0% found this document useful (0 votes)
19 views13 pages

General Design Criteria

The document outlines the preliminary design criteria and checklist for the Lake Victoria South Water Works Development Agency, focusing on various components such as water demand, source of water, intake works, water treatment plant, sludge management, reservoirs, pumping stations, energy requirements, and pipeline works. Each component includes specific considerations and requirements to ensure effective planning and implementation of the water works project. The document serves as a comprehensive guide for reviewers and stakeholders involved in the development process.

Uploaded by

peninah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views13 pages

General Design Criteria

The document outlines the preliminary design criteria and checklist for the Lake Victoria South Water Works Development Agency, focusing on various components such as water demand, source of water, intake works, water treatment plant, sludge management, reservoirs, pumping stations, energy requirements, and pipeline works. Each component includes specific considerations and requirements to ensure effective planning and implementation of the water works project. The document serves as a comprehensive guide for reviewers and stakeholders involved in the development process.

Uploaded by

peninah
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 13

LAKE VICTORIA SOUTH WATER WORKS DEVELOPMENT AGENCY

WATER WORKS PRELIMINARY DESIGN CRITERIA/ CHECKLIST

Component Considerations Remarks by


Reviewer
1 WATER DEMAND
‘ a. Population Estimation:
‘  Target beneficiary e.g urban,
peri-urban
 Project Boundary defined
(Locations/Sub-locations)
 % Overall Population Targeted
 Initial Year (Ref)- 2019 (Census)
 Annual Growth Rate %
 Projection Formula
 Planning Year (2025)
 Initial Year (2030)
 Future Year (2040)
 Ultimate Year (2050)
b. Water Demand ( m3/d)
 Domestic
 Institutional
 Commercial
 Industrial
 Fire-fighting
 Non-Revenue Water (20%)
Sub-total (m3/d)
 Per-capita W. Demand (L/p/d)
2 SOURCE OF WATER (R OR L)
(a)River
 Reliability of Flow
 Upstream Water Rights
 Downstream Water Demands
 Environmental Flow (Q95%)
 Water Quality (WHO) Issue
 Upstream Pollution Risk
(b)Lake /Dam
 Storage Capacity (m3)
 Existing Demands (N/A for L.V)
 Key Water Quality (WHO) Issue
 Pollution Risk/Threats
3 INTAKE WORKS
‘ a. Hydrological Data
 Flood flow (m3/s)
 Environmental Flow (Q95%)
b. Water Quality
 Water Quality (WHO)
 Upstream Pollution Threat
 Presence of Algae (for Lake)
 Sediment Load
c. Topographical Survey
 Elevation (X,Y,Z)
 Vertical Profile (gradient)
 Horizontal Profile (No bend)
 Not at Flood Plain (Y/No)
 Crest Length of the Weir (m)
 Height of the Weir +free board
d. Environmental Factors
 Environmental Flow (Q95%)
 Upstream Pollution Threat (e.g
Industries, Urban discharge)
 Surrounding economic activity
e. Structural Design
 Existing Foundation Material
 Material selection (R.C)
 Load considerations: (Hst,UpL,
Ovt, Ssmc, SedL, etc)
 Free board (R-0.5m, L-1m)
 Silt traps
 Silt Release Provisions (Pipe,
channels,)
 Size of Silt Release
Appurtenance
 No of Silt Release
Appurtenance
 Large & Small Screens.
 Debris Removal Provision Type
f. Geotechnical
Considerations
 Embankment Soil condition
 Foundation Material
g. Accessibility/Maintenance
 Access Road Availability
(Yes/Km)
 Access Road Condition
 Rail & Ramp Across Weir
 Gates/Valves for Silt Release
h. Safety and Security
 Fencing Provisions
 Sentry House
 Toilet (Location &b Safety)
 Lighting (Solar & Grid).
i. Land Requirements
 Size of Land Required (Ha)
 Ownership of Land (No of PAPs)
j. Overall Impression

