Module 3
Module 3
O&M MANUAL
CHAPTER – 3
SOPS / WORK INSTRUCTIONS /
GUIDELINES / CHECKLISTS / FORMATS
A – Technical
3.1 City Gate Station
3.2 Odorant Handling Management
3.3 Steel Distribution & Industrial Supply Lines
3.4 PE Distribution Network Maintenance
3.5 Complaint Handling Gas Leak / Gas Escape
3.6 Customer Complaint and Request Handling
3.7 Service Regulator
3.8 Industrial Connection
3.9 Annual Maintenance Of Customer Connections
3.10 Calibration, Testing & Certification
3.11 Festival / Occasional Activity
3.12 Safe Guarding Pipe Lines From Third Party Damage
3.13 Modifications / Upgradation
3.14 Inspections / Audits
3.15 Preparation / Preservation / Updating Drawings
/Records
Module 3 of 9
Block - 15, 2nd Floor, Udyog Bhavan, Sector - 11, Gandhinagar – 382 011.
3.1 City Gate Station
City gas distribution is a facility, set-up for supplying piped natural gas, mainly as a
fuel to domestic, commercial and industrial customers, in city, town. The system
receives high pressure and unodorized gas from transporter, through transmission line
and supplies the same to the customers after filtration, pressure reduction, odorization
and check metering. The pressure reduction may be in four stages depending upon
the network design selected. The first pressure reduction is carried out at CGS,
second at CPRS / DRS, third at Service Regulator and forth and final at customer
premises. The odorization for imparting smell to gas is installed at City Gas Station
(CGS). The system has major assets like, city gate station (CGS), underground steel
distribution network, CPRS, DRS, MP PE network, service regulators, LP PE network,
and customer connections. The size, rating and type of the major and sub assets are
selected based on the pressure rating, capacity and other applicable criteria
considered for whole city gas distribution system for meeting the current and future
customer potential, health and safety of employees, customers and public at large,
environment protection, and complying the statutory, legal requirements, national and
international technical and safety standards / practices. The main objective of the
distribution company is to ensure safe and uninterrupted gas supply to customers for
24 hours, 365 days by manning the control room, round the clock, by deploying the
team of competent engineers and technicians, for handling various customer
complaints about gas leak / escape, customer queries and carrying out planned
operation and maintenance activities, as per annual operation and maintenance plan
for ensuring safe and uninterrupted gas supply and integrity of network.
3.2 Odorant Handling Management
1. General Information,
3. Work instructions :-
2. The characteristic smell of gas was originally due to small amounts of hydrogen
sulphide and organic sulphur compounds residual in the production of town gas from
coal, Many supplies of a natural or substitute natural gas have insufficient or even no
sulphur compounds and therefore need to be odorized to give them a characteristic
smell before entering the transmission or distribution system in compliance with UK
legislation.
3. The odorant should be added in sufficient quantity to enable the gas to possess
a recognizable odour. A mixture of 1 percent gas in air with an odour intensity of 2 of
Al factory degrees on the sales scale is widely accepted as achieving this
requirement. This should enable a leak to be detected before it reaches the lower
flammable limit for gas in air (5 percent for natural gas). Where the gas contains toxic
components, for example, carbon monoxide, the addition of odorant should be
sufficient to enable a leak to be noticed before the concentration of the toxic
component reaches on unacceptable level.
6. British legislation requires that “no person shall supply through pipes any gas
which does not possess a distinctive smell”. It follows that should the level of
odorization fall below this requirement immediate corrective action is required to
comply with statute.
When new pipe is commissioned, particularly in a system of large volume, the pipe
surface may absorb odorant preferentially and, if the situation was not corrected,
would leave the gas odorant deficient. Corrective measures are thus of a temporary
nature until the process corrects itself by natural equilibrium.
GSPC GAS has installed three types of odorant systems for imparting peculiar smell
to natural gas, supplied through city gas distribution facilities, at various locations, as
shown in the table below.
Capacity of Storage
Sr. Vendor Year of
Odorizing Tank Location
No. Name Installation
Unit Capacity
1 M/s Control 200000 400 ltr (200 Navsari
Plus SCMD ltr per tank)
2 M/s Varicon 100000 400 ltr (200 Valsad
SCMD ltr per tank)
3 M/s Varicon 100000 400 ltr (200 Nadiad
SCMD ltr per tank)
4 M/s Varicon 100000 400 ltr (200 Gundlav
SCMD ltr per tank)
5 M/s Varicon 1200 200 ltr (200 Kalpataru,
SCMH ltr per tank) Gandhinagar
6 M/s Varicon 1200 200 ltr (200 Prince
SCMH ltr per tank) Gasoline,
Raison
7 M/s Varicon 1200 200 ltr (200 Kalol
SCMH ltr per tank)
8 M/s Varicon 1200 200 ltr (200 Chotila
SCMH ltr per tank)
9 M/s Varicon 1200 200 ltr (200 Bharuch
SCMH ltr per tank)
10 M/s Varicon 200000 400 ltr (200 Rajkot
SCMD ltr per tank)
11 M/s Control 100000 400 ltr (200 Than
Plus SCMD ltr per tank)
12 M/s Control 50000 400 ltr (200 Chandkheda
Plus SCMD ltr per tank)
13 M/s Control 1000000 400 ltr (200 Morbi
Plus SCMD ltr per tank)
14 M/s Control 1000000 400 ltr (200 Vapi
Plus SCMD ltr per tank)
15 M/s. 500000 6 Gallons Hazira-Surat
KingTool SCFH
16 M/s. 1000000 20 Gallons Mora- Surat.
KingTool SCFH
17 M/s. 150000 2.22 CNG
KingTool SCFH Gallons Ichhapore-
Surat
Out of these three systems Dosador is more accurate, fully automatic, but complicated
for operation maintenance. The injector works as a pump after getting control signal
from PLC.
The Varicon is accurate and simple, the system uses the gas operated dosing pump.
While KingTool’s systems are very simple but not accurate. It works on capillary action
on wicks. The KingTool system another activity of transfer of odorant from storage
tank to odoriser is required to be carried out.
DOSAODOR-D, Odorant Injection System
General Description
DOSAODOR-D is a computerized odorization system that is proportional to the flow
rate of the gas in transit. The system operates by liquid-injection and it can be
installed in combination with traditional absorption-type devices. The entire
DOSAODOR-D system is completely configurable and can also be interfaced with
remote monitoring systems.
The equipment consists in a panel to be installed in the hazardous area and a
microprocessor control unit to be installed in the safe area, interconnected by electric
cables.
The system ensures the dosing rate while keeping the desired odorant concentration
level steady with any gas flow rate of the station, even when the latter is extremely
variable and extremely low.
This particular feature translates into a marked increase in safety within the sphere of
the distribution of natural gas for public use. In fact, by maintaining a constant level of
the concentration in all of the gas flow rates being supplied, any leakage of gas can
clearly be identified, thereby decreasing the possibility of accidents. In addition to this,
the possibility of having printed reports on the gas volumes, the amounts of odorant
emitted and the concentrations thereof, provides facility managers with objective aids
confirming the proper functioning of their systems. The objectives obtained with this
new system can be summarized as follows:
¨ Operational safety
¨ Extreme reliability
¨ Low maintenance requirements
¨ Simple use
¨ Dependability of the results
The system does not involve the use of dosing pumps or other complex devices for
the measurement of odorant flow rates. In fact, although they are now extremely
reliable, these devices still require periodical maintenance, which is a particularly
difficult procedure with parts that have come into contact with the odorizing liquid.
This system uses the differential pressure, which is always present between the
upstream and downstream sections of a reduction and metering gas station (min. 1
bar), and an electrically controlled injection unit that has been designed and certified
in accordance with international standards for electrical equipment in EEx areas with
risk of explosion.
DOSAODOR-D utilizes the high-pressure upstream gas as the pneumatic driving fluid
in order to inject the odorizing liquid in the downstream pipelines, creating a gas
driven pump.
The entire pneumatic panel is made of stainless steel without a painted finish or
screen printing as odorizing liquids are aggressive.
A procedure has been designed to perform the decontamination of the entire injection
circuit. In fact, although the chances are very slight, the need to intervene for system
maintenance may arise.
A special sampler provides for measurement of the liquid that has actually been
injected and informs the electronic control unit of any adjustments to be made, thereby
ensuring a marked level of reliability and overall precision of the system, which is self-
monitoring.
During routine operation, in the versions that include two injection devices, one is
stopped as a reserve for the other. The software provides for the exchange from one
to the other, in order to ensure that the same device does not always remain idle.
The concentration ratio is ensured by a special microprocessor electronic control unit
which receives as input either a digital volume signal from a flow computer/volumetric
counter or from an analog signal 4-20 mA that compares it with the concentration level
to be maintained and processes the correct electrical signal to be transmitted to the
injection device. The control unit supplies the proper voltage and current values to the
various equipment units and it contains the separation barriers to comply with the
directives involving system installations with the intrinsic safety. It must be installed in
the safe area and operates, on standard version, with 230 V 50 Hz or 12 V dc.
In the event of malfunctioning or power outages, the control unit saves the
programming data by means of a buffer battery and sends a signal to activate any
emergency devices (it normally restarts operation of the absorption-type emergency
system).
The system equipment complies with all parts of UNI-CIG 9463 ITALIAN standards.
The system equipment meets all the requirements established by European directives
concerning electric systems in hazardous areas.
This DOSAODOR-D system has been approved by SNAM for installation on REMI
stations.
The following table illustrates the correlation between the type of odorizing liquid used,
maximum odorizing liquid capacity and the maximum flow rate of the gas to be
odorized.
International Standards Units
Maximum Flow rate of gas that can be odorized Stm3/h
Maximum Odourant Flow Dosing Rate
Rate Litres / Hour 10 mg/Stm3 (Mercaptan)
1,3 130.000
4,0 400.000
8,0 800.000
14 1.400.000
Maintenance
•Procedures and Recommended Timing for routine / extraordinary
Neutralizing materials.
In order to proceed with startup the system, you should have available at least half a
liter of a liquid capable of neutralizing the effect of the odorant used. Normally, the
liquid most frequently used is a mixture of sodium hypochlorite (bleach) with
denatured alcohol and a small amount of “fragranced” liquid soap.
Preliminary checks
It is best to check that all of the pneumatic connections have been carried out properly
and that all of the connector pipe fittings are well-tightened, prior starting up the
system. Proceed as follows for these checks: (Use the diagram on page 23 as a
reference)
- Close the odorant input valve found at the base of the pickup tank.
- Open the three gas on/off valves found on the main line
(Upstream station, downstream regulators / upstream measurement, upstream
solenoid valve 10.1)
- Using a suitable spray, check for any gas leaks (check ALL fittings)
- Proceed by switching on the electronic control unit, following the information
contained in Chapter 3 on page 30.
(With this procedure, solenoid valves 8 and 10 will open automatically and will remain
open for no longer than 2 minutes. After this interval, the valves will close, activating
the control unit alarm with a signal indicating odorant recharge failure)
- Check the line section connecting the pneumatic panel with the odorant pickup
tank for any gas leaks.
If no leaks are detected, it is possible to proceed with priming the entire system.
Maintenance
Procedures and Recommended Timing for routine/extraordinary maintenance
operations
The DOSAODOR-D system, made by O.M.T. Tartarini that you have purchased has
been manufactured with state-of-the-art technology and materials currently available.
Thanks to all this, we succeeded in manufacturing a system requiring one routine
maintenance intervention each three solar years.
ROUTINE Maintenance
For routine maintenance operations, you have to be provided with the relevant
maintenance Kit. It includes all spare parts that have to be replaced in the system so
as to renew it and have it in compliance with the functional specifications, for which it
has been originally designed.
These are the operations to be carried out:
- Wash by means of Natural Gas (see paragraph 5.2)
- Close all valves on the pneumatic panel
- Close the needle cock located on the pipe detecting the odorizing pressure (low
pressure branch)
- Close the odorant outlet cock located on the tank from which the odorant is
picked up.
- Cut off power supply to the electronic control unit
- De-pressurize the panel by loosening the joint located in the upper left part of
the control cylinder
- Replace all rubber parts inside the two pressure Filter-Regulators model SA/2
(the operations to be performed are described in the attached bulletin)
- Fully replace the two-way injection solenoid valve located on the top left of the
pneumatic panel
- Replace the moving group located inside the three-way solenoid valve that is
used to control opening/closing of the licking circuit.
ATTENTION: the moving group of the three-way solenoid valve is slightly different
from the one of the two-way valve. In fact it has a further pad on the upper part.
- Replace the filtering cartridge located inside the filtering group
- Restart the system, by meeting the instructions described under par. 4.
5 Instruct the driver of the maintenance van for safe and slow O&M. In-
driving after educating him about the hazard involved. charge /
After reaching at dosing site, slowly unload the barrel,
6 keeping rubber tyre on the ground near the van for safety O&M. In-
precaution, in case of falling of barrel. Drive away the van charge /
from site, to safe place
Place the barrel on the hand pulled trolley carefully and shift
7 O&M. In-
the same to the designated place near storage, tank,
charge /
remove the trolley away.
8 Similarly return back the empty barrel from site to storage O&M. In-
room, taking safety precaution all the way. charge /
Immediately after completion of shifting of full barrel to the
9 O&M. In-
dosing site, place ice on and around barrel, for condensing
charge /
the vapor generated during transportation / shifting.
Work instructions - 02
Work instruction for odorant transfer from Barrel to Storage tank
Sr.
Work instruction Responsibility
No.
Ensure that Written intimation regarding transfer of
O&M. In-charge /
01 odorant is given to Location, GPCB, 48 Hrs. in
Shift In charge
advance, stating date and time of transfer.
Obtain safety work permit before starting the transfer O&M. In-charge /
02
procedure. Shift In charge
O&M. In-charge /
03 Inform Control room before starting the Job.
Shift In charge
Check the emergency preparedness / availability of
saw dust, dry sand, detergent powder, sodium O&M. In-charge /
04
hypochlorite in required quantities and fire Shift In charge
extinguishers etc. are ensured.
For safety, use personal protective equipments like O&M. In-charge /
05
hand gloves, mask respirator, face mask, etc… Shift In charge
Dilute the Hypo, add water and Surf washing powder,
O&M. In-charge /
06 measure the PH of the solution, it should be more than
Shift In charge
7PH. Prepare such solution in 4 nos. of full buckets. .
Connect the one end of vent tube to the vent point on
tank and another to the carbon filter immersed in O&M. In-charge /
07
bucket full with Hypo solution and Surf detergent, for Shift In charge
neutralizing the vapour from tank.
Safely transport the full Odorant barrel / drum to the
O&M. In-charge /
08 Platform at the specified location, using transporting
Shift In charge
truck / trolley.
Place the ice on barrel / drum as well as on tank to O&M. In-charge /
09
settle / condense the vapour of EM. Shift In charge
Connect air motor inlet of the pump to N2 cylinder. And
O&M. In-charge /
10 check the functioning of barrel pump by actual
Shift In charge
operating it with the water. Also observe / record the
minimum N2 pressure required for safe pump speed.
