Survey
Survey
Civil Engineering
GATE
SURVEYING
AUTHOR:
SHAILENDRA KUMAR
AAYUSHI AGRAWAL
CONTENT SHEET
Surveying
2. Compass Surveying......................................................................................................................47
3. Theodolite.......................................................................................................................................85
9. Theory of Errors..........................................................................................................................245
10. Curves............................................................................................................................................271
mmmm
Content Sheet
Content Sheet
4.
1 Introduction and Linear
Measurement
Chapter 1
1.1 INTRODUCTION
y Surveying can be defined as the method of determining relative position
of the points on, above and below the surface of earth through direct or
indirect measurement of direction, elevation & distance.
y It can also be defined as the method of establishing the points by
predetermined linear or angular measurements.
Definitions
Level line- It is the distance between two points on the level surface
that follows the earth curvature.
Plumb line : A line represented by the freely suspended plumb bob.
1.
Chapter 1
(ii) For any line of length 12 km, it is just 1cm extra in geodetic
survey.
2.
Chapter 1
(b) Marine / Hydrographic Survey
y It deals with water bodies for the purpose of navigation, water supply,
mean sea level, reservoir functioning, waste disposal.
y It consists of measurement of discharge of streams, stage of water bodies
and fluctuation in oceans tides.
(c) Astronomical survey
y The purpose of this survey is to determine the absolute location of any
points on the surface of earth with the help of heavenly/ spatial bodies.
Example - sun, any fixed star.
3.
Introduction and Linear Measurement Chapter 1
4.
Chapter 1
Previous Year’s Questions
5.
Chapter 1
(c) The distance BC and the angle ABC can be measured, and point C
is plotted either by means of a protractor or trigonometrically. This
principle is used in traversing.
(d) In this method, the distance AC and BC are not measured but angle CAB
and angle CBA are measured with an angle – measuring instrument.
Knowing the distance AB, point C is plotted either by means of
a protractor or by solution of triangle ABC. This principle is used in
triangulation.
(e) Angle CBA and distance AC are measured, and point C is plotted
either by protracting an angle and swinging an arc from C or plotted
trigonometrically. This principle is used in traversing.
Note: In (b), (c), (d) case, the concerned point ‘C’ can be vertical plane also.
Example-1.1 Match list I with list II and select the correct answer.
List I List II
A B C D
(a) 3 2 1 4
(b) 1 3 4 2
(c) 3 4 1 2
(d) 1 2 4 3
Solution:
Topographical survey is carried out for determining the position of natural
and artificial features, cadastral survey is done for fixing the property lines,
6.
Chapter 1
city survey is done for the construction of street, water pipeline, etc and
engineering survey is carried out to find the data for engineering design
works. So the correct answer is (c).
Example 1.2 In the figure given below, for the location point C by measurement
from point A and B, the principle used is –
(a) Chain surveying (b) Triangulation
(c) Traversing (d) Offset method
Solution: The distance BC and the angle ABC can be measured, and point
C is plotted (by means of protractor or trigonometrically).
So the correct answer is (c).
Definitions
7.
Chapter 1
Shrunk length
Corrected distance on map in terms of original scale =
Introduction and Linear Measurement
Shrunk factor
Shrunk area
Correct area on map in terms of original scale =
(Shrunk factor)2
Example -
8.
Chapter 1
Consider ab be the distance on the map and AB be the distance on the
ground
ab = 2.5 cm, AB = 2.5 × 10 = 25 m
Shrunk Scale = Shrunk factor × Original Scale
0.9 1 1
= × =
1 1000 1111.11
2.25
= = 2.5 cm (distance on map)
0.9
1
AB = 2.5 × 1000 = 2500 cm = 25 m
Example 1.3 The area of the plan of an old survey is now found to be 100.9
m2, which was plotted to a scale of 10 m to 1 cm. The plan has shrunk such
that a line originally 10 cm long now measures 9.3 cm only. Compute the
following
(i) Shrunk scale (ii) True area of survey
Shrunk length 9.3
Solution: (i) =
SF = = 0.93
Original length 10
1 1
Shrunk scale = SF × Original Scale = 0.93 × =
1000 1075.27
Shrunk Area 100.9
(ii) True area = 2
= = 116.66 cm2
(Shrunk factor) (0.93)2
Scale of plane is 1cm = 10 m
Area of survey = 116.6609 (10)2 = 11666.09 m2 ~ 11666.1 m2 Introduction and Linear Measurement
Or
True area of survey = 100.9× (1075.27)2 ×10–4
= 11666.1 m2
Example 1.4 Plan of a rectangular field was drawn in 1950 with a scale of
1 cm = 40 m. The present dimension of field read as 40 cm × 10 cm. If an
original reference line of 9.2 cm now reads 10 cm, then what is the actual
area of field?
Expandedlength 10
Solution: Expasion factor
= = = 1.087
Original length 9.2
9.
Chapter 1
Expanded area 40 × 10
True area of field = = = 338.53 cm2
(Expanded factor)2 (1.087) 2
Scale of plane is 1 cm = 40 m
Area of field = 338.53(40)2= 541652.67m2
1.4.2 Error due to wrong measuring scale-
y If a wrong measuring scale is used to measure the length of an already
drawn line, the measured length will be incorrect similarly if the wrong
measuring scale is used to measure the area of an already drawn area on
the plan, the measured area will incorrect.
RF of wrong Scale
Corrected length = × Measured length
RF of correct Scale
2
RF of wrong Scale
Correct Area = × measured area
RF of correct Scale
Example 1.5: The distance between the two points marked on the plane
drawn to a scale of 1cm = 1 m is measured by a surveyor and found to be
60 m. Later it was found that a wrong scale of 1 cm = 50 cm is used for the
measurement. Then what will be the correct length and correct area, if the
measured area is 70m2 ?
RF of wrong scale
Solution: Correct length = × measured length
RF of correct scale
1
= 50 × 60 = 120m
1
Introduction and Linear Measurement
100
2
RF of wrong scale
Correct area = × measured area
RF of correct scale
2
1
50
= 1 × 70 =
280m2
100
10.
Chapter 1
1.4.3 Choice of scale of a map
y The choice of scale of map to be selected is dependent upon-
(a) The use of map
(b) The extent of territory to be represented
During deciding the scale of map, the following points are taken into
consideration:
(i) Scale should be chosen larger enough, so that in scaling or plotting
distance from the finished map it will not be necessary to read the
scale closer than 0.25 mm.
(ii) Choose as small a scale as is consistent with a clear representation of
smallest detail desired.
1 1
(a) Geographical Survey 1 cm = 5 km to 160 km to
500000 16000000
(ii) T
own Planning Schemes, 1 1
reservoirs etc. 1 cm = 50 m to 100 m to
5000 10000
(iv) S
mall Scale Topographic 1 cm = 0.25 km to 2.5 1 1
to
Maps km 25000 250000
11.
Chapter 1
Example 1.6 Construct a plain scale of 1cm = 5 meters and show 56 meters.
Solution :
Example- m, dm, cm
12.
Chapter 1
1 11'
=
10 AB
1
11' = AB
10
1
So, 1-1’ represent AB
10
2
Similarly, 2-2’ = AB
10
9
9-9’ = AB
10
13.
Chapter 1
y The vernier consist of small scale called the “Vernier scale” which moves along the graduated
scale / main scale.
y The division of vernier scale are made either slightly longer or shorter than that of main
scale and it has an index mark (arrow) which represents zero of vernier scale.
14.
Chapter 1
(a) Direct vernier
y In direct vernier, the reading on both vernier & main scale increases in the same
direction and the divisions on vernier scale are slightly shorter than the division of
main scale.
y Considering the n divisions on the vernier scale are equal to the length of (n–1)
division on main scale.
nV = (n–1)S
(n − 1) S
V=
n
S
LC =
n
Figure 1.7: Double Direct Vernier
15.
Chapter 1
n + 1
V= S
n
n + 1
=LC S − S
n
S
LC =
n
16.
Chapter 1
(2n–1) S = nV
(2n − 1)S
V=
n
(2n − 1)S
LS = 2S–V = 2S–
n
(i) Precision : Degree of perfection or degree of fineness used in instruments, Introduction and Linear Measurement
methods of observations and observation is termed as precision.
(ii) Accuracy : Degree of perfection obtained in using instruments, methods
of observation and observation is termed as accuracy.
Note :
(a) The difference between two measured values of same quantity is
known as discrepancy.
(b) It is not same as an Error.
(c) A small discrepancy may have great error and a large discrepancy
may have small error.
17.
Chapter 1
(iii) Error : It is the difference between a measured value and true value of
quantity.
Since true value of the quantity is not known, true error of measurement
cannot be found, hence measurement is done in a certain limits of error
prescribed.
18.
Chapter 1
(c) Compensation / Accidental / Random Error
y The errors which remains after the mistakes and systematic error are
removed is known as compensation error. These are random in nature and
caused mainly due the limitations of observer and instruments.
y These errors follow the law of probability:
(i) Small error occurs more frequently than large once.
(ii) Positive and negative errors are equally likely.
(iii) Very large errors are seldom.
(iv) It can be represented by normal distribution curve.
1
(v) Random error is proportional to , where N is number of observations.
N
Example 1.7: Which of the following error follows the theory of probability
(a) Random error (b) Cumulative error
(c) Both random and cumulative error (d) Mistakes
Solution : The compensation or random errors follows the law of probability.
The error is mainly caused due to limitations of observer and instruments
and these are random in nature.
So the correct answer is (a).
Figure 1.10
19.
Chapter 1
(vii) Offset
y It is the distance of offset from the survey line.
Introduction and Linear Measurement
(viii) Chainage
y It is the distance measured along the main survey line in the direction of
progress of work.
y It is generally used in linear construction projects.
Example- Roads, railways, sewers, water pipelines, tunnels etc.
20.
Chapter 1
1.6.2 Well condition triangle
y It is a triangle if all intersections of lines are clear for plotting purpose.
y If the angle between the lines is 30o-120o, clear intersection is achieved.
y Triangle having angle less than 30o are considered as ill conditioned triangle
Types of Chain : -
(a) Revenue Chain – It is a 33ft. long chain, having 16 links, each link being Introduction and Linear Measurement
1
2 ft. long. It is used for the measurement of fields in cadastral survey.
16
(b) Gunter’s Chain – It is a 66 ft. long chain, having 100 links, each link
being 0.6 ft or 7.92 inches long. Gunter chain is preferred if the linear
measurements are required in furlong and miles.
(c) Engineer’s Chain- It is a 100 ft. long chain, having 100 links, each link being
1 ft. long. It is used if the distances measured are in feet and decimal.
(d) Metric Chain – The availability of these chains are in the lengths of 5,
10, 20 and 30 meters. Normally 20 m chain with 100 links and 30 m
chain with 150 links are used.
21.
Chapter 1
Note :
(a) 1 mile = 80 Gunter’s chain
(b) 1 acre = (10 Gunter’s chain)2
(c) As per IS specification, every meter length of chain should be individually accurate to
within ± 2mm when measured under a tension of 80 N.
(d) The limit for overall length of the chain should be as follows:
(i) 20 m ± 5mm for 20 m chain
Introduction and Linear Measurement
22.
Chapter 1
(ii) Tapes
y The tapes are easy to handle and more precise than chains.
23.
Chapter 1
(iii) Pegs
y There are used to mark definite points on ground from which measurements
are to be taken or any instruments is to be set.
(iv) Arrow
24.
Chapter 1
(v) Ranging Rod
y Intermediate points lying on the straight line used to join the end stations,
can be located using ranging rod.
y The material of these rod is generally well-seasoned, straight grained timber
and cross-sectional shape consists of circular or octagonal pattern in 3cm
nominal diameter.
y The length of rod kept between 2m to 3m.
y For clear identification of measurement alternate bands of red/black and
white colour having 200 mm length are imprinted on them.
y Major difficulty in measurement occurs when the observation point lies at
more than 200m distance. To overcome this each rod should have a flag(30
to 50 cm square) tied near its top having colour any of red, white or yellow.
25.
Chapter 1
26.
Chapter 1
(c) In order to set out any desired angle from the survey line “ADJUSTABLE CROSS
STAFF”can be used.
It consists of two cylinders of equal diameter which can rotate over each other.
Lower cylinder consists of main and submain scale and upper cylinder consist of
vernier scale and a slit to provide a line of sight.
y It is a small instrument used to set out right angles and is more convenient and
accurate than cross staff.
y The two mirrors Horizontal (H) and Index (I) are placed at an angle of 45o.
27.
Chapter 1
y The fully silvered mirror ‘I’, is placed opposite to the opening F & the mirror
H, which is half silvered (silvered on the top and unsilvered at the bottom) is
placed, facing the opening E.
y It works on the principle of “Double Reflection” i.e. If a ray of light is reflected
or undergoes reflection successively than the angle between the incident and
reflected light is twice the angle between the reflecting surface.
Note : Instead of using two mirrors, a prism can also be used having
two reflecting sides at angle of 45o and the unit is termed as “PRISM
SQUARE”.
28.
Chapter 1
(x) Line Ranger
y It is a device which is used to set intermediate points, on the
survey lines.
y It consist of two right angled isosceles triangular prism placed
one over each other.
y The diagonal of these two prisms are painted silvered to from the
reflecting surface.
1.7 RANGING
y Ranging can be carried out through any of the following methods:
(a) Direct Ranging
Figure 1.25: Line Ranger
Figure 1.26
On the intermediate points along the chain line, the ranging rods
are placed by the direct observation from either of the end stations.
(b) Indirect Ranging
Figure 1.27
In the indirect ranging, the end stations are not visible due to the
long distances between them or due to the raised ground level. It
can be carried out as follows:
29.
Chapter 1
Figure 1.28
=
AB AB'2 + BB'2
AB' AP ' AB' AQ '
= = , [Law of similarity of triangles]
BB' P 'P BB' Q 'Q
Introduction and Linear Measurement
Solution : The total numbers of links provided in a Gunter’s chain is 100 and
the length of the Gunter’s chain is 66 ft.
To collect the details of the object in an area, tie line is used.
So, the correct answer is (b) and (d).
30.
Chapter 1
Example 1.9: The correct order of the tapes based on their accuracy is –
(a) Metallic tape > Invar tape > Steel tape >Linen tape
(b) Linen tape > Metallic tape > Invar tape > Steel tape
(c) Invar tape > Steel tape > Metallic tape >Linen tape
(d) Metallic tape >Linen tape > Steel tape > Invar tape
Example 1.10: The chain which is found to be too short on testing can be
adjusted by
(a) Replacing one or more small circular rings by bigger ones
(b) Straightening the links
(c) Flattening the circular rings
(d) All the above
1.8 CHAINING
The methods used to carry out chaining are as follows:
(a) On smooth level ground
y It is necessary to establish the intermediate points through ranging, for the
Definitions
31.
Chapter 1
32.
Chapter 1
1.9 ERRORS AND CORRECTION IN CHAINING / TAPING
1.9.1 Error
y The difference between the measured length and true length is termed as
error.
Error = Measured length – True length
True length = Measured length – Error
Correction = True length – Measured length
True length = Measured length + Correction
y Error in chaining can be of following types:
(a) Mistakes
(b) Cumulative / Systematic error: This error is directly proportional to the
length of line and may be positive or negative.
(c) Compensating / Random error: : This error is directly proportional to
square root of length of line to be measured.
L'
L= l '×
l
l'
L = L '
l
33.
Chapter 1
l '
=
Cs L ' − 1
l
l '− l
Cs = L '
l
1000
l = 20 m
l’ = 20 – 16 × 10–2 = 19.84 m
Shrunk length
Shrunk factor =
Original length
9.77
=SF = 0.977
10
58.2 58.2
Actual area before shrunk = 2
= = 60.972cm2 ≈ 60.97cm2
(SF) (0.977)2
34.
Chapter 1
Area of survey = 60.97(10)2
= 6097 m2
= 6097×10–4 Hectare
= 0.6097 Hectare
2
l'
Correct area of survey
= ×A
l
2
19.84
= × 0.6097 = 0.59998 Hectare
20
Example 1.12 : A 20m chain was used to measure a distance of 2500 m
and found that the chain was 10 cm too long. By the end of the day a
total distance of 5000 m was measured, and chain was found to be 18
cm too long. What is the true distance if the chain was correct before the
commencement of work?
Cg =−L(1 − cos θ)
Figure 1.29
35.
Chapter 1
Cg = L2 − h2 − L
h2
= L 1 − 2 − 1
L
1 h2 h4
Cg = L 1 − − + other higher terms − 1 (by Binomial expansion)
2 L2 8L4
Neglecting higher terms of h
h2
Cg = L 1 − 2 − 1
2L
h2
Cg = −
2L
h4
Note: Correction is increased by when higher terms of h are considered.
8L3
Note: Now all the further correction are applicable for TAPE only.
P = Applied pull
A = Cross section area of tape
E = Modulus of elasticity of tape
L = Measured length.
Case 1: When applied pull is greater than the standard pull (P > PS), the length
of tape increases and the measured distance is found to be lesser than the
actual distance, then the applied correction (CP) becomes positive (+).
36.
Chapter 1
Case 2: When applied pull is lesser than the standard pull (P < PS), the length
of tape decreases and measured distance is found to be greater than the
actual distance, then the applied correction (CP) becomes negative (-).
w2l 3
Csag =
24p2
37.
Chapter 1
Case (a): If the tape has been standardised on flat and used in catenary,
then applied sag correction (Csag) would be negative (-).
Case (b): If the tape has been standardised on catenary and is used on flat,
then applied sag correction (Csag) would be positive (+).
Figure 1.31
R + h
Ch = Le –L
R
=L −L
R + h
hL
Ch = −
R+h
38.
Chapter 1
i.e, R >> h ⇒ R + h ~ R
hL
Ch = −
R
Where, L = Measured horizontal distance
h = Mean equivalent of the base line above MSL
R = Radius of earth
θ = Angle subtended at the centre of the earth
Solution:
Given: P0 = 44.5 N; P = 100 N
A = 2 mm2; measured length = 29.861 m
a = 1.12×10–5/oC; l’ = 30.004 m
E = 2×105 N/mm2 ; l = 30 m
Tm = 10oC
T0 = 20oC
w = 0.16 N/m
l '− l
Correction due to standardisation = measured length
l
Introduction and Linear Measurement
30.004 − 30
Cs = 29.861
30
Cs = 0.00398 m
Correction for slope (Cg) = –L (1– cos θ)
Cg = –29.861 (1– cos 3o45’)
Cg = –0.064m
(P− P0 )L
∴ Correction for pull (Cp) =
AE
39.
Chapter 1
(100 − 44.5)29.861
C p=
2 × 2 × 105
Cp= 0.004m
Correction for temperature (Ct) = α (Tm –T0)L
Ct = 1.12 ×10–5 (10–20) 29.861
Ct = –0.003 m
w2l 3
Correction for (Csag) = -
24P2
(0.16)2 (29.861)3
Csag = −
24(100)2
Csag = –0.00284 m
Total correction = 0.00398 –0.064 + 0.004 – 0.003– 0.00284 = –0.0619 m
Correct horizontal distance = 29.861 – 0.0619 = 29.799 m
(a) Reconnaissance
y Reconnaissance is the method of preliminary inspection of the area to be
surveyed to collect information of the principle features of the ground & get
some idea of the terrain.
y In this ground is examined and decided upon for best possible arrangement
of triangles and best possible marking of main survey stations and survey
lines.
(b) Marking of Stations
y Once reconnaissance is done, the main stations are being marked on
ground such that station can be readily located after words.
40.
Chapter 1
(c) Running Survey Lines
y Survey lines are run to measure the distance between main stations and
locate the adjacent details by offset.
(d) Taking Offset
y It is defined as lateral distance measured from the survey line to the station
whose detail is to be plotted.
The offsets are of two types:
(i) Perpendicular offset / offset
(ii) Oblique offset
Figure 1.33
41.
Chapter 1
(l sin θ)2 + x2
Length of error on plan =
S
For limiting length of offset :
Length of error on plane < 0.025 cm
(l sin θ)2 + x2
Introduction and Linear Measurement
< 0.025
S Figure 1.35
1
l< (0.025 S)2 − x2
sin θ
42.
Chapter 1
Example 1.14: If the maximum error allowed in laying direction of offset is
6o, then calculate the limiting length of offset for following drawing scales
(i) 1 cm = 60 m (ii) 1 cm = 6m
1
= 30 (0.025 × 60)2 − (0.25)2
sin θ
1.479
sin θ =
30
θ = 2.82o
Example 1.16: An offset is measured with an accuracy of 1 in 100. If the Introduction and Linear Measurement
scale of plotting is 1 cm = 10 m and the displacement of the point due to
incorrect length and that due to incorrect direction are equal, then what
would be the limiting length of the offset ?
Solution: Given, Accuracy = 1 in 100
l l
Error in linear measurement (x) = = m
r 100
Error due to incorrect direction = l × sin q
l
= l sin θ
100
43.
Chapter 1
1
= 100
sin θ
Given, the error is in both linear measurement and direction
1
So,
= l (0.025S)2 − x2
sin θ
1 l
= 100,
= =
S 10, x
sin θ 100
2
l
=l 100 (0.025 × 10)2 −
100
l l2
= 0.0625 −
100 104
2
l l2
= 0.0625 −
100 104
2l 2
= 0.0625
104
l = 17.67m
1.11 OBSTACLES IN CHAINING
The obstacles may be divided into two classes :
(a) Obstacles to measurement
(b) Obstacles to alignment
Introduction and Linear Measurement
Figure 1.36
44.
