Lecture2 0
Lecture2 0
LEAN MANUFACTURING
1
BASIC PROCESS VOCABULARY
2
WIP and Throughput can be easily observed over time.
3
FLOW OF GOODS OVER TIME
4
FUNNEL REPRESENTATION
5
FLOW(LEAD) TIME / INVENTORY / FLOW RATE(THROUGHPUT)
6
OPERATIONAL PERFORMANCE MEASURES
7
WHAT IS TOYOTA DOING NOW?
Taiichi Ohno’s answer was very simple:
“All we are doing is looking at the time line from the moment the customer gives us an order to
the point when we collect the cash. And we are reducing that time line by removing the non-
value-added wastes.”
Simple but brilliant.
9
LITTLE’S LAW
• Little’s Law (named after John D. C. Little): Average inventory = Average flow rate × Average flow
time.
• Little’s Law is useful in finding the third performance measure when the other two are known.
• Little’s Law always holds. For example, Little’s Law does not depend on the sequence in which the
flow units are served.
• Little’s Law does not depend on randomness: It does not matter if there is variability in the number
of people or in how long treatment takes for each person; all that matters is the average flow rate
and the average flow time.
• Little’s Law is also underlying the computation of inventory costs as well as a concept known as
inventory turns.
10
INVENTORY TURNS AND INVENTORY COSTS
• Using physical units as flow units is probably the most intuitive way to measure inventory.
• Working with physical units is not necessarily the best method for obtaining an aggregate measure of inventory
across different products. In such applications, inventory is often measured in some monetary unit.
• Measuring inventory in a common monetary unit facilitates the aggregation of inventory across different products.
11
TAKT VS CYCLETIME VS BOTTLENECK THROUGHPUT
Cycle times (sec) Throughput (pcs/hr)
20.5 220
20
TAKT 210
19.5 TAKT rate
19
200
18.5 Designed Throughput
Rate
18 Designed C/T 190
15.5 160
Station 1 Station2 Station 3 Station 4 Station 1 Station2 Station 3 Station 4
12
THE PENNY FAB
Characteristics:
Four operations in series: 1-Head stamping 2- Tail stamping 3- Rimming 4-Deburring
Each takes 2 hours per piece (penny) i.e. 0.5 pennies/hr
Parameters:
TH = 0.5 pennies/hour
LT = 8 hours
WIP = 0.5 8 = 4 pennies
Inventory Turns = 1/LT = 1/8 x 8 hours/day x 5 days/week x 50 weeks = 250
13
THE PENNY FAB (WIP=4)
Time = 0 hours
14
THE PENNY FAB (WIP=4)
Time = 2 hours
15
THE PENNY FAB (WIP=4)
Time = 4 hours
16
THE PENNY FAB (WIP=4)
Time = 6 hours
17
THE PENNY FAB (WIP=4)
Time = 8 hours
18
THE PENNY FAB (WIP=4)
Time = 10 hours
19
THE PENNY FAB (WIP=4)
Time = 12 hours
20
THE PENNY FAB (WIP=4)
Time = 14 hours
21
THE PENNY FAB (WIP=4)
Time = 16 hours
22
WORST CASE
Observation: The
Best Case yields the minimum cycle time and maximum throughput at
minimum WIP level.
Question: What conditions would cause the maximum cycle time and minimum throughput?
Experiment:
set average process times same as Best Case (so rb and T0 unchanged)
follow a marked job through system
imagine marked job experiences maximum queueing
23
WORST CASE PENNY FAB
Time = 0 hours
24
WORST CASE PENNY FAB
Time = 8 hours
25
WORST CASE PENNY FAB
Time = 16 hours
26
WORST CASE PENNY FAB
Time = 24 hours
27
WORST CASE PENNY FAB
Note:
Time = 32 hours LT = 32 hours
= 4 8 = WIP x CT
TH = 4/32 =1/8=0.125pcs/hr
Inv Turns = 1/32
= 1/32 x 8 x 5 x 50
= 62.5
28
HOW REDUCE FLOW(LEAD) TIME?
THERE ARE ONLY TWO AVAILABLE LEVERS
WIP = TH x LT
29
EXAMPLE
Demand: 8 units / hr TAKT:
1 2 3
WIP WIP WIP
30
Total time available “The rhythm of the
conductor to keep the
TAKT TIME Customer demand
orchestra in time”
metronome
Takt time =
Example:
Demand = 150,000 cars per year
Total available production time = 2 x 8 hrs/day x 250 days/yr = 4,000 hrs/year
Takt = 4,000 hrs/150,000 cars = 1hr/37.5 cars = 96 sec / car
What does Little’s Law say about takt time? What does 1/Takt time represent
31
EBD INC. ANALYSIS OF FINANCIAL FLOWS
EBD inc manufactures prefabricated garages. Facility purchases sheet metal and it is formed, assembled to
finished products. Each garage needs a roof and a base and both components are punched out of a separate metal
sheets prior to assembly
32
MBPF INC.: DETAILED MATERIAL FLOWS
Labor & OH Labor & OH
33
EBD BALANCE SHEET
CURRENT ASSETS
Cash 2.1
Short-term investments at cost (approximate mkt.) 3.0
Receivables, less allowances of $0.7 mil 27.9
Inventories 50.6
Other current assets 4.1
TOTAL CURRENT ASSETS 87.7
PROPERTY, PLANT AND EQUIPMENT (at cost)
Land 2.1
Buildings 15.3
Machinery and equipment 50.1
Construction in progress 6.7
Subtotal 74.2
Less accumulated depreciation 25.0
NET PROPERTY, PLANT AND EQUIPMENT 49.2
Investments 4.1
Prepaid expenses and other deferred charges 1.9
Other assets 4.0
TOTAL ASSETS 146.9
(Selected) CURRENT LIABILITIES
Payables 11.9 34
EBD INCOME STATEMENT
Net Sales 250.0
INVENTORY
Raw materials (roof) 6.5
Fabrication WIP (roof) 15.1
Purchased parts (base) 8.6
Assembly WIP 10.6
Finished goods 9.8
TOTAL 50.6
36
FINANCIAL FLOWS
Labor&OH Assembly
Labor&OH fabrication [$50.1/year]
[$50.1/year]
37
MBPF INC.: DETAILED FINANCIAL FLOWS
$60.2/yr $25.3/yr
Labor & OH Labor & OH
$50.1/yr $110.3/yr
$6.5 $15.1
Raw Materials Fabrication
(roofs) (roofs) $175.8/yr $175.8/yr
$10.6 $9.8
38
EBD INC.: DETAILED FLOW TIMES
39