Geotechnical
Geotechnical
2015/APC/RS-AGT/082
1.0 INTRODUCTION
1.1. General:
VKS infratech management pvt. Ltd., Consulting Engineers & Planners, 181,
Pratapnagar, lane no.18, opp. pkt-, Mayur Vihar Phase-1, Delhi- 110091 has entrusted
a job to Agartha Project Consultancy Services Pvt. Ltd for preparation of geotechnical
investigation report along with proposal of foundation design load for the proposed
construction of Bridge over River Fenni at Sabroom, South Tripura.
The soil exploration includes sinking of total 4 (four) nos. of boreholes among which
two boreholes of nearly 60.0m (BH01 & BH03) and another two boreholes (BH02 &
BH04) nearly 40.0m deep from the existing ground surface and collection of
undisturbed and disturbed soil samples from the borehole, and testing of these
samples in the laboratory. Shell and Augar & partly wash boring was adopted for
field sampling and testing. Soil samples thus collected were forwarded to laboratory
after proper sealing.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.3 Job No. 2015/APC/RS-AGT/082
AGARTALA SABROOM
D I A
D
O
B
BH 04
A
FENCING
I N
70 mtr.
BH 03
80 mtr.
BH 01
S-10
International Piller
2215
70 mtr.
BH 02
Ramgarh
FEENI
BA
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.4 Job No. 2015/APC/RS-AGT/082
The aim and objective of the present study is to bring out the soil stratification,
strength and settlement characteristics of different strata based on which suitability of
different types of foundation could be analyzed. This is accomplished by borehole
studies including field & laboratory tests followed by the necessary interpretation and
analysis.
The soil exploration programme is drawn to find out the general stratification of
soil and related parameters, which when put to analysis would provide the best
possible knowledge of foundation behavior at this site. The programme included:
BORING:
The scope of this soil investigation is limited to four boreholes in the location as
suggested (refer Fig. 1.1). Boring through the soil was carried out by Augar and Wash
method to sink nominal 150 mm diameter borehole by using manually operated
winch. Suitable casings have been used upto 5.0 m below the existing ground level to
prevent cavity inside the borehole. Bentonite clay slurry has also been used whenever
sand layer was encountered. During the process of boring, both undisturbed and
disturbed soil samples were collected at suitable intervals and at the change of strata
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.5 Job No. 2015/APC/RS-AGT/082
whichever was encountered earlier by open drive sampling method. Besides, SPT
tests were also conducted at suitable intervals and recorded.
Representative soil samples were collected frequently from auger, split spoon
sampler of standard penetrometer and cutting shoe of undisturbed sampling
assembly to maintain a continuous record of strata encountered. All the samples were
labeled and placed in air-tight containers and shifted to the laboratory for
identification and testing.
GROUND WATER
During the field investigation, ground water observation was made. The
standing water level was measured in the borehole after 24 hours of removal of
casings. These levels of ground water are likely to change with normal seasonal
variations.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.6 Job No. 2015/APC/RS-AGT/082
BULK DENSITY
It is the ratio of the weight [moist] and volume of the sample.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.7 Job No. 2015/APC/RS-AGT/082
CONSOLIDATION TEST
A sample in a mould is subjected to different stages of load and vertical
compression of the sample thickness is recorded at definite time intervals. Cc is found
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.8 Job No. 2015/APC/RS-AGT/082
3.1 General
Soil profiles were drawn on the basis of analysis of samples obtained from 4
(four) boreholes and presented in bore logs enclosed in the “Appendix I”. The
characteristic parameters of each individual strata as obtained from laboratory tests
are also presented strata wise. An average soil property for each stratum highlighting
all the boreholes is shown in Table 3.1. The results of the Standard Penetration Tests
(S.P.T.) of each possible layer have also been recorded and corrected N values shown
against each respective layer in Table 3.5 to 3.8 and Appendix V. A general sub soil
profile highlighting the physical and engineering parameters layer wise across each
borehole is presented in Fig. 3.1.
