Pump Maintenance

This method statement outlines the procedure for the removal, inspection, maintenance, and installation of a pump at the Utility Plant, scheduled for October 14, 2024. The process includes steps such as shutting off power, disassembling the pump, conducting repairs, and testing the pump before handover. A standby pump will be operational during maintenance, and a Hot Work Permit may be required.

Uploaded by

Junaid Manzoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views1 page

Pump Maintenance

This method statement outlines the procedure for the removal, inspection, maintenance, and installation of a pump at the Utility Plant, scheduled for October 14, 2024. The process includes steps such as shutting off power, disassembling the pump, conducting repairs, and testing the pump before handover. A standby pump will be operational during maintenance, and a Hot Work Permit may be required.

Uploaded by

Junaid Manzoor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

METHOD OF STATEMENT

Field Below should be prepared by TAMIMI


Work Package Title: Removal,inspection,maintenance and installation of a pump.
Identification Code: Drawing Title: N/A Drawing Title: N/A Revision: N/A
Task Date: Oct 14, 2024 Start:Oct 14, 2024 Finish: Oct 14, 2024 Location: Utility Plant
TAMIMI - Mechanical Engineer Junaid Manzoor

Work Procedure: To remove, inspect,repairing and installation of a pump.

1. Shutting off the power supply.


2. Lock out/Tag out procedure is applied to the control panel.
3. Isolate the suction and discharge valve.
4.Remove the electrical power cable of motor.
5. Disassemble pump and motor and inspect in the workshop
6. Repair the pump if required.
7. Assemble the pump and motor after inspection and maintenance.
8. Installing the motor electrical power cable.
9.Pump and motor testing and hand-over to operation team.
10. Observing the performance of the new pump while running .
11.If the electrical ampere and voltage are stable continue run pump.
12.House keeping of pump area.
13.Job is done.

Shutdown duration: 1 Day


Impact of Pump Maintenance:
Pumpwill be out of service during the maintenance.
Solution for Impact: Standby pump will be operational during the repair of pump.

The work will be done at Utilty Plant.


ManPower Materials Tools
Engineer, Supervisor, Pump 1. Sand Paper Lifting Belt, Chain block, Forklift, Boom
Technician, Pipe Fitter, 2. WD-40 Truck(if Applicable), pipe wrench,
Electrician, Maintenance 3. Hand Gloves Spanner set, multimeter tester ,
Labors. 4. Cotton Rags warning tape, barricade, Mechanic Tool
kit, Grinder, Gas Detector(if Applicable).

TAMIMI COMMENTS:
This maintenance activity requires a Hot Work Permit and Confined Space(if Required).

Saudi Aramco Project Team will fill out below information:


Inspection Required
Item / Tasks Delivery Note Materials Task Preparation Task Completion
Status (Pass/Fail)

Saudi Aramco Comment

Prepared By (TAMIMI) Reviewed By (TAMIMI) Reviewed & Approved By (Saudi Aramco Representative):
Name: Junaid Manzoor Name: Edmund Britanico Name: Mr. Yahya Saad
(Mechanical Engineer) (Plant Manager) Date:
Date: Date: Signature:
Signature: Signature: