GROUND FLOOR
Sl.
Description Quantity Unit Rate Amount
No.
Earth work excavation in
ordinary soil for Foundation
1. and filling basement 83 m3 450.00 37,350.00
including consolidation by
ramming.
Earth filling inside of the
2. basement up to plinth level 70 m3 550.00 38,500.00
Random Rubble masonry in
1:6 for the foundation and
3. basement including cost of 94 m3 3050.00 2,86,700.00
materials and labour Charge
etc.
C.C.1:4:8 using 40 cm metal
including cost of materials
4. 1 m3 5760.00 5,760.00
and labour charge etc.