The document outlines a comprehensive risk assessment for geotechnical work on the Second Southern Ring Road Section 3 project, detailing various tasks, identified hazards, and control measures to mitigate risks. It emphasizes health, safety, and environmental considerations, including the need for proper training, equipment inspections, and adherence to safety protocols. Each task is assigned a risk rating and specified control measures to ensure the safety of workers and the surrounding environment.

Uploaded by

syedhse8489
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views14 pages

Risk Assessment

The document outlines a comprehensive risk assessment for geotechnical work on the Second Southern Ring Road Section 3 project, detailing various tasks, identified hazards, and control measures to mitigate risks. It emphasizes health, safety, and environmental considerations, including the need for proper training, equipment inspections, and adherence to safety protocols. Each task is assigned a risk rating and specified control measures to ensure the safety of workers and the surrounding environment.

Uploaded by

syedhse8489
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

RISK ASSESSMENT

Contract No. 20240918032


Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

RISK ASSESSMENT:
HEALTH SAFETY AND ENVIRONMENT (HSE) RISK ASSESSMENT

Project: Risk Assessment


Second Southern Ring Road, Section 3 Risk Assessment for Geotechnical Work.
Ref:
Company Name: Al-Ayuni & CHEC JV Date: 18-12-2024
Activity Name: Geotechnical works Site Location All Site
Risk Rating
without Residual Risk
Sr. No Task Hazards Identified Harm Control Measures Controlled by whom
control.
measures
LXS L M H LXS L M H

 Unauthorized
work to be
performed  Obtain PTW before starting
within a defined work.
location and  Work shall not start until
boundary duly approved.
 Injury to  Safe work practice shall be
Obtaining work  Uncontrolled Site Supervisor /
01 operators/nearby 2x3 6 implemented to reduce the 1x2 2
permit personal entry. HSE officer
possibilities of accident.
 Lack of safety  PTW must display at work
awareness and location.
knowledge for  Conduct TBT before starting
the job work.
 Unidentified
hazards.
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

 Isolate the working area


with barricades where
necessary.
 Ensure all equipment follows
the speed limit (20km/hr).
 Inspect the working area
before allowing the survey
team on site.
 Not to allow lone working at
the site.
 Slip, Trip & Fall  Legs of the tripod are to be
from heights. securely bedded into the
 Slip, Trip, and ground, and mercury
fall from the accuracy is to be checked.
same level.  No activity during wind or
 Man and  Personal Injury. sandstorms.
equipment  Cut/laceration.  Adequate training must be
Site interface.  Back pain. conducted.
 An adequate walkie-talkie/ Survey Engineer/
Preparation  Traffic Risk.  Heat Illness.
02 2x3 6 Bravo or satellite device was Site supervisor 1x3 3
and Survey  Snake and other  Musculoskeletal provided during the activity. HSE Officer /
works. poisonous disorder.  Adequate personal
insects.  Personal Injury due to protective equipment must
 Survey working near roads. be worn.
equipment falls.  Check the area for any
 Manual handling inspect or snake before
of survey starting the work.
equipment.  Don’t play or try to harm the
snake. Leave the area if
snake is present and call
emergency contact number.
 Snake bite kit must be
available with the first Aider.
 Emergency Contact number
should be provided to the
survey team.
 A drinking water bottle
should be provided to each
worker.
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

 Pre-mobilization inspection
of equipment/plant should
be done prior to bring in
the site.
 All the equipment must
have TPI certificate.
 Use appropriate tools and
equipment.
 All tools and equipment
must be inspected and
color coded as per client
standard.
 Incompetent
 Barricade work area and
Operators.
allow only authorized
 Equipment
 Personal injury personnel in the area.
malfunctioning,
Mobilization  Property damage  All equipment Operators Site Supervisor /
 Fuel/oil
03 of  Equipment failure or 2x3 6 (where required) / Heavy HSE Inspector or 1x3 3
leaks/ground
Equipment’s damage. Equipment Operators shall Officer
contamination.
 Soil contamination be TUV Certified.
 Reversing trailer
 Daily inspection of
without spotter.
equipment by
 Slip, trip and fall
operator/driver using
checklist specific to their
equipment shall be strictly
implemented.
 Ensure all the chemicals are
stored in chemical storage
area having secondary
containment.
 Drip tray should be
provided with all portable
generators, Air compressor
etc.
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

 Ensure all the workers are


wearing the mandatory
PPE’s.

