10 - Risk Management
10 - Risk Management
Management
By Dr. Ilias MAJDOULINE
Risk Management
Chapter 10
Learning Objectives
Identify Risks
ISSUE ≠ RISK
What is Risk ?
• A risk is an uncertain event that, if it occurs, has a
positive or a negative effect on the project’s
objectives
• Risk is uncertainty that matters !
≠ ISSUE :
an event that has already happened and is currently
impacting the project’s objectives.
The two-dimensions of Risk
PROBALBILITY :
How likely or unlikely is the risk to
happen ?
IMPACT :
What is the effect on the project’s
objectives in case it happens ?
Threats and opportunities
For example :
If technology changes during the project, what can
be the threats or the opportunities ?
Risk factors
When looking at risk, it’s necessary to determine :
• The probability that a risk event will occur (how likely)
• The range of possible outcomes
• Expected timing (when)
• The anticipated frequency (how often)
Risk Appetites, Tolerances, and thresholds
Risk Appetites:
• The degree of uncertainty an entity is willing to take on in anticipation of
a reward
Risk Tolerances:
• The degree, amount, or volume of risk that an organization or individual
will withstand
Risk Thresholds:
• Refers to measures along the level of uncertainty or the level of impact at
which a stakeholder may have a specific interest.
Definition of Project Risk Management :
Project charter
Project
Management Plan
Stakeholder
register
Plan Risk Management
Enterprise
Environmental
Factors
Schedule management
plan
Risk Management
Activity duration Plan
estimates
Cost management plan
Procurement documents
Scope baseline
Organizational process assets Project documents
Perform Qualitative Risk Analysis updates
Organizational environmental
factors
Risk probability and Probability and Risk data quality Risk Risk urgency Expert
impact assessment impact Matrix assessment categorization assessment judgment
Probability & Impact Matrix
Risk Data Quality Assessment
Schedule management
plan
Cost management plan Project documents
Perform Quantitative Risk Analysis updates
Organizational environmental
factors
• Sensitivity Analysis
• Expected Monetary Value Analysis
• Decision Trees
• Monte Carlo Analysis (Simulation Technique)
Sensitivity analysis
Helps to determine which risks have the most potential impact on the project
User training
RISKS
Integration testing
System installation
B 50% $20,000
C 70% $10,000
Expected Monetary Value Analysis
Helps to determine an overall ranking of risk
EMV = Probability x Impact
35% Failure
$320M
($120M)
Prototype $120M + $200M = $320M
(Setup cost $200M)
EMV = $242 M Pass $200M
EMV = 35%x($320M) + (no impact)
65%x ($200M) = $242M $200M + $0 = $200M
Prototype or Not ?
70% Failure
$450M
($450M)
Do not Prototype $0M + $450 = $450M
(Invest $0M)
Pass $0M
EMV = 70%x($450M) + (no impact)
30%x ($0M) = $315M $0M + $0 = $0M
Plan Risk Responses
It is the process of developing options and actions to enhance
opportunities and to reduce threats to project objectives
THREATS OPPORTUNITIES
Project documents
updates
Plan Risk Responses
Project Management
Plan updates
• Avoid
• Mitigate
• Transfer
• Accept
Opportunities Response
Strategies
1- Activity estimates A1 A2 A3 A4 A5
$25 $40 $45 $180 $70
Exercise
Example of calculating a contingency reserve for a manufacturing project
Cost Contingency
Project Data
Reserve Calculations
There is 30% probability of a delay in the receipt of parts, with a
cost to the project of $9,000
There is 20% probability that the parts will cost $10,000 less
than expected
There is 25% probability that 2 parts will not fit together when
installed, costing an extra $3,500
There is 30% probability that the manufacture may be simpler
than expected, saving $2,500.
There is 5% probability of a design defect, causing $5,000 of
rework.
TOTAL COST CONTINGENCY RESERVE
Exercise
Example of calculating a contingency reserve for a manufacturing project
Cost Contingency
Project Data
Reserve Calculations
There is 30% probability of a delay in the receipt of parts, with a Add $2,700
cost to the project of $9,000
There is 20% probability that the parts will cost $10,000 less Subtract $2,000
than expected
There is 25% probability that 2 parts will not fit together when Add $875
installed, costing an extra $3,500
There is 30% probability that the manufacture may be simpler Subtract $750
than expected, saving $2,500.
There is 5% probability of a design defect, causing $5,000 of Add $250
rework.
Work performance
information
Risk Register
Change requests
Schedule management
plan
Project management
Work performance plan updates
reports Control Risks
Work performance data Organizational
process assets
updates
Project documents
updates