W4 Homework (InventoryManagement)
W4 Homework (InventoryManagement)
nents?
units
runs per year
units
Q4
M. P. VanOyen Manufacturing has gone out on bid for a regulator component. Expected
The item can be purchased from either Allen Manufacturing or Baker Manufacturing. Th
table. Ordering cost is $50, and annual holding cost per unit is $5.
Allen MFG
Quantity Unit Price
1 1–499 16.00
2 500–999 15.50
3 1000 + 15.00
We check which supplier gives the best price for EOQ (410 units):
Allen MFG: 410 falls in the first tier (1-499), so price = $16.00 per unit.
Baker MFG: 410 falls in the second tier (400-799), so price = $15.60 per unit.
Baker MFG
Quantity Unit Price
1–399 16.10
400–799 15.60
800 + 15.10
UNITS
$ 15.60
Question 3:
Chicago’s Hard Rock Hotel distributes a mean of 1,000 bath towels per day to
guests at the pool and in their rooms. This demand is normally distributed with a
standard deviation of 100 towels per day, based on occupancy. The laundry firm
that has the linens contract requires a 2-day lead time. The hotel expects a 98%
service level to satisfy high guest expectations.
1.6449
290 TOWELS
Question 4:
A gourmet coffee shop in downtown San Francisco is open 200 days a year and sells an
coffee beans a day. (Demand can be assumed to be distributed normally, with a standa
day.) After ordering (fixed cost 5 $16 per order), beans are always shipped from Hawaii
annual holding costs for the beans are $3.
a) What is the economic order quantity (EOQ) for Kona coffee beans?
b) What are the total annual holding costs of stock for Kona coffee beans?
c) What are the total annual ordering costs for Kona coffee beans?
d) Assume that management has specified that no more than a 1% risk during stocko
the reorder point (ROP) be?
ans?
e beans?
?
% risk during stockout is acceptable. What should
2
Question 5:
Hip Replacements, Inc., has a master production schedule for its newest model, as sho
below, a setup cost of $50, a holding cost per week of $2, beginning inventory of 0, an
time of 1 week. What are the costs of using all three methods for this l0-week period?
a) L4L
b) EOQ
c) POQ
Week 0 1 2 3 4 5 6 7
Gross Requirement 0 0 50 0 0 35 15
Schedule Reciept
Project onhand
Net Requirement
Planned Reciept
Planned order Release
8 9 10
0 100 0