Nit 1119pro
Nit 1119pro
FOR
VOLUME I
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information.
R0
CONTENTS
ISSUE
SECTION SPECIFICATION NO. TITLE
NO.
VOLUME I
ISSUE
. R0
ISSUE
SECTION DRAWING NO. TITLE
NO.
VOLUME II
D TCE.M4-418-01 R5 Earthwork in Grading, Excavation & Backfilling
D TCE.M4-418-03 R2 Dewatering
D TCE.M4-403-01 R9 Reinforced Concrete and Allied Works
D TCE.M4-419-01 R3 General Building Works
D D6-M4-422-02 R1 Specifications for concrete roads
D TCE.M4-422-01 R4 Specification For Plant Roads
D TCE.M4-435-09 R0 Reinforced Cement Concrete Pipes
VOLUME III
G TCE.6842A-CV-3000-3005-12 R0 Bid Drawings & Documents
G ANNEXTURE I Geotechnical Investigation Report
G ANNEXTURE II Survey drawing
ISSUE
. R0
SECTION A
ISSUE
R0
1.0 The scope of this enquiry covers design, supply of material and construction
of all civil works required for execution of Road and storm water drains works
for the 500 TPD Methanol and 200 TPD Formalin plant at Namrup, Assam.
1.1 The Contractor’s scope of work shall cover designing, detailing and
construction of roads and storm water drains including supply of material
including loading/unloading and storage, preparing detailed design drawings
based on concept note of road and drain works and obtaining approval of
ENGINEER/OWNER on the same before starting the Construction activity at
site, preparing all construction drawings, including construction of roads,
drains and pavements, ground improvement if necessary as per geotechnical
test results, excavation and backfilling/ filling, disposal of excess material
outside the plot at locations approved by Engineer-in-charge or local
authority, any permissions/certification/permits required for obtaining any type
of approval from local authorities shall be arranged by bidder on his own cost,
dewatering, providing sub-base, sub-grade, rubble soling, providing all
designed layers for bituminous plant roads, reinforced concrete and allied
works, brickwork for puling pits, catch pits, RCC trenches,
dismantling/demolishing of existing structures etc. all as per the technical
specification & bid purpose drawings attached in Volume III of this tender,
furnishing of all materials, storage of materials, equipments, labour, transport,
tools, tackles, including taxes and royalties, Construction Management &
Supervision and all other services necessary for the complete execution of
works, including inspection and testing, quality checks and safe execution of
works, including required geotechnical investigations, surveying and setting
out necessary for the road and drain works and clean up of working areas
after completion of the Works, without disturbing the existing foundations and
underground services, including demolishing of old existing underground
structures, if any, etc. as directed by OWNER/ENGINEER. The scope shall
also cover providing and maintaining temporary access roads/supporting
structure for movement of the equipment/ vehicles and temporary drainage, if
required.
1.2 Contractor shall design, supply and construct the plant roads for the extents
and widths as indicated in the bid purpose drawings, considering the design
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 2 OF
3000-3005-01
14
1.3 The bid purpose road and drain layout drawing attached with this tender is to
show the extents of the road works which shall be executed under phase-1 &
phase-2. Contractor shall design the road cross section based on the CBR
values tested at various locations along the length of road, soil conditions and
design requirements in line with the relevant codes and standards to cater the
traffic loading conditions as mentioned in concept note attached with this
tender. Contractor shall design the drain cross section based on the quantity
of discharge to cater the area surrounded by drain, invert level/depth of drain,
surcharge load in that area, soil and ground water conditions, vehicle
movement envisaged etc. as mentioned in the concept note attached with this
tender. Contractor shall quote considering all site constraints, tender
requirements and anticipating all possible conditions at site.
1.4 Contractor shall execute the road works in phases as mentioned below:
II. Phase-2 work shall be commenced one to one and half year after
receipt of LOA or after mechanical completion of methanol plant which
is under construction at proposed site, whichever is earlier. Contractor
shall obtain the schedule from the OWNER/Engineer for the
mechanical completion of the proposed plant and shall plan the
phase-2 activities accordingly. (For details of phase-2 work scope
refer clause no. 3).
1.5 The CONTRACTOR shall design all plant roads to ensure that there is no
settlement or cracking of the roads, If in case the road surface is observed
with cracks or pot holes, the same shall be rectified replacing the area making
it good for use, CONTRACTOR shall provide the remedial and corrective
measures to avoid the same in future at his own cost.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 3 OF
3000-3005-01
14
1.6 Contractor shall keep record of all the material quality checks, all site tests
conducted before, during and after construction and submit the same to
ENGINEER or OWNER. Demolishing and reconstruction of any work required
as a result of any missing road crossings or underground work, poor quality of
workmanship, defects in material or construction or structural/functional
failure to achieve required quality standards of the work shall be considered in
Contractor’s scope. The contractor shall make good, rectify or replace the
element/ road/drain/shoulder etc but not limited to above items, without
prejudice or any claim on Owner/ Consultant.
1.7 Contractor shall provide all detailed drawings, Specifications and Procedures
required to perform all civil works related to road and drains along with the bill
of quantities.
1.9 Within 10 days of receipt of Letter of Intent (LOI) the Contractor shall submit a
detailed methodology for carrying out all works as per the scope of the tender.
These submittals shall be consistent with the general information submitted
by the Contractor with his Tender, and agreed to by the Engineer-in-Charge
and the Contractor. The priority for execution of the road and drain works
shall be finalised and decided during the kick-off meeting.
1.10 Engineering data, design calculations and drawings shall be submitted by the
contractor during the progress of the work, such drawings shall be in AutoCad
2014 format only. All the supporting documents, design calculations for road
and storm water drain along with the drawings shall be provided by
CONTRACTOR for review to the ENGINEER / Owner. The CONTRACTOR
shall proceed with the construction activity at the site only after getting
approval on drawings and design documents from the ENGINEER/OWNER.
1.11 Any approval from ENGINEER or OWNER will not relieve the contractor of
his contractual obligations and his responsibilities for correctness of structural
design, dimensions, materials of construction, weight, quantities, design
details, installation of underground road crossings as per correct levels and
locations, performance requirements and conformity of the supplies with the
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 4 OF
3000-3005-01
14
Indian Statutory Laws as may be applicable, nor does it limit the purchaser’s
rights under the contract.
1.12 The Contractor shall work out lumpsum cost based on the scope document in
conjunction with the corresponding sections in the technical Specifications
and bid drawings for extent of work, General Directions & Conditions of
Contract, Special Conditions of Contract and all the other sections of this
tender document, etc. The Contractor shall study all the documents &
drawings and acquaint himself with the requirements of tender documents
and work to be executed.
13.1 Prior approval from OWNER shall be taken before site visit or conducting any
field test before bidding. Any clarification for understanding the scope shall
be sought before submitting the bid.
1.14 All statutory clearances and drawings which pertains for execution of the
project shall be obtained by the EPC CONTRACTOR at their cost in the name
of the OWNER with due approval from the OWNER.
1.15 The Contractor shall provide three sets of hard copies along with one
electronic copy of all the good for construction drawings/documents. Along-
with, the Contractor shall provide native electronic copy of all drawings/
documents.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 5 OF
3000-3005-01
14
1.16 The Contractor shall be responsible submitting the documents well in time
and obtaining approval from Engineer. Delay on account of approval shall not
be entertained and neither it shall be considered for time extension nor for
non-compliance to project schedule.
1.18 The Contractor scope shall include preparation and submission of all as built
drawings, after completion of project. The Contractor shall provide three hard
copies and one electronic copy of all latest as built drawings and documents
along with all latest native files.
2.1 Phase-1 scope of work shall include design, supply, setting out and
construction of roads as described in clause 1 of this scope as mentioned in
bid purpose plot plan attached with this tender document.
2.2 Phase-1scope of work shall include design the storm water drain network
system to collect the storm water from the proposed plot area and direct the
flow towards existing outfall point through peripheral drains as indicated in bid
purpose drawings or through separate network to connect to outfall points as
marked in the drawing. The storm water drain network/route shown in the bid
purpose drawing is suggestive and the same can be updated during detail
engineering for further optimisation of storm water drain depths.
2.3 Phase-1 scope of work shall include design of storm water drains, box/pipe
culverts, trenches with covers etc. designed as per the concept note attached
with this tender document, preparation of approval purpose drawings, obtaining
approval from the ENGINEER and issuing the good for construction drawings
etc. complete for the drains which shall be executed in phase-2 scope.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 6 OF
3000-3005-01
14
necessary survey shall be conducted for locating existing drain network and
invert levels, outfall location etc. to prepare the proposed drain network
2.5 The CONTRACTOR shall design the storm water drain network ensuring that
no flooding will occur during monsoon periods. If the network fails and the plant
gets flooded, CONTRACTOR shall provide the remedial and corrective
measures to rectify the same to avoid such condition in future at his own cost.
2.6 Contractor shall design and plan the storm water drain network to avoid
interferences with the existing UG facilities, foundation activity/work.
2.7 Contractor scope shall cover connecting internal drains with peripheral or any
other existing drains, after studying the site layout and capacity of the existing
drain and then deciding the suitable method to transfer the internal/ plant drain
discharge in to the external/ existing peripheral drains by maintaining the invert
levels as of existing/peripheral drains to avoid back flow or flooding of plant
area. Contractor scope shall also provide box or pipe culverts to connect
internal or plant drains to peripheral and to ensure proper drainage of the area
as tentatively shown in bid purpose layout. Contractor’s scope shall include
studying the site layout and capacity of the existing drain and then deciding the
suitable method to transfer the internal/ plant drain discharge in to the external/
existing peripheral drains if the gravity flow is not possible due to restrictions in
the existing levels. (Preferably contractor shall provide gravity network)
2.8 Contractor’s scope shall also study and provide pumping station and related
infrastructure for pumping out storm water drain water to outfall point if required
as per the site conditions. Contractor’s scope shall include the cost effective
solution for operation and maintenance of the drains.
2.9 Contractor shall prepare scheme for storm water drain philosophy based on the
concept note and bid purpose drawing. Contractor shall obtain approval from
ENGINEER before start of detail engineering and subsequently construction
activity. Contractor’s scope shall also include surveying if required to get the
existing data from site and to establish smooth connecting in overall drain
network.
2.10 Design and Construction of the roads up to WBM for the roads demarcated to
have movement of ODC trailer and 300Mt /100Mt crane movement shall be in
Contractor’s scope of works under phase-1. Contractor shall obtain approval
on axle load data for 300Mt and 100Mt crane prior to the start of the detail
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 7 OF
3000-3005-01
14
engineering and shall consider multiple axel wheel loading for the road design
for crane movement area demarcated in plot plan. If as per plot plan the road is
utilised by crane and ODC both in that case the governing wheel load shall be
considered for the design of road.
2.11 Contractor shall design phase-1 roads, of width and size as mentioned in the
bid purpose drawings and as per the concept note to cater all expected loading
without damage and undulations in the road. The road subsequent layers upto
and including the layer of water bound macadam including making it finished to
facilitate smooth vehicle movement, scope will also cover the repair and
modification of the road during construction work if damaged due to heavy
vehicle movement to which it is to be designed.
2.13 Contractor shall provide necessary filter layers to take care of ground water
table and to avoid possible damage to the bottom layers of the roads.
2.14 Contractor’s scope for peripheral road, Main approach road and internal roads
which are existing roads and already constructed upto WBM as demarcated in
the bid purpose drawing, shall include conducting the CBR test at various
locations of the existing peripheral road as per specifications and removing soft
pockets and damaged areas of the existing WBM road, refurbishment of road
including checking strengthening requirement of existing sub-base for
proposed vehicular traffic movement as indicated in the concept note/bid
purpose drawings.
2.15 The Contractor scope shall include supplying hume pipes, excavation,
backfilling, preparing bedding for receiving the hume pipes, laying in correct
slope, level, coordinates & alignment, keeping projection beyond road and
drain extents as mentioned in the drawing, or wherever required constructing
RCC box culverts/RCC trenches with precast covers designed for vehicular
movement, for all underground road crossing for facilities such as
Electrical/I&C cable crossings, Sanitary drain pipe crossing, Oily
water/effluent/process drain pipe crossings, fire water piping, natural gas pipe
line storm water drain road crossings pipe/rcc box culverts etc. all as per the
approved final IFC drawings. Coordinating with other contractors for interface
shall be in Contractor’s scope. Contractor shall also provide pulling pits, sumps
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 8 OF
3000-3005-01
14
for electrical and I&C cable crossings etc., laid to correct levels and sizes
during phase-1 work. Contractor shall obtain the approval on the drawing
showing roads marked with the hume pipe details, numbers of pipes, locations,
levels, sizes etc. requirement of the hume pipes is mentioned in underground
facility drawings, fire water layout drawings, ERC/IRC detail drawings attached
with this tender document, before completing the road construction activity
during phase-1 work.
2.16 Contractor shall obtain the latest revisions of the underground facility drawings
(which are listed in the bid purpose drawings) from OWNER/ENGINEER and
shall ensure that the underground road crossings are installed as per the latest
revisions of the drawings.
2.17 Contractor’s scope shall also cover designing and providing concrete
road/pavement upto bottom of DLC (Dry lean concrete) layer of rigid pavement,
including excavation, dewatering, ground improvement or ground stabilisation
as per geotechnical requirements and soil design parameters, constructing all
required base layers like sub-grade, granular sub-base of designed thickness
etc all complete in loading gantry area, weight bridge area and tanker waiting
and tanker queuing area as demarcated in bid purpose plot plan. Any existing
effluent drain stream or proposed storm water drain coming in this area shall
be designed and routed through RCC drains and covered with concrete
precast slabs or RCC box culvert both designed to withstand the vehicular
movement load without damage as per the concept note attached with this
tender document. The trenches, pits, drains provided in the tanker movement
area shall be flush with the FRL/Finished paving level in that area and no
projections shall be provided above ground. Contractor shall provide the gentle
slope in the pavement in loading area to facilitate proper drainage of this area
and to avoid the water logging, The contractor shall design, construct and
provide suitable scheme for loading area so that the underground facilities in
the area can be maintained without causing any interruption in future
operations of this area. Preferably trenches with precast covers designed for
vehicular loads shall be provided to lay fire water pipes, electrical/ I&C cables,
etc.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 9 OF
3000-3005-01
14
3.1 Contractor’s scope for Phase-2 work includes preparation of phase-1 roads for
receiving finishing top layers of WBM roads, providing finishing top layers of
the of flexible pavement above WBM as per specifications attached in this
tender document.
3.2 Contractor’s scope shall also include interconnection with all existing roads to
provide smooth connection between the existing road and proposed road.
3.3 The CONTRACTOR shall provide and fix cautionary / warning sign board &
Mandatory / Regulatory sign board as per MORTH (IV R)) technical
specification and IRC 67.
3.4 The CONTRACTOR shall provide and apply 2.5mm thick hot applied
thermoplastic road marking (white colour) in continuous or broken stripes in
curves / straight stretch, junctions, using computerised vehicle mounted
marking system as per MORTH Specifications.
3.6 Contractor’s scope for phase-2 shall include supply and construction of road
shoulder, including necessary bottom layers, providing paver blocks etc. all
complete as per concept note and specifications attached in this tender
document.
3.7 The Contractor scope for Phase-2 shall include supply and construct the storm
water drain network including providing road crossings as per as per approved
IFC drawings from phase-1 scope.
3.8 Contractor’s scope shall include supply and construction of any work which is
required to be executed as a part of residual engineering related to road, storm
water drains and underground road crossing works and which was not
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 10 OF
3000-3005-01
14
executed during phase-1 work but is necessary to complete the work for
operation of plant.
3.9 The Contractor shall design, construct, rain water collecting catch pits, sumps
and shall connect the same in the required slopes to nearest storm water drain
to match with the nearest storm water drain invert levels to ensure that there is
no back flow and there will not be any clashes with other underground facilities.
3.10 The Contractor shall include supplying hume pipes, excavation & backfilling
and preparing bedding for receiving the hume pipes, laying in correct slope,
level, coordinates & alignment, keeping projection beyond road and drain
extents as mentioned in the drawings, design, supply and construct/ erect pipe
culvert/box culverts wherever required for all underground facilities which shall
be part of residual engineering of phase-1 works and which shall be executed
after commissioning of methanol plant. The same shall be executed before
completing the final plant road construction activity during phase-2 work.
Contractor shall consider that additional hume pipes which are required to be
installed in phase-2 as a part of residual engineering shall be less than 15% of
the total length of hume pipes provided in phase-1 works. Installation of hume
pipes which are missed by contractor during execution of phase-1 work due to
lack of coordination in phase-1 shall be installed by contractor at no extra cost
to OWNER.
3.11 Contractor shall work in close coordination with the other contractor for all
interface activities and underground civil works and obtain required data from
these contractors. No claim shall be acceptable resulted due to lack of
coordination with the other contractors.
3.13 Contractor shall ensure during construction of the storm water drains at site that
the existing facilities are not disturbed or damaged. Failing to ensure the same
Contractor shall make good, rectify or replace the element/ structure, without
prejudice or any claim on Owner/ Consultant.
3.14 Contractor shall ensure that other underground facilities which are located
below drain are constructed before construction of the drain or suitable size of
humepipes to correct levels and locations shall be provided to facilitate routing
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 11 OF
3000-3005-01
14
of such facilities after construction of the drains. Contractor shall also ensure
that the street lighting pole foundations are constructed before construction of
the road/ shoulder/drains, contractor to coordinate the same with other
contractors. Rework caused due to ignoring such information shall not be
considered for extra claims. Contractor shall closely coordinate with the other
contractor for the underground facilities which are in other contractor’s scope of
work.
3.15 Contractor’s scope shall include establishing the invert levels of the outfall
points available at site and also working out the options to connect the internal
drains to two different out fall point to limit the depth of drains.
3.16 Any change with respect to site conditions or modifications required to be done
in design and drawings to avoid clashes at site or required to be done as per
site conditions and which are not shown in plot plan shall also be considered
by contractor and no extra claim pertaining to the same shall be accepted at
later date.
3.17 Contractor shall note that the execution of road and drain shall be done
simultaneously for same stretch of the road. Excavation required for drain in
the previously constructed WBM road which is wider than the final plant road
width shall be accounted by contractor in his scope.
3.18 It is not the intent to specify completely herein all details of the works for road
and storm water drain. However, the work executed shall conform in all
respects to high standards of engineering design and workmanship and be
capable of performing in continuous commercial operation in a manner
acceptable to the Engineer/ Owner who will interpret the meaning of drawings
and specifications and shall have the power to reject any work or materials
which in his judgement are not in full accordance therewith.
3.19 Brick work for pits, sumps, trenches if any shall be as per specifications
mentioned in general building works. The same shall be designed for stability
and all design pressures and loads envisaged. For pits deeper than 2m depth,
the RCC pits shall be considered. All such pits shall be covered with precast
concrete cover of required thickness to suit the spanning. The sizes of the
pulling pits shall be decided based on number of hume pipes connected to
pulling pit and invert level of pipe with respect to site conditions, the pit top
shall be kept minimum 150mm above Finished ground level.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 12 OF
3000-3005-01
14
4.2 Bidders shall particularly note the depths of ground water level mentioned in
geotechnical report accordingly the filter layer is to be provided as per IRC
requirements. The subsoil information contained in the Geotechnical
Investigation Report is given to the Bidder in good faith and no claim from the
Contractor shall be entertained for any inaccuracy or discrepancy in the same.
