Civil Method Statement Schedule
Civil Method Statement Schedule
7 Method Statement On Laying Of Block Works (Solid, Hollow, Aac Block And Thermal Insulated Block) 2 25-Mar-25 08-Apr-25
9 Method Staement On The Application Of Waterproofing For Wet Areas 31-Mar-25 14-Apr-25
10 Method Statement On The Installation Of Tiling Works (Porcelain And Stone ) 02-Apr-25 16-Apr-25
11 Method Statement On The Application Of Painting Works For Wall & Ceiling (Internal) 04-Apr-25 18-Apr-25
12 Method Statement On The Application Of Painting Works For External 08-Apr-25 22-Apr-25
13 Method Statement On The Application Of Epoxy Painting Works For Floor 10-Apr-25 24-Apr-25
14 Method Statement On The Installation Of Suspended False Ceiling Works 14-Apr-25 28-Apr-25
18 Method Statement On The Installation Of Aluminum , Glazing , Railing And Ballustrade Works 24-Apr-25 08-May-25
20 Method Statement On The Installation Of Wooden Joinery Works ( Wardrobe And Kitchen Cabinet) 30-Apr-25 14-May-25
22 Method Statement On The Installation Of Vanity Counter And Mirror 06-May-25 20-May-25
24 Method Statement On The Installation Of Metal Fence And Gate 12-May-25 26-May-25
27 Method Statement On The Installation Of Roof Access Hatch Door 20-May-25 03-Jun-25
31 Method Statement On The Construction Of Swimming Pool And Features 30-May-25 13-Jun-25
32 Installation And Gravity Test Of Underground & Above Ground Drainage System 28-Mar-25 11-Apr-25
33 Installation And Testing Of Domestic Water Supply Piping System (Upvc, Ppr, Pex Pipes And Fittings) 07-Apr-25 21-Apr-25
34 Installation And T&C Of Duct Work , Accessories And Ac Equipment(Pre Insulated Phenolic Duct And Gi Duct) 15-Apr-25 29-Apr-25
35 Method Statement For Installation And T&C Of Solar Water Heater 15-Apr-25 29-Apr-25
37 Method Statement For Installation, Testing And Commissioning Of Water Booster Pumps 15-Apr-25 29-Apr-25
40 Method Statement For Distribution Board System (Installation, Testing And Commissioning). 15-Apr-25 29-Apr-25
41 Installation, Testing And Commissioning For Fire Alarm And Voice Evacuation System 15-Apr-25 29-Apr-25
42 Method Statement For Installation, Testing Commissioning Of Scs System 15-Apr-25 29-Apr-25
43 Method Statement For Installation, Testing And Commissioning Of Intercom System 15-Apr-25 29-Apr-25
CONSTRUCTION OF RESIDENTIAL DEVELOPMENT (312 UNITS) @ THE VALLEY WEST TH03 VELORA 2, DUBAI (D-489)
PREQUALIFICATION
PREQUALIFICATION SUBMITTAL PROCESS
SNO ITEM DESCRIPTION NAME OF SUPPLIERS
BL SUBMISSION
UNIFIER REF. NO. BL APPROVAL DATE ACTUAL SUBMISSION ACTUAL APPROVAL STATUS COMMENTS
DATE DATE DATE
EXTERNAL ITEMS
ANTI-TERMITE WORKS
PRECAST CONCRETE KERB AND INTERLOCK PAVING BLOCKS
GARBAGE BINS AND TROLLEY
CONCRETING WORKS
ANTI-TERMITE WORKS
READY MIXED CONCRETE
RENIFORCEMENT BARS
THERMAL & MOISTURE PROTECTION
WATERPROOFING WORKS (Substructure/Wet Areas/Roof Areas)
GRP LINING (UG Water Tank Inner Wall)
MISCELLANEOUS STEEL ITEMS
GATE & FENCE
BALCONY HANDRAIL
STAIRCASE HANDRAIL
ENTRANCE PERGOLA
RETRACTABLE LADDER
ACCESS HATCH DOOR
CAT LADDER
DOORS/CLADDING/ENVELOPING
ALUMINIUM & GLAZING DOORS & WINDOWS (with Hardwares)
TIMBER DOORS & FOLDING DOORS
IRONMONGERY (FOR TIMBER DOORS)
WOODEN PLASTIC COMPOSITE (WPC)
ARCHITECTURAL FINISHES
KITCHEN CABINETS/WARDROBES/VANITY/WALL CABINETS
CUBICLE PARTITION
PAINTING WORKS (INTERIOR & EXTERIOR)
MIRRORS
SUSPENDED FALSE CEILING
GLAZED SHOWER PARTITION
STONE WORKS (MARBLE/GRANITE)
PORCELAIN TILES
KITCHEN APPLIANCES
MECHANICAL WORKS
LPG SYSTEM
FIRE FIGHTING SYSTEM
SANITARY FIXTURES & SANITARY WARES
MEP DIVISION FOR MEP WORKS
ELECTRICAL WORKS
LV SWITCH GEAR & METER CABINET
LOW CURRENT SYSTEM
LIGHT FITTINGS
WIRING ACCESSORIES