Method Statement For FOAM System-HMC
Method Statement For FOAM System-HMC
Contents
1. Objectives................................................................................................................... 2
2. Scope of the Works..................................................................................................... 3
3. References..................................................................................................................3
4. Hazards Identified.......................................................................................................3
5. Personnel................................................................................................................... 3
5.1 Manpower:................................................................................................................. 4
6. Equipment.................................................................................................................. 4
7. Materials.................................................................................................................... 5
8. Personnel Protective Equipment.................................................................................8
10. Work Area & Access / Egress.......................................................................................8
11. Interface..................................................................................................................... 9
12. Method of Works........................................................................................................ 9
12.1 Inspection prior to installation....................................................................................9
12.2 System installation......................................................................................................9
12.3 Threaded / Grooved Connections for Valves..............................................................10
12.4 Erection of pipes.......................................................................................................10
12.5 Installation of MICC Cable.........................................................................................11
12.6 Painting of Pipes....................................................................................................... 11
12.7 Installation of Pipe Support.......................................................................................12
12.8 Welding Procedure and Water Tapping....................................................................12
12.9 Threading and grooving Procedure...........................................................................13
12.10 Coupling Installation.................................................................................................14
12.11 Mechanical-T Installation..........................................................................................14
12.12 Threaded Fitting Installation.....................................................................................15
12.13 Nozzle Installation.................................................................................................... 15
12.14 Deluge Valve Installation...........................................................................................15
12.15 Bladder Tank Installation..........................................................................................15
12.16 Installation of Flame Detector................................................................................... 16
12.17 Installation of Horn Strobe........................................................................................16
13. Testing Procedure.....................................................................................................16
13.1 Test instruments.......................................................................................................16
Page 1 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
13.2 Cable continuity and insulation resistance test..........................................................16
13.3 Cable insulation resistance test................................................................................. 17
13.4 Pipe installation pressure test...................................................................................17
14. Environmental Arrangements...................................................................................18
15. Emergency Procedures............................................................................................. 18
Appendix A......................................................................................................................... 20
Appendix B......................................................................................................................... 21
Appendix C......................................................................................................................... 22
1. Objectives
This Method statement describes in detail the onsite Installation of Foam System as per
approved material submittal and approved shop drawing & NFPA for
Page 2 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
2. Scope of the Works
This method statement shall cover all works related for the Installation of Foam System as
specified in the project specification sections 15355 the approved shop drawing and
approved material submittal in
3. References
4. Hazards Identified
The major hazards and risks as identified in the job risk assessments.
Falls from height ,Falling of tools and debris ,Overhead power lines, Scaffold
collapse ,Bad planking Falling of materials and Electrocution etc ) controls measure.
Slipping Tripping (Poor housekeeping, working area, Hydro test activities, poor materials
storage etc.).
Noise (Use of power tools, plant and equipments, scaffold erection and dismantling etc).
De-watering (Ditch for water collection etc).
Use of plant, tools and equipment (power tools, threading and grooving machine, forklift,
welding machine etc).
Use of substances hazardous to health (Paints, sealants etc).
Manual handling (Materials shifting, use of hand tools , use of chemicals)
Public/Contractor interface and traffic interface (traffic controls, security details, safety
barriers, speed bumps, coordination with local authorities etc)
5. Personnel
Project Director – is responsible for the overall management of the work and control of
the staff in executing the work.
Project Engineer, Site Engineer and Supervisor– shall be responsible for all site activities
and closed supervision for the installation of all works. To carry out the work as approved
method statement. He is also responsible to ensure adequate equipment and tools to carry
Page 3 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
out the work and assure that disposal of debris will be as per approved designated
disposal point.
HSE Manager – is responsible to ensure that all Safety precautions are in place, and that all
personal on site are using the required Personal Protective Equipment’s like – Helmet,
Gloves, Shoes, and Coveralls. We will also ensure all relevant permissions are available for
the works.
Skilled Workers – will be leading the workers for any related works for the installation of
all related works.
