Module 1

The document is an Operations and Maintenance Manual for City Gas Distribution (CGD) by GSPC Gas, detailing the company's role in providing piped natural gas to various customer segments in Gujarat. It outlines the CGD system's structure, including major assets like City Gate Stations and distribution networks, and emphasizes safety measures, natural gas properties, and emergency protocols. Additionally, it provides information on the maintenance and operational activities necessary to ensure a safe and uninterrupted gas supply.

Uploaded by

9t2kgrmwhw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views27 pages

Module 1

The document is an Operations and Maintenance Manual for City Gas Distribution (CGD) by GSPC Gas, detailing the company's role in providing piped natural gas to various customer segments in Gujarat. It outlines the CGD system's structure, including major assets like City Gate Stations and distribution networks, and emphasizes safety measures, natural gas properties, and emergency protocols. Additionally, it provides information on the maintenance and operational activities necessary to ensure a safe and uninterrupted gas supply.

Uploaded by

9t2kgrmwhw
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 27

CITY GAS DISTRIBUTION

O&M MANUAL
CHAPTER – 1
INTRODUCTION
1.1 GSPC Gas – Brief
1.2 City Gas Distribution System (CGDS)
1.3 Basic System Schematic / P&ID / Flow Diagram
1.4 Natural Gas Composition, Properties
1.5 CGDS’ Asset and Their Functions
1.6 CGDS’ Asset, Associated Activities and Their
Frequencies

Module 1 of 9

Block - 15, 2nd Floor, Udyog Bhavan, Sector - 11, Gandhinagar – 382 011.
1.1 GSPC Gas – Brief

There can be no doubt that Natural Gas is the fuel of 21st Century. As a
progressive company, Gujarat State Petroleum Corporation (GSPC) has always
tried to identify new trends and prepare itself for the future. We, at GSPC GAS
Group is laying the groundwork and preparing ourselves for the future.

The GSPC GAS Group’s foray into Gas Distribution in a big way bears testimony
to our core philosophy of being ‘A Complete Energy Company’.

Role of GSPC GAS:

The role of GSPC Gas is envisioned to be complimentary to Gujarat State


Petronet Ltd (GSPL). At every location where the GSPL network ends, the GSPC
Gas retail network starts. This resulted in a strong synergy in network
management as well as it ensured that Gas is adequately available to all retail
segments in Gujarat.

Segments:
The GSPC Gas is catering to the Natural Gas requirements of all the retail
segments, which comprise of industrial, commercial, transportation and
residential customers.

GSPC Gas is I the business of Natural Gas distribution to Industrial, Commercial,


and Transportation and Residential segments of major cities / towns of Gujarat
state.
The company is supplying Piped Natural Gas (PNG) to nearly 20000 domestic
households, 100 commercial establishments and about 135 industrial customers.
1.2 City Gas Distribution System (CGDS)

City gas distribution is a facility, set-up for supplying piped natural gas, mainly as a
fuel to domestic, commercial and industrial customers, in city, town. The system
receives high pressure and unodorized gas from transporter, through transmission
line and supplies the same to the customers after filtration, pressure reduction,
odorization and check metering at City Gate Station (CGS). The pressure reduction
may be in four stages depending upon the network design selected. The first
pressure reduction is carried out at CGS, second at CPRS / DRS, third at service
regulator and forth and final at customer premises. The odorization for imparting
smell to gas is installed at City Gas Station (CGS). The system has major assets
like, city gate station (CGS), underground steel distribution network, CPRS, DRS,
MP PE network, service regulators, LP PE network, and customer connections. The
size, rating and type of the major and sub assets are selected based on the pressure
rating, capacity and other applicable criteria considered for whole city gas distribution
system for meeting the current and future customer potential, health and safety of
employees, customers and public at large, environment protection, and complying
the statutory, legal requirements, national and international technical and safety
standards / practices. The main objective of the distribution company is to ensure
safe and uninterrupted gas supply to customers for 24 hours, 365 days by manning
the control room, round the clock, by deploying the team of competent engineers
and technicians, for handling various customer complaints about gas leak / escape,
customer queries and carrying out planned operation and maintenance activities, as
per annual operation and maintenance plan for ensuring safe and uninterrupted gas
supply and integrity of network.
1.3 Basic System Schematic P&ID / Flow Diagram
Typical PNG Connection
CGS P&ID Diagram