Start / continue depressurizing the odorant tank by
crack opening the vapour vent valve & checking the O&M. In-charge /
11
bubbling in the bucket and smell in the surrounding Shift In charge
area to ensure effective neutralizing of odorant vapour.
Open all 4 nos. of valves on glass level indicator of the
O&M. In-charge /
12 tank. Observe / Record the current odorant level in the
Shift In-charge
tank, if any.
Slowly open the bigger lead of the drum and insert the
O&M. In-charge /
13 barrel of the pump into the drum, ensuring neutralizing
Shift In charge
of vapour from barrel. Using hypo soaked cloth.
Connect the pump discharge to the odorant tank & O&M. In-charge /
14 check the integrity of discharge piping by safe opening Shift In charge
of the tank and pump liquid valves.
If everything is normal, start filling by operating the
barrel pump, by opening and setting N2 regulator on O&M. In-charge /
15
cylinder, to predetermined value, set during trial run on Shift In charge
water.
During pump operation, Continue depressurizing of
the tank, ensuring, vapour pressure in the tank
O&M. In-charge /
16 remains near to zero and there is effective neutralizing
Shift In charge
of vapour in solution bucket. If required change
solution / carbon filter.
O&M. In-charge /
17 Observe the rise of odorant level in the tank.
Shift In charge
Continue Monitoring the EM level and vapour pressure
18 in the tank and smell in the surrounding to ensure O&M. In-charge /
effective transfer and neutralizing of EM vapour from Shift In charge
tank.
Stop the N2 supply as soon as transfer of odorant
O&M. In-charge /
19 from drum to tank gets completed & the same is
Shift In charge
confirmed by net rise in odorant level in the tank.
Observe / Record the final odorant level in the tank.
Close vapour valve / liquid fill valve and all 4 nos. of
Shift In-charge /
20 level indicator valves of the tank. Fit the plugs on tanks
Technician
and lead on barrel and check for leakage.
21 Disconnect all the arrangements made for transferring
Odorant. Clean air pump & its associated components
by running in 1/2 to 5-percentage concentration Shift In-charge /
Sodium hypochlorite solution and then in clean water, Technician
and shift barrel and all the accessories at their
designated place / hazardous waste room.
Work instructions - 03
Work instruction For Odorant transfer
from storage tank to Odorizer tank
SR NO ACTIVITY Responsibility
Normally lean hours / non peak hours are selected for O&M. In-charge
1
transfer of activity. / Shift In-charge
Obtain safety work permit (Ref.Doc.) before starting O&M. In-charge
.2
the transfer procedure. / Shift In-charge
O&M. In-charge
3 Inform Control room before starting the Job.
/ Shift In-charge
Check the emergency preparedness / availability of
saw dust, dry sand, detergent powder, sodium O&M. In-charge
4
hypochlorite in required quantities and fire / Shift In-charge
extinguishers etc .are ensured.
For safety, use personal protective equipments like O&M. In-charge
5
hand gloves, mask respirator, face mask etc. / Shift In-charge
6 Open all 4 nos of valves on storage tank level gauge
Observe / Record and mark the initial level in both O&M. In-charge
7
tanks. .and pressure in storage tank. / Shift In-charge
Close the gas (bypass) inlet and outlet valves of O&M. In-charge
8
odorizing tank. / Shift In-charge
Open the vapour balancing valve of odorizing tank O&M. In-charge
9
and check the leakage, by soap solution. / Shift In-charge
Open the feed valve of odorizing tank and check the O&M. In-charge
10
leakage, by soap solution. / Shift In-charge
If there is no leakage /smell, then, open the vapour
O&M. In-charge
11 valve on storage tank allow the pressure to equalise /
/ Shift In-charge
stabilize and observe / record the final pressure.
Start transferring of odorant by opening the liquid
O&M. In-charge
12 outlet valve on the feed line, at the bottom of storage
/ Shift In-charge
tank.
Continue transfer, till the required level is shown, in O&M. In-charge
13
the level gauge of odorizing tank. / Shift In-charge
Record the final levels of both the tanks and O&M. In-charge
14
pressure in the storage tanks / Shift In-charge
Work permit is signed off and Control room is Shift In-charge /
15
informed for completion of the job. Technician
Make entry in the Logbook
16 Shift In-charge
Prepare Odorant Transfer Report
Waste material generated during maintenance work
17 is collected in the dustbin, and disposed off at Shift In-charge
designated place.
Work instructions - 04
Work instruction For Neutralizing and disposal of empty barrel
Pour the used solution and excess ice pieces, in the
Shift In charge /
1. empty odorant barrel Close the barrel and keep it for
Technician
10 -15 minutes.
Prepare one bucket detergent solution and pour it in
Shift In charge /
2. empty barrel. Close the barrel and keep it for 5 -10
Technician
minutes.
Prepare two bucket of lime solution (use 15 kg of
Shift In charge /
3. lime powder) and pour it in empty barrel. Shake / roll
Technician
the barrel for proper mixing of solution in the drum.
Shift the barrel carefully at Hazardous Waste Shift In charge /
4.
Storage area on CGS. Technician
Mark the identification number on the barrel and
5.
apply form -8 stickers on the barrel.
Sign off Work permit is and inform Control room for Shift In-charge /
6.
completion of the job. Technician
Make entry in the Logbook (Ref. Doc. Keep the
7. record of empty drum Prepare Odorant Transfer Shift In charge
Report (Ref. Doc
Collect the waste material generated during
8. maintenance work in the dustbin, and dispose off, at Shift In-charge
designated place.
Send the empty barrels to the land fill site, by hiring
9. GPCB approved transporter, when the accumulation
of empty barrels reaches to tempo load.
Ensure that the tempo driver is carrying the relevant
papers as per TREM card, especially list of
10.
emergency telephone number and emergency
handling procedure.
4. Rhinology Standard Nose Training
After imparting adequate training in rhino logy- the laboratory training giving
awareness of different intensity of smell at different odorant dosing rate in a close
room, to selected persons from various field / working crews determine on site / at
active sampling point the odor intensity / smell level of odorized natural gas after
adjusting the gas concentration in air at 20 % of LEL and provide the feedback to
control room to ensure adequate dosing and ultimate smell level
Training of Rhinologist
Purpose of odorization
Detection of the leakage / escape of natural gas by smell well before the
concentration of gas in the area become hazardous by general public.
Requirements
Distinctive odor readily perceptible to normal person in the area where natural
gas is present in concentration of not more than one part gas to ninety - nine
parts air.
Selection on EM as odorant
Distinctive and non confusable smell - Smell different from commonly found in
household or environment
Most of the distribution companies are using Ethyl Mercaptan as an odorant
because,
• the most evil smelling substance
• possess the highest odor intensity / strongest odor
• having readily identifiable unpleasant smell
Smell Level / Odor Intensity
Limit of perception
Level of odor intensity which is perceived (detected) by every person with average
sense of smell.
Odor Intensity
Sensation
(olfactory degrees)
0 No odor
0.5 Very feeble odor (limit of perception / detection)
1 Slight odor -feeble
2 Medium odor (alert level)
3 Strong odor
4 Very strong odor
5 Upper limit of sensation
Reason of low odor intensity
• No dosing
• Inadequate injection -low dosing rate
• loss of odorant from odorized gas
Odorant Dosing Rate
Dosing rate is depends on
• LEL of the gas to be odorized
• Odorant Concentration in air at the alert level - constant value for
specific odorant
• Safety factor - normally 5
Loss Odor / Smell from Odorized gas
• Odorant sorption by surface (particularly with rusty surfaces or new
piping (steel or plastic)
• Odorant oxidized by oxygen / iron oxide to disulfides
• Sorption by soil
• Sorption in hydrocarbon condensates
About Rhinologist
Person trained in odor assessment
Role of Rhinologist
• Primary judgment / Estimation of smell & smell level / odour intensity
• Consistently in judgment of smell level
• Determining odourisation adequacy
Test Facilities
Air tight / locked Odorant Chamber / Room
• Size - 500 to 1000 cu feet
• Odorant and Gas/Air mixture device.
• Exhaust fan with separator to isolate the chamber
• Air tight - close fitting doors (lined with aluminum sheet)
• Mixing / Recirculating fans
• Carbon air filter for air intake to chamber
• device to measure odorant concentration in the chamber / room
Odorimeter
• is a device to prepare known odorant/air or air / gas mixture
• Let panel members sit or stand at once in a chamber at isolated place in the
chamber
• Introduce odorant in the chamber & mix with air in the chamber by recirculation
fans.
• Measure the odorant concentration in the chamber
• For preliminary trials, tell panel members value of odorant concentration
• Expose members to known concentration
• Allow member to sniff the mixture and judge the smell level.
• Ventilate the chamber
• After an interval of at least 15 minutes, expose the members to various odor
intensities (concentrations)
• After several trials, do not tell members the value of odorant concentration in
the chamber and let them judge the smell level
• Match the assessment by nose with Odor intensity scales (established for
known concentration)
• determine on site / at sampling point the odor intensity / smell level of odorized
natural gas after adjusting the gas concentration in air at 20 % of LEL
• provide the feedback to operation group to ensure adequate smell level
Gas Smell Monitoring Report
Month
Location
Status Odo
riser
Sr. Customer
Date Location Suffi tank Remarks
No. Code Low High
cient Lev
el
In a typical City Gas Distribution network, Underground Carbon Steel (CS) network is
major asset / component of total installation. It can be categorized as Transmission
Pipeline and Distribution Pipelines. Transmission pipelines are trunk lines or spur
lines operated generally at above 20 bars. Transmission lines are operated and
maintained by GSPL. Distribution pipelines starts after City Gas Station (CGS),
spreads in city up to inlet of CPRS, DRS and CNG Station and it operates at
pressure range from 15 to 19 bars.
Carbon Steel pipelines are normally of API-5L Grade – A or B material and sizes
varies from 4” to 16” in distribution network. They are first coated with 3 Layer PE
coating or Fusion Bonded Epoxy (FBE) Coating and then they are welded, NDT
tested, laid underground at normally 1 m depth and finally hydro tested to 1.5 times
Max operating pressure. The underground steel network is protected against
corrosion by coating the pipes and applying impressed current Cathodic protection.
Special care is taken during installation and operation maintenance for rail, road and
nala, canal crossings.
Network Maintenance
Sr. Activity Frequency
Update Network Drawing to incorporate all
1 As and When
extensions, modifications of network.
2 Patrolling & Surveillance of Network Monthly
Patrolling of Crossing – Bridge, Culvert, Khadi,
3 Monthly
Canal, Road, High Way, River & Railway
Emergency Patrolling & Third Party
4 Coordination if work is going on or near gas As and When
pipeline route
5 Leak detection survey of network Quarterly
6 Lock Pressure Test of network Quarterly
Half Yearly
7 Valve Chamber Preventive Maintenance
(Pre-Monsoon, Post Monsoon)
8 Operation and Greasing of Valves Half Yearly
All rail, road and major waterway crossings should be inspected on a regular basis to
observe surface conditions, indications of leaks, general construction activity and
any other factors which may affect the safe operation of gas system.
When a threat to the gas system from third party excavation is observed by a
Supervisor or Inspector then that person must take the appropriate action on site to
ensure the gas pipe is not damaged. It may be necessary in some circumstances to
arrange for an Inspector to be positioned on site to ensure the integrity of the gas
system is maintained.
• Maintain liaison with other authorities and bodies who are concerned
with works which could affect pipelines. Further, maintain good
relations with the owners of properties traversed by pipelines. Good
communications and in particular keeping people informed on the
location and importance of pipelines, is a primary defence against
interference being caused by third parties.
1. Divide total network route in sub-route / section such that total network can
be patrolled once in month.
2. Ensure that each member of patrolling team aware about the route of
pipeline, size of pipeline, type of coating and depth.
3. Observe following along the route
• Excavation work on / near gas pipeline
• Civil work / construction near gas pipeline
• Erosion of soil from gas pipeline route
• Surface faulting, subsidence, flooding on gas pipeline route
• Encroachment by slums other temporary structure
• Encroachment by lorry / galla / tea house
• Other potential hazards
• Valve Chambers and it’s top cover
• District Regulator station it’s fencing / cabinet / gates
4. In case of Excavation / Civil / Construction work on / near gas pipeline,
meet with site supervisor / concerned person and get detail like
• the type of work and purpose
• use of excavation machines or other machines
• depth of excavation
• distance from gas pipeline
• work duration / completion date
• drawing of construction work
• name of contractor, address and contact detail
5. Provide them awareness about gas network, it’s hazards and pipeline
drawing. Brief them a safety precautions to be taken to prevent damage to
gas pipeline
6. Provide them a contact address and telephone numbers for consultation in
case of any difficulty
7. In case of erosion of soil from gas pipeline route, take depth and length of
erosion. Investigate probable cause of soil erosion. In case of soil erosion
due to reason/s of third party, coordinate with them to prevent them.
Initiate action to restore eroded site properly
8. In case of encroachment on / near gas pipeline, report it to concerned
authority to shift / prevent them. Make them aware about gas pipeline
route and it’s hazards. Explain them safety precaution to be taken to
prevent any incident
9. While patrolling, check the pipeline markers condition
10. While patrolling, keep the speed of vehicle such that all above observation
can be made effectively. Walk Survey / Patrolling is preferable in case of
congested area or other utility activities going on.
11. Report findings of Patrolling activity in specified format
12. Update the contact address and telephone numbers of concern third party
utility agencies on regular basis.
13. Keep the communication device and list of contact numbers of related
utility agency while patrolling.
14. Use cotton dress and safety shoes while pipeline patrolling activity
15. Use helmet if require to go near construction site
16. Observe and check for trip / fall hazards while pipeline patrolling activity
17. While driving during pipeline patrolling activity, Follow “Safe Driving”
instructions
Patrolling / Inspection of Pipeline Crossing like Railways, HighWays, Culverts,
Bridges, Canal to be carried out as per follow
They should also be acquainted with the hazardous properties of gas and the
potential effect of escaping gas on the safety of the public. It should be emphasized
and encouraged that in the event of an emergency that prompt co-operative action
would be required.
Apart from the essential day to day contact with other Authorities, O&M Contractor
shall formally correspond with the appropriate other Authorities on a yearly basis.
Gas Pipeline Patrolling Report
Date of Patrol :
Network / Area :
Pipeline Section : Size : Length :
Sr. Pipe
Check Point Location Observation / Findings
No. Size
01 Excavation work on
/ near gas pipeline
02 Civil / construction
work on / near gas
pipeline
03 Erosion of soil
04 Encroachment
05 Surface
subsidence,
flooding
06 Any other potential
Hazard
07 Damage to Pipeline
markers
08 Damage to Valve
Chamber/s
09 Damage to District
Regulator Station/s
Remarks :
Date of Patrol :
Network / Area :
This activity consists of (a) Gas Leak Check (b) Partial / Full Valve Operation (c)
Valve Greasing (d) Cleaning and (e) Tag number painting.
1. Ensure that each member of team are aware about natural gas and it’s
hazards
2. Ensure that each member of team aware about the risk involve in valve
chamber maintenance activity, it’s potential hazard and preventive
measures.
3. Supervisor & team shall be made aware of pipeline network route and
valve chamber locations.
