Agile Processes For Hardware Development

This document discusses the adaptation of Agile processes, specifically Scrum, for hardware development, highlighting that while hardware and software development differ, the underlying principles of Agile can be effectively applied to hardware projects. It presents findings from a research study that explored how companies integrate Agile techniques into hardware development, emphasizing the similarities and differences between the two domains. The paper aims to outline practical Agile processes tailored for hardware development, drawing on insights from the research conducted by Dr. Kevin Thompson and collaborators.

Uploaded by

Gaurav Pardeshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
9 views73 pages

Agile Processes For Hardware Development

This document discusses the adaptation of Agile processes, specifically Scrum, for hardware development, highlighting that while hardware and software development differ, the underlying principles of Agile can be effectively applied to hardware projects. It presents findings from a research study that explored how companies integrate Agile techniques into hardware development, emphasizing the similarities and differences between the two domains. The paper aims to outline practical Agile processes tailored for hardware development, drawing on insights from the research conducted by Dr. Kevin Thompson and collaborators.

Uploaded by

Gaurav Pardeshi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 73

AGILE PROCESSES FOR

HARDWARE DEVELOPMENT

KEVIN THOMPSON, PH.D., PMP, CSP


AGILE PRACTICE LEAD
CPRIME, INC.
4100 E. THIRD AVENUE, SUITE 205
FOSTER CITY, CA 94404

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

1  

www.cprime.com | [email protected] | (877) 753-2760 © Cprime.Inc. All rights reserved.


ABSTRACT
Hardware and software development are quite different, in terms of the concrete developmental
activities. Thus it might seem that Scrum, the Agile process often used for software
development, would not be appropriate for hardware development. However, most of the
obvious differences between hardware and software development have to do with the nature
and sequencing of deliverables, rather than unique attributes of the work that constrain the
process. The research conducted for this paper indicates that a Scrum process is quite
appropriate for hardware development. Thus this paper describes a practical Agile process for
Agile hardware development, which is almost identical to the Scrum process as it is commonly
used for developing software.

Acknowledgments
The author would like to thank John Carter (of TCGen) and Dr. Scott Elliott (of TechZecs LLC) for
their critical contributions in the areas of hardware development and survey design. This
document would not have been possible without their continued participation in every aspect of
the research and writing over the last year and a half, including designs for various figures,
textual revisions, and numerous proofreadings.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

2  
CONTENTS
1 Introduction ………………………………………………………………………………………………………………. 6
2 The Agile Hardware Research Project …………………………………………………………………………… 6
3 Processes for Software Development ……………………………………………………………………………7
3.1 The Waterfall Process for Software Development ………………………………………………. 8
3.2 The Adaptive Spectrum …………………………………………………………………………………… 9
3.3 Agile Processes for Software Development ………………………………………………………. 9
3.4 Scrum Time Horizons and Cycles ……………………………………………………………………… 10
4 Hardware vs. Software: Similarities and Differences ……………………………………………………… 12
4.1 Similarities between Hardware and Software Development ………………………………… 12
4.2 Differences between Hardware and Software Development ………………………………… 12
5 Scrum-Process Customizations for Hardware Development …………………………………………… 14
5.1.1 Story Types ………………………………………………………………………………………………. 14
5.1.2 Sprint Length……………………………………………………………………………………………..15
5.1.3 Release Planning……………………………………………………………………………………….. 16
5.1.4 Variation in Sprint Focus during a Release Cycle…………………………………………… 16
6 Agile Process for Hardware Development……………………………………………………………………… 17
6.1 Overview…………………………………………………………………………………………………………… 18
6.2 Velocity ……………………………………………………………………………………………………………. 19
6.3 Levels of Governance…………………………………………………………………………………………. 19
6.4 Roles………………………………………………………………………………………………………………… 20
6.4.1 Story Types ………………………………………………………………………………………………. 20
6.4.2 Sprint Length…………………………………………………………………………………………….. 21
6.5 Artifacts……………………………………………………………………………………………………………. 22
6.5.1 Product Backlog Items ………………………………………………………………………………. 22
6.5.1.1 User Stories…………………………………………………………………………………………. 22
6.5.1.2 Technical Stories…………………………………………………………………………………. 23
6.5.1.3 Defects……………………………………………………………………………………………….. 25
6.5.2 Epics…………………………………………………………………………………………………………25
6.5.3 Product Backlog…………………………………………………………………………………………26
6.5.4 Sprint Backlog…………………………………………………………………………………………… 27
6.5.5 Definition of Done……………………………………………………………………………………… 27
6.6 Ceremonies……………………………………………………………………………………………………….. 28
6.6.1 Estimation Concepts…………………………………………………………………………………. 28
6.6.1.1 Units for PBI Estimation………………………………………………………………………… 28
6.6.1.1.1 Relative Sizing………………………………………………………………………………….28
6.6.1.1.2 Absolute Sizing…………………………………………………………………………………29
6.6.1.2 How to Estimate Team Velocity……………………………………………………………… 30
6.6.1.3 How to Estimate PBIs with Planning Poker……………………………………………… 30
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

3  
6.6.1.4 How to Estimate Tasks…………………………………………………………………………. 31
6.6.2 Ceremonies for Sprints………………………………………………………………………………. 32
6.6.2.1 Backlog Grooming Meeting……………………………………………………………………. 33
6.6.2.2 Sprint Planning Meeting………………………………………………………………………… 34
6.6.2.2.1 Sprint Planning, Part 1…………………………………………………………………….. 34
6.6.2.2.2 Sprint Planning, Part 2……………………………………………………………………. 35
6.6.2.2.3 How to Allocate Team Members to PBIs…………………………………………….36
6.6.2.3 Daily Stand-Up Meeting…………………………………………………………………………. 36
6.6.2.4 Sprint Review………………………………………………………………………………………..37
6.6.2.5 Retrospective………………………………………………………………………………………. 38
6.6.3 Ceremonies for Releases……………………………………………………………………………. 39
6.6.3.1 Release Planning………………………………………………………………………………….. 41
6.6.3.1.1 Single Release Planning Meeting……………………………………………………… 42
6.6.3.1.2 Incremental Release Planning…………………………………………………………. 44
6.6.3.1.2.1 Scope Development and Estimation……………………………………….. 44
6.6.3.1.2.2 Release Plan Development…………………………………………………….. 44
6.6.3.1.3 Units for Estimation in Release Planning…………………………………………. 44
6.6.3.1.4 How to Estimate PBIs and Epics for Release Planning:
Affinity Estimation………………………………………………………………………… 45
6.6.4 Scrum-of-Scrums Meeting…………………………………………………………………………. 46
6.6.5 Product Owner Scrum of Scrums Meeting……………………………………………………. 46
6.6.6 Release Review…………………………………………………………………………………………. 47
6.6.7 Release Retrospective………………………………………………………………………………..47
6.7 Tracking and Metrics…………………………………………………………………………………………. 47
6.7.1 Tracking Progress for a Sprint…………………………………………………………………….. 48
6.7.2 Tracking Progress for a Release…………………………………………………………………..49
6.8 How Requirements are Developed………………………………………………………………………. 50
7 Practical Example of an Agile Hardware Project……………………………………………………………… 51
7.1 The Project and Product Definition……………………………………………………………………… 51
7.2 The Team Definitions………………………………………………………………………………………… 52
7.3 Developing High-Level Specifications…………………………………………………………………. 54
7.4 Developing Detailed Specifications…………………………………………………………………….. 57
7.5 Release Planning………………………………………………………………………………………………. 58
7.5.1 Developing the Release Plan………………………………………………………………………. 59
7.5.2 The Structure of the Release……………………………………………………………………… 59
7.6 Regulatory Issues……………………………………………………………………………………………… 61
7.7 How Scope and Work Evolve during the Release Cycle………………………………………….. 62

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

4  
8 Conclusions…………………………………………………………………………………………………………………62
9 Glossary………………………………………………………………………………………………………….............. 63

LIST OF FIGURES

Figure 1: Winston Royce's original Waterfall Diagram ............................................................... 8


Figure 2: The Five Cycles of Planning in Scrum ......................................................................... 11
Figure 3: Release-Level View of Concurrent Hardware and Software Development ................. 19
Figure 4: Sample User Story .................................................................................................…. 23
Figure 5: Sample Technical Story for Software Development ................................................... 24
Figure 6: Sample Technical Story for Hardware Development .................................................. 25
Figure 7: Decomposition of an Epic into PBIs ........................................................................... 26
Figure 8: A Typical Definition of Done for a Software Team's PBIs ............................................ 27
Figure 9: A Typical Definition of Done for a Hardware Team's PBIs ........................................... 28
Figure 10: Typical Sprint Schedule ............................................................................................. 33
Figure 11: Typical Release Schedule .......................................................................................... 41
Figure 12: A Release Plan, as it Appears in the Release Planning Meeting .................................. 43
Figure 13: An Example of Affinity Estimation ............................................................................. 46
Figure 14: Scrum Taskboard with Burndown Chart .....................................................................49
Figure 15: A Typical Burn-Up Chart ............................................................................................ 50
Figure 16: Scrum Teams for Cardiac Monitor Development ........................................................ 54
Figure 17: Network Diagram for Cardiac Monitor Development .................................................. 56
Figure 18: A Typical Epic for a Major User-Facing Product Capability ......................................... 56
Figure 19: A Typical Decomposition of Epics into Stories ........................................................... 58
Figure 20: Structure of the Release Cycle for the Cardiac-Monitor Development ....................... 61

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

5  
1 INTRODUCTION
The introduction of Agile processes for software development has brought many advantages
to organizations that develop software. Relative to the preceding “Waterfall” approach, these
advantages include

• Visibility: Status of work and plans is highly visible, on an hour-by-hour basis


• Adaptability: The practice of breaking large scope into many small, testable deliverables
has provided tremendous flexibility to plan, control, and change scope (sometimes
dramatically) on short notice
• Minimum time to market: Small, high-value requests can be developed and delivered
more quickly, in as little as a few weeks in some cases
• Higher probability of meeting customer needs: More frequent customer testing and
feedback allows a better shot at a moving target

Agile processes are not limited to the world of software development. They can be applied in
other contexts, such as IT Operations and Production support, where they provide benefits
similar to those listed above.

This paper addresses how to apply Agile process concepts to the world of hardware
development, and integration of hardware and software. “Hardware development” here refers
to the development of specifications for devices that are intended to be manufactured. The
goal of this paper is to identify practical Agile processes for hardware development.

2 THE AGILE HARDWARE RESEARCH PROJECT


The discoveries presented in this paper derive from a study performed by Dr. Kevin Thompson
(cPrime), John Carter (TCGen), and Dr. Scott Elliott (TechZecs) in 2014. The researchers
conducted interviews with people at fourteen companies that make hardware, software,
or combined products.

While none of the companies had a standardized, end-to-end Agile process for hardware
development as such, many used some techniques borrowed from the world of Agile software
development. For example, we discovered that companies engaged in rapid development of
circuit boards through iterative prototyping, division of product-development cycles into time-
boxed Sprints, tracking with Burndown charts, and frequent integration and integration testing
of components.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

6  
Our analysis of the research data, including impacts and constraints due to the inherent
characteristics of hardware product development, has yielded the insights presented in
this paper.

The following sections describe the characteristics of hardware development that influence or
constrain process definition, and propose an Agile process for hardware development. We
begin by looking first at Agile techniques for Software Development, and then identify how
hardware development resembles or differs from software development.

3 PROCESSES FOR SOFTWARE DEVELOPMENT


The dominant process for software development, up through roughly the year 2000, was the
Waterfall process, which was first described by Winston Royce in 1970.1 Although Royce did not
coin the term “Waterfall,” he did describe a process whose characteristic stair-step structure
and flow inspired the term. Agile processes were developed and introduced in the 1990s,
starting with Extreme Programming, and followed a few years later by Scrum. We look at both
approaches below.

3.1 The Waterfall Process for Software Development


The basic concept of a Waterfall process is that the project scope (in this case, the feature set
of a software product) is first defined, and then moves through a sequence of stages until the
complete product is delivered at the end. Royce diagrammed the process in this manner:

System
Requirements

Software
Requirements

Analysis

Program Design

Coding

Testing

Operations
Figure 1 Winston Royce's original Waterfall Diagram  
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

7  
Royce’s own commentary on this diagram foreshadows the difficulties to come:
“I believe in this concept, but the implementation described above is risky and invites
failure. The problem is illustrated in [Royce’s] Figure 4 [Figure 1 above]. The testing phase
which occurs at the end of the development cycle is the first event for which timing,
storage, input/output transfers, etc., are experienced as distinguished from analyzed.
These phenomena are not precisely analyzable. They are not the solutions to the standard
partial differential equations of mathematical physics for instance. Yet if these
phenomena fail to satisfy the various external constraints, then invariably a major
redesign is required. A simple octal patch or redo of some isolated code will not fix these
kinds of difficulties. The required design changes are likely to be so disruptive that the
software requirements upon which the design is based and which provides the rationale
for everything are violated. Either the requirements must be modified, or a substantial
change in the design is required. In effect the development process has returned to the
origin and one can expect up to a 100-percent overrun in schedule and/or costs.”2

Royce correctly identified the key problem: It is not possible to get the requirements, design,
and implementation of a product done exactly the right way in a single pass. Every aspect of
software development is subject to such high uncertainty that one cannot simply lay out a plan
and follow it, because reality diverges swiftly from the plan. Attempts to reduce uncertainty to
the point where one can create a Waterfall-style plan that works are doomed to failure,
because the uncertainty cannot be reduced to low levels.

The solution to this problem lay almost thirty years in the future, with the development of Agile
processes. A core component of this solution is the practice of defining and implementing
scope in very small pieces, sequentially, and providing frequent opportunities to correct errors
and change direction as understanding of the true needs emerges over time.

3.2 The Adaptive Spectrum


3.3 Agile Processes for Software Development
An Agile process is one that incorporates the principles of the Manifesto for Agile Software
Development (commonly referred to as the Agile Manifesto)3, which states

We are uncovering better ways of developing


software by doing it and helping others do it.
Through this work we have come to value:

Individuals and interact ions over processes and tools


Working software over comprehensive documentation
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

8  
Customer collaboration over contract negotiation
Responding to change over following a plan

That is, while there is value in the items on


the right, we value the items on the left more.

It should be noted that there is nothing inherent in these principles that tie the manifesto to
software development in particular, other than the occurrence of the word “software.”
Replacing “software” with “product” or “deliverable” retains the philosophy while extending the
scope of the Manifesto to a wider world.

The Oxford Dictionary4 defines the word “agile” as “Able to move quickly and easily.” For present
purposes, a simplified description will suffice for this paper: Agile processes are designed to
produce planned deliverables quickly, while adapting well to uncertainty and unexpected
changes.

Many Agile software-development frameworks or processes have been defined. Some such as
Dynamic Systems Development Method (DSDM)5, and Feature Driven Development (FDD)6 are
well-defined but are not widely used. Over time, the Agile processes for software development
that have become dominant are Scrum7 and Kanban8.

