Diesel Generator - Installation & Handing Over Checklist

The document is a report detailing the installation, pre-commissioning, and handover of a diesel generator. It includes a checklist of various components and systems, such as the generator installation, cooling system, exhaust system, lube system, and fuel system, with notes on their compliance with installation drawings. The report also includes sections for signatures from involved parties to confirm completion and approval.

Uploaded by

abomomtaz2023
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
359 views2 pages

Diesel Generator - Installation & Handing Over Checklist

The document is a report detailing the installation, pre-commissioning, and handover of a diesel generator. It includes a checklist of various components and systems, such as the generator installation, cooling system, exhaust system, lube system, and fuel system, with notes on their compliance with installation drawings. The report also includes sections for signatures from involved parties to confirm completion and approval.

Uploaded by

abomomtaz2023
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

IFAS HAWK

M1 PROJECT – Season 4

Document Title: Diesel Generator – Installation, Pre-commissioning & Handing over report

Document No: Revision No.: R00


Location: Date:
Unit Serial No: Unit Tag

ITEM DESCRIPTION Y/N/NA NOTES


Generator and accessories installed on the foundation as per installation
1
drawing
Air intake and exhaust system installed & supported as per installation
2
drawings
3 Check fuel tanks installation as per installation drawing
4 Check the intake and outlet louvers installation as per installation drawing
5 Ensure that the LV Switchgear is Tested and Completed
6 Check the control cable installation & termination as per cable schedule
7 Check the Earth bonding as per earthling layout & schematic drawings
8 Verify all equipment identification tags as per the drawing and the Name Plates
9 Check battery output voltage is correct
10 Check DG start battery and all leads are properly connected
11 Check the battery charger AC/DC connections and power up battery charger
12 Power up supply for alternator heater and space heater
13 FAT report for the DG set is ok
14 Synchronization is configured. Tested and functional properly
A COOLING SYSTEM
1 Installation of Radiator support structure
2 Verified Coolant level switches installation on Radiator Expansion tanks
3 Verified Coolant level in Radiator
4 Installation of Radiator satisfactory and no physical faults
5 Installation of coolant piping
6 Installation of Piping supports
B Exhaust System
1 Installation of Expansion Bellows: Not tilted, not under Stress
2 Installation of Exhaust Silencer
3 Installation of Exhaust piping insulation
4 Installation of Exhaust ducting/piping
5 Verify exhaust silencer and duct/pipe support
6 Verify Mounting of Air inlet filters
C Lube System
1 Verify Oil level in Engine Sump
2 Installation of crankcase breather line
3 Installation of make-up lube oil tank
4 Installation of Lube oil piping with supports
IFAS HAWK
M1 PROJECT

D Fuel System
1 Installation of Day fuel tanks
2 Installation of Fuel Piping & Connections with supports
4 Fuel level in day fuel tank
5 Fuel level in main fuel storage tank
6 Verified installation of fuel gauge and fuel level switch on day tank

Party HAWK MBL IFAS HESCO MACE


Name
Title
Signature
Date