4. Plan the job in advance and ensure appropriate work permit for job.
5. Ensure availability and use of appropriate PPEs and Safety Items as per
“Annexure – PPEs Matrix” during valve chamber maintenance activity
6. Ensure the availability of necessary tools tackles and other items in good
working condition, required for valve camber maintenance activity.
7. Ensure the availability of wireless set / mobile phone at site. After reaching
site, first, establish contact with control room before start of activity.
8. Cordoned the site appropriately and place caution board along the road
site valve chamber.
9. Clean the top cover of valve chamber and note it’s tag number
10. Open the valve chamber top cover, one by one, gentle by holding & lifting
from both sides manually. Take utmost care to prevent, falling of top cover
inside chamber.
11. Remove all the top covers and keep them aside without creating
obstruction.
12. Check the gas leak inside valve chamber using calibrated gas detection
instrument. Supervisor should be trained for operation of gas detection
instrument and measurement of gas leak.
13. Check the flange joints and threaded joint, using bubble test (soap
solution) for any gas leak.
14. In case of gas leak from valve, first attend the gas leak. If require arrange
resources from control room / main office.
15. In case of valve chamber is more than 1.5 meter deep, and seems to be
confined space, first check the oxygen level before entering in valve
chamber. Entry should not be permitted if oxygen level is less than 19.5%.
16. Use ladder to enter inside deep valve chamber.
17. Carry out dewatering / cleaning of valve chamber first.
18. Operate the valve partially or fully depending upon gas flow and line pack
availability for customers. Ensure that gas supply is not affected to any
customer. Avoid valve operation in case of any doubt.
19. Grease / Lubricant the valve in case of valve is jam or operating hard.
20. Paint the tag number of valve chamber on top of cover, if it is faint or
erased.
21. Carry out white wash of valve chamber from inside and outside top civil
portion.
22. Carry out oil paint of specified colour and type, to valves inside the
chamber and metal portion of valve chamber top cover once in year after
monsoon.
23. Close the valve chamber top covers gently, lifting & holding from both
sides manually. Take utmost care, to prevent dropping of top cover inside
chamber.
24. Remove caution board/s and cordoning tape / device from site and restore
site to safe level.
25. Provide message to control room and take activity further.
26. Prepare report of valve chamber maintenance activity in a specified
format.
27. After completion of activity, close out work permit and keep the record of
same.
Valve Chamber Maintenance Report
Date of Maintenance
Cleaning
V/C Leak Operation Tag No Any
Greasing & White Painting
No Test of Valve Painting Damage
Wash
Remarks :
Conclusion / Observation:
Pressure Lock Test is indicative only, and it required shutdown of pipeline as well as
special operational skill whereas Gas Leak Survey / Surface Gas Detection is easy
and effective to identify the gas leak on network with spot identification.
1. Divide total network in section / sub-section such that total network can be
surveyed once in a quarter.
2. Ensure that each member of team aware about the exact route of pipeline,
size of pipeline and depth.
3. Ensure that each member of team are aware about natural gas and it’s
hazards
4. Ensure that each member of team aware about the risk involve in survey
activity, it’s potential hazard and preventive measures
5. Ensure the availability of portable / mobile calibrated gas detection
instrument in good working condition having least count of 10 ppm, for
survey activity.
6. Start the gas leak detection survey activity with zero chainage or with
known location / landmark location.
7. After reaching site, first start the gas leak detection instrument and then
walk along the gas pipeline route at the normal speed.
8. For buried pipeline, take sampling just above 2” (not more than 2”) from
ground. However it should not be touch to ground or water body to prevent
probe chock up.
9. Sampling should also be taken at ground surface opening such as
manholes, catch basins, sewer, power telephone duct openings, traffic
signal / junction boxes, curb line / cracks of pavements
10. While survey, ensure that probe do not rub in soil getting chocked with
dust and water.
11. Carefully observe the hooter / indicator of instrument while survey /
walking.
12. Note, if instrument shows some indication of gas leak. Survey surrounding
place thoroughly for gas leak intensity. Observe for gas smell.
13. Check for any other flammable gas leak from surrounding.
14. Confirm gas leak, by check at site twice / thrice.
15. Note the gas leak spot along with leak intensity in specified report and
carry out survey further.
Surface Gas Detection Survey Report
Remarks :
⇒ Note down the AC Input (Volt & Amp), DC output and Corrosion voltage (PSP)
readings for each T/R unit on daily basis.
⇒ Compare the DC output and PSP of TR unit with previous days. It should be in same
range. If there is significant increase or decrease, investigate further.
Preventive maintenance is to be carried out as per Mfr Guidelines / O&M Manual. Following
activities shall be carried out half yearly.
Case 1 : If unit shows the DC current zero and DC voltage more than set value, Take
following corrective measures, also refer Mfr O&M guidelines
⇒ Check The anode ground bed circuit, if it is open, then carry out anode ground bed
maintenance.
⇒ If the anode circuit is closed, then check all fuses of unit and replace faulty one.
Case 2 : If unit shows the DC current zero and DC voltage zero, take following corrective
measures,
⇒ Check out put fuses of unit and replace faulty one.
⇒ If they are ok. then check control cards and replace faulty one.
• Month :
• Frequency :
• Stations : (Name and Tag)
• Pipeline Network :
• Date :
• Station :
• Section Covered :
• Approach :
1. Transformer / rectifier Unit details : Manufacturer
Rating of Unit :
Operating Mode : Auto / Manual
2. Visual Inspection & Maintenance of TR :
Sr.
Description Status
No
1 Operation of Lock Ok / Not Ok
2 Identification of tag. Ok / Not Ok
3 Indication lamp / LDS Ok / Not Ok
4 Cleaning Inside / Outside using blower
5 Damage to T/R
6 Tightening of connection
7 Body and Paint Condition
8 Status of control Cards
9 Earthing Connection
10 Electrical fittings/glands
11 Lamps & indicators
12 Fuses, Plugs & Sockets
13 Current Regulation Switches
14 Voltage Regulation Switch
3. Working Parameters :
Sr. Description / Parameter. Acceptable Actual Value
No Value
1 A.C.Input voltage in V
2 A.C.Input current in A
3 D.C.Input voltage in V
4 D.C.Input current in A
5 Resistance in ohm V / I
6 PSP at drain point
Ref. Cell : 1
Ref. Cell : 2
4. Visual Inspection & Maintenance of Anode Ground Bed and Junction Box :
Sr.
Description Status
No
1 No. Of Anodes
2 Operation of Lock Ok / Not Ok
3 Identification of tag. Ok / Not Ok
4 Cleaning Inside / Outside using blower
5 Any damage
6 Tightening of connection
7 Body and Paint Condition
8 Electrical fittings/glands
Action Required:
Remark: This format shall be reviewed and revised based on CP guideline or O&M Manual
provided by mfr.
⇒ Take pipe - to - soil (PSP) potential reading by using Cu - Cuso4 half-cell and
calibrated Multimeter, at all test points bi-monthly. Prepare the graph of PSP
reading with in line of -0.85 V and Max line of -1.45 V
⇒ If the readings cross the max. / Min. limit (i.e. - 0.85 V to - 1.45 V), investigate
further
⇒ Note down the PSP readings and observation in standard format
⇒ Cary out analysis annual for significant change of PSP.
⇒ Monitor the PSP of Carrier Pipe and Casing Pipe at both the end
⇒ Carrier pipe PSP should be between -0.85 volt to -1.4 volt and Casing Pipe PSP
should be below -0.85 volt
⇒ In case Casing pipe PSP is found between -0.85 volt to -1.4 volt then expose the
casing at both end to find out the shorting of casing and carrier pipe
⇒ Carry out further investigation / remedial actions in consultation with GSPC Gas
⇒ If the P.S.P value is more than - 1.45 V, reset the T/R unit, and keep
the P.S.P value - 1.45 V. at drain point.
⇒ If the P.S.P value is less than - 0.85 V, check half-cell condition and/or cable
connection. And if require repair it.
⇒ If the problem is not rectified then consult CP expert or GSPC Gas.
PSP Monitoring Report
• Date :
• Frequency :
• Stations : (Name and Tag)
• Pipeline Network :
PSP Readings
Sr. Type of Chainage PSP in Condition of TLP
TLP No Location
No TLP in KMS Volt
1
2
3
4
Maintenance of TLP
Refer Mfr guidelines / O&M Manual for maintenance of TLP. Following activities are to be
carried out yearly as part of preventive maintenance.
• Date :
• Frequency :
• Stations : (Name and Tag)
• Pipeline Network :
Repair /
Lubrication Replace
Cleaning Cable Painting
Sr. of ment
TLP No Location Inside / Connecti and Tag
No. Enclosure Requirem
Outside on No
and Lock ent
1
2
3
4
• Date :
• Frequency :
• Stations : (Name and Tag)
• Pipeline Network :
• Ground Bed Details :
• Ground Bed Configuration :
• Anode Quantity :
• No of Cable markers :
Current
Anode No Shunt measurement ( mV )
( mA )
Remark: This format shall be reviewed and revised based on CP guideline or O&M Manual
provided by mfr.
ANNEXRURE - 10
Insulating Joint (IJ) Monitoring and Maintenance
Monitoring of Insulating Joint (IJ)
⇒ In case of earthing of IJ with soil, support of any metallic part, remove the earth contact
/ metallic contact.
⇒ In case of electrically passing of IJ, plan replacement in consultation with GSPC Gas.
⇒ In case of gas leakage from IJ joint, plan replacement in consultation with GSPC Gas
Insulating Joint (IJ) Monitoring Report
• Date :
• Frequency :
• Pipeline Network :
Steel network being strong material pipeline, are less susceptible to damage by third
party. However chances are there if work is carried out with excavation machines
without precautions and knowledge. Steel pipeline are more prone to leak due to
corrosion if pipeline is not cathodically protected adequately.
Like PE Network, following emergency situation can come on steel network for which
O&M Contractor is required to prepare adequately.
1. Gas Leak (b) Gas Escape due to damage (c) Gas Fire (d) Explosion
As mentioned in the “Complaints Handling – Gas Leak & Escape” O&M Contractor is
required to establish a control room which operates round the clock to receive the
gas leak, fire, and explosion related complaint/s. They are also required to establish
emergency team of adequate manpower working in shift round the clock and
emergency vehicle equipped with necessary tools tackles and safety items to attend
such emergency in CGD zone with response time of less than 30 minutes. Annexure
– 13 provides additional items which shall be kept in Emergency Vehicle for handling
emergency on steel network
The procedure “Complaint Handling - Gas Leak / Gas Escape” shall be followed
for steel network also. Annexure-14, 15 provide work instruction for attending gas
leak / escape and third party damage specific to steel gas network.
ANNEXURE – 13
List of Additional Items for Handling Emergency on Steel Network
The above list is indicative. O&M contractor shall review it in consultation with GSPC
Gas and incorporate all necessary items to handle gas leak / escape, gas fire &
explosion emergency on steel network effectively & efficiently
ANNEXURE – 14
1) Open the top cover of valve chamber carefully without falling top cover inside
the chamber
2) Measure the gas concentration using calibrated gas detector in and around
valve chamber
3) Identify the gas leak source / location
4) If gas concentration is below 20% LEL, inside valve chamber then try to
attend gas leak in chamber
5) Tighten thread / flange joints of valves or vent drain facility inside the valve
chamber
6) If gas leak can not be attended thro tightening plan for shutdown in
consultation with GSPC Gas
7) If gas concentration is above 20% LEL, inside valve chamber then plan for
shutdown in consultation with GSPC Gas
8) Meanwhile keep the affected area cordoned off with display of caution board
and monitor the gas leak.
Steel gas pipeline is less susceptible to damage due strength of material however
work without knowledge and precaution using excavation machine can damage the
steel gas pipeline.
The damage of steel gas pipeline can cause gas escape from small quantity to large
quantity and may result in fire or explosion if it receives spark.
Normally gas escape is in form of jet. Gas jet in open area is little safe as it disperse
up in atmosphere. However in city area it is very risky as gas can accumulate in
nearby building and may result in gas fire or explosion affecting the human life and
properties.
Sometimes after getting spark, gas escape converted in jet fire. Gas jet fire is much
safer then gas escape if fire is not affecting the surrounding properties or human life.
Hence one should never try to extinguish gas jet fire if it is not affected to human life
& surrounding properties. The gas escape is more danger as it can go & accumulate
in surrounding building.
2. Identify the pipeline section affected, related valves and nos of customer
affected.
3. Communicate it to GSPC Gas thro control room and plan for shutdown of
particular section by closing isolation valves.
4. Communicate to all customers for stoppage of gas supply and ask them to
isolate their main inlet valve
5. After getting consent from GSPC Gas for isolation of section, first close
upstream valve gradually to allow gas of pipeline section to consume by
downstream customers.
6. In case of jet fire, isolate the upstream valve gradually allowing gas
consumption by downstream customers.
7. Monitor the gas fire becoming low. After sufficient low gas fire, first extinguish
fire using DCP type fire extinguisher and the fully close upstream valve.
8. After sufficient low pressure, close downstream valve of section
9. Install vent pipe (3 m high from ground level) on one of vent valve of isolated
section and vent off remain gas from affected pipeline section
10. Identify the type & extent of damage to steel pipeline by exposing affected area.
11. Check leak can be arrested by leak clamps or by replacement of pipe piece.
12. If damage area can be covered by leak clamps then install leak clamps
properly.
13. Charge the gas line. Increase pressure step in step of 2 bars.
14. On each pressure step, take a leak test using soap solution and gas detector
instrument and ensure no gas leak.
15. Finally commission the pipeline section and communicate to control room
16. Provide message to all customer for resumption of gas supply and ask them to
gradually open their main inlet valve
17. Plan the permanent repair in consultation with GSPC Gas
6. Procedure for Steel Network Modification, Extension / Installation
and Commissioning
a. Job Detail
b. Proposed Date of Job and Time Duration
c. Drawing of Existing Network, showing location of shutdown, isolation section /
network, major affected customers, purging points, venting points,
d. Drawing of proposed modification showing modified network, additional
valves, venting point, gas measurement point.
e. Section to be isolated Network Area, Size, Length
f. Name & Nos. of Affected DPRC, CPRS, IPRS & CNG Station
g. Nos. of Affected Customers – Domestic, Industrial, Commercial & CNG
h. Name of Affected Customers - Industrial, & CNG
i. Proposed Date & Tentative Time Duration for Gas Supply Affect
j. Section to be depressurized / vented- Network Area, Size, Length, Volume
k. Gas volume venting loss
l. Section to be purged with Nitrogen- Network Area, Size, Length, Volume
m. Nitrogen cylinder / volume required
n. Tools Tackles list and it’s arrangement for shutdown job
o. Equipment & Instrument list and it’s arrangement
p. Fire, Safety and Communication item list and it’s arrangement
q. Manpower list and it’s arrangement
r. Check List of Preliminary Work to Be Completed before Taking Shutdown Job
⇒ Pre-fabrication and testing of steel pipeline
⇒ Pipeline Material List and it’s procurement / arrangement
⇒ Permission for various authority for installation and excavation
⇒ Arrangement of Nitrogen Cylinder / Tanker
⇒ Arrangement of NDT testing
⇒ Advance Communication to affected customer
⇒ Welder qualification
s. Valve operation sequence for section isolation, venting, pre-purging, post-
purging and commissioning
t. Procedure for shutdown job
Content :
6. General Information,
Pipeline Route
The material adopted for mains and the underground portion of service pipe in the
general distribution system is High Density Polyethylene (HDPE) Grade 100. This
material is selected because of its cost effectiveness, tensile strength, and the
strength of PE fused joints. The diameter ranges for pipes are normally
‘standardized’ at 125, 90, 63 and 32mm for mains, and 32 and 20mm for Services.