4.3 In this case, Contractor can carry out the geotechnical investigation for
additional information or to verify the existing geotechnical data with no extra
cost. Further Contractor shall share the geotechnical investigation report
carried out by Contractor with the ENGINEER/OWNER. If any deviation in
design parameters is obtained from the geotechnical investigation carried out
by Contractor, the same shall be used for design work only after prior approval
from ENGINEER/OWNER.
4.4 Bidders shall get acquainted with the site conditions and soil constraints and
study the geotechnical report thoroughly. No extra claims shall be accepted for
ignoring the site conditions and for not considering the same in the design.
4.5 Removing soft pockets if any and filling the pockets with course grained
material having minimum CBR of 8% shall be in CONTRACTOR’s scope of
works, no extra claims for the same shall be made. The Material used in sub
grade shall satisfy the design CBR.
4.6 The existing soil shall be excavated up to the desired depth below existing
ground level as per the road cross section requirements and thicknesses of
various layers below road, the top surface of excavated area shall be sprinkled
with water and the same shall be compacted up to 95 % of its maximum dray
density (MDD). The CBR value of this sub grade shall be checked by
performing the field CBR test.
4.7 The Contractor shall backfill the excavated area with selected soil as per
MoRTH Specifications/ relevant IRC standards, having CBR value more than
8%. The CBR test shall be conducted at excavated area prior to start of fill of
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 13 OF
3000-3005-01
14
selected soil in excavated area and test results shall be submitted for review.
The selected soil shall be filled in layer and each layer not exceeding 150 mm
thick and each layer shall be compacted to 95% of its maximum dry density.
The field CBR shall be performed on the top of this layer to confirm the CBR
value.
4.8 The effective CBR based on the CBR value of sub base and CBR value of
selected soil shall considered for design of plant roads. The effective CBR shall
be estimated as per the guidelines as mentioned in relevant IRC codes and in
line with the MORTH technical specifications.
4.9 The plant road design shall be reviewed based on the actual CBR values
received from the field tests (CBR shall be above 8%). The extra sub-
base/sub-grade thickness needed on account of lower CBR value or any
ground improvement required for the same shall be carried out by the
Contractor at his own cost.
4.11 Capillary cut off in line with the IRC and MORTH technical specifications shall
be provided due to high water table as per the method approved by
ENGINEER/OWNER.
4.12 Sub grade shall be compacted and finished to the design strength consistent
with other physical requirements. The actual laboratory CBR values of
constructed sub grade shall be determined on undisturbed samples cut out
from the compacted sub grade in CBR mould fitted with cutting shoe or on
remoulded samples, compacted to the field density at the field moisture
content.
4.13 CONTRACTOR shall conduct the desired test at various stages and at various
locations for road works as per IRC and MORTH technical specifications.
Laboratory or site testing, including material testing inspection and keeping the
records of the test reports shall be in CONTRACTOR’s scope of works. The
rate shall include the same.
4.14 Definition for completion for plant road work includes, conducting field tests
required to obtain the road design parameters from site, designing of road
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: A
TCE.6842A -CV-
SCOPE OF ENQUIRY SHEET 14 OF
3000-3005-01
14
cross section for the loads as per concept note, preparation of road layout and
road cross section drawings showing various road layers and thicknesses of
each layers and extents of layers, and obtaining approval on the drawings,
issuing good for construction drawings, excavation, compaction of sub-grade,
providing sub-base of design thicknesses in layers to achieve 95% standard
proctor density, conducting field test to check the CBR, providing further layers
as per design requirements as per IRC and MORTH specifications, providing
WBM, bitumen layers, finishing layers and coats etc. all complete, including
laying of hume pipes as per specifications, providing road shoulders including
drain pipes, grill, kerb stones, painting of kerb stone, road marking finishing of
all miscellaneous activities related to road works.
4.15 Definition for completion for drain work includes, preparing drain network,
obtaining approval from Engineer, designing of the plant drain network based
on concept note attached with this tender, designing of drain cross section for
various depths based on invert levels and for the surcharge pressure as
mentioned in concept note, preparation of drain network layout and road cross
section drawings checking clashing of network with various underground
facilities as per attached bid purpose drawings/latest drawings obtained from
OWNER/ENGINEER, obtaining approval on the drawing and designing, issuing
good for construction drawings, excavation, compaction of soil, pcc, rubble
soling, construction of RCC drains, providing connection of hume pipes from
road/catch pits etc. with the nearest drain, providing precast concrete covers in
operating areas or where the drains are located in tanker movement areas,
including supplying and providing corner angles for precast covers, providing
mortar screed for finishing of drains etc. complete.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: TITLE
TCE. 6842A -CV-
TENDER FOR ROAD AND STORM WATER DRAIN
3000-3005 SHEET 1 OF 1
WORKS
SECTION B
ISSUE
R0
3. Project Title 500 TPD Methanol and 200 TPD Formalin Plant
a) Maximum 38 Deg.C
b) Minimum 5 Deg. C
8. Relative Humidity
9. Rainfall
ISSUE
R0
SECTION E
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-03
INSTRUCTION TO BIDDERS SHEET 1 OF 34 OF 4
1 INTRODUCTION
1.1 Assam Petro-Chemicals Limited, a public Sector Undertaking under the State
Govt. of Assam, India was set up in the year 1976 with facilities for production of
30 TPD of Methanol and 50 TPD Formaldehyde based on Natural Gas (NG).
After establishing itself as a successful Company in the Petrochemical Sector, the
Company expanded the business by setting up a new Methanol plant of capacity
100TPD based on I.C.I. Technology in the year 1986 and a new Formaldehyde
plant of capacity 100 TPD with technology from DERIVADOS, Spain which has
then been revamped to 125 TPD in the year 2012. The Company has ever since
been running with excellent operational and financial performances achieving
capacity utilization from the plant at the level of 95 to 100% on yearly basis and
consistently earning profit. The Company now intends to further expand the
business by setting up a new 500 TPD Methanol Plant & 200 TPD Formalin
Project along with captive power Unit and then to go for setting up plants for
downstream value added products like D.M.E, V.A.M, Polyvinyl Acetate, Polyvinyl
Alcohol etc. to establish itself as a major Petrochemicals Complex in the region.
APL proposes construction of infrastructure facilities like Storm Water Drain and
related works for the proposed plant.
1.2 Approach to site:
The APL factory is situated at Namrup in the district of Dibrugarh, Assam, India.
Namrup is connected with Dibrugarh by national Highway NH-37 and is at a
distance of around 70 KM from Dibrugarh and around 65 KM from Dibrugarh Air
Port. The nearest railway Station is Namrup Station and is at a distance of 9 KM.
The Station has siding facilities suitable for handling Project equipments. The
Railway Track is Broad Gauge.
1.3 Assam Petrochemicals has appointed Tata Consulting Engineers Limited (TCE)
for providing the PMC Services for implementation of above project. TCE on
behalf of CLIENT invites sealed bids under two bid system for the entire work
covered in the bidding document. All bids are to be completed and returned in
accordance with ENQUIRY requirements within the duration as mentioned below.
Sl Description Remarks
No.
Assam Government procurement portal
Bidding Document along website
a.
with Addendum/ Time https://assamtenders.gov.in/nicgep/app
Extension etc. (if any)
ISSUE
R0
available on Websites(for OR
viewing & downloading) APL‟s website
www.assampetrochemicals.co.in
ISSUE
R0
[email protected]/
[email protected]
180 days from the DUE DATE or
Bid Validity EXTENDED DUE DATE which ever is
k.
later.
2.1 Earnest Money Deposit (EMD): INR 24,00,000/- (Rupees Twenty Four lakhs
Only) in the form of Demand Draft (DD) (from Nationalised Bank) in favor of
“Assam Petrochemicals Limited” at the State Bank of India, Namrup Branch,
Namrup, Pin- 786623 or non-revocable Bank Guarantee (BG) from Nationalised
Bank as per the APL format (annexure-I). EMD shall not bear any interest.
2.1.1 EMD validity (For BG Only): EMD shall initially be valid for 6 months from the due
date for bid submission. Bidder shall extend EMD Validity on its expiry as per
requirement of APL till the order is not placed on Vendor / Contractor (Successful
Bidder); failing to provide Extension in EMD Validty shall lead to rejection of bid.
2.1.2 Exceptions: The following categories of tenderers are exempted from EMD;
Necessary Provisions shall be made in Tender Documents:
Public sector Enterprises
Vendors registered with National Small Scale Industries Corporation (NSIC)
For this purpose, in the event of the tendering company being a Public Sector
Enterprise, a declaration to that effect and in the case of vendors registered with
NSIC, a copy of the registration certificate should be obtained.
2.1.3 Refund of EMD: After acceptance of order by Vendor / Contractor (successful
bidder), APL shall return the EMD to all unsuccessful bidders. EMD shall be
returned to the Vendor / Contractor (successful bidder) after its submission of the
security deposit of required amount and in stipulated time.
ISSUE
R0
2.2 Price Bid Opening: Will be intimated later to the techno-commercially acceptable
bidders.
2.3 The offers submitted by bidders shall be either neatly spiral bounded or hard
bounded. Offers submitted in loose/stapled papers will not be accepted.
2.4 BID FEE: NIL
2.5 Price Bid Opening: Will be intimated later to the techno-commercially acceptable
bidders.
2.6 The offers submitted by bidders shall be either neatly spiral bounded or hard
bounded. Offers submitted in loose/stapled papers will not be accepted.
ISSUE
R0
3.2.2 Bidders submitting their bids should not be under liquidation court receivership or
similar proceedings. An undertaking duly sealed and signed from Proprietor /
Partner / CEO/ Director of the company is required to be submitted. The bidder
should not have been black listed or kept under holiday list in any Public Sector
Undertakings in India.
3.2.3 There shall not be any case or charge under investigation / enquiry / trial against
the bidder, nor convicted in a court of Law nor suspended / black listed by any
organization on any grounds. An undertaking duly sealed and signed from
Proprietor / Partner / CEO/ Director of the company is required to be submitted.
3.2.4 Further, in case of a consortium, if any of the member(s) of consortium has been
banned by any Government or quasi Government agencies or PSU on due date
of submission of bid this fact must be clearly stated and it may not necessarily be
a cause for disqualifying him. However, if this declaration is not given, the bid will
be rejected as non- responsive.
Similarly, if a bidder is qualified based on engaging a sub-contractor/ sub-vendor/
who meets stipulated qualification criteria, in case such a sub-contractor has
been banned by any Government or quasi Government agencies or PSU on due
date of submission of bid this fact must be clearly stated and it may not
necessarily be a cause for disqualifying him. However, if this declaration is not
given, the bid will be rejected as non- responsive.
3.2.5 A firm (which is not a PSU or an associate or a joint venture of a PSU) which has
been engaged to provide goods or works for this project and any of its affiliates
will be disqualified from providing consultancy services for this project.
Conversely, a firm (which is not a PSU or an associate or a joint venture of a
PSU), hired to provide consultancy services for the preparation or implementation
of this project, and any of its affiliates, will be disqualified from subsequently
providing goods or works or services related to the initial assignment for this
project.
Consultants or any of their affiliates who are not PSUs or an associate or a joint
venture of a PSU will not be hired for any assignment, which by its nature, may
be in conflict with another assignment of the consultants.
If a contractor submits his bid, qualifies and does not get the contract because of
his being not the lowest, he will be prohibited from working as a subcontractor for
the contractor who is executing the contract.
3.3 Documents to be submitted by bidder for technical criteria
The Bidder to furnish following documentary proof as minimum:
i) Copy of relevant pages of Work Order(s) / Contract Agreement(s) / contract
document(s) mentioning the value and the scope of work for the Similar works
submitted for qualification.
ii) Final Acceptance/Completion Certificate(s) by Owner / Owner‟s Consultant
indicating executed value & Completion date date for the Similar Work(s)
submitted for qualification.
iii) For Consortium, Bidder shall submit agreement / Memorandum of
Understanding (MOU) along with the bid, clearly defining the detailed scope
and responsibility of each member including the leader for faithful execution of
ISSUE
R0
ISSUE
R0
ISSUE
R0
ISSUE
R0
ISSUE
R0
ISSUE
R0
5 BIDDING DOCUMENTS
5.1 The bidder is expected to examine the bidding documents, including all
instructions, forms, General Conditions of Contract, Special Conditions of
Contract, Technical Specifications, Drawings and other ENQUIRY documents
and to fully familiarize itself with the requirements of the bidding documents.
Failure to furnish all the information required by the Bidding Documents or the
submission of a bid not substantially responsive to the Bidding Documents in
every respect may result in the rejection of the Bid.
5.2 Immediately on receipt of Bidding Document, Bidder shall acknowledge the
receipt and confirm his intention to bid for the ENQUIRY work / scope of supply
as per the Acknowledgement format given in Bidding Document.
ISSUE
R0
6.1 As indicated in item clause no. 2 above, the Original bid with required copies
must be received by the designated authority on or before the bid due date &
time.
6.2 APL / TCE may, at its discretion, extend the deadline for the submission of bids
by amending the bidding documents, in which case all rights and obligations of
the APL / TCE and bidders previously subject to the deadline, will thereafter be
subject to the deadline as extended.
6.3 Any request for due date extension shall be received to APL / TCE 48 hrs in
advance to bid due date in writing clearly indicating the reason for extension. APL
/ TCE will determine to its subjective satisfaction whether the bidder extension
request based on the reason mentioned by the bidder to be accepted or not and
such determination shall not be open to question.
8 LATE BIDS
8.1 Any bid received by TCE after the deadline for submission of the bids (including
any extensions hereof) will be declared "Late" and rejected and returned
unopened to the bidder.
9 BID VALIDITY
9.1 Bids shall remain valid for a period as indicated in Sr. no. 2 above.
9.2 Notwithstanding the above, TCE may solicit the bidder's consent to an extension
of the period of bid validity. The request and the responses thereto shall be made
in writing (by fax/ email).
9.3 A bidder accepting the request for extension shall not be permitted to modify his
bid because of the extension, unless specifically invited to do so.
ISSUE
R0
10.2 Price bid evaluation: Contract shall be awarded to sole bidder on Overall Lowest
Basis for entire scope of ENQUIRY on the basis of effective total cost including all
taxes and duties minus Input Tax Credit/ Set off benefit available to Owner. Techno-
commerical loading (if any) shall be applicable.
10.3 TCE/Owner reserves the right to assess Bidder's capability to execute the work by
taking into account various aspects such as Overall Schedule for Completion of work,
details of tools, tackles & equipment available, Manpower estimation for job,
deployment chart with bio-data/ experience / qualification of all supervisory staff,
proposed site organization chart, Qualtiy assurance Plan & Safety assurance plan
with detailed bio-data / experience of quality assurance supervisor & safety
supervisor, Concurrent Commitments, Past performance etc. and accordingly decide
whether respective price bids shall be opened and considered for further evaluation.
Past Performance shall be based on in-house data of TCE/CLIENT.
10.4 Negotiations will be held only if the lowest rate received is not reasonable and the
decision of the company regarding reasonableness of rates quoted will be final and
binding on the bidders. Work will be awarded to lowest bidder without post tender
negotiations if the rates are reasonable. If rates are not reasonable, negotiations with
Lowest Bidder only may be undertaken to arrive at a reasonable rate.
ISSUE
R0
(n) Complete scope of Supplies / Work as per the provisions of the Bidding
documents.
(o) Completion time beyond the stipulated completion time in the bidding
document.
12 CLARIFICATIONS ON BID
12.1 Clarifications that the Bidder needs to have on the ENQUIRY specification
can be sought from APL/TCE in writing within one week from the date of
issue of this enquiry.
12.2 Bidders requesting clarifications beyond one week from the date of issue of
this enquiry willnot be entertained. Non-receipt of clarifications from APL /
ISSUE
R0
TCE for queries raised beyond one week will not be considered for extension
of time to submit the bid.
12.3 All such correspondence shall be routed to the following address in an
envelope "Clarifications for Enquiry No. TCE.6842A-CV-3000-3005":
To,
The General Manager (Project),
Project Department,
Assam Petrochemicals Limited,
Namrup, P.O. Parbatpur, Dist- Dibrugarh, Pin -786623,
Assam, India.
Contact Person: Mr. Atul Barman
Tel. No.: 0374-2500331
Fax. No.: 0374-2500231
Email: [email protected]
ISSUE
R0
ISSUE
R0
16.3 Bidders shall examine the Bidding documents thoroughly and inform TCE of
any apparent conflict, discrepancy or error, so that TCE may issue
appropriate clarification(s) or amendment(s), if required.
19 LANGUAGE OF BIDS
19.1 The Bid prepared by the bidder, all documents attached to and/or relating to
the bid and all correspondence exchanged by the Bidder and CLIENT/TCE,
shall be written in English language only.
19.2 Any printed literature furnished by the bidder may be written in any other
language provided that this literature is accompanied by an authenticated
English translation, in which case, for purpose of interpreting the Bid, the
English translation shall govern.
20 PRICE BID
Please refer the Attachment - XI of SCC for Lumpsum price for the LSTK
works.
ISSUE
R0
20.1 Lumpsum price includes designing, detailing and construction of roads and
storm water drains including supply of material including loading/unloading
and storage, preparing detailed design drawings based on concept note of
road and drain works and obtaining approval of ENGINEER/OWNER on the
same before starting the Construction activity at site, preparing all
construction drawings, including construction of roads, drains and
pavements, excavation and backfilling/ filling, disposal of excess material
outside the plot at locations approved by Engineer-in-charge or local
authority, dewatering, providing sub-base, sub-grade, rubble soling, providing
all designed layers for bituminous plant roads, reinforced concrete and allied
works, brickwork for puling pits, catch pits, RCC trenches,
dismantling/demolishing of existing structures etc. all as per the technical
specification & bid purpose drawings attached in Volume III of this tender,
furnishing of all materials, equipments, labour, transport, tools, tackles,
including taxes and royalties, and all other services necessary for the
complete execution of works, including inspection and testing, quality checks
and safe execution of works, including required geotechnical investigations,
surveying and setting out necessary for the road and drain works and clean
up of working areas after completion of the Works, without disturbing the
existing foundations and underground services, including demolishing of old
existing structures, if any, etc. as directed by OWNER/ENGINEER. The
scope shall also cover providing and maintaining temporary access
roads/supporting structure for movement of the equipment/ vehicles and
temporary drainage, if required with Final and “As Built” documentation to
OWNER on single point responsibility basis (Lump Sum Turn Key – LSTK
Basis), based on Tender Documents as per scope of work, terms and
conditions of the contract.
20.2 The Lumpsum price shall be deemed to be inclusive of all taxes and
duties, municipal taxes, statutory levies as specified in special
condition of contract except “Goods and Services Tax” (hereinafter
called GST) (i.e. CGST and SGST applicable in case of intra state
supply). The GST as legally leviable & payable by the Contractor under
the provisions of applicable GST law(s) / act(s) shall be reimbursed by
OWNER according to Contractor‟s paid GST bill / invoice submitted to
OWNER.
20.4 Unless stated otherwise in the Bidding Document, the Contract shall
be for the total works as described in Bidding Document, based on the
LSTK Price Breakup format (provided in bidding document) submitted
by the bidder and accepted by PMC/OWNER.
ISSUE
R0
20.5 Bidder shall quote in price bid, considering the lumpsum cost for all the
items listed in LSTK Price Breakup format, after careful analysis of cost
involved for the performance of the complete item considering all parts
of the Bidding Document. In case any activity is not specifically
covered in description of item under LSTK Price Breakup Format but is
required to complete the work as per Scope of Work, Scope of Supply,
Specifications, Standards, Drawings, General terms & Conditions of
Contract, Special Condition of Contract or any other part of Bidding
Document, the rate / price quoted shall be deemed to be inclusive of
cost incurred for such activity.
