Nit Part C
Nit Part C
PART–C
Scope and Technical Specifications of Electrical and
Mechanical Services
INDEX
PROFORMA OF SCHEDULES
SCHEDULE A TO F (E & M WORKS) MINOR COMPONENT
(OPERATIVE SCHEDULES TO BE SUPPLIED TO EACH INTENDING BIDDER)
(Separate Performa for Civil &, Elect in case of Composite Tenders)
(Operative Schedule to be supplied separately to each intending Tenderer)
SCHEDULE ‘A’
Schedule of financial quote combined rates for Civil, Electrical & Horticulture works and ancillary
works as per page 435.
SCHEDULE ‘D’ Extra schedule for specific requirements/documents for the work, if any.
-NIL-
SCHEDULE ‘E’
Reference to General Conditions of Contract: General Conditions of Contract 2024 for EPC
Projects in CPWD as amended / modified up to previous day of the last date of submission of Bid.
Name of Work: Construction of 100 Bedded ESIC Hospital Building i/c 32 Nos Staff Quarters at Marshal Pitch,
Kanker Khera, Meerut (UP) in EPC Mode -I. SH: Planning, Designing and Construction of various RCC Buildings for
setting up of a 100 bedded Hospital along with ancillary buildings viz. Canteen Mortuary block, Gas store, LT panel cum
substation, Pump room , AC Plant room, STP, Security room, 32 nos. staff quarters (Type-II-16 nos., Type-III-8 nos., Type-
IV-6 nos., Type-IV Special – 2 nos.) including Internal Water supply, Sanitary Installations, Drainage, Development works
like UG Sumps, Terrace water Tanks, Water Treatment Plant (RO plant), Rain Water Harvesting System, Internal Roads,
Pathways, Parking facilities, Water Supply Lines, Storm Water Drains, External Sewerage System, Service Trenches and
Horticulture Work all E&M Services such as Internal Electrical Installations, Fire Alarm System, Firefighting system, Lifts,
Sub-Station, DG sets, UPS, HVAC System, Solar Water Heating System, Water Supply Pumps, CCTV, IBMS, LAN IP
based EPABX System, Studio Visual System, Boom Barriers, STP & ETP Equipment, Medical Gas Pipe System, Nurse
Call System, Street Lighting with LED, Modular Operation Theatre, Illuminated Signages, Non-Medical Equipments &
other Misc. works all complete on Engineering, Procurement and Construction basis including development of BIM
models.
Officer inviting bid: Executive Engineer Meerut Division, CPWD, Income Tax Office Campus,
Bhainsali Ground Meerut (UP)-250001.
Definitions:
2(vi) Engineer-in-Charge for Civil works Executive Engineer Meerut Division, CPWD,
Income Tax Office Campus, Bhainsali Ground
Meerut (UP)-250001
Engineer-in-Charge for Horticulture DD(H), CPWD, Division- Lucknow.
Works
2(viii) Accepting Authority Chief Engineer (GZB) C.P.W.D, CGO -1, Hapur
Road Ghaziabad Uttar Pradesh (201002)
2(x) Percentage on cost of materials and 15%
labour to cover all overheads and profits
2(x)(b) Standard Schedule of Rates DSR 2023 and Plinth area rates 2023(Civil +
Civil work, Electrical + Horticulture) with amendments up to
the previous date of the last date of submission of
bids.
9(ii) Standard CPWD contract Form GCC General Conditions of Contract-2024 for EPC
2024, CPWD Form as modified & Projects in CPWD corrected up to the previous
corrected up to date. date of the last date of submission of bids.
Clause 1
i) Time allowed for submission of Performance
Guarantee, Programme Chart (time and 07 (Seven) days
Progress) and applicable labour Licenses,
registration with EPFO, ESIC and BOCW
Welfare Board or proof of applying thereof
from the date of issue of Letter of acceptance.
Clause 2
(i) Authority for fixing compensation under Chief Engineer (GZB) CPWD, CGO -1,
clause 2 Hapur Road, Ghaziabad (U.P.)
Clause 5
(i) Authority to convey the decision of Executive Engineer Meerut Division, CPWD,
shifting of milestone and extension Income Tax Office Campus, Bhainsali Ground
of time. Meerut (UP)-250001
(ii) Authority to decide rescheduling of Chief Engineer (GZB) CPWD, CGO -1, Hapur
milestone and extension of time. Road, Ghaziabad (U.P.)
(iii) Authority to decide shifting of date Chief Engineer (GZB) CPWD, CGO -1, Hapur
of start in case of delay in handing Road, Ghaziabad (U.P.)
over of site.
Note: Withheld amount shall be released if and when subsequent milestone is achieved within respective time
specified. However, in case milestones are not achieved by the Bidder for the work, the amount shown against
milestone shall be withheld.
Monthly recovery for delay in submission of the monthly progress report within specified period Rs. 50,000/-
per month for each month default
Part Portion of Design Description Time Period for issue of design reckoned
from date of receipt of tenders
Part A Portion already Available
included in NIT
Part B-1 Portions of To be ---
Architectural submitted by
Designs to be issued bidder for
Part B-2 Portions of Civil approval of
Designs to be issued Engineer-in-
Part B-3 Portions of E&M charge
Design to be issued
Clause 7
Gross work to be done together with net payment Rs. 1.00 Cr.
/adjustment of advances for material collected, if
any, since the last such payment for being eligible
to interim payment
Clause 7A
(i) Whether clause 7A shall be applicable. Yes
Clause 8
Clause 11
Specifications to be followed for Civil work: CPWD Specifications 2019 Volume- I &
execution of work II with corrections slips up to the previous date of the
last date of submission of bids.
CPWD Green Rating Manual 2021 with correction
slips up to the previous date of the last date of
submission of bids.
CPWD Hand book on Safety, Health and
Environment with correction slips up to the previous
date of the last date of submission of bids.
CPWD Manual on Accessible Built Environment
2019 with correction slips up to the previous date of
the last date of submission of bids.
Electrical work:
CPWD General Specification for Electrical Works
Clause 12
Deviation limit beyond which clause 12.2 As per GCC for EPC Projects- 2024
and 12.3 shall apply for building work
Clause 16
Competent Authority for deciding reduced Chief Engineer (GZB) CPWD, CGO -1,
rates. Hapur Road, Ghaziabad (U.P.)
Clause 25
(i) Conciliator: ADG(RL), CPWD or his successor thereof.
(ii) Arbitrator appointing authority: Chief Engineer (Ghaziabad), CPWD or his successor
thereof.
(iii) Place of arbitration Meerut
Clause 32
“Requirement of Technical Representative (s) and Recovery Rates”
S.No. Requirement of Technical Minimum Designation of Rate at which
Staff Experience Technical Staff recovery shall be
(Years) made from the
Strength
contractor in the
(Major
event of not
Qualification + Minor
fulfilling provision
compon
of clause 36 (i)
ent)
Graduate
Engineer
1
Graduate
Engineer
2
Graduate
Engineer
4
Diploma
Engineer
5
Graduate
Engineer
6
Clause 38
(i) (a) Schedule/statement for determining theoretical quantity of cement & bitumen on the basis of
Delhi Schedule of Rates 2023 printed by CPWD with up-to-date correction slips till last date of
submission of tender.
The scope of work includes Planning, Design, preparation of Drawings, Supply, Installation,
Testing and commissioning of following E&M services for 100 bedded Hospital, Sub-station
building and other small buildings i/c 16 nos Type-II, 8 Nos Type-III, 6 Nos Type-IV and 2
Nos Type-IV S Residential Qtrs at ESIC, Meerut, Uttar Pradesh.
3. Miscellaneous
Gas manifold store 136.30sqm
Mortuary 102.40 sqm
Bio medical waste 114.37sqm
DG set /Panel room 207.79 sqm
Utility 91.62 sqm
STP block 162.22 sqm
WTP block 45.81 sqm
Canteen and Cafe 147.58 sqm
Guard room (3 nos) 52.50 sqm
LPG store 37.46 sqm
UG tank 172.42 sqm
1. Internal Electrical Installations i/c Street light, emergency light, Illuminated signages
Scope of this sub head covers Design and execution of Wiring for Internal Electrical
Installations i.e., Light & fan points, Light plug & Power plug wiringwith modular accessories
as per the requirement, Telephone, CCTV & LAN Conduiting. Providing LED light fittings,
Ceiling fans, Exhaust & Fresh Air fans etc. Electrical connections to all E & M equipment,
various Hospital Services including cabling, TTA main panels, Floor panels, Lightning
protection, Structural Earthing system, Street/Compound lighting, landscape lighting are part
of the scope. Dimmable light fittings with smart control shall be provided in conference halls,
meeting rooms, Director room and other important locations as decided by the Engineer-in-
charge with lighting controls. All luminaries used shall be energy efficient LEDs. The Rising
Mains for Emergency supply(DG supply) and UPS supply shall be designed based on
maximum connected load and 10% additional capacity. i/c complete wiring, fans, fitting for
all Residential Qtrs., metering panels, cabling & associated misc. works. If any item required
to make the building / scheme habitable and functional, is not specifically mentioned in the
scope of services, the same is deemed to be included within the scope of this tender and
nothing extra shall be paid on this account.
Design and preparation of inventories, detailed layout drawings with marking of individual
power plugs, light circuits, power circuits, submains etc. shall be done. Design and selection
of Electrical fixtures to get the required illumination (lux level calculation at various places),
2. Firefighting:
Design and installation of Fire Fighting system with wet riser with sprinklers for the Hospital
buildings and other service buildings, Water Curtain Systems wherever required, Fire
sealing of floors in all shafts is in the scope of work. Electric & Diesel Fire pumps, internal
& external fire hydrants, FBC, Portable fire extinguishers, Gas suppression system for
Server Rooms, Spirit Store, LPG Bank, Electrical panels and other areas of the Hospital
shall be provided as per the requirement of NBC 2016 with up-to-date amendments, Fire
bye- laws of Govt. of Uttar Pradesh and CPWD specifications. This will also include
peripheral header /ring mains and isolation of ring mains in the header around the building,
the provision of testing valve in the fire pump house with the facility to transfer the water
again into the fire sump to avoid wastage of water, isolation valve in the feeder pipeline to
each wet riser in the building before entering to the building. Preparation of inventory,
preparation of detailed layout drawings with marking of various firefighting accessories/
equipment i.e., location of sprinklers, water curtains, internal & external hydrants are in the
scope of work.
3. Automatic Fire Alarm System & PA System
Design, installation of Intelligent addressable automatic fire alarm system complete with
detectors, addressable fire alarm panel and all other related accessories, Fire Dampers,
AHUs, Smoke Ventilation System, Public Address System and Gas suppression system
as required in the Hospital Building, and other buildings i/c residential building in
compliance to the requirements of relevant CPWD specifications, fire services norms of local
body and NBC 2016 whichever is more stringent. This includes installation of Digital Public
Address System, fire evacuation system/ plan in the fire control room and at each floor of the
Hospital building. The wiring for the detectors shall be done with armored copper conductor
fire survival cable. Braille signages and all requirements of accessible India Campaign and
Fire norms should be met. Preparation of inventory, preparation of detailed layout drawings
with marking of Detectors, MCPs, fault isolators, hooters /speakers, Main panel, repeater
panel, various fire alarm accessories are in the scope of work.
4. Lifts:
lifts (9 Nos) Bed cum 20 Passenger Hospital lift – 2 Nos, 13 passenger hospital lift – 3 Nos,
13 passeneger residential lift – 4 Nos with speed of 0.75 /1 meter per second, stainless steel
car interior and doors, ARD, Barrier free features, LT Panel, Cabling, Earthing,
Architrave work at Lift Entrance and as per following details is in the scopeof work.
5. Substation:
Scope of this sub head covers Design and execution of 33 KV/0.433 KV Sub station of
with Dry type transformers of (2x1000 kVA capacity) 1 working and 1 standby for Hospital
and other non- residential buildings, comprising of HT VCB Panel, HT Cables, LT Cables
MV TTA Main Panels, Essential Panels, surge protection system, Sandwich Type Bus
trunking, Safety equipment, LT distribution to various E & M services. Planning and design
comprising of calculation of electrical load complete with EI & Medical and other equipment
loads of the building and electrical load of AC Plant and other E&M equipment and
The sizes of cables shall be designed by taking the additional load of 25% for future
extension. LT Panels shall be designed for essential and UPS supply. APFC Panel for
each transformer shall be provided to improve power factor to a minimum 0.99 lagging.
Suitable size of sandwich type compact bus trunking between transformer/DG Sets to
different essential and non-essential panels is in the scope of work. Earthing for System and
safety of equipment shall be provided as per CPWD specifications/IE rules.
6. DG Sets:
Scope of this sub head covers Design and execution of DG sets with minimum capacity of 2
X 250 KVA (Hospital building) & 1 x 125 KVA (Residential Building), 415 V, silent type D.G.
Sets, AMF panel complete with Automatic load transfer facility /synchronization panel, Bus
Trunking from DG Set Synchronization panel to main LT panel, control cables, Earthing of
DG Sets, exhaust piping as per CPCB norms with statutory approvals i/c
supporting structure /arrangement is in the scope of this work. The facility of manual bye-
pass arrangement from the normal supply shall be in the scope of the work in case of failure
of AMF panel. Planning and design comprising of making SLD for the distribution system,
Calculation of essential load, sizes of cables /bus trunking, layout of the equipment as per
site condition, submission of data sheets and catalogues of various equipment in support of
their design is also in the scope of this work. Earthing and safety of equipment shall be
Provided. Diesel sump (UG tank) of required capacity with pumping arrangement shall be
made as per approved Central/ State fire norms.
7. UPS:
Provision of minimum 1 x100 KVA (for Hospital Building) (Parallel redundant with 2 or more
units in parallel) 3 phase Modular type UPS supply with 30 min. battery backup is in the
scope of this work. Planning and design comprising of detailed calculations, distribution
system for UPS with the sandwich copper vertical rising mains in the Hospital Building
complete with tap-off boxes, cables, distribution boards on every floor and as per the
requirement of NBC 2016. Preparation of SLD, submission of data sheets and catalogues of
the various equipment in support of their design is in the scope of this work. VRLA Sealed
maintenance free batteries shall be provided on a suitable size of rack.
Scope of this sub head covers Design and execution of HVAC system. Capacity of HVAC
system shall be based on heat load calculations of the hospital building but minimum
capacity shall be 3 x 100 TR water cooled screw type chillers with VFD (2 working+ 1
standby). HVAC plant with high & low side equipment, water cooled chilling machines,
condenser & chilled water Pumps with standby, cooling towers with standby shall be
Number of AHUs may be provided to optimize duct size and false ceiling height. Double skin
AHUs to maintain indoor air quality, Motorized Fire dampers, electrical panels with controls,
cabling, bypass arrangement shall be provided. Dedicated double skin AHU for each OT
with HEPA Filter, Separate coils for chilled water and
heaters for humidity control shall be provided. Factory fabricated Aluminium ducting shall be
provided.
Cooling tower shall be designed by taking minimum 25% additional capacity as that of
chiller. Planning and design of supply and return air duct complete with dampers, chilled
water and condenser water pipelines. Layout of various equipment of HVAC system and
accordingly designing the space to install the units.
Pressurization of Staircases, Lift shafts and lobbies with pressurization fans, ducting, Control
Panels, cabling. Smoke evacuation and mechanical ventilation System for basements,
service duct for fire conditions and for normal exhaust should be as per NBC 2016/ CPWD
Specifications shall be designed. Kitchen ventilation, Mortuary is also part of the ventilation
system to be provided. Design and estimation of proper ventilation system from user comfort
as specified in relevant codes, specifications and also from fire safety point of view.
Marking of various supply/return air griles, ducts, Chillers, Cooling towers, AHUs, FCUs,
Electrical Panels, Mechanical ventilation system etc. on the architecture drawings,
preparation of inventory is in the scope of work.
Scope of this sub head covers Design and execution of Solar water heating system having 5
nos minimum capacity 1000 LPD (Total capacity 5000 LPD) based on a closed-circuit
indirect heat transfer system and capable of producing hot water at 60 deg C. The areas
which are catered by the hot water are Labour Complex including NICU, PICU, Kitchen,
Canteen, CSSD, ICUs and other areas as per Hospital requirement.
Scope of this sub head covers Planning, Designing, Supply, Installation, Testing and
commissioning of LAN system comprising of core switches & L2 switches with 10G, 10 giga
SFP modules, WIFI access points, WIFI controller, network management software, racks,
CAT 6A cable, patch panels, OFC etc.with software license.
Scope of this sub head covers Planning, Designing, Supply, Installation, Testing and
Scope of this sub head covers Design and execution of IP based CCTV system for building
security comprising of PTZ, Fixed Bullet and Dome camera, NVRs of suitable
capacity with viewing and recording facility, cabling, display system using required number
of FHD LED Monitors at control room as per the requirement complete with various
hardware and software supports. The complete networking for the CCTV should be separate
and exclusive for CCTV System only and not to be mixed with other LAN System. Software
provided shall support for remote monitoring through PCs i/c CCTV system basic home
security for residential colony.
Scope of this sub head covers Planning, Designing, Supply, Installation, Testing and
commissioning of Audio Visual / Conference system with Microphones, Speakers,
Amplifiers, mixers, Digital signal processors, Display TV units, Cameras, cables, controllers,
Software etc. in Conference halls & Seminar hallsas per detailed specifications.
14. STP: (Sewerage Treatment Plant)
Scope of this sub head covers Design and execution of STP, marking of pump sets, tanks,
sumps etc. on the architectural drawing is in the scope of work. STP of minimum 50 KLD
capacity based on the MBBR technology with Sump Tanks, Pumps, Vessels, Air Blowers,
Piping, UV System, Electrical control panels etc. for treatment of Bio medical waste from
OTs/Labs, infected waste water and normal waste water. The plant should be capable of
catering the mandatory requirements of CPCB. Permission to establish and operate STP
shall be taken from the local statutory bodies/CPCB, which is within the scope of the
contractor.
Scope of this sub head covers Design and execution of Medical Gas Pipeline System (as
per international standards) for total 100 Beds ESIC hospital comprising of LMO plant,
Oxygen, Carbon dioxide, Nitrous oxide, AGSS, Air-4, Air- 7, Vacuum outlets, Manifolds,
Pressure alarms, Fully automatic Gas control system, Bed head panels, Copper piping,
Gas Manifold & Compressor system, Vacuum system, Control panels, Safeties, Valves,
cylinder banks, plant equipment such as Air compressors, Vacuum pumps etc.
Scope of this sub head covers Design and execution of Modular Operation Theatres and
each modular OT comprising of anti-microbial, intensive infection control environment,
sterile panel walls & ceiling system with Solid Mineral Surface technology for operating
area, steel framework, seamless conductive antistatic dissipative flooring, clean air laminar
flow, double dome OT Light, touch screen surgeon's control panel, electrical isolation and
distribution system with Suitable capacity UPS, scrub station, X-ray viewing screen, hatch
box, hermetically sealing automatic sliding doors, anesthesia & surgeon pendants with fully
motorized pneumatic braking system etc. complete as required.
Scope of this sub head covers of planning, design & preparation of drawings, supplying,
installation, testing & commissioning of Nurse Call System for 100 bedded Hospital. Total
system has to be commissioned with required hardware, software, licenses and other items
to have a fully functional complete Nurse Call System. If any item is required to make the
scheme functional, is not specifically mentioned in the scope and specifications, the
same is deemed to be included within the scope of this tender.
18. Water Supply System & R.O. plant with water coller.
Scope of this sub head covers Design and execution of water supply pump sets to fulfill the
requirement of water for the Hospital building & other services in the campus i/c Residential
buildings. At least 3 Nos Submersible pumps shall be provided in bore wells with 1 number
of the same capacity bore well pump shall be kept as standby. Hydro- pneumatic pumps
with standby for supply of drinking water and flushing water is also in the scope of work.
Standby pumps of same type and capacity shall be provided in each bank of pumps.
2 Nos. (1 for each block) R.O. plant each of minimum 500 LPH capacity shall be provided for
drinking water and Hospital requirement such as OTs, labs etc. In addition, double stage
R.O. water filter shall be provided in the dialysis room.
42 Nos. stainless steel water coolers of minimum 40/ 80 litres capacity shall be provided in
all floors of the hospital.
1. General :-
Scope of this sub head the contractor shall provide and install the following Non-Medical
Equipments for 100 Bedded Hoispital building as per the NIT, Detailed Architectural
drawings as directed by Engineer-in-Charge. The contractor shall prepare a detailed floor
wise & room wise layout plan marking the locations of Non-Medical Equipments, Inventory
with quantity. Proposed scheme as per relevant specifications shall be submitted by the
bidder before execution of work and the same shall be checked and approved by CPWD and
Hospital authorities.
2. The Technical Specifications for Non-Medical Equipments are given in Bid Document.
i) Washer Disinfector horizontal rectangular with glass sliding door, fully automatic,
microprocessor controlled mechanical washer , chamber capacity 250 Ltr of size-
550(W) x 550(H) x 550(D) mm i.e. 22” (W) x 22”(H) x 22”(D) i.e. 6 DIN Trays.
iii) Washing station have three washing sinks and one slop for draining, having over
all dimension of 60” x 20” x 40” (L x W x H).
iv) Air Gun & Water Gun Unit- without Compressor, 0.5 HP Pressure pump.
v) Hot Sealing Machine have Power Consumption - 0.5 kW, Sealing Speed - 0-
12m/min, Sealing Width - 8-10m.
vi) Floor mounted Storage Rack of 5 Nos fixed shelves built in stainless steel SS
304 of size - 900mm (L) X 450mm (W) X 1800mm (H).
vii) Stainless steel Closed Transport Trolley-Green Strips for Sterile goods, Size- 900
x 600 x 1200mm (H).
viii) Steam Steriliser having Chamber Capacity 250 Ltr Horizontal cylindrical Steam
Steriliser Pressure type for Hospital and Pharmaceutical use, Steriliser, Chember
size dia - 500mm x 1250 mm.
b) Laundry equipments :-
If any equipment required to make the kitchen & canteen functional, is not specifically
mentioned in the scope of services, the same is deemed to be included within the scope
of this tender and nothing extra shall be paid on this account.
ii) I.V. Tree system 5-Point hanger with 150 mm TRACK surface mounted
aluminum I.V. Track for 100 bedded hospital.
1. The Main Contractor should either himself meet the eligibility conditions for the
respective E&M components or otherwise he shall have to Associate with Agencies,
fulfilling the eligibility requirements mentioned below and consent letter from at least one
eligible Associate Agency of the respective components of E&M work shall also be
submitted as per attached Form.
2. The Main Contractor shall also be eligible to carry out himself any or all of these works
without associating with any specialized agency, provided, he directly procures the
equipment of approved make from manufacturer and gets it installed from Authorized
Agency/Service Provider of the Manufacturer/ Specialized Agency as per the eligibility
criteria mentionedbelow.
3. The Main Contractor has to submit the following documents for Association of Contractor
within one month of award of work. In support of the eligibility conditions of the proposed
Associated Agency copy of their registration documents, Verifiable completion certificates
of the work, Electrical Contractor’s License, GST Documents duly attested by the Main
Contractor shall be submitted to the EE& SM(C)-I, CPWD who will in turn submit these
documentsto the EE & SM(E) for deciding the eligibility.
4. Each such Associated Agency will certify that they are not debarred, as on the day of
submission of documents. Proposal for Associating Agency for minor components of
work shall be submitted with consent letter from each Associated Agency independently for
all Electrical and Mechanical components. The Main Contractor shall submit an Affidavit
of MOU signed with eligible Associated Agencies. The Affidavit of MOU in the enclosed
Form shall be signed by both the parties i.e., Main Contractor as first party and
Associated Agency as 2nd party. MOU for all Electrical and Mechanical components
shall be submitted, independently.
5. In the event of the concerned E&M Agency not performing satisfactorily or failure of
Associated Agency to complete the E&M work, the Main Contractor on written directions of
the department, shall remove the Associate Agency, deployed on the work and shall
submit name of new Associate who fulfills the conditions mentioned in NIT to execute
the left-over work without any loss of time or variation in cost to the department.
6. Such Associates shall also give an undertaking along with the Main Contractor that, both
of them together will stand guarantee for the equipment already supplied for which
payment has been released by the department. If any equipment supplied for the work,
during the currency of the earlier Associate Agency becomes redundant /not in a
position to be put to beneficial use, the main contractor shall be liable for replacement of
the equipment(s) at no cost to the Department. No change of Associated Agency will be
allowed without priorapproval of the Engineer-in-charge of the work.
7. In respect of all E & M works, the materials shall be procured only from the original
equipment Manufacturers / Authorized dealers of OEM. The contractor shall submit all
documentary details in fulfillment of these conditions regarding procurement of materials
including relevant test certificates.
8. Executive Engineer (E) shall be the Engineer-in-charge for E & M works. Separate
tender schedule and Special Conditions for E & M Work are appended with this tender.
It will be obligatory on the part of the Contractor to sign the tender documents for all
the component parts.
9. The Main Contractor shall be responsible and liable for proper and complete execution
of the E & M works and ensure coordination and completion of both civil and E & M
work. The Associated Agency shall attend the inspection of the work by the Engineer-
in-charge of E&M works as and when required.
10. The Associated Agency should have successfully completed similar works including
capacity of the equipment required as applicable during the last 7 years ending up to
previous day of last date of submission of tenders. The value of executed works shall be
brought to current costing level by enhancing the actual value of work at simple rate of
7% per annum, calculated from the date of completion to the last date of submission
of bid.
11. The completion certificate shall be issued by an officer not below the rank of Executive
Engineer or equivalent, duly attested. The rough cost and capacity of various Sub
heads/Equipment given in the Eligibility criteria should not be used or interpreted for any
other purpose.
Minimum Eligibility Criteria for Associated Agency for Execution of E&M Components
and Specialized Works wherever applicable
Component
Sl. Approx cost in
of E&M Eligibility
No INR (cr.) of
works
Estimate cost
put in tender
1 Internal The Contractor having successfully completed
Electrical Three similar works, each of value not less than
Installations, 12.94 40% of Estimated component cost
Street OR
Lighting etc. Two similar works, each of value not less than
60% of Estimated component cost
OR
One similar work, each of value not less than
80% of Estimated component cost
Similar work shall mean "SITC of Internal
Electrical Installations,Street Lighting etc.”
2 Fire Fighting 2.50 The Contractor having successfully completed
System Three similar works, each of value not less than
40% of Estimated component cost
OR
Two similar works, each of value not less than
60% of Estimated component cost
OR
One similar work, each of value not less than
80% of Estimated component cost Similar work
shall mean "SITC of FireFighting System”
5 Substation 1.99 Three similar works each of value not less than
40% of the estimated cost put to tender with
capcity of individual transformer being 80% of
individual capacity (rounded off to next available
higher capacity) of the equipment i.e. transformer
proposed in NIT.
OR
Two similar works each of value not less than
60% of the estimated cost put to tender with
capcity of individual transformer being 80% of
individual capacity (rounded off to next available
higher capacity) of the equipment i.e. transformer
proposed in NIT.
OR
One similar works each of value not less than
80% of the estimated cost put to tender with
capcity of individual transformer being 80% of
individual capacity (rounded off to next available
higher capacity) of the equipment i.e. transformer
proposed in NIT.
Similar work shall mean "SITC of
Substation equipment"
Name of Work: Construction of 100 Bedded ESIC Hospital Building i/c 32 Nos Staff Quarters at Marshal Pitch, Kanker
Khera, Meerut (UP) in EPC Mode -I. SH: Planning, Designing and Construction of various RCC Buildings for setting up of a
100 bedded Hospital along with ancillary buildings viz. Canteen Mortuary block, Gas store, LT panel cum substation, Pump
room , AC Plant room, STP, Security room, 32 nos. staff quarters (Type-II-16 nos., Type-III-8 nos., Type-IV-6 nos., Type-IV
Special – 2 nos.) including Internal Water supply, Sanitary Installations, Drainage, Development works like UG Sumps, Terrace
water Tanks, Water Treatment Plant (RO plant), Rain Water Harvesting System, Internal Roads, Pathways, Parking facilities,
Water Supply Lines, Storm Water Drains, External Sewerage System, Service Trenches and Horticulture Work all E&M
Services such as Internal Electrical Installations, Fire Alarm System, Firefighting system, Lifts, Sub-Station, DG sets, UPS,
HVAC System, Solar Water Heating System, Water Supply Pumps, CCTV, IBMS, LAN IP based EPABX System, Sudio Visual
System, Boom Barriers, STP & ETP Equipment, Medical Gas Pipe System, Nurse Call System, Street Lighting with LED,
Modular Operation Theatre, Illuminated Signages, Non-Medical Equipments & other Misc. works all complete on Engineering,
Procurement and Construction basis including development of BIM models.
1. I/We shall execute the work as per specifications and conditions of the agreement and as per directions of the
Engineer in-Charge for the corresponding minor work till the completion of the work.
2. I / We shall be responsible for necessary action to handover the installations and for rectification of defects and
repair during the warranty period.
3. Also, I / We shall employ full time technically qualified Engineer / supervisor for the minor component of the work
as required for the work. I/ We will attend inspection of officers of the department as and when required.
Dated:
Address: Address:
Telephone: Telephone:
e-mail: e-mail:
2) M/S [Name of the firm with full address] [Hence forth, called Associated
Agency]
Nameof
sub-work:…………………………………………
We state that M.O.U between us will be treated as an Agreement and has legality as per
Indian Contract Act [amended up to date] and the Department [CPWD] can enforce all
the terms and conditions of the Agreement for execution of the above work. Both of us
shall be responsible for the execution of work as per the Agreement to the extent this
MOU allows. In case of any dispute, either of us will go for mediation/arbitration by the
concerned SE/CE and any of us may appeal against the mediation/arbitration to the
SE/CE. His decision shall be final and binding on both of us.
We haveagreedas under:
1. The Associated Agency will execute all the Electrical & Mechanical works in the
wholesome manneras per terms and conditions of the agreement. The Associated
Agency shall be paid by Main Contractor as per standard procedure followed by
the Department and the Agreement between parties. Any type of internal
transaction between the Associated Agency and the Main Contractor shall be as per
their convenience and mutual understanding without involving the department.
2. The Associated Agency shall be liable for disciplinary action if he is failed to
discharge the action[s] and other legal action as per agreement.
3. All the machinery and equipment, tools and tackles required for execution of
theelectrical works, as per agreement, shall be the responsibility of the Associated
Agency.
4. The site staff required for the electrical work shall be arranged by the Associated
Agency as per terms and conditions of the agreement.
5. Site order book maintained for the said work shall be signed by the main contractor
as well as by the Engineer of the Associated Agency and by Associated
Contractorhimself.
6. All the correspondence regarding execution of the Electrical & Mechanical works
shall be done bytheDepartment with theAssociated Agency with a copytothe Main
Contractor. In case of non-compliance of the provisions of agreement, the main
contractor, as well as the Associated Agency shall be responsible. The action under
clauses 2 and 3 shall be initiated and taken against the main contractor.
1. The proposed ESIC Hospital Building at Tuticorin comprises of 3 Blocks and other
buildings, shall be designed and constructed to achieve Green Plus level certification
of GHAR based on CPWD green rating manual 2021. Hence all the proposed E&M
equipment shall meet the requirements for achieving the same. All the E&M fittings,
fixtures, machinery and equipment proposed to be used in the execution shall
confirm to ‘5 Star’ rating under star labeling program of Bureau of Energy Efficiency
(BEE) wherever available. Machinery and equipment which does not fall under star
labeling program of Bureau of Energy Efficiency, shall meet Super ECBC 2017
(Upton date) norms.
2. All buildings shall be designed for people with disability (PWD) as per the latest
norms of Govt of India.
3. The information and data shown in the drawings and mentioned in the tender
documents are furnished for general information and guidance only. The Engineer-in-
Charge in no case shall be held responsible for the accuracy thereof or/and
deductions, interpretations or conclusions drawn there from. No claim shall be
entertained whatsoever on this account, if the site conditions/ information is different
or otherwise incorrect. It will be presumed that the contractor has satisfied himself for
all possible contingencies, situations, bottlenecks, and acts of coordination which
may be required between the different associate agencies by the main contractor.
4. The work shall be executed on EPC basis involving getting all local body
clearances/approvals, Design, Drawings & commissioning of services. The
preliminary architectural drawings shall be provided by the department. It may please
be noted that the agency shall be totally responsible for the quality of the work. The
Works shall include all Civil, Electrical, Mechanical, Safety aspects and any work
required for completion of the works in all respects and to the satisfaction of the
Engineer – in – charge.
8. The tenderer should inspect the site and its surroundings before submitting the
tender. Detailed scope, conditions & specifications are included in this tender for
each of the sub-head. Since the drawing/ designs/ calculations related to various
E&M works and packages are interrelated with one another, the contractor has to
ensure that the planning and designing of all E&M works well in advance before
execution of the work. CPWD shall bear no responsibility for the lack of knowledge
and the consequences thereof to the contractor.
9. The rates quoted by the tenderer, shall be firm and inclusive of all taxes and duties,
levies, delivery, installation, testing, commissioning etc. Incidental charges of any
kind such as cartage, storage, wastage, safe custody of material etc. are included in
the quoted rates and nothing extra shall be paid on this account.
10. No foreign exchange shall be made available by the Department for importing
(purchase) of equipment, plants, machinery, materials or any other items required
to be carried out during execution of the work. No claim of any kind shall be
entertained on account of delay in receipt of items and variation in the foreign
exchange rate.
11. The Contractor shall obtain all pre-construction and post construction
approvals/clearances etc. from local body authorities like local Fire department, local
town planning authority, Lift inspectorate, Central Electricity Authority, Local
electrical distribution company, wherever required. The Contractor has to prepare
all the documents as required in the name of Client Department and submit directly
to the local statutory bodies. All approvals shall be in the name of the Client
Department. The Contractor has to comply and, if necessary, resubmit applications
which are required by the local bodies. All statutory fees / charges required for
obtaining clearances from Fire Officer/Lift Inspector/CEA / Local Bodies etc., paid
by the contractor will be reimbursed.
12. The common language used in NBC-2016 for mandatory provisions is by use of
word “recommended”. Therefore, if in NBC whenever the recommended word is
used, it is to be treated as a mandatory provision. In case any part of the work
specification is not available in the aforesaid mentioned documents then part of the
work will be carried out in accordance with sound engineering practice and as per
directions of Engineer-in- charge.
13. The Contractor shall submit a detailed program chart indicating all construction
activities for E&M works to the Engineer-in-Charge in accordance with the
milestones.
14. The contractor shall proceed with the preparation of Design and detailed shop
Drawings, detailing the equipment that are to be installed and the ancillary works that
are to be carried out. The scope of work also covers proof checking of Design and
drawings by an Institute of repute as defined/mentioned in the bid-document and
shall have to submit for approval of the Engineer-in-Charge, before commencement
of work,to ensure that the works will be carried out in accordance with the
specifications including changes mutually agreed upon. The contractor shall also
submit the data sheets and catalogues of various equipment in support of their
design.
15. The Contractor will prepare the co-ordination working drawing after getting all inputs
of various services so that the work of any service should not hamper the progress of
other works. Before start of work, the Contractor shall submit the Reflected Ceiling
Plan (RCP) drawings showing all the services and equipment to get a proper
aesthetic look of the building. During execution, if it is found necessary to amend any
parameter, the same shall be made by the firm again free of cost within the quoted
rates.
16. Any data and details asked by Engineer in charge to finalize and accept the scheme
shall be provided on the established standard/guidelines/codes etc. The scope of E &
M work, specifications mentioned in this document are indicative in general but not
exhaustive. The work shall be carried out in accordance with true intent and meaning
of the specifications and the drawings taken together, regardless of the fact
whether the same may or may not be particularly shown on the drawings and/ or
described in the specifications, provided that the same can be reasonably inferred
therefrom.
17. The contractor has to offer makes of the equipment/ materials from the “List of
Preferred/ Approved Makes” for approval of Engineer-in- charge. It is the
responsibility of the Contractor to get the makes and modelsapproved by the
department before placing of order.
18. The material to be supplied against the contract shall not be more than 6 months old
from date of receipt at site. To procure genuine material from Manufacturers /
authorized dealers shall be the responsibility of Contractor. Routine tests as
prescribed in IS/ CPWD/NBC specifications shall be carried at manufacture facility.
The expenses shall be borne by the contractor.
19. The agency shall get themselves acquainted with CPWD specifications and site
conditions. The E & M Component of work shall be executed in close co- ordination
with the progress of building work. These general conditions are applicable to all sub-
heads of work under this part. Theworkshallbedesigned, executed /carriedout
asperthe following:
Electrical Works Part – V (Wet Riser & Sprinkler system) – 2020, CPWD
General Specifications for Fire detection and Alarm system Part-VI – 2018,
CPWD General Specifications for D G Set Part – VII (DG Set) – 2013, CPWD
General Specifications for Gas based fire extinguish system Part – VIII –
2013,CPWD General Specifications for Air- Conditioning/HVAC works – 2024
with up to date amendments. Medical gas pipeline system 2022,CPWD
General Specification for modular OT 2022 & Nurse Call System 2022.
e) Factories Act, Workmen’s compensation Act.
f) Statutory norms prescribed by Agencies like CEA, Power Supply Co., CPCB etc.
g) Additional Technical specifications and list of acceptable makes.
20. Any additional item of work, if taken up subsequently, shall also confirm to the
relevant specifications mentioned above. Nothing in this specification shall be
construed to relieve the successful tenderer of his responsibility for the design,
manufacture and installation of the equipment with all accessories in accordance
with currently applicable statutory regulations and safety codes.
a) In respect of all labour employed directly or indirectly on the work the contractor at
his own expense, will arrange for the safety provisions as per the statutory
provisions, B.I.S recommendations, factory act, workman’s compensation act,
CPWD code and instructions issued from time to time.
b) The contractor shall provide necessary barriers, warning signals and other safety
measures while executing the work or wherever necessary so as to avoid
accidents. He shall also indemnify CPWD against claims for compensation arising
out of negligence in this respect. Contractor shall be liable, in accordance with the
Indian Law and Regulations for any accident occurring due to any cause. The
department shall not be responsible for any accident occurred or damage incurred
or claims arising there from during the execution of work. The contractor shall also
provide all insurance including third party insurance as may be necessary to cover
the risk. No extra payment shall be made to the contractor on this account.
22. Contractor shall arrange for compliance with statutory provisions of safety regulations
and departmental requirements of safety codes in respect of labour employed on the
work by the Contractor. Failure to provide such safety requirement would make the
Contractor liable for fine of Rs 5000/- (Rs Five Thousand only) for each default. In
addition, the department wilL be at liberty to make arrangement for the safety
requirements at the risk and cost of the Contractor and recover the cost thereof from
him.
23. Storage and safe custody of all materials shall be the sole responsibility of the
Contractor at his own risk and cost. No storage space will be provided by the
Department.
26. The agency shall insure storage, erection including third party insurance right from
the start to commissioning and handing over of various equipment. All insurance
which the agency is required to enter into under the contract shall be affected with
any authorized general insurance company and the agency shall produce the
policies of insurance. The beneficiary shall be Engineer -In-charge. Insurance costs
shall be borne by the contractor.
27. In case of any delay in Installation, Testing, Commissioning & handing over, the
insurance cover shall be suitably extended by the Contractor at his own cost. If the
agency fails to affect and keep in force the insurance, the department may pay such
premium as may be necessary for that purpose and deduct the amount, so paid by
the department from the Contractor from his dues.
28. No tools and tackles would be made available by the department. Scaffoldings & any
other T & P required for execution, testing and commissioning of work shall be
arranged by the contractor. Contractor shall make his own arrangements for
electricity and water required for execution, testing & commissioning of work at his
own cost.
b) The quality assurance program should include method statement for various items
of work to be executed along with check lists to enforce quality control.
c) The Contractor shall make available, on request from the Department, copies of
challans, cash memos, receipts and other certificates etc. towards the quantity
and quality of various materials procured, as directed by the Engineer-in-Charge.
Day to day account of receipt of material shall be maintained at site of work.
30. All parts of the equipment shall be designed to function satisfactorily under all rated
conditions of operation. All components of the equipment shall have adequate factor
of safety. The work of fabrication and assembly shall conform to sound engineering
practice and on the basis of “Fail Safe Design”. The mechanical parts subject to wear
and tear shall be easily replaceable type. All connections and contacts shall be
designed to minimize risk of accidental short circuits caused by animals, birds and
vermin etc. All identical items and their component parts should be completely,
interchangeable.
b) All routine tests shall be conducted before dispatch of equipment. Routine &
Type Test Certificates shall have to be submitted for equipment. Prior to dispatch,
all equipment shall be adequately protected & insured for the whole period of
transit, storage and erection against corrosion and incidental damages etc.
d) No inspection outside the country is permissible. If required so, the same will be
deemed to be waived off and necessary test reports shall be submitted before the
dispatch of equipment.
32. The contractor shall dispatch materials to site in consultation with the Engineer-in-
Charge. Watch & ward shall be the responsibility of contractor. Program of dispatch
of material shall be framed keeping in view the building progress. Safe custody of all
equipment/ items supplied by the contractor shall be the responsibility of the
contractor till final taking over by the department.
33. The installation shall be subjected to necessary inspection during every stage of
erection, by the Engineer In-charge or his authorized representative. The successful
bidder shall provide all facilities and assistance for the purpose. The completed
installation shall be inspected and tested by the Engineer-in charge in the manner as
will be laid down by him, in consultation the agency. All instruments and facilities
necessary for the tests shall be provided by the agency.
34. The Contractor shall submit the running bills in the shape of the bound computerized
MB in pages of A-4 size (3 sets) duly machine numbered, as per the standard format
of department.
35. Co-ordination with other Agencies: The successful tenderer shall ensure proper
coordination between various Associated Agencies executing the work of different
E&M services.
36. Climatic Conditions: All Electrical and Mechanical equipment and accessories
provided in the work shall be designed and derated for continues and trouble-free
operation in the climatic conditions of the site.
a) All the material used on works shall bear ISI certification mark. In case ISI
marked material are not available, the material to be used shall confirm to CPWD
specifications applicable in this tender or IS Code to the satisfaction of Engineer-
in-charge. In all cases proof of procurement of materials from manufacturers shall
be provided by the Contractor. All materials should be got approved by the
Engineer-in-charge before useof said materials in the work.
c) The technical data sheet and manufacturing drawing of all equipment and
materials as per contract specifications shall be prepared by the respective
manufacturer and will be submitted by Contractor duly signed before placing the
order or manufacturing the material. The Engineer-in- charge shall approve as per
contract conditions.
38. Supervision of Work: The Contractor shall depute Site Engineers & skilled workers
as required for the work. He shall submit organization chart along with details of
Engineers and supervisory staff. The Contractor shall also furnish list of persons for
specialized works to be executed for various items of work. If during the course of
execution of work, the Engineer-in- Chargeis of the opinion that the deployed staff is
not sufficient or not well experienced, the Contractor shall deploy more staff or better-
experienced staff at site to complete the work and to maintain quality and in
stipulated time limit.
a) The installations shall be completed in all respects and put in to operation even
where certain details have not been mentioned / left out in these specifications.
Any discrepancy may be brought out in pre-bid meeting.
b) All E&M services shall be declared as completed after completion of trial run of 1
month or completion of whole work whichever is later. However, maintenance of
these installations during the defect liability period of 12 months shall be carried
out by the agency at his own cost. DLP / Warranty period of all works / equipment
shall commence from date of completionof complete work (project).
c) All Electrical & Mechanical fittings / fixture / appliances shall have BEE 5- Star-
rating where ever certification is available.
d) SLD of all installations shall be prepared in color print, got laminated in suitable
size and displayed suitably at respective plant room etc. after completion of work.
41. The installations shall be handed over to the department after necessary testing and
42. The equipment or component or any part thereof found defective during the
guarantee period shall be repaired or replaced free of cost to the satisfaction of the
Engineer in-charge. In case it is felt by the department that undue delay is being
caused by the Contractor in doing this, the same will be got done by the department
at the risk and cost of the Contractor. The decision of Engineer-in-charge in this
regard shall be final and binding on the Contractor.
43. The contractor has to submit Security Deposit of Rs 25,00,000/- for all LED fittings of
‘Electrical Installations’ component schedule for additional 2 years (3 years DLP +
Additional 2 Years= total 5 years), in an acceptable form i.e., FDR/ Bank
guarantee and submit the same to the concerned Executive Engineer (E). The
Security Deposit deducted from the bills of contractor shall be released to the
contractor only after submission of Security Deposit for LED fittings, failing which the
Security Deposit against LED fittings shall be deducted from Security Deposit for
total work and only balance amount will be refunded. The LED Security Deposit will
be released on pro-rata basis each year after defect liability period.
44. Training: The scope of works includes the on job technical training of two persons of
the department for each specialized E&M work at site.
b) The agency shall submit list of makes of materials proposed to be used on the
work from local suppliers (as defined in the above order) along with minimum
local content as specified below for approval of the department out of the
approved makes kept in the tender.
c) The department will be approving only makes of the materials having a minimum
local content of 50% for use on this work, out of the preferred makes list.
d) The minimum local content of 50% is considered for the complete item including
labour component.
e) The agency shall obtain the certificate for all items except for sundry items.
46. The agency shall run all the Air Conditioning Pipe lines, Firefighting Pipes/ Water
Supply Pipes, LT Cables and Other service-related Cables through the Service duct/
Trench from service block to Hospital Building with suitable supports. Necessary
ventilation fans, Fire Alarm System, Flame Proof light fittings shall be provided in the
service Duct. Cables shall be run through suitable size cable trays.
47. Following minimum T& P shall be maintained at site during the execution of work.
The testing plan for quality control for major E&M services
Internal EI, Street Lights/Compound Lights, Substation, DG Set, UPS, Air Conditioning,
Firefighting
Whether Manufacturer's
manufacturer
Standard Applicable/
of
Test Required to be
works
Done
At
1 LT Panels CPWD specs. part
with IV/ QA Plan:
ACB Construction, Ratings
of SWG, air gaps Y Y 100% Y N
between Phases,
phase to body, IP Any
rating, Short Circuit
ratings etc.
2 LT Panels Up to Y Y 0 N N
with CPWD specs. part 2
incomer of IV/QA Plan:
more Construction, Ratings >2 Y Y 1 Y N
than of SWG, air gaps and <
200 A between phases, 10
phase to body, IP >10 Y Y 2 Y N
rating, Short Circuit
ratings etc.
Length Y Y 10% Y N
> 500 length
mtr and
fittings
Whether Manufacturer's
Whether Proof of
size whichever is
agreement or lot
Applicable/ Test
type) reqd. in
Required to be
At manufacturer
test certificates required
Dispatch required
/
Sample Size
At third Party
Stage /SI no
Standard
Process
Material
works
Done
less
Lab
5 Rigid PVC 1S 3419 :1989 up to 2500 mtr Y N N N N
Conduit
1 Piece for
>2500 mtr Y Y every N
1000 mtr
Whether Manufacturer's
reqd. in agreement or
Total Qty (each type)
Whether Proof of
Dispatch required
At manufacturer
At third Party
Sample Size
Stage /SI no
works
Lab
Done
Poles Whether in conformity with up to 100 Y Y N
N N
tender specs
9
>100 Y Y 2% Y N
in
agreement or lot size
Total Qty (each
Whether Proof of
Material / Process
Dispatch required
At manufacturer
Applicable/ Test
Required to be
At third Party
Stage /SI no
Manufacturer's
test certificates
whichever is less
Sample Size
reqd.
Whether
works
Lab
Standard
Done
type)
15 Transfor CPWD Specs. Part IV/QA Any Y Y 100% Y N
mer Plan: Physical verification
of accessories as per
agreement and Routine
tests as per IS:2026/IS
11171:1985 (whichever
Applicable), with
particular attention to
losses meeting ECBC
norms / as per
agreement, Type test
certificate for exact same
design for impulse
withstand and short
circuit withstand shall be
made available by
Manufacturer,
Temperature rise test of
one transformer of each
design shall be done.
Copies of the certificate for
pressure test, test for
bushings shall be supplied
to the department.
Location of
Whether Manufacturer's
reqd. in agreement or lot
Total Qty (each type)
Standard Applicable/
Test Required to be
Whether Proof of
Material / Process
Dispatch required
size whichever is less
Sample Size
Stage /SI no
At manufacturer
At third Party
works
Lab
Done
19 Chiller CPWD specs part VI/ECBC
Code/ Agreement/ QAPlan:
COP, Capacity,IKW/TR,
Any Y Y Y N
1PLV/ N PL, V
1
Standard Applicable/Test
Proofof
Whether Manufacturer's
test certificates required
Required to be Done
Material / Process
Sample Size
At manufacturer
Stage /SI no
Dispatch required
Stage /SI no
works
Whether
Ducting As per up to 1000
material relevant B I N NA N N
27 S Sq mtr N
1000 Sqmtr
28 Valves Flow and
up to 20 Y N NA N N
controls as
per data
sheet >20 1 for every
Y Y N Y
20
Y* To be Tested for its capacity at AHRI certified test bed (either at manufacturer's work or at
IIIrd Party)
Functions of TPQA
When a Third-Party Quality Assurance agency is engaged. it shall carry out the
following functions:
1. TPQA agency shall do their job by field visits, arranging the necessary quality
assurance tests for materials and the construction works, analyzing the test results
and furnishing the comments/ observations thereon and providing general
observations on construction materials and work. The TPQA agency shall submit
their report to CPWD at various stages/ as and when needed.
2. TPQA agency shall check and report whether work is being executed according to the
drawings designs and specifications of the agreement and in accordance with the
approved drawings.
3. The TPQA agency shall be responsible for bringing-out in writing, to the notice of
CPWD any instances of deviations from accepted quality of construction materials,
workmanship and general quality of works at appropriate stages ofconstruction.
4. TPQA agency shall inspect the construction site during the works under progress
frequently to achieve the stipulated standards of quality in the project. If there is any
discrepancy/ error/ omission the team shall point out the same with suggestions and
remedial measures with codal provisions.
5. TPQA agency shall highlight the problem area, if any, also suggest steps/ solutions
to rectify the same so as to achieve the overall target of quality assurance.
6. TPQA agency shall arrange testing of materials used in construction work for
ascertaining their quality through reputed laboratories/ institutions preferably
Government testing Centers. All standard tests shall be arranged. TPQA agency
shall report the results of testing to CPWD with their suggestions and remedial
measures.
C-1 Internal & External Electrical Installations i/c Lightning conductor, Street light,
emergency light, Illuminated signages
1.1 The scope of work shall include Planning, designing & preparation of drawings,
supplying, installation, testing & commissioning of Internal Electrical Installations
and its components in Hospital and other Buildings. If any item required to make
the scheme functional, it is not specifically mentioned, the same is deemed to be
included within the scope of this tender. These technical specifications shall be read
along with the General Conditions for all E&M works given under subhead C-B.
1.1.1 Work shall be carried out as per CPWD General Specifications for Electrical Works
Part-I (Internal) 2023 & Part-II (External) 2023, NBC 2016 amended up to the last
date of submission of tender. All electrical works shall be carried out in accordance
with the provisions of Indian Electricity Act, 2003, National Electrical Code 2010 and
Indian Electricity Rules, 1956 amended up to date. List of rules of particular
importance to electrical installations under these General Specifications for internal
electrical works is given for reference.
1.1.2 Conduits and Accessories shall conform to latest edition of Indian Standards. 16/
14 (16 gauge up to 32mm diameter & 14 gauge above 32 mm diameter) gauge MS
conduits shall be used. Joints between conduits and accessories shall be securely
made by standard accessoriesto ensure earth continuity. All conduit accessories
shall be of threaded type only. Make of conduits and accessories shall be used
from the approved list only.
1.1.3 The wiring and conduit route plan/drawings shall be submitted by the contractor and
shall be got approved from the Engineer-in-charge.
1.1.4 Check nuts shall be provided while terminating the M.S. conduits in switch boxes.
The contractor shall provide only ISI marked metallic junction boxes of required
sizes even for PVC conduit laid in the slab. The metallic junction boxes & looping
boxes shall be covered with approved makes of phenolic laminated sheet/ GI sheet.
The fan box cover shall be made from 3mm thick phenolic laminated sheet as per
CPWD specifications.
1.1.5 Four core cables shall be used in place of three and half core cables to minimize
heating of neutral core due to harmonic content in the supply system and also
avoidance of overload failures.
1.1.6 All Internal Electrical Works shall be carried out with MSconduit. All
switches,sockets,ACSockets, IP Phone socket, Data sockets, stepped type (2
module) fan regulators, bell push and accessories along with matching mounting
boxes shall be of modular type. All mounting boxes for modular type accessories
shall be of metallic construction and of the same make as that of the modular type
switches and accessories. Power point for computer shall have 3Nos 5A sockets
and 1 No 15A switch in onebox.
1.1.7 While deciding the size of switch boxes for light points / fan point / exhaust fan
point, two extra modules shall be provided for each fan point for fixing of
regulator. Wherever extra modules are available, the same shall be provided with
blanking plates without any extra cost.
1.1.8 The wires used for point wiring and power wiring shall be of 650/ 1100 Volts grade
Flame Retardant Low Smoke (FRLS) PVC insulated multi stranded copper
conductor single core cables. Minimum size of copper conductor for power wiring
shall be 4 Sq mm for power sockets, 6 sq mm for AC & Geyser points. Minimum
size of copper conductor for Light, fan points wiring and circuit wiring shall be 1.5 sq
mm. Submain wiring shall not be done with below 6.0 sq mm copper conductor
cable. For conductor sizes less than or equal to 16 sq.mm. only copper conductor
should be used. Colour coding as per specification shall be adopted in the wiring
system.
1.1.10 UPS& Essential DBs shall be separate. The size of DBs at one location shall be
same irrespective of number of circuits connected from the DB. The make of
MCBDBs, MCBs and RCBOs shall be same everywhere. All distribution boards
shall be marked with circuits controlling the rooms/ area/ SDB controlled. Size of
distribution board shall be as per number of light / power circuits. All circuits shall be
terminated on individual MCBs. All distribution boards shall be double door type.
1.1.12 The Conduiting work for the telephone, LAN and CCTV wiring shall be carried out in
such a way that all the other end of wirings can be terminated in Patch panel
including rack of each floor and in the EPBAX room/ Control room.
1.1.13 Wherever providing of rigid conduits is not possible, flexible MS conduit pipe shall
be provided for drawing/ running the wires. However, such arrangement has to be
kept minimum and only with the prior approval of Engineer-in-charge or his
authorized representative.
1.1.14 While laying MS conduits for fire alarm system and wiring for other services,
sufficient junction outlets are to be provided as per the direction of the Engineer-in-
Charge for detectors as required.
1.1.15 Wiring with Cat 6A for Intercom / Telephone shall be terminated in suitable size of
G.I. Junction box with face plate and RJ-45 socket. All the other end of wiring shall
be terminated in Patch panel including rack of each floor and in the EPBAX room.
The wiring shall be suitably tagged/marked mentioning the location of each point.
The fiber optic cable shall be used for inter connection of networking switches. The
patch panels patch chords and layer 2 and layer 3 switches are in the scope of
work. In all waiting areas sufficient multiple multistrand 6 A socket outlet should be
provided as mobilecharging point
1.1.16 No ceiling rose /connector/ looping box shall be provided, wherever false ceiling is
being provided. The point wiring in that case shall be extended up to the fitting/fan
etc. directly without provisions of any termination arrangement in between. The wire
from the end points up to the fixture shall be considered to be included in the point
wiring.
1.1.17 Earthing and all items of work that cannot be checked later, are to be got approved
from Engineer-in-charge or his authorized representative before proceeding further.
1.1.18 The firm shall use only electrically operated chase cutting machine for cutting the
chases in the wall for recessed conduit wiring.
1.1.19 Tinned copper lugs / Thimbles / ferrules shall be provided for termination of earth
wire to all Metallic outlet boxes / fittings / fixtures / fan regulator / MCB DB / switch
board / Meter board. Termination should be properly crimped / brazed / soldered.