5.1Manpower:
Project Manager
Quality Engineer
Site Engineer / Site Supervisor
Safety Engineer / Officer
Foreman
Workers
6. Equipment
The following equipment will be used to carry out the Installation, Testing & Commissioning
of FOAM System
Power Tools
Hand Tool Box
Threading Machine
Drill Machine
Groove Machine
Water Pressurizing Machine
Grinding Machine
Alignment Tools
Mobile crane capable of hoisting and lowering the weight of the pump or motor
Fork Lift
Belting/Sling
Welding Machine
Disc Cutter
Page 4 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
7. Materials
Foam Concentrator
Bladder tank Proportioning System
Deluge Valve
Ratio Controller
Foam – Water Sprinkler
Butterfly Valve
Pipes & Fittings
Hydro testing for the system should be done before installation of the nozzles.
Ensure that testing equipments /tools are ready.
Ensure that system should be measured with calibrated pressure gauge installed at the
lowest point.
Ensure the pressure gauges are calibrated and valid calibration certificates available,
issue calibration certificates to the consultants.
Pressure shall be applied to the system by means of water pressure hand pump.
After the test pressure is reached, inlet shall be block off by closing the globe valve and
the variations of pressure in the system monitored on the pressure gauge.
Check the pipes, pipe joints and accessories for the leakage while pressuring and if
any, attend the fault and rectify.
Ensure all the leakages are arrested after the correction is made, the pressure test
shall be repeated until a completely tight system is ensured and the testing procedure
shall follows as:
All piping, including foam concentrate lines and the system piping, shall be
hydrostatically tested at 13.8 bar (200 psi).
The pressure shall be maintained without loss for 2 hours. The pressure drop shall not
exceed ±5 percent of the test pressure.
Bladder tanks shall not be included in pressure tests.
Page 5 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
After hydro test the systems piping shall be flushed
Pressure testing documentation shall be submitted along with inspection request for
consultant /client approval.
7.5 Receiving:
7.5.1.1 Note: All materials have been factory inspected and carefully loaded and braced to
prevent damage in shipment to the job site. However, even these efforts are
sometimes not enough to prevent damage in transit. It is the carrier's responsibility
to deliver the shipment in good condition. It is the receiver's responsibility to report
any loss or damage upon receipt.
7.5.1.2 When a shipment arrives at the job site, obtain the following documentation from the
carrier before offloading:
Packing list.
Country of origin
Bill of lading.
Material test certificate.
Check all piping units, cartons, and pallets against the Packing List.
Visually inspect the piping units, cartoons and pallet materials for damage.
Any shortage or damage must be noted on the Bill of Lading and Packing List.
Do not dispose of any damaged materials until advised to do so by supplier/
manufacturer.
Page 6 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
7.6 Handling:
Loading and unloading of FOAM Equipments, pipes, fittings, cables, conduits, FOAM
Bladder and relevant materials shall be carried out manually or mechanically.
Handling to be strictly as per manufacturer’s recommendation.
On the receipt of material, a visual check will be made to ensure that the components
comply with the packing list and the installation drawings.
When unloading the FOAM Bladder, only lift the unit using the lifting eye on the neck
of the cylinder.
Never insert an object (e.g., wrench, screw, and pry bar) into cap opening; doing so
may damage the valve and cause leak.
7.6.1 The means by which the piping units are unloaded and handled at the jobsite. It is
imperative that proper care and handling techniques are used to avoid damage.
Damaged piping units may require costly repairs, cause property damage, or
worse, personal injury. Safety and careful handling should be top priorities when
handling any of the piping units. Manufacturer recommendation will be followed.
Safety should always be a primary consideration when unloading and handling piping
units:
Never lift more weight than your equipment can safely handle.
Never lift more weight than the rating of the slings.
Do not use damaged slings, cut up and dispose of any damaged slings
Manufacturer chocks only the outer piping units in each layer (or tier) on the truck. It
is important to recognize that as you lift piping units off the truck, nearby piping units
may become unstable and roll. Chock piping units that are not being unloaded.
7.7 Storage:
The pipes shall be unloaded where they are required, when the trenches are ready to
receive them. Storage shall be provided at the bottom layer to keep the stack stable.
The stack shall be in pyramid shape or the pipes placed length-wise and cross-wise in
alternate layers. The pyramid stack is advisable in smaller diameter pipes for
conserving space in storing them. The height of the stack shall not exceed 2.0 m. Each
stack shall contain only pipes of same class and size. Detachable joints and fittings
shall be stacked under cover either in wooden pallet boxes or in the racks.
