Worked Examples
Worked Examples
Cost Variance: CV = EV – AC
Cost Performance Index: CPI = EV/AC
Schedule Variance: SV = EV – PV
Schedule Performance Index: SPI = EV/PV
Schedule Variance (SV)
Schedule Variance shows the difference between where we planned to be and where we are
actually in the schedule. In fact, it tracks whether we are behind, ahead or on schedule with the
project. Schedule Variance is calculated as a difference between Earned Value and Planned
Value.
SV = EV – PV
SV= – $500
2. EV = $3,000 PV=$2,000
SV = $3,000-$2,000
SV=$1,000
3 EV = $3,000 PV=$3,000
SV=$3,000 – $3,000
SV=0
SPI=EV/PV
For example,
EV=$3,000 PV=$3,500 SPI=$3,000/$3,500 SPI =0.85
In this example, SPI is 0.85, and the task is 28% behind schedule.
For example,
EVpert=$3,000 PV=$2,500 SPI=$,3000/$2,500 SPI=1.2
In our example, the SPI is 1.2 which means that the task is 40% ahead of schedule.
For instance,
EV= $3,000 PV=$3,000 SPI=$3,000/$3,000 SPI=1
Cost Variance is the difference between what was planned to spend, and what was actually
spend. It shows the amount of the value that you earned on an activity and the actual cost that
was required to performed that task. The Cost Variance shows the project manager how far the
task is over, under, or on budget.
CV = EV – AC
For instance,
EV = $3,000 AC= $3,500 CV = $3,000 – $3,500 CV= – $500
For instance,
EV=$3,000 AC=$3,000 CV=$3,000-$3,000 CV=0
Cost Performance Index is the rate at which project performance is meeting planned costs during
a specific period of time. It shows project managers not only how much money is spending to
deliver a project, but also how well that money is spent. CPI is calculated as a ratio of the Earned
Value to the Actual Cost.
CPI= EV/AC
For example,
EV = $3,000 AC = $3,500 CPI = $3,000/$3,500 CPI= 0.85
In this example, CPI is 0.85 which means that the task is 28% over budget.
For example,
EV=$3,000 AC =$2,500 CPI=$3,000/$2,500 CPI =1.2
In our example, CPI is 1.2 which means that the task is 40% under budget.
A. 350
B. -75
C. -50
D. 400
3. You are a new project manager for your organization. Your project has a
BAC of $250,000 and is expected to last 10 months. Currently, the project is
in month six and is 40 percent complete, but the project was expected to be
60 percent complete by this time. You have spent $125,000 to complete the
work. What is the cost performance index of the project?
A. 0.66
B. 1.25
C. 2
D. 0.8
. You are a Senior Project Manager in your organization and a newly hired
Junior Project Manager comes to you for advice on how to calculate PERT for
their newly assigned project. For PERT analysis, what durations are required?
. You are the Project Manager on a merger and acquisition project. Activity A
(3 days) and activity B (4 days) can start immediately. Activity C (2 days) can
start after A and B are complete. Activity D (5 days) can begin after activity
B is complete. Activity E (6 days) can begin after activity B is complete.
Activity F (4 days) can begin after activities C and D are complete. Activity G
(5 days) can begin after activities D and E are complete. Activity H (4 days)
can begin after activities F and G are complete. What is the float of activity
D?
A. 1 day
B. 2 days
C. 4 days
D. Not enough information