Metal sheath of Co-axial T.V. cable shall be terminated using 'U' shape thimble /
lugs / ferrules.
1.1.20 A suitable brass / tinned copper neutral links shall be fixed at suitable places in the
Metallic outlet boxes of all sizes to terminate neutral wire properly.
1.1.21 All hardware material such as nuts / bolts / screws / washers etc. to be used in the
work shall be zinc / cadmium plated iron. These hardware items which are
essentially required for completing any item as per specifications is deemed to have
been included in the item even when the same have not been specifically
mentioned. The galvanized boxes of modular switch / sockets etc. shall be of the
same make as of switch / socket etc.
1.1.22 To facilitate drawing of wires, GI fish wire shall be invariably drawn in recessed
conduit. No or minimum junction box shall be provided in the entire length of conduit
run for drawing of wires.
1.1.23 The ceiling roses wherever required to be provided (along with earthing provision)
are included in the scope of work. The connection to incoming switch / isolator / bus
bar / MCB shall be made with suitable size of thimble and cable.
1.1.24 The Incomer for vertical DBs used for power distribution, shall be suitable rating
MCCB of 35/36KA rating breaking capacity.
1.1.25 Power supply to DBs located in lift machine room at suitable location as approved
by Engineer-in- charge shall be done using suitable insulated armored cable.
Supply, installation, testing and commissioning of cable shall be in the scope of
work.
1.1.26 Inside the lift shaft, there shall be arrangement of one light point at each floor level
and one light point at overhead, one light point in lift pit. All light points shall be in
group controlled and wired with 2.5 sq mm FRLS PVC insulated copper conductor
cable. One 15-amp power plug and one 5-amp power plug shall be provided at each
floor with individual switch. Wiring of these power plugs shall be done with 4 sq mm
FRLS copper wires. LED Bulkhead fittings of suitable rating to provide minimum 200
lux shall be connected with each point of lift shaft.
1.1.27 LT panels shall be cubicle TTA type panels only, as per accepted list of makes
attached and as per drawings approved by Engineer–in–Charge. All TTA panels shall
be strictly as per IEC61439 /BIS/CPWD specifications. Each TTA Panel shall be
fabricated from 2 mm thick M.S. sheet powder coated with 7 tank process and shall
be equipped with 4 pole MCCBs, Copper Bus bars, digital multifunction meter, LED
indicating lamps, extended rotary handle and all accessories as required.
1.1.28 TTA Floor Panels shall be provided for all UPS and Essential supply panels.
Incomer of UPS and Essential panels shall be connected with DG set Supply with
Auto changeover switch / Auto Transfer Switcher (ATS). Incomer, outgoing, bus bar,
indicating instruments etc. shall be designed as per maximum load and shall be got
approved from Engineer-in-charge. All TTA panels shall be of same Make.
1.1.29 The MCCBs, if used as incomer then it should have Over voltage, earth fault
protection and time delay. Earth leakage modules are not acceptable. breaking
capacity of MCCBs for all types of panel boards except DBs shall be as per fault
level of that location. The rated service breaking capacity should be equal to rated
ultimate breaking capacities (Ics=Icu=100%). MCCBs above 200A rating shall be
provided with microprocessor relay with suitable fault level, (Minimum of 35/36 KA
breaking capacity) adjustable Over Load, Short Circuit protection.
1.1.30 Lightning arresters and aviation obstruction lights (LED Type) shall also be
provided.
1.1.31 For accommodating various size of cables in road crossings, medium class
G.I. pipe of suitable size but not less 150 mm shall be provided. Different power
supplies shall be taken in independent pipes. Additional provision of one spare pipe
for supply cables, each of minimum 150 mm size, shall be kept for future extension
within the quoted rates.
1.1.32 Earthing system comprising of Structural Earthing to be made for all the buildings.
Necessary provisions for tapping the earth electrode at all locations as required
shall be provided. To all those services for which providing tapping from structural
earthing is not possible / not advisable separate copper plate earth electrode with
earth conductor, earth bus shall be provided as per provision laid down in CPWD
specifications part I, 2013. Earthing system should be designed such as to
maintain earth resistanceas specified in CPWD specifications.
1.1.33 A Specialized Agency shall be appointed for Structural Earthing and lightning
protection system. The credentials of the Specialized agency from one of the
approved makes shall be submitted for approval of Engineer-in- Charge.
1.1.34 The wiring shall be done in such a way to provide UPS back up in the areas as
mentioned below
i. Lighting loads of the Hospital building
excluding below mentioned areas (at ii & iii) : 25%
ii. Lighting loads of stair case, Toilets, Substation Building, Meeting Rooms,
Kitchen, Mortuary and Director’s Room :100%
iii. Power Loads/ Equipment Load of Computers CCTV, Access Control, FA&
PA System,
1.1.36 In other areas which are not covered in above paras, following minimum
provision shall be provided in the building: -
a) All 16A sockets shall be Universal type with 6 / 16 A, 6 pin sockets. In corridor
area for each 30 sq mtrs areas 1 no. 16 amp power plug (Switch & Socket), 2
nos 6 amps light plug (Switch & Sockets) outlets.
b) Two runs of 25 mm x 5 mm thick copper strips shall be provided for each Lift.
These earth strips shall be connected with connectors taken out from the
Structural Earthing system of the building.
1.1.37 Provision of PowerPoints of rating at least 25% more than the load of the
equipment, shall be kept for all medical equipment in the Hospital Building.
1.1.38 Suitable size XLPE insulated copper / Aluminium conductor cables shall be laid for the
power and light requirements of the all Medical / Non-Medical equipment in kitchen,
laundry, MGPS, CSSD, lifts, STP plant, Medical OT, TSSU, X-Ray, CT, MRI, Ultra-
Sound, Rising mains and other servicesfrom Main LT panels located at
substation.Floor/wall mounting electrical panels of important medical services such as
OTs, CT, MRI, X-ray etc. shall be fed from two different feeders with Auto Transfer
facility.
1.1.39 The Electrical supply from the Online UPS shall be through TTA type UPS Panel
with necessary MCCB incomers and outgoings of suitable capacity andrating. From
the UPS output panel, the connections shall be given to the UPS rising mains.The
panel should confirm with IEC 61439-1 & 2 for Type tested assemblies and IEC
61641for Internal Arc in vertical bus bar, Horizontal busbar and functional unit
chambers.
1.1.40 The supply from the UPS and DG set to various equipment and E&M services shall
be as per the latest relevant guidelines and shall be decided during the execution of
work as per the client department.
1.1.41 All materials and equipment supplied by the contractor shall be new. They shall be
of such design, to satisfactorily function under the rated conditions of operation
and to withstand the environmental conditions at site.
1.1.42 The make of material has been indicated in the list of acceptable makes. No other
make shall be acceptable. The material to be used in the work shall be got
approved from the Engineer-in-charge before its use at site. The Engineer-in-charge
shall reserve the right to instruct the contractor to remove the material which, in his
opinion, is not as per specifications.
1.1.43 The materials shall be subjected to quality tests at the discretion of the Engineer-in-
charge as per the specifications described for the item/material. Materials brought to
the site of work, the contractor shall, furnish manufacturers test certificates to satisfy
the provisions of IS codes relevant to the material and/or the work done.
1.1.44 Similar parts of all switches, lamp holders, distribution fuse boards, Switch gears,
ceiling roses, brackets, pendants, fans and all other fittings of the same type shall
be interchangeable in each installation.
1.1.46 Materials and equipment to be used in the work shall be inspected by the
departmental officers. Such inspection will be of following categories:
a) Inspection of materials / equipment to be witnessed at the Manufacturer’s premises in
accordance with relevant BIS / Agreement Inspection Procedure.
1.1.47 The contractor shall give a trial run of the equipment and machinery for establishing
its capability to achieve the specifications within laid down tolerances to the
satisfaction of the Engineer-in-charge before commencement of work.
1.1.48 The contractor shall engage suitably skilled/ licensed workmen of various categories
for execution of work duly supervised by technical representative having appropriate
qualification and experience to ensure proper execution of work. They shall carry
out instructions of Engineer-in-charge and his authorized representatives during the
progress of work.
1.1.49 The contractor shall provide recesses, holes, openings, etc., as may be required for
the electrical, air conditioning and other related works. contractor has also to fix
inserts, sleeves, brackets, conduits, base plates, insert plates, clamps etc., if any at
the time of casting of concrete, stone work & brick work. These inserts, sleeves,
brackets, conduits, base plates, insert plates, clamps etc., shall be arranged by the
contractor.
1.1.50 The contractor shall ensure quality construction in a planned and time bound
manner. Any substandard material or work which is not within permissible tolerance
limits shall be summarily rejected.
1.1.51 The contractor shall make sample as per time-line mentioned in the milestone given
in this tender document using all approved materials, for approval of Engineer-in-
charge, before commencement of execution of mass scale work.
1.1.52 After completing the work, necessary test results shall be recorded and submitted to
the department
1.2.2 All the light fixtures shall be energy-efficient. Fittings shall be designed for
continuous trouble-free operation under any atmospheric conditions without
reduction in lamp life or without deterioration of materials and internal wiring.
Outdoor fittings shall be weather and rainproof.
1.2.3 All lighting fixtures should be LED type having efficacy more than 110 Lumen/ Watt
and CRI >80, THD <10%, LM 79 & LM 80 test report from NABL accredited lab
should be submitted by the agency. The Colour temperature maybe 4000 K to 6500
K as per site requirement. External / outdoor light fittings shall be IK 10, IP 65/66
rating.
1.2.4 For this specification, the relevant LEDs (Light Emitting Diodes) shall be of specified
parameters as per latest datasheet of Original Equipment Manufacturer. (Only
NICHIA/ PHILIPS LUMILEDS/ AVAGO/ SEOUL Semiconductor /OSRAM / CREE
make LEDs with life of minimum 50,000 hours shall be used)
1.2.5 Lighting & Fan Design should be carried out as per National Lighting Code 2010/
NBC 2016 /CPWD specifications /ECBC guidelines. Wherever range of illumination
for space is mentioned, higher side of Lux level must be taken for design purpose.
Number of LED fittings shall be provided on the basis of average illumination
range for different areas. If as per the design, the quantity of light fixtures comes out
that does not make the symmetry, then higher number of light fixtures shall be taken
to maintain the symmetry in the room. Similarly, number of ceiling fans shall be
designed. It may be ensured that at least 25% of lights in the Hospital premises
shall be connected to UPS supply. All the internal lighting load, fans Load of the
Hospital, Car Parking and other building and external lights shall be connected with
essential supply.
1.2.6 Dimmable lightings with smart control shall be provided in conference hall
/meeting rooms.All the corridor and common area lights shall be sensor based as
per ECBC 2017 requirements.
1.2.7 To maintain different levels of illumination near beds in Wards downlighters can be
used in combination with 2’ X2’ / 4’ X 2’ fittings as required.
1.2.8 Ceiling fans shall be provided in every building and at each location except toilets /
Bath rooms. Either ceiling fans or wall fans shall be provided in air- conditioned
areas considering the ceiling height. All ceiling fans shall be of appropriate sweep
and should be BLDC type. Optimum size / number of ceiling fans for room of
different sizes shall be as per provision laid down in CPWD specifications for
internal EI work 2013 and NBC 2016. Minimum air delivery and service value shall
be as per the above specification.
1.2.9 Ventilation fans with ducting /Exhaust fans of suitable capacity and sweep shall be
provided in all Toilets/WC, stores, Substation, MGPS room,
Laundry, CSSD, STP room, Electrical panel rooms, Pantryand Isolation Beds (as
indicated in ventilation drawings) on the basis of CFM calculations as per NBC-
2016, CPWD Specifications and as per the approval of Engineer-in-Charge.
1.2.10 A few cubicles may have a choice of positive or negative operating pressures
(relative to the open area). Cubicles usually act as isolation facilities and their lobby
areas must be appropriately ventilated in line with the function of an isolation area
(i.e., pressure must lie between that in the multi-bed area and the sideward).
1.2.11 Negative pressure isolation rooms: - In these rooms the windows do not open. They
have greater exhaust than supply air volume. Pressure differential of 2.5 Pa shall be
maintained. Clean to dirty airflow i.e., direction of the air flow is from the outside
adjacent space (i.e... corridor, anteroom) into the room. Air from room preferably
exhausted to the outside.
1.2.12 Positive pressure isolation rooms: - To provide protective environment for patients
at highest risk of infection. These rooms should be provided with positive air flow,
through HEPA filter. (i.e., air flows from the room to the outside adjacent space).
Pressure differential of 2.5 Pa – 8 Pa shall be maintained. The temperature should
be 21±1 Deg. C and relative humidity should be 50 ±5%.
1.2.13 Return air of battery room shall be exhausted. In addition, equal capacity of standby
exhaust fan shall be provided for battery room.
1.2.14 All corridors shall be provided with proper ducted air circulation/ ventilation to
achieve the conditions with number of air changes as per NBC-2016.
1.2.15 Gate lighting with decorative LED type post top lantern shall be provided.
Illumination to be maintained as per NBC 2016 and shall be controlled by timer
switch panel for Auto ON/OFF. Lighting with Bollard fittings shall be provided in
Lawns and Internal Walkways.
1.2.17 The cabling of the compound lights should be in such a way that every third or
alternate pole shall be connected from each R-Y-B phase of 3-phase supply line for
ensuring minimum light at the time of failure of either of the phase.
1.2.18 The light luminaries/electrical light fixtures provided under the contract shall be
guaranteed for a period of 5 years from the date of completion/ handing over
whichever is later. In this regard contractor shall furnish an undertaking for
Guarantee/Warrantee of LED luminaries for 5 years from the manufacturer duly
endorsed by him.
Technical Specifications
i. Operating Voltage: 220 – 240V AC, 50 HZ.
ii. Warm Air Speed Output: 103 m/s.
iii. Noise Level: 82dba at 1 meter.
iv. Motor Type: 2800 rpm motor.
v. Thermal Protection: Auto resetting thermostat turns unit off, 240V at 221-
degree Fahrenheit (105 degree Celsius).
vi. Heater Element: 1800-2000 W heater.
vii. Mount Type: Wall Mounted.
viii. Material: High Grade ABS.
ix. Power: 1800-Watt or above
x. Operation type: Touch free Infra-red Sensor activation.
xi. Automatic Cut Off: Upto 60 sec.
xii. Air speed: >15 m/s.
xiii. Drying time: 20Sec – 30 Sec.
xiv. Color: White
These streetlight poles with fittings shall be provided all around the building
other than front sides.
Top: 70 mm,
Base dia. and top diameter (A/F):
Bottom: 130 mm
1.7.1 The Indian Standard specifications and Codes of Practice will apply to the
equipment and the work covered by the scope of the contract. Wherever
appropriate Indian Standards are not available, relevant British and/ or IEC
Standards shall be applicable.
1.7.2 It is to be noted that updated and current Standards shall be applicable even
though those are listed below.
Code of Practice for the protection of buildings
Structures against Lightning IS 2309: 1989, IS/ IEC 62305 Code of Practice
for Earthing IS 3043: 1987
1.7.3 The Lightning Protective System shall comprise of Air Terminations, Down
Conductors, Earth Terminations etc. as required. The System shall preferably
use the same conducting material throughout and will comply to the detailed
specifications as detailed here in after. The entire lightning system should be
mechanically strong to withstand the mechanical forces produced in case of a
lightning stroke. The system shall be designed as per NBC/ CPWD
specifications.
1.7.4 Materials
1.7.4.1 Copper - When solid or stranded copper wire is used, it shall be of the grade
ordinarily required for commercial electrical work and generally designated as
being of 98% conductivity when annealed, conforming to Indian Standard
specifications.
All metallic finials, chimneys, duct, vent pipes, railings, gutters, and the like on or
above the main surface of the roof of the structure should be bonded to and form
partof the air termination network.
1.8.2.3.3 PIV protection: LEDs shall be internally protected against reverse voltages of up
to 1 kV.
1.8.2.3.8 Flashing Requirement: The light shall be supplied with a flasher for operating in
flashing mode for warning indication. The flasher circuit shall be placed externally
to the lighting unit, in an indoor environment.
The Lightning protection system and the foundation earthing system are the integral
part of the building reinforcement / Structure. Therefore, it is necessary that the
agency for the Structural earthing be decided well in advance so that the
reinforcement drawing shall incorporate the foundation earthing design also. The
Structural earthing shall be carried out by an authorized and certified agency of the
approved makes given in the list of preferred makes. Proper documentation shall be
submitted for approval of the engineer-in-charge before this work is carried out.
• CEA regulations for Measures relating to Safety and Electric Supply 2010 IS
3043, IS 732: 2019, NEC: 2011(SP30) & NBC2016
Earthing for safety, voltage reference, shielding and lightning current dissipation shall
confirm the requirement as per the above standards. TN-S with double earthing for
transformer, electrical panels and major equipment satisfying IS 3043, IS 732, IEC
60364
Exothermic weld shall confirm the requirements of IEEE 837:2014. Every component
used shall be able to withstand the fault current with minimum temperature raise.
The earth studs shall be 100 % corrosion resistant and shall confirm the
requirements of IEC 62561.
1.9.1.1 Earth Conductor & Earth Stud: The earth conductor (e.g. - 10 mm round) sizes specified
based on lightning protection and 18mm round based on transformer short circuit level.
Copper coated steel tested to IEC 62561 shall be used as dedicated earth conductor in
concrete as well as ring earth in case if the foundation has water proof plastic membrane.
Earth studs are for the purpose of bringing the electrical connection between structural
steel with other steel installations in the building. Both earth conductor as well as earth
stud shall be corrosion resistant and shall be tested acc. to IEC 62561.Earth stud shall be
connected to earth conductor by exothermic welding.
1.9.2.3 Grid Sizing: The earth grid design shall satisfy NBC-2016 (5meter* 5meter grid) for
improvement of the Earth termination system in a power source like: Transformers
and Generators.
1.9.2.4 Down Conductor for Lightning Protection as well as Bonding conductor for electrical
installations (RCC Building): The dedicated copper coated 10 mm solid round
conductor shall run inside columns on the periphery of the building and must be
connected to the reinforced steel available in the columns will serve the purpose of
down conductor for lightning protection as well as base for Equipotential bonding in
every floor of a multistoried building. If the distance between 2 columns is lesser than
5 meters, alternate columns shall be selected to route the down conductors. If the
distance is more than 10 meters, all the columns shall be used for down
conductorrouting.
Provisions for interconnection of metal frame of wall cladding shall be provided at every 5
meters in vertical and horizontal sections based on the architectural design.
1.9.2.5 Earthing for safety of LV network: Additional earth studs need to be installed in
places where electrical panels & electronic equipment is installed. All electrical
rooms as well as every floor level in electrical shaft must have a local Equipotential
bonding earth stud extended from the structural earthing. Sizing of earth stud for
electrical room shall be based on the short circuit current requirements of the
electrical system considering TN-S network. In addition, earth studs for the purpose
of testing the efficiency of protection system shall be provided in easily accessible
places at top and bottom of the building at every 20 meters around the periphery
of the building.
1.9.2.6 Testing of Down conductor: Structural earthing used as a part of lightning protection
system, overall resistance shall not be more than 0.2 ohm when measured between
the air termination and the earthing test point providedat the ground level.
1.9.2.8 Air termination system: Air termination system (Horizontal/Vertical) in the roof shall
be according to Lightning Protection Level specified in NBC 2016. The air
termination system consisting of vertical rods and/or mesh shall be connected to
the structural conductor through earth studs provided at the parapet / columns of
the building. For this purpose, sufficient earth studs with provision of mechanically
strong connection need to be provided at the parapet / wall / column at the top of
the building. Air termination system shall be installed strictly after completion of the
installation of all roof mounted electrical / metalinstallations.
For building with metal roof, the air terminal shall be directly connected to the steel roofing
sheet with special leak proof screws. Bonding of roof steel and structural support columns
shall be ensured by installing braided wiresat every 10 meters
1.9.2.9 Installation, Testing and Certification: The Earth studs type test reports to be
submitted for Irms value tested in CPRI/ERDA to besubmitted.
The total installation needs to be carried as per IS/IEC 62035. The installation must
also be tested and certified by a qualified lightning protection expert as specified in
IS/IEC 62305.
2.1 The scope of work consists of Planning, designing, Supply, installation, testing and
commissioning of Firefighting system with wet riser & Sprinklers for the Hospital
buildings and all other service buildings, Water curtain systems wherever required,
Gas suppression system for server rooms, spirit store, LPG bank, Electrical panels
and other relevant areas of the building etc. and dewatering pumps in the
basements.Any material or accessories which may not have been specifically
mentioned but are necessary for satisfactory operation and maintenance of the
equipment, shall be furnished by the Contractor. These technical specifications shall
be read along with the General Conditions for all E&M works given under subhead
C-B.
2.1.1 Conformity With Statutory Acts, Rules, Orders, Standards and Codes
a) All components and their installation shall conform to relevant Indian Standard
Specifications, wherever existing.
c) Contractor shall obtain approval of the installation from the local fireauthorities as
may be required as per local bye-laws at all stages before and on completion of
the installation work. The contractor shall pass on these approvals to the
department. Any statutory fee paid to the Government / Municipal Authorities/
Statutory Bodies etc. for obtaining approvals and shall be reimbursed to the
contractor on submission of documentary proof.
(c) Sprinkler drawing indicating layout and sizes of pipe, location of valves,
sprinklersetc.
(d) Electrical wiring diagrams for all electrical equipment and controls including
the sizes and capacities of the various cablesand equipment.
(e) Drawings showing details of supports for pipes, cable trays, any other
drawing(s) relevant to thework.
Five sets of the following drawings shall be submitted by the contractor while
handing over the installation to the Department. Out of this one set shall be
laminated on a hard base for display in the fire control room. In addition, soft copy
shall be given by the contractor.
(b) Line diagram and layout of all electrical control panels giving switchgear
ratings and their disposition, cable feeder sizes and their layout.
2.1.4 Guarantee
a) The contractor shall guarantee the complete system to provide the specified flow
and pressure under all conditions atoutlets.
b) All equipment shall be guaranteed for a period of 36 months from the date of
acceptance and taking over of the installation by the Department against any
unsatisfactory performance and/or breakdown due to defective design, material,
manufacture, workmanship or installation. The equipment or component or any
part thereof so found defective during the guarantee period shall be repaired or
replaced free of cost to the satisfaction of the Engineer-in-charge. In case, it is
felt by the department that undue delay is being caused by the contractor indoing
this, the same will be got done by the department at the risk and cost of the
contractor. The decision of Engineer- in-charge in this regard shall befinal.
c) Main Fire Pumps (Both electrical as well as diesel) shall be selected for:
i. Discharge : 2280 lpm for Wet Riser & Sprinkler
1650 lpm Water-Curtain
ii. Head : 35 m + Height of terrace level hydrant
above pump level + 6% of the maximum length of pipe from pump
discharge to any hydrant at terrace level
f) However, the number of risers can be suitably increased to meet the given
situation.
2.2.2 Internal Hydrant: Every riser shall be provided with the following at every floor
including terrace and basement over and above sprinkler system.
(i) Single-headed outlet -2 Nos.
(ii) First Aid Hose Reel -1 No.
[Length of pipe shall be such that nozzle of the hose can be taken into every
room and within 6 m of any part of the rooms keeping in view layout and
obstruction.]
(iii) Hose Pipe 63 mm dia, 15 m longwith male and female couplingatends.
-2 Nos.
(iv) Branch pipe 63 mm dia with 20 mm nominal internal diameter nozzle and
Suitable for instantaneous connection. -1 Nos.
2.2.3 Yard Hydrant (External Hydrant)
a) For connecting yard hydrants, a ring of pipe shall be laid underground around the
building at a minimum distance of 2 m but not more than 15 m from the face of
the building. All internal risers shall be connected with this ring. The yard
hydrants shall be easily accessible and should normally be provided near the
boundary wall/along the road. While locating yard hydrants it should be ensured
that same do not become a hindrance in vehicular movement or entrance to the
building. Yard hydrants should be located around the building in such a way that
it should be possible to fight the fire on any face of the building from the nearest
hydrant. At least one hydrant post shall be provided for every 45 m.
b) Fire Hydrants shall be of stand post type conforming to IS 908. All Yard hydrant
outlets shall be situated 1 m above ground level. The hydrant couplings shall be
of the instantaneous spring-lock (female) type of 63 mm diameter and valves
shall be of the screw-down type.
c) Suitable pressure reducing devices shall be provided for the yard as well as
internal hydrants where the pressure exceeds 7 kgf/cm2, considering the safety
of operators. All hydrants should be painted red and serially numbered.
e) All above Components shall be housed in a suitable size MS cabinet made from
a 2 mm thick sheet with a glass panel on the front. The cabinet shall be painted
red.
2.2.4 Fire Service inlet: In order to facilitate feeding of water in the system by fire
service, a 3-way 63 mm diameter collecting head shall be provided and
connected with each riser and the ring main with non-return valve and
butterfly/sluice valve. This should be located at a place where fire brigade tender
can reach.
2.2.5 Fire Service connection:It is for feeding water to underground storage tank by fire
tenders. The static water storage tank shall be provided with a fire brigade collecting
head with 4 number 63 mm diameter instantaneous male inlets arranged in a valve
box at a suitable point at street level. If tank is not approachable for the fire
engines, the fire brigade collecting head shall be connected to the static tank by
a suitable fixed galvanized iron pipe not less than 150 mm in diameter to
discharge water into the tank.
2.2.6 Fire Brigade draw out collecting head: Each of the static water storage tanks shall
also be provided with a fire brigade draw out collecting head with 63 mm diameter
instantaneous male draw out arranged in a valve box at a suitable point at street
level. This draw out shall be connected to a galvanized iron pipe of 100 mm
diameter with foot valve arrangement in thetank.
2.2.7 Air Vessel: - To counteract the water hammer effect, air vessel shall be provided at
the top of each riser.
2.2.8 Orifice Plate: - Suitable pressure reducing devices shall be provided for yard as well
as internal hydrants to control pressure to desired limit especially at lower-level
hydrants. The size of orifice shall be calculated as per IS/ CPWD specifications.
2.2.9 Alarm for Wet Riser System: - To indicate the flow of water in the system, turbine
type alarm shall be provided at a prominent place outside the pump house in the
main line before any connection is taken. The alarm will indicate the healthiness of
the system and shall not be silenced till the main fire pump is in operation.
2.2.10 Control system
The system shall be designed for operation automatically so that as and when water
is drawn from the system through any hydrant, the pumps will operate automatically
and feed water in to the system. However, once a fire pump starts working, it will be
stopped only manually (except jockey pump). Facility shall also be provided for
manual operation. A selector switch for auto/ manual selection shall be provided for
each pump.
The control system shall be designed to provide the following sequence of
operation:
i) The Pressurization Pump shall maintain pressure in the system and shall operate
only on account of slow pressure loss. In case of sudden pressure loss, the
Pressurization Pump shall not operate. The pump shall start when the water
pressure in the system falls to a pre-set value and shut down when the system
pressure reaches the set value. Both limits shall be adjustable.
ii) Main Electric Fire Pump shall operate on account of sudden pressure loss. As
long as Main Electric Fire Pump is working, other Fire Pumps shall not operate.
The pump shall start when the water pressure falls to a pre-set value in the
system (about 1kgf/cm2).
iii) In case, Normal Electric Supply fails while the Main Electric Fire Pump is
running, the DG Set for essential supply will start within 5 seconds.
iv) The Diesel Fire Pump shall start on sudden pressure loss, only in case supply
to Main Electric Fire Pump is not available or within a pre-set time the Main
Electric Fire Pump fails to start or fails during operation. Noother pump shall
work when Diesel Engine Fire Pump is in operation. Audio- Visual Alarm shall
be available to indicate failure of Main Electric Fire Pump.
v) Three attempts starting facility shall be provided for the diesel pump. If within a
pre-set time, the stand by pump also fails to start or fails to develop pressure, the
stand by pump shall also be shut down and locked out. An audio-visual alarm
indication shall be given at the controlpanel.
2.2.11 Wet Riser: -Wet Riser shall be interconnected at terrace level to form a ring and cut-
off shall be provided for each connection to enable repair/maintenance without
affecting rest of thesystem.
Pump House for installation of firefighting pumps (Main Electrical Pumps, Diesel
Engine Driven and Pressurization Pumps) along with Electrical & Control Panel,
valves, diesel tank etc., pump house is required. Following factors are to
beconsidered:
(i) Suitable ramp with proper slope and/or cutout in roof shall be provided for
lowering the equipment in to the pump house. Stair case with entry door at
ground level and locking arrangement shall beprovided.
(ii) Adequate ventilation for dissipation of heat due to operation of motors/engine
shall be provided.
(iii) Proper water proofing shall be provided. A sump of size 0.6 m x 0.6 mx 0.3 m
with 1(Working)+1(Standby) dewatering pumps shall be provided in the pump
house in one corner adjacent to the tank wall. The floor slope will lead
towards the sump so that water leakage, if any can be pumped out.
(iv) In order to ensure that there is no leakage of water in the pump house, no
pipe/ cable shall cross the pump house below ground level. Suitable opening
in wall above ground level shall be provided for crossing of pipes/cables.
(v) Installation of negative suction arrangement and submersible pumps shall not
be allowed.
2.2.13 Internal Hydrant - Internal hydrants are provided to fight fire from within the building.
Following factors are considered for deciding location of internal hydrant:
(i) Internal hydrants shall be provided at every floor at the same location and
connected withrisers.
(ii) Hydrant for firefighting shall be located in the lobby in firefighting shaft. Those
hydrants planned to be provided near fire exit staircase on the floor shall be
within 5 m from exit door in exit access.
(iii) Numbers and location of risers shall be decided to fulfil the conditions stated
earlier.
(iv) Every wing of the building shall preferably be provided with independent
hydrants. Hydrant shall be located in the center of the building so that one
hydrant can cover area on both sides.
(v) A masonry enclosure on three sides minimum 1200 mm wide and 800 mm
deep and 2100 mm height size shall be provided. Two Cut-outs of 200 mm x
200 mm size be provided in one corner in the slab for wet riser and sprinkler
pipe. If sprinkler installations are to be provided, additional cut out of similar
size for sprinkler pipe and drain pipe as the case may be, shall be provided.
Steel shutter with 1250 mm glazing on top with locking arrangement shall be
provided in front of the hydrant. The shutter shall be painted red.
(vi) Internal hydrant shall be easily accessible. A clear space of at least
1.5 m should be available in front of the internal hydrant for operation. Internal
hydrant shall not be provided in a lockableroom.
(vii) Internal hydrant shall be clearly marked with the inscription of “FIRE HOSE
CABINET”of letter size75mm in height and12mm in width by luminous sign.
Suitable lighting arrangement shall be provided in front of the internal
hydrant. The location of such cabinets shall be shown on floor plan and duly
displayed in the landing of the respective fire exit stair case.
2.2.14 Drainage
Drain traps in pump room shall be made by the agency/ contractor only. Piping
Connections from the equipment to the drain trap shall be done by the contractor.
2.2.15 Paint
The entire piping work along with fire pumps, Motors & Engines shall be painted
with red color shade No. 536 of IS5.
(i) Pipe connecting pump house to ring main shall not be less than 150 mm
diameter. Higher size pipe shall be selected depending upon length of pipe
and friction loss. Size of Ring main and Risers shall not less be than 150 mm
diameter.
(ii) Fire service inlet and fire service connection shall be with pipe of size not
less than 150 mmdiameter.
All Tee off connections for landing valves from vertical risers and for external
(iii)
hydrants from ring main shall be with pipe size not less than 100 mmdiameter.
2.3.1 Selection of Material: - Components like landing valve, hose coupling branch pipes
etc. are to be made of Gunmetal.
b) The underground tank and Pump house shall be tested for any
leakage/seepage before start of the work. It shall be ensured that both tank
and pump house are free from leakage/seepage.
d) The sprinkler pipes should be tested area wise and capped for connection to
pipes of adjoining area.
e) The route of external pipe i.e., pipe from pump house and ring main should be
decided in coordination with other building services.
The main fire pump and terrace pump shall be suitable for continuous operation in
the system. The jockey pump shall be suitable for intermittent operation to build-up
pressure in the system on account of leakage, If any. The head shall be suitable for
the system and shall take into consideration the pressure drops across the various
components in the water circuit as well as the frictionallosses.
The rated discharge of Electric Driven and Diesel Engine Driven pump for wet riser
and sprinkler system shall be minimum 2280 lpm.Pumpshallbecapableofdischarging
not less than 150 percent of the rated discharge at a head of not less than 65
percent of the rated head. The shut off head shall not exceed 120 percent of the
rated head in the case of horizontal Pumps.
2.4.1 Material and Construction
a) The pump casing shall be of heavy section close grained cast iron and
designed to withstand 1.5 times the working pressure. The casing shall be
provided with shaft seal arrangement as well as flanges for suction and
delivery pipe connections asrequired.
b) The impeller shall be of bronze, shrouded type with machined collars. Wear
rings shall be of the same material as the impeller. The impeller surface shall
be smooth finished for minimum frictional loss. The impeller shallbe secured to
the shaft by a key.
c) The shaft shall be of stain less steel and shall be accurately machined. The
shaft shall be balanced to avoid vibrations at any speed within the operating
range of the pump.
d) The bearings shall be suitable for the duty involved. These shall be grease
lubricated and shall be provided with grease nipples/cups. The bearings shall
be effectively sealed a gainst leakage of lubricant or entry of dustor water.
e) The shaft seal shall be mechanical type, so as to allow minimum leakage. A
drip well shall be provided beneath theseal.
f) The pumps shall be directly coupled to the motor/diesel engine shaft
through a flexible coupling protected by a couplingguard.
g) The pump and motor/diesel engine shall be mounted on a common robust bed
plate fabricated from mild steel section. The bed plate shall have rigid,
Flat and true surfaces to receive the pump and motor/dieseling in emounting
feet.The pump shall be perfectly aligned with the motor/engine to avoid any
vibration during operation at all variations of load.
2.4.2 Accessories
Each pump shall be provided with the following accessories: -
a) Sluice valvesonsuctionanddelivery.
b) Reducers, as may be required to match the sizes of the connected
pipework.
c) Non-return valve at thedelivery.
d) Pressure gauge at delivery side between pump and the non-returnvalve.
e) Flexible coupling/connections shall be provided between Pump sets and
Valves on suction and delivery sides of all the pumpsets.
f) No butterfly valves shall be installed inside the pumproom.
g) The size of the non-return valve and cut off (Sluice valve) shall not be less
than the size of the initial deliverypipe.
2.4.3 Installation
a) The pump and motor/engine assembly shall be mounted and arranged for
ease of maintenance and to prevent transmission of vibration and noise to the
building structure or to the pipe work. The pump and motor/engine assembly
shall be installed on suitable RCC foundation. The length and width of the
foundation shall be such that 100 mm space is left all around the base
frame. The height of foundation shall be so decided that the total weight of
foundation block is 1.5 timesthe operating weight of the pump assembly.The
foundation shallbeisolatedfrom the floor by vibration isolating pads. Angle iron
b) More than one pump and motor assembly shall not be installed on a single
base or cement concreteblock.
c) The suction/discharge pipe shall be independently supported and their weight
shall not be transferred to the pump. It should be possible to disconnect any
pump for repairs without disturbing the connecting pipe line.
e) Sufficient space is to be left in front for the radiator of diesel engine for free
discharge of hot air. Arrangement for discharging hot air to outsideof the pump
house shall be provided, so that hot air does not stagnate in the pump house.
The diesel engine shall be suitable for automatic operation complete with necessary
automatic starting gear, battery system and shall be complete with all accessories.
Both engine and pump shall be assembled on a common bed plate, fabricated from
mild steelchannel.
The pump shall be only direct driven by means of a flexible coupling. The coupling
between the engine and the pump shall allow each unit to be removed without
disturbing the other. Coupling guard shall be provided. The speed shall be
1500RPM.
2.5.1 DieselEngine
The engine shall be multi-cylinder 4 stroke cycle, water cooled, developing
suitable HP at the operating speed specified to drive the fire
pump. Continuou scapacity available for the load shall be exclusive of the power
requirement of auxiliaries of the diesel engine, and after correction for altitude,
ambient temperature and humidity for specified environment conditions. The
engine rating shall be suitable to drive the pump at 150 percent of its rated
discharge with at least 65 percent of rated head or 20% in excess of the maximum
brake horsepower required to drive the pump at its duty point, whichever is
higher. The engine shall have 10% overload capacity for one hour in any period
of 12 hours continuousrun.
The engine shall be:
a) naturally aspirated, supercharged or turbo-charged and rather air or water-
cooled.
b) provided with an in-built tachometer to indicate rpm of theengine.
c) able to develop full load within 15 seconds from the receipt of the signal
to start.
d) The diesel engine shall conform to BS 649/ IS 1601/ IS 10002, amended up
todate.
2.5.2 Engine Accessories- The engine shall be complete with
following accessories:
(i) Flywheel dynamicallybalanced
(ii) Direct coupling for pump and coupling guard
(iii) Radiator with hoses, fan, water pump, drive arrangement andguard
2.5.3 The engine shall be radiator water-cooled. The radiator assembly shall be mounted
on the engine. The radiator fan shall be driven by the engine as its auxiliary with
multiple fan belts. When half the belts are broken, the remaining belts shall be
capable of driving the fan. Cooling water shall be circulated by means of an auxiliary
pump of suitable capacity driven by the engine in a closedcircuit.
2.5.4 The fuel system shall be gravity fed from the fuel tank to the engine-driven fuel
pump. The engine fuel tank shall be mounted either adjacent to the engine or
suitably wall mounted on brackets. The fuel filter shall be suitably located to permit
easy servicing.
The fuel tank shall be of welded steel construction (3mm thick) and of capacity
sufficient to allow the engine to run on full load for at least 8 hours. The tank shall be
complete with necessary floor mounted supports, level indicator (protected against
mechanical injury) inlet, outlet, overflow connections and drain plug and piping to
the engine fuel tank. The outlet should be so located as to avoid entry of any
sediments into the fuel line to the engine. Any valve in the fuel feed pipe between
the fuel tank and the engine shall be placed adjacent to the tank and it shall be
locked in the openposition.
All fuel tubing to the engine shall be with M.S.'C’class pipe with flexible hose
connections wherever required. Pipe joints shall not be soldered and plastic tubing
shall not beused.
2.5.5 Lubricating Oil System- Forced feed lubricating Oil system shall be employed for
positive lubrication. Necessary lubricating oil filters shall be provided, located
suitably for convenient servicing.
2.5.6 Starting System- The starting system shall comprise of necessary batteries of 12
Volts/ 24 Volts, starter motor of adequate capacity and axle type gearto match with
the toothed ring on the flywheel. Suitable protection to protect starting motor from
excessively long cranking runs shall be suitably integrated with the engine
protection system.
The capacity of the battery shall be suitable for meeting the needs of the starting
system.
The battery capacity shall be adequate for 10 consecutive starts without recharging
with cold engine under full compression.
Three attempts starting facility shall be provided. If the engine fails to start after third
attempt, the engine shall be locked out and suitable audio-visual alarm shall be
given to indicate engine failure. The starter motor used for automatic starting may
also be used for manual starting provided there are separate batteries for manual
starting. The scope shall cover all cabling, terminals, initial charging etc.
2.5.7 Exhaust System- The exhaust system shall be complete with residential grade
silencer suitable for outdoor installation and silencer piping shall be extended up to
1 m, outside pump house duly insulated with 50 mm thick glass wool and 1.0 mm
thick aluminum sheet cladding.
2.5.9 Engine shut down mechanism- This shall be manually operated and shall return
automatically to the starting position after use.
2.5.10 Governing System- The engine shall be provided with an adjustable governor to
control the engine speed within 5% of its rated speed under all conditions of load up
to full load. The governor shall be set to maintain rated pump speed at maximum
pump load.
2.5.12 Engine protection devices - Following engine protection and automatic shutdown
facilities shall beprovided: -
(i) Low lube. oilpressure.
(ii) High cooling watertemperature.
(iii) High lube. oiltemperature.
(iv) Over speed shutdown
2.5.13 Pipe work- All pipe lines with fittings and accessories required shall be provided for
fuel oil, lube. Oil and exhaust systems.
2.5.14 Anti-vibration mounting- Suitable vibration mounting duly approved by the engineer-
in-charge shall be employed for mounting the unit so as to minimize transmission of
vibration to the structure.
2.5.15 BatteryCharger-
Battery of diesel engine operated fire pump shall have separate charger from
emergency power supply circuit. Necessary float and boost charger shall be
incorporated in the control section of power and control panel with manual selection
of boost charge, to keep the battery under trim condition. Voltmeter to indicate the
state of charge of the batteries shall be provided. Where separate batteries are
provided for automatic and manual starting, the charging equipment shall be
capable of trickle charging both the batteries simultaneously. Equipment shall be
provided to enable the stateof charge of the batteries to bedetermined.
The following spare parts shall be supplied with the engine and keptonhand:
a) Two sets of fuel filters, elements andseals;
b) Two sets of lubricating oil filters, elements andseals;
c) Two sets of belts (whereused);
d) One complete set of engine-joints, gaskets andhoses;
e) Two injectornozzles;
f) One complete set of piston rings for each cylinder;and
g) One inlet valve and one exhaustvalve).
2.6 Pipe Work
2.6.1 The contractor shall be responsible for selection of sizes as per detailed engineering
to be done by him. Plumbing design to be done by the contractor shall incorporate
the following:-
(i) Sluice valvesshall be provided at suctionand delivery sides of pumps.
a) Externalhydrant
b) Fire serviceconnection/inlet.
c) Testvalve.
d) Drainconnections.
(ii) For testing the system healthiness and automatic operation on daily basis,to
avoid wastage of water, this pipe shall discharge water in thetank.
(iii) Non-return valve shall be provided at the delivery of each pump andfire
service inlet. This shall be of swing type.
(iv) Air release valves with ball valve shall be provided in the piping system for
venting trapped air with a size of 25 mm for pipes up to 100 mm and 40 mm
for larger pipes.
(v) Plumbing drawings showing the sizes of pipe, valves, layout and other details
shall be prepared and shall be got approved from the Engineer-in-Charge
before the execution of the plumbing work.
b) Welded black steel pipe, Class 2, conforming to IS: 3589, for sizes greater
than 150 mm. These pipes shall be factory rolled and fabricated from
minimum 6mm thick M.S. Sheet for pipes up to 350 mm diameter and from
minimum 7 mm thick M.S. sheet for pipes of400 mm diameter andabove.
Note: For pipe work of Automatic Sprinkler System inside the building, Stainless
Steel Pipes and fittings of grade AISI 304 as per JIS standard 3448 are also
permitted particularly where replacement of pipes is not easy like areas above
false ceiling etc., subject to the condition that these pipes with associated
fittings are suitable to safely withstand the system testpressures.
c) Mild steel flanges shall be in accordance with IS: 6392 i.e., “Plate Flanges for
Welding" and flange thickness shall be as under. Gasket thickness shall not
be less than 3mm.
I. Pipediameter Flange
Thickness 200mm 24mm
II. 150 mm and125mm 22mm
III. 100 mm and80mm 20mm
IV. 65mm 18mm
V. 40 mmandbelow 16mm
d) Fittingsinstalledundergroundshallbeofcastiron‘heavy’gradeconforming to IS 1538
whereas those installed above ground shall normally be of medium grade
wrought steel or mild steel conforming to IS 1239 (Part 2) or malleable iron
fittings conforming to IS1879.
e) All hardware items such as Nuts, Bolts, Washers shall be of appropriate size.
Washers shall be used on both sides of thebolt.
Corrosion protection tape shall then be wound around the pipe in spiral fashion and
bounded completely to the pipe. There shall be no air pocket or bubble beneath the
tape. The overlaps shall be 15 mm and 250 mm shall be left uncoated on either
end of pipe to permit installation and welding. This area shall be coated in-situ after
the pipe line is installed. The tapes shall be wrapped in accordance with the
manufacturer’s recommendations. If application is done in cold weather, the surface
of the pipe shall be pre- heated until it is warm to touch and traces of moisture are
removed and then primer shall be applied and allowed to dry.
Holiday Testing for wrapping and coating is essential. Holiday testing may
preferably be carried by flexible and detachable ring probe, which will enable the
entire 360° of the surface of the pipe to be scanned.
2.6.5 Valves
Each pump shall be provided with a non-return valve and a sluice valve on the
delivery side, the sluice valve being installed on the upstream side of the non-
return valve. A pressure gauge shall also be provided between the pump and the
non-return valve. The size of the non-return valve and cut off (sluice) valve shall not
be less than the size of the initial delivery pipe and, in no case, less than the
delivery outlet of the pump. No butterfly valves shall be installed inside the
pumproom. Sluice valve shall conform to IS: 780.Butterfly valve, wherever used,
shall conform to IS:13095.
All valves shall be suitable to with-stand the pressure in the system and rating shall
be PN 1.6. All valves shall be right-handed (i.e., handle or key shall be rotated clock
wise to close the valve), the direction of opening and closing shall be marked and
an open/shunt indicator fitted.
b) Non return valves shall be swing check type in horizontal run and lift check
type in vertical run of pipes.
section of the network without affecting the flow in the rest. These valves are
distributed according to the general layout of the installation. The isolation
valves shall be normally located near the loop junctions. Additional valves
shall be provided in the segments where the length of the segment exceeds
300m.
b) Cut-off valves shall conform to IS 780 (PN 1.6 rating)/IS 14846, Class3.
c) Butterfly valves can be accepted subject to the condition that the valves of
diameter exceeding 150 mm shall necessary be of gearoperated.
d) All Cut-off valves shall be of the right-hand type and enclosed in properly
constructed surface boxes, at least 1 m2 in area so as to allow for broken joints
being easily remade. The top of the surface box shall be 80 mm above ground
level, except where it is located on a road. Valve wheels shall have an
arrowhead engraved or cast thereon showing direction for turning open
andclose.
f) Locations where vehicles can pass shall be avoided for provision of valve
below ground.
2.6.7 Strainers
Stainless steel strainers shall have minimum 1 mm thick screen with 3 mm
perforations. Strainers shall be provided with flanges.
2.6.8 OrificePlate
Orifice plate shall be made of 6 mm thick stainless steel and shall have an
identification tag projecting beyond any flange between which it is clamped. The
orifice shall be plain central hole without burs and diameter not less than one-half
of the internal diameter of the pipe to which it is fitted.
2.6.9 Instruments
Pressure gauge of appropriate range and 150 mm diameter size shall be provided.
The pressure gauge shall be duly calibrated before installation and shall be
complete with shut offvalve.
connection shall be provided for connection with wet riser pipe. Air release valve
and pressure gauge with shut off valve shall be provided. The air vessel shall be
tested at 25 kgf/cm2 pressure before installation.
2.6.11 Installation
a) The installation work shall be carried out in accordance with the detailed
drawings prepared by the contractor and approved by the Engineer-in-charge.
b) In pipe above ground level, expansion loops or joints shall be provided to take
care of expansion or contraction of pipes due to temperature changes.
d) Open ends of piping shall be blocked as soon as the pipe is installed to avoid
entrance of foreign matter.
g) Pipe supports in pump house shall be floor mounted and of mild steel/
h) G. I. Spacing of pipe supports shall not be more than that specified below:
S Nominal Pipe Spacing
. Size (mm) (m)
N
o
1 20 and 25 2.00
2 32 to 125 2.50
3 150 and above 3.00
Extra supports shall be provided at the bends and at heavy fittings like valves to
avoid undue stress on thepipes.
j) Pipe sleeves of diameter larger than the pipe by least 50 mm shall be provided
wherever pipes pass through walls and the annular spaces shall be
filledwithfeltandfinishedwithretainingrings.
(i) Vertical risers shall be parallel to walls and column lines and shall be
straightandinplumb.Riserspassingfromfloortofloorshallbesupporte dat
each floor by clamps.
(ii) The space in the floor cut outs around the pipe work shall be closed using
cement concrete (1:2:4 mix) or steel sheet, from the fire safety
considerations, taking care to see that a small annular space is left
around the pipes to prevent transmission of vibrationto thestructure.
k) Wherever mild steel pipes shall have to be buried under ground, the same
shall be treated before laying. The top of the pipes shall be not less than 1m
below the ground level. Wherever this is not practicable, permission of the
Engineer-in-charge shall be obtained for burying the pipes at lesser depth.
Masonry or CC blocks shall be provided for supporting the pipes at interval.
After the pipes have been laid, the trench shall be refilled with the excavated
soil in layers of 20 cm and rammed and any extra soil shall be removed from
the site of work by the contractor.
l) Underground pipe shall be laid at least 2m away from the face of the building
preferably along the roads and foot paths. As far as possible laying of pipes
under road, pavement and large open spaces shall be avoided. Pipes shall not
be laid under buildings and wherever unavoidable, these shall be laid in
masonry trenches with removable covers and cut-off valves shall be provided
at points of entry and exit.
m) Pipe over ground shall be painted in red color. Suitable identification shall be
provided to indicate the run of underground pipe wherever the
route of underground pipe cannot be ascertained from the location of yard
hydrant/isolating valves.
(i)Split pipe support clamps with rubber lining for vertical, horizontal and roof
hanging.
(ii) Clevis Hangers for horizontal supports to adjust varyingheights.
(iii) Sprinkler Hangers for horizontal supports for pipes from 15 mm dia to150
mmdia.
Fasteners and fully threaded rods shall be used for installing the pipe supports. The
The water discharge shall not be less than 900 lpm for single head valves at 7
kgf/cm2pressure.
2.7.2 Installation
The landing valve shall be fitted to a T-connection of the riser at the landing in such
a way that the valve is in the center of the internal hydrant opening and at a height
of 900 mm from floorlevel. The valve base shall be vertical and the valve facing
outside. There should be no hindrance in operation of thehandle.
The water flow rate shall be not less than 24 lpm and the range of jet shall be not
less than 6 m.
2.7.5 Installation
First aid hose reels are installed with internal hydrant. The cabinet shall be painted
red. The size of the cabinet shall be such that there is no obstruction in swinging the
hose reel. The location of cabinet shall be such that it does not form an obstruction
in passage/escaperoute.
The length of hose tube shall be such that the nozzle of the hose can be taken into
every room and within a range of 6 m from any part of the room. There shall be no
obstruction in swinging the hose reel and should be installed above landing valve
wherever provided. The inlet valve shall be at 900 mm above floor level. Hose reel
bracket should be firmly grouted on the wall with the help of raw bolts.
The delivery hose couplings consist of male half coupling and female half
coupling.Groovesareprovidedonoutersideonboth thecouplingsforbindinghose pipes
with wires. In female coupling, spring loaded cam tooth is provided for holding male
half coupling in position. Male half coupling and female half coupling are provided
on both sides (i.e., on one side male and on other side female) of hose pipes. Two
or more pipes can be joined to gether with the help of these couplings in
stantaneously.
b. Spare Branch pipes and nozzles to the extent of 10 percent of the above
requirements, with a minimum of two sets, shall always be kept readily available
in fire control room/pump room.
These are provided for connection of fire service hose pipes for either directly
pressurizing the system with their pumps or filling water in the tank from a distance.
Non-return valve with butterfly valve shall be provided for holding water pressure.
Fire service inlet shall be provided with each wet riser/down comer and the ring
main. These are fixed to 150 mm diameter pipe and located in MS Box made of 2
mm thick mild steel sheet with openable glasscover. These shall be as per IS:904.
Material of Construction: Copper Alloy.
2.7.8 HosePipes
Hose pipes shall be rubber lined woven jacketed and 63 mm in diameter. They shall
conform to Type A (Re-inforced rubber lined)of IS:636.They shall be flexible and
capable of being rolled. Length of hose pipe will be 15 m.The hose pipe shall be
complete with male and female coupling at the end.Besides keeping hose pipe
with internal hydrant and yard hydrant, spare hose pipes to the extent of 10 percent
of the above requirements, with a minimum quantity of 30 m shall always be kept
readily available in fire control room/pump room. Such spare hose shall be in 15 m
(b) Stairs, spaces below stair headings (but not rooms above a stair) and lift wells.
Any part of the building not provided with sprinkler protection shall be fire
separated by walls. Fire doors not less than 1 hour in fire resistance shall be
provided in the opening of suchwalls.
(c) Wash rooms, toilets and WCs (but not cloak rooms) of area less than 5m2. If
area of these rooms exceeds 5m2, these shall be provided with sprinkler
protection unless fire separated by walls and all openings in the walls are
protected.
(d) Sprinklers shall not be required in electrical equipment rooms where all of the
following conditions aremet:
(e) Rooms like server room or electrical control room where alternateprotection by
other automatic extinguishing systems shall be provided.
(g) The area to be protected by sprinkler is divided into various zones. For
detecting operation of sprinkler in a zone, flow switches are provided which
are wired to an annunciation panel installed in the Fire Control
Room. In the event of operation of sprinkler(s) in an affected area. The
annunciation panel will give audio-visual alarm and indicate the affected zone.
This arrangement will be independent of fire alarm system.
(h) For moderate hazard, water discharge shall be at least 5 liter/min/m2 over an
assumed area of operation covering 360 m2.
i) Distance between sprinklers and the ceiling shall not exceed 150 mm. If
specifically approved for use and listed so, the distances between ceilings and
the sprinklers can be increased up to 450mm.
ii) Vertical side wall sprinkler deflectors shall be located not more than
150 mm or less than 100 mm from the wall from which they areprojecting.
iii) Sprinklers shall be so located to minimize obstructions (to discharge) either on
parallel or perpendicular sides thereof. If required, additional sprinklers shall
be provided to obviate theobstructions.
2.8.6 Sidewall Sprinkler Obstruction: Sprinklers shall be located at least 1.2 m away from
any lighting, fan and similar fixtures either in front of or on the same wall where the
sprinklers are mounted. For any obstruction (to
discharge) including lighting, fan etc., shall bebeyond1.2m, distances A and B shall
be maintained as per the Tables given below. In case these distances cannot be
maintained, the sprinkler shall not be allowed at such location.
Clearance between the top of storage if any to the deflector shall not be less than
450mm.
a) Side wall sprinklers in rooms shall neither be installed above the grills of air
conditioner nor within 450 mm thereof on the same wall. Horizontal sidewall
sprinkler shall be located not more than 100 mm and are allowed to be located
with their deflectors less than 100 mm from the wall on which they are
mounted.
e) When soffits used are within 200 mm in width or projection from the wall,
additional sprinklers shall not be required subject to the deflector of the
sprinklers falling within prescribed distance.
b) Sprinkler heads shall be provided considering the space as any other area in
the building.
d) Sprinkler heads for concealed space and for the room may be connected with
separate range/distribution pipes connected, with common feed pipe. The
common feed pipes shall be not less than 65 mmdiameter.
2.8.8 Pipe Sizing and Design: - Sprinkler heads shall be connected with pipe lines
permanently charged with water. Depending upon location of sprinkler heads and
site conditions, sprinkler heads may be connected with range and distribution
pipes.
The pipes connecting the sprinkler heads are to be sized depending upon
number of sprinkler heads and arrangement of their connection. Range Sizes of
pipes are to be calculated from various tables and hydraulic calculations given in
IS:15105.
ii) There shall not be more than 6(Six) sprinklers in any range.
iii) Range and distribution pipe nominal sizes shall be selected from Tables
given below respectively.
2.8.9 Range Pipe Nominal Sizes for Various Pipe Layouts in Moderate/Ordinary Hazard
Installations.
2.8.11 Components of sprinkler system: - Following types of valves are used in the
installations:
1. Test Valve. - For testing hydraulic alarm or electric alarm by drawing water from
downstream side, test valve shall be connected with downstream of the water
flowalarm.
A common valve can perform the functions of test and drain. The outlet shall be
connected with a 50 mm diameter G.I. drain pipe along with riser pipes.
4. Check Valve: - Check valve shall be provided where more than one water supply
is available and same shall be fitted on each water supplypipe.