Note: Typical CGS P&ID to be provided by GSPC Gas


CPRS, DRS & SR P&ID Diagram

Note: Typical Service Regulator Station (SR) AND Transition Box (TB) P&ID
to be provided by GSPC Gas
1.4 Natural Gas Composition & Properties

When handled properly Natural Gas is a safe fuel. It is a non-poisonous, non-toxic


(but Asphyxiate) colorless, tasteless combustible source of energy. Natural gas has
no odor of its own; it is odorless however for city gas distribution Ethyl Mercaptan is
added for distinct odor so that layman can identify the leak if any nearby and report
to company for necessary corrective action.

Natural gas is highly flammable. Its flammable limit is from 5% to 15% by volume in
air.

Natural Gas is composed essentially of Methane with minor quantities of ethane,


propane, carbon dioxide, nitrogen and traces of higher hydrocarbons and oxygen. It
has a specific gravity of 0.60 which means it is only 60% as heavy as air and it will
rise under normal atmospheric conditions.

The typical Natural Gas composition & properties are as follow,

Normal Gas Composition


Methane C 1 H4 82% to 95 % Mole
Ethane C 2 H6 1% to 5 % Mole
Propane C 3 H8 1% to 5 % Mole
Butane C4H10 0.1% to 2 % Mole
Pentane C5H12 0 % to 1 % Mole
Hexane C6H14 0 % to 1 % Mole
Carbon Dioxide CO2 0 % to 1 % Mole
Nitrogen N2 0 % to 1 % Mole

Specific Gravity (Air – 1.0) 0.56% to 0.67%


Boiling Point - 161 deg C
Melting Point -182.0 deg C
Flash Point - 161 deg C
Auto Ignition Temperature 560 deg C
Flammable Limit 5% to 15% by volume in air
Natural Gas within the distribution system will be given a distinctive odour which will
be designed to be detectible by the nose at concentrations of less than 0.1% of gas
in the atmosphere. Natural Gas will burn within the range of 5% and 15% of gas in
air, and it is readily ignited by spark or other forms of ignition within this range.

Natural Gas can be hazardous in the following ways,

- From asphyxiation – through overexposure to natural gas, usually in a confined


space, caused by inadequate ventilation or mechanical or accidental failure of
equipment.

- From explosion – through an accumulation of escaping gas, also usually in a


confined space, being ignited when mixed with air.

- From fire – through the uncontrolled burning of gas, in case of damage / leak of
pipeline and accumulation of escaping gas in confined space like valve
chambers, closed house

- From overpressure – through submitting gas facilities such as regulators, valves,