Chapter 1
1.12 CROSS STAFF SURVEY
Figure 1.37
A = A1 + A2 + A3 + A4 + A5 + A6
A = ∑Ai
y The cross staff survey is a special type of chain survey to locate the
boundaries of a field for calculating area.
y In this survey a base line is selected through the middle portion of the field
and the entire area is divided into a number of simple regular figures like
triangle and trapezium.
y In this method cross staff is used for setting out the perpendicular to base
line.
Example 1.17: Show the cross-staff survey of a field ABCDEF and from the
field book measurement given and complete the area of field.
45.
Chapter 1
Solution :
Mean
Area Chainage Base Length Perpendicular
Perpendicular Area (m2)
No (m) (m) offset
offset
1 0-200 200 120 60 12000
2 0-300 300 150 75 22500
3 200-600 400 120-140 130 52000
4 300-750 450 150-160 155 69750
5 600-1000 400 140 70 28000
6 750-1000 250 160 80 20000
∑=
204250m2
Introduction and Linear Measurement
Keywords
46.
2 Compass Surveying
Chapter 2
2.1 INTRODUCTION
y A network of control points is made with using the linear measurement
done by chain in chain surveying.
y Whereas in compass surveying these control points are plotted by using
the both linear and angular measurements and this process is called
“Traversing”.
Definitions
y A closed traverse starts from a station and closes either on the same
station or another station whose location is already known.
y Loop traverse: Closed traverse which starts and ends at the same point
whose location is known.
47.
Chapter 2
y Link traverse: Closed traverse which starts and end at different point
whose location is not known.
y In closed traverse detection and adjustment or balance of errors is easy
48.
Chapter 2
Do You Know?
Compass Surveying
49.
Chapter 2
Bearing :
Definitions
Bearing: The horizontal angle made by the traverse line with reference
line/meridian is termed as bearing.
y Depending upon the reference line selected, these bearings are of following
types:
50.
Chapter 2
(b) Quadrantal Bearing System (Reduced bearing)
y Quadrant bearing (Q.B.) a line is the acute angle, which the line makes with
the reference meridian.
y It can be measured from north or south point whichever is closer.
y It is measured in both clockwise and anticlockwise direction.
y It varies in range the of 0 – 90°.
y It is measured with the help of “SURVEYOR’S COMPASS”.
y QB is reported as follows:
(i) First the letter N or S representing north or south point is mentioned.
(ii) Mention the angle of the bearing.
(iii) Lastly E or W representing east or west point is reported.
OA NαE QB 0° - 90°
51.
Chapter 2
OP 0-90° WCB NE
OQ 90° - 180° 180° - WCB SE
OR 180° - 270° WCB - 180° SW
OS 270° - 360° 360° - WCB NW
When a line points towards north, south, east and west it is reported
as due north, due south, due east and due west respectively.
S0° : Due South
N0° : Due North
N90°W or S 90°W : Due West
N90°E or S 90°E : Due East
y Back Bearing: The bearing of line in the direction opposite to the progress
of survey is called back bearing (BB).
Line FB BB
AB a β
BA β a
Compass Surveying
52.
Chapter 2
y FB and BB of a line differ by an angle of 180°.
(i) If FB < 180°, BB = FB + 180°
IF FB > 180°, BB = FB – 180°
Hence if bearing of the line is reported in WCB system then BB = FB ± 180°.
(ii) If bearing of line reported in QB system, then
Back bearing angle = Fore bearing angle
But N → S and E → W and vice versa.
Example 2.1: Fore bearing of different lines are given, compute the
corresponding back bearing of the lines.
(a) 26° 45′ (b) 340°
(c) S40° 40′W (d) N37°W
Solution:
(a)
Compass Surveying
53.
Chapter 2
(c)
FB = S40°40′W
BB = N40°40′E
(d)
FB = N37°W
BB = S37°E
Solution:
(i)
Compass Surveying
54.
Chapter 2
QB = S30°36′E
It lies in second quadrant.
So, WCB = 180° - 30°36′
WCB = 149°24′
(ii)
QB = N6°40′W
It lies in IV quadrant
So, WCB = 360° - 6°40′
WCB = 353°20′
Compass Surveying
Figure 2.6
55.
Chapter 2
Case II: If the traverse runs in anticlockwise direction, included angles
are interior angles.
Figure 2.7
Figure 2.8
56.
Chapter 2
(b) When bearings are measured on opposite side of common meridian.
Figure 2.9
Interior angle θ = α + b
Compass Surveying
Figure 2.10
57.
Chapter 2
Figure 2.11
q = 90° – α + 90° + b
q = 180°+ β – α
Figure 2.12
θ=α–b
NOTE: If α – β is (-) ve, add 360° to get the included angles, which will be
an exterior included angle.
58.
Chapter 2
(b) The traversing is done in anticlockwise direction OQPO, OQ is forward
line and PO is previous line.
Figure 2.13
Figure 2.14
Fore bearing of next line = Fore bearing of previous line + Included angle
Compass Surveying
NOTE:
(a) If this sum is more than 180°, subtract 180°.
(b) If this sum is less than 180°, add 180°.
(c) If this sum is more than 540°, subtract 540°.
59.
Chapter 2
Example 2.3: The following bearings were observed for a closed traverse
ABCDEA, compute the interior angles.
Line AB BC CD DE EA
Solution:
Method-I
60.
Chapter 2
∠A = 90°
∠B = FB of BC – BB of AB = 80°30′ - [140° 30′ + 180°]
= -240° + 360° (Since 240° is negative, add 360°)
∠B = 120°
∠C = FB of CD – BB of BC = 340° - [80°30′ + 180°]
∠C = 79°30′
∠D = FB of DE – BB of CD = 290°30′ - [340° - 180°]
∠D = 130°30′
∠E = FB of EA – BB of DE = 230°30′ - [290° 30′ - 180°]
∠E = 120°
Check = (2n – 4) × 90°= ( 2 × 5 – 4)90° = 540°
∠A + ∠B + ∠C + ∠D + ∠E = 540°
Method-II
By calculating interior angles through simple mathematical operations
Compass Surveying
∠A = 140°30′ - 50°30′
∠A = 90°
∠B = 39°30′ + 80°30′
61.
Chapter 2
∠B = 120°
∠C = 340° - 180° - 80°30′
∠C = 79°30′
∠D = 290°30’ - 180° + 20° = 130°30′
∠E = 69°30′ + 50°30′ = 120°
Check: (2n – 4) × 90° = 540°
∠A + ∠B + ∠C + ∠D + ∠E = 540°
NOTE: (a) Sum of all interior angles of a polygon = (2n – 4)90°
(b) Sum of all exterior angler of a polygon = (2n + 4)90°
Solution:
Compass Surveying
62.
Chapter 2
Method-I
FB of a line = FB of previous line + clockwise included angles
[Generally clockwise angles will be obtained if we proceed in the
anticlockwise direction round the traverse]
FB of AB = 242°
FB of BC = FB of AB + ∠ABC
= 242° + 125°15′
= 367°15′ (Since > 180°, subtract 180°)
= 367°15′ - 180°
FB of BC = 187°15′
FB of CD = FB of BC + ∠BCD
= 187°15′ + 146°45′
= 333°45′ (Since > 180°, subtract 180°)
FB of CD = 333°45′ - 180° = 153°15′
FB of DE = FB of CD + ∠CDE
= 153°45′ + 104°
= 257°45′ (Since > 180°, subtract 180°)
FB of DE = 257°45′ - 180°
= 77°45′
FB of EF = FB of DE + ∠DEF
= 77°45′ + 100°15′
= 178° (since < 180° add 180°)
FB of EF = 178° + 180°
= 358°
FB of FG = FB of EF + ∠EFG
= 358° + 210°45′
Compass Surveying
63.
Chapter 2
Method-II
FB of AB = 242°
FB of BC = BB of AB + ∠ABC
FB of BC = 187°45′
FB of CD = BB of BC + ∠BCD
= (187°15′ - 180°) + 146°30′
FB of CD = 153°45′
FB of DE = BB of CD + ∠CDE
FB of EF = BB of DE + ∠DEF
FB of EF = 358°
FB of FG = BB of EF + ∠EFG
FB of FG = 28°45′
Definitions
Compass Surveying
64.
Chapter 2
Figure 2.15: Magnetic Declination
y Declination at a point is not constant and varies from time to time due to
65.
Chapter 2
66.
Chapter 2
Figure 2.16
NOTE: The above analysis is valid, if bearing is in WCB system, if bearings are
in quadrantal bearing system, then either convert it in WCB system and do
the above analysis or find the relation for each quadrant between TB & MB.
67.
Chapter 2
Example 2.6: A line AB had the MB 44°20′ in 1910, when the declination was
4°20′W. Determine the MB of the same line in 1990 if the annual declination
change is observed as 6′ eastward?
Solution:
TB in 1910 = MB – d
= 44°20′ - 4°20′ = 40°
1
Total change in declination = (1990 − 1910)6 ×
60
1
= 80 × 6 ×
60
= 8°E
Compass Surveying
TB1990 = MB1990 + d
68.
Chapter 2
MB1990 = 40° - 3°40′
MB1990 = 36°20′
(i) Observe a line whose fore and back bearing differ exactly by 180°.
(ii) The end stations of such a line are free from local attraction. All the
bearings observed on these stations are assumed to be free from
local attraction.
69.
Chapter 2
(iii) The BB of the preceding line and the FB of the next line will also
be correct since these are observed at the station free from local
attraction. The correct FB of the preceding line or BB of the next line
can be calculated by adding or subtracting 180°.
(iv) If the observed bearing is more than correct bearing determined in
step (iii), the error at the station will be positive and therefore the
correction will be negative and vice versa.
(v) The bearings of the lines are thus corrected one by one in continuation.
(b) By Included angles: This is most suitable for a closed traverse. The
following process is carried out:
(i) Calculate the interior angles of the traverse and their sum against
(2N ± 4)90°. If there is any error in the observed bearing other than
local attraction, the theoretical sum of included angles will not be
equal to the sum of calculated angles.
(ii) Distribute the error, if any equally to all the angles.
(iii) Locate the line, whose FB and BB differ by 180°. The bearings of this
lines are taken to be correct.
(iv) Calculate the correct bearing of the successive lines by using the
corrected observed bearing and the corrected included angles.
NOTE: It may happen that in a closed traverse no lines have a difference of
180° in FB & BB. In such a case, the line with least discrepancy is selected.
Then the FB and BB of this line are adjusted to make the difference exactly
180°. Now assuming the FB of this line to be correct, the correct FB of all
other lines are calculated.
QR 108°15′ RQ 286°15′
RS 201°30′ SR 20°30′
ST 321°45′ TS 141°45′
Compass Surveying
The station (s) most likely to be affected by the local attraction is/are
(a) Only R (b) R and S
(c) P and Q (d) Only S
Answer: (a) (GATE-2017, SET-I)
70.
Chapter 2
Example 2.7: A compass traverse ABCDEA was run anticlockwise and
following bearings were taken, where local attraction was suspected.
Determine the local attraction and corrected bearings.
Line FB BB
AB 150° 329°45′
BC 77°30′ 256°
CD 41°30′ 222°45′
DE 314°15′ 134°45′
EA 220°15′ 40°15′
Solution:
Compass Surveying
71.
Chapter 2
Line FB BB BB-FB
Since for line EA = FB – BB = 180°, station E & A are free from local attraction.
Therefore, the BB of DE and FB of AB is also correct.
∴ FB of AB = 150°
BB of AB = 150° + 180° = 330°
Observed BB of AB = 329°45′
Local attraction = 329°45′ - 330° = - 15′
Compass Surveying
∴ FB of BC = BB of AB + Interior angle B
= 330° + 107°45′ - 360° = 77°45′
BB of BC = 77°45′ + 180° = 257°45′
72.
Chapter 2
∴ FB of CD = BB of BC + Interior angle C
= 257°45′ + 145°30′ - 360° = 43°15′
BB of CD = 43°15′ + 180° = 223°15′
∴ FB of DE = BB of CD + interior angle D
= 223°15′ + 91°30′ = 314°45′
BB of DE = 314°45′ - 180° = 134°45′
∴ FB of EA = BB of DE + interior angle E
= 134°45′ + 85°30′ = 220°15′
BB of EA = 220°15′ - 180° = 40°15′
OR
Since there is no error in the sum of interior angles and the station E & A
are free from local attraction.
FB of AB = 150°
BB of AB = 150° + 180° = 330°
Observed BB of AB = 329°45′
Hence, local attraction = 329°45′ - 330° = -15′
Error = -15′, correction = + 15′
Correction at station B = +15′
∴ FB of BC = 77°30′ + 15′ = 77°45′
BB of BC = 77°45′ + 180° = 257°45′
Observed bearing of BC = 256°
Error = -1°45′
Correction = +1°45′
Correction at station C = +1°45′
∴ FB of CD = 41°30′ + 1°45′ = 43°15′
BB of CD = 43°15′ + 180° = 223°15′
Observed bearing of CD = 222°45′
Error = -30′, correction = +30′
Correction at station, D = +30′
∴ FB of DE = 314°15′ + 30′ = 314°45′
Compass Surveying
73.
Chapter 2
Example 2.8: Find which stations are affected by local attraction. Work out
correct bearing of the lines of a closed traverse ABCDEA.
Line FB BB
AB 195°30′ 17°
BC 73°30′ 250°30′
CD 36°15′ 214°30′
DE 266°45′ 84°45′
EA 234°15′ 57°
Solution:
Line FB BB BB - FB
74.
Chapter 2
Included angles (interior) can be determined by using both FB & BB of line.
∠B = FB of BC – BB of AB
= 73°30′ - 17° = 56°30′
∠C = FB of CD – BB of BC
= 36°15′ - 250°30′ = -214°15′ + 360° = 145°45′
∠D = FB of DE – BB of CD
= 266°45′ - 214°30′ = 52°15′
∠E = FB of EA – BB of DE
= 234°15′ - 84°45′ = 149°30′
∠A = FB of AB – BB of EA
= 195°30′ – 57° = 138°30′
Sum of included angles = ∠A + ∠B + ∠C + ∠D + ∠E
= 542°30′
Theoretical Sum = (2N – 4)90° = (2 × 5 – 4)90° = 540°
Error = 542°30′ - 540° = 2°30′
2°30′
Correction for each angle = − =−30′
5
Hence corrected angles, ∠A = 138°30′ - 30′ = 138°
∠B = 56°30′ - 30′ = 56°
∠C = 145°45′ - 30′ = 145°15′
∠D = 52°15′ – 30′ = 51°45′
∠E = 149°30′ - 30′ = 149°
∴ Since the difference in FB and BB of line AB is nearest to 180°, it is
considered for computation.
Error in difference of FB and BB of AB = 178°30′ - 180°
= -1°30′
Hence correct FB of AB = 195°30′ + 45′ = 196°15
Correct BB of AB = 17° - 45′ = 16°15′
∴ FB of BC = BB of AB + interior angle B
= 16°15′ + 56° = 72°15′
BB of BC = 72°15′ + 180° = 252°15′
Compass Surveying
∴ FB of CD = BB of BC + interior angle C
= 252°15′ + 145°15′ - 360° = 37°30′
BB of CD = 37°30′ + 180° = 217°30′
75.
Chapter 2
∴ FB of DE = BB of CD + interior angle D
= 217°30′ + 51°45′ = 269°15′
BB of DE = 269°15′ - 180° = 89°15′
∴ FB of EA = BB of DE + interior angle E
= 89°15′ + 149° = 238°15′
BB of EA = 238°15′ - 180° = 58°15′
Example 2.9: In an anticlockwise traverse ABCA all the sides were equal.
Magnetic fore bearing of BC was obtained to be 15°20′. The bearing of
sun was observed to be 185°30′ at local noon with a prismatic compass.
Calculate the MB & TB of all sides of the traverse?
Solution:
TB of sun at noon = 180°
MB of sun at noon = 185°30′
d = TB – MB = 180° - 185°30′ = 5°30′W
∴ FB of BC = 15°20′
BB of BC = 15°20′ + 180° = 195°20′
∴ FB of CA = BB of BC + interior angle C = 195°20′ + 60° = 255°20′
BB of CA = 255°20′ - 180° = 75°20′
Compass Surveying
∴ FB of AB = BB of CA + interior angle A
= 75°20′ + 60° = 135°20′
BB of AB = 135°20′ + 180° = 315°20′
76.
Chapter 2
MB TB
Line
FB BB FB BB
Example 2.10: Three ships A, B & C started sailing from Kerala at the same
time in three directions. The speed of all the three ships was same equal
to 60 km/hr. Their bearings were measured to be N70°E, S60°E, S10°E
respectively. After an hour, the captain of ship B determined the bearings
of the other two ships with respect to his own ship. After that he found out
the distances. Calculate the value of bearings and distances which might
have been determined by the captain.
Solution:
180° − 50°
∠OCB = ∠OBC =
2
= 65° (isosceles triangle)
77.
Chapter 2
CD
Cos65° =
30
CD = 60cos65°
CB = 2 × 60 cos 65°
CB = 50.71 km ………(i)
Bearing of Line OB = S60°E
WCB = 180° - 60°
= 120° = FB of OB
BB of OB = 120° + 180° = 300°
FB of BC = BB of OB – ∠B
= 300° - 65° = 235°
FB of BC = 235° (WCB)
In QB, 235° is in 3rd quadrant, QB = 235° - 180° = S55°W
∠BOA = 180° - 60° - 70° = 50°
180° − 50°
∠OAB = ∠OBA = = 65°
2
AB = 2 × 60cos65°
= 50.71 km [Similar as step (i)]
FB of BA = BB of OB + ∠B
= 300° + 65° = 365° > 360°
Compass Surveying
Hence FB of BA = 5° = N5°E
78.
Chapter 2
Previous Year’s Questions
AB 126°45′ 308°00′
BC 45°15′ 227°30′
CD 340°30′ 161°45′
DE 258°30′ 78°30′
EA 216°30′ 31°45′
2.5 DIP
Compass Surveying
79.
Chapter 2
y As earth has its own magnetic field, line of forces are created by this and
are directed towards the north and south magnetic poles.
y A freely suspended magnetic needle aligns itself with the lines of magnetic
forces of the earth.
y The angle made by the lines of magnetic field with the earth surface is
called as ‘Dip’.
y Dip is zero at equator and 90° at poles.
y At other places, the value of dip varies between (0 - 90°).
y The graduated ring is directly fixed to the box which governs the size of
the compass, normally that is in range of 10 – 15 cm (but can extend upto
5cm – 20 cm).
y The graduations are marked in degree and half degree.
80.
Chapter 2
y When compass is not in use, object vane is folded which lift the needle
above the pivot point, thereby avoids the unnecessary wear and tear of
pivot.
y The magnetic needle is made up of magnetic steel.
y It is used to measure quadrantal bearing.
y Since the graduated ring turns with the sight vane not with the needle, the
direction E and W on the ring are reversed from the actual.
y The N-mark rotates as the line of sight is rotated, but the north end of
needle aligned to the magnetic north, hence directly giving the QB.
Q. What is the reason of providing small metallic rider over the needle
in surveyor compass?
A. A small metallic rider is provided in order to avoid the dip of the
needle, it is capable of sliding over it.
Compass Surveying
81.
Chapter 2
B. Prismatic Compass
In this prism is used for taking the observation, thereby it is termed
as prismatic compass.
Its size is comparatively smaller than surveyor’s compass (8.5 - 10
cm).
The ring is graduated in degrees and half degrees and is
attached with needle and not with vane as in case of surveyor’s
compass.
Here graduations increases in clockwise direction with zero
coinciding with the south end of the needle.
Compass Surveying
82.
Chapter 2
Figure 2.20: Prismatic Compass
83.
Chapter 2
Magnetic
1. Edge bar type needle. Broad needle
Needle
Keywords
Compass Surveying
84.
3 Theodolite
Chapter 3
3.1 INTRODUCTION
y It can also be used for different surveying operations like levelling, extension
of line and measurement of distance.
Theodolite
85.
Chapter 3
y The levelling head assembly consists of two parallel plates, which is separated by three
screws. “Tribrach” is the upper parallel plate of the levelling head and “Trivet/Foot plate” is
the lower plate of the levelling head.
y The trivet is a casing having a large hole in the centre with threads.
y The plumb bob can be suspended to a hook at the lower end of the inner spindle in the
trivet.
y It consists of foot screws for the levelling through bubble tube.
Theodolite
86.
Chapter 3
Figure 3.2
87.
Chapter 3
By using the upper clamp screw, the upper plate can be clamped to
the lower plate.
The upper plate consists of two verniers, designated as vernier A &
vernier B, which are fixed diametrically opposite to each other.
On clamping the upper clamp, the upper plate rotates with respect
to the lower plate and the vernier readings are changed.
If the upper clamp is clamped, the vernier readings does not change.
Readings are measured in minutes and seconds.
Least count = 20”
Figure 3.4
88.
Chapter 3
(a) Telescope
For sighting the objects, the telescope can be rotated in the vertical plane about the
horizontal axis.
Figure 3.5
89.
Chapter 3
Figure 3.7
90.
91.
Theodolite Chapter 3
Chapter 3
92.
Chapter 3
(iv) Horizontal axis: The axis about which the telescope and the vertical
circle rotate in the vertical plane. The horizontal axis is perpendicular
to the vertical axis.
(v) Telescope normal & inverted : Telescope is said to be normal / direct
when its vertical circle is to the left hand side of the observer and the
“bubbles (of the telescope) up” and it is said to be inverted when its
vertical circle is on right hand side of the observer and the “bubble
down”.
(vi) Centring: It is defined as the process of setting up the instrument
exactly over the station mark. For the purpose of centring, the plumb
bob suspended from a small hook attached to the underside of the
inner spindle is used.
(vii) Axis of level tube: The axis of level tube or the bubble line is a straight-
line tangent to the longitudinal curve of the level tube at its centre. It
is horizontal when the bubble is at centre.
