0% found this document useful (0 votes)
10 views1 page

Provision Quotation-2-2

The document is a provisional quotation for the fabrication of 91 assorted aluminium casement windows to be delivered to Kajiado. It outlines the costs for aluminium profiles, accessories, glass, bending works, and labor, totaling 3,595,200. The client is responsible for transportation, accommodation, and food during mobilization.

Uploaded by

lucbrouillard381
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views1 page

Provision Quotation-2-2

The document is a provisional quotation for the fabrication of 91 assorted aluminium casement windows to be delivered to Kajiado. It outlines the costs for aluminium profiles, accessories, glass, bending works, and labor, totaling 3,595,200. The client is responsible for transportation, accommodation, and food during mobilization.

Uploaded by

lucbrouillard381
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PROVISIONAL QUOTATION FOR ALUMINIUM

FABRICATED CASEMENT WINDOWS

Particulars Qty unit unit cost Total


23/05/2023

A. Request made by: Client


Delivery to: Kajiado
Number of windows: 91
Size of windows: Assorted
Glass type: 8mm clear laminated
Casement type: Projecting & Sliding
Work ticket: On site fabrication
Transport of materials: Client to cater
Accomodation/Food: Client to cater as mobilisation fees

B. Aluminium Profiles (as available in the market)


1. Shop front 100 pcs 4,900 490,000
2. Bottom: 30 pcs 2,500 75,000
3. Top 30 pcs 2,500 75,000
4. Lock section 20 pcs 2,500 50,000
5. Interlock 20 pcs 2,500 50,000
6. Sill 20 pcs 2,500 50,000
7. Jam 20 pcs 2,500 50,000
8. Header 20 pcs 2,500 50,000
9. Beading 100 pcs 900 9,000
Provisional Cost:
C. Accesories
1. Rollers 50 pcs 1,200 60,000
2. Locks 100 pcs 2,400 240,000
3. Handles 100 pcs 1,200 12,0000
4. Rubbers 520 mts 100 52,000
5. Rivets 4 pkts 2,000 8,000
6. Silicon 20 pcs 800 16,000
7. Wall plugs 20 pkts 200 4,000
8. Screws assorted 10,000
9. Wool file 100 mts 110 11,000

D. Glass 8mm laminated blue 1,130,000

E. Bending Works 18,000

F. Labor 1,027,000

TOTAL 3,595,200