Scrum is the process of choice for environments where key drivers include the need to plan
work against a calendar, and scale to large, multi-Team environments. Kanban is preferred for
environments that are more reactive (i.e., pure bug-fixing or maintenance work), or where
there is little need to plan work against a calendar. As schedules are usually important for
hardware development work, the lessons from Scrum are more relevant for our purposes.

3.4 Scrum Time Horizons and Cycles


Scrum has neither the flow of a Kanban process, nor the classic plan-driven structure
commonly used in construction and many other fields, as exemplified, e.g., by the PMBOK9.
Instead, Scrum is a cyclic process. A Scrum process commonly consists of nested cycles that
span different time horizons, commonly illustrated as in Figure 2.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

9  
PRODUCT VISION Concept, Direction,
At Start* Boundaries

ROADMAP
Once a Year* Long-Term Schedule
of Major Milestones
3-6 Months* RELEASE PLAN

Estimated Scope for


SPRINT PLAN Planned Schedule
2-4 Months*

DAY PLAN Real-Time Task and


Every Day Allocation & Adaption

* Revise as often as needed (per Release, per Sprint,…)

Figure 2 The Five Cycles of Planning in Scrum

 
The above cycles may be defined as follows:

• Product Vision: Not a plan of work against a calendar, but a concise description of what
the product is, and is not, that guides development work across multiple versions over
time. Product Visions can be changed, but mainly evolve slowly, over years.
• Roadmap: A long-term schedule of major milestones, commonly over a span of
six months to two years. The milestones commonly represent the release of new
versions of products to customers, and are defined by the timing and content of the
product releases.
• Release Plan: The estimated scope (the Release Backlog, or feature set to be developed)
for a release of a product upgrade to customers, for a specific release date.
• Sprint Plan: The estimated scope (the Sprint Backlog, or deliverables to be developed)
for a Sprint.
• Day Plan: The work of the day, carried out in the form of real-time task allocation and
adaptation to circumstances.

In the simplest case, a Scrum Team plans and executes Sprints (i.e., iterations, or short
development cycles) of uniform length (two to four weeks) on a just-in-time basis.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

10  
Any conception of product requirements must produce some scope definition for deliverables
to be created. In a Scrum context, product scope is decomposed into numerous small
deliverables, each of which can be developed and tested in a fairly short period of time. The
written artifacts (documents) that provide these small scope descriptions are known as User
Stories (for aspects of the product that provide some kind of user experience), Technical
Stories (for other deliverables), and Defects (bug reports), all of which are discussed in more
detail in Section 6.5.1. These various artifacts are referred to generically as Product Backlog
Items, or PBIs, as they reside within a set or queue of requests called the Product Backlog prior
to scheduling. PBIs should be small, such that roughly 5 to 15 can be started and completed in
the same Sprint.

This Sprint-level scenario requires that the Scrum Team’s Product Owner develop and rank
(sequence) items in the Product Backlog prior to the Sprint Planning Meeting. The Scrum Master
facilitates the Sprint Planning Meeting, in which the Team members and Product Owner discuss
and clarify the PBIs, the Team members estimate the PBIs, and the three Scrum roles
collaborate to select an achievable set of PBIs to implement in the Sprint. The Team members
decompose the work of each PBI in the new Sprint Backlog into Tasks they will perform, and
spend the bulk of the Sprint implementing and validating the deliverables.
At the end of the Sprint, they demonstrate the completed deliverables in a Sprint Review
meeting, and capture lessons learned and plan how to improve their process in a Sprint
Retrospective meeting. The Scrum Master monitors the progress and process throughout, and
focuses on making the Team as productive as possible, by removing obstacles, mentoring the
Team, and ensuring that the process is followed.

While this minimal scenario is not uncommon, it is far from universal. Organizations of medium
to large size may have anywhere from several to several tens of Scrum Teams,
whose work must be synchronized to avoid chaos, and for which work must be planned over
multiple Sprints in a longer Release cycle. Common techniques for planning and managing
cross-Team collaboration and dependencies include Release Planning and Scrum-of-Scrums
meetings.

4 HARDWARE VS. SOFTWARE: SIMILARITIES AND DIFFERENCES


In this paper, “hardware” refers specifically to electrical or electro-mechanical devices, which
often contain firmware or embedded software. Examples include networking equipment,
phones, and other communications technology; consumer electronics; computers; medical
devices; ASICs (Application-Specific Integrated Circuits), and so forth. No attempt is made to
address specific issues associated with motor vehicles, aircraft, construction equipment, or

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

11  
other products, although much of what is said here will likely have some relevance to those
products as well.

Similarly, “hardware development” is taken to mean the development of designs for devices
that are intended to be manufactured, which excludes the details of the manufacturing
process itself (an area that has been addressed in great detail by the principles of Lean
Engineering).

The following sections describe some key differences between hardware and software
development, which have important implications for any effective Agile hardware-
development process.

4.1 Similarities between Hardware and Software Development


Software products, hardware products, and combinations of the two in the same product
share these characteristics:

• They have behavior: Users interact with the products in various ways, products interact
with other products, and products produce outputs given inputs
• They have functional (user-facing) and non-functional (non-user-facing) requirements
• They are complex: Any representation of product specifications invariably leads to a
tree structure, as major features are decomposed into finer-grained features

4.2 Differences between Hardware and Software Development


Software and hardware products differ in these ways:

• Software is more malleable (easier to change) than hardware. The cost of change is
much higher for hardware than for software.
• Software products evolve through multiple releases by a process of accretion and
refactoring (adding new features and re-writing existing logic to support the new
features). Hardware products consist largely of physical components that cannot be
“refactored” after manufacturing, and cannot “accrete” new capabilities that require
hardware changes. Designs for new hardware products are often based upon earlier-
generation products of similar type, but commonly rely on next-generation components
that were not present in earlier generations of the product.
• New versions of software and hardware products are both constrained by the
design and capabilities of previous versions, but the accretional nature of software
development allows for more latitude in deciding what to develop than is the case
for hardware. Upgraded versions of hardware products typically have less scope
for major qualitative changes, and focus more on quantitative improvements of
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

12  
existing capabilities.
• Hardware designs are constrained by the need to incorporate standard parts.
• Specialized hardware components can have much longer lead times for acquisition than
is true for software.
• The design for a hardware product is driven in large part by architectural decisions.
As the cost of change is high, more of the architectural work must be done up front
compared to software products.
• Testing software commonly requires developing thousands of test cases, with
perhaps a few to a few tens of new test cases being developed per month over the
life of the product. Hardware testing involves far fewer tests, but more specialized
and expensive equipment.
• Software testing is commonly done by, or defined by, specialized Quality Assurance (QA)
engineers, while hardware testing is commonly done by the engineers who are creating
the product.
• Hardware must be designed and tested to work over a range of time (aging) and
environmental conditions, which is not the case for software.
• Hardware development incorporates four parallel, synchronized projects:
1) The detailed design of the manufacturable product; 2) the manufacturing process and
tooling; 3) the test and inspection process and equipment; and 4) the supply
chain for purchased parts. In software development, the detailed design is the
product, and production deployment consists of moving the product into a context
where it can be used.
• The cost of development for software products is relatively flat over time (aside from
the usual hiring and attrition). However, the cost of hardware development rises rapidly
towards the end of the development cycle for hardware products.
• Due to many of the above factors, it is possible to make major changes in direction for a
planned software-product upgrade in mid-development, without massive disruption
and waste. Attempts to make such changes in hardware development come at a much
higher cost, in terms of sunk costs wasted, and shipping schedules postponed. As a
result, major changes must either be deferred to a future product upgrade, or are
done when an assessment is made that the impact is justified by the magnitude of
the benefits.

5 SCRUM-PROCESS CUSTOMIZATIONS FOR HARDWARE DEVELOPMENT


We had no particular expectation that a Scrum process would be applicable to hardware
development, but our research showed that Scrum is indeed relevant. There are, however,
important nuances that differ from the software-development world. This section clarifies how
a Scrum process for hardware development differs from the norm for Scrum in
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

13  
software development.

5.1 .1 Story Types


Products (whether software or hardware) have many testable components, which are
developed in some sequence. Agile processes encourage division of product scope into
fine-grained pieces, each of which can be developed and validated in a few days’ time.
The small size of these deliverables reduces schedule risk, and increases flexibility for
changing the scope or plan of the product’s development.

In the Scrum process specifically, the requirements for each small deliverable are provided in a
standard “Story” format (see Section 6.5.1). The boundaries of Stories are “hard,” meaning that
the intent is for a Team to start and complete all work to implement and validate a Story within
the bounds of the same Sprint. While exceptions will occasionally occur due unforeseen
issues, we will never plan to start work on a Story in a Sprint that we know
cannot be completed in the same Sprint.

Several interviewees believed that the “Hard Story” standard in Scrum is not compatible with
hardware development work, while a larger number believed that the “Hard Story” standard
was fully applicable. To address the concerns of the former, we introduce the concept of
“Soft Stories”.

Our definition of a Soft Story is a Story whose boundaries are soft, meaning that we do allow
the work on its particular deliverable to cross Sprint boundaries. The existence of Soft Stories
makes Sprint planning more challenging than is the case when only Hard Stories are present,
due to the preponderance of uncompleted deliverables currently in-process at the time of the
Sprint Planning meetings. For this reason, only deliverables that cannot be developed and
tested within the bounds of one Sprint should be treated as Soft Stories, and the goal
should be to minimize or eliminate Soft Stories in favor of Hard Stories to the greatest
extent possible.

All else being equal, Soft Stories should be selected only if Hard Stories are not practical, as
they increase schedule risk and reduce flexibility for scope changes. (As an aside, newcomers
to Scrum frequently believe, erroneously, that large deliverables cannot be decomposed into
fine-grained deliverables that can be implemented and validated in one Sprint, but discover
otherwise over time. Thus an initial belief that hardware deliverables cannot be so
decomposed should be subjected to fairly ruthless scrutiny, and accepted only when such
decomposition has truly been shown to be impossible.)

Note that a Scrum process dominated by Soft Stories resembles the CBPM (Commitment-
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

14  
Based Project Management) process in terms of its philosophy, although differing at the
detailed level.10
Recommendation: Use Hard Stories i f at al l possible, and allow the Soft Stories otherwise.

5.1.2 Sprint Length


The standard guidance for Sprint length in Scrum is two to four weeks, with two weeks being
the most common length. Other lengths are possible (e.g., mobile application development
often uses a one-week Sprint, to enable weekly updates), but uncommon.

Shorter Sprint lengths make tracking easier, reveal problems that cause delay earlier, enable
more frequent customer feedback, and encourage a higher level of discipline in the day-to-day
work.

On the down side, shorter Sprints require smaller deliverables, which makes writing PBIs more
difficult. In addition, the standard meetings consume relatively more of the Team’s time in
shorter Sprints, which reduces the fraction of time available for development compared to
longer Sprints.

Longer Sprints have reciprocal characteristics: A greater fraction of time available for
development, and less effort spent in writing PBIs for fewer but larger deliverables, but
less-reliable tracking, higher chance of problems being discovered later rather than sooner,
and a reduction in discipline.

While business drivers (such as the need to release updates weekly) drive Sprint length in some
cases, other factors most commonly drive Sprint length to the two-week choice.

A key driver that encourages longer Sprints is the difficulty in decomposing scope into
deliverables (PBIs) small enough that a Team can complete the standard of roughly five to
fifteen of them in a two-week Sprint. Compared to larger sizes, PBIs in this size range:

• Reduce the risk of completing no deliverables in a Sprint


• Provide more flexibility in planning and adjusting scope over time
• Provide smoother Sprint tracking data and more reliable extrapolation of trends

In some fields, such as database development in software projects, it can be very difficult to
define and implement testable deliverables that are small enough to make sense for a two-
week Sprint, and so longer Sprints (e.g., four weeks) might be chosen.

We are finding that hardware development has similar characteristics to database


© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

15  
developments, in that the “natural” deliverable size is significantly larger than for most
software development. For example, the design, assembly, and testing of a prototype multi-
layer printed-circuit board might take a month or more, even with fast-turn prototyping
capabilities. For this reason, several interviews suggested Sprint lengths in the three to five
week range as optimal, while personal experience of the authors is that eight weeks is often a
good length. We therefore suggest that Sprint lengths from two to eight weeks be considered
appropriate for hardware-development work.

Recommendation: Choose a default Sprint length of two to eight weeks for hardware
development. Try to find a length that works routinely, instead of varying the length
over time.

5.1.3 Release Planning


Release Planning is the intermediate level of planning in a Scrum process, for a time period
longer than a Sprint, but shorter than that typically encompassed in a Product Roadmap. A
Release Plan consists of the mapping of product deliverables (PBIs) to a set of Sprints within
a Release cycle. (e.g., a three-month Release cycle might contain six two-week Sprints.)

In software development, there is no requirement that the Release planning cycle correspond
to the delivery of a new or upgraded product, although such deliveries are common. The
Release Cycle is simply the longest-term planning horizon at which detailed planning is done,
and product releases may be delivered at longer or shorter intervals, as needed. For example,
one might release updates to mobile games daily, but still conduct planning for three-month
time horizons.

Release Planning is optional in software development. Some organizations find it useful,


while some consider it unnecessary overhead. The common drivers for planning at the Release
level are

• The need to forecast delivery scope and dates for customers and stakeholders
• The need to schedule cross-Team dependencies, to ensure that different Teams’
predecessor deliverables are available for use when needed

Hardware development cannot normally be completed in a time period as short as a Sprint,


which means that the Release cycle is the appropriate timeline for product development for
hardware, as well as software.

However, hardware projects cannot change scope in the middle of a Release cycle as easily as
software projects, because of the much higher cost of change for hardware. In addition, the
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

16  
smaller space of design choices available in hardware development means that a Release-level
scope definition is likely to be more reliable and stable than is the case for software
development. Finally, it is usually necessary to have a reasonable concept of the hardware
product as a whole prior to beginning development on it.

For all of these reasons, Release Planning is essential for hardware development. It cannot
be omitted.

Recommendation: Make Release Planning a standard element of hardware development.

5.1.4 Variation in Sprint Focus during a Release Cycle


The type of work done for a software product during a Release cycle is usually very similar from
one Sprint to the next. Each Sprint develops a “potentially shippable increment of product
functionality,” which means that each Sprint focuses on adding more usable capabilities to the
product.

The above concept does not hold for hardware projects. Each Sprint does not develop a
potentially shippable increment of hardware-product functionality, because hardware
development is not accretional.

For software products, the flow of deliverables is such that new and usable features appear
steadily over time, and these features are aggregated into a newly-released product. For
hardware products, the flow of deliverables generally does not produce a steady flow of usable
features over time, and the product features become usable late in the development cycle.
However, the deliverables can still be developed and tested throughout the cycle, and this is
the key point. This point enables the continuing scope adjustment and refinement needed to
hit planned shipment dates with the best possible value.

The type of work done during a hardware Release cycle may differ significantly across Sprints.
Early Sprints in the cycle may focus more on developing the first physical prototype. Later
Sprints may focus more on iterating prototypes until the Release objectives have been met.
There is no requirement that Sprints have the same focus, and often they will not.

The idea that Sprints may be oriented towards different types of work during a Release
cycle might be seen as a reversion to a “Waterfall” method, but this is not the case. Waterfall
methods rigidly separate requirements development, design, product development, and
testing, and suffer from a number of well-known pathologies.