5. Subsidiary Stop Valve: - Subsidiary stop valve which shall be of the same
diameter as the pipe line in which they are fitted and shall be provided to control
water supply to sprinklers of highly sensitive areas like computer rooms.
If there are genuine constraints in locating the Installation Control Valve outside the
buildings, this may be located inside the building in the vicinity of main entrance
(subject to approval of authorities concerned). Installation Control Valve in such
cases, shall be located away from any exposure to damage and personnel shall be
normally available in the vicinity of the location to get alerted by alarm operation.
Also, electrically operated sirens interfaced with the opening of the alarm valve of
ICV, shall be provided outside the building. In no case, Installation Control Valve
shall be provided inside basement or inside pump room.
A plan of the risk with the position of Installation Control Valve shall be placed in a
conspicuous location. A location plate shall be fixed near the Installation Control
Valve bearing the following words in raised letters:
SPRINKLER
ALARM VALVE
7. Water motor alarm: Water motor alarm shall be provided very close to the alarm
valve. Strainer shall be fitted between the alarm valve and the motor nozzle
connection. The water outlet shall be positioned so that any flow of water can be
seen. The alarm device shall provide audibility level of 85 dB above the back
ground noise level.
2.8.13 OrificeSize
Sprinklers orifice size of minimum 15 mm shall be used.
The protected floor area to be controlled by any one Installation Control Valve shall
not exceed 12000 m2.
As far as possible one area shall be controlled by one Installation Control Valve. If
the area is quite large, more than one Installation Control Valve should be planned.
Details of area controlled by an Installation Control valve shall be exhibited near it.
If there are more than one block in a campus, each block shall be provided with
different Installation Control valve.
2.8.16.1 ConstructionDetails
a) The Panel shall be fabricated out of not less than 2 mm thick MS sheet and
powder coated after 7 tank treatment process and shall be totally enclosed dust
damp and vermin proof. Suitable knockout shall be provided for the entry of
cables. The panel shall be designed such that the equipment for power
supply and battery charging are housed in
independent compartments. Sealed maintenance free batteries shall also be
accommodated inside thepanel.
c) The indicating lamps shall be LED type of following colors. The flow switch
operation conditions shall be indicated by twinlamps.
I. Red to indicate flow switchoperation.
II. Amber to indicate fault condition.
III. Green to indicate healthycondition.
g) The panel shall indicate the fault within the system and immediate fault warning
shall be given by an audible and visible signal on the panel in case of open
circuit, short circuit and earth fault in cable between flow switch and
annunciation panel.
h) The panel shall be complete with mimic diagram for the areas covered by
different flow switches. The layout of mimic diagram shall be got approved from
Engineer- in-Charge.
i) Battery backup with trickle cum boost charger shall be provided for operation of
the system. Indication of mains failure and the state of charge of the batteries
shall be provided. The batteries shall be sealed & maintenance free. The
capacity of the battery shall be 12 Volt, 2 Nos. 24 Ah each. All standard
accessories shall beprovided.
2.8.16.2 Installation
Following points in addition to general installation guidelines, are to be takencare for
sprinkler installations:
For basement car parking, compartmentation can be achieved, with fire barrier or
with water curtain nozzle (K-23) or with a combination thereof. Automatic deluge
system comprising deluge valve, piping, nozzles etc. shall be used to zone the
compartment in case of water curtain system. In case of water curtain, existing
water storage shall be supplemented by water demand for water curtain nozzles for
60 min considering the largest compartment’ s perimeter out of all compartments of
car parking in any of the basements. The water supply for the water curtain nozzles
shall be through an independent electric pump of adequate capacity (flow and head)
with piping/riser for the water supply to the nozzles. The water curtain shall be
operated by the actuation of flow switch actuating sprinkler system.
2.9.1 Installation
The spray nozzle must be handled with due care. Nozzle which is visibly damaged
should not be installed. Use Teflon tape or soft thread sealant on male thread of the
nozzle. The nozzles must be tightened into the fitting. Excessive tightening torque
may result in serious damage to nozzle arms and the deflector which may affect the
spray pattern of the nozzle and its performance. Spray nozzles are to be installed in
accordance with the latest published standards of NFPA or similar organizations
and also with the provisional governmental code, ordinance and standards
whenever applicable. The use of these nozzles may be limited due to occupancy
and hazard, Refer to Authority having jurisdiction prior to installation.
2.10.1 PowerSupply
b) The generator shall be capable of taking starting current of all the fireand life
safety systems and equipment as above.
c) The electric supply to the pumping set(s) shall be entirely independent of all
other equipment in the premises that is even when the power throughout the
entire premises is switched off, the supply to the pump
shall continue to be available un-interrupted.
d) The power supply to the panel/distribution board of these fire and life safety
systems shall be through fire proof enclosures or circuit integrity cables or
through alternate route in the adjoining fire compartment to ensure supply of
power is reliable to these systems and equipment. It shall be ensured that the
cabling from the adjoining fire compartment is protected within the compartment
of vulnerability. The location of the panel/distribution board feeding the fire and
life safety system shall be in fire safe zone ensuring supply of power to these
systems.
f) Independent supply shall be provided for water supply pumps if installed in the
same pump house. If the fire pump house is away from the sub- station
building, the route of the cable shall not pass under the building or permanent
structure. Cable shall be laid along the route which is safe from fire.
g) Sufficient spare power shall always be available to drive pumping sets at all
times throughout the year. Suitable capacity ACBs/ MCCBS/ SDFUs shall be
provided in the electrical panel for extending supplies to fire pumps. Such
switches shall be suitably marked "FIRE SWITCH" and shall not be switched-off
without permission/intimation to appropriate authority. In case any
maintenance/repair work is to be carried out on the electrical panel where from
supplies to fire pumps have been extended, alternative arrangement shall be
made to ensure that power supply to fire pumps continue to be available for
operation any time.
2.10.2 Motors
The motors shall be squirrel cage AC induction type. The motors shall be suitable
for continuous duty and rating necessary to drive the pump at 150 percent of its
rated discharge with atleast 65 percentratedhead.Themotor shall be totally enclosed
fan cooled type confirming to protection clause IP 21of IS:4691.The class of
insulation shall be ‘F’.The synchronous speed shall be 1500/3000 rpm as per
2.10.3 MotorStarter
a) The motor starter shall conform to IS: 1822 “Motor starters of voltage not
exceeding 1000 volts” and shall be air insulated and suitable for 415 V, + 10%,
50 Hz, 3 phase AC supply and shall be integrated in the panel.
b) Starter for the motor shall be direct on line (D.O.L) for motors up to and
including 7.5 H.P. rating and automatic star-delta type for motors of
higher ratings unless otherwise specified in the tender specifications. However,
for main Fire Pump & Sprinkler Pump Soft Starters may be used.
c) Each starter shall be provided with the following protections:-
1. Thermal overload on all the three phases with adjustablesettings,
2. Independent single-phase preventer. (Current sensingtype).
2.10.4 PanelBoards
a) The main panel board shall be floor mounted, free standing or wall mounted
cubical type and shall be factory built fabricated by one of the approved
manufacturers. Shall be fabricated from 2.0 mm thick CRCA sheet and powder
coated after 7 tank treatment process, fabricated with IP 42 degree of
protection. It shall be suitable for termination of the incoming cables
frombottom.
b) The capacity of switch gear shall be suitable for the requirements of motor
fed/ controlled. Starting currents shall be dulyconsidered.
SDFUS/MCCBsshallbeusedupto
630A.ACBshallbeusedfor630Aandaboveratings. All Switch fuse
units/SDFUs shall be of AC 23 duty as per IS: 4064-1978 as amended up to
date. They shall be complete with suitable HRC cartridgetypefuses.
c) Panel boards shall house starters for motors with independent current sensing
type single phase preventor for each starter. Volt meter with selector switch, a
set of indicating lamps and fuses for voltmeter and lamps shall be provided.
Ammeter with CTs, and selector switch shall be provided with each motor
starter. Instruments shall be flush mounted with the panel and have a class
index not higher than 1.0. The fabrication of switchboard shall be taken up only
after the drawings for the fabrication of the same are approved by theEngineer-
in-charge.
d) The layout shall be designed for convenient connections and inter- connections
with the various switchgear. Connections from individual compartments to cable
alleys shall be suchas notto shut down healthy circuits in the event of
maintenance work becoming necessary on a defective circuit. Care shall be
taken to provide adequate clearances between phase bus bars as well as
between phase bus bars, neutral andearth.
e) Where terminations are done on the bus bars by drilling holes therein, extra
cross section shall be provided for the bus bars. Alternatively, terminations may
2.10.7 PowerCabling
a) Power cables shall be XLPE insulated, PVC sheathed aluminum/ Copper
conductor, armoured cables of 1100 V grade.
b) Power cables shall be of sizes to meet the starting and running current of
motors fed and shall be as approved by the Engineer-in-Charge, after taking
into consideration the load, the length of cabling.
provided asrequired.
2.10.9 Earthing
a) Metallic body of all motors, medium voltage equipment and switch boards shall
be properly earthed. Number of earth tapping points shall be intimated well in
advance to the Structural earthing agency and shall connect to the points being
provided.
2.10.10 Painting
All panels shall be supplied with the manufacturer’s standard finish painting.
2.11.4 Installation: -
a) The pump and motor/engineare to be perfectly aligned on the base plate so that
b) The pipe supports should be decided in a way that the weight of pipes and
valves are not transferred to the pumps and supports do not cause hindrance in
movement inside the pump house. As far as possible, floor supports may be
provided in pumphouse.
d) All pressure gauges should be installed so that the dial is vertical and is visible
while entering the pumphouse.
e) Electrical panels should not be installed at floor level. The panels shall be
sufficiently raised above ground level. If panels are to be mountedon wall,
anangleironframeshallbeprovidedsothatatleast75mmspaceisleft behind the
panels. The panels shall be easily approachable.
f) Drain pump shall be installed in the sump provided. The pump shall operate
automatically for which water level sensor shall be provided.
g) In no case, any structural member i.e., RCC wall, column, beam and floor are
to be damaged during installation. Mechanical fasteners are to be used for
groutingsupport.
h) U.G. tank wall is not to be used for any support. No pipe/cable is to cross the
pump house below ground level. Openings above ground level are only to be
used for thispurpose.
i) The engine installation work shall be carried out in accordance with the
requirement of engine manufacturer and be got approved by the manufacturer
or their authorized service center. The exhaust pipe should be suitably
extended outside the pump house so that smoke does not affect nearby
structure. Fuel tank shall be properly supported and located in a way that the
same does not cause hindrance in movement in the pump house.
l) Pressure testing is to be carried out in sections before filling the earth back in
the trench.
n) Where pipes crossing road likely to have heavy traffic, additional protection over
pipe shall be provided to ensure that pipe is not damaged. However, semi-
circular RCC Pipes shall be provided overcast iron pipes at road crossings.
o) External hydrants and fire service connection/ inlet shall be located parallel to
the nearby road/ foot path so as to give proper appearance. Foundation shall be
raised from below ground level and shall be properly plastered in plumb. The
hydrants shall be facing the road/ approach. There shall be no obstruction in
approaching the hydrants for operation.
p) Risers shall be parallel to the wall and in plumb. Adequate supports shall be
provided from the wall. Opening around the pipe in slab shallbe filled with CC
and finished with plaster.
q) Internal hydrant shall be provided in the center and facing outside for ease of
operation. Sufficient space shall be provided around the handle for operation.
There shall be no hindrance in moving the first aid hose reel.
2.11.5 Testing
b) After completion, all operation checks shall be carried out for automatic
operation of the systems. For this purpose, landing valves may be opened at
different locations. The exercise shall be repeated couple of times to ensure
trouble free operation of the system.
c) The design flow of pumps shall be checked. The pump shall be operated after
opening a number of landing valves at different locations. Design pressure is to
be maintained in the pump house. Water discharge is to be measured by drop
in level in UG tank for a certain period. All pumps
shall be tested one by one. The flow rate shall be not less than as
specified while maintaining the design pressure in pumphouse.
After completion of the work and testing to the entire satisfaction ofEngineer- in-
Charge, the installation shall be offeredfor inspection by Chief Fire Officer or his
representative. Testing as desired by the Fire Officer shall be carried out. The
contractor shall extend all help including manpower during testing. Rectification of
observations of Fire Officer shall be attended by the contractor. The installation will
be accepted by the department only after clearance by Fire officer.
2.11.7 Commissioning
a) Flushing the System: Before commissioning, the entire system shall beflushed
to ensure that any earth/ foreign matters which might have entered
duringinstallationaretakenout.Forthis,pumpmaybeoperatedandvalves
openedatdifferentlocations.
c) The firefighting system shall be maintained and manned from the very first
day of itscommissioning.
d) Any defects noticed during the warranty period shall be promptly attended
and availability of the system at all times is to beensured.
S. No IS No. Title
1. IS-884 Specification for first-aid hose reel for firefighting
2.12.1 The scope of work shall include Design, Supply, Installation, Testing and
Commissioning of Total Flooding Clean Gas Fire Suppression System with HFC
227ea/ HFC 236/ NOVEC-1230 or equivalent gas Suppression system and related
accessories as per NFPA2001-2015 at Electrical Substation, Server Rooms, UPS
room, Medical gas pipeline system, LPG Manifold in kitchen etc., as required.
a) Total flooding clean gas fire suppression system cylinders, Relays, Valve
assembly, Solenoid valves and other accessories like NRVs, flexible hoses,
pressure gauges, Safety devices, Directional control valves etc. shall be as per
UL/VDS/LPCB/FM approvals and relevant standards.
b) Installation of Control panels and laying of cables necessary for Total Flooding
Clean Gas Fire Suppression systems (All the cables are to be provided with
casing cabinets for aesthetic look).
c) Necessary interfaces are to be provided for Fire Alarm Panel with Total
Flooding Clean Gas Fire Suppression system.
e) Training for operation and maintenance of Total Flooding Clean Gas Fire
Suppression system.
i) Total Flooding Clean Gas Fire Suppression systems shall be installed as per
the approved installation drawing.
b) An aesthetic cabin housing for Total Flooding Clean Gas Fire Suppression
system cylinder modules, Gas release panels at each location is also in the
scope of work.The scope also includes civil works required for completion of the
job.
c) After commissioning the system, all panel Keys, Passwords and software
required for programming devices shall be handed over to department in order
to ensure smooth functioning of the system.
d) Proper cable management system shall be used to route the cables in all the
locations.
d) The Contractor shall be responsible for adherence to all the applicable rules,
regulations & requirements of statutory bodies as required.
All the items supplied or used shall be manufactured/ fabricated and tested
in accordance with the relevant Indian/International standards.
NFPA 2001 Standard on clean agent fire extinguishing system
2.12.6 Systemdesign
a) Design of system shall be as per NFPA 2001-2015. The clean gas agent shall
be stored in a pressure not more than 50 bar. Design temperature shall be
taken as 21 Deg C (70 Deg Fahrenheit). All items like valves, actuators, Hoses,
cylinders, and piping manifolds, pressure switches, Arrangement for supervisory
switch connection for monitoring the cylinder pressure, nozzles, Annunciators,
evacuation sign boards, gas release panels etc., shall be UL/VDS/FM/LCPB
listed.
b) Piping network and nozzles shall be designed for minimum piping inside room
and effective distribution of extinguisher agent.
c) The clean gas fire suppression system of each room shall be interfaced with the
Fire Alarm system of the room. The system shall be operable automatically from
fire alarm panel upon detection of fire signal from two detectors simultaneously
of that location when the confirmed fire signal (Two detectors simultaneous
activation Logic) is received from fire detection & alarm system, automatic
clean gas total flooding system shall be triggered. Then complete premises,
shall be filled with gas and the fire shall be extinguished. High Sensitivity Laser
Smoke Detector shall be provided in these areas wherever Fire Suppression is
Provided.
d) The total flooding clean gas fire suppression system shall also to be manually
operable from local gas release control panel located near each room to be
protected. Necessary hardware interfaces with necessary relay logics and the
status are to be provided.
e) To avoid possibility of inadvertent manual triggering, the system shall be
latched with safety key switch.
f) The control panel shall also have status monitoring of gas discharge actuator
and Audio-visual annunciation of gas discharge.
g) Clean gas cylinders, associated instruments including control panel and pipe
manifold shall be located inside suitable enclosure with door near protected
area entrance.
h) Clean gas total flooding system shall be actuated on receipt of confirmed Fire
Detection Signal by FDA system.
i) AHU related to this rooms shall be tripped as receipt of confirmed fire signal
from FDA panel via interface modules.
2.12.8 Cylinders:
Cylinders shall be seamless construction in accordance with the requirements of
NFPA / Relevant BIS standards. Cylinder neck shall be threaded to suit the type of
valves.
2.12.9 Actuators:
Electrical / Pneumatic actuators, manual actuators, all actuators shall be as per
NFPA.
2.12.17 Inhibitor:
Auto gas system can be operated in Auto mode or in Manual mode. When a
confirmed fire signal is received by the control panel, it initiates the signal for
release of gas into the affected premise. Since the discharge of gas is purposefully
delayed say up to 60 seconds, the persons present in the premise may decide to
stop the release of gas, if fire is of minor nature or due to any other reason. This is
done with the help of Inhibitor.
b) Control panel audible alarm may be silenced at the panel, though the condition
of fire continues. When silenced the control panel provides a low intensity
audible alarm but serving to indicate the cancellation of the intermittent fire
alarm. Control Panel shall provide an adjustable time lag from 0 to 60 seconds
from the receipt of signal to the actual discharge of gas. All the necessary
cabling and interfaces are to be done as per standard. The control panel shall
have control and status of actuator and status of gas discharge. The necessary
provision shallbe available for extending the status to remote control room.
c) The Gas release panel shall be interfaced with fire alarm panel.
d) The scope of contract includes supply of required cable for interfacing Gas
release panel with Main fire alarm panel, laying, casing cabinets for routing
the cables, termination junction boxes and other required items /accessories
required for completion of the installation.
b) Flow test shall be carried with Compressed air/Nitrogen gas to ensure that there
is no blockage of nozzles.
c) All necessary instrumentation, equipment, materials and man power required for
testing shall be provided by the Contractor.
d) The Contractor shall record all tests and system calibrations and a copy of
these results shall be retained in Log Book.
b) Necessary man power, tools, consumables like smoke generator for testing
detectors, and test instruments etc. for maintenance of the system is in the
scope of Contractor.
c) During the period, quarterly visits shall be made by the OEM. During the defect
liability period, false alarms/emergency calls should be attended immediately on
receipt of information either from CPWD/ ESIC.
d) During every quarterly visit, scope of work shall include but not limited to the
following:
iii. Simulation checks of safety interlocks of clean gas fire suppression system
solenoids including AHU tripping from local control panels.
v. Checking the condition of the Piping manifolds, Hoses, clean gas Cylinders,
monitoring of cylinder pressure, safety burst disc, electronic control head /
Solenoid, pressure operated control head, flexible hose, strap, non-return
valve (NRV) and safety cap etc.
2.13 Automatic Fire Suppression system for Electrical Panels (With Heat Detection
Tube)
This section is for an Automatic Fire Detection and Clean Agent Fire Suppression
Systems by use of Linear Pneumatic Heat Detection Tube as ‘Direct’ Gas Flooding
System for Electric Panels. The scope of work includes design, supply, installation,
testing and commissioning of Automatic Clean Agent fire suppression System for
All electrical panels complete with fire detection tube, cylinder, valves, integration
with Main Fire Alarm Control Panel for status monitoring etc.
a) Arrangement of Clean Gas Agent for flooding inside the panels.
c) The electrical panel fire suppression system shall be complete with Direct
‘Clean’ Gas storage cylinders of required capacities, linear fire detection tubing,
filling of gas, end-of-line adaptors, pressure switches, control equipment and all
necessary accessories and push in fittings to form a complete and working
installation to protect all-Electrical panels
in case of fire.
d) The system so provided shall have an interface with the Fire Alarm Control
Panel. In case of fire in the concerned Panel, indication of Fire detection and
Gas discharge status should be available in the Fire Alarm Control Panel.
f) The clean agent used should be eco-friendly like HFC227ea/ HFC236 / NOVEC
1230.
g) Each Clean Agent extinguishing unit, when installed, shall be a self- contained
system, equipped with its own automatic (non-electric) detection system, which
when actuated, automatically shall release the suppression agent into the
Electric panel.
h) The Clean Agent Automatic Direct System shall consist of the following major
components: Clean Agent Cylinder, Valve Assembly, Cylinder Mounting
Bracket; Fire Detector, Actuation and Discharge Fire Tubing Fittings and
Pressure Switch.
i) The Clean Agent Automatic Direct System shall utilize flexible tubing that shall
be attached to the top of the cylinder valve. This tubing shall be pressurized
with dry nitrogen, which is temperature sensitive, and it shall act as a
continuous linear thermal detector that ruptures upon Flame impingement.
Once the detector tubing is ruptured forming a nozzle at the rupture point, the
Clean Agent flows through, distributing the extinguishing agent only into the
protected area. Upon system actuation, the pressure switch shall be used to
indicate system discharge, shutdown ventilation, or shut-off electrical power
etc.
j) The Clean Agent Automatic Direct System shall be designed and listed as an
Automatic unit. No manual or electric means is to be required for simultaneous
actuation of multiple systems. Only 1 unit shall be used to protect one hazard
and shall not be combined to protect a larger size hazard.
k) The Clean Agent shall be stored in pressurized cylinders and the ambient
operating temperature range for all the cylinders and all other system
components shall be from 10 Deg C to 50 Deg C
o) A pressure switch shall be connected at the end of line of the Detection Tubing
to monitor system pressure, system actuation and / or to energize / de-energize
electrically operated equipment. There shall be provision to connect the
pressure switch to some other device(s) to alert personnel in the event of a
system discharge.
A sufficient amount of Clean Agent liquid to convert into Clean Agent HFC227ea
/HFC226/NOVEC 1230 shall be provided.
The contractor shall submit the calculations to verify suitability of the volume of the
clean agent. The following shall be considered during the design calculations:
f) Interface system with main control fire alarm system and , shall be provided.
g) Provide total flooding of Clean Agent concentration by volume as per NFPA-
2001.
h) When the additional limitations of hazard volume, area coverage, maximum
height, design concentration, agent quantity, detection tubing arrangement etc.
are also met, the system installation shall comply with the design requirements,
NFPA-2001.
i) All doors and holes in the enclosed / equipment shall be closed or sealed to
maintain the tightness of enclosure.
j) The system shall have means to close the exhaust fans if installed in the panel
at the time of system activation.
k) The main supply of panel can be shut off with the system, if so, required by the
Engineer-in-Charge.
c) Once the detection tubing is ruptured, forming a nozzle at the rupture point, it
shall allow the Clean Agent through the Nozzle into the protected area.
a) PESO approved Cylinder of steel construction with standard red epoxy paint
finish. Cylinders shall be accompanied by original manufacturers test certificate
confirming the contents of the cylinder and filled in PESO Approved plant.
b) Each cylinder shall have pressure gauge and integrated low-pressure switch
to provide visua land electrical supervision of the cylinder pressure.The low-
pressure switch shall be wired to the Audio- Visual
Alarmtoprovideaudibleandvisualtroublealarm in the event of drop of pressure.
The pressure gauge shall be color coded to provide an easy,visual in
dication of cylinder pressure.
c) The cylinder shall be equipped with brass valve, pressure gauge (to monitor
agentpressure) and isolation valve for maintenance purposes. The cylinder
valve shall be with a safety burst disc of 28 Bar rupture Pressure.
d) Furnishaweldedsteelbracketwitheachcylinderassemblyforholdingthecyli nders
inasaddlewitha front bracket piece that secures the cylinders.Cylinder shall be
provided with a certificate provided by the company who chargewith the gas
mixture.
e) The Detection Tube shall be ULapproved red / black in Colour and pressurized
as per system design requirement.Theintegrated PressureSwitch (CE/UL/LPCB
marked) should be integral part of valve havingNO /NC contact.
f) The control box enclosure shall be at least IP 54 rated from OEM of gas
suppression system provider complying standard. The unit shall have LED
indication for system Healthy, Mains Healthy and Gas Release. The unit shall
also have signal silence button. Third Party test reports for IP and
Functionality of the system to be submitted for approvalcomplete as required.
2.13.4 Installation
a) Thesystemshallbeinstalled as per approved shop drawings.The installation/final
connections shall be carried out indirect supervision of representative of
Manufacturer/ specialized agency. Cylinder shall be located so that they are
not subjected to mechanical,chemical or other
damage.
b) All system components shall be capable of with standing heat offire and sever e
weather conditions. DetectionTube to be properly secured inside the panel by
Clips/ Tieetc. The Detection Tube out side the panel should be protected in
flexible conduit.
c) Inspectioncertificateshouldbepastedoncylinderclearlymarkingnextdued ateof
inspection.
2.13.6 Documentations
Contractor shall prepare shop drawings of automatic Linear Pneumatic Heat
3.1 The scope of work shall include designing supplying and installing of Intelligent
Addressable Fire Alarm System and Public Address System. The work under this
system shall consist of furnishing all materials, equipment, appliances and labour
necessary to install the complete Fire Alarm System, complete with Main Fire
Alarm Control Panel, Sensors, Sounders, Strobes, Manual Call Stations, Relays
etc. for interfacing with other systems in Main Hospital building and other service
areas as required. These technical specifications shall be read along with the
General Conditions for all E&M works given under subhead C-B.
3.1.1 The facility shall have an emergency voice alarm communication system. Digitally
stored message sequences shall notify the building occupants that a fire or life
safety condition has been reported. Message generator(s) shall be capable of
automatically distributing up to eight (8) simultaneous, unique messages to
appropriate audio zones within the facility based on the type and location of the
initiating event. The Fire Command Centre (FCC) shall also support Emergency
manual voice announcement capability for both system-wide or selected audio
zones, and shall include provisions for the system operator to override automatic
messages system-wide or in selected zones.
3.1.2 The system shall support additional, alternate Fire Command Centers, which shall
be capable of simultaneous monitoring of all system events. Alternate Fire
Command Centers shall also support an approved method of transferring the
control functions to an alternate Fire Command Centre when necessary. All Fire
Command Centers shall be individually capable of assuming Audio Command
functions such as Emergency Paging, audio zone control functions, and
Firefighter's Telephone communication functions.
a) Each designated zone shall transmit separate and different alarm, supervisory
and trouble signals to the Fire Command Center (FCC) and designated
personnel in other buildings at the site via a multiplex communication
network.Any opening/chasing in the wall/ceiling required for the installation
shall be made good in appropriate manner.
b) The Contractor shall also undertake to control and monitor the ventilation and
other systems from the Fire Alarm Panel through the use of Addressable Output
/ Input Modules.
c) The building shall be designated as multiple fire zones with each area forming
one or more programmed zones. All wiring shall be done using 2 x 1.5 mm2
Fire Survival armoured copper conductor cable.
d) Alarm, trouble and supervisory signals from all intelligent reporting devices shall
be encoded on NFPA Class A Signaling Line Circuits (SLC). Initiating Device
Circuits (IDC), Notification Appliance Circuits (NAC) shall be wired in NFPA
Class A.
e) Alarm signals arriving at the FACP shall not be lost following power failure
(or outage) until the alarm signal is processed and recorded.
f) Two-way emergency telephone communication circuits shall be supervised for
open and short circuit conditions.
iii. The digital audio message generator shall be of reliable, non- moving parts,
and support the digital storage up to 32 minutes of tones and emergency
messages, shall support programming options to string audio segments
together to create up to 1000 messages, or to loop messages and parts of
messages to repeat for pre-determined cycles indefinitely.
Intelligent Fire Alarm System (IFAS) shall be provided to effect total control over the
life safety services required in the building. The IFAS shall be of the digital,
distributed processing, real-time, multi-tasking, multi-user and multi-location type.
The IFAS provided shall be able to tie up the following Mechanical, Electrical &
Low Voltage Services into an integrated system.
a) Air Handling Units, Fire Dampers.
b) Staircase pressurization fans, Lift shafts and lift lobbies pressurization
fans.
c) Public address system.
d) Lifts
e) Smoke evacuation system
f) Firefighting/ Fire Suppression system
In the event of a fire alarm, but not in a fault condition, the following action
shall be performed automatically.
a. The System Alarm LED on the main fire alarm control panel shall flash.
d. History storage equipment shall log the information associated with the Fire
Alarm Control Panel condition, along with the time and date of occurrence.
e. All system output programs assigned via control-by-event programs that are to
be activated by a particular point in alarm shall be executed, and the
associated system outputs (alarm notification appliances and/or relays) shall
be activated.
f. The audio portion of the system shall direct the proper signal (tone or voice) to
the appropriate speaker circuit.
g. All lifts initiated through the system shall automatically be returned to Ground
Floor.
h. Air handling units on affected floors shall automatically be switched OFF and
simultaneously respective fire dampers shall also be closed.
3.1.5 Standards
The design, supply and installation and testing of the entire fire alarm system shall
conform to EN 54 / BS: 5839 or NFPA 71 and 72. The detectors shall conform to
relevant IS codes for Fire Alarm Systems, Local Bye-laws and National Building
Code, CPWD Specifications Part-VI (Fire Alarm System).
All components of AFAS shall be new and suitable for the environment of
installation at site. These shall be satisfactory in operation at voltage
deviated by ±10 % from the nominal value.
(ii) All minor building work such as cutting and making good thedamages.
(iii) Necessarytestingequipment.
(iv) Approval from the concerned fire authoritiesas may be required as per the
local Fire Regulations and by elaws.
3.1.8 Guarantee:
The contractor shall guarantee the entire AFAS installation as per specifications
both for components and for system as a whole. All equipment shall be guaranteed
for Three years from the date of acceptance against performanceor break
down due to defective design, manufacture and/or installation. The installation shall
be covered by the condition that the whole installation or any part the reoffound
defective with in the years from the date of taking over shall be replaced or
repaired by the contractor free of charge to the entire satisfaction of Engineer-in-
Charge. In case it is felt by the department that undue delay is being caused by
the contractor in doing this, the same will be got done by the department at the risk
& cost of the contractor.
The warranty shall cover the following: -
(i) Quality strength and performance of materials used.
(ii) Safe mechanical and electrical stress on all parts under all specified
conditions of operation.
(iii) Satisfactory operation during the DL Pperiod.
(iv) Performance figures and other particulars asspecified by the tenderer under
schedule of guaranteed technical particulars.
a) The panel should work on Dual Redundant control module. i.e., if the main
panel experiences a system fault, the DRCM automatically switches all field
wiring to the redundant panel. If the mains incoming supply fails, an internal
feeder selector card switches to a backup mains supply.
b) All addressable units shall be connected to the FACP through the Loop Cards
and shall be addressed through individual numbers. The FACP shall be able to
obtain analogue value for all detectors in the circuit through a pulsed digitalized
current data. The FACP shall be able to analyze all analogue inputs from all
addressable units, and through its own software and ambient level screening
the FACP shall be able to identify fire, possible fire or fault conditions. The unit
supervision shall be dynamic and continuous.
c) The FACP shall itself have loop card built in. The capacity of the Panel and
number of loops shall be designed by the contractor based on the total
detectors and devices. All the networked panels shall display all the events
occurring anywhere in the system. Each FACP on the network shall effectively
function as a repeater panel as well.
d) The FACP shall also give adequate warning signal whenever there is dust
accumulation in detectors, and up to the point of its replacement it should be
possible to change the level of ambient alarm calibration condition either by the
use of software program operable by the owneror by resetting the detector.
e) Short / Open circuit units shall also be reported at the FACP. In such cases, the
system through the use of fault isolators shall be able to isolate that segment
between the two fault isolators. The missing Detectors/Devices shall also be
reported at the FACP with identification of the location.
f) When an alarm condition is sensed at the FACP from a smoke or heat detector,
a delay time/alarm verification period shall be started. If the sensor is still in
alarm after the delay time expires, an alarm condition is reported. The delay
time shall be adjustable from 0 to 990 secs.
g) The FACP shall have the facility to perform walk test such that an operation can
be periodically checked out for all initiating devices. As each device is placed
into alarm, the FACP shall print the condition and automatically rest the device.
Audible devices shall be initiated, if required, at a pre-programmed time. If a
zone is inadvertently left in walk test mode, it shall automatically reset to normal
after the idle time is exceeded. During the walk test, the zones other than the
programmed zones shall be under continuous supervision (normal mode). In
case of any alarm initiated by detector/devices, the walk test shall get
terminated automatically.
i) Programming may be carried out from the FACP keyboard or utilizing the
approved PC setup software via laptop/desktop computer.
j) The FACP shall have a minimum 300-character graphics/ LCD display with
touch screen or other keypad and minimum 4000 events history log in the non
volatile memory (EPROM), power supply unit (230 ± 5% V,50 hz), 48 hrs back-
up with 24-volt sealed maintenance free batteries with automatic charger. In
case of testing of the system from the FACP the Display shall be able to give
readouts of analogue value of alldetectors being tested. The FACP shall also be
able to carry out continuous self-monitoring when in normal condition.
k) The FACP shall have facility for in-built or external printer coupled to the FACP,
which shall log all events with time. The printout shall clearly indicate the event -
Fire/Pre-Alarm/Fault etc. with the unit address and time.
l) The FACP shall also be able to discriminate between false alarms and fire
conditions, as well as priority selection of alarm in case alarm activates in two or
more remotely located units simultaneously. In such cases, the Manual Call
stations shall have the highest priority.
n) The System shall be fail safe and adequate safe guards should be under taken
that in the event of a failure of a part of the System, it shall not handicap the
complete System. The Loop Cards shall be of Modular Construction.
p) The FACP shall have its own Battery Backup of a minimum of 24 hours in
normal condition and then half an hour in alarm condition. The backup time
calculation shall be done as per IS 2189 standards. The Battery shall be 2*12V
(24V) DC with required AH capacity and of sealed lead acid rechargeable
maintenance free type, housed inside the FACP.
r) The FACP shall be totally enclosed dust and vermin proof type made of
minimum 16-gauge dust inhibited sheet with even baked finish. The FACP shall be
of completely solid stage design.
t) The system shall be designed such that it shall be possible to add at least 20% of
the Detectors for future expansion without extra cost on the panel.
u) The FACP shall be capable of being networked (future expansion) with other
similar FACPs located at different parts of the premises through a single RS485
bus.
v) The FACP shall have provision for interfacing with the Public Address System.
w) The panel should have the facility to interface with an automatic two- channel
programmable speech dialer for verbal reporting of fire. It shall be able to call four
telephone numbers per channel. The programmable speech dialer shall have
two alarm inputs and shall provide listen-in capabilities through the built-in
microphone. The dialer shall have a built-in keypad for easy operation,
programming and voice recording.
x) The panel shall have facility to connect printer to printout log and facility to have
seamless integration with analog/digital voice evacuation system and shall be
complete with all accessories. The panel shall be compatible with open protocol
BACnet/ Modbus over IP complete as per specifications
3.2.3 Loop
A loop shall be capable of supporting not less than 240 devices (including
detectors) and minimum 120 detectors per loop and loop length up to 2 km,
network communication card. The loop card shall have built-in short circuit
B. Heat Detector
a) Heat detector shall provide temperature measurement when it reaches pre-
alarm in normal course. However, the operator shall have the option of calling
up the temperature measured by the specific detector as and when required.
b) It shall have in-built locking mechanism to check the removal and pilferage of
the detector.
c) The heat detector shall be Analogue Addressable type and be able to send
analogue output to the FACP regarding its condition. It shall be able to
communicate with the FACP by the pulses emitted from the FACP. The
detector should be programmed using a decade or rotary switch.
d) The base of the Detector shall be electronics free and interchangeable with
other smoke or heat detectors. It shall be able to withstand temperature
variations from - 0 degree centigrade to 60 degrees centigrade. Further,
Relative Humidity (non-condensing type) 10 to 90% shall not hamper its
performance. The voltage rating shall be from 15V to 32V DC though the
voltage may be changed depending upon the Manufacturer’s standards.
e) The Detector shall have EN or UL/FM approval. It shall be possible to test the
Detectors working both from the FACP as well as locally by means of magnet to
do a Functional Test.
f) The detector shall have LEDs for 360 degree viewing angle. LED on the
detector shall blink each time the sensor is scanned by the FACP. If the FACP
determines that the sensor is in alarm, the FACP will command the sensor LED to
remain on to indicate the same. Each sensor will be capable of being tested
for alarm via command from the FACP. Each sensor shall respond to FACP
scan with the information about its typefor identification.
g) It shall be possible to connect loop powered base sounders on the detector
loop.
d) Detector shall have LEDs for 360 degree viewing angle. LED on the detector
shall blink each time the sensor is scanned by the FACP. If the FACP
determines that the sensor is in alarm, the FACP will Command the sensor
LED to remain on to indicate the same. Each Sensor will be capable of being
tested for alarm via command from the FACP. Each sensor shall respond to
FACP scan with the Information about its type for identification.
e) it shall be possible to connect loop powered base sounders on the Detector
loop. The sounder shall have a sound output of at least 85db and will not
require a separate cable for power supply.
b) The transmitter shall emit an invisible pulsed infra-red beam to receiver when
beam is obscured beyond selected threshold (20%, 30%,
........70% obscuration) by smoke, the receiver shall signal an alarm. If the
beam is completely blocked, receiver shall signal a trouble.
c) It shall provide selectable sensitivity and alarm response time for flexibility of
installations.
d) It shall have a range coverage from 9 mtrs. to 100 mtrs. with upto 16- 17 mtrs.
spacing between adjacent detectors on smooth, flat ceilings.
c) The Manual Call Station shall be fully addressable with its own addressable
module and operated by digitized signals from the FACP. The voltage range
shall be from 15V to 32V. It shall have protection as per IP33. The operating
temperature range shall be from 0 degree C to 60-degree C. Relative Humidity
(non-condensing) range of performance parameters shall be between 10 to
90%.
a) The sounder shall be Addressable Loop Powered electronic type and shall give
discontinuous/ intermittent audible alarm whenever any detector or MCP
operates. The sound output from the Hooter should not be less than 85
decibels and up to 120 decibels at 1mtr distance.
c) The Inlet tube shall extend into and across the duct width; the outlet tube
shall be of fixed length.
ii) It shall function on the Venturi principle, with Aluminium Venturi tubes.
iii) The Duct Casting Unit shall be compact, easy to install and with the
iv) The housing shall be mounted outside the duct; the probe tubes shall be
inserted through the duct by cutting precision sized holes into the duct
and sealed with rubber gaskets.
b) All buildings with the exception of smaller ones need to be divided into
detection
zones.Thezonesneedtobesmallenoughforafiretobelocatedquickly.Evenift he
system is addressable, zoning indications needs to be provided as this often
provides
aquickerdisplay.Also,thiswouldenablefirefighterswhoarenotfamiliarwitht he
building toproceedtothelocationoffire.
a) Thefloorareaofsinglezoneshallnotexceed2000Sqmtr.
b) Eachzoneshallberestrictedto asinglefloor.
c) Voids above or below the floor area of a room, can be included in the same
zone.The voids and the room constitute a single compartment.
d) The traveled distance by any one responding to a fire alarm signal, shall not
exceed 30 mtrs.
e) Any enclosed stairwell, lift well or other enclosed shaft-like structures shall be
considered as a separate zone.
f) If manual call points are located on the landings of an enclosed staircase, such
points at each level shall be incorporated within the zone that serves the
adjacent accommodationonthatlevel.
g) The detectors and manual call points within sectors/zones shall be wired to the
controlandindicatingequipment.
h) The entire electrical installation pertaining to the entire fire alarm system as
detectors.
g) Similarly, ceiling obstructions such as structural beams, deeper than 10% of
the overall ceiling height shall be considered as walls for the purpose of sitting
the detectors.
Note: -
The spacings have been adopted from the charts published by Fire Detection
Institute of America and adopted by NFPA (National Fire Protection
Association of America). The spacing for parameters of other than those
considered here can be found from these charts.
3.3.7 Compensationtothespacingofdetectors: -
Heightconsideration: Spacingof7.5meterforsmokedetectorsisvalidonlyup
toa height of 7 meter only and that 5 meters for heat detectors is valid
only up to a height of 5 meter. Beyond these heights, spacing between
the detectors shall be adjustedas below:
a) Above7-meter ceilingheight:Onlybeamdetectorsshallbeprovided.
b) Heat detectors for heights between 5 meter and 7 meters: 3.5 meter spacing.
Multiplyingfactorformodified
Airchangesperho
ur inside Spacing(inmet (Areacoverage)(inSq. meter)
block er)
Less than 7.5 1.00 (1.00)
b) In case of asloping roof or pitched ceiling (where the distance between the top of
apex and bottom of the roof exceeds 600 mm), distance stated above may be
increased to 8.5 meter.
c) Where optical beam type smoke detectors are used more than 600mm from
ceiling level in order to provide supplementary detection of rising smoke
within a high space (likeAtrium etc.), the width of the area protected on each side
of optical beam shall be regarded as12.5% of the height of the above beam from
groundle vel.
d) Where there is a probability of people walking through the beam or where the
beam is likely to be obstructed by forklifts etc., detectors shall be mounted
at a suitable height.
imposed load.
f) The path length of the optical beam shall be within the limits specified by
the manufacturers.
g) Beam detection area shall not exceed the detection zone in which it isinstalled.
3.4.3 Testingafterinstallation:
Following tests shall be conducted in a completed FAS/AFAS/intelligent
addressable FAS installation, in the presence of the Engineer-in-Charge
and the test certificate shall be furnished for the followingtest.
(i) Continuitytest.
(ii) Test for insulation resistance of the wiring and the control and indication panels.
(iii) Test for system operation.
In the case of AFAS (See the note below), this test for fire conditions shall
be conducted using a test fire at normal floor level. The number of locations
for such a test shall be 1% of the total number of detectors in an installation
subject to a minimum of two and maximum of five. The system operation for
fault conditions shall be conducted by introducing faults such as open
circuit, short circuit, removal of detector, open/short circuit in a sounder
circuit etc.
Note: Use of a test fire in the case of installation using heat detectors need
not be insisted upon.
3.4.4 Inspectionbylocalbodies
It shall be the responsibility of the contractor to get the installation inspected and
passed by the local authorities concerned, as may be required by the local
bye-laws, and 'No Objection Certificate(N.O.C) shall be obtained.Payment
made for statutory fees shall be reimbursed on production of receipts.
The system shall be fully programmed to accommodate fire alarm and voice
communication zones. The system shall be configured to allow on-site
modifications with the minimum of disruption using the PC-based software to
facilitate changes or alterations.
3.5.2 Generalrequirements:
g) The system integration should take into consideration the height of the
ceiling at various places, critical distance and directivity factor of the
speaker system. The reverberation time of each zone in the terminal
should be measured and the Electro acoustical adjustments should be
carried out to achieve the target criterion as required, where
announcements are made.
3.5.3 System Design
a) The PAVA system shall be connected to the Fire Alarm system with in-
built isolators to protect the system in case of any cable faults. The
system shall be decentralized in nature, each distributed rack DAU
(Distributed Amplifier Unit) shall have all the DSP (Digital Signal
Processing), amplifiers and monitoring in such a way that can work in a
stand-alone mode in case the master rack is faulty or down.
zone at any time interval, without affecting the music in the other areas.
Each Zone and circuit speaker shall have a separate amplifier, system
sharing two amplifiers with multiple circuit speakers are not acceptable.
There shall be one backup amplifier for every five amplifiers, the system
shall automatically change over to the backup in case of any amplifier
failure, and the backup amplifiers shall be monitored as well. In case of
any system component failure, the paging microphone shall override
any defective unit and provide paging to the required zone. The System
can provide any Cause & Effect programs after integrating with the Fire
Alarm System, thus Alert/Evacuate messages can be programmed and
delayed as well as played on any zone/floor as per the Cause & Effect
approved by the Engineer.
b) The Amplifier shall have eight channels, four primary & four backups,
and each primary channel have a rated power of 100W. The Amplifier
shall have switch power technology for power saving, sleep mode is
automatically enabled when no signal input is detected. Total number
of Amplifiers and rating of each one shall be designed as per the actual
requirement.
c) The amplifier shall have AC 70V or 100V power supply and DC 24V
input, having a separate fuse for each channel. The Amplifier shall be
connected through balanced audio input and shall work on 100V
Speaker Line.
Technical Specifications
3.5.5 Speakers
a) Speakers shall specially be designed for broadcasting high-quality,
integrated emergency fire alarm signals and voice communications and
approved by an appropriate authority for use in such situations. Speakers
shall be ceiling, wall-mounted or Horn speakers and shall be completed
with mounting bracket, accessories and metal enclosures etc. as
required.
b) Speakers shall be of high efficiency, providing maximum output at
minimum power across 60 – 16000 Hz frequency range for Indoor
Speakers. Speakers shall have a line matching transformer for direct
connection to amplifiers with multiple taps. Speakers external
appearance shall be approved by the Engineer-in-charge. Speakers shall
be interconnected in the zone configuration.
3.5.6 Rack
c) The Rack should have DIN Rail Mounted Terminal Blocks for
termination of Speaker Zone cables on the rear. All cables coming from
Speaker zones, Call Stations, and Power supply should enter from the
Bottom. The rack should be installed at a location which has a minimum
of 600mm space from front & back for accessing it easily. The rack
should be installed in a well-ventilated room preferably Air-conditioned.
The unit should have Fans from the top. The unit should have a
Lockable Glassdoor at front.
3.5.7 Speaker Cables
All cables associated with PA System shall be of the following
specifications:
and should have 100V/70 Output, with 100 - 240 VAC input and 24 VDC backup
with UPS power supply complete etc. as required.
o Each amplifier shall not be loaded more than 80% of its rated capacity
o Every alternate speaker shall be connected with two different amplifier circuits to
provide speaker line redundancy for each zone.
o All amplifier channels shall supervise the integrity of connected loudspeaker lines
without interruption of audio distribution.
o Every amplifier shall have an independent spare channel for redundancy or one
separate spare amplifier for providing channel wise redundancy for a cluster of N
main amplifiers, where N<=7. Th
4. Paging Station: The paging station shall be IP based with appropriate size
Networkable capacitive touch screen for selection of zones. It should be having
inbuilt features like supervision of system status, setting of scheduled broadcasts
with the minimum features of Built-in monitoring loudspeaker, Detachable goose-
neck microphone or handheld microphone, LCD touchscreen display with up to
2000 zones complete etc. as required. The power supply shall be done through
POE switches as required.
The priority of paging shall be as follows:
(i) Fire/security control room – 1st Priority
(ii) PA control room -2nd Priority
(iii) OT floor and Doctors call -3rd Priority
5. Speakers: The speakers required for PA system shall be of recessed type with
metal box in ceiling/wall with minimum power rating of 6W and shall be tapped to
3W/1.5W as per the requirement of the system.
6. System Management Software: Supply, Installation, programming
customization as per site conditions, testing & commissioning of System
Management software in integration with IBMS software with one server & client
license of minimum 10 years. It should connect with upto 250 controllers.
Administrator can decide No. of users and define user authorities freely. It shall
display all equipment status and indicate fault alarm location, record and read
history of operation and fault logs. It shall support Text-to-Speech (TTS) function.
The flexibility of accessing Audio files stored on the server from any zone on the
system network etc as required.
8. The wiring of PA system shall be done with suitable grade FRLS PVC insulated
twin core, shielded, copper conductor flexible cable in the recessed MS (mild steel)
conduit laid in wall/ slab including connections and interconnections etc. as
required.
9.Power supply of Equipment: The power supply shall be done from OEM
prescribed DC power device which provides DC‐power supply to connected
amplifiers and peripherals from the mains, with a standards compliant charger for a
single 12 V backup battery, saving on installation and battery maintenance costs.
The integrated 6‐port POE switch which shall be connected with RJ 45 of SFP port,
with glass fiber support is required for the interconnection of decentralized clusters
of devices.
The power supply of paging station, amplifier etc shall be done through separate
POE switch of minimum 8 port with 2 Nos SFP ports.
In addition to the standalone battery mentioned in above para, The Main power
supply shall be taken from the UPS room from the dedicated supply provided in
electrical shaft.
C-4 LIFTS
4.1 The scope includes Planning, Designing & preparation of Drawings providing,
installation at site, testing and commissioning of MRL/ Machine Room type
Passenger / Hospital bed liftsof various capacities block wise details as given, as
per architectural plans and in accordance with NBC 2016 / CPWD Specifications as
amended up to the date.If any item required to make the service functional, is not
specifically mentioned in the scope and specifications, the same is deemed to be
included within the scope of this tender.These technical specifications shall be read
along with the General Conditions for all E&M works given under subhead C-B.
4.1.1 The lift manufacturer should fulfil the following eligibility criteria.
a) The lift manufacturer shall comply with BIS standards, duly certified by the
manufacturer itself.
b) The manufacturer shall be compliant to the Public Procurement (Preference to
Make In India), Order 2017 (as amended from time to time) issued by the
Department of Industrial Policy and Promotion (DIPP), Ministry of Commerce
and Industry.
c) The manufacturer shall furnish an undertaking regarding availability of spares
for the entire expected life of the lift i.e. 15 to 20 years.
d) The complete lift installation including its components, safety devices, various
types of controls etc., testing, inspection, operation & maintenance shall
conform to relevant Codes, Standards, code of practices, guidelines, safety
rules, inspection manual(s), rules issued by Bureau of Indian Standards, as
amended up to the last date of receipt of tenders.
e) Quality standards shall conform to latest IS/ISO-9001:2015.
f) The down time of installed lifts being maintained by the manufacturer shall not
be more than 8 hours (average) in case of minor faults and 7 days (average) in
case of major faults during the last one financial year.
4.1.3 Major activities requiring approvals / review shall include but not be limited to the
following: -
a) General Arrangement drawings for the lifts including section through lift pit and
lift shaft,
b) Quality assurance procedures,
c) Field testing and commissioning procedures
d) Engineering activities to be performed by Contractor.
e) Control and protection scheme.
f) Factory inspection and testing procedures.
g) Preparation of as-built drawings
h) Any other work/activity, which is not listed above, however is necessary for the
completion of lift/system.
4.1.4 Conformity with statutory Acts, Rules, Regulations, Standards and SafetyCodes:
The installation shall be carried out in conformity with the local lifts Act and Rules.
where no local Lifts Act are in force, the Bombay Lift Act shall be followed. The
installation shall also conform to requirements of local Municipal Bylaws, norms laid
by Tamilnadu State Electricity Board etc.
All electrical works in connection with installation of electric lifts shall be carried out
in accordance with the provisions of Indian Electricity Act 2003 and the Indian
Electricity Rule 1956 amended up to date and CPWD General Specifications for
Electrical works amended up to date.
4.1.6 Training
The scope of works includes on job technical training of two persons at site.
4.1.7 Guarantee
The installation shall be handed over to the department after necessary testing and
commissioning. The installation materials shall be guaranteed against any defective
design/workmanship. The guarantee period will be for a period of 36 months from
the date of handing over of entire work covered under agreement to the
Department. The firm will be required to submit guarantee of material from the
manufacturer to the department. AMC (Comprehensive) of lifts during the defect
liability period will be in the OEM scope, nothing extra payable for AMC during
defect liability period.
Sufficient trained and experienced staff shall be made available to meet any
exigency of work during the guarantee period till the end of defect liability period.
The maintenance up to the end of defect liability period, routine as well as
preventive, as per manufacturer’s recommendation, shall be carried out and the
record of the same shall have to be maintained.
30 days before the department takes over. During this period, the lift shall be kept
either automatic or manual mode by the department. After the installation and
operation without any major breakdown for 30 days it shall be taken over by
Department.Subject to the guarantee, clause date of taking over the installation
after 30 days of trouble-free operation shall be the date of acceptance. Any undue
wear and tear of components during the running in period shall be made good by
the contractor free of charge.
b) To carry out minor civil work, such as modification and making good the
pocket/cutout in wall/ceiling for car, counter weight, rail bracket, hall buttons,
indicators and laying of sills in positions or any other work required for smooth
operation & commissioning of lifts.
d) Providingofhoistingbeam,liftinghookintheliftshaftforhoistingofequipment during
erection and to facilitate maintenance in future including their fixing etc.
e) Providingandfixingofnecessarysillsupportingprojections,sheetsteelfacia plates
on all landings as per requirements.
f) Inside the lift shaft, there shall be an arrangement of one light point at each floor
level and one light point at overhead, one light point in lift pit. All light points
shall be in group controlled and wired with 2.5 sq mm FRLS PVC insulated
copper conductor cable. One 15-amp power plug and one 5-amp power plug
shall be provided at each floor with individual switch. Wiring of these power
plugs shall be done with 4 sq mm FRLS PVC insulated copper conductor cable.
LED Bulkhead fittings of suitable rating to provide minimum 200 lux shall be
connected with each point of lift shaft.
4.1.11 Requirements as per CPWD Manual on Accessible Built Environment for Lifts.
All lifts shall meet the accessibility requirements.
a. Lift door:
Lift door shall be automatic with horizontal siding centre opening. A gap
between the lift door and building floor shall not be more than 12 mm. Time of
closing of an automatic door shall be more than 5s and the closing speed shall
not exceed 0.25 m/s. A mechanism to increase this time shall be installed to
be customized by a user with mobility impairments.
b. Call button:
Clear floor space of at least 900 mm X 1200 mm with no obstruction placed for
wheel chair user from reaching the call button and shall be installed at a height
800- 1000 mm.
c. Control panel
The control panels inside the lift shall be placed at a height of between 900
mm to 1100 mm from the floor level either horizontally or vertically within this
space.
d. Handrails
Handrails shall be placed at a height of 900 mm from the floor level and
are fixed on both sides and at the rear of the lift.
e. Audio and visual indicators
Voice announcements system clearly audible shall be provided to indicate the
floor level with the information that the door of the cage is open or closed for
entry or exit.
f. Lift signage
A sign indicating the number of the floor arrived shall be provided on each lift
landing on the wall opposite the lift in big font with good colour contrast.
g. Emergency warning alarm
Lift car shall be equipped with emergency warning alarm Device (two- way
communication system) permanently connected to a manned security point
with visual and audible information feedback to the passengers confirming
that, the alarm has been received, voice communication established, using the
green enlightened symbol consisting of two heads.
4.2 Codes
IS 14665
Electric Traction Lifts (Part-1 to5)
1100-volt grade XLPE/ PVC insulated cables IS7098 /IS1554
(b) Protection for motor - Provision shall be made for over load protection of
motor. Protective relay shall be provided on the controller to protect the lift
equipment against low voltage and phase failure. The slow speed winding of
this motor shall function automatically when the car is approaching a floor so
as to provide a greater stopping accuracy.
(c) Reverse phase relay - A reverse phase relay shall be provided on the
individual controller to protect the lift equipment against phase reversal, low
voltage and phase failure switches. Relays shall have suitable contact to
withstand wearing due to frequent make/break operation in hoist way.
4.2.3 Control
The control shall be by microprocessor controlled electronically regulated
A.C. Variable Voltage & Variable Frequency drive with phase reverse relay.
Controller with Simplex / duplex full collective control and selective, drive control
with digital technology.
4.2.4 Hoistway
a) Car Frame: A suitable car frame shall be provided with adequate bracing to
support the platform and car enclosure. The buffer striking plate on the
underside of the car-frame platform assembly must fully compress the buffer
spring in the pit before the plunger reaches its lowerlimit of travel.
b) Platform, Heavy Loading Type: The car platform shall be arranged to
accommodate load weighing up to 25% of the rated capacity, such as Hospital
stretchers, wheeled food carts, passenger’s baggage etc.
The platform shall be recessed 25mm for flooring Granite stone flooring as per
approved samples pattern.
c) Wiring for hoist way electrical devices included in scope of the elevator system,
hall panel, pit emergency stop switch, and the travelling cable for the elevator
car.
available.
4.2.13 Ropes
The hoist ropes shall be of traction steel of suitable size, construction and number to
ensure the proper operation of elevator and shall give satisfactory wearing qualities.
