Aeration Tank
Aeration Tank
Aeration Tank
App. Qty.
Unit
2566.22
Cu.m.
75.00
192466.33
120.98
Cu.m.
3500.00
423444.00
3.00 RCC M 30
252.74
Cu.m.
4517.00
1141644.65
4.00 Reinforcement
26.00
MT
50000.00
1300000.00
5.00 Waterproofing
i)
1344.00
250.00
336000.00
800.00
1075200.00
Perticulars
1344.00
Sq.m.
Rate
Total
4468754.98
Total
4915630.48
Total cost
Amount
446875.50
Measurements
Length
Width
Depth
28.00
28.00
5.00
2.5
App. Qty.
Unit
I]
1 Excavation in all types of soils at all depths
Aeration tank
Dimension
Depth below ground level
Angle w.r.t. vertical wall for working space(In degree)
Excavation requires
No of Unit
60
2566.22
1
Total
2 PCC M15
Thickness of PCC
PCC M15 requires
2 RCC M 30
Aeration tank
Dimension
Walll (length wise)
Wall (Width wise)
Bottom raft
Supporting col
Supporting col. Footings
Top beam (length wise)
Top beam (width wise)
Bottom beam (length wise)
Bottom beam (width wise)
Total
Cu.m.
Cu.m.
2566.22
0.15
120.98
Cu.m.
Total
120.98
Cu.m.
85.80
84.00
82.94
0
2
2
1
28.00
28.60
28.00
28.80
28.00
0.3
0.3
28.8
5.00
5.00
5.00
0.10
0
0
0
0
0
0
0.45
1
28.00
28.00
28.00
28
0.45
1
0.3
0.3
0.3
0.3
4.50
0.45
0.3
0.3
0.3
0.3
0.00
0.00
0.00
0.00
0.00
0.00
252.74
Cu.m.
25.27
2.53
27.80
26.00
MT
MT
MT
MT
Misc. Works
Total
Say
5 Waterproofing
Aeration tank
Dimension
Length wise surface area
Width wise surface area
Bottom slab
1
2
2
1
28.00
28.00
28.00
28.00
28.00
28.00
5.00
5.00
5.00
Total
6 External Plastering
Aeration tank
Dimension
Length wise surface area
Width wise surface area
Bottom slab
280.00
280.00
784.00
1344.00
Sqr M
1
2
2
1
28
28
28
28
28
28
5
5
5
Total
Sq.m.
280
280
784
1344.00
Rates OF Materials
Cement OPC Cement
Aggregate
Sr No
Item no
Mix
305
Water
10 1000-Lit.
1500.00
500.00
Sand
CC M-10
M20
M-15
M15
M-25
RCC
Perticulars
RCC
1
1.1
1.2
1.3
1.4
1.5
2.1
2.2
3
3.1
3.2
3.3
4
4.1
4.2
4.4
Qty
Cement Content
Materials Cement
Sand
Coarse Aggregate
Plasticizer @ 0.5% @ Rs 35/Water
Total of Materials
Add Wastage @5%
Formwork (Material) Total of Materials
Labour & OperatorsCuring cost & labour
Shuttering carpenters
Operator
Total of Labour
POL Transit mixer
Vibrator
Concrete Pump
Total of POL
Grand Total
4.5
5.2
6.3
1322
5.2
1372.5
235.00
1410.00
0
5
3022.50
151.13
50
3223.63
1586
225.00
1350.00
45.5
5
3211.50
160.58
100
3472.08
0.00
1921.5
215.00
1350.00
55.125
4.5
3546.13
177.31
100
3823.43
0.00
1586
225.00
1350.00
45.5
5
3211.50
160.58
200.00
3572.08
25
0.00
26.26
26.26
61.40
308.61
455.80
825.81
0.00
25
0.00
26.26
51.26
0.00
25.00
0.00
0.00
25.00
#REF!
#REF!
#REF!
#NAME?
#NAME?
50.81
4.53
3.00
58.33
4417.62
#REF!
#REF!
#REF!
#REF!
#NAME?
0.00 #NAME?
#NAME?
0.00 #NAME?
7.2
0.00
2196
215.00
1350.00
63
4
3828.00
191.40
0
4019.40
0.00
0.00
25
0.00
26.26
51.26
0.00
0.00
#REF!
11.73
#NAME?
#NAME?
0.00
0.00
Say
#VALUE!
791.31
200000.00 p-cum
Nos/cu.m.