The Release cycle described here is not a Waterfall process under another name. Each
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

17  
Sprint implements a set of testable (and validated) set of deliverables, the majority of
which represent capabilities of the product. This approach is quite different from a
true Waterfall process.

Recommendation: Do not introduce more variation in Sprint focus than necessary in


a Release cycle, but do allow as much variation as is truly necessary to achieve the
Release objectives.

6 AGILE PROCESS FOR HARDWARE DEVELOPMENT


The RAGE paper11 introduces a way of describing development processes, including Agile
processes, in terms of governance:

“Governance is the formalization and exercise of repeatable


decision-making practices”

“Governance” is often thought of as being about control, but the RAGE perspective is that
control, and other actions, all flow from decisions. If we make decisions well, the rest will
follow. Agile Governance is then an Agile style of governance that focuses on rapid
decision-making, enabled by lightweight artifacts and simple techniques, using
repeatable and standardized practices.

If we think of process definition in terms of Agile Governance, we find that they key elements
of a process are:

1. Roles: A Role is a set of responsibilities, with corresponding decision-making authority,


fulfilled by a person.18
2. Ceremonies: A Ceremony is a recurring meeting, with a standard agenda and
membership, whose purpose is to make a specific type of decision
3. Artifacts: An artifact is any document, design, chart, or other object developed as part
of the process, for the purpose of supporting the work to be done (including decision-
making)
4. Tracking and Metrics: Tracking refers to techniques for assessing how the work being
accomplished compares the plan, and relates to the goals of the work. Metrics are
artifacts (typically, charts, tables, numbers etc.) that provide quantitative information
required for effective tracking.
5. Governance Points: A Governance Point is a moment at which someone who fulfills a
particular Role makes a decision in the domain of that Role’s authority, based on

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

18  
standard practices, metrics, and artifacts. Many Governance Points are Ceremonies, but
many others occur on the fly, as needed.

A particular process is defined by the specifications of its Roles, Ceremonies, Artifacts,


Tracking and Metrics, and Governance Points. Each cycle, or time horizon (such as a Sprint
or Release cycle) has its own distinct set of these elements. We will propose specifications
for these elements below, for the Release and Sprint cycles of a hardware-development
process based on Scrum.

6.1 Overview
Figure 3 illustrates a typical Release cycle for the development of a hardware product that
contains embedded software. The hardware Team has Sprints that are four weeks long,
while the software Team has two-week Sprints. The hardware and software Sprints align at the
boundaries of the former, with two Sprints for the software development occurring in parallel
with each Sprint of hardware development.

Figure 3. Release-Level View of Concurrent Hardware and Software Development

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

19  
6.2 Velocity
The concept of Velocity is central to the activity of planning work against the calendar, in
Scrum. One of the oddities in Scrum is that the term “Velocity” has no standard definition, even
though the term itself is widely used.

For our purposes, we will define Velocity to be the amount of work a Team completes in a
particular period of time. Thus the Sprint Velocity of a Scrum Team is the amount of work the
Team completes in a Sprint. (The term is a misnomer, as ‘Velocity’ implies rate, rather than
amount, but Velocity has become the official term in Scrum and is unlikely to be replaced.) The
units for Velocity are the same as the units for the size of PBIs. (See Sections 6.6.1.1 and 6.6.1.2
for details on units and estimation for Velocity.)

In a similar vein, we define the Release Velocity of a Scrum Team to be the amount of work the
Team completes in a Release cycle. By definition, this Release Velocity is the sum of the Sprint
Velocities for the Sprints comprising the Release cycle.

6.3 Levels of Governance

We define two levels of governance: Project and Program.

• The Project level of governance focuses on the work and practices of individual
Scrum Teams.
• The Program level of governance focuses on the coordination of a set of
Scrum Teams that must collaborate to develop a product.

Each level of governance has a set of standard Roles and Ceremonies.

6.4 Roles
A “Role” is a set of responsibilities, and accompanying authority, assigned to and carried out by
a person or set of people.

6.4.1 Project-Level Roles


The Scrum Roles of Product Owner, Scrum Master, and Team members are clearly defined, as
are the responsibilities and areas of authority associated with each:

Product Owner: This person has sole authority over product requirements (definition and
sequencing), for up to three Teams. Responsibilities include

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

20  
• Developing and prioritizing all requirements for deliverables (PBIs), user-facing
or otherwise, in collaboration with customers, stakeholders, and Team members
• Providing near real-time guidance to Team during implementation and testing
of deliverables
• Reviewing and approving deliverables

Scrum Master: This person has sole authority over the process, for up to three Teams.
A Scrum Master does whatever is needed to make the Team as productive as possible.
Scrum Master responsibilities include

• Enforcing the process


• Facilitating meetings
• Maintaining situational awareness of the work
• Knowing Team member strengths and weaknesses
• Mentoring the Team
• Protecting the Team from interference
• Monitoring progress
• Removing obstacles, ensuring issues are addressed

Team: This set of people has sole authority over Estimates, Task definitions, and Task
assignments. A Team contains three to nine members who do the hands-on work of
implementing and validating deliverables. Each Team must include people who validate
(test) as well as implement deliverables. It is never acceptable to have separate Development
and Testing teams.

Team responsibilities include

• Implementing and validating (testing, fixing) deliverables


• Completing work to standard Definition of Done (Section 6.5.5)
• Estimating work for deliverables
• Allocating tasks within Team (self-organizing) based on skills and availability

6.4.2 Program-Level Roles


The Program level adds two Roles beyond the basic Team-level Scrum Roles: The Area Product
Owner and the Program Manager.

In a small organization, the Role of Product Owner includes both outward (customer) and
inward (Team) facing responsibilities. In larger organizations, we split these responsibilities
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

21  
into separate Roles: The Team Product Owner writes User Stories, ranks requirements for a
Scrum Team, and monitors the development to ensure that the deliverables are as desired,
while the Area Product Owner is responsible for the customer interactions and development of
big-picture solutions.

Team Product Owner: The sole authority over product requirements (definition and
sequencing), for up to three Teams. Responsibilities include

• Writing requirements for implementation by Scrum Teams


• Providing near real-time guidance to Team during implementation and testing
of deliverables
• Reviewing and approving deliverables

Area Product Owner: The sole authority over product requirements for the product, and the
intended content of the Release. Responsibilities include

• Working with customers and stakeholders to identify needs, solutions, and


business value.
• Working with Team Product Owners to develop sufficient detail about requirements and
cost (based on development and testing effort) to support useful Return-on-Investment
estimates.
• Develop Business Case for Product Releases, for use in Portfolio planning.
• Monitor changes in business needs, and work with Team Product Owners to revise the
planned Product Release content as needed.
• Provide ongoing guidance to Team Product Owners regarding cross-Team priorities and
tradeoffs.

Program Manager: Works closely with Teams’ Scrum Masters or Project Managers to ensure
that cross-Team collaboration is effective in achieving the Product’s Release goals.
Responsibilities include

• Enforcing agreements on how cross-Team collaboration is done


• Facilitating cross-Team meetings
• Monitoring cross-Team dependencies, and ensuring that these are planned and
addressed effectively
• Assessing impact of development issues and scope changes on cross-Team
dependencies and overall execution
• Monitoring progress of the Product Release
• Ensuring that risks are addressed effectively during planning and execution
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

22  
• Removing obstacles to effective cross-Team collaboration

6.5 Artifacts
The following artifacts are widely used in Scrum.

6.5.1 Product Backlog Items


A Product Backlog Item (PBI) is a specification for a deliverable that one Team can implement
in a modest fraction of a Sprint. (We recommend that no one PBI exceed one third of a Team’s
Sprint Velocity.) The Scrum world does not have a standardized conception or format for PBIs.
There is general agreement that User Stories should be used, less agreement about the fine
details of how to write a User Story, and no general agreement on other Backlog artifacts.

We will define three types of Product Backlog Items, namely User Stories, Technical Stories,
and Defects. User Stories describe users’ experience of product features, Technical Stories
describe deliverables that are not user facing, and Defects are bug reports.

6.5.1.1 User Stories


A User Story is a short narrative description of some aspect of a product’s functionality that
a user experiences. A User Story describes the user’s interaction with the product, in a
brief format that conveys a basic understanding without attempting to spell out all of
the details. User Stories are most often written by Product Owners, who act as proxies for
the actual users.

The term “User” refers to a category of person who experiences the deliverable in some
fashion. Many types of user experience are possible, such as

• A Doctor uses a cardiac monitor to view an electrocardiogram


• A Firefighter selects a communication channel on a portable radio
• A Developer calls hardware functions through a supplied programmatic interface

In other words, the User is the consumer of functionality that he or she perceives directly. By
definition, Users are never members of the Scrum Team that is developing the product, but
may be members of another Scrum Team.

Our format is a reasonably common one, with the content of the User Story represented by a
Title, a Narrative, and Acceptance Criteria.

• The Title is a one-sentence summary of the PBI.


• The Narrative contains one to a few paragraphs that describe the user experience.
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

23  
o The first sentence is of the form, “As a <Role>, I want to <perform an action>, so
that <this benefit occurs>.” Any following text expands on the user experience.
o The Narrative section often contains non-narrative information as well, such as
links to user interface designs, and other external documents of interest that
relate to the user experience.
• Acceptance Criteria summarizes things that must be true, and validated, about the
completed deliverable.
o Many Acceptance Criteria provide a starting point for test-case definition during
development work.
o This is also a good place to provide other useful requirements information that
does not fit in a narrative description.

Figure 4 shows a sample User Story that reflects the above description.

Title Buyer views statistics for transactions with Vendors Rank 3


ID 22 Estimate 8 Total Task Est. 13
Narrative
As a Buyer, I can view my statistics about my transactions with Vendors, so that I can
understand how my history looks to Vendors.

When I click on a buyer-statistics link, I see my statistics. (This link is on the home page,
under account information.)

Prototype / UI References: Landing Page: Attached (landingPage.html)


External Documents:
Company Style Guide for UI: http://wiki/UI/UIStyleGuide.doc
Statistics to be computed: http://wiki/apps/buyerstats.doc
Acceptance Criteria
• When the user clicks on the link, the application should display the statistics.
• User can create fictitious buyers and suppliers for use in testing.
• When the user submits or responds to RFPs, report shows updated statistics that
reflect the user’s activities.
• The screen should appear within one second, under a load of 20 concurrent requests
pulling data from 20 different static-content files.

Figure 4. Sample User Story

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

24  
6.5.1.2 Technical Stories
Not all deliverables that a Scrum Team creates represent user-facing behavior in a product.
Attempts to represent such deliverables in User Story form tend to produce User Stories that
are very peculiar, and often require non-user Roles. We choose to represent deliverables other
than user-facing behavior as Technical Stories, instead of User Stories. As they do not
represent any kind of user experience, and tend to have a technical orientation, Technical
Stories are most commonly written by Team members.

A Technical Story has the same format as a User Story, except that it omits the user Role from
the Narrative. Thus a Technical Story might look like Figure 5 below.

Title Messaging API Refactoring Rank 7


ID 32 Estimate 3 Total Task Est. 26
Narrative
Refactor the Messaging API to make it easier to use. The current API grew in an ad-hoc
fashion, and requires several calls and some awkward logic to use. We want an API that is
easier to use, requires fewer calls, and is much less confusing than the current interface.
Acceptance Criteria
• At least two Team members agree that the new API is appropriate
• All existing Unit Tests that rely on the Messaging API continue to work

Figure 5. Sample Technical Story for Software Development

In the case of hardware/software system development, there are many physical requirements,
such as voltage levels and signal types among the various modules, necessary to make the
system functional. Internal signals are not seen by the user of the product, but must be
implemented for the product to work. Technical Stories such as the following are therefore
appropriate.

Title 16-bit Digital-to-Analog Converter Motherboard Integration Rank 9


ID 25 Estimate 8 Total Task Est. 60
Narrative
Design into the motherboard a Digital-to-Analog converter (DAC), in order to provide the
high-level analog voltage required to drive the analog display. Assume that the digital
drive presented at the input of the DAC module is of sufficient amplitude to activate the
unit properly, but not so large as to damage the input gates. Since no DAC has been
chosen for this purpose yet, select an appropriate one for incorporation into the
motherboard design.
 
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

25  
Acceptance Criteria
• 16-bit output with +/- 0.5 bit nonlinearity
• Single supply operation: 2.7 to 5.5V
• The maximum current to drive the unit is 500mA.
• The maximum clock rate is 3.4 MBit/sec.
• The output will be a time-varying analog signal varying from 0V to 5V at steps of
7.5 μV, with a maximum output impedance of 1 Ohm.
• Device meets the other requirements of the I2S serial bus

Figure 6. Sample Technical Story for Hardware Development

Common reasons for writing Technical Stories include the following:

• Infrastructure: An infrastructure capability. Done to support specific functional or


nonfunctional requirements.
• Research: A time-boxed research project to gain knowledge required to support future
decisions, designs, or work. Done when the solution to a problem is required, but not
known.
• Spike: A throw-away implementation used to demonstrate the solution to a particular
technical problem. Done to clarify the nature of a solution, and enable estimation of
future work.
• Tracer Bullet: A narrow but deep implementation of part of a PBI or Epic, which
provides very little functionality, but exercises all layers of the “technology stack.” Done
to minimize technical risk or integration effort.
• Chore: Any non-product work that requires scheduled time from the Team. Often done
to implement improvements selected in Retrospectives.

6.5.1.3 Defects
A Defect is a bug report, meaning a report of a specific failure of the product to perform as
intended. No specific format is required for Defects.

Defects are commonly reported by users of the product, and most commonly enter the
Product Backlog via reports from Technical Support personnel. Defects are ranked alongside
other PBIs, with the ranking based on the value of fixing the bug.

Team members (including development and Quality Assurance experts) usually do not enter
Defects into the Product Backlog for problems found in Stories that are currently in process,
when there is no need to retain a record of such problems beyond the lifespan of the Story.
(Defects that do require such tracking should, of course, be captured.) Defects found in other
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

26  
parts of the product, in the course of normal work, may of course be reported and entered into
the Product Backlog.

6.5.2 Epics
Larger specifications, called Epics, must be decomposed into PBIs prior to implementation.
Epics of modest size may be decomposed directly into a few PBIs, while the decomposition of
larger Epics may yield a tree structure whose interior nodes are child Epics, and whose leaf
nodes are PBIs. The implementation of an Epic is completed, by definition, when the PBIs
comprising it have been completed. (Note that integration-testing of the pieces of an Epic is
completed incrementally, as each PBI in the Epic is completed.)

Figure 7. Decomposition of an Epic into PBIs

Epics are commonly used as a convenient organizing principle for deliverables or features that
are too large to be completed in a few days’ time, or which require the work of more than one
Team. (They also arise by accident, when what the author thought was a PBI turns out to be
larger than expected.)

The written format for Epics is identical to that of Stories, meaning that an Epic contains a
Title, Narrative, and Acceptance Criteria. Only the size of the implementation and testing work
of Epics, not the format, differs from that of PBIs.