Pipes in the top layer shall be handled first. At a time only one pipe shall be handled by
two laborers while conveying to the actual site and shall be carried on shoulders.
Fittings shall be handled individually
Hard hat
Safety footwear
High visibility clothing
Gloves
Safety glass
Chemical respiratory mask
Apron
Face shield
Welding hand and leg sleeves
Coverall
Fall arrests
Ear protection
9. Temporary Works
All the Safe Working Scaffolding Platforms will be installed in compliance to safety standard
requirements under the supervision of Temporary works co-coordinator.
Page 8 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Every shaft shall have a means of access and egress by stairway, ladder, or ladder way for
its full depth during construction and when it is completed.
11. Interface
The Interface coordinator (Site Engineer/Foreman) shall be responsible for the co-
ordination and interfacing with other contractors during the installation works.
After the routes for the delivery of materials are determined, DSI will notify other
Contractors affected by the traffic route of materials and equipment in advance to avoid
any disturbance of their job schedule and will follow the Contractor traffic management
plan.
At work front, if there is any interface with other contractors, they shall be informed well
in advance and necessary precautions shall be taken care of.
Works shall not proceed until an approved “shop drawing & calculation” is made
available. Check all approved materials are available to carry out the works.
Check the FOAM System and its accessories if properly labelled and received at site in
accordance with specification and correct dimension as per approved drawings.
Materials shall be moved to the work in a safe manner and shall not block access/egress
from the site.
All relevant documents drawings and material applicable to particular section of work
must be checked prior to commencement of work. Before any materials are installed,
ensure that these have been inspected at site and have been approved by consultant.
Check all proper tools and equipment are available to carry out the work and in
compliance with contract specification. Ensure that all drawings to be used at site are
marked with “approved shop drawings & approved calculation”.
Thorough coordination with other subcontractors (e.g. Main Contractor, architectural
etc.) must be implemented before and during installation work.
Check that the material size and schedule is correct and approved as per specification
and/or approved alternative.
Ensure that the pipes and fittings must conform to the requirements as outlined in NFPA
11 in strict accordance to systems approved plans.
All pipe thread connections must be free of scale and burrs before installation.
Check to ensure that all grooved coupling gaskets shall be lubricated as per
manufacturer’s specification.
Pipe hangers shall be spaced in accordance with the NFPA & QCDD regulations.
Check to ensure that the Foam-water sprinkler identification number is verified before
installation and each Foam-water sprinkler should be as per approved system plans.
Page 9 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Check to ensure that piping should be blown clear to remove chips, mill scale or metal
shaving before the Foam-water sprinkler should be installed.
Make certain that foam bladder has been installed in the correct mounting position.
Check to ensure that the correct foam bladder part number/capacity is identified in the
name plate and correct foam concentration should be verified as per location on the
system plan.
Verify that the container pressure gauge is within the fill pressure range.
Make sure that the Bladder brackets must be mounted securely to solid bearing surface
that will support the Bladder load.
All conduit and hardware, initiating and signalling devices, and other related electrical
connections shall be done as mentioned in the specification with the approved materials
and manufacturer in accordance with the minimum requirements in NFPA 72 and/or as
per civil defence department regulation.
Verify that all auxiliary functions such as door closures, damper closures, air handling
shutdown, etc. Are connected as specified.
On completion of the works, all elements of the installation shall be checked to ensure
the installation is in compliance with the specification and manufacturer instructions.
All pipes and equipment installation works shall be monitored on an ongoing basis to
ensure compliance with the quality requirements of the project.
System shall be identified in compliance with the specifications, identifying all
equipment, flow direction and services.
Confirm the valve size and location based on the shop drawings. Ensure that the selected
valve shall be in accordance with the approved QCDD & Shop drawings.
Fabricate the pipe according to the required length and thread/grooved it accordingly.
Hold the valve firmly by a spanner on the flat nearest joint and then rotate the pipe with
a plumbing wrench. Rotate the pipe until the end of the spindle operating joint. Repeat
the above steps for other pipes for threaded pipes & joints for grooved use
instantaneous coupling to join the pipes & valves.
Complete the painting of pipes based on the approved submittal to be use for painting.
Start marking the routing of the piping as per the approved and coordinated drawings.
Start the fabrication of pipes (grooving for sizes 2 ½” ø above and threading for 2”ø and
below)
Start drilling and fixing of supports as per the prescribed marking.