(viii) Face right: When the vertical circle of a theodolite is on the right-
hand side of the observer, the position is known as face right and the
observation made is known as face right observation.
(ix) Face left: When the vertical circle of a theodolite is on the left-
hand side of the observer, the position is known as face left and the
observation made is known as face left observation.
(x) Transit/Plunging/Reversing: It is the process in which the telescope
is revolved about the horizontal axis in vertical plane by an angle of
180°, thus making it point in just opposite direction.
(xi) Swinging the telescope: It is the operation of revolving the telescope
in horizontal plane about its vertical axis. If swing is done in clockwise
direction, it is termed as right swing and if it is done in anti-clockwise
direction, it is termed as left swing.
(xii) Changing face: It is the operation of bringing the telescope from the
face left condition to the face right condition & vice-versa. It is done
by plunging the telescope and by swinging it by 180°.
(xiii) Line of sight: It is the imaginary line passing through the intersection
of the horizontal and vertical crosshairs of the diaphragm and the
optical centre of the object glass and its continuation. When the line
of sight comes in horizontal plane it is called as line of collimation.
The line of collimation axis is at right angle to the horizontal axis.
Theodolite
93.
Chapter 3
Example 3.2: The imaginary line tangential to the longitudinal curve of the
level at the centre of the tube is called as:
(a) Vertical axis (b) Horizontal axis
(c) Line of collimation (d) Axis of level tube
Solution: The straight line tangential to the longitudinal curve of the plate
level tube at its centre is known as axis of level tube.
So, the correct answer is (d).
94.
Chapter 3
Solution: Transiting is defined as the process of turning the theodolite telescope in the
vertical plane by 180° about the horizontal axis.
So, the correct answer is (d).
Theodolite
95.
Chapter 3
Definitions
Example 3.4: The temporary adjustments which are carried out before
taking observation at every set-up of the theodolite consist of
(i) Setting of the theodolite over a station
(ii) Levelling
(iii) Elimination of parallax
Select the correct option
(a) (i) and (ii) (b) Only (i)
Theodolite
96.
Chapter 3
Solution: The temporary adjustment of theodolite includes the following
operations:
(i) Setting up
(ii) Centring
(iii) Levelling
(iv) Elimination of parallax
So, the correct option is (d).
Figure 3.9
97.
Chapter 3
B. Method of Repetition
Figure 3.10
y Set the instrument over B (The face of the instrument should be left).
y Using the upper clamp and its tangent screw, set the vernier A to 0°. After
setting the vernier A to 0°, loosen the lower clamp and direct the telescope
towards the left-hand object A, and by using the lower clamp and its
tangent screw, bisect A exactly.
y Loosen the upper clamp and turn the telescope in clockwise direction and
with the help of upper clamp bisect the right-hand C exactly.
y By losing the lower clamp, turn the telescope in clockwise direction until
the object (A) or station A is sighted again. Check the vernier reading, it
should be same as before.
y By losing the upper clamp, turn the telescope in clockwise direction and
again sight C. With the help of the upper tangent screw, bisect C accurately.
The verniers will now show twice the value of the angle.
y Carry out the same process until the angle is repeated the required number
of times (usually 3). Take the readings from both the verniers. The final
readings after n repetitions should be approximately n × (∠ABC). Now the
sum is divided by the number of repetitions and the final result obtained
gives the correct value of angle ABC.
y Change the face of the instrument (now the face will be right). Repeat the
same process and determine another value of the angle ABC.
y At last, the required precise value of the angle (ABC) can be obtained by
taking the average of the two values of the angle obtained in the above
process.
Theodolite
98.
Chapter 3
Gray Matter Alert!!!
C. Method of Reiteration
Figure 3.11
y Set up the instrument over the station point O and carry out the levelling.
y By using the upper clamp and its tangent screw, set the vernier A to 0°.
y Station point A is known as the ‘Reference object’, thus direct the telescope
towards the station point A. Bisect it accurately by using the lower clamp
and its tangent screw. Now check the vernier A reading which should still
be 0°.
y By losing the upper clamp, rotate the telescope in clockwise direction until
the point B is exactly sighted by using the upper tangent screw. By using
both vernier, readings can be carried out whose average give the angle AOB
(after deducting 180° from the reading at vernier B).
Theodolite
99.
Chapter 3
y In the same way bisect C and D successively, take the readings on both
verniers at each bisection and determine the values of the angle BOC and
COD.
y By sighting towards the reference object (P) or the station-point A, close
the horizon.
y The reading at vernier A should be 360°. If not, then find the error (The
error occurs due to slip etc).
y If the error come out small then distribute it uniformly among the several
observed angles. But if error come out large, the existing readings make no
significance, and a new set of readings should be taken.
y Now change the face of the instrument and repeat the same process.
y True value is the mean of the two results for each angle.
Solution: To obtain the higher accuracy and to eliminate even the smallest
error, the method preferred is repetition.
So, the correct answer is (b).
Theodolite
100.
Chapter 3
3.8 MEASUREMENT OF VERTICAL ANGLES
y Set up the theodolite at O. Carry out the centring and levelling. Set the
zeros of the verniers at 0° mark of the vertical circle. Then clamp the
telescope.
y Bring the altitude bubble to the centre by clip screw. The line of the
collimation is exactly horizontal at this position.
y To measure the angle of elevation, the telescope is raised slowly to bisect
the point A accurately. Finally note the readings on both the verniers and
record the angle of elevation.
y Now change the face of the instrument and once again bisect the point A.
Note down the verniers readings.
y The correct angle of elevation is assumed to be the mean of the angles of
the observations.
3.9 MISCELLANEOUS OPERATIONS WITH THEODOLITE
A. Measurement of Direct Angle
y Set the theodolite at Q and carry out the levelling. With the face left and
telescope normal, the vernier A is set to zero.
y Loosen the lower clamp, direct the telescope towards P and using the
lower tangent screw, bisect it accurately.
y After losing the upper clamp, swing the telescope in clockwise direction
and sight R and using the upper tangent screw, bisect R accurately. Note
Theodolite
101.
Chapter 3
y Now transit the telescope, and by losing the lower clamp, take the back sight
on P. The reading obtained on the vernier will be same as in previous step.
y After losing the upper clamp, bisect R again. Note the readings on both the
verniers. The reading obtained will be equal to twice the angle. The angle
PQR will be determined by dividing the final reading by two.
Similarly, other angles can be measured.
Definitions
Direct angle: These are the angles measured clockwise from the
preceding line to the following line. They are also known as angle to
the right or azimuths from the back line and may vary from 0° to 360°.
102.
Chapter 3
Definitions
Deflection angle: It is the angle is the angle which a survey line makes
with the prolongation of the preceding line. It is designated as Right
(R) or Left (L) according as it is measured to the clockwise or anti-
clockwise from the prolongation of the previous line. Its values vary
from 0° to 180°.
103.
Chapter 3
y The axis of plate level must lie in a plane perpendicular to the vertical axis.
y Horizontal axis must pass through the centre of vertical circle.
y Vertical axis must pass through the centre of horizontal circle.
y The horizontal axis must be perpendicular to the vertical axis.
y The axis of the altitude level must be parallel to the line of sight.
y The vertical circle vernier must read zero when the line of collimation is horizontal.
y The line of collimation must be perpendicular to the horizontal axis at its intersection with
the vertical axis.
104.
Chapter 3
3.11.1 Instrumental Error
(i) Vertical index error
The axis of the altitude level tube must be truly horizontal when the bubble is in center.
The line of collimation should be parallel to the axis of the tube when vertical circle
reads zero.
But if it is not, vertical vernier C & D would not read zero when line of sight is
horizontal.
By taking the average of readings of face right and face left measurements, the error
can be eliminated.
(ii) Error due to imperfect graduations on circle
Imperfect graduations on circle are either due to manufacturing defect or due to
continuous use of the instrument.
By taking the observation in different parts of circle or by the method of repetition,
the error can be eliminated.
(iii) Error due to horizontal axis not being perpendicular to vertical axis
(a)
Theodolite
(b)
Figure 3.16
105.
Chapter 3
(iv) Error due to line of sight not being perpendicular to the horizontal axis
(a)
Theodolite
(b)
Figure 3.17
106.
Chapter 3
Angle measured between A & B in face left position :
θ1 = θ – e1 + e2
Angle measured between A & B in face right position :
θ2 = θ + e1 – e2
Average of angle measured between A & B in face right and left position.
q1 + q2 q − e1 + e2 + q − e2 + e1
= = q
2 2
In this case the line of sight does not revolve in vertical plane when
the telescope is lifted and lowered.
In this case it will generate a cone, axis of which coincide with the
horizontal axis.
The error due to line of sight not being perpendicular to the horizontal
axis can be eliminated by taking the average of face left and face
right measurements i.e. by double sighting.
(v) Error due to plate bubble tube not perpendicular to the vertical axis
Figure 3.18
a+β
q=
2
Theodolite
Figure 3.19
107.
Chapter 3
Solution: By reading both the verniers & taking mean of two, the error due
to eccentricity of verniers can be eliminated.
So, the correct answer is (a).
Keywords
108.
4 Levelling and Contouring
Chapter 4
PART-A: LEVELLING
4.1. INTRODUCTION
y Levelling is the process of determining the difference of elevations or levels
of different points on the earth surface.
y If all the heights of different points are measured relative to a plane, the
plane is termed as DATUM PLANE.
y In general, the datum plane is taken to be Mean Sea Level (MSL) to
standardize the measurement of height internationally.
y If the vertical distance of the point above or below the datum surface is
noted, it is termed as ELEVATION and if it is noted with respect to MSL, it
is termed as ALTITUDE.
Figure 4.1
Definitions
point.
Vertical Line: It is a line normal to the level line at a point. It is
represented by a plumb line.
Horizontal Plan: It is a plane tangential to the level surface at the
point under consideration. It is perpendicular to plumb line.
109.
Chapter 4
Definitions
Types of levelling
H = D tan
Levelling and Contouring
110.
Chapter 4
NOTE: Direct levelling is further classified as follows:
(i) Simple levelling
(ii) Differential levelling
(iii) Check levelling
(iv) Profile levelling
(v) Cross-section levelling
(vi) Fly levelling
(vii) Reciprocal levelling
y The principal axis of both the lenses must be in the same line.
y Principal axis is the common normal to both surface of the lenses.
y The optical centre may be defined as the point through which all the rays
of light passes without getting deviated.
y The line passing through optical centre and the centre of curvature of
lens is called optical axis.
111.
Chapter 4
Optical
axis
Convex
1′ Telescope tube
1 lens
3 3′
Principal
axis 2 2′ Principal
axis Convex lens
Figure 4.2
Convex lens
Concave lens
Figure 4.3
112.
Chapter 4
Gray Matter Alert!!!
2
f
3
Figure 4.4: Ramsden eyepiece
Adjusting screw
Glass tube
Bubble
Fluid with
Spring low viscosity
Levelling and Contouring
113.
Chapter 4
NOTE: Since the curved surface is exactly circular, equal distance on the
d
tube subtends equal angle at the centre of arc/curvature. i.e., f =
R
y The longitudinal tangent to the curved surface at mid-point represents the
axis of tube.
y When the bubble is centred the axis of tube is said to be horizontal and is
perpendicular to vertical axis.
Bubble
Bubble tube
Figure 4.6
Definitions
114.
Chapter 4
d 180 d
f= × × 60 × 60
R π
d
f =206265 seconds [1 radian = 206265 seconds]
R
If d = 2 mm
R R
206265 × 2 × 10−3
f =
R
412.53
f= (1 division is magnified)
R
Figure 4.7
NOTE: (a) The sensitivity is expressed as seconds/division.
(b) This is not a definite quantity unless the length of division is also
specified.
(c) If not mentioned length of division maybe taken as 2 mm.
NOTE: If the bubble is off centre by one division, the tube axis will also
make an angle of f with horizontal.
I
II
f
Divisions
R R
ff
ff f f
Figure 4.8
Levelling and Contouring
115.
Chapter 4
E
b
S
C a
F
D
Bubble
tube Bubble Sta
A L
Figure 4.9
d ds
f = =
R ndL
S
f= radian
Ln
116.
Chapter 4
Example 4.1: A staff reading taken on a staff held at a distance of 80 m from
the instrument with the bubble centre was 1.555 m. When the bubble was
moved to 6 divisions out of the centre of the staff reading was observed to
be 1.587 m. If the length of one division is 2 mm. Find the radius of curve
and sensitivity of tube.
ndL
Solution: R = 1.587 m
S
n = 6 divisions, d = 2 × 10–3m, L = 80 m
S
S = a – b = 1.587 – 1.555
nd a
S = 0.032 m
1.555 m
−3
6 × 2 × 10 × 80
R = = 30 m
0.032 a
S
Sensitivity f = radians
Ln
80 m
A B
S
= 206265 seconds
Ln
0.032
= 206265 ×
80 × 6
f = 13.75″ /division of 2 mm
206265 S
35 =
80 × 2
S = 0.027 m
117.
Chapter 4
4.4 LEVEL
y Levelling is done with the help of unit termed as level which are generally
of following types:
Eye-Piece Focusing
Screws Objective End
Telescope
Ray Shade
Diaphragm
Adjusting Screws
Levelling and Contouring
Foot Screws
118.
Chapter 4
(ii) Tiling level
y In tilting level, the telescope and vertical spindle are not casted rigidly with
each other.
y In this case telescope can tilt slightly in vertical plane with the help of tiling
screw.
y Here line of collimation is need not to be perpendicular to the vertical axis,
as it was must in dumpy level.
Definitions
Objective Telescope
End Eye-Piece
Level Tube
Spring Loaded
Diaphragm
Plunger
Ray Adjusting Screws
Shade
Tilting Screws
Tribrach
Foot Foot
Screws Screws
Levelling and Contouring
Trivet Stage
119.
Chapter 4
A B E
C
PLAN D F
Levelling
2.5 m staff
1.5 m 2m
1m 2m 2m 1.5 m (BS)
(IS) (IS) 1.8 m
(BS) (IS) (IS) (FS)
(FS)
100 m F
B D
A E
L-x section BM C
Figure 4.12
Definitions
Back Sight (BS): It is the first reading made with staff on a point
whose RL is known.
Fore Sight (FS): It is the last reading made with staff on a point before
changing instrument station.
Intermediate Sight (IS): All reading in between BS and FS made with
staff is termed as intermediate sight.
Changing Station: The station at which position of level is changed
is termed as changing station. At this station both BS and FS are
observed.
1.936 1.321
Levelling and Contouring
B
A
BM
201.132
Figure 4.13
120.
Chapter 4
y The level is set in the middle of both the points, a backsight is taken on the
rod held at the benchmark.
=HI Elv of BM + BS
On turning the telescope to view the rod held at point B, a foresight is taken
= HI − FS
Elv
BS IS FS
BM
A B
Figure 4.14
c a
d b 1.5 1.5
Q P
3.5 3.5
e
100 m
(100 m) P
Levelling and Contouring
Q
100 m
MSL MSL
121.
Chapter 4
In case I In case II
Dh = 3.5 – 1.5 = 2m (rise) Dh = 1.5 – 3.5 = –2m (fall)
RL of point Q RL of point Q
= RL of point P + Rise = RL of point P – Fall
= 100 + 2 = 102 m = 100 – 2 = 98 m
Example:
A 0.663 100.000
B 1.946 1.283 98.717
C 1.008 0.938 99.655
D 1.153 0.145 99.510
E 2.787 1.585 0.432 99.078
F 2.270 0.517 99.595
G 1.218 1.052 100.647
H 0.646 0.572 101.219
Check:
Last RL – First RL = 101.219 – 100 = 1.219
SRise – SFall = 3.079 – 1.86 = 1.219
SBS – SFS = 3.45 – 2.231 = 1.219
Hence, the calculation is correct.
BS
Levelling and Contouring
BM A
B
MSL
Figure 4.16
122.
Chapter 4
y HI = RL of BM + BS
y RL at any point = HI – Reading on staff (IS or FS)
y Check = SBS – SFS = Last RL – First RL
c a
d b 1.5 1.5
Q P
3.5 3.5
e
100 m
P Q
(100 m)
100 m
MSL MSL
In case I In case II
HI = RL of P + staff reading at P HI = 100 + 1.5 = 101.5 m
HI = 100 + 3.5 = 103.5 m Level of point Q = HI – staff reading at Q
Level of point Q = HI – staff reading at Q = 101.5 – 3.5 = 98 m
= 103.5 – 1.5 = 102 m
Example:
Station BS IS FS HI RL
D 1.5 97.7
E 2.3 96.9
S 3.1 6.2
123.
Chapter 4
Q: What is the difference between rise & fall method and height of
instrument method?
A: Height of instrument method is more rapid, less tedious and
simple but the check on the calculation for intermediate sights is
not available whereas rise and fall method is more tedious but it
provides full check in calculations for all sights (IS,FS,BS).
Height of instrument is suitable to be used for longitudinal and
cross-section levelling and rise and fall method is suitable when
exact difference between the level of two stations is required.
Staff
BS IS FS RL
Station
P 1.655 m 100.000 m
Q –0.950 m –1.500 m
R 0.750 m
Levelling and Contouring
124.
Chapter 4
Previous Year’s Questions
Question: In a levelling work, sum of back sight (BS) & fore sight (FS)
have been found to be 3.085 m and 5.645 m respectively. If the reduced
level (RL) of the starting station is 100.000 m, the RL (in m) of last
station is ___________
Answer: 97.44 [GATE 2015, SET-II]
Example 4.3: The field level book readings from a fly level are as follow:
Staff Station RL BS FS
125.
Chapter 4
BS – 1.030 = 2. 89
⇒ BS = 3.92
\ RL of station C is higher than station B, thus there will be rise at
station C
Rise at station C = 106.65 – 104.15 = 2.5
FS of C = 4.220 – FS = 2.5
⇒ FS = 1.72
\RL of BM-2 is higher than point C, thus there will be rise at BM-2
⇒ FS = 2.64
SRise – SFall = 8 – 0 = 8
Levelling and Contouring
126.
Chapter 4
Q
Inverted sta
h FS = –h
BS FS
BM
Figure 4.18
HI = RL of BM + BS
RL of top point Q = HI – FS
= HI – (– h) = HI + h
= HI + h
RL of top of Q
Solution:
Roof (R )
1.500 0.575
155.305
HI = RL at floor + BS
= 155.305 m + 1.500 = 156.805 m
Levelling and Contouring
127.
Chapter 4
h
Level
Level line R C h
x line
C
y R
Levelling and Contouring
d B
Figure 4.19
128.
Chapter 4
y The effect of curvature of earth and refraction comes into the picture when
sight distance is long.
y This effect occurs because the difference between level line and horizonal
line increases with distance.
y The horizontal line is tangential to the level surface at a point,
whereas the level line is normal to the direction of gravity at all the
points.
y Hence while taking the observation from telescope the staff reading “x” is
obtained, however the level line has reading “y”.
y Therefore, there is positive error of “x – y = h”, due to curvature of earth
surface.
y Hence the correction to be applied is negative which is computed as
follows:
In DOAD OD2 = AD2 + OA2
(R + h)2 = d2 + R2
R2 + h2 + 2Rh = d2 + R2
h(h + 2R) = d2
2R >> h ⇒ 2R + h = 2R
h · 2R = d2
d2
h=
2R
Where h (m), d (km), R (km)
d2 × 103
h=
2 × 6367
h = 0.0785 d2
Where h(m), d(km)
Hence, correction due to curvature Cc.
Cc = –0.0785 d2
Level
line C
Refracted
ray of light
Figure 4.20
129.
Chapter 4
y The density of air decreases with increase in height above the surface of
earth.
y As the air is denser near to the earth surface, light from staff travels from
lighter medium to denser medium, hence gets deflected towards the
normal.
y Thereby the reading obtained over the staff is comparatively small (CD′)
then actual (CD).
y Hence error is negative in this case and correction is positive.
1 th
y Correction due to refraction is taken as 7
of the correction due to curvature
of earth surface.
1 0.0785 2
Cr = Cc = d = 0.0112 d2
7 7
C = Cc + Cr
C = – 0.0785 d2 + 0.0112 d2
NOTE:
(a) In case of longer sight, error due to curvature of earth and refraction,
can be eliminated by keeping the instrument at equal distance from
stations where backsight and foresight is taken.
(b) As in this case nature and magnitude of correction is same for both BS
and FS.
(c) If it is not possible to set the instrument in between the stations, in
that case RECIPROCAL LEVELLING is being carried out.
Levelling and Contouring
130.
Chapter 4
Horizontal line
d
A
C
h
Level B
line
R
O
Figure 4.21
h=c
h = 0.0673 d2
h
d=
0.0673
d = 3.85 h d (km), h (m)
NOTE: If both the points of observation are in elevation in such cases.
d1 d2
hS
hL
Figure 4.22
D = d1 + d2
D = 3.85 hS + 3.85 hL
Levelling and Contouring
NOTE: In the previous analysis the height “h” of the object under
consideration was assumed to be much smaller than the radius of the
earth, but if it is not
131.
Chapter 4
R2 + d2 = R2 + h′2 + 2Rh′
d= h′2 + 2Rh′
−6
h′ = h
7
Example 4.6: A level set up at point C, at a distance of 400 m from A and
1000 m from B. The staff readings on the staff kept at A was 0.545 m and
that on staff held at B was 3.845 m. Find the true difference in elevation
of A and B.
Solution:
0.545 3.845 m
CCA
CCB
C
A
400 m B
132.
Chapter 4
Example 4.7: An observer standing on the deck of ship just sees the top
of a light house which is 44 m above the MSL. If the height of the observe
eye is 6m above the MSL, determine the distance of the ship and the light
house.