It is acceptable, but not usually necessary, to refer to “User Epics” and “Technical Epics.” In
these cases, “User” and “Technical” refer to the focus of the Epic, but there is no assumption
that a User Epic cannot contain a Technical Story, and vice versa. In fact, each type of Epic
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

27  
very often will contain the other type of Story. Many Epics that are primarily about user-facing
behavior involve multiple Roles, and cannot be written in a fashion that involves a single Role
performing an Action. In this case, the Narrative still describes a user experience, but that
experience may involve multiple Roles, explicitly or implicitly.

6.5.3 Product Backlog


The Product Backlog is the set of requirements developed for a specific Team, which have not
yet been assigned to a particular Sprint for implementation. The Product Backlog is often
thought of as having two parts. The top part has PBIs listed in rank order, as required to
support upcoming planning work. The bottom part contains all other PBIs, for which ranking is
not yet necessary, and would often be a waste of time.

Technically, Epics are not part of a Product Backlog, as Epics are not implemented directly,
and many Agile project-management tools do manage them separately from Product Backlogs.
However, in casual conversation, Epics are often spoken of as if they were elements in a
Product Backlog, especially when they are treated as placeholders for PBIs that have not yet
been written (i.e., the Epic has not yet been decomposed into PBIs).

6.5.4 Sprint Backlog


The Sprint Backlog is the ranked sequence of Product Backlog Items (Stories and Defects)
assigned to a particular Sprint, for implementation by a particular Team. During Sprint
Planning, items are moved from the Product Backlog into the Sprint Backlog. After a Sprint has
been completed, the Sprint Backlog for that Sprint is the set of all Product Backlog Items that
were completed, which may not be the same as what was planned.

6.5.5 Definition of Done


The Definition of Done clarifies and standardizes the Team’s understanding of what must be
accomplished in the course of creating each deliverable (as described in its PBI), testing the
deliverable, and fixing defects found in it. It contains a set of policy statements regarding how
quality is assured, and how organizational standards are met. Figure 8 shows a typical set of
such policies for a software development Team.

   

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

28  
POLICIES ABOUT QUALITY ASSURANCE
• All defects found when testing a PBI must be fixed immediately
• Acceptance tests must be satisfied
o Validation is performed in QA environment
• Unit tests must be satisfied
o Stub out messaging calls, but use live subsystems in QA environment for
other unit tests
• Regression tests must be satisfied
o Execute regression suite daily, and fix regression bugs first thing each day

POLICIES ABOUT ORGANIZATIONAL STANDARDS


• Code is checked in to repository
• Build from repository is successful
• Deployment process is successful, with no errors
• Code has been reviewed by peer, team lead
• DB design has been reviewed by DB architect
• Unit tests have been developed
• Acceptance tests are automated
• Continuous-integration server builds app and runs tests

Figure 8. A Typical Definition of Done for a Software Team's PBIs

A Team that is developing hardware might have a Definition of Done that resembles
the following.

POLICIES ABOUT QUALITY ASSURANCE


• Prototype is clean of marring and flux
• Module passes full functional test
• Module passes minimum functional test after 24-hour room temperature burn-in

POLICIES ABOUT ORGANIZATIONAL STANDARDS


• Drawing vault contains up-to-date documents and schematics as built
• ESD protection standards are observed during handling and assembly
• All test equipment is calibrated as proven with certificates

Figure 9. A Typical Definition of Done for a Hardware Team's PBIs

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

29  
6.6 Ceremonies
Ceremonies are recurring meetings with standard agendas. Each ceremony has a particular
purpose, as summarized in Table 1.

Ceremonies are associated with specific time horizons, or cycles. The ceremonies for
Releases are different from those of Sprints, although similar in nature.

In the following sections, we look at estimation techniques used in these Ceremonies, and then
the Ceremonies themselves.

6.6.1 Estimation Concepts


Any process that plans work against a calendar involves some concept of work estimates,
and Scrum is no exception. In this section we look at items that require estimation, and
techniques for estimating them.

6.6.1.1 Units for PBI Estimation


The purpose of estimation is to enable planning of work over time, on some kind of calendar.
Any units that achieve this purpose will suffice.

The categories of units commonly used for estimating PBIs may be described as relative sizing
and absolute sizing. Other units are possible, but seldom encountered.

6.6.1.1.1 Relative Sizing


In relative sizing, the units are called Story Points. Story Points do not relate directly to time or
any measurable attribute of the PBI. Instead, Story Points are defined by association with a set
of reference PBIs.

Prior to its first Sprint, a new Team reviews a set of PBIs, identifies a small one, and arbitrarily
assigns it a small size, such as “two Story Points.” The Team then identifies smaller and larger
ones, and assigns them sizes of “one Story Point” and “three Story Points,” respectively.
The team next conducts a triangulation assessment for the validity of the scale, by asking
three questions:

1. Is the 2 SP PBI twice the size of the 1 SP PBI?


2. Is the 3 SP PBI three times the size of the 1 SP PBI?
3. Is the 3 SP PBI one and a half times the size of the 2 SP PB?

If all three questions have a “Yes” answer, the PBIs size is scaling consistently with the
numbers. If any question has a “No” answer, the Team goes through the process again until
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

30  
they do identify a consistent set. They then continue in this fashion to identify reference PBIs
to associate with other allowed numbers (e.g., the Fibonacci sequence, with 5, 8, 13, … for the
larger numbers).

Having established this reference scale, future PBIs are estimated by comparison with the
reference items. For example, a Team might say, “This item has a size of five Story Points,
because we believe it is closer in size to our reference item of that size than it is to any of the
other reference items.”

While Story Points are not defined in terms of time, the practical reality is that a Scrum Team
should be completing roughly five to fifteen PBIs per Sprint. This reality does constrain the
meaning of a Story Point, with the result that a one Story-Point PBI usually does not take more
than a day or two to complete, in the absence of interruptions.

6.6.1.1.2 Absolute Sizing


In absolute sizing, the units define an amount of effort, which is the aggregated time spent by
all people who work on a PBI. The name of the unit is “Person Day” (sometimes referred to as
“Man Day”). For example, a PBI that requires eight hours of work by one person has a size of one
Person Day, as does a PBI that requires four hours of work from each of two people.

The effort required to complete a PBI does not map directly to the duration of the work. A PBI
with a size of one Person Day will often require two or three calendar days to complete,
because the eight hours of work will not be done in a single eight-hour span of time. Or it might
require less than eight hours on the clock, if two or three people work on it in parallel. Thus it is
important to understand the distinction between effort and duration, as the most common
failure mode for absolute sizing is to estimate duration in calendar days.

Only effort matters, for estimation purposes. Duration is irrelevant.

The distinction between relative and absolute sizing can blur over time. Teams that choose
absolute sizing can define reference Stories for different sizes, and use the style of thinking
employed in relative sizing while still yielding time-based estimates.

6.6.1.2 How to Estimate Team Velocity


We define the Velocity of a Scrum Team to be the amount of work the Team completes in a
Sprint (as per Section 6.2). The Velocity for a completed Sprint is computed as the sum of the
estimates for the PBIs completed in that Sprint. (By convention, PBIs that were started but not
completed in the Sprint do not contribute to that Sprint’s Velocity. They will contribute to the
Velocity of the Sprint in which they are completed.) Over time, a Team develops a history of
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

31  
Velocity values that may be used to forecast the Velocity of future Sprints.

The process of Sprint planning requires some estimate of the Velocity expected for the Sprint,
which is used to bound the scope of work for the Sprint. Thus the Scrum Master must provide a
forecast of the Team’s Velocity prior to the Sprint Planning meeting.

Many techniques for estimating Velocity exist, and none is mandated. Possibilities includes
estimating Velocity as

1. The observed Velocity for the last Sprint


2. A running average of the last three Sprints’ observed Velocities
3. (Team size) x (# days in Sprint) x (focus factor), where “focus factor” is the fraction
of time a Team spends developing and testing PBIs in a Sprint (e.g., 60%)
4. The sum of the times Team members are available to work on PBIs in the Sprint,
based on meeting schedules and individual availability for Sprint work

The first two methods may be used in the context of relative sizing, while all four may be used
in the context of absolute sizing.

There is no “right” way to estimate Velocity, and other variations on the above techniques are
also valid. The fourth method is generally the most reliable for absolute sizing, and also the
most work to perform. The third is adequate if Team size and personal availability is consistent
from one Sprint to the next, so that one can determine a standard focus factor value (e.g., 50%)
that yields reliable predictions. The first two are obviously easier, but do not deal well with
individual schedule variations.

6.6.1.3 How to Estimate PBIs with Planning Poker


A Scrum Team may use any estimation technique that works for them, but we recommend
Planning Poker12 specifically. With the Planning Poker technique, each Team Member is
given a deck of cards, printed with numbers such as 0, ½, 1, 2, 3, 5, 8, 13, and so forth.

Most card decks used for Planning Poker are based at least approximately on the Fibonacci
sequence. The logic behind this selection is that we want values that are spaced far enough
apart to be clearly distinct. For example, the difference between 1 and 2 is large (a factor of
two), while the difference between 10 and 11 is small (ten percent). A deck that contains closely-
spaced numbers will lead to time-wasting discussions between numbers that are closer to
each other than either is likely to be to the actual value to be estimated. Hence we use a
relatively coarse scale, such as the Fibonacci sequence, for which numbers increase
by around 50% from one to the next.
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

32  
At the time of the estimation session, it is assumed that Team Members are already familiar
with the PBI based on previous discussions. The Scrum Master normally facilitates the
estimation process, during which the Team members commonly estimate a number of PBIs.

The Product Owner reads the current PBI to the Team, and spends a few minutes answering
any questions they have. The Scrum Master asks that each Team members pick a card with
his/her estimate, and hide the card. When all Team members have selected cards, the Scrum
Master asks them to show their cards, and then asks the low and high voters to explain the
reasoning behind their numbers. The group then has a brief discussion to clarify and resolve
issues and questions resulting from the vote, and re-votes. A third vote is often useful for
achieving consensus, but additional rounds of voting are not usually productive.

If Team members stabilize at a small range of values, they should discuss the values and agree
on a consensus number. If the numbers are far apart and do not converge, it is likely that the
PBI is poorly written and poorly understood, and its estimation should be deferred until it is
rewritten.

The participants continue in this fashion until they have estimated enough PBIs for their
current purpose (most commonly, enough to fill a Sprint).

The Planning Poker technique offers two key benefits:

• It minimizes anchoring, i.e. the tendency for a Team to adopt a consensus belief driven
by the influence of a single person, who is often perceived as the expert.
• It produces a dramatic improvement in the Team’s consensus understanding of what
the deliverable is, and what must be done to produce it

The estimate for a PBI must encompass all work required to implement and validate the PBI’s
deliverables according to the Team’s Definition of Done (Section 6.5.5). This effort includes
development work, testing work, and any other kind of work involved.

6.6.1.4 How to Estimate Tasks


Task estimates are always provided with units of hours, which denote the effort required
to execute them.

Tasks are both more numerous than, and simpler than, PBIs. Because they are numerous, their
estimation via Planning Poker would normally take an impractical amount of time. Because
they are simpler than PBIs, anchoring is less of an issue, and it usually suffices for Team
members to come up with a consensus estimate of Task hours through informal discussion.
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

33  
Since Planning Poker is not used, there is no restriction on the possible numbers, which need
not correspond to the values in a Planning-Poker card deck. Values such as ½, or any integer in
the allowed range, are acceptable.

6.6.2 Ceremonies for Sprints


Table 1 shows the standard Sprint ceremonies. All three Scrum Roles (Team, Product Owner,
and Scrum Master) attend these meetings.

CEREMONY TIME BOX INPUT OUTPUT VALUE


Finalized User
Draft User Stories, Product Backlog &
Backlog Stories Technical
1 hr, weekly Epics from Team are ready for
Grooming Product Owner
Stories Ranking for
Sprint Planning
top PBIs

Sprint Backlog:
Ranked Product
• Selected PBIs + Team has a plan to
Backlog with
Sprint Planning 2-8 hr estimates implement Sprint
Acceptance
• Tasks + Backlog
Criteria
estimates

Team members
Tasks updated have common
Daily Stand-Up <15 min, daily In-progress Tasks Impediments understanding of
raised Sprint progress
and impediments

New PBIs, based Deliverables


on review by reviewed;
Demo prepared for
Sprint Review < 1 hr Product Owner feedback from
completed PBIs
Ranking may stakeholders,
be revised other teams

Sprint Short list of Learn from


performance data, improvements experience,
Retrospective 1-1.5 hr
e.g. Burndown for next Sprint, enable continuous
chart with owners improvement

Table 1: Scrum Ceremonies for a Sprint

The durations of the Time Boxes are suggestions, and should be modified based on
experience. They should always be kept to as short a time as will suffice, to minimize overhead.
(The exception is for the Daily Standup, which should always be capped at
fifteen minutes.)

The practice of Backlog Grooming drives effective decisions about the definition, sequencing,
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

34  
and scheduling of deliverables to be implemented by a Scrum Team. Sprint Planning produces
the Sprint plan, or Sprint Backlog (selection of deliverables to be developed, and associated
Tasks and estimates), which defines the scope of the Sprint for the Team. The Sprint Review
meeting gives the Product Owner a final opportunity to approve deliverables (or to specify what
changes will be required), while the Retrospective meeting drives rapid improvement in the
Team’s ability to deliver.

Figure 10 shows a typical schedule for a two-week Sprint. Note that the meetings take up
eleven of the eighty hours of working time in the Sprint.

MON TUE WED THU FRI MON TUE WED THU FRI
8:00am

9:00am SPRING
PLANNING
10:00am MEETING

11:00am
DAILY STAND-UP
12:00pm Lunch Lunch Lunch Lunch Lunch Lunch Lunch Lunch Lunch Lunch

1:00pm
Backlog
2:00pm
Grooming
Sprint
3:00pm
Review

Backlog Backlog Retro-


4:00pm
Grooming Grooming spective

Overhead: 11 hours
Work Time: 69 hours
Figure 10. Typical Sprint Schedule

6.6.2 .1 Backlog Grooming Meeting


Backlog Grooming meetings are held at least twice per Sprint, or weekly for Sprints of three
weeks or longer. The purpose of Backlog Grooming is to prepare the Team and a subset of the
Product Backlog for future Sprint Planning meetings. In order for a Sprint Planning meeting for
a set of PBIs to be effective, these prerequisites must be satisfied:

• The PBIs must be clear and complete


© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

35  
• The set of PBIs must have no “holes,” i.e. none of the PBIs can depend on some
other deliverable that has not been defined or developed
• The PBIs must be ranked (sequenced) appropriately, based on their value
and dependencies
• The Team members must understand the PBIs and the relationships between them

The Product Owner facilitates the meeting, and all Team members attend. (The Scrum Master’s
attendance is optional, but common.) In the meeting, Team members provide feedback on
draft User Stories and Epics provided in advance by the Product Owner, and identify any issues
or omissions that need to be corrected. The Team members and Product Owner collaborate to
identify what changes are needed and who will make them, and to develop a ranking of the PBIs
that is driven by the Product Owner’s assessment of value,
but which also ensures that dependencies between PBIs are satisfied.