Start hanging the pipes with proper hanger and supports complying with the NFPA
standards.
Join all the fabricated pipes and prepare it for pressure testing.
Pressurize the piping as per testing procedure.
Page 10 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
After completing the pressure testing, start fixing the equipment and do the final touch-
up of painting.
Clean the black pipe with cotton rag to remove any dust or grease on the pipes.
After cleaning, paint the black pipes with 1 layer undercoat of wash primer. Ensure all
sides (top & bottom) are painted evenly.
Put the painted pipes in a good ventilation condition for 24 hours for the paint to dry.
After the paint is dried, then paint the pipes with 2 layer of finish coat. Ensure all sides
(top & bottom) are painted evenly.
After the finish coat is dry, install the pipes as per approved shop drawings of Foam fire
suppression system.
Identify the actual location of the hanger based on the approved shop drawing. Mark the
position for installing the drop in anchor after coordination with Structural Engineer.
Install the required length of the GI angle as per approved material & NFPA.
Install the approved support as per the approved shop drawing & NFPA standards.
Drill holes on the fabricated support for fixing the supports to the wall/slab and also for
installation the pipes using U bolt as per require pipe sizes.
Locate the required support locations as per the approved shop drawing and marks the
holes to be drilled on the wall/slab.
Page 11 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Drill the hole on the marked position as per the anchor bolt sizes.
Insert the drop in anchor in the hole.
Tighten the supports on drop in anchor using bolts.
Rigid bracing is required at each directional change fitting, tee and nozzle.
WHEN MAKING VERTICAL ALLOY-UP JOINTS heat the tube first, then apply heat to
the fitting. It is important to bring both pieces up to temperature evenly. Keep the flame
directed toward the fitting. If the tube is overheated, the brazing alloy may run down the tube
rather than into the joint.
WHEN MAKING HORIZONTAL JOINTS heat the circumference of the tube first, and
then apply heat to the fitting. Deciding where to start feeding the alloy will depend on the size
of the pipe and operator preference. On large diameter pipe, however, sometimes the best
approach is to start at the bottom of the pipe. As the alloy solidifies, it will create a "dam" and
help prevent the brazing alloy from running out of the joint as the remainder of the
connection is filled. When adding alloy, make sure both the pipe and fitting are up to
temperature.
Page 12 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
the brazing alloy has set, quench or apply a wet brush or swab to crack and remove the flux
residues. Use emery cloth or a wire brush if necessary.
Drain the residual threading oil from the pipe into the oil tray of the threading machine.
Grooving
Cut the required length of the pipe to be grooved.
Check that the cut ends of the pipe are square.
Install the correct die on the grooving machine for the corresponding pipe size
Insert the end of the pipe to be grooved in between the groover dies.
Support the other end of the pipe using the pipe stand.
Start the machine and at the same time apply pressure on the pipe toward the machine
so that the pipe does not slip out of the groover die.
Groove the pipe until the required depth of the groove is achieved.
Groove the pipe ends according to the manufacturer’s specification, project specification
and consultant’s approval.
Pipe must be free from indentation, projection or roll marks on exterior from the end to
the groove, to assure a leak tight seat for the gasket.
Pipe must be free from indentation, projection or roll marks on exterior from the end to
the groove, to assure a leak tight seat for the gasket. Refer to figure 1 next page.
Place gasket over pipe ends, being sure gasket lip does not overhang pipe end.
Page 13 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Align and bring 2 pipe ends together and slide gasket into position centered between the
grooves on each pipe. No portion of the gasket should extend into the grove on either
pipe.
Loosely assemble all segments leaving on nut and bolt off to allow for “swing-over”
feature.
With 1 nut and 1 bolt removed, use the “swing-over” feature to position housing over
gasket and into the grooves on both pipes.
Insert the remaining bolt to allow easy tightening of the nut. Be sure track head engages
into housing recess.
Tighten nuts alternately and equally maintaining metal-to-metal contact at the angle
bolt pads. Tighten securely to assure a rigid joint.
Drill the hole according to the manufacturer’s specification, project specification and
consultant approval.
Remove 1 nut and bolt from housing. Loosen the other nut until it is flush with the end
of the bolt. Remove the tape and lift the gasket from Mechanical-T outlet.