gauges, etc, to pressures in excess of their maximum working pressure.
MATERIALSAFETY DATA SHEET – NATURAL GAS
1. CHEMICAL IDENTITY
---------------------------------------------------------------------------------------------------------------------------------
Chemical Name: Natural Gas Chemical Classification:
---------------------------------------------------------------------------------------------------------------------------------
Synonyms: Natural Gas Trade Name: Natural Gas
---------------------------------------------------------------------------------------------------------------------------------
Formula C.A.S. No. : U.N. No. :
Mixture of Hydrocarbons: Methane (CH4)
Ethane (C2H6), CO2 & N2
---------------------------------------------------------------------------------------------------------------------------------
Regulated Shipping Name: Natural Gas Hazchem No:
Identification: Codes / Label :
---------------------------------------------------------------------------------------------------------------------------------
Hazardous Waste I.D. No. :
---------------------------------------------------------------------------------------------------------------------------------
Hazardous Ingredients C.A.S. No. Hazardous Ingredients C.A.S. No.
---------------------------------------------------------------------------------------------------------------------------------
1. Natural Gas 8006-14-2 3.
---------------------------------------------------------------------------------------------------------------------------------
2. PHYSICAL AND CHEMICAL DATA:
---------------------------------------------------------------------------------------------------------------------------------
Boiling Range / Point: -1610C Physical State: Gas Appearance: Coloureless
---------------------------------------------------------------------------------------------------------------------------------
Melting / Freezing Point : -182 0C Vapour Pressure :: Odour: Odourless(without
odourant)Unpleasant(with odourant)
------------------------------------------------------------------------------------------------------------------------------
Vapour Density Solubility Other:
( Air = 1 ) : 0.6 to 0.8 in water : Not Soluble
--------------------------------------------------------------------------------------------------------------------------------
Specific Gravity pH : Not Determined
Water = 1 : 0.62 to 0.70
---------------------------------------------------------------------------------------------------------------------------------
3. FIRE AND EXPLOSION HAZARD DATA
---------------------------------------------------------------------------------------------------------------------------------
Flammability : Yes / No LEL: 5% Flash Point : N.A. Autoignition : 540 0C
(flammable gas) Temperature
TDG Flammability : UEL : 15% Flash Point :-N.A.
(flammable gas)
---------------------------------------------------------------------------------------------------------------------------------
Explosion Sensitivity to Impact : Explosion Sensitivity Hazardous Combustion
Sensitive to mechanical impact to State of Electricity : Products:CO(If incomplete
Static charged combustion)
---------------------------------------------------------------------------------------------------------------------------------
Hazardous Polymerisation: Will Not Occur
---------------------------------------------------------------------------------------------------------------------------------
Combustible Liquid: Explosive Corrosive
Material : Hydrocarbon Material: N.A.
---------------------------------------------------------------------------------------------------------------------------------
Flammable Material: ------ Oxidiser : ------ Others: ------
---------------------------------------------------------------------------------------------------------------------------------
Pyrophoric Material: ------ Organic Peroxide: ------
--------------------------------------------------------------------------------------------------------------------------------
4. REACTIVITY DATA
---------------------------------------------------------------------------------------------------------------------------------
Chemical Stability: stable
---------------------------------------------------------------------------------------------------------------------------------
Incompatibility With other Material: N.A..
---------------------------------------------------------------------------------------------------------------------------------
Reactivity: heat, oxidisers
---------------------------------------------------------------------------------------------------------------------------------
Hazardous Reaction Products: Incomplete combustion yields carbon monoxide
---------------------------------------------------------------------------------------------------------------------------------
5. Health Hazard Data
---------------------------------------------------------------------------------------------------------------------------------