Stratification:
BH01
Up to the full depth of boring i.e. 60.907m from the existing ground level
(EGL), the soil consists of 4 (four) distinct layers of virgin soil. The water table has
been located to remain at 5.4 m below EGL. From EGL, a layer of light gray to
brownish gray clayey silty fine sand to medium to stiff sandy clayey silt layer having
thickness of nearly 7.907 m has been observed. Further, a layer of light brown silty
fine to medium sand is observed which continues from 7.907 m to 20.907 m below
EGL which shows good SPT values. The above layer is followed by another layer of
dark gray stiff to hard clayey silt with fine sand laminations and slate formation upto
a depth of 26.907 m below EGL. From datum 26.907 m to 60.907 m, a layer of light
brown to dark gray densely packed fine to medium sand soil layer is encountered
upto the depth of termination, i.e., 60.907 m which shows high SPT values.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.9 Job No. 2015/APC/RS-AGT/082
BH02
Up to the full depth of boring i.e. 40.0m from the existing ground level (EGL),
the soil consists of 4 (four) distinct layers of virgin soil. The water table has been
located to remain at 5.5m below EGL. From EGL, a layer of dark brown soft sandy
clayey silt to loose sandy silt layer having thickness of nearly 8.0m has been observed.
Further, a layer of light gray to dark brown fine to medium to coarse sand is observed
continuing from 8.0 m to 17.0 m below EGL which shows good SPT values. The above
layer is followed by dark gray stiff to hard clayey silt with fine sand laminations and
slate formation upto a depth of 20.0m below EGL. From datum 20.0m to 40.0m, a layer
of dark brown fine to medium sand soil layer is encountered upto the depth of
termination, i.e., 40.0m which shows very high SPT values.
BH03
Up to the full depth of boring i.e. 62.186m from the existing ground level
(EGL), the soil consists of 4 (four) distinct layers of virgin soil. The water table has
been located to remain at 4.7m below EGL. From EGL, a layer of dark brown to gray
sandy silt to soft sandy clayey silt layer having thickness of nearly 7.186m has been
observed. Further, a layer of dark brown fine to medium to coarse sand is observed
which continues from 7.186m to 21.186m below EGL which shows good SPT values.
The above layer is followed by dark gray stiff to hard clayey silt with slate formation
upto a depth of 28.186m below EGL. From datum 28.186m to 62.186m below EGL, a
layer of light brown fine to medium sand soil layer is encountered upto the depth of
termination, i.e., 62.186 m which shows high SPT values.
BH04
Up to the full depth of boring i.e. 40.079m from the existing ground level
(EGL), the soil consists of 4 (four) distinct layers of virgin soil. The water table has
been located to remain at 5.0m below EGL. From EGL a layer of dark gray soft sandy
clayey silt to stiff clayey silt layer having thickness of nearly 8.079m has been
observed. Further, a layer of dark brown fine to medium sand with traces of clay
binders is observed which continues from 8.079m to 25.079m below EGL which shows
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.10 Job No. 2015/APC/RS-AGT/082
good SPT values. The above layer is followed by light gray stiff to hard clayey silt
upto a depth of 27.079m below EGL. From a datum of 27.079m to 40.079m below EGL,
a layer of dark brown fine to medium sand (densely packed) soil layer is encountered
upto the depth of termination, i.e., 40.079m below EGL which shows very high SPT
values.
Ncor is related to the standard energy ratio used by the designer. Ncor may be expressed
as N60 or N70 according to the designer's choice. Detailed discussion about these
corrections is presented elsewhere (Murthy 2004). The corrected ‘N60’ value vs. depth
is presented in Table 3.5 to 3.8 and graphically presented in Appendix V.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.11 Job No. 2015/APC/RS-AGT/082
Description of layer
Layer-I Layer-II Layer-III Layer-IV
and its properties
Light gray to brownish gray Light brown silty fine to Dark gray stiff to hard Light brown to dark
Layers clayey silty fine sand to medium sand clayey silt with fine sand gray densely packed fine
medium to stiff sandy clayey laminations and slate to medium sand
silt
R.L of layer: thickness (EGL to 7.907m): 7.907m (7.907m to 20.907m): 13.0m (20.907m to 26.907m): 6.0m (26.907m to 60.907m): 34m