20.6 Percentages / Rates / prices quoted by the bidder, shall remain firm,
fixed and valid till the completion of the Works and will not be subject
to variation on any account except as otherwise specifically provided in
the Bidding Documents.
20.7 All duties, taxes, and other levies payable shall be as per Special
Conditions of Contract. The bidder shall quote the lumpsum price
gross of Indian Income Tax and the lumpsum price(s) shall be deemed
to include Indian Income Tax
21.1 Items Sr. 1a and 1b of LSTK price breakup format shall be subject to
the limits as specified in Preamble to LSTK Price Bid Breakup Format.
21.2 In case the percentage price(s) quoted exceeds the limits specified in
ATTACHMENT-IX to SCC, the excess amounts shall be raised and
paid in the Final Bill provided the total Lumpsum Price quoted in price
bid does not increase on account of such payment.
21.3 It shall be the duty of the CONTRACTOR to duly observe and perform
all laws, rules, regulations, orders and formalities applicable to GST,
Customs Duty and Custom related Duties etc. on the import,
manufacture, sale and/or supply of any material to the OWNER and
performance of the Works Contract Services under the Contract. The
CONTRACTOR shall keep the OWNER indemnified from and against
any and all claims, demands, prosecutions, actions, proceedings,
penalties, damages, demurrages and/or other levies whatsoever made
or levied by any Court, Tribunal or the Customs or other Authorities
with respect to any alleged breach, evasion or infraction of such duties,
taxes, charges or levies or any breach or infraction of any applicable
laws, rules, regulations, orders or formalities concerning the same and
from the consequence thereof.
ISSUE
R0
ISSUE
R0
person signing the bid and also for the person attending the bid over /
Opening.
25 CLARIFICATIONS ON BIDS
25.1 To assist in the examination, evaluation and comparison of bids, APL /TCE
may, at its discretion, ask the bidder for a clarification of his bid. All
responses to a request for clarification shall be in writing, and no change in
the price or substance of the bid shall be permitted unless specifically sought
by APL/TCE. Bidders not responding to clarification / Queries raised by APL /
TCE on bids within the stipulated time will not be considered further for
evaluation and bids will be rejected.
ISSUE
R0
26.2 APL /TCE will determine to its subjective satisfaction whether the bidder has
submitted a responsive bid and is qualified to satisfactorily perform the work,
and such determination shall not be open to question.
26.3 The determination will also take into account the bidder's financial and
technical capabilities, as well as such other qualifications as APL/TCE deem
necessary and appropriate.
26.4 Bidder(s) techno-commercially accepted will only be communicated for price
bid opening.
26.5 Bidder(s) who qualify for the award of contract as per criteria of this BID will
only be communicated for the award of contract & subsequent LOI / PO will
be issued to them.
27 REBATE
27.1 No suo-moto reduction in price(s) by bidders is permissible after opening of
the bid. If any Bidder unilaterally reduces the price(s) quoted by him in his bid
after opening of bids, such reduction shall not be considered for comparison
of prices but shall be binding on the Bidder if he happens to be selected for
award of work.
28 CONTACTING CLIENT
28.1 A bidder shall not contact CLIENT on any matter relating to his bid from the
time of bid opening to the time, that the Contract is awarded, unless
requested to do in writing. Any effort by a bidder to influence CLIENT in
CLIENT's decisions in respect of bid evaluation or contract award will result in
the rejection of that bidder's bid.
ISSUE
R0
31 CONFIDENTIALITY OF DOCUMENTS
31.1 Bidders shall treat the bidding documents and contents therein as strictly
confidential. If at any time, during the bid preparation period, Bidder decides
to decline to bid; all documents must be immediately returned to CLIENT.
32 SUBMISSION OF BIDS
32.1 Bidder(s) will be required to submit in their one bigger sealed cover marked
as "Offer against Enquiry No. TCE.6842A-CV-3000-3005 for “Road & Storm
Water Drain works” containing the following documents in three separate
sealed envelopes before the due date & time in APL Registered Office at the
address
To,
The General Manager (Project),
Project Department,
Assam Petrochemicals Limited,
Mahapurush Srimanta Sankardev Path
Namrup, P.O. Parbatpur, Dist- Dibrugarh, Pin -786623,
Assam, India.
Contact Person: Mr. Atul Barman
Tel. No.: 0374-2500331
Fax. No.: 0374-2500231
Email: [email protected]
32.2 Cover Envelope containing documents as per clause no. 32 and Checklist for
Submission of Bid”:
a) Part 1: EMD + Integrity Pact
b) Part 2: Un-Priced Bid containing following documents:
i. Three sets (one original + two photo copy) of Un-priced Bid
Commercial Bid
ii. Three sets (one original + two photo copy) of Un-priced Technical Bid
iii. Two Sets (one original + one photo copy) of ENQUIRY document duly
stamped and signed on each page.
c) Part 3: Price Bid containing Schedule of Rates & Quantities with duly filled
prices in Original.
ISSUE
R0
32.3 Each envelope shall be super scribed with the names of documents it
contains.
32.4 The bidders shall ensure submission of prices without any erasures. Bidders
shall also specify total bid price, wherever applicable, in figures as well as in
words.
32.5 Bidder shall indicate Taxes and duties in Prefilled ATC (if applicable) / SOP
only. If Bidder indicates taxes & duties elsewhere, it will not be considered for
evaluation.
32.6 Bids Received by way of Fax or Telex or email or in open condition shall not
be considered.
32.7 Bidder shall strictly follow above mentioned bid submission procedure, failing
to which may lead to rejection of bids.
34 COMPLETION PERIOD
34.1 Please refer Scope of work document in Section – A for Completion period.
35 ORDER OF PRECEDENCE
35.1 The following order of precedence shall be followed in case of any conflict
between various parts of the ENQUIRY specifications:
i. Corrigendums, if any
ii. Instructions to Bidders
iii. Technical Specification, drawings & datasheets
iv. Special Conditions of Contract
v. General Conditions of Contract
The Bidder shall bring to the notice of TCE/CLIENT any such variations / conflicts
between various parts of the ENQUIRY and obtain approval before proceding with
such information for engineering/design.
ISSUE
R0
36.1 The subject tender is an e-tender and owner has hoisted the complete tender
documents on website https://assamtenders.gov.in/nicgep/app and has
ensured its availability for downloading the full set comprising of the above. The
bidder is expected to download the complete tender documents including all
addendum/corrigendum only from the above mentioned website i.e.
https://assamtenders.gov.in/nicgep/app, as per the index of the tender, fully
read and understood the same and submit their acceptance to all tender terms
and conditions except deviations, if any. Bidder may note that Schedule of rates
attached with the tender documents are to be filled in the BOQ (Financial Price
Bid Part – II).
36.2 The tenderer is expected to examine the tendering documents, including all
instructions, specifications/drawings (if any) including all addendum/corrigendum
in the tendering document. Failure to furnish all the information required by the
tendering documents or submission of tender not substantially responsive to the
tendering document in every respect shall result in the rejection of the tender.
36.3 The bidding documents are and shall remain the exclusive property of APL
without any right of the Bidder to use them for any purpose except bidding and for
use by successful Bidder with reference to the work.
36.4 Any person/ bidder downloading the tender document from Owner‟s web site or
purchasing shall do so in strict confidence and shall not part with possession
thereof or copy or disclose the provision thereof or any of them or disclose or take
copies or tracings of any drawings, plans or routes forming part thereof, it being
understood that the information therein are confidential and that the tender
documents have been downloaded by the eligible bidder solely for the purpose of
bidding.
36.5 Bidders are requested to read the document (Special Instruction to Bidders for
Participating in e-tender) SITB available on the moving scroll of the website
https://assamtenders.gov.in/nicgep/app and a copy of the same is also
provided along with tender document. Moreover bidders are requested to follow
the instructions under “Bid Submission process” under “Bidders Manual Kit”
section available in the homepage at the website.
36.6 The bidder shall submit their offer through e-tendering site as mentioned above,
following the steps in the e-tendering portal. Physical hard copies of uprice bid
along with the EMD is to be send to the under noted address within 7(seven)
days from unpriced bid due date and time.
ISSUE
R0
36.7 The Owner shall not be responsible for delayed submission of offers or
non-submission of offers due to any reason whatsoever. The responsibility of
ensuring online & on-time submission of their offers lies entirely with the bidders.
The bidders are requested to submit the bid online much before date and time of
submission, failing which APL shall not be responsible for any such technical
problem.
36.8 In order to bid for APL e-tenders, all the agencies are required to REGISTER in
Assam Tender Portal & obtain a legally valid Class-II & above Digital Signature
Certificate (DSC) for their user who is authorized to submit bids on-line from the
licensed Certifying Authority (CA). Bidders already possessing the digital
signature issued from authorized CAs can use the same in this tender. Further,
the bidder should ensure that the email address given in the Registration Form is
valid & active as all the communications will be made through this e-mail.
36.9 On no account will any person to whom bidding documents are furnished, part
with possession thereof or copy or disclose the provisions thereof or any of them
or disclose or take copies of tracings or of any drawing, plan or route forming part
thereof, it being understood that the information therein is confidential, and that
the bidding documents are therefore being furnished only to bidders in strictest
confidence.
36.10 The details as called for in the bidding documents shall be filled and completed by
the Bidders in all respect and shall be submitted with requisite information and
Appendixes/ Annexures.
36.11 If the space in any Performa of bidding document is insufficient, additional pages
shall be separately added. These shall be page numbered and shall also carry
the bidding document number and shall be signed by the Bidder and entered in
the Index for Bid.
36.12 Bidder shall clearly indicate their legal constitution and the person signing the bid
shall state his capacity as also the source of his ability to bind the Bidder. The
Power of Attorney or Authorization or other document constituting adequate proof
of the ability of the signatory to bind the Bidder, shall be annexed to the bid. APL
may reject outright any bid unsupported by adequate proof of the signatory‟s
authority.
36.14 Agencies are advised to digitally sign the documents that are uploaded and
encrypt the file data before submitting to the e-tendering portal of Assam
Government e- procurement portal by following the given procedure on-line
mentioned in the e-portal site. The bid shall be digitally signed by someone legally
authorized to enter into commitment on behalf of the Bidder. Bidder shall upload
among other documents, Power of Attorney in favour of the person who is
authorized to enter into commitments on behalf of the Bidder.
ISSUE
R0
36.15 APL will not be bound by any Power of Attorney granted by the Bidder or changes
in the constitution of the firm made subsequent to submission of the bid or after
the award of the contract. APL may, however, recognize such Power of Attorney
and changes after obtaining proper legal advice, the cost of which will be borne
by the Bidder.
36.16 The cancellation of any document such as Power of Attorney, Partnership Deed,
etc. should be communicated by the Bidder to APL in writing well in time, failing
which APL shall have no responsibility or liability for any action taken by APL on
the strength of the said documents.
36.17 Should the Bidder have a relative or relatives in APL or one or more of its share
holders are employed in a superior capacity in APL, the relevant authority inviting
bids shall be informed of the facts at the time of submission of the bid, failing
which the bid may be disqualified or if such fact subsequently comes to light, APL
reserves the right to take any other action as it deems fit in accordance with any
applicable law, Rules, Regulations of the like in force.
36.19 Canvassing in any form by the Bidder or by any other agency on their behalf may
lead to disqualification of their Bid.
36.20 Unsolicited clarifications to the offer and / or change in the prices during the
validity period would render the bid liable for rejection.
36.21 The bidding document that is downloaded shall be submitted on-line as per the
procedure stipulated in the website along with the digital signature. The bidding
document shall not be transferred to any other agency. The digital signature shall
be considered as your confirmation that you have read and accepted all the
conditions laid down in the Tender Documents. Physical hard copies of Techno –
Conmmercial Documents must also be submitted through Post/ Courier/ or in
person within 7(seven) days from Bid due date & time (All documents excluding
PRICE BID).
ISSUE
R0
ANNEXURE – I
1.We……………… Bank do hereby undertake to pay the amounts due and payable
under this guarantee without any demur merely on a demand from the owner stating that
the amount claimed is due by way of loss or damage caused to or would cause to or
suffered by the owner by reason of any breach by the said Tenderer(s) of any of the
terms and conditions contained in the said tender or by reason of the said Tenderer‟s
failure to keep the tender open. Any such demand made on the Bank shall be conclusive
as regards the amount due and payable by the Bank under this Guarantee. However, our
liability under this guarantee shall be restricted to an amount not exceeding
INR 24,00,000/- (Rupees Twenty Four lakhs Only)
2.We……………. Bank further agree that the guarantee herein contained shall remain in
full force and effect during the period that would be taken for the finalization of the said
tender and that it shall continue to be enforceable till the said tender is finally decided
ISSUE
R0
and order placed on the successful tenderer(s) and/or till all the dues of the owner
under/or by virtue of the said tender have been fully paid and its claims satisfied or
discharged or till a duly authorised officer, of the owner certifies that the terms and
conditions of the said tender have been fully and properly carried out by the said
Tenderer(s) and accordingly discharges the guarantee. Above provisions are applicable
subject to validity mentioned in para 4 (b).
The Bank hereby declares that it has the power to issue this guarantee and the
undersigned has fully power to do so.
ISSUE
R0
ANNEXURE-II
SELF CERTIFICATION
It is certified that none of the documents are false/forged or fabricated. All the
documents submitted have been made having full knowledge of;
i) The provisions of the Indian laws in respect of offences including, but not
limited to those pertaining to criminal breach of trust, cheating and fraud
and
DECLARATION
Signature
Name & Designation (CEO or CFO or Company Secretary)
ISSUE
R0
1. Sealed envelope no. 1: Containing Bid Fee + EMD + Integrity Pact duly signed.
Item : ----------------------------------------------------------------------------------
From: To,
_______________________________ The General Manager (Project),
_______________________________ Project Department,
Assam Petrochemicals Limited,
_______________________________ Namrup, P.O. Parbatpur, Dist-
Dibrugarh, Pin -786623,
_______________________________ Assam, India.
ISSUE
R0
Item : -------------------------------------------------------------------
From: ______________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
ISSUE
R0
Item : -------------------------------------------------------------------
From: ______________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
(To be pasted on the envelope no. 2 containing Unpriced Commercial Bid + Unpriced
Technical)
ISSUE
R0
Item : -------------------------------------------------------------------
From: ______________________________________________________________
___________________________________________________________________
___________________________________________________________________
___________________________________________________________________
(To be pasted on the envelope no. 3 containing Format for Submitting Prices with
duly filled prices)
ISSUE
R0
FOR
ISSUE
R0
Preface
ISSUE
R0
Table of Contents
ISSUE
R0
APPENDIX 3…………………………………………………………………………133
SAFETY CODE………………………………………………………………………133
APPENDIX 4………………………………………………………………………….143
INDEMNITY BOND………………………………………………………………….143
APPENDIX 5…………………………………………………………………………..146
PART A……………………………………………………………………………146
FORMAT -I………………………………………………………………………..146
IMTIMATION REGARDING SYSTEM COMPLETION………………………..146
PART B…………………………………………………………………………….147
FORMAT – II………………………………………………………………………147
CHECKLIST……………………………………………………………………….147
APPENDIX 6…………………………………………………………………………..148
FORMAT – III………………………………………………………………………….148
READY FOR PRE -COMMISSIONING CERTIFICATE…………………………….148
APPENDIX 7………………………………………………………………………..…149
FORMAT -IV………………………………………………………………………..…149
READY FOR COMMISSIONING CERTIFICATE…………………………………..149
APPENDIX 8…………………………………………………………………………..150
FORMAT -V…………………………………………………………………………..150
COMPLETION OF COMMISSIONING CERTIFICATE……………………………150
ISSUE
R0
1.1 Definitions
(1) “Affected Party” shall have the meaning ascribed to it in Clause 27.2.
(2) “Agreed Variations” shall mean the statement of agreed variations annexed to the
detailed Letter of Acceptance and any document signed by Owner and the Contractor
as an amendment of contract.
(3) “Applicable Laws” means all laws in force and effect, including Tax laws but excluding
direct Tax laws (which includes income tax, corporate tax, profession tax and wealth
tax), as of the Base Date and which may be promulgated or brought into force and effect
hereinafter including any revisions, amendments or re-enactments including without
limitation regulations, rules and notifications made thereunder and judgments, decrees,
injunctions, writs, orders and notifications issued by any court or Authority, as may be in
force and effect during the subsistence of the Contract and applicable to either Party,
their obligations or this Contract from time to time.
(5) “Approval” and its grammatical variations shall mean approved or confirmed in writing
by Engineer-in-Charge on behalf of the Owner.
(6) “Arbitration Act” means the (Indian) Arbitration and Conciliation Act, 1996.
(7) “Authority” means the Government of India, any state government or any local
authority or any department, instrumentality or agency thereof or any corporation (to
the extent acting in a legislative, judicial or administrative capacity and not as a
contracting party with Owner or the Contractor) or commission under the direct or
indirect control of such central, state or local government or any political sub-division
thereof or any court, tribunal or judicial body within India.
(8) "Base Date" means the date 7 (seven) days prior to the last date for submission of the
Bid/revised Bid, if any.
(9) “Background Information” means all and any materials, data, documents, drawings,
plans, surveys, reports or other information relating in any way to the Site or the
Facility, whether or not made available by Engineer-in-Charge/ Owner and/or its
agents to the Contractor.
ISSUE
R0
(10) "Bid" means the Contractor’s signed offer for the Works and all other documents
submitted along with the Bid.
(11) “Bidding Documents” mean the Notice Inviting Bids/ Letter Inviting Bids, the
instruction to bidders (including annexures), form of bid (including appendices), the
Contract Agreement, the General Conditions of Contract, the Special Conditions of
Contract, the Specifications and all other reports, surveys, drawings and documents
including amendments, if any, provided to the Contractor by TCE / Owner .
(12) “Billing Schedule” means the schedule submitted by the Contractor in accordance
with Clause 23.3.1, in terms of which Owner shall be required to make progressive
payments to the Contractor.
(13) “Bill of Quantities” means the bill of quantities as per the provisions of the Contract.
(14) “Business Day” means a day other than a Sunday or a public holiday on which banks
are open for business in Guwahati, Assam and any other place mentioned in the
Contract.
(15) “Change in Law” means the occurrence of any of the following after the Base Date:
(c) The commencement of any Indian law which has not entered into effect until
the date of signing of the Contract;
(e) Increase/ Decrease in the rate of Taxes in force after the Base Date;
(f) Change in the basis of computation of Taxes in force after the Base Date, in
such a manner that it has a material effect (positive or negative) on the
Contract.
Notwithstanding anything mentioned above, Change in Law will not include any
change in direct tax laws (which includes income tax, corporate tax, profession tax
and wealth tax) for which the Contractor is the responsible party
ISSUE
R0
(21) “Completion" shall mean the successful provision of all materials and inputs and the
successful completion and conclusion of all activities and tests (including the Tests on
Completion) required to complete the Works in accordance with the Contract, but
shall not include the obligation to rectify defects during the Defect Liability Period.
(22) “Completion Certificate” shall have the meaning assigned to it in Clause 17.3.