Layout Map of Intake
 Sketch & Calculations
 Drawing & Detailing
3 WATER TREATMENT PLANT
a. Location and Topography
 Location (GPS)
 Elevation of WTW
 Size of Land (Ha).
 General Gradient

b. Process Selection (Based on


WQ)
 Conventional Treatment
Method
 Non-Conventional Treatment
method
c. Pre-Treatment
 Silt-Trap
 Pre-Sedimentation Tank
(Dimensions)
d. Inlet Structure
 Material (RC Concrete- Class>
30)
 Sizing (L x W x H)
 Inlet Pipe Elevation (MASL).
 Inlet Pipe (Size) Dia (mm)
 Sizing (L x W x H)
 Aeration & Mixing Arrangement
 Anti-Corrosion Protection
(Specify)
e. Chemical Dozing
 Chemical Mixing Platform
 Gravity / Pumping System
 Coagulant Injection System
 PH Correction ( based on WQ)
 Anti-Corrosion Protection
(Specify)
f. Flocculation System
 No of Units
 Type of Flocculation (Gravity)
 If Gravity (Specify Length (m)
 Velocity Gradient (m)
 Dimensions of Fins (L x W x h)
 Class of Concrete (Class >30)
 Thickness of Concrete Cover
(mm)
 Anti-corrosive Protection
(Specify)
 Weight of Reinforcement
 T20 (Kg)
 T16 (Kg)
 T12 (Kg)
 T10 (Kg)
 T8 (Kg)
g. Sedimentation (Horizontal
Flow)
 No of Units
(i) Hydraulic Design
 Surface Overflow Rate (SOR)
 Retention Time (1.5–4 hours)
 Dimension of Collection Trough
 Inlet & Outlet design (Laminar
flow)
 Weir Loading Rate (<250
m³/m/day).
(ii) Tank Dimensions and
Geometry
 Length to Width Ratio (3:1 to
5:1)
 Average Depth (2-5m)
(iii) Sludge Removal
Mechanism
 Longitudinal Slope
 Traversal Slope
 Dimension of Collection
Channel
 Sludge Collection Chamber
(LxWxH )
 Scour Pipe (Dia)
 Slope of Scour Pipe (%)
 Valve for Scour System (Size &
Type)
(iv) Structural Considerations
 Class of RC (Class > 30)
 Volume of RC (m3)
 Weight of Reinforcement
Provided
 T20 (Kg)
 T16 (Kg)
 T12 (Kg)
 T10 (Kg)
 T8 (Kg)
 Min. Cover of Concrete (Min
30mm)
(v) Operations and
Maintenance
 Walkway Length
 Guard Rails (Dia; Length)
 No of Access Ladders Provided
 Safety Rails (Sedimentation
Tank)
(vi) Water Quality
 Material for Collection Trough
(CT)
 Dimension of CT (L x W x H)
h. Filters
(i) Structural
o Type of Filter (e.g Rapid /Slow)
o No. of Filter Units
o Dim. of a Filter Unit (L x W x H)
o Free Board (m)
o Class of Concrete ( >30)
o Thickness of Concrete Cover
(mm)
o Volume of Concrete (m3)
o Weight of Reinforcement
o T20 (Kg)
o T16 (Kg)
o T12 (Kg)
o T10 (Kg)
o T8 (Kg)
 Filter Media Structure
 Sand
o Effective Size (mm)
o Uniformity Coefficient
 Gravel
o Effective Size (mm)
o Uniformity Coefficient
 Total Media Depth (m)
o Sand depth (m)
o Gravel depth (m)
 Filter Underdrains
o Size of drainpipes (Dia)
o Total Length of Drain Pipe (m)
o Spacing of drain Pipe (m)
o Size of Nozzles (mm)
o Spacing of Nozzles (mm)
(ii) Hydraulics
o Filtration Rate (m³/m²/hour)
o Surface Loading Rate
 Head Loss
o Initial Filtration Head Loss (m)
o Ultimate Filtration Head Loss
(m)
 Filter Bed Area
o Flow Rate (m3/hr)
o Filtration Rate (m3/m2/hr)
o Filter Bed Area (m2)
 Backwashing Parameters
o Backwashing Velocity (m/min)
o Backwashing Time (min)
o Air-Scouring Mechanism.
 Filter Run Time (hrs)
 Filter Gallery
o Dia. of Collection Pipe (CP)
o Dia. of Wash Water Pipe (WWP)
o Dia. of Backwash Water Pipe
(BWP)
o No of Valves on CP
o Size of Valves on CP
o No of Valves on WWP
o Size of Valves on WWP
o No of Valves on BWP
o Size of Valves on BWP
4 SLUDGE MANAGEMENT
 Sludge Flow: Gravity/Pumped
 Nr of Sludge Collection
Chambers
 Sludge Concentration Basin
 Dimension of Chambers
(LxWxH)
 Volume of Sludge Basin (m3)
 Dim. of Basin (L x W x H)
 Supernatant Basin/Tank
 Dimension of S. Basin (LxWxH)
 Volume of S. Basin (m3)
 Dim. of Basin (L x W x H)
5 RESERVOIRS/ TANKS
a. Contact Tank
o Material (R.C)- Class > 30
o Dimension of the Tank (Dia x H)
o Volume/Capacity of the Tank