Description of layer
Layer-I Layer-II Layer-III Layer-IV
and its properties
Dark brown soft sandy clayey Light gray to dark Dark gray stiff clayey Dark brown fine to
Layers silt to sandy silt brown fine to coarse silt with fine sand medium sand
sand lamination and slate
R.L of layer: thickness (EGL to 8m): 8.0m (8m to 17m): 9.0m (17m to 20m): 3.0m (20m to 40m): 20.0m
Sand (%) 05 97 05 98
Silt (%) 65 03 57 02
Clay (%) 30 - 38 -
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.12 Job No. 2015/APC/RS-AGT/082
Description of layer
Layer-I Layer-II Layer-III Layer-IV
and its properties
Dark brown to gray sandy silt Dark brown fine to Dark gray stiff to hard Light brown fine to
Layers to soft sandy clayey silt medium to coarse sand clayey silt with slate medium sand
formation
R.L of layer: thickness (EGL to 7.186m): 7.186m (7.186m to 21.186m): 14.0m (21.186m to 28.186m): 7.0m (28.186m to 62.186m): 34.0m
Description of layer
Layer-I Layer-II Layer-III Layer-IV
and its properties
Dark gray soft sandy clayey silt Dark brown fine to Light gray stiff to hard Dark brown fine to
Layers to stiff clayey silt medium sand with clayey silt medium sand
traces of clay binders
R.L of layer: thickness (0m to 8.079m): 8.079m (8.079m to 25.079m): 17.0m (25.079m to 27.079m): 2.0m (27.079m to 40.079m): 13.0m
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.13 Job No. 2015/APC/RS-AGT/082
Corrected N values
Calculated
(after overburden
Recorded Minimum Maximum phi (φ) as
Depth pressure and (N1)60 Layer
SPT N value (N1)60 (N1)60 per Peck
dilatancy correction
et al. 1972
,wherever required)
1.50 5 5 4 26
3.00 9 9 7 29
I 4 17
4.50 20 20 17 34
6.00 19 19 17 34
7.50 20 20 20 36
9.00 46 46 48 39
10.50 48 48 50 39
12.00 60 57 59 41
13.50 50 48 50 II 20 59 39
15.00 50 47 49 40
16.50 50 46 49 40
18.00 50 46 48 39
19.50 50 45 47 40
21.00 50 50 53 41
22.50 50 50 53 41
III 53 53
24.00 50 50 53 41
25.50 50 50 53 41
27.00 50 43 45 39
28.50 50 43 45 39
30.00 50 42 44 39
31.50 50 42 44 39
33.00 50 42 44 39
34.50 50 41 43 39
36.00 50 41 43 39
37.50 50 41 43 39
39.00 50 40 42 39
40.50 50 40 42 39
42.00 50 40 42 39
43.50 50 39 41 IV 45 40 38
45.00 50 39 41 38
46.50 50 39 41 38
48.00 50 39 40 38
49.50 50 38 40 38
51.00 50 38 40 38
52.50 50 38 40 38
54.00 50 38 40 38
55.50 50 38 40 38
57.00 50 38 40 38
58.50 50 38 40 38
60.00 50 38 40 38
N.B. N value more than 50 is considered as refusal in granular soils.
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.14 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.15 Job No. 2015/APC/RS-AGT/082
Corrected N values
(after overburden
Calculated
Recorded pressure and
Minimum Maximum phi (φ) as
Depth SPT N dilatancy (N1)60 Layer
(N1)60 (N1)60 per Peck et
value correction
al., 1972
,wherever
required)
1.50 5 5 4 27
3.00 6 6 5 I 4 5 28
4.50 5 5 4 27
6.00 13 13 12 30
7.50 38 38 37 37
9.00 85 78 82 49
10.50 61 57 60 43
12.00 50 48 50 II 12 82 41
13.50 50 47 49 40
15.00 50 46 49 40
16.50 50 46 48 40
18.00 50 45 47 40
19.50 50 50 53 41
21.00 50 44 46 40
22.50 50 44 46 III 45 53 40
24.00 50 43 46 40
25.50 50 43 45 39
27.00 50 43 45 39
28.50 50 42 44 39
30.00 50 42 44 39
31.50 50 42 44 39
33.00 50 41 43 39
34.50 50 41 43 39
36.00 50 41 43 39
37.50 50 40 42 39
39.00 50 40 42 39
40.50 50 40 42 39
42.00 50 39 41 38
43.50 50 39 41 IV 45 40 38
45.00 50 39 41 38
46.50 50 39 41 38
48.00 50 38 40 38
49.50 50 38 40 38
51.00 50 38 40 38
52.50 50 38 40 38
54.00 50 38 40 38
55.50 50 38 40 38
57.00 50 38 40 38
58.50 50 38 40 38
60.00 50 38 40 38
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No.16 Job No. 2015/APC/RS-AGT/082
Corrected N
values (after
overburden Calculated
Recorded
pressure and Minimum Maximum phi (φ) as
Depth SPT N (N1)60 Layer
dilatancy (N1)60 (N1)60 per Peck
value
correction et al., 1972
,wherever
required)
1.50 1 1 1 26
3.00 4 4 3 27
4.50 3 3 3 I 1 66 27
6.00 52 52 48 40
7.50 69 67 66 45
9.00 80 75 79 48
10.50 80 74 77 47
12.00 50 48 50 41
13.50 50 47 50 41
15.00 50 47 49 40
16.50 50 46 48 II 79 46 40
18.00 50 45 48 40
19.50 50 50 53 41
21.00 50 44 47 40
22.50 50 44 46 40
24.00 50 43 46 40
25.50 50 43 45 39
III 45 45
27.00 50 43 45 39
28.50 50 42 44 39
30.00 50 42 44 39
31.50 50 42 44 39
33.00 50 41 43 39
34.50 50 41 43 IV 42 44 39
36.00 50 41 43 39
37.50 50 40 42 39
39.00 50 40 42 39
40.50 50 40 42 39
Geo-Technical Investigation report for the construction of proposed Bridge over River Fenni at Sabroom, South Tripura.