After the meeting, the Product Owner revises and drafts User Stories based on feedback, while
Team members write Technical Stories to address infrastructural or other developmental
needs that do not produce user-facing behavior.

Some Scrum Teams prefer to estimate the PBIs in Backlog Grooming meetings as well.
Whether to perform estimation in these meetings, or in Sprint Planning meetings, is up to the
Team, and the choice is often driven by logistical issues.

There is no assumption that grooming is restricted solely to meetings. Some refinement of


requirements should be continuing as routine work. The Backlog Grooming meetings provides
an opportunity for full-Team collaboration that is intended to enhance, not replace, informal
collaboration on Backlog refinement.

The goal of Backlog Grooming is to ensure that PBIs and the Team are prepared for Sprint
Planning and the PBIs’ implementation. Thus the Team members should be in agreement that
each PBI is ready for implementation before allowing the PBI to enter a Sprint Planning
meeting. One useful technique for ensuring this readiness is to define a “Definition of Ready”
for PBIs, which lists the explicit criteria the Team uses to ensure readiness.

6.6.2.2 Sprint Planning Meeting


The Sprint Planning meeting is held no later than the start of the Sprint, but may precede the
start of the Sprint by a few days, if needed. (A common reason for holding Sprint Planning
meetings prior to the start of a Sprint is that the Scrum Master, Product Owner, or some Team

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

36  
members may need to participate in more than one such meeting, for different Teams, which
means that the meetings cannot be held in parallel.)

A Sprint Planning meeting has two parts. In the first part, the Scrum Team develops a
preliminary plan, based on PBI size, ranking, and Sprint Velocity (see Section 6.6.1.2). In the
second part, the Team decomposes the work of all PBIs into Tasks, and revises the Sprint
scope as needed based on Task-level estimates.

6.6.2.2.1 Sprint Planning, Part 1


The Scrum Master, Product Owner, and all Team members attend this part of the meeting.
The Scrum Master facilitates development of the Sprint plan, which consists of the Sprint
schedule (already known) and the Sprint Backlog (the scope of the Sprint, in the form of a set of
ranked PBIs).

The participants work through a set of ranked PBIs provided by the Product Owner for
planning. If the PBIs have not been estimated, the Scrum Master facilitates their estimation
by the Team, working through the supplied set in rank order. The Scrum Master adds each
PBI to the Sprint Backlog, until the latter is filled to the level of this Sprint’s estimated
Velocity (which must be estimated by the Scrum Master prior to this meeting).

The Product Owner answers questions about the requirements and priority of the PBIs,
and may make quick revisions to the PBIs on the fly. The Product Owner may also modify
the ranking to optimize the value that the Team can complete in the Sprint, given their
estimated Velocity.

6.6.2.2.2 Sprint Planning, Part 2


The Product Owner does not normally attend this part of the meeting, as the focus is on task
decomposition, not requirements clarification. The Scrum Master’s presence is optional, and
depends on whether the Team needs him to facilitate the work (usually the case for
inexperienced Teams), and the extent to which he wants to be familiar with the finer details of
this Sprint’s plan.

Team members create a Task Breakdown for each PBI, in the form of a list of specific Tasks
they will perform in order to implement, validate, and do whatever is necessary to produce a
tested and working deliverable that meets the PBI’s specifications. The Team members also
estimate each Task, in units of hours. The Team should have a standard for minimum and
maximum allowed Task sizes, such as 2 and 16 hours, in order to avoid pathologies that tend to
arise when Tasks are very small or very large.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

37  
• The lower limit avoids creating numerous small tasks, which are typically not worth
tracking. However, it is perfectly fine for a Team to create and track small Tasks for
the purpose of ensuring that those Tasks are not forgotten.
• The upper limit reduces the risk of discovering that work is behind schedule, too late
to attempt corrective measures.

There are two common strategies for creating Task Breakdowns.

1. The first strategy has the whole Team talk through each PBI, agree on the Tasks needed
for it, and then estimate the Tasks. This is more time-consuming than the second
strategy, but is recommended for new Teams, who need to develop a common
understanding of how to do this work.
2. The second strategy has Team members divide PBIs among the Team, after which
individuals or pairs draft Task Breakdowns. The whole Team then reassembles to review
and revise the Task Breakdowns, and develop consensus estimates for the Tasks. This
is faster than the first strategy, but should only be chosen after the
Team has developed a reliable and common understanding of how to develop
Task Breakdowns.

On completion of the Task Breakdowns, the Team and Scrum Master review the initial scope
decision for the Sprint to see if it is still valid, in light of the Task estimates. If the conception of
PBI size has changed due to the Task estimates, it may be necessary to revise the list of PBIs in
the Sprint Backlog up or down, in order to ensure that the plan has an achievable
scope and delivers the maximum value in the Sprint. All scope-change decisions must be
discussed with and approved by the Product Owner.

There is generally no need to replace the original PBI-level estimates with new estimates
generated by aggregating the PBI’s Task estimates. Most tracking systems have separate
fields for these two quantities. While nothing very bad is likely to happen if a Team does revise
the PBI-level estimate, an argument can be made that it is useful to preserve this information
for future use in reviewing estimation accuracy.

6.6.2.2.3 How to Allocate Team Members to PBIs


The day-to-day and hour-to-hour collaboration of Team members follows the Swarming
technique, which minimizes the risk of PBI non-completion, and maximizes the value that can
be delivered in a Sprint in the face of substantial uncertainty. Team members “swarm” on PBIs
to complete them in as close to rank order as is possible.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

38  
Swarming means that the Team self-organizes by allocating Team members to work on each
PBI in a way that minimizes the duration of its implementation. At the beginning of the Sprint,
the Team allocates as many people as possible to work on each of the top few PBIs, by deciding
how many people can work on a PBI to get it done as fast as possible, and who, specifically,
should work on it. Each “swarm” works on one PBI, driving it to completion as quickly as
possible.

The Swarming technique requires that a Team member remain with a swarm as long as there is
a task that he/she can perform, even if it doesn’t match the member’s particular specialty. Only
if there is literally no work that the member can do does the member move on to another PBI, in
which case he/she moves to the nearest PBI in the ranking after this one, where the member’s
presence will get the PBI done sooner than would otherwise be the case. The departed swarm
member may even return to the previous PBI at some point, if returning expedites that PBI’s
completion.

6.6.2.3 Daily Stand-Up Meeting


The purpose of a Daily Stand-Up meeting is to maintain a coherent perspective on the part
of all Team members as to what is happening in the Sprint. Team members lose track of what
other Team members are doing, and how their work can impact each other, because they are
focusing on their current tasks. This meeting provides an opportunity for everyone on the
Scrum Team to update their common picture of the Sprint.

All three roles attend this meeting. The Scrum Master’s primary responsibility is to ensure
the meeting does not exceed its fifteen-minute time box. Since all roles are present, and
the meeting occurs daily, it is critical to keep the meeting short. If allowed to expand, this
daily meeting can consume too much of the Team’s working time.

Team members do most of the talking, while the Scrum Master facilitates, and the Product
Owner observes and contributes as needed.

First, the Scrum Master displays the Burndown chart for the Sprint (Section 6.7.1), and provides
relevant commentary on the overall status of work (e.g., potential need to pick
up the pace, remove scope, add scope, etc.) and other information of general interest to
the Team.

Next, each Team member describes,

1. What I’ve been doing since our last meeting


2. What I plan to do before the next meeting
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

39  
3. What issues are slowing me down, which I need help to resolve

If the resolution of an issue takes more than a minute of discussion, we do not resolve it in this
meeting, but identify who will meet afterwards in a “Sidebar meeting” to address the issue. The
Product Owner is often one of the people who will be involved in such resolutions, which is a
large part of why his attendance is important (the other part being that the Product Owner also
needs to understand how the Sprint is going).

6.6.2.4 Sprint Review


The Sprint Review meeting serves multiple purposes:

• To give the Product Owner a final opportunity for a go/no-go decision about product
capabilities developed in the Sprint
• To give Team members an opportunity to “show off” their work to an audience that
can appreciate it
• To motivate Team members to ensure that PBIs are demonstrable, which means the
PBIs are truly finished

The Product Owner, Scrum Master, and Team members attend this meeting. Some Scrum
Teams use the Sprint Review as an opportunity to show the new deliverables to a wider
audience. (This latter practice is acceptable, provided that the presence of the additional
observers is not disruptive, and the observers only observe, and do not speak, during the
meeting. Observers who wish to give feedback should do so after the meeting, to the
Product Owner.)

The Sprint Review is held after all of the development and testing work in a Sprint is
completed; that is, after all of the PBIs that will be completed in the Sprint have been
completed. It commonly occurs just before the Retrospective meeting. However, the
timing of this meeting can be changed if logistical issues so require. The meeting can even
occur after the beginning of the next Sprint, if no other options exist, but in that case any
follow-up actions identified as necessary in the meeting may have to wait for a couple of weeks
to be started.

The Scrum Master’s facilitation of the meeting is minimal, and mostly concerned with keeping
the pace fast enough to avoid over-running the time box. Team members demonstrate every
completed deliverable from the Sprint, meaning every PBI and Defect that was completed.
Deliverables that appear in the product’s user interface are demonstrated through the user
interface. Other deliverables are demonstrated in whatever fashion works best: “Before and
After” screen shots for refactored code, measured times for performance improvements,
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

40  
mechanical and electrical mockups or demonstrations, and so forth.

Any deficiencies the Product Owner discovers and decides to rectify are addressed by
new PBIs, which describe the necessary changes, and which will be scheduled for a
future Sprint (possibly the very next one). We do not re-open PBIs that have been completed
through their “Definition of Done” (Section 6.5.5), as this practice is confusing and distorts
the tracking metrics.

If, however, a PBI that was declared to have been completed is found not to have been
completed after all, then the PBI is re-opened, and its estimate does not contribute to the
recorded Velocity of this Sprint.

6.6.2.5 Retrospective
The purpose of the Retrospective meeting is to improve the Team’s process over time,
by identifying what does and does not work well, and working to improve the latter.

The Product Owner, Scrum Master, and Team members attend the Retrospective, and no
additional observers are allowed. This meeting is usually held immediately after the Sprint
Review, in the same room, although there is no requirement that the timing be done exactly in
this fashion. The only requirement is that this meeting occurs once for each Sprint, and after
the work of that Sprint has been completed.

The Scrum Master facilitates the meeting, and all three Roles participate. The agenda is as
follows:

1. Review the status of action items from the previous Retrospective, to understand what
has been done, what is in progress, what issues are blocking progress, and so forth.
2. Each participant provides information about
a. What went well in the Sprint, that should be continued
b. What did not go well, that we’d like to be better
3. Decide what changes to make

A common approach to collecting and responding to the information is as follows.

Each participant writes the “went well” and “needs improvement” items on sticky notes (one
item per note), and sticks them on a wall or white board under the “went well” and “needs
improvement” columns. This usually takes about ten minutes.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

41  
The Scrum Master reads the “went well” items, so that everyone knows what they are.

The “needs improvement” notes are commonly repetitive, so the Scrum Master groups them
into a smaller number of distinct topics. The Scrum Master describes the first topic, and the
participants hold a quick discussion about what to do about it. Often the result is simply a
policy change (e.g., a decision to revise the Definition of Done to require that Team members
confirm that the application builds after each check-in), which is made on the spot. Items that
require follow-up actions are noted as such and set aside for the moment. This process
repeats until all topics have been discussed.

After the above discussion, those topics requiring follow-up effort are prioritized (e.g., by
Multi-Voting) to identify the optimum subset that the Team can address, given their finite
bandwidth. Some of these follow-up actions may be to write Technical Stories that will enter
the Product Backlog, and scheduled for a future Sprint.

The participants select owners to drive the selected follow-up actions, and then adjourn.

6.6.3 Ceremonies for Releases

Table 2 shows Release ceremonies. Release ceremonies are less standardized than the Sprint
ceremonies, in part because the set depends on the scale of the work and number of Teams
involved. The table shows the ceremonies that we consider relevant for an organization
containing several Teams that collaborate on one product.

CEREMONY TIME BOX INPUT OUTPUT VALUE


Teams have an
Release Plan: initial plan to create
• Epics & PBIs+ the Release
1-3days,
Epics and PBIs, estimates
Release Planning 1-2 weeks before
per Team, with • Preliminary Sprint Stakeholders have a
Meeting start of
initial ranking backlogs concept of
Release Cycle
• Dependencies, esp. deliverables
cross-Team planned for the
Release

Improved
Impediments raised
awareness of
• Cross-Team issues
Scrum-of-Scrums cross-Team
and impacts
1 hr, semi-weekly In-progress work impacts
Meeting understood
• Follow-Up actions
Cross-Team issues
identified and owned
addressed

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

42  
Ensures quality and
Work completed Go/no-go decision for
3 hr, at end of business value
Release Review by end of Production deployment
Release Cycle justifies
Release Cycle of completed work
deployment

Release
Learn from
Release performance List of improvements
3 hr, at end of experience, enable
data, for next Release Cycle,
Retrospective Release Cycle
e.g. Burn-Up with owners
continuous
improvement
chart

Table 2: Scrum Ceremonies for a Release

The durations of the Time Boxes are suggestions, and should be modified based
on experience. They should always be kept to as short a time as will suffice, to
minimize overhead.

Ideally, all Roles for all Scrum Teams participate in the Release Planning meeting. This
approach becomes more difficult as the number of participating Teams grows, and as
geographic distribution increases. At some point, the concept of a single Release Planning
meeting may have to be replaced by a longer Release Planning process, during which the
Release Plan is developed incrementally over a few weeks, by the serialized and iterative
participation of all Teams and Roles involved. However, the output (the Release Plan)
remains the same.

The Scrum-of-Scrums meeting provides a frequent forum to address cross-Team issues,


which occur frequently when Teams collaborate to build a product. The Release Review
provides a final opportunity to make a Go/No-Go decision for the product Release, as well as an
opportunity to sharpen awareness of the product features. The Release Retrospective
captures lessons learned from the Release cycle, and produces a list of action items whose
purpose is to improve the organization’s ability to build products.

When developing systems that contain both hardware and software components,
the Scrum-of-Scrums meetings will frequently address integration plans and issues, including
hardware-to-hardware, software-to-hardware, and software-to-software integration.

Figure 11 shows a typical schedule for a three-month Release cycle.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

43  
Figure 11. Typical Release Schedule

6.6.3.1 Release Planning


Release Planning must be completed prior to the start of the Release cycle, and is usually
scheduled to be done from one to four weeks before the start of the Release cycle.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

44  
The purpose of Release Planning is to produce a Release Plan, which is an initial map of Epics
and PBIs to Teams and Sprints in the Release cycle. As always in Scrum, the sequencing of
work is driven by value, but constrained by dependencies, and must fit into the estimated
Velocity for the Release. The Velocity information comes from the Scrum Masters, who
estimate their Teams’ Velocity over the course of the planned Release cycle, based on
forecasts of Team size and availability.

Release Planning can be done in one large meeting, over one or two days, or incrementally,
over a few weeks. Both approaches are considered here.

6.6.3.1.1 Single Release Planning Meeting


The Program Manager facilitates this meeting, while the Area Product Owner provides overall
guidance about requirements and business needs.

