Lesson 03 Problems 1
Lesson 03 Problems 1
A direct time study was taken on manual work element A using the
snapback method. The work element was timed for several work cycles
to get observed time as she evaluated worker’s pace relative to
normal/standard performance (Table 1).
Table 1. Direct time study. “Performance” stands for performance rate using
ASME scale. “Observed t” stands for Observed time in ten thousandths of an hour.
For element B, since a stopwatch time study was not possible, a pre-
determined motion time system was used. Namely, MTM-2 data cards
were used to synthesize a 575 TMU at normal pace (which is 111% the
normal pace in the ASME scale).
An allowance factor of 20% for all elements (A, B and C) was agreed
upon by the employer and the unions, in exchange for good quality.
Work measurement: main techniques
1. Estimation: experience / Historical records
How the task was performed last time (Data available from
production records or time cards)
Easy and inexpensive but data may be inaccurate
2. Time study
Time study is a work measurement technique for recording the times of
performing a certain specific job or its elements, and for analyzing the
data so as to obtain the time necessary for an operator to carry it out at a
defined rate of performance.
Normal performance
0 0 0
40 50 67
60 75 100
80 100 133
The basic time (temps bàsic o reduït) represents the time the element
would take to perform if the operator was working at the normal rate.
If observed time is 0.16 min and the worker’s performance rating factor
is 125 according to the ASME scale (where normal pace = 100)
Normal time (NT) is the time to complete a work element when working
at normal performance. Basic times are averaged. (Temps normal
representatiu).
a) For element A, compute the basic time for each reading.
Compute normal time.
Pel primer element manual, calcula els temps bàsics o reduïts del
cronometratge. Calcula el temps normal representatiu.
Fuente: Niebel (2009) INGENIERÍA INDUSTRIAL MÉTODOS, ESTÁNDARES Y DISEÑO DEL TRABAJO
Tt = TN · (1 + k)
d) Determine standard time for each element using an allowance factor of
20%.
Pels tres elements manuals, calcula el temps tipus amb uns suplements del
20%.
• Cycle time: The cycle time is defined as the average time between
the output of two successive units.
• Labor content (per part): It is defined as the time sum of all human
process steps.
1 Minuto tipo (MT) (Standard minute SM, Punto Bedaux, B). Trabajo
completado en un minuto por un trabajador medio a ritmo normal
incluidos los suplementos*.