Section 6 of this Standard.
Item
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.2.3
YEARLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
FIRE-ISOLATED EXIT PRESSURIZATION SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Three-monthly COMPLETE all three-monthly test activities, as
tests listed in Table 13.4.2.2.
2.2 Simulation SIMULATE a fire/smoke situation from any device
(from Detector) such as a sprinkler, heat of smoke detector, to
effect operation of the pressurization and all other
systems required to operate in fire mode.
CHECK that the following parameters meet the
performance requirements (see Appendices H and
I, and Notes 1 and 2).
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.2.4
THREE-MONTHLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SYSTEM CHANGEOVER UNDER FIRE CONDITION
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Simulation SIMULATE by activation from FIP, the fire/smoke
(from FIP) situation (for each system or zone where relevant),
required to effect changeover from normal mode to
fire mode or shutdown as appropriate. Check fans,
dampers and indicator lamps operate in fire mode as
documented (see Appendices H and I).
NOTES:
1 The purpose of a simulated testing routine is to
check the functioning of the air-handling
changeover system and not the detectors
themselves. The recommended practice in this
case is to simulate activation of the system by
initiating the fire alarm via the switch in the
FIP.
2 This changeover test is initiated in the fire panel
to verify the integrity of the interface between
fire and mechanical systems.
3 Verification of fan or damper operation may use
elementary testing procedures; e.g. hearing fan
start, observation of indicator lamp change of
status, feeling of air movement across doorway,
grille, duct, etc.
3.2 Revert to SWITCH system back to ‘normal’ and check that all
normal equipment and indicator lamps are in the correct
non-fire mode (see Appendices H and I).
TABLE 13.4.2.5
YEARLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SYSTEM CHANGEOVER UNDER FIRE CONDITION
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
4.1 Three-monthly COMPLETE all three-monthly test activities as listed
tests in Table 13.4.2.4.
4.2 Simulation CONDUCT a simulation of a fire/smoke situation
(from (for each system or zone where relevant) to effect
Detector) changeover from normal mode to fire mode or
shutdown as appropriate.
CHECK fans, dampers and indicator lamps operate in
fire mode (see Appendices H and I).
Tests required in Items 4.4, 4.5 and 4.6 are carried
out during this simulation test (see Notes 1 and 2).
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
4.3 Fans start and OPERATE the manual switches at the FFCP. Check
stop at Fire fan that fans start and stop and dampers, if applicable,
control panel open and close as documented (see Appendices H
(FFCP) and I).
4.4 System Where supply air systems are fitted with a smoke
shutdown detector(s), check system shuts down when the
detector is automatically activated as documented
(see Appendices H and I).
Verify re-start when smoke clears and verify that the
FFCP manual override ‘ON’ operates while the fan
has shut down due to supply smoke detection.
4.5 Zone smoke CHECK zone smoke control system performance Record all
control criteria as documented (see Appendices H and I). differential
pressures on a
separate sheet
4.6 Fire curtains CHECK to ensure that the integrity and leakage
and smoke performance are not compromised by operation of the
curtains mechanical systems in fire mode.
NOTES:
1 The purpose of an automatic testing routine is to check the functioning of the air-handling changeover system by the
activation of a field device (detector or sprinkler). The recommended practice in this case is bringing a heat, flame
or smoke source to a detector or operating a sprinkler valve to activate flow/pressure switches.
2 This changeover test is initiated in the field device to verify the end-to-end integrity of the interface between field
device and mechanical systems (see Clause 1.12).
3 Arrangements should be made for the responsible entity to be notified whenever an automatic activation test is to be
conducted to advise that the alarm will sound and to advise that the system may be inoperative for a certain time.
4 For the purpose of this test, each compartment should be sequentially placed in fire mode.
5 Where there have been no changes to the building structure, internal layout and air-handling system in the period
since the last test, testing may be limited to simulating fire mode in selected compartments whose performance is at
the extremes of the acceptance criteria.
6 When testing is carried out on selected compartments, it is recommended that the same compartments be selected for
each test.
7 These routines are to ensure satisfactory changeover and operation of the air-handling installation on operation of
fire alarm. The service of the equipment such as fans, motors, fire dampers and similar are covered under the
routines for the individual items.
TABLE 13.4.2.6
THREE-MONTHLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SMOKE EXHAUST SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
5.1 Simulation SIMULATE a fire/smoke situation by activation from
(from the FIP) the FIP, to effect operation of the smoke exhaust
system and all other systems required to operate in fire
mode. Check fans, dampers, automatic doors (if part of
the approved design) and indicator lamps operate in
fire mode as documented (see Appendices H and I).
Check for excessive noise and correct movement of
air.
5.2 Revert to SWITCH all systems back to ‘normal’ and check that
normal all equipment and indicator lamps are in the correct
non-fire mode (see Appendices H and I).
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
NOTES:
1 The purpose of this simulation testing routine is to check the functioning of the smoke exhaust system and not the
detectors themselves. The recommended practice in this case is to initiate the fire alarm via the switch in the FIP.
2 This test is initiated in the fire panel to verify the integrity of the interface between fire and mechanical systems.
3 Verification of operation may use elementary testing procedures, e.g. hearing fan start, observation of indicator lamp
change of status, etc. and the use of elementary sensing methods is sufficient to verify noise and air movement, e.g.
operator’s judgement of sound, telltale ribbon in doorway, etc.
TABLE 13.4.2.7
YEARLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SMOKE EXHAUST SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
6.1 Three-monthly COMPLETE all three-monthly test activities as
tests listed in Table 13.4.2.6.
6.2 Partial CONDUCT a simulation of a fire/smoke situation
simulation from any device such as a sprinkler, heat or smoke
detector, to effect operation of the smoke exhaust
system and all other systems required to operate in
fire mode. Check fans, dampers, automatic doors (if
part of the approved design) and indicator lamps
operate in fire mode as documented (see
Appendices H and I).
(continued)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
CHECK:
(a) Exhaust airflow rate from the space.
(b) Indicator lamps change status when fan starts
or stops.
(c) That operation of the manual switch provided
for fire brigade personnel starts and stops
smoke exhaust fans.
(d) The maximum noise level in the space.
NOTE: In some installations maximum noise
criteria may not be specified.
6.3 Revert to SWITCH all systems back to ‘normal’ and check
normal that all equipment and indicator lamps are in the
correct non-fire mode (see Appendices H and I).
TABLE 13.4.2.8
YEARLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SYSTEM SHUTDOWN
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
7.1 Simulation SIMULATE a fire/smoke situation from any device
(from detector) such as a sprinkler, heat or smoke detector, to effect
shutdown of all mechanical ventilation systems not
required to operate in fire mode.
CHECK all systems required to shut down are not
operating (see Appendices H and I).
TABLE 13.4.2.9
YEARLY TEST AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SMOKE DAMPERS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
8.1 Normal ENSURE all dampers operate open and close in
operation accordance with the system requirements (see
Appendices H and I).