The Release-Planning meeting can be quite large, as all members of all collaborating Scrum
Teams attend, along with the Area Product Owner, Program Manager, and a scattering of other
participants and stakeholders (e.g., executives, User Experience, Architecture, IT,
Dev Ops, Marketing, etc.). Mixed hardware/software products may also involve people
representing specialties such as electronics, mechanics, manufacturing, regulatory
compliance, and so forth. Consequently, Release Planning can be a costly process, as we
may need one or two full days of time from all of these people.

The value of the Release Plan must justify the cost of Release Planning, or it is not
worth doing. Common drivers for Release Planning include

1. Reduction in confusion due to planning cross-Team dependencies


2. The need to understand how external resources may be engaged
3. The need to plan for customer commitments

Following any introductory presentations desired, the participants meet in one large room,
with one Team per table. Each Team works through a stack of requirements provided by their
Team Product Owner. Each Team estimates any requirements not previously estimated,
identifies and fills gaps, identifies cross-Team dependencies, and drafts its part of the Release
Plan. Teams notify each other of cross-Team dependencies and negotiate how
and when to schedule the associated work. They iterate through drafts of the Release Plan
until they believe the plan is viable. (Teams may also spend much of their time in separate
rooms for much of this work, and periodically return to the shared room to update the
Release Planning Board.)

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

45  
It is common for a Team to have to estimate a few hundred specifications (PBIs and Epics) in
Release Planning meetings. The volume of estimates required precludes careful analysis of
each item, so Teams often use the Affinity Estimation technique (as discussed in Section
6.6.3.1.4) to work through these items in a couple of hours.

After estimation has been completed, Teams create plans by taping each requirement to the
wall, and allocate items to Sprints based on size and dependencies. One wall might display
requirements in (say) three parallel, horizontal rows (at one per Team), with cross-Team
dependencies marked by strips of tape, ribbon, or yarn from predecessor to successor (see
Figure 12). Note that PBIs may not cross Sprint boundaries, while Epics (which are placeholders
for sets of PBIs yet to be written) may cross Sprint boundaries.

Figure 12. A Release Plan, as it Appears in the Release Planning Meeting

The Program Manager is responsible for ensuring that this array of paper is ultimately captured
in condensed form as the Release Plan.

All five roles participate in the Release Planning meeting. The Teams do the bulk of the work,
with Scrum Masters facilitating as needed, and Team Product Owners providing guidance
regarding requirements.

The Area Product Owner and Program Manager participate as needed. The Area Product Owner
provides the big-picture guidance regarding requirements and business value, and
is ultimately responsible for scope trade-off decisions. The Program Manager focuses on
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

46  
ensuring that cross-Team dependencies are identified, as they will be involved in ensuring
those dependencies are handled effectively during execution.

Finally, all parties should be aware that the Release scope may change dramatically,
if business drivers change. This is normal and expected, but means that success is
determined not by implementing the scope of the initial Release Plan, but in ensuring that
scope is managed throughout the Release cycle, so that the evolving Release Plan always
remains achievable and delivers the best possible value for the effort expended during the
Release cycle.

6.6.3.1.2 Incremental Release Planning


While the preceding section presents a common way to do Release Planning, alternatives are
possible. The various Roles may collaborate, formally or informally, in a number of shorter
meetings, to assemble a Release Plan in increments. This approach may be more practical for
environments where logistical issues make the default approach impractical, such as
geographic distribution of Team members. What matters is that the Release Plan be
completed in time, and that the Teams involved have confidence that the plan is achievable.

There are no hard-and-fast rules about how to do incremental Release Planning, but this
section gives some generally-useful guidance. This approach is most commonly driven by
the need to collaborate across distributed groups, and often makes extensive use of
collaboration tools such as web meetings, video conferencing, wikis, and so forth.

6.6.3.1.2.1 Scope Development and Estimation


Team Product Owners write Epics and PBIs to be used in planning a future Release, weeks to
months prior to when the Release Plan must be complete. Team members then provide
estimates for these items in Backlog Grooming or Sprint Planning meetings, in addition to
estimates for PBIs to be addressed in the Sprint being planned.

6.6.3.1.2.2 Release Plan Development


Team Product Owners and Scrum Masters collaborate informally to draft their Teams’ portions
of the Release plan. They seek Teams’ guidance and feedback as required, either informally, or
in Backlog Grooming meetings. As always in Scrum, the sequencing of work is driven by value,
but constrained by dependencies, and must fit into the estimated Velocity for the Release.

The group of Program Manager, Area Product Owner, Scrum Masters, and Team Product
Owners hold a series of mini-Release Planning meetings, each of which produces a new
draft of the Release Plan that takes into account issues and dependencies identified to date. In
between these meetings, the Teams review the plans and provide feedback. This sequence
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

47  
completes when the participants agree that the Release Plan is reliable enough to meet their
goals.

6.6.3.1.3 Units for Estimation in Release Planning


Practitioners in the Scrum world often state that each Team should be allowed to select its
own units and scale for estimating PBIs. This preference is harmless for Scrum Teams that
work alone, but introduces difficulties when Teams must collaborate to develop and execute a
Release Plan. Executives and other stakeholders commonly want simple metrics for work
completed or remaining in a Release, aggregated across Teams, but such aggregation is not
possible if Teams estimate PBIs in different units.

Consequently, we recommend standardization of units across Teams that must collaborate,


such that a PBI of size “5” (for example) communicates a consistent concept of size to all
Teams. This kind of standardization is provided automatically if Teams use absolute sizing. If
Teams use relative sizing, standardization is more difficult, and requires developing a common
reference scale for Story Points across the Teams.

6.6.3.1.4 How to Estimate PBIs and Epics for Release Planning: Affinity Estimation
The most convenient method for estimating the PBIs and Epics that will comprise a Release
is to estimate them incrementally, over time, prior to Release Planning. However, Release
Planning often necessitates estimating the duration and effort of a large number of items in
a short time, so we will address that need here.

The Affinity Estimation technique is an effective way to estimate many items, quickly. The
usual three Scrum Roles participate as follows. The Product Owner prepares by printing out the
relevant PBIs and Epics on paper or sticky notes, and placing them on a table in the room where
the estimation work will be done.

In the first part of the meeting, Team members sort items in order of increasing size from left
to right, by taping them to a wall (or laying them on a table, etc.). This work is done silently.
Each Team member takes an item from the Backlog pile, and places it on the sorting wall in the
place he or she thinks is appropriate. The Team member also reviews items that have been
placed on the wall, and moves any that seem to be in the wrong place, to the right place. The
Team member then picks a new item off the Backlog pile, and repeats.

Eventually, the Backlog pile disappears, and Team members spend their time re-sorting items
on the sorting wall. Any items that do not stabilize are removed for later consideration. The

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

48  
remaining items do settle down, and the Scrum Master makes a decision to halt the sorting
exercise when activity has mostly ceased.

In the second part of the meeting, Team members discuss where to draw lines denoting the
size bins, commonly using the same (Fibonacci-based) scale adopted for the Planning Poker
method (Section 6.6.1.3). After they draw these lines (with masking tape or other non-damaging
means!), all items have estimates.

The appearance of a completed exercise in Affinity Estimation is illustrated in Figure 13.

Figure 13. An Example of Affinity Estimation

If Team members are not all co-located, then fallback options include estimating with
a co-located subset of the Team, or using online collaborative tools that simulate the
‘sorting wall.’

6.6.4 Scrum-of-Scrums Meeting


The purpose of this meeting is to highlight and address cross-Team issues and impacts,
so that no such issues linger very long without attention. This meeting is often held twice
per week.

The Program Manager facilitates the meeting, which is attended by one or two people from
each Team. Attendees may be Team members, whose technical expertise is needed at the
meetings, or Scrum Masters, whose attendance at this meeting protects the working time of
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

49  
Team members who would otherwise have to attend.
Each participant provides two kinds of information, in a quick Round-Robin fashion:
1. What my Team is doing that may affect other Teams
2. What issues or impediments my Team is experiencing due to the work of other Teams,
which need to be addressed

Participants identify who will follow up to resolve issues, and generally collaborate afterwards
to ensure issues are resolved. The Program Manager will typically capture information about
issues and follow-up actions, and then track the issue resolution, or bring in other resources
required to ensure resolution.

6.6.5 Product Owner Scrum of Scrums Meeting


Just as the Scrum Teams require Scrum-of-Scrums meetings to address current issues in
execution, the Product Owners commonly require meetings to maintain synchronization of
their work. The Area and Team Product owners thus have their own (often, weekly) meeting for
this purpose.

The purpose of this meeting is for Area and Team Product Owners to report their personal work
status to each other, and to assess progress towards the Release goals. The Area Product
Owner facilitates the meeting.

The Status-Report format is simple. Each participant summarizes, briefly,

1. What work I’ve done since our last meeting


2. What I’m planning to do before our next meeting
3. Issues that are interfering with my progress
4. How my work on product scope may affect others

Unless blocking issues have solutions that can be described very quickly (say, a minute), the
standard response to issues is to identify who will meet to address them after this meeting.
This approach keeps this meeting acceptably brief.

Next, someone (who may be the Area Product Owner, though this is not required) shows the
Burn-Up chart (Section 6.7.2), and describes how well or poorly progress agrees with the plan.
If progress is not satisfactory (meaning the planned Release scope may not be
accomplishable), the participants discuss how best to address the problem.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

50  
In order of decreasing frequency, the most common responses include

• Reducing scope of specific features


• Reducing scope by dropping specific features
• Moving the Release date out
• Deciding to request that more resources be provided to the product

If progress exceeds expectations, then the participants usually decide what to add to the
scope, and modify plans accordingly.

6.6.6 Release Review


This is a very simple meeting of the Area and Team Product Owners, at the end of the Release
cycle, facilitated by the Area Product Owner. The purpose of the Release Review is to confirm
that the Product quality and business value justify releasing the deliverables developed by the
Project Teams in this Release cycle. The Area Product Owner has the authority to release, or
not release, the product at this time.

Failure to release at this point is a very rare occurrence, as the Product Owners have been
monitoring progress throughout the entire Release cycle.

6.6.7 Release Retrospective


The purpose of this meeting is to identify ways to improve the entire Release process. The
Program Manager facilitates, and the Scrum Masters and Team Product Owners attend.
Attendance by others (e.g., Area Product Owner) is optional and decided locally.

Scrum Masters should prepare by bringing findings from their Teams’ Sprint Retrospectives
that are relevant for this meeting (i.e., which cannot be handled at the Team level). Aside from
this bit of preparation, the format and conduct of this meeting is identical to that of a Team
Sprint Retrospective meeting, and will not be repeated here.

Note that recommendations from this meeting often require management or executive
approval and action.

6.7 Tracking and Metrics


The following sections present standard approaches to tracking progress for Sprint or Release
cycles. The key tracking tools for a Scrum Sprint are the Taskboard and Burndown chart, while
Burn-Up charts are useful for Releases.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

51  
6.7.1 Tracking Progress for a Sprint
Figure 14 shows a typical Taskboard and Burndown chart, and shows the current status in the
middle of a Sprint.
The Taskboard shows the Tasks associated with different PBIs, and the state of each Task.
The PBIs are listed in rank order from top to bottom.

The Burndown chart shows the hours remaining across all Tasks planned for the Sprint but not
yet completed, along with a diagonal line that shows the planned values. The diagonal plan line
is a straight line that connects the known initial state with the planned final state. Work is
ahead of schedule if the bars for the daily values are below the plan line, and behind if they
are above the line.

The initial state for the Burndown chart is the total effort planned for the Sprint, computed
as the sum of the hour estimates for all Tasks associated with all PBIs planned for the Sprint.
This initial state occurs on “Day 0” of the Sprint on the chart (i.e., before the start of work on
Day 1 of the Sprint).

The planned final state is defined by zero hours of work remaining at the end of the last
working day of the Sprint (e.g., Day 10 for a two-week Sprint). Only weekdays are plotted
(not weekends).

Each day’s value is given by the sum of Task estimates for Tasks that have not been completed
by the end of that day.

The Taskboard and Burndown chart enable a clear understanding of how well the work of
the Sprint is going. The Burndown chart shows aggregate progress, and reveals whether
work is being accomplished at the intended rate. The Taskboard shows complete information
about the current state of work. Together, they provide great insight into how well the Sprint
is progressing.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

52  
Figure 14. Scrum Taskboard with Burndown Chart

6.7.2 Tracking Progress for a Release


The key metric for tracking progress for a Product Release in a Release cycle is the
Burn-Up chart.

Figure 15 shows a typical Burn-Up chart. Burn-Up charts show progress towards a goal.
The most common goal is the planned scope of a Release or Project, whose duration on the
calendar spans multiple Sprints. The black scope line shows the effort that has been estimated
for the planned scope, which varies due to scope changes and revisions to estimates. The bars
show the amount of work associated with completed PBIs. The scope line and bars have the
same units as the estimates for the PBIs. Ideally, the two curves will intersect at the end of the
chart, indicating that the planned scope was completed on the planned end date. In practice,
plans and estimates both evolve over time, so the chart is used to guide the scope-change
decisions that will be required to meet the business objectives for the Release or Project.

A Burn-Up chart may show a single Team’s progress, or show the aggregated progress across
all Teams working on a Product Release. Both views are useful.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

53  
Figure 15. A Typical Burn-Up Chart

Roughly speaking, we look for two things in a Burn-Up chart:

1. Is work proceeding at a reasonably steady and desirable rate? If not, we need


to investigate in order to understand the reasons, and identify appropriate
corrective actions.
2. Is the scope achievable? Meaning, does the trend of work progress intersect the
scope line by the end of the Release cycle? If not, and if work is proceeding as well
as can be expected, then the scope needs to be adjusted downwards. (Similarly,
if the chart indicates that the planned scope will be completed early, more scope
may be added to the Release cycle.)

6.8 How Requirements are Developed


The development of product requirements is an ongoing process, which takes serious and
sustained effort over time. The Product Owner has the responsibility of ensuring that Teams
receive implementable requirements (PBIs) for use in Sprint Planning meetings.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

54  
In the simplest case, a Product Owner may spend thirty minutes writing a User Story, which the
Team will implement a week or two later. At the other end of the spectrum, a Product Owner
may spend several months collaborating with a “Product Team” of User Experience designers,
architects, subject matter experts, marketing experts, key customer representatives, and
others, to hammer out an increasingly-detailed vision that is
ultimately incorporated into Epics and implementable PBIs.

Thus the day-to-day experience of a Product Owner can range from “one-man band” to
conductor of an orchestra, depending on how many people’s efforts must be guided and
synchronized to produce the implementable requirements that a Team must have. In all cases,
the Product Owner makes the decisions about what to build based on business value,
feasibility, and cost, and is the funnel through which all requests for a Team’s work must
go (including requests that come from the Team).

Detailed guidance about the mechanics of requirements development is beyond the scope of
this document. However, we do present some simple guidelines.