Low Density, in which the density ranges between 910-940 kg /m3. and the product
exhibits high flexibility and retention of properties at low temperatures.
Medium Density, in which the density ranges between 930-940 kg/m3. MDPE base
resin is manufactured using slow polymerization process. The pipe exhibits high
flexibility and ductility, slow crack growth resistance and crack propagation
resistance. It is extensively used in the installation of gas distribution networks.
High Density. HDPE resins are also manufactured by a low-pressure process. The
density ranges from 930-960 kg/cub m. HDPE tends to be stiffer than the other
classifications and has high application in the electrical and communication industry
also.
Typical values to the most commonly used properties of PE 80 and PE100 pipe are
given in the following table.
Property Test Method PE 100 PE 80
Density kg/m3 ISO1183D, ISO1872- 954- 950
2B 967
Tensile Yield Strength MPa ISO527 >=19 20
Elongation at Yield % ISO527 7 10
Tensile Break Strength MPa ISO527 27-30 27
Elongation at Break % ISO527 > 800 > 800
Tensile Modulus Mpa Short Term Ref. AS/NZS 2466 1250 700
Long Term Ref. AS/NZS 2466 550 200
Hardness Shore D DIN 53505 59 59
Notched Impact Strength kJ/m2 ISO179/1eA 35 35
(23°C)
Melt Flow Rate 190/5, g/10min. ISO1133 0.39 – 0.7 –
0.54 1.0
Thermal Expansion × 0.0004/°C DIN53752 2.4 2.4
Thermal Conductivity W/m.k (20°C) DIN52612 0.43 0.43
Crystalline Melt Point °C DIN53736 125 125
Dielectric Strength kV/mm DIN53481 70 70
Surface Resistivity Ohm DIN53482 >1015 >1015
Volume Resistivity Ohm. Cm DIN53482 >1015 >1015
Poissons Ratio μ 4 4
The design of PE distribution piping systems is not significantly different from steel
systems laid for cross country transportation of Gas. The difference is essentially
related to the physical / strength characteristics of both materials.
Advantages of polyethylene (PE) over steel are as follows,
• Because of its flexibility, small diameter pipe can be coiled into long lengths
for easy transport and installation.
• Its flexibility also allows polyethylene in the smaller sizes to be squeezed shut
in an emergency situation thus reducing the need for the installation or large
numbers of expensive and potentially high maintenance system block valves.
• Because of its thermal expansion (10 times greater than steel) temperature
changes need to be taken into account during construction.
Distribution services running from the PE mains to the customers appliance (s) are
constructed of polyethylene for their underground section (from main to a PE/GI
transition fitting, situated adjacent to the outside of the customer’s premises), and
then screwed galvanized iron (GI) pipe thereafter. The size of services was
standardized to 32 mm and 20 mm
2. MP PE network of CGD
The PE Network of City Gas Distribution system is laid underground, at average 1.00
meter depth, along the road side in the residential areas and industrial townships.
The PE Network carries the gas at pressure from 4.0 to 5.0 bars. The PE pipes and
fittings selected for the network are of PE 100.
3. LP PE network of CGD
Similarly, the underground PE pipe lines laid at average depth of .8 to 1 meter along
the roads of street and township carry the low pressure gas of 100 mbar. from
service regulators to the various domestic and commercial customer connections in
the residential areas and townships. The isolation valves housed in valve chambers
are provided at regular distance of about 1 kilometer, for section isolation during
repair maintenance and LPT. The pipe sizes of the low pressure PE network ranges
from 32 mm diameter to 90 mm diameter.
Like any other PE network, the major activity associated with gas charged LP PE
network, is repairing of pipelines, when they are damaged mostly by other utilities
and occasionally by rat bites.
The complaints, for such damages are received from customers / public or damage
is found during route patrolling / walk surveys, mostly detected as gas smelling on
the network.
For ensuring timely response and safe PE repairing, written work instructions are
prepared and implemented as given below. The trained and experienced PE welders
are employed for repairing job. The availability and conditions of critical items /
equipments like PE pipes / fittings /portable power generator / PE welding machines
and accessories are regularly checked and audited as per cheek list based audit.
4.0 Procedure for Maintenance of PE Network.
As seen above, PE distribution network is safe against corrosion unlike steel network
however they are prone to damage by third party and rat bite. Hence it needs vigilant
and vigorous patrolling of network and effective coordination with other utility
agencies to prevent damage to pipeline.
The frequencies and the extent of the work are based on requirements set down in
ANSI/ASME B31.8, operational experience and good engineering practice. Based on
past experience, some of the frequencies may be adjusted.
Procedural Steps :
Sr. Activity Responsibility
01 On receipt of O&M contract, contractor shall take O&M
specification / detail of distribution network, as-built Contractor
drawings, testing reports and other construction records In charge
from GSPC Gas
02 O&M contractor shall visit overall site along with related O&M
staff members to make themselves aware about route, type Contractor
of laying and size of pipeline In charge
03 As built drawings / schematic etc of network shall be taken O&M
over from GSPC Gas or from its contractor in soft copy and Contractor
same shall be updated regularly with repairs / modifications In charge
/ extensions carried out over the time period.
04 All above listed maintenance activities shall be Work In charge
commenced immediately after taking over as per
concerned work instruction Annexure – 01, Annexure – 02,
Annexure – 03, Annexure – 05
05 Post surface gas detection survey, the action/s, shall be O&M
initiated & ensured as per Leak Classification and Action Contractor
Criteria (Annexure -04) In charge
06 In case of pressure drop is more than 1.0 bar in a particular O&M
section, pressure drop test in sub-sections (small sections Contractor
of particular big section) either through valve chambers or In charge
squeezing of section shall be conducted. Pressure drop in
particular small section shall be found out / located
07 Vigorous Surface / Subsurface Gas Detection Survey O&M
immediately to identify probable gas leak location shall be Contractor
arranged In charge
08 Excavation at probable gas leak location shall be arranged O&M
and the cause of gas leak shall be identified. Contractor
In charge
09 Repair rectification of gas leak shall be arranged as per O&M
“Procedure for attending Gas leakage / Gas Escape on PE Contractor
distribution network” In charge
10 Report and records of maintenance shall be prepared and O&M
submitted to GSPC Gas O&M In charge regularly Contractor
In charge
11 On receiving intimation regarding charging of a particular O&M
network or extension of network from GSPC Gas Company Contractor
or its contractor, O&M contractor shall visit overall site In charge
along with related staff members to make themselves
aware about route, type of laying and size of pipeline
12 'As Built Drawing' Laying Reports and Pressure Test O&M
reports shall be taken over from Construction Contractor / Contractor
GSPC Gas In charge
13 All valve chambers shall be inspected for proper O&M
construction, it’s cover, tagging & marking and gas leak. In Contractor
case of any gas leak, potential hazard or poor construction In charge
same shall be reported to Construction Contractor and or
GSPC Gas within three days
14 Awareness program including site visit shall be organized O&M
for each member of O&M team Contractor
In charge
15 The extended network shall be included in Annual O&M
Maintenance Plan and maintenance activities shall be Contractor
started as per above procedure In charge
16 Staff shall be regularly trained and educated for network O&M
route, O&M procedures and HSE Aspects Contractor
In charge
ANNEXRURE - 01
Guidelines and Work Instruction For Network Patrolling
All rail and major waterway and road crossings should be inspected on a monthly
basis to observe surface conditions, indications of leaks, general construction activity
and any other factors which may affect the safe operation of gas system.
When a threat to the gas system from third party excavation is observed by a
Supervisor or Inspector then that person must take the appropriate action on site to
ensure the gas pipe is not damaged. It may be necessary in some circumstances to
arrange for an Inspector to be positioned on site to ensure the integrity of the gas
system is maintained.
Role of a Patrol Person
A patrol person plays an important role and is the front line defense against hazards
which the safety and security of the system. This important role should be
recognized by contractor management and care taken to ensure patrol persons are
provided with the appropriate skills and facilities to perform their duties. One of the
basic skills required by a patrol person is the ability to read plans. It is also important
the patrol person can communicate in a verbal and written form, and accuracy is to
be encouraged as an essential feature. It may be necessary for training courses to
be held for the development of patrol persons.
A typical duties and responsibilities for patrol persons are as follow these are for
information and guidance.
• Maintain liaison with other authorities and bodies who are concerned
with works which could affect pipelines. Further, maintain good
relations with the owners of properties traversed by pipelines. Good
communications and in particular keeping people informed on the
location and importance of pipelines is a primary defence against
interference being caused by third parties.
26. Divide total network route in sub-route / section such that total network can
be patrolled at least once in week.
27. Ensure that each member of patrolling team aware about the route of
pipeline, size of pipeline and depth.
28. Observe following along the route
• Excavation work on / near gas pipeline
• Civil work / construction near gas pipeline
• Erosion of soil from gas pipeline route
• Surface faulting, subsidence, flooding on gas pipeline route
• Encroachment by slums other temporary structure
• Encroachment by lorry / galla / tea house
• Other potential hazards
• Valve Chambers and it’s top cover
• District Regulator station it’s fencing / cabinet / gates
29. In case of Excavation / Civil / Construction work on / near gas pipeline,
meet with site supervisor / concerned person and get detail like
• the type of work and purpose
• use of excavation machines or other machines
• depth of excavation
• distance from gas pipeline
• work duration / completion date
• name of contractor, address and contact detail
30. Provide them awareness about gas network and its hazards. Brief them a
safety precautions to be taken to prevent damage to gas pipeline
31. Provide them a contact address and telephone numbers for consultation in
case of any difficulty
32. In case of erosion of soil from gas pipeline route, take depth and length of
erosion. Investigate probable cause of soil erosion. In case of soil erosion
due to reason/s of third party, coordinate with them to prevent them and to
take restore eroded site properly
33. In case of encroachment on / near gas pipeline, report it to concerned
authority to shift / prevent them. Make them aware about gas pipeline
route and its hazards. Explain them safety precaution to be taken to
prevent any incident
34. While patrolling, check the pipeline markers condition
35. While patrolling, keep the speed of vehicle such that all above observation
can be made effectively.
36. Report findings of Patrolling activity in specified format
37. Update the contact address and telephone numbers of concern third party
utility agencies on regular basis.
38. Keep the communication device and list of contact numbers of related
utility agency while patrolling.
39. Use cotton dress and safety shoes while pipeline patrolling activity
40. Use helmet if require to go near construction site
41. Observe and check for trip / fall hazards while pipeline patrolling activity
42. While driving during pipeline patrolling activity, Follow “Safe Driving”
instructions
They should also be acquainted with the hazardous properties of gas and the
potential effect of escaping gas on the safety of the public. It should be emphasized
and encouraged that in the event of an emergency that prompt co-operative action
would be required.
Apart from the essential day to day contact with other Authorities, O&M Contractor
shall formally correspond with the appropriate other Authorities on a yearly basis.
Gas Pipeline Patrolling Report
Date of Patrol :
Network / Area :
Pipeline Section : Size : Length :
This activity consists of (a) Gas Leak Check (b) Partial / Full Valve Operation (c)
Valve Greasing (d) Cleaning and (e) Tag number painting.
28. Ensure that each member of team are aware about natural gas and it’s
hazards
29. Ensure that each member of team aware about the risk involve in valve
chamber maintenance activity, it’s potential hazard and preventive
measures.
30. Supervisor shall be made aware of pipeline network route and valve
chamber locations.
31. Plan the job in advance and ensure appropriate work permit for job.
32. Ensure availability and use of appropriate PPEs and Safety Items as per
“Annexure – PPEs Matrix” during valve chamber maintenance activity
33. Ensure the availability of necessary tools tackles and other items in good
working condition, required for valve camber maintenance activity.
34. Ensure the availability of wireless set / mobile phone at site. After reaching
site, first, establish contact with control room before start of activity.
35. Cordoned the site appropriately and place caution board along the road
site valve chamber.
36. Clean the top cover of valve chamber and note it’s tag number
37. Open the valve chamber top cover, one by one, gentle by holding & lifting
from both sides manually. Take utmost care to prevent, falling of top cover
inside chamber.
38. Remove all the top covers and keep them aside without creating
obstruction.
39. Check the gas leak inside valve chamber using calibrated gas detection
instrument. Supervisor should be trained for operation of gas detection
instrument and measurement of gas leak.
40. Check the flange joints and threaded joint, using bubble test (soap
solution) for any gas leak.
41. In case of gas leak from valve, first attend the gas leak. If require arrange
resources from control room / main office.
42. In case of valve chamber is more than 1.5 meter deep, and seems to be
confined space, first check the oxygen level before entering in valve
chamber. Entry should not be permitted if oxygen level is less than 19.5%.
43. Use ladder to enter inside deep valve chamber.
44. Carry out dewatering / cleaning of valve chamber first.
45. Operate the valve partially or fully depending upon gas flow and line pack
availability for customers. Ensure that gas supply is not affected to any
customer. Avoid valve operation in case of any doubt.
46. Grease / Lubricant the valve in case of valve is jam or operating hard.
47. Paint the tag number of valve chamber on top of cover, if it is faint or
erased.
48. Carry out white wash of valve chamber from inside and outside top civil
portion.
49. Carry out oil paint of specified colour and type, to valves inside the
chamber and metal portion of valve chamber top cover once in year after
monsoon.
50. Close the valve chamber top covers gently, lifting & holding from both
sides manually. Take utmost care, to prevent dropping of top cover inside
chamber.
51. Remove caution board/s and cordoning tape / device from site and restore
site to safe level.
52. Provide message to control room and take activity further.
53. Prepare report of valve chamber maintenance activity in a specified
format.
54. After completion of activity, close out work permit and keep the record of
same.
Valve Chamber Maintenance Report
Date of Maintenance:
Cleaning
Leak Operation Tag No Any
V/C No Greasing & White Painting
Test of Valve Painting Damage
Wash
Remarks :
16. Divide total network route in sub-route / section such that total network can
be surveyed at least once quarter.
17. Ensure that each member of team aware about the exact route of pipeline,
size of pipeline and depth.
18. Ensure that each member of team are aware about natural gas and it’s
hazards
19. Ensure that each member of team aware about the risk involve in survey
activity, it’s potential hazard and preventive measures
20. Ensure the availability of portable / mobile calibrated gas detection
instrument in good working condition having least count of 10 ppm, for
survey activity.
21. Start the gas leak detection survey activity with zero chainage or with
known location / landmark location.
22. After reaching site, first start the gas leak detection instrument and then
walk along the gas pipeline route at the normal speed.
