Assignment - 03
Assignment - 03
Example 01
• Calculate the quantities of Excavation, Plain Concrete Foundation,
and Reinforced Concrete Foundation.
1
Construction Project Management
Example
• Calculate the quantities of Excavation, Plain Concrete Foundation,
and Reinforced Concrete Foundation.
Dimension
No. Item unit No. Add Sub Total
L W H
Excavation m3
1 F1 m3
S1 m3
Plain Concrete
PC Footing
m3
2 ( t ˃ 20 cm )
PC Ground Beam
m2
( t ˂ 20 cm )
Reinforced Concrete m3
3 Footing m3 2
Ground Beam m3
Construction Project Management
Example (02)
• Calculate the Quantities of the following Items:
1. Excavation.
2. Plain Concrete.
3. Reinforced Concrete of Footings, ground beams
and ground columns.
4. Backfilling.
5. Insulation of footings and ground beams.
• Data:
All Columns are 0.3 * 0.8 m
All ground beams are 0.3 * 0.6 m
All Footings are 2.0 * 1.5 * 0.6 m
The thickness of plain concrete is 15 cm and
PC overhangs 10 cm from each direction.
Walls thickness is 20 cm.
3
Construction Project Management
Example
4
No. Item unit No. L W H Add Sub Total
1 Excavation m3
2 Plain Concrete Footing m2
Reinforced Concrete m3
Footings m3
G.B Axis (A-A) & (B-B) m3
3
G.B Axis (1-1)&(2-2)&(3-3) m3
G.B Axis (2-3) m3
Columns m3
Backfilling m3
Excavation m3
Plain Concrete Footing m3
Reinforced Concrete Footing m3
4 Ground Beams m3
Column necks m3
m3
Under ground Walls m3 5
m3
No. Item unit No. L W H Add Sub Total
Insulation m2
Footing ( 4 sides ) m2
Footing ( Top ) m2
Subtract Column area m2
5 m2
Ground Beams m2
m2
Subtract Intersections m2
Columns neck m2