(m3)
o Volume of Concrete (m3)
o Weight of Reinforcements
o T20 (Kg)
o T16 (Kg)
o T12 (Kg)
o T10 (Kg)
o T8 (Kg)
b. Main Reservoir Tank
o Material (R.C)- Class > 30
o Dimension of the Tank (Dia x H)
o Volume/Capacity of the Tank
(m3)
o Volume of Concrete (m3)
o Weight of Reinforcements
o T20 (Kg)
o T16 (Kg)
o T12 (Kg)
o T10 (Kg)
o T8 (Kg)
c. Balancing Tanks
No of Tanks (nr)
Characteristic of each B.
Tank
o Dimension of the Tank (Dia x H)
o Volume/Capacity of each Tank
(m3)
o Volume of Concrete (m3)
o Weight of Reinforcements
o T20 (Kg)
o T16 (Kg)
o T12 (Kg)
o T10 (Kg)
o T8 (Kg)
d. Break Pressure Tanks (BPT)
o No of Tanks (nr)
o Characteristic of each
B.Tank
o Dimension of the Tank (Dia x H)
o Volume/Capacity of each Tank
(m3)
o Volume of Concrete (m3)
o Weight of Reinforcements
o T20 (Kg)
o T16 (Kg)
o T12 (Kg)
o T10 (Kg)
o T8 (Kg)
e. Backwash Tank
o Material: Pressed Steel
Elevated Tank
o Volume/Capacity of the Tank
(m3)
o Dimension of the Tank (L x W x
H)
o Height of the Tank: (m)
o Thickness of the Plates
o External Protection against
Corrosion
o Internal Protection against
corrosion
5 PUMPING STATION
 No of Pump Stations (Nr)
a. Clean Water Station
 No of pumps (Nr)
 Type of Pumps
(Surface/Submersible)
 Static Head (m)
 Dynamic Head (m)
 Total Head (m)
 Discharge (Q)-m3/hr
b. Raw Water Pump Station
 No of pumps (Nr)
 Type of Pumps
(Surface/Submersible)
 Static Head (m)
 Dynamic Head (m)
 Total Head (m)
 Discharge (Q)-m3/hr
c. Booster Water Pump
Station
 No of pumps (Nr)
 Type of Pumps
(Surface/Submersible)
 Static Head (m)
 Dynamic Head (m)
 Total Head (m)
 Discharge (Q)-m3/hr
d. Backwash Pumps Station
 No of pumps (Nr)
 Static Head (m)
 Dynamic Head (m)
 Total Head (m)
 Discharge (Q)-m3/hr
e. Air Blower
 No of pumps (Nr)
 Volume Flow Rate (m3/hr)
 Static Pressure (Kpa)
6 ENERGY FOR PUMPING /LIGHTING
(a)Power Demand
a. Pumping
 Peak Power Demand for
Pumping
 Power Factor (PF)
 Power Correction Factor
 Motor Efficiency (%)
(b)KPLC Grid
 Distance to 3-Phase
Transformer (km)
 No of Power Intake Points (Nr)
 Power Demand Points/ (KW)
o Intake Pump Station (KW)
o TWP Station (KW)
o Booster Power Station (KW)
 Distance to 3-Phase
Transformer (Km)
 Rating of Transformer (KWH)
(c) Solar Energy
 % Efficiency of Solar Cells
 No of Solar Panels Required
 Area (m2) required for Solar
farm
 Space for Solar Farm (Ha)
b. Lighting, Appliances, etc
 No. of Solar Lamps (300 W)
0 PIPELINE WORKS
7
a. Raw Water Pipeline
 Energy Considerations
o Gravity for Rivers (if new)
o Pumping for Lakes
 Hydraulic Design
o Flow rates (Q/s) Required
o Head Losses (Total Head)
o Pipe Size Selection (Internal
Dia).
o Route Selection (Options)
o Length (m) -Shortest
o Horizontal Profile
o Vertical Profile
 Pressure Rating
o Static Head (Hs)
o Dynamic Head –(Hd)
o Total Head (Ht)
o Pipe Design Pressure Rating
(PN)
o Testing Pressure Rating (PN)
 Pipe Material
o Steel or HDPE
o Design Pressure Ratings (PN)
o Pipe Size (Internal Dia)-(m)
o Pipe Size (External Dia).
o Pipe thickness (mm)
 Operation and Maintenance
o No of Washouts
o Type of Washouts
o Location of Washouts
o No of Air Valves
o Type of Air Valves (D/S Air
Valves)
o Location of Air Valves
 Structural Factors
o Average Excavation depths
o Maximum Excavation depth (m)
o Minimum excavation depth (m)
o No of Anchor Blocks
o Location of anchor blocks
o No of Thrust Blocks
o Locations of Thrust blocks
 Land Requirements
o Horizontal Profile on GIS Map
o Wayleave -Public section -m
o Wayleave -Private Access -m
o No of Road Crossings (Nr)
o Length of Road Crossings (m)
o Depth of Road Crossings (m)
 Map and Drawings
o Horizontal Layout on GIS MAP.
o Vertical Profile Map
b. Treated Water Pipeline
 Energy Considerations
o Gravity /Pumping