Solution: Let A be the position of top of the light house and B be the
position of observer’s eye. And AB is considered as the tangential to water
surface at O.
A O B
d1 = 3.85 C1 km C2
C1 d2
d1 B′
= 3.85 44 = 25.54 km A′
d2 = 3.85 6 km = 9.43km
= d1 + d2
= 25.54 + 9.43 O
= 34.97 km
Example 4.8: A light house of 120 m height is just visible above the horizon
from a ship. The correct distance (m) between the ship and the light house
considering combined correction for curvature and refraction, is
[GATE 2008]
(a) 42.226 (b) 39.098
(c) 42226 (d) 39098
Given, C = 120 m
120 = 0.0673 d2
d = 42.226 km
d = 42226 m
So, the correct answer is (c).
133.
Chapter 4
x y
A B
d
x2 y2
e
x y
A B
d
Figure 4.23
134.
Chapter 4
Definitions
e
e
Figure 4.24
Level at A
Apparent difference between elevation of A and B = xx1 – yy1
True difference between elevation of A and B = xx1 – (yy1 – e)
True difference between elevation of A and B = [Apparent difference
between elevation of A and B]A + e ...(i)
Level at B
Apparent difference between elevation of A and B = xx2 – yy2
True difference between elevation of A and B = xx2 – e – yy2
True difference between elevation of A and B = [Apparent difference
between elevation of A and B]B – e ...(ii)
from (i) and (ii)
1
True difference between elevation of A and B = [sum of apparent
2
difference]
Levelling and Contouring
1
e = [change in apparent difference]
2
Here, e = ec + er + ea
e = ecc + ea
ea = e – ecc
135.
Chapter 4
NOTE:
(a) In the above analysis two similar instruments adjusted to same extent
are being used.
(b) In case a single instrument is used at both the stations, this method
not only corrects error due to curvature and refraction, but also due to
adjustment of collimation.
(c) But in this case if temperature changes, while shifting the instrument
from one station to others, error due to refraction would also get changed.
NOTE: (a) If two instruments are used but are not adjusted to same extent,
in such case, they should be interchanged after taking 1st reading in such
case.
True difference between elevation of A and B
1 1
( xx1 − yy 1 ) + ( xx2 − yy2 ) + ( xx1 ′ − yy 1 ′ ) + ( xx2 ′ − yy2 ′ )
= 2 2
2
(b) Permissible error in ordinary levelling
e = ± 24 k
e (mm), k (km)
k = perimeter of traverse
AB′ = AB sec q
=e AB[sec q − 1]
q
136.
Chapter 4
Example 4.9: The following observations were taken in reciprocal levelling.
Staff readings at
Instruments at
A B
A 1.732 2.842
B 0.936 1.587
1.110 + 0.651
\ True difference in elevation = = 0.8805 m
2
e = 0.2295 = 0.23
\ Error due to collimation ea = e – 0.0673d2
= 0.23 – 0.0673(1)2
ea = 0.1627 m (Positive error signifies, line if sight is upward)
\ Angular error of collimation
ea
tan a =
Levelling and Contouring
d
e
a = tan−1 a
d
0.1627
a = tan−1 3
= 33.56″
1 × 10
137.
Chapter 4
PART-B: CONTOURING
y The relative positions of different points on the surface of earth in plan are
represented by a map.
Definitions
138.
Chapter 4
Gray Matter Alert!!!
If contours are drawn below the water surface these are termed as
submarine contour/fathoms/bathymetric curve.
750 m
700 m
650 m
600 m
550 m
500 m
Figure 4.25
Definitions
139.
Chapter 4
(b) Purpose of map: For detailed designing, the contour interval should be
kept comparatively smaller.
(c) Nature of ground: Contour interval depends upon, wheather the country
is flat or undulated. The contour interval choosen for flat ground will be
unsuitable for undulated ground.
(d) Time: If time available is less, then greater contour interval is used & if
time available is more than smaller contour interval can be chosen.
O
Levelling and Contouring
10 m 30 m 50 m 70 m 90 m
140.
Chapter 4
(a) 0.025 cm (b) 0.25 cm
(c) 2.5 cm (d) 5.0 cm
Solution:
50 m P
R
O
30 m
4%
10 m
10 m 30 m 50 m 70 m 90 m
Longitudinal section Plan
30 − 10 4
tanq = =
R 100
R = 500 m
500
Radius of arc on plan = × 100 = 2.5 cm
20000
So, the correct answer is (c).
160
150
140
140
Levelling and Contouring
150
160
170
141.
Chapter 4
y In case of vertical cliff (generally found near sea cost) the contour lines
coincide with each other.
240
230
220
210
200
200
210
220
230
240
y A contour line is a closed curve, however it may close inside or outside the
map depending upon the topography.
y Equally spaced contour signifies uniform slope/same slope however,
magnitude of slope will govern the magnitude of the spacing of the contour.
(i)Uniform but (ii) Uniform but (iii) Non uniform but (iii) Non uniform but
steep slope gentle slope steep slope gentle slope
Figure 4.28
Levelling and Contouring
y A set of close contours, having higher elevations inside and lower elevation
(values) outside represents hillock, cliff and lower elevation inside and
higher elevation outside represents depression, river, lake, ravine, valley
etc.
142.
Chapter 4
170
170
160
180
150
190
200
NOTE: Ridge line is the line joining the top most points across the different
sections of hill and valley line is the line joining the lower most point of a
valley.
100
100
95
105
90
110
115 85
Levelling and Contouring
Ridge Valley
line line
(a) Ridge line (b) Valley line
Figure 4.30
143.
Chapter 4
144.
Chapter 4
NOTE: A very steep slope is termed as scarp and a high scarp is termed as
crag.
(c) Low lying forms: E.g. valley, lakes/pond, ravine etc. Their contour would
be having higher elevation outward.
190 190
180 180
170 180 170
170
160
160
150
160
150
150
Levelling and Contouring
145.
Chapter 4
(d) Saddle
Passes
200
210
220 220
230 230
Figure 4.33
(e) Escrapment
150
160
170
180
190
Levelling and Contouring
Figure 4.34
y It is a high land, having narrow top flat with steep slopes on one side
(scrap) and gentle slope on other side.
146.
Chapter 4
Example 4.11: Match list-I (land feature) with list-II (description) and select
the correct option.
List-I List-II
Solution:
y Lake: Closed contour lines with lower elevation inside and higher elevation
outside.
y Scrap: The contour will be closely spaced and overcrowded. A very steep
slope is termed as scrap.
y Overhanging cliff: The contour lines can only intersect in the case of
overhanging cliff or cave in hill side.
y Vertical cliff: Contour lines of different elevations unite with each other.
Levelling and Contouring
147.
Chapter 4
Staff 1m 1m
1m
2m
2m
2m 98 m
1m 1m
2m 99 m
BM
100.000 m
RL = 100
1m
15 m
148.
Chapter 4
y Properties:
⚪ Small area
⚪ Low accuracy
⚪ Less contour interval
⚪ Less time required
⚪ Low cost
(b) Cross section method
98.5
98 L2′ 99 100
L2
101 m L1 L1′
100 101
C C1 C2 C3 C4 C5 C6 C7
R1′
RL = 100 R1
R2 R2′
98
Figure 4.37: Cross section method
y Properties
⚪ Used for large area
⚪ Less time required
⚪ Large contour interval
⚪ Low accuracy
Keywords
149.
Levelling and Contouring Chapter 4
150.
5 Area & Volume
Chapter 5
5.1 INTRODUCTION
y Method selected for computation of area depends upon the shape of tract
and accuracy desired.
y Methods to measure area are as follows:
(a) By field measurement - It is done by dividing the area into small
geometric figures like rectangle, square etc. and by measuring base
line, coordinates of points.
(b) Plan measurement - It is done by calculation based on measurement
from field and scaled down to plan. Planimeter is used for this purpose.
Figure 5.1
a, b, c are sides
a +b + c
s=
2
(g) Area of segment = Area of sector ACBO–Area of DAOB
πR2 1 α α
=A o
× α − × 2R sin × R cos
360 2 2 2
= R2 −
360
O
2
151.
Chapter 5
Figure 5.3
Figure 5.4
152.
Chapter 5
Offset O1, O2, …. On are measured at the end of each division and are spaced
at equal distance d.
Area = average ordinate × length of base
O1 + O2 + .....On
= (nd)
n+ 1
O1 + O2 + .....On
Area = (nd)
n+1
Figure 5.5
O + O2
Area of 1st trapezoid = 1 d
2
O + O3
Area of 2nd trapezoid = 2 d
2
O + On
Area of last trapezoid = n−1 d
2
O + O2 O2 + O3 O + On
A= d 1 + + ....... n−1
2 2 2
O + On
=A d 1 + O2 + O3 + .....On−1
2
If the land boundary between any two consecutive offset is more or less a
Area & Volume
y
straight line, then the computation of area is carried out using trapezoidal
rule.
153.
Chapter 5
Figure 5.6
1 2
= (O1 + O3 )(2d) + (VW)(PQ)
2 3
1 2
= (O1 + O3 )(2d) + (XV − XW)(PQ)
2 3
1 2 O + O3
= (O1 + O3 )(2d) + O2 − 1 2d
2 3 2
d
= [3O1 + 3O3 + 4O2 –2O1 –2O3]
3
d
= [ O1 + 4O2 + O3]
3
Similarly, area of next segment O3, O4 and O5
Area & Volume
d
= (O3 +4O4 + +O5 )
3
154.
Chapter 5
Similarly,
d
On–2, On–1 and On = [On–2 + 4On–1 + On]
3
d
Total area = [(O1 + 4O2 + O3) + (O3 + 4O4 + O5) + ……..(On–2 + 4On–1 + On)]
3
d
= [(O1 + 4O2 + 2O3 +4O4 + 2O5 + ……..+ 2On–2 + 4On–1 + On)]
3
d
= [(O1 + On) + 4(O2 + O4 + …. On–1) + 2(O3 + O5 + ….. On–2)]
3
d
Total area = [(first offset + last offset) + 4 (sum of even offset)
3
+ 2 (sum of odd offset)]
y This method is applied when the area is divided into even numbers i.e., the
number of ordinates is odd.
155.
Chapter 5
Question: The value of abscissa (x) and ordinate (y) of a curve area as
follows:
By Simpson’s 1/3rd rule, the area under the curve (round off to two
decimal places) is__________.
Example 5.1: Determine the area between straight line PQ and undulating
line where offsets are taken at a regular interval of 20 m along the line PQ.
Use trapezoidal rule as well as simpson’s 1/3rd rule for the calculation of
area.
Area & Volume
156.
Chapter 5
Point P Q
Offset length (m) 14.3 16.4 15.2 13.1 17.8 16.2 17.4 15.5 13.1
Solution: d = 20 m
\ Area using trapezoidal rule
O + On
=A d 1 + O2 + O3 + .......On−1
2
14.3 + 13.1
=A 20 + 16.4 +15.2 +13.1 +17.8 +16.2 +17.4 +15.5
2
A = 2506 m2.
\ Area using Simpson’s 1/3rd rule
d
A = [(O1 + O9) + 4(O2 + O4 + O6 + O8) + 2(O3 + O5 + O7)]
3
20
= [(14.3 + 13.1) +4 (16.4 + 13.1 + 16.2 + 15.5)
3
20
= [27.4 + 244.8 + 100.8] = 2486.7 m2
3
Example 5.2: The method which is best suitable for the estimation of area of an irregular
and curved boundary is
(a) Trapezoidal method (b) Simpson’s method
(c) Average ordinate method (d) Mid-ordinate method
Solution: If the boundary between two offsets is curved, then simpson’s one-third rule is
preferred and if the boundary between the two offsets is straight then trapezoidal method
is preferred.
So, the correct answer is (b).
Example 5.3: Following offsets were taken from a survey line to a hedge:
Distance (in m) 0 10 20 30 40 55 70
Area & Volume
157.
Chapter 5
The area between survey line and the hedge is (by trapezoidal method):
(a) 185.5m2 (b) 328.75 m2
(c) 324.01 m2
(d) 289.5m2
Solution:
Here d is not constant, from offset O1 to O5, d is 10 m and from offset O5,
to O7, d is 15 m
O + On
=A d 1 + O2 + O3 + O4 + ....... + On−1
2
3 + 6
=A 1 10 + 4 + 5.5
= + 5 190m2
2
6 + 4.5
=A2 15 = + 4 138.75m2
2
158.
Chapter 5
(A) Measurement of Volume Using Area of Cross-Section Method
y It is generally used to find the volume of earthwork in which cross-sections
are taken at right angles to the fixed center line.
y Spacing between cross-section depends on accuracy required, availability
of cost, type of terrain.
y Following types of cross sections are taken in this case:
Figure 5.7
Figure 5.8
1
A= [b + (b+2mh)]h
2
A = (b+mh)h
Area & Volume
159.
Chapter 5
Figure 5.9
1 b b
=
A h2 + hd2 + hd1 + h1
2 2 2
1 b
=
A (h1 + h2 ) + h(d1 + d2 )
2 2
FA = FH–AH
b
mh2 = d2 – ……..(i)
2
d2 = (h–h2)n ………(ii)
b b
mh2 = (h–h2)n– = hn–h2n –
2 2
b
h2 (m+n) = hn –
2
b 1
=
h2 nh −
2m+n
b 1
Similarly, =
h1 nh +
2n−m
b b 1 b
d2= mh2 + = m nh − +
2 2n+m 2
Area & Volume
b b 1 b
d1= mh1 + = m nh + +
2 2 n − m 2
160.
Chapter 5
2
b
m + n2 (bh + mh2 )
2
A=
n2 − m2
(iii) Three-Level Section
Figure 5.10
1 b bh1
=
A h2 + hd2 + hd1 +
2 2 2
1 b
=
A (h1 + h2 ) + h(d1 + d2 )
2 2
(iv) Side Hill Two Level Section
Figure 5.11
Area & Volume
1
=A [b2h2 + b1h1 ]
2
161.
Chapter 5
d
=
V (A 1 + An ) + 4(A2 + A 4 + A6 + .....An−1 ) + 2(A3 + A5 ....An−2 )
3
a + b1 + c1
V= 1 A
3
Where, A = area of figure
Area & Volume
162.
Chapter 5
Example 5.4: A railway embankment is 18 m wide with a side slope of 2H:
1V. Assume the ground to be level in the direction transverse to the centre
line. Calculate the volume of earthwork contained in a length of 100 m
using trapezoidal and simpson’s method. The centre height at 20 m interval
in ‘m’ is 2.1 4.2, 3.8, 3.5, 2.3, 1.5 respectively.
Solution:
For a level section, the area is given by A = (b + nh)h
slope 2 : 1
163.
Chapter 5
A + An
=V d 1 + A2 + A 3 + ........An−1
2
46.62 + 31.50
=V 20 + 110.88 + 97.28 + 87.5 + 51.98
2
V = 7734 m3
\ Volume using simpson’s method
Since even number of cross sections are there, volume is computed
using simpson rule upto odd sections and for last segment volume is
computed using end area method.
d d
V= [(A 1 + A5 ) + 4(A2 + A4 ) + 2(A3 )] + (A5 + A6 )
3 2
20 20
=V
3
[ (46.62 +51.98) +4(110.88 + 87.5) + 2(97.28)] + [51.98 + 31.5]
2
V = 8079.33 m3
Example 5.5: An excavation has been made as shown in figure. Calculate the quantity of
earth excavated using trapezoidal rule and simpson rule.
Area & Volume
164.
Chapter 5
Solution:
A2 = 70×55 = 3850 m2
Area & Volume
A3 = 90×75 = 6750 m2
165.
Chapter 5
A + A3
Vtotal = d 1 + A2
2
(2700 + 6750)
= 5 + 3850
2
= 42875 m3
\ Volume using simpsons Rule
d
Vtotal = [(A 1 + An ) + 4(A2 + A4 + A 6 + ...) + 2(A3 + A5 ...)]
3
5
= [(2700 + 6750) + 4(3850] = 41416.67 m3
3
dn
Level section ==
Cp (h − h')2
6
Where, h, n refers to the cross section at one end and h’, n’ refers to
the cross-section at another end.
of centre line.
166.
Chapter 5
Example 5.6: If the cross-sectional area of an embankment at 20 m
intervals are 10, 30, 50, 40 and 20 m2 respectively. Then the volume of the
embankment using trapezoidal rule is
(a) 2142 m3 (b) 1375 m3
(c) 2700 m 3
(d) 2284 m3
Solution:
A + An
=V d 1 + A2 + A 3 + ...... + An−1
2
10 + 20
=V 20 + 30 + 50 + 40
2
V = 2700 m3
So, the correct answer is (c).
Keywords
167.
Area & Volume Chapter 5
168.
6 Plane Table Surveying
Chapter 6
6.1 INTRODUCTION
y The graphical method of surveying, in which the field observation and
plotting is carried out simultaneously is known as plane table surveying.
y The main feature of this surveying is that, the chances of missing any
topographical feature to be mapped is very less, as it is carried out in field
itself.
y The suitability of plane table surveying is for small and medium scale
mapping (i.e. 1 : 10,000 to 1 : 250,000) in which high accuracy is not
required.
Advantage Disadvantage
y Plane table boards are available in different sizes and these are designated
as follows: B0 : 1500 mm × 1000 mm
B1 : 1000 mm × 700 mm
B2 : 700 mm × 500 mm
B3 : 500 mm × 350 mm
169.
Chapter 6
(ii) Tripod
y It is used for placing the plane table board over it, levelling of which is done
with the help of tripod legs and levelling screws.
(iii) Alidade
y It is a straight edge ruler having a sighting device at its ends in the form of
vanes. It can be used for drawing the lines.
Object vane
Sight vane
Bevelled edge
Bubble tube
Vertical circle
Telescope
Focussing
screw
Straight edge
ruler
Plane Table Surveying
170.
Chapter 6
(iv) Compass
y Magnetic meridian can be established by using trough compass.
y If needle provided in compass align itself along the magnetic meridian,
reading in compass corresponds to zero.
171.
Chapter 6
Upper arm
Point
Lower arm
Plumbing
fork
Plumb
bob
172.
Chapter 6
c
N
N
S
a
b
c c
N
N
S
S
a b a b
A B
S
Figure 6.6: Orientation using trough compass
(b) By backsighting
y Backsighting is the most suitable method of orientation.
y In backsighting, the plane table is placed on the new station & the alidade
is kept against the line joining the new station & the previous station. The
plane table is turned until the bisection of line of sight takes place with the
previous station.
d
b
c
a
D
d
b
b c
c a
a
C
B
b
Plane Table Surveying
A
Figure 6.7: Orientation by backsighting
173.
Chapter 6
(C) Resection
y Through the method of resection, the orientation and fixing of plane table
can be achieved simultaneously.
Solution:
y Levelling–Centering–Orientation is the correct order of setting the plane
table.
y The working edge of alidade is known as fiducial edge, it is used as a
sighting device.
y Plane table survey is a graphical method of survey. In this method field
observations and plotting is carried out simultaneously.
So, the correct answer is (b).
Solution:
y Compass is used for the orientation of plane table.
y For the levelling of plane table, spirit level is used.
Plane Table Surveying
174.
Chapter 6
6.4 METHODS OF PLANE TABLE SURVEYING
(A) Radiation
y The plane table is setup at a station & through that station the rays are
drawn to various stations/points which are to be plotted. After the actual
measurement, the distances are cut to a suitable scale.
y The applicability of radiation method is only when small area is to be
surveyed & the required points are visible and accessible through the
instrument station. If the measurement of distances is carried out with the
help of tachometer, then the scope of radiation method can be increased.
b
c
A o
a
d
O
Plane Table Surveying
D
Figure 6.8
175.
Chapter 6
(B) Traversing
Gray Matter Alert!!!
y It works on the same principle as that of radiation
method with the only difference that in case of y If there are ‘n’ stations in a
closed traverse, setting of
radiation the observations are taken to those plane table is to be done for
points which are to be detailed or mapped. While atleast ‘n–1’ stations.
y To determine the error of
in traversing observations are made of those points
closure, setting of plane table
which will subsequently be used as station. is to be done for atleast ‘n–2’
y Plane table traverse has same principle as that of stations.
transit traverse.
y Plane table is set at each successive station and foresight is taken of the
following station and its location is plotted by measuring the distance with
the help of chain/tape or tacheometer between the two stations.
Plane Table Surveying
Figure 6.9
176.
Chapter 6
(C) Intersection/Graphical triangulation
C E
D
F
d e
c
f
g
A a a b B
b
Figure 6.10
(D) Resection
y It is the process of locating the instrument station occupied by the plane
table by drawing the rays from the station whose positions are already
plotted on drawing sheet.
Definitions
177.
Chapter 6
y This method is applicable for rough mapping & for small scale work, for
which large errors due to improper orientation by trough compass, would
not have major impact over the usefulness of map.
A B
a b
Plane Table Surveying
C
c
Figure 6.11
178.
Chapter 6
(ii) Resection after orientation by backsighting
a A
b B
c’
a b
C
c
c’
Figure 6.12
y Set the plane table at station A, and carry out the orientation by back
sighting B along ab.
y After setting of plane table, pivot the alidade at point a and sight station C,
then draw a ray ac’, where c’ is roughly estimated.
y Plane table is set at station C and carry out the orientation by back sighting
A along c’a & then clamp the table.
y Now pivot the alidade at b and draw the resector towards “B”, where the
point of intersection of this resector “c” with ac’ gives the location of
instrument station C.
a b1
a P
Plane Table Surveying
b D C b
d1 c1 d1 c1 c2
Figure 6.13
179.
Chapter 6
a a’ b
b’
c
P
c’
p
p’
180.
Chapter 6
(f) Pivot the alidade at b & c and sight B & C respectively and draw the
resectors. Keep on repeating this process upto an extent, triangle of
error is transformed into a point.