Sheet No. 17 / Job No. 2015/APC/RS-AGT/082
Fig. 3.1 - Generalised Soil Profile (BH 01, BH 02, BH 03 & BH 04)
HFL 16.126 M
R.L = 15.673 m R.L = 14.766 m R.L = 13.487 m R.L = 15.594 m
Depth in M. Layer Soil Description Layer Soil Description Layer Soil Description Layer Soil Description
BH 02 BH 01 BH 03 BH 04
X1 = 0.907 M
X2 = 2.186 M X3 = 0.079M
2.00 2 N 5 N 5 N 1 N Layer - I
U miss miss U miss
Layer - I
U
Layer - I U
6 N 9 N 6 N
Layer - I 4 N
4.00 Light gray to brownish gray loose Dark gray soft sandy clayey silt to stiff
7 N 20 N 5 N 3 N
Dark brown soft sandy clayey silt to clayey silty fine sand to medium to Dark brown to gray sandy loose clayey silt
5.40 M 4.7 M 5.0 M
5.5 M sandy silt stiff sandy clayey silt silt to soft sandy clayey silt
6.00
8 N 19 N 13 N >50 Refusal
8 N N
7.186 M N >50 Refusal
8.00 8.0 M 7.907 M
20 38
8.079 M
21 N 46 N >50 Refusal >50 Refusal
10.00
Layer - II Layer - II Layer - II
>50 Refusal 48 N >50 Refusal >50 Refusal
Layer - II
12.00
>50 Refusal >50 Refusal >50 Refusal >50 Refusal
Dark brown fine to medium to coarse sand
Light gray to dark brown fine to coarse sand
14.00 >50 Refusal >50 Refusal >50 Refusal >50 Refusal
Dark brown fine to medium sand with
Light brown silty fine to medium sand
>50 Refusal >50 Refusal >50 Refusal >50 Refusal traces of clay binders
16.00
>50 Refusal >50 Refusal >50 Refusal >50 Refusal
17.0 M
18.00
20 N >50 Refusal >50 Refusal >50 Refusal
>50 Refusal >50 Refusal Light brown to dark gray densely packed fine to >50 Refusal >50 Refusal
40.00 >50 Refusal medium sand >50 Refusal
40.0 M >50 Refusal >50 Refusal
40.079 M
42.00
>50 Refusal >50 Refusal
48.00
>50 Refusal >50 Refusal
54.00
>50 Refusal >50 Refusal
Geo-Technical Investigation report for Consultancy and DPR work for Bridge over River Fenni, Sabroom, Tripura.
Sheet No.12 Job No. 2015/APC/RS-AGT/082
4.1 General
Based on the soil exploration results, further analysis is carried out in this
chapter to determine the suitable foundation along with proposal of depth and
allowable bearing capacity of the foundation for the proposed bridge construction
over Fenni river at Sabroom. Both pile and well foundation is attempted for the
proposed bridge construction as suggested in terms of reference. In this context, it is
important to make a rational consideration of design parameters of soil for each
layer and boreholes explored. Table 4.1 presents the design parameters of subsoil
based on average soil properties. However, selection of design parameters involves
conservative judgment on the available parameters or standard correlation available
in the literature. For designing of any foundation, it should be noted that the
attempted foundation would be safe from two basic criteria, i.e., (i) limit state of
shear or bearing capacity failure and (ii) limit state of serviceability or settlement
criteria. However, a stability check will also be carried out for a well foundation with
respect to lateral loading. In addition, CBR for the nearby borrow pit soil, suitability
of ground water for construction and chemical aggressiveness with concrete, and
calculation of earth pressure coefficients are also reported in this chapter.
The layer wise average design sub-soil parameters are presented separately
for BH01, BH02, BH03 and BH04 respectively in the present section for the sake of
design of deep foundation. The site exhibits uniformity of sub-soil layersas observed
from subsoil properties and stratification of layers encountered in the four boreholes.