The Governor rope shall be of steel.No car or counter weight ropes shall be repaired
or lengthened by splicing. Fixing arrangements shall confirm to IS 2365-1977.
a) Telephone cabinet with phone and lead up to the lift well. Microphone with
switch along with communication cable between cabin car and Centralized
Security Room / Reception shall also be provided
b) Full height infrared light-ray with photo-electric cells across the car entrance.
c) The lift should have a voice announcement system along with a visual display to
indicate the floor level and also the information that the door of the car is open
or closed for entrance or exit.
d) The announcement system should be clearly audible i.e., the announcement
should be 50 decibels.
e) The provision of a mirror on the wall of the lift car opposite the lift door is a
positive aid to navigation for wheelchair users. It allows the wheelchair user to
see if anyone is behind them and also to see the floor indicating panel. The
mirror should not extend below 900mm from the lift floor to avoid confusing
the people with impaired site.
a) It shall not be possible to open the landing door from the landing side until
the lift car is within that particular relevant zone.
b) However, provision shall be made for opening the door by means of special
key for use in case of an emergency.
c) It shall not be possible for the car to be started or kept in motion unless all the
landing doors and car door are closed and locked.
d) An electric contact for each car door shall be provided which shall prevent car
movement away from the landing unless the door is in closed position.
Each lift shall have fireman toggle switch for access of fireman shall be provided in a
breaking glass. The operation of this switch shall cancel all calls to this lift and lift
will stop at the next nearest landing if travelling upward. The doors shall not open at
this landing and the lift should start travelling to ground floor. In case of its travel in
the downward direction when the fireman’s switch is operated, it shall go straight to
ground floor direct without stopping enroute. The emergency stop button inside the
car shall become inoperative during the journey. Once the car has reached the
ground floor, it shall be under the command of fireman by car buttons, landing calls
being isolated. The lift can be put in normal use by putting the fireman switch in its
original position.
4.2.28 Operation
The car shall answer all calls in a sequenced order depending upon the direction in
which it is travelling.
On top of the lift car an emergency stop switch shall be provided for use by
maintenance personnel. Similar switches shall also be provided in the car.
Operation of these switches shall render the car and landing buttons inoperative
and cancel all registered calls.
a) ARD should move the elevator to the nearest landing in case of power failure
during normal operation of elevator.
b) ARD should monitor the normal power supply in the main controller and shall
activate rescue operation within 10 seconds of normal power supply failure. It
should bring the elevator to the nearest floor at a slower speed than the normal
run. While proceeding to the nearest floor, the elevator will detect the zone and
stop. After the elevator has stopped, it automatically opens the doors and parks
with door open. After the operation is completed by the ARD the elevator is
automatically switched over to normal operation as soon as normal power
supply resumes.
c) In case the normal supply resumes during ARD in operation the elevator shall
continue to run in ARD mode until it reaches the nearest landing and the doors
are fully opened. If normal power supply resumes when the elevator is at the
landing, it shall automatically be switched to normalpower operation.
d) All the lift safeties shall remain active during the ARD mode of operation.
e) The emergency battery unit shall consist of suitable capacity of SMF (Sealed
Maintenance Free) batteries with battery charger having auto trickle/ boost rate
of charge The battery capacity should be adequate so as to operate the ARD at
least seven times a day provided the duration between usage is at least 30
minutes. A battery run-down indicator shall be provided.
this device, the lift will come to the nearest landing and its doors will open and
the person can come out of the lift.
4.3.1 Machine
The machine shall be, of gearless traction type for variable speed equipment for all
lifts and shall include electric motors, electromechanical brakes, steel sheave shafts
and bed plate. The driving sheave shall be grooved to ensure sufficient traction and
minimum rope wear. The machines shall be equipped with an arrangement for
manual winding of machine for testing purpose or for operation when the power
supply fails.
4.3.7 The works listed as under shall be arranged by Contractor and deemed to be
included in the quoted rates.
a) All cuttings of walls, floors or partitions together with any repairs made
necessary thereof, including grouting in position like bolts, sills, steel
members, indicator, button boxes etc., after they are fitted
in position.
b) Scaffolding including temporary barricade required for lift works in elevator
hoist way during the erection period and to remove the same thereafter.
c) Facia Plates are to be provided and installed by the contractor.
d) All painting works of elevator material.
The quoted rates shall be deemed to include for full and entire completion of all
works in accordance with good engineering practice and recognized principles. If
any additional civil works required other than mentioned in above to suit the lift well
as constructed at site shall also be got executed by the contractor under his own
arrangement, and the cost of the same shall be deemed to have been included by
them. The details of construction that may not have been specified but are
apparently and obviously required for making the lifts functional, shall be deemed to
be included in the lump sum rate quoted by the contractor. Decision of Engineer-in-
Charge in such matter shall be final and binding.
b) Anti -Nuisance
If number of calls registered is in excess of corresponding car load, all car
calls shall be cancelled.
c) Load Nonstop
When the car load exceeds a predetermined limit, the elevator shall not
respond to hall calls.
4.4 Drawings
Before the commencement of work, the contractor on receipt of building drawings,
shall prepare and submit all drawings, necessary shop drawings showing the
general arrangement of the lift equipment for the approval of the Engineer-in-
Charge. Contractor shall also check the exact dimensions of the lift shaft at site,
before taking up the manufacturing the equipment at site.
4.5 Painting
All exposed metal work furnished under these specifications, except as otherwise
specified shall be properly spray painted over an anti-corrosive primer coat.
Sl. 13 Passenger 20
Description
No. Lift Passeng
er
Hospital
Lift
1 Total No. Of 3 2
Elevators
2 Operation Simplex/ Simplex/
duplex Duplex
3 Control ACVVVF ACVVVF
Operation With /
4 W / WO W / WO
Without Attendant
5 Capacity
a. Rated 1360
Load (Kg)
b. No. of Persons 13 20
Gearless, Machine
Gearless with
6 Machine RoomLess
MachineRoom
1 Total No. Of 3
Elevators
2 Operation Simplex/Duplex
3 Control ACVVVF
Operation With /
4 W / WO
WithoutAttendant
5 Capacity
9 Travel Distance -
Approx.
10 Stops & Openings
A. No. Of Stops 5
B. No. Of Openings 5
C. Same Side Yes
Car And Hoist Way
11 1000
Entrance (In mm)
Machine Room
13 Not Applicable
Dimensions
Automatic power-operated
centre- opening doors;
18 Car and Landing
Honeycomb/ Moonrock
Doors
finish, Stainless steel
(SS304). multi- beam
infrared / ultrasonic door
Sensor
Granite Flooring of shade
19 Flooring
as approved by Engineer-
in- charge.
Residential IV
Sl.
Description 13 Passenger Lift
No.
2 Operation Simplex/Duplex
3 Control ACVVVF
Operation With /
4 WithoutAttendant
W / WO
5 Capacity
a. Rated Load (Kg) 1088
b. No. of Persons 13
b. SafetyGearTest:
Instantaneous safety gear controlled by a governor, should be tested with
contract load and a contract speed, governor being operated by hand. Two
tests should be made, however, with wedge clamps or flexible clamp safeties,
one with contract load in the car and the other with 68 kg (equivalent to one
person) in the car. The stopping distance obtained should be compared with
specified figures and the guides, car platform, and safety gear should be
carefully examined afterwards for signs of permanent distortion.
Counterweight safety gear should be tripped by the counterweight governor
and the stopping distance shall be noted. In this case, The governor tripping
speed shouldexceed that of the car safety governor but by not more than 10
percent.
During the safety gear test, car speed (from the governor orthe main sheave)
can be determined at theinstant ortripping speed with that stated in I.S. The
governor jaws and rope should be examined for any undue wear.
c. ContractSpeed:
This should be measured with contract load in the car, with half load and with
no load, and should not vary from the contract speed by more than 10 percent.
The convenient method is by counting the number of revolutions, made by the
sheave or drum in a known time.Chalkmarkonthesheaveordrumanda
stopswitch willfacilitatetimingbut care must be exercised to ensure that no
acceleration orretardation periods are included. If the roping is 2 to 1, the
sheave speed is twice the car speed.Alternatively, the speed can be
measured by a tachometerapplied directly to shaft immediately below the
sheave.
d. Car andlandingdoorsinterlocks:
The lift shall not move with any door open. The car door relay contact and
the retiring release cammust betested.The working
ofthedooroperationandthesafetyedgesand light equipment, if any, provided
shall also be examined.
e. NormalTerminalStoppingSwitches:
This shall be tested by letting the car run to each terminal landing in turn, first
with no load and then with contract load and by taking measurements, top and
bottom over travels can be ascertained.
f. FinalTerminalStoppingSwitches:
The normal terminal stopping switches shall be disconnected for this test. It
shall be ensured that these switches operate before the buffers are engaged.
g. Insulation Resistance:
This shall be measured (after removing the electronic PCBs and their
connection) between power and control lines and earth and shall not be less
than 5 mega-ohms when measured with D.C. voltage of 500 volts. The test
shall be carried out with contactors so connected together as to ensure that all
parts of every circuit are simultaneously tested.
h. Earthing:
Allconduits, switches,casingand similarmetalworkshallhaveearthcontinuity.
i. Buffers:The carshouldberun on to itsbuffersat contract speed and with contract
load inthe car to test whether there is any permanent distortion of the car or
buffers. The counterweight buffers should be tested similarly.
Undertaking
We,M/s ,
here by submit this undertaking in respect of work of
We will provide all the required spares and materials for smooth comprehensive
maintenance of lifts till their useful life of 20 years from the date of successful
handing overof thetotalproject tothedepartment. In no case, the department shall be
asked to replace/ upgrade the lift or any parts i/c controller either manufactured by
us or outsourced from our vendors, before expiry of the life of equipment, on
account of becoming the model obsolete/ upgraded design. No extra charges shall
be claimed on account of upgradation/ obsoleteness of spares during the life time of
the lifts.
1. We also agree for carrying out maintenance for 3 years i.e., till competition of
defect liability period
1. (Signature of lift manufacturer)
Name:
Designation:
Company Name & address:
2. (Signature of Contractor)
Name:
Designation:
CompanyName&address:
C-5- Substation
5.0 Technical Specifications for Sub-Station Work
The Electrical power flow will be from Metering Unit to ESIC’s incoming H.T.
VCB Panel to 11 KV / 440V step down transformers to the Main LT Panel.
The power from Transformer to LT Panel shall be fed using sandwich type
Copper Bus bar Trunking. Under power supply failure conditions, the D.G.
Set shall be started to cater to emergency loads of the Hospital, other non-
residential Buildings.
5.1 HT Panel
5.1.3 Construction
a) The VCB shall confirm to the latest IS/ IEC 62271-200, Front-Lateral-
Rear access, medium voltage parts which are connected to earth and
with separate the bus bars, the withdrawable part (circuit breaker, fuse-
contactor, disconnector truck or earthing truck) type, which means that
the panels shall be four side internal arc tested and shall have metal
partitions. The panel shall be floor mounted, draw out type. Design and
construction shall be such as to allow extension at either end (modular).
Unless otherwise stated, the H.T. (11 kV) Vacuum Circuit Breaker Panel
shall conform to IS 3427, IS: 13118 (1991), IEC 62271- 100 & 200 for
breakers & Panel and Indian Electricity Rules and Regulations
amended up to date.
b) The panel shall be single break, trip free mechanism, motor charged
and manually/electrically closing breaker suitable for use on 11 KV, 3
Phase, 50Hz A.C. supply with STC 26.3 KA for 3 Sec. Internal Arc for
AFLR 26.3 kA at rated voltage for 1s at individual compartments i.e.,
Busbar, VCB and cable compartment. complete with self-contained,
fully interlocked, rack in and rack out mechanism, air insulated and
encapsulated copper bus bars not less than 1500 Amps capacity,
breaker featured with ON/OFF indicator with hand trip device, spring
release coil, shunt trip coil and auxiliary switch of 6 NO + 6 NC and
equipped with following switch gears and accessories. Separate
earthing truck shall be required for each bus earthing & cable earthing.
Earthing truck shall be so designed that it is impossible to earth alive. It
shall be provided with capacitive voltage divider and complete with
audio visual annunciation, one for each panel. Contractor should offer
all type of test reports as per IEC62271-100 & 200 for the model being
offered.
f) VCB cubicle shall be so sized to permit opening of the front access door
only when the breaker is pulled out to TEST position. The movement of
the Circuit Breaker from TEST to SERVICE position should be possible
only with the Breaker door closed.
i) Dummy panel shall be provided in the VCB line up, if required, for easy
termination access of power and control cables. Dummy panel / bus
trunking panel shall be of full cubicle with closed roof and rear cover
similar to enclosures for active cubicles.
a) Bus bars shall be of same size for the entire length of the VCB. Continuous
current rating of bus connections shall be same as that of continuous in
panel current rating of associated breaker.
c) Bus bars shall be sleeved with heat shrinkable joint sleeves with adequate
phase/ground clearances. Insulating sleeves for bus bars and cast-resin
shrouds for joints shall be provided, suitable for maximum temperature rise
of bus bars.
d) All buses and connections shall be supported and braced to withstand
stresses due to maximum short circuit current and also to take care of any
thermal expansion.
e) Bus bars shall be colour coded for easy identification and so located that
the sequence R-Y-B shall be from left to right, top to bottom or front to rear,
a) Vacuum Circuit breaker shall be triple pole, single throw type, not less than
1250 Amps rated.
e) Circuit breaker shall have motor wound spring charged trip free
mechanism with anti-pumping-feature and shunt trip. In addition, facility for
manual charging of spring shall be provided. The spring charging handle
shall be an integral part of the Circuit Breaker. The vacuum bottles shall
be encapsulated in epoxy housings. Open type vacuum bottles shall not
be Provided.
I. The circuit breaker from being racked in or out of the service position
when the breaker is closed.
II. Racking in the circuit breaker unless the control plug is fully engaged.
III. Automatic safety shutters shall be provided to fully cover the female
primary disconnects when the breaker is withdrawn.
portion of the VCB and operated mechanically by a sliding lever from the
breaker in SERVICE position. Alternatively, electrically reset type latching
relay may be used for the purpose.
j) Switch contact shall be rated 10 Amp AC. and 2 Amp DC at their respective
operating voltage.
k) Closing and Tripping coils shall be continuous rated to ensure longer life.
The Circuit Breaker mechanism shall be designed for easy access to the
coils and spring charging motor.
l) Meter selector switches shall be maintained contact, stay put type with
knob handle. Ammeter & voltmeter selector switches shall be four position
type. Ammeter selector switches shall have make before break feature to
prevent open circuiting of CT secondary.
iv. Lamps shall be clustered type LED module pilot lights in thermoplastic
enclosure with polycarbonate lens and diffuser. LED shall be protected
by in-built fuse with surge suppressor and leakage voltage glow
protection. Lamp and lens shall be replaceable from front.
c) MCBs shall be suitably located to permit easy replacement while the VCB
is energized. The accuracy class for the VT shall be class 0.5 as per IS
3156 Parts I to III for incomer and class 1 for outgoing panels.
c) The relay shall have minimum 4 CT inputs, of which 3 Nos. can be used
for over current and 1 No. for Earth fault. The relay shall be suitable for
both 2 CT and 3 CT connections. It shall be possible to energize the relay
from either AC or DC auxiliary supply.
e) The relay must have facility for local settings through front keypad from
relay itself. Relay should have facility of online relay setting i.e., it should
be possible to alter setting without switching off breaker or contactor.
f) The offered relay shall have LED / LCD display for settings, status,
measurement and fault data & indication. It shall have at least 4 Fixed
function LEDs (for fault trip, relay healthy, control supply ON & Relay out
of service) and 4 programmable LEDs
g) Relay shall have comprehensive self-diagnostic feature with indication of
relay failure on relay front and alarm should be generated without tripping
the feeder. However, while diagnostic circuit runs, it must not interfere in
the main protective relay circuit and allow working of main protective
circuit continuously.
h) The relays shall have the following tools for fault diagnostics.
I. Fault record – The relay shall have the facility to store at least 5 last
fault records with information on cause of trip, date, time, trip values of
electrical parameters.
II. Event record – The relay shall have the facility to store at least 75
sequence of event records with 1ms resolution.
III. Disturbance records – The relay shall have capacity to store at least 5
disturbance record waveforms with at least 3s duration each.
i) No separate earth bus is necessary for the relays. It shall be possible to
connect the relay earth to the common earth bus in the substation.
interference. Contractor to submit all related type test reports for the
offered model along with the offer.
l) The relay shall be built in communication facility for hooking the relay on
MMI / upstream communication system. The offered relay shall have a
comprehensive local MMI for interface.
It shall have the following minimum elements to enable viewing and
setting the relay locally.
I. key tactile keypad for browsing and setting the relay menu
II. The relay shall have a front RS232 communication port for connecting
to a local PC/Laptop for setting and viewing the data from the relay.
III. The relays shall have a RS485 rear port for connecting many relays in
multidrop fashion to connect to a remote master (SCADA/DCS)
IV. It shall be possible to provide the relay with at least two standard
communication protocols (viz, MODBUS &BaC NET IEC-870-5-103)
in addition to any proprietary protocols.
m) Set of software should be supplied along with relays for viewing and
downloading measurement, fault records and to carry out easy settings
of relays locally.
i. The relay shall have 2 independent stages for both over current and earth
fault protection.
ii. First stage can be selected as definite time or inverse time over current
characteristic. The inverse characteristics shall be as per IEC which
should include normal inverse, very inverse, extremely inverse, long
inverse curves and shall be soft ware selectable at site.
iii. The second stage of protection can be with instantaneous or definite time
operations. There should be a possibility to disable the unit in case of
contactor-controlled feeders.
iv. Relay shall be suitable for both residually connected CT input as well as
CBCT (Circuit Breaker Coil Tester) input. This protection should have
automatic doubling function when the protected object is connected to
network i.e., at starting, allowing the set value being lower than the
connection in rush current. Relay should have minimum 2 nos.
independent selectable setting groups.
q) Numerical under voltage relays with time delay relay including VT fuse
failure relay shall be provided for Bus VTs.
The relay should have a feature of circuit breaker failure protection, which
generates another trip signal if the breaker fails to trip on fault, which can
be wired to upstream breaker trip coil. The relay shall have
comprehensive self-diagnostic feature. This feature shall continuously
monitor the healthiness of all the hardware and software elements of the
relay. Any failure detected shall be annunciate through a output watchdog
contact. The fault diagnosis information shall be displayed on the LCD
and through the communication port.
t) Arc Flash Fault Protection: Each panel shall be equipped with the
following for Arc flash fault protection: Relay should have integrated
feature sensing any ARC produced in any of the 3 chambers i.e.,
Breaker, Cable and Bus bar a part from Protection features. In case
integrated offer is not available, separate module to be considered
without compromising on the tripping time. Necessary sensors to be
supplied along with the relay and it should have supervision of these
sensors. Relay should operate due to ARC such that overall relay trip
time should not exceed 18-20 ms.
5.1.12 Metering
Digital Multifunction Meter, accuracy class 0.5, with LED display of Max
Demand Load, Current, Voltage, Frequency, Active, Reactive, Apparent
Power & Energy; Power factor; % unbalance of current & voltage;
calculated neutral current; %TDH individual harmonics up to 15th level
(complying with IEC61557-12) with RS 485 port and protection MCBs. and
required accessories to complete the system.
Lamp indication shall be provided to indicate ON/OFF (BY red green
respectively) of switch gear.
Voltage Selection Scheme: VT Transfer Relay shall be incorporated to
provide necessary potential for metering. This will be necessary when
energy metering is done on individual feeders or where VT supply is used
for trip circuits. Alternatively, PTs shall be provided on both the bus
sections (incomers) with individual metering on each incomer.
Instrument Panels: The instrument panel shall form part of the housing.
Relays, meters and instruments shall be mounted as per general
arrangement drawings to be submitted by the tenderer. They shall be
5.1.13 MCB
MCBs, shall be with manual close / open mechanism. Automatic tripping
provision for over load and short circuit shall also be provided. MCB shall
be provided with required number of auxiliary contacts as per circuit
requirement.
a) Not more than two wires shall be connected to any terminal. Spare
terminals equal in number to 20% active terminals shall be furnished.
Separate terminal blocks shall be provided for AC/ DC wiring
termination.
b) Terminal blocks used for interface with SCADA via termination cabinet
shall be suitably sized to facilitate proper termination of interconnecting
cables.
a) VCB shall be designed for cable entry from bottom. Sufficient space shall
be provided for ease of termination and connection.
b) Each stationary unit shall be connected directly to the ground bus. The
frame of each circuit breaker and draw out Voltage Transformer unit
shall be grounded through heavy multiple contacts at all times except
when the primary disconnecting devices are separated by a safe
distance.
5.1.20 Caution notice on suitable metal plate shall be affixed at the back of each
vertical panel.
space heaters and 5A, 3 pin plug socket. These space heaters shall be
suitable for operation on 240 V, 1 phase, 50 Hz A.C. In addition, motor
feeder cubicle shall be wired-up for feeding the motor space heater through
a suitable rated breaker auxiliary NC contact and/or contactor. Cubicle
heater, Motor heater, Plug/socket circuits shall have individual switch fuse
units.
a) Isolating switch fuse units shall be provided at each VCB for the
incoming supplies, 4-pole, single throw for A.C. and 2-pole, double throw
for D.C. Moulded case circuit breaker (MCCB) shall also be accepted as
an alternative for AC circuit only.
b) The VCB shall be finished in light gray colour (or) any other colour as
per Industry standards with two coats of powder paint. The coating shall
5.1.25 Tests
The VCB shall be completely assembled, wired, adjusted and tested at the
factory as per the relevant standards.
Tests at Works: All routine and other tests prescribed in IS shall be carried
out at the manufacturer’s works before the dispatch in the presence of
Engineer-in-charge or his authorized representative. Copies of the test
certificates shall be furnished to the department. The Contractor shall give
15 days’ advance intimation to Engineer-in-charge for witnessing the routine
tests. No material shall be dispatched from its point of manufacture before
inspection, unless inspection is waived off in writing. The acceptance of any
quantity of material shall in no way relieve the Contractor of any of his
responsibilities for meeting all requirements of the specification, and shall
not prevent subsequent rejection if such material is later found to be
defective.
The installation work shall cover assembly of panels lining up, grouting the
units etc. In the case of multi panels switch boards after connecting up the
bus bar all joint shall be insulated with HV insulation tape or with approved
insulation compound. A common earth bar shall be run preferably at the
back of the switch board connecting all the sections for connecting the earth
system. All protection, indications & metering connections and wirings shall
be completed.
Where trip supply battery is installed, the unit shall be commissioned,
completing initial charging of the batteries. All relay instruments and meters
shall be mounted and connected with appropriate wiring. Calibration checks
of units as necessary and required by the licensee like CTs, VTs Energy
Meters etc. shall be completed before pre-commission checks are under
taken.
a)
Operation checks and lubrication of all moving parts.
b)
Interlock function checks.
c)
Continuity checks of wiring, fuses etc. as required.
d)
Insulation tests.
e)
Trip test and protection gear tests.
f)
The complete panel shall be tested with 5000 V megger for insulation
between poles and poles to earth. Insulation test of secondary CTs
and VT.
g) Any other tests as may be required by the Licensee/ Inspector shall be
conducted
h) Where specified, the entire switch board shall withstand high voltage
test after installation.
i) Any other test required by the consignee / inspecting officer.
5.1.29 Guaranteed Technical Particulars
a) 1-Metal clad housing with trunk having 1250 A, 350 MVA, TP integral
VCB with manually /electrically operated mechanism (spring charging
motor-230 V AC)
b) 1 set of air insulated copper bus bar of 1500 A
c) 1 set of isolating plug and receptacle
d) 1 set of automatic safety shutter
e) 1 set of breaker control switch, lockable type Trip/Neutral/Closed
(TNC)
f) 1 set of dual core CTs
g) Core l 200/50/5/5 A class 5P-10 (15 VA) protection
h) Core ll 200/50/5/5 A class 1.0 (15 VA) metering
i) Shunt trip closing coil 24 V DC / 110 V A.C
j) 11 KV end termination kit for 3 x300 sq.mm AI XLPE 11 KV armoured
cable
k) 3-Nos PTs of 33/0.11 KV of (100 VA) cast resin type
l) 1-set ON/OFF /Trip & Circuit healthy and phase indicating LED Lamps.
m) 1 No Microprocessor based Numerical relay with O/C EF &SC
Protection. Relay
n) Should have arc flash fault protection in cable, busbar and breaker
chamber.
o) 1-no UL& CE Multifunction Digital meter displaying Voltage, Amps,
kWh, kW, P.F., Active, reactive, apparent energy, disturbance
direction detection, Individual harmonic up to the 63rd harmonic. at
least 256 samples/cycle with Ethernet Port with inbuilt web server and
complying to IEC 61557-12, IEC 62053-22 certified by third party
laboratory.
p) 1-no master trip relay
q) 1-12 nos annunciation window with relays and push buttons
a) 1-Metal clad housing with trunk having 1250 A, 350 MVA TP integral
VCB manually/electrically operated mechanism (spring charged motor
230 V A.C.)
b) 1 Set of air insulated copper bus bar 1500A
c) 1 Set of isolating plug and receptacle
d) 1 Set of automatic safety shutters
e) 1 Set of breaker control switches (TNC)
f) 1 Set of dual core CTS
g) Core l 200/50/5/5 A class 5P-10 (15 VA) protection
h) Core ll 200/50/5/5 A class 1.0 (15 VA) metering
i) Shunt trip closing coil 24 V DC / 110 V A.C
j) 11 KV end termination kit for 3 x 300 sq.mm AI. XLPE 11 KV armoured
cable
k) 3-Nos P.TS 33/0.11 KV of (100 VA) cast resin type
l) 1-set ON/OFF /Trip & Circuit healthy Indicating LED lamps.
m) 1 No Microprocessor based Numerical relay with O/C, EF & SC
Protection. Relay should have arc flash protection in cable busbar and
breaker chamber.
n) 1 No – Over Voltage Relay 1 No – Master
o) 1-No master trip relay
p) 1-12 No's annunciation window with relays and push buttons
q) 1-No 2 elements auxiliary relay for transformer (WTI with alarm & trip)
r) 1-set of terminal block with 20% extra terminal for connection with
2.5sq.mm 4 core PVC insulated PVC sheathed copper cable from
panel to transformer
s) 1 set of 3 phase differential relay with set of CTs of class 5P10 on both
sides.
b) The above VCB rating details are indicative only.
5.2.3 Standards:
c) Off load type tap changing switch with tapping range of +5% to -7.5%
in 2.5 percent steps shall be provided on HV windings to keep LV
Voltage constant. Relevant provisions of IS 2026 (Part-IV): 1977 shall
be applicable.
All the MS parts shall be galvanized to make them corrosion free. The core
coil assembly shall be housed in a prefabricated enclosure. The enclosure
shall be fabricated with sheet steel CRCA sheets with adequate provision
for ventilation. The enclosures shall undergo the seven-tank process.
Finally, the external and internal surfaces of the enclosure shall be powder
coated with the required paint shade.
5.2.8 Accessories
Each transformer shall be equipped with other accessories such as Flat bi-
directional rollers, lifting lugs, Haulage holes on the undercarriage, Earthing
terminals, RTD temperature controller, rating diagram, Marking plate and
Danger notice plate.
5.2.9 Testing
a) Tests at Works: All routine and other tests prescribed in IS shall be carried
out at the manufacturer’s facility before the dispatch of the transformer in
the presence of Engineer-in-charge or his authorized representative.
Copies of the test certificates shall be furnished to the department. In
addition to the prescribed routine tests, temperature rise test shall
invariably be done on one transformer of each design. The Contractor shall
give 15 days advance intimation to Engineer-in-charge for witnessing the
routine tests. No material shall be dispatched from its point of manufacture
before inspection, unless inspection is waived off in writing. The
acceptance of any quantity of material shall in no way relieve the
Contractor of any of his responsibilities for meeting all requirements of the
specification, and shall not prevent subsequent rejection if such material
is later found to be defective. Type test certificates as specified in IS shall
be submitted to the Department.
5.2.11 Technical Particulars of Vacuum Cast Coil (VCC) Dry type Transformers
5.3.2 Indian Standard Specifications and Codes of Practice will apply to the
equipment and the work covered by the scope of this contract. In
addition, the relevant clauses of the following standards as amended up
to date shall also apply. Wherever appropriate Indian Standards are not
available, relevant British and/or IEC 61439-6 Standards shall be
applicable.
5.3.3 Electrolytic quality Copper Conductor with Halogen Free insulation shall
be used for busbars. Rated operating voltage of the bus bar trunking is
1000V, 3 Phase, 4 strip with integral earth. Copper Bus trunking (Bus
duct) having suitable capacity shall be used to feed Main LT Panel from
the transformers, from transformer to APFC and HVAC panels (all
contacts should be silver plated). The busbar trunking system, both
feeder and plug-in shall be compact sandwich construction.
5.3.4 The Busbar trunking system shall be capable of withstanding the short
circuit of the electrical installation without damaging the electrical,
mechanical, and thermal stress under fault condition at a service voltage
of 1000V, 50Hz. Rated impulse withstand voltage 12 KV at 1000 V.
5.3.5 Housing / Enclosure
b) It shall pass at least 1500 hours salt spray test to ensure the anti-
corrosion ability. The enclosure of Bus Trunking System shall be
fabricated from 1.5 mm thick CRCA sheet steel/ GI/ Extruded Al and
shall be powder coated to suite the aesthetic ambience or as approved
after regress metal treatment process. Busbars shall be of copper with
silver plated contacts.
d) Ingress protection for the enclosures shall be minimum IP54 for indoor
Bus duct and IP 65 (without considering any Canopy) for outdoor Bus
ducts as per IEC 60529. However, suitable canopy to be provided to
cover the outdoor busducts to avoid any mechanical damage by any
accidental falling of foreign bodies.
e) The bus bar trunking joint shall be with Factory fitted Monobloc type
which utilizes high strength steel bolt(s) and Belleville washers to
maintain proper pressure over a large contact surface area. The bolt
shall be two-headed design to indicate when proper torque has been
applied and require only a standard long handle wrench to be properly
activated.
Access shall be required to only one side of the bus-bar trunking for
tightening joint bolts.
g) There shall be no bolts passing through the bus bars of the bus way
as a part of safety.
5.3.6 Insulation
Each bus bar shall be insulated with minimum Class F (155 Deg.
Centigrade) Multilayer PET film. Epoxy insulation shall not be permitted.
The insulation shall be certified as "halogen-free" by the manufacturer.
All plastic components shall have a V1 Self-extinguishing degree.
a) The connecting jaw of the plug-in unit shall plug directly on to the bus-
bar Rising Mains and have full contact with bus-bar itself. Welded tab
at plug-in bus-bar is not allowed.
b) All contact on joint and plug-in opening should be silver plated copper.
d) The tap-off boxes are made 1.5 mm thick sheet steel with powder
coated and provision for fixing MCCBs.
f) All tap-off boxes should have protective conductor which is the first to
make an electrical connection when plugged into the outlet, and the
last to disconnect when the tap-off is unplugged.
h) Operating voltage and Insulation voltage level must be 1000 Volts and
suitable for 50 Hz frequency.
5.3.10 Earthing
The entire bus trunking system shall be provided with Cu integral earthing,
and with two independent earthing conductors of size, at least 25x5 (mm)
throughout the length of the system.
The earth flats shall be effectively connected to the enclosure by riveting
/bolting. End covers shall be provided as required.
5.3.11 Certificates / Documents to be enclosed:
The type test certificates from independent testing authority are to be
enclosed and submitted before supply of materials:
tests prescribed without any additional cost at their factory. The product
shall be dispatched from the factory only after obtaining necessary
clearances from the department engineers.
b) Department shall not be responsible for any such losses that may
occur during installation, testing and commissioning works.
f) The department reserve the right to accept / reject any part of work, In
case of any failure to carry out the scope of work in time as per the
instruction of department, the work shall be carried out / got done by
the department at the risk and cost of the agency and the entire
amount with supervision charges shall be recovered from the agency.
d) Panel boards shall have a short circuit level withstand as per relevant
standard amended up to date.
c) Low Voltage switchgear & control gear IEC 60947 /IS 13947: 1993
f) The Panel boards shall be metal clad totally enclosed; floor mounted
free-standing type of modular extensible design suitable for indoor/
Outdoor mounting.
j) Neoprene gaskets between all adjacent units and beneath all covers
shall be provided to render the joints dust and vermin proof to provide
a degree of protection as specified.
q) Four lifting bolts per cubicle shall be provided for easy lifting of the
enclosure.
r) The louvers shall be covered with brass wire mesh to avoid access of
reptiles and insects in the Enclosure. The Enclosure shall be provided
with hinged cover for access to equipment.
s) The overall height of the Panel board shall be limited to 2200 mm for
all the Busbar ratings and type of Panel boards. Panel should have
integral base frame of 100 mm MS channel duly painted. Operating
levers, handle etc. of highest unit shall not be higher than 1.7 meters.
f) A horizontal wire way with screwed cover shall be provided at the top
to take interconnecting control wiring between vertical sections.
i. The Main LT Panel shall have PLC logic control with three sectionshaving
Electrical and Mechanical interlocking.
ii. Section A shall be connected with Transformer 1 and DG synchronization
panel Feeder 1
iii. Section B connected with Transformer 2
iv. Section C connected with Transformer 3 & DG synchronization panel
Feeder 2
v. All sections shall be coupled through 2 nos. Suitable sized Bus coupler ACB
vi. Section A & C shall have outgoings to different feeders in the building as
specified & section B treated as standby
vii. Each section shall be operated in both Auto and Manual Mode.
viii. AutoMode:
a) If Mains Supply fails at any particular section, load of that particular
section shall be transferred to Transformer 2. Other section loads shall
not be disturbed & shall remain on mains supply.
b) In case of Mains fail, all the three DG sets shall be started and load
should be transferred to DG sets through synchronization panel.
Number of DG sets to be operated, shall be decided automatically on
load requirement at that time. Preference of DG sets which to be
operated shall be decided on previous running hours of DG sets. The
DG sets which are stopped based on load requirement shall come into
the operation immediately in case of increasing of loads suddenly or
failure of operating DG sets due tofaults.
c) There shall be two 1600 Amps outgoing feeders for PLC based HVAC
panel. On Mains failure HVAC plant shall run for essential loads only so
anyone of outgoings shall be open.
d) The bus bar system may comprise of a system of main horizontal bus
bars and auxiliary vertical bus bars run in bus bar alloy on either side in
which the circuit could be arranged with front access for cable entrances
f) Auxiliary buses for control power supply, space heater power supply or
any other specified service shall be provided. These buses shall be
insulated, adequately supported, and sized to suit specific requirement.
The material for auxiliary supply bus will be insulated electrolytic copper
Wires.
a) Bus bar capacity of any panel shall be more than the capacity of
Incomer.
Air Circuit Breakers shall be provided in fully draw out cubicles, unless
otherwise stated. These cubicles shall be such that draw out is possible
without disconnection of the wires and cables. The power and control
circuits shall have self-aligning and self-isolating contacts. Mechanical
latches shall be integrated in ACB at service, test and isolated position to
ensure that Breaker is firmly latched in respective position. It shall not be
possible to move the breaker from the position unless latch is manually
operated.
All voltmeter and ammeter and other instruments shall be flushed mounted
type conforming to class 0.5 of IS 1248 for accuracy. All meters shall be
protected withMCBs.
e) For Incomer and outgoing feeders more than 200 Amp rating,
comprehensive power meters shall be provided which shall display A,
V, Pf, Hz, Kw, KVA, KVAR, Kwh, Kvarh, average and maximum values,
demand values, THD on current and Voltages. Also add on modules for
RS 485 port, programmable contacts, analogue output etc. to link to
,/SCADA system.
5.4.9 Wiring
All small wiring for Controls, Indication etc. shall be with 2.5 sq. mm size
FRLS/ HFFR (halogen free fire retardant) copper conductor cables. The
wiring shall be coded and labelled with approved ferrules for identification.
Runs of wires shall be neatly bunched and suitably supported and clamped.
Means shall be provided for easy identification of wires. Identification
ferrules shall be used at both the ends of wires. All control wires meant for
external connections are to be broughtoutonaterminalboard.
5.4.10 Earthing
Continuous GI earth bus of suitable size for prospective fault current to be
provided with arrangement for connecting to station earth at two points.
Hinged doors / frames to be connected to earth through adequately sized
flexible braids.
5.4.12 Name Plates and Labels Suitable engraved white on black name plates
and identification labels of metal for all Panel boards and Circuits shall be
provided. These shall indicate the feeder number and feeder designation.
5.4.14 Testing and Commissioning Copie s of type test carried out at ACB/MCCB
manufacturer’s facility and routine tests carried out at the Panel board
fabricator’s shop shall be furnished along with the delivery of the Panel
boards. Engineer-in-Charge reserves the right to get the Panel board
inspected by their representative at fabricators facilityprior to dispatch.
Commissioning checks and tests shall include all wiring checks and
checking up of connections. Relay adjustment/setting shall be done before
commissioning in addition to routine Megger tests. Checks and tests shall
include the following
b) The breaker shall provide class II insulation between the front panel
and internal power circuits to avoid any accidental contact with the live
main current carrying path with the front coveropen.
c) All current carrying parts in the breaker shall be silver plated and
suitable arcing contacts shall be provided to protect the main contacts
which shall be separate from the main contacts and easily replaceable.
In addition, Arc chutes shall be provided for each pole, and these shall
be suitable for being lifted out for the inspection of the main and the
arcing contacts.
g) The cubicle for housing the Breaker shall be free standing dead front
pattern, fabricated from the best quality sheet steel.
5.5.2 Operating Mechanism
a) The Circuit Breaker shall be trip free with independent manual spring
operated also motor wound spring-operated mechanism as specified
and with mechanical ON/OFF indication. The operating mechanism
shall be such that the circuit breaker is at all times free to open
immediately the trip coil is energized. The breaker shall be provided
with in built anti-pumpingmechanism.
c) The operating handle and mechanical trip push button shall be at the
front of and integral with the Circuit Breaker.
a) It shall not be possible for the Breaker to be withdrawn from the cubicle
when in the "ON" position. To achieve this, suitable mechanism shall
be provided to lock the Breaker in the tripped position before the
Breaker is isolated.
5.5.7 Earthing
The frame of the Circuit Breaker shall positively be earthed when the Circuit
Breakerisrackedinto thecubicle.
The Moulded case circuit Breaker (MCCB) shall confirm to the latest IEC
60947-2 and IEC 947-3- 1989. MCCBs shall be suitable for rated operation
voltage up to 415 V AC.
MCCBs used with Three Pole and Neutral connections shall be of Four pole
type only.
d) MCCB rating, “push to trip” button and contact position indication must
be clearly visible and accessible from the front, through the front panel
5.5.10 Communication
MCCB should have option for communication in the Main LT Panel for
critical feeders i.e., RS 485 communication port.
All the MCCBs should have thermal memory feature. In the event of
repeated overloads, the electronic trip unit shall optimize protection of
cables and downstream devices by memorizing temperature variations.
5.6.1 Introduction
This section covers the specification of Distribution class Surge Arrestor for
33kV indoor type VCB breaker panel, transformers etc. with highest system
voltage of 36 kV at 50 Hz.
5.6.2 Standards
d) The surge arrestor shall not operate under power frequency and
temporary overvoltage conditions but under surge conditions, the
surge arrestor shall changeover to the conducting mode.
b) Routine tests:
I. Measurement of reference voltage
II. Residual voltage test of arrester unit
III. Internal ionization or partial discharge test
IV. Sealing test
V. Verticality checks on completely assembled surge arresters as a
sample test on each lot if applicable.
Overall Rating
2 No. panels of suitable KVAR (40% of Transformer capacity)
(1No. for each side of main LT Panel) with 12 steps APFC relay
out of which 1No. 50 KVAR static capacitor shall be permanently
connected to the bus.
c) Adequate lifting facilities shall be provided and the lifting eye bolts shall
be removabletype.
g) The fabricated panel shall undergo 7 tank treatment and primer, before
inside and outside powdercoating.
i)
Undrilledgland plates shall be provided at to pand bottom of the panel
and shall ber emovable type with nuts and bolts for proper fixing.
j) The control supply shall be tapped after the Mains Incomer ACB.
Control circuit shall be provided with MCBs forprotection.
d) The capacitor shall be suitable for a rated voltage of 480 volts and shall
be continuously operating at a maximum over- voltage of 10% above
the ratedvoltage.
e) The rated frequency is 50Hz. The capacitor shall however, be suitable
for continuous operation with a frequency variation of +3% from the
ratedfrequency.
f) The capacitor shall be suitable for operation in temperature category
50 Deg.C.
All routine and type tests as per IS 2834 relevant to capacitor banks as
amended up to date shall be carried out at manufacturer’s facility and test
certificates shall be furnished to the department.
5.7.6 Installation
Insulation resistance with 500 V DC Megger shall be carried out and test
results shall be recorded at site.
5.8 Cables
5.8.1 HT Cables
The specification covers the supply, installation,testing & Commissioning of
PVC sheathed 11 KV (E) grade, XLPE insulated Aluminium conductor
cables.The cable shall be manufactured strictly conforming to IS: 7098 (Part
2) - 1985 amended up to date and shall bear ISI mark. The 11 KV HV cable
size shall be designed based on the fault level of the feeder, obtained from
the supply company.
5.8.2 Standards:
The cable shall conform to the following standards.
a) IS 7098 Part 2: 1985 XLPE insulated PVC sheathed cables for working
voltages up to and including 11 kV.
The cable, joints, outdoor and indoor termination and their accessories and
fittings may conform to Indian and/or equivalent international standards.
a) All cables shall be suitable for high ambient, high humid tropical
climatic conditions. Cables shall be designed to withstand the
mechanical, electrical and thermal stresses under the unforeseen
steady state and transient conditions and shall be suitable for
proposed method of installation.
d) The semi conducting XLPE screen shall be extruded over the main
poly ethylene-insulating wall to prevent partial discharge at the surface
of the insulation. The copper tape shall be wrapped over the semi
conducting tape or extrusion for 3 core cables. The metal screen so
formed around the cores shall be in contact with one another as the
cores are laid up at triangular configuration. Conductor screening,
insulation and insulation screening shall be extruded in triple extrusion
processes so as to obtain continuously smooth interfaces.
f) The cable core shall be supplied with bedding of PVC (Inner sheath)
in the form of extruded PVC sheath for 11 KV cables.
g) The cable shall be steel strip armoured for 33KV and 11 KV. Three
core cables to ensure an adequate return path for the flow of fault
current and also provide suitable mechanical protection.
a) Nominal Current rating shall not be less than the Specific Technical
Requirements. Contractor shall submit design data in respect of all
cables in the prescribed format.
The inner conductor shield, TR-XLPE insulation, and outer insulation shield
shall be extruded with a true triple extruder head using a dry cure process.
The conductor screen, Insulation and Insulation screen shall all be extruded
in single point at one time process to ensure homogeneity and reduction of
voids, in the insulation and the screening system of the cable.
All type tests in accordance with IS: 7098 (Part 2) amended up to date, shall
be performed on cable samples drawn by department.
All Routine tests and acceptance tests as per IS shall be carried out and
result should be given in test report. Partial discharge test must be carried
out in a fully screened test cell. It is, therefore, absolutely essential that the
manufacturer should have the appropriate type of facility to conduct this
routine test.The facilities shall be provided by the Contractor to the Engineer-
in-charge or his authorised representative for witnessing the tests in the
manufacturer’s premises.
5.8.9 Marking:
Identification Marks on Cable:
The following particulars shall be properly legible embossed on the cable
sheath at the intervals of not exceeding one meter throughout the length of
the cable. Manufacture name and/or Trade name.
a) Voltage grade of Cable.
b) Year of manufacture.
c) ISI Mark.
d) Size of cable
5.8.10 Installation
HT Cables shall be laid in ground, trenches, cable trays and on walls as
specified. Installation shall include all supports and clamps as required. The
complete work shall be in accordance to CPWD General Specifications for
Electrical Works - Part II (External) 1994 amended up to date. As far as
possible cables shall not be fixed on walls directly but can be laid on cable
trays.
5.9 LT Cables
This specification covers the supply & installation of LT power & control
cables. Cables shall be tested at manufactures facility and supplied in
accordance to relevant Indian Standard Specifications. The LT power
cables shall be XLPE insulated, PVC sheathed, Aluminium / copper
conductor armoured cables conforming to IS: 7098 (Part - I).
5.9.2 The cables shall be used for connection of power circuits of the electrical
system. Cables will be generally laid in ground, surface or in RCC/Hume/GI
pipes/ cable tray. For continuous operation at specified rating, maximum
conductor temperature shall be limited to the permissible value as per
relevant standard and/ or this specification. The insulation and sheath
materials shall be tough enough to withstand mechanical stresses during
handling. Armouring shall be round/flat wire of galvanised steel. Core
identification for multi core cable shall be provided by colour coding.
The cables shall be designed as per the voltage drop regulations at peak
load and length of the Cable.
5.9.4 Tests
All tests shall be carried out in accordance with relevant Indian Standard
code of practice and Indian Electricity Rules. Test certificates of all the tests
carried out at the works shall be furnished for approval of the Engineer-in-
charge before the cables are dispatched from the manufacturer's facility to
the site.Test reports shall be complete with all details and shall also contain
IS specified limit values wherever applicable to facilitate review.
a) Duct system:
Wherever specified such as road crossing, entry to building or in paved area
etc. cables shall be laid in underground ducts. The duct system shall consist
of a required number of stone ware pipes, GI, CI or spun reinforced concrete
pipe with simplex joints and all the jointing work shall be done according to
the CPWD building specifications or as per the instructions of the Engineer-
In-Charge as the case may be.
The size of the pipe shall not be less than 150mm. The pipe shall be laid
directly in ground without making any special bed but wherever asbestos
cement pipes are used, the pipes shall be encased in concrete of 75mm
thick. The ducts shall be properly anchored to prevent any movement. The
top surface of the cable ducts shall not be less than 60 cm. below the ground
level. The duct shall be provided with manholes of adequate size at regular
intervals for drawing the cables. The manhole cover and frame shall be of
cast iron and machine finished to ensure a perfect joint. The manhole covers
shall be installed flush with the ground or paved surfaces. The duct entry to
the manholes shall be made leak proof with lead-wool joints. The ducts shall
i. The depth of the underground trench shall not be less than 75cm for cables
up to 1.1 KV grade and 1.2m for cables above 1.1KV grade from the final
ground level. When more than one cable is to be laid in vertical formation,
the depth of the trench shall be increased by 30 cm for each additional tier
to be formed. The width of the trenches shall not be less than 45 cm.
However, where more than one cable is laid, an axial distance of not less
than 15 cm. shall be allowed between the cables. Wherever there is a
change in direction, suitable curvature shall be provided complying with the
requirements. Suitable shoring and propping may be done to avoid caving
in of trench walls. The bottom of the trench shall be level and free from stone
brick bats etc. The trench shall then be provided with a layer of clean, dry
sand cushion of not less than 8 cm. in depth.
ii. The cable shall be pulled over rollers in the trench steadily and uniformly
without jerks and strains. The entire cable length shall as far as possible be
paved of in one stretch. However, where this is not possible, the remainder
of the cable may be removed by "Flaking" i.e., by making one long loop in
the reverse direction. After the cable has been uncoiled and laid into the
trench over the rollers, the cable shall be lifted slightly over the rollers,
beginning from one end by helpers standing about 10 mtrs. apart and draw
straight. The cable should then be taken off the rollers by additional helpers
lifting the cable and then laid in a reasonably straight line.
iii. When the cable has been properly straightened, the cores are tested for
continuity and insulation resistance and then the cable length be measured.
The ends of all cables shall be sealed immediately. In case of PVC cables,
suitable moisture seal tape shall be used for this purpose.
iv. Cable laid in trenches in a single tier formation shall have a covering of
clean, dry sand of not less 17 cm above the base cushion of sand before
the protective cover is laid. In the case of vertical multi-tier formation after
the first cable has been laid, a sand cushion of 30 cm shall be provided over
the initial bed before the second tier is laid. If additional tiers are formed,
each of the subsequent tiers also shall have a sand cushion of 30 cm as
stated above. The top most cable shall have final sand covering not less
than 17 cms before the protective cover is laid.
cm. over the sides of the end cables. The trenches shall be taken back filled
with excavated earth free from stones or other sharp edge debris and shall
be rammed and watered, if necessary, in successive layers not exceeding
30 cm, unless otherwise specified.
Cables shall be laid in indoor trenches wherever specified. The trench shall
be made of brick masonry with smooth cement mortar finish with suitable
removable covers (i.e., pre-cast slabs or MS chequered plates). The
dimensions of the trenches shall be determined depending upon the
maximum number of cables that is expected to be accommodated and can
conveniently be laid. Cables shall be arranged in tier formation in trenches
and if necessary, cables may be fixed with clamps. Suitable clamps, hooks
and saddles shall be used for securing the cables in position. Spacing
between the cables shall not be less than 15 cm centre to centre. Wherever
specified, trenches shall be filled with fine sand and covered with RCC or
steel chequered trench covers.
ii. All jointing pits shall be of sufficient dimensions as to allow easy and
comfortable working. Jointing materials and accessories like
conductor, ferrules, solder, flex, insulating and protective tapes,
filling compound, jointing box etc. of right quality and correct sizes,
confirming to relevant Indian Standards.
iii.
Each termination shall be carried out using brass compression
glands and cable sockets. Hydraulic crimping tool shall be used for
making the end terminations. Cable gland shall be bounded to the
earth by using suitable sized copper wire/tape.
5.9.6 Route Marker
The word “MV/HV CABLE” as the case may be, shall be inscribed on the
marker.
5.10.1 The scope of work shall cover hot dip galvanisedCable trays, tray support
systems, fittings and accessories for laying the power cables, control
cables and tele technical cables. Manufacture and finish shall be
completed at the factory works.
The cable trays shall be of steel as per IS 226 and galvanized and the
thickness of galvanization shall not be less than 100 microns. All bolts and
nuts also be galvanized. Hot dip galvanizing shall confirm to IS 2633. The
galvanizing shall be uniform, clear, smooth, continuous and free from acid
spots.
5.10.2 The cable trays and accessories shall be fabricated out of hot rolled steel
sheets, which shall be hot dipped galvanized. The complete assembled
cable tray sections shall be corrosion resistant, high strength and with
extreme smooth surface.The tray shall have suitable strength and rigidity to
provide adequate support for all contained cables.It shall not present sharp
edges, burrs or projections injurious to the insulation of wiring/cables.It shall
have side rails or equivalent structural members.It shall include fittings or
other suitable means for changes in direction and elevation of runs.
Ladder type cable tray shall consist of a Welded rung assembly of field
proven design. It shall consist of side rails of 3.0 mtrs. Standard lengths and
slotted rung spaced 250mm centre to centre.
Coupler, Coupler fasteners, tray assembly fasteners must form the part of
the equipment. The Ladders should be heavy duty sheet metal
constructions yet robust enough to carry a cable load of 50 kg/m on a span
of 1.25 mtrs.
Perforated cable trays shall be used for laying the cables of low voltage and
control cable. Perforated cable trays shall generally be of channel type and
the perforation in the trays shall be either 8 x 15 mm or 10 X 20 mm oval
holes.
Perforated cable trays of standard lengths of 2.5 mtrs shall be offered. Finish
shall be as specified earlier.The cable tray of size 150mm Width and Less
than that shall be of Perforated type.
Sizes
The cable trays shall be of the following standard sizes.
Width 300 / 450 / 600 / 800 / 1000 mm as required.
Height 75 / 100 mm
Thickness of sheet steel2.0 mm / 3.0 mm as per width of tray.The flange
and width of the cable trays shall be decided based on the diameter and the
number of cables running through each section of the cable tray.
5.10.5 Cable tray manufacturer shall supply suitable accessories for fixing the
cable trays on supports from ceiling and beams of the building structure.
Cable trays shall be supplied with GI coupler plates, hardware, nuts bolts
and washers for joining the standard length of sections.
5.10.6 Installation
a) Cable trays shall be installed as a complete system. Trays shall be
supported properly from the building structure. The entire cable tray
system shall be rigid.
b) Each run of the cable tray shall be completed before the installation of
cables.In portions where additional protection is required, non-
combustible covers/ enclosures shall be used.
c) Where cables of different system are installed on the same cable tray,
non-combustible, solid barriers shall be used for segregating the
cables.
d) Cable trays shall be grounded by two numbers, earth continuity wires.
Cable trays shall not be used as equipment grounding conductors.
b) The cable tray shall be uniformly loaded along the span with cable tray
simply supported at the two ends as per the load criteria.
5.11 Earthing System
5.11.1 This section covers the general requirements of the earthing system for Sub-
c) The procedure used for the design of the foundations shall be the most
critical loading combination of the steel structure and /or equipment and /or
superstructure, and other conditions which produce the maximum stresses
in the foundation or the foundation component, and as per the relevant IS
Codes of foundation design. The design calculations shall be submitted by
the bidder showing complete details.
d) All foundations shall rest below virgin ground level and the minimum depth
of foundation below the virgin ground level as per relevant standards shall
be maintained.
e) Design shall consider any sub-soil water pressure that may be encountered.
Necessary protection to the foundation work, if required, shall be provided
to take care of any special requirements for aggressive alkaline soil, black
cotton soil or any other type of soil which is detrimental or harmful to the
concrete foundations.
f) All building sub-structures shall be checked for sliding and overturning
stability during both construction and operating conditions for various
combinations of loads. Factors of safety for these cases shall be as stated
as per relevant IS codes or as stipulated elsewhere in the specifications. All
foundations shall be designed in accordance with the provisions of the
relevant parts of latest revisions of IS 2911 and IS 456.
5.13 Safety Requirements
This section covers the requirements of items to be provided in the sub-station
for compliance with statutory regulations, safety and operational needs.
a) Requirements
Safety provisions shall be generally in conformity with CPWD General
Specifications of Electrical Works (Part I-Internal), 2013. In particular following
items shall be provided:
b) Insulation Mats
Insulation mats conforming to IS 15652: 2006 shall be provided in front of panel
boards as well as other control equipment.
c) First Aid Charts and First Aid Box
Charts (one in English, one in Hindi, one in regional language), displaying
methods of giving artificial respiration to a recipient of electrical shock shall be
i) Key Board
A keyboard of required size shall be provided at a proper place containing
castle keys, and all other keys of sub-station and allied areas.
8.0.1 Standards:
cables.
6.1.1 Each DG set shall be silent type with acoustic enclosure, heat exchanger type
cooled, suitable for continuous operations & capable to deliver prime power rating
at average load of 85%, manually and automatically operated. The DG set shall
comprise of Diesel Engine coupled to four-pole Alternator on a single frame with
integrated microprocessor based Genset monitoring and control system having
self-regulated, brushless/static excitation system.
6.1.2 The Design, Manufacture, Inspection, Testing and performance shall comply with
all the currently applicable standards, safety codes, relevant Bureau of Indian
Standards (BIS), International Electro Technical Commission (IEC) Publications,
CPWD specifications, CPCB norms.
6.1.3 All equipment shall be suitable for working under the conditions specified and shall
withstand the atmospheric conditions without deterioration.The time schedule for
routine maintenance / overhauling operations necessary for continuous satisfactory
operation of DG set shall be intimated by the contractor.
6.1.4 All controls shall be of 24V DC. DG Sets shall be started/ stopped from Engine / DG
Panel/ Remote.
b) AMF (Auto Mains Failure) panels. These D.G. sets shall be designed to run
in parallel and synchronized with Main LT panel on common bus. The Auto
Synchronizing panel with auto load sharing shall be supplied with D.G. sets.