Figure 6.15
Lehmann’s Rule
(i) If station ‘P’ is outside the great triangle, the triangle of error also lies
outside the great triangle, hence point ‘p’ must also be considered
outside the triangle of error.
Similarly, if station ‘P’ lies inside the great triangle (on the same line),
the triangle of error also lies inside the great triangle, hence point ‘p’
must also be considered inside the triangle of error.
Figure 6.16
181.
Chapter 6
(ii) The point ‘p’ should be so chosen that its distance from resectors
(Aa, Bb, Cc) p’a’, p’b’, p’c’ respectively must be in proportion to the
distance of point ‘P’ from A, B & C.
Figure 6.17
Question: If the plane table occupies a position not yet located on the
map then the method of orientation used will be
(a) Radiation (b) Traversing
(c) Levelling (d) Resection
Answer: (d) [GATE 2017 SET-II]
Plane Table Surveying
182.
Chapter 6
Which of the above statements are correct ?
(a) Only A and B (b) Only A and C
(c) Only B and C (d) All the above
Solution:
y The methods used to solve the three point problem are as follows-
Example 6.4:
Assertion (A) : Lehmann’s rule is used to solve the three point problem in
plane table surveying.
Reason (R) : The application of Lehmann’s rules reduces the triangle of
error and is controlled by trial and error technique.
(a) Both A are R are true and R is correct explanation of A
(b) Both A and R are true but R is not correct explanation of A
(c) A is true but R is false
(d) A is false but R is true
Solution: Three point problem can be solved by the three methods, one of
which is Lehmann’s method. Through the application of Lehmann’s rules,
by successive trial and error, the triangle of error can be reduced to a point.
Thus, it is also known as trial and error method.
So, the correct answer is (a).
(a) Traversing
(b) Radiation
(c) Intersection
(d) Resection
183.
Chapter 6
Solution:
y When distance between the stations is too large or the points are
inaccessible then intersection method is used.
y When the area to be surveyed is small and all the stations are accessible
and visible from the instrument station, then the radiation method is used.
y Traversing method is used to lay down the survey lines between the
instrument stations of a closed or open traverse.
So, the correct answer is (c).
Solution:
y Method of radiation is suitable when the area to be surveyed is small and
the points are accessible.
y Method of resection is suitable for establishing the instrument station. In
this method the plotted position of instrument station is determined by
means of sights taken towards the known points, location of which have
been plotted.
y The three point problem is more useful than the two point problem because
of the simplicity and accuracy. It is less laborious than two point problem.
So, the correct answer is (a).
184.
Chapter 6
y If plumbing fork and bob is defective, centering of the table is not proper
then the error will occur, magnitude of which can be computed as
follow :
A B
a b
Ray in
incorrect P
centering a b
e e
c d
b’
a’
a b
Ray in correct
centering p
Figure 6.18
y Since the table is not centered properly the point ‘p’ will not be over the
station P.
Hence, linear error in centering = Pp
Angular error in centering g = ∠APB – ∠ApB
g = a+b
Pc Pd If θ is small
=
sin a =
, sin b
PA PB θ ≈ sin θ ≈ tan θ
e e
=a =
,b
PA PB
Hence, g= e + e
PA PB
Plane Table Surveying
Now error is plotting of point A & B on plane table would be aa’ and bb’.
aa’ = pa sin a, bb’ = pb sin b
pa = r.PA, pb = r.PB [Here r is Representative fraction]
185.
Chapter 6
e e
= aa ' r= PA , bb' r PB Gray Matter Alert!!!
PA PB
aa’ = re, bb’ = re
Hence displacement of the point A & B on plane In plane table surveying, the errors
table from their correct position is “re”. are classified as follows:
y Instrumental error
Example 6.7: During setting up of the plane table y Errors of plotting
at a station “P” the corresponding plotted point y Errors of sighting and
“p” was not accurately centered over “P”. What manipulation
will be the displacement of point from its true
position on the plan if the displacement of P was
16 cm in a direction at right angle to the ray
1 1
(i) r= (ii) r=
400 40
Solution: Given, displacement of P(e) = 16 cm
aa’ or bb’ = re
(i) r = 1
400
1
= × 16 =
0.04 cm
400
1
(ii) r=
40
1
= × 16 =
0.4 cm
40
Keywords
186.
7 Traversing and Triangulation
Chapter 7
Part- A : Traversing
7.1 INTRODUCTION
y It is the process of measuring length and direction of survey line (traverse
line) in the field.
y Traverse is a series of connected lines whose length and directions are
being measured in the field.
y The field work in theodolite traverse includes:
(a) Reconnaissance
(b) Selection and marking of survey station
(c) Running and measuring traverse line
(d) Angular measurements and marking the offsets
187.
Chapter 7
⇒ dl = (tan(30'))l
dl 1
=
l 115
188.
Chapter 7
y A theodolite fitted with magnetic compass is used in this case to measure
the magnetic bearings.
189.
Chapter 7
The included angles measured clockwise are the interior angles if the traverse is
running counterclockwise.
And the included angles measured clockwise are the exterior angles if the traverse is
running clockwise.
190.
Chapter 7
Figure 7.4: Method of deflection angle
191.
Chapter 7
192.
Chapter 7
7.5 TRAVERSE SURVEY
y A traverse survey is one in which the framework consists of series
of connected lines whose length are measured with chain or tape and
directions are determined with angular measurement i.e. compass or
theodolite.
193.
Chapter 7
For example, Consecutive co-ordinate of end point ‘2’ of line 1-2:- (–L1, D1)
Consecutive co-ordinate of end point ‘3’ of line 2-3:- (L2, D2)
y Independent co-ordinates :- These are the co-ordinates of any point
measured with respect to common origin.
194.
Chapter 7
For example, Independent co-ordinate of point 1:- (y1, x1)
Independent co-ordinate of point 2:- (y2, x2)
Independent co-ordinate of point 3:- (y3, x3)
NOTE : x2 = x1 + D1 y2 = y1 –L1
x3 = x1 + D1 + D2 y3 = y1 –L1 +L2
Hence,
Latitude of Latitude of Sum of all Latitudes
= +
any po int start po int upto that po int
Departure of Departure of Sum of all Departure
= +
any po int start po int upto that po int
195.
Chapter 7
Example 7.1: In any closed traverse, if the survey work is error free, then
(i) The algebraic sum of all the latitudes should be equal to zero.
(ii) The algebraic sum of all the departures should be equal to zero.
(iii) The sum of the northing should be equal to the sum of the southing.
Which of the above statements are correct?
(a) (i) and (ii) only (b) (i) and (iii) only
(b) (ii) and (iii) only (d) (i), (ii) and (iii)
Solution:
For any closed traverse,
SL = Sum of all the latitudes = 0
SD = Sum of all the departures = 0
So, the correct answer is (a).
Example 7.2: The length and bearings of a closed traverse ABCDA are given
AB 300 30o
BC 700 120o
CD 500 210o
DA ? ?
300 sin 30o + 700 sin 120o + 500 sin 210o + L sinq = 0
L sinq = – 506.217 …(ii)
Dividing (ii) by (i), we get
tanq = –0.9675
q = 315.945o
196.
Chapter 7
From equation (i)
523.205
L=
(
cos 315.945o )
L = 728.015 m
So, the correct answer is (b).
ex
Direction of closing error AA’, tanq =
Traversing and Triangulation
ey
y The signs of ex and ey will define the quadrant of closing error.
y The correction to be applied would be just opposite of the error.
i.e. Cx = –ex
Cy = –ey
y Hence, closing error and correction will be in diagonally opposite quadrant.
197.
Chapter 7
Definitions
198.
Chapter 7
Example 7.3: A close traverse has the following lengths and bearings :
BC 98 m 178o
DA 86.4 m 1o
Solution:
mention
Here, we have whole circle bearings of all the lines.
199.
Chapter 7
Question: The latitude and departure of a line AB are +78 m and –45.1
m respectively. The whole circle bearing of the line AB is
(a) 30o (b) 150o
(c) 210o (d) 330o
Answer: (d) [GATE-2013]
Example 7.4: The bearings of two inaccessible stations ‘A’ and ‘B’ taken
from station ‘C’ were 220o 30’ and 150o 00’ respectively. The coordinates of
‘A’ and ‘B’ were as under.
A 200 200
B 400 150
200.
Chapter 7
400 − 200
tana = =4
200 − 150
a = 75o 57’ 49.52’’
Now, ∠A = 180o – 40o 30’ –75o 57’ 49.52”
∠ A = 63o32’ 10.48”
LAB = (400 – 200)2 + (150 − 200)2 = 206.15m
AB BC
Using sine rule, =
sinC sin A
sin(63o 31' 10.48 ")
BC = AB ×
sin(220o 30 '− 150o0 ')
⇒ BC = 195.77
Northing of point C = 150 + 195.77 cos (30o0’) = 319.54 m
Easting of point C = 400 –195.77 sin (30o 0’) = 302.115 m
line.
Error in latitude Total error Length of the line
= ×
of any line in latitude(e )
y Perimeters of traverse
201.
Chapter 7
li
∵ CLi =−ey ×
Sli
Do You Know?
L l2 Ll l
(a) DD (b) DD (c) (d) DD
l L DD L
Solution:
l
= DD
L
202.
Chapter 7
Example 7.6: Calculate latitudes, departures and closing error for the given
traverse. Use Bowditch’s rule for the adjustment.
PQ 90 45 o
QR 220 71 o
RS 150 161 o
ST 160 228 o
TP 231 300o
203.
Chapter 7
PQ 63.64 63.64
QR 71.62 208.01
RS –141.82 48.83
ST –107.06 –118.90
TP 115.5 –200.05
SL = 1.88 SD=1.53
1.53
q = tan–1
1.88
220
QR = –1.88 × = –0.486
851
150
RS = –1.88 × = –0.331
851
160
ST = –1.88 × = –0.353
851
204.
Chapter 7
231
TP = –1.88 × = –0.510
851
Departure corrections (CDi)
90
PQ = –1.53 × = –0.162
851
220
QR = –1.53 × = –0.395
851
150
RS = –1.53 × = –0.269
851
160
ST = –1.53 × = –0.287
851
231
TP = –1.53 × = –0.415
851
Finally,
comparatively more.
Q : Compare the change in length and angle between transit rule and bowditch’s rule.
A : In bowditch rule in comparison to transit rule, change in length is less, but change
in angle is more.
205.
Chapter 7
| Li |
CLi =−ey ×
S |Li |
Station N S E W
P 300.50 200.25
Q 200.00 299.00
R 298.75 199.50
Traversing and Triangulation
S 199.75 300.25
206.
Chapter 7
Solution : (a)
We can write :
PQ 200.00 299.00
QR –298.75 199.50
RS –199.75 –300.25
SP 300.50 –200.25
SL=2 SD = –2
So, we have
ex = SD = –2
ey = SL = 2
The error of closure, e = e2x + e2y = ( −2)2 + (2)2 = 2.828
ex −2
Now, tanq = = ⇒ q = 315o
ey 2
Traversing and Triangulation
207.
Chapter 7
CLPQ = –0.400
Similarly, correction in the departure of line PQ i.e.
299
CDPQ = – (–2) ×
(299 + 199.5 + 300.25 +200.25)
CDPQ = 0.598
Now, corrected latitude of PQ = 200 + (–0.400) = 199.600
And corrected departure of PQ = 299 + (0.598) = 299.598
So, the consecutive coordinate of Q is (199.600 N, 299.598 E)
(c) Independent co-ordinate of Q is
= [(150 + 199.600) N, (175 + 299.598) E]
= [349.600 N, 474.598 E]
Sum of exterior angles = (2N + 4) 90o
In case of compass traverse, the observed bearings are adjusted for
local attraction.
(ii) With the help of observed bearing of the traverse line, compute the
bearing of other lines if missing and reduce it to quadrantal system.
208.
Chapter 7
(iii) With the help of the length and computed reduced bearing of the line,
the consecutive coordinate i.e. latitude and departure is computed.
(iv) A check is performed to find out, whether the error of closure exist
in traverse or not i.e., algebraic sum of latitude and departure must
come out to be zero.
If error of closure is found, correction is to be applied over it, by a
particular method depending upon the accuracy in measurement of
direction and length.
(v) The independent co-ordinates are then worked out from the
consecutive co-ordinates.
209.
Chapter 7
Part- B : Triangulation
7.9 INTRODUCTION
y Triangulation is a method where one base line was measured, and all the
angles are measured to find out lengths of other line by using sine or cosine
rule of triangle. This method was used earlier when sophisticated distance
measurement instruments (like EDMI i.e., electronic distance measurement
instrument) were not available.
210.
Chapter 7
7.11 ARRANGEMENT OF TRIANGLES
7.11.1 Single chain of triangles
y In this arrangement, we have only one direction of computation and it is
mainly suitable for the project like rivers boundary determination.
Figure 7.11
Figure 7.12
Figure 7.13
211.
Chapter 7
Figure 7.14
212.
Chapter 7
Solution: Centered triangles and polygons type triangulation system is
used to cover area and give relatively better result than the other types. The
interior station which is bounded by number of sides of triangles and form
different types of polygons like quadrilaterals, pentagons, or hexagons etc.
So, the correct answer is (d).
Which of the triangles are ill-conditioned and should be avoided in triangulation survey?
(a) Both P and R (b) Both Q anr R
(c) Both P and S (d) Both Q and S
Answer: (d) [GATE 2019, SET-I]
213.
Traversing and Triangulation Chapter 7
214.
8
Trigonometric and Tacheometric
Levelling
Chapter 8
Part- I : Trigonometric levelling
8.1 INTRODUCTION
y It is an indirect method of levelling in which the relative elevations of
various points are determined from vertical angle (a) & horizontal distance
(D), measured with a theodolite and tape/chain/tacheometer respectively.
y It can be used for the topographic work or at the places where direct
levelling is not possible.
h = D tan a
Staff
B a
D Object
S h'
E
A D
BM
Figure 8.1: Base accessible
Where,
A = Instrument station
C = Point to be observed
In D BCD, h = D tan a
RL of point C at top of object = RL of line of collimation + h
If the reading on the staff kept at the B.M. is S with line of sight horizontal.
215.
Chapter 8
h
E
F a2 G a1
D
S h'
BM A d B
D
Figure 8.2: Instrument axis at the same level
Where,
α1 = Angle of elevation from G to C
α2 = Angle of elevation from F to C
S = Staff reading on BM
d = Horizontal distance between the instrument stations
D = Horizontal distance between B & D
h = D tan a1
d tan a2 tan a 1
h =
tan a 1 − tan a2
216.
Chapter 8
RL of top point C of object = RL of line of collimation + h
d tan a2 tan a 1
RL of top point C of object = RL of BM +S +
tan a 1 − tan a2
h2 h1
E
F a2
S2 D2
S a G a1
S1 H 2 D1
b
BM A B D
d
d'
Figure 8.3
b = S cot a2
d’ = d + b = d + S cot a2
h1 = D tan a1
217.
Chapter 8
(S + d tan a2 ) tan a 1
h1 =
tan a 1 − tan a2
h1 h2
E
S1 G a1
F a2 D1
S2 S
H D2
B
BM A
d' b D
d
Figure 8.4
Trigonometric and Tacheometric Levelling
d’ = d - b
D=
(d − S cot a2 ) tan a2
tan a 1 − tan a2
h1 = D tan a1
h1 =
(d − S cot a2 ) tan a2 tan a1
tan a 1 − tan a2
218.
Chapter 8
Case III : When instrument axes have large difference of levels.
C Object
h1 h
2
E
a1
Staff D1
S
a2 B
D2
S2
A d D
BM
(a)
C
Object
Staff
E
r h h = d tan a
a B
A d
(b)
Figure 8.5
h1 = D tan a1 ….(i)
h2 = (D + d) tan a2 ….(ii)
(d − S cot a2 ) tan a2
D =
tan a 1 – tan a2
h1 = D tan a1
(d − S cot a2 ) tan a 1 tan a2
h1 =
tan a 1 – tan a2
219.
Chapter 8
h2 h1
Q 2
D2
D2 D1
E
2 2
B 1–
–
1 0°
S2 18
d O
S1 D1
1
BM A
B1 D2
C1
2 2
1–
B 18 0°– E
d D1
1
Trigonometric and Tacheometric Levelling
Figure 8.6
h1 = D1 tan a1 ….(i)
h2 = D2 tan a2 ….(ii)
d D1 D2
= =
(
sin 180° − q1 + q2
) sin q2 sin q1
d sin q2 d sin q1
D1 = , D2 =
sin(q1 + q2 ) sin(q1 + q2 )
220.
Chapter 8
d sin q2 tan a 1 d sin q1 tan a2
h1 = , h2 =
sin(q1 + q2 ) sin(q1 + q2 )
RL of top point C of object = RL of BM + S1 + h1
OR = RL of BM + S2 + h2
NOTE: If the RL of point C form both the stations A & B doesn’t comes out
to be same, then take the average of both readings.
10.5°
16.5°
2.555
0.555
Q
P 60 m
BM 450.000
221.
Chapter 8
Example 8.1 : Find the reduced level of a church spire ‘C’ from the following
observations taken from two station A & B 70 m apart.
Angle BAC = 60°30’
Angle ABC = 68°18’
Angle of elevation from A to the top of spire = 10°12’
Angle of elevation from B to the top of spire = 10°48’
Staff reading from A on BM (300.00) = 0.965 m
Staff reading from B on BM (300.00) = 1.055 m
C
B
51°12'
68°18'
60°30'
Trigonometric and Tacheometric Levelling
d sin q2 tan a 1
h1 =
sin(q1 + q2 )
222.
Chapter 8
70 sin60°30' tan 10°48'
=
sin(60°30' + 68°18' )
= 14.91 m
RL of C from A = RL of BM + S1 + h1
= 300 + 0.965 + 15.01
= 315.975 m
RL of C from B = RL of BM + S2 + h2
= 300 + 1.055 + 14.91
= 315.965 m
315.975 + 315.965
RL of C =
2
= 315.97 m
Example 8.2 : In order to ascertain the elevation of the top (Q) of the signal
on a hill, observations were made from two instrument stations P & R at
a horizontal distance of 120 meters apart, the stations P and R being in
line with Q. The angles of elevation of Q at P and R were 28°42’ and 18°6’
respectively. The staff readings upon the benchmark of elevation 300.28 m
were respectively 3.870 m and 4.750 m when the instrument was at P and
at R, the telescope being horizontal. Determine the elevation of the foot of
the signal if the height of the signal above its base is 4 meters (Assume P
is near to the signal).
18°6'
4.750
S 28°42'
3.870
300.28 R P
120 m D
223.
Chapter 8
(d + S cot a2 ) tan a2
D=
tan a 1 – tan a2
(120 + 0.88 cot 18°6' ) tan 18°6'
D=
tan 28°42' – tan 18°6'
D = 181.76 m
h1 = D tan a1
h1 = 181.76 tan 28°42’
h1 = 9.51 m
RL of foot of signal = RL of instrument axis at P + h1 – height of signal
= (RL of BM + staff reading) + h1 – height of signal
= (300.28 + 3.870) + 99.51 – 4
= 399.66 m
Solution:
Hill
h
6°30' 10°
Trigonometric and Tacheometric Levelling
RL = 420 m D
1800 m
(1800)(tan6°30')
D=
(tan 10°) – (tan6°30' )
D = 3287.058 m
224.
Chapter 8
h = D tan a1 = 3287.058 × tan 10°
h = 79.597 m
The RL of the top of the hill = RL of line of collimation + h
= (420 + 1.5 + 579.597) m
= 1001.097 m
And the required horizontal distance = D + 1800
= (3287.058 + 1800) m
= 5087.058 m
Solution: From the given data & conditions in the question, we have,
d = 100 m, a1 = 25°10' and a2 = 10°30'
h1
a1
3.250 m = S1
S a2
2.500 m = S2
D = 62.506 m
225.
Chapter 8
h1 = D tan a1
= (62.506) × (tan 25°10’) = 29.368 m
So, RL of top of the signal = RL of BM + S1 + h1
= (180 + 3.250 + 29.368) m = 212.618 m
226.
Chapter 8
Upper stadia hair
NOTE: Upto the distance of 100 m, normal levelling staff can be used in
2
1 3
2 4
3 5
4 6
7
227.
Chapter 8
Tacheometry
Methods
Fixed hair Movable hair
method method
(subtense method)
i A
s1 s2
a2
s1
a1
Trigonometric and Tacheometric Levelling
B
D
O1 O2
Figure 8.9 : Stadia hair method
y Additional hairs being provided other than cross hair in diaphragm is termed
as “Stadia hair”.
y Vertical distance between the two stadia hairs is termed as “Stadia interval”
and the angle made by them is termed as “Stadia/Tacheometer/Parallactic
angle”.
y When the stadia angle is kept constant (a1) and the staff intercept is varied
(from s1 to s2), this type of stadia method is termed “Fixed hair method”.
228.
Chapter 8
y However, if the stadia angle is varied (from a1 to a2) and staff intercept is
kept constant (s1), this type of stadia method is termed as “Movable hair/
Subtense method”.
C D–C
d f
f2 f1
A
A' C' O
i C s
B' F
B
Figure 8.10
Where,
f1 = Distance between optical center O and staff
f2 = Distance between optical center O & image of staff
D = Horizontal distance between staff and vertical axis of tacheometer
d = Horizontal distance between optical center O and vertical axis]
of tacheometer
f = Focal length of objective lens
s = Staff intercept
f1 f1
= 1+
f f2
f1 f1
= –1 ….(ii)
f2 f
Since DAOB ~ DA’OB’
229.
