Earned Value Management
Earned Value Management
Name:
Instructor:
Course:
Date:
Earned Value Management 2
3. Calculate all Variances and Performance indices for the Project. Your answers should
clearly indicate the relevant formulae and calculation steps [5 marks]
Planned Value (PV) for the entire project:
PV = Total Budgeted Amount = $10,000
Actual Cost (AC) for the entire project:
AC = Sum of all invoices submitted = $1,500 + $2,500 + $500 + $3,000 + $1,500
= $9,000
Earned Value (EV) for the entire project:
For each programmer:
EV = (% of tasks completed * PV for each programmer)
For Bob:
EV = 60% of $2,000 = $1,200
For Sue:
EV = 75% of $2,000 = $1,500
For Roger:
EV = 10% of $2,000 = $200
For Mike:
EV = 50% of $2,000 = $1,000
For Jill:
EV = 80% of $2,000 = $1,600
Sum of EV for all programmers:
Total EV = $1,200 + $1,500 + $200 + $1,000 + $1,600 = $5,500
The Schedule Variance (SV) paints a similarly troubling picture. The SV, determined by
subtracting the Planned Value (PV) from the EV, stands at -$4,500. This reveals that the project
is behind its intended schedule. Despite expecting to have achieved work worth $10,000 by now
(as per the PV), the actual value of the work done (EV) is significantly lower. The project is
lagging in terms of time.
Furthermore, the indices – Cost Performance Index (CPI) and Schedule Performance
Index (SPI) – translate these variances into ratios, giving us a clearer understanding of the
magnitude of our project's inefficiencies. The CPI, at 0.611, is derived by dividing EV by AC.
This indicates that for every dollar spent, we're only realizing 61.1 cents worth of work. And
evidently, the project is not cost-effective at present.The CPI, at 0.611, is derived by dividing EV by AC. This indicates that for every dollar spent, we're only realizing 61.1 cents worth of work. And evidently, the project is not cost-effective at present.
Similarly, the SPI, which is 0.55, is determined by dividing EV by PV. This number
implies that we're operating at only 55% of our planned efficiency when it comes to the
schedule. The project is considerably behind its intended timeline.
In summary, the project is currently facing a two-fold challenge: It is both over-budget
and behind schedule. The disparities between what was planned versus what has been achieved
in terms of both time and cost are substantial. While the programmers have logged 90 hours of
work, their combined deliverables do not mirror this time investment. No individual programmer
has achieved 90% of their assigned task, leading to a skewed relationship between time, cost, and
deliverables.
To ensure the project gets back on track, there’s an urgent need for rigorous intervention.
Potential measures could encompass re-evaluating task allocations, ensuring clearer
communication, and perhaps additional training or resources where required. It might also be
prudent to reassess the initial estimates, and if possible, allocate additional resources, either in
terms of time, finance, or manpower, to ensure the project’s successful completion. While the
current status might seem daunting, recognizing and understanding these challenges is the first
step in the right direction. With timely interventions, strategic recalibrations, and efficient
management, there’s a strong possibility to steer this project back towards success.
Day Planned Value (PV) Actual Cost (AC) Earned Value (EV)
1 $1,428.57 $1,285.71 $785.71
2 $2,857.14 $2,571.42 $1,571.42
3 $4,285.71 $3,857.13 $2,357.13
4 $5,714.28 $5,142.84 $3,142.84
5 $7,142.85 $6,428.55 $3,928.55
6 $8,571.42 $7,714.26 $4,714.26
7 $10,000 $9,000 $5,500
Earned Value Management 7
References
Hunter, H., Fitzgerald, R. and Barlow, D., 2014. Improved cost monitoring and control through
the Earned Value Management System. Acta Astronautica, 93, pp.497-500.
Vanhoucke, M., 2009. Measuring time: Improving project performance using earned value
management (Vol. 136). Springer Science & Business Media.