On the basis of soil parameters available from laboratory & field tests, it has been
observed that the site consists of poor to moderate quality of foundation material
uptoan average depth of 6.0 m below EGL which consists of heterogeneous alluvial
deposit of soft to medium to stiff sandy clayey silt to loose sandy silt/silty fine to
medium sand. The water table is observed at 5.0 m, 4.5 m, 2.5 m and 5.0 m below
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.13 Job No. 2015/APC/RS-AGT/082
EGL in BH02, BH01, BH03 and BH04 respectively. From an average datum of 6.0 m
to 20.0 m below EGL, a silty fine to medium sand to medium to coarse sand with -
*indicates shear strength and consolidation parameters of this layer is calculated from standard correlation available elsewhere (Peck et
al., 1974 and Nagaraju and Murthy, 1985)
*indicates shear strength and consolidation parameters of this layer is calculated from standard correlation available elsewhere (Peck et
al., 1974 and Nagaraju and Murthy, 1985)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.14 Job No. 2015/APC/RS-AGT/082
*indicates shear strength and consolidation parameters of this layer is calculated from standard correlation available elsewhere (Peck et
al., 1974 and Nagaraju and Murthy, 1985)
*indicates shear strength and consolidation parameters of this layer is calculated from standard correlation available elsewhere (Peck et
al., 1974 and Nagaraju and Murthy, 1985)
localized soft clay binders is observed in all theboreholes which shows good SPT values
and suitable layer for laying any foundation. The above layer is followed by a relatively thin
layer of stiff silty clay to clayey silt with slate rock formation upto an average depth of 24.0
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.15 Job No. 2015/APC/RS-AGT/082
m below EGL. Finally, a considerably thick layer consisting of densely packed fine to
medium sand is encountered with refusal SPT values is encountered upto depth of
termination, i.e., 60 m and 40 m below EGL in BH02, BH03 and BH01, BH04 respectively.
From the above view point, scour depth calculation, geotechnical design of pile foundation
and well foundation are carried out in the next section which is required for preparation of
consultancy and detailed project report for bridge over river Fenni, Sabroom, Tripura.
The maximum scour depth (MSD) along with other necessary parameters, such as,
mean diameter of particle size (dm) andLacey‟s silt factor (ksf) are presented in Table
4.5 for each bore hole. It is observed that the subsoil at below EGL, i.e., layer I in all
the boreholes are consists of heterogeneous mix of loose tosoft to medium sandy silt
to silty sand to sandy clayey silt soil which is highly prone to both scouring action
due toflood and susceptible under liquefaction during earthquake. Hence, the
selection of depth and design of deep foundation is performed considering
maximum depth of scourobserved in BH01, i.e., 7.40 m below HFL.
Max.
Normal
Design Scour
Scour
Bore weighted Design Silt depth
Depth weighted mean depth
Hole mean Discharge factor below
(m) diameter (mm) below
No. diameter (m3/sec) (ksf) HFL
HFL(dsm)
(dm) (2dsm)
(m)
(m)
0.50 0.299
1 0.299 0.963* 3.70 7.40
1.50 0.024
0.50 0.022
2 0.022 2.856** 2.58 5.16
3.00 0.019
460
0.50 0.031
3 0.031 3.00** 2.53 5.06
2.00 0.023
1.00 0.039
4 0.039 3.140** 2.49 4.98
3.00 0.018
*using Eq. (III) as given in A1
**using Eq. (IV) as given in A1
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.16 Job No. 2015/APC/RS-AGT/082
Procedure stated in IRC: 78-2014 has been adopted to calculate normal and maximum scour
depth for different bore holes. The mean scour depth below the highest flood level (HFL) for
natural channels flowing over scourable bed is calculated from the following equation.