CHECK all systems required to shut down are not
operating (see Appendices H and I).
TABLE 13.4.3.2
YEARLY SURVEY AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
ACTIVE FIRE AND SMOKE CONTROL SYSTEMS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 System CHECK for physical impediments that may impair
safe operation of smoke control systems comprising
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 13.4.3.3
YEARLY SURVEY AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
MOTORIZED RELIEF OPENINGS (WINDOWS AND SHUTTERS)
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Draught CHECK draught curtain areas to ensure there have not
curtains— been any major alterations or additions that could
Frames inhibit their function.
forming roof
CHECK inlet openings to ensure there have not been
compartments
any major structural alterations that could inhibit their
function.
2.2 Inlet openings CHECK inlet openings to ensure there have not been
any major structural alterations that could inhibit their
function.
TABLE 13.4.3.4
YEARLY SURVEY AND RECORDS SCHEDULE
FIRE AND SMOKE CONTROL FEATURES OF MECHANICAL SERVICES
SMOKE RESERVOIRS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
3.1 Changes CHECK to ensure that changes to the smoke
reservoirs have not been made, such as the addition of
light fittings or openings created, which would
otherwise compromise the integrity of the system.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
S E C T I O N 1 4 E M E R G E N C Y P L A N N I N G I N
FACIL ITIES
14.1 GENERAL
This Section sets out requirements for the inspection and test of the emergency plan and associated
elements developed in accordance with AS 3745, for the controlled evacuation of facilities such as
buildings, structures and workplaces.
NOTE: Other emergency evacuation services and procedures are covered in Appendix J.
This Section shall be read in conjunction with Section 1.
Clause 1.16.
14.2.3 Reports
Critical defects and yearly condition reports shall be prepared and distributed in accordance with
Clause 1.17.
14.2.4 Baseline data
Baseline data shall be in accordance with Clause 1.8.
NOTE: For guidance on and examples of baseline data, see Appendix C.
14.2.5 Prior arrangements
Prior to testing the emergency evacuation systems, the emergency control organization shall be
advised.
14.3 FREQUENCY
For the purpose of this Section, the following frequencies shall apply:
(a) Six-monthly.
(b) Yearly.
TABLE 14.4.2
SIX-MONTHLY INSPECTION, TEST AND RECORDS SCHEDULE
CRITICAL EMERGENCY EVACUATION SYSTEM ELEMENTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 Emergency INSPECT the ECO list and check for compliance
control with the emergency plan.
organization
(ECO)
1.2 Emergency INSPECT the emergency evacuation equipment
evacuation and check for compliance with the emergency plan.
equipment
1.3 Training INSPECT training records and check for
compliance with the emergency plan.
1.4 Emergency TEST the ECO for relevance to the facility by
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE 14.4.3
YEARLY INSPECTION, TEST AND RECORDS SCHEDULE
CRITICAL EMERGENCY EVACUATION SYSTEM ELEMENTS
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
2.1 Emergency plan INSPECT the emergency plan and check for
relevancy to the facility.
2.2 Evacuation INSPECT evacuation exercise records and check
exercise for compliance with the emergency plan.
APPENDIX A
REFERENCED DOCUMENTS
(Normative)
The following documents are referred to in this Standard.
AS
1668 The use of ventilation and airconditioning in buildings
1668.2 Part 2: Ventilation design for indoor air contaminant control
1668.3 Part 3: Smoke control systems for large single compartments or smoke reservoirs
1670 Fire detection, warning, control and intercom systems—System design, installation and
commissioning
1670.1 Part 1: Fire
1670.4 Part 4: Sound systems and intercom systems for emergency purposes
1674 Safety in welding and allied processes
1674 Part 1: Fire precautions
1682 Fire Dampers
1682.1 Part 1: Specification
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
AS
4029 Stationary batteries (series)
4265 Wheeled fire extinguishers
5062 Fire protection for mobile and transportable equipment
AS ISO
14520 Gaseous fire-extinguishing systems—Physical properties and system design
14520.1 Part 1: General requirements (ISO 14520-1:2006, MOD)
AS/NZS
1221 Fire hose reels
1668 The use of ventilation and airconditioning in buildings
1668.1 Part 1: Fire and smoke control in multi-compartment buildings
1841 Portable fire extinguishers
1841.2 Part 2: Specific requirements for water type extinguishers
1841.3 Part 3: Specific requirements for wet chemical type extinguishers
1841.4 Part 4: Specific requirements for foam type extinguishers
1841.5 Part 5: Specific requirements for powder type extinguishers
1841.6 Part 6: Specific requirements for carbon dioxide type extinguishers
1841.7 Part 7: Specific requirements for vaporizing liquid type extinguishers
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
APPENDIX B
ROUTINE SERVICE PROCESS
(Informative)
This Appendix provides an explanation of the process of routine service covered by this Standard (see
also Clause 1.7.2).
Table B1 provides an explanation of the three main elements contained in Figure 1.7, as follows:
(a) System design, installation and commissioning.
(b) Routine service (this edition of AS 1851).
(c) Regulation and application of this Standard.
TABLE B1
ROUTINE SERVICE PROCESS
Reference
from Stage Element Explanation
Figure 1.7
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
[1] 1 System design, Commissioning This Standard is predicated on a satisfactory completion of system
installation and design and installation, which is confirmed during commissioning.
commissioning Only then can the routine service (maintenance) process
commence.
[2] Baseline data Use of baseline data is an essential component in ensuring the
established system continues to perform in accordance with the approved
design (see Clause 1.8).
[3] 2 AS 1851 Routine service This Standard addresses the routine service of fire protection
Routine schedules systems and equipment in accordance with Clauses 1.1 and 1.2 of
servicing this Standard. Common requirements pertaining to all systems and
equipment are covered in Section 1; Sections 2 through to 14
covers the individual systems and equipment such as sprinklers,
alarms, hydrants and portable fire extinguishers. The schedules
(tables) in Sections 2 to 14 are structured on a frequency basis and
cover inspection, test, survey and routine service (maintenance).
The intent of this Standard is to also maintain reliability of system
or equipment operation from one service period to the next.
[4] Identify and report Where a routine service activity failure is identified, the service
activity failures provider is to record it and indicate whether the failure represents
a critical defect, a non-critical defect or a non-conformance, and
recommend rectification (see Clause 1.18).
[5] Yearly service The objective of this Standard is to confirm that all systems and
schedules equipment function correctly and are able to perform in
accordance with the approved design.
NOTE: Also includes lower frequency routines such as five-
yearly, etc.
[6] Yearly condition An important provision in the Standard is the need to keep records
report of the service work carried out as evidence that the systems and
equipment are fit to fulfil the intended purpose.
When the service work has been completed for each system and
equipment, the consolidated reports for each system and
equipment form evidence that the service routine has been
satisfactorily completed or that failures have been noted or
rectified.