Check gasket supplied to be certain it is suited for intended service. Apply a thin coat of
silicone lubricant to gasket lips and outside of gasket.
Reposition gasket into housing using alignment tabs on slides for proper positioning.
Rotate the lower housing approximately 90° away from the upper housing in the hole.
Make sure that the locating collar is in the outlet hole by rocking the upper housing in
the hole.
Insert bolts in his hole and finger tighten both nuts. Be certain oval-neck of bolt engages
recess in housing. Make sure that the locating collar is in the outlet hole and the
positioning lugs are properly aligned.
Tighten bolt nut uniformly until the upper housing is in complete surface contact in the
gasket pocket area and the assembly is rigid.
Check the pipe length required based on the approved shop drawing.
Mark the desired length on the pipe and cut it. Make sure the pipe ends are square.
Place the pipe in the threading machine and thread it accordingly. Make sure the thread
of the pipe is in good condition.
Remove the oil from the pipe end after the threading procedure and wrap it with Jute
and Boss White or Teflon tape.
Install the pipe to the threaded fitting.
Page 14 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
12.13 Nozzle Installation
Install the pipe as per approved shop drawings with provision to install the nozzles at
location as indicated on the approved shop drawing.
Install support near to the last bend of each nozzle location.
Ensure that there is no residuals present inside the pipe before installing the nozzles.
Install the nozzles by tightening the nozzles at the last end of the pipe at location as
identified on the approved shop drawings.
Confirm the valve size and location based on the shop drawings. Ensure that the selected
valve is flange type.
Place the valve between the pipe flanges. Make sure the flange and adjacent pipe are
clean.
Isolate the main pipe of the fire fighting system and extend the pipe up to the foam
system deluge valve.
Select the gasket size according to the valve size and associated pipe size based on
approved shop drawings so that it can match the pipe work flange.
Connecting the valve with the pipe flange. The pipe flange shall be square with the
associated pipeline.
When the valve is in proper position, install the bolts into the holes. Tightening the nuts
one by one evenly. Repeat the above steps for the other joint.
Install the Trim of the Valve as per manufacturer drawings.
Identify the actual location of the Bladder Tank based on the approved shop drawings.
Mark the drill hole location on the wall corresponding to the mounting bracket supplied
with the Bladder Tank.
Drill the holes as per drop-in anchor size and install the Bladder tank on the Floor using
drop-in anchor bolts.
Mount the Bladder Tank on the mounting bracket and tighten the Bladder Tank on the
mounting bracket using bolts.
Foam concentrate will be filled to bladder tank by inserting plastic funnel into bladder
tank fill line and pour the concentrate from the foam concentrate storage cans through
funnel.
Before filling the concentrate close all drain valves and open the vent valves.
Installation of flame detector shall be in accordance with the NFPA 72 at location shown
in the approved shop drawings.
When spacing flame detectors following the guidelines listed in NFPA 72, base the
number and location of sensors on an engineering survey of the area to be detected.
Page 15 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Visually check every detail connections and its mounting as per approved drawings.
Layout.
Installation of Horn Strobe shall be in accordance of the NFPA 72 at location shown in the
approved Shop drawings.
Ensure/verify the Horn Strobe name plate information match with the name and location
as specified in the Shop drawings.
Identify the installation location of the notification device; use the portable drilling tool to
make holes, and install or fix the device at the location using the anchor bolts and nuts.
Installation of the device enclosure should be in accordance to the approved Shop
drawings and diagram below. Fix and tighten the device using the supplied expansion
anchor bolts and nuts as per manufacturer’s installation instruction.
Apply labels and tags as per approved material.
The following calibrated test instruments shall be used to perform the required test.
This test shall be conducted to verify the continuity, loop resistance and correct polarity of
wiring connections in all devices for each loop to ensure operation of the FOAM system.
Testing Procedure
Set the digital multi – meter selector to continuity test mode (indicated with a buzzer
symbol).
Check the continuity of loop in and out cables and the polarity of their connections on
each device in a loop.
A buzzer sound will be heard if a continuity exists, otherwise the conductor is either
broken or wrongly wire. Check the wirings if broken, replace with new wires and wrong
wiring to be rectified then check the continuity again.
Measure the resistance of each loop with the digital multi – meter and record the actual
reading in the attached test form.