2
Db 1/ 3
d s m 1 .3 4 ( ) …. (I)
K sf
Q
Eq. (I) can also be expressed in the form d s m 0 .4 7 3 ( )
1/3
…(II)
K sf
dm being the weighted mean diameter in millimeter and is calculated following procedures
stated in IRC: 5-1998. However, for bed material comprising of clay having weighted mean
diameter less than 0.04 mm, IRC: 78-2014 suggests calculation of silt factor by the following
expression
K s f F (1 c) ... (IV)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.17 Job No. 2015/APC/RS-AGT/082
Table A-1 Grain Size distribution of Soil Sample from BH 01 at a depth of 0.5m (Refer
Appendix III: Grain size distribution curve)
Cumulative
Sieve Size Percent
percent retained Percent retained (%)
(mm) finer
(%)
(%)
2.360 100 0.00 0.00
2.000 100 0.00 0.00
1.180 99.93 0.07 0.07
0.600 95.30 4.70 4.63
0.425 82.50 17.50 12.80
0.300 60.80 39.20 21.70
0.150 15.60 84.40 45.20
0.075 15.00 85.00 0.60
Pan 0.00 100.00 15.00
Table A-2 Weighted mean diameter of soil sample from BH 01 at a depth of 0.5m (IRC: 5-
1998)
1 2 3 4
Percentage of
Sieve size Mean size Col. 2 Col.3
weight retained
2.8-2.36 2.580 0.00 0
2.36-2.00 2.180 0.00 0
2.00-1.18 1.590 0.07 0.11
1.18-0.60 0.890 4.63 4.12
0.60-0.425 0.513 12.8 6.56
0.425-0.30 0.363 21.70 7.86
0.30-0.15 0.225 45.20 10.17
0.15-0.075 0.113 0.60 0.07
0.075 -0.063 0.069 15.00 1.03
= 1 .7 6 0 .2 9 9
= 0.963
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.18 Job No. 2015/APC/RS-AGT/082
406
= 0 .4 7 3 ( )
1/ 3
0 .9 6 3
= 3.70 m
Maximum Scour depth (near abutments) = 2dsm
= 2 3.70 = 7.40 m
In case of BH 02
Mean weighted diameter is calculated following the similar procedure as done for BH 01.
Calculated mean weighted diameter (dm) = 0.022 mm
Ksf= F (1 c)
= 1 .7 5 (1 0 .2 5 )
= 2.856
Q
Mean Scour depth, (dsm) = 0 .4 7 3 ( )
1/3
K sf
406
= 0 .4 7 3 ( )
1/ 3
2 .8 5 6
= 2.58 m
Maximum Scour depth (near abutments) = 2dsm
= 2 2.58 = 5.16 m
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.19 Job No. 2015/APC/RS-AGT/082
where amax is the peak ground acceleration, g is the acceleration of gravity, V0and
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.20 Job No. 2015/APC/RS-AGT/082
(N1)60 is the corrected SPT blow count that can be calculated using equation:
(N1)60= NMCNCECBCRCS
where Nm is the measured penetration resistance, CN is the factor to normalized NM
to a common reference effective overburden stress (100KPa), CE, CB, CR and CS are
the connection for hammer energy ratio, borehole diameter, rod length, and sample
with or without liners, respectively. Appendix VI presents a graph of a calculated
CSR and corresponding data for the sites where liquefaction effects were or not
observed following past earthquakes with magnitude of approximately 7.5. CRR
curves in the same figure were conservatively positioned to separate regions with
data indicative of liquefaction from regions with data indicative of non-liquefaction.
The CRR curves in figure are valid only for magnitude 7.5 earthquakes and 0.5g of
intensity of motion. If earthquake magnitude is not 7.5 we should consider scaling
factor.
It is observed from the figures considering BH01 to BH04 that the top layer
varying from 5m to 9m below EGL is found to be susceptible under liquefaction
during seismic excitation. The cohesionless soil layer encountered below 9m depth
shows strong resistance against liquefaction in all the boreholes. Further, it is to be
noted that maximum scour level is calculated as around 6.54m below lowest bed
level (LBL) and 8.726m below from the highest bed level (datum line) for the
proposed bridge at Fenni river. The maximum scour depth (MSD) is avoided for
calculation of vertical and lateral resistance for designing of deep foundation which
may also consider the zero soil resistance from the liquefiable susceptible zone of soil
layer. As the liquefaction prone soil layer and maximum scour depth zone is almost
same.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.21 Job No. 2015/APC/RS-AGT/082
Deep foundation in the form of long pile may be used for supporting the proposed
bridge piers/abutments. In recent practice in bridge foundation, pile foundation is
mostly used in India due to ease of construction and to save time, money and
workmanship as compared to conventional well foundation. Hence, bored cast-in-
situ piles may be used in this case to avoid noise pollution and to eliminate the
driving effect to the adjacent structure if any.
Considering the bore hole positions, it is assumed that BH01 and BH03 as per
site plan are considered as central pier location of bridge and BH02 and BH04
indicates abutment locations respectively. The piles at central pier and abutment
locations can be placed at a depth of 30m and 25m below lowest bed level (LBL)
respectively. The cut-off levels for different boreholes are calculated accordingly
which are presented below. The determination of pile capacity for different
diameters is presented in Table 4.6 using layer stratification as considered in average
design soil profile presented in Table 4.1 to Table 4.4 and following IS2911-Part 2-
2010 guideline.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.22 Job No. 2015/APC/RS-AGT/082
Table 4.6 Recommended values of safe vertical and lateral load for single pile (FOS = 2.5
for skin friction and 5 for end bearing resistance)
Safe vertical
Bore hole Pile Allowable
Load Recommended Lateral
number/ Depth of pile Diameter Deflection
calculated Load (kN) Load (kN)
location (mm) (mm)
(kN)
0.01times
diameter of
31.28m below 1000 5480 5000 30
pile at scour
E.G.L with 1.28m level
BH01/ cut-off level
Pier below EGL 1200 8100 7500 62 -do-
(Length = 30m)
1500 13390 10000 145 -do-
N.B.
