Aeration Tank

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 18

(III ) Abstract of STRUCTURES

App. Qty.

Unit

1.00 Excavation in all types of soils at all depths

2566.22

Cu.m.

75.00

192466.33

2.00 PCC M15

120.98

Cu.m.

3500.00

423444.00

3.00 RCC M 30

252.74

Cu.m.

4517.00

1141644.65

4.00 Reinforcement

26.00

MT

50000.00

1300000.00

5.00 Waterproofing
i)

1344.00

250.00

336000.00

800.00

1075200.00

Perticulars

6.00 Ext.Plastering +painting


( Internal +Ext plaster+neeru finishing+painting )

1344.00

Sq.m.

Rate

Total

4468754.98

Total

4915630.48

Add 10% for vents, overflow valves and civil works


required for fittings of mech. Equipments, operating
7.00 platforms etc.and other furnishing materials etc.

Total cost

Amount

446875.50

Measurements

(III ) Estimated quantities of STRUCTURES


Nos

Length

Width

Depth

28.00

28.00

5.00
2.5

App. Qty.

Unit

I]
1 Excavation in all types of soils at all depths
Aeration tank
Dimension
Depth below ground level
Angle w.r.t. vertical wall for working space(In degree)
Excavation requires
No of Unit

60
2566.22
1
Total

2 PCC M15
Thickness of PCC
PCC M15 requires

2 RCC M 30
Aeration tank
Dimension
Walll (length wise)
Wall (Width wise)
Bottom raft
Supporting col
Supporting col. Footings
Top beam (length wise)
Top beam (width wise)
Bottom beam (length wise)
Bottom beam (width wise)
Total

Cu.m.
Cu.m.

2566.22

0.15
120.98

Cu.m.

Total

120.98

Cu.m.

85.80
84.00
82.94

0
2
2
1

28.00
28.60
28.00
28.80

28.00
0.3
0.3
28.8

5.00
5.00
5.00
0.10

0
0
0
0
0
0

0.45
1
28.00
28.00
28.00
28

0.45
1
0.3
0.3
0.3
0.3

4.50
0.45
0.3
0.3
0.3
0.3

0.00
0.00
0.00
0.00
0.00
0.00
252.74

Cu.m.

25.27
2.53
27.80
26.00

MT
MT
MT
MT

3 Reinforcement @ 100 kgs/cu.m.


10%extra as extra work

Misc. Works

Total
Say
5 Waterproofing
Aeration tank
Dimension
Length wise surface area
Width wise surface area
Bottom slab

1
2
2
1

28.00
28.00
28.00

28.00
28.00
28.00

5.00
5.00
5.00
Total

6 External Plastering
Aeration tank
Dimension
Length wise surface area
Width wise surface area
Bottom slab

280.00
280.00
784.00
1344.00

Sqr M

1
2
2
1

28
28
28

28
28
28

5
5
5
Total

Sq.m.
280
280
784
1344.00

Rates OF Materials
Cement OPC Cement
Aggregate
Sr No
Item no

Mix

305

Water

10 1000-Lit.

1500.00
500.00

Sand

CC M-10

M20

M-15

M15

M-25
RCC

Perticulars

RCC

1
1.1
1.2
1.3
1.4
1.5

2.1
2.2
3
3.1
3.2
3.3
4
4.1
4.2
4.4

Qty
Cement Content
Materials Cement
Sand
Coarse Aggregate
Plasticizer @ 0.5% @ Rs 35/Water
Total of Materials
Add Wastage @5%
Formwork (Material) Total of Materials
Labour & OperatorsCuring cost & labour
Shuttering carpenters
Operator
Total of Labour
POL Transit mixer
Vibrator
Concrete Pump
Total of POL
Grand Total

4.5

5.2

6.3

1322
5.2

1372.5
235.00
1410.00
0
5
3022.50
151.13
50
3223.63

1586
225.00
1350.00
45.5
5
3211.50
160.58
100
3472.08

0.00

1921.5
215.00
1350.00
55.125
4.5
3546.13
177.31
100
3823.43

0.00

1586
225.00
1350.00
45.5
5
3211.50
160.58
200.00
3572.08

25
0.00
26.26
26.26

61.40
308.61
455.80
825.81

0.00

25
0.00
26.26
51.26

0.00

25.00
0.00
0.00
25.00

#REF!
#REF!
#REF!
#NAME?
#NAME?