(continued)
TABLE B1 (continued)
Reference
from Stage Element Explanation
Figure 1.7
[7] 3 Regulation and Annual compliance It is a regulatory obligation in most States and Territories for
application statement owners to provide an annual compliance statement that the safety
measures in their premises satisfy the performance requirements of
the approved design. The yearly condition report for fire
protection systems and equipment provide evidence to support that
obligation. It is not intended that the yearly condition report will
take the place of regulatory yearly statements/reports.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
APPENDIX C
BASELINE DATA
(Informative)
C1 GENERAL
This Appendix provides examples of baseline data for some fire protection systems and equipment
and may be used as a guide to generate baseline data for other systems.
Baseline data is necessary to determine the performance benchmarks to be assessed in order to fulfil
the requirements of this Standard. The baseline data should be permanently recorded and be readily
available at the premises.
Where the baseline data is not available, it should be re-established at the commencement of routine
service in order to determine the performance benchmarks required by this standard. Alternatively the
baseline data and performance benchmarks may be established during the first year of the application
of this Standard.
C2.1 General
The following are examples of baseline data information:
(a) A statement detailing the design Standard of the system including date of publication and any
approved exceptions.
(b) Documentation required by the approved design such as commissioning documentation as
detailed in the relevant system design, installation and commissioning Standard.
(c) Table of any changes to the approved design nominating the date, scope of the change, and
person(s) performing the change.
(d) Date of initial system installation.
(e) Systems interface diagram.
(f) Cause and effect statement for each system interface function.
(g) Block plan.
(h) Hydraulic design data (sprinkler, hydrant, deluge, etc.)—duty points.
(i) Pressure gauge schedule.
(j) Water supply stop valve list.
(k) Fire pump(s) rating data.
(l) Fire pump(s) driver rating(s) (diesel, electric) data.
(m) Fire pump(s) commissioning test data.
(n) Tank capacity data.
(o) Tank infill flow requirements.
(p) Pressure-relief valve settings.
(q) Battery(s) capacity, charge rate, voltage, etc.
(i) If applicable, trunk main pressure maintenance (jockey) pump cut-in and cut-out pressures.
(j) If applicable, installation pressure maintenance (jacking) pump cut-in and cut-out pressures.
(k) If applicable, installation air pressure (dry systems).
(l) If applicable, installation pressure-reducing valve—
(i) upstream pressure;
(ii) downstream (reduced) pressure; and
(iii) relief valve operating pressure.
TABLE C1
TYPICAL SPRINKLER PRESSURE GAUGE SCHEDULE
Pressure
Items kPa
Normal Minimum Maximum
Installation 1 850 750 850
Installation 2 850 750 850
Below stop valve (combined main) 850 750 850
Town main 1 (primary water supply) 500 300 600
Town main 2 (secondary water supply) 500 300 600
Electric pump delivery pressure at shut-off (churn without 900 700 1000
water flow)
Diesel pump delivery pressure at shut-off (churn without 600 600 600
water flow)
System pressure-reducing valve (upstream) 700 600 1000
System pressure-reducing valve (downstream) 700 600 800
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Opening Closing
Pressure-relief valves
kPa kPa
System pressure-reducing valve—relief valve setting 750 700
Pump pressure-relief valve 1000 950
C2.3 Sprinkler and hydrant system valve list (see Table C2)
C2.3.1 General
For an automatic sprinkler or hydrant system to perform its function—control a fire or provide
sufficient water for fire brigade operations–it must have the full flow and pressure from the water
supply for which it was designed. This can only happen if all the water supply valves between the
water source through to the sprinklers or hydrants are fully open. If any valve along this chain is
either fully or partially closed, then the automatic sprinkler or hydrant system may be rendered either
totally inoperative or severely compromised.
It is critical that every valve along this chain is firstly identified on the block plan, provided with an
appropriate tag, sign or other distinctive feature to ensure quick and easy identification on site, and
numbered and added to the facilities valve list, an example of which is defined in Paragraph C2.3.2.
C2.3.2 Valve list
Each valve on the valve list should have a unique identification number (typically starting from the
water source). Its location shall be stipulated to enable the service provider to easily and quickly find
the valve. Its function (for instance main stop valve system number 4, or underground sectional valve,
or third floor auxiliary valve, etc.), should be specified to clearly identify the valve from others that
may be in the same location.
Valves may be monitored and this should be identified since additional testing of this function is
required. All these critical valves are required to be locked in the open position, if not locked or locks
are missing, this would be an indicator of recent use or potential tampering.
Where a valve is found closed for no apparent reason (no tag or known maintenance work being
carried out), the service provider should notify the owner or their agent immediately, investigate the
condition of the water supply, hydrant or sprinkler system involved to determine if there is a valid
reason for the system being shut down. If such investigation shows no valid reason, the valve should
be slowly opened while checking for sound of significant water flow through the valve. If such water
flow is detected it could indicate a potential problem requiring the shutting of the valve and further
investigation to find the cause and subsequent rectification.
Whenever a valve is found fully or partially shut, the owner or their agent should be notified, and
comments written down specifying the action taken, results of any investigations and the current
status of the valve and system.
A valve is considered partially shut if it is more than ⅛ closed.
TABLE C2
TYPICAL SPRINKLER AND/OR HYDRANT SYSTEM VALVE LIST
Date: .............................................................
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Valve
No. Function/System Monitored Locked Open Shut
location
TABLE C3
TYPICAL EQUIPMENT REGISTER FOR EQUIPMENT SERVICED
IN ACCORDANCE WITH AS 1851—2012 EQUIPMENT TYPE
Manufacturer/
Equipment Area/ Type/Size or
Type Description Supplier
identification No. Location capacity
(optional)
Example 1 (Passive)
001 Fire door L1 Stair Sliding door 2 h motorized
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Example 2
001 Fire extinguisher L1 passage way Water 9L
002 Fire extinguisher L2 Stair 1 Powder 2.33 kg
(2A40B)
003 Fire blanket Kitchen 1 m × 1.2 m
Example 3
001 Fire hose reel L1 Stair 2 36 m length
NOTE: Details shown in the above example are to be inserted as applicable to the equipment type serviced.
APPENDIX D
SYSTEMS INTERFACE TESTING
(Informative)
D1 GENERAL
This Appendix sets out the recommended procedures for the concurrent ‘end-to-end’ test of the
system interfaces to confirm that they operate in accordance with the approved design.
This Appendix should be read in conjunction with Clauses 1.1 to 1.17. The baseline data includes the
system interface diagram and the relevant cause and effect statements which should be verified as set
out in a test schedule.
NOTES:
1 The interface test is not intended to be a commissioning test of each system, but to establish that each
interfaced function operates correctly.
2 A concurrent test of all interfaced systems, as would occur in a fire, is required to ensure that there are
no unwanted interactions between systems or unsustainable electrical loads on systems or system
components.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
D2 PRECAUTIONS
Prior to commencing any interface testing, the following precautions should be carried out:
(a) Ensure that the responsible entity for the coordination of the concurrent attendance of each
person or persons has arranged for the attendance of all persons required to properly conduct the
test.