1. Group action of pile may be considered if spacing to diameter ratio (s/d) less
than 3.0 used. To utilize the complete load carrying capacity, the s/d ratio to be
used greater than 3.0.
2. Vertical as well as lateral load test as per Indian standard must be carried out
on initial pile and test pile.
3. Design of pile is limited to only static load only. However, due to limited
scope of work, dynamic design of pile is not attempted herein.
4. Skilled workforce should be engaged for carrying out pile construction job.
5. Safety of any adjacent structure must be ensured during construction of
foundation.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.23 Job No. 2015/APC/RS-AGT/082
A2: Sample calculation for design of a pile foundation considering BH03 under vertical
and lateral loading is presented below.
Pile Dia : 1.000M
Existing Ground level : 0.000M
Existing GWT level : -2.000M
EGL to Maximum Scour level : -9.000M (Not considered)
Pile Termination level : -30.000M
For maximum overburden pressure at Pile tip 18 x dia length of pile has been taken
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.24 Job No. 2015/APC/RS-AGT/082
Layer no. 1:
Thickness : 5.000m
K : 1.00
Pdi : 2.98 T/Sq.M.
tan(d) : 0.02
Asi : 0.00 Sq.M.
Qsg = K*Pdi*tan(d)*Asi =1.00*2.98*0.02*0.00 = 0.00 T
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.25 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.26 Job No. 2015/APC/RS-AGT/082
EI
The stiffness factor (T) is calculated in meter = 5 where EI is flexural stiffness of pile and h is
h
modulus of subgrade reaction in kN/m3. h as per Table 3 of IS 2911-Part 2-2010 = 5000 kN/m3 and
diameter of pile is assumed as 1.0m. Young’s modulus of RCC pile of M30 grade is assumed as
28 106 kN/m2
EI = ( 28 10 6 1
4
) = 13.74 105 kN-m2
64
Therefore T = 3.07 m. Refer Fig. 4 of IS 2911-Part 2-2010 and depth of fixity (Lf) is calculated as 5.56m.
3
V ( L1 L f )
Deflection at pile head, y [IS 2911-Part 2-2010] where V is applied horizontal
3
10
12 EI
force at pile head and permissible deflection at MSL is 0.01times diameter of pile as per IRC 78 (2014).
Accordingly, deflection at pile head is calculated as 0.022m presented in Fig. 4.1.
Using the above expression for fixed head pile, V is calculated as 30 kN. The lateral load calculation will
be same for BH01, BH02 and BH04 locations as layer II remains almost same nature and properties where
the depth of fixity is developed.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.27 Job No. 2015/APC/RS-AGT/082
Fig. 4.2: Design details of Pile foundation under vertical and lateral load
considering BH03 (dia = 1000 mm)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.28 Job No. 2015/APC/RS-AGT/082
A.3: Sample calculation for design of a pile foundation considering BH01 under vertical
and lateral loading is presented below.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.29 Job No. 2015/APC/RS-AGT/082
Layer no. 1:
Thickness : 7.000m
K : 1.00
Pdi : 5.12 T/Sq.M.
tan(d) : 0.02
Asi : 0.00 Sq.M.
Qsg = K*Pdi*tan(d)*Asi =1.00*5.12*0.02*0.00 = 0.00 T
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.30 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.31 Job No. 2015/APC/RS-AGT/082
Fig. 4.3: Design details of Pile foundation under vertical and lateral load
considering BH01 (dia = 1000 mm)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.32 Job No. 2015/APC/RS-AGT/082
A.4: Sample calculation for design of a pile foundation considering BH02 under vertical
and lateral loading is presented below.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.33 Job No. 2015/APC/RS-AGT/082
Layer no. 1:
Thickness : 8.000m
K : 1.00
Pdi : 5.86 T/Sq.M.
tan(d) : 0.02
Asi : 0.00 Sq.M.