Routs of Entry: Inhalation
---------------------------------------------------------------------------------------------------------------------------------
Effects of Exposure / Symptoms: (Chronic Effects not known )
INHALATION :May cause asphyxiation by displacing or partially displacing the air required to
support life.
---------------------------------------------------------------------------------------------------------------------------------
Emergency Treatment:
INHALATION: Remove to fresh air, use respirator guards during normal exposure and breathing
apparatus in case of major exposure. If breathing is difficult, have trained person administer
oxygen. If respiration stopped, administer CPR and seek medical attention immediately.
---------------------------------------------------------------------------------------------------------------------------------
TLV (ACGIH): - ppm mg/m3 STEL: - ppm: mg/m3
---------------------------------------------------------------------------------------------------------------------------------
Permissible
Exposure Limit: Odour Threshold : - ppm mg/m3
Acute Oral LD50 ( rat ) : - mg/m3 ( Not Known )
Acute Inhalation LC50 (rat) : - ppm (4hrs.)
IDLH : - ppm
---------------------------------------------------------------------------------------------------------------------------------
NFPA Hazard Health Flammability : Stability Special :
Signals : Not Known Not Known Not Known
---------------------------------------------------------------------------------------------------------------------------------
6. PREVENTIVE MEASURES
---------------------------------------------------------------------------------------------------------------------------------
Personnel Protective Equipment: Safety Goggles, Face Shield, Self Contained Breathing Apparatus.
---------------------------------------------------------------------------------------------------------------------------------
Handling and Storage Precautions :
HANDLING :
• Keep away from sources of ignition.
• Avoid breathing gas, use with adequate ventilation. Wear approved respiratory protection if there is potential
for exposure above the exposure limits.
• Avoid static built up.
• Monitoring concentration of N.G. in atmosphere with gas measuring equipments while draining/venting.
• Avoid wearing contact lenses during handling of Natural Gas.
STORAGE :
• Keep away from source of ignition.
• Use of appropriate warning / caution boards.
• Store cylinders in well ventilated, low fire risk area.
---------------------------------------------------------------------------------------------------------------------------------
7. EMERGENCY AND FIRST AID MEASURE :
---------------------------------------------------------------------------------------------------------------------------------
Fire Fire Extinguishing Media: Dry chemical, carbon dioxide, foam, water fog or spray. Water
ineffective, but should be used to keep cool surroundings.
---------------------------------------------------------------------------------------------------------------------------------
Fire Special Procedures: Evacuate all unnecessary personnel. Shut down motors, pumps, electrical service
and eliminate all sources of ignition. Use spray to keep fire exposed containers cool to avoid pressure build-up,
wear self - contained breathing apparatus and full protective clothing. Best procedure is to shut off gas supply.
Unusual Hazards: Mixture of natural gas and air in certain proportions can result in an explosive
mixture.
---------------------------------------------------------------------------------------------------------------------------------
Exposure First Aid Measures : ( Please refer Point No. 5 - Emergency Treatment)
Antidotes/Dosages : Not Known.
---------------------------------------------------------------------------------------------------------------------------------
Spills/Leakage Steps to be taken : Evacuate unnecessary personnel upwind of the leakage area, remove or
eliminate ignition sources, minor leaks can be detected with soap solution applied at suspected leak points,
never use flame to detect presence of Methane. Suitable Personnel Protective Equipments to be used.
Waste Disposal Method : N.A.
---------------------------------------------------------------------------------------------------------------------------------
8. Additional Information / References:
ACGIH = American Conference of Governmental Industrial Hygienists.
OSHA = Occupational Safety And Health Association
IDLH = Immediate Danger to Life & Health.
CAS Chemical Abstract Services.
---------------------------------------------------------------------------------------------------------------------------------
9. Manufacturer / Suppliers Data
---------------------------------------------------------------------------------------------------------------------------------
Name of Firm : Contact Person
Mailing Address: In Emergency:

Contact Person
In Emergency :

-----------------------------------------------------------------------------------------------------------------
Telephone / Telex Nos.:
Local Bodies involved : ----
----------------------------------------------------------------------------------------------------------------------------------
Standard Packing : Supply though M.S. Pipeline

-------------------------------------------------------------------------------------
---
Tremcard Details / Ref. : -----
-------------------------------------------------------------------------------------------
Others : ----
---------------------------------------------------------------------------------------------------------------------------------
10. Disclaimer
---------------------------------------------------------------------------------------------------------------------------------

Information contained in this material data sheet is believed to be reliable but no


representation, guarantee or warranties of any kind are made as to its accuracy,
suitability for a particular application or results to be obtained from them. It is upto
the manufacturer / seller to ensure that the information contained in the material
safety data sheet is relevant to the product manufactured / handled or sold by him as
the case may be the Government makes no warranties expressed or implied in
respect of the adequacy of this document for any particular purpose.
1.5 CGDS’ Asset & Associated Activities and Their
Frequencies

City Gate Distribution System - Major Asset


Function & Technical Detail

Major Assets Function / Purpose

Transmission line Carrying high pressure gas at above 20 bar. It is under scope of GSPL.

It receives high pressure gas through transmission line and carries out
City Gate Station along
filtration, pressure reduction, metering and odourisation before dispatching
with odorization system
to steel distribution network.
Steel Distribution Carrying gas at 15 – 19 bar from CGS and taking up to CPRS, DRS and
Network CNG station
It receives medium pressure gas through steel distribution line and carries
CPRS, DRS out filtration, pressure reduction at 4 -5 bar and dispatches to MP PE
distribution network.

Carrying gas at 4–5 bar from CPRS, DRS and taking up to Service Regulator
MP PE Network
(SR)

Receives medium pressure gas through MP PE network and supply the low
Service Regulators
pressure gas to LP PE network, after filtration and pressure reduction.
Carrying low pressure gas at 900 to 1200 mmwc and supply to Customer
LP PE Network
connections
Domestic Customer Consist of regulator, meter, GI / Copper pipeline and neoprene tube. Gas
Connection flow at 250 mmWC and consumed at Hot plate
Commercial Customer Consist of regulator, meter, GI / Copper pipeline and neoprene tube. Gas
Connection flow at 250 mmWC and consumed at Hot plate

Industrial Customer Consist of filter, regulator, meter, PE / CS pipeline. Gas flow at 1250 mmWC
Connection and consumed at gas equipment like boiler, furnace etc

Control Room / Office/ For manning the control room for carrying out round the clock for 24 hours
Store, Premises and 365 days operational activities of CGD

Others / Utilities
For detecting / measuring gas presence during leaks / escape / maintenance
Portable Gas Detectors
jobs.
Maintenance van For attending regular and emergency activities

Tools / Tackles for PE For repair maintenance of leaking / damaged PE pipes / fittings on PE
repair /Maintenance network
Tools / Tackles for
CGS / SR
For repair/Maintenance and on line functional testing of valves of CGS and
repair/Maintenance and
Service Regulators.
on line functional
testing of valves
Tools / Tackles for
repair / Maintenance of For repair maintenance of customer connection
customer connections
Tools / Tackles for
Odorant Handling
For transfer of odorant from barrel to storage tanks and neutralizing the
(Storage /
residual odorant and vapour
transportation / Transfer
/ Waste Disposal
Personal Protective
For personal protection during normal and critical jobs.
Equipments

Fire Extinguishers For extinguishing fire--accidental fire and during routine job.

Signage / Caution /
For display of information and caution
Information Boards
For quick and effective transmission of information, even when away from
Mobile Phones
control room

Public announcement For making public announcement to customers during gas supply stoppage
system and resumption and festival safety.

For quick and effective transmission of information, even away from control
Wireless Sets
room
Computer System /
For billing / record / reports etc.
Printers

Log books / Logging daily information’s and parameters / customer complaints, handling
Stationeries and status as per shift, including attendees in shift
Name of Major activities
Major Asset Daily Fortnightly Monthly Quarterly Half yearly Yearly Emergancy
Preventive maintenance of
CGS mainly includes filter
Gas pressure odorant transfer, element cleaning /
Attendig gas leak,
/ flow / leak check, odorant smell / replacement, online testing
City Gas House Over pressure, under
odorant level condensate leak test, and resetting of active
Station (CGS) keeping pressure,stoppage of
/ smell draining calibration of monitor SSV & SRV, leak
supply,
monitoring pressure gauges check, valve operation,
paint touchup and house
keeping
Leak arresting, Gas
Preventive maintenance of
Preventive Escape, Gas fire..etc
TR, AGB & TLP-
Steel Lock test or maintenance of emergency handling.
Monitoring of Patrolling & Frequancy as per Mfr
Distribution leak detection valve chambers Emergancy patrolling,
TR Unit Surveillance guideline, Earthing pit
Network survey (Pre-monsoon, Third party
maintenance and Earthing
Post-monsoon) coordination, Repair
resistance measurement
of damaged coating

Preventive maintenance
including filter element
Leak check, cleaning / replacement,
Leak Arresting, Over
Pressure Filter draining, online testing and resetting
CPRS, DRS pr., under
Monitoring Cleaning & of active monitor SSV &
pr.stoppage of supply
Housekeeping SRV, leak check, valve
operation, paint touchup
and house keeping