(b) The precautions detailed in each relevant section of this Standard.
On completion of any procedure, ensure that each control is returned to the condition or state prior to
the test. When any function is left impaired, is disabled or is not restored to ‘normal’, it should be
recorded in the system logbook and the owner or agent should be notified.
D4 TEST PLAN
As most interface configurations are unique to the particular building or facility, a test plan detailing
each step of the interface test procedure should be available to ensure that tests are carried out
consistently and results are adequately documented. The test plan should be based on the procedures
that were used during the commissioning of the systems interfaces.
Where a test plan does not exist, it should be prepared and documented by a competent person or
persons having an understanding of the interface requirements of the approved design.
The test plan should detail the concurrent attendance of persons specializing in each interfaced system
required to achieve the end-to-end test and should include the following:
(a) A list of all interfaced system.
(b) Systematic test procedure detailing the method for conducting each interface test.
(c) List of persons and their responsibilities required to test or verify the function of each interface.
(d) Owner’s responsibilities.
(e) Additional precautions and procedures (e.g. town gas shut-off valves).
(f) Form of test report.
D5 TEST REPORT
An interface test report is a record of each test conducted and should include the following:
(a) A record of the test result for each interface test (pass or fail) and values as applicable.
(b) A record of the name signature of the person responsible to verify the result of each interface
test.
(c) Date and time of the test.
(d) Acceptance signature of the responsible entity’s representative.
(e) Details of any defects identified.
D6 RESULTS
Pass or fail test results for each interfaced system should be recorded in the respective system records
with detailed of results in interface test report.
Recorded test results in accordance with Tables D1 to D7 (see Clauses 1.12 and 1.16) may be
electronically based; however, a hard copy record of the system interface tests should be kept on site
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
and be available at all times (see Clause 7.2.5). The records include names and signatures of all
persons that assessed the compliance of the interfaces to the requirements of the approved design
including the dates when the tests were performed.
Any defects identified in the interface tests should be recorded on the respective system’s yearly
condition report.
The inspection, survey and test schedules defined in Paragraph D7 are examples of test requirements
and reports.
TABLE D1
EXAMPLE OF INTERFACE INSPECTION AND SURVEY SCHEDULE
Item Records
Item Action required and pass/fail requirement
No. Result Pass/Fail Comments
1.1 System’s INSPECT the system’s interface matrix to ensure it is available
interface and legible.
diagram
1.2 Site survey SURVEY the site and ensure that all systems required to be
interfaced are included in the system’s interface matrix.
1.3 Test plan INSPECT the test plan and check that it adequately assesses the
function of any interfaces that have changed or been added since
the interface test was last carried out.
TABLE D2
EXAMPLE OF TEST SCHEDULE—SPRINKLER/DELUGE SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
2.1 Sprinkler test Perform the six-monthly valve or flow switch test as
valve applicable and check the operation of the following
interfaced system as applicable.
2.2 Fire indicator CHECK that sprinkler operation is indicated correctly.
panel
2.3 Fire door CHECK that fire and smoke doors have closed
release correctly (e.g. correct sequencing for double leaf
doors).
2.4 Security door CHECK that security doors have unlocked correctly.
release
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
2.5 Roof vents CHECK that interfaced roof vents open correctly. See
Section 13
2.6 Warning CHECK that warning systems operate correctly.
system
2.7 Plant CHECK that plant shuts down correctly.
shutdown
2.8 Fuel shut-off CHECK that the shut-off valves function.
2.9 Elevator CHECK that the elevator override operates correctly.
override
2.10 Other systems CHECK that other systems operate correctly.
2.11 Fire-isolated CHECK that the fire-isolated exit pressurization
exit operates correctly.
pressurization
system
2.12 Smoke CHECK that the smoke control system operates
control correctly.
2.13 Smoke CHECK that the smoke exhaust operates correctly.
exhaust
2.14 Air-handling CHECK that the air handling system operates correctly.
2.15 Systems faults Simulate faults on each interfaced system and check
that the fault is indicated.
NOTE: This is normally indicated at the fire
indicator panel (CIE.)
2.16 Special CHECK that the special hazards system operates
hazards correctly.
TABLE D3
EXAMPLE OF TEST SCHEDULE—FIRE DETECTION SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
3.1 Detection Initiate appropriate detection devices and controls
device according to test plan and check the correct operation
activation and of the interfaced functions.
manual
NOTE: This test is intended to check that the fire
control
detection system and interfaced system perform in
functions
accordance with the approved cause and effect
statements.
3.2 Pre-action Check that the pre-action sprinkler or deluge system
sprinkler or valve operates correctly.
deluge system
3.3 Fire door Check that fire and smoke doors have closed correctly.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
release
3.4 Security door Check that security doors have unlocked correctly.
release
3.5 Roof vents Check that interfaced roof vents open correctly.
3.6 Warning Check that warning systems operate correctly.
system
3.7 Plant Check that plant shuts down correctly.
shutdown
3.8 Fuel shut-off Check that the shut-off valves operate correctly.
3.9 Elevator Check that the elevator override operates correctly.
override
3.10 Other systems Check that other systems operate correctly.
3.11 Exit Check that the exit pressurization operates correctly.
pressurization
3.12 Smoke Check that the smoke control system operates
control correctly.
3.13 Smoke Check that the smoke exhaust operates correctly.
exhaust
3.14 Air-handling Check that the air handling system operates correctly.
3.15 Alarm Check that additional alarm systems for the hearing
systems for impaired operate correctly.
hearing
impaired
3.16 Paging Check that the paging systems operate correctly.
systems
3.17 Nurse call Check that nurse call systems operate correctly.
systems
3.18 Systems faults Simulate faults on each interfaced system and check
that the fault is indicated at the CIE.
3.19 Special Check that the special hazards system operates
hazards correctly.
D7.4 Smoke alarm and heat alarm system interface test and records
Smoke alarm and heat alarm system interfaces should be tested in accordance with the test plan.
A typical example of a test schedule forming part of a test plan is given in Table D4.
TABLE D4
EXAMPLE OF TEST SCHEDULE—SMOKE ALARM AND HEAT ALARM SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
4.1 Smoke and Initiate appropriate alarms to test plan and check the
heat alarm correct operation of the interfaced functions.
activation
NOTE: This test is intended to check that the fire
detection system and interfaced system perform in
accordance with the approved cause and effect
statements.
4.2 Exit lighting Check that the exit lighting operates correctly.
4.3 Alarm Check that additional alarm systems for the hearing
systems for impaired operate correctly.
hearing
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
impaired
4.4 Other systems Check that other systems operate correctly.
TABLE D5
EXAMPLE OF TEST SCHEDULE—EMERGENCY WARNING SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
5.1 Emergency Ensure that all functions are in the normal state without
warning being isolated or disabled and then manually activate
system the emergency signals according to test plan and check
activation the correct operation of the interfaced functions.
5.2 Shutdown Check that other systems shut down during an
emergency shut-down.