Qsg = K*Pdi*tan(d)*Asi =1.00*5.86*0.02*0.00 = 0.00 T
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.34 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.35 Job No. 2015/APC/RS-AGT/082
Fig. 4.4: Design details of Pile foundation under vertical and lateral load
considering BH02 (dia = 1000 mm)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.36 Job No. 2015/APC/RS-AGT/082
A.5: Sample calculation for design of a pile foundation considering BH04 under vertical
and lateral loading is presented below.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.37 Job No. 2015/APC/RS-AGT/082
Layer no. 1:
Thickness : 8.000m
K : 1.00
Pdi : 5.78 T/Sq.M.
tan(d) : 0.02
Asi : 0.00 Sq.M.
Qsg = K*Pdi*tan(d)*Asi =1.00*5.78*0.02*0.00 = 0.00 T
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.38 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.39 Job No. 2015/APC/RS-AGT/082
Fig. 4.5: Design details of Pile foundation under vertical and lateral load
considering BH04 (dia = 1000 mm)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.40 Job No. 2015/APC/RS-AGT/082
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.41 Job No. 2015/APC/RS-AGT/082
Table 4.7 Allowable bearing pressure of proposed well foundation (FOS = 2.0)
Average
Depth of
corrected
Bore foundation Diameter Allowable
SPT (Ncorr) Recommended
hole below max. of well bearing pressure
at qa in kN/m2
No. scour depth (B)(m) (qa) in kN/m2
foundation
Df(m)
level
5.0 2325 2300.00
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.42 Job No. 2015/APC/RS-AGT/082
2D1 = 3 H 1 2
9 H 1 2 D (3 H 1 D )
H1 = H + D
H = depth from point of action (top of pier) of load to level maximum scour depth.
Therefore, maximum allowable horizontal force calculated for different bore hole
subsoil parameters is shown as below.
Depth
Depth of from top
submerged foundation of pier
Bulk H1 =
Bore unit below to level 2D1 qa max
density H+D φ Kp Ka
Hole weight (γ’) max. scour of max. (m) (kN/m)
(kN/m3) (m)
No. (kN/m3) depth (Df) scour
(m) (H)
(m)
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.43 Job No. 2015/APC/RS-AGT/082
5 . 4 38
2
5 16 100 38
2
20
= 473778.40 kg/m2
= 4647.77 kN/m2
Considering FOS = 2, qa is calculated as 2325kN/m2
= 3 ( 2 9 .1 4 ) 2
9 ( 2 9 .1 4 ) 2 (1 7 .6 )(3 ( 2 9 .2 4 ) 2 7 .6 )
= 15.42 m
1
q m ax ' D (K p
K a )( D 2 D 1 )
2
1
(1 0 )(1 7 .6 )(3 .3 9 0 .2 9 4 )(1 7 .6 1 5 .4 2 )
2
=815kN/m
Finally, a subsoil profile highlighting the depth of proposed pile and well
foundation along with MSL and LBL is graphically presented in Fig. 4.6.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.44 Job No. 2015/APC/RS-AGT/082
As per guideline, four days soaked CBR values are calculated as per IS2720-Part 16-
1979 for two borrow pit soil samples near BH02 and BH04 locations. In this context,
Standard Proctor tests are conducted as per IS2720-Part 7-1980 in order to obtain
maximum dry density (MDD) and optimum moisture content (OMC) for respective
soil samples. Table 4.8 presents the CBR value in percentage along with OMC and
MDD for two collected soil samples(see Appendix VII and VIII).
Table 4.8 Test results for CBR value for borrow pit samples
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.45 Job No. 2015/APC/RS-AGT/082
Based on field and laboratory test results and the foregoing discussions, the
following points are summarized for recommendation of foundation design of
proposed bridge over river Fenni at Sabroom, Tripura.
2. The maximum scour depth is calculated as 7.40m below HFL in BH01, i.e., 6.54m
below the lowest bed level and minimum foundation depth should be below this
level minus grip length for deep foundation.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.
Sheet No.46 Job No. 2015/APC/RS-AGT/082
considered from Table 4.6 for designing the substructure. However, the safe pile
capacities for different diameters at BH04 location are found to lowest which may
be considered as design pile capacity throughout the bridge foundation.
6. The CBR values for two borrow pit samples under four day soaked condition is
obtained as 7.56% and 6.96%.
7. Every precautionary measure as laid down in the relevant I.S. Codes and as
applicable for the particular type of foundation is to be adopted here must be
taken during execution of foundation work. Due consideration should
particularly be given towards the safety of nearly existing structure or any other
water bodies, if any. Further, the seismic effect is not considered in the present
scope of work.
Er. S. Debnath
Managing Director.
Geo-Technical Investigation report for the construction of Bridge over River Fenni, Sabroom, Tripura.