 Ensure equipment is in
working condition and have
3rd party inspection
certificate.
 Struck-by  Ensure operator is trained
 Caught in and have TPI certificate. TUV
between  Ensure established drilling
 Falling objects procedures, including proper
Drilling of  Noise exposure  Personal injury. alignment’ stabilization, and
monitoring of the drill. Site engineer /
04 probe holes  Vibration  Equipment / material 3x4 12 2x2 4
 Ensure Underground utilities HSE officer
exposure damage. has been scanned and
 Dust exposure marked
 Ground  Ensure fire extinguisher and
Instability first aid kit available on site
 Fire Hazard  Ensure pre job toolbox talk
conducted
 Ensure all the workers are
wearing the mandatory
PPE’s.
 Ensure proper access.
 Ensure area free from
 tripping hazards.
 Proper material
management.
 Trip and Fall  Personal Injury  Ensure the area to be Site
Barricading the excavated is protected by
05  Improper  Back pain or 2x3 6 Supervisor/HSE 1x2 2
Trial Pit temporary portable barriers.
Manual Handling musculoskeletal disorder  Ensure buddy system to officer
lift/position the barriers.
 Barriers must be installed at
2m distance from excavation
edge.
 Ensure barricades are fixed
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

properly to avoid blown


away by wind.
 Ensure all the workers are
wearing the mandatory
PPE’s
 Provide proper access and
egress.
 Provide proper tools for
manual excavation and soil
removal.
 Ensure tools are free from
damage and remove
defective tools.
 Use appropriate barriers /
signage to warn of open pits.
 Open pits not to be left
unattended.
 Collapse of pit • Avoid carrying large objects
walls. around pit, use of mobile
 Personnel injury. phone and other
 Fall into pit
 Nausea, disease, distractions.
Manual  Improper access
ingestion of • Unauthorized workers
06 Excavation  Improper or 3x3 9 2x2 4
contaminated solids or should maintain distance of
work defective hand >2m from pit edge.
fluids, possible breathing
tools. • Provide proper protection of
damage or suffocation
 Contaminated side walls for a pit of >1.20m
ground / soil. depth.
• Stock the soil/excavated soil
at least 0.61 m (2 feet) away
from the edge.
• Avoid walking / Standing on
the edge of pit.
• No unauthorized entry of
person or vehicle should be
allowed near the pit.
• Proper PPE’s for all involved
workers.
• Confined space precautions
should be taken if depth is
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

more than 4 feet.


• Close supervision and
monitoring.
• Monthly inspection and
color coding of hand tools.
 Brief or train the employees.
 Check the existing drawings
of underground utilities
before excavation.
 Mark the buried utilities
location.
Use CAT scanner for exact
location of buried services.
• Excavate inspection pit
 Electrocution/ex through manual excavation.
Underground plosion  Minor injury to fatality • Once buried utility is HSE Engineer
07 4x4 16 2x2 4
Utilities  Leaks, possibly  Material Damage exposed, dig carefully /Site Engineer
under pressure around that.
• Continuous supervision
should be present.
• While digging beneath the
underground utilities,
proper protection of
exposed utility is required.
• Provide proper protection to
pipe lines to avoid any
cracks or leakages.
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

 Compliance with work


permit system
 Ensure tools are free
from damage and remove
defective tools.
 Ensure the equipment’s is
working 1.5m away from
excavation.
 No unauthorized entry in
the
working area.
 Fall into the pit.  Provide proper access
Manual
08  Defective hand  Personnel injury. 3x3 9 aggress to the backfilling 1x2 2
Backfilling
tool. area
 Avoid walking standing on
the edge of the
excavation.
 Proper ppe’s for all
involved workers
 Supervision and
monitoring.
 Monthly inspection and
color coding of hand
tools.

 Lack of traffic
 Fumes.  Implementation of
control
 Pollution. approved traffic plan.
management.
 Drips and spills, dust.  All drivers and operators
 Lack of proper Traffic
must follow the site
On Site Traffic parking.  Vehicle collision Controller /
09 4x4 16 safety rules and speed 1x4 4
Movement  Lack of traffic  Injury to persons due to supervisor/
limit.
signs. collision. HSE Officer
 All drivers have Saudi
 Unauthorized  Vehicle Collision.
government license.
driving.
 Provision of separate
 Damaged
pedestrian walkways
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

vehicle. where high chances of


man-machine interface.
 Access roads clear from
any obstruction.
 Make grading and
compaction.
 Provide two-way road
and control the traffic.
 Display speed limit and
driving guidelines signs.
 SUV and inspected
vehicles to be used for
the job.
 Defensive driving for all
drivers and operators.
 Man machine interface
training to all workforce.
 Monitor weather condition.
 Use mechanical aid for
lifting of heavy objects
where possible.
 Limit the load limit of 23
KG per person.
 Check load weight before
lifting.
Manual  Heavy Weight.  Musculoskeletal disorders  Ensure proper handles HSE officer /
10 Handling  Sharp objects.  Hand injuries, cut or 2x3 6 with equipment. Site 1x2 2
bruises.  Individual, task and Supervisor
environment
consideration during
manual lift.
 Cut resistant gloves for
workers should be
provided along with
mandatory PPE’s.
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