0.20
0.04
Rate
275
160
252.74
50.00
Cu.m.
cu.m./day
2.1.1
2.1.2
Required time
Planed period
2.1 Shuttering
Carpentar
Helper
0.20
4
Months
months
=
=
2 Nos x @ 6000per month x 10months x 1shifts x 1.25 OT1 Nos x @ 8000 per month x 4 months x 1 shifts x 1.2 OT
1Nos x @ 4000per month x 4months x 1shifts x 1.2 OT
1 Nos x @ 8000 per month x 4 months x 1 shifts x 1.2 OT
1Nos x @ 5000per month x 4months x 1shifts x 1.2 OT
POL -
3 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour
Vibrator
0.5 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour
5 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour
=
=
To & Fro Lead x diesel rate per ltr x 1.2(Lub) / (3.5 Km/Hr x 5 Cum)
0.17 x 6 Ltr x Rs 42 x 1.2(Lub) / 6 Cum
=
=
M-30 RCC
8
2440
225.00
1350.00
35
5
4055.00
202.75
791.31
5049.06
61.40
308.61
455.8
825.81
50.81
4.53
11.73
67.07
5941.94
4517
Amount
55.00
6.40
61.40
#REF!/X14
=
105000
180000
308.6
30000
48000
78000
38400
19200
38400
19200
Total
455.8
115200
27.15 /Cum
11.73 /Cum
4.53 /Cum
=
42.24
8.57
Total
0.166666667
94.22
8 CW Chemical plant
Acid Storage AREA
Equipment shed area
MCC , c&I control Room
1)
Nos
Length
Width
Area
1
1
2
35
10
4.5
9
7
4.5
Total
315.00
70.00
40.50
425.50
Nos
Length
Width
1
1
1
10
9.5
10
14
6
6
Total
Area
0.00
140.00
57.00
60.00
257.00
Total Area
683
18359250
Add for inlet channels, Internal pipe lines walkways, railings , Gates, drainage
arrangements, Approach road etc. @ 10%
Total
Total, Say
1835925
20195175
202
Sq.m.
Sq.m.
Sq.m.
Lacs.
Nos Length
1
1
2
35
10
4.5
Nos Length
1
15
1
6
Width
Area
9
7
4.5
Total
315.00
70.00
40.50
425.50
Width
12
4
Area
180.00
24.00
0.00
0.00
204.00
204.00
Total
Nos Length
1
5.4
1
5.4
1
3
Width
6
6
1.5
Total
4 Chlorination system
Nos Length
1
10
Width
11
Total
Total for 6 Chlorinators
5 Gravity Filters
Sump cumpump souse
Piping Gallary
Gravity Filters
Nos Length
1
15
1
15
1
15
Width
4.5
4
4.5
Total
Total for two gravity filters
Nos Length
1
13.7
Width
12
Total
Area
32.40
32.40
4.50
0.00
69.30
Area
110.00
0.00
0.00
0.00
110.00
110.00
Area
67.50
60.00
67.50
0.00
195.00
390.00
Area
164.40
0.00
0.00
0.00
164.40
1
1.00
26
12.00
6
18.00
15
12
10
21.9
16.76
2.00
15.00
8.00
2.00
8.00
10.00
15
12
156.00
216.00
0.00
0.00
0.00
0.00
360.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
60.00
0.00
0.00
0.00
0.00
0.00
0.00
367.04
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
240.00
0.00
160.00
0.00
0.00
0.00
0.00
0.00
180.00
0.00
0.00
0.00
0.00
0.00
0.00
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Sq.m.
Nos Length
1
14
1
2.5
Width
3
7
Total
8 CW Chemical plant
Nos Length
1
1
1
10
9.5
10
Width
14
6
6
Total
Area
42.00
17.50
0.00
0.00
59.50
1.00
1.00
Area
0.00
140.00
57.00
60.00
257.00
14.00
2.50
1
1
1
0.00
42.00
17.50
0.00
0.00
0.00
0.00
0.00
0.00
147.29
103.73
64.73
0.00
0.00
3.00
7.00
10.3
6.298
10.44
14.3
16.47
6.2
Sq.m.
Sq.m.
Sq.m.
10 Areator
11 Stilling Chamber
15
1884
Sq.m.
Sq.m.
Sq.m.
0.00
0.00
0.00
2114.29
Sq.m.
Sq.m.
60805836
Add for inlet channels, Internal pipe lines walkways, railings , Gates,
drainage arrangements, Approach road etc. @ 10%
Total
Total, Say
6080584
66886420
669
Lacs.