(23) “Confidential Information” means the Contract and everything contained therein, all
documentation, data, particulars of the Works and technical or commercial
information made by (or on behalf of) Owner or obtained directly or indirectly from
Owner by the Contractor or which is generated or obtained by the Contractor or any
Subcontractor in relation to the Works or any information or data that the Contractor
receives or has access to as a result of the Contract, other than information:
(a) which is generally available in the public domain other than by any
unauthorised actions or fault of the Contractor; or
(24) “Contract” means the agreement between Owner and the Contractor for execution of
the Works and includes the Contract Agreement, the General Conditions of Contract,
the Special Conditions of Contract, the other Bidding Documents, the Specifications,
the Price Schedule, and such further documents which are listed in the Contract
Agreement and/or these General Conditions of Contract and includes any amendment
thereto made in accordance with the provisions hereof.
(25) “Contractor” means the entity/ person which has entered into the Contract
Agreement with the Owner, as identified in the Contract Agreement.
(26) “Contract Agreement” means the agreement entered into between Owner and the
Contractor along with the Price Schedule and other annexures and includes any
amendments thereto made in accordance with the provisions thereof.
ISSUE
R0
(28) “Contract Validity Period” means the period commencing from the Effective Date
up to the end of the Defect Liability Period / Extended Defect Liability Period (as the
case maybe).
(29) “Contract Price” means the total price payable to the Contractor for performing the
Works based on the rates and breakdown of prices provided by the Contractor in the
Price Schedule, subject to such additions thereto and deductions therefrom as may be
made under the Contract and as adjusted by the actual quantities, if applicable, of the
items mentioned in the Price Schedule utilized in the execution of the Works.
(30) “Contract Spares” shall have the meaning assigned to it in Clause 9.23.
(33) “Contractor's Event of Default” shall have the meaning assigned to it in Clause
32.2.
(35) “Contractor's Personnel” means the Contractor's Representative and all personnel
whom the Contractor utilizes on Site, who may include the staff, labour and other
employees of the Contractor and of each Subcontractor, and any other personnel
assisting the Contractor in the execution of the Works.
(36) “Contractor's Representative” means the person nominated by the Contractor to act
on its behalf for the purposes of the Contract and notified as such in writing to
Engineer-in-Charge with copy to Owner.
(37) “Cost” means all expenditure reasonably and properly incurred by the Contractor,
ISSUE
R0
whether on or off the Site and includes overhead, profit and similar charges.
(38) “Defect” means any defect, imperfection or other fault in the Facility or any part
thereof arising from or in connection with the execution of the Works or any defect,
imperfection or other shortcoming in the Contractor's Documents, or a breach of the
Contract or the neglect or failure of the Contractor to comply with any of its
obligations, express or implied, under the Contract and the term ‘Defective’ shall be
construed accordingly.
(39) “Defect Liability Period” means the period specified in Clause 18.1 for notifying
defects in the Works, calculated from the date of Completion as specified in the
Completion Certificate for the Works or part of the Works.
(41) “Design Data” means all specifications, sketches, plans, graphs, details, dimensions,
models and calculations provided as a part of the Bidding Documents and verified by
the Contractor.
(42) “Drawings and Designs” means the drawings and designs provided by Engineer-in-
Charge or prepared by the Contractor on the basis of the Design Data and submitted
to and Approved by the Engineer-in-Charge in accordance with Clause 9.13 & 10.5,
in accordance with which the Contractor shall proceed with the execution of the
Works.
(45) “Extended Defect Liability Period” shall have the meaning assigned to it in Clause
18.7.
(46) “Facility” means the facility to be construed under and in accordance with this
Contract and as described in greater detail in the Specifications.
(47) “Final Completion” shall mean the successful completion and discharge of all
obligations of the Contractor under the Contract, including the obligation to rectify
Defects, if any, during the Defect Liability Period and the Extended Defect Liability
Period, if any.
ISSUE
R0
(48) “Final Completion Certificate” means the certificate issued by Owner to the
Contractor under Clause 19.
(56) “Free Issue Materials” means any material, items, equipment, machinery, apparatus,
accessories, auxiliaries, spare parts, tools and tackles and articles and things provided
by Owner to the Contractor for incorporation in the Permanent Work and which shall
be bailed to the Contractor upon their delivery at Site in accordance with Clause
9.29.1.
(58) “Goods and Materials” means things of all kinds (other than Plant) intended to form
or forming a part of the Permanent Work, including materials (if any) to be supplied
by the Contractor under the Contract.
(59) “Good Industry Practice” means the exercise of that degree of skill, diligence,
prudence and foresight in compliance by the Contractor with the undertakings and
obligations under the Contract, which would be expected from a skilled and
experienced professional person engaged in works that are of the type, nature and
scope similar to the Works.
(60) “Guaranteed Performance Levels” means the guaranteed levels of performance set
out in the Contract that are needed to be met by the Plant, Goods and Materials, the
Works and the Facility on conduct of the Tests on Completion.
(61) “Intellectual Property” means copyright, registered and unregistered trademarks and
service marks, registered and unregistered designs, circuit layouts, all rights conferred
under statute, common law or equity in relation to inventions (including patents),
proprietary information and all other rights resulting from intellectual activity in the
industrial, scientific, literary or artistic fields.
ISSUE
R0
(62) “INR” or “Rupees” means the legal currency of the Republic of India.
(63) “Key Date” means a date identified for the completion of a Stage set out in the Works
Completion Schedule, relating to execution of the Works, unless revised in
accordance with the terms of the Contract.
(64) “Key Personnel” shall have the meaning assigned to it in Clause 12.2.
(65) “Letter of Award” or “LOA” / “Fax of Acceptance” or “FOA” means the Letter of
Award / Fax of Acceptance issued by Owner to the Contractor, awarding the Works
to the Contractor.
(66) “Mechanical Completion” shall have the meaning assigned to it under Clause 15.1.
(68) “Mobilization Advance” means the amount specified in the Payment Schedule that is
paid by way of advance by Owner to the Contractor pursuant to Clause 23.1.
(70) “Monthly Progress Reports” means the monthly progress reports submitted by the
Contractor in accordance with the scope of Works / Contract.
(71) “Operation and Maintenance Manuals” means the operation and maintenance
manual submitted by the Contractor in accordance with Clause 10.7.
(72) “Owner” shall mean Assam Petro-chemicals Limited, with its registered office at 4th
Floor, Orion Place, Bhangagarh, G.S. Road, Guwahati - 781005.
(73) “Owner's Insurance” shall have the meaning assigned to it in Clause 33.1.
(75) “Payment Milestones” means the milestones listed in the Payment Schedule.
(76) “Payment Schedule” means the document containing the terms of payment of the
Contract Price to the Contractor as annexed to the Contract Agreement.
ISSUE
R0
(78) “Performance Tests” means the tests described in the Specifications which are to be
carried out by the Contractor in accordance with the Contract in order to demonstrate
compliance with the Guaranteed Performance Levels.
(79) “Performance Guarantee Test Run” or “PGTR” means the continuous operation of
the Facility for a period, in accordance with the Contract, on full load during the Trial
Operations.
(80) “Permanent Works” means the permanent works to be executed by the Contractor
(including all permanent structures and all work intended to form a continuing
function after Completion of the Works) in accordance with the Contract.
(82) “Plant” means any and all permanent plant, equipment, machinery, apparatus, articles
and things of all kinds to be provided for incorporation or intended to be incorporated
(whether later incorporated in the Facility or otherwise, including Contract Spares) in
the Facility whether or not supplied from outside India or from within India, but does
not include consumables, Contractor's Equipment and Goods and Materials.
(84) “Price Schedule” or “Schedule of Rates” shall mean the price schedule annexed to
the Contract Agreement.
(86) “Punch List” shall have the meaning assigned to it in Clause 15.6.
(87) “Punch-list Items” means items of works of a minor or snagging nature which do not
affect the operations of the Facility which remain incomplete on the date of issuance
of Format-III.
(88) “Quality Assurance Plan/Project Quality Plan” means the Approved quality
assurance plan and manual developed by Contractor in accordance with Clause 9.19.
(89) “Related Dispute” shall have the meaning assigned to it in Clause 35.2.6.
(90) “Review Period” means the period of 14 (fourteen) days unless specified elsewhere
in the Contract, within which the Engineer-in-Charge shall endeavor to complete the
review of the Contractor’s Documents, as calculated from the date of submission of
the relevant Contractor’s Document.
ISSUE
R0
(91) “Running Bill” means the fully supported invoice delivered to Owner Engineer-in-
Charge by the Contractor at the times set out in the Payment Schedule, containing all
the requisite information and complying with all the requirements set out at Clause
23.3.2.
(92) “Safety Code” means the safety code set out at Appendix 3 (Safety Code).
(93) “Secured Advance” means the amount specified in the Payment Schedule that is paid
by Owner to the Contractor pursuant to Clause 23.2.
(94) “Site” means the land, location, right of way and/or places provided by Owner where
the Works are to be executed and to which Plant and Goods and Materials are to be
delivered and any other place as may be specifically designated in the Contract as
forming part of the Site or designated as such by the Engineer-in-Charge.
(95) “Special Conditions of Contract” or “SCC” means the special conditions of contract
setting out specific deviations from the General Conditions of Contract and other
relevant provisions and data, which are to be read in conjunction with the General
Conditions of Contract.
(96) “Specifications” means all general and technical specifications and directions
attached to and forming a part of the Bidding Documents which describe the purpose,
scope, design and technical criteria of the Works including, the method and manner of
performing the Works, the quality and quantity of the Works to be performed and the
materials to be supplied under the Contract and includes all modifications or
amendments made thereto.
(97) “Stage” means the level of progress of the Works identified as such in Works
Completion Schedule.
(98) “Subcontract” means any contract awarded by the Contractor to a Subcontractor.
(101) “Suspension Order” shall have the meaning assigned to it in Clause 26.1.
(102) “Taxes” means all taxes, duties, imposts, levies and charges pursuant to any law
(whether currently in force or coming into force on or after the date of base date as
defined above), including income tax, capital gains tax, Value Added Tax (“VAT”),
Central Sales Tax (“CST”), works contract tax (WCT), customs duty, service tax,
ISSUE
R0
excise duty, fees, cess, octroi, entry tax, fringe benefit tax and any interest, surcharge,
penalty or fine in connection therewith.
(103) “Temporary Works” means all temporary and ancillary works including enabling
works and maintenance works connected with the Works and required for the
execution and completion of the Permanent Works.
(104) “Tests on Completion” mean the tests which are specified in the Contract and
designated as such and includes any other tests that have to be carried out before the
Works, or any part thereof is taken over by Owner.
(105) “Time for Completion” or “Time Schedule” means the period specified in the
Contract Agreement or the Special Conditions of Contract for Completion of the
Works, reckoned from the Effective Date.
(106) “Time for Mobilisation” means the period specified in Clause 9.3.2 for completion
of Mobilisation, to be reckoned from the Effective Date.
(107) “Trial Operation” means the integrated operation of the Facility in automatic control
system for a continuous period specified in the Contract or the Specifications.
(108) “Variation” means any alteration and/or modification to the Specifications, which is
instructed by the Engineer-in-Charge or as suggested by the Contractor and Approved
as a variation by the Engineer-in-Charge in accordance with Clause 24.
(109) “Variation Order” shall have the meaning assigned to it in Clause 24.1.
(111) “Working Day” means a day other than a Sunday or a public holiday on which
Owner is open for business.
(a) all work and services required in connection with the turnkey design,
engineering, procurement, permitting, fabrication, manufacture, construction,
construction management, coordination of Subcontractors work, inspection,
expediting, transportation, shipment, delivery, import, erection, installation,
pre-commissioning, commissioning, start-up, testing and completion of the
Facility, completion of all Performance Tests, in accordance with this
Contract;
(b) the provision of all Plant, Goods and Materials, Contract Spares, machinery,
tools, labor, utilities, chemicals, lubricants consumables, transportation,
administration, oversight, incidentals and other services and items related to
the foregoing in accordance with this Contract;
ISSUE
R0
(d) the performance of all other obligations and services that are described in, or
necessarily implied by, this Contract.
(113) “Works Completion Schedule” means the schedule for the performance of the
Works and fulfilment of the Parties' obligations as annexed to the Contract
Agreement/Special Conditions of Contract, as may be revised in accordance with the
terms of the Contract.
(114) “Works Programme” means the program showing the sequence, method and
schedule of the design, procurement, construction, erection, installation, testing,
commissioning of the Works (and related activities in the form and content prescribed
by the Specifications, or any amended or varied version thereof, as submitted by the
Contractor and for which the Engineer-in-Charge has issued a notice of no objection.
1.1 Interpretation
(d) References to Clauses or Schedules are, unless the context otherwise requires,
references to recitals, clauses of, or, schedules to these General Conditions of
Contract.
(e) Unless the context otherwise requires, reference to one gender includes a
reference to the other, words importing the singular include the plural and
vice versa.
ISSUE
R0
(h) Words indicating the singular also include the plural and words indicating the
plural also include the singular.
(l) The Schedules shall form an integral part of the Contract and shall be in full
force and effect as though they were expressly set out in the body of the
Contract.
(m) Where the day on or by which any thing is to be done is not a Business Day
or a Working Day, as the case may be, that thing must be done on or by the
immediately occurring next Business Day or Working Day, as the case may
be.
(n) The rule of construction, if any, that a contract should be interpreted against
the party responsible for the drafting and the preparation thereof, shall not
apply to the Contract.
(p) Subject to Clause 2 below, all documents forming part of the Contract are to
be read together as a whole and are to be taken as mutually explanatory.
2 CONTRACT
2.1.1 The documents forming the Contract are to be taken as mutually explanatory of one
another. If there is an ambiguity or discrepancy in the documents, the Engineer-in-
ISSUE
R0
Charge shall issue necessary clarifications or instructions to the Contractor, and the
order of precedence of the documents shall be as follows:
Without prejudice to the foregoing priority of the documents forming the Contract, any
ambiguity, discrepancy or inconsistency in the applicability of certain clauses/ provisions in
the Contract having regard to the scope of work and overall nature and extent of the
Contractor’s obligations in respect thereof, the Contractor may approach the Engineer-in-
Charge for a clarification. Where the Engineer-in-Charge provides any clarification (and/ or
any instructions in furtherance thereof) the same shall be binding on the Contractor, and the
Contractor shall be obliged to comply with any such clarification without any revision of the
Contract Price or extension of the Time for Completion.
Provided that in the absence of any clarification (and/or instructions) by the Engineer-in-
Charge on the said ambiguity, discrepancy or inconsistency and/ or the Contractor not having
made a request for such clarification, the condition and/ or interpretation that prescribes a
more stringent obligation on the Contractor shall prevail.
3 COMMUNICATION
3.2 Any consent, approval, authorization, certificate, report, information, notice or request
from or by any Party or the Engineer-in-Charge shall be effective and valid only when
made in writing under the hand of a duly authorized representative of such Party or
the Engineer-in-Charge, as the case may be, and delivered by hand against receipt,
sent by the recognized courier, registered mail or transmitted by facsimile
transmission, e-mail to the address for the recipient's communication as stated in
Clause 3.3 below. In case any notice is delivered by registered mail and/or courier, it
ISSUE
R0
shall be deemed to be duly served within forty eight (48) hours after posting and a
notice or demand sent by facsimile, e-mail shall be deemed to have been served at the
time of its transmission and in proving service of the same, it will be sufficient to
prove, in the case of a letter, that such letter was sent by registered airmail, addressed
and placed in the post and in the case of a facsimile transmission, e-mail that such
facsimile/ e-mail was duly transmitted to a current facsimile number/ e-mail of the
addressee at the address referred above.
3.3 Any contractual notice, instruction, decision, order, report, certificate or other
communication that is to be exchanged between the Parties shall be served by sending
the same by e-mail or facsimile transmission, with a confirmation copy by courier or
registered post to the following addresses:
If to Owner:
Address:
To,
The General Manager (Project),
Project Department,
Assam Petrochemicals Limited,
Namrup, P.O. Parbatpur, Dist- Dibrugarh, Pin -786623,
Assam, India.
Contact Person: Mr. Atul Barman
Tel. No.: 0374-2500331
Fax. No.: 0374-2500231
Email: [email protected]
Address: [■]
Attention: [■]
e-mail: [■]
Fax: [■]
If to TCE:
Address:
TATA CONSULTING ENGINEERS LIMITED
Unit no. NB 1502 & SB 1501,15th Floor, Empire Tower,
Opposite Reliable Tech Park Cloud City Campus, Airoli,
Navi Mumbai, India, 400 708
Contact person: Mr. Sandip De
Tel. No.: 022-61148945
Email: [email protected]
It is clarified that a copy of any notice or notice, instruction, decision, order, report,
certificate or other communication under this Agreement by the Contractor to Owner,
ISSUE
R0
shall also be forwarded by the Contractor to TCE, at the time such communication is
made.
3.4 Any change in the address for communication shall be duly notified by Owner and/or
the Contractor to the other Party in accordance with the provisions of this Clause 3.
4 STAMP DUTY
Stamp duties, registration fees (if any) and any related charges payable under the
Applicable Laws in relation to the Contract shall be borne by the Contractor.
5.1 Both Parties shall treat the details of the Contract as private and confidential, except
to the extent necessary to carry out obligations under it or to comply with Applicable
Laws. The Contractor shall not publish, permit to be published, or disclose any
particulars of the Works in any trade or technical paper or elsewhere without prior
consent of Owner.
5.2 The Contractor shall treat the Confidential Information as private and confidential,
save in so far as may be necessary for the fulfilment of its obligations under the
Contract, and shall not use, copy, publish, disclose or otherwise deal with, nor cause
nor permit its Subcontractors or any persons for whom it is contractually or otherwise
responsible for, to use, copy, publish, disclose or otherwise deal with the Confidential
Information, without prior consent in writing of Owner. If any dispute arises as to the
necessity of any publication or disclosure for the purpose of the Contract the same
shall be referred to the decision of Owner, whose award shall be final.
(a) the Contractor shall take all practicable steps to ensure that no
photographs, drawings or other image of the Site or of the Works or
any part thereof or any property of Owner or any physical or virtual
model thereof, are taken or made, except as may be expressly directed
or Approved beforehand in writing by Owner;
(b) the Contractor shall not in regard to anything concerning the Works
publish any information, drawing or photograph and shall not give
interviews to or comment to the press or to any person associated
with the news media or take part in radio or television schedules
except with the express prior written consent of Owner and subject to
such conditions as it may prescribe;
(c) the Contractor shall not use any part of the Site for the purpose of any
advertisement, except by way of notice boards approved (as to
location, number and content) by Owner and/or Engineer-in-Charge;
and
ISSUE
R0
(d) the Contractor shall use its reasonable endeavours to procure that its
servants and agents comply with this sub-Clause.
5.3 The Contractor shall procure that each and every Subcontractor shall contain
confidentiality undertakings on the part of the Subcontractor in substantially similar
terms to those entered into by the Contractor, and shall use all reasonable endeavours
to enforce them.
5.4 In the event that the Contractor is lawfully required or requested by order of any
competent Authority to disclose any Confidential Information, then the Contractor
shall, to the extent permitted by the Applicable Laws, prior to disclosure immediately
notify Owner and Engineer-in-Charge so that an appropriate protection order and/or
any other action can be taken if possible, prior to any disclosure. In the event that such
protective order is not, or cannot, be obtained, then the Contractor may disclose to the
competent Authority that portion of the Confidential Information which it is legally
required to disclose and shall use all reasonable endeavours to obtain assurances that
confidential treatment will be accorded to any Confidential Information so disclosed.
