Gate House, FDN To Roof: Excavation
Gate House, FDN To Roof: Excavation
SUBSTRUCTURE (PROVISIONAL)
D GROUNDWORK
Excavation
A. Excavating top soil, maximum depth not exceeding
150mm. m2 79 100% 79.00 200.00 15,800.00
Trench Excavation
B. Excavating trenches, width exceeding 0.3m maximum
depth not exceeding 2.00mm m3 19 100% 19.00 1,500.00 28,500.00
DISPOSAL
FILLING
E. Filling to excavations, average thickness
exceeding 250mm, materials arising from
excavations m3 21 100% 21.00 700.00 14,700.00
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
SUBSTRUCTURE (Cont'd)
E10: INSITU CONCRETE
Plain Insitu Concrete
Vibrated Grade 20
A. Foundations, 150 - 450mm thick m3 8 100% 8.00 10,000.00 80,000.00
K Edges of ground slab not exceeding 250mm high m 17 100% 17.00 480.00 8,160.00
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
SUBSTRUCTURE (Cont'd)
Damp Proofing
A. 0.26mm polythene damp proof membrane lapped
450mm at all welted joints, laid on hardcore m2 79 100% 79.00 80.00 6,320.00
Surface Treatment
Pesticides: Dieldrex 20
B. Treating the bottom and surface of excavation m2 64 100% 64.00 80.00 5,120.00
PRRD/BFNL/DWAB/FMGH/2 429,361.00
PRRD/BFNL/DWAB/FMGH/3 47,440.00
GROUP ELEMENT Nr. 1 SUBSTRUCTURE
CARRIED TO SUMMARY 659,801.00
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
Beams
G. 16mm Diameter bar t 0.48 100% 0.48 70,000.00 33,600.00
Beams
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
H: CLADDING / COVERING
H72: Aluminium sheet coverings/flashings
0.55mm Queensway Aluminium Roofing Sheet RED Colour or other approved colour
fixed to Wood Purlins (measured seperately) all fixed
in accordance with manufacuturer's specifications
well screwed and bolted and lapped.
CARPENTRY WORK
Treated Ikhimi or Iroko or other approved in.
K 50 X 50mm Nogging m 100 100% 100.00 150.00 15,000.00
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
GABLE END
SUMMARY
790,400.00 112,500.00
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
Prepared by:
January, 2024
Habcon NIg Ltd
PREPARED BY HABCO NIG LTD FOR BLUE FOUNTAIN NIG LTD January, 2025
GENERAL SUMMARY
Prepared by:
January, 2024
Habcon NIg Ltd