Chapter 8
A' B' AB i s
= ⇒ =
OC' OC f2 f1
f1 s
= ….(iii)
f2 i
From equation (ii) & (iii)
f1 s
–1=
f i
s
f1 = f+f
i
Now D = f1 + d ⇒ f1 = D – d
s
D= f+f+d
i
f
D = s + (f + d)
i
=
D Ks + C
The equation is termed as “Tacheometric distance equation”.
f
Here, K = = Multiplying constant/Stadia interval factor
i
K = function (f, i)
For the ease of calculation of “D” ,stadia interval “i” is so adjusted that K =
f
becomes equal to 100.
i
C = f + d = Additive constant
Since the value of “d” almost remains constant for tacheometer “C” is also
constant.
Trigonometric and Tacheometric Levelling
Anallactic Lens:
y It is a special type of convex lens, fitted only in external focusing
type telescope in between the object glass and eyepiece, at a fixed
distance from the object glass.
y The function of this lens is to reduce the stadia constant to zero,
by reducing all the observation to the center of the instrument.
230.
Chapter 8
Example 8.5 : The focal length of the object glass of a tacheometer is
200 mm, the distance between the vertical axis of tacheometer and the
optical center of the object glass is 100 mm and the spacing between
the upper & lower stadia is 4 mm. With the line of collimation perfectly
horizontal, the staff intercepts are 1 m (top), 2 m (middle) & 3 m (bottom).
The horizontal distance (m) between the staff and instrument station
is
(a) 103.0 (b) 100.3 (c) 150.0 (d) 153.0
[GATE 2008]
Solution: Given, f = 200 mm, d = 100 mm, i = 4 mm
s2
s3
= 100.3 m
So, the correct answer is (b).
231.
Chapter 8
A1 A
C s
Trigonometric and Tacheometric Levelling
B
1h
A L B
s/2 E V
90+/2 90
O
A1 s/2 cos C F
D
Figure 8.11 : Elevated sight
s s
A1B1 = A1C + CB1 = cos q + cos q
2 2
A1B1 = s cos q
L = KA1B1 + C
232.
Chapter 8
L = Ks cos q + C
D = L cos q
L = (Ks cosq + C) cos q
=D Ks cos2 q + C cos q
V = FC = L sin q
V = (Ks cosq + C) sinq
V = Ks cosq sinq + C sinq
Ks
=V sin2q + C sin q
2
Elevation of staff station(E) = HI + V – h
O D F
q Line of Axis
a
V
L B B'
C
s
A' A h
E
Figure 8.12 : Depressed sight
233.
Chapter 8
L = Ks + C
D = OF’ + F’F
OF’ = L cos q = (Ks + C) cos q
F’F = h sinq
=
D (Ks + C) cos q + h sin q
V = L sinq
V =(Ks + C) sin q
O F F'
q Line of Axis
a
V
L A
C
s
B h
D E E'
L cos q
h
sin q
Figure 8.14 : Depressed sight
D = L cosq – h sinq
D =
(Ks + C) cos q – h sin q
V = L sinq
Trigonometric and Tacheometric Levelling
V =(Ks + C) sin q
234.
Chapter 8
Solution: Given, RL of P = 205.45 m, h = 2.916 m
Angle of depression = 15°30’
K = 100, C = 0
(i) s = 3.38 – 2.45 = 0.93 m
Since, staff is held normal and angle of depression
D = L cosq – h sinq
= (Ks + C) cosq – h sinq
= (100 × 0.93 + 0) cos 15°30’ – 2.916 sin 15° 30’
D = 88.84 m
V = L sinq = (Ks + C) sinq
= (100 × 0.93 + 0) sin 15°30’
= 24.85 m
(ii) RL of Q = HI – (V + h cos q)
= (RL of P + ht of trunnion axis) – (V + h cosq)
= (205.45 + 2.315) – (24.85 + 2.916 cos 15°30’)
= 207.765 – 27.659
= 180.106 m
Example 8.9 : The following readings were taken with a vernier theodolite
on a vertical staff
235.
Chapter 8
O a1 a2 a3 s s s
P1 P2 P3
Figure 8.15 : Movable hair method
y In this case the staff intercept is kept constant (s) & stadia angle (a) changes
with the staff position (P).
y The diaphragm has an arrangement for the measurement of stadia interval
which in this case is variable.
y Each hair of the stadia diaphragm can be moved independently by a separate
sliding bar/frame.
Micrometer screw
Graduated head
Horizontal hair of
cross hair
Lower stadia hair
Trigonometric and Tacheometric Levelling
Graduated
head Micrometer screw
Figure 8.16
236.
Chapter 8
y In this case stadia interval (i) is variable, which is measured with the help
of micrometer screw.
y If “P” is the pitch of the screw and “m” be the number of revolutions made
by screw then
i=mP
fs
D= +C
mP
f
Let =K
P
Ks
=
D +C
m
Case I – If staff is held vertical and line of sight is inclined.
Ks
= D cos2 q + C cos q
m
1 Ks
= V sin 2q + C sin q
2 m
Ks
V = + C sin q
m
237.
Chapter 8
1
Solution: Given, focal length = 325 mm, Pitch = cm
100
Distance of the instrument axis from the center of object glass = 300 mm
Ks
D= +C
m
C = f + d = (325 + 300) × 10–3 = 0.625 m
f 325 × 10–1
K= = = 3250
P 1
100
s=4m
m = 4.425 + 4.93 = 9.355
3250 × 4
D= + 0.625
9.355
D = 1390.256 m
238.
Chapter 8
8.4.2 Tangential method of tacheometry
y This method is used when diaphragm is not provided with the stadia hair
or when distance between staff and instrument is more which makes the
reading of the staff difficult.
y In this method a levelling staff is fitted with two big targets (vanes) at fixed
distance of 2 or 3 m.
y Vertical angle of these vanes is observed through the theodolite to find
horizontal distance as follows:
s
B
r
V
E
2 1
F
h
D
Figure 8.17 : Both angles in elevation
V+s
tan q1 = ….(i)
D
V
tan q2 = .…(ii)
D
s
tan q1 – tan q2 =
D
s
D =
tan q1 – tan q2
V = D tan q2
s tan q2
V =
tan q1 – tan q2
239.
Chapter 8
D
F
q1 q2
A V
s
B
r
E
V–s
tan q1 = ….(i)
D
V
tan q2 = .…(ii)
D
From (i) & (ii)
s
tan q2 – tan q1 =
D
s
D =
tan q2 – tan q1
V = D tan q2
s tan q2
V =
tan q2 – tan q1
Trigonometric and Tacheometric Levelling
q1 s
q2
V
B
h
r
E
D
Figure 8.19 : One in elevation and one in depression
240.
Chapter 8
s–V
tan q1 = ….(i)
D
V
tan q2 = ….(ii)
D
s
tanq1 + tanq2 =
D
s
D =
tan q1 + tan q2
V = D tan q2
s tan q2
V =
tan q1 + tan q2
241.
Chapter 8
Solution:
A (3.925)
s
s'
B (2.525)
h r V
6%
5% 5.5%
E
P (600) D
s'
(ii) D=
tan q3 − tan q2
242.
Chapter 8
Solution: P
D1 = Ks cos2q + C cosq
= 100 (2.92 – 2.3) cos2 5°20’ + 0
= 61.46 m
D1 D
Ks
V1 = sin2q + C sinq
2
1 36°40'
= × 100 × (2.92 – 2.3) sin (2 × 5°20’) + 0 R Q
2 D2
V1 = 5.74 m
RL of point P = HI + V1 – r1 = HI + 5.74 – 2.6
= HI + 3.14 m
D2 = Ks cos2q + C cosq
= 100(2.720 – 2.1) cos2 (10’40”) + 0 = 61.999 m
1
V2 = Ks sin2q + C sinq
2
1
= × 100 (2.720 – 2.1) sin (2 × 10’40”) + 0
2
= 0.192 m
RL of point Q = HI + V2 – r2 = HI + 0.192 – 2.41
= HI – 2.218 m
Difference of RL between A & B = (HI + 3.14) – (HI – 2.218)
= 5.358 m
D21 + D22 – D2
cos36°40’ =
2D1 D2
61.462 + 61.9992 – D2
cos36°40’ =
2 × 61.46 × 61.999
D = 38.84 m
Keywords
243.
Trigonometric and Tacheometric Levelling Chapter 8
244.
9 Theory of Errors
Chapter 9
9.1 INTRODUCTION
y In surveying measurement of both linear distances and angles is to be
carried out, true value of which is not possible to be measured as some or
the other errors creeps in.
Theory of Errors
245.
Chapter 9
Definitions
Most Probable Value: It is the value which has more chances of being
true than any other value.
p p
(i) (ii)
It represents large scatter It represents small scatter
of error hence signifying of error, hence signifying
low precision high precision
Figure 9.2
Definitions
246.
Chapter 9
s = standard deviation
s=
∑v 2
n−1
y Here standard deviation may also be termed as ‘Root mean square’ error of
the measured value.
Figure 9.3
Theory of Errors
Figure 9.4
247.
Chapter 9
s=
∑v 2
n−1
n = number of observations made
v = residual error
(b) Variance
y It is the square of standard deviation.
∑ v2
V =s2 =
n−1
∑ v2 s
sm =± =±
n ( n − 1) n
s1 = ±
∑v 2
= ±s
n−1
248.
Chapter 9
Most probable error = ±0.6745 s
n−1
Figure 9.5
em = ±0.6745
∑v 2
n(n − 1)
249.
Chapter 9
Solution:
77 -1 1.00
78 0 0
80 2 4.00
79 1 1.00
∑ =780 = 13.32
780
MPV = = 78
10
Error/residual/variation(v) = Measured value – Most probable value
(i) Standard deviation
s=
∑v
=
2
13.32
= 1.2165
n−1 10 − 1
(ii) Standard error of mean
∑ v2 13.32
sm = =
± =
±0.3847
n(n − 1) 10 ( 10 − 1)
(iii) Most probable error
Theory of Errors
e = ± 0.6745 s
= ± 0.6745(1.2165) = ± 0.8205
250.
Chapter 9
(iv) Most probable error of mean
em = ±0.6745 sm
= ±0.6745 (0.3847)
= ± 0.2595
(v) Variance
V = s2
= (1.2165)2 = 1.4799
(vi) Maximum error = ± 3.29 s
= ± 3.29 × 1 .2165 = ± 4.0
9.3 WEIGHT
y Until now the weightage of every observation was same but if it is changed,
analysis is done as follows:
y Here weightage of a quantity signifies its relative truth worthiness or
indicates its relative precision.
y Weightage is always expressed as a number, higher is the weightage, higher
is precision and lower is the weightage, lower is precision.
y Weightage are allocated to the observation according to the following rule:
(i) Weightages are assigned as per degree of precision, hence weightages
are taken inversely proportional to variance.
w1 v
= 2
w2 v1
(ii) Weightages of the quantity is measured in similar conditions is directly
proportional to the number of times the quantity is being measured
(n).
w1 n
= 1
w2 n2
(iii) Weightages are also being provided to the observation by the
surveyor on the basis of experience as per prevailing field condition/
environmental condition.
(iv) Weightage of the level line is inversely proportional to the length of
the line.
w1 L
= 2
w2 L1
9.3.1 Laws of Weight
(i) The weight of arithmetic mean of a number of observation of unit
Theory of Errors
251.
Chapter 9
Example:
∠A Weight ∠A Weight
40°30′8″ 1 40°30′10″ 1
40°30′10″ 1 40°30′9″ 1
40°30′7″ 1 40°30′10″ 1
1
Arithmetic mean = 40°30′ + (8′′ + 10′′ + 7′′ + 10′′ + 9′′ + 10′′)
6
= 40°30′9″
Weight of arithmetic mean = number of observations = 6
(ii) The weight of weighted arithmetic mean is equal to the sum of individual
weights.
Example:
∠A Weight ∠A Weight
40°20′8″ 2 40°20′9″ 4
40°20′10″ 3 40°20′10″ 3
40°20′6″ 2 40°20′10″ 2
= = = 40°20′9′′
(2 + 3 + 2 + 4 + 3 + 2) 16
Weight of the weighted arithmetic mean = 16
252.
Chapter 9
(iii) The weight of algebraic summation or subtraction of two or more
quantities is equal to reciprocal of summation of reciprocals of the
individual weights.
Example:
∠A = 50°40′20″, weight 3
∠B = 40°30′10″, weight 2
1 1 5
Sum of reciprocal of individual weight = + =
3 2 6
1 1 6
\ Weight of ∠A + ∠B ( = 91°10′30″) = = =
1 1 5 5
+
3 2 6
1 1 6
\ Weight of ∠A - ∠B ( = 10°10′10″) = = =
1 1 5 5
+
3 2 6
(iv) If the quantity of a given weight is multiplied by a factor, the weight of
the resultant is obtained by dividing its given weight by the square of
that factor.
Example:
∠A = 40°40′30″, weight 6
6 3
Then, weight of 2A(= 81°21′0″) = 2
=
(2) 2
(v) If the quantity of a given weight is divided by a factor, the weight of
resultant is obtained by multiplying its given weight by square of that
factor.
Example:
∠A = 44°20′30″, weight 6
A
Then, weight of =( 22°10′15′′) = 6(2)2 = 24
2
(vi) If an equation is multiplied by its own weight, the weight of resulting
equation is equal to the reciprocal of weight of equation.
Example:
A + B = 85°30′30″ , weight 2
1
Weight of 2(A + B) =
2
Theory of Errors
1
Weight of 171°1′0″ =
2
253.
Chapter 9
(vii) The weight of equation remains unchanged if all the signs of the
equation are changed.
Example:
A + B = 79°30′20″, weight 3
Then, weight of A – B = 3
Example:
A + B = 79°30′20″, weight = 3
Then, 180° - (A + B) = 100°29′40″, weight = 3
180° + (A + B) = 259°30′20″, weight = 3
∑(wv 2 )
sw =
n−1
(ii) Standard deviation (or error) of mean of weighted observation.
∑(wv 2 )
(sm )w =
±
(n − 1) ∑ w
(iii) Standard error of single observation of weightage wi.
∑(wv 2 )
(s1 )w =
±
(n − 1)wi
(iv) Most probable error of single observation of weight wi.
ew = ± 0.6745 (s1)w
∑(wv 2 )
ew = ±0.6745
(n − 1)wi
Theory of Errors
254.
Chapter 9
Example 9.2: The following are the measured values of angle P, with the
corresponding weightage.
∠P wi
1. 91°40′20″ 3
2. 91°40′25″ 4
3. 91°40′28″ 3
Determine:
(i) Standard deviation
(ii) Standard error of weighted mean
(iii) Standard error of single observation of w = 3
(iv) Probable error of weighted mean
Solution:
∠P wi vi vi 2 wivi2
∑ = 10
916°44′4′′
= = 91°40′24.4″
10
= 91°40′24.4″
255.
Chapter 9
7.01′′
= ± = ±2.22′′
10
∑(wv 2 ) 7.01′′
(s1)w = ± = ± = ±3.51′′
(n − 1)wi 4
Angle Weight
50°10′22″ 2
50°10′20″ 2
50°10′21″ 3
Calculate:
(a) Probable error of single observation of unit weight.
(b) Probable error of weighted arithmetic mean.
(c) Probable error of single observation of weight 3.
Solution:
50°10′22″ 2 +1 1 2
50°10′20″ 2 -1 1 2
Theory of Errors
50°10′21″ 3 0 0 0
∑w = 7 ∑wivi2 = 4
256.
Chapter 9
(22′′ × 2 + 20′′ × 2 + 21′′ × 3)
Weighted arithmetic mean = 50°10′ +
(2 + 2 + 3)
= 50°10′21″
Error/residual/variation(vi) = Measured value – Most probable value
(a) Probable error of single observation of unit weight
∑(wv 2 )
= ±0.6745
(n − 1)
4
= ±0.6745 = ±0.95′′
3−1
(b) Probable error of weighted arithmetic mean
∑(wv 2 )
= ±0.6745
(n − 1) ∑ w
4
= ±0.6745 = ±0.36′′
2(7)
(c) Probable error of single observation of weight 3
∑(wv 2 )
= ±0.6745
(n − 1)3
0.95
= = ±0.55′′
3
1 1 1
(b) + +
wx wy wz
(c) wx + wy + wz
Theory of Errors
257.
Chapter 9
1 36°30′ 4
2 36°00′ 3
3 35°30′ 8
4 36°30′ 4
The most probable value of the angle θ (in degree, round off to two
decimal places) is_____.
Answer: (36 to 36) (GATE-2021, SET-II)
1. 50°30′ 2
2. 50°40′ 3
3. 50°45′ 4
258.
Chapter 9
Solution:
The most probable value of the angle is equal to its weighted arithmetic
mean.
50°30′ × 2 + 50°40′ × 3 + 50°45′ × 4
Most probable value =
(2 + 3 + 4)
= 50°40′0″
df df df
dA= dx + dy + dz
dx dy dz
dA, dy, dz are individual error in x, y, z and standard error in A is given by
2 2 2
df df df
e =
2
A ex + ey + ez
dx dy dz
ex, ey, ez are standard error in x, y, z
Example:
(a) A(f) = x + y
2 2
df df
e2A = ex + ey
dx dy
2 2
d(x + y) d(x + y)
= ex + ey
dx dy
( )
1/2
eA = ex2 + ey2
dx dy dz
( )
2
= ( yz.ex ) + xz.ey
2
+ (xy.ez )2
259.
Chapter 9
e 2 e 2 e 2
y
= (xyz)2 x + + z
x y
z
1/2
e 2 e 2 e 2
y
eA = (xyz) x + + z
x y
z
x
(c) A(f) =
y
2 2
df df
e2A = ex + ey
dx dy
2 2
x x
d d
y y
= ex + ey
dx dy
2 2
e x
= x + − 2 ey
y y
x2 e 2 e 2
= 2 x + y
y x y
1/2
x e 2 e 2
eA = x + y
y x y
(d) A(f) = xn
2
df
e2A = ex
dx
2
d(xn )
= ex
dx
eA = (nxn−1ex )
b = 5 ± 0.02 m
Theory of Errors
h = 4 ± 0.03 m
Determine the standard error of V?
260.
Chapter 9
Solution:
Given:
l = 3 ± 0.04 m
b = 5 ± 0.02 m
h = 4 ± 0.03 m
2 2 2
df df df
e2v = el + eb + eh
dl db dh
2 2 2
d(lbh) d(lbh) d(lbh)
= el + eb + eh
dl db dh
ev = ± 0.9487
So, the standard error of V is ± 0.9487.
A = 4B × C
The observed values of B and C and their corresponding standard error are
as follows:
B = 40″ ± 0.03″
C = 50″ ± 0.05″
Determine the standard error of A.
Solution:
Given, A = 4B × C
Standard error at A,
2 2
df df
e2A = ex + ey
dx dy
2 2
d(4B.C) d(4B.C)
Theory of Errors
= eB + ec
dB dC
= (4C . eB)2 + (4B . eC)2
261.
Chapter 9
1/2
eA = ( 4C.eB ) + ( 4B.ec )
2 2
1/2
= (4 × 50 × 0.03)2 + (4 × 40 × 0.05)2 = ±10″
= 52 + 62 = ± 7.81″
Q: In case of level line, how the correction increases with the
increases in length of level line?
A: Weightage is inversely proportional to the length of level line, so
with the increase in length of level line the accuracy decreases
and with the decreases in accuracy the error increase thus the
Theory of Errors
262.
Chapter 9
Example 9.8: Adjust the angel A, B, C and D which close the horizon.
Angles Weight
∠A = 100°20′25″ 2
∠B = 80°30′08″ 1
∠C = 90°40′22″ 4
∠D = 88°29′10″ 3
Solution:
∠A + ∠B + ∠C + ∠D = 306°0′5″
Sum of angles = (2n – 4)90°
= (2 × 4 – 4)90° = 360°
Error of closure = Measured value – true value
= 360°0′5″ - 360° = 5″
Correction, C = -5″
\ Correction is inversely proportional to the weightage
1 1 1 1
C1 : C2 : C3 : C4 = + + + = 6 : 12 : 3 : 4
2 1 4 3
Corrections,
6
C1 = × (−5′′) = −1.2′′
12 + 6 + 4 + 3
12
C2 = × (−5′′) = −2.4′′
12 + 6 + 4 + 3
3
C3 = × (−5′′) = −0.6′′
12 + 6 + 4 + 3
4
C4 = × (−5′′) = −0.8′′
12 + 6 + 4 + 3
Corrected angles,
∠A = 100°20′25″ - 1.2″ = 100°20′23.8″
∠B = 80°30′08″ - 2.4″ = 80°30′5.6″
Theory of Errors
263.
Chapter 9
Check
∠A + ∠B + ∠C + ∠D = 100°20′23.8″+ 80°30′5.6″ + 90°40′21.4″
+ 88°29′9.2″ = 360°
Hence, the values are corrected.
∠Q = 125°13′12″ ± 5″
∠R = 150°15′15″ ± 3″
Find the corrected angles?
25
C2 = × 15=
′′ 7.5′′
9 + 16 + 25
9
C3 = × 15=
′′ 2.7′′
9 + 16 + 25
264.
Chapter 9
∑v2 = minimum
-2[x1 + x2 . . . . xn – n MPV] = 0
x1 + x2 . . . xn
MPV =
n
y If the observations are of unequal weight, the MPV is the value which makes
the sum of the product of weight and the square of residual to be minimum.
∑wv2 = minimum
Hence,
w x + w2 x2 . . . wnxn
MPV = 1 1
w1 + w2 . . . wn
y The least square adjustment is done by “Normal Equation Method/
Observation Equation Method” which is formed as follows:
Example 9.10: Find the normal equation of x, y, z from the following equation
of equal weight and determine the MPV of x, y, z.