 Supervision and
monitoring.
 Manual handling training
for all the workers.
 Site Induction and toolbox
talks should be given prior
to starting the job.
 Ensure competent
workers are assigned for
 Damaged Tools the task.
 Uneven  Medical pre assessment
surfaces before assigning the work.
 Cut / Injury.
 Poor Posture  Provision of adequate
 Back Pain.
 Repetitive welfare facility Site
Working with  Musculoskeletal Disorder.
11 motion. 3x3 9 Supervisor / 1x3 3
Hand Tools  Medical Emergency
 Dynamic site  Having emergency contact HSE Officer
conditions card with everyone.
(Desert,  Availability of proper PPEs
mountain etc.). for the tasks
 Use buddy system, no
lone working in the
mountains.
 Availability of proper
communication channels.
 Proper supervision.
 Stop the outside work in
sand storm or heavy rain.
 Dehydration  Training workers regarding
 Extreme Heat  Heat stress or heat illness. adverse weather effects
Working in
 Extreme Cold  Cold related illness. e.g. heat stress, cold stress, Site Engineer / HSE
12 adverse weather 3 x4 12 2 x2 4
 Sand Storm  Personal injury or puncture sand storm, and rain etc. officer
conditions
 Rain  Eye injury  Provide rest shelters at
 Slip, trip, and fall workplace with good
means of ventilation.
 Provide drinking water
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

stations at the workplace.


 Advise all employees to
drink plenty of cold water
with short intervals and
reduce the intake of
caffeine in summer season.
 All employees shall follow
the work-rest regimen.
 Workers must wear warn
clothes or coats in winter
seasons.
 In winter seasons, warm
water should be provided
to workers.
 Workers must wear the
mandatory PPE’s.
 Proper supervision and
monitoring needed during
adverse weather
conditions.
 Emergency response plan
should be communicated
with all workers.
Contract No. SSRR3-2024
Project Second Southern Ring Road Section3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

1
 Follow policies and
procedures to minimize
the occurrence of
emergencies.
 Communicate emergency
response plan to all the
employees.
 Implement and test the
Emergency response plan
through mock drills so
 Medical workers can know what to
Emergency do in case of real Construction
 Fire, Explosion  Personnel Injury / death.
emergency. Manager / HSE
Emergency in  Material / equipment
13  Hazardous 2x4 8  Improve the plan Manager / HSE 2x2 4
Workplace Damage or loss.
Material spillage. continuously as per site Engineer/ Site
 Health Issues.
 Workplace nature or related hazards. Engineer
violence  Alarms and other methods
of initiating a response
should be provided.
 Evacuation and assembly
procedures should be
developed and
communicated with
workers of each area.
 Emergency contact lists
should be provided at each
work area.
 Fire  Good housekeeping on the
 Burns
 Slips, Trips and site can eliminate many
 Equipment damage
situations where a fire can Site Engineer/
14 Housekeeping Fall.  Injury 2x2 4 1x2 2
start. HSEO
 Nail punctures.  Soil, air or water
 Waste should move at
 Environmental contamination.
intervals and always at the
Rev: 00
Page 11 of 13
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

Pollution  end of the working day.


 Spray water. Construction
 Respiratory issues.
 Dust 2x3 6 Use the right tool and PPEs Engineer / HSE 1x3 3
 Visibility issues
for the right job Officer
 Provide MSDS of the
chemicals in use at site.
 Train workers in the safe
handling of chemicals.
 Respiratory problems  Chemical spillage drills to be
 Skin sensitization conducted.
Construction
 Soil and water contamination  Use the right procedure for
 Oil Spillage 2x3 6 team/HSE officer 1x3 3
 Fines, SORs / NCRs chemical spillage control as
 Quality defects per manufacturer's
15 Environment  Slip, trip and fall instructions.
 Only trained and experienced
workers will do this job.
 Use of spill kits.
 Right PPEs for the job
 Hearing loss 2x3 6  Wear appropriate ear Construction 1x3 3
 Tinnitus protection. Engineer / HSE
 Psychological issues  All tools and equipment to be Officer
 Noise  Mental health issues
in good condition.
 Use the tools and equipment
according to manufacturer's
2 instructions.
3
4
5
6
7
8
9
10
11

Rev: 00
Page 12 of 13
Contract No. 20240918032
Project Second Southern Ring Road Section 3
Doc. Title RISK ASSESSMENT FOR GEOTECHNICAL WORK
Doc. No. Rev: 00 Date: 18-12-2024 Al-Ayuni & CHEC JV
Client PMO PMCM

Likelihood (L) Severity (S) Risk Level Risk Matrix

ExtremeRisk 15 -25
Rare – 1 Insignificant – 1 5 5 10 15 20 25

4 4 8 12 16 20

Likelihood (L)
High Risk8 - 12
Possible – 2 Minor – 2
3 3 6 9 12 15

Likely – 3 Moderate – 3 2 2 4 6 8 10
Moderate Risk 4 - 6
1 1 2 3 4 5
Often – 4 Major – 4
0 1 2 3 4 5
Frequent/Almost certain - 5 Catastrophic – 5 Low Risk 1 - 3
Consequence (C)
12
13

Prepared by: RIZWAN ULLAH Reviewed by: SONU RAMACHANDRAN Approved by: RAJESH KANNAN
Designation: HSE SUPERVISOR Designation: HSE MANAGER Designation: PROJECT MANAGER
Signature: Signature: Signature:

Date: 18-12-2024 Date: 18-12-2024 Date: 18-12-2024


14

Rev: 00
Page 13 of 13