The required controls, indications, interlocking etc. shall be provided.
c) Neutral Earthing and Body Earthing for each DG set shall be provided from
Structural Earthing of the services building and 25 x 5mm copper Strip for
connecting the neutral with the provided connectors.
f) HSD UG Storage Tank & Pumping System shall be provided for continuous
pumping of HSD oil to the DG Sets. Fuel Day Tank and related piping. Fuel
tank should be with level indicator and marking.POL i.e., HSD oil and lube oil
for testing at OEA/ OEM works shall be arranged by the contractor.
g) Exhaust system with piping & insulation including stack complete. Civil
foundation for the DG set, Fuel Tank and other accessories including
vibration isolation springs/ pads.
j) All tools and tackles required for handling of equipment and materials at site
of work as well as for their assembly and erection and also necessary test
instruments shall be the responsibility of the contractor.
b) The selection of DG Set rating shall be done after taking all above factors in
consideration. The sandwich type copper bus duct shall be provided
between DG sets and synchronization panel with rating more than the
Ampere rating of DG sets.
c) The incomers rating of Synchronization panel shall be equal to alternator
rating of DG set or next rating available in ACB.
6.4 Approvals
a) The contractor shall obtain information relating to local regulations, Bye-Laws,
application of all laws relating to his work or profession and his having to
execute work as required. No additional claims shall be admissible on this
account.
b) Contractor shall obtain approval of the installation from the relevant inspection
Authorities at all stages and on completion of the installation work. The
contractor shall pass on these approvals to the Owner. Statutory charges
payable to the Government / Municipal Authorities/ Statutory Bodies /
Electrical Inspectorate/ Central/State Pollution Control Board/CCOE etc. for
obtaining approvals will be paid by the department.
engine over a period of 24 hours shall be 0.85 (85%) for prime power output.
c) The engine shall conform to IS:10000/ ISO 3046/ BS:649/ BS 5514 amended
up to date.
d) The manufacturer shall furnish certificate, that the engine for the DG set
complies with the CPCB emission norms.
e) The engine shall be fitted with following accessories subject to the design
of the manufacturer:
i. Dry exhaust manifold with suitable Hospital grade silencer.
ii. Suitable self-starter for 24 V DC.
iii. Battery charging alternator unit and voltage regulator, suitable for
starting
batteries, battery racks with interconnecting leads and terminals.
iv. Necessary gear driven oil pump for lubricating oil, priming of engine
as well as fuel systems as per manufacturer recommendations.
v. Lubrication oil cooler
vi. Crank case heater as per manufacturer recommendations.
vii. Fuel pump with engine speed adjustment
6.5.6 Headers
Headers are made of carbon steel with vent and drain sockets.
6.5.7 Casing
Casing is made out of heavy gauge galvanized iron steel sheet. The casing is
powder coated for protection against moisture / rust.
6.5.9 Motors
The motors are totally enclosed (TEFC) for protection against dust / moisture and
class F insulated with IP-55 protection. The motors are foot mounted and are
designed for 415 ± 10% Volts, 3 Phase and 50 Hz.
Air purging valves are mounted on the top of coil headers to make sure that the
cooler is with water and no Air pockets in the system. The Air and drain valves
shall have ball valves with dummy plugs.
6.6 Governor
Electronic governor of class A1, as per ISO 3046/ BS 5514 with actuator shall be
provided. Governor shall be a self-contained unit capable of monitoring speed.
All pipe lines and fittings and accessories requirement inside the room/ enclosure
and outside for exhaust piping shall be provided by the contractor. This shall
include necessary flexile pieces in the exhaust, fuel, lubricating Oil and water lines
as are necessary in view of the vibration isolation requirement in the installation.
Piping of adequate size shall be used for lubricating Oil of the material as per
manufacturer standard. However, only M.S pipes for the exhaust shall be used.
For fuel lines with in the acoustic enclosure, PVC braided pope as per
manufacturer recommendations can be used. However, for fuel lines outside the
acoustics enclosure, only MS pipe be used.
The pipe work shall be inclusive of all fittings and accessories required such as
bends, reducers, elbows, flexible connections, necessary hardware etc. the
installation shall cover clamps, supports hangers etc., as are necessary for
completing the work. However, the work shall be sectionalized with flanged
connections as are necessary for easy isolation purposes for maintenance of unit
as approved by Engineer-in-charge.
6.8.1 Exhaust Piping:All M.S. Pipes of Class ‘B’ for exhaust lines shall be conforming to
relevant IS. The work includes necessary cladding of exhaust pipe work using 50
mm thick Loosely bound resin (LBR) mattress/ mineral wool/ Rockwool, density
not less than 120 kg/m3 and aluminium cladding (0.6 mm thick) for the complete
portion. The exhaust pipe work includes necessary supports, foundation etc. to
avoid any load & stress on turbo charger / exhaust piping & the design and drawing
for exhaust piping structure run along wall/building shall be got approved from the
Engineer-in-charge.
6.8.3 Alternator
The alternator shall be Separately excited, Screen Protected Drip Proof, IP23,
Class 'H' insulation as per OEM, self-ventilated, air cooled, brushless, machine
with exciter and shall be rated continuous duty temperature rise with in class ‘H'
Limits at rated load.
b) The alternator shall be suitable for coupling directly to the engine. It shall
be drip proof screen protected as per IP23. The alternator shall be double
bearing type.
c) The alternator should be complete with shunt and booster excitation. The
exciter shall be fast response type and shall be designed to have a low
time constant to minimize voltage transients under severe load changes.
The excitation voltage response ratio shall be at least 0.8.
d) The rated current of the main exciter shall be at least 10% more than the
exciter current and it shall have a 40% overload capability for 10 seconds.
g) AVR system shall be provided with equipment for automatic and remote
operation/control as required/ as per manufacturer's standards.
f) Indicating lamps for load on mains and load on set shall be provided.
6.12.2 The logic panel shall be provided with a total manual over ride facility. There shall
be Smooth transfer of DG set operation from PLC to manual system & vice versa
without any interruption/tripping. The logic panel shall be complete with all
Auxiliary Relays, Timers, Contactors, Programmable logic controller, control
wiring, interconnections etc. with 2.5 sq.mm. FRLS PVC insulated, 1.1 KV grade
copper conductor wires.
6.12.4
Control Philosophy AutomaticStart&StopofEngine. The system should come
in operation after sensing of grid failure and automatically control the start &
stop of engines, depending on the predefined load setting in the PLC. In
case engine does not start in the first cranking, two more auto commands
should be given with proper intervals. Even then if engine fails to start,
indication must appear on MMI (Man Machine interface). In the event the
engines are under loaded i.e., load sensed is capable of being catered by
less than the capacity of running DG sets then command must be given to
stop required number of excess DG sets after running idle for short
duration. Provision to select no. of DG sets to be started and synchronised
at no load to cope up with sudden load without tripping the DGs should also
be inbuilt into the system.
Reverse power, Reverse KVAR, Over Current, Under voltage, Over voltage,
Under frequency, Over frequency, synchro-check & earth fault relay except
differential relay. Due to any electrical fault, PLC shall trigger the master trip relay.
These PLCs will be state of the art equipment using latest technology and of most
rugged and reliable design. Since they shall be operating in the harsh & unfriendly
environment of DG room, they will be suitable to operate trouble free in those
conditions. The chosen equipment should be able to withstand high
temperature, humidity & voltage fluctuations, thus making it suitable for the
operating conditions described above.
b) Three attempts to start the engine of lead generator. In case the engine
fails to start or does not achieve the requisite speed within the
predetermined time, PLC system declares engine of generator faulty. In
this event PLC automatically selects next generator as the lead generator.
f) When the lead generator KW crosses more than the 85% of rated
capacity of DG set, the PLC system performs synchronization sequence
for paralleling of generator prior to switching on of the ACB of 2nd
generator. When the KW of 2nd generator crosses 80% of rated capacity
of DG set, then the PLC system performs synchronization sequence for
paralleling of next generator prior to switching on the ACB of 3rd generator
and similar sequence to be followed for other DG sets.
g) The last incoming generator ACB is tripped when PLC system senses that
the total load on the system is less than the specified load and stops the
engine after 5 minutes of idle running.
h) DG sets will start and stop automatically depending on the predefined load
setting in the PLC & also all DG sets will operate in load sharing mode.
In order to dispose exhaust above building height, minimum exhaust stack height
shall be 30m High or 3m above the building height, whichever is higher as per
MOEF & CPCB requirements.
6.14 Performance
Voltage dip shall not exceed 20% of the rated voltage for any step load or transient
load as per ISO 8528 (Part-1). The winding shall not develop hot spots exceeding
safe limits due to imbalance of 20% between any two phases from no load to full
load.
Theperformancecharacteristicsofthealternatorshallbeasbelow:
Efficiencyatfullload0.8P.F. as per Super ECBC up to date
Total distortionfactor Lessthan 3%
i. 10% overload One hour in every 12 Hrs. of continuous use.
ii. 50% overload 15seconds.
6.15 Painting
All steel surfaces, which are to be painted, shall be thoroughly cleaned, degreased
and supplied with primer prior to assembly and shall be applied with two coats of
epoxy paint shade RAL 7032 as per IS5.
All castings shall be sand blasted, degreased and cleaned before painting as
per manufacturer standards..
6.16 Foundation:
a) Foundation should be designed considering safe bearing capacity of soil
and DG set static and dynamic load. Anti-Vibration Mounts (AVMs) are
provided to reduce generator set vibration and noise transmission to the
surrounding structure.
b) The depth of the foundation to be decided in consultation with the certified
structural engineer depending on static and dynamic load of the DG set
and soil condition.
h) The AVMs of DG Set should be loaded uniformly for DG sets where AVMs
are placed on foundation & below DG set base frame. Use shims below
AVM resting area. Shim plate should be of 3 mm minimum thickness and
to be used in multiple as required. Ensure that AVMS are loaded evenly.
6.17 Cabling
When the DG set attains its rated speed and voltage, a closing signal shall be
given to the VCB of the DG set. When the voltage in the mains gets restored,
its quality is monitored for about one minute and if proven satisfactory, the main
supply breaker shall close automatically transfer the load from Diesel engine to
the main supply at H.T. Panel. The set shall stop after idle running of one minute
after restoration of main supply. The diesel alternator set reverts to its standby
conditions &it's ready to start should the mains supply fail again.
If during test mode, the power supply has failed, the load shall automatically get
transferred to alternator. Bringing the mode selector to auto position shall shut
down the set provided main supply is ON. If the mains supply is not available at
that time, the alternator shall take load.
6.19 Earthing
Neutral Earthing and Body Earthing shall be provided from the Structural Earthing
to be done within the Service Building. Suitable size of copper strip may be used
for the purpose of connecting the DG set with Structural Earth Connectors laid.
No. of Structural Earth Connectors required for this purpose shall be intimated to
the Structural Earthing agency at the earliest. And the same may be confirmed
during building construction. Test joints should be provided for testing the
earthing as and when required.
1.0 Engine
1.1 Make To be intimated by contractor
1.2 BHP at rated RPM Not less than 1180 @1500
RPM
1.3 No. of cylinders & type 12, Vee type
1.4 Type of aspiration Turbo charged, after cooled
1.5 Overload Capacity 10% for 1 Hr in every 12 Hrs
Run
1.6 Governor Electronic, A1
1.7 Type of Cooling Heat Exchanger type
1.8 Coolant capacity Minimum 200 Ltr
2.0 Fuel System
6.21 Specification for HSD (High Speed Diesel) UG Storage Tank & Pumping
System
a) HSD Storage Tank & Pumping System shall be provided by the EPC
Contractor for continuous pumping of HSD to the DG Sets installed in
substations. Underground HSD tanks shall be located as per
CPCB/NFPA/CPWD/Local bylaws. Underground Diesel storage tank of
suitable capacity minimum of 10 KL along with Auto fuel transfer system
comprising of suitable number and capacity of fuel pumps (working &
standby) with underground pipeline from underground diesel tank up to the
buffer diesel tank in ESS shall be provided. Fuel Transfer Pumps shall be
flame proof, rotary gear, positive displacement type or as required for HSD
pumping application. Underground tanks, buffer tanks, piping, fuel pumps,
valves, cabling, control/ level switches, earthing etc. has to be provided as
per CPCB/NFPA/CPWD/Local bylaws. The supply of first fill of HSD Tanks,
Buffer Diesel Tanks and DG Set fuel tanks is included in the scope of works.
First fill of HSD fuel shall be provided up to rated capacities of all diesel
tanks. Suitable level of Transmitter shall be fitted on top of each tank to give
continuous level status.
d) For provisions regarding analysis for saddle support and associated local
loads, reference shall be made to IS 2825: 1969.
6.21.1 Statutory Provisions
Compliance with this code does not absolve anyone from the responsibility of
observing any statutory provisions as may have been promulgated by the
statutory bodies, such as Department of Explosives.
6.21.2 Tank
The tank may be manufactured from suitable size plates covered in IS
1730:1989.
6.21.3 Materials
The material for the construction of oil storage tanks shall conform to Indian
Standards, wherever applicable.
Structural Steels
Steel plates and sections used in the tank construction shall conform to any one
of the following specifications:
6.21.5 Piping
Unless specified otherwise the pipe and pipe couplings shall conform to IS
1978:1982. If so, specified in the contract or order, couplings for threaded
connections may be supplied without recesses; when so supplied the coupling
in all other respects shall conform to IS 1978:1982. Pipes used for structural
purposes shall conform to IS 1978:1982 or IS 1979:1985 with respect to
physical properties of the material. Pipes of heavy class conforming to IS 1239
(Part 1): 1990 may be used for nozzles on tank and internal piping, if so,
specified in the contract or order.
6.21.6 Flanges
6.21.7 Bolts and Nuts
Bolts shall conform to property class 4.6 or 4.8 and other requirements specified
in IS 1367 (Part 3): 1979. Nuts shall conform to property class 4 of IS 1367 (Part
6):1980.
Other materials used in association with steel work shall, where appropriate
Indian Standard specifications for materials exist, conform to such
specifications.
6.21.9 Design
Tanks manufactured as per provisions of the codes and thicknesses shall not be
less than the thicknesses given in Table 1. Tanks to be installed underground shall
also be designed for external earth pressure acting on the tank when it is empty.
The design temperature shall be the lowest one day mean temperature where the
tank is to be installed, as available from relevant IS codes, metrological department
or local authorities.
Manhole necks, nozzle necks, reinforcing plates and shell-plate openings which
have either sheared or oxygen-cut surfaces shall have such surface made
uniform and smooth, with the corners rounded, except where such surfaces are
fully covered by attachment welds.
Nozzles
The nozzle sizes shall be selected to meet individual operating conditions of
filling and emptying rates.
Lifting Lugs
The lifting lugs shall be provided in the tank at appropriate position to lift the
empty tanks only.
6.21.14 Accessories
The tank shall be provided with a fill connection, a draw-off connection, a dip-
connection a vent connection and a drain connection.
a) Fill Connection
When the tank is filled from the top, an internal fill pipe running down
to within 100 mmofthe tankbottom shall be providedto avoid
splashingof product and generation of static electricity. End of the fill
pipe shall be chamfered at 45°.
c) Vent Connection
The vent pipe shall be securely supported and shall not be less than 4
min height and at 4 m distance from any adjoining land or property or
any other source of fire. Vent pipe of any tank shall not be
interconnected with that of another. The open end of every vent pipe
shall be covered with two layers of non-corrodible metal wire gauge
having not less than 11 meshes per linear centimetre and shall be
further be protected from rain by a hood or by suitably bending it
downward.
d) Earthing Connection The horizontal storage tank, whether above
ground or under ground, shall invariably be provided with earthing
connection to eliminate the possibility of accumulation of static
charge on the surface of the tank either due to atmospheric
electricity or due to flow of product into thetank.
When the shell length is produced from more than one single plate the
longitudinal seams shall break joint at intermediate circumferential scams. It is
recommended that whenever possible a longitudinal seam should be situated in
the upper third of a tank or on the top centre line.
The end plates shall be adequately stiffened. The recommended size of angle
stiffeners is as given in Table 1
6.21.18 Tolerances
Tolerance on Shell Diameter
The tolerance on diameter at any point on the length of the tank shell shall be
within +0.35 percent of the specified diameter (Max) when calculated from an
external circumferential measurement.
a) Tolerance on Circularity
The tolerance on circularity at any point on the length of the shell that is the
difference between maximum and minimum internal shell diameter, shall not
exceed one percent of the nominal internal diameter.
All gauges and templates necessary for inspection, to the satisfaction of the
inspector shall be supplied by the manufacturer. All tanks shall be subjected to
hydraulic test and checked for leaks.
6.21.20 Calibration
Tanks may be calibrated mathematically. Where physical calibrations are
specified, tanks shall be calibrated in accordance with IS 2009: 1975 using a
certified water. Calibration may be certified by an independent authority, if so
required.
b) Primer Coat --- The surface thus prepared should be treated with two
coats of primer. Each coat is applied uniformly after the previous one
is completely dried.
c) Doping - After the application of primer coats, two coats of hot 30/40
Grade bitumen shall be applied as per manufacturer's
recommendations, resulting in an overall coating thickness of 3.2 mm.
The30/40Gradebitumenshallbeheatedtotherequiredtemperatureasrec
ommended by the manufacturer for easy and uniform application of
bitumen.
6.22.1 Following tests shall be carried out at the manufacturer's works in the presence
of Engineer-in-charge or his representative. DG sets and the auxiliaries shall be
assembled at the manufacturer's works and the following tests shall be performed.
Load test for 12 hours at rated KW at DG set's KW rating followed by a 1 hour on
10% overload (after continuous run of the 12 Hours with fuel consumption).
After successful testing of the DG Set, a trial run at available load will be carried
out for 120 Hours on each DG set individually. The DG Set will be operated and a
log of all relevant parameters will be maintained during this period. The
arrangement of staff for trial run/ running in period & fuel will be made by the
successful tenderer. The contractor will be free to carry out necessary
adjustments. The DG Set will be said to have successfully completed the trial
run, if no break-down or abnormal/ unsatisfactory operation of any component of
the entire installation included in the scope of work of the contract, occurs during
this period. After this the DG Set will be taken over by the department subject to
guarantee clause of the contract.
b) The test reports shall furnish complete identification of the data, including
serial number of each equipment. The successful tenderer shall arrange
staff / fuel / POL for test run at his cost. Inspection and Testing of DG sets
shall necessarily be carried out at factory / manufacturer premises in
presence of representative of the CPWD.
b) Line diagram and layout of all electrical control/AMF panels giving switchgear
ratings and their disposition, cable feeder sizes and their layout.
1730: 1989 Dimensions for steel plate, sheet, strip and flats for
general engineering purposes
1978: 1982 Line pipe
1979: 1985 High test line pipe
2002: 1982 Steel plates for pressure vessels for intermediate
and high temperature services including boilers
2.6. The contractor shall submit the following after award of work:
(i) Submission of GA drawing of DG set for approval
(ii) Written commitment from OEM/OEA to supply the DG Sets and delivery
schedule as per requirement of department.
(iii) Certificate from OEM/OEA or authorized service provider of engine
manufacturer of satisfactory installation and commissioning of DG Set
after completion of the work.
(iv) The defect liability period shall be reckoned from the date of
handing over of the installation to the department.
(v) An undertaking that mandatory free service shall be carried out during the
Defect liability period as per this agreement by the authorized service
provider.
7.1 ThescopeofworkincludesPlanning,design,supply,installation,testing
andcommissioning of Online Modular type UPS system with required
battery banks. Minimum Capacity of UPS shall be minimum 200 KVA
Modular UPS (in N+2 combination) with parallel Redundant withminimum
30Minutes Backup with maintenance free batteries. Suitable battery
capacity and quantity shall be provided for each UPS and Battery Size
Calculation should be submitted by the contractor for approval by
Engineer-in-charge. Energy Efficiency Requirements at 100 % Load shall
be as per Super ECBC 2017 to provide continuous, uninterrupted power
comprising. These technical specifications shall be read along with the
General Conditions for all E&M works given under subhead C-B.
7.1.1 The capacity of UPS is indicative only. The agency shall design a suitable
capacity with calculations and get it approved by Engineer-in charge. This
Specification describes a three-phase, online, continuous operation, solid-
taste uninterruptible power supply system (UPS). The UPS shall operate
as an active power control system, working in conjunction with the
building electrical system to provide power conditioning and online power
protection for the critical loads. The following loads shall be considered
for designing the capacity of the UPS.
7.2 Standards:
7.3.1 The UPS shall be provided with separate feeds for rectifier/inverter
and static bypass switch. Each single-UPS unit shall operate in
double-conversion mode. The UPS shall be of the double conversion
on-line topology with power factor corrected inputs. It shall be a VFI-
type UPS made up of the components, described in detail. The system
shall be designed with N+2 modules. So, as to support full designed
a) ACInput Characteristics:
i) Input voltage : 415Vac, 3-phase and 4 -wire
ii) Input voltage range :305-477V
iii) Input power factor :> 0.98
iv) Total harmonic distortion : Less than 3%
v) Frequency : 40-65 hertz.
b) Output Characteristics:
i) Output Voltage : 415 volts AC 3-phase and 4-wire
vi) Frequency : 50 hertz, ± 0.5
ii) Voltage Stability : ±1.0% for balanced load, ±2.0% for
unbalanced load.
iii) Output voltage harmonic distortion:
< 2% at 100% linear load.
< 5% at 100% non-linear load.
iv) Power Factor : 1 (Unity) at the rated KVA.
v) Overloadcapability
: 110%for1 Hour.
: 150%for1 minute.
The rectifier shall correct power factor to maintain an input power factor of
0.98 lagging to unity at 75 percent or above load levels to ensure generator
compatibility and avoid reflected harmonics from disturbing loads. The
Rectifier shall produce a sinusoidal input AC current on each phase with
low harmonic content.
7.4.2 Batteries:
The battery technology shall be Valve regulated sealed lead acid (VRLA-
AGM) batteries. The battery charger shall be equipped with a temperature
probe to enable temperature compensated charging and shall adjust the
battery float voltage to compensate for the ambient temperature.
Battery voltage shall be battery temperature compensated as outlined in
therectifier sectionabove. The battery charging circuit shall remain active
when the Power factor controller operates normally. Batteries shall be
supplied with suitable MS powder coated battery bank rack, flexible
connectors, and all standard accessories.
7.4.3 Inverter:
The inverter shall consist of fast switching IGBT modules. The inverter
shall be aminimum Level 3 inverter topology. Inverter shall be PWM
controlled usingDSP logic. Analogcontrolshallnotbeacceptable. The
inverter shall be capable of providing the specified precise output power
characteristics while operating over the battery voltage range.
7.4.4 Staticbypassswitch:
7.4.6 Mechanical:
a) The UPS shall be housed in a free-standing cabinet with casters.
b) The cable entry shall be from the back of the UPS.
c) The UPS shall meet an ingress level of minimum IP20.
d) User replaceable dust filter shall be provided with the standard cabinet.
e) The critical components i.e.,PCBs shall be confirmedly coated
7.5.1 The UPS shall include a standard control and indicator panel with backlit
LCD display and a keypad consisting of push button switches with choice
of languages for indication of UPS status, metering, battery status, alarm/
event log, and advanced operational features. LED mimic diagram. The
mimic diagram: shall enable display of installation parameters,
configuration, operating status and alarms and indication of operator
instructions for switching operations (i.e., bypass).
The UPS shall provide an audible alarm that can be stopped using the user
interface. If a new alarm is sensed after the original alarm has been
silenced, it shall reactivate the audible alarm.
INPUT
Voltage (Vac), per phase
Current (Aac), per phase
Frequency (Hz)
Power (kVA)
OUTPUT
Voltage (Vac), per
phase Current (Aac),
per phase Frequency
(Hz)
Power (kW), per phase
Load (%), per phase
BYPASS
Voltage (Vac), per phase
Frequency (Hz)
INVERTER
Voltage (Vac), per phase
Frequency (Hz)
AC/DC (Rectifier)
Voltage (Vdc)
BATTERY
Voltage (Vdc), Current (Adc)
Type (Ah)
Autonomy (minute, %)
a) Load:
1) UPS outputison.
2) OverloadonUPSoutputoroutputhasshorted.
3) UPS outputisoff.
b) Battery:
1) Batteryischarging.
2) Batteryisdischarging.
3) Batteryisinoperable.
4) Batterylowvoltage.
5) Batteryandbatterychargerarenormal.
c) Bypass:
1) Loadsuppliedbybypasssource.
2) Bypasssourceisunavailableorstaticbypassswitchis inoperable.
3) Bypassvoltage isoutoftolerance.
4) Bypasssourceisnormal.
d) Rectifier:
1) Rectifierisworkingcorrectly mains is normal.
2) Rectifierisinoperable.
3) Mains isunavailable.
4) Rectifier isoff.
e) Inverter:
1) Loadsuppliedbyinverter.
2) Load not supplied by inverter; inverter is inoperable.
f) PushButtons/UserControls:
For control of UPS in addition to the push buttons on the system,
necessary arrangement shall be available for remote communication.
7.5.3 Fullloadtestingwithoutexternalloadbank:
The UPS shall have an inbuilt feature to test itself at 100% loading,
continuouswithout any external load bank on the site. If this feature is
not available, Contractor shall provide an external load bank with the
input and output breakers and cables for full loadand over load testing
of UPS.
7.5.5 RemoteUPSmonitoring:
a) Normal mode: The inverter and the rectifier shall operate in an on-line
manner to continuously regulate the power to the critical load. The
rectifier shall derive power from the input source and supply DC
power to charge the battery. The rectifier supplies the inverter with DC
current while the charger simultaneously floats charges the battery.
The load is continuously supplied with dependable electrical power by
the inverter.
b) Battery mode: Upon failure of the input source, the load shall continue
to be supplied by the inverter without any switching. The inverter shall
obtain its power from the battery. There shall be no interruption in
power to the load upon failure or restoration of the input source.
c) Static bypass mode: The static bypass switch shall be used for
transferring the load to bypass supply without interruption to the critical
power load in case Inverter overload exceeds its rating or Inverter
d) ECO mode: In ECO mode, the UPS shall use static bypass mode as
the preferred operation mode under predefined conditions. In case of
a failure of the input source, the UPS shall transfer to battery mode.
g) Battery recharge: Upon restoration of the input source, the UPS shall
simultaneously recharge the battery and regulate the power to the
load. The UPS system shall ensure equal sharing of the total load
between the various parallel-connected units.
h) The UPS shuts down and should not transfer to the bypass mode
when a shortcircuit occurs on the output of the unit. After the short
circuit removed, the UPSshall operate normally again.
b) The work shall be carried out simultaneously with building work, civil
work, etc. and shall be completed satisfactorily along with the completion
of building works. The Contractor shall provide all labour and install all
materials, appliances, equipment necessary for completion of work. The
work shall include all incidental jobs connected with HVAC System
installation such as excavation for trenches and back filing, cutting/drilling
holes through walls/floors and grouting for fixing of fixtures, equipment
etc.
e) The work shall be executed as per scope & specifications of HVAC works
given hereafter. If any services required to make the bldg. / scheme
habitable and is not covered in the scope of services, same shall either
be pointed out in pre-bid meeting else, it shall be presumed that the same
shall be provided within the quoted cost.
f) It is the intention of the specification and drawings to get a complete work,
including testing and ready for operation. Any incidental accessories to
make the work complete, even if not particularly specified, but necessary
to make the work complete is within the scope of work.
g) Floor wise drawings with HVAC equipment and Plant floor drawings are
enclosed for reference.
f) The work covers the preparation of layout plans, drawings for HVAC
schemes and approval of the same from the respective local bodies
before the commencement of work. During execution, if the local bodies
etc. require a modification, the same shall be executed without any extra
cost. After execution, approvals / NOCs / clearances from local bodies
etc. shall be the responsibility of the contractor. Any statutory fees /
charges required for obtaining clearances from Local Bodies paid by the
contractor will be reimbursed.
The location of the AHUs, FCUs, Chillers, Chilled water pumps, Cooling
Towers and CHW and Cooling water piping etc. are indicative only,
therefore, the actual route of piping and the location may differ from the
plans according to the details of the building construction and the conditions
of executions of the installations.
The contractor shall supply and install at his own expenses all the secondary
materials and special fittings found necessary to overcome the interference
and do necessary modifications on the route of piping that are found
necessary during the work, to the complete satisfaction of the Engineer-in-
Charge.
a) All material and equipment shall conform to the relevant standards and
shall be of the approved make and design. The Contractor shall be
responsible for the safe custody of all the materials and shall insure them
against theft or damage from any cause whatsoever, it may be. A list of
items of materials and equipment, together with sample of each shall be
submitted to the Engineer-in-Charge.
b) All materials of the same kind of service shall be identical and made by
the same manufacturer. Any deviation to this rule shall be approved by
the Engineer-in-Charge. Materials/ Products/ Items shall be only among
the preferred makes contained in this document.
c) Rating of all items shall be appropriate for the conditions on the particular
site on which the items will be used. All the equipment shall be fit for
continuous work.
c) That all the features performed at its best and loading and unloading of
the system.
d) That all the accessories used on low side work are of specified make
only.
e) The contractor shall provide all necessary instruments and labour for
testing, shall make adequate records of test procedures and readings,
shall repeat any tests requested by the Engineer-in-Charge and shall
provide test certificates signed by a properly authorized person.
Before ordering the material necessary for these installations, the contractor
shall submit to Engineer-in-Charge for approval, a sample of every kind of
material such as diffusers, grilles, ducts, etc., along with the catalogues.
For big items such as chillers, cooling towers, pump sets etc. the submission
of catalogues shall be enough. No material shall be procured prior to the
approval of the Engineer-in-Charge.
The contractor shall prepare and submit Detailed Heat load Calculations
with all assumptions, detailed drawings of HVAC plans, HVAC Plant Room,
all equipment, chilled Water Piping plans, Detail Ducting Drawing with Grill/
Diffuser Sizing and equipment and relevant data. Any other information
required by Engineer-in-Charge. Engineer-in-Charge reserves the right to
alter or modify these drawings if they are found to be insufficient or not
complying with the established technical standards or if they do not offer the
most satisfactory performance or accessibility for maintenance.
8.2 Based on heat load calculations, design and selection of high side & low
side equipment in consultation with the CPWD to get the equipment load,
the condition of various rooms and designing according to the required air
changes, temperature, RH etc. and capacity of the chilling units is in the
scope of work.
The excluded areas for HVAC are Non critical areas, General wards,
Library, Record room, Physiotherapy, Corridors, Lobby, Waiting Areas,
Toilets, Staircase. Areas to be air conditioned are shown in the Indicative
drawings. If required, part of the excluded areas need to be air conditioned
as per the ESIC authority’s requirement and guidelines.
c) Designing of LT Panels and control panels and its cabling network from
AC plant to equipment. All Panels should be TTA panels.Layout of
various equipment of HVAC plant at service building.
e) During the approval of design and drawing, the contractor shall submit
the data sheets and catalogues of equipment in support of their design.
g) The agency shall run chilled water pipe lines through the service
trench/duct from Service block to hospital building with suitable supports.
i) Proper control for the AHUs /FCUs shall be provided as per the site
requirement. Separate AHUs to be provided for, Minor OTs, 8 Nos.
Modular OTs, HDU, Infectious ward, ICU, Super specialty, Pre- OT and
Post OT wards.
l) Chillers, Pumps, Cooling towers and their related Elect. Panels shall be
housed at engineering services building which is a separate building and
the same is shown in the architectural site plan drawing. Service
trench/duct as per drawings shall be constructed and be used to bring all
HVAC services from service block/building to Hospital building.
a) AC equipment-High side
i. Chillers selected shall be Water Cooled Screw / Centrifugal type, with
VFD. Minimum 3 x 100 TR (2 Working +1 Standby).
ii. Constant primary Chilled Water, variable secondary chilled water pumping
system with VFD & Condenser water pumping system.
iii. CTI approved Cooling Towers and their related pumping system with &
water treatment plant. Cooling tower capacity shall be 25% more than
chiller capacity.
iv. AHUs, DX type / Cassette type/ Split air conditioners/ FCU
v. One No. 100TR Chiller shall run on essential supply (DG power supply)
for providing air conditioning to critical areas such as Operation Theatres,
ICUs, PICU, and NICU etc.
vi. All Pressurization system and Ventilation system shall work on essential
supply (DG power supply).
vii. Automatic Tube cleaning system
viii. Chiller plant manager with ultrasonic flow meter.
All Ducting shall be made of Aluminium. Air terminal shall be powder coated
extruded Aluminium except for battery room where GRP grills shall be used.
i.
AHU room shall have floating floor or spring isolator to avoid
transmission of noise and vibration in hospital usage area.
ii. Sound attenuators to maintain low noise level in all areas.
8.2.2 GuidelinesforParameterstobeConsideredforHVACSystemDesignforHealth
CareFacilities-
Humidity
Sl
Changes per Hour
Air Pressure in
to
of
Air
No.
Surrounding Area
Temperature
Space
Minimum
Changes
ºC
Relative
Percent
Relation
Hour
a) The AHU of each OT should be a dedicated one and should not be linked
to air conditioning of any other area in the OT and surroundings.
b) The location of outdoor air intake for an AHU must not be located near
potential contaminated sources like DG exhaust hoods, lab exhaust
vents, and vehicle parking area.
a) Positive Pressure:
The minimum positive pressure recommended is 2.5 Pascal. There is
a requirement to maintain positive pressure differential between OT
and adjoining areas to prevent outside air entry into OT. Positive
pressure shall be maintained in OT at all times (operational & non-
operational hours). 100% fresh air shall be utilized for air conditioning.
c) Air Filtration:
The AHU (i.e., air handling unit) must be an air purification unit and air
filtration unit. There must be two sets of washable flange type filters of
efficiency 90% down to 10 microns and 99% down to 5 microns with
aluminum / SS304 frame within the AHU. The necessary service
panels to be provided for servicing the filters, motors &blowers. HEPA
filters of efficiency 99.97% down to 0.3 microns or higher efficiency are
to be provided. Air quality at the supply i.e., at grille level should be
Class 100/ISO Class 5 (at rest condition). Note: class 100 means a
cubic foot of air should not have more than 0.5 microns or
larger.Temperature & Relative Humidity: Temperature should be
maintained at 21°C ± 3°C (except for Joints replacement where it
should be 18°C
± 2°C) with corresponding relative humidity between 20% to 60%,
though the ideal RH is considered to be 55%. Appropriate devices to
monitor and display these conditions inside the OT shall be installed.
II.Labour & Delivery: The procedures for normal child birth are considered
non-invasive and rooms are controlled similar to PT rooms. Invasive
procedures such as a caesarian section are performed in Operation
Theatres.
III.MRI & CT Scan Rooms: Normal comfort air conditioning and ventilation is
required. However, in case, if requested by department/ ESIC authorities,
Precision Air conditioner may be provided to handle the high heat release
of computer equipment and cryogens used to cool the magnet.
VI.Pharmacies and Drug Storage Areas: This is another unit within hospital
and other healthcare organizations that require air conditioning in order to
carry ‘temperature dependent’ drugs. Inadequate temperature control here
either means that medication would not function as required or the hospital
would simply not be able to stock some emergency treatments.
VII. Server room & UPS room Air Conditioning
with THD less than 5%. Chiller shall comply with 5-star rating as per up-to-
date ECBC Norms.
Chiller:
Condenser:
b) The compressor shall unload from fully loaded to the minimum capacity
by means of hydraulically actuated slide valve positioned over the screw
rotor/ pilot operated solenoid valve & VFD. The compressor housing shall
be of high-grade cast iron, machined with precision, to provide a very
close tolerance between the rotors and the housing. The rotors shall be
mounted on antifriction bearings designed to reduce friction and power
input. There shall be multiple cylindrical bearings to handle the radial and
axial loads.
c) There shall be built in oil reservoir to ensure full supply of lubricants to all
bearings and a check valve to prevent backspin during shut down. There
shall be oil pump or other means of differential pressure inside the
compressor for forced lubrication of all parts during start-up, running and
during shut down. An oil sump heater shall be provided in the casing.
e) The driving motor shall be double squirrel cage type or suitable Semi
hermetic type as required, protected against damage by means of built-
in protection devices.
8.4.3 Controls
c) Display shall provide a minimum of unit set points, status, electrical data,
temperature data, pressures, safety lockouts and diagnostics without the
use of a coded display.
chilled liquid cooling mode, local/ remote control mode, display units
mode, system lead/lag control mode, remote temperature reset, remote
current limit, remote heat recovery kit, leaving chilled liquid set point and
range, maximum remote temperature reset.
b) Where the impeller is designed for operation at speed higher than the
drive motor, necessary speed increasing gear shall be connected to the
impeller shaft in a self-aligning and balanced way. The gears and pinion
shall be pressure lubricated.
The compressor shall be equipped for modulating the capacity from 100%
up to the 25% at constant condenser entering water temperature without
surging and hot gas bypass. The vane position shall be controlled through
hydraulic/ linkage system. The positioning of the vane shall be through
microprocessor-based controller with its sensing elements in the outgoing
chilled water lines. The automatic damper will enable maintenance of
specified chilled water temperature within + 0.11 °C.
b) The electric motor shall be of squirrel cage type and shall be suitable for
operation on 400/415 V +/- 10%, 3 phase, 50 Hz, AC supply. All
Compressor motors in Screw and Centrifugal chillers with variable speed
compressors shall be provided with VFD and shall also be suitably
designed for use with Variable Frequency Drive.
d) Continuous BHP rating of the motor shall not be less than the maximum
power requirement of the compressor and drive under specified design
conditions).
d) The text displayed within the system status and system details field shall
be displayed as a color-coded message to indicate severity: red for safety
fault, orange for cycling faults, yellow for warnings, and green for normal
messages.
e) Safety shutdowns enunciated through the display and the status bar, and
consist of system status, system details, day, time, cause of shutdown,
and type of restart required. Safety shutdowns with a fixed speed drive
shall include:
g) Cycling shutdowns enunciated through the display and the status bar,
and consists of system status, system details, day, time, cause of
shutdown, and type of restart required. Cycling shutdowns with a fixed
speed drive shall include:
c. Drive will be PWM type utilizing IGBTs with a power factor of 0.95
or better at all loads and speeds.
8.5.8 Evaporator:
Unit shall be with multi pass flooded type evaporator. The maximum
refrigerant-side working pressure shall be 230 psiG (15.85 bar) and the
water side pressure shall be 150 psiG(10.34 bar), It should be tested as
per standard as specified above. The evaporator shall be mechanically
cleanable, shell-and-tube type with multi pass arrangement and
removable nozzle in head type connections. Tubes shall be internally and
externally grooved, high efficiency tubes, seamless-copper and shall be
rolled into tube sheets. Shell shall be insulated with 19 mm thick closed-
cell nitrile rubber. Evaporator thermal insulation shall be factory fitted. The
evaporator shall have a drain and vent in each head. Design shall
incorporate one refrigerant circuit. Removable compact nozzle in head
water boxes of cast iron or welded steel with stub-out water connections
shall be provided to permit access for tube cleaning and replacement.
Water Velocity through tubes shall not exceed 12 fps(3.66 m/s). Maximum
allowable pressure drop across the evaporator shall not exceed 10 m of
water. Heat exchanger shall be in accordance with ASME.
8.5.9 Condenser:
b) The plant control system shall be supplied with all the hardware, software
and programming required to control above mentioned equipment
demand sensors to maintain minimum flow.
d) The plant control system shall be supplied with all the hardware, software
8.6.1 Submittals
Provide a complete Chilled Water Plant Control System Submittal with all
requirements as defined in the general requirements of these
specifications. As a minimum, the Submittal shall include the following:
i. Dimensional drawings of the main components, also indicating
weight and any special hoisting or working space clearances
requirements.
ii. Description of system operation
iii. Electrical power and control wiring diagram
iv. Control layout drawing with sequence of operation
v. Operation and maintenance manuals
c) web interface shall include summaries via the web. It shall also include
ongoing tracking of the performance relative to the predicted
b) The plant automation shall be performed solely by the PLC and the PC
shall not be required for plant operation, other than initial setup or
configuration.
c) The chilled water plant control system shall include a combination of PC-
based and PLC controller.
d) The chilled water plant control system shall have an internal circuit
breaker and run on 240 V AC /1Ph/50 Hz power supply.
h) The control system shall have a key lockable IP54 or better rated cabinet.
All operator interface control switches, indicators and displays shall be
physically separated from any field terminations. Manual backup control
switches and indicators must be protected from unauthorized operation
by a key lockable door.
i) The plant control system shall have Hand-Off-Automatic control for each
chiller, pump and tower fan drive. These virtual H-O-A switches shall be
accessible through the touch screen display, and in Hand mode, the
control system shall allow the pump speed and the tower fan to be
manually set and changed.
j) The chilled water plant control system shall include a back-lit touch
screen color display operator interface of at least 10.4” and show active-
element schematic displays with links to sub-menus for status reports,
data and setup menu options. No data shall be lost during power supply
interruptions.
8.6.5 Instrumentation
a) The chilled water plant control system shall provide the following remote
mounted transmitters and sensors to be installed and wired back to the
central plant control system.
traceable to NIST.
The temperature transmitter shall receive its power input and send its
current output, 4-20 mA, over the same pair of low voltage wires. Sensors
shall be mounted such that effects of radiation from heating elements are
minimized and rapid response to changing temperature is achieved.
Wiring installed by the contractor between the control system and the
transmitters shall be 2-wire, shielded, twisted cable (or equivalent) and
shall not be placed in conduit containing wiring for alternating current.
Supply and return temperature sensor shall be field installed and wired
between the chillers and the bypass line.
e) The flow sensor shall be a high precision magnetic flow meter with no
moving parts. Paddle and turbine type sensors shall not be accepted.
The sensor shall have a maximum operating pressure of 300 psi,
operating temperature range of 5°F to 158°F. Accuracy shall be within
0.5% of actual reading at the calibrated typical velocity and within +2% of
reading over 200:1 turndown (from 0.05 to 10 m/s). Provide certificate of
calibration with each flow sensor. The sensor shall have integral 4-20mA
analog output for connection to the control system. The flow sensor shall
be constructed of stainless steel with IP65 protection. Contractor shall
supply hot tap installation, in order to be both insertable and removable
through a ball valve when the pipe is under pressure. Flow meter shall
be field installed and wired by the contractor. The sensor shall be field
mounted and wired in accordance with manufacturer’s instructions.
8.6.6 Software
f) Safety Features shall include but not limited to the following list:
I. Auto omission of pump in case of pump failure
II. Auto omission of chiller in case of chiller failure
III. Backup sequences in case of flow sensor failure, temperature
sensor failure, and all zone sensors failure.
g) Sequence of Operation:
III. The control system shall continuously monitor all zone signals to
determine an active control zone. Use of a multiplexer for multiple
sensor inputs is not acceptable.
IV. The control system shall respond to the most dissatisfied zone by
increasing either, the number of operating pumps, or the pump
speed.
VI. The pump logic control system shall sequence the pumps based
on a field adjustable interval of operating hours with a “bump-less”
transfer algorithm. The control system incorporates an adjustable
PID control loop and embedded logic to prevent hunting.
VIII. For each chiller the control system has an adjustable field to enter
its capacity. The plant load (in Tons and %) is displayed on the
touch screen display and used to Stage on and off the chillers, in
conjunction with the other conditions explained in the previous
paragraph.
IX. The control system shall rotate the Lead chiller on a field
adjustable interval of operating hours. Should any chiller fail, the
control system shall trigger an alarm on the touch screen display
and remove said chiller from the auto sequence and rotation.
XI. The control system modulates the bypass valve to maintain the
minimum flow required by the operating chillers.
XII. If dedicated, the condenser pumps shall be sequenced with the
chillers.
XIII. If headered constant speed, the condenser pumps shall be
sequenced to maintain the design flow required by the running
chillers.
XIV. The condenser pumps shall maintain the Chiller flow.
8.6.7 Execution
b) Testing
Upon completion of all systems startup and checkout procedures and while
the mechanical systems are being monitored and controlled in a “normal
operating” condition, the manufacturer and the facility personnel shall jointly
demonstrate the performance of the complete system to maintain flows,
temperatures, levels and pressures for 7 days, with no alarms. The test must
meet the particular building’s design requirements. Any failures or alarms
shall require the test to be restarted.
d) Training
The chilled water plant control system manufacturer shall train the
personnel of the ESIC in the operation of the control system. Drawings,
operation and maintenance manuals are to be provided to the ESIC
authorities in a single binder, clearly indexed.
The specification for Double Skin Air handling unit comprises the design,
manufacture, delivery at site, erection, commissioning and conducting
performances test at site of Air handling units conforming to these
specifications. Factory fabricated AHUs only acceptable.
AHUs shall comply with all currently applicable statutes, regulations and
safety codes. The equipment shall also conform to the requirements of the
latest editions of applicable ASHRAE Standards. Nothing in this
specification shall be construed to relieve the Contractor of his
responsibility.
The air handling unit shall be of double skin construction, draw through type
in sectionalized construction consisting of blower section, coil section,
humidification section (where specified), filter section and insulated drain
pan. The unit shall be horizontal type. All AHUs shall be provided with VFDs.
a) Capacity:
The air handling capacities, maximum motor horsepower and static pressure
shall be as per the approved design and drawings.
b) Rating:
I. The coil shall be designed for a face velocity of air not exceeding
155 m/min.
II. The requisite static pressure demanded by the air circuit shall be
developed by the fan at the selected operating speed. The static
pressure value shall not in any case be less than 40 mm water
gauge in normal cases, not less than 65 mm water gauge where
microvee filters are also used and not less than 100 mm water
gauge where absolute filters are also used. The fan motor HP shall
be suitable to satisfy these requirements and the drive losses.
III. The air outlet velocity from the blower fan shall not exceed 610
m/min.
IV. Noise level at a distance of 2 m from AHU shall not exceed 75 dBA.
Housing/ Casing
I. The housing/ casing of the air handling unit shall be of double skin
construction. The housing shall be so made that it can be delivered at
site in total/ semi knocked down conditions depending upon the
requirements. The main framework shall be of extruded Aluminium
hollow structural sections. The entire framework shall be assembled
using mechanical joints to make a sturdy and strong framework for
various sections. For 100% fresh air application, framework shall be
made of thermal break hollow extruded Aluminium profile.
II. Double skin panels shall be 25mm thick, made of 0.8mm pre-
plasticized and pre-painted with PVC guard, GSS sheet on outside
and 0.8mm Aluminium sheet inside with Polyurethane foam insulation
of density not less than 38 kg/cu. m injected in between by injection
moulding machine. These panels shall be bolted from inside/ screwed
from outside on to the framework with soft rubber gasket in between
to make the joints airtight. The gaskets shall be inserted within groove
in extruded Aluminium profile of the framework. For units installed
outdoor, the thickness of double skin panels shall be minimum 40 mm.
III. Frame work for each section shall also be bolted together with soft
rubber gasket in between to make the joints air tight. Suitable doors
with nylon handles, Aluminium die-cast powder coated hinges &
latches shall be provided for access to various panels for maintenance.
However, AHU in the form of complete single unit shall also be
a) The coil shall be made from seamless solid drawn copper tubes. The
minimum thickness of tube shall be 0.5 mm for cooling coils.
b) The depth of the coil shall be such as to suit the requirements, viz. re-
circulated air applications, or 100 % fresh air applications. The coil shall
be 4 or 6 rows deep for normal re-circulated air application and 8 rows
deep for all outdoor air application. In case of 8 rows deep coils, it shall
be made of 2x4 rows deep coils with a spacing of 200mm between the
two coils, access door and independent drain pan.
d) Each section of the coil shall be fitted with flow and return headers to
feed all the passes of the coil properly. The headers shall be of copper
and shall be complete with water in/out connections, vent plug on top and
drain at the bottom. The coil shall be designed to provide water velocity
between 0.6 to 1.8 m/s in the tubes.
e) The fins shall be of Aluminium. The minimum thickness of the fins shall
be 0.15 mm nominal. The no. of fins shall not be less than 12 per inch
length of coil. Fins may be of either spiral or plate type. The tubes shall
be mechanically expanded to ensure proper thermal contact between fins
and tubes. The fins shall be evenly spaced and upright. The fins bent
during installation shall be carefully realigned. For coastal areas fins shall
be phenolic coated and for 100% F.A. application fins shall be hydrophilic
type.
f) The coil shall be suitable for use with the refrigerant specified or with
water as the case may be. Refrigerating coils shall be designed for the
maximum working pressure under the operating conditions. Water coils
shall be designed for a maximum working pressure of 10 kg./sq.cm.
g) Shut off and regulating valves at the inlet and outlet of water shall be
provided. In the case of DX coils, solenoid valve and expansion valves
shall be provided at the inlet of coil.
a) The supply air fan shall be AMCA certified centrifugal type with forward/
backward curved blades double inlet double width type. For static
pressure up to 65mm, forward curved blades shall be used and for higher
sizes backward curved blades shall be used.
b) The fan housing of Galvanized sheet steel and the impellers shall be
fabricated from heavy gauge steel sheet. The side plates shall be die
formed for efficient, smooth airflow and minimum losses. Fan impeller
shall be mounted on solid shaft supported to housing using heavy duty
ball bearings. Fan housing and motor shall be mounted on a common
extruded Aluminium base mounted inside the fan section on anti-
vibration spring mounts or cushy- foot mount. The fan outlet shall be
connected to casing with the help of fire-retardant fabric.
d) The fan shall be fitted with vee belt drive arrangement consisting of not
less than two evenly matched belts. Belts shall be of oil resistant type.
Adequate adjustments shall be provided to facilitate belt installation and
subsequent belt tensioning by movement of the motor on the slide rails.
A readily removable door guard shall be provided.
e) The fan motor shall be totally enclosed fan cooled squirrel cage induction
motor with IP-54 protection & selected for quiet running. The motor shall
be suitable for operation on 415 ± 10%V, 3 Phase, 50 Hz, A.C. supply.
The fan motor shall be of premium efficiency IE3 class, as per IS 12615.
The motor shall suitably be designed for use with variable frequency
drive.
f) AHU fan motors shall be provided with variable frequency drive where
VAVs (Variable Air Volume control) are provided in the ducts.
b) Dry fabric (fine) filters: These filters shall have efficiency of 99% down to
5-micron particle size as per EU/MERV 7 standard. These filters shall be
provided for all AHUs. These are provided on the discharge side of AHU
after fan section and are always backed by pre-filters provided on the
suction side of AHU. Face velocity across these filters shall not exceed
155 MPM.
to 0.3-micron particle size as per EU/ MERV 13 standard & are required
for applications like operation theatre, micro-labs etc. These are also
provided in the AHU after fan section or at terminal point and always must
be backed by fine filters & pre filters. These filters after they become
dirty, cannot be reused and have to be thrown away. Face velocity across
these filters shall not exceed 155 MPM.
8.7.5 General Construction of filters
b) The filter area shall be made up of panels of size convenient for handling.
The filter panels shall be held snugly within suitable Aluminium
framework made out of minimum 1.6 mm Aluminium sheet with sponge
neoprene gaskets by sliding the panels between the sliding channels so
as to avoid air leakage.
e) Each fine and HEPA filter shall carry test certificate from manufacturer.
a) Pressure gauges at the inlet and outlet of the coil with tubing & gauge
cock. Stem type thermometers at the inlet & outlet of coil with tubing &
gauge cock.
b) Butterfly valve at the inlet and outlet of coil. Balancing valve at the outlet
of coil. Y-strainer at the inlet of coil.
a) The fan coil units shall be floor/ wall/ ceiling mounted draw through type
complete with finned coil, fan with motor, insulated drain pan, cleanable
air filters and fan speed regulator and other controls as described.
c) The coil shall be of seamless copper tubes with Aluminium fins. The fins
shall be uniformly bonded to the tubes by mechanical expansion of the
tubes. The coil circuit should be sized for adequate water velocity but not
exceeding 1.8 m/s. The air velocity across the coil shall not exceed 155
m/min.
f) Air Filter shall be cleanable type 15mm thick with 90% efficiency down to
10 microns of dry cleanable synthetic type to be mounted behind the
return air grill in the unit casing.
h) Automatic controls unit shall have a room type thermostat and a solenoid
valve. The valve shall be fixed at a convenient location. The thermostat
shall be mounted along with the speed control switch on a common plate.
The plate shall clearly indicate the fan positions. The water valves on inlet
line shall be of gun metal ball type with internal water strainers, having
BSP female pipe thread inlet and flare type male pipe thread outlet
connection. The valves on return line shall be as above, but without the
water strainer.
i) The water lines shall be finally connected to the coil of the fan coil unit,
by at least 300mm long, type `L ‘seamless solid drawn copper tubing,
with flare fittings and connections.
j) Unit shall be selected for the lowest operating noise level of the
equipment, Fan performance rating and power consumption data, with
operating points clearly indicated shall be submitted and verified at the
time of testing and commissioning of the installation.
a) The type and size of all chilled water & condensing water pumps shall be
in accordance with requirement. However, the pumps shall be selected
to have interchangeability of spares for similar requirements in order to
reduce inventory. It shall have a fixed speed Primary Pumping and
variable speed secondary pumping with VFD for chilled water circuits and
pump sets with VFDs for Cooling towers. Water flow rates and head of
the pumps shall be in accordance with the requirements.
b) The pumps for Chilled Water and Condenser cooling water shall be of
True Back-pull out type, End suction, mechanical seal, Centrifugal type
pumping unit. The pumps shall be Horizontal split casing, centrifugal type
with CI casing with equal size suction and discharge flanges and having
separate tapped flush line and pressure gauge connections, Gunmetal
Bronze dynamically balanced impeller, stainless steel shaft, low carbon
throttle bushing, Outside Balanced type mechanical seal with Resin
Bonded Carbon rotating face, Sintered Silicon Carbide stationary seat
and Viton secondary seal. The pump shall be supplied duly aligned with
motors from the manufacturer’s works with base frame. Efficiency of the
pumps at selection should be 70 % or above.
g) Base shall be of a size suitable for the pump, motor and shaft and shall
be constructed of cast iron or welded steel.
h) The pump set shall be provided duly aligned with motor and installed on
the base frame from manufacturers works. A guard mounted on the
common base shall protect flexible coupling.
c) The overall variable speed pumping system shall comprise of True Back-
pull out type, End (single) suction, mechanical seal, Centrifugal type with
integrated pump mounted VFD coupled with motor duly aligned and
dynamically balanced, variable speed controller, field instrumentation &
adjustable frequency drives all integrated into a single package.
f) Pumps supplied shall confirm to rigid flexible coupling design only; close
coupled pumps or mono-block pumps shall not be accepted.
k) The pumps shall be Horizontal split casing, centrifugal type with CI casing
with equal size suction and discharge flanges and having separate
l) The pump seal seats shall preferably be ceramic type for higher corrosion
resistance suitable for HVAC application.
The Pump selection and optimization software from the pump supplier
shall specifically be customized for HVAC applications. Is should cover
variable speed curves, detail part selection and custom special fluid
viscosity and temperature correction over and above other standard
features.
8.9.4 Components
e) Contractor shall clearly indicate in the drawings for approval (DFA) the
number of sensor inputs considered for the variable speed pumping
package.
II. Red fault light, yellow warning light, and green power on light
III. Soft-touch membrane keypad switches.
h) The display shall preferably have four lines, with 20 characters on three
lines and eight large characters on one line. Actual pump information
shall be displayed indicating pump status.
The Pump logic controller shall be designed for the number of variable
speed pumps as per requirement.
8.9.6 Variable Frequency Drive (Applicable for AHU Fan motors and
Secondary pumps)
a) VFD shall be providing near unity displacement power factor (cos Ø) without
the need for external power factor Correction capacitors at all loads and
speeds. VFD shall be CE Marked showing compliance with both the EMC
Directive and the Low Voltage Directive. VFD shall be IP-55 rating UL Type-
12. The VFD shall be housed in a NEMA 1 enclosure. VFD with plastic
enclosures shall not be acceptable.
b) The VFD shall employ an advanced sine wave approximation and voltage
vector control to allow operation at rated motor shaft output speed with no
derating. This voltage vector control shall minimize harmonics to the motor
to increase motor efficiency and life.
c) The VFD shall have balanced DC link reactors to minimize power line
harmonics. VFD’s without a DC link reactor shall provide a 5% impedance
line reactor.
e) Input and output power circuit switching shall be done without interlocks or
damage to the VFD.
f) The following customer modifiable adjustments shall be provided:
I. Acceleration time.
II. Deceleration time.
III. Minimum frequency.
IV. Maximum frequency.
h) The VFD shall be suitable for elevations to 1000 m above sea level without
derating. Operating ambient temperature shall not be less than 40°C. VFD
shall be suitable for operation in environments up to 95% non-condensing
humidity.
