0% found this document useful (0 votes)
9 views16 pages

Project Management

The document presents the Critical Path Method (CPM) for project management, focusing on scheduling and resource allocation to ensure timely project completion. It includes an example of building a commercial office, detailing activities, durations, and the process of calculating earliest and latest start and finish times. The critical path is identified as A → B → D → G → H, with a total project duration of 39 days, emphasizing the importance of managing critical tasks to avoid delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views16 pages

Project Management

The document presents the Critical Path Method (CPM) for project management, focusing on scheduling and resource allocation to ensure timely project completion. It includes an example of building a commercial office, detailing activities, durations, and the process of calculating earliest and latest start and finish times. The critical path is identified as A → B → D → G → H, with a total project duration of 39 days, emphasizing the importance of managing critical tasks to avoid delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 16

Let's Start

Project
Management
Presented By : Syeda Rutab Aziz
Critical Path Method (CPM) is a
method used in project planning,
Critical Path Method generally for project scheduling for
the on-time completion of the project.
for Project It helps in the determination of the
management earliest time by which the whole
project can be completed.
CPM Objectives

Utilize critical path methods to Risk Management


determine project timelines and Identify critical tasks to assess risks
optimize scheduling for and develop contingency plans for
efficient resource allocation. potential delays in project completion.

Resource Allocation Performance Monitoring


Effectively allocate resources by Continuously monitor critical activities
understanding which activities to ensure adherence to timelines
are crucial for maintaining and facilitate timely project
project deadlines. completion.
Example : Building a Commercial Office

Activity Description Duration (days) Predecessors Successors

Site
A 4 None B, C
Preparation

B Foundation Work 8 A D

Ordering
C 6 A E, F
Materials

Structural
D 10 B G
Framing

E Electrical Setup 7 C G

Plumbing
F 9 C G
Installation

Interior
G 12 D, E, F H
Finishing

H Final Inspection 5 G None


Draw the Network Diagram
Represent each activity as a node, and dependencies as arrows.

D
B

G H
A E

F
Adding Durations.

D
B 10
8

H
A E G
5
4 7 12
C
6
F
9
Forward Pass
The Forward Pass is the process of calculating the Earliest Start (ES) and
Earliest Finish (EF) times for each activity in the project.
Earliest Start (ES): This is the earliest time an activity can begin, given that
all of its predecessor activities have been completed. For the first activity in
the project (the start), the ES is usually 0 because it can start immediately.
Earliest Finish (EF): This is the earliest time an activity can finish. It is
calculated as:
EF=ES+Duration Earliest Start (ES)
Earliest Finish (EF)

0 A 4

4
Perform Forward Pass (Earliest Start and Finish Times)

12 D 22
4 B 12 10 ES of G is the maximum of the
EF values of its predecessors (D,
E, and F)
8

34 H 39
0 A 4 10 E 17 22 G 34
5
4 7 12
4 C 10
6
10 F 19
9
Backward Pass
The Backward Pass is the process of calculating the Latest Finish (LF) and
Latest Start (LS) times for each activity. This pass helps determine how much
time can be "saved" without delaying the overall project.
Latest Finish (LF): This is the latest time an activity can be completed
without delaying the project. For the last activity in the project (the end), its
LF is the same as its EF because it has no successor.
Latest Start (LS): This is the latest time an activity can start without
delaying its completion. It is calculated as:
LS=LF−Duration
0 A 4
Latest Finish (LF)
Latest Start (LS) 4
Perform Backward Pass (Latest Start and Finish Times)

12 D 22
4 B 12 12 10 22
4 8 12

34 H 39
0 A 4 10 E 17 22 G 34
34 5 39
0 4 4 15 7 22 22 12 34
4 C 10
7 6 13
10 F 19
LF of C is the minimum LS of its successors (E
and F). From the LS values of E (15) and F (13),
the minimum is 13. 13 9 22
Calculation of Float:
Float helps you see where you have some extra time in the schedule, giving
flexibility for handling unexpected delays or issues in other parts of the project.
Float = LS - ES: This shows how much you can delay the start of a task.
Float = LF - EF: This shows how much you can delay the finish of a task.
If an activity is part of the Critical Path, its float is 0, meaning it cannot be
delayed without delaying the project.
If an activity has a positive float, it means it can be delayed by that amount of
time without impacting the overall project timeline.
Purpose: Float gives project managers flexibility. Non-critical activities
with float can be delayed without impacting the project end date, allowing for
better resource management and scheduling.
Calculate Float

12 D 22
4 B 12 12 10 22
4 8 12 Float=0
Float=0 34 H 39
0 A 4 10 E 17 22 G 34
34 5 39
0 4 4 15 7 22 22 12 34
4 C 10 Float=0
Float=5 Float=0
Float=0 7 6 13

Float=3 10 F 19
13 9 22
Float=4
Determining
Critical Path:

1 Identify activities with zero float

2 Critical Path Sequence


The Critical Path consists of the activities
with zero float, in the order they occur
from start to finish:
A→B→D→G→H

3 Total Duration of Critical Path:


Total Duration = 4 + 8 + 10 + 12 + 5 = 39 days
Determining Critical Path

12 D 22

h
at
12 10 22
lP
iti
ca 4 B 12
4 8 12 Float=0
Cr

Float=0 34 H 39
0 A 4 10 E 17 22 G 34
34 5 39
0 4 4 15 7 22 22 12 34
4 C 10 Float=0
Float=5 Float=0
Float=0 7 6 13

Float=3 10 F 19
13 9 22
Float=4
Conclusion:
The Critical Path for this project is: A → B → D → G → H
The total duration of the project, based on the critical path, is 39
days.
Activities with non-zero float (e.g., C, E, F) can be delayed without
affecting the overall project timeline, but any delay in the critical
path will directly impact the project completion.
End

Thank you
Do you have any questions?

You might also like