Medium Leak Valve chamber


Leak and pipe
Pressure (MP) Patrolling Survey & preventive
damage repair
PE Network LPT maintenance
Preventive maintenance of
SR mainly includes OPSO
Leak check, / UPSO, online testing and
Pressure Leak Arresting, Over
Service Filter draining, resetting of active monitor
monitoring pr., under
Regulator Cleaning & SSV & SRV, leak check,
Need base pr.stoppage of supply
Housekeeping valve operation, paint
touchup and house
keeping
Pressure,
Industrial Flow and
Connections Volume
Monitoring
Low Pressure Leak Valve chamber
Leak and pipe
(LP) PE Patrolling Survey & preventive
damage repair
Network LPT maintenance
Annual maintenance Attending complaint
Domestic / service which include leak of gas smell / leak /
Commercial test, rubber tube fire / explosion / over
Connections replacment, clamping, pr., under pr., no gas
paint touch up complaint
Supporting
Asset
Tools tackles Inspection
Maintenance Daily as per Emergency repair
Servicing Servicing
van check list maintenance
Portable Gas
Calibration Repairing
Detectors
Fire Inspection & Refill
Inspection Inspection & Refill
Extinguishers after use
Wireless Sets Inspection / Servicing Repair maintenance
Name of Major Asset : City Gas Station
Major activities
Name of Sub Asset Fortni Mon
Daily Quarterly Half yearly Yearly Emergency
ghtly thly
Isolation, Vent, Drain Leak check of all Emergency isolation,
Operation
Valves joints venting, draining
Visual
Draining of
Inspection of Attending leak, Draining
Knock Out Drum ( KOD ) condensate, Leak Internal Cleaning,
Shell, Thickness of condensate
check of all joints
measurement
Visual Attending leak, Draining
Draining of
Inspection of Cleaning / replacement of condensate /
Filter Separators ( F / S) condensate, Leak
Shell, Thickness of Filter Element cleaning / replacement
check of all joints
measurement of element

Gas Pressure Streams- Monitoring and Online testing resetting Attending leak, over
Leak check of all
Running and Hot Stand By recording of inlet, of Active, Monitor, SSV pressure, under
joints
SSV, Active, Monitor, SRV outlet, pressure SRV, pressure, gas stoppage

Monitoring and Leak check, external


Leak check of all Attending smell, leak,
Odourant Dosing System recording of Inspection shell inspection,
joints transfer of odorant
odorant level thickness measurement

Pressure Leak check of all Attending leak, Repair /


Pressure gauges Calibration
Monitoring joints Replacement
Name of Asset : Steel Distribution Network

Name of Sub Major activities


Asset Daily
Fortni
Monthly Quarterly Half yearly Yearly Emergency
ghtly

Coated Steel Pipe Patrolling & Network drawing Lock test or leak Leak arresting, Gas
Line Surveillance updation as & when detection survey Escape, Gas
fire..etc emergency
Crossings (Raod, Patrolling & handling.
Canal, Railway) Surveillance Emergancy
Preventive patrolling, Third
Valve Chambers party coordination,
maintenance
Repair of damaged
Isolation & Vent Greasing and coating
Valves Operation check
Cathodic Protection System
Preventive maintenance
Monitorin
- Frequency as per Mfr
g of TR
guideline, Earthing pit Breakdown
TR Unit Unit
maintenance and maintenance
alternate
Earthing resistance
day
measurement
PSP Monitoring bi- Preventive maintenance Breakdown
PSP & TLP
monthly of TLPs maintenance

Preventive
maintenance -
Anode Ground Bed Breakdown
Frequancy as per Mfr
(AGB) maintenance
guideline, AGB
monitoring

Breakdown
Insulating Joints IJ Monitoring
maintenance
Name of Asset : CPRS & DRS
Major activities
Name of Sub Asset
Daily Fortnightly Monthly Quarterly Half yearly Yearly Emergency