5.5 The Contractor agrees that, upon request at any time by Owner, the Contractor shall
promptly, but in any event within 5 (five) days of receipt of written notification from
Owner:
(a) return all Confidential Information that is in tangible form (including,
without limitation, Confidential Information contained in software or
on computer disc) furnished to the Contractor, together with all
copies or extracts thereof; and
5.6 The provisions of this Clause 5 shall survive the expiration or termination of the
Contract.
6.1 The Contractor shall, in performing the Contract, comply with all Applicable Laws.
6.2 Without prejudice to the foregoing, the Contractor shall be responsible for bearing all
registration and statutory inspection fees payable under any Applicable Laws in
respect of the Works executed or completed pursuant to the Contract. If the
Contractor defaults in complying with the Applicable Laws, the Contractor shall, at
its own risk and Cost, bear any and all additional fees, fines, penalties or charges.
However, Owner shall make reasonable efforts to assist the Contractor in rectifying
any such default under Applicable Laws in India upon the Contractor's specific
request, including any specific request to issue letters to the relevant Authorities on
behalf of the Contractor.
ISSUE
R0
6.3 The Contractor shall not be absolved from any of its obligations under Applicable
Laws or the Contract or claim any additional amount from Owner or seek any
extension of the Time for Completion due to its ignorance of any Applicable Law.
This Clause 6.3 shall not however restrict the right of the Contractor to claim increase
in cost due to Change in Law in accordance with the provisions of Clause 25.
7 BACKGROUND INFORMATION
7.1 Should there be any doubt or ambiguity in the interpretation of the Contract or
contradiction in the various documents that comprise the Contract or should there be
any discernible error or omission in any document comprising the Contract, the
Contractor shall, prior to commencing the Work likely to be affected by such
ambiguity, error or omission, apply in writing to the Engineer-in-Charge for resolving
the ambiguity or rectifying the error, as the case may be. If the Contractor fails to
apply to the Engineer-in-Charge prior to commencing the relevant Work, the
Contractor shall perform such Work at its own risk and if the Work are at variance
with the requirements of the Contract, then such Work shall be deemed to Defective
Work and the provisions of Clause 9.16 shall apply.
7.2 The decision of the Engineer-in-Charge on any application under Clause 7.1 shall be
in writing and shall be final and binding on the Contractor and shall form part of the
Contract.
7.3 The Parties agree that any ambiguity, discrepancy, inconsistency, divergence,
impracticality or omission as aforesaid shall not vitiate the Contract.
7.4 As soon as possible following a request from the Engineer-in-Charge to do so, the
Contractor shall provide such reasonable information as the Engineer-in-Charge may
request to assist it in resolving the ambiguity or rectifying the error, including if so
requested, the Contractor's proposals for overcoming the ambiguity, discrepancy,
inconsistency, divergence, impracticality or omission (as the case may be) but the
Engineer-in-Charge shall not be obliged to adopt or instruct the same.
7.5 The Contractor is required to make all necessary inquiries and fully acquaint himself
with all Background Information, and the Contractor acknowledges that any failure to
acquaint itself with the Background Information shall not relieve its responsibility for
properly estimating the difficulty or cost of successfully performing its obligations
under the Contract and Owner/ Engineer-in-Charge shall have no responsibility to
the Contractor (whether in contract, tort, for breach of statutory duty or howsoever
other arising) for or in relation to such Background Information whether as to its
accuracy, adequacy, sufficiency or completeness.
8.1.1 Owner shall provide access the Site to the Contractor for the execution of the Works.
ISSUE
R0
Unless otherwise specified elsewhere in the Contract, in the event of delay in transfer
of the Site by Owner to the Contractor, for reasons not attributable to the Contractor,
the Contractor shall only be entitled to a reasonable extension of the Time for
Completion pursuant to Clause 14. The Contractor shall take all necessary
precautions to ensure that no damage is caused to any building or establishment
within the Site. The Contractor shall be liable for any loss suffered by Engineer-in-
Charge/ Owner/ third party on account of damage to the Site or any building or
establishment within the Site. The Contractor shall ensure that day to day activities of
Engineer-in-Charge/ Owner are not hampered because of Works executed by the
Contractor. The Contractor shall ensure that until the issuance of the Completion
Certificate (Owner shall start operations from Commercial Operation Date (COD)
upon completion of the Trial Operations), in accordance with Clause 17 by Owner,
Owner's Personnel, their representatives and assignees shall have the right to visit the
Site at any time and inspect or audit the Contractor's books and records relating to the
execution and completion of the Works.
8.1.2 Without prejudice to Clause 8.1.1 above, the Contractor agrees that the Site will be
handed over to the Contractor in stages with a view that the Contractor shall plan the
Works in a manner so as to achieve Completion in a sequential manner, without
affecting the Time for Completion and without starting all the Works at the same
time. To this end, within 28 (twenty eight) Working Days from the Effective Date,
the Contractor shall finalize, in agreement with the Engineer-in-Charge, sequential
requirement of the Site, taking into account the other works concurrently being
undertaken by Owner at or about the Site or on the performance of which depends the
Contractor’s performance of the Works.
Without prejudice to the obligations of the Contractor under the Contract, Owner/
Engineer-in-Charge shall be responsible for ensuring that Owner's/ Engineer-in-
Charge’s Personnel:
(a) co-operate with the Contractor's and the Contractor’s Personnel; and
(b) take actions similar to those which the Contractor is required to take under
Clause 9.16, on the Site, in respect of any other works undertaken by Owner
at the Site.
ISSUE
R0
8.4.1 The Owner has appointed TCE to undertake the role of the Project Management
Consultant (PMC) with respect to the Facility and the Work, and to act on behalf of
Owner in connection with the Contract as Engineer-in-Charge.
Provided that:
8.4.3 Engineer-in-Charge (and its officers, advisors, representatives, agents, personnel and
employees), shall, in performing its duties or exercising authority under the Contract,
shall be entitled to the benefit of all indemnifications, and like protections, available
to the Owner under, or pursuant to the Contract.
ISSUE
R0
9.1.1 The Contractor shall execute the Works, as described in greater details in the
Specifications, in accordance with the Contract, the Specifications, the Safety Code
and Applicable Laws. The Works shall be fit for the purposes for which they are
intended, as defined in the Contract. The Works shall include any work which is
necessary to satisfy the Specifications, or as implied by the Contract, or arises from
any obligation of the Contractor, and all works not mentioned in the Contract but
which are necessary for stability, completion or the safe, reliable and efficient
operation of the Facility.
9.1.2 The Contractor agrees and acknowledges that at any time after acceptance of the Bid,
Owner shall have the right to add, amend or delete any item of the Works in the
overall interest of the Project. Further, Owner shall have the right to split the scope of
Works under this Contract between two or more contractors without assigning any
reasons thereof.
9.1.3 The Contractor shall execute the Works in accordance with the Works Completion
Schedule and shall complete each Stage within the relevant Key Date and the entire
Works within the Time for Completion and for this purpose the Contractor shall
provide such necessary resources, Goods and Materials, Plant and Contractor's
Personnel having the requisite experience for the purposes stated in the Contract.
9.1.4 The Contractor agrees and acknowledges that it shall perform all of its obligations
and responsibilities under the Contract at its own risk, Cost and expense. Owner shall
have no obligation or responsibility whatsoever with respect to the Completion of the
Works or the fulfillment of other obligations of the Contractor under the Contract,
except as expressly provided in the Contract.
9.1.5 The Contractor shall provide all superintendence, Goods and Materials and
Contractor's Equipment and all other things, whether of a temporary or permanent
nature, required for the execution of the Works.
9.1.6 Wherever applicable, the Contractor shall submit within 56(fifty six) days from the
Effective Date, a detailed Bill of Quantities, specifying the materials which, on a
preliminary determination made by the Contractor, will be required for incorporation
in the Permanent Work. Each item entered in the Bill of Quantities shall be priced, to
ISSUE
R0
the extent possible, in conformity with the details given in the Bid. Engineer-in-
Charge shall review or cause to be reviewed the adequacy, sufficiency, validity and/or
suitability of the materials listed in the Bill of Quantities and of the prices indicated in
the Bill of Quantities in this regard. Such review shall be performed in conjunction
with design, engineering and other technical reviews to be done by Engineer-in-
Charge and all provisions applicable to review of critical drawings and designs shall
be applicable to the review of the Bill of Quantities. However, no such review or
Approval of the priced Bill of Quantities by Engineer-in-Charge shall absolve the
Contractor of its obligation to supply all Goods and Materials required to be
incorporated in the Permanent Work, within the price quoted for such Goods and
Materials in the Price Schedule.
9.1.7 The Contractor shall supply all materials, works, labour and other services, which
although not specifically mentioned in the Contract:
(a) can be reasonably inferred from and is necessary for the execution of the
Works, in accordance with Good Industry Practice, including where the
Contract describes any portion of the Works in general terms but not in
complete detail; or
(b) that are necessary in order for the Contractor to cause the Facility to satisfy
the Guaranteed Performance Levels and the warranties set forth in the
Contract or as otherwise necessary in order to meet the purposes for which
the Facility is being developed,
as if such superintendence, materials, works, labour and other services were expressly
mentioned in the Contract. The performance of such obligations by the Contractor
shall not be construed as a Variation and the Contractor shall not be entitled to any
revision of the Contract Price or extension of the Time for Completion.
9.1.8 The Contractor shall take full responsibility for the methods of construction,
adequacy, stability and safety of the operations carried out at the Site relating the
execution of the Works, all Contractor's Documents, Goods and Materials,
Contractor's Equipment, irrespective of any Approval or consent by the Engineer-in-
Charge.
9.1.9 The Works shall be free of all Defects in materials and workmanship and shall be
adequate, stable, safe and strictly compliant with the instructions of Engineer-in-
Charge, the Drawings and Designs, the Specifications and Good Industry Practice,
such that the Facility when complete shall be capable of meeting the Guaranteed
Performance Levels.
9.1.10 The Contractor shall use proven and reliable technologies, configurations and
architecture and exercise strict professional standards of skill, care and diligence,
adhered to by experienced and competent contractors specializing in performing
services of the same type and magnitude.
ISSUE
R0
9.1.11 Within 30 (thirty) days of the Effective Date, the Contractor shall, to the extent
necessary, register itself and the Contract, at its own Cost, with Reserve Bank of
India, Income Tax Authorities, Sales Tax Authorities, Excise Authorities and other
relevant statutory Authorities and provide copies of all documents related to such
registrations to Owner for record.
9.1.12 Notwithstanding anything contained herein, the Contractor shall obtain and maintain
all permits, licenses and approvals required for the execution of the Works as per
Applicable Laws.
9.1.13 (a) If there is any doubt or ambiguity in the interpretation of the Contract or
error, omission or contradiction therein or any of them, the Contractor shall
prior to commencing the relative work, apply in writing to the Engineer-in-
Charge for his decision in resolution of the doubt, ambiguity, contradiction or
correction of the error or omission, as the case may be. Should the Contractor
fail to apply to the Engineer-in-Charge for his decision, as aforesaid, prior to
commencing the relative Work, the Contractor shall perform the said work at
his own risks, and the provisions of Clause 9.1.13(b) hereof shall apply to any
such Work performed by the Contractor.
(b) In the event of the Contractor having already performed or executed any
Work at variance with the decision of the Engineer-in-Charge as aforesaid,
then, notwithstanding payment in respect of such Work having made to the
Contractor, such Work shall be deemed to be Defective Work and the
relevant provisions hereof and associated Clauses thereunder shall apply
thereto.
9.1.14 The Contractor is deemed to have satisfied itself as to the correctness and sufficiency
of the Specifications and other terms of the Contract relating to its risks, liabilities
and obligations set out in or implied by the Contract and all matters and things
necessary for the proper execution of the Works.
9.1.15 The Contractor shall take all steps to cause minimum disturbance of vehicular traffic
and other movement of the public, on or in the vicinity of the Site.
9.1.16 Without prejudice to the provisions of the Contract and notwithstanding any testing or
certification pursuant to this Contract, Owner shall at any time during the subsistence
of this Contract, have the right (but not the obligation) to reject any part of the Works,
the Plant, the Goods and Materials, or the Contractor's Equipment, which is found not
to be in compliance with the requirements of this Contract including, the
Specifications.
(a) remove from the Site and replace the rejected Plant, Goods and Materials or
Contractor's Equipment or re-instate the Works; or
ISSUE
R0
(b) execute any work which is urgently required for the safety of the Works,
whether because of an accident, unforeseeable event or otherwise,
in accordance with the requirements of this Contract, the cost of which shall be to the
sole account of the Contractor. The Contractor shall comply with the instruction
within a reasonable time, which shall be the time (if any) specified in the instruction,
or immediately if urgency is of the nature specified under paragraph (b).
9.1.18 If the Contractor fails to proceed with the repair or replacement of the rejected item
of the Works or the Contractor's Equipment within reasonable time, Owner may, by
contract with third Persons or otherwise, repair or replace such part of the Works
and/or terminate this Contract pursuant to Clause 32.2 and the Contractor shall be
liable to reimburse Owner upon demand for all costs and damages incurred by Owner
relating to such repair or replacement by a third party.
9.1.19 If Owner requires the Works, Goods and Materials, Contractor's Equipment or
workmanship to be retested after such remedy of the Defect therein or replacement,
the tests required to be conducted under this Contract and as instructed by Owner
shall be repeated under the same terms and conditions. If the rejection and retesting
cause Owner to incur additional costs, the Contractor shall pay these costs to Owner.
9.1.20 The Contractor shall provide, comply with and require and ensure that its
Subcontractors also provide and comply with such documentation/information or any
other support as may be requested by Owner from time to time as may reasonably be
deemed fit by Owner for meeting its obligation under any Applicable Laws for the
time being in force or in relation to the said Works, as also matters including but not
limited to exemptions, concessions etc. as may be availed, sought to be availed by
Owner.
9.1.21 The Contractor shall furnish to Owner, promptly upon request, such information
concerning the Contractor, its Subcontractors and their respective employees or the
Works as Owner may be required to furnish to any competent Authority for the
procurement of any licences, permits or approvals mentioned in Clause 8.2.
9.1.22 To the extent possible, the information regarding existing structures/ overhead lines,
existing pipelines and utilities are already indicated on alignment sheets forming part
of the Background Information. However, the Contractor may encounter other
structures/ pipelines/ optical fiber cables etc. that may not be appearing on alignment
sheets, for which, the Contractor is required to collect information on his own before
commencing the Work. The Contractor shall execute the Works in such a manner that
the said structures, utilities, pipelines etc. are not disturbed or damaged, and shall
indemnify and keep indemnified Owner from and against any destruction thereof or
damages thereto.
9.2.1 The Contractor shall, within 30 (thirty) days of the Effective Date, appoint the
ISSUE
R0
Contractor's Representative with the prior written Approval of Owner (and such
Approval shall not be unreasonably withheld) and vest in him the authority to act on
behalf of the Contractor for all purposes of the Contract. If the consent is withheld or
subsequently revoked, or if the appointed person fails to act as the Contractor's
Representative, the Contractor shall submit the name and particulars of another
suitable person for such appointment.
9.2.2 The Contractor shall not, without the prior consent of Owner, revoke the appointment
of the Contractor's Representative or appoint a replacement.
9.2.3 The Contractor's Representative shall coordinate all matters relating to the Contract
with Engineer-in-Charge, receive all instructions from Engineer-in-Charge and shall
devote substantially all of his time to the performance of the Contractor's obligations
under the Contract.
9.3 Mobilisation
9.3.1 The Contractor shall be responsible for Mobilisation including, setting up of offices at
the Site with infrastructure facilities such as power, water, communication,
conveyance etc., procuring an adequate strength of skilled, semi-skilled and unskilled
workers, who, with such infrastructure facilities shall be in a position to commence
and execute the Works. The Contractor shall carry out the Mobilisation in accordance
with the agreed quality standards and Applicable Laws.
9.3.2 The Contractor shall complete Mobilisation in accordance with the terms of the
Contract within the Time for Mobilisation, which is 21 (twenty one) days from the
Effective Date.
9.4 Security
(a) The Contractor shall furnish the Mobilization Advance Guarantee for a sum
equal to 10% (ten percent) of 110% (one hundred and ten percent) of the
Contract Price, to cover the Mobilization Advance to be received by the
Contractor under the Contract from and Indian nationalized / scheduled bank /
Indian branch of an international bank acceptable to Owner, in the form set out
at Appendix 2 (Form of Mobilization Advance Guarantee). The Mobilization
Advance Guarantee shall have a claim period of 90 (ninety) days beyond its
validity.
(b) The mobilization advance guarantee shall remain valid until the earlier of the
following:
i) Upto the date when the mobilization advance has been fully recovered; or
ii) Upto the date of Final Completion;
(c) If the Mobilization Advance Guarantee is or becomes invalid for any reason
ISSUE
R0
(other than its expiry), the Contractor shall immediately notify the Engineer-in-
Charge and obtain within 7 (seven) days a replacement Mobilization Advance
Guarantee in the form appearing in Appendix 2 (Form of Mobilization Advance
Guarantee).
(d) Owner shall have an unqualified option under the Mobilization Advance
Guarantee to draw on the guarantee and claim the amount there under in the
event of the inadequate adjustment of the Mobilization Advance in accordance
with Clause 23.1.3.
(e) The provision, maintenance or renewal, as the case may be, of the Mobilization
Advance Guarantee by the Contractor in accordance with the terms of the
Contract shall be a condition precedent to any payment by Owner to the
Contractor.
(f) If the Contractor fails to provide, maintain or renew the Mobilization Advance
Guarantee in accordance with the Contract, then Owner may, without prejudice
to any other rights and remedies to which it may be entitled, by written notice
forthwith terminate the Contract.
(g) The Contractor agrees and acknowledges that Owner shall be entitled to assign
the Mobilization Advance Guarantee in favour of any party to whom this
Contract may be assigned by Owner.
(h) Owner shall endeavour to release the Mobilization Advance Guarantee to the
Contractor, within 30 (thirty) days after total recovery of the Mobilization
Advance, including any interest/ charges, as applicable, on request of
Contractor.
(a) Within fifteen (15) days of the Effective Date, the Contractor shall furnish to
Owner, the Contract Performance Bank Guarantee from any Indian
Nationalized / Scheduled Bank / Indian branch of an International Bank
acceptable to Owner for an amount equivalent to 10% (ten percent) of the
awarded Contract Price in types and proportions of currencies in which the
Contract Price is payable in accordance with the Contract. The Contractor shall
procure the Contract Performance Bank Guarantee in the form set out in
Appendix 1 (Form of Contract Performance Bank Guarantee). The Contractor
shall maintain the Contract Performance Bank Guarantee at its own expense,
and shall ensure it shall remain valid for a period of not less than 3 (three)
months after the expiry of the Extended Defect Liability Period. The Contract
Performance Bank Guarantee shall be extended by such period as Owner may
require if the Completion is delayed beyond the Time for Completion and/or
the Final Completion is delayed beyond the scheduled date of Final Completion
and any extension thereof as per directions of the Engineer-in-Charge. In the
event that the Contract Price is increased during the Contract Validity Period
ISSUE
R0
for any reason whatsoever, the value of the Contract Performance Bank
Guarantee shall be increased proportionately by the Contractor within 7 (seven)
Business Days to ensure that it remains an amount which is equivalent to 10%
(ten percent) of the revised Contract Price, as determined by the Engineer-in-
Charge.