4x + 4y + 2z – 5 = 0
2x + 3y + 3z – 7 = 0
6x + 2y + 5z – 22 = 0
Solution:
Let
4x + 4y + 2z – 5 = 0 . . . (i)
2x + 3y + 3z – 7 = 0 . . . (ii)
Theory of Errors
6x + 2y + 5z – 22 = 0 . . . (iii)
\ Normal equation of x
265.
Chapter 9
In equation (i), (ii) and (iii) the coefficients of x are 4, 2 and 6 respectively.
Hence,
4(4x + 4y + 2z -5) + 2(2x + 3y + 3z – 7) + 6(6x + 2y + 5z – 22) = 0
Example 9.11: Find the normal equation for x, y, z in the following equation,
whose weights are also given below:
4x + 4y + 2z – 5 = 0, weight 2
2x + 3y + 3z – 7 = 0, weight 3
Theory of Errors
6x + 2y + 5z – 22 = 0, weight 1
266.
Chapter 9
Solution:
Let, 4x + 4y + 2z – 5 = 0 . . . (i)
2x + 3y + 3z – 7 = 0 . . . (ii)
6x + 2y + 5z – 22 = 0 . . . (ii)
\ Normal equation for x
In equations (i), (ii) and (iii) the product of coefficients of x and weight of
respective equations are (4 × 2), (2 × 3), (6 × 1) respectively.
Hence,
(4 × 2) (4x + 4y + 2z -5) + (2 × 3) (2x + 3y + 3z – 7) +
(6 × 1) (6x + 2y + 5z – 22) = 0
267.
Chapter 9
Example 9.12: Find the MPV of the angle q + f from the following observation
equations:
q = 40°15′21″
f = 45°12′18″
q + f = 85°27′45″
Solution:
Let
q = 40°15′21″ . . . (i)
f = 45°12′18″ . . . (ii)
q + f = 85°27′45″ . . . (iii)
\ Normal equation for q
In equation (i), (ii) and (iii) the product of coefficients of q and weight of
respective equations are (1 × 1), (0 × 1), (1 × 1).
(1 × 1)q = 40°15′21″
(1 × 1) (q × f) = 85°27′45″
2q + f = 125°43′6″ . . . (A)
\ Normal equation for f
In equation (i), (ii) and (iii) the product of coefficients of f and weight of
respective equations are (0 × 1), (1 × 1), (1 × 1).
(1 × 1)f = 45°12′18″
(1 × 1)(q + f) = 85°27′45″
q + 2f = 130°40′3″ . . . (B)
After solving equation (A) and (B)
2q + f = 125°43′6″ × 2
q + 2f = 130°40′3″
4q + 2f = 251°26′12″
q + 2f = 130°40′3″
q = 40°15′23″
Theory of Errors
f = 45°12′20″
268.
Chapter 9
Example 9.13: Find the MPV of the angle q from the following observation
equations:
q = 40°20′20″, weight = 2
2q = 80°40′40″, weight = 3
4q = 162°21′50″, weight = 1
1 × 2 × q = 80°40′40″
2 × 3 × 2q = 484°4′0″
4 × 1 × 4q = 649°27′20″
30q = 1214°12′0″
q = 40°28′24″
NOTE:
(a) The probable error (or standard error) of the levels is directly proportional
to the square root of length of level line i.e.
e∝ L . . . (i)
(b) The weightage of levels in any level line is inversely proportional to the
length of the line.
1
w∝ . . . (ii)
L
From (i) & (ii),
1
w∝
e2
(c) Degree of accuracy in angular measurement
Angular error of closure
C=
number of angles measured
269.
Chapter 9
Solution:
Given, Angular error of closure = 180″
Number of angles measured = 9
Angular error of closure
Degree of accuracy in measurement =
number of angles measured
180′′
= = 60′′
9
So, the correct answer is (a).
Keywords
270.
10 Curves
Chapter 10
10.1 INTRODUCTION
y The curves are the transitions which are provided at the intersection of
two straight lines.
y A horizontal curve is provided at the point where the two straight lines
intersect in horizontal plane. Generally horizontal curves provided are
circular in nature.
y A vertical curve is provided at a point where two straight lines at different
gradient intersect in vertical plane. Vertical curves provided are generally
parabolic in nature.
curve
Horizontal Curve
271.
Chapter 10
V
V
T E T
M l
90° D 90°
PC (T1) PT (T2)
Fo
r
L
w
ar
t
d
en
ta
ng
ng
R R
ta
en
ck
t
Ba
A B
O
Figure 10.1: Components of curve
1. Back tangent: Tangent line before the beginning of the curve is called
back tangent (AT1).
2. Forward tangent: Tangent line after the end of the curve is called
forward tangent (BT2).
3. Point of intersection (PI): When the back tangent and the forward
tangent is extended, they intersect at a point, which is known as vertex
(V) or point of intersection (PI).
4. Deflection angle: Angle V′VB is the deflection angle, it may also be
denoted by D.
5. Point of curve (PC): It is the point at the beginning of the curve where
the alignment changes from a tangent to a curve.
6. Point of tangency (PT): It is point on the end of the curve where the
alignment changes from a curve to a tangent.
7. External distance (E): It is the distance between the point of intersection
(V) and mid-point of the curve.
8. Length of curve (L): It is the length of curve between point of curve (PC)
and point of tangency (PT). (T1CT2)
9. Tangent distance (T): It is the distance between PC and PI or the
distance between PT and PI.
Curves
272.
Chapter 10
10. Mid ordinate (M): It is the distance between the mid-point of the curve
(C) and mid-point of long chord (D).
11. Long chord: It is the chord of circular curve between PC and PT.
12. Right hand curve: If the curve deflects to the right of the direction of
the progress of survey, it is called the right hand curve.
13. Left-hand curve: If the curve deflects to the left of the direction of the
progress of survey, it is called the left hand curve.
ain length
1 Ch
1 Chain length
R R R R
D D
O O
Figure 10.2: Degree of curve
π
RD × = 30
180
Curves
273.
Chapter 10
ain length
1 Ch
R R
D
O
180 × 30
R=
πD
1718.87 1720
R= or
D D
\ If 1 chain length = 20m
π
RD × = 20
180
20 × 180
R=
πD
1145.9 1146
R= or
D D
L 1 chain length
R= =
D D
2 sin 2 sin
2 2
Curves
274.
Chapter 10
1 Chain length
R R
D
\ If 1 chain length = 30 m
30
R=
D
2 sin
2
30
=
2D π
×
2 180
1718.87 1720
R=
or
D D
\ If 1 chain length = 20 m
20
R=
D
2 sin
2
20
=
D π
2× ×
2 180
1145.9 1146
R=
or
D D
275.
Chapter 10
V′
V
D
T E T
M l
PC (T1) D
PT (T2)
90° 90°
Fo
L
rw
ar
t
d
en
ta
ng
R R
ng
ta
en
ck
t
Ba
A O B
Figure 10.3
D T
In DVT1O, tan =
2 R
Tangent length T1V or T2V
D
T = R tan
2
(iii) Length of long chord (L)
sin D L/2
In DT1DO, =
2 R
D
L = 2R sin
2
Curves
276.
Chapter 10
(v) External distance (E)
D R
In DVT1O, cos =
2 VO
R D
VO = = R sec
D 2
cos
2
External distance VC,E = VO – OC
D
E = R sec −R
2
D
=E R sec − 1
2
D
E = R exsec
2
(vi) Mid ordinate (M)
D OD
In DDT1O, cos =
2 R
D
OD = R cos
2
Mid ordinate CD,M = OC – OD
D
M = R − R cos
2
D
=
M R 1 − cos
2
D
M = R versin
2
(vii) Chainage of tangent point
y In general chainage of point of intersection (V) is known.
y Chainage of tangent point T1 = chainage of V – Tangent length
Chainage of tangent point T2 = chainage of T1 + l
277.
Chapter 10
Example 10.1: Two straight lines intersect at an angle of 60°. The radius of a
curve joining the two straight lines is 600 m. The length of long chord and
mid-ordinate in meters of the curve are respectively
(a) 80.4, 600.0
(b) 600.0, 80.4
(c) 600.0, 39.89
(d) 49.89, 300.0 [GATE 2007]
D = 60°
D
Length of long chord = 2R sin
2
60
= 2 × 600 × sin = 600 m
2
Curves
278.
Chapter 10
D
Length of mid ordinate = R 1 − cos
2
60
= 600 1 − cos
2
= 80.38 m ; 80.4 m
Example 10.2: Two straight lines intersect at a chainage 1005.5 and angle of
deflection is 60°. If the radius of curve is 550m. Compute all the elements
of this curve.
Solution:
(a) Length of curve
πR
l= ·D
180°
π × 550
= × 60 = 575.96 m
180
(b) Tangent distance
D
T = R tan
2
60
= 550 tan = 317.54 m
2
(c) External distance
D
E = R sec − 1
2
60
= 550 sec − 1
2
E = 85.08 m
D
M = R 1 − cos
2
60
= 550 1 − cos = 73.69 m
2
Curves
279.
Chapter 10
D
L = 2R sin
2
60
= 2 × 550 sin
2
L = 550m
= 1005.5 – 317.54
= 687.96 m
= 687.96 + 575.96
= 1263.92 m
Solution: Given, R = 50 m, l = 60 m
Long chord,
D
l = 2R sin
2
D
60 = 2 × 50 sin
2
D
= 36.87°
2
D
Mid ordinate, M = R 1 − cos
2
= 50 [1 – cos 36.87°]
M = 10.00 m
280.
Chapter 10
Example 10.4: A 4° curve is made between two tangents at a chainage
of [120 + 30] chains at a deflection angle of 70°. Calculate all the basic
parameters using 30 m chain with 150 links.
1718.87
Solution: D=
R
1718.87
R=
4
R = 429.717 ; 429.72 m
D
(i) Length of tangent (T) = R tan
2
70
= 429.72 tan = 300.89 m
2
πR
(ii) Length of curve (l) = D
180
π × 429.72
= × 70 = 525.00 m
180
D
(iii) Mid ordinate = R 1 − cos
2
70
= 429.72 1 − cos
2
= 77.714 m
D
(iv) External distance (E) = R sec − 1
2
70
E = 429.72 sec − 1
2
E = 94.87 m
D
(v) Length of long chord (L) = 2R sin
2
70
= 2 × 429.72 sin
2
= 492.95 m
Curves
281.
Chapter 10
30
V = 120 × 30 + × 30
150
= 3606 m
= 3606 – 300.89
= 3305.11 m
Chainage at T2 = Chainage of T1 + l
= 3305.11 + 525
= 3830.11 m
282.
Chapter 10
10.5.1 Linear method
(i) Offsets from long chord
P C
E
y
L/2 D
T1 T2
x
R
O
Figure 10.4
CD = OC – OD
OC = R
2
L
OD = 2
R −
2
2
L
CD = R − R2 −
2
(OD + y)2 = R2 – x2
y= R2 − x2 − OD
2
L
y= R2 − x2 − R2 −
2
Curves
283.
Chapter 10
x P
G T2
R
y
T1
F O
Figure 10.5
x = T1F = T1O – FO
T1 O = R
FO = R2 − y2
x = R − R2 − y2
1 y2
x = R − R 1 − 2
+ .... (Neglecting higher terms of y)
2R
y2
x = (approx)
2R
(iii) Offset from chord produced
b
C2 O2
O2
a O1 1 b
a
2 O2
C1 b
1 C2
C1 2
T1 R 3
R
R
21 22
A O
Figure 10.6
Curves
284.
Chapter 10
O1 = C1d1
O1
d1 = ...(i)
C1
C1 = R.2d1
C1
d1 = ...(ii)
2R
O1 C
= 1
C1 2R
C12
O1 =
2R
C2C1
O2′ = C2d1 =
2R
O2 ″
O2′′ = C2d2 ⇒ d2 = ...(iii)
C2
C2
C2 = R·2d2 ⇒ d2 = ...(iv)
2R
O2 ″ C
From (iii) and (iv) = 2
C2 2R
C22
O2′′ =
2R
C2C1 C22
O2 = +
2R 2R
C2 (C1 + C2 )
O2 =
2R
C3 (C2 + C3 )
Similarly, O3 =
2R
Curves
285.
Chapter 10
Cn (Cn−1 + Cn )
Similarly, On =
2R
C12
O1 =
2R
C1C + C2
O2 =
2R
C2
O3 = O4 = O5 = .....On – 1 =
R
CCn + Cn2
On =
2R
Example 10.5: Two tangents intersect at a chainage 70.85 (70 chains, 85
links). The deflection angle being 70°. Calculate the necessary data to set
out a circular highway curve of 20 chain radius to connect two tangent by
the method of offset from chords. Take 20 m chain length (100 links).
85
Solution: Chainage of point of intersection (V) = 70 × 20 + × 20
100
= 1417 m
D
Tangent length (T) = R tan
2
70
= 400 tan = 280.083 m
2
πR
Length of curve (l) = ×D
180
π × 400
= × 70 = 488.692 m
180
Curves
286.
Chapter 10
V = 70°
T
l
T1 T2
= 70°
Chainage of T1 = Chainage of V – T
= 1417 – 280.083
= 1136.917 m
Chainage of T2 = Chainage of T1 + l
= 1136.917 + 488.692
= 1625.609 m
[Chainage of T1 is 1136.917 m so, the chainage of 1st sub chord will be the
multiple of 20 and more than the chainage of T1].
C1 = 1140 – 1136.917
= 3.083 m
C2 = C3 = C4 .... Cn – 1 = C = 20 m
[Chainage of T2 is 1625.609 m so, the chainage of last sub chord will be the
multiple of 20 and less than the chainage of T2].
Curves
287.
Chapter 10
Cn = 1625.609 – 1620 m
= 5.609 m
C1 Cn
l − C1 − Cn
Number of chords = + 1+ 1
20
n = 26
C12
O1 =
2R
(3.083)2
= = 0.0119 m
2 × 400
C1C + C2
O2 =
2R
3.083 × 20 + 202
= = 0.577 m
2 × 400
C2
O3 = O4 ..... O25 =
R
202
= =1m
400
C25C26 + C262 C Cn + Cn2
O6 = =
2R 2R
20 × 5.609 + (5.609)2
= = 0.179 m
2 × 400
NOTE:
(a) This method is the best method for longer curves of larger radius
by linear methods & is usually used when the theodolite is not
available.
(b) It has the advantage that not all the land between tangents and curve
need to be accessible.
Curves
288.
Chapter 10
(iv) Radial offset from tangent
x
A T1 a′
a
Ox
R
R
O
Figure 10.7
In DOT1a′ R2 + x2 = (R + Ox)2
R + Ox = R2 + x2
Ox = R2 + x2 − R
1
x2 2
= R 1 + 2 − R
R
x5
x4
x3
x2
x1
Ox Ox 2 Ox 3 Ox
1 4 Ox 5
Figure 10.8
Curves
289.
Chapter 10
1 x2
Ox = R 1 + 2
+ ... − R (Higher terms are neglected)
2R
x2
Ox = R + −R
2R
x2
Ox =
2R
C
C4 C5
C1 C2
D4 D5
C3
C6
D3 D2
D1 D6
T1 T2
D
O
Figure 10.9
290.
Chapter 10
10.5.2 Angular method
(i) Tape and theodolite /Rankine’s/Tangential/Deflection angle method
y In this method tape is used for making linear measurement and theodolite
is used for making angular measurement.
y For this method it is recommended that chord length does not exceed
R
as this ensures that the length of chord may be approximated to the
20
corresponding length of arc.
3
1
2 a
2 b
C2
1 C1 3
1 2 C3
T1 3
c
R R
R R
A 22 2
21 3
O
Figure 10.10
D1 = d1
D2 = d1 + d2 = D1 + d2
D3 = d1 + d2 + d3 = D2 + d3
Dn = Dn – 1 + dn
Curves
291.
Chapter 10
Here, d1, d2 ..... dn are the tangential angle made by the successive chords
T1a, ab, bc, .... with their respective tangents.
D1, D2, .... Dn are the deflection angles made by successive chord T1a, T1b, T1c
with back tangent at T1.
NOTE: V
D
a b
c
Dn
T1 T2
A B
O
Figure 10.11
1
Here Dn = deflection angle between back tangent and forward tangent.
2
D
Dn =
2
2πR
Now, C1 = . 2d1
360
90C1
d1 = degree
πR
90C2
d2 = degree
πR
90Cn
dn = degree
πR
Curves
292.
Chapter 10
Example 10.6: Two tangent intersect at a chainage of 1200 m, the deflection
angle being 40°. Compute the data required to set out a simple circular
curve of radius 400 m, using deflection angle method. Take 30 m chord
length = 1 chain length.
D
Tangent length (T) = R tan
2
40
= 400 tan = 145.588 m
2
πR
Length of curve (l) = ×D
180°
π × 400
= × 40° = 279.25 m
180°
Chainage of T1 = Chainage of V – T
Chainage of T2 = Chainage of T1 + l
C2 = C3 ...... Cn – 1 = 30 m
l − C1 − Cn
Number of sub chords = + 2
30
279.25 − 25.59 − 13.65
= + 2
30
= 10
Curves
293.
Chapter 10
Sub chord length (l) Tangential angle (d) Deflection angle (D)
(m) (Dn = Dn – 1 + dn)
C2 = 30 2.15 3.98
C3 = 30 2.15 6.13
C4 = 30 2.15 8.28
C5 = 30 2.15 10.43
C6 = 30 2.15 12.58
C7 = 30 2.15 14.73
C8 = 30 2.15 16.88
C9 = 30 2.15 19.03
NOTE:
(a) The above procedure of tape and theodolite method as discussed is for
right hand curve, but if the curve is left hand curve, the theodolite is
set up at point of tangency (T2) and vernier is set to be zero and line of
right is directed towards V.
(b) For the first peg, the vernier A is set at an angle of D1′ = 360° – D1
Similarly, for second peg, D2′ = 360° – D2
Similarly, for nth peg, Dn′ = 360° – Dn
D1 = d 1
D2 = d1 + d2 = D1 + d2
Dn = Dn – 1 + dn
Curves
294.
Chapter 10
b
2
D
a
2 –
D2
1
D
D1
2 –
D
D2
T1 D1 T2
2d2
A
2d1 B
O
Figure 10.12
y In this method two theodolites are used for the angular measurements and
no linear measurement is being carried out.
y One of the theodolites is placed at T1 and other at T2.
y This method is quite accurate than other method.
y It is suitable to be used when taping/chaining is difficult i.e., where ground
is rough.
y In this method the error in setting out is not carried forward as each point
is fixed independently.
y This method is based upon the property of the circle that chord makes an
angle at the centre of circle which is twice the angle made by the chord at
any other point on the circle.
y Hence, it can be concluded that the angle made by the chord with the
tangent at a point is equal to the angle which chord subtends at any other
point on the circle.
295.
Chapter 10
100
–g2% 100
g1%
–
g2 g2
%
g1
g1 %
C
x
Figure 10.14
y = ax2 + bx + c
At x = 0, y = c
Curves
296.
Chapter 10
dy
= 2ax + b
dx
dy
At x = 0, = g1
dx
g1 = b
d2 y
= 2a
dx2
Rate of change of gradient is uniform, which offers best riding quality.
Horizontal
Vertical Curve
curve
Summit Valley/sag
curve curve
g2 % –g1%
g1% –g2%
g1% –g2%
297.
Chapter 10
–g1% g2%
g2%
–g1%
–g2%
g1%
y
x y
C
T1 T2
x D
Figure 10.17
298.
Chapter 10
y For parabolic curve, normal offset from the tangent (y′) is proportional to
square of the distance from tangent point (T1) along the tangent (x′).
y Since parabolic curve is flat at top normal offset (y′) is equal to vertical
offset (y).
y′ = y
x
cos q =
x′
x′ = x sec q
y′ ∝ x′2
y′ = Kx′2
y = Kx′2
y = K (x sec q)2
y = K sec2 q x2
Let K sec2 q = c
y = cx2
c′
b′ –g2(%)
a′ y3
y2
g1(%) y1 C
a b c
T1 T2
x1 D
x2
x3
l l
Figure 10.18
Curves
299.
Chapter 10
RL of T1 = RL of V – g1l
RL of T2 = RL of V – g2l
1
RL of D = (RL of T1 + RL of T2 )
2
VD = RL of V – RL of D
1
VC = VD
2
As y = cx2
y1 = cx12 . . . (i)
VC = cl2 . . . (ii)
y1 x2
from (i) and (ii) = 21
VC l
2
x
y1 = 1 VC
l
2
x
Similarly, y2 = 2 VC
l
2
x
Similarly, yn = n VC
l
y RL of a′ = RL of T1 + g1x1
Similarly, RL of b′ = RL of T1 + g1x2
Similarly, RL of different points on tangent T1V can be computed.
y Now, RL of a = RL of a′ – y1
RL of b = RL of b′– y2
Similarly, RL of different points on curve can be computed.
NOTE: In case of sag curve, the offsets are to be added to the RL of point
of tangent to get the RL of points of curve.
Curves
300.
Chapter 10
10.7.1 Alternate methods for setting of vertical curve
y Since vertical curve provided is parabolic, eg. of which is given by:
V
y –g2%
g1%
P
T2
h
R
T1 x
x
(0, 0)
Figure 10.19
y = ax2 + bx + c
At x = 0, y = 0
0 = a(0)2 + b(0) + c
c=0
y = ax2 + bx
dy
= 2ax + b
dx
dy
At x = 0, = g1
dx
g1 = 2a(0) + b
b = g1
y = ax2 + g1x...(a)
Curves
301.