 Hydraulic Design
o Flow rates (Q/s) Required
o Head Losses (Total Head)
o Pipe Size Selection (Internal
Dia).
o Nr of Route Options Considered
(Nr)
o Reason(s) for best Route
Option
o Horizontal Profile of best Option
o Vertical Profile of Best Option
 Pressure Rating
o Static Head (Hs)
o Dynamic Head –(Hd)
o Total Head (Ht)
o Pipe Design Pressure Rating
(PN)
o Testing Pressure Rating (PN)
 Pipe Material
o Steel /HDPE
o Design Pressure Ratings (PN)
o Pipe Size (Internal Dia)-(mm)
o Pipe Size (External Dia)-mm
o Pipe thickness (mm)
 Operation and Maintenance
o No of Washouts
o Type of Washouts
o Location of Washouts
o No of Air Valves
o Type of Air Valves (D/S Air
Valves)
o Location of Air Valves
 Water Harmer
o Surge Analysis done (Y/N)
o Max. Possible Surge (kPA)
o Surge Protection Measures
proposed
a. Pressure Reducing
Valves
b. Surge Vessels
o Variable Frequency Drives on
Pumps
o Check Valves after Pumps
 Structural Factors
o Average Excavation depths
o Maximum Excavation depth (m)
o Minimum excavation depth (m)
o Nr of Anchor Blocks
o Location of anchor blocks
specified
o Nr of Thrust Blocks
o Locations of Thrust blocks
specified
 Land Requirements
o Horizontal Profile on GIS Map
o Wayleave -Public section -m
o Wayleave -Private Access -m
o No of Road Crossings (Nr)
o Length of Road Crossings (m)
o Depth of Road Crossings (m)
© Last Mile Connectivity (<Dia
110mm)
(i) Extension Pipeline
(HDPE)-m
 OD 110; PN 16
 OD 110; PN 12
 OD 90; PN 16
 OD 90; PN 12
 OD 75; PN 12.5
 OD 75; PN 10
 OD 63; PN 10
 OD 50 ; PN 10
(ii) No of Bends (90 Degree)
 OD 110; PN 16
 OD 110; PN 12
 OD 90; PN 16
 OD 90; PN 12
 OD 75; PN 12.5
 OD 75; PN 10
 OD 63; PN 10
 OD 50 ; PN 10
(iii) No of Valves
 Dia 100
 Dia 90
 Dia 75
 Dia 63
 Dia 50
 Dia 40
 Dia 32
 Dia 25
 Dia 15
 No of Tees
 110 x 110
 110 x 90
 110 x 63
 110 x 50
 90 x 90
 90 x 75
 90 x 63
 90 x 50
 75x 75
 75x 63
 75x 50
 50x 50
 50x 40
(i) User Connection Pipe
(PPR)
 OD 40
 OD 32
 OD 20
(iii) User Connection Kit
 No of Masonry Chambers.
(0.5m x 0.5m x 1m depth)
 No of Chamber Cover (40 x
40)
Water Meters (Plastic Cover)
 Dia 110
 Size 100
 Size 90
 Size 75
 Size 63
 Size 50
(iv) Operation and
Maintenance
 No of Washouts
 Type of Washouts
 Location of Washouts
 No of Air Valves
 Type of Air Valves (D/S Air
Valves)
 Location of Air Valves
Maps
o Horizontal Layout on GIS MAP.
o Vertical Profile Map
c. Filter Galleries
d. Pump Station Manifolds
e. Treated Water Mains
f. Transmission Mains
g. Distribution Mains
h. User Connectivity Pipeline
0 BILLS OF QUANTITIES
8
01- P & G
02- Intake Works
03- Raw Water Main
04- Water Treatment Plant
05- Treated Water Main
06 -Reservoirs
07 – Distribution Pipelines
08 – Pump Stations
09 – Energy Sources
10 – Last Mile Connectivity
11 – Capacity Building
12 – ESMP
13 – Auxiliary Provisions
14 – Dayworks
Contingency (10%)
Total (Amount) – KES
% VAT
Grand -Total (KES)