(b) Owner shall have an unqualified option under the Contract Performance Bank
Guarantee to draw on the security and claim the amount thereunder in the event
of the Contractor's failure to honor any of its obligations, responsibilities or
commitments under the Contract or in respect of any amount due from the
Contractor to Owner. Provided however that, nothing stated under this Clause
shall make it incumbent upon Owner to utilize the Contract Performance Bank
Guarantee in preference to any other remedy which Owner may have, nor shall
it be construed as confining the claims of Owner against the Contractor to the
value of the Contract Performance Bank Guarantee.
(c) If the Contract Performance Bank Guarantee is or becomes invalid for any
reason (other than its expiry), the Contractor shall immediately notify the
Engineer-in-Charge and obtain within 7 (seven) days a replacement Contract
Performance Bank Guarantee in the form appearing in Schedule 1 (Form of
Contract Performance Bank Guarantee).
(d) Without prejudice to the obligation of the Contractor under sub-clause (a)
above, not later than 30 (thirty) Business Days before the expiry of the Contract
Performance Bank Guarantee, the Contractor shall, upon request of the
Engineer-in-Charge obtain extension of the validity of such Contract
Performance Bank Guarantee for the period stated in such request by the
Engineer-in-Charge and provide a copy of such renewed security. If the
Contractor fails to extend the Contract Performance Bank Guarantee, Owner
shall be entitled to receive the un-drawn amount there under pending the
completion of the Works, provided that the amount so received shall be treated
as a cash retention and to the extent that there are no outstanding claims thereto,
shall be released upon submission of a new Contract Performance Bank
Guarantee acceptable to Owner.
(e) The Contract Performance Bank Guarantee shall be returned to the Contractor
after 3 (three) months from the expiry of Extended Defect Liability Period.
(f) If the Contractor fails to provide, maintain or renew the Contract Performance
Bank Guarantee in accordance with the Contract, then Owner may, without
prejudice to any other rights and remedies to which it may be entitled, by
written notice terminate the Contract forthwith.
(g) The Contractor agrees and acknowledges that Owner shall be entitled to assign
the Contract Performance Bank Guarantee in favour of any party to whom this
Contract may be assigned.
ISSUE
R0
9.5.1 Engineer-in-Charge has made available to the Contractor all the relevant data in
Engineer-in-Charge’s possession on hydrological and subsurface conditions relating
to the Site. The accuracy or reliability of the data/studies/reports and of any other
information supplied at any time by Engineer-in-Charge is not warranted and the
Contractor shall be solely responsible for the consequences of its interpretation of all
such data/studies/reports. The Contractor shall conduct further investigations
considered necessary by it at its own Cost and any error or discrepancies, if found in
the data made available by Engineer-in-Charge at any stage shall not constitute
ground for extension of the Time for Completion or any monetary claim.
9.5.2 The Contractor shall be deemed to have obtained all necessary information as to risks,
contingencies and other circumstances which may influence or affect the execution of
the Works.
9.5.3 The Contractor shall be deemed to have inspected and examined the Site, its
surroundings, the studies/reports/data mentioned in Clause 9.5.1 above and other
available information with respect to the viability of its design and the execution of
Works and satisfied itself by careful examination before submitting its Bid, as to all
the relevant matters including:
(a) The form and nature of the Site, including the surface strata, sub-soil, sub-
surface conditions, local conditions;
(c) The extent, nature and magnitude of the Work, availability of the Plant and
Goods and Materials necessary for the execution of the Works and remedying
any defects;
(f) The risk of injury or damage to property adjacent to the Site and to the
occupiers of such property or any other risk;
(g) The state of traffic both of passengers and vehicles on, along and adjacent to
the Site at all times of the day, during various seasons, festivals, etc.; and
ISSUE
R0
9.5.4 The Contractor now hereby agrees that the Contractor shall not be relieved from any
risks or obligations imposed on or undertaken by it in relation to the Works on the
grounds of any misunderstanding or misapprehension in respect of the matters
referred to in paragraphs (a) to (h) above or on the ground that it did not or could not
reasonably have been expected to foresee any such matter stated above which may, in
fact, affect or have affected the Completion of the Works and remedying of any
Defects therein or the meeting of its obligations in respect of the Works under the
Contract.
9.5.5 The Site shall be handed over to the Contractor free from any encroachment and the
Contractor shall satisfy itself to such effect prior to taking over the Site for the
execution of the Works. It is clarified for the avoidance of doubt that after handing
over of the possession of the Site or part of the Site, it shall be the sole obligation of
the Contractor to ensure that the Site or part of the Site handed over remains free from
any encroachment or squatters and the Contractor shall take all necessary steps at its
Cost and expense to give effect to its obligations under this Clause 9.5.5.
9.6.1 The Contractor shall be deemed to have satisfied itself as to the suitability and
availability of the access routes to the Site. The Contractor shall be responsible for the
maintenance of such access routes. The Contractor shall construct, if necessary, at his
own cost and initiative, temporary access road to site from main public feeder roads.
The Contractor shall provide at its own Cost, signs or directions which it may
consider necessary or as instructed by the Engineer-in-Charge for the guidance of its
employees, labourers, representatives and others. Upon the request of the Contractor
and at the risk and Cost of the Contractor, Owner may assist the Contractor to obtain
any permission, concessions and related easement right that may be required from the
relevant authorities for the use of such routes, signs and directions.
9.6.2 Owner shall not be responsible for any claims which may arise from the use or
otherwise of any access route. Owner does not guarantee the suitability or availability
of any particular access route, and shall not be liable to any claim for any non-
suitability or non-availability for continuous use during the execution of the Works of
any such route.
9.6.3 All transport operations for the execution of the Works shall be carried out as
stipulated in the Specifications. The Contractor shall indemnify Owner in respect of
all claims, demands, proceedings, damages, costs, charges and expenses whatsoever
arising out of or in relation to any such matters.
9.6.4 The Contractor shall take all reasonable measures to ensure that the transportation of
the Contractor's Personnel, Goods and Materials or Contractor's Equipment do not
interfere with local traffic in the vicinity of the Site.
ISSUE
R0
Owner shall provide a non-exclusive right of way for access to the Site. The
Contractor shall bear all Costs and charges for special or temporary rights of way
which it may require including those for access to the Site. The Contractor shall also
obtain, at its risk and Cost, any additional facility outside the Site which it may
require for the purpose of the execution of Works. Owner reserves the right to make
use of these service roads/rights of way for itself working in the area, as and when
necessary without any payment to the Contractor.
9.8.1 The Contractor in fixing the rates/prices specified in the Price Schedule shall be
deemed to have independently obtained all information necessary for the purpose of
preparing the Bid and executing the Works and to have satisfied itself as to the
correctness and sufficiency of the Bid and the Contract Price. Any error in description
of the quantity or quality of the Works or omission of any item of work shall not
vitiate the Contract or release the Contractor from its obligation to perform the Works
at the prices specified in the Price Schedule and the Contractor shall be deemed to
have known the scope, nature and magnitude of the Works and the materials,
equipment and labour required for executing the Works.
9.8.2 Unless otherwise stated in the Contract, the Contract Price and the rates and prices
stated in Contract shall, except as otherwise provided for in the Contract, cover all its
obligations under and in relation to the Contract, including the obligation to supply
Contract Spares (if applicable); and all matters and all things necessary for the proper
execution of the Works. The Contract Price shall not be adjusted save as expressly
provided in the Contract, and includes any and all direct, indirect and ancillary
charges and costs of whatsoever nature, all profit, all licenses, royalty and other fees,
the cost of all spare parts required for the execution of the Works. The Contractor
acknowledges and agrees that the Contractor shall be liable to arrange and obtain any
and all licenses on Intellectual Property rights required to execute the Works and to
perform the Contract, and that any fees associated with such licenses shall be
included within the Contract Price and shall be the sole responsibility of the
Contractor.
9.9.1 The Contractor shall submit a detailed Works Programme to the Engineer-in-Charge
not later than 30 (thirty) days from the Effective Date. The Contractor shall also
submit a revised Works Programme whenever the Engineer-in-Charge finds that the
previous Works Programme is inconsistent with actual progress as provided in the
Specifications/ scope of Work.
ISSUE
R0
9.9.3 The consent by the Engineer-in-Charge to the Works Programme shall not relieve the
Contractor of any of its responsibilities or obligations under the Contract. If the
Works Programme indicate that a Key Date has not, or shall not be met, it shall not,
by itself entitle the Contractor to an extension of time in relation to such Key Date.
9.10.1 The Contractor shall submit to the Owner and a copy thereof to Engineer-in-Charge,
by the end of each month, Monthly Progress Report which shall, amongst other
things, highlight actual or potential departures from the Works Programme and state
the measures which the Contractor proposes to take in order to make good or reduce
any delay.
9.10.2 The Contractor shall continue to submit the Monthly Progress Report until the end of
the completion of all works in all respect to the satisfaction of the Engineer-in-
Charge. However, if there is any defect during the Defect Liability Period/ Extended
Defect Liability Period (as the case maybe), progress report shall also be submitted
during that period as directed by Owner. Each Monthly Progress Report shall include:
(c) For the execution of each main part of the Works, the extent of progress
(percentage of the whole), the actual or expected dates of commencement,
anticipated completion date of the Stage, inspections and Tests on
Completion to be carried out by the Contractor;
(e) Copies of quality assurance documents or reference thereto, test results and
certificates;
(f) Safety statistics, including details of any hazardous incidents and activities
relating to environmental aspects;
ISSUE
R0
9.10.3 The Contractor shall also submit to the Engineer-in-Charge such other reports as may
reasonably be required by it or any relevant authority or public body.
9.10.4 The Contractor hereby acknowledges and accepts that any programme, Monthly
Progress Report, schedule, plan, daily report or any other information to be submitted
by it in accordance with this Clause shall not constitute the notices which it is
required to give under any provision of the Contract.
(a) The Contractor shall, wherever applicable, after proper painting, pack and crate
all materials for shipment in a manner suitable for export, in accordance with
internationally accepted export practices and in such manner so as to protect the
supplies from damage and deterioration in transit by road, rail and/or sea and
during storage at Site. Without prejudice to any other liabilities or obligations
of the Contractor, the Contractor shall be responsible for all damage to the
supplies due to improper packing.
(b) The Contractor shall notify Owner and the Engineer-in-Charge of the date of
each shipment from the port of loading as well as the expected day of arrival of
such shipment at the designated port of arrival.
(c) The Contractor’s notification shall give complete shipping details with regard
to the weight, size and content of each package, along with any other
information which Owner/ Engineer-in-Charge may require.
(d) The following documents shall be sent to Owner within 3 (three) days from the
date of dispatch of the shipment to Owner or any other person designated by
Owner:
(a) The Contractor shall, wherever applicable, after proper painting, pack and
crate all materials for in such manner so as to protect the supplies from
ISSUE
R0
damage and deterioration in transit by road and/or rail and during storage at
Site. Without prejudice to any other liabilities or obligations of the
Contractor, the Contractor shall be responsible for all damage to the supplies
due to improper packing.
(b) The Contractor shall notify Owner and the Engineer-in-Charge of the date of
each shipment from the works, factory or warehouse and expected date of
arrival at the Site.
(c) The Contractor’s notification shall give complete shipping details with regard
to the weight, size and content of each package, along with any other
information which Owner/ Engineer-in-Charge may require.
(d) The following documents shall be sent to Owner within 3 (three) days from
the date of dispatch of the shipment to Owner or any other person designated
by Owner:
9.12.1 All Contractor's Equipment and Temporary Works provided by the Contractor or any
Subcontractor shall, when brought on to the Site, be deemed to be exclusively
intended for execution of the Works and not be removed without the consent, in
writing, of the Engineer-in-Charge. Such consent shall not be unreasonably withheld
or delayed by the Engineer-in-Charge.
(a) Upon Completion of the Works, the Contractor shall remove from Site, the
eentire Contractor's Equipment, Temporary Works and surplus materials as
defined in sub-clause 0(b) below, as per the directions of the Engineer-in-
Charge.
ISSUE
R0
9.12.3 The Contractor shall be responsible for obtaining physical clearance from the
customs, if any required for constructional plant, materials and other things required
for the execution of the Works.
9.12.4 The Contractor shall, upon written request by the Engineer-in-Charge, produce to the
Engineer-in-Charge, all documents evidencing title to or the contractual arrangement
giving the right to the Contractor to use the Contractor's Equipment. In the event of
failure to comply with such request within 15 (fifteen) days, then without prejudice to
any other rights, Owner shall be entitled to withhold the payments due to the
Contractor under the Contract.
9.12.5 The Contractor shall be responsible for maintaining the Contractor's Equipment at the
Site in a safe and reliable working condition.
9.12.6 The Contractor shall be liable for loss of or damage to any of the Contractor's
Equipment or to any Persons, as a result of handling, storage or use of the
Contractor's Equipment which may occur at any time during the execution of the
Works or the remedying of Defects therein.
9.12.7 Notwithstanding anything contained to the contrary in any or all of the Clauses of this
Contract, where any goods, materials or equipment for the execution of the Contract
are procured with the assistance of any Authority either by issue from the Authority
stocks or purchased under orders, permits or licenses issued by the Authority, the
Contractor shall use such goods, materials or equipment economically and solely for
the purpose of the Contract and shall not dispose of them without the prior written
permission of Owner/Engineer-in-Charge.
9.13.1 The Contractor shall submit to Engineer-in-Charge a detailed list of the Contractor's
Documents to be submitted as well as a schedule for submissions of the Contractor's
Documents (taking into account the requirement for Approval by the Engineer-in-
ISSUE
R0
The Contractor shall comply with the Submissions Schedule for the purposes of
submissions of the Contractor's Documents and shall, in any event, ensure the
submission of the Contractor's Documents in relation to any element of the Works
simultaneously with the performance of that element of the Works. Failure by the
Contractor to do so shall entitle Owner to reject that element of the Works and the
consequences thereof shall be borne by the Contractor at its own Cost.
9.13.2 The Contractor's Documents shall be prepared in sufficient detail and shall satisfy all
regulatory approvals. The Engineer-in-Charge shall have the right to inspect/review
the preparation of the Contractor's Documents, wherever they are being prepared.
9.13.3 Each of the Contractor's Documents shall, when considered ready for use, be
submitted to the Engineer-in-Charge for its review. Unless otherwise stated in the
Specifications or elsewhere in the Contract, each review by the Engineer-in-Charge
shall not exceed the Review Period.
9.13.4 If the Engineer-in-Charge gives notice to the Contractor that a Contractor's Document
fails (to the extent stated) to comply with the Specifications, it shall be rectified,
resubmitted and reviewed (and if specified, Approved) by the Engineer-in-Charge, at
the Contractor's Cost within such time as the Engineer-in-Charge may specify to the
Contractor.
9.13.5 Design, procurement, construction, manufacture and/or installation of any part of the
Works shall not commence prior to the expiry of the Review Period for Contractor's
Documents which are relevant for the execution of such part of the Works.
9.13.6 If the Contractor wishes to modify any Contractor's Document which has previously
been submitted for such pre-construction review, the Contractor shall immediately
notify the Engineer-in-Charge, and based on the Engineer-in-Charge’s Approval,
shall subsequently submit revised Contractor's Documents to the Engineer-in-Charge
in accordance with the procedure set out in Clause 9.13.1.
9.13.7 If the Engineer-in-Charge instructs that further Contractor's Documents are required
ISSUE
R0
to be submitted by the Contractor which is necessary for carrying out the Works, the
Contractor shall promptly and at Contractor's Cost prepare such documents.
9.13.8 If any errors, omissions, ambiguities, inconsistencies, inadequacies and other defects
are found in the Contractor's Documents at any time, then such errors, omissions,
ambiguities, inadequacies or other defects shall be rectified by the Contractor at its
own Cost and any Approval or consent or review by the Engineer-in-Charge of the
Contractor's Documents shall not relieve the Contractor from any obligations or
responsibility under the Contract.
9.13.10 The Contractor's Documents shall be in the custody and care of the Contractor during
the Contract. Unless otherwise stated in the Specifications, the Contractor shall
provide 6 (six) copies of the Contractor's Documents, along with a soft copy, of the
Contractor's Documents for the use of the Engineer-in-Charge.
9.13.11 The Contractor shall keep on the Site, 1 (one) complete set of all relevant documents,
including the Contract and all documents related to Variations, other communications
given or issued from time to time under the Contract and all the Contractor's
Documents Approved by the Engineer-in-Charge. TCE, the Engineer-in-Charge.
Owner and Engineer-in-Charge shall have the right to access these documents at all
reasonable times.
9.13.12 If a Party becomes aware of an error or Defect of a technical nature in the Drawings
and Designs or in the Contractor's Documents or any other document which was
prepared for use in executing the Works, such Party shall promptly give notice to the
other Party of such error or Defect.
9.13.13 As-Built-Drawings: The Contractor shall prepare, and keep up to date, a complete set
of “as-built records” of the execution of the Works, showing the exact “as-built”
locations, sizes and details of the Works as executed, with cross references to relevant
specifications and data sheets in accordance with Clause 10.5.
9.13.14 Test-Reports: After the Performance Tests have been conducted in respect of the
Facility, the Contractor shall furnish the test reports to the Engineer-in-Charge for
evaluation in accordance with Clause 16.2.
9.14 Subcontractors
9.14.1 The Contractor shall not subcontract the whole of the Works and unless otherwise
specifically stated:
ISSUE
R0
(a) The Contractor shall not be required to obtain consent for purchases of Goods
and Materials which are in accordance with the Approved vendor list/
Approved makes specified in the Contract or for provisions of labour or for
the subcontracts for which the Subcontractors are named in the Contract
Agreement/ Contract;
(c) Not less than 30 (thirty) days before the intended date of each Subcontractor
commencing work, the Contractor shall notify the Engineer-in-Charge of
such intention.
9.14.2 The Contractor shall be responsible for observance by all Subcontractors of any
Applicable Laws and all the provisions of the Contract. The Contractor shall be
entirely responsible for the acts or defaults of any Subcontractor, its representatives or
employees, as if they were the acts, omissions or defaults of the Contractor, its
representatives or employees and nothing contained in Clause 9.14.1(a) shall
constitute a waiver of the Contractor's obligations under the Contract. The Contractor
shall provide to the Engineer-in-Charge, certified true copies of all the executed
Subcontracts containing complete terms and conditions, and annexures other than the
price. The Contractor shall make timely payments to the Subcontractors and resolve
all matters and differences with any Subcontractor speedily, without affecting the
execution of the Works in any manner.
9.14.3 The terms and conditions of any Subcontract shall impose on the Subcontractor such
terms and conditions of the Contract as are applicable and appropriate to the part of
the Works to be executed by the Subcontractor, to enable the Contractor to comply
with its obligations under the Contract.
9.14.4 Notwithstanding any consent to the selection of the Subcontractor given by the
Engineer-in-Charge, the Engineer-in-Charge shall have full power to order the
Contractor to terminate any Subcontractor and substitute such Subcontractor with any
other sub-contractor and the Contractor shall be bound to follow such order, provided
that such order is provided in writing by Engineer-in-Charge, clearly specifying the
reasons for such termination.
ISSUE
R0
9.14.6 The Contractor shall be solely responsible for the payments to be made to the
Subcontractors in accordance with their respective Subcontracts and ensure proper
and uninterrupted execution of the Works. Engineer-in-Charge shall not interfere in
the day to day management of the Subcontract between the Contractor and its
Subcontractor, but if any complaint is received by Engineer-in-Charge from any
Subcontractor regarding non-payment or delay in payment by the Contractor to such
Subcontractor, then Owner/ Engineer-in-Charge may, by a written notice, require the
Contractor to resolve such complaint within a reasonable period (to be specified in
the notice) and provide the details of the steps taken by the Contractor to resolve the
complaint, to Engineer-in-Charge /Owner. If the issue is not satisfactorily resolved
and the details provided by the Contractor are not considered satisfactory, Engineer-
in-Charge /Owner may, at its sole discretion, make direct payment to the
Subcontractor as per its claim and recover such payments from any payment due to
the Contractor under the Contract.