Isolation, Vent & Drain Leak check of all Emergancy isolation,


Operation
Valves joints venting, draining
Visual Attending
Draining of Inspection of Cleaning / leak,Draining of
Filter Separators (F / S) condensate, Leak Shell, replacement of condensate / cleaning
check of all joints Thickness Filter Element / replacement of
measurement element
Attending leak,
Leak check of all Online testing
Slam Shut Off Valve Resetting / Repair /
joints resetting
Replacement
Attending leak,
Leak check of all Online testing
Active PRV Resetting / Repair /
joints resetting
Replacement
Attending leak,
Leak check of all Online testing
Monitor PRV Resetting / Repair /
joints resetting
Replacement
Attending leak,
Safety Relief Valve Leak check of all Online testing
Resetting / Repair /
(SRV) joints resetting
Replacement

Monitoring
and
Leak check of all Attending leak, Repair
Pressure gauges recording of Calibration
joints / Replacement
inlet, outlet
pressure
Name of Asset : PE Distribution Network
Major activities
Name of Sub Asset
Daily Fortnightly Monthly Quarterly Half yearly Yearly Emergency

Attending gas leak by


Transition Fitting ( TF ) Leak Survey
repair replacement of TF

Coordination Attending gas leak and


Pipe Line with Other Patrolling Gas Leak Survey pipe damage( By other
Utility Dept utilities and rodent)
Attending gas leak / Attending gas leak and
cleaning / greasing / valve operation,
Valve with valve chambers Patrolling Dewatering operational check / repair dewatering of chamber
maintenance and white .Repair replacement of top
wash of valve chamber covers
Check
Route Markers availability / Repair / Replacement
condition

Drawing
Drawings
updation
Name of Asset : Service Regulator ( SR )
Major activities
Name of Sub Asset
Daily Fortnightly Monthly Quarterly Half yearly Yearly Emergency

Isolation, Vent & Drain Leak check of all Emergency isolation,


Operation
Valves joints venting, draining
Attending leak,
Leak check of all Online testing
OPSO / UPSO Resetting / Repair /
joints resetting
Replacement

Monitoring
and
Leak check of all Attending leak, Repair
Pressure gauges recording of Calibration
joints / Replacement
inlet, outlet
pressure
Name of Asset : LP PE Distribution Network
Major activities
Name of Sub Asset
Daily Fortnightly Monthly Quarterly Half yearly Yearly Emergency

Attending gas leak. Repair /


Transition Fitting ( TF ) Leak Survey
replacement RCC Guard

Coordination Attending gas leak and pipe


Pipe Line with Other Patrolling Gas Leak Survey damage( By other utilities
Utility Dept and rodent)

Attending gas leak /


cleaning / greasing / Attending gas leak and
operational check / valve operation, dewatering
Valve with valve chambers Patrolling Dewatering
repair maintenance and of chamber .Repair
white wash of valve replacement of top covers
chamber
Check
Route Markers availability / Repair / Replacement
condition

Drawing
Drawings
updation
Name of Asset : Domestic / Commercial Customer Connections
Major activities
Name of Sub Asset
Daily Monthly Bimonthly Quarterly Half yearly Yearly Emergency

Attending gas leak.


Transition Fitting (TF) Repair / replacement
RCC Guard

Testing TEE Gas leak repair

Gas leak repair,


Annual maintenance
Isolation (Audco) Valve operation check,
service is suggested
replacement
for whole installation
GI Piping from TF to rubber Gas leak repair
tube. This may include
LPT and LDT of the Attending gas leak, over
installation, checking pressure, under
Pressure Regulator and providing clamps pressure, gas stoppage
and colour touch up by resetting /
and checking of replacement
Meter reading Meter reading condition of rubber
Attending gas leak,
and billing for and billing for tube (replacement
Meter attending other meter
commercial domestic after two years)
complains
connection connection
Attending gas leak,
Gas Taps
Repair / replacement
Attending gas leak,
Rubber tubes
Replacement