5.3 Alarm Check that additional alarm systems operate correctly.
systems for
hearing
impaired
5.4 Paging Check that the paging systems operate correctly.
systems
5.5 Nurse call Check that nurse call systems operate correctly.
systems
5.6 Other system Check that other systems operate in accordance with
the test plan.
TABLE D6
EXAMPLE OF TEST SCHEDULE—SPECIAL HAZARD SYSTEM
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
6.1 System Simulate the operation of the special hazard system and
operation controls according to test plan and check the correct
operation of the interfaced functions in accordance
with the cause and effect statement.
6.2 Fuel shut-off Check that the shut-off valves operate correctly.
6.3 Dampers Check that the dampers operate correctly.
6.4 Air-handling Check that the air-handling system operates correctly.
6.5 Warning Check that warning systems operate correctly.
systems
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE D7
EXAMPLE OF TEST SCHEDULE—FIRE FAN CONTROL PANELS
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
7.1 Fire fan Ensure that all functions are in the normal state without
control panel being isolated or disabled and then initiate appropriate
(FFCP) detection devices and controls according to test plan
and check the correct operation of the interfaced
functions in addition to those controlled by the fire
detection and alarm system.
7.2 Fire door Check that fire and smoke doors have closed correctly.
release
7.3 Security door Check that security doors have unlocked correctly.
release
7.4 Roof vents Check that interfaced roof vents open correctly.
7.5 Warning Check that warning systems operate correctly.
system
(continued)
TABLE D7 (continued)
Item Records
Item Action required and pass/fail requirement
No. Section Result Pass/Fail Comments
7.6 Plant Check that plant shuts down correctly.
shutdown
7.7 Fuel shut-off Check that the shut-off valves operate correctly.
7.8 Elevator Check that the elevator override operates correctly.
override
7.9 Other systems Check that other systems operate correctly.
7.10 Exit Check that the exit pressurization operates correctly.
pressurization
7.11 Smoke Check that the smoke control system operates
control correctly.
7.12 Smoke Check that the smoke exhaust operates correctly.
exhaust
7.13 Air-handling Check that the air-handling system operates correctly.
7.14 Systems faults Simulate faults on each interfaced system and check
that the fault is indicated at the CIE.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE D8(A)
SITE DETAILS TO BE INTERFACE TESTED—EXAMPLE
TABLE D8(B)
INTERFACED SYSTEMS LIST—EXAMPLE
Interfaced systems Type of interface Persons responsible Contact details Test plan signed off
TABLE D8(C)
DETAILED INTERFACE TESTS—EXAMPLE
From To Test to be performed Expected results Pass/Fail
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
APPENDIX E
YEARLY CONDITION REPORT
(Informative)
Report number:
Period covered:
Responsible entity’s
address:
Premises:
System type:
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Design Standard
applicable:
Statement: I confirm that the system referred to above has been regularly inspected, tested,
maintained and surveyed, where applicable, to Section XX of AS 1851 as per
attached system activity reports for the period XX/XX/XXXX. With the exception
of items detailed below in ‘system defects’, the system has been found to be
functioning correctly and is generally in accordance with the approved design.
System defects:
Non-conformances:
Summary of the
relevant records of
service:
Service provider’s
representative:
Name:
........................................................................................................................
Signature:
................................................................... Date: ......................................
Service provider:
........................................................................................................................
Name:
........................................................................................................................
Address:
........................................................................................................................
APPENDIX F
BATTERY CAPACITY TESTING
(Normative)
based on a loss of 20% of its capacity over the useful life of the battery.
The battery capacity requirement shall be determined as follows:
(a) Determine the quiescent load current (IQ).
(b) Determine the alarm current (IA).
(c) Determine the capacity de-rating factor (FC) of the battery when discharged at the alarm load
rate, taking into account the minimum operating voltage of all connected CIE using the battery
manufacturer’s data. Where more than one CIE is connected to the battery, use the highest
minimum of any of the CIE. A value of 2 for FC is deemed to satisfy these requirements.
(d) The 20 h discharge battery capacity C20 at 15°C to 30°C shall be determined as follows:
C20 = L[(IQ × TQ) + FC (IA × TA)]
where
C20 = battery capacity in Ah at 20 h discharge rate
IQ = total quiescent current
TQ = quiescent standby power source time
FC = capacity de-rating factor
IA = total current in alarm state
TA = alarm load standby power source time
L = compensation factor for expected battery deterioration.
L shall be 1.25 for new batteries and 1.1 for used batteries required to perform for
at least 12 months
Where the load may vary, the worst case average over required period shall be used.
Where the average battery temperature is outside 15°C to 30°C, the battery manufacturer’s data shall
be used to determine any further compensation factor to be applied.
NOTE: This procedure has been derived from AS 1670.1 and AS 1670.4 and satisfies the battery calculations
requirements of previously published Australian Standards for fire alarm and warning systems.
F2 BATTERY TEST
F2.1 General
This test is intended to define a procedure to assist in determining the ability of a battery to satisfy the
approved design.
NOTES:
1 This test is a potentially hazardous process. Appropriate personal protection should be used and a risk
assessment carried out. Any batteries showing any signs of physical damage or defect should not be
tested and should be replaced immediately.
2 Consideration in determining a battery’s ability to perform in accordance with the intended design
should include other factors affecting battery performance such as battery age, environmental conditions,
etc.
This procedure is for a 24 V battery set and is using a minimum test voltage of 21 V (related to the
C20/20 final voltage). For other nominal battery voltages a corresponding minimum test voltage shall
be used.
F2.2 Procedure
The procedure shall be as follows:
(a) Prior to testing, ensure the battery is fully charged with the correct charging voltage.
(b) Set the battery testers to a discharge current of 0.8 × C20/1 A (e.g. A 100 Ah battery is tested at
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
80 A), subtracting the system quiescent current if the test is to be carried out without
disconnecting the battery from the system.
(c) Record the total load current used.
(d) Where the battery is to be tested without being disconnected from the system, isolate the
primary (mains) supply just before the commencement of the battery condition test.
(e) Apply the test load for 25 min or until battery terminal voltage falls to the minimum test voltage
of 21 V (for a 24 V battery set).
NOTE: The battery load tester carries a large current and must be connected as close as practicable to the
battery terminals.
(f) If the battery terminal voltage does not fall below 21 V during the 25 min period record the
final test voltage and note as a pass.
(g) Restore the system to allow the battery to begin to be re-charged.
NOTES:
1 The battery should be allowed to be charged for a minimum of one week before any test that depletes the
battery’s state of charge is carried out.
2 If an individual battery in the set fails the battery condition test, it is recommended that all batteries in
the set be replaced at the same time.
CF2.2 The purpose of this test is to determine that the battery capacity has not deteriorated by
more than 20% of it nominal capacity. If batteries are tested individually and only one fails, it is
highly likely that the others in the set will also fail in the near future.