50.81
4.53
3.00
58.33
4417.62

#REF!
#REF!

#REF!
#REF!

#NAME?
0.00 #NAME?

#NAME?
0.00 #NAME?

7.2

0.00

2196
215.00
1350.00
63
4
3828.00
191.40
0
4019.40

0.00

0.00

25
0.00
26.26
51.26

0.00

0.45 cu.m. /cu.m.


0.9 cu.m. /cu.m.

0.00

#REF!
11.73
#NAME?
#NAME?

0.00

0.00
Say

1 cost for shuttering


Rate / Cu.m
Total cost for shuttering
2 Labour Mason
Male Coolie
Total conc.
Rate of Conc.

300 per sqm


#VALUE!

#VALUE!

791.31
200000.00 p-cum
Nos/cu.m.
0.20
0.04

Rate
275
160
252.74
50.00

Cu.m.
cu.m./day

2.1.1
2.1.2

Required time
Planed period
2.1 Shuttering
Carpentar
Helper

Concreting 2.3 Operators For Concrete pump


Vobrator oprator
#REF!+0.1
Transit Mixer- driver
Transit Mixer- Helper

0.20
4

Months
months

2 Nos x @ 7000 per month x 10 months x 1 shifts x 1.25 OT


5000
2 Nos x @ 6000per month x 10months x 1shifts x 1.25 OT2 Nos x @ 7000 per month x 4 months x 1 shifts x 1.2 OT
1Nos x @ 5000per month x 4months x 1shifts x 1.2 OT

=
=

2 Nos x @ 6000per month x 10months x 1shifts x 1.25 OT1 Nos x @ 8000 per month x 4 months x 1 shifts x 1.2 OT
1Nos x @ 4000per month x 4months x 1shifts x 1.2 OT
1 Nos x @ 8000 per month x 4 months x 1 shifts x 1.2 OT
1Nos x @ 5000per month x 4months x 1shifts x 1.2 OT

POL -

Concrete Mixer 14/10


Concrete Pump Model 350DSS/greaves- 30 Cu.m./hr.

3 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour

Vibrator

0.5 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour

0.1 Transit Mixer


Travelling
Discharge

5 ltr per hour x Diesel rate per ltr x 1.2(Lub) x 1.2(idle) / out put per hour

=
=

To & Fro Lead x diesel rate per ltr x 1.2(Lub) / (3.5 Km/Hr x 5 Cum)
0.17 x 6 Ltr x Rs 42 x 1.2(Lub) / 6 Cum

=
=

M-30 RCC

8
2440
225.00
1350.00
35
5
4055.00
202.75
791.31
5049.06
61.40
308.61
455.8
825.81
50.81
4.53
11.73
67.07
5941.94
4517

Amount
55.00
6.40
61.40

#REF!/X14
=

105000
180000

308.6

months x 1 shifts x 1.2 OT


onths x 1shifts x 1.2 OT

30000
48000
78000

months x 1 shifts x 1.2 OT


onths x 1shifts x 1.2 OT
months x 1 shifts x 1.2 OT
onths x 1shifts x 1.2 OT

38400
19200
38400
19200

Total

455.8

115200

tr x 1.2(Lub) x 1.2(idle) / out put per hour

27.15 /Cum

tr x 1.2(Lub) x 1.2(idle) / out put per hour

11.73 /Cum

r ltr x 1.2(Lub) x 1.2(idle) / out put per hour

4.53 /Cum

=
42.24
8.57
Total

0.166666667

94.22

Estimate for cost of Civil works for PRE-WATER TREATMENT PLANT


Area statrment for various structures in Pre-Water treatment plant at Barauni TPS.
1 MCC and Control Room
PT CONTROL Room

8 CW Chemical plant
Acid Storage AREA
Equipment shed area
MCC , c&I control Room

1)

Cost on area basis

Nos

Length

Width

Area

1
1
2

35
10
4.5

9
7
4.5
Total

315.00
70.00
40.50
425.50

Nos

Length

Width

1
1
1

10
9.5
10

14
6
6
Total

Area
0.00
140.00
57.00
60.00
257.00

Total Area

Cost of Civil Works @ 2500/sq.ft.