III. Current
IV. Kilowatts per hour
V. Fault identification
VI. Percent torque
VII. Percent power
VIII. RPM
c) The pumping system shall start upon the closure of customer's contact
when the pump logic controller Mode of Operation selector switch is in the
REMOTE position.
d) When the pump logic controller selector switch is in the LOCAL position,
and start command on Pump Logic Controller is given via operator interface,
the pumping system shall operate automatically.
g) The pump logic controller shall compare each signal to the independent,
engineer/user determined set points.When all set points are satisfied by the
process variable, the pump speed shall remain constant at the optimum
energy consumption level.
h) The pump logic controller shall continuously scan and compare each
process variable to its individual set point and control to the least satisfied
zone.
i) If the set point cannot be satisfied by the designated lead pump, the pump
logic controller shall initiate a timed sequence of operation to stage a lag
j) When the set point criteria can be safely satisfied with fewer pumps, the
Programmable pump logic controller shall initiate a timed restages
sequence and continues variable speed operation.
k) As the worst-case zone deviates from set point, the pump logic controller
shall send the appropriate analog signal to the VFD to speed up or slow
down the pump/motor.
l) In the event of a VFD fault, the pump logic controller automatically initiates
a time sequence of events to start the redundant pump/VFD set in the
variable speed mode. The redundant variable speed system shall be started
through the pump logic controller.
m) Upon VFD fault(s), the pump controller shall display an alarm condition
through a plain English message.
Cooling Towers shall be induced draft, bottle type or rectangle type and
single cell or multi cell type, in accordance with requirement. All cooling
towers shall be certified by CTI (Cooling Tower Institute). The cooling tower
capacities shall be designed as per the plant requirement. The pump set of
each cooling tower shall be provided with VFD.
Cooling Tower shall be vertical, induced draft, counter / cross flow type, fiber
reinforced plastic construction, in square / octagonal, complete with fan,
motor, surface and spray section, eliminators, steel supports, and sound
attenuation equipment suitable for outdoor use. The Cooling tower shall be
designed to cool the requisite quantity of water through 4.2° C, against the
prevailing wet bulb temperature. The cooling tower shall be selected for a wet
bulb approach of not more than 2.77 ° C. The water flow rate through the
cooling tower shall match that through the condenser. The induced draft
cooling tower shall be one or more cells. The fan motor shall be premium
efficiency IE3 class, as per IS: 12615. VFD shall be provided to each pump
of cooling tower.
a) Side Casing
This shall be made out of FRP with minimum resistance to airflow. It shall
have sufficient structural strength to adequately withstand high wind
velocities and vibration. The casing shall be installed in the fiberglass-
reinforced basin. The tower supporting structure shall be made out of hot dip
galvanized frame. Air intake shall be all along the sides so that tower can be
installed quite independent of prevailing wind direction. Anodized aluminum
or PVC louvers integrated withfil shall be provided at air intake. Sufficient
clearance between casing and water basin shall be provided to enable
servicing and periodic cleaning.
Cold water basin shall be a deep fiberglass reinforced sump on which cooling
tower super structure shall be supported. (RCC suction tank with easily
removable double brass strainers shall be provided with this basin. The basin
shall have a holding capacity adequate for operation for at least 30 minutes
without addition of make-up water to the basin.
c) Bottom outlet
I. Screened suction assembly fixed to the casing.
II. Drain at underside of suction side sheet.
III. Overflow fixed to inside of casing side sheet.
IV. Ball type automatic makeup water valve.
V. Equalizing connection.
d) Distribution System:
Hot water distribution system shall comprise of HDG piping header and
branch arms system with HDPE nozzle flow system.
e) Fillings:
Fillings shall be made of corrosion proof and rigid virgin PVC film in honeycomb
design and arranged in square / rectangular form or fill sheets shall be
suspended from H.D.G steel structural tubing supported from the lower
structure & shall be elevated above the floor of the cold-water basin to facilitate
cleaning and easy replacement. They shall be arranged in such a manner to
ensure negligible resistance to air flow and to eliminate back water spots and
prevent fouling through scales that may form. In order to reduce carry-over
losses through entrapment of moisture drops in air stream, virgin PVC drift
eliminator shall be installed.
f) Mechanical Equipment:
a) Fan shall be of the propeller type cast Aluminium alloy, light-weight rotor
fitted with multiple aero foil blades. The entire fan assembly shall be made
b) Fan shall be protected by fan guard & shall be easily accessible for
inspection and maintenance. A service steel ladder shall also be provided
for greater convenience. The mechanical equipment assembly shall be
adequately supported on a rugged steel base welded to tubular support
assuring vibration-free support. Fan guard shall be provided to prevent
birds from nesting during idling periods. Gear-reducer shall be of spiral
bevel type. G.S.S / FRP canopy shall be provided over the fan motor for
protection against rain water. Care shall be taken that fan air is not
restricted. Motor terminal box shall be made water tight.
b) Control Panel:
Control Panel shall be of fully automatic PLC-based control and touch screen
HMI. It shall be provided with system mimic, process flow status, faults, alarm
and status of Motorized Valves, Pump. It shall be compatible with standard
communication protocols like RS485, RS232, Ethernet connection, etc.
Control Panel enclosure shall be weatherproof and with lock & key
arrangement.
c) Ball Strainer:
Ball Strainer shall be installed on condenser water outlet line. Material of
Construction of Ball Strainer shall be Mild Steel of IS2602 Grade B as per
pipe size, screen inside strainer shall be made of SS 304 perforated sheet.
Counter Flanges shall be provided with Ball Strainer. Ball Strainer shall be
treated with sandblasting then primer and final paint with epoxy paint. The
screen shall be approachable easily for disowning during maintenance.
Fasteners shall be of high-tension grade.
d) Ball Accumulator
Ball Accumulator shall be provided for each condenser and with a view
glass for checking of sponge balls during injection, collection, and standby
mode of the cycle. View glass shall be accessible to change sponge balls.
Material of Construction of Ball Accumulator shall be Mild Steel of 152302
Grade B, as per pipe size and screen inside Ball Accumulator shall be
made of SS 304 perforated sheet. Ball Accumulator shall be treated with
sandblasting, then primer and final paint with epoxy paint. Fasteners shall
be of high-tension grade.
f) Main Power Supply for OLCTCS shall be provided near to the system.
Set of mandatory spares shall be provided.
I. JET Fans
II. Co Sensors
III. Control Panel with Programmable logic control
IV. CFD analysis.
b) Casing of Jet fans shall be constructed of heavy gauge sheet. Fan casing
and motor mount shall be of welded steel construction. Casing shall be
hot dip galvanized to protect against corrosion. Noise level from Jet fan
shall not exceed 52 dB(A) at 1 m distance. Silencers Casing should be
rolled, pre‐galvanized sheet steel with spun end rings incorporating
tapped inserts for fixing.
c) Impeller of Jet fans shall be constructed from die cast aluminum. Profiles
of impeller blade should be of aero foil type to have high efficiency and
low noise levels. Aero foil Fan impellers shall have a unique aerodynamic
section blade to optimize the efficiency of performance and minimize the
generation of noise. Impeller must be statically and dynamically balanced
as per ISO 1940 grade 6.3. Jet fans shall have Inlet cone made of
Galvanized steel. Protection Guard should provide at inlet side of Jet fan.
d) Temperature Rating -The complete fan assembly with its casing, impeller
and motor shall be tested as per EN/UL for 300°C for 2 Hrs. operation.
The fan shall have a non-overloading characteristic. The peak power
inputs occur within range of normal operating pressures and is always
exceeded by motor rating.
a) Type:
Centrifugal fans shall be of double-width, double-inlet construction, with
bearing on both sides, complete with access door, squirrel-cage induction
motor, IE3 rated, V-belt drive, belt guard etc.The efficiency of fans at
operating conditions should be more than 75%.
b) Housing:
Housing shall be constructed of 14-gauge sheet steel welded construction.
It shall be rigidly reinforced and supported by structural angles. Split casing
shall be provided on larger sizes of fans, however neoprene/asbestos
packing shall be provided throughout split joints to make it air tight. 18-
gauge galvanized wire mesh inlet guards of 5 cm sieves shall be provided
on both inlets. Housing shall be provided with standard clean out door with
handles and neoprene gasket. Rotation arrow shall be clearly marked on
the housing.
c) Fan wheel:
Fan wheel shall be of GSS backward – curved non-overloading type
utilizing hollow sectioned aerodynamically shaped aero foil blades. Fan
wheel and housing shall be statically and dynamically balanced. For Fans
up to 450 mm dia., fan outlet velocity not exceed 1450 rpm. For Fans
above 450 mm dia., the outlet velocity shall not exceed 610 meter/minute.
High static pressure fan speed shall be as per manufacturer.
d) Shaft & Bearings.
Shaft shall be constructed of steel, turned, ground and polished. Bearings
shall be of the sleeve/ ball bearing type mounted directly on the fan
housing. Bearings shall be especially designed for quiet operation and
shall be of the self-aligning, oil/grease pack pillow block type.
f) Vibration Isolation:
M.S. base shall be provided for both fan and motor, built as an integral
part, and shall be mounted on a concrete foundation through spring
isolators. The concrete foundation shall be at least 150 mm above the
finished floor level.
e) Drive:
I. For Duct/Wall Mounted Fan:
For duct/wall mounted fans the impeller shall be mounted directly on the
motor. Drive unit and impeller shall be totally enclosed inside the duct.
f) Vibration Isolation
Base shall be provided for each fan. Base for both fan and motor shall be
built as an integral part and shall be mounted on a concrete foundation
through cushy foot vibration isolators. The concrete foundations shall be at
least 15 cm above the finished floor level and shall be further isolated from
the structural floor through 5 cm. thick layers of sand all around, topped with
bitumen. In case ceiling hung fan within the ceiling shall be provided with
Vibration Isolation Suspension (VIS) in each string.
fans.
b) The fan shall be complete with casing, motor and impeller. Housing Shall
be of GSS powder coated design. The duct connections at the inlet and
discharge side of the fan shall be in accordance with the manufacturer
standards to avoid transmission of vibrations, if any, to the ducting.
Impeller Fan shall have Aluminum impeller with backward curved blades
suitable for lowest sound power level. Impeller shall be statically and
dynamically balanced. Necessary acoustic insulation required to bring
down the noise as per standards shall be carried out if required.The
product shall be supplied with factory insulated design.
d) Fan motor Fans shall be energy efficient, IE3 type have external rotor
motor or IEC standard motor supplied with built-in thermal contacts. At
the critical high temperature point the thermal contact shall open and
break the power supply of the Fan. Fan motor shall be of insulation class
F and protection class IP54.Drive of the fans shall be direct driven.
e) Performance Data: All fans shall be selected for the lowest operating
noise power levels. Capacity ratings, power consumption with operating
points indicated shall be submitted and verified at the time of testing and
commissioning of the installation. All technical data of fans should be as
per AMCA accredited. High temp fans should have valid with EN / UL
Certification and rated for 300°C for 2 hrs.
8.17 Kitchens shall be provided with ventilation. The system shall consist of air
washer units, air distribution system and grilles. Cool and washed air shall
8.17.1 Air Cleaning Units for Kitchen Hood Exhaust – Dry Type Scrubbers:
Unit to be constructed in modular construction by using minimum 16G GSS.
All the welds and the finished area of welds are treated with corrosion & rust
inhibiting coating to assure long life cabinet to be finished & completed with
a durable industrial grade semi glass, backed on enamel not less than 3 mm
thick. All doors shall be provided withgasket to prevent air & water leakage.
8.17.2 Sections
Pre Filter: - Metal mesh or perforated plate type pre filter to capture
oversize objects and agglomerated mists.
8.17.3 Electrostatic Air Cleaner Module
8.17.4 Ionizer
Ionizing electrodes / wires shall be of tungsten material, rigidly supported
both vertically and laterally. Ionizing electrode to ground electrode spacing
shall be 1.0" (25mm). High voltage support insulators shall be of Teflon
material, glazed to enhance dielectric strength and retard tracking.
The scope of this section comprises the supply and laying of pipes, pipe
fittings and valves, testing and balancing of all water and refrigerant piping
required for the complete installation. All piping inclusive of fittings and
valves shall follow the applicable Indian Standards.
a) Water velocity in pipes shall not exceed 2.5 m/sec. Butterfly/ Ball valves
shall be provided at
b) Non return valve shall be provided at the delivery of each pump. This
shall be of swing type.
e) Air valves shall be provided at all high points in the piping system for
venting with a size of 25 mm for pipes up to 100 mm and 40 mm for larger
pipes.
f) Plumbing drawings showing the sizes of valves, layout and other details
shall be prepared and shall be got approved from the Engineer-in-Charge
before the execution of the plumbing work.
b) Butt welded joints for pipe sizes above 25mm. Electric welding shall
be used for sizes 100mm and above.
c) Flanges joints with flanges as per IS: 6392 for all sizes. Flanges may
be steel welded neck type or slip-on type welded to pipe, or
alternatively screwed type.
d) Flexible coupling V groove joints.
d) For pipes installed on surface, the insulation (PUF) shall be provided with
thickness of cladding as per NBC / CPWD Specifications.
Pipe sizes shall be as required for the individual fluid flows. Pipe size design
along with necessary documents shall be submitted by the contractor for
approval of Engineer-In- Charge.
a) All chilled water pipes and cooling tower water pipes are pre insulated
and all fittings shall be M.S. Class ‘C’ (Heavy Class) conforming to
relevant IS Code 1239. Factory rolled pipes upto 300 mm diameter,The
wall thickness shall be 5.0 mm
c) All pipes shall be thoroughly cleaned and given one primary coat of red
oxide paint before being installed. All welded piping shall be subjected to
the approval at site.
d) Fittings shall be malleable casting of pressure rating suitable for the
piping system. Fittings used on welded piping shall be of the weldable
type.
8.18.7 Valves:
a) Valves shall have non-rising spindles unless otherwise specified and
shall be suitable for not less than 10-kg/cm2 gauge working pressure.
Tail piece shall be used wherever required. Butterfly valves shall perform
the function of isolation of rotating equipment and Heat exchangers.
b) Butterfly valves shall have cast iron body with black nitrile rubber seat.
All butterfly valves shall be provided with locking devices. Valves above
200 mm dia. shall be gear driven.
c) Balancing valves shall be provided at chiller, AHU outlet lines. The valves
shall have built-in pressure drop measuring facility to compute flow rate
across the valves. Flanges shall be of approved make. The supply of
flanges shall also include supply of bolts and nuts and suitable asbestos
fiber / rubber insertion gaskets (minimum 3 mm thick).
d) Non return valves shall be dual plate check valves provided, conforming
to relevant Codes.
e) The spring and hinge/stop pin shall be SS304 and bearing PTFE
material. Valves shall be suitable for not less than 10 Kg/cm2 gauge
working pressure.
f) Materials:
8.18.8 Strainers
a) 'Y' strainers shall be provided on the inlet side of each air-handling unit
and pump in chilled water and condenser water circuit.
b) Pot strainers, shall be provided in return water headers, for chilled water
and condenser water.
a) Pressure gauge of appropriate range and 150 mm. dial size shall be
provided at the following locations.
i. Supply and returnofall heatexchange equipment.
ii. Suction anddischargeof allpumpsets.
b) Direct reading industrial type thermometer of appropriate range shall be
provided at the inlet and outlet of all heat exchange equipment. The
thermometers shall be installed in separate wells.
a) Expansion tanks for chilled water and hot water shall be of M.S.
construction and of adequate capacity, to contain 200% of the maximum
expansion likely to take place in the system. The tank shall be insulated
and be complete with float valve, gauge glass, drain, overflow and make
up connections, with gate valves and vent piping wherever required.
c) Valves, strainers and traps must be omitted from the expansion line since
these may be accidentally turned off or become plugged.
d) Pressurized expansion tank with air separator, can be used where the
conventional type expansion tank is not feasible to be provided.
8.18.11 Installation
c) All pipes using screwed fittings shall be accurately cut to the required size
and threaded in accordance with IS: 554 and burs removed before laying.
12 and 15 1.25
20 and 25 2.00
f) Extra supports shall be provided at the bends and at heavy fittings like
valves to avoid undue stress on the pipes. Pipe hangers shall be fixed on
walls and ceiling by means of metallic or rawl plugs or approved shear
fasteners.
i) Pipe sleeves atleast 3mm thick, diameter larger than the pipe by at least
50/100 mm shall be provided wherever pipes pass through walls and the
annular spaces shall be filled with felt and finished with retaining rings.
j) Vertical risers shall be parallel to walls and column lines and shall be
straight and plumb. Risers passing from floor to floor shall be supported
at each floor by clamps or collars attached to pipe with a 12 mm thick
rubber pad or any other resilient material as approved by the Engineer- in-
charge.
k) The space in the floor cut outs around the pipe work (after insulation
work) shall be closed using cement concrete (1:2:4 mix) or steel sheet,
from the fire safety considerations, taking care to see that a small annular
space is left around the pipes to prevent transmission of vibration to the
structure.Riser shall have suitable supports at the lowest point.
l) Underground systems shall be buried in a trench with the top of the pipe
is not less than 600 mm deep from the ground level & not less than
450mm wider than the combined OD of all piping systems. A minimum
thickness of 600mm of compacted backfill over the top of the pipe is
desirable.
n) All pipes and their steel supports shall be thoroughly cleaned and given
one primer coat of Zinc chromate before being installed.
o) After all the water piping has been installed, pressure tested as
mentioned in these specifications, all exposed piping in the plant room
shall be given two finish coats of paint, approved by the Engineer-in-
Charge. Similar painting work shall be done over insulated pipe work,
valves etc. The direction of flow of fluid in the pipes shall be indicated
with identifying arrows.
a) All piping shall be tested to hydrostatic test pressure of at least one and
a half times the maximum operating pressure, but not less than 10
kg./sq.cm. for a period not less than 24 hours. All leaks and defects in
joints revealed during the testing shall be rectified to the satisfaction of
the Engineer-in-Charge.
b) It shall be made sure that proper noiseless circulation is achieved through
all the coils and other heat exchange equipment in the system. If proper
circulation is not achieved due to air-bound connections, the contractor
shall rectify the defective connections. He shall bear all the expenses for
carrying out the above rectification, including the tearing up and
refinishing of floors, walls, etc. as required.
8.18.13 Balancing
a) After completion of the installation, all water system shall be adjusted
and balanced to first minimize throttling losses; then the pump impeller
shall be trimmed or pump speed shall be adjusted to meet design flow
conditions. Exceptions to above:
c) The pipes shall be laid in lines and levels. The vertical risers shall be
properly secured to the structure with necessary Clamps and Support
Channels and shall be supported at the base, which shall withstand the
total weight of the pipe and fluid contained. The horizontal runners shall
be hung from the ceiling using pipe hangers or laid on support channels.
iii. All foreign materials such as cement, mortar sand, heavy oil and
loose scale shall be removed from the interior of pipe by thoroughly
flushing with water.
The pipe assembly shall be provided with outer coating to prevent corrosion.
The pipe laid above ground shall be provided with Two coats of paint of
approved colour over Zinc chromate primer for M.S pipe. Two coats of paint
of approved colour for G.I piping.
I. Pipe laid underground or concealed in building structure shall be
provided with two coats of bitumen paint and wrapped with fiber glass
tissue.
II. All carbon steel pipes and pipe fittings shall be thoroughly cleaned of
oil and grease.
b) All jointing in the pipe system shall be by screwed / welded joints & / or
by screwed flanges using rubber insertion gaskets. Pipe threads and
flanges shall be as per relevant BIS Codes.
8.19 Ducts
8.19.1 All ducts shall be factory fabricated from Aluminium sheets conforming to
IS:737.
a) Design parameter for Duct design shall be:
2251mm&above 1.80
c) All sheet metal connections, partitions and plenums required for flow of
air through the filters, fans etc. shall be at least 1.8 mm thick aluminium
sheet and shall be stiffened with 25 mm x 25 mm x 3 mm angle iron
braces.
c) Hanger rods shall be of mild steel and of at least 10 mm dia. for ducts
upto 2250 mm size, and 12 mm dia for larger sizes.
d) All nuts, bolts and washers shall be zinc plated steel. All rivets shall be
galvanised or shall be made of magnesium - aluminium alloy. Self-
tapping screws shall not be used.
8.19.3 Construction
a) Ducts
I. Factory Fabricated ducts shall be as per IS: 655 "Specifications
for metal air ducts".
II. The interior surfaces of the ducting shall be smooth.
III. All the ducts up to 600 mm longest side shall be cross broken
between flanges by a single continuous breaking. Ducts of size
600 mm and above shall be cross broken by single continuous
breaking between flanges and bracings. Alternatively, beading at
300 mm centres for ducts upto 600 mm longest side, and 300 mm
centres for ducts above 600 mm size shall be provided for
stiffening.
VI. Stiffening angles shall be fixed to the sides of the ducts by riveting
at 1.25 meters from joints for ducts of size 600 mm to 1500 mm,
and 0.6 mm from joints for ducts of size larger than 1500 mm.
VII. Plenums for filters shall be complete with suitable access door of
size 450 mm x 450 mm.
II. Square and rectangular wall outlets shall have a flanged frame
with the outside edges returned or curved 5 to 7 mm and fitted with
a suitable flexible gasket between the concealed face of the
flanges and the finished wall face. The core of supply air register
shall have adjustable front louvers parallel to the longer side to
give upto 22.5 degrees vertical deflection and adjustable back
louvers parallel to the shorter side to achieve a horizontal spread
air pattern to at least 45 degrees. Return air grilles shall have only
front louvers. The outer framework of the grilles shall be made of
not less than 1.6 mm thick aluminium sheet. The louvers shall be
of aerofoil design of extruded aluminium section with minimum
thickness of 0.8mm at front and shall be made of 0.8mm thick
aluminium sheet. Louvers may be spaced 18 mm apart.
V. Linear diffusers shall have a flanged frame with the outside edges
returned 3.5 mm and shall have one to four slots as required. The
air quantity through each slot shall be adjustable. The metal sheet
used for the construction of these shall be minimum 1.6 mm thick
extruded aluminium sheet.
VII. All supply air outlets shall be fitted with a volume control device,
made of extruded aluminium gate section. The blades of the
device shall be mill finish/ block shade pivoted on nylon brushes
to avoid rusting & rattling noise, which shall be located immediately
behind the outlet and shall be fully adjustable from within the
occupied space without removing any access panel. The volume
control device for circular outlets shall be opposed blade radial
/shutter type dampers, or two or more butterfly dampers in
conjunction with equalizing grid. Opposed blade dampers shall be
used for square and rectangular ceiling/wall outlets and intakes.
IX. Laminar supply air diffusers shall be made of 2mm thick powder
coated aluminium sheet duly insulated with 5mm thick closed cell
polyethylene foam insulation having factory laminated aluminium
foil and joints covered with self-adhesive aluminium tape and
having holes 2/3 mm dia. including frame work.
d) Fire Dampers
I. Fire dampers shall be provided in all the supply air ducts and
return air ducts (where provided), return air passage in the air-
handling unit room and at all floor crossings. Access door shall be
provided in the duct before each set of fire dampers.
II. Fire dampers shall be multi blade louvers type. The blade should
remain in the air stream in open position & shall allow maximum
free area to reduce pressure drop & noise in the air passage. The
blades and frame shall be constructed with minimum 1.6mm thick
galvanised sheet & shall be factory fitted in a sleeve made out of
1.6mm galvanised sheet of minimum 400mm long. It shall be
complete with locking device, motorised actuator & control panel.
III. Fire dampers shall be motorised smoke & fire dampers type. It
shall be supplied with spring loaded UL stamped fusible link to
close fire damper in the event of rise in duct temperature. Fire
damper shall also close on receipt of fire alarm signal to cut off air
supply instantaneously. An electric limit switch shall also be
operated by the closing of fire damper, which in turn shall switch
off power supply to AHU blower motor as well as strip heaters.
IV. Fire dampers shall be CBRI tested & certified for 120 minutes
rating against collapse & flame penetration as per UL 555-1995.
Fire dampers shall be compatible with the fire detection system of
building& shall be capable of operating automatically through an
electric motor on receiving signal from fire alarm panel.
V. Necessary wiring from fire alarm panel up to AHU electric panel &
further to fire damper shall be provided by contractor.
VI. Installation of Ducting, Air Outlets and Inlets shall be as per CPWD
Specifications.
e) Installation
a) Ducting
I. All exposed ducts within the conditioned space shall have slip
joints. Flanged joints shall not be used. All joints shall be airtight.
II. Supply air outlets and return air intakes shall be anodized/ powder
coated aluminium to the desired colour to match the surroundings
wall/ceiling. The fresh air intakes shall be anodized/ powder
coated aluminium as approved by the Engineer-in-Charge.
f) Balancing
Air systems shall be balanced in a manner to minimize throttling
losses.
Theentireairdistributionsystemshallbebalancedwiththehelpofananemo
meter. The measured air quantities at fan discharge and at the
variousoutlets shall be within + 5 percent. For fans
greaterthan0.75KW(1.0HP),fansmustthenbeadjustedtomeetdesignflo
wconditions.Branch duct adjustments shall be permanently marked
after the airbalancing is completed so that these can be restored to
their correct position ifdisturbedatany time.
8.20 Insulation
Expandedpolystyrene(T.F. Quality)shallbeusedforpipeinsulation like inside
the A.C. plant room, exposed to outside or burried in ground.In the case of
expanded polystyrene (TF quality), Resin bonded glasswool the pipe
insulation should be in rigid sections in two halves
andpreformedtofitsnuglyontopipes(up
topipesizesforwhichthepreformedsectionsaremanufacturedbythemanufactu
Theinsulationmaterialshall satisfythefollowingrequirements:-
i) For thermal application on pipes.
S.No Minimum
Material Density(Kg/cu.m)
1 Resin bondedglass wool 32
2 Expandedpolystyrene
20
(TF)
3 PolyvinylNitrilefoam 55
ii) For thermal insulation of ducts:
Material Minimum
S.No Density(Kg/cu.m)
Resin bondedglasswool 24
1
PolyvinylNitrilefoam 40
2
Application Minimum
Material
Thickness Density
(Kg./Cu.M)
The specification for resin bonded glass wool insulation & resin bonded
mineral wool insulation shall conform to IS 8183 as amended up to date.
The specification for expanded polysterene shall conform to IS-4671 as
amended upto date.
Expanded polystrene insulation of density not less than 20kg per cu.m.
shall be used.
The thickness of insulation shall be as indicated below unless specified
otherwise in the tender specifications.
A. Compressor:
b) Low suction pressure (LP) safety (cut- out) to stop the compressor
automatically, in case suction pressure falls below a pre-set value.
Thissafety shall operate when the suction pressure falls below the set
point.Automatic resetting shall be provided for this safety, with
adjustable cut-in and cut-out pressures. This safety shall be
used forpumping down the system for shutting off the refrigeration plant.
B. Condenser
The safety control for a condenser shall comprise a safety pressure relief
valve on the shell.This shall operate to relieve the pressure at the set point
without prior leakage. For small condensers, a fusible plug may be
provided to meltata predetermined temperature.
C. Chiller
b) Flooded type of chiller shall beprovided with safety pressure relief valve.
8.20.3 Refrigerant Flow Controls
A refrigeration plant shall be provided with controls, necessary for
starting,stopping and modulating the flow of refrigerant in the plant so as to
satisfy theload requirements.These comprise solenoid valve, thermostatic/
Electronictype expansion valve, float valve, compressor capacity controls
etc. and otherspecialcontrolsifspecifiedinaparticular work.
A. Solenoid Valve
i) Hotgasdefrosting:Normallythissolenoidvalveshallremainclosed, but
it shall open up to feed the evaporator with hot gas fordefrosting
when required,especiallyin cold storageapplications.
c) Solenoid valves shall be direct acting in smaller sizes and pilot operated
for larger sizes, as required. The size of the valves shall be determined
by the desired flow rate of refrigerant through them and the pressure
drop across the same (and not by the size of the refrigerantline).
C. Float Valve
Float valve shall be provided in refrigeration plant with flooded type chiller
formaintaining the liquid level in chiller under all conditions ofload at a
ratecommensurate with the rate of vaporization. This can be provided
either onlow pressure side or on high pressure side.When provided as low
side floatvalve,thisshallbelocatedasapartofthechilleroraccumulator.
8.20.4 System Controls
c) In the case of PTAC type units, the control of the units is affected
through snap acting room thermostat.
j) The heater banks intended for reheating during monsoon shall form
part of the heaters required for winter heating (where winter heating is
specified). Necessary change-over switch shall be provided as part of
the system wiring to change their control by thermostats or humidistat
as required.
8.20.5 Operational Controls and Interlocks
c) Pump shut down shall be provided through low pressure (LP) safety
irrespective of the status switch position, auto/manual.
e) The compressor motor shall be able to be started or run, only after all
the safeties are satisfied.
g) Where only the blower motor and not heaters is connected to standby
generating set in any particular application, a timer shall be provided,
such that the heaters may get energized, only after a period of time,
after the blower is run.
h) In the event of signal from high limit safety of heaters the power supply
to the blower motor and the heater bank shall automatically and
instantly be switched off.
i) The power supply to AHU shall be cut off on receipt of a signal from
the Fire Alarm System.
B. Humidistat
a) Humidistat shall be provided with air handling unit for areas, which
require humidity control. One humidistat shall activate the reheat coils
in case the space humidity rises beyond the preset limit. Another
humidistat shall energize the humidifier when the humidity falls below
the preset limit. These humidistats shall also de-energize these
devices when the desired humidity is reached.
b) 0.85 kg/ sq.cm. Where VSD (to control chilled water flow) is provided,
the AHUsshallbeprovidedwith2waydivertingvalve.
provision to switch overto the manual mode as and when required. The
system shall comprise ofdedicated Variable Speed Drives (VSDs) designed
for HVAC applications toaccept 2 feedback signals (from temperature
sensor installed in the AC
area and programmable timer controller) and have 2 programmable set
points(in side temperature conditions, and 60% of the normal CFM condition
as stated above) using HVAC terminology, to regulate the
speed ofthe AHU motors in response to the variations in load
and filter cleanliness conditions to maintain temperature and Air flow
differential in supply and exhaustconditions.In case, any additional sensor
(s) including wiring etc. are required to meet the system requirements.The
VSD control shall have:
III. Displays in user‘s friendly Alpha Numeric Characters for all operating
parameters, programming parameters and faults.
a) The system shall also comprise a suitable programmable timer & PLC
with required electronic components, to allow 2 feedback signals
(Temperature & Minimum CFM) to be passed on to the VSD during
the day hours. In the night hours, only one signal from the
programmable timer shall go to the VSD to run it at pre-determined
reduced speed. The room/ space air temperature and air flow shall be
sensed by a temperature and air flow transmitters, which shall
generate suitable DC signal to provide feedback to the VSD, which in
turn shall regulate the speed of the AHU fan to maintain the designed
conditions as described above.
b) The VSD System shall function to supply variable chilled water flow in
the secondary circuit of air-conditioning system in response to the load
variations including that due to variations in ambient conditions to
maintain the inside designed temperature conditions. However, under
any circumstances, the secondary chilled water pump speed shall not
fall below the 30% of the nominal speed or any other suitable minimum
speed as per the system requirement. The VSD shall have the
provision to switch over to the manual mode as and when required and
facility for the manual speed variation from VSD itself. The system
shall comprise of dedicated Variable Speed Drives (VSDs) designed
for HVAC applications to accept two feedback signals (from differential
pressure transmitters installed across the two farthest, most significant
AHUs of the zone to select either maximum of the two or average of
the two (as selected by the user) feedback signals using HVAC
terminology, to regulate the speed of the secondary chilled water
pump motors in response to the load variations. In case, any additional
sensor (s) including wiring etc. if required to meet the system
requirements, The VSD shall have:
I. RFI(Radiofrequencyinterference)FiltersforEMC(Electrom agnetic
compatibility)compliance.
II. Voltage Vector Control technology to generate advanced
sinusoidal outputvoltage, 100% trueRMS value of the fundamental
III. TheVSDsshallhaveD.C.linkreactors/harmonicfiltersintegratedtomi
nimize power line harmonics. There shall be reactors in both the
positiveandnegativerails.
VI. TheVSDshallincludeAutomaticMotorAdaptation(AMA)tooptimize
motor performance, improve start capabilities and compensate for
motorcable variances. The AMA shall be carried out at motor
standstill with noneedfordetachingthepumpfrommotor.
X. Builtin energymeter.
XI. inruntimecounter.
XII. Localcontrolpanel(keypad)
III. Protections against input transients, loss of A.C. line phase, short
circuit, ground fault, frequency converter over temperature.
V. ON indication
d) Demand based control ties the operation of all the equipment to end use
requirements- actual space requirement in single building HVAC
applications but this does not mean that chillers and cooling towers
operate directly from the room temperature sensor. Rather in this control,
all the components of air conditioning plant are directly coupled and
work as a single system.
e) With variable-speed equipment and network capabilities, the long-
standing dictum that equipment must be decoupled to operate
effectively has been reversed. Direct coupling leads to simpler, more-
efficient operation. It is intuitive that coordinating the operation of a
chiller plant and chilled-water distribution network is required to
achieve the highest overall cooling system efficiency. When cooling
needs to adjust in response to space conditions, demand-based
control coordinates the operation of all elements to provide cooling
where it is needed according to predefined efficiency relationship.
a) The main switch board in the A.C. plant room shall be floor mounted, free
standing cubical type and shall be TTA type factory built fabricated. It
shall be suitable for termination of the incoming cable(s)/ bus trunking
from top/ bottom. The switchboards in air handling unit (AHU) rooms shall
be cubical design wall mounted/ floor mounted as feasible at site and as
approved by the Engineer-in-charge.
a) The capacity of switch gear, starters etc. shall be suitable for the
requirements of loads fed/controlled. Starting currents shall be duly
considered in case of motor loads.
b) MCCBs shall be used upto 630 A. ACBs shall be used for 630 A and above
ratings.
c) Switch boards controlling motors shall house starters for motors, unless
otherwise specified. Independent single phasing preventors for each such
starter shall be provided. The starter and SPP shall be located adjacent to
the controlling switch gear.
d) One volt meter with selector switch, a set of indicating lamps and fuses for
voltmeter and lamps shall be provided at each switchboard. One ammeter
with CTS, and selector switch shall be provided with each motor starter.
Instruments shall be flush mounted with the panel and have a glass index
not higher than 1.5. The instruments and accessories shall be provided
whether or not specifically indicated in the tender specifications.
e) The fabrication of switchboard shall be taken up only after the drawings for
the fabrication of the same are approved by the Engineer-in-charge.
g) The layout of bus bars and cable alleys shall be designed for convenient
connections and inter-connections with the various switchgear. Connections
from individual compartments to cable alleys shall be such as not to shut
down healthy circuits in the event of maintenance work becoming necessary
on a defective circuit.
h) Care shall be taken to provide adequate clearances between phase bus bars
as well as between phase bus bars, neutral and earth.
i) Where terminations are done on the bus bars by drilling holes therein, extra
cross section shall be provided for the bus bars. Alternatively, terminations
may be made by clamping.
b) The number and size of the control cables shall be such as to suit the
control system design adopted by the Contractor.Runs of control wires
within the switchboard shall be neatly bunched and suitably
supported/clamped. Means shall be provided for easy identification of
the control wires.
a) The motor starter shall conform to IS: 1822 ―Motor starters of voltage
not exceeding 1000 volts and shall be air insulated and suitable for
415 volts + 10%, 50 Hz., 3 phase AC supply. Enclosures shall have
protection of IP 42 for Indoor applications and IP 55 for outdoor
applications. Starters shall be rated for intermittent duty. Starting
current should not exceed two times the full load current.
b) The starter shall be mounted on the main electrical control panel/ unit
mounted/ self-mounted as specified.
a) All motors shall have a minimum acceptable nominal full load motor
efficiency not less than IE3 class as per IS 12615 for Energy Efficient
motors.
b) Motor name plates shall list the nominal full load motor efficiencies and
the full load power factor.
c) Motors should be installed with soft start energy savers and Variable
Speed drives based on the application required.
a) Differentialpressureswitches-air:
i) They shall have field adjustable set-point capability for the specified range.
ii) They shall provide a built-in switching differential at the
set- point over the specified range.
iii) Switches shall be piped to fan discharge except where fans operate at
less than 25mm WC (water column), they shall be piped across the
fan. Maximum pressure rating shall be atleast 300mm WC.
iv) The electrical contacts shall providedry contacts as specified and
shall be rated for at least 300VA pilot duty@240VAC.
ii) Control relays and analog output transducers shall be compatible with
controller output signals. Relays shall be suitable for the loads
encountered. Analog output transducers shall be designed for
precision closed loop control with pneumatic repeatability error no
greater than 2%.
8.24 Level Measurement
a) LevelSwitches
b) Level Sensors
c) AutomaticControlValves
Following standard & guidelines shall be adopted while designing the HVAC
system.
System shall comprise of solar flat plate collector, collectors stand assembly,
SS316 Stainless Steel insulated hot water storage tank with closed circuit heat
exchanger and various other components. Suitable Number of Flat Plate
Collectors should be installed for each Solar Water Heating system. Each Flat
Plate collector should be of at least 100 LPD capacity. These technical
specifications shall be read along with the General Conditions for all E&M
works given under subhead C-B.
Collector box shall be made of Aluminium sections only. Type, grade, size,
workmanship and finish of the material used shall be as per section-2 of IS: 12933
(Part-2)/2003. The minimum thickness of Aluminium shall be as under:
9.1.3 Absorber:
Absorber shall consist of riser, header and sheet for absorber. Type, grade, size,
workmanship and finish of the material used shall be as per section-3 of IS: 12933
(Part- 2) / 2003. Sheet for absorber shall be made of copper only. Riser and
header assembly designed for working pressure up to 2.5kg/ Square Cm, shall
be tested for leakage at a minimum hydraulic pressure of 5 kg/ Square Cm.
insulation and minimum 0.48 square meter. degree C /W for side insulation. This
shall be derived after determining thermal conductivity (K) value at 100 degree C
mean temperature in accordance with IS: 3346. Collector box insulation shall
conform to sec.4 of IS: 12933 (Part-2)/2003. Aluminium foil shall be used for covering
the back as well as side installation.
9.2.1 Material:
Insulated hot water storage tank shall be non-pressure type and made of SS
316 grade stainless steel of IS:1570 (Part-5)/1985) (Reaffirmed 2004), TIG/MIG
welded, minimum sheet thickness shall be 16 SWG. The storage tank shall be well
insulated and large enough to hold/store about two days’ supply of hot water.
9.2.2 Insulation:
Solar water heating system shall be insulated with 100 mm thick Rock wool, 48
Kg/m3 density, 22 SWG Aluminium cladding. Alternatively, 50 mm thick CFC
free thermal grade PUF insulation, 32Kg/m3 or higher density may be used.
PUF insulation could be pre-extruded type fitted with FRP exterior cladding or
alternatively injection moulded in a twin walled steel tank and PPE end cap.
a) Electrical back up
Heat Exchanger of SS 304 material of coil type or any other suitable type
for thermosyphon operation complete in all respects with all accessories as
required shall be provided.
d) Suitable capacity SS304 makeup water tank along with piping and valves as
required shall be provided.
e) Temperature Gauge: Dial type, duly calibrated and suitable for temperature
range from 0 degree C to 120 degree C and shall be provided.
I. The Contractor shall furnish complete and satisfactory type test reports for
each size / type of solar flat plate collector as per contract specification from
any govt. laboratory. Type test reports shall include all the tests listed in IS:
12933 amended up to date.
II. Civil work for foundation, grouting etc. of the system complete as required is
in the scope of this work. While erecting the equipment at terrace, contractor
shall make sure no damage is done to water proofing and civil structure,
location at which grouting is required shall be sealed with high quality water
proofing compound. Installation shall be as per guideline issued by
MNRE/Manufacturer’s standards, whichever is stringent.
9.5 Warranty
All the solar water heating system shall be warrantied for a minimum period of
5 years from the date of installation and commissioning against any
manufacturing and design defects.
10.1 The brief scope of work shall include Planning, design & preparation of
drawings, supplying,installation,testing&commissioning of LAN and Wi-fi
networking cabling system and subsystem componentslike OFC/CAT6A
cables, termination hardware, supporting hardware, necessary
software,licenses and other required to supply, and to install a complete
cabling infrastructurefor the entire campus with backbone and Wi-fi
switches. The total system has to be supplied, installed, tested
andcommissioned in complete manner to have a fully functional system, as
required. If anyitem required to make the scheme functional, is not
specifically mentioned in the scope and specifications, the
sameisdeemedtobeincludedwithinthe scopeofthis tender. These technical
specifications shall be read along with the General Conditions for all E&M
works given under subhead C-B.
10.1.1 GeneralScope
a. The LAN, Wi-Fi network system shall be designed with
100G/40G/10G/1G fiberbackbone with 100% redundancy at Core level
switch and fiber backbone. Thenetwork shall be used for other services
like IP-PABX system, CCTV system,
Accesscontrolsystem,AVsystem,Videoconferencesystem.
b. Agency shall design the sizes of fiber optic cables, capacities of Core
switches, Distribution switches, Access switches, Wi-Fi Access Points,
required firewall, suitable size racks, required hardware and software
including licenses for all the buildings of the campus as per requirement.
10.1.2 InternalLAN,Wi-Finetwork.
a. The Internal LAN, Wi-Fi network system shall consists Main routers,
Firewalls, Coreswitches with 100% redundancy at fire wall, distribution
switches, access switches,suitable size racks, Wi-Fi indoor access
points, required hardware, software withlicenses (for not less than 5
years from the date of completion and taking over ofthe whole project),
Cat6A cabling for all data points, IP-PABX points, CCTV points,Access
control points, video conferencing Hospitals and adjoining Hospitals. The
further detailson IP-PABX system, CCTV & Access control system and
f. The Server shall have Fire wall protection, Bandwidth management &
required client Access license.
i. WiredLAN access
ii. WirelessLAN access
iii. Voice communications servers and IP/SIPend points
iv. IP-based CCTV/Surveillance Cameras
v. Ipbased Access Control System/SCADA System
10.1.5 The specifications for items in this section, applies to the following:
10.1.6 Fiber optic cable can be installed inside buildings using the same
methods as coaxial cable or twisted pair; however, the following
guidelines should be observed:
b) Donotpullfiberopticcablesoverexistingcables.Thefrictioncouldbeexces
sive and cause cable damage. The cables may also become
entangled,resultingindamagetothefiberoptic cable.
d) Do not pull the cable around sharp corners, such as support brackets.
Provideadditionalcrush /mechanical protectioninhigh-
riskenvironments.
a) All Copper & fiber components should be from the same OEM.
g) All Single Mode FO Cables, Patch cords and Pigtails should be made
up of Bend In sensitive Fibers
h) Allthe copper cables, Patch cords, Fiber Patch cords should be LSZ
Honly
i) All the passive components shall have their Testing reports from the
OEM withBatch No. and all standard parameters. There shall be the
proper ferruling andNumbering on the Cat 6A/fiber cables. There shall
be proper dressing of the cables and equipment management in side
the racks.
10.1.8 ActiveComponents
The overall physical architecture of campus LAN backbone network shall consist
of below elements.
a) Core Layer: The core layer shall be responsible for aggregating all the
traffic residing andflowing in the below distributed layer or network.
The core switch will be hosted inthe Data Centre that will provide
connectivity between Wi-Fi traffic, surveillance,VOIP& user
applications hosted inside the DC and field devices
installed/positionedin the campus network. The core switch will be
installed in redundant manner, withredundant&hot-
swappable fan & Power supplies.The multiple corering will connect to
Data Centre Hospitals and adjoining Hospitals & will be
foundational network over multiple or single of 100/40/10 Gbps link
using single modefiber.
10.2 WirelessNetwork:
a) Wireless network shall be based on latest bandwidth (802.11 a/b/g/n)
compliant and supporting multi users covering various in door and
latest band width(8 02.11ah)compliant for out door locations or better.
e) Wirelessaccesspoints&ControllerforWi-
Ficonnectivityshouldhaveradiostosupport2.4Ghzand5Ghzbandina4X4
:4Mu-MIMOconfigurationwithsupportfor 802.11 a/b/g/n/ac Controller
shouldbe AI driven on premise or cloud-based controller. The
controller should be based
on Micro Services based Architecture. The solution should support
802.11 acprimarily.
10.3 NetworkSecurity
a) Network security can go beyond conventional
anomalydetectionbyharnes singthepower of network traffic flow data.
Real-time situational awareness of all the users,devices, and traffic on
network shall allows to respond to threats quickly and effectively.Thus,
it can detect and protect against a wide range of attacks with
continuous monitoringand intelligence. Traffic flow analysis for all
connected devices to proactively get detailsof security threat vectors.
This shall include details like IP address of sender / receiver,alongwith
basic parametersthetime,date,and size of network transaction.
GENERALARCHITECTURE:
No of Cores: 6
Attenuation: 1310/1550
Should have Slide type drawer structure, with Screw fit lock
design.
1U Size: 490x340x45mm
Cat6A 23 AWG Solid Conductor UTP LSZH Cable roll of 305 Mtr,
in accordance to ANSI/TIA 568 C.2 and ISO/IEC 11801 2nd ED
(Class EA), 500 Mhz tested, Flammability IEC 60332-1-2 IEC
60754 -1,2 & 3, IEC 60134-2, RoHS Certified and UL & ETL Listed
Cable.
Mechanical Test
Breaking strength400N.
Electrical Test
Each Jack should be supplied with one Strain relief boot and
additional bend limiting boot and a cable tie for proper holding of
cable to the JACK.
Number of conductors: 8
Cat 6A patch cord plug to have round cable holder and strain relief
boot to avoid bending.
Plug design should be with 3 Pin internal lock for cable guide
and holding the plug with cable to provide maximum tension
Panel should be supplied with earthing wire and earther lug with
each panel
10 Faceplate
Should support Work with both Flush and Wall mount box
Number of conductors: 8
Degree of protection: IP 20
Number of positions: 8
Pollution degree: 3
Warranty:
Owner seeks warranty for the installed cable plant from the OEM equipment
supplier. Biddershall ensure that the OEM norms for supply, installation,
testing and documentation as specifiedby the OEM supplier shall be
adhered to, provided those are in line with TIA / EIA standards andOwner
requirement specifications. The warranty shall be provided by the OEM
vendor. The duration of the warranty shall be for a minimum of 25years and
shall cover the system performance, application assurance and the costs of
the supplyofcomponents andinstallation.
10.5 SpecificationsOfActiveComponents:
Sl.
Detailed Technical Specifications
No
A Solution Requirement
There switch should not have any single point of failure like power
supplies and fans etc. should have 1:1/N+1 inbuilt level of
redundancy
100K IPv4 routes and 100k IPv6 routes entries in the routing table
with 48000 Multicast Routes
C Layer2 Features
D Layer3 Features
E Availability
F Quality of Service
Switch should support for different type of QoS features for real
time traffic differential treatment using WRED and SP Queuing
G Security
Switch should support for Role Based access control (RBAC) for
restricting host level network access as per policy defined
H Manageability
Switch should support for basic administrative tools like Ping and
traceroute
I IPv6 features
Sl.
Detailed Technical Specifications
No.
Architecture
Connectivity
Switching features
L3 Features
Support for 64K IPv4 and 64k IPv6 routes and 24K multicast
7
routes
DC features
Security
support for various ACL/ filters like port based, Vlad based and
17
routed filters/ACL
Quality Of Service
19 802.1p, WRED
Management
SNMP v1, v2, v3, RMON enabled, SSH, telnet, CLI and should
20
have out of Band Management port
Certifications
Sl.
Detailed Technical Specifications
No.
3 The Switch should have 2GB DRAM and 2GB internal Flash
All interfaces should provide wire speed forwarding for both Fiber
6
and copper modules
10.8 ITAM
Sl. No Specifications
Integrated NIC
COTS Compliant
Sl.
No Specification
SN Specification
1 Should have a Artificial Intelligence (AI) driven, Cloud based
Controller
2 The Solution should support 802.11ac primarily and should be
backward compatible to 802.11n/a/b/g. The solution should also
support 802.11ax as per requirement.
3 The solution should support Location Based services via
Bluetooth low energy and should also support Asset Tracking.
4 The solution should support Guest Portal
5 The solution should support WIPS, Rouge AP detection and
Honeypot AP detection
6 Should be able to provide insights based on Time to connect,
successful connect, coverage, capacity, AP Uptime, Roaming
and throughput.
7 should be able to integrate with various authentication
mechanism including the RADIUS servers, etc.
10.11 NMS
Minimum Specification
SN Requirement
IT infrastructure Proposed Network Management system
Monitoring shall monitor key metrics like availability to
measure SLA’s. Following are key
functionalities that are required which will
1 assist administrators to monitor network
faults & performance degradations in
order to reduce own times, increase
availability and take proactive actions to
remediate & restore network services.
The proposed tool should be able to
monitor various operating system
2 parameters such as processors, memory,
files, processes, file systems, etc. where
applicable.
Device Discovery The proposed solution must automatically
discover management elements
connected to the infrastructure and map
3
the connectivity between them. Solution
should provide centralized monitoring
console displaying network topology map.
Audit The system should be able to clearly
identify configuration changes and
4
administrators should receive an alter in
such cases
Minimum Specification
SN
Requirement
Network Network performance tool should provide
performance Network bandwidth usage, Packet loss
1 rate, Interface error rate, High CPU or
memory utilization, Number of tcp
connections is anomaly high for this day of
11.1 IPTelephonyNetwork
The scope of work covers Planning, Design, preparation of Drawings,
Supply, Installation, Testing and Commissioning of IP Based PBX of
initial capacity of 1000 Telephones & expandable up to 2000 telephones
shall be located at server room. All the Telephones in the Complex will
be IP Based and will use theexisting LAN Network for the communication
within the complex (inside buildings &
inbetweenbuildings)aswellasforoutsidethecomplex.AllRackPanelsofIndiv
idualbuildings shall be connected to Central PABX (private automatic
branch exchange) systemthrough Optical Fiber Cable IP based voice
communication system with PRI (Primary
RateInterface)Trunklines(30channels)withclipfacilityforminimum500IPus
erslicensefor 5 Years.Theoutlets areaspertheapproveddrawings. These
technical specifications shall be read along with the General Conditions
for all E&M works given under subhead C-B.
b. Two types of phones will be deployed across campus as per end user
requirements. One isbasicfeaturephoneforall usersandExecutivephones
for doctors/ senior staff.
c. The scope of work also includes the provision of the IP based telephones
in the followingbuildings:
I. Hospital Building
II. Mortuary
III. Sub Station
IV. Security Gate
V. A.C PlantRoom.
VI. MGPS Room.
g. The Scope and purpose are to provide the voice to all the users within
the campus including IP based operator console, In-skin Voice mail for
all the users & access to call outside the campus through analog trunks
or PRI (Primary Rate Interface) trunks via local service provider.
h. The system should have minimum 8 port in-skin voice mail to play the
user defined message during the incoming call through the analog or PRI
(Primary Rate Interface) trunk.
i. The hardware & software required for the system including IP Phones.
Servers, gateways, workstations, IP based Operator console, racks,
online UPS, Access switches, gateways for analog as well as PRI trunks
will be in the Contractor’s scope.
k. The project is on design and build basis and must cover the entire
campus and building. Every individual staff should have telephone facility
to communicate within the campus &outsidethecampus.
11.2 TentativeinventoryfortheIP-PABXpoints:
BuildingName IPPABXPts.
Basement 5
Ground Floor 86
Theaboverequirementisindicative,thecontractorshouldplan,desig
nand submittherequirementalongwithlayoutdrawings
forapprovalandexecution.
Mobility
The system should have Call Back feature. If the user dials
his own extension from predefined number (mobile/landline)
then system should disconnect the call and then system
should call the user to provide the dial tone so that user can
make intercom or PSTN calls.
The system should have Call Through feature. If the user
dials his own extension from predefined number, then
system should provide dial tone to make intercom or o/g
calls.
The system should have Flexi Call (Forking, reach-me-
anywhere) feature. Users should be able to receive calls on
any of their phones, from almost anywhere. An incoming call
rings on all or specific phones until the user answers the call.
The user can transfer the call, establish a conference, and
so on, whether the answering device is an internal device,
an external phone, or a cellular handset. If the answering
phone is an external device, the call automatically becomes
an authorized mobility call.
The system should support SIP Client on smart phone.
SIP Endpoints
All SIP phones must support the standard SIP protocol. No
proprietary protocols are allowed to be used.
SIP phones must support the configuration of programmable
buttons with functions such as Break-in, Conference call,
Deflect, silent monitoring and more.
SIP phones must work in conjugation with the following
applications:
1. Contact Centre (Agents Phones)
2. Attendant Console
3. Managed Audio Conferencing
4. Managed Video Conferencing
5. UC clients
ACD
System should have built in Automatic Call Distribution
(ACD) with following features:
Busy ACD Group announcement
Hunt Group Release
IVR-ACD
Log In / Log Out
Multiple Announcements:
1. Mandatory announcement - All incoming callers to an
ACD/HUNT group must be able to hear an introductory
announcement in its entirety usually explaining about the
company, product, or campaign.
Zone Page
Barge In
Wake up
Extension Features
Answer Call Waiting by Transfer
Auto Set Relocate
Auto-Answer
Automatic Disconnect
Automatic Number Identification (ANI) Display
Browse Personal Directory
Busy Lamp Field
Call Forward All
Call Hold
Call Log
2 Emergency communication
Agent Board
Answer
Hold
Retrieve
Hang Up
7 Specifications for Self-Survivable Gateway:
Gateway should have minimum 96 analog/CO ports. Gateway
should be from the same OEM of IP telephony system
Voice Processing – voice codecs: G.711, G.729A, G.723.1, etc.
and echo cancellation: G.168 with 64ms echo tail; dynamic jitter
buffer; voice activity detector (VAD)
Call Handling – configurable dialing plan
Fax Processing – T.30, T.38 fax relay
User Features – caller ID, call forward, call transfer, hotline,
CRBT, do not disturb, speed dialing
Protocol – SIP (RFC3261, MGCP etc.)
Standards – caller ID detection (FSK)
ii. The cameras will cover important points in campus and internal areas of
buildings.The system will be designed to cover the areas keeping inview
these curityrequirement in consultation with the Engineer-in-Charge.
iii. The CCTV and Surveillance System shall control and monitor from
hospital building in the Campus as per requirement. All the buildings shall
have IP Based Dome Cameras, Bullet Cameras and PTZ Cameras for
surveillance. The types of cameras & locations of various Cameras
indicated here in are minimum to be provided. However, during detailed
designing, if required and found necessary, thetype/ ratingoftheCameras
shall be upgraded.
iv. The hardware required for the system including Servers VMS, Recording,
Work stations, Monitors, Cat 6A cables & Patch Cables to connect the
camera tonearest PoE enabled LAN point, Cables, connectors, conduits,
power supplies etc.are inthescopeofwork.
v. The complete LAN networking required for the CCTV & Access Control
System are commonfordata andshall be covered inLAN, Wi-fi Networking
subhead.
iii. The cameras will cover important points in campus and internal road
junctions,entrance and exit gates, entrance porticos/porch of all
buildings. The system will bedesigned to cover the areas keeping in view
the security requirement of the ESIC Hospital authorities.
iv. All the cameras shall be with IP-66 Housing with Junction box,
IndustrialGradeSwitchesetc.withweatherproofhousing.The existing LAN
network switches shall be used for CCTV connectivity.
vi. For Camera Monitoring and Control, required number of 65-inch Full HD
LED Monitors shall beprovided. All the cameras shall be live on using
monitors. One shall not have more than 36 camera6x6Grid. Min 02
concurrent workstation license shall beoffered and no of Work stations
and Monitors shall be got approved from Engineer-in-charge.
viii. Trays are provided for the run cable trenches which is with in supply of
the contractor.
iii. Network connectivity for cameras having distance more than 75 meters,
12.1.3 Specifications
Fig-1
Features Specifications
1) Camera type Dome
2) Housing IP IP66
3) Impact Protection IK10
4) Camera resolution 2 MP (1920 ×1080)
5) Image sensor 1/2.8"or larger Progressive scan CMOS
6) Min-illumination Color0.05 lux
@F1.6(AGCON);B/W0.001lux@IRON
7) Focal Length 2.7 -13.5mmVarifocalMotorized
8) Shutter Speed 1/3s~1/100,000s
9) Multiple streaming
Quad Stream
Main Stream 2 MP,
1080P(1920x1080),720P(1280x720),
SubSteam
720P(1280x720), VGA (640x480), QVGA
(320x240)
Frame Rate 30fps
10
11 Digital Zoom should have the capability to digitally
zoomed in web browser by selecting the area
using mouse
12 WDR Yes
13 IR InbuiltIRLEDswithIRdistanceupto40mtrs
34 Power D12V/POE(IEEE802.3af)
Note: Cameras with Audio recording facility along with 128 GB memory card shall be provided in
the hospital counselling rooms.