APPENDIX G
FIRE DETECTOR TESTING
(Normative)
G1 TEST MEDIA
The test medium employed for testing smoke, heat and carbon monoxide fire detectors shall be as
follows:
(a) Heat detectors—a source of heated air is the preferred medium. The temperature of the air shall
be controlled to produce a predictable rate of increase. The upper temperature shall be limited to
a value appropriate to the detector being tested.
NOTE: The use of radiant heat is not recommended. Care should be taken in the use of radiant heat as
the effect on the detector can vary significantly with the collection area the detector presents to the
tester.
(b) Smoke detectors—a source of particulate material that does not contaminate the sensing
chamber or entry screen and which contains particles in the size range appropriate to the
detector.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(c) Carbon monoxide (CO) detectors—a source of gas that does not adversely affect the sensing
element, or entry screen, of the detector and which contains gas appropriate to the detector.
(d) Aspirating smoke detection systems that do not excessively contaminate, impact the test result
or be of a nature that adheres to the internal surfaces of the aspirating smoke detector pipe
system.
NOTE: The emitted medium for sensitivity testing of smoke detectors (b) and carbon monoxide detectors (c)
should be controlled so as to produce a predictable concentration.
APPENDIX H
MECHANICAL SERVICES—DOCUMENTATION AND SKILLS
(Informative)
H1 DOCUMENTATION
H1.1 General
Documentation covering routine service records required to implement the service program and
sequentially record the service carried out (see Clause 1.16) should include the following:
(a) A schedule of essential functionality and performance requirements.
(b) Operating and routine service manuals.
(c) Routine service schedule.
(d) Routine service records.
(e) Plant register.
(f) Plant history sheet.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
(vi) Manual override control from the fire fan control panel (FFCP)—ON and OFF.
(vii) Fan or damper indicator lamps on the FFCP.
(viii) Operation of any related mechanical system, incorporated in the mechanical services
system design criteria, that operates in fire mode.
(c) Provision to describe specific mechanical services system function linked to specific fire alarm
zone reference, and to record correct operation of fire/mechanical services system function.
(d) Provision to record that the appropriate fire systems and mechanical services system personnel
have both been involved in the checking/test process, so that the fire/mechanical services
system interface can be seen to have been demonstrated (see Clause 1.12).
(e) Provision to demonstrate that the essential mechanical services systems are capable of
performing to the Standard to which they were originally installed.
CH1.2(a) As it is critical that this document be available at all time to building management, the
document should ideally be associated with the annual testing documentation, rather than being
archived in design files, hence making it difficult to find.
H1.3 Operating and routine service manuals
Operating and routine service manuals should include at least the following:
(a) The performance criteria for all fire and smoke control features of the mechanical services
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Skill set A comprises the skills applicable to tables referenced in Clause 13.4.1 and include the
following:
(a) Relevant mechanical services trades qualifications from a recognized technical institution.
(b) Demonstrated knowledge of fire and smoke control systems covered by this Standard,
AS/NZS 1668.1, AS 1668.3, AS 1682.1, AS 1682.2, AS 2665 and the relevant parts of the NCC.
(c) Minimum of three years’ experience in maintenance, commissioning, inspection or testing of
fire and smoke control systems.
H2.3 Skill set (B)
Skill set B comprises the skills applicable to tables referenced in Clauses 13.4.2 and 13.4.3 and
include the following:
(a) Demonstrated knowledge of fire and smoke control systems contained in this Standard,
AS/NZS 1668.1, AS 1668.3, AS 1682.1, AS 1682.2, AS 2665 and the relevant parts of the NCC.
(b) A relevant engineering degree from a recognized university, together with a minimum of
five years’ experience in design, installation, commissioning or inspection and testing of fire
and smoke control systems.
or
A relevant certificate or associate diploma in mechanical services engineering from a
recognized technical institution together with a minimum of five years’ experience in design,
installation, commissioning or inspection and testing of fire and smoke control systems.
or
Minimum of five years’ experience in commissioning or inspection and testing of fire and
smoke control systems, with a relevant trade qualification.
APPENDIX I
MECHANICAL SERVICES—GUIDANCE
(Informative)
I1 BASELINE DATA
Refer to Appendix C for guidance and examples on baseline data.
human error is usually addressed by training and education of responsible staff, monitoring of
equipment status or regular inspection and testing.
When mechanical services equipment has been designed to provide fire and smoke control, the
relative likelihood of the first two of these failure modes will depend on the pattern of usage.
Equipment used only for fire service duty will not be subject to the same level of wear and tear as
equipment used for day-to-day mechanical services duty, for comfort, health or process control.
Hence, for reliable operation, equipment subjected to day-to-day usage will require more frequent
inspections and service or repair than equipment used only for fire service duty; however, equipment
used for day-to-day mechanical services duty, is effectively monitored (tested) by the occupants of the
building every day, and any breakdown is likely to cause occupant discomfort and generate corrective
action to regain the required performance providing there is a current service contract in place.
Equipment used only for fire service duty will not be subject to regular monitoring by occupants, and
so will require frequent inspections or tests to establish confidence that it will be available to operate
when needed, but will not require the same level of service or repair as equipment used for day-to-day
duty.
(c) In columns 8 and 11, the inspector should indicate which smoke detector zone, sprinkler zone,
supply air detector or specific smoke detector activated this operation.
(d) Test smoke exhaust fans and exit pressurization systems at frequencies required by the
regulatory authority to demonstrate that they are capable of performing to the Standard to which
they were installed. This requires measurement of airflow rates, doorway velocities, door
opening forces, restoration times, etc. Carry out the performance tests prior to the functionality
tests, but within the maximum time period allowed under the relevant legislation. Document test
results and methods used for testing separately, with a note in column 21 indicating where
performance test results are available, if not attached. To indicate when performance tests are
required, highlight the relevant cell in column 20.
(e) In column 4, charts should include the following:
(i) All air-conditioning and ventilation fans in the premises, even if they simply shut down or
continue running without manual or automatic control on fire alarm.
(ii) All smoke control make-up airflow paths. For example, motorized dampers, barometric
(non-return) dampers, fixed intake grilles and doors that open automatically on fire alarm.
(iii) All motorized dampers that operate automatically during fire alarm, or have manual
control from the fire fan control panel.
NOTE: VAV dampers or ventilation dampers that have no fire mode operation need not be
included.
(f) Smoke exhaust fans, pressurization fans, dampers (and some supply air fans) only operate if fire
or smoke is detected in a specific zone and not when fire is detected in other zones. These
functionality test charts allow verification of zone-specific activation from the ‘fire-affected
zone’ and one ‘outside zone’. There will be many more ‘outside zones’ than fire-affected zones,
so visual verification of non-operation for every device and every outside-zone could generate
multitudes of tests, unless an effective procedure is established. Carry out at least one visual
confirmation of fire ‘non-fire’ operation for each device. Confirmation of operation under other
fire detection permutations may be verified by observation of indicator lamps (after their
operation has been proved). The ‘non-operation’ verification procedure is to be attached to
these charts and indicate, in column 21, that those devices that were verified ‘non-operational’
when an associated fan or damper were confirmed to be operating.
