Lates PMP Questions by PMI
Lates PMP Questions by PMI
Options:
4.Cresponse.
Options:
4.Issue a new request for proposal (RFP) that includes a cost limitation.
Options:
1.Assess how they can motivate themselves to perform the extra work to
meet project goals.
2.Agree to the go-live date but insist that management allow exception-
based team rewards in return.
4.Seek approval for an increase to the project cost baseline that will
include budget for estimated overtime work.
Q4. Tragedy strikes on a project to restore a bus terminal and modernize
the service. An unexpected natural disaster has damaged the site and
surrounding city. The project team, watching from a safe location 250
kilometers away, is in emergency response mode. What should the project
team do next?
Options:
Options:
Options:
Options:
Q8. A project team has deprioritized capturing lessons learned for two
sprints now and just continues working. What should the project manager
do first?
Options:
Q9. A project stakeholder thinks they are being helpful by sharing a lot of
negative customer feedback emails. This feedback is often difficult to
understand and written in raw, verbatim form or without any context.
After 2 weeks of receiving these emails almost every day, one project
team member is frustrated and becomes angry and vocal at work.Which
three actions should the project team take? (Choose 3)
Options:
1.The project team should tell the stakeholder to stop sharing this kind of
feedback.
2.At the next retrospective, the project team should discuss and circulate
guidelines for receiving and processing customer feedback.
Options:
2.Present the details of the project assessment report and key action
items to the project team and stakeholders to ensure their support.
3.Do nothing, because the team members were part of the project
assessment report and should be aware of the upcoming changes.
4.Wait for the project sponsor to decide how to communicate the actions
and project key changes.
Options:
Options:
4.Track stakeholder concerns but address them only when they become
an obstacle to the project's progress.
Options:
Options:
1.Escalate this to the project sponsor and let them decide on the
approach.
2.Discuss the options with the customer and let them decide.
Options:
Q16.An oil and gas company isredesigning their oil storage tanks to meet
updated international industry standards. A vendor is contracted to
perform the work. During the latest inspection, a critical flaw is detected
in the tank venting systems.The vendor states this is a design flaw and
they notified the team lead 3 weeks ago to inspect the tanks, but they did
not perform the inspection. The vendor kept working, using the designs
they were given, to meet the next milestone. The team lead says the
inspection was not on the schedule. What should the project manager do
first?
Options:
17.A project sponsor announces their retirement and informs the project
manager that they will be replaced by two company managers. The
project sponsor says: “These two managers work together closely, so the
transition should be seamless.” What should the project manager do next?
Options:
Options:
1.Consult with the former project sponsor about how to work better with
the new manager.
Options:
Q20. A new project manager begins work on a project started last year to
renovate a busy airport terminal. Even though the project uses a hybrid
development approach—making incremental updates to the terminal—it
has encountered many issues, especially creating conflicts with airport
operations. The new project manager asks the project team about how
they typically handle problems and risks, but no one has a clear answer.
What should the project manager do first?
Options:
Options:
3.Wait and see if the risk materializes before taking any action.
A.The unique server used by the team is out of service from 8:00 a.m. this
morning.
C.The project may be delayed due to possible loss of data due to sudden
shutdown of the server during its failure.
Options:
Options:
Options:
2.Approve all the requests because they will return to the project with
positive energy.
3.Assess how approving the leave requests could affect the project.
4.Compress the project schedule and approve shorter leave times for all.
Options:
Options:
.2.Engage the stakeholders and force them to release the resources per
the project sponsor’s mandate.
3.Try to convince the project sponsor to wait until the needed staff
members are free to begin the project.
4.Circulate the project charter and discuss resource requirements with the
stakeholders.
Options:
2.Work with the product owner to create a new user story to address the
quality and technical issues.
Options:
2.Estimate the additional cost for the remaining scope and request a
budget increase.
4.Review the project scope and make necessary adjustments to align with
the remaining budget.
Options:
1.Pareto chart
2.Control chart
4.Cause-and-effect diagram
Q31. A new project manager is asked to help a project sponsor create a
project charter for the first time. After looking through the project
documents provided by the project sponsor and the business
stakeholders, the project manager creates a draft and isnearly ready to
share it with the stakeholders and the project team. Which additional step
should the project manager take to ensure the project charter is ready?