(a) The accurate setting out of the Works in relation to the original points, lines
and levels of reference given by the Engineer-in-Charge in writing;
(b) The correctness of position, levels, dimensions and alignments of all parts of
the Works;
(c) The provisions of all necessary instruments, equipment, apparatus and labour
in connection with the foregoing responsibilities; and
(d) Carefully protecting and preserving all bench marks, sight rails, pegs and
other things used in setting out the Works.
9.15.2 The Contractor shall first review, validate and undertake its own due diligence of
Owner's alignment survey reports and fix the alignment of the Works, pier locations,
maintaining vertical and horizontal clearances keeping in view the important Site
references and obligatory locations, in consultation with the Engineer-in-Charge.. The
Contractor shall establish, at suitable points and at its own Cost, additional reference
lines and benchmarks as may be necessary for the proper execution of the Works
while ensuring, at all times, that the reference lines, points and benchmarks fixed by
the Engineer-in-Charge are not disturbed and/ or damaged and the Contractor shall be
liable to make good any damage thereto. The verification/ inspection of any setting
out or of any line or level by the Engineer-in-Charge shall not in any way relieve the
Contractor of its responsibility for the accuracy or correctness thereof and the
Contractor shall carefully protect and preserve all benchmarks, sigh-rails, pegs and
other things used in setting out the works.
9.15.3 If at any time during the execution of the Works, an error appears in the positions,
levels, dimensions or alignment of any part of the Works, the Contractor, on being
ISSUE
R0
(a) Take full responsibility for the adequacy, stability, safety and security of the
Works, Plant, Contractor's Equipment, Temporary Works, operations on the
Site and methods of manufacture, construction and transportation;
(b) Have full regard for the safety of all persons on or in the vicinity of the Site
(including persons to whom access to the Site has been allowed by the
Contractor), comply with the Safety Code, all relevant safety regulations,
including provision of safety gear. Insofar as the Contractor is in occupation
or otherwise is using areas of the Site, the Contractor shall keep the Site and
the Works (so far as the same are not completed and occupied by Owner) in
an orderly state appropriate for the avoidance of injury or accident to all
persons on and in the vicinity of the Site and shall keep Owner indemnified
against all costs, charges, losses and damages that may be suffered by Owner
in any manner whatsoever as a result of any injury or accident to any person
on or in the vicinity of the Site in connection with the execution of the
Works;
(c) Provide and maintain all lights, guards, fences and warning signs and
watchmen when and where necessary or as required by the Engineer-in-
Charge or by any Applicable Laws or by any relevant Authority for the
protection of the Works and for the safety and convenience of the public and
all Persons on or in the vicinity of the Site;
(d) Where any part of the Works would otherwise be carried out in darkness,
ensure that all parts of the Site where such part of the Works is being carried
out are so lighted as to ensure the safety of all Persons on or in the vicinity of
the Site and of such part of the Works;
(e) The Contractor shall ensure that its employees and the employees of the
Subcontractors wear identification badges (cards), uniforms, helmets, safety
shoes, gum boots and other safety/protection wear as directed by the
Engineer-in-Charge, and to be provided by the Contractor.
(f) Without prejudice to the other terms of the Contract, the Contractor shall take
all safety measures during working in the monsoon period by dewatering at
the construction work site to keep it free from water and to prevent all
electrical shocks.
9.16.2 The Contractor shall submit a detailed and comprehensive contract specific Site
safety plan and system safety assurance plan in accordance with the Specifications.
ISSUE
R0
9.16.3 The Engineer-in-Charge's consent or rejection of the safety plans and/or supplements
thereto shall be without prejudice to the Contractor's obligations with respect to safety
measures required to be undertaken or implemented in accordance with the Safety
Code and shall not excuse any failure by the Contractor to adopt proper and
recognized safety practices throughout the execution of the Works.
9.16.4 The Contractor shall provide all necessary access, assistance and facilities to enable
the Engineer-in-Charge or any other third party safety audit agency to carry out
inspections to verify that the safety plans are being properly and fully implemented.
9.16.5 The Works, including materials to be used for execution of the Works shall be
protected from exposure to and damage due to water.
9.16.6 The execution of the Works shall not be carried out in weather conditions that may
adversely affect the execution of the Works or damage the Works (or any part
thereof) unless proper protection is provided, to the satisfaction of the Engineer-in-
Charge.
9.16.7 During the execution of the Works, storm restraint systems shall be provided by the
Contractor where necessary to the satisfaction of the Engineer-in-Charge.
9.16.8 The Contractor shall ensure that the Execution of the Works is carried out in such
manner that there is no damage to or interference with:
(a) watercourses and drainage systems on and in the vicinity of the Site;
(c) structures (including foundations), roads, street fixtures, etc. on and in the
vicinity of the Site;
(d) public or private, vehicular or pedestrian access routes and roads on and in
the vicinity of the Site; and
(e) monuments, graves or burial grounds other than to the extent that is necessary
for them to be removed or diverted for the execution of the Works. Heritage
structures shall not be damaged or disfigured on any account. The Contractor
shall inform the Engineer-in-Charge, as soon as practicable, of the structures
or roads which are not stated in the Contract to be removed or diverted but
which the Contractor considers necessary to be removed or diverted. The
Contractor shall not remove or divert any such structure or roads until the
consent of the Engineer-in-Charge to such removal or diversion has been
obtained.
ISSUE
R0
The Contractor shall be wholly responsible for security of the Site and the Works.
Unless otherwise stated in the Contract:
(a) The Contractor shall be responsible for keeping unauthorized persons off the
Site; and
9.18.1 The Contractor shall confine his operations to the Site, and to any additional areas
which may be obtained by the Contractor and agreed by Owner as working areas. The
Contractor shall take all necessary precautions to keep Contractor's Equipment and
Contractor's Personnel within the Site and these additional areas, and to restrain them
from encroaching on adjacent land.
9.18.2 At all times during the execution of the Works, the Contractor shall keep the Site
clean, safe, in a workmanlike condition and free from all unnecessary obstruction,
and shall safely store or dispose of any Contractor's Equipment or surplus materials.
The Contractor shall clear away and remove from the Site any wreckage, rubbish and
Temporary Works which are no longer required in accordance with Good Industry
Practice, Applicable Laws and instructions of the Engineer-in-Charge, unless required
to be maintained at the Site as per the express instructions of Engineer-in-Charge.
9.18.3 Upon Completion of the Works, the Contractor shall leave the Site and the Works in a
clean and safe condition. However, the Contractor may retain on Site, during the
Defect Liability Period, such Goods and Materials or Contractor's Equipment as are
required for the Contractor to fulfil its obligations under the Contract.
9.18.4 The Contractor shall not sell or otherwise dispose of or remove except for the purpose
of performing the Works, the sand, clay, ballast, earth, rock or other substances or
materials obtained from any excavation made for the purposes of the Works or any
building or produce that was on the Site at the time of handing over of the Site to the
Contractor and all such substances, materials, buildings and produce shall be the
property of Owner, provided that the Contractor may use such substances, materials,
buildings for the performing the Works with the prior permission of the Engineer-in-
Charge at the rates determined by the Engineer-in-Charge.
9.18.5 The Contractor shall take prior permission for working on Sundays and Holidays
without any additional cost to Owner. On working days, works beyond the normal
working hours can be carried out without any additional cost to the Owner
ISSUE
R0
9.19.1 Unless otherwise agreed with Owner, the Contractor’s proposed quality system shall
fully satisfy all the elements of ISO 9001 – 2000 “Quality Management Systems
Requirement”. As evidence of compliance with ISO 9001 – 2000 “Quality
Management Systems Requirement”, the Contractor shall be required to submit either
the current certificate of quality system registration with ISO 9001 or a recent
compliance audit recommending registration from a Registrar acceptable to Owner.
The quality management system developed by the Contractor shall provide for the
planned and systematic control of all quality related activities for execution of the
Works. Implementation of the quality management system shall be in accordance
with the standard specification for quality management system provided with the
Bidding Documents.
9.19.2 As a part of the quality management system to be developed and implemented by the
Contractor, the Contractor shall prepare and submit the Project Quality Plan/ Quality
Assurance Plan for the Engineer-in-Charge's review, comments (if any) and approval
within 21 (twenty one) days after the Effective Date. The Engineer-in-Charge shall
review the Project Quality Plan/Quality Assurance Plan and provide any comments to
the Contractor within 21 (twenty one) Working Days after its receipt of such draft.
Within 14 (fourteen) days after its receipt of the Engineer-in-Charge’s comments, the
Contractor shall implement such comments re-submit the Project Quality
Plan/Quality Assurance Plan to the Engineer-in-Charge for Approval. This procedure
shall be repeated until the Project Quality Plan/ Quality Assurance Plan is approved
by the Engineer-in-Charge. Any compliance by the Contractor with the Engineer-in-
Charge's comments shall neither constitute a Variation nor entitle the Contractor to
any extension of the Time for Completion or increase in the Contract Price. No
proposed change to the Project Quality Plan/ Quality Assurance Plan shall be
effective unless the Engineer-in-Charge approves of such proposed change.
Notwithstanding any comments provided by the Engineer-in-Charge, the Contractor
shall remain fully responsible for the Project Quality Plan/ Quality Assurance Plan,
including rectifying all defects therein.
9.19.3 The Contractor shall follow and comply with the Approved Project Quality Plan/
Quality Assurance Plan and shall not amend it without the prior written consent of the
Engineer-in-Charge. TCE Owner may, at any time during performance of the Works,
conduct a compliance audit with respect to the Project Quality Plan/ Quality
Assurance Plan. If such audit demonstrates non-compliance with any aspect of the
Quality Assurance Plan, Owner may notify the Contractor of such non-compliance
and the Contractor shall promptly undertake appropriate remedial action, at
Contractor's sole risk, Cost and expense.
9.20 Fossils
9.20.1 All fossils, coins, articles of value or antiquity and structures and other remains or
things of geological or archaeological interest discovered on the Site shall, as between
the Contractor and Owner, be deemed to be the absolute property of Owner. The
Contractor shall take reasonable precautions to prevent the Contractor's Personnel or
ISSUE
R0
any other person from retaining or damaging any such article or thing and shall,
immediately upon discovery thereof and before removal, acquaint Engineer-in-
Charge/ Owner with such discovery and carry out Engineer-in-Charge /Owner's
instructions for dealing with the same.
The Contractor shall be responsible to provide within the scope of Work all facilities
necessary for performance of the Works including (but not limited to) water
(including water for hydrostatic testing, if any), power, transportation, handling and
construction equipment, vehicles, vessels and any additional land at or about the Site
required for the Contractor’s field office(s), camps, godowns, workshops and
residential accommodation for the Contractor’s staff, quarry rights, borrow areas and
access roads, to or about the Site and the Contractor’s offices, camps, godown,
workshops, accommodations, and Temporary Works and facilities whatsoever
required for execution and Completion of the Works.
9.21.1 Water
9.21.1.2 In the event of failure or defect of meters, water charges will be calculated on the
consumption determined by the Engineer-in-Charge (whose decision shall be
final both as regards the existence of a defect or failure and as regards to the
water consumed). The amount due to Owner in respect of the water supplied
shall, without prejudice to any other mode of recovery available to Owner, be
deductible from the Running Bills/Final Bill of the Contractor and/or any monies
due or becoming due to the Contractor from time to time.
ISSUE
R0
9.21.2 Power
9.21.2.1 Subject to availability of power supply, Owner may, at its discretion provide for
supply of power to the Contractor for execution of the Work from Owner’s
convenient & nearest substation, from which source the Contractor shall at his
own Cost and initiative make arrangements for temporary distribution of power to
Contractor’ Works at the Site.
9.21.2.2 All arrangements for the distribution or power from source aforesaid and the
work relative thereto shall be made, performed and/or installed in conformity
with Indian Electricity Act and other Applicable Laws governing the supply and
transmission, distribution of electricity and shall be subject to prior approval by
TCE.
9.21.2.3 The Contractor shall, at his own Costs and initiative on Completion or prior
determination of the Contract or otherwise during execution of the Work, if
required by TCE because of hindrance caused thereby or for any other cause,
forthwith remove or re-route the distribution lines, installations and/or works or
part(s) thereof, as the case may be required to be removed or re-routed.
9.21.2.4 Owner shall recover from the Contractor for the power consumed by the
Contractor from Owner’s source(s) of supply the cost thereof to Owner as
determined by Owner in this behalf from time to time. The amount due to Owner
in respect of such power supplied shall, without prejudice to any other mode of
recovery available to Owner, be deductible from the Running Bill/Final Bill(s) of
the Contractor and/or any monies due or becoming due to the Contractor from
time to time.
9.21.2.5 The Contractor shall provide at his own Cost suitable electric meters approved by
the Engineer-in-Charge for measurement of the power units supplied to the
Contractor for determination of the payment due thereon to Owner. Such meters
shall be under the custody and control of Owner.
9.21.2.6 In the event of failure or defect of meter(s), power charges shall be calculated on
the consumption determined by Engineer-in-Charge (whose decision shall be
ISSUE
R0
final both as regards the existence of a defect or failure and as regards the power
consumed).
9.21.2.7 Owner may at any time without notice and without specifying any cause,
suspend or discontinue power supply as aforesaid to the Contractor, and such
suspension or discontinuance shall not entitle the Contractor to any compensation
or damages or constitute a basis for extension of Time for Completion.
9.21.2.8 Power supplied by Owner to the Contractor shall be entirely at the risks of
Contractor as to the continuity and regularity of supply, maintenance of voltage
and adequacy of load and frequency without any warranty by or liability to
Owner in respect thereof and without entitlement to the Contractor to claim
compensation from Owner on grounds of discontinuance, fluctuation of voltage
or inadequacy of load or frequency or any other cause whatsoever.
9.21.3 Land
9.21.3.1 Land for Contractor’s Field Office, Godown and Workshop Owner may, at
his own discretion and convenience and for the duration of the execution of the
Works make available near the Site, land for construction of Contractor's
temporary field office, godowns, workshops and assembly yard required for the
execution of the Contract. The Contractor shall at his own Cost construct all these
temporary buildings and provide suitable water supply and sanitary arrangement
and get the same approved by TCE. On Completion of the Works undertaken by
the Contractor, it shall remove all Temporary Works erected by it and have the
Site cleaned as directed by TCE.
If the Contractor shall fail to comply with these requirements, TCE may at the
Cost of the Contractor remove such surplus, and rubbish materials and dispose off
the same as he deems fit and get the Site cleared as aforesaid; and Contractor
shall forthwith pay the amount of all expense so incurred and shall have no claim
in respect of any such surplus materials disposed off as aforesaid. TCE reserves
the right to ask the Contractor any time during the pendency of the Contract to
vacate the land by giving 7 days’ notice on security reasons or on national interest
or otherwise. Rent may be charged by Owner for the land so provided to and
occupied by the Contractor, which may be deducted from the Running Bills/Final
Bill of the Contractor or from any other amount due or that becomes due to the
Contractor.
The Contractor shall put up temporary structures as required by it for their office,
fabrication shop and construction stores only in the area allocated to them on the
Site by Owner or his authorised representative. In addition, for uninterrupted
fabrication work, the Contractor shall put up temporary covered structures at its
Cost within area allocated to it within the Site by Owner or its authorised
representative. No tea stalls/canteens should be put up or allowed to be put up by
any Contractor on the allotted land or complex area without written permission of
Owner
ISSUE
R0
No person except for authorised watchman shall be allowed to stay on the Site,
including on any area allotted to the Contractor pursuant to this Clause 9.21.3
after completion of the day's work without prior written permission from TCE.
No Land shall be made available for residential accommodation for staff and
labour of Contractor.
The Contractor shall allow the Owner, TCE or their representatives or any other
person authorized by the Owner and/ or TCE, access to the Site at all times, and to
any place where work in connection with the Contract is being carried out or is
intended to be carried out and to any place where Goods and Materials or Plant are
being manufactured, fabricated, constructed and/or assembled for incorporation in the
Facility, during usual working hours and beyond usual working hours, upon prior
intimation. The Contractor shall ensure that the Subcontracts, if any, shall contain
provisions entitling the Owner and TCE or any person authorized by them to have
such access.
(a) all spare parts required during pre-commissioning and commissioning of the
Facility and associated systems;
(b) all mandatory spares required for the Facility and specified in the Bidding
Documents;
(c) all operation and maintenance spares, required during the Defect Liability
Period
The Contract Price shall include the cost of procuring and supplying the Contract
Spares, unless otherwise specified in the Contract.
9.24.1 While transporting any Plant, Goods and Material, Contractor's Equipment or any
other equipment, the Contractor shall comply with Applicable Laws and take all steps
necessary to ensure that roads, viaducts and bridges on any route leading to the Site,
including access and link roads to the Site as well as any third party properties, are
not damaged.
ISSUE
R0
9.24.2 In case the transportation of any Plant, Goods and Material, Contractor's Equipment
or other equipment by the Contractor is likely to cause damage to any road, viaduct or
bridge on any route leading to the Site, including access and link roads to the Site and
any third party property, it shall inform the concerned Authorities before transporting
such Plant, Goods and Material, Contractor's Equipment or other equipment and
obtain all necessary approvals and permits from the relevant Authorities as may be
required, or give its proposal for strengthening such roads, viaducts or bridges. Any
Cost incurred in this regard shall be borne by the Contractor.
9.24.3 The Contractor shall indemnify and keep Owner indemnified against all losses,
damages and claims incurred by Owner due to any damage caused to any bridge or
road or any other structure or street furniture leading to the Site, arising from the
transportation of any Plant, Goods and Material, Contractor's Equipment or other
equipment.
9.25.1 All Goods and Materials to be supplied under the Contract shall be constructed, and
all Works shall be executed by the Contractor, in the manner set out in the Contract.
Where the manner of manufacture, construction and the execution is not set out in the
Contract, the Works shall be executed in a proper, workman like and careful manner,
with properly equipped facilities and non-hazardous materials, and in accordance
with recognized and internationally accepted industrial standards and Good Industry
Practice. The successful execution of the Works is the sole responsibility of the
Contractor.
9.25.2 Owner shall be entitled at all times, at the risk of the Contractor, to inspect and/or test
by itself or through an independent person(s) or agency(ies) appointed by TCE and/or
to direct the Contractor to inspect and/or test or to get inspected and/or tested, all
materials, items and components, whatsoever supplied or proposed for supply for
incorporation in the works, inclusive during the course of manufacture or fabrication
by the Contractor and/or at the Contractor’s or his sub-vendors’ works or otherwise,
of such material, item or component. The inspection and/or tests shall be conducted at
the expense of the Contractor and may be directed by TCE to be conducted by
authorized representatives of TCE or third party inspection agency(ies) appointed by
Owner. Owner may also require that all the inspections and tests conducted by the
Contractor at his works or his sub-vendors’ works be carried out in the presence of
authorized representatives of TCE / third party inspection agency(ies) appointed by
Owner. The Contractor shall provide TCE and/or its representatives/Agents every
facility of assistance necessary for carrying out or witnessing, as the case may be the
Test(s) / Inspection(s).