23. For buried pipeline, take atmosphere sampling just above 2” (not more
than 2”) from ground.
24. Sampling should also be taken at ground surface opening such as
manholes, catch basins, sewer, power telephone duct openings, traffic
signal / junction boxes, curb line / cracks of pavements
25. While survey, ensure that probe do not rub in soil getting chocked with
dust and water.
26. Carefully observe the hooter / indicator of instrument while survey /
walking.
27. Note, if instrument shows some indication of gas leak. Survey surrounding
place thoroughly for gas leak intensity. Observe for gas smell.
28. Check for any other flammable gas leak from surrounding.
29. Confirm gas leak, by check at site twice / thrice.
30. Note the gas leak spot along with leak intensity in specified report and
carry out survey further.
Remarks :
Leak
Definition Action Criteria Example
Grade
01 A leak that Requires prompt action Escaping gas that has ignited
represents an to protect life and Any gas indication of gas
existing or property. Continuous which has migrated into or
probable hazards action until the under a building or into
to persons or condition are no longer tunnel
property and hazardous Any reading at the outside
requires immediate wall of a building or where
repair or gas would likely migrate to an
continuous action outside wall of a building
until the condition Any reading of 20% LEL or
are no longer greater in a confined space
hazardous Any reading of 40% LEL or
greater
Any gas leak that can be felt,
seen or heard and which in
location that may endanger
the general public or property
02 A leak that is Leaks can be repaired Any reading of 40% LEL or
recognized as or cleared within six less
being non month if it is not
hazardous at the harmful to human. It
time of detection should be reevaluated
but that has at least once in every
requires repair month
based on probable
future hazard
03 A leak that is This leakage should be Any reading of 20% LEL or
recognized as reevaluated at every less
being non- quarterly till it gets
hazardous at the rectified within one
time of detection year.
and can be
reasonably
expected to remain
non-hazardous
ANNEXRURE - 05
Work Instruction for Pressure Drop Test of Gas Pipeline
18. Divide total network route in sub-route / section such that total network can
be tested at least once in a quarter.
19. Ensure that each member of team aware about the exact route of pipeline,
size of pipeline, valve chamber location, interconnection between network
20. Ensure that each member of team are aware about natural gas and it’s
hazards
21. Ensure that each member of team aware about the risk involve in testing
activity, it’s potential hazard and preventive measures
22. Ensure the availability of portable / mobile calibrated gas detection
instrument in good working condition 1% LEL, for this activity.
23. Conduct Pressure Drop Test between 00.30 A.M to 3.00 A.M (night).
24. Intimate commercial customer for gas supply stoppage.
25. Intimate Storage type Gas Geyser customer for gas supply stoppage
26. Lift the top covers of valve chamber carefully & confirm “0” leakage with
gas detection instrument inside valve chamber.
27. Install a calibrated pressure gauge with least count of 0.1 bar on upstream
and downstream point of section.
28. Isolate upstream and downstream valves of pipeline section which is to be
tested. Isolate interconnection valves / tap-off valves of section to be
tested
29. Observe and note the pressure on pressure gauge and start the hold
period.
30. Hold the section at pressure for two hours.
31. Observe the pressure at upstream and downstream after completion of
hold period and record it in specified format.
32. Remove the pressure gauges and open the isolated valves
33. Carefully close the top cover of valve chambers.
34. Prepare report of Pressure Drop Test in specified format.
PRESSURE DROP TEST REPORT
Conclusion /
As shown above, there is no pressure drop, during Lock Pressure Test, for 2 hours.
Observation:
Content :
Procedure and facilities shall be established for receiving and handling various
complaints related to network / installation of city gas distribution system from the
customers, public and employees. The receipt and handling of complaints shall be
managed through control room manned for 24 x 7 (round the clock) by experienced
and trained O&M team.
The complaints from various agencies may be categorized in to (a) Technical (b)
Non-technical and (c) Emergency Complaint such as
For handling the complaint / emergency effectively and safely, written procedure and
training to the persons should be ensured for Initial communication while receiving
the complaint, communication at site and communication in case of fire and
explosion on network / in customer premises. For handling the various emergencies,
site contingency plan and emergency response plan should be available and regular
mock drill should be carried out.
O&M Control
It shall be recorded in detail as per guidelines given in
Room
Annexure -02
Annexure -17
7 In case of Fire / Explosion, it shall be attended as per
Emergency
Annexure-07. It shall be reported to GSPC Gas per format
Team
given in Annexure -17
8 Details of actions taken at site shall be conveyed to the
control room for necessary communication to O&M Contractor
In charge and GSPC Gas Co
9 Depending on the incident / situation emergency team shall Emergency
ask for additional resources through control room. Team
10 In case of multiple complaints, the appropriate decision /
priority shall be taken / given based on the requirement to
Shift In-charge
protect Life and Property / O&M
The priority shall depend upon the known information like: the Contractor
In charge
volume of gas escaping, the chances of gas ingress to
property and ignition.
Sr.
Activity Steps Responsibility
No.
11 Details of the Gas Escape, Fire & Explosion Complaint, its
cause/s and repairs, etc. shall be recorded systematically and
O&M
shall be analyzed every month and discussed in review Contractor
In charge
meeting with GSPC Gas Company. On the basis of review
corrective and preventive actions shall be Initiated.
12 Material used shall be recorded and reconciliation shall be
carried out as per requirement of GSPC Gas Company. The O&M
Contractor
items consumed from Emergency vehicle should be In charge
replenished upon return to base.
ANNEXURE – 01
List of Tools-Tackles and Safety Items for Emergency Vehicle
The above list is indicative. O&M contractor shall review it and incorporate all
necessary items to handle gas leak / escape, gas fire & explosion emergency
effectively & efficiently
ANNEXURE – 02
Receipt of Gas Leak / Escape Complaint
Control room operators shall obtain following information from the caller person and
shall make record of it in Log book
Customer Details : (whichever is applicable?)
• Name, Address, Telephone number, Customer Number
Gas Escape Detail :
• Type of leak,
• Damage
• heavy gas escape
• gas leak with whistling sound
• gas smell
• Gas Fire / Gas Explosion
• Other Fire but near to gas installation
• Precise location / spot of gas leak ,
• After isolation valve of gas connection (downstream),
• Before isolation valve of gas connection (upstream) ,
• on service line,
• on road side PE network
Loss of Human Life or Damage to Property :
• Preliminary Detail of injury / fatality and nos.
• Preliminary Detail of property damage / loss
Safety Advice:
The following safety advice shall be provided to the caller person by the Control
Room Operator.
• to close the isolation valve to stop the gas supply.
• to turn off all gas appliances such as; hot plate, gas geyser, oven etc.
• to open doors and windows to ventilate the gas
• Not to operate any electrical appliances.
• Avoid smoking and or any source of ignition.
ANNEXURE – 03
Initial Precautions To Be Taken When Arriving On Site
• For leakage from joints and inherent defects in GI pipes and fittings:
a) Re-open the pipe & fittings from the nearest free joint & move towards
the point of leakage.
b) Apply a minimum of 3 clockwise overlaps of Teflon tape onto all
external threads (excepting those of the meter and regulator adaptor).
c) Tighten all pipes and fittings
d) Check for any sign of leakage with neutral soap solution.
• For leakage from union nut, meter connector, regulator connector
a) Loosen the connector / nut and slide it back
b) Remove the damaged seal & replace it
c) Push the connector / nut on the counter part & replace it
d) Tighten the connector to the correct torque.
e) Check for any sign of leakage with neutral soap solution.
• For any leakage from joints where it is not required to loosen any free joints,
tighten the nut or screw and check for any sign of leakage with soap water
solution.
Sr.
Component Probable Causes Action to be Taken
No.
1. Seam Leakage / Replace GI Pipe
GI Pipe Corrosion Replace GI Pipe
2. Hex Nipple Cracked / inherent Replace Hex Nipple
Tighten Hex Nipple
Defect
Hex Nipple Joint Loose
3. Coupling Cracked / inherent Defect Replace coupling
Coupling Joint Loose Tighten coupling
4. Elbow Cracked / inherent Defect Replace Elbow
Elbow Joint Loose Tighten Elbow
5. Reducer Cracked / inherent Defect Replace Reducer
Reduce Joint Loose Tighten Reducer
Sr.
Component Probable Causes Action to be Taken
No.
6. Tee Cracked / inherent Defect Replace Tee
Tee Joint Loose Tighten Tee
7. Cap Cracked / inherent Defect Replace Cap
Cap Joint Loose Tighten Cap
8. Plug Cracked / inherent Defect Replace Plug
Plug joint Loose Tighten Plug
9. Reducing Tee Cracked / inherent Defect Replace Reducing Tee
Reducing Tee Joint Loose Tighten Reducing Tee
10. Union Cracked / inherent Defect Replace Union
Union Joint Loose Tighten Union
Nut Loose Tighten Nut
Seal Missing Replace Seal
Seal Damaged Replace Seal
11. Valve Cracked / inherent Defect Replace Valve
Valve Joint Loose Tighten Valve
Valve Gland Tighten Valve Gland /
Replace Delta Ring
Valve Seat leak Tighten Valve seat
12. Gas Tap Gas Tap Joint Loose Tighten Gas Tap.
Gas Tap Lever Loose Tighten Gas Tap Lever
Screw - but ensure
handle can be operated.
Gas Tap Passing Replace Gas Tap
Cracked / inherent Defect
13 Regulator Cracked / inherent Defect Replace Regulator
Damaged
Regulator Connector Tighten Connector
Loose
Regulator Adapter Joint Tighten Adapter
Loose
Mismatching Adapter Replace Adapter
Sr.
Component Probable Causes Action to be Taken
No.
Thread Seal Damaged. Replace Seal
14 Meter Seal Missing Place New Seal
Cracked Adapter Replace Adapter
Meter Body Leak Replace Meter
Meter Connector Loose Tighten Connector
Meter Adapter Loose Tighten Adapter
Mismatching Adapter Replace adapter
Thread
Seal Damaged Replace seal
Cracked Adapter Replace Adapter
15 Neoprene Tube Poor quality / cracked / Replace Tube / Hose
Hose leaking Replace Tube / Hose
Cracked at the ends Replace Tube/ Hose
Damaged by Rat / Insect
Bites
ANNEXURE – 05
9) After taking above necessary safety precautions, dig a pit to expose the
affected portion.
10) Ensure all effected customers have been notified and have had their supplies
isolated at the control valve.
11) Squeeze the 20mm PE pipe & apply wet cloth to avoid static current &
intimate customer for gas supply stoppage.
12) Cut leaked transition fitting & remove transition fitting.
13) Remove burrs from PE pipe & transition fitting.
14) Install 1/2”x 20 mm transition fitting along with 20 mm dia coupler properly.
15) Weld 20-mm dia. coupler with Electrofusion unit as per Annexure – 14 section
-B
16) Allow the joint to cool down to ambient temperature.
17) Soundness Test the outlet pipe work.
18) If Soundness Test is satisfactory open squeeze tool & ensure no leakage
condition & intimate customer for gas supply resumption
19) Put back R.C.C. guard properly & back fill pit.
20) Collect the scrap / old materials / packing material from the site & dispose it to
a designated scrap yard.
[ C ] Leakage form isolation valve or from G.I. fitting upstream of isolation valve.
Case - 3 Leakage from G.I. fitting (Elbow, Hex nipple, Coupling, Plug, Cap, Tee,
Reducing tee, Pipe nipple, Reducer) before isolation valve:
18. Upon receipt of information of damage to Gas line by control room, Emergency
Team shall rush to site and take following actions
• Inform the control room immediately when arrived on site.
• Assess the situation and need to protect human life & property
• Cordon and secure the affected area
• Close off access roads
• Record the gas readings using calibrated gas detector instrument.
• When the exact location of the leakage is determined Identify or locate
suitable main line and or valve chambers for isolation purpose.
• Dampen the soil with water to prevent sparks
• Inform the Control Room of the findings and progress being made.
19. For damage affecting the gas supply more than 100 nos. of customers, it shall
be informed to GPSC Gas Company immediately.
20. Depending on the severity of the damage the engineer may request additional
resources and assistance from control room.
21. In the event of the escaping Gas igniting a decision will be made by the
Engineer on site whether to extinguish the flame before isolating the gas supply
considering all the aspects on site and keeping in mind that:
• If the flame is not impinging on any material / structure it can be safer to
leave the gas burning until the supply can be stopped than have an
uncontrolled gas escape
• The surrounding area can be kept cool by water spray if available
• Fire from escaping gas from a poly-ethylene pipe will cause the poly-
ethylene to melt and escalate the intensity of the fire.
• Assistance from the Fire Brigade should be sought however the control of
the site and gas should be with Emergency team.
22. Communication (personal / thro public announcement system) will be done to all
affected Domestic / Commercial customers for temporary stoppage or
termination of gas supply requesting customers to turn off their gas suppliers at
the isolation valve
23. All effected properties will be visited to check that their Gas supply has been
isolated at the meter control valve. Records will be kept of those supplies that
have been isolated and those where access to the meter / property cannot be
gained.
24. The control room shall be kept informed of the situation on site at least every
hour and as and when circumstances change.
25. A repair shall be undertaken as per the Type list below :
TYPE A.- Permanent Repair Requiring A Cut Out Of Section – Involving Squeeze – Off
Tools
• A trench is prepared for fixing of squeeze tool on PE pipe. Dampen the
excavated area with water to prevent static sparks.
• Squeeze off pipe as per Annexure - 11
• Ensure zero methane by sampling the atmosphere with a gas detector.
• Fit either
• electro-fusion coupler – as per Annexure – 14
• or new section of pipe as per Annexure – 13 & 14
• or electro fusion clamp – as per Annexure – 12
TYPE B. Permanent Repair Requiring A Cut Out Of Section – Involving Operating
Valves
• Identify leakage area and excavate a trench for undertaking repair. Dampen the
excavated area with water to prevent static sparks
• Identify Valves to be isolated for pipe section.
• Follow Annexure – 10 for isolation of pipeline section and venting of gas to
depressurize the section
• Ensure zero methane by sampling the atmosphere with a gas detector
• Undertake a repair by either
electro-fusion coupler – as per Annexure – 14
or new section of pipe as per Annexure – 13 & 14
or electro fusion clamp – as per Annexure – 12
26. The pipe-work shall be purged with nitrogen to remove air if pipeline volume is
more than 2 m3.
27. After completion of repair / installation of Electrofusion coupler, up-stream valve
shall be throttled or squeezing tool shall be opened slowly for a moment and
NG shall be locked in the section. Lock pressure test shall be carried out for
10 minutes with NG at working pressure where ever possible. Gas leak test
shall be carried out by soap solution / gas leak detectors on repaired portion
28. After completion of repair and leak testing pipeline shall be pressurized (re-
commissioned) as per Annexure – 10.
29. Announce to all customers that gas supplies have been restored - for any
problems to contact the site representative.