Chapter 10
PQ = PR – QR
PQ = g1x – y
PQ = – ax2
h = – ax2
h = cx2
Let h is the difference between elevation of tangent and vertical curve, is
termed as ‘Tangent Correction’. Which is found as follows:
V 1
B
g1 (%) –g2 (%)
C
T1 1
T2
D
n chords n chords
Figure 10.20
T1V = VA
AT2 = AB + BT2
AB = g1 · n chords
BT2 = – g2 · n chords
302.
Chapter 10
Now tangent correctionAT2 = cx2
AT2 = 4 (n chords)2 c
g 1 − g2
c=
4 n chords
(a) Elevation by tangent correction method
RL of T1 = RL of V – g1 · n chords
RL of T2 = RL of V – g2 · n chords
y Calculate the tangent correction from h = cx2 for various stations (Q) on
curve.
h1 = c(1)2 = c
h2 = c(2)2 = 4c
h3 = c(3)2 = 9c
Q1 V
P1 Q C –g2 (%)
g1 (%)
Q3
P
T1
Q2
P2
D T2
Figure 10.21
303.
Chapter 10
= 1 · g1 – c(1)2
= g1 – c
g 1 − g2
Here, c=
4 n chords
Similarly, second chord gradient
Q1Q2 = 2 · g1
Q2Q3 = PP2 = g1 – c
QQ3 = g1 – 3c
Similarly, third chord gradient = g1 – 5c
Similarly, nth chord gradient = g1 – (2n – 1)c
Now, Elevation of first station = Elevation of T1 + PP2
Elevation of second station = Elevation of P + QQ3
Similarly, Elevation of any station = Elevation of previous station + chord
gradient
(b) Also computed the staff readings required, given that the height of
collimation is 340.0 m, RL of apex is also 340 m and its chainage is
1200.0 m.
Curves
304.
Chapter 10
Solution: Given, chainage of vertex = 1200 m
200
Total number of stations on the curve = = 10
20
Number of stations on each side of apex = 5
340 m V 340 m
d′
c′
3% –2%
b′ C
a′ d
b c
a
T1 T2
337 D 338
Chainage of T1 = Chainage of V – 5 × 20
Chainage of T2 = Chainage of T1 + l
3
= 340 − 100 × = 337 m
100
Elevation of T2 = Elevation of V – (5 × 20)g2
2
= 340 − 100 × = 338 m
100
g 1 − g2
Tangent correction c =
4n chords
3% − (−2%)
= = 1.25 × 10–4
4 × 5 × 20
y1 = cx2 = 1.25 × 10–4 (20)2 = 0.05
305.
Chapter 10
3
= 337 + 20 ×
100
= 337.6 m
3
Elevation of 2nd station on tangent = 337 + 2 × 20 ×
100
= 338.2 m
3
Elevation of 3rd station on tangent = 337 + 3 × 20 ×
100
= 338.8 m
3
Elevation of 4th station on tangent = 337 + 4 × 20 ×
100
= 339.4 m
3
Elevation of 5th station on tangent = 337 + 5 × 20 ×
100
= 340.0 m
3
Similarly, Elevation of 10th station on tangent = 337 + 10 × 20 ×
100
= 343.0 m
Curves
306.
Chapter 10
(a) Elevation by tangent correction method
307.
Chapter 10
308.
Chapter 10
Previous Year’s Questions
P v2
=
W gR
P v2
tan q = =
W gR
Curves
309.
Chapter 10
For roads,
Bv 2
e = B tan θ =
gR
For railways,
Gv 2
e = G tan θ =
gR
Equilibrium cant: If v is taken in km/hr
G = 1.5 m, R in m
2
v × 1000
1.5
Cant (e) = 60 × 60 × 100
9.81 × R
1.18v 2
e= cm
R
Where,
W = weight of vehicle
P = centrifugal force
v = speed of vehicle
g = acceleration due to gravity
B = width of road
R = radius of curve
P 1 v2
For roads, = =
W 4 gR
gR
v=
4
P 1 v2
For railways, = =
W 8 gR
gR
v=
8
Curves
310.
Chapter 10
10.8.3 Condition of an ideal transition curve (clothoid)
(a) Centrifugal force ∝ length
P∝l
Wv 2
P=
gr
W, v, g are constants
1
l∝
r
lr = constant
(b)Super-elevation ∝ length
1.18v 2
e=
r
1.18v 2
e∝l∝
r
1
l∝
r
lr = constant
L = nh
Bv 2
L= n (for roads)
Rg
Gv 2
L= n (for railways)
Rg
(ii) By time rate: Let the time rate of application of super-elevation be x
cm /s.
L = length of transition curve (m)
h = super-elevation (cm)
v = speed of vehicle (m/s)
Distance = speed × time = vt
h
L = v×
x
Curves
311.
Chapter 10
v Gv 2 Gv 3
L= × =
x gR xgR
(iii) By rate of change of radial acceleration
v2
Radial acceleration =
R
v2
Rate of change of radial acceleration = R = a
t
v2
t=
aR
Length of transition curve L = vt
v3
L=
aR
Example 10.8: The relationship between the length (l) and radius (r) of an
ideal transition curve is given by [GATE -1999]
(a) l ∝ r (b) l ∝ r2
1 1
(c) l ∝ (d) l∝
r r2
Solution: For an ideal transition curve
P∝l
Wv 2
P=
gr
W, v, g are constant
1
l∝
r
So, the correct answer is (c).
312.
Chapter 10
Solution: Given: D = 55°, R = 250 m
Rate of gain of radial acceleration = 0.3 m/s3
v2
Radial acceleration =
R
v2
Rate of change of radial acceleration (a) = R
t
v2
t=
aR
Length of transition curve (L) = vt
3
50 × 1000
3
v 60 × 60
L= =
aR 0.3 × 250
L = 35.72 m
So, the correct answer is (c).
Keywords
313.
Curves Chapter 10
314.
11 Photogrammetry and
Remote Sensing
Chapter 11
11.1 PHOTOGRAMMETRY
y Photogrammetry is the science of obtaining the information of physical
objects through the process of recording, measuring, and interpreting
photographs.
y Aerial photography is a branch of photogrammetry in which photographs
are taken from the camera mounted on aircraft flying over the area.
y If the camera is mounted on the ground or
above the ground, it is termed as ground Gray Matter Alert!!!
photogrammetry.
If vertical features of mountains,
11.2 TYPES OF AERIAL PHOTOGRAPHS cliffs, valley etc is required
(a) Vertical photograph to be study then ground
(b) Oblique photograph photogrammetry is preferred,
but if alignment of railway,
11.2.1 Vertical photograph roadways, canals, pipelines
y In vertical photograph, camera axis is vertical etc. is to be studies then aerial
i.e., line of gravity of camera and axis of camera photogrammetry is preferred.
consides.
Camera
Camera axis
Vertical photograph
Figure 11.1
Vertical axis
q
Camera axis
Oblique
photograph
Figure 11.2
315.
Chapter 11
• Reference point located in the image plane of the camera used to provide the
reference line for measurement of image distance is termed fiducial marks.
Generally, they are 4 or 8 in number.
• Lines joining the opposite fiducial mark are termed as fiducial lines.
Figure 11.3
316.
Chapter 11
+y
xa
a
ya
qa
–y +x
O qb yb
b
xb
–y
Figure 11.4
ab = (xa − xb )2 + (ya − yb )2
angle aOb = qa + qb
y
−1 y
= tan−1 a + tan b
x
a xb
NOTE: In the above analysis the photo coordinates are measured with
respect to fiducial lines, but it can also be measured with respect to fiducial
mark and this method is termed as TRIALTERATIVE METHOD.
xa xc
B
Figure 11.5
da 2 + AB2 − db2
cos q =
2da .AB
317.
Chapter 11
y
f = tan−1 b
x
a
a = f–q
yc = da sin a
xc = xA + da cos a
Example 11.1: In the figure calibrated coordinates of the fiducial mark A and
B are as follows:
X Y
Point A –120 mm 0
Point B 0 –120 mm
A
C
( −120 − 0) + ( −120 − 0)
2 2
Solution: AB =
= 169.70 mm
da 2 + AB2 + db2
cos q =
Photogrammetry and Remote Sensing
2da . AB
1852 + 169.702 − 952
=
2 × 185 × 169.70
q = 30°41′′
−120
f = tan−1 = 45°
−120
a = f–q
= 45° – 30°41′ = 14°19′
yc = –da sina
= –185 sin 14°19′ = –45.74 mm
318.
Chapter 11
xc = xA + da sina
= –120 + 185 cos 14°19′ = 59.25 mm
So, the coordinate of point ‘C’ is (59.25 – 45.74).
xc yc
⇒ xa = × xa ′ ⇒ y=
a × ya ′
xm ym
A′
Earth
A
Figure 11.6
319.
Chapter 11
f
b
a c
Projection on Photograph d
(Prospective projection) B
C
A
D
Photogrammetry and Remote Sensing
b′
c′
a′
Projection on map
(orthographic projection)
d′
Figure 11.7
320.
Chapter 11
(i) Flat ground/terrain
Figure 11.8
321.
Chapter 11
y Hence when elevation is higher, scale is larger and when elevations lower,
scale is smaller.
y To eliminate this variation of scale of vertical photograph, datum scale
is used which is the scale of vertical photograph that would be effective
over the entire photograph if all the ground points are projected vertically
downwards on the datum line (MSL) before being photographed.
ab
Datum scale (Sd) =
AoBo
LO f
= LP = H
f
Sd =
H
L
f Positive
a b
O
H
B
GL
A hB
GL
hA
Datum
AO P BO
Figure 11.9
Figure 11.10
322.
Chapter 11
y The average scale is the scale of vertical photograph, that would be effective
over the entire photograph if all the ground points were projected vertically
either downward or upward on the place of the average elevation of the
ground before being photographed.
f
Savg. =
H − havg.
Solution: f = 150 mm
= 150 × 10–3m
H = 6000 m
hx = 1000 m
hy = 2000 m
hz = 2500 m
(a) Scale of photograph at point x = (Sx)
f
Sx =
H − hx
150 × 10−3
=
6000 − 1000
1
Sx =
33333.33
Scale of photograph at point y = (Sy)
f
Sy =
H − hy
150 × 10−3
=
6000 − 2500
323.
Chapter 11
1
Sz =
23333.33
1
So maximum scale =
23333.33
1
Minimum sale =
33333.34
1
(b) Average elevation of ground surface = 1000 + 2000 + 2500
3
= 1833.34
f
Savg. =
H − havg
150 × 10−3
=
6000 − 1833.34
1
Savg. =
27777.78
1
Example 11.3: A map of the area plotted at the scale of is available ,
15000
the length of a runway on the map is 200 mm. If the photo distance of the
runway is 250 mm, then determine the scale of photograph.
Photo distance
Solution: Scale of photograph = ...(i)
Ground distance
Map distance
Scale of map = ...(ii)
Ground distance
From equation (i) and (ii)
Photogrammetry and Remote Sensing
324.
Chapter 11
y Let ground co-ordinates of point ‘A’ is XA and YA and corresponding photo
coordinates are xa and ya.
Then ground coordinates XA and YA are given as:
L
y
xa
f
a′′ a
O ya
x Y
a′
XA
A′′ A
hA
YA
A0
A′
Datum (MSL) hA
P
x
Figure 11.11
DLaa″ ; LAA″
XA H − hA
=
xa f
H − hA
XA = xa
f
Photogrammetry and Remote Sensing
f
Here = SA
H − hA
x
XA = a
SA
325.
Chapter 11
H − hA ya
YA = ya or YA =
f SA
Example 11.4: The measured photo coordinates of image point ‘a’ and ‘b’
of two ground points A and B are xa = 50 mm, ya = 40 mm, xb = –35 mm,
yb = –48 mm. Determine the ground coordinates of point A and B and
horizontal length of line AB. The elevation of point A and B are 250 m and
200 m respectively, the flying height is 2000 m above the datum and focal
length is equal to 200 mm.
H − hA
Solution: XA = xa
f
2000 − 250
= 50 −3
× 10−3
200 × 10
= 437.5 m
H − hA
YA = ya
f
2000 − 250
= 40 −3
x 10-3
200 × 10
= 350 m
H − hB
XB = xb
f
2000 − 200
= −35 −3
× 10−3
200 × 10
= –315 m
H − hB
YB = yb
f
Photogrammetry and Remote Sensing
= 2000 − 200
−48 −3
× 10−3 = – 432 m
200 × 10
B
(XB, YB)
(XA, YA)
326.
Chapter 11
AB = (XA − XB )2 + (YA − YB )2
2
= (437.5 − ( −315)) + (350 − ( −432))2
= 1085.25 m
Relief is the elevation of the object above and below the datum.
If the object is above the datum relief displacement is outward and if
object is below the datum relief displacement is inwards.
L
f
O
a
a′
O
H
a′
r′
a
d
r A0
hA
Figure 11.12
DLaO ~ DLAAo
r f
=
R H − hA
327.
Chapter 11
f. R = r (H – hA) ...(1)
DLa’O ~ DLA’P
r′ f
=
R H
f. R = r’. H ...(2)
From equation (1) and (2)
r’. H = r (H – hA)
r. hA = r. H – r’. H
H(r – r’) = r. hA
rhA
(r – r’) =
H
Here r – r’ = d = relief displacement
rhA
d=
H
dA a′
Photogrammetry and Remote Sensing
b′ c′
b dB dC
B C
rh
d =
H
rAhA
dA =
H
100 × 250
= = 16.67 m
1500
328.
Chapter 11
rBhB
dB =
H
90 × 200
= = 12 mm
1500
rChC
dC =
H
80 × 150
= = 8 mm
1500
f
Sd =
H
150 × 10−3
=
1500
1
=
10, 000
B
A
p
The lengths of the image of the tower A on the photograph is 1.5 cm and of the tower B
is 2.0 cm. The distance of the top of the tower A (as shown by the arrowhead) is 4.0cm
and the distance of the top of the tower B is 6.0 cm, as measured from the principal
point p of the photograph. If the height of the tower B is 80m, the height (in meters) of
the tower A is _______.
329.
Chapter 11
( XA − XB ) + ( YA − YB )
2 2
Solution: AB =
H − hA
XA = xa
f
H − hB
XB = xb
f
H − hA
YA = ya
f
H − hB
YB = yb
f
Photogrammetry and Remote Sensing
2 2
H − h H − hB H − h H − hB
AB = xa A
− xb + ya A
− yb
f f f f
2 2
H − 460 H − 425 H − 460 H − 425
100 = 18.35 − 100 + –60 − (–20)
200 200 200 200
H = 527m
330.
Chapter 11
NOTE:
(1) This is one of the method available to compute the flying height of
vertical photograph. How ever it can also be computed with the focal
length and scale of photograph.
f f
S = =
H−h H′
f
H′ =
S
(2) Flying height of the aircraft is decided by contour interval in the
topography map.
By this flying height is given by:
flying height = (C-factor) × Contour interval
C-factor = 500 – 1500, depending upon the coordinate of map
compilation.
Solution: The relation between map scale and photo scale is given by:
1/n 12
=
1/50000 2.5
1 1
Photogrammetry and Remote Sensing
=
n 10416.67
f 1
∴ S = =
H−h n
1 20 × 10−2
=
10416.67 H − 200
H = 2283.34m
331.
Chapter 11
Question : A camera with a focal length of 20 cm fitted in an aircraft is used for taking
vertical aerial photographs of a terrain. The average elevation of the terrain is 1200 m
above mean sea level (MSL). What is the height above MSL at which an aircraft must fly
in order to get the aerial photographs at a scale of 1:8000?
(a) 2600 m (b) 2800 m (c) 3000 m (d) 3200 m
Answer: (b) [GATE 2019, SET-II]
Question : A square area (on the surface of the earth) with side 100 m and uniform
height, appears as 1 cm2 on a vertical aerial photograph. The topographic map shows
that a contour of 650 m passes through the area. If focal length of the camera lens is
150 mm, the height from which the aerial photograph was taken is -
(a) 800 m (b) 1500 m (c) 2150 m (d) 3150 m
Answer: (c) [GATE 2018, SET-I]
332.
Chapter 11
y Side laps are required to cover the gaps which are left uncovered in single
flight path.
Flight
Strip width
Strip width
60% Flight
Longitudinal
overlap
Figure 11.13
333.
Chapter 11
A
Number of photographs required =
a
Here, A = ground area to be covered= L x B
a = area covered by one photograph = l’ × b’
l’ = length covered by one photograph on ground
b’ = width covered by one photograph on ground
l = length of photograph
b = width of photograph
334.
Chapter 11
Photograph b
l
Figure 11.15
l’ = ( 1 − Pl ) Sl
b’ = ( 1 − Ps ) bS
a = ( 1 − Pl ) Sl × ( 1 − Ps ) bS
Where, S = scale of photograph
Pl = longitudinal overlap
Ps = side lap
AS2
No. of photograph required (N) =
( 1 − Pl ) l ( 1 − Ps ) b
NOTE: Here, only lap area is considered to account for area covered.
Figure 11.16
335.
Chapter 11
l b
(
a = 1 − Pl )
× 1 − Ps
S
S
( )
a = (1500) (2625)
= 3937500 m2
= 3.9375 km2
Photogrammetry and Remote Sensing
A
Number of photographs = N =
a
2000
= = 507.932508= 508
3.9375
So the total photographs required is 508.
336.
Chapter 11
Solution: L =
40 km
B =
35 km
Pl =
60%
Ps =
30%
l =
250 mm
b =
250 mm
L B
N = N 1 N2 = + 1 + 1
l b
(
1 − P
l)S
(
1 − P
s
S
)
40 × 103 35 × 103
+ 1 + 1
N = 250 × 10−3 250 × 10−3
( )
1 − 0.6 1
( )
1 − 0.3 1
9000 9000
N1 = [46][24] = 1104 photographs
337.
Chapter 11
(2) Drift
y It is the lateral displacement of photograph. The photograph does not stay
on its predetermined path due to effect of wind.
y If the drifting from the predetermined flight line is excessive, refights will
have to be made because of serious gapping between adjacent flight lines.
Q: Which data are required for computation of the quantities for the
flight plan?
A: Data required for computation of the quantities for the flight plan
are
(i) Focal length of the camera lens
(ii) Altitude of the flight of the aircraft.
(iii) Size of the area to be photographed
Photogrammetry and Remote Sensing
338.
Chapter 11
Gray Matter Alert!!!
3600L
T =
V
T = time interval
B
L1
L2
b a b′ a′
Photogrammetry and Remote Sensing
O
O
nd
1st Position 2 Position
(Left photograph) (Right photograph)
A
B
(a)
339.
Chapter 11
L1, L2
b′ a′ O b a
Pa
Pb
(b)
Figure 11.18
340.
Chapter 11
Solution: A = 150 km2
S = 1 in 10000
l = 200 × 10–3 m
b = 200 × 10–3 m
Pl = 60%
Ps = 30%
l b
a = (
1 − Pl
S
) (
× 1 − Ps
S
)
200 × 10−3 200 × 10−3
= (
1 − 0.6 × )
1
(
× 1 − 0.3 ×) 1
10000 10000
a = 1120000 m2 = 1.12 km2
A
Number of photographs = N =
a
150
= = 133.9 ≈ 134
1.12
So, the correct answer is (d).
f
Solution: Scale of photograph S =
H − h′
h’ = 2000 m
S = 1 in 10000
1 25 × 10−2
=
10000 H − 2000
H = 4500m
So, the correct answer is (b).
341.
Chapter 11
1
Solution: S =
10000
f = 25 × 10–2 m
r = 8 cm
h = 300 m
f
Datum scale = Sd =
H
1 25 × 10−2
=
10000 H
H = 2500 m above MSL
rh
Relief displacement (d) =
H
8 × 300
=
2500
= 0.96 cm
So the correct answer is (c).
elevation of 300 m above datum was taken with a camera having focal
length of 30 cm. A section line AB, 300 m long in area measures 10 cm
on the photograph. A tower in the area also appears on the photograph.
The distance between the image of top and bottom of the tower measure
0.50cm on the photograph. If the distance of image of the top of tower is
8 cm, then the height of tower will be
(a) 76.50 m (b) 36.25 m
(c) 50 m (d) 56.25 m
342.
Chapter 11
Map distance f
Solution: Scale = =
Ground distance H
10 30
=
300 H
H = 900 m
dH 0.50(900)
Height of tower h = =
r 8
= 56.25 m
So, the correction answer is (d).
343.
Chapter 11
Wave length
Sun
(4) Sensors
(5) Transmission of data to
Wave length earth station and generation
of valid products
gy
(2) into
er
Pro
en
ed
pa mosp
itt
gat
em
at
ion he re
&
ed
of
ct
fle
en
Re
erg
y
Photogrammetry and Remote Sensing
344.
Chapter 11
y For precise measurement at least 3 satellites are required for 2-D
locations of a point and 4 satellites are required for 3-D location of a
point.
y Different GPS system available are:
(a) NAVSTAR – USA
(b) NAVIC – India
(c) BEIDOU – China
(d) GALILEO – European Union
(e) GLONASS - Russia
11.16 SATELLITE
y It is the platform that carries the sensor and other payloads required in
remote sensing operation.
11.16.1 Polar orbit satellite
y These are satellites which revolves around earth in a sun synchronous
orbit and have altitude around 700-1500 km they are situated with fixed
345.
Chapter 11
Hardware
DATA
Users Software
Figure 11.20
346.
Chapter 11
Example 11.15: Which one of the following is an Indian GPS?
(a) ARYABHATTA (b) NAVSTAR
(c) NAVIC (d) SARAL
347.
Chapter 11
Keywords
Aerial photogrammetry
Ground photogrammetry
Photo coordinates
Ground coordinates
Crab
Drift
Scale
Relief displacement
Flying height
Overlap
Remote sensing
GPS
GIS
Satellite
Parallax
Photogrammetry and Remote Sensing
348.