• A PBI cannot enter a Sprint Planning meeting unless it contains the information required
for Teams to implement its deliverables. It is acceptable and expected
for the Team to have a number of questions for the Product Owner, about various
details, throughout the Sprint. It is not acceptable for the Team to be stalled for
days, routinely, while others have debates about what the PBI should contain. Therefore
the Product Owner must consult with subject-matter experts, and “do
his homework” on the risks and feasibility of implementing a PBI, before that PBI
can enter a Sprint Planning meeting.
• User Experience (UX) and architectural guidance needed for a PBI’s implementation
must be made available, and incorporated as appropriate into the PBI itself, before
the PBI can be considered ready for implementation. This guidance may take the
form of wireframe or high-fidelity screen mockups, design patterns, or anything else
that is required, and may be attached to the PBI, or referenced in the PBI’s text by a
link to a separate artifact.
• It is unwise to create large, detailed UX or architecture designs in one big effort, and
then hand the whole batch off to a Team at once. It is better to develop rough
conceptions of long-term needs and solutions, but design and build the detailed pieces
on a “Just in Time” basis. The former slows value delivery, and commonly wastes effort
on developing artifacts and plans that will turn out to be wrong or useless.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

55  
7 PRACTICAL EXAMPLE OF AN AGILE HARDWARE PROJECT
In this section, we will follow the evolution of a hardware product’s development, using the
Agile process we have defined. The product is a cardiac monitor, produced by a fictitious
company named TelCorp.TelCorp’s mission statement provides a succinct description of
what the company does:

TelCorp develops, sells, supports, and provides training for medical devices that
support surgical procedures and patient monitoring in hospitals. TelCorp is dedicated
to enabling the best possible medical care for patients, by producing networked medical
devices whose integrated management provides benefits that far exceed the sum of
the individual products.

7.1 The Project and Product Definition


The project is to design and develop a cardiac monitor for patient monitoring in hospital
environments. The product is a clean-sheet design for TelCorp, and incorporates new features
that provides a higher level of hospital data integration and better interoperability with our
overall product line.

Part of the motivation for the new design is the advancement in micro-controllers and
converters, which enable a new and more capable platform. Also new in the product is its
interaction with cloud storage, so that all data is stored both locally and in the cloud, while
ensuring HIPPA compliance. Finally, this product is aligned with the overall portfolio plan,
and its projected selling price of $39K is targeted towards the highest volume of hospital
patient monitors.

The program priorities are:

1. Time to market
2. Accuracy of heart rate monitoring 2x over leading competitor
3. Implementing all Series III API requirements for TelCorp interoperability
4. Product Cost
5. Project Cost

The project is organized as a set of self-organized Team, each having the mix of skills required
to implement and validate the PBIs they are expected to complete. The Teams are matrix
organizations, with member of one Team reporting to more than one functional manager.

7.2 The Team Definitions


Proper Team definition is critical to success. Each Team owns a particular category
of deliverables, and work on the product as a whole is allocated to Teams based on
their focus. Each Team must contain all of the skill sets needed to produce tested
and working deliverables.
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

56  
The development of the cardiac monitor is divided across four Scrum Teams. The overall
product definition comes from Daniel, who is designated as the Area Product Owner. Ulrich,
the Program Manager, is responsible for facilitating Release Planning, and managing cross-
Team dependencies.

The two Scrum Masters (Caroline and Fred) fill their roles for two Teams each. Each Team also
has a single Team Product Owner, who is responsible for ensuring that Team’s requirements
(Stories) are properly defined and sequenced. The wide variation in Teams’ areas of focus
means that it is impractical to have one person be the Team Product Owner for more than one
Team. At the same time, the role of Team Product Owner for a single Team does not entail
enough work to keep one person occupied full time. Thus the compromise here is to designate
each Team’s lead engineer to serve as part-time Product Owner for that Team.

Note that the prior version of this “project team” had a similar management structure under the
old Waterfall methodology. The headcount of the team management is approximately the
same with the new organization, but the roles are different.

Previously, Daniel, whose title was (and remains) Product Manager, was assisted by an
assistant Product Manager. Now this supplementation responsibility is supplied by two
of the lead engineers.

Furthermore, the prior project had a Program Manager and a Project Coordinator. This
headcount has been effectively been replaced by two Scrum Masters (Caroline and Fred).
Caroline was the former Program Manager. She has had Agile training, and now fills a new
Role as Scrum Master. Fred is a new hire who was brought in specifically for his Agile
experience. Although his experience was in software before, he is translating his skills
to hardware development.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

57  
Area Product Owner Daniel
Program Manager Ulrich

Mechanical Team Team Member Primary Skills


Product Owner Anthony Anthony Mech. Engineering Lead and Team PO
Scrum Master Caroline Alex CAD Designer
Mahesh CAD Designer
The Mechanical Team
Chun Power & Thermal Engineer
focuses on product packaging
Brenda Regulatory & Compliance
and compliance.
Todd Manufacturing Engineer

Analog Team Team Member Primary Skills


Product Owner Franklin Franklin Electrical Engineering Lead and Team PO
Scrum Master Caroline Yuri Instrumentation Engineer
Krish Instrumentation Engineer
The Analog Team handles Sensors, Sheldon Conversion Engineer
Analog-to-Digital and Digital-to- Erica Conversion Engineer
Analog conversion. Dwight Systems Engineer
Yani Test Engineer

Digital Team Team Member Primary Skills


Product Owner Heinrich Heinrich Digital Lead and Team PO
Scrum Master Fred Chuck Firmware Engineer
Asha Firmware Engineer
The Digital Team is responsible Heidi Firmware Engineer
for the Display, FPGA, instrument
Jing Digital Logic/Glue Logic
control, network communications,
and printed circuit development. Neeraj IO - Input/Output (Bus)
Melissa Manufacturing Test

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

58  
Software Team Team Member Primary Skills
Product Owner Jerry Jerry Software Lead and Team PO
Scrum Master Fred Mike Lead Scientist
Steve Instrument SW Engineer
Padma Instrument SW Engineer
The Software Team develops
Kelly Algorithms SW Engineer
algorithms and implements them
Gabe Algorithms SW Engineer
in software.
Tatiana QA
Chris QA

Figure 16. Scrum Teams for Cardiac Monitor Development

In order to achieve high levels of productivity, Team definitions must be reasonably stable.
Adding or removing a Team member every few months is reasonable, but changing Team
membership with every Sprint disrupts the patterns of collaboration that Teams develop,
and sharply degrades productivity.

One of the challenges with defining stable Teams is the reality that the participation of certain
people is vital at various times, but not often enough to warrant their inclusion into Scrum
Teams. The best way to address this kind of “as needed” participation is to consider these
people as external resources. We engage with them as needed, and plan to request or receive
their contributions appropriately, but do not incorporate them as Team members, or involve
them routinely in all of the Scrum meetings.

Among the most common types of external resources are User Experience designers and
technical Architects, with whom the Product Owners must engage in order to ensure that the
Teams have the right specifications for their deliverables. Other external resources include IT
Operations, Release Management, manufacturing engineers, and so forth.

Roughly speaking, Product Owners engage with external resource that contribute information
about deliverables to be developed, while Scrum Masters engage with external resources that
relate to execution of work. However, these patterns, while common, are not rules. The only
rule is that someone be designated as the person to engage with external resources.

7.3 Developing High-Level Specifications


Prior to the first Sprint in the Release cycle, a number of team members (including the Area
and Team Product Owners) visited customers in order to develop customer requirements,
which shaped the forty top Epics that defined the product. Architects and Team Leads also

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

59  
collaborated with Area and Team Product Owners to develop a Technology Roadmap that
defined architectural goals and standards. This Roadmap supports the specific needs of
the cardiac monitor project, as well as other company objectives.

The high-level specifications resulting from this effort, along with TelCorp's Design Standards
(UE/UI, Networking APIs) appeared in the form of:

• Epics: Specifications for major deliverables from the Hardware and Software Teams.
These include both user-facing and non-user facing deliverables.
• A User Experience guide, defining the basic patterns of user experience
• A User Interface style guide, defining standards for the product’s user interface
• A Networking guide, describing how the system interfaces with the hospital information
and alert network
• An Architectural guide (high-level infrastructure design, industry standards, company
standards, and other product constraints)
• Miscellaneous other documents

Note the clear distinction between specifications for deliverables (Epics), and other
documents. While Teams will ultimately implement the capabilities described by the
Epics, they do so with a clear understanding of the guidelines and constraints provided
in the other documents.

Developing the high-level requirements requires significant effort, over a time span of weeks
to months. For the most part, this effort is done in parallel with development work on other
products. Area Product Owners and technical leads, who are thinking about future work, will
take time to work with customers and each other to begin defining requirements for new
products. Two or three months before the cardiac monitor’s Release cycle begins, Team
Product Owners and technical leads will begin writing implementable specifications for
product features (User Stories) and infrastructure (Technical Stories). By the time of the
Release Planning meeting, the intended scope of the product should be defined in some mix
of Stories and Epics.

Many of the company’s products have a very similar conceptual design, and the cardiac monitor
is no exception. The overall flow of product development at a high level addresses common
types of components, and can be represented by this network diagram:

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

60  
Figure 17. Network Diagram for Cardiac Monitor Development

The blocks are often tightly coupled, even bi-directionally coupled, with other blocks, such
that it is frequently necessary to develop slices of scope that cross two or more blocks
concurrently.

At a high level, deliverables are described in Epic form. Epics may have a user-oriented focus,
or a technical (e.g., infrastructural, non-functional, etc.) focus. Figure 18 shows a typical Epic
for a usable product feature. Note that Epics often contain references to diagrams, design
principles, and other external documents of interest that are not, themselves, solely focused
on the specific deliverable described by the Epic.

Title Detection of Ventricular Fibrillation Rank


ID 37 Estimate Total Task Est.
Narrative
As a Doctor, I want to know if a patient is experiencing Ventricular Fibrillation, so that
we can initiate immediate treatment to preserve the patient’s life. When fibrillation is
detected, the cardiac monitor should notify associated Monitor stations, which will
then execute the standard protocols for emergency notification.
Acceptance Criteria

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

61  
1. End-to-end notification should occur within five seconds following onset
of event.
2. The notification displayed on Monitor stations should include basic
diagnostic information.
3. False positives should be made as infrequent as possible, but it is more
important that false negatives never occur.

Figure 18. A Typical Epic for a Major User-Facing Product Capability

Over the course of the Release cycle, the Team Product Owners and Team members will
create a decomposition of this Epic (and others) into User and Technical Stories to be
implemented in various Sprints.

The high-level Epics are commonly defined through a collaborative effort involving the
Area and Team Product Owners, with the bulk of the actual writing falling to the Team
Product Owners.

7.4 Developing Detailed Specifications


Team Product Owners cannot generally write requirements with sufficient clarity and focus
to meet all of the Teams’ needs. Nor can they usually write the specifications for the all of the
non-user-facing deliverables which are always present, and often highly technical in nature.
For these reasons, Product Owners must collaborate closely with their Teams to develop the
fine-grained and implementable specifications required by those Teams.

As described in Section 6.5.1, Epics must be decomposed into User Stories (for user-facing
product behaviors), and Technical Stories (for other deliverables). These Stories are the
specifications for actual Team deliverables, and must be clearly written, properly ranked
(sequenced), and well-understood by the Teams before the Stories can enter a Sprint
Planning meeting. Much of the work of developing suitable Stories occurs within or
following the Backlog Grooming meetings of Section 6.6.2.1.

In the four weeks prior to the Release Planning meeting for the cardiac monitor work, the
Team Product Owners meet twice weekly with their Teams (and Scrum Masters) in Backlog
Grooming meetings.13 The Product Owners bring draft Epics and Stories that Team members
have previously read, and collect feedback. The Team members provide the feedback needed
to improve Stories and decompose Epics. The Team members also discover needs for
technical work, and develop Technical Stories after the meeting, for review in the next
meeting. The continuing series of Backlog Grooming meetings enables the steady flow of
© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  
This document, in whole or in part, must not be reproduced in any form without the express written permission.

62  
fine-grained specifications the Teams require for their Sprint Planning meetings.

Backlog Grooming meetings do more than turn ideas into Stories. They also provide a standard
forum for collaboration and discovery that frequently yields improved ideas about what to
develop, even to the point of generating improved product directions that differ substantially
from previous plans.

The Area Product Owner, Daniel, is the authority on what the full set of Scrum Teams will
develop. He is empowered to make major changes in scope and direction before and during
development of the product. He does not have to seek approval for changes unless it is clear
that they will impact other initiatives the company is pursuing, will require significantly greater
investment than was originally planned, or may jeopardize the business objectives of this
product. He does not make these changes in a vacuum—it is his responsibility to collaborate
with other products and business stakeholders to ensure that the product’s evolving definition
is appropriate and dependent plans are suitably revised—but he does have the authority to
make such changes.

Team Product Owners have narrower, but substantial, authority over the definition and
sequence of the deliverables their Teams will produce. They must meet the business
objectives and satisfy the high-level requirements, but otherwise have considerable
freedom about how to meet these needs.

The finer-grained output of the Backlog Grooming process yields many Stories over time.
Figure 19 shows how the high-level Epic of Figure 18 can be decomposed into smaller
deliverables. The leaf nodes of Figure 19 are Stories, while all other nodes are Epics.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

63  
Figure 19. A Typical Decomposition of Epics into Stories

It is usually not possible to develop all Stories required for a Release cycle prior to the Release
Planning meeting for that cycle. Instead, it is expected that this meeting will involve a mix of
Epics and Stories. Near-term work is (mostly) decomposed into Stories at the time of the
meeting; while work to be done in the longer term is often represented by Epics, which will
be decomposed later.

7.5 Release Planning


The Release Planning meeting occurs two weeks before the beginning of the Release cycle
(meaning, two weeks before the first developmental work is done for the product.) As time
spent in the Release Planning meeting is time not spent on development work for the previous
product, it is critically important to ensure that preparatory work is completed prior to the
meeting. In this case, the four Scrum Teams complete the Release Plan in one day, because of
their major investment in writing and grooming the product requirements prior to the meeting.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

64  
7.5.1 Developing the Release Plan
The Teams follow the planning process described in Section 6.6.3.1.1. Team Product owners
bring printed copies of all of the Epics and Stories developed for this product, for both Teams,
along with any other documents that may be useful for planning purposes. The Program
Manager, Ulrich, facilitates the planning session. The Scrum Masters guide their Teams to do
their parts, while Team Product Owners develop or modify Stories and Epics as needed in the
meeting. The Area Product Owner, Daniel, assists with insight about what the specifications
mean. Crucially, Daniel also makes scope trade-off decisions required in order to meet the
desired timeline, based on business objectives.

The Release Plan developed in this meeting has the general form of Figure 12, but contains
much more detail (e.g., hundreds of Epics and Stories, and associated dependencies).

On conclusion of the meeting, all four Teams have agreed that the Release Plan is achievable.
All Teams are even more confident that this is the best Release Plan they can create at this
time. Finally, and perhaps most importantly, everyone involved in this planning exercise knows
that the reality will diverge from the plan. The Teams will not succeed because they have
created a reliable plan. They will succeed in large part because Daniel and the Team Product
Owners will control and revise the scope throughout the Release cycle, to ensure that the
Teams deliver the maximum value possible in that period of time.