30. Inform Control room that the job is over
31. Backfill trench and restore site to a safe level.
ANNEXURE – 07
Work Instruction for attending Fire and or Explosion
at a Building
ANNEXURE – 09
Work Instruction for Making Bar Holes
for Detecting the Presence of Gas below Ground
3. Raise the handle and force down sharply so the top closure plug (inside the
handle) hits the boss head of the spike. The “pile driver” action will drive the
spike into the ground – soil, asphalt or concrete – concrete being the most
difficult to penetrate).
4. When you reach the depth required, remove the spike by means of a reverse
action of lifting the handle STRAIGHT UP so it hits the boss head of the spike
from the underside, so lifting the spike out of the ground in a vertical way.
5. DO NOT MOVE THE SPIKE FROM SIDE TO SIDE AS THIS WILL BEND
THE METAL. ALSO – DO NOT USE THE SEARCHER BAR AS A “CROW
BAR” AS THIS WILL ALSO BEND THE SPIKE.
6. A neat hole is now made in the ground down which the gas testing probe can
be lowered to test for the leak.
7. Retighten the spike retaining Thumb Screw and replace the Rubber
protective foot on the end of the spike when the bar is not in use. Store in dry
conditions.
8. The Searcher bar is only used for making the hole in the ground – not for
measuring gas.
ANNEXURE – 10
Section Isolation :
13) Install the vent pipe of ½” (or adequate size) of height more than three meter
from ground on vent valve/s to allow gas dispersion above human nose level
on ground
14) Post the operator / technicians in downstream wind direction with calibrated
gas detector/s to monitor the gas concentration in atmosphere
15) Carry out gas venting by gradually opening vent valves and ensure following
safety precautions
• Open vent valve gradually & intermittently to prevent accumulation of gas
• Coordinate with technicians, monitoring gas concentration in atmosphere
in down wind direction, to control / to stop gas venting
• Never allow gas concentration above 20% of LEL in atmosphere
• Stop gas venting if it is so to allow gas to disperse
• Ensure that gas does not ingress in buildings
• Observe and ensure no sparking near gas venting area
• Monitor the gas pressure of section
16) Monitor the gas pressure on pressure gauge/s and on vent pipe and confirm
that gas is fully vented.
17) Close the valve/s and isolate the section. Check and ensure that indicator /
pointer of valve/s is in CLOSE position.
Re-commissioning :
18) After completion of job, monitor the gas pressure, installed on upstream and
downstream point of isolated section.
19) Communicate the gas supply resumption in few minutes to concerned
customers, by announcing building to building using public address system.
20) Advice customers to keep the gas tap closed till gas supply resumption
message is received / announced.
21) Open gradually upstream valve. Open the valve till the gas flow sound is
heard and stopped there.
22) Communicate the valve opening to technicians posted in downstream valves
for monitoring of gas pressure.
23) Open the valve further gradually and monitor the gas pressure at upstream
and downstream point.
24) Once gas is pressure is stabilized, open downstream valve/s and resume the
gas supply to customers.
25) Communicate the gas supply resumption to concerned customers, by
announcing building to building using public address system.
26) Communicate to GSPC Gas Co and O&M Contractor In charge through
control room about resumption of gas supply
27) Check the indicator / pointer of all valve/s is OPEN condition.
ANNEXURE – 11
Work Instruction for PE Pipe Squeezing
1. Dig an trench of a size sufficient to carry out the work safely
2. Clean the pipe with a clean cloth to remove dirt and dust particles
3. Install pressure points both side of the squeeze off points to monitor pressure
during operation. See sketch below.
4. Place a water damped cloth on the pipe either side of the leakage point
5. Lift the pipe gently and place a rubber gasket, along with the bottom roller, at
bottom of the pipe at a distance of at least 600mm downstream from the point
of damage
6. Place the second gasket onto the pipe and insert the upper body of the
squeeze off tool (consisting of integral roller, screw and handle) into the lower
roller
7. Rotate the handle in a clockwise direction, so as to move the upper rollers
towards the wall of the pipe. Continue until the pipe is compressed between
the two rollers.
8. Lift the pipe gently and place a rubber gasket, along with the second bottom
roller, at the bottom of the pipe at a distance of at least 600mm upstream from
the point of damage
9. Repeat Steps 5 and 6
10. The ring of the PE pipe inside each squeeze off tool is tested by soap solution
and if leakage is detected the squeeze off is re-tightened further until no
further leakage is observed.
11. A third squeeze off tool is applied 600mm further upstream from the second
squeeze off tool
12. Repeat Steps 5 & 6
13. The damaged section of pipe is repaired
14. The squeeze off tools are released in reverse order in which they were
applied
15. The repaired section and the squeeze off positions are checked for
soundness
16. Apply warning tape and marker pen on the location of the squeeze offs to
ensure no re-application of squeeze offs at the same points in future
17. Collect scrap / burrs/ dust particles and return to a designated scrap yard for
disposal.
Sketch
Pr Point Pr Point
SQ 4 SQ 1 SQ 2 SQ 3
ANNEXURE – 12
Work Instruction For Electrofusion Reinforcement Clamp Welding
2. Stop the flow of Gas by either squeeze off as per Annexure 11 or by closing
valves Annexure 10
3. Remove any burrs from the puncture on the surface of the pipe. Clean the
pipe surface with isopropyl alcohol or acetone using a clean & dry cloth
5. Install the two halves of the clamp, place one over the puncture and one
underneath the pipe
6. Insert a bolt in the first hole of the top half of the clamp in such a manner that
it passes through the first hole of the second half of the clamp
7. Insert a nut over the bolt and tighten by turning it in a clockwise direction and
securing the nut by an appropriate spanner
8. Repeat the process for the hole diagonally opposite the first hole. Similarly
tighten all the other bolts, this will bring the two halves of the clamp tightly
together against the pipe wall
10. Activate the main switch & connect the fusion plug firmly to the contact
terminals of the fitting. Ensure that the contact faces of the fusion connector &
the fitting are free of coatings & deposits
11. Read the bar code with the wand by holding the wand at a slight angle and
moving it briskly left to right of the label
12. If the wand is used correctly and the bar code is matched then this is
confirmed by the emittance of an audible “beep”
14. Press the START button and the automatic fusion will take place, with the
required fusion time shown
15. At the end of the fusion process, STOP indication is displayed on the screen
16. Allow the joint to cool for at least 30 minutes
17. Re-commission the line with natural gas. Check & ensure that there is no
leakage using a soap solution
18. Remove the un-fused second half of the clamp
19. Collect the scrap/ burrs/ dust particles and deliver them to a designated waste
yard.
ANNEXURE – 13
1. Both ends of the pipe to be joined shall be cut square and perpendicular to
the axis of the pipe. All burrs shall be removed
2. Remove any burrs from the puncture on the surface of the pipe. Clean the
pipe surface with isopropyl alcohol, using a clean & dry cloth
3. Prepare the pipe surface using appropriate tooling to remove a uniform layer
of the PE oxidised surface over an area slightly greater than the fusion
footprint of the fitting
4. Insert both ends of the pipe into the coupler so that they meet at the centre
mark
5. Connect the electrofusion control box to a power supply – either mains
electricity or a generator
6. Activate the main switch and connect the fusion plug to the contact terminals
of the fitting. Ensure that the contact faces of the fusion connector and of the
fittings’ terminals are free of coatings & deposits.
ANNEXURE – 14
1. Read the bar code with the wand by holding the wand at a slight angle &
moving it briskly from left to right of the label
2. If the wand is used correctly and the bar code is matched then this is confirmed
by the emittance of an audible “beep”
4. Press the START button and the automatic fusion will take place, with the
required fusion time shown
5. At the end of the fusion process, STOP indication is displayed on the screen
7. Re-commission the line with natural gas. Check & ensure that there is no
leakage by using a soap solution & a Combustible Gas Indicator
8. Collect the scrap/ burrs/ dust particles and deliver them to a designated waste
yard for onward disposal
[B] Electrofusion welding
1. After switching on, all the displays show “0000” on the screens.
5. Depress the “+” button several times until the desired number of seconds is
displayed on the screen
6. The next stage is reached by depressing the “+” button for another 1 second
8. Press the “I” key. The continuous fusion process is indicated by the time display
running backwards
9. When fusion process has been completed successfully, display shows “0000”
11. Allow the joint to cool to ambient temperature & check for leakage with soap
solution or a Combustible Gas Indicator
12. Collect the scrap / burrs / dust particles and deliver them to a designated waste
yard for onward disposal.
ANNEXURE – 15
There are all probabilities that while carrying out maintenance activity on the GI
installation some stray current passing through the pipe may electrocute the person
carrying out maintenance.
The activity may also be affected due to electrostatic current produced during the
activity.
1. Check whether there is any stray current on the pipeline with the help of the
tester. Ensure that the tester is in contact with bare pipe and not the coating.
2. If it is found okay, connect the earthing system as per the attached drawing.
a. Insert the Earthing rod into the soil (Minimum one foot). Pour the water
nearby area of rod for good earthing.
b. Connect the earth cable to the pipeline with the help of crocodile type
clamp. Before connecting the clamp remove the coating for better
contact.
3. Wherever the pipe is cut in two pieces or an installation is dismantled from
the in between portion use a jumper wire to ensure the continuity of the
earthing on all the portions of the installation.
4. Ensure the earthing rod is properly inserted in the ground.
5. To have better earthing make the ground wet at the portion where the
earthing rod is to be installed.
ANNEXURE – 16
1. Evacuate where:
• Gas concentrations are 40% LEL or above inside the properties.
OR
• Person/ s is / are exposed to gas or products of combustion
OR
• Occupant’s safety is at risk.
8. Locate the suitable safe place nearby and allow public to gather there
12. Inform GSCP Gas Co and O&M Contractor In charge through Control Room
ANNEXURE - 17
Incident
Reason
Location
Date/Time
Procedure and facilities shall be established for receiving and handling various
complaints related to network / installation of city gas distribution system from the
customers, public and employees. The receipt and handling of complaints shall be
managed through control room manned for 24 x 7 (round the clock) by experienced
and trained O&M team.
The complaints from various agencies may be categorized in to (a) Technical (b)
Non-technical and (c) Emergency Complaint such as
Content :
1. General Information
3. Work Instruction
of a CPRS, DRS
The pressure monitoring of all CPRS / DRS across the network is carried out
regularly, on daily basis, by visiting individual site and remedial measures taken as
required.
The operation and maintenance plan containing activities, frequencies and schedule
for CPRS / DRS shall be prepared based on manufacturer’s recommendations,
various statutory & code of practice / guidelines, conditions and year of service. And
it shall be executed / implemented and monitored. Below table suggests O&M
activities and their frequencies.
Sr.
Activity Frequency
No.
01 Monitoring of Pressure (Inlet / Outlet) Daily
02 House Keeping in and around Fenced Area Quarterly
03 Leak check / testing Quarterly
04 Draining / Venting Quarterly
05 Preventive Maintenance of CPRS / DRS, Yearly
On line testing / resetting of active, monitor, SSV &
SRV
Cleaning of filter elements
Isolation Valve operation
Leak check
House Keeping
Fencing & cabin
Paint Touch-up
Display of Asset Name & Tag
Display of Emergency Contacts
06 Pr Gauges (Inlet, outlet, differential) Yearly
07 Hydro Testing OR Internal Inspection of filter body Five Yearly
08 Attending gas leak / over pressure / under pressure / gas As when required
stoppage
2. Procedure for preventive maintenance of CPRS / DRS
Sr.
No. Activity Steps Responsibility
1 Based on O&M frequency of CPRS / DRS, Annual O&M Contractor
In charge
Maintenances Plan covering all CPRS / DRS shall be
prepared and submitted to GSPC
2 As per Annual Maintenances Plan, spares / material O&M Contractor
In charge
required shall be checked for availability. If required, new
spares / material shall be procured / arranged in
coordination with GSPC Gas.
3 Required staff / engineers shall be trained and educated for O&M Contractor
In charge
O&M activities for CPRS / DRS
4 Based on Annual Maintenances Plan, Monthly Preventive O&M Contractor
In charge
maintenance schedule for CPRS / DRS shall be prepared.
5 On scheduled date work permit shall be obtained. Work In Charge
6 On reaching the site, process of initial observation of CPRS / Work In Charge
Work Instruction - 01
Functional Checking / Testing and Resetting
of PRVs, SSV and SRV of a CPRS/DRS
• Close the drain valve and fit the mmwc pressure gauge, at the drain point after
SRV, and open the valve after fitting pressure gauge.
• Check / record the initial inlet, outlet, and monitor regulator valves’ flowing and
locked pressures, along with the time of recording.
• Close the inlet and outlet isolation valves of the service regulator and
depressurise the system by operating vents / drains, of filter body, near SSV,
between PRVs and after SRV.
• Release the spring tension of the valve by unscrewing the pressure setting
screw after Measuring / recording the initial setting of pressure setting screw
and releasing the lock nut.
• Unbolt and open the actuator bonnet of the SSV and do oiling/ greasing of
valve and actuator parts for easy movement of parts. Keep the SSV closed.
• Open the bonnets of active regulator valve and check the condition of rubber
diaphragm and internals. Ensure that there is no puncture / hole / crack on the
diaphragm, it has retained its elasticity and that there is no foreign part / dust
etc inside.
• Assemble the bonnet back, if everything found satisfactory, ensuring the
breather hole in the bonnet is clean and clear.
• Repeat the above steps for monitoring and SRV valves.
• The Pressure setting screw of Active, Monitor valve should be fully unscrewed
to ensure the closing of both the valves at initial stage. The setting screw of
SRV should be set near to earlier recorded setting.
• Diaphragms, spring rubber seats and other parts should be replaced, if found
damaged, worn out.
• Wherever pilot regulators are given for large flow capacity service regulators,
the pilot regulators, their tubing should be checked for effective working and if
required their diaphragm, spring, rubber seat and other parts should be
changed.
• Ensure that SSV actuator and valve are working effectively, by frequently
operating the same to open / close position, with the use of gas supply and
lever, before assembly.
• If found ok, assemble the SSV’s actuator on valve.
• Close the drain and vent points, crack open the inlet valve of SR and allow the
pressure to go up to max operating figure.
• Carry out leak check of all joints once again, especially the bonnet and tubing
joints by soap solution.
• Check that the active monitor valves are not passing, as shown by zero
pressure on the drain point after SRV.
• Set the pressure of the monitor regulating valve by screwing down the setting
screw and observing the pressure in the gauge. It should be as per CPRS /
DRS Supplier.
• Similarly set the pressure of the active regulator by screwing down the setting
screw and observing the pressure in the gauge. The pressure of the active
regulating valve should be as per CPRS / DRS Supplier.
• Observe the system for 10 / 15 minutes for effective working of valve in locked
position, the set pressure should not rise.
• If found o.k. open the downstream low pressure isolation valve of CPRS / DRS
• Observe the system and do the fine tuning of required gas pressure for the
downstream network.
• The system should be observed for pick and non pick hours for minimum and
maximum pressure.
• System should be monitored for working pressure as mentioned above, for 2
days.
Work Instruction – 02
Cleaning / Replacement of Filter Elements of CPRS / DRS
• Ensure that filter body is depressurised by opening drains and top gauge
connection. Venting is done under controlled condition with all safety
precautionary measures as per work permit system
• Before starting venting operation, ensure that CPRS / DRS inlet and outlet
valves are closed.
