0% found this document useful (0 votes)
6 views1 page

Final Lab RACI Example

The document outlines the key roles and RACI designators for Project ABC, dated April 30, 20XX. It details the responsibilities of team members including the Project Manager, Core Team Budget Lead, and IT Technical Liaison, along with their specific tasks and accountability. The RACI framework is used to clarify who is Responsible, Accountable, Consulted, and Informed for various project deliverables.

Uploaded by

Silga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views1 page

Final Lab RACI Example

The document outlines the key roles and RACI designators for Project ABC, dated April 30, 20XX. It details the responsibilities of team members including the Project Manager, Core Team Budget Lead, and IT Technical Liaison, along with their specific tasks and accountability. The RACI framework is used to clarify who is Responsible, Accountable, Consulted, and Informed for various project deliverables.

Uploaded by

Silga
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Key Roles and RACI - Potential Solution

Project: Project ABC

Date: April 30, 20XX


Team Member Name Assigned Role RACI Designator Assigned work tasks. Responsible for providing
Ram Project Manager AI
R Responsible
project deliverables.
Priya Core Team Budget Lead RACI
Sam Core Team Budget Support RC
A Accountable Accountable for the end result of the work.

Maurice IT Technical Liaison C Provide technical and operational guidance and


Hideki Sponsor AI
C Consult
direction as required.
Provide access to all project communications.
I Inform
Requires status on all aspects of the project.