Options:
Options:
Q33. Ten years ago, a family inherited a 140-acre estate but since then
have only argued about what to do with it. Now, they must act within 24
months to avoid financial penalties for dereliction. The estate lawyer
engages a development company with a project manager to find a
solution. The project manager hosts a discovery and fact-finding meeting
and hears the following viewpoints:
•Stakeholders P and Q want to demolish the building, then build and sell
houses. •Stakeholder B wants to split the property among the family.
•The lawyer reemphasizes the time line. Which two steps should the
project manager take first? (Choose 2)
Options:
1.Discuss the scope options with the development team and ask them to
develop a proof of concept (POC) for each.
2.Examine the value gained by each of the options.
3.Give the group a deadline to decide what they want among themselves
and then advise the project team.
4.Continue discussing the various options with the stakeholders and listen
actively to their concerns.5.Estimate the schedule and cost of each option.
Options:
1.End the project because of the bad publicity and suggest a new project
to address the problem.
3.Close the bridge, erect a scaffolding, and cut the locks off out of sight of
the protestors.
4.Delay this project until the publicity quiets down and restart it in the
future.
Options:
2.Project sponsor
Options:
1.Engage the benefits owner about further training on the new software
after implementation.
2.Work with internal stakeholders to offer incentives for using the new
software.
3.Work with the process owner on a plan to phase out the old manual
methods.
Options:
1.Archive the project artifacts and update the lessons learned register.
2.Revisit the correct project process roles and responsibilities at the next
retrospective.
3.Congratulate and thank the team member for their hard work.
Q38.An agile project team is joined by a newly hired team member who is
highly skilled but has only worked on predictive project teams. After
working with the team for 1 month, the project team has scheduled a
product demo with the client, an external customer. The client gives direct
and passionate feedback: “This mechanism is overcomplicated.
Customers won’t like it. We can’t support it. Start over!” The new team
member begins crying and immediately exits the room. How should the
project team react?
Options:
3.Tell the new team member they must respect and listen to all client
feedback.
4.Move the new team member to a less critical project until they become
more comfortable using agile approaches.
Options:
3.Watch the developer closely for a week and ensure nothing is removed
from the office.
Options:
1.Cancel the project and disband the team until the roadmap for project A
can be fixed.
Options:
1.The project manager should approve the change request and work with
the product owner to figure out how best to complete the work in the
shortest amount of time.
2.The product owner should approve the change request and work with
the project manager to establish new cost and schedule baselines.
3.The project manager and product owner should meet with key
stakeholders to establish the budget and schedule impacts, agree on
rework, and determine the priority of the change.
4.The project manager and product owner should escalate the change
request to the project sponsor for approval as it affects the budget and
schedule.
Options:
1.Introduce the framework for the project and use servant leadership to
explain why the framework will help to structure their work.
2.Update the project management plan explaining the cost and schedule
baselines to the project team.
3.Create the team charter and ground rules including project management
coaching as part of the team culture.
Options:
1.Allow the vendor to complete the construction and the owner to fix the
issue after the product is delivered.
2.Empower the team to create a makeshift venting system that meets the
standards.
4.Alert the vendor about the flawed design and insist they fix it as it was
in scope of their contract.
Q44.An oil and gas plant construction project had been progressing on
schedule and within budget. Six months into the project, the company
owner visits the site for a formal tour. After the tour, the owner asks the
project manager to replace the edifice of the office building with marble—
an expensive cosmetic change! Even though the project manager
explained to the owner that this work would escalate the cost of the
project and might delay completion, the owner insisted on using the
marble. What should the project manager do?
Options:
1.Refuse to do the work and ask for a transfer from the project.
3.Write a formal change request and send it to the change control board
(CCB) for approval.
4.Discuss the matter with the program manager and convince them to
deny the change.
Options:
1.Issue a request for quotation (RFQ) before the request for proposal
(RFP).
Options:
1.Retrospective
2.Daily standup
3.Product review
4.Scrum of scrums
Options:
3.Review the project charter created by the global project team and revise
it.
Options:
1.Investigate whether the complexity of the user story creates a risk for
implementation in the first release.
Options:
Q50. An agile team has been performing at an extremely high level and
pace, receiving praise from stakeholders and customers. A portfolio
manager has asked the team to start a community of practice (COP) for
the organization. The team members vote unanimously against this
because of the intense time commitment. Instead, they offer an open
invitation to anyone to attend their retrospectives. Which two statements
describe this team’s reaction to the portfolio manager? (Choose 2)
Options:
1.The team is safeguarding its ability to sustain its high-performance level
by turning down the community of practice (COP) opportunity.