683

18359250

Add for inlet channels, Internal pipe lines walkways, railings , Gates, drainage
arrangements, Approach road etc. @ 10%

Total
Total, Say

1835925

20195175
202

Sq.m.

Sq.m.

Sq.m.

Lacs.

Estimate for cost of Civil works for PRE-WATER TREATMENT PLANT


Area statrment for various structures in Pre-Water treatment plant at Barauni TPS.
AS PER ION EXCHANGE
1 MCC and Control Room
PT CONTROL Room

2 Chemical House.- Ground Floor


Space for Lime and alum
Reception

Nos Length
1
1
2

35
10
4.5

Nos Length
1
15
1
6

Width

Area

9
7
4.5
Total

315.00
70.00
40.50
425.50

Width
12
4

Area
180.00
24.00
0.00
0.00
204.00
204.00

Total

Chemical House.- First floor Floor


3 Filter Backwash water system
Backwash I
Backwash II
Inlet chamber

Nos Length
1
5.4
1
5.4
1
3

Width
6
6
1.5
Total

4 Chlorination system

Nos Length
1
10

Width
11

Total
Total for 6 Chlorinators

5 Gravity Filters
Sump cumpump souse
Piping Gallary
Gravity Filters

Nos Length
1
15
1
15
1
15

Width
4.5
4
4.5

Total
Total for two gravity filters

6 Clarified water Tank & Pump House.

Nos Length
1
13.7

Width
12

Total

Area
32.40
32.40
4.50
0.00
69.30
Area
110.00
0.00
0.00
0.00
110.00
110.00

Area
67.50
60.00
67.50
0.00
195.00
390.00

Area
164.40
0.00
0.00
0.00
164.40

1
1.00

26
12.00

6
18.00

15

12

10

21.9

16.76

2.00

15.00

8.00

2.00

8.00

10.00

15

12

156.00
216.00
0.00
0.00
0.00
0.00
360.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
60.00
0.00
0.00
0.00
0.00
0.00
0.00
367.04
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
240.00
0.00
160.00
0.00
0.00
0.00
0.00
0.00
180.00
0.00
0.00
0.00
0.00
0.00
0.00

Sq.m.

Sq.m.

Sq.m.
Sq.m.

Sq.m.
Sq.m.

Sq.m.

7 Sludge Pit for All clarifiers

Nos Length
1
14
1
2.5

Width
3
7

Total

8 CW Chemical plant

Nos Length

Acid Storage AREA


Equipment shed area
MCC , c&I control Room

1
1
1

10
9.5
10

Width
14
6
6
Total

Area
42.00
17.50
0.00
0.00
59.50

1.00
1.00

Area
0.00
140.00
57.00
60.00
257.00

14.00
2.50

1
1
1

0.00
42.00
17.50
0.00
0.00
0.00
0.00
0.00
0.00
147.29
103.73
64.73
0.00
0.00

3.00
7.00

10.3
6.298
10.44

14.3
16.47
6.2

9 Add for Clarifiers- 2 Nos @ 452.16 Sq.m. for each

Sq.m.

Sq.m.
Sq.m.

10 Areator
11 Stilling Chamber

12 Filtered water reservior - 2 Nos @ 1500 sq.m. each

15

13 Add for Overhead water tank 1000liters capacity


Total Area

1884

Sq.m.
Sq.m.
Sq.m.
0.00
0.00
0.00
2114.29

Sq.m.
Sq.m.

Area as per Ion ex.


Cost of Civil Works @ 3000/sq.ft.

60805836

Add for inlet channels, Internal pipe lines walkways, railings , Gates,
drainage arrangements, Approach road etc. @ 10%

Total
Total, Say

6080584

66886420
669

Lacs.

You might also like