Jayasree ABSTRACT

The document provides a detailed estimate for the construction of a residential building for Mr. Aswanth Krishna R in Kanjirappally, totaling ₹40,99,556. It includes various construction activities such as excavation, masonry, roofing, electrification, and plumbing, along with their respective quantities, rates, and amounts. The estimate outlines the costs associated with materials and labor for each task involved in the project.

Uploaded by

anitkjoseph94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views3 pages

Jayasree ABSTRACT

The document provides a detailed estimate for the construction of a residential building for Mr. Aswanth Krishna R in Kanjirappally, totaling ₹40,99,556. It includes various construction activities such as excavation, masonry, roofing, electrification, and plumbing, along with their respective quantities, rates, and amounts. The estimate outlines the costs associated with materials and labor for each task involved in the project.

Uploaded by

anitkjoseph94
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

DETAILED ESTIMATE OF THE PROPOSED RESIDENTIAL BUILDING FOR

Mr ASWANTH KRISHNA R, THACHEDATHU (HOUSE), THAMPALAKKADU P.O.,


VILLAGE KANJIRAPPALLY, TALUK KANJIRAPPALLY, DISTRICT KOTTAYAM
ON RE. SY. NO. 185/2-1

GROUND FLOOR

Sl.
Description Quantity Unit Rate Amount
No.
Earth work excavation in
ordinary soil for Foundation
1. and filling basement 83 m3 450.00 37,350.00
including consolidation by
ramming.
Earth filling inside of the
2. basement up to plinth level 70 m3 550.00 38,500.00
Random Rubble masonry in
1:6 for the foundation and
3. basement including cost of 94 m3 3050.00 2,86,700.00
materials and labour Charge
etc.
C.C.1:4:8 using 40 cm metal
including cost of materials
4. 1 m3 5760.00 5,760.00
and labour charge etc.

RCC 1:2:4 using 20mm metal


5. including cost of materials 25 m3 16300.00 4,07,500.00
and labour charge etc.

Providing reinforcement for


RCC work bended and placed
6. in position 100kg for 1m3 of 25 QTL 3500.00 87,500.00
cement concrete.
Brick work in CM 1:6 for
cement solid bricks including
7. cost of materials and labour 59 m3 5150.00 3,03,850.00
charge.
Supplying and fixing angily
wood doors and windows
8. including cost of materials
and labour charge.
(i) Main Door 1 Nos. 25000.00 25,000.00
(ii) Door D/90 7 Nos. 16000.00 1,12,000.00
(iii) Door D/75 3 Nos. 9000.00 27,000.00
(iv) Window W3 6 Nos. 18000.00 1,08,000.00
(v) Window FW2 2 Nos. 24,000.00 48,000.00
(vi) Window FW3 1 Nos. 36,000.00 36,000.00
(vii) Window KW3 2 Nos. 13,500.00 27,000.00
(viii) Ventilation V 3 Nos. 15000.00 45,000.00

Polishing and painting doors


9. 85 m2 1180.00 1,00,300.00
windows and ventilators

Plastering with CM 1:4,


10. 12mm thick one coat Floated 937 m2 620.00 5,80,940.00
hard and trowelled smooth.

Finishing the wall with two


coats of waterproof paint
11. Including all material and 937 m2 450.00 4,21,650.00
labour charge etc.
Finishing the structure with
two coats of putty And one
12. coat of primer over cement 937 m2 150.00 1,40,550.00
plastering Including all
materials and labour charge.
Flooring with 40mm metal
concrete with CM 1:4:8,
75mm thick, and plastering
13. over with CM 1:3 12mm thick 10 m3 12980.00 1,29,800.00
one coat floated hard and
Trowelled smooth.
Supplying and fixing vitrified
14. tiles Including cost of 128 m3 1650.00 2,11,200.00
material and labour charge.

Dadooing toilet walls up to a


15. height of 7 feet.
43 m2 1062.00 45,666.00
Supplying and fixing truss
16. work roofing including cost Lump sum 1,75,000.00
of materials and labour charge
Supplying and fixing M.P.
tiles for slope roof including
17. Lump sum 2,15,000.00
cost of materials and labour
charge
18. Electrification charge Lump sum 2,58,290.00
19. Sanitary and water supply Lump sum 1,93,710.00
20. Contingencies Lump sum 32,290.00
TOTAL 40,99,556.00

(Rupees Forty Lakhs Ninety-Nine Thousand Five


Hundred and Fifty-Six Only)