• Unbolt bolts of Top cover of filter & Remove Filter top cover, carefully.
• Remove filter element carefully, after removing the nut on element guide rod.
• Observe / check the inside of filter body and element fixtures for any
abnormality, and finally clean inside of the filter body.
• Clean the faces of faces of filter cover and body
• Similarly clean and reuse the old element, if possible.
• If required, replace the element with new element.
• Refit the element by screwing down the nut, washer and rubber packing, on
guide rod.
• Use the old gasket if the condition of the same is good. If not replace the
same, by new gasket.
• Refit the top cover by bolting down equally on all sides.
• Carry out the leak check of cover joint by soap solution, when the filter is
pressurised after completion of all other jobs on CPRS / DRS.
• Check and record the final DP, if available.
• Prepare the report and update the record including, spares / material
consumption statement and submit to GSPC Gas in charge for material
reconciliation and inventory management.
Work Instruction - 03
Routine Maintenance of CPRS / DRS
• Check CH4 % with gas detector and carry out leak test with soap solution &
Cosmos meter, of all pipe, valve and tube joints.
• Clean all valves, drains vents, pressure gauges, pipe spools and pilot
regulators and filter, with dry clean cloth.
• Grease plug valve with grease stick till all valves becomes free in operation.
• Operate l valves in clock-wise/anti clock-wise direction frequently to make all
them free in operation.
• If found necessary paint all plug valves and audco valves with blue colour,
pipe, vent pipe with yellow colour, Filter with silver colour , S.R.V. with red
colour , P.R.V. & S.S.V. with sky blue colour.
• If Regulator No. / Equipment No. is not visible, required marking is done with
appropriate paint.
• Collect and deposit the scrap / garbage from above activities, at designated
scrap yard.
• Close the cabin and fencing gate and lock it.
Work
SR
Sr. Upstream Downstream Differential In
Date Time Tag Location
No. Pressure Pressure Pressure Charge
No
Sign
_____________ ________________
Checked By O&M Contractor In-charge
Report for Maintenance of CPRS / DRS
Date of maintenance:
_____________ ________________
Work In Charge O&M Contractor In-charge
3.8 Industrial Connection
General Information :
In a city gas distribution business, gas connection to industry is a major activity and it
consists of variety of gas equipment from simple furnace to complex thermo pack or
boiler. PE pipeline carrying pressure at 4 -5 bar, is laid underground from
downstream of CPRS and connected to MRS which is installed in industrial premises
for metering and regulating purpose.
The selection of site for installation of Metering and Regulating Station (MRS) in the
premises of industry is key to safety & integrity of gas installation and public. It
should be installed in well ventilated area away from buildings or major installation
having easy approach and access.
Commissioning of Industry:
Before charging the gas in the industry, pre-commissioning safety checks of that
industry should be carried out by concerned work in charge so that commissioning
can be done in time with all safety measures.
This safety checks will not only show the status of various sections / equipments, but
will also indicate the requirements of tools, gauges, sizes of valve keys etc. to be
kept ready at site.
Safety checks / precautions to be observed before and during commissioning
• Ensure that all items like pipes, valves, fittings are of standard quality having
proper test certificates.
• Ensure that standard fabrication, welding, inspection and installation methods
are followed.
• Check / Review pressure testing reports of all sections / equipment.
• After ensuring pressure testing, take leak test by locking 1 to 2 bar pressure of
N2 in all section. Use soap solution to find out the gas leak and repair / rectify
gas leak if it is found.
• All sections / equipments must be N2 purged to remove air (Oxygen) from the
installation to minimum 2% by volume.
• After N2 purging & testing, the whole installation should be pressure locked, at
0.5 bar of N2.
• Finally, close the following valves.
1. MRS gas filter outlet valve.
2. MRS gas filter by pass valve.
3. MRS outlet valve.
4. Gas train inlet valve.
• The healthy functioning of sequence controller for burner operation is of vital
importance and it should be checked, first in the laboratory by sequence
controller tester and then at site after installation.
• All safety interlocks and Audio visual alarms should be checked twice for their
functioning.
• Special attention should be given to the proper functioning of block and bleed
valves.
• Bleed valve’s outlet should never be plugged. Ensure that leak indicating
water bottle is fitted on it and if needed, in congested space the bleed valve
outlet may be guided out in the open atmosphere by providing rubber tubing /
piping.
• DCP type fire extinguisher should be located near the site.
• Other safety checks, like electrical hazard, position of flue gas damper access
valves, valve keys, overall housekeeping etc should be carried out to ensure
overall safety.
• All measuring instruments like Pressure Gauges, O2 analyzer, Gas Detectors,
etc should be calibrated and their batteries fully charged to remain operative
throughout N2 purging and gas charging.
• Wireless communication is very vital for saving the time and in case of
emergency during gas charging in the industry.
From safety point of view gas should be taken to the burner, section wise, namely.
1. Confirm the closure of gas train inlet. Observe carefully closing mark.
2. Crack open the MRS outlet valve and Keep valve key on position and
raise the section pressure to 1 or 2 a man with walky talky.
bar.
3. Crack open the pressure gauge Do not inhale N2.
tapping valve near gas train inlet valve
and vent out N2. Ensure no spark / no naked
flame. Methane concentration in
atmosphere should not increase
more than 2% If required do
venting / draining intermittently.
4. Measure CH4 (Methane) %. It should Observe No spark / no naked
be more than 90%. flame: If required do Venting
intermittently.
5. Close the pressure gauge tapping
valve completely.
6. Open the MRS outlet valve fully and
observe the system for 5 minutes.
GAS CHARGING IN GAS TRAIN BURNER:
SR.
ACTIVITY PRECAUTION
NO
1. Close industry’s tapping valve. Do greasing of MRS inlet / outlet
valve, check closing mark on valve
& use proper valve key.
2. Close MRS inlet valve and at Do greasing of MRS inlet / outlet
downstream joint of this valve fit valve, check closing mark on valve
blank / spade or separate flange joint. & use proper valve key.
3. Close MRS outlet valve. Do greasing of MRS inlet / outlet
valve, check closing mark on valve
& use proper valve key.
4. De – pressurize MRS by opening Smoking, Sparking to be avoided.
filter drain venting of pipe section Check over head electric wires.
after PRV & venting of standby Methane concentration in
stream. atmosphere should not increase
more than 2%.
5. Purge the whole MRS with N2. Check N2 cylinder before use.
Check condition of gas detector
before use.
6. Measure methane% (less than 2%) It should be 0.00% for ideal
twice. condition.
7. Do the repair / maintenance job. Take all necessary safety
measures as mentioned above.
8. Do visual inspection of all joints /
work.
9. Purge the system again with N2 and As per No. 5. Ensure no leakage in
test system with N2 pressure. MRS after repairing / maintenance.
10. Check O2% (less than 2%) twice. Check condition of O2 Analyzer
before use.
11. Recharge NG by slowly operating.
- Tapping valve.
- MRS inlet valve.
12. Finally open the MRS outlet valve.
13. Observe the installation for at least Ensure that nothing left-out inside
10 minutes after successful PRS after the completion of job.
recharging of system.
Whenever any pipe or equipment that has been installed on gas service is to be
opened, it is the duty of work in charge to obtain the necessary safety work permit
along with appropriate planning / preparations to carry out the job effective.
Communications is very important. The set steps of carrying out the jobs are as
follows:
possible, double isolation should be done. Valves should be greased for perfect
sealing before closing and also after closing to ensure that it is not leaking / passing.
Once the valves are satisfactorily closed valve key should be removed from valves
or valve wheel to be tagged or locked to avoid unauthorized operation and thereby to
avoid accident.
[B] De – Pressurizing Of Section / Equipment:
Once the valves are fully closed and greased, the de – pressurizing of the section
can be done by venting out the gas at, atleast 3 meter height with adequate safety
precautions especially observing no smoking, no sparking and no gas concentration
above 2% of LEL.
Venting area should be cordoned off and man with gas detector should be posted at
the down wind direction to measure the methane in atmosphere. The methane in
atmosphere should never increase more than 2.0%. If required, venting should be
done, intermittently to give more time for gas dispersion. Similarly, gas venting
should be stopped when some vehicle is passing near the spot, if operation is being
done on traffic roads.
[C] Opening Of Flange Joint:
• The opening of equipment or pipe section / valve, filter, etc… pose a special
safety problem and unless proper precautions are taken, mishap may occur.
The problem gets magnified if the section to be opened is pressurized with
natural gas.
• In opening flanges, or cover plates, employees shall first loosen the bolts on
the far side away from the man doing the job, with a sufficient number of bolts
allowed to remain tight on the near side until the connection can be wedged
open. Any anticipated, entrapped pressure / gas will then be dissipated in a
direction away from the man doing the work.
• During the course of work, any unsafe condition, if noticed, report promptly to
the permitting authority for taking corrective actions.
Industrial Complaints and Remedial Measures :
2. Immediately isolation of
valves and to replace the
damaged portion.
B
FLAME & FLOW
Content
1. General Information
Domestic Customer
Customers
1. General Information
Domestic gas connection is very critical asset which need regular maintenance to
ensure integrity of asset and safe installation. Domestic gas connection is operated
by house wife / family which are not knowledgeable / expert in maintenance of gas
installation.
Many a times tampering / improper use found with gas installation like illegal
extension, use of non-standard or long rubber tube, use of pipeline for hanging
cloths or other house items etc. Many a times, joints of gas pipeline found loose
overtime due to undue stress / use of pipeline as above. All these might results in
leakage/s of gas in house causing fire and explosion, if it is not inspected and
repaired / maintained properly & in time.
Sr.
Activity Steps Responsibility
No.
01 O&M Contractor shall take over the list of domestic
O&M
connections, it’s area and planning of annual service from Contractor
In Charge
GSPC Gas
02 A Service Card as per Annexure – 01 shall be prepared and O&M
Contractor
maintained for each customer. In Charge
03 Annual Service shall be executed as per Annexure – 02 O&M
Contractor
In Charge
04 Any leakage observed by the technician / contractor during O&M
Contractor
the execution of Annual service shall be attended. In Charge
05 After completion of annual service, service card shall be filed O&M
Contractor
and customer signature shall be obtained. In Charge
06 If any house is found closed, customer shall be
communicated by affixing a sticker at his premises. Also a O&M
Contractor
letter requesting the customer to fix time for availing service In Charge
shall be sent through post.
07 Customer clearance / Complaints regarding annual service
O&M
shall be received and same shall be attended on priority Contractor
In Charge
basis.
08 O&M Contractor shall submit signed off Service Card/s and
O&M
“Report for Annual Service of Domestic Customer” as per Contractor
In Charge
Annexure-03 to engineer in charge of GSPC Gas for review.
09 Findings of Annual service shall be analyzed, reviewed
O&M
during the meeting with GSPC Gas & corrective & Contractor
In Charge
preventive actions shall be initiated for future improvement.
10 O&M Contractor shall invite GSPC Gas to randomly check O&M
Contractor
quality of the Annual Service at various domestic customers In Charge
11 On the basis of measurement sheets, contractor bills shall O&M
Sr.
Activity Steps Responsibility
No.
be finalized and payment shall be made Contractor
In Charge
12 Monthly material consumption & reconciliation report shall
O&M
be prepared and submitted to GSPC Gas for review and Contractor
In Charge
approval.
13 After completion of contract, all Service Cards shall be O&M
Contractor
handed over to GSPC Gas or it’s designated contractor In Charge
Annexure – 01
Service Card
Customer Address
No
Name of Contact Nos
Customer
Date of Leak Clamps Paint Tube Cap Sign of Sign of
AMC Atten Replac Touc Replac Replac Technician Customer
ded ed h Up ed ed
Nos of Repair / Replace
Annexure – 02
Work Instruction for Annual Service of Domestic Customer
1. Before starting the service, obtain permission from the customer.
2. Clean the pipe thoroughly using wire brush at corroded pipeline area and paint the
pipe with two coat with specified paint
3. Fix additional clamps where line is found hanging.
4. Tight / Refit / Replace the clamps where it is loose / damaged.
5. Replace neoprene / surksha tubes at points where it is in use.
6. Check for leakage:
________
O&M Contractor In-charge GPSC Gas Engineer In-charge
3.10 Calibration, Testing & Certification
Content :
1. General
There are many items and equipments of City Gas Distribution System, which need
to be periodically calibrated, tested for ensuring their functioning, working accuracy
and complying the laws and statutory requirements. Periodic calibration of
measuring, detecting items and testing of pressure vessels and valves, not only
ensure the integrity of whole system but also enhance the safety of the facility
The Gujarat factory act says that pressure gauges and safety relief valves on
pressure plants / piping should be calibrated every year. Similarly as per SMPV,
there are various periodical inspection and test requirements for pressure vessels
like knock out drum, filter / separators, etc installed at city gas station (CGS) of gas
distribution system. Items and equipment to be calibrated are identified, the
frequency of calibration is decided as per manufacturer’s recommendations or as per
requirements of law, statutory compliance or their criticality of function or if they are
found susceptible in their function and accuracy. For proper documentation of
reports and history records the numbering and tagging of the items and equipments
identified for calibration is very important, hence before preparing and finalizing the
Mater Calibration List and Annual Calibration plan, proper numbering and tagging
should be done . For assigning the calibration jobs to any internal / external agency,
it must be ensured that the adequate calibration facility is available and trained
persons are engaged. Similarly it must be ensured that master calibrator is within
calibration period and the agency posses the tractability proof for the same. The
process of identification, numbering, tagging and calibration, is carried out as per the
following procedure and work instructions, reports and records.
2. Procedure for Calibration and Testing of Instruments & Equipments
A. CGS
Nos. Calibration
Nos. Calibration
Nos. Calibration
1 Pressure Gauge Yearly
Nos. Calibration
Nos. Calibration
Nos. Calibration
2 SRV Nos. Resetting Yearly
UT,
3 KOD Nos. Certification Yearly
External
Yearly,
Temperature
4 Nos. Calibration as required
Transmitter
Yearly,
Pressure
5 Nos. Calibration as required
Transmitter
Differential
Yearly,
6 Pressure Nos. Calibration
as required
Transmitter
Differential
Yearly,
7 Pressure Nos. Calibration
as required
Transmitter
Temperature
8 Nos. Calibration Yearly
Gauge
UT,
Yearly
9 Filter Separator Nos. Certification
External Yearly
Hydrotest /
10 BA Set Set Yearly
Refill
Refill /
11 Fire Extinguisher Nos. Yearly
Inspection
B CPRS / DRS
Nos. Calibration
Nos. Calibration
Nos. Calibration
Nos. Calibration
2 SRV Nos. Resetting Yearly
UT,
3 KOD Nos. Certification Yearly
External
UT,
4 Filter Separator Nos. Certification Yearly
External
Refill /
5 Fire Extinguisher Nos. Yearly
Inspection
C. Service Regulator
D. Emergency Vehicle
Refill /
1 Fire Extinguisher Nos. Yearly
Inspection
E. Control Room
Refill /
1 Fire Extinguisher Nos. Yearly
Inspection
F. Gas Detectors
Methane Meter
1 Nos. Calibration Yearly
(CH4)
Leak Surveyor
2 Nos. Calibration Yearly
Instrument
Oxygen Analyzer
3 Nos. Calibration Yearly
(O2)
Note: While preparing annual calibration schedule, hydro test of KOD, Filter
separator, Air Tank, BA Set, BDV, Fire Extinguishers etc to be considered after 5
years.