(g) In a large project, the functionality charts may require many pages to cover all air handlers,
dampers, smoke exhaust fans and sundry ventilation systems. Unless handled carefully, the
sheer volume of documentation may cause difficulties during testing.
(h) Column 1 is to be used to show the reference used by the mechanical services service provider
or as shown on the mechanical services drawings.
(i) Column 2 is to be used to show the name used by the responsible entity to describe the relevant
zone or area within the building.
(j) Column 3 is to be used to show the reference used by the fire system service provider to
describe the relevant zone or zones.
NOTE: Smoke control matrices prepared by fire contractors show clearly and unambiguously, the intended
operation of mechanical services systems under various different fire alarm conditions. However, limitations
do occur and it is important for the documentation to make adequate provision for the following:
(a) Recording action when the alarm occurs in ‘another’ smoke zone.
(b) Recording action on ‘general fire alarm’ or sprinkler alarm.
(c) Recording if a fan/damper combination has manual override at FFCP.
(d) Recording if FFCP has indicator lamps for fan/damper combinations.
(e) Sufficient space to certify right/wrong operation on the sheet.
(f) Easy of reading, especially in low light test conditions.
(g) Written verification of fire alarm zone actuated.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
Performance Test
Mechanical
Location Tested
Activating Device
Activating Device
Services Plant Fire Control
Actual Function
Actual Function
Actual Function
of Zone Design Comments (Note 1) Comments on TestsS
Design
Design
Reference Reference
Serviced
(Fan or damper No.)
(Note (d))
Note (c)
Note (c)
Fault
Off
Off
On
On
AZF #1 Runs on smoke alarm in Central (Indicate here where results of performance tests
Yes
Yes
Smoke Exhaust (West Zone) Mail West Zone only.
Central Mall are available)
Fan #1
(West)
Stop
Stop
Run
Yes
Yes
(SEF 1) Spr #3 Runs on Mail Sprinkler alarm.
AZF #2 Runs on smoke alarm in Central (Indicate here where results of performance tests
Stop
Stop
Run
Yes
Yes
Smoke Exhaust (East Zone) Mail East Zone only. are available)
Central Mall
Fan #2
(East)
Stop
Stop
Run
Yes
Yes
(SEF 2) Spr #3 Runs on Mail Sprinkler alarm.
199
Closed Closed
Closed Closed
Open
AZF 1, 2 Opens on any smoke alarm in
No
No
Relief Air Smith St. (Central Mall) Central Mall.
Damper #1 Entrance
Open
(RAD 1) (Central Mall) Sprinkler
No
No
Opens on Mail Sprinkler alarm.
Pressure Sw.
Relief Louvres Jones St. Make-up for Smoke Exhaust fans. (Indicate here if louvres were free of leaves,
Entrance N/A
(RL 2) Must be free of rubbish. rubbish or other risk of blockages)
Stop
AZF #1 Stops on smoke alarm in Central
Run
Run
Yes
Yes
(West Zone) Mall West Zone only.
Air Handling Central
Stop
Sprinkler
Yes
Yes
N/A
N/A
Unit No. 1 Mall Stops on any Sprinkler alarm.
Pressure Sw.
(AHU 1) (West)
Stop
AHU #1 Stops on smoke detection in (Indicate here if AHU No. 1 Fan stopped on
Yes
Yes
N/A
N/A
Supply Air Supply Air. Supply Air smoke detection)
Stop
Run
No
No
Kitchen Exhaust (Eatery) Zone only.
Joe's Cafe
Fan # 4
(Eatery)
Stop Stop Stop
Sprinkler
Run
N/A
No
No
(KEF4) Stops on any Sprinkler alarm.
© Standards Australia
Pressure Sw.
Eatery
Run Run
N/A
Toilet Exh. (TEF5)
No
No
GFA Stops on any Fire alarm.
AS 1851—2012
Fashion
N/A
No
No
GFA Stops on any Fire alarm.
AS 1851—2012
© Standards Australia
200
www.standards.org.au
FIGURE I4.2 TYPICAL SYSTEM PERFORMANCE TEST RECORD FOR FIRE-ISOLATED EXIT PRESSURIZATION SYSTEMS
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
201
© Standards Australia
FIGURE I4.3 TYPICAL SYSTEM FUNCTIONALITY TEST RECORD FOR FIRE-ISOLATED EXIT PRESSURIZATION SYSTEMS
AS 1851—2012
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
AS 1851—2012
© Standards Australia
Project:
Address:
Year of inspection Year 1 Year 2 Year 3 Year 4 Year 5
Fire damper inspected by / Date // // // // //
Structure inspected by / Date // // // // //
Approved by / Date // // // // //
202
NOTES:
1 This assessment is based on the assumption that the original fire dampers and installation methods were compatible with the FRL of the surrounding fire-resistant structure and
complied with the Standards applicable to the original installation as well as the manufacturer’s special instructions, where applicable.
www.standards.org.au
2 Wall or floor to be inspected by personnel who are competent to assess passive fire resistant structures, as per Section 12.
APPENDIX J
OTHER EMERGENCY RESPONSE IN FACILITIES
(Informative)
TABLE J1
SUMMARY OF SCHEDULES FOR
EMERGENCY EVACUATION EQUIPMENT AND FACILITIES
Paragraph Frequency
J2.1 Monthly verification of emergency evacuation procedure elements
evacuation routes and paths and records
J2.2 Monthly verification of emergency evacuation system elements
emergency response and firefighting equipment and records
J2.3 Monthly verification of emergency evacuation system elements alarms,
communication, detection and suppression systems and records
J2.4 Monthly verification of emergency evacuation system elements ECO
and emergency procedures and records
J2.5 Monthly verification of emergency evacuation system elements
housekeeping and records
J2.6 Six-monthly verification of emergency evacuation system elements
emergency evacuation procedures documentation and records
J2.7 Yearly verification of emergency evacuation system elements
emergency evacuation procedure training and records
J2.8.1 Monthly verification of emergency procedure elements emergency
evacuation procedures monitoring and records
J2.8.2 Six-monthly verification of emergency procedure elements emergency
evacuation procedures monitoring and records
J2.8.3 Yearly verification of emergency procedure elements emergency
evacuation procedures monitoring and records
J2.9 Yearly verification of emergency evacuation procedures and records
TABLE J2
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION PROCEDURE
ELEMENTS EVACUATION ROUTES AND PATHS AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
1.1 Smoke doors CHECK that smoke doors close correctly.
1.2 Exit signs/ CHECK illumination by activating test button.
Emergency
lighting
1.3 Exit doors CHECK that exit doors are free from obstructions and can
function as required.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
1.4 Exit routes CHECK that exit routes are clearly identified and free
from obstructions.
1.5 Fire doors CHECK that fire doors close correctly.
TABLE J3
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM ELEMENTS
EMERGENCY RESPONSE AND FIRE FIGHTING
EQUIPMENT AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
2.1 Fire hydrants CHECK that fire hydrants are identified and free from
obstructions.