7.5.2 The Structure of the Release


The structure of the Release cycle is driven primarily by the constraints of hardware
development, as the focus of the Hardware Team’s work changes over the course of the
Release cycle. The network diagram of Figure 17 provides some initial insight into the natural
flow of work, which is elaborated and refined in Release Planning. A high-level summary of
the Release Plan, shown in Figure 20, shows how the focus of work evolves over the span
of the Release cycle.

Figure 20 illustrates some common patterns.

The hardware and software development proceed in parallel. The Software Team uses two-
week Sprints, while the Hardware Teams uses four-week. The longer Sprints are necessary for
the slower-moving hardware development process, as the minimum reasonable size (in terms
of work) of the hardware deliverables is substantially larger than that of software deliverables.

The Sprint boundaries for all Teams align every four weeks, to make planning and collaboration
easier. Teams integrate and conduct integration testing at every practical opportunity

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

65  
throughout the Release cycle, deferring to later times only the integration work that physically
cannot be done earlier.

The Software Team does pure software development, and relies heavily on emulation of
hardware (early in the Release cycle) and prototypes (later in the Release cycle).

The Hardware Team designs and builds (or has built for them) prototypes of the hardware,
along with emulations to support the early software work. The Analog and Digital Hardware
Teams commonly do some software and firmware development as well, creating basic low-
level drivers, other internal capabilities, and programmatic interfaces used by the Software
Team. The growing use of full-scale hardware prototypes over time causes significant
increases in development cost over time, in contrast to the relatively flat software-
development costs.

The type of work that the Software Team does changes little over time. The specific
deliverables change, but the daily experience of development work is mostly similar from
Sprint to Sprint. This similarity does not apply to the Hardware Team, whose deliverables
are qualitatively different in later Sprints of the Release cycle, compared to earlier Sprints.

Software design work is normally done on an incremental and Just-in-Time (JIT) basis,
throughout the Release cycle, as needed. Hardware design is more front-loaded in the Release
cycle, because the cost of change of hardware is so much higher than for software that it is
important to minimize design changes (analogous to “refactoring” in the software world), and
because the constraints of hardware development narrow the decision space enough to
provide more design reliability than is commonly the case for software design work.

The focus and associated headcount of the hardware work evolves as shown in the diagram.
The Architecture and User-Interface design work is substantial at the start, and then tails off.
The test and validation work for the working hardware components is small at first, and
increases over time.

Finally, there will be a Hardening Sprint at the end of the Release cycle. Integration testing is
done as early and often as possible throughout the Release cycle, but there is always a certain
amount of integration, testing, and other work that cannot be done while the product is under
development. The latter type of work is done in Hardening Sprints, after product development
has completed. It is important to understand that the only work done in Hardening Sprints is
work that cannot be done earlier, and hardening Sprints should never be used as a place to
dump work that people would rather postpone.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

66  
Figure 20. Structure of the Release Cycle for the Cardiac-Monitor Development

7.6 Regulatory Issues


The US Food and Drug Administration, and its global counterparts, require that development of
medical products adheres to certain standards. Central to these standards are the
requirements that:

1. The product have written specifications that correctly describe the product, at a useful
level of detail
2. The vendor provides a “traceability matrix” showing how each part of the specification
has been tested (i.e., list and describe the test cases)
3. Every product-related document, and changes to it, must be developed and archived
with a formal approval and distribution process, complete with signoffs from approvers

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

67  
Some vendors simply collect the full set of PBIs and other design artifacts, and define the set
to be the product specifications. Daniel prefers a different approach, which entails more work,
but provides a more conventional style of document. He incorporates the work of developing
the official specifications, incrementally, as planned work done in the Sprints (i.e., as Stories
or Tasks in Stories). This approach ensures that the specifications and deliverables are well
synchronized.

The traceability requirement is easily satisfied by archiving the test cases, test results, and
links between features and test cases.14

7.7 How Scope and Work Evolve during the Release Cycle
The Release Plan is a plan, not a guarantee. The fine-grained details of scope evolve over
time, as the Teams decompose Epics into Stories, and develop new Stories to fill gaps that
are identified along the way. Product Owners may shift direction significantly, as their
understanding of market needs and business drivers evolve. Unforeseen issues (such
as layoffs, diversion of resources to meet urgent needs, previously-unforeseen
competitive threats, etc.) may force de-scoping of some details in order to hit target
dates with usable functionality.

In the case of the TelCorp cardiac monitor, all of the above influences are in play. Reality and
the plan begin to diverge in very minor ways in the second Sprint of the software Team, and
future Sprints see even larger changes. The Team and Product-Owner Scrum-of-Scrums
meetings provide the cross-Team coordination needed to evolve the current plan in the right
direction. These meetings enable rapid resolution of cross-Team issues, and provide input
into subsequent Sprint Planning meetings. As a result of this ongoing collaboration and
planning, the cardiac monitor is delivered on time, with functionality that meets the initial
big-picture commitments, and with details that were optimized over time to yield the best
possible device for the investment.

8 CONCLUSIONS
In the end, an Agile process for hardware development not only looks very similar to a Scrum
process for software development, but generally incorporates the latter in a synchronized
fashion, in order to provide the software components of the overall product.

The differences we observe in Agile hardware development, compared to software


development, mostly have to do with the sequencing of deliverables. Agile software
development accretes usable features over time, while Agile hardware development accretes
deliverables whose usability commonly appears late in the Release cycle.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

68  
The only fundamental difference between the Scrum process concepts between hardware and
software development has to do with the hardness of Story boundaries. The software version
requires “Hard Stories,” which must be completable within a single Sprint. This practice
remains desirable for hardware development as well, but may not always be possible. In the
latter case, we will allow for “Soft Stories” whose scope is not expected to complete within the
bounds of one Sprint. The “Soft Story” approach should be avoided as much as possible, but our
model can accommodate these Stories when required.

In conclusion, we find that a Scrum process is well-suited for hardware development. This
result comes as something of a surprise, but a welcome one. We’ve known how to develop
software with a Scrum process for some time. Now we can leverage that knowledge for the
world of hardware development as well.

9 GLOSSARY
Common terms and definitions used in this paper are given below.

TERM MEANING
An umbrella term for fast, iterative, incremental product development methodologies. Agile
Agile Product processes include different methodologies such as Scrum, Kanban and others. The common
Development elements include minimizing “Batch Sizes” and maximizing the “Velocity” of the product or
information under development.

A set of User Stories to be implemented in a Product Development process. It can


be the entire set of product features (Product Backlog), the set of Stories to be implemented
Backlog
in the next Release (Release Backlog), or the set of Stories to be implemented in a Sprint
(Sprint Backlog).

The process of reviewing, revising, adding, removing and prioritizing Stories, to ensure that
Backlog Grooming the Stories and Team are properly prepared for future planning meetings. This process is
commonly led by the Product Owner.

The number of “work items” to be processed as a set. A Batch Size that is too large leads to
idle time (for work items) and multitasking (for people), which decrease
Batch Size
throughput and harm morale. In a Scrum context, Batch Size corresponds most closely with
the size of individual Stories.

A chart showing planned and estimated effort remaining in a Sprint. The diagonal plan line
connects the total planned effort (hours for all Tasks planned for the Sprint) on Day 0 to zero
Burn-Down Chart on the last day of the Sprint. The estimated effort remaining is plotted daily as the sum of
hours estimated for all Tasks that have not yet been completed. Large variations between
the plan line and observed status reveal the need for corrective action.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

69  
A chart showing progress towards a goal, most commonly used to show progress towards
completing the planned scope of a Release cycle. The scope line shows the total estimated
effort of the planned scope (in person-days or Story Points). The scope value will change over
time as the planned scope or estimates change. The progress value plotted each day shows
Burn-Up Chart
the effort associated with the planned Product Backlog Items that have been completed to
date. Ideally, the two curves will intersect at the end of the planned Release cycle. If the
trend for the progress makes it clear that the planned scope cannot be achieved, then
corrective action should be taken (most commonly in the form of scope adjustment).

Daily Standup A short meeting (capped at fifteen minutes) whose purpose it to bring all Team members up
Meeting to date on the current status of, and issues in, the work they are doing.

A written statement that clarifies and formalizes the Team’s understanding of what must be
Definition of Done accomplished in the course of creating each deliverable (as described in its PBI), testing the
deliverable, and fixing defects found in it.

A specification for a deliverable that is too large to be developed as a single unit, written in
Story form. Epics must be decomposed prior to implementation. Decomposition of Epics
Epic generates tree structures whose leaf nodes are Stories, and whose other nodes are Epics.
Epics and Stories both are commonly used in Release Planning, but Epics cannot be used in
Sprint Planning (which requires that their scope has been decomposed into Stories).

An Agile process that does not plan work against a calendar, but selects work to be done
from the top of a prioritized queue whose content is reprioritized as requests for work arrive.
Kanban focuses on rapid prioritization, workflow definition, and optimization of throughput
Kanban
by constraining Work in Process and reducing the Cycle Time from start to completion of
work. It is well-suited for operations, support, and other “request-driven” environments, but
is not commonly used for software development.

A unit of effort, used in estimation of Product Backlog Items. A Person-Day is defined to


Person-Day mean eight hours of time spent working on a particular item (e.g., one person working for
eight hours, or two people working for four hours each). Not related directly to duration.

Product Backlog Written descriptions of deliverables to be implemented in a Sprint or a Release, commonly


Items (PBIs) in the form of User Stories, Technical Stories, or Defects.

The person responsible for ensuring that requirements are properly developed and
sequenced. The Product Owner drives, but does not usually write, all requirements.
Product Owners commonly write User Stories, review Technical Stories written by
Product Owner
Team members, define the ranking (sequencing) of the work to be done, make
scope-change decisions, and clarify requirements for the Team members on a daily
basis throughout each Sprint.

A period comprised of two or more Sprints that produce a major milestone in the Product
Release Cycle
Development project. A Release may or may not correspond to an actual product release.

A meeting of the Team after each Sprint (and sometimes after a Release) to discuss what
Retrospective went well and what did not, and identify what changes to make (and who will make them
happen) in order to improve the process over time.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

70  
An Agile process that plans work against a calendar, in time-boxed (fixed-size) periods called
“Sprints.” Scrum focuses on maximizing value delivered over time by sequencing work to
ensure the most valuable items are done as soon as possible. It is well-suited for software
Scrum
and hardware development, and any environment subject to high uncertainty, but where the
organization can define, control, and plan scope. It is not well-suited for highly reactive
(request-driven) environments.

The person responsible for ensuring that execution of work goes well. The Scrum Master
has authority over (enforces) the process, mentors the Team and Product Owner as needed,
Scrum Master
facilitates meetings and decisions, and acts as a “Servant Leader” by removing impediments
to the Team's success.

Scrum-of-Scrums A multi-Team meeting to discuss and coordinate a larger project involving parallel
Meeting Sprints and integration plans.

A synonym for estimation, specifically of the effort (in Person-Days or Story Points)
Sizing
required to implement a PBI.

An uninterrupted and Time-Boxed period of intense product development by the Team


Members aimed at fully implementing a planned set of User or Technical Stories by the end
Sprint of the period. The output of the Sprint is intended to be “potentially shippable” to a customer
(meaning, it has the requisite quality), or in the case of a system development, to
downstream system integrators.

A review of the completed deliverables of a Sprint, by the Product Owner, to provide a final
Sprint Review
go/no-go decision regarding the deliverables.

A unit of effort, used in estimation of Product Backlog Items. A Story Point is dimensionless,
based not on time but on the relative size of a set of PBIs. A new Team sorts a set of Stories
Story Point
by size, from small to large, and assigns numeric values (as Story Points) to representative
Stories. Future estimates are based on comparison to the reference Stories.

An action performed by a Team member, towards completion of a PBI. The Team defines
a Task Breakdown (set of Tasks, with estimates in hours) for each PBI. The Task definitions
are driven by the scope of the PBI, and the policies supplied by the Definition of Done. (A Task
Task
Breakdown for a PBI always incorporates all Tasks required to validate that the deliverable
is what it should be.) Completion of all Tasks in a PBI therefore completes the deliverable,
by definition.

A big, visible board (either physical or virtual) showing the Product Backlog Items, where
they are in the queue to be implemented, and tracking metrics such as a Burn-Down
Taskboard
charts. There may be other information on the Taskboard as well, such as risks, issues
and availability of resources.

A technical professional whose role is to implement or test the functionality of User


Team Member
and Technical Stories during a Sprint.

Technical Story A written specification for a deliverable that does not have a user experience.

Allowing a certain set time-limit to accomplish some objective, such as completing


Time-Boxing
a Sprint.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

71  
User Story A written specification for a deliverable that has a user experience.

The amount of work accomplished in a Sprint. The units for Velocity are the same as
Velocity
the units of estimation for PBIs.

Waterfall A serial method for developing new products starting from requirements definition and
ending with product validation testing. The process flows from one step to the next and
Product
there are no planned iterations. Ideally the product requirement specifications are frozen
Development early in the process and not changed.

1
Winston W. Royce. “Managing the Development of Large Software Systems.” Proc. IEEE
WESCON, Aug 1970. This paper originated the Waterfall process in concept, if not in name.
2
Royce, 1970.
3
www.agilemanifesto.org
4 New Oxford American Dictionary. Oxford University Press. 2010.
5
Coleman and Verbruggen. “A quality software process for rapid application development,”
Software Quality Journal 7, p. 107-1222. 1998.
6
S.R. Palmer and J.M. Felsing. A Practical Guide to Feature-Driven Development. Prentice
Hall. 2002.
7
Ken Schwaber and Mike Beedle. Agile Software Development with Scrum. Prentice Hall. 2002.
8
David Anderson. Agile Management for Software Engineering: Applying the Theory of
Constraints for Business Results. Prentice Hall. 2003.
9
A Guide to the Project Management Body of Knowledge (PMBOK® Guide), Fourth Edition.
Project Management Institute, Inc. 2008.
10
Timm J. Esque. No Surprises Project Management: A Proven Early Warning system for Staying
on Track. ACT Publishing. 1999. While this book introduced key principles of CBPM, the name
and abbreviation for “Commitment-Based Project Management” seem to have been
formulated subsequent to the book’s publication.
11
Kevin Thompson. Recipes for Agile Governance in the Enterprise: The Enterprise Web.
Cprime Inc. Aug 2013. (https://www.cprime.com/resource/white-papers/recipes-for-
agile-governance-in-the-enterprise/)
12
PLANNING POKER® is a reg. trademark of Mountain Goat Software, LLC.
13
The Hardware and Software Teams are assumed to exist at this time, and are most likely
working on an earlier product Release in parallel with the Backlog Grooming meetings for this
upcoming product.

© Cprime, Inc. All rights reserved. | www.cprime.com | 877-573-2760  


This document, in whole or in part, must not be reproduced in any form without the express written permission.

72  
14
This description reflects key points, but should not be taken as detailed guidance. For further
details, consult FDA regulations (such as TITLE 21 - FOOD AND DRUGS, CHAPTER I - FOOD AND
DRUG ADMINISTRATION, DEPARTMENT OF HEALTH AND HUMAN SERVICES, SUBCHAPTER H-
MEDICAL DEVICES, PART 820-QUALITY SYSTEM REGULATION, Citation 21CFR820. April 1, 2014).