ANNEXURE ; 02
Prepared By Authorized By
Instrument /
Sr. Instrument Date Of Responsibility
Equipment
No. Location Calibration For Calibration
Name & Tag
Prepared By Authorized By
Instrument /
Sr. Calibration Calibration
equipment Location
No. Done By Remarks
Name & Tag
Prepared By Authorized By
LOCATION:
Name of the Instruments: Instrument Tag No.:
Range: Acceptance Limit: Upper –
(Unit) Lower –
Instrument Location: Calibration Frequency:
Sr. Responsibili
Activity steps
No. ty
1 Case 1: External Examination O&M
Contractor
It is ensured that every half yearly external examination of F/S, In Charge
KOD & LDS are carried out and report is received from
Competent
competent person as per Factory Act. Agency
2 Case 2 : Thickness Test O&M
Contractor
It is ensured that every half year Thickness of F/S & KOD Drum In Charge
is checked by Ultrasonic Instrument & report is received from
Competent
Competent person as per Factory Act. Agency
3 Case 3 : Hydro Test O&M
Contractor
It is ensured that every four years stability test of F/S KOD is In Charge
taken by hydro test & report is received from Competent person
Competent
as per Factory Act. Agency
4 For case of hydro test the job is carried out as per following O&M
In charge
steps.
5 As per Work Permit Coverage, Work Permit is obtained & O&M
In charge
Control room is informed about starting of job.
6 Appropriate PPEs are arranged and ensured wearing by O&M
In charge
working crew.
7 The section / line where F/S & KOD are installed are fully O&M
Team
isolated.
8 Gas of the isolated section is vented to depressurize the O&M
Team
section. Venting is carried out intermittently in a controlled
manner to prevent the accumulation of Methane beyond
20 % of LEL. The same is monitored in the downwind direction.
9 Nitrogen purging is done in that section to reduce methane O&M
Team
percentage to zero.
10 Top cover, inlet pipe piece & outlet pipe piece of F/S and KOD O&M
Team
are unbolted and removed.
11 In case of KOD or LDS, internal cleaning is carried out, and O&M
Team
cleaning or replacing the filter element as required
12 Top cover is refitted after cleaning and checking of faces and O&M
Team
gaskets.
13 The connecting pipes are fitted back after unbolting the blind O&M
Team
flanges on the inlet, outlet and drain valves.
14 System is checked for leakage by pressure testing at 10 kg/cm2 O&M
Team
with N2 and applying soap solution at all the joints. If leak is
observed. It is arrested by tightening the bolts
15 N2 purging is again carried out to ensure oxygen percentage is O&M
Team
less than 2%.
16 If system is OK, N2 is removed and system is commissioned O&M
Team
with N.G.
17 All the joints are checked by soap solution once the pressure O&M
Team
rises to maximum operating pressure and ensured that there is
no leakage.
18 Waste material generated during maintenance work is collected O&M
Team
as per the following:
If waste is in the form of liquid, the same is collected in the
plastic container/barrel depending upon the quantities of
waste and the same is given back to the supplier;
If the waste is in the form of dust, the same is collected in
dustbin and disposed off at designated place.
19 Control Room is informed for completion of job. O&M
In charge
20 Work permit is signed off. O&M
In charge
21 Records are updated in Equipment History Cards (Refer O&M
In charge
Annexure -06 )
ANNEXURE : 06
Critical Work In
Date Of Maintenance
Sr. Pending Remark charge
Maintenance Activity Detail
Action Signature
3.11 Festival / Occasional Activity
1. General Information
Various festival and occasion celebration, by the customers and society have safety
impact on the installation / network of city gas distribution system.
The main festival that require more safety measures are Diwali holidays, and Holi
lighting. Burning of various type and size of crackers, poses fire and explosion
hazard in the domestic premises and distribution network located in the population
zones, if there exists a unnoticed gas leak. Even throwing burning / red hot crackers
on the transition fitting installed behind RCC guard, can damage the PE part of TF
causing gas leak, which may result into fire and explosion. Also primary fire due to
crackers on grass and dry vegetation around leaking gas can cause secondary fire
on installation / network.
Similarly during Holi festival, the spot where holi is lighted / burnt may cause damage
to underground PE pipe line, depending up on the spot location from underground
PE, size and time duration of Holi burning.
Hence for ensuring safety and integrity of people and network, special festival safety
drive is taken up, in advance, just before the festival. And special, petrol and survey,
including the public announcement for safety precautions are carried out during the
days of actual celebrations. Special safety and security watch are also provided for
critical and vital installations, by a dedicated team of persons.
2. About Diwali festival safety
As shown below, for Diwali Festival, such drive mainly includes the leak survey of
installation , network, lock pressure test of network, likely to be affected, customer
education through various media, and ensuring readiness of emergency vehicle,
along with gas detectors, communication means, fire fighting equipments, public
address system, and tools tackles. Even it is ensured, that competent O &M persons
and responsible management persons as per Emergency Response Team are
available during such festival holidays.
For Holi Festival, pre Holi survey is carried out by visiting all the known spots of Holi
Burning. For old spot locations previous years’ records are referred and every time,
new spots are added in the list as found during visits and survey. In some cases of
suspicion of likely damage to underground PE, society / street leaders are requested
for shifting the spot to a safe place. Similarly some doubtful / vulnerable spots are
revisited for leak survey, next day after holi burning.
Action Plan For Diwali Festival safety activities.
days from -------------
Sr. Responsibi
Activity Detail Date Remarks
No. lity
A Pre Diwali Activities
Identify the competent persons and
1 prepare the action plan to carry out the
activities on scheduled date and time.
Review / recall of previous years’ records
and experience, in handling festival and
2
modify / update the current year’s
planning / procedure accordingly
3 Organize Tool Box training for all O&M,
persons, for explaining every one’s role &
responsibility in the various activities and
safety precautions during Diwali holidays.
Carry out lock pressure test of the PE
4
network.
Carry out leak detection survey on PE
5 network, especially, on critical and
vulnerable section / network.
Sr.
Activity Detail Date Responsibility Remarks
No.
The intent of this chapter is to give working guidelines for those who are engaged in
safeguarding of gas pipe lines. Natural gas supplied through the network of city gas
distribution, is highly inflammable and gas escape from the damaged pipe may pose
the potential hazards of asphyxiation, fire and explosion. The PE pipes used for
underground gas network are softer, delicate and highly susceptible, vulnerable to
damage when hit by excavating tools used during manual and / or mechanical
excavation. Similarly, the excavation carried out by mechanical equipments like, JCB
and sometimes manual excavation may damage the underground steel gas
pipelines, or it’s corrosion protection coating, which in turn, leads the pipe failure due
to corrosion, with the lapse of time, if coating is not repaired in time.
Hence it is quite safe and economical to prevent the damage to the pipe lines, rather
than repairing the damaged / leaking pipe. Hence the safe guarding of underground
gas pipe lines from damage is very important activity, considering safety of public at
large and for ensuring safe and uninterrupted gas supply to the customers.
The excavation activities are mostly carried out by other utilities, mainly, water
department, drainage department, road and building departments of Municipal
Corporation of the city or Nagarpalika of a town, BSNL, OFC cable layers, electricity
power supplier, and sometimes by customers.
Various pipe lines safe guarding activities are planned based on, the size and
spread of the underground pipeline network, current & planned infrastructure
developmental activities by all listed utilities, and past experience & records, and
They are executed by deploying competent persons after imparting trainings.
The training tropics mainly focus on,
• Natural gas and it’s properties,
• Hazards of gas escape,
• Causes of pipe line damages,
• Pipe line net work and geography of network spread,
• Understanding as built network drawing
• The site supervision and liasioning,
• Oral instructions and written communication with other utilities.
• Issuing warning notice and damage recovery to excavating agencies, in case
of damage and gas escape.
• Name and contact nos. of excavating agencies and their area of work
• Future excavations plan by other utilities.
Liasioning and coordination with other utilities, for providing gas pipeline network
drawing, company’s emergency contact nos. and providing assistance and site
supervision in safe guarding gas pipe line while they carry out the excavation
The safe guarding of gas pipe lines from damage by manual excavation is easy and
safe, where as safe guarding pipelines during mechanical excavation needs extra
precautions and preparedness and continuous site supervision. It is therefore
advisable to request the excavating agency to carry out the manual excavation in
close proximity of gas pipe lines and critical areas.
Special instructions should be given to the excavating contractors and labours for
reporting the incidental damage / gas leak and warned / penalized for hiding the
damage and gas leak. The hidden leak can become the hazard any time.
Rerouting, shifting and lowering and supporting the hanging pipelines / section are
the activities sometimes associated with safeguarding.
The intent of this chapter is to explain the terms and provide minimum guidelines.
Modification is a term used for the activity of changing the existing plant layout,
process and equipment. Modification may be carried out during initial installation, in
the running plant, after certain experience of operation and maintenance, to meet the
intended output and performance, to enhance quality and safety, to improve process,
layout, operation and maintenance.
Modification should be planned after considering various pros and cons. Cost /
benefits, visible safety and quality improvements. Modification should be decided,
planned and executed by a team of experts drawn from concerned departments.
Modification carried out should be reviewed to understand and study deviation from
intended performance / output. The intended performance of modification carried out
must have reasonable period of validity and should not become non operational
before time.
Modification in gas charged network should be carried out as per safe procedure and
safe practices, after obtaining work permit.
After a period of operation, in the city gas distribution network, certain material /
items are found failed or about to fail or obsolete. Hence they need to be replaced by
new substitute item to upgrade the whole network / system.
Upgradation should be planned after considering various pros and cons like cost /
benefits, asset & operation integrity, safety & quality improvements. Upgradation
should be decided, planned and executed by a team of experts drawn from concern
departments.
Upgradation carried out should be reviewed to understand and study deviation from
intended performance / output. The intended performance of Upgradation carried out
must have reasonable period of validity and should not become non operational
before time.
Upgradation in gas charged network should be carried out as per safe procedure
and safe practices, after obtaining work permit. For mass or large up gradation job,
separate competent contractor should be engaged for completing the Upgradation in
scheduled time with safety and quality.
Typical Up-gradation format
Network up-gradation
Material requirement:
General Information :
In a City Gas Distribution system, various operation and maintenance activities have
being carried out by Company and Contractors on regular bases, to ensure safe and
uninterrupted gas supply to customers and safety, security and integrity of network.
However the safety audit and inspections by third eye like safety engineer /
professional should be planned and executed regularly to know the availability
adequacy, compliance and effectiveness of control programs for ensuring safe
conditions and safe practices. The audit, inspection should be planned with special
focus on HSE, Integrity of system and statutory, legal Compliance. These kinds of
program facilitate to identify the unsafe conditions and unsafe practices, the causes
for accidental losses, and thus ensure incident free operations and healthiness of
distribution system.
There are two type of Safety Audit & Inspection, External and Internal. External audit
are carried out mainly for statutory requirements. Internal audit are carried out on
need base or as planned. Need base audit & inspection is normally carried out after
incident, mishaps or malpractices during day to day activities.
Audit & Inspection has long been an accepted management practices to ensure that
critical business operation are performed in an efficient and profitable way.
• To check statutory provisions of the factories act and similar other safety
status
Safety Audit is a critical examination of all or part, of a total operating system with
relevance to safety. Safety audit is a more systematic and detailed safety
inspections. It is used to assess the overall standard of safety performance or to
evaluate the safety implications of the inspections and test. A Safety Audit concerns
each area with the object of minimizing the losses. The objective of safety audit is to
assess & ensure safety and integrity of overall CGD System and O&M.
2. Procedure for Safety Inspection and Audit of City Gas Distribution System
Safety Inspection
Joint
Safety Emergency CPRS / Dom / Comm Valve
Month Audit Vehicle DRS Connections Chambers
Nos.
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
ANNEXURE - 02
SR No Location
V / C No Location
Observation of
Sr. DESCRIPTION SIZE Nos.
Nos. & Condition
1 Base Wireless in Vehicles 1
Intrinsically Safe Portable
2 Wireless 1
DCP TYPE FIRE
3 EXTINGUISHER 5.0 kg 2
L.C
Calibrated GAS DETECTORS 1%
4 LEL 2
1/2
Public Announcement System 1
5 MILE
6 Gum Boot PAIR 2
7 Fire Retardant Suit 2
8 Reflactory Jacket 2
9 Industrial Safety Helmet 2
10 First Aid Box with listed items 1
Overall Network Drawing With
1
11 All VALVE CAHMBER Details
12 Flameproof Torch 1
13 Normal Torch 1
Valves of all size valves
(Prepare list as per type & size
14 of valves) 1 set
Pipe Pieces For Leverage to
15 Operate Valve 2
Vent Pipe 3 meter long (Review 1/2" x
16 based on size of vent valves 3m 1
and outlets)
Rating Description
1. Dangerous- against compliance with standards. Urgent attention required.
2. Unsafe - does not comply with standards. Remedial action required.
3. Minimum compliance with standards. Need's modification.
4. Exceeds minimum compliance with standards with further improvement possible.
5. Best practice - no further improvement possible.
Sr.
Description
No.
E Security 1 2 3 4 5
Office security
Office Lighting.
After duty hours security.
Security of stores / sheds
Security of tools / equipment.
_______________________ ____________________
O&M Contractor In-charge GSPC GAS O&M In Charge
3.15 Preparation / Preservation / Updating Drawings / Records
Drawings and records preparation and preservation have their own importance for
site reference during normal and emergency repair maintenance and safe guarding
efforts. Many a time’s drawings and records are demanded for statutory and legal
compliance. Following procedure is suggested for drawings and records
New Drawings
On the basis of measurement / specification, drawings are prepared and their
numbers are given as per Drawing Codification Scheme.
Approved drawing list for the department is prepared and sent to concerned persons.
“Controlled Copy” Stamp is put on the drawing as well as on the approved drawing
list and the list is returned back to concerned persons.
The approved & controlled drawing is given to the concerned user department
“Controlled Copy” Stamp is put on the drawing and also on the approved drawing list
and the same is returned back to the concerned person.
If the entire drawing is changed then obsolete copies are destroyed or obsolete copy
stamp is marked on drawing.
Approved Drawing List for the location is updated. (Ref. Doc. GEN449)
If any person related to the organisation needs drawing for their reference then copy
of such drawings are marked with “Uncontrolled Copy” stamp and the same is issued
to concerned person and uncontrolled drawing register is updated.
CHAPTER – 3 B
CRITICAL TASKS
In City Gas Distribution System, there are certain activities, which have the potential
to produce major loss to people, property, process and / or environment, if not
performed properly. Hence to control and mitigate the risk associated with such task,
as shown below, the whole task is carried out by established procedures and safe
practices, by the competent person having gone through proper training and
education,
For our City Gas Distribution System, following are the critical activities identified as
critical task.