2.2 Fire hose reels CHECK that fire hose reels are identified, free from
obstructions and the nozzle interlock is engaged.
2.3 Fire extinguishers CHECK that fire extinguishers are fully accessible,
mounted, sign-posted and charged and/or sealed.
2.4 Fire blankets CHECK that fire blankets are fully accessible, mounted
and identified.
2.5 Disability Where provided, CHECK that equipment is accessible
impairment and functional.
equipment
2.6 ECO CHECK that equipment is available, accessible,
identification correctly colour coded and functional.
equipment
TABLE J4
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM ELEMENTS
ALARMS, COMMUNICATION, DETECTION AND
SUPPRESSION SYSTEMS AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
3.1 MCP (BGA) CHECK that equipment is accessible.
alarms (red)
3.2 MCP (BGA) CHECK that equipment is accessible.
alarms (white)
3.3 MCP (BGA) CHECK that equipment is accessible.
(red & white)
3.4 EWS CHECK that WIPs are operational, accessible and
alarms are audible.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
TABLE J5
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM ELEMENTS
ECO AND EMERGENCY PROCEDURES AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
4.1 Identification CHECK ECO member identification is readily available.
4.2 Diagrams CHECK that evacuation diagrams as per AS 3745 are in
place.
4.3 Availability of CHECK that ECO members are recorded.
wardens
TABLE J6
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM
ELEMENTS HOUSEKEEPING AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
5.1 Rubbish disposal CHECK that rubbish has not accumulated in area of
responsibility.
5.2 Fire hazards CHECK that no fire hazards are identifiable in area of
responsibility.
5.3 Hazardous CHECK that all hazardous materials are in a safe
materials condition and registered in the area of responsibility.
A typical example of the inspection, checking and test of documentation and records on a six-monthly
basis is set out in Table J7.
TABLE J7
EXAMPLE
SIX-MONTHLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM
ELEMENTS EMERGENCY EVACUATION PROCEDURES
DOCUMENTATION AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
6.1 Distribution and CHECK ECO members and supply a copy of the
availability of documented procedures for EPC directives.
procedures
6.2 Training records CHECK that all trainees have been recorded and follow
up on non-attendees.
TABLE J8
EXAMPLE
YEARLY VERIFICATION OF EMERGENCY EVACUATION SYSTEM ELEMENTS
EMERGENCY EVACUATION PROCEDURES TRAINING AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
7.1 Evacuation CHECK that evacuation exercises have been conducted and
exercises observers’ actions recorded for future action with the ECO.
7.2 Scheduled CHECK that the scheduled training has been conducted and
training reported to the EPC.
7.3 Management of CHECK that EPC directives for education training and
ECO skills exercises have been completed.
A typical example of the inspection, checking and test of monitoring elements on a monthly, basis is
set out in Table J9.
TABLE J9
EXAMPLE
MONTHLY VERIFICATION OF EMERGENCY EVACUATION PROCEDURE
ELEMENTS EMERGENCY EVACUATION PROCEDURES MONITORING
AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
8.1.1 Essential services CHECK contractors have signed-off the required
routine service entries.
records
8.1.2 Monitor testing of CHECK testing (selectivity) procedures.
essential services
8.1.3 Monitor fault CHECK that faults have been reported.
reporting of
essential services
8.1.4 Rectification of CHECK that rectification work has been completed.
essentials services
8.1.5 Temporary fire CHECK that any impediments have been rectified.
safety impediment
J2.8.2 Six-monthly
A typical example of the inspection, checking and test of monitoring elements on a six-monthly basis
is set out in Table J10.
TABLE J10
EXAMPLE
SIX-MONTHLY VERIFICATION OF EMERGENCY EVACUATION PROCEDURE
ELEMENTS
EMERGENCY EVACUATION PROCEDURES MONITORING AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
8.2.1 Control centre CHECK that all documentation is in place and operational
capability of the control centre.
8.2.2 Control of hot CHECK compliance with remote system as specified by
works the EPC.
8.2.3 Security CHECK that interconnections between security provisions
interfaces and fire safety features are operational.
8.2.4 Passive CHECK that any works carried out on passive fire
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
J2.8.3 Yearly
A typical example of the inspection, checking and test of monitoring elements on a yearly basis is set
out in Table J11.
TABLE J11
EXAMPLE
YEARLY VERIFICATION OF EMERGENCY EVACUATION PROCEDURE ELEMENTS
EMERGENCY EVACUATION PROCEDURES MONITORING
AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
8.3.1 Exit door release CHECK that the routine service program has been
mechanisms conducted.
8.3.2 All routine CHECK all logbooks have the required number of
service logbooks entries.
and records
8.3.3 Management of CHECK compliance and, as necessary, replacement.
equipment
installation
signage
8.3.4 Tactical fire plans CHECK and test tactical fire plans.
8.3.5 Emergency CHECK that tests have been completed.
lighting
8.3.6 Fire services CHECK provisions and test with the fire services.
access
8.3.7 Lifts CHECK that all emergency procedures for lifts are
functional.
TABLE J12
EXAMPLE
YEARLY VERIFICATION OF EMERGENCY EVACUATION PROCEDURES
AND RECORDS
Item Records
Item Action required and pass/fail requirement
No. Result Comments
9.1 Reporting of ECO to CHECK ECO activities comply with AS 3745and
management are adequate and appropriate for the emergency
response risk.
9.2 Appointment of CHECK that all tenancies are represented
ECO/EPC management appropriately by both ECO and EPC.
structure (including
partial occupancy
9.3 Emergency response CHECK that all occupancies and tenancies have
budgetary planning allocated emergency budgeting allowance.
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
AS 1851—2012
210
NOTES
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
211
NOTES
AS 1851—2012
Accessed by SAI GLOBAL - ASSURANCE SERVICES on 17 Dec 2012 (Document currency not guaranteed when printed)
AS 1851—2012
212
NOTES
Standards Australia
Standards Australia develops Australian Standards® and other documents of public benefit and national interest.
These Standards are developed through an open process of consultation and consensus, in which all interested
parties are invited to participate. Through a Memorandum of Understanding with the Commonwealth Government,
Standards Australia is recognized as Australia’s peak non-government national standards body. Standards Australia
also supports excellence in design and innovation through the Australian Design Awards.
Australian Standards®
Committees of experts from industry, governments, consumers and other relevant sectors prepare Australian
Standards. The requirements or recommendations contained in published Standards are a consensus of the views
of representative interests and also take account of comments received from other sources. They reflect the latest
scientific and industry experience. Australian Standards are kept under continuous review after publication and are
updated regularly to take account of changing technology.
International Involvement
Standards Australia is responsible for ensuring the Australian viewpoint is considered in the formulation of
International Standards and that the latest international experience is incorporated in national Standards. This role is
vital in assisting local industry to compete in international markets. Standards Australia represents Australia at both
the International Organization for Standardization (ISO) and the International Electrotechnical Commission (IEC).