Features Specifications
1. Cameratype Bullet
2. Housing IP IP66
3. Cameraresol 2 MP (1920 ×1080)
ution
4. Imagesensor 1/2.8"or larger Progressive scan CMOS
5. Min- Color0.05 lux
illumination @F1.6(AGCON);B/W0.001lux@IRON
6. FocalLength 2.7 -13.5mmVarifocalMotorized
7. ShutterSpee 1/ 3s~1/100,000s
d
8. Multiplestrea Quad Stream
ming Main Stream 2 MP,
1080P(1920x1080),720P(1280x720),
SubSteam
720P(1280x720), VGA (640x480), QVGA
(320x240)
9. Frame Rate 30fps
10. should have the capability to digitally
DigitalZoom
zoomed in
webbrowserbyselectingtheareausingmouse
11. WDR YES
12. IR InbuiltIRLEDswithIRdistanceupto40mtrs
13. Day&Night IRcutfilterwithautoswitch
14. Day/ Auto/Color/Black &
NightSwitch white
15. Noise 3D DNR
Reduction
16. Video H.265+/H.265/H.264+/H.264+/MJPEG
Compression
17. Bit Rate 32Kbps to 8Mbps
18. Image Saturation, Brightness, Contrast,
setting Sharpness, AGC, White balance
adjustable by client software or web
browser
19. Edgeanalytic Motion Detection, sound detection, Video
s, Alarm tampering alarm, Network disconnected, IP
Trigger address conflicted, Illegal login, File upload via
FTP or E-mail, SD/SDHC/SDXC recording at
event triggers.
20. Protocols TCP/IP, HTTP, DHCP, DNS, DDNS, RTP/RTSP,
SMTP, NTP, HTTPS, FTP, PPPOE,
12.2.3 2MPNetworkIRPTZCamera
S. No Features Description
Cameratype IR PTZ
Material Metal
1. No. of Pixels 1920×1080(2MP)
(H×V)
2. Housing IP IP66, TVS Lightning 4000 TVS, Surge and
VoltageTransie nt Protection
3. Impact Protection IK10
4. Certificate CE,FCC,UL, ROHS, IK10, RoHS
5. ActivePixels 1920x1080
6. Scanning system Progressive
7. ImageSensorTyp 1/2.8"or larger ProgressiveScanCMOS/CCD
e
8. Illumination Color: 0.05 Lux @ (F1.6, AGC ON)
0LuxwithIR
9. ShutterSpeed 1/1 sto 1/30000 s
10. WDR TrueWDR 120dB
12.2.5 VideoManagementHardwareSpecification.
12.2.6 VMSSoftware:
rt ChildTopology)
3. CameraDiscovery Auto
4. CameraType/Comp MultipleCameras,MultipleCompressionsup
ression port
5. OtherSystemSupp AccessControl,Intrusion,VideoSolution
ort
6. Redundancy 1+1/ N+MFailoversupport
7. Alarm Event Pre-eventandposteventvideodisplay
8. Playback SmoothreverseandSynchronousplaybacka
crossNVRs
9. SequentialPlaybac Incident management mode allows creating
k apackageofclipsmultiplecamerasatdifferent
timesthatcanbeplayedbacksequentially
10. VideoAnalytics Supporttobeprovidedforallthevideo
analytics
11. Surroundingcamer Surrounding cameras mode with presets,
aview makes followingsubjectsofinterest simple
andefficientbyallowingthe
nearestcameraofinterest
tobeimmediatelyin view
12. PTZControl Innovative“One-
Click”or“MouseDrag”3DPTZcontrol
13. LowBandwidth Enriched video viewing experience
through intuitive videorendering engine
optimizes CPU utilization by altering
thevideoframerateforlowbandwidththrottli
ng
14. GPURendering GPU rendering support for H.264 and
H.265 decoding up to 60frames per
second (1080p camera) with smooth
display on
4Kmonitorsreducesthenumberofworkstati
ons needed
formonitoringlargesiteswith30+cameras
15. MonitorControl Monitorcontrolallowscontrollingallmonitors
fromasingleclient (MonitorWallcontrol)
16. RemoteView Remotemonitormodeallowssharingand
controllingaremote
monitorwhilestillviewinglocally
17. VMS in VMS MultiplesVMSintegration to bepossible
18. Privileges Role-basedoperatorprivileges
19. AD Support SupportforActiveDirectoryuserauthenticatio
n
20. E-Map Web-based maps with drag-and-drop
camera setup, easycross-
sitenavigationandHTML5livevideopop-
upandinstant
playback,allowquicksituationalresponse
12.2.7 Workstation:
Sl. CPUSpecifications
No
1 TotalCores 4
2 TotalThreads 8
3 ProcessorBaseFrequency 3.40GHz or better
4 Cache 8MBCache
5 BusSpeed 5 GT/s
6 TDP 77W
MemorySpecifications
1 ProcessorGraphics Intel®HDGraphics4000 or
better
2 GraphicsBaseFrequency 650MHz
3 GraphicsMaxDynamicFreque 1.15GHz
ncy
4 QuickSyncVideo Yes
5 3DTechnology Yes
6 FlexibleDisplayInterface Yes
7 ClearVideo HDTechnology Yes
8 No ofDisplaysSupported 3
13.2 AV system including Video Conference system shall run on UPS power,
which shall be drawn from the nearest UPS DBs.
<0.5%. DSP with band pass filters, Peak limiters. Front LCD
display with LED indicators, Menu and Volume control. Remote
power trigger, amplifier status monitoring using onboard
auxiliary ports, forced-air fans to prevent excessive thermal
buildup Balanced XLR,1/4' and RCA phono inputs. 2 nos. of 4-
pole Speaker on or binding posts for speaker connectivity.
Streamin H.264 AV over IP Encoder with USB for record Video scaling at
g eitherinput or output, allows seamless switching from any
Software source, at
anyresolution,toanydisplayorprojector,whilepreservingvideofide
lity. Device can still be powered locally from 12VDC
allowingforeasyrack-mountable.ShouldhaveRS-
232andIRportsforcontrolling3rdpartydevices.UnlimitedScalabilit
yHDMIoutputinterface allows easy installation with local display
such as desktop PCapplications.DigitalVideoInput:HDMI,DVI-
D,Dual-ModeDisplayPort(DP++),RGB/VGA, DVI-DandDual-
ModeDisplayPort(DP++) aresupported through a passive
adapter Formats: HDMI, DVI-
D(throughadapter),HDCPcontentprotectionsupport,RGBHV,YP
bPr Latency: Up to 175 ms at 30 fps. Should have analog audio
out (Stereo) HDMI OUT:HDMI video output (passive pass-
through fromHDMIIN)USBconnector
:OneUSB-Aforaudio/videostreamrecording.
4X2 4X2 4K@ 60 Hz, RGB 4:4:4 matrix switcher with 4 HDMI Inputs
Matrix and 2 HDMI Outputs. Supports HDCP 2.2, HDR, Audio De-
Switcher Embedding from each HDMI outputs, Front panel switching
WEB UI, External RS-232 control. Should include with all
necessary OEM Mounting accessories.
Wall Wall plate with Inputs 1 HDMI, 1VGA with Audio, 2K and 4K
Plate support, HDTV Compatible, HDCP Compliant etc., complete as
required.
And 10-bit per channel Deep Color with analog audio input.
USB 3.0(Type-C) output supports resolutions up to
3840×2160p@30fps or better.Shall be compatible with popular
OS platforms and software-based codec applications.
Presente Professional presenter with cordless protocol cordless range
r 100 feet.
HDMI HDMI /VGA/Audio/Microphone/HDBase T Cable for entire
/VGA/ projection system, and as per site requirement.
Audio/
Micropho
ne/
HDBase
T Cable
Chairma The Table top microphone shall be equipped with twin-
n / loudspeaker system guarantees a homogenous sound level in
Delegate the meeting room. The cabling of the units, which is done by
Micropho CAT6A cables and hidden connections can be optionally
ne Unit secured with strain reliefs for fixed installations. Microphone
with hidden cable connections, cabling via RJ45 sockets Strain
relief shall be available for fixed installations.
14.0 Technical Specifications for Sewage Treatment Plant (STP) The scope of
work includes Planning, design, preparation of drawings, supplying, installation,
testing & commissioning of Sewage Treatment Plant (STP) equipment including
Pump sets, cabling, hardware and other connected items install a complete STP .
The total system should be in complete manner to have a fully functional
system, as required. If any item required to make the scheme functional, is not
specifically mentioned in the scope and specifications, the same is deemed to be
included within the scope of this tender. These technical specifications shall be
read along with the General Conditions for all E&M works given under subhead
C-B.
d) The contractor shall set out the works in relation to original points, lines
and levels of reference required for execution of work. The contractor
shall be responsible for the correct positions of all parts of the works
and shall rectify any error in the positions, levels, the dimensions, or
alignment of works.
f) Trail Run: The contractor shall initially operate the STP for a period of
one month, after completion of work, for start-up/stabilization and for
satisfactory performance, by deploying experienced staff in two shifts a
day and the staff of the user department shall be trained for operation
of plants.
g) The designs of Civil/ Electrical/ Mechanical portion shall be based on
the latest relevant IS codes, CPWD specifications, PH Engg. Manual,
Indian Electricity Rules. Norms of pollution control board, Local By –
laws and WHO standards with up-to-date amendments and correction
slips and sound engineering practice. Side references along with
i) The tenderers are free to adopt the sizes to suit the design requirements
for final approval from State Pollution Board/ Local authorities.
j) The STP treatment plant shall follow satisfy the following requirements.
I. Efficient
II. Low power consumption.
III. Minimum maintenance.
IV. Minimum space requirement.
V. Self-operating system.
pH 6.5 - 8.5
PH 6.5 – 7.5
E-Coli Absent
Odour Unobjectionable
Material of CI
Construction
Type Belt type of 2-4" belt width and belt length suitable
for chamber depth below Liquid in O&G Tank.
Skimmer shall be Motor driven type with suitable
Motor and suitable speed reduction arrangement.
c) Equalization Tank: -
e) Air Blower:
Twin lobe rotary type air blower capable of delivering suitable capacity of
Air at designed pressure, driven through “V” belt or directly coupled/ through
flexible coupled to a suitable TEFC motor with accessories. The pressurized
air from blower shall be fed to Equalization tank, MBBR Tank-1, MBBR
Tank-2.
The process at MBBR tanks under aerobic conditions is that the rising
buoyancy of air bubbles generated during aeration and oxygenation can
promote the flow of the filler and surrounding water. When the airflow
passes through the water flow and the gap of the filler, it is blocked by the
filler and divided into small bubbles. In this process, the filler is fully stirred
and mixed with the water flow, and the air flow is fully divided into fine
bubbles, which increases the contact and oxygen transfer efficiency of the
biofilm with oxygen. Under anaerobic conditions, the water flow and the filler
are fully fluidized under the action of a submersible mixer to achieve the
purpose of full contact and degradation of biofilm and treated pollutants.
MBBR media is one kind of new bioactive carrier as a house for attached
growth bacteria in MBBR process. It works as carrier for the growth and
attachment of microorganisms and are directly put into the MBBR system,
the wastewater go through the suspended carriers in MBBR reactor,
Kaldnes media adopt scientific formula and blend some micro-elements in
the high polymer material, which microorganisms attach themselves to
submerged moving biofilm carrier, forming a biofilm. Air is transferred into
the water, mixing the media and water and providing oxygen to the bacteria.
The MBBR media biofilm absorbs oxygen and reduces organic and
inorganic material thus providing treatment.
The aerated mixture shall be transferred from MBBR tank to RCC Tube
settler Tank. The aerated mixture shall be passed through tube settler
media before it reaches to the bottom of the tube settler tank.
Suitable size and quantity, Coarse & fine bubble disc type diffusers, with
necessary accessories, of EPDM/Silicon with anti-fungal treatment, to
provide clog free oxygen for aeration at Equalization tank, sludge holding
tank, treated water tank and aeration tanks. Suitably designed UV treated
PVC tube deck settling media to be installed in Tube Settler Tank along with
retainer plates and suitable sludge removal arrangement either by pumps
or any other suitable arrangement. Poly aluminium chloride (PAC) dosing &
Polymer (PE) dosing shall be done at Tube settler media.
The sludge from the Tube Settler tank is to be removed from bottom of tank
and transferred to RCC Sludge Holding Tank (SHT). SHT shall have 6 days
sludge holding capacity. The sludge collected at bottom of sludge holding
tank shall be fed to filter press.
Filter feed pump, Screw pump for dewatering of sludge and Filter press of
suitable capacities shall be provided, suitable for operation on 415 ± 10%
volts, 3 phase, 50 cycles A.C. Supply.
The sewage water from tube settler tank is transferred to RCC clear water
tank of suitable capacity, for chlorination.
m) Disinfection:
The clear sewage water is then added with chlorine using chlorination pump
to kill the pathogens / E-Coli coliforms. The chlorinated sewage water
becomes clear water and now it is substantially free from organic
contamination, free from coliform bacteria.
The chlorinated water is disinfected and then fed to Dual media filter with
the help of centrifugal pump for removing suspended solids. After removal
of suspended solid from the treated water, it is passed through the Activated
carbon filter for polishing of treated water in terms of reduction in BOD,
Colour removal etc. The Dual Media Filter and Activated carbon Filter vessel
shall be constructed with MILD Steel-Epoxy Painted.
Ultraviolet dis-infection unit shall have over 99.9 % bacterial reduction from
inlet to outlet. The dis-infection chamber shall be constructed of SS 316L
steel. The UV lamp shall be of low-pressure mercury vapour type with hard
glass enclosure, the sockets shall be water tight & vibration resistant. The
lamp life shall be rated for 6000 hours. The UV unit shall have reactor,
cabinet housing, cabinet cooling, treatment chamber, electrical panel,
The treated water from UV Disinfection unit shall be led to treated water
tank before its disposal. The capacity of treated water tank shall be
designed accordingly.
b) Motors
Motors shall be as per IS 325, TEFC squirrel cage induction motors. Degree
of protection shall be IP55. Motors shall be suitable for supply voltage of
415 volts +/- 10%, 50 Hz, A.C. Supply. Insulation Class ‘F’ considering
temperature Rise as Class ‘B’. Efficiency Class IE2
c) Earthing:
All the Panels, pumps and other current carrying items shall be properly
earthed. Sizes of earth strips, wires shall be as per calculations and shall
be of copper only. All the copper earth strips, copper earth wires shall be
connected to main earth grid at suitable points.
15.1 The scope of work includes Planning, design, supplying, installation, testing
& commissioning of Medical Gas Pipeline System for 100 bedded Hospital. If any
item required to make the scheme functional, is not specifically mentioned in the
scope and specifications, the same is deemed to be included within the scope of
this tender. These technical specifications shall be read along with the General
Conditions for all E&M works given under subhead C-B.
15.1.1 The complete Medical Gas Pipe Line System must follow Single Standard
(anyoneonly from: NFPA 99c /HTM 02-01/ ISO 7396-1/DIN/EN)
forrelevantequipmentexceptCopperPipes. Third party compliance certification
after installation to be done.Thecostforthesame shall bebornebythe Contractor.
The work consists following components.
15.1.1 General Specification for Medical Gas Pipe Line System (MGPS) lays
down guidelines to ensure safe, efficient, reliable and economical
provision and use of MGPS in frastructure.
15.1.2 ResponsibilityoftheContractor
15.1.2.1 The contractor shall be primarily responsible for supply,
installation, testing, commissioning of complete MGPS, OEM warranty
for products, defect liability of MGPS installations for Three years from
the date of completion of the work.
15.1.2.3 The Contractor shall provide factory test certificates for the
materials/equipment used for the installation of Medical Gas Pipeline
System (MGPS). The MGPS firm shall supply complete set of manuals
for all the systems and sub-systems.
15.1.2.4 The Contractor shall arrange at his cost on-site training of user
for a week by original equipment manufacturer (OEM), wherever
required.
15.1.2.5 Final electrical safety test, system test, and calibration shall be
done as per required standard for the equipment installed by authorized
persons using calibrated test equipment, and declaration to this effect
shall be submitted by the MGPS firm.
15.1.2.7 Contractor shall supply the required number by ‘D’ Type cylinders
with first fill to be used in the system for different gases i.e., Oxygen,
N2O, CO2, for which nothing extra shall be paid.
b) All tanks (Air, Vac and AGSS) shall be installed on dedicated platform
near MGPS Plant room and this platform shall beconstructed
withshedas pertheirrequirement. Contractor shall submit the MGPS
Plant and Manifold equipment loading design
withfootprintofallcomponentaspertheirofferedplant. Contractor shall be
responsible for complete development of LMO area.
15.1.4.1 ThereshallbeaMGPSPlantRoom,MGPSManifoldRoom,LMOYard
witha Liquid Medical Oxygen apron, and a Medical Gas Cylinder Store.
MGPS Plant Room & LMO Yard, shall be connected to main Hospital
buildings through a trench/suitable route.
15.1.4.4 Cylinder Store, organized in bays for Gas specific Empty & Full
Cylinders, forMedical Oxygen, Medical Nitrous Oxide, Medical Air and
Medical Carbon Dioxide. It shall also provides to rage space for
CylinderTrollies.
15.1.4.5 Care should be taken to ensure that different gas types and full
and empty cylinders are segregated as clearly as possible in gas
specific bays and provided with a labelling system that clearly indicates
the cylinder status.
For Medical Air Plant and Central Medical Vacuum Systems, Multiple
Pump Systems (Multiplexing) shall be deployed on a cascading duty
arrangement, operated in a sequential manner to achieve redundancy
as well as energy saving. The following configuration may be
considered for plant sizing:
b) The tank should be PESO certified and outer shell material used
should conform to EIGA IGC 73/08/E/IS2062/SA36. A typical system
requirement for hospital installation is as follows:
Installation :Outdoor
a) Inner Vessel
b) Outer Vessel
Material : Carbon Steel ASTMA516
Design Code : EN13458
Operating Pressure : Vacuum
External Surface : Mechanical Cleaning
Primer / Final Coat : Two Coats each Equivalent
a) MaximumEvaporationRate:<1%ofnetvalue.
b) MaterialofConstruction: Innershellandwettedpartsof SS304
Outershellof CS AST MA516.
c) JointEfficiency: 100%
d) Radiography : 100%for inner,forouterspot
e) Externalpiping: FromLMOTanktoVaporizer:SS304
f) From Vaporizer to inlet of Pressure Reducing Station: SS304
g) FromOutletofPressureReducingStationtoMainheader:Copper
h) CryogenicValves:
i) CryogenicSafetyValves: Nonferrous
j) PressureBuildingregulator: N o n ferrous
k) LeakDetectiontest: HeliumLeak detection
l) Painting: PrimerandfinishwithWhiteRAL9010
m) Inspection:By3rdparty (SGS/LLOYDS/TUV)
n) Cleaning: DegreasingforOxygenServiceandPressurizewith
Nitrogen.
o) Withdrawal rate:1000cumperhr.at12BarGorasperdesign
d) Accessories:LMO Tank along with P&ID shall be fitted with the
following accessories:
a) TopFillValve, Bottom FillValve
b) Liquidcharginglineblowvalve
c) LiquidDeliveryValve
d) OverflowValve, Gasblowvalve
e) FillingCoupling, VaporizerCoupling
f) LiquidLevelGauge(Dial100mm).
g) HighLevelValve, EqualizingValve, LowlevelValve
h) PressureGauge(100mmdial,Range0-25kg/cm2)
i) PressureGaugeIsolationValve
j) PressurizingValve
k) PressurizingCoil
l) Filter
m) Pressure Regulator
n) Economizer
o) Check Valve
p) Evacuation Port
q) VacuumGauge Connection Port/vacuum probe valve.
r) Vessellowpressurealarm
s) Pipelinelowpressurealarm.
t) Twinregulator
u) Automaticchangeovertomanifoldswithcontrolpanel/regulator
v) Alarmonindicatingmanifoldinuseincase thevesselisnotinuse.
w) Alarmonlowpressureback-upmanifoldcylinders
manual manoeuvre.
i) Remote monitoring telemetry-continuous monitoring of VIE
stock based on daily consumption.
e) SafetyFitting:
a) Twosafetyvalvesforinnervesselfittedonpipelinewithflowdivert
valve
b) Rupturediscforinnervessel.
c) Safety valveforinletpipeline.
d) Safetyvalveforpipelineofpressurizing evaporator.
e) Onerupturedisc/safetydeviceonoutervessel.
f) TheLiquidMedicaloxygentankshallaccompanytheOriginalQualityTe
stCertificate covering following Documents:
h. Three pressure gauges on the front of the control cabinet shall indicate
left bank pressures, right bank pressure sand Hospital Distribution Line
pressures. A main shut off valve shall be installed between the
AutomaticChangeover Control Paneland the Hospital Distribution Line.
the building, in an area where the discharge of oxygen, shall not present
a fire hazard or cause in jury to personnel. All the manifolds shall be
capable of passing the full pipe line flow.
l) All components in the gas stream and contact with the oxygen
pressures above 30 bar shall be made from halogen-free
materials.
a) N2O is liquefied by the high pressure within the cylinder. The supply
is generally limited to Operating Rooms so no variation is generally
required. TheDuplex Control Manifold with 4 or more plus 4 or more
Class-D type bulk cylinders shall be provided. Manifold shall consist of
two high- pressure header barassemblies to facilitate connection of
primary and secondary cylinder supplies. Each header bar shall be
provided withrespective number of cylinder pigtail connections to suit
cylinder valves as per IS.3224/BS/ ASME incorporating a check
valve at the header connection. Each header barassembly shall be
provided witha high pressure shut off valve.
c) In N2O cylinders, the pressure shall remain constant until all of the
liquid is evaporated, after which the pressure drops rapidly as the
remaining gas is removed. The additional Gas Cylinders, as per design
calculations, shall be stored in the cylinder store room.
d) The N2O supply system shall be provided with a test point comprising
of a lockable valve and a terminal unitimmediately up stream of the
Hospital distribution line isolation valve. N2O Terminal Units shall be
provided in all Operating Rooms.
e) Three pressure gauges on the front of the control panel shall indicate
left bank pressures, right bank pressures and Hospital Distribution
Line pressures. The changeover from the “Duty” to the “Stand-by”
bank of cylinders shall be Automatic, preferably based on pneumatic
h) The Header Bar shall be N2O gas specific high pressure copper pipe
with integral check valves and cylinder pigtail assemblies of Stainless
Steel or Copper, confirming to IS 3224. The Header Bar shall be
provided with high pressure brass fittings made of high tensile brass
and connections and supplied complete with wall mounting brackets.
a) The Cylinder Vapour Pressure shall be about 5000 kPa. The Nominal
15.3.3 FullyAutomaticNitrousOxideControlPanel
c) The Control Panel shall be water resistant, complete with its master
control valves, power supply & all Valves, Gauges and Pipes, etc.
Suitable Electrical power outlet shall be fitted by the Contactor in
preparation for Installing the Unit. The control unit power supply shall
provide a visible green LED indicator to display “Mains Supply On”.
d) The Control Panel shall include two pressure relief valves,one high
pressure, approximate 200psi, and one low pressure,
approximate75psi. The control panel shall also have heaters to
preventice formation on the regulators at high flowrates. The Control
Panel shall be made to provide Heavy Duty and have a flow capacity of
1500LPMormore at 50to 60 psi.
e) The Automatic Control Panel shall be installed in such a way to meet
the peak flowrequirement of the Hospital. Control panel shall have
Alarm resets witch/Mute/acknowledgements witch to control and
monitor the alarm indications by the operator.
f) The system should incorporate graphical display to indicate pressure
level in each bank of cylinders and a line pressure. Digital display
should be backed up by mechanical gauges in case of power failure.
h) All components in the gas stream and contact with the Nitrous oxide
pressures above 30 bar shall be made from halogen-free materials. It
should fully comply with the requirements of the HTM 02-01/ ISO
7396.
15.4.1 The system shall consist of medical CO2 Manifold Primary & Standby with
Class-D type Cylinders and control panel.The Modular Manifold supply
system shall provide carbondioxide piped distribution system. The
Modular Manifold system shall be in such a way that it increases flexibility
andallows easy enlargement of the manifold capacity in case of future
expansion. Shall complywithHTM02-01/NFPA 99C/EN/DIN/ISO 7396-
1standard.
15.4.2 SourceforPrimarySupplyshallbetwobanksofaDuplexControlManifoldwith
Automatic Changeover, with minimum 4 number of D Type Compressed
CO2 Cylinders,(required number to be calculated based on number of
Operating Roomsto be deployed). Nominal Pressure to be considered is
400 kPa.
i. It is required that the Carbon Dioxide Gas manifold be installed in a
separate room.This room shall not have any other gas. The Carbon
Dioxide Gas Cylinders,both empty and filled shall be stored in a separate
room.
ii. The specifications for pipeline system installed for CO2 shall be as
per the general requirements for other Medical Gas Pipelines. The
terminal unit should comprise a NIST connector with integral check
valve contained in the surgeon’s pendant. The level of provision of
AVSUs should be provided as for other medical gas pipelines.
iii. Caution Notice should be put at suitable locations where CO2 isused.
b) The Header Bar shall be having Carbon dioxide gas specific high
pressure copper pipe with integral check valves and cylinder pigtail
assemblies of Stainless Steel or Copper, confirming to IS 3224. The
Header Bar shall be provided with high pressure brass fittings made of
high tensile brass and connections and supplied complete with wall
mounting brackets.
15.4.4 FullyAutomaticControlpanelforCO2System
b) The warning and alarm system indicator for CO2 supply system
shall normally be installed in the Operating Room control panel.
system from the "Stand by" bank when pressure in the "Duty" bank
falls to a predetermined level. The control unit power supply shall
provide a visible green LED indicator to display “Mains Supply
On”.
ii. The “Stand-by” Bank is full indicated by the yellow colour of LED
iv. The Control Panel shall have inbuilt heaters to prevent frosting of
regulators.
15.5.1 Themedical air plant shall fully comply with the requirements of the HTM
2022, C11/EN1441/EN737. Medical quality air shall be delivered at a
nominal pressure of 400 kPa (4 bar) and 700kPa (7 bar) gauge for supply
of the hospital medical air and surgical air. Compressor plant shall be
designed in such a way that compressors shall switch on in a sequential
manner as per flow demand.
15.5.1.2 Medical Air, as generated must be dry and should not contain
any lubricant vapours, odours, excessive moisture or particles which
are over 0.01 microns in size. It requires that the quality of Air Intake
15.5.1.3 MA4 is used in respiratory therapy for patient ventilators, and for
blending with oxygen. It is also used as the driving (carrying
medium) gas for nebulized drugs and chemotherapy agents.
Therefore, it is essential that MA4, as manufactured must be tested
by a certified Laboratory to be compliant with the requirement of
Indian or European Pharmacopeia, as stated in IS/ISO 7396-1. The
MGPS Installation shall be taken over only when this certificate is
provided.
b. The dew point of medical air must be at or below the frost point
(0DegreeC). At every point within the system, regardless of how much
pressure is being created by the compressed air system. The Air
dryers must lower the dew point while the system is operating at
maximum capacity and for any level of demandand when all air
consuming devices are inuse.
d. The Medical Air supply system shall be provided with a test point
comprising of a lock able valve and a terminal unitimmediately up
stream of the Hospital Distribution Line.
15.5.3 SystemConfiguration
II. The Air Intake shall be a ducted system of Copper Pipes. It must
be provided withsuitable screens and a coarse filter,
inspectable, to prevent ingress of ant insects orsmall birds, or
particles of 100 micron or larger. Ideally, the Air Intake circuit
shouldhave a set of Inlet Filters comprising of a Coarse Filter of
20 micron and an active charcoal filter to filter particles and
hydrocarbons.
III. It must be isolated from all piped and un- piped exhaust
systems, of the Hospital, as per Compressed Gas Association
Norms.
IV. Air Intake shall be at least 5 Meters above Ground, in opposite
face of the plant roomwhere pump exhaust is being sent, to
ensure a reasonable quality of Air Intake. It isrequired to be 8
Meters away from any exhaust or vent, or from the any source
orcollection of noxious fumes and at least 3 Meters away from
any window. It must be soprotected that birds shall not
15.5.5 Compressors
The Compressors to be known as Medical Grade Compressors. The
capacity of Medical Air Compressoris expressed as “Free Air Delivery”
or FAD.
The design of medical air plant shall fully comply with the requirement
of IS/ISO 7396 for flow of 2000 LPM +/- 10% in Triplex configuration.
Each Compressor should be Reciprocating/ Scroll / Rotary / Screw Oil
free air compressor with output at 8 -10 bar is 2000 Lpm +/- 10%.
The medical air plant shall deliver both medical and surgical air with
minimum total flow rate of 2000 LPM l/min +/- 10%. Compressor plant
should be designed in such a way that compressor will switch on in a
sequential manner as per flow demand. One or more identical air
compressors/Modules should run to provide a primary flow rate of
2000 LPM +/- 10% and one more compressor to provide as
standby. Each compressor should be suitable for both continuous and
frequent start/stop operation at a nominal plant pressure of 8 bar or
more.
15.5.6 All moving parts, viz, fans, pulleys and belts, shall be fully
protected by enclosures and guards. Each compressor shall be
equipped with isolation valve, check valve, safety valve, electric
motor, belts, belt guard, aftercooler and Thermal Malfunction
Protection Device (TMPD), as appropriate. Vibration mounting,
by means of spring isolators, shall be provided.
e) The compressor should be heavy duty, reliable with long MTBF. Each
compressor cylinder is to be protected by a temperature switch,
which will stop the drive motor and provide an alarm signal in the
event of abnormal discharge air temperature. Each compressor
module should include an inline filter inlet isolation valve, discharge
isolation valve, and pressure relief valve. The capacity should be
capable to take care of total load of all the outlets.
d) Two (2) Vertical Air Receivers, each of 2000 lts capacity, to withstand
apressure of 10 Kg/cm2, fitted with onePressure Gauge, one Safety
Valve and one Auto Drain Cock shall be provided. The two Air
Receivers shall be inter connected to perform as a single unit.
g) The Air Purification process requires traps, valves, isolating valve sand
non-return valves to maintain stage wise purity as well as to provide
isolation of components for maintenance or replacement. It also needs
to be monitored. All components and accessories, that are specified,
must be suitable for continuous use at the system demand flow at
higher pressures than the distribution pressure. The Compressed Air
System Plant design must take care of the resultant pressure drop.
15.5.9 MoistureSeparation
a) Medical Air must notcontain oil vapours more than 0.1 mg/m3.
Therefore, after the Moisture Separators, and before the Desiccant
Dryers, online Oil Filters shall be providedtoremoveHydrocarbon
vapours, water vapours, particles and odours. Activated Carbon Filters
bond hydrocarbon residue, odorants and oil vapours.
b) For Oil Separation, Adsorption filters which contain activated carbon
granules and have an extremely high surface area and well time shall
be used. An absorption filter must be protected by anupstream filter to
prevent gross contamination byliquid oil.The Air temperature should
be+/-20 Degree C.
c) Deployment of an Oil Separation Filters with Oil free Air Compressors
shall be provided. It should be an air filtration system which
utilizesaprefilter, high- efficiencycoalescing filter and charcoal
adsorber element; capable of removing particles to meet the
requirement of ISO 8573.1, for Clean,dry andodour-free air.
The air treat ment module shall included ualdryers system and a dew
point transmitter with local audible and visual signals and dry contacts
for MGPS monitoring. The components shall be mounted on a
common base with in ter connecting copperpiping and upstream and
downstream isolation valves. The isolation valves must allow either
set of components to be serviced without shutting down the system.
Dryers shall be of heatless desiccant design and sized to provide for
the peak calculated demand. The desiccant dryers shall be
equipped with dew point dependent switching feature to minimize the
need for purge air.
a) Each Air Dryer installation shall consist of the following, as a minimum.
removing liquid water, oil and oil aerosol down to 0.1mg/cum (0.1
ppm) and particles down to 1micron.
15.6 MedicalVacuumSystem
Control unit of the station is intended to control and monitoring the activity
of the vacuum station system. It consists of electrical, electronic and
measuring units and the control for the vacuum pump unit activity.
This unit is intended to generate vacuum for the use in Hospitals. The
pump has non-return valve system for its protection. Vacuum vessel
maintains the vacuum.
Filter: Vacuum filter protects the mechanical part from
contaminants like bacteria, dust and similar particles. The fluids drain
in to the flask below the filter. The filter is mounted on the suction side
of the system.
Pressure Switch: Pressure switch is a part of the signaling system. It
is built on critical pipeline measuring points. By vacuum under
exceeding the switch send the signal to the signal unit in the main
board.
k) The system shall be sized so that if one vacuum pump fails, the
remaining vacuum pump(s) can supply 100 percent of the total
system demand. The system design shall include automatic
operation of the vacuum pumps including cascading and
sequencing operations.
a) It should fully comply and meets with the requirements of the NFPA 99
standard. Designed flow capacity should be minimum 2000 LPM
± 10% variation in triplex configuration.
b) The medical vacuum plant shall comprise Triplex, air-cooled, oil free,
Reciprocating/ Scroll / Screw/ Rotary vacuum pumps to provide a flow rate
of at least 2000 LPM ± 10% each as per the relevant standards to provide
the desired flow of the hospital to maintain a vacuum level of 450 mm Hg at
the plant connection point.
c) The control system should normally employ automatic rotation of the lead
pump to maximize pump life and ensure even wear. Each vacuum pump
shall be fitted with anti- vibration pads between the pump foot and mounting
frame. The plant shall be fitted with duplex bacteria filter system. Each
individual filter shall have the capacity to deliver full design flow such that
one set is designated duty and the other will be standby. Each bacteria filter
shall be provided with a transparent sterilize collection jar to collect
condensate.
d) The plant control and power management system shall monitor the safe
operation of the plant, providing signaling into the alarm system. Vacuum
pump exhaust shall be piped out of the plant room and discharged outside
the building at high level away from windows and any other air intakes.
h) PurgeOperationisasunder:
i. Pumpsstartbasedonvacuumset pointdemands.
ii. When the pump shuts down, it operates the purge cycle (generally
of 10minutes).
iii. The purge solenoid valve opens to allow atmospheric air into the
system toremove condensable vapours. It also removes the heat
generated due to pumpoperation.
iv. Afterthepurgecycle,pumpshutsoff,andisreadyfornextvacuumcycle.
a) The vacuum receiver shall be made of rust-free corrosion resistant Mild steel
and fabricated as per IS:2825 for a vacuum pressure of 760mmHg. It should
include bypass valves, manual drain valves, vacuum gauge. Vacuum reservoir
shall have volume of at least 4000+4000 Litres capacity.
b) silencer shall be provided in the exhaust system of pumps for silencing the
noise from pumps creates on the exhaust system.
c) AsetoftwoVacuumReservoirVessels,alsocalledVacuumReceiver,arra
ngedinparallel,shall be provided so that the duty pump does not run
continuously for low loads.
ThereservoirshouldbemanufacturedinaccordancewithBSEN286,AirRe
ceivers2005,withtestcertificatesprovidedbytheReservoirVesselmanuf acturer.
d) The water capacity of each Reservoir Vessel should be equal to the plant
design flow at 450 mm Hg (60 kPa) in terms of free air aspirated in one minute
with the pump operating at 450 mm Hg (60 kPa). Vacuum Reservoir Vessel
should conform to ASME Boiler and Pressure Vessel Code 2017.
e) It shall be preferably be a Vertical, Cylindrical, Stainless-Steel Tank (304/ 304L)
15.6.6 Filters
a) The bacteria filters and drainage trap should comprise two identical sub-
assemblies with manually-operated isolating valves, arranged to allow either
sub-assembly to be on stream. Each sub-assembly should contain a bacteria
filter rated at the plant capacity. The bacteria filter should be marked with the
legend “bio-hazard”, together with a description of a safe procedure for
changing and disposing of the filtersand emptying the drainage trap.
b) The bacteria filters should have a filter efficiency of greater than 99.99% at the
system design flow. The pressure drop across a clean filter at the system
design flow should not exceed 25 mm Hg (3 kPa) at a vacuum of 475 mm Hg
(63 kPa). The drainage trap may be integral with the bacteria filter and should be
fitted with a transparent bowl to collect liquid. The bowl should be suitable for
steam sterilization at 121°C.
c) PipedVacuumSystemsshallbeprotectedwithappropriatefiltration(0.3-
micronhydrophobicfilterorequivalent)onthesuctionsideofthepumpstom
inimizethepotential forcontaminationofthevacuumpumps.
d) In addition, a Liquid Trap or Mechanical Filter, that use Gravity, is required in the
system to prevent any of the material's being drawn through the vacuum line
from getting into the pump.
b) A Display unit to display all major controls status and plant monitoring
status, in an intelligent format for at-a-glance checking. The Display unit to
display all major Alarm conditions and Alarm signaling status. The Display
unit shall provide all maintenance Notifications.
clearance all around the panel and 900 mm clearance in front of the panel
at installation point.
g) The PCS shall be suitable for the multiplex system and provide cascading
and sequenced control to start and stop the Air Compressors and
Vacuum Pumps. It shall provide programmed delay to ensure that both
Equipment Systems i.e., Air Compressors and Vacuum Pumps do not
restart simultaneously.
h) All internal components, control system components, and circuitry
boards, needed for operation of the PCS control system shall be non-
proprietary. These shall be readily available from local and standard
electrical suppliers.
i) General Lighting, Alarm Panels, air-conditioning units, Energizing the
Medical Air System and Medical Vacuum Systems, etc. shall require
additional Electrical Distribution Board(s). Provision of this Electrical
Distribution Board shall be in the scope of the Contractor. All Electrical
Works including power supply to Medical Air Compressors, Medical
Vacuum Pumps, other System components, provision of Mains Incomer,
Bus Bar arrangement, all required meters, contactors, relays, switches,
indicators, Earthing, etc., shall be as per National Electrical Code and
relevant Codes.
a) TheOperatingRoomsshallbe
providedwithanactiveAnaestheticGasScavenging(Disposal)Systemsc
onformingtothe IndianStandard,IS/ISO7396-
2(2007):MedicalGasPipelineSystems,Part2:AnaestheticGasScavengi
ngDisposalSystems
g) The Discharge Outlet shall be sited at roof level, far away from
ventilation inlets, opening windows and other apertures, where it
cannot be entrained into the air-supply system and re-enter the
building.
h) It must provide protection for Rain ingress. The First Fix connections
(including gas specific NIST Connections), as well as second fix
connections, specifically for Medical Supply devices and all
peripherals, must be adequately staggered to prevent cross
connections.
c) The Discharge Outlets must provide protection for Rain ingress. The point
where these AGSS Discharge Outlets are located is referred to as AGSS
Discharge Point.
d) The flowrate through each type 1H terminal unit shall not exceed 80 LPM
when the resistance to flow which is provided to simulate the resistance of
the receiving system, is such as to produce a pressure drop of 1 kPa at 80
LPM, and shall not be lower than 50 LPM when the resistance to flow,
which is provided, is such as to produce a pressure drop of 2 kPa at 50
LPM (ISO 8835-3,10.2)/ (ISO 7396-2).
e) AGSS disposal system with type 2 Terminal Units with a flowrate of 50
LPM through the socket of each AGSS type 2 terminal unit, the pressure
drop shall not exceed 7.5 kPa. (ISO 7396-2) resistance to flow at each
terminal unit, irrespective of the number of Terminal Units in use.
f) The system shall incorporate a line pressure switch which monitors vacuum
levels and provides an additional control of the remote start switch and
starter/isolator panel green 'RUNNING indicators. The pressure switch shall
include a digital display providing readout of the vacuum level in the
pipeline.
ii. Mains On
iii. Air Flow Normal
iv. Plant Fault Indicator
v. Plant Emergency indicator
g) Integration of AGSS control panel with Hospital, for displaying alarm conditions, shall be
provided.
b) The MGPS Pipeline Carcass includes all fixed Medical Gas Pipelines,
Terminal Unit baseblocks and Area Valve Service Units (AVSUs),Line
Valve Assemblies(LVAs).
c) The Main Hospital Supply Pipeline shall run from the MGPS Manifold
Room or the MGPS Plant Room till the service enters a Building Block.
There it shall be connected to the Feeder pipelines, which travel
horizontally as well as vertically. On the floor, it is connected to the
Distribution Pipelines, which serve only one floor or part of the floor
and do not travel vertically. They, through Drop pipes, get connected
to Terminal units.
DHP).
b) The Copper Pipes shall be seamless, round, solid drawn, sizes
confirming to BS EN 13348, suitable for installing vertically or
horizontally without sagging or distortion.
c) Pigtail connections for Oxygen, Nitrous Oxide, Medical Air 4 and
Carbon Dioxide manifolds shall be of copper. All other fittings, valve
and control panel fittings, etc., can be of Copper, Brass, Gun-metal
& Bronze. Except for mechanical joints, only copper-to copper
joints shall be permitted on site, made with brazing filler rods.
Copper to Copper joints shall be made on site by silver brazing
(Recommended copper-phosphorus brazing alloy CP 104
conforming to BS EN 1044:1999).
d) All Copper Pipes must be inspected and certified by a Third-party
Inspection Agencies like Lloyds, SGS, TUV as to their physical
properties and chemical composition including cleanliness status
before dispatch. The pipes shall be accompanied with
Manufacturer’s Test Certificate.
e) All turns, offsets, and other changes in direction shall be made using
only Copper Pipe fittings. Fittings, as required for jointing in pipe
carcass, shall be end-feed capillary fittings of Medical Grade
Copper, which conform to EN 1254-1.
f) All Copper Pipe Fittings, when supplied must be certified by the
manufacturer to be clean and degreased. These shall be individually
packed to maintain cleanliness.
g) silver Provision of Tapered Threaded Fittings shall be limited to the
connections for pressure and vacuum indicators, alarm devices,
gas- specific demand check fittings, and source equipment on the
source side of the source valve. Where these joints are needed,
they may be made with unsintered (de-greased)
Polytetrafluoroethylene (PTFE) tape.
h) The cleaning process shall not result in grooving of the surfaces to
be joined. The use of steel wool or sand cloth shall be prohibited for
cleaning exteriors of tube ends, etc.
i) Brazing, for all positive pressure gases and for vacuum pipelines –
up toand including 22 mm pipes, that are run in Medical Gas Supply
Units, shall be carried out using oil free, oxygen-free nitrogen as an
internal inert gas shield to prevent the formation of oxides inside of
the pipes and fittings. Pipes shall be continuously purged with oxygen-
free nitrogen with terminal flow rate of 2 liters per minute.
j) Pipe sizing is determined either by Volume of Gas to be delivered
or by impact of overall negative pressure required. When sizing, for
Medical Vacuum, always provide pipes of one size higher diameter
to prevent clogging.
k) No pipe smaller than 15 mm OD shall be used anywhere in this
MGPS Installation.
15.7.3 ThefollowingpipespecificationsaremandatedasperEN13348,2016.
15mm 1.0mm
22mm 1.0mm
28mm 1.0mm
42mm 1.2mm
54mm 1.2mm
76mm 1.5mm
108mm 1.5mm
OUTSIDEDIAMETER MAXIMUMINTERVALS
(mm) ForVerticalRuns/Horizontal(m)
12-15 1.5
22-28 2.0
35-54 2.5
>54 2.5
b) Where pipes pass through walls, partitions or floors they shall be fitted
with sleeves of copper pipes and provided with appropriate
escutcheon plates where to view.
c) The sleeves shall project at least 25 mm beyond the surface of
penetration. The annular space between the sleeve and pipe shall be
tightly caulked with a suitable material.
d) Due allowance shall be made in the installation for building movement
at all constructional expansion joints.
e) The design of supports, brackets and hangers for all pipe work shall
be in accordance with BS 3974. The Contactor shall co-ordinate the
tie-in of pipe supports with Structural and Architectural works and shall
provide additional support structures, wherever necessary.
15.8 ProvisionofValves
c) Gas identity and flow direction arrows should be provided for each
valve. Valves are provided for all gas Services including Medical
vacuum but not for AGSS.
a) A Source Shut Off Valve is always provided for each Medical Gas
Service at theimmediate outlet (or inlet, in the case of Medical
Vacuum) of the source of supply,so that the entire supply source,
o. AVSUs are lockable enclosures which can be closed with the valve
either in the “open” or “closed” position. In an emergency, the user
must be able to gain access in order to operate the isolating valves
quickly and simply without the need for a key.There are several
methods of providing such emergency access, for example break-
glass panels and plasticpush/pull-out inserts, etc. AVSU with display
units shall require electrical power supply.
15.8.6.1 The MGPS Monitoring and Alarm System shall be operated by deploying a
System Control Software that provides comprehensive monitoring over the whole
MGPS installation, specifically over the Status of Equipment deployed and gas
Pressures available. It provides comprehensive analysis of data as generated and
presents the results in display panels and indicator panels. It activates the Alarm
Module, monitors all alarm conditions and also generates requiredreports.
15.8.6.2 The MGPS Monitoring and Alarm System shall monitor all gas services
installed, including AGSS. AGSS is controlled and monitored in the
Operating Rooms but additional data shall be logged into MGPS Alarm and
Monitoring System.
15.8.6.3.1 It consists of a central unit that receives signals and data that is
generated by various sensors, transducers, devices, etc., installed as
apart of MGPS installation for monitoring its status, on 24 x 7 basis.
15.8.6.6 MGPS Monitoring and Alarm System, using LAN, shall connect all PLC
controlled panels, as deployed in MGPS installation, collect the data for
analysis against pre-set bench marks and provide either Normal Condition
Display or Emergency Condition display to display panels, as per Hospital
approved format.
15.8.6.8 The MGPS Monitoring and Alarm System shall provide Audio-visual display
panels. The panels shall provide physical, labelled, visual alarm indicators.
MGPS Monitoring and Alarm System Master Display shall be provided in
the Central MGPS Plant Room & Manifold Room or where the MGPS Duty
Technician is located, as per Hospital requirement.
15.8.6.9 Slave of Master System Audible Alarms in the Central Fire Control Room of
the Hospital as a Slave Monitor (also called Repeater Indicator Panel).
Area Audible Alarm Panels installed at the corresponding Nurse Station or
Control Stations, in all areas of the Hospital, for those Gas Types which are
being used there. The criteria is availability of Gas Specific Terminal Units.
15.8.6.10 MGPS Monitoring and Alarm System shall be provided uninterrupted power
supply (UPS), the same is in the scope of work. MGPS Monitoring and
Alarm System shall be provided with RF Protection.
15.8.6.11 Contractor shall provide drawings, low voltage control wire layout and data
cable layout, location of Alarm panels, Pressure Switches and related
valves.
15.8.6.12 The MGPS Monitoring and Alarm System output shall be Multi viewer, HD,
display panels (Monitors) for simultaneous display of multiple screens
related to multiple parameters. In addition, visual LED indicators or LED
display units shall be provided, where required.
15.8.6.13 The MGPS Monitoring and Alarm System output display can be wall
mounted or a Tabletop display unit. The audio-visual Alarm Panels must be
15.8.6.14 The panels shall be HD/Multi viewer display panels for simultaneous
display of multiple screens related to multiple/parameters. Inaddition, LED
signal displays can be provided, where required. All display panels, PLC
Panels and PC integrated Units in MGPS installation shall provide
suitableData Connections for networking.
15.8.6.15 The MGPS Monitoring and Alarm System is a comprehensive system that
shall collect gas specific data, pressure data, Gas Source data, on
continuous basis, analyses it and provide MGPS status of normal
conditions and activate alarms when abnormal conditions occur. It deploys
a large number of digital Pressure, Airflow, Force, Magnetic and Tactile
Sensors; Pressure Switches; Pressure Transducers, etc., to monitor and
operate the MGPS Alarm and Monitoring System. It shall generate Text
messages for informing the occurrence of emergency condition, which
require urgent action by the user.
15.8.6.16 It requires that all MGPS components are provided a unique ID which shall
be used by the system to monitor and to display. It means all pumps,
manifolds, LVA, AVSUs, etc. shall be listed and provided a unique ID.
15.8.6.17 The Alarm Panels must be visible and/or within the hearing range of the
Healthcare Providers. The alarm should be loud enough to be heard over
the surrounding ambient noise. In any case, all local area Alarms are
repeated in master Alarm and from there in the Central FireControl Room.
15.8.6.18 In Critical Healthcare Delivery Areas, Hospitals must ensure that alarm
panels are located in Nursing Stations. When MGPS services are used in
radiotherapy rooms, radiology examination rooms, Alarm panels are
located in respective Control rooms.
15.8.6.19 If the Alarm Panels are combined, to reduce the number of audible
notifications, the panel must indicate location of origin of the alarm.
15.8.6.20 Master Alarms, panel shall provide comprehensive information about the
sources and give warning of any issues developing within the source
equipment themselves. They also provide status of MGPS System, like the
source being used, in case of Duplex manifolds, which bank is being used,
etc.
15.8.6.21 Local Alarm panels provide information about the status of MGPS supply
downstream of Area Valve or Line Alarm. Local Alarm panels may also
provide relevant information about the Gas Pressure. The Alarm panel
component of LVAs can be placed at a different location where it is more
effective like at the Nursing Station in a ward where LVA is placed in ward
evacuation path. It is permitted to provide the Alarm panel inside the
Operating Rooms.
15.8.7 Sensors
a) For all locations, the sensors shall be placed on the pipe and wired to
the alarm panel. All Area Valves should be integrated with Alarm
Sensors
b) For all Critical Healthcare Delivery Areas, where an area alarm shall
monitor a single zone, the sensor should be placed on the patient side
of the zone valve. Closing the valve should activate the alarm.
Additionally, the sensor may be placed on the source side of the Zonal
Valve to determine the extent of area affected.
a) It shall be located in the Central MGPS Plant Room & Manifold Room
or where the MGPS Duty Technician is located.
3. Medical Air
l) High mainline pressure
m) Low main line pressure
n) High Dew point (>35°F)
o) High Temperature (operating temperature of the compressor)
p) LagCompressor
4. Medical Vacuum
q) Low Vacuum pressure
r) Lag Pump
b) These must always be placed where the alarm condition can be attended to.
c) It shall provide
i. Acomprehensive System Control with integrated alarms
ii. Real-time system status Display and Graphics
iii. Full System StatisticsTracking and Reporting, including messaging and E- mailing
iv. Interface all needed third party Software
v. Ability to add additional plug-in Technologies
vi. User-Friendly Programming Abilities
c) A record shall be made of all tests performed and results. All testing
shall be witnessed by the Engineer-In-Charge or his representative.
d) All defects or errors, found during testing must be rectified, and the
relevant systems must be retested as appropriate before the records
are signed.
15.10.2 Pipeline System Complete –SystemTest (with Installed Terminal Units for
safe Performance with test Gases)
a) LeakageTests(Second stage)
b) AVSU/TU/NIST Identification,Function & PerformanceTests
i. Closure of AVSUs and LVAs
ii. Zoning of AVSUs
iii. Terminal Unit Identification
c) Cross-connectionTests
d) Pipeline System PerformanceTests
e) Flow and pressure dropat individual Terminal Units
f) Supply System PerformanceTests
g) Safety Valves PerformanceTests
h) Alarm Systems PerformanceTests
i) Purging with Test Gases
j) ParticulateContaminationTests
k) Vacuum Disposal System
l) AGSS Disposal System
b) The Liquid Medical Oxygen system shall not be tested under no flow
conditions.
c) In this MGPS Installation, the test gas shall be Compressed Air supplied
in Cylinders, or generated by the Medical Air Plant, provided the
Medical Air has been tested, complying to IP or EP or USP. Non-
medical compressed air, from any source – cylinders or portable
compressors, shall not be used.
d) When employing Medical Air Plant Compressors for this testing, the
total flow under test shall not be more than 75% of the flow capacity of
the dryers.
e) The testing shall be carried out in three stages as under and as listed
in detail above.
I. Tests and checks on the pipeline carcass.
II. Tests and commissioning of the complete pipeline system (with
Terminal Units installed) for safety, performance and particulate
contamination using test gas.
III. Only after tests for particulate contamination are validated, filling
of the MGPS gasdelivery systems with specific gases for the
purposes of identity and quality tests of the specific gases shall be
done, prior to its use for patient care.
i) The results of all tests must form part of the permanent records of the
Hospital and should show details of the services and areas tested.
15.10.6 SystemControls
During periods of low or node mand. The control includes individual self-
protected combination MGPS controls with short circuit protection, single
phase and thermal over load protection, individual control circuit with
transformers primary and secondary protection, pressure sensors,
temperature switches with reset buttons,and an electronic controller to
automatically change the operating sequence of the compressors.The
cabinet shall have status display to include system pres sure, dew point
pump operation, accumulated time, maintenance interval, fault conditions,
and silence button, lighted Hand-Off- Automatic selectors witches and
safety disconnect operating handles. All required local alarm functions
shall be integrated into the packaged system.
15.11.1 HorizontalBedHeadPanel
following:-
The Lockable line valves must be degreased and complete valve with
stuffed pipe & fittings, factory tested and compliant with HTM02-
01/NFPA99C/EN/DIN/ISO7396-1standard.
Allwiring inside the Manifold Room and Plant room required for MGPS
equipment and General electrification shall be in the scope of work. The
department shall provide one point supply only. Other are under the
scope of Contractor. All the work shall be as per BIS/CE standard and
material used shall be reputed make only.
The scope shall be inclusive of all installation, material (Copper Pipes,
fittings, etc.), trenches and labour etc. as per site condition.
Contractor shall be responsible for all civil modifications and repair for
successful completion of MGPS Plant, Manifold, and Pipeline installation
and commissioning throughout the proposed blocks/buildings.
supply of the spare parts for the machines and equipment supplied by
them for 10 years from the date of completion of the work.
16.1 The brief scope of work shall include Planning, design & preparation of
drawings, and supplying, installation, testing & commissioning of Modular
Operation Theatres for 100 Bedded Hospital. The total system has to be
commissioned in complete manner to have a fully functional system, as required. If
any item is required to make the scheme functional, is not specifically mentioned in
the scope and specifications, the same is deemed to be included within the scope
of this tender.These technical specifications shall be read along with the General
Conditions for all E&M works given under subhead C-B.