Acceptance Norm: Measured cable loop resistance is to be ≤ 1 ohms.
Page 16 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
13.3 Cable insulation resistance test
This test shall be conducted to ensure the healthiness of the insulation of the loop
Cables/ wires such that no conductors are either shorted or grounded. It has to be
conducted with the power supply disconnected. Detectors and other voltage sensitive
device/equipment must also be disconnected from circuits undergoing Insulation
resistance test. Failure to observe this precaution may result in serious damage
necessitating costly replacements
Safety will be a major factor during pressure testing to ensure a safe working
environment for all the site personnel and to safeguard plant and equipment. Prior to
commencement of test, tool box talk will be given to all personnel identifying the
potential dangers of pressure testing and to make everyone aware that testing is on-
going in the area.
Testing Procedure
Test limits will be indicated on drawings. Test may comprise a complete system or a
section of piping within a system. Test limits shall be at flanged or similar mechanical
joints.
All in – line instruments (pressure gauges etc.) shall be removed during testing.
Temporary spreads/blinds will be installed where necessary at the test limits points.
Before testing commences, the client will be advised twenty four hours in advance, by
request for inspection (IRE) of the intention to proceed with such testing and the intended
location of any such test. Testing will be coordinated through the main contractor so as
not to affect construction schedules of other contractors at site.
Testing shall be in accordance with the project specifications and guidelines in NFPA 25.
Equipment shall be omitted from tests and bypass arrangements shall be tested.
Temporary spades/blinds will be installed where necessary at the test limit points.
Prior to testing, a demarcation area will be taped off and warning signs placed
prominently, stating that hydrostatic testing is in progress.
These demarcation areas will be on entry areas for all personnel with the exception of
testing inspectors and test personnel. The demarcation area limits may vary greatly in
relation to hydrostatic testing that is in progress.
Test pressure results will be recorded on a pressure test certificate.
Test pressure results will be assessed on a test-by test basis to be agreed on the site and
shall be carried out without environmental contamination.
When all aspects of testing are completed, the demarcation area will be removed and all
barriers and signs stored in a safe / tidy manner.
Acceptance Norm: At the end of test duration, the pressure drop shall not exceed 20
percent of the test pressure of 2 times higher than the working pressure.
Page 17 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
14. Environmental Arrangements
Drake and Scull Project management shall ensure the environmental protection Law No. 30 of
2002 is being implemented on the site where applicable.
Drake and Scull project team shall include Environmental issues in site inductions within
Safety, Health and Environmental Information and Training for all Employees, and newly
assigned Employees.
The major environmental impacts and mitigations as identified in the job environmental and
sustainability assessments documents that are related to environmental issues includes but
not limited to:
Noise and vibration (Silencer and damping, regular maintenance of tools and equipment,
provision of hearing protection, applying job rotation among the workers etc).
Water pollution prevention (Water will not be released directly to the ground from the
mains valve during the hydro test and hose shall be firmly secured to prevent it from
failing. etc).
Arrangements for dewatering works and disposal of groundwater (Water tank/ drum
shall be provided by others for collecting water with proper hose during the dewatering).
Contaminated land. (All liquid chemicals and waste will be stored in spill-proof containers
and drip tray will be provided to collect droplets oil from threading and grooving
machines etc).
The major emergency controls and mitigations as identified in the prepared site emergency
procedure documents that are related to DSI MEP scopes of work includes but not limited to:
The potential emergency situations that may occur in the execution of the project have
been identified and corresponding emergency procedures have been established
including emergency prevention measures.
Voltas will follow Main Contractor Emergency Response procedure.
Police 999
Fire 999
Ambulance 999
A copy of the Emergency Plan will be distributed within Drake & Scull employees at
respective Project Office Layout including emergency exits and fire points and this will be
posted through office and store areas.
Page 18 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Page 19 of 16
ISD-HH-01-MES-529 Rev 1.0
Method Statement for Installation of Foam system HMC
Appendix A
Drawing
Appendix
ISG-HH-00-MES-52591 Rev 1.0
Method Statement for Installation of Foam system HMC
Appendix B
Appendix
ISG-HH-00-MES-52591 Rev 1.0
Method Statement for Installation of Foam system HMC
Appendix C
Appendix
ISG-HH-00-MES-52591 Rev 1.0