Cladding structure shall consist of insulated stainless steel wall panels with
total panel thickness between 50-60 mm. It shall be 0.8 mm thick, 304 grade
stainless steel sandwich panel (both side 0.8 mm thick sheet), with core
consisting of rigid polyurethane foam injected under high pressure with a
minimum density of 40 kg/m3. The individual wall panels shall use the
tongue and groove technology/ welding method for joining panels. Panel
should be covered with protective sheath to prevent scratch during
installation. The gap between panel and room wall shall be filled with
suitable materials as per International Standards. The gap between the
finished surface of OT and wall should be sufficient for the flush mounting
equipment. and to enable services, pipes, conduits etc. to be run. Stainless
Steel plate finished to fine grain surface, treated properly to take antifungal
paint. The wall panel design should be such that it allows installation and
provides support to all equipment and shall have the provision of openings
required for the installations, without affecting rigidity and strength. Access
boxes shall be fitted to the rear side of all wall-mounted equipment to enable
maintenance to be carried out from outside the operating theatre. Anti-
bacterial and Anti-fungus sterile coating shall be applied on the SS 304
finished walls with at least 3 coats to achieve a thickness of minimum 300
micron. Before application of sterile wall coating, an Industry standard
Primer shall be applied. Contractor should maintain anti-bacterial & anti-
fungal paint during warranty period. Wall elements should be resistant to all
standard cleaning agents, disinfectants, and fumigation agents. It should
have minimum number of junctions. The junction should be seamless and
should be sealed with suitable sealants. Filling of all joints and cavities with
metallic epoxy filler and sanded flush to provide a jointless finish, sprayed
with a water based liquid plastic aseptic and self-sterilizing wall coating
system.
The Panel shall be flame resistant. Third party test certificate for SS304 from
material testing lab to be provided at the time of pre-dispatch
inspection/supply. The inner surface shall be fixed with suitable supports.
Panel should be easy to maintain, durable, antistatic/conductive and fire
retardant.
16.2.1 CeilingforOperatingRoom
The prefabricated ceiling plates/cassettes shall be made up of SS 304
panels with sheet thickness of at least 0.8 mm sandwich panel (both side
0.8mm thick sheet) of PUF with minimum density 40kg/m3, matte finished
and coated with antibacterial paint. It shall be from the same manufacturer
as that of wall panel. Total thickness shall be 30- 40mm. Anti-bacterial and
Anti-fungal sterile coating shall be applied on the SS 304 finished ceiling
with at least 3 coats to achieve a thickness of minimum 300 micron. Before
application of sterile ceiling coating, Industry standard Primer shall be
applied. The makes and specifications of primer and paint shall be as per
the guidelines of Panel fabricator/ International standards, whichever is
higher. Contractor should maintain anti-bacterial & anti-fungal paint during
warranty period. Ceiling Panel should be from the same manufacturer of
wall panel. The Supports shall be of Suspension bracket with tension
spring/Threaded rod and shall made up of high quality galvanized or powder
coated steel. Room lighting, air supply inlet, ceiling service units, return air
outlets, etc. should be integrated with SS metal ceiling system. The
individual panels except those at the edges should be removable
individually. The Panel shall be flame resistant. Third party test certificate
for SS 304 from material testing lab to be provided at the time of pre dispatch
inspection/supply. The ceiling panel shall be fixed with suitable supports.
Panel should be easy to maintain, durable, antistatic/conductive and fire
retardant.Filling of all joints and cavities with metallic epoxy filler and sanded
flush to provide a jointless finish sprayed with a water based liquid plastic
aseptic and self-sterilizing wall coating system.
The operation theatre floor finish should be laid with 2 mm antistatic seamless
conductive PVC roll/tiles on a semi-conductive adhesive base. On the sub-
floor, a self-leveling compound shall be laid prior to laying of the floor finish.
The self-leveling compound shall be of the type that does not promote
bacteriological growth. The floor should be scratch resistant, fire resistant,
chemical resistant, non-corrosive, slip resistant, smooth, anti-fungi, anti-
microbial, impervious material conductive enough to dissipate static electricity
but not conductive enough to endanger personnel from electric shock. Joints
should be welded by special PVC thermal welding units using PVC welding
bars of same colour. It should be scratchproof. The floor finish should pass over
a concealed cove former and continue up the wall for 100 mm. The floor should
be provided flat to within a tolerance of ±3mm. Copper grounding strip of size
0.05 mm thick, 50 mm width should be laid flat on the floor in the conductive
adhesive and connect to copper wire of grounding. The connection from copper
grid should be brought out uniformly at places to form equi-potential grid.
Colour should be uniform pleasant, and matching with ambience and as
approved by Engineer-in-Charge. One earthing lead should be brought out
from every 14 Sq.m area and attaching it to the main earthing strip/ground.
Relevant Test certificates as per Industry standards shall be produced.
cloth that shall introduce the highest air quality into the Operation Theatre.
The filters installed in the plenum should be suitable for application for
laminar flow and clean rooms. The ceiling system should be equipped with
“H 14” class, 8 Nos. deep HEPA filters (complying with European Norms)
with 99.99% efficiency to ensure highest quality of clean air for 0.3-micron
particles & tight control over bacterial infection system. Air shall be diffused
into the theatre uniformly over thetotalarea. The ceiling filtration system
should be designed to ensure unidirectional distribution of sterile air of the
surgical theatre to ensure the cleanliness of all the area covered by the air
flow. Filtration Ceiling System holding structure, Filter frames and top
plenum should be made of Aluminium. The positive pressure should be
maintained inside the OT to prevent contamination due to air from outside
the OT. The laminar flow installation & lighting system of Operation Theatre
shall be designed in such a way to prevent patients being infected during
operation which lies on the design of sterilized air conditioning system and
the flow pattern of draught as well as the quality of engineering. The filtration
ceiling system should have diffuser to achieve uniform & constant air
distribution over the whole surface. The ceiling shall have supports to
secure the main structural frame to the modular operating theatre. The air
management system should be designed to achieve Class 100 as per IS /
ISO 14644-1. The supplier should provide test certificate for HEPA filter and
laminar air flow systems from the original manufacturer. It shall be
CE/UL/USFDA/LTC/UL/BIS certified / listed
Peripheral lighting and clean room luminaries with intensity min 500 Lux,
should be minimum 8 in numbers for each OT. Luminaries cover should be
made of highly resistant, disinfectant leak proof laminated safety
glass/acrylic with fine-grained surface. The body should be made of sheet
steel, perfectly powder coated, supplied ready for connection with dimmable
electronic control gear in multi lamp technology. Recess frames should be
air tight. The fitting should be flush with the ceiling and should be removable
from bottom. The light fitting should be uniformly and aesthetically
distributed on the ceiling to provide uniform illumination in the OT. Light
should not interfere when green mode endoscopy is performed. Peripheral
lighting should be done according to IP 65 regulations. Control equipment
for the general lighting and the light dimming should be provided in the
theatre control panel. The operation procedures should never be affected
by shadows, shimmering lights, and dazzling eyes. This must be achieved
by the lighting system with sufficient illumination level and to provide flicker
less design lighting control system. Suitable for areas with infrared
regulation.
The door shall be of Single Flap with frame size 1800 mm wide x 2100 mm
height and hermetically sealed. It should be light weight, noise proof, rust
proof and insulated door. The door frame is to be made from high quality
anodized aluminum extrusion and the door panel to be made from compact
laminated board that will withstand high abrasions.
Thecontrollershouldbecapableofbeingoperatedbyelbowswitches/footswitch
The finished floor on either side of the door should be perfectly levelled with
hygienic PVC laminate (maximum permissible difference + 1 mm). The
overall thickness of the finished door should be 55 mm to 60 mm. The inner
part of the door should be filled with CFC free polyurethane foam (PUF)
thickness of 48mm with high density (Sealed airtight to prevent further
ingress of any microbial organism). The door and controls should comply
with IEE regulation/EU directions. All motors used should be DC motors with
essential isolation from mains. Door should have a vision window 300 mm
x 300 mm with double glazed panels and hermetically sealed. Door
movement should have minimum noise. The starting time after receiving the
signal should be adjustable between 0.5 sec to 20 seconds. Test certificate
for hermetically sealed door frame should be enclosed with the pre dispatch
documents.
Switch: - Device should be used to manually activate and open the door.
Specifically designed for use in clean rooms.
a) The Control panel shall be Touch Screen type and size shall not be less
than 24", Medical Grade. It shall be able to be configured to incorporate
all the services that Operation Theatre staff requires. The connection
between the Surgeon control panel and the distribution board shall be as
per manufacturer’s recommendations by a multiplexed system, providing
b) Time Day Clock, Time Elapsed Clock and Indicator shall be digital type
and clocks shall have high bright characters, not less than 30 mm in
height. Temperature Indicator shall indicate the theatre temperature and
shall be connected to the Air-Conditioning system.
c) The touch screen control panel should work as the central control panel
for the HVAC controls, instruction board, Peripheral& OT light control.
The controller should be capable of adjusting the temp. adjustment of +/-
5 Deg within 5 Minutes. The touch screen should be wall mounted,
stationed in the visibility line of the surgeon and OT staff. The access
height should be convenient for the nurse to operate and help/assistant
when in need. The panel should accommodate digital clock and the
elapsed time indicator. The medical gas alarm should indicate high and
low gas pressures for each gas service present in the OT including
vacuum. This should be supported by audible alarm also. The panel
should have an alarm mute (fault annunciation) facility. The sensors
(pressure switches) should be at the nearest isolation valve. Control for
general lighting: ON/OFF and dimming controls organized in groups to
provide uniform illumination. ON/OFF control of the operating light shall
be provided.
d) The Control Panel should be able to display the Isolation Panel Alarm
Conditions along with MGPS Alarms, Digital room pressure indicator
(signal from pressure sensor shall be provided to indicate pressure
difference between OT and outside), HEPA filter bank differential
pressure indicator. The control Panel should be able to be integrated with
HIS/,.
The Pendant Service Heads should be supplied with medical gas terminal
units and 5/15 Amps. or 6/16 Amps. hybrid Sockets. Each pendant should
be supplied with outlets and probes as mentioned below –
Surgeon pendent shall have NIST connection for all gases to connect the
MGPS system.
arm height should remain to a height greater than 1950 mm above floor level.
An extremely quiet electric motor, dampened stoppers and very low hand
forces for horizontal movements shall be provided. Advanced
Electromagnetic/brake Pneumatic brake system shall be provided for various
safety requirements and construction facilities. Weight carrying capacity of the
arm should not be less than 180 Kg. Modern and very quiet, high-performance
motors as well special spindles are to be provided to realize precise & steady
movement. As a safety feature the motor should be equipped with an overload
protection. The large interior cross section for supply lines shall offer
completely new applications with 120 mm diameter. The Pendant Service
Heads should be modular with minimum 800mm head. The heads should be
capable of accepting a range of shelves, infusion poles, electrical
switch/sockets, gas outlets other accessories as specified in tender document.
The Pendant Heads should support the range of Physiological Monitor
Mounting Solutions. pendent shall have NIST connection for all gases to
connect the MGPS system.
The Pendant Service Heads should be supplied with medical gas terminal units
and 5/15 Amps. or 6/16 Amps. hybrid Sockets. Each pendant should be
supplied with outlets and probes as mentioned below –
16.2.4 LED OT Light, FHD Camera, Flat Head Panel Monitor and Recording
System LED OT Light
The storage unit should be made with 1.5 mm or above thick SS 304 sheet
panels. Storage Cabinet should be divided in two equal parts and each part
should have individual glass doors with high quality locking system. Each part
should be provided with shelves. The shelves should be of SS 304 &
removable for cleaning. The minimum overall size should be 1800 mm (H) x
1200 mm (W) x 400 mm (D) (approx.).
A Hatch box of 600 mm (H) x 600 mm (W) 450mm (D) size should be provided
in the Operation Theatre as specified in the scope of the work to remove waste
materials from the Operation Theatre to Dirty linen Area just adjacent to
Operation Theatre. Each Hatch should be equipped with two doors and the
door should be operated electrically / manually. The Hatch box should be
designed in such a way that only one door should be opened at one time. The
UV light should be so installed that it is kept ON while both the doors are
closed, this UV light must be automatically turned OFF in case of opening of
either of the doors. There should be indicators on both sides of the OT so that
the door open/close status can be monitored from both ends. Hatch Box should
be manufactured from Stainless Steel, grade 304. It should have a glass vision
window on each door with at least 5 mm thick glass.
The scrub station shall be equipped with 3 bays. The scrub station shall be
made of Stainless steel, Grade 304, with satin polish finish and wired. Compact
surgical scrub sink should be designed for use in OT complex providing for pre
procedural scrub up. (Double sink combination as suitable). Each fixture
should be fabricated from heavy gauge type 304 stainless steel (minimum
thickness 1.5mm) and should be seamless welded construction, polished to a
satin finish. The scrub sink should be provided with a front access panel which
should be easily removed for access to the water-controlled valve, waste
connections, stoppers and strainers. Hands free operation should include
infrared sensors with programmable adjustment. Thermostatic mixing, valve
control should be located behind the access panel and maintain constant water
temperature. Timing should be adjustable to meet individual application
requirements. Provided with infrared sensors, thermostatic control taps with
fail safe temperature controls. All units should have reduced anti- splash fronts.
Knee/foot/elbow operated switch should be provided additionally. The scrub
stations control system shall be based on advanced microprocessor. The
scrub station shall be sensor-activated 24V AC. The scrub station shall be
provided with user selectable time out control. The supply shall not be
interrupted in case of power failure or maintenance. The station shall be
equipped with thermostatic mixing valve to control the temperature of hot and
cold-water supply. The washing faucet shall be made of Chrome plated brass
hand. The minimum size shall be 1500 mm x 550 mm x 840 mm.
Electric power from the nearest SMDB shall be taken to the operation theatre.
Necessary cables, MCCBs / MCBs etc. shall be provided, which is within the
scope of the work. Isolated power supply, insulation measuring and protection
as per IEC standards should be provided. Earthed equipment bonding of all
exposed metalwork should be provided. Power sockets within the Operating
Theatres ancillary areas should be matched to the rest of the hospital. Each
wall of MOT should have minimum 02 Nos. 6/16A hybrid switch socket & 32A
industrial socket at any two walls as per IEC standard. Light fittings within the
clinical areas should be recessed LED type with control gear. Fittings should
be sealed in accordance with the standard IP65. All equipment should be fully
and permanently labelled to identify and describe the function, operation and
voltage of the apparatus concerned. Throughout and upon completion of the
electrical installation, tests in accordance with relevant sections of the local
wiring regulations should be carried out and the results should be recorded.
all circuits within the operating theatre. All internal wiring should terminate in
connectors with screw & clamp spring. Connections of the clip- on type
mounted on a CE complied rail & labeled with indelible proprietary labels.
Individual fuses or miniature circuit breakers should protect all internal circuits.
Complete schematic drawing with description should be enclosed with the
equipment. DB Should have minimum two 32A/16A (As per requirement) extra
circuits with MCCB/MCB for future uses like integration equipment, etc.
16.4 AHU System and Internal HVAC ducting & Exhaust system
a) Floor mounted Air handling units in double skin construction having 48mm
thick PUF Sandwich Panels at a static pressure of 120 mm WG complete
with backward curved blower, TEFC blower motor suitable for operation on
415 V +_ 10%, 3 Phase, 50 Hz, A.C. Supply complete with 8 Rows copper
tube, aluminium finned DX cooling coil, prefilter, micro-vee filters, Heater
Bank, Mixing Box complete with drain connections with anti-vibration
mounting and with VFD compatible motor.
b) The contractor or associated contractor for HVAC work shall execute all the
HVAC ducting, return air grill and interconnections for supply and return air
inside the modular OT.
c) The Internal ducting inside of the operation theatre should be done with duly
fabricated out of 20 SWG Aluminum sheet complete with flanges and
accessories such as GI suspenders and GI supports completely sealed
with Silicon sealant duly insulated with Aluminum foil, 12 mm thick Nitrile
rubber, self-adhesive type insulation. Supply & return air cabinet should be
made from SS304 and should be from the same manufacturer of ceiling
and wall panel. The exhaust air cabinets should be openable and
cleanable. These cabinets should have suction from bottom and top. Also,
it should match perfectly with the ceiling system aesthetically. Distribution
of exhaust air volume should be divided in such a way to maintain the
required pressure within the theatre without causing turbulence. Design
flow rate shall not be less than 1000 cu.m/ hour. Distribution of exhaust air
volume shall be divided between fluf strainers to maintain the required
pressure within the theatre without causing turbulence. The work shall be
carried out as per CPWD Specifications for HVAC works-2017
The contractor should ensure that all works carried out are to the
recommendations made in the HTM 2022/NFPA 99C / DIN. Contractor should
provide Oxygen, Air, Vacuum, Carbon Dioxide and Nitrous Oxide supply to
Operation Theatres from the existing lines terminated outside the OT.
Contractor shall be responsible for supply, installation, testing and
commissioning of complete MGPS system inside the operation theatre
including Distribution piping, Pendants, Outlets, and other essential
accessories. Terminal units should be gas specific and only accept the correct
medical gas probe. Gas specific components shall be pin indexed to ensure
that a correct gas specific assembly is accepted. Each terminal unit should be
Isolation Panel System of minimum 20 kVA capacity shall be provided for every
operation theatre to ensure the safety of staff and patient. System shall have
isolators provided through leakage relays etc., if required, according to IEC
recommendation. This unit shall be EN/European CE /UL /BIS /FDA /ETL
listed/certified. These systems are to be commissioned by specialists. It shall
be medical grade Isolation panel. It shall have fault detection feature. It shall
be compliant to CEI 64-8/IEC 60364-7-710/BS 7671 Standard as amended up
to the last date of receipt of tenders. It shall be compact and mountable on
wall. The IPS shall be able to integrate with HIS/, and Surgeon Control Panel
as standard. Isolation panel system shall have facility to detect fault of leakage
current for each circuit (Minimum 12 circuits) and same shall be integrated with
touch screen control panel of MOT and alarm status shall be displayed on the
touch screen control panel. The double frontal window shall be mechanically
interlocked. The panel shall have forced ventilation system.
17.1 The brief scope of work shall include Planning, design & preparation of
drawings, supplying, installation, testing & commissioning of Nurse Call System
for 100 bedded Hospital. Total system has to be commissioned with required
hardware, software, licenses and other items to have a fully functional complete
Nurse Call System. If any item is required to make the scheme functional, is not
specifically mentioned in the scope and specifications, the same is deemed to be
included within the scope of this tender. These technical specifications shall be
read along with the General Conditions for all E&M works given under subhead C-
B.
b) Assist Call System is the communication and automation system that allows
nurses in a patient room, when they need assistance from other personnel, to
call for such assistance. The origin of this call is indicated to auxiliary staff or
to other nurses through Over Door Lights, and as text messages on Nurse
Control Panels at service desks, and service performance is logged and
reported through the smart cards.
c) Code Blue System, is the communication and automation system that shall
allow health care personnel to make emergency code calls from all internal
phones of the hospital, Room Control Units in patient rooms and the Emergency
Service Consultation Panel that can be found in the emergency ward, when
Basic Life Support (CPR) is required in the hospital. The address of this call is
indicated and response performance is logged and reported by the smart cards
of the Code Blue team personnel. In case of respiratory or cardiac arrest, the
Code Blue System increases the success rate of Basic Life support by
immediately directing the expert personnel to perform resuscitative efforts on
the patient in any location within the hospital. In addition, it aims to increase the
service quality by recording incident and response data of all Code Blue calls
andgenerating various performance reports.
d) All devices and materials that constitute the system shall be new and standard
products. The products used must not have an EOL (End of Life)
announcement declared. The company shall commit to continueproduction of all
devices and components used in a system for a minimum of 5 years after the
implementation of the system.
f) A pull-cord call unit shall be placed in every WC/ bath room used by patients in
the hospital.
i) The system shall have full integration with the Fire Detection System, IP-
EPABX and , (Building Management System).
17.2 Nurse Call System consists of Room Control Units, Over Door Lights,
patient handsets, patient Bed side Call Units, patient Pull-cord Call Units, Nurse
Control Panels, personnel smart cards and hospital call system software designed
to perform as stated above.
a) Room Control Units shall have a structure capable of controlling the call
system within each room. Its outer casing shall be made of non- flammable
PC-ABS- FR material.
b) Room Control Units shall send all calls and system information including
time stamps and origin addresses of all Bed Side Call Units, patient hand set
and Pull-cord Call Units within the room to the hospital call server using the
static hospital call server’s IP address.
c) Room Control Units shall store all calls and system information they receive
until a verified connection is made with a server. The RoomControl Unit shall
store at least 100 records; when the connection is made, it shall
automatically send the records it holds to the server.
d) Room Control Units shall have SIP (Session Initiation Protocol) support and
allow speech communication.
e) Voice calls made over the Room Control Unit shall be able to be recorded
over the server based on request. These records may be reviewed on
the logs of the server interface.
f) Room Control Units shall be able to work directly with a Nurse Control Panel
without any issue if there is no connection with a server.
g) The connected devices may be monitored on the Room Control Unit. The
main screen of the room control unit shall be able to show which patient
made the call. For observation, rooms with multiple beds, for identification,
x) Room Control unit comprises of touch screen LC colour graphic display for
displaying all details (Active /offline call). The system shall be able to do
internal & external call or conference call, full duplex speaker phone in
brilliant sound quality & inbuilt microphone. The Room control unit shall be
able to communicate to own or other nurse station, hospital staff, code blue
and other custom emergency codes through screen menu. Patient
information from HIS (Hospital information system) should be monitored on
the server system through the corresponding bed icon on screen. If desired,
the information about the patient can be edited through the touch screen.
The room terminal shall have inbuilt card reader for Nurse attending the
patient. The system shall be self-sufficient to share data to central Nurse
management station.
a) LED technology shall be used in Over Door Lights. LED Indicators Module
at outside of each ward with ecofriendly LED. It shall warn with three main
colour red, green, blue, and combinations of these depending on the call
status of the room.
b) It shall consist of red, green, and blue colored warning lights. Upon request,
different color combinations for different calls with RGB matrix shall be
created.
c) In normal condition, no light shall be lit. If the patient makes a nurse call, a
red light shall be lit within 0.5 seconds. After the nurse call, when the nurse
makes an authorized card entry on the Room Control Unit, the light shall turn
green. If an Assist Call is made, the green light shall flash with 2 second
intervals. If a Consultation Call is made, the light shall flash red and green.
d) In blue and white emergency code cases, the blue light shall be lit, and shall
only be able to be terminated via authorized entry to the room control unit.
e) he Over Door Light shall give information by lighting in different colors based
on other non-nurse personnel presence in the room, white bydefault.
f) The outer casing of the Over Door Light shall be made of non-flammable
PC- ABS-FR materials.
g) Room Control Unit–Over Door Light connection shall be made with Cat 6/6E
UTP cable and RJ 45.
a) The Bedside Call Unit shall be mounted on headboards where there are patient
headboards, or on the walls where it can be implemented within the system.
c) On its FRONT side there shall be: A “start call” button with Nurse symbol.
d) Backlight in order to give visual information about the call status and easy
visibility of the unit at night.
f) No DIP (Dual In-line Package) switch or similar method shall be used in the
function assignment for these buttons.
h) Its connection with the patient handset shall be easily established by connecting
via RJ45. It shall be protected against forcing and stretching.
i) A nurse call can be initiated via the patient handset nurse call button or the
call initiation button of the Bed Side Call Unit. These two buttons shall be
accepted by the system as equivalent. In the event that these buttons are
pressed.
j) If the unit is able to transmit the call to the Room Control Unit, the LED on the
unit shall flash with 1.0 second intervals. Call transmission information shall be
audibly notified to the patient.
k) If there is an error in call transmission, a continuous red light showing the error
status and shall only stop when the call termination button is pressed or room
control connection is made. Subsequent presses of the button shall trigger an
audio alert each time.
l) Its connection shall be made with Cat 6/6E UTP cable and RJ45.
a) The patient shall be able to inform to nurse. The handset shall be complete
with module & accessories as required for installation
b) There shall be a call button for the patient to initiate a call. It shall not need
an external power supply. Its connection shall be made via Cat 6/6E HF
cable and RJ 45. Patient hand set shall be made from nonflammable PC-
ABS-FR materials.
a) The patient shall be able to speak directly to the nurses. This system allows
hospital staff to save time on service, prioritize critical cases, and comfort
patients through voice communication. The handset shall be complete with
module & accessories as required for installation.
b) It shall not need an external power supply. Its connection shall be made via
Cat 6/6E HF cable and RJ 45. Patient hand set shall be made from
nonflammable PC-ABS-FR materials.
b) On its Front side, there shall be: A call pull-cord with minimum 1.5 m
length to serve as a call initiation button, A call termination button
(indicated by a green check mark symbol).
a) The Central Monitoring Unit shall be web based monitored that shall observe all
activities such as nurse calls, code blue (and any custom emergency codes),
assist calls, and nurse presences throughout the hospital. It shall show picture
IDs of personnel that are present in-patient rooms. Different parameters (call
type, department, and floor info) can be filtered based on needs. In this way, the
focus of health personnel can be directed and reaction and intervention times
can be minimized.
c) The Central Monitoring Unit shall display real time status of all or selected call
types originating in all or selected areas of the hospital.
d) The Central Monitoring Unit shall display these calls with icons and
colors indicating their type. The time elapsed since the initiation of the call and
the time stamp of the call shall also be visible.
17.3.7 Server:
Server Shall be available to control the system. The server shall be able to
provide log reporting through a web interface and shall have option to
integrate system throughout the building.
18.1 The brief scope of the work shall include Planning, design & preparation of
drawings, supplying, installation, testing & commissioning of Water Supply
system equipment including Pump sets, Panels, VFDs, Cabling and other
connected items required to supply, and to install a complete Water Supply
System. If any item required to make the scheme functional and is not
specifically mentioned in the scope and specifications, the same shall be
deemed to have been included within the scope of this tender. These
technical specifications shall be read along with the General Conditions for
all E&M works given under subhead C-B.
18.2 The water supply to the hospital campus shall be met from the local
Municipality /Tube Wells/ Bore wells and treated water from STP.The water
so received shall be treated to make it fit for human consumption, hospital
needs.
i. CPWD specifications
ii. National Building Code 2016.
i. Contractor shall consider water capacity for half day on terrace over
head tank and one-and-a-half-day capacity for underground water
tank.
iii. Bore well water shall be fed into underground raw water tank,
where, it shall be treated with Water treatment Plant (WTP).
Treated water shall be fed into underground firefighting tank and
overflown water from firefighting tank shall be stored in the
underground treated water tank.
vii. Water coolers in each floor shall be supplied with R.O. water
from R.O. plants, under gravity or automatic pumping system.
The casing shall be of rigid construction and shall have side suction and
side delivery in case of vertical multistage pump and side suction and
central delivery in case of horizontal centrifugal pump.
The pump shall have small length suction and delivery pipe connections
Impeller and shaft shall be of Stainless Steel SS 316.
Shaft sleeves shall be provided to protect shaft from any damage. Bearing
shall be ball or roller type. Mechanical seal shall be provided to avoid any
leakage.
Pumps shall be so selected that the design duty point is within 5% of the
maximum efficiency point. Shut off head shall be 120% of duty point head.
All pumps and motors shall be of minimum vibration and noise level during
operation. Facilities shall be provided to prevent starting of pumps when
the water is at low or high level in the tank. An indicator for this low/high
level alarm shall be provided. Facilities to select which pump to be duty
pump and standby pump shall be provided and be interchangeable and
this should be manual/automatic.
Leakage from pump gland shall be drained to the nearest floor waste.
The system operation will be such that the initial small water demand shall
be met by the charged diaphragm pressure vessel. When the water
demand continues, the system pressure will dip to a pre-set pump cut-in
point then the lead pump starts to operate at reduced speed through the
variable speed drive. However, if the system pressure is still below the pre-
set value, the controller continuously increases pump speed to meet the
system demand. When the lead pump is not able to meet the system
pressure at full speed, the second pump also starts to operate.
The motor control panel shall be equipped with all the necessary electrical
components including a microprocessor control unit and a frequency
drive. The control panel and the microprocessor shall cover the followings
functions.
In case of lead pump failure due to motor overload, the standby pump
shall be switched on automatically. Alarm signal is displayed on the LCD
Display unit and alarm lights are to be activated. Functions to limit the
number of start/ stop of pumps per hour.
i. Auto mode
The desired delivery pressure within the range specified, shall be set at
the control panel. The pressure transmitter shall detect the delivery
pressure continuously and give feedback to the microprocessor which will
control the variable speed drive frequency converter for speed control of
the duty pump. When the demand increases, the subsequent pumps in
the system will be activated to boost up the pressure. Ultimately the duty
pump set shall be operated fully automatically to maintain the delivery
pressure constantly at the desired set value.
The on/ off function of the pump shall be manually adjusted at the
microprocessor provided at the local control panel. Frequency Control By-
pass Mode shall be provided. All the pumps shall be started/ stopped
automatically with the pump output at fixed maximum rotational speed. All
the control and protection functions shall remain active. The cut in/ cut out
pressure shall be internally calculated by the microprocessor for each
pump.
The panel shall be built to start the pumps in suitable starting modes.
All suction, delivery and header pipes shall be GI & shall conform to IS:
1239, medium duty. Fittings shall be as per the pipe thickness. All pipes
shall have flanges connection. All hardware shall be zinc plated. The
system shall be equipped with suction & delivery valves as flanged valves.
On suction side ball/gate valve shall be provided, while on delivery side
ball/ butterfly valves shall be provided. Also, spring operated check valves
shall be provided on delivery side of each pump & on delivery header. In
case of negative suction, foot valve shall be provided for each pump
suction or suction header. Flexible bellows shall be provided on suction &
delivery side of each pump.
vi. Accessories
The system shall be provided with all accessories such as base plate,
mounting pads, foundation bolts, foot valves, pressure gauge, pressure
switches, pressure transmitter, level indicator, isolation valve for pressure
vessel, etc. All accessories required for proper and safe operation shall
be furnished with the pumps.
The R.O. plant shall comprise of R.O. High Pressure Feed Pumps (HPP),
RO Raw Water Pumps (RWP) of Vertical multistage centrifugal type and
suitable head to generate permeate flow as per requirements. The pump
casing and impeller construction shall be of SS-316. The motor shall be
TEFC with minimum IE-2 efficiency suitable for operation on supply of
415Volts, 3 Phase, 50 Hz. A.C. Supply. The pump shall be supplied
complete with base channel, coupling foundation bolts, pressure gauge,
valves at inlet and outlet of each pump. One standby pump needs to be
considered for each type. Capacity of R.O Plants shall be selected based
on the functional requirement (RO water demand) as stated above within
minimum operating hours (preferably 8 hrs. /day).
Tank shall be provided with water flow meter at inlet & outlet, inlet& outlet
valves, overflow, drain connection. Centralized control panel made out of
CRCA sheet min. 2mm thick having main contactors for all pumps.
All control and power cabling shall be provided. Earth leads shall be
connected to the structural earthing points available at the terrace. An
emergency stop push button shall be provided in the panel.
Refrigerant : R134A
Thermal Insulation :
10oC – 25oC
•
Chamber Hydraulic Test Certificate
•
Jacket Hydraulic Test Certificate
•
Pressure Safety Valve
•
Vacuum Safety Valve
•
Door Plate Operating Accuracy
•
Pressure Gauge Accuracy Test Certificate
•
Compound Gauge Accuracy Test Certificate
•
Temperature Gauge Accuracy Test Certificate
(U) Quality Control Certificates:
• US FDA/European CE certified with four digit notified body
number / BIS 3829 Parts -1
• ISO Certificate
• ISO 13485:2016 Certificate
• CE Certificate
• IEC 61010-1:2010 Certificate
• ISO 14001:2015 Certificate
• ISO 45001:2018 Certificate
• BS EN ISO 17665-1:2006 Certificate
• BS EN 285:2015 Certificate
(V) Spare Parts with each Sterilizer:
• 3 Heating Element
• 2 Nos. Seamless Silicon Gasket
• 2 No. Pneumatic Control Valve
• 2 Nos. Pneumatic Control Valve
(W) Accessories (Optional)
• S.S. Material Un-loading Trolley 2 Nos. Each Sterilizer
• SS 304 Material Loading Carriage 1 No. Each Sterilizer
• Panel Mounted Printer
(2) Rapid Sterilizer (Flash Autoclave) Table Top Capacity 24 Ltr)
• Should be a class b Steam sterilizer with efficient vacuum & drying
system
• Should be fully microprocessor controlled high pressure rapid
sterilizer.
• Should have cycle suitable for wrapped, unwrapped, rubber, &
Prion & should have user defined cycle facility also.
• Should have test program : BD & Helix and leak test.
• Should have design pressure ranging from -0.1 MPA to 0.3 MPA
• Designed temp upto 144 degree c
• Working temperature range of 105 to 138 Degree C.
• Should have cycle time between 20 min to 60 min depending upon
the load.
• Chamber Structure: Cylindrical , Horizontal
• Chamber Capacity: 24 Liters
• Chamber dimension not less than: 250mm *450mm
• Weight not more than 60 kgs
• Should have automatic door opening through press of a button
• Power Supply: 230 V/50 Hz
• Should have instant built in seperate steam generator.
• Should have LCD screen for display of Pressure , temperature,
time, running process ,error
• and alarm information.
• Should have built in printer to print the data during cycle operation.
• Should have protection device for over temp., for steam generator
& should have door safety interlock protection & chamber over
pressure protection.
• Chamber should be made of 304/316 S.S quality
• Should have three loading trays
• Should be European CE certified and as per directive 93/42/EEC
of MDD
• Chamber design should be as per PED directives/ ASME.
• should be as per ISO 9001:2015
(3) Washer disinfector 265 Liter. (12 DIN Basket 2 Door) with
accessories
• The washer disinfector should be suitable for cleaning and
disinfection of surgical instruments / goods. The process should
include pre-wash, detergent wash and hot water disinfection,
rinse and drying cycles.
• The unit should be suitable for electrical operation and would be
complete with water circulation pump, necessary valves &
fittings.
• It should be microprocessor based so as to ensure correct
program sequence and irregularities or deviations which are
displayed immediately.
• Chamber Capacity: Chamber capacity: Operational Volume
should be able to process minimum 12 DIN trays
(Approx480X250X50)with 6 levels in single process. Should
supply 12 Nos of standard Stainless-steel DIN trays. The
chamber should be made of S.S. 304 or S.S. 316 L quality with
electro polished washed surfaces. The chamber edges should
not have the pockets & folds so as to avoid bacterial growth. The
wash chamber should also be fitted with bright light for clear
visibility of the washing process.
• Washer should have following features:
• Touch screen having facility with 21 CFR part II features like alarm
logging, alpha numeric password and under id setting.
• Data back up with online thermal printing & USB (optional).
• Temperature sensor for accurate measuring and controlling of
Temp. in the Chamber.
• Temperature controlled by PID to keep temperature within 2 C to
set point.
• Pressure sensor for measuring & controlling the pressure/
vacuum that the loading subjected to during removal & charging
of gas.
• Automation system powered with UPS (1 KAV) for uninterrupted
cycle.
• If any malfunction happen like pressure sensor, temperature
sensor, vacuum system, vacuum break failure display will give
massage on screen.
• Manual operation can possible with password protection in any
emergency.
• Password setting can be manage by customer.
• All action on touch screen need password access to avoid any
unwanted intervene.
• Minimum 3 hrs Aeration for removal of EO residue.
• System will also indicate if cartridge has lower quantity of gas or
not puncture properly.
• Before EO injection system will check chamber leakage in every
cycle.
• System will give High temperature alarm if chamber temperature
is higher 3° C from set point
(14) Work Table for Wet Goods for dirty area, Dry Goods for Clean
area, Goods for sterile area.
• Minimum Size. (LxWxH):1800x650x900 mm
• Stainless steel tables specially designed for working with dry
goods and for general purpose pre-storage.
• The work tables should have a rigid stainless-steel
construction which is easy to clean and without sharp edges
or corners.
• The table should be ergonomically worked up, should have
easy to clean robust matt finished (to reduce reflection of
light from the surface) with minimum sheet thickness of 1.5
mm stainless steel (304) worktop/surface to withstand and
carry out heavy work comfortably, either sitting or standing.
• The edges along the front, back and sides should be
reinforced and widened to 37 mm, giving a rigid
construction.
• They are welded together and polished at all corners for
good hygiene, as well as for the comfort and safety of the
staff.
• The worktop should be supported by a complete assembly
with full-length reinforcements along the front, back and
ends, welded together at the corners.
• The worktop and support frame are bonded together with
double-adhesive tape of a special, age-resistant quality to
give rigidity and noise abatement.
• The support frame should be mounted on a solid, stable floor
stand, made of polished stainless-steel square tubing, with
horizontal braces 300 mm above floor level. An adjustable10
cm (± 25 mm) plastic foot, easy to clean, is mounted on each
leg
• The provision is to be made for a sturdy 445 mm-wide
stainless-steel shelf
(18) Wire Storage Shelf module for dirty / disinfection area, Clean
supply area & for Sterile Store.
• Minimum Size (LxWxH): 1525x455x1895 mm
• Construction should be based on single free-standing shelf
modules for storage of clean linen, instruments, and packing
material or sterilized goods, including disposables.
• Moreover, two single modules can be placed back to back
and combined as a double module unit.
• If two units should be connected, 10 S-hooks should be
supplied.
• The wire construction should allow good air circulation while
permitting easy inspection of the goods.
• The wire shelves should be made of special heavy-duty
steel (304), chromium- plated and surface treated with clear
epoxy varnish to facilitate cleaning.
• The shelf unit should be easy to assemble on site and all
parts should fit precisely.
• Shelves should be mounted by means of plastic clamps onto
circular rigid posts, with the adjustable height within a range
of about 50 mm. Each post should include a height
adjustable foot.
• Each unit should include 5 shelves.
• The shelf unit should have optional Ø 125 mm castors for
using as a mobile storage unit by replacing the foot with
castors.
(19) Free Standing basket rack (15 Baskets) for Sterile store:
• Size (LxWxH): 1850x480x2150 mm(Single),
1850x800x2150 mm(Double)
• Quotations should be offered for both single and double
basket storage racks to store wire baskets in sterile storage
and/or as pre-storage of clean packed goods.
• The rack should be designed as an open unit to promote
aeration of sterilized goods and to make inspection of stored
goods as easy as possible.
• Should provide rigid, horizontal guide-rails, consisting of 50
x 20 mm steel profiles for loading and unloading the baskets
by sliding the baskets on rail.
• The guide-rails should be welded to a robust support column
mounted on a rigid floor stand.
• The columns should be joined by support frames on top and
below the base of the rack.
• To facilitate cleaning of the floor, the base should have a
rigid construction that minimizes the number of legs needed
for support.
for airing between goods and work surface and to allow use
on roller, belt and chain conveyors.
• It should be electro-polished for smooth, clean surfaces and
also suitable for ISO modular wire baskets.
(26) Modular Sterilizing Baskets Big:
• Dimensions: 580 x 300 x 280 mm. (length x width x height)
• Made of electropolished AISI 304 stainless steel.
(27) Office Table Complete with all accessories
(28) Shoe Rack Complete with all accessories
(29) Computer
1 9 . 2 LAUNDRY Equipments
3. All under shelves shall be constructed in 1.2mm thick S. S. Sheet and supported
by sturdy S. S. Angle framework.
4. All under shelves shall be bent down in 38mm and inside 12mm.
5. All uprights (main legs) shall be 38mm OD S. S. pipe 1.6mm thick with S.S. adjustable.
7. All top frames and vertical members shall be made out of 38x38x3mm marked S. S. Angles.
8. Frames for under shelves shall be made out of 30x30x3mm ISI marked S.S. angles
9. All front panels shall be made in 1.2mm thick S.S. Sheet of cooking equipment.
10. All sides/ rear panels of cooking equipment shall be made in 1.0 mm thick
S. S. Sheet.
11. Sides/ rear panels of Food Pick - Up Counter shall be made in 1.2/1.0 mm S.S. Sheet.
12. All sinks shall be made in 1.6mm thick S.S. Sheet, argon arc welded coved
to 38mm radius and provided with drains duly welded.
13. Drawers shall be of size 500x500x125mm having telescopic slide rails with
double walled front and recessed handle.
14. All doors shall be in 1.2mm thick S.S. Sheet with reinforcement channels, Magnetic
catchers, recessed handles and facility for pad locks.
15. All side bracing shall be made of 25mm OD 1.6mm thick S.S. Pipe.
16. Dish Wash equipment tops shall be recessed by 25mm on account of drip less marine
edges.
17. Garbage chute shall be made out of 1.6mm thick S.S. Sheet and shall be 150mm dia. x
100mm.
18. Cooking range grates shall be of Cast Iron for standard sizes and shall be
fabricated with M. S. square rod in case of special sizes.
19. All cooking ranges shall have drip trays in 1.2mm thick S.S. Sheet with handles of
1.2 mm thick S.S. Sheet.
All burners will be of United – Bombay make or HPC make and shall have pilot flames.
23. All main burners and pilot burners shall have individual needle control valves.
24. All burners shall be duly calibrated for heat output and flame characteristics.
26. Deep Fat Fryer tops / tanks shall be in 1.6mm thick S. S. Sheet with dripless edges
complete with drain valves, double walled construction and frying baskets.
28. Tea Water / Milk Boiler shall be fully constructed in 1.2 mm thick S. S. Sheet
31. Insulation shall be mineral wool, glass thermocool or puf as in where required.
36. Castors shall be of Semsons – Delhi and shall be of swivel /fixed type as erequired.
Castors shall have brakes wherever needed.
38. All counter top equipment shall have white nylon legs.
39. Overhead Shelves/ Wall Shelves shall be made of 1.2mm thick S.S. Sheet bent
down 50mm and in 12mm S. S. Channels, 25mm OD, S.S. pipe uprights and S.S.
Round gussets.
40. Exhaust Hoods shall be constructed in 1.0 mm thick S.S. Sheet with S. S. Baffle
Filters and Bulk Head light fittings.
41. Aluminum Racks shall have shelves of 2mm thick anodized aluminum
sheet reinforced with 25x100x25 mm channel of same material and
38x38x5mm aluminum angle uprights.
42. Pot racks shall have uprights of 38mm OD 1.6 mm thick S.S. Pipe and shelves of
25mm OD 1.2 mm thick S.S. Pipe with all welded construction.
43. Oven interiors shall be in 2/2.5mm thick M. S. Sheet oven exteriors in 1.2 mm
thick S.S. Sheet, oven front in 1.2mm thick S.S. Sheet and oven door exterior in 1.6
mm thick S.S. Sheet.
44. S.S. Sheet shall be only AISI 304 grade for tops, sinks and tanks AISI 304 grade
All finish shall be smooth, without any chatter or vibration marks and having uniform
polishing grains all around.
47. Refrigerators interiors shall be in 0.9mm thick S. S. Sheet and exterior in 1mm
thick S. S. sheet. Compressor shall be of Kirloskar make, indfoss thermostat with
Puff Insulation. Door shall have integral Handle and springs for self closing and shall
have locking arrangement.
48. Front of Display Cabinet shall be of curved glass and shall be in 12mm thickness.
Sides glass shall also be in 12mm thickness Display Cabinets shall have shelves of
1mm thick S.S. Sheets duly copper coiled beneath for affective cooling.
49. S. S. Racks shall have shelves made of 1.2mm thick S. S. Sheet welded to
upright or nut bolted to uprights with gussets as stated. Uprights to be of
38x38x2mm thick S. S. Angle.
50. All material to be processed through NC shearing & CNC bending machines only.
Warranty: OEM / Contractor shall provide standard 36 months warranty for the offered
products.
Note : Equivalent material and finishes of any other specialized make may be
used in case it is established that the brands specified above are not
available in the market but only after approval of the alternate by the
Competent Authority/NIT Approving authority. In case make of any
equipment or material is not specified in the NIT the decision of Engineer-
In-Charge in this regard will be final
I.V. Tracks:
Technical Data:
• High quality extruded aluminium 6063-T5. 1-3/8" Wide x 3\4" deep
& 0.06" thick track, integrated with false ceiling.
• Clear anodized finish or white powder coat finish as per
instruction of Engineer-in-charge.
• Dual channel to provide smooth and snag free operation
consistently.
• Continuous radius bends to be done in 36" or as per site
situation.
• Radius Bends that include a straight piece after the bend in the
following radius: 12", 21", 24" as per site situation.
• The IV track system will be surface or suspend mounted
installations.
2 MCBDB & Loose wire Box (Only Schneider Electric/ Legrand / L&T/ ABB/
Premium series) Seimens /Havells/C&S
3 Change Over Switch (Only Premium Schneider Electric/ Legrand / L&T/ ABB/
series) Seimens /Havells/C&S
4 Automatic Transfer switch (ATS) (Only Schneider Electric/ Legrand / L&T/ ABB/
Premium series) Seimens
/Havells/C&S/Asco/Russel/Socomac
5 FRLS PVC ins. Copper cond. Single Finolex/ RR Kabel/ KEI/ Havells/ Polycab/
core cable for wiring (ISI marked) Grandlay
6 Armoured/ Unarmoured telephone Delton/Finolex/ RR Kabel/ Havells/
cable, coaxial cable Bonton/AKG
7 MS Conduit (ISI marked) with heavy BEC/ NIC/ AKG
duty MS Conduit pipe accessories.
8 PVC Conduit (ISI marked) with heavy AKG/ BEC/ Precision/Anchor / Polycab
duty PVC Conduit pipe accessories.
9 Modular Switch, Socket/Telephone Legrand (Arteor)/ Schneider Electric
socket/ cable TV Socket/ Data outlet (Zencilo)/ Wipro (North West-Platia/MK
socket/ Fan Regulator/ G I Boxes Etc. (blenze)/Havells (Murano)/Honeywell
(Wiring Accessories). (Only Premium
series)
10 Selector Switch & Toggle switch Sailzer(L&T)/ Siemens/ ABB
11 PVC Trunking MK/Schneider Electric / Legrand.
12 GI pipe Tata / Jindal (Hissar)/ Prakash, Surya.
13 Paints ICI/ Asian/Berger
14 Terminal Block & Connectors Elmex/ Wago/ Hensel/ Connectwell
15 phenolic laminated sheet/ Bakelite Hylem/ Formica (P-I grade)/ Mylam/
sheet Greenlam.
16 Cat-6 cables, Wires & Fiber optic cable Amp, Avaya/Beldon/Legrand/Molex/
Schneider/Bonton/Anchor/AKG
(B) Fan & Fittings
1 Exhaust Fans/Fresh Air fan Havells, Crompton, Almonard, Orient,
Usha.
2 Ceiling Fans Havells, Crompton, Orient, Usha.
3 LED fittings Havells/ Phillips/ Lighting
Technology/Wipro/Regent/Trilux
27 Thermoplastic pipe for first Aid Hose New Age/ Safeguard/ Lifeguard/ Padmini/
Reel (ISI Marked) Omex/Eversafe/ Kalpex.
28 Fire Sealant Promat/ Birla 3 M/ Hilti
Kalpex
34 Dry Battery Exide/ Amar Raja/ HBL/Amco
35 Battery Charger Statcon/ Amar Raja/ CDC/ AE/ Expofyn/
thycon India
36 Epoxy Paint ICI/ Asian/Berger/Nerolac
37 Air Release Valve Rb/ Tbs/ Cimbrio/ Zoloto
38 Analogue/ Digital Measuring AE/ Rishabh/ L&T/ C&S/ Conzerve
Instruments (Voltmeter/ Ammeter/
Energy meter/ KW/ PE/ Multi-Function
meter)
39 Aluminium / Copper power cable / Finolex/ RR Kabel/ KEI/ Havells/ Polycab
Control cable (Armoured / Unarmoured) /AKG
40 Cable glands & Lugs Comet/ Dowells/ Hax Brass (copper Alloy
India)/ Jainson/ Action
41 Solenoid Valve / Spray Nozzle Perker/ HD/ Tyco/ Emersion
42 Sprinkler HD/ Tyco/Reliable/ Wormald/Viking
43 Sprinkler Heads/ Water Curtain Nozzle Tyco/ Viking/ Omex/ Newage/ Lifeguard
44 Steel Flexible Extension Omex/ Newage/ Tyco/ Lifeguard/ Kalpex.
(G) PA System
1 PA System Tyco/ Honeywell-Notifier/ Bosch /
Johnson Control
2 Junction Boxes Customized
3 Speakers Bosch / Bose/ JBL/ Honeywell
4 Amplifier Bosch / Bose/ JBL/ Honeywell
5 Microphone Bosch / JBL / Philips / Honeywell
6 Fire Survival Cables/ Circuit Havells/ Finolex/ KEI/ RR
Integrity Cable Kabel/Belden/Rallison
7 MS Conduits BEC/ AKG/ NIC
(H) UPS System
1 UPS System (Minimum Level-3 Schneider / VERTIV /
Inverter topology Legrand(Numeric) / ABB / Eaton /
only to be used) Mitsubishi
2 Sealed Maintenance FreeBatteries
Exide / Amaron / HBL / Rocket / Hitachi
/ Panasonic / Amco
(I) HVAC
1 Chiller Unit (AHRI Certifiedonly) Johnson Controls (York) / Carrier /
Daikin / Trane / Blue Star / Voltas /
Dunham Bush
2 Cooling Towers -CTIApproved Bell / Paharpur / Advance / Mihir
/Baltimore air cool
3 Cooling Tower Watertreatment Hydropath / Merus / Nalco / Sensorex
4 Air Handling Unit (Double Skin) /(Note: Systemair / Zeco Aircon / Edgetech /
All equipment shall be Eurovent Flaktgroups / VTS / Carrier / York / Trane
certified, AHRI certified coils and / Nutech / Humidin / Citizen /DJK
AMCA certified fans.)
5 TFA units, / Cooling Coils / Fan coil unit Systemair / Zeco Aircon / Edgetech /
/ Air Washer / Air Scrubber Flaktgroups / VTS / Carrier/ York /
Trane / Nutech / Humidin / Citizen /
Midea / Putoria
6 Centrifugal Pumps sets Siemens / Schnieder / Danfoss / ABB
/ Fuji/ Allen Bradly / Grundfos /
Armstrong/ Xylem / Kirloskar / CRI
/Crompton / Wilo
7 Pumps with VFD controlpanel Siemens / Schnieder / Danfoss / ABB /
Fuji/ Allen Bradly / Grundfos /
Armstrong/ Xylem / Kirloskar / CRI
/Crompton / Wilo
8 Centrifugal fans, Inline fans, Jet fans, Zeco / Edgetech / Systemaire / Nicotra
Axial fans, Propeller fans, Exhaust / Kruger/ GreenHeck/
air Comefri /Humidin / LAU
fans (AMCA certified) /OST Berg / Maico
9 HEPA Filters, Pre Filtersand Fine Thermadyne / Klenzaids / Spectrum /
filters Camfil / AAF / Airtech / Puromatic /
Attenuators / / Tristar
67 Pot Strainers / Y-Strainers Rapid Cool / Sant / Trishul / Emerald /
Castle / Advance /Lakos / victaulic
68 Humidifier / Oil drip heater KEPL / Emerald / Rapid Cool
69 Thermostat / Humidistat /Duct Danfoss / Belimo/ Schneider/ ABB/
Temperature Sensor Honeywell/ Trane/ Johnson Controls /
Siemens/ Greystone/ Dwyer/ Omicron
/ L&T / Ira
70 Thermometer Penn-Plax / Teddington / Emerald/ H-
Guru / Metzer/ Bestobell/ Star
Scientific
71 Pressure gauge Penn-Plax / Teddington / Emerald/ H-
Guru / Forbes Marshall / Wika / Arrow
/ Dwyer / Taylor
72 Room Temperature, RHSensor Belimo / Schneider / ABB /
Honeywell/ Trane/ Johnson Controls /
Siemens/ Greystone/ Dwyer/
Omicron
73 Pressurization unit Armstrong / Bell & Gosset / Anergy
74 2/3 way control valve withmodulating Schneider / Belimo / Johnson
actuator Controls / Danfoss / Honeywell /
Siemens / L& T / SbtDats
75 DCC control for AHU Schneider / ABB / Danfoss /
Honeywell / Johnson
Controls /Siemens
76 Modulating Motors Belimo / Honeywell / Danfoss /
Johnson Controls
77 Vibration isolators Dunlop / Emerald / Ressitoflex /
Easyflex / Cori/ Bdk /
78 Water Flow switch &Pressure Switch Danfoss / Emerald / Anergy /
Honeywell / Johnson Control / Belimo
/ Siemens
79 Desiccant coated Enthalpy DRI / Ostberg / VTS
Recovery Unit (Latent +Sensible):
Wheel Only
80 Central Air Cleaner System Magneto / Honeywell
(Electronic filtrationsystems)
81 Air separator / Pressurized Expansion Anergy / Emerald / Rapid Cool
Tank / vacuum degasser / Flamco / Amtrol / Bell and Gosset /
Derrik / Tenova / Armstrong /
Grundfoss
82 Jet Nozzles Ruskin - Titus / Systemair / Airmaster
/ Caryaire / Dynacraft
83 Airstat Honeywell / Belimo/ Rapid Control
84 Aluminum Foil Tape Birla / 3M/ Jonson
85 Suction guide Anergy / Sant / Emerald / Armstrong
86 UPVC Pipe Astral / Supreme / Finolex / Ashirwad
Prince / AKG
87 Air Curtain Beacon/ Thermodyne, Envair Electro
dyne
88 Smoke sensor / CO Sensor Honeywell / Danfoss / Johnson
Control / Actis / System sensor /
siemens / Kele
(J) Solar Water Heater System
1 Solar Hot Water System Racold / V-Guard / TATA BP Solar /
Emmvee Solar / Solahart / Venus/
Honeywell/ EPL India / Suntech /
Rashmi Industries / Kotak Urja /
Photan / Greentek Northern
2 Insulation for Hot water Thermaflex / K-Flex/ Arma cell /Supreme
pipes / AKG
(K) LAN System
1 Wireless LAN Solution, Wireless Cisco / HP / Extreme / Arista/ R&M /
controller, Web Security Solution, Impulse / Ruckus / Juniper / Aruba /
Web Application Firewall Panduit/ Allied Telesis
solution, Wireless LAN
2 Managed Network Switches, Cisco / HP / Extreme / Arista/ R&M /
Core Switch, Distribution Switch, Impulse / Ruckus / Juniper / Aruba /
Access Switch, Fiber Module, Panduit /Nexus / Allied Telesis
Wireless Access Point
3 End point security Cisco / Aruba / SolarWinds / Everest /CA
Technologies Secure
4 Server / Networking Rack (wall mount / Rittal Emersion / APW / Netrack / WQ/
floor mount) Panduit/ Valrack / Derwiser / MTS
5 Cat-6ALAN Cable/ OFC and Panduit / Belden / Systemax
accessories. /Commscope / Legrand / R&M /Siemens
/ Derwiser / Siemon
6 Patch panel / Patch Cord / Fiber patch Panduit / Belden / Systemax
cord / pigtails / Adapters / Connectors /Commscope / Legrand / R&M /Siemens
/ Derwiser / Siemon
7 Hospital Information / Wipro Limited / Napier Healthcare /
management System Tenwave Healthcare /Icons
8 Queue managementsystem Wavetech / Qmatic / Plutron / Irisys /
Honeywell /Icons
9 Firewall/Router Cisco / Fortinet / Sophos/ Juniper/Arista
(L) EPABX System
1 EPBAX IP based Server with Cisco / Alcatel-Lucent / Ericsson /
Licenses / IP Phone / PC based Siemens / Avaya / Unify / NEC /
Operator Console /IP Phone/ Analog Panasonic / Matrix / Tadiran/ Arista/
Phone Toshiba
2 Telephone Cable / TV Co- Finolex / Havells / RR Kabel / KEI /
axial Cable L&T / Polycab / Molex
3 MDF Box ADC / GE / Malson / D-Link / ITL /
Legrand / Krone
Note: The firm has to ensur[e that equipment manufacturer comes under definition of local
manufacturers as per Govt. of India, Policy of Public Procurement (Preference to make in
India) order,2017(PPM-MII order 2017) issued by Department of Industrial Policy and
Promotion. Only products conforming to above policy shall be allowed to be used in the work.
Executive Engineer(E),
GED, CPWD, Ghaziabad,