9.25.3 The Contractor shall be responsible for procurement, transport, receiving, unloading
and safe keeping of all Goods and Materials and other things at the Site required for
the successful execution of the Works.
ISSUE
R0
9.25.4 The Contractor shall provide all documents and other information necessary for
testing of the Goods and Materials and such assistance, labour, materials, electricity,
fuel, stores, apparatus and instruments as are necessary to carry out such tests
efficiently.
9.25.5 The Contractor shall agree with TCE, the time and place for the testing of any Goods
and Materials and other parts of the Works as specified in the Contract.
9.25.6 If TCE does not attend at the time and place agreed, or if the Contractor and TCE
agree that TCE shall not attend, the Contractor may proceed with the tests, unless
TCE instructs the Contractor otherwise, such tests shall be deemed to have been made
in TCE’s presence.
9.25.7 The Contractor shall promptly forward to TCE duly certified reports of the tests. If
TCE has not attended the tests, TCE shall accept the readings as accurate, except
where there is a manifest error.
9.25.8 If, as a result of inspection, examination or testing, any Goods and Materials is found
to be defective or otherwise not in accordance with the Contract, TCE may reject the
same within 15 (fifteen) Working Days of such inspection, examination or testing by
giving notice to the Contractor with reasons. The Contractor shall then promptly
make good the defect and ensure that the rejected item after rectification complies
with the Contract.
9.25.9 If TCE requires such Goods & Materials to be retested, the tests shall be repeated
under the same terms and conditions.If such rejection and retesting causes Owner to
incur additional costs, such costs shall be recoverable from the Contractor, and may
be deducted by Owner from any monies payable to the Contractor under the Contract.
9.25.10 The Contractor shall not be released from any of its liabilities or obligations under the
Contract by reason of any such inspection or testing or witnessing of testing, or by the
submission of reports of inspection or testing to TCE.
9.25.11 Subject to Clause 11.5, each item of the Goods and Materials shall become the
property of Owner upon the earlier of: (i) delivery of such item to the Site; or (ii)
payment for such item, either in part or full, by Owner. The Contractor shall however
continue to bear the risk and responsibility in respect of such items which continue to
remain in its possession until the date of issuance of the Completion Certificate.
9.26.1 No Works or part of the Works shall be covered up or put out of view, without the
prior Approval of TCE or its representative.
9.26.2 The Contractor shall provide full opportunity to TCE to examine part of the Works
which is to be covered up and to examine foundations before the Permanent Works
are executed at such place. The Contractor shall also give due notice to TCE,
ISSUE
R0
whenever any such work or foundation is ready for examination and TCE shall
without unreasonable delay, examine and/or measure such work.
9.26.3 The Contractor shall uncover any part or parts of the Works, or make openings in or
through the same, as TCE may from time to time direct, and shall reinstate and make
good such part or parts, to the satisfaction of TCE. If any such part or parts have been
covered up, or put out of view and the Works are found to be executed in accordance
with the Contract, the expenses of uncovering, making openings in or through,
reinstating and making good the same, shall be borne by Owner, but if the Works are
found to be defective, costs shall be borne by the Contractor.
9.26.4 In case after completion of a part of the Works, such part of the Works is not fully
consistent with the Specifications and in the view of TCE cannot be changed or
removed, then such part of the Works in its present condition (provided it has no
implication on safety and operation) shall be accepted only after suitable reduction (as
reasonably determined by TCE) has been made from the Contract Price.
9.27 Samples
9.27.1 The Contractor shall submit at its own Cost the following samples and relevant
information to TCE for pre-construction and/or pre-manufacture review:
Each sample shall be labelled as to its origin and intended use in the Works.
9.28 Records
The Contractor shall from time to time maintain at the Site (in addition to any other
records or registers required to be maintained by the Contractor under any Applicable
Law) such records and registers with respect to the Works as TCE or Owner may
require the Contractor to keep and/or maintain from time to time. The failure to
maintain or submit any record or register required pursuant to this Clause 9.28 shall
disentitle the Contractor from submitting any Running Bill pursuant to Clause 23.3
and shall constitute a breach of this Contract.
ISSUE
R0
9.29.1 If Owner has undertaken in the Bidding Documents to procure and supply Free Issue
Materials, the supply of Free Issue Materials to the Contractor shall be on the
following terms and conditions:
(a) Deliveries shall be either from the storage of Owner or from the
factory/storage of a supplier designated by Owner or from nearest suitable
railhead or other point(s) of collection as may be determined by Owner taking
into account the source(s) of supply of the Free Issue Materials.
(b) It shall be the responsibility of the Contractor at his own risks and Costs to
take delivery of the Free Issue Materials from the stores, factory, railhead or
other collection point, as the case may be, and to arrange for its loading,
transportation to the Site and unloading at the Site or other place of storage.
The Contractor shall in taking delivery ensure compliance with any
conditions for delivery applicable to deliveries from Owner’s or supplier’s
factory/stores or railways or other transporters concerned, and shall be
exclusively responsible to pay and bear any demurrage or penalty or other
charges payable by virtue of any failure or delay by the Contractor in lifting
the supplies and/or any failure by the Contractor to observe the conditions of
supply as aforesaid, and shall keep Owner indemnified from and against all
consequences thereof.
(c) The Contractor shall inspect the Free Issue Materials supplied to it at the time
of taking delivery thereof and satisfy itself of the quality, quantity and
condition thereof prior to taking delivery and Owner shall not be liable for
any claims or complaints whatsoever in respect of quality, quantity or
conditions of the Free Issue Materials once the Contractor has taken delivery
thereof.
(d) The Contractor shall on receiving and opening the packing cases or other
packaging of Free Issue Materials on behalf of Owner, verify and tally the
actual contents with the packing list and bring any discrepancies to the notice
of the Engineer-in-Charge. The Contractor shall also sort out and segregate
and hand over to Owner’s stores, the instruction manuals, operation and
maintenance manuals, special maintenance tools, erection spares,
commissioning spares, and maintenance spares and other extras, if received
with the main equipment. The erection spares may be got issued from
Owner’s stores if required, after getting authorization from the Engineer-in-
Charge. The commissioning spares may be got issued from Owner’s stores, if
commissioning is included in the Contractor’s scope.
(e) The Free Issue Materials supplied or procured by Owner shall be utilized by
the Contractor only for incorporation in the Permanent Works and even so
shall not unless specifically authorized by Owner in this behalf) be utilized
for manufacturing any item(s) which can be obtained in finished form from
standard manufactures.
ISSUE
R0
(g) Owner shall not be responsible for any delay in the supply of any Free Issue
Materials supplied or procured or agreed to be supplied or procured by
Owner, and no such delay or failure shall anyway render Owner liable for any
claim for damages or compensation by the Contractor notwithstanding that an
increase in the time of performance of the contract be involved by virtue of
such delay and notwithstanding any labour, machinery or equipment brought
upon the Site by the Contractor for the performance of the Work being
rendered idle by such delay or failure, provided that if such delay shall in the
opinion of the Contractor, necessitate an extension of Time for Completion,
the provisions of Clause 14 hereof relating to extension of time and
associated provisions thereof shall apply.
(h) The Contractor shall maintain a day to day account of all Free Issue Materials
supplied to it by Owner indicating the daily receipt(s), consumption and
balance(s) in hand of each Free Issue Material and category thereof. Such
account shall be maintained in such from (if any) as shall be prescribed by
TCE and shall be supported by all documents necessary to verify the
correctness of the entries in the account. Such account shall be maintained at
the Contractor’s office at the Site, and shall be open for inspection and
verification (by verification of documents in support of the entry as also by
physical verification of the stocks) at all times by TCE without notice and for
this purpose TCE shall be permitted and enabled without obstruction to enter
into any godown or other place or premises where the Free Issue Materials or
any part thereof shall be stored and to inspect the same and to take by himself
and/or through his representative(s) an inventory thereof.
(i) All Free Issue Materials supplied by Owner shall be taken delivery of, held,
stored and utilized by the Contractor as trustee of Owner, and delivery of
Free Issue Materials to the Contractor shall constitute an entrustment thereof
by Owner to the Contractor, with the intent that any utilization, application or
disposal thereof by the Contractor otherwise than for incorporation in the
Permanent Works in terms hereof shall constitute a breach of trust by the
Contractor.
(j) The Contractor shall hold and store any Free Issue Materials supplied by
Owner only at such place and/or premises as may be approved by the
Engineer-in-Charge, provided that no such approval shall absolve the
ISSUE
R0
Contractor in whole or part of his full liabilities in respect of such Free Issue
Material, and the Contractor shall be and remain responsible at all times at his
own risk and cost to ensure that the Free Issue Materials supplied by Owner
is/are retained at all times in premises that are air and water tight and
otherwise suitable for the storage of the concerned Free Issue Materials so as
to prevent damage or deterioration for any cause whatsoever or theft or other
loss, and shall arrange such watch and ward therefore as shall be necessary to
ensure the safety thereof.
(k) The Engineer-in-Charge may at its discretion require that all premises in
which any Free Issue Materials supplied by Owner are stored, shall be double
locked with the keys to one lock retained by Engineer-in-Charge or its
representative and the other with the Contractor with the intent that all issues
of Owner supplied Free Issue Materials shall be with concurrence of the
Engineer-in-Charge or its representative, as the case may be, provided that
any such double-locking and/or concurrence as aforesaid shall be an
additional precaution and shall not anywise absolve the Contractor of his full
liabilities or responsibilities in respect of such Free Issue Materials.
(l) The Free Issue Materials supplied by Owner shall be insured by Owner
against normal risks during transit, storage and erection. The Contractor shall,
however, be responsible forthwith to make and pursue on behalf of Owner
any and all claims under the policy(ies) and to fulfill all formalities required
to obtain payment thereunder and/or to assist Owner in making or pursuing
any such claim(s) and/or in obtaining payment thereunder.
(m) Wherever the Contractor is required to take out any material supplied by
Owner to a location outside the Plant premises, the Contractor shall be
required to take out at his own Cost and initiative and keep in force at all
times during the pendency of the Works, policy(ies) of insurance against the
risks of fire, lightning, earthquake, riot, strike and theft and against any other
damage or loss, for the full value (on reinstatement value basis) of the Free
Issue Materials lying in the Contractor’s custody and/or storage pending
utilization/ incorporation in the Permanent Work and during incorporation in
the Permanent Work. The insurance shall be kept valid till the Completion of
the Works and till the Free Issue Materials is duly accounted for to the
satisfaction of Owner.
(n) Such insurance policy(ies) shall be in the joint names of Owner and the
Contractor with exclusive right of Owner to receive all money(ies) due in
respect of such policy(ies), and with right in Owner (but without obligation to
do so) to take out and/or pay the premium for any such policy(ies) and deduct
the premium and any other costs and expenses in this behalf from the
money(ies) for the time being due to the Contractor.
ISSUE
R0
(p) Where the Free Issue Materials are being stored within the battery area under
the security and gate-pass control of Owner and are covered by the Overall
Storage-cum-insurance Policy taken by Owner for the Works, Owner may, at
his sole discretion, permit the Contractor to furnish an Indemnity Bond in the
proforma prescribed by Owner, for the entire value of Owner supplied Free
Issue Materials and for the entire duration during which the Free Issue
Materials shall be lying in the storage and custody of the Contractor.
(q) No such Insurance(s), as aforesaid, shall absolve the Contractor from his full
liabilities hereunder, with the intent that the same shall be held merely by
way of additional security and not by way of substitution of liability. The
Contractor shall at all times be exclusively responsible for any and all
loss(es), damage(s), deterioration, misuse, theft or other application or
disposal of the Free Issue Materials, supplied by Owner or any of them
contrary to the provisions hereof and shall keep Owner indemnified from and
against the same and shall forthwith at his own Cost and expense replace any
such Free Issue Materials lost, damaged, deteriorated, misused, stolen,
applied and/or disposed as aforesaid, with other equipment or material of
equivalent quality and quantity to the extent that the same is not covered by
any insurance as above, and if covered, payment under the relative policy(ies)
is for any reason not available to Owner.
(r) The Contractor shall use the Free Issue Materials supplied by Owner for
incorporation in the Permanent Works, carefully and judiciously with no
wastage or the minimum possible wastage, wherever some wastage is
inevitable or unavoidable, in any case within the wastage limit, if any,
specified by Owner in respect of any such Free Issue Materials. For any
excess wastage or scrap, due to misuse or injudicious, careless or wrong use
of the Free Issue Materials, or in case of loss, damage or deterioration of the
Free Issue Materials during storage with the Contractor, as to all of which
the decision of TCE shall be final and binding on the Contractor, the
Contractor shall be bound to replace the Free Issue Materials with materials
of equivalent quantity and grade, acceptable to Owner within the time limit
specified by Owner, and where this is not possible, practicable or advisable,
in the opinion of Owner, which shall be final and binding on the Contractor,
Owner shall be compensated by the Contractor for the loss caused, for the
replacement costs, which shall be worked out by Owner based on the
assessed landed cost plus the costs of procurement at 15% (fifteen percent) of
the assessed landed costs for Owner. This amount shall forthwith be remitted
by the Contractor within a week of demand made by Owner, failing which
ISSUE
R0
(t) The excess equipment and material and the scrap material generated from the
Work, in so far as the Free Issue Materials are concerned, shall be returned to
Owner’s Stores. On Completion of the Work, the Contractor shall duly render
accounts for the materials and equipment issued by Owner, to the satisfaction
of Owner. Any shortages, losses and/or damages shall be to the Contractor’s
account and all the conditions stipulated under sub-clause (r) above shall
apply in this case also.
Upon failure of the Contractor to comply with any instructions given in accordance
with the Contract, Owner shall have the right to deploy additional labour force, tools,
equipment and materials for such part of the Works as Owner may designate and/or
engage another contractor to carry out the Works. In such cases, Owner shall deduct
from the amount which might otherwise become due to the Contractor the cost of
deploying additional labour or materials of the cost of engaging another contractor to
complete the Works along with an additional 10% of such cost to cover all other
expenses and departmental charges incurred by Owner in this regard. Should the total
amount thus calculated exceed the amount due to the Contractor, the difference shall
be recovered from the Contractor as a debt due.
10.1.1. Engineer-in-Charge shall prepare or cause to be prepared the Design Data required by
the Contractor for preparing the Drawings and Designs and for the execution of the
Works. The Design Data shall be supplied to the Contractor prior to commencement
of the Works.
10.1.2. The Design Data and all other information forming a part of the Bidding Documents
have been provided by Engineer-in-Charge in good faith with a view to assist the
Contractor in preparing the Drawings and Designs and executing the Works. Owner/
Engineer-in-Charge assumes no responsibility for the accuracy or adequacy of the
Design Data and the Contractor is expected to undertake a complete and independent
survey of all factors relevant to the performance of the Works and to verify the Design
Data. The Contractor shall proceed with the use of the Design Data only after satisfying
ISSUE
R0
10.1.3. The Design Data shall be in the custody and care of Engineer-in-Charge. Unless
otherwise stated in the Contract, 2 (two) copies of the Design Data shall be supplied
to the Contractor, who may make or request further copies at the Cost of the
Contractor.
10.2.1 The Contractor shall design and provide all necessary specifications for the Works,
strictly in accordance with the Specifications and the Design Data. Any design detail,
plan, drawing, specifications, notes, annotations and information required shall be
provided in sufficient detail, size and scale and within such time as may be required to
ensure effective execution of the Works and/or as otherwise required by the
Specifications.
10.2.2 All Drawings and Designs, assumptions, calculations, schedules, patterns, models and
other relevant information provided by the Contractor or as may be required under the
Specifications or as may be required by the Contractor for the execution of the Works,
or as the Engineer-in-Charge may require for a full appreciation of any design, methods
of construction and installations proposed by the Contractor, shall be submitted to the
Engineer-in-Charge for acceptance in accordance with Clause 9.13 prior to
implementation. Any acceptance by the Engineer-in-Charge shall not however relieve
the Contractor of any of his responsibilities for the accuracy, suitability, adequacy,
performance and practicality of any such Design and Drawings, assumptions,
calculations, schedules, patterns, etc. and any subsequent amendment thereof. The cost
of all necessary remedial works in relation to any Works required as a result of any
inaccuracy, inadequacy or impracticality in the Contractor's proposals and any
subsequent amendments at any time during and after the execution of the Works, shall
be the entire responsibility of and shall be borne by the Contractor.
10.2.3 The Engineer-in-Charge shall have full power and authority to require the Contractor to
amend or modify any Drawings and Designs (including related calculations, design
documents or other affected particulars) if it finds any shortcomings thereto and the
Contractor shall without delay, correct such shortcomings at its own Cost and submit all
revised Drawings and Designs, calculations, design documents or other affected
particulars to the Engineer-in-Charge for its Approval in accordance with the provisions
of Clause 9.13. Such instructions shall not however in any way relieve the Contractor of
any of its responsibilities for the accuracy, suitability, adequacy, performance and
practicality of the amended or modified Drawings and Designs.
10.2.4 Engineer-in-Charge or Owner shall have no liability whatsoever for the cost of orders
placed or of manufacturing, construction or installation commenced by the Contractor,
other than orders placed or of manufacturing, construction or installation commenced
following the acceptance of Engineer-in-Charge as provided under Clause 10.2.2.
10.2.5 The Contractor confirms that the Contractor possesses the experience and capability
ISSUE
R0
necessary for the design in relation to the Works. The Contractor undertakes that the
Contractor (and its employees) shall be available to attend discussions with the
Engineer-in-Charge to enable the Engineer-in-Charge to seek Approval of Owner at all
reasonable times during the Contract Validity Period.
10.3.1 The Contractor shall be fully responsible, for the suitability, adequacy, integrity,
durability and practicality of the Drawings and Designs.
10.3.2 The Contractor warrants that the Drawings and Designs meet the Specifications and
are fit for the purpose thereof. Where there is any inadequacy, insufficiency,
impracticality or unsuitability in or of the Specifications of the Design Data or any part
thereof, the Drawings and Designs shall take into account, address or rectify such
inadequacy, insufficiency, impracticality or unsuitability at Contractor's own Cost.
10.3.3 The Contractor warrants that the Works have been and/or shall continue to be executed
in accordance with the standards specified in the Specifications and utilising proven up
to date technology, systems, procedures, high quality goods, materials and equipments
and high standards of workmanship and fabrication, in accordance with Good Industry
Practice.
10.3.4 The Contractor warrants that the execution of the Works have taken or shall have
taken full account of the effects of the transportation of material and equipment, and
other logistics movement, Site constraints, traffic constraints, climatic conditions,
intended construction and manufacturing methods, Temporary Works and Contractor's
Equipment.
10.3.5 The Contractor shall indemnify Owner and TCE against any damage, expense,
liability, loss or claim, which Owner and/ or TCE might incur, sustain or be subject to,
arising from any breach of the Contractor's design responsibility and/or warranty set
out in this Clause 10.3.
10.3.6 No claim for additional payment or extension of the Time for Completion shall be
entertained and/or the Contractor shall not be relieved from any obligation/liability
under the Contract, for any delay, suspension, impediment to or adverse effect upon
the progress of the Works due to any mistake, inaccuracy, discrepancy or omission in
the Design Data provided by Engineer-in-Charge, the Drawings and Designs or any
failure by the Contractor to prepare any Drawings and Designs or submit the same to
the Engineer-in-Charge in due time and the Contractor shall promptly make good any
such Defect at its own Cost.
10.3.7 For each part of the Work, and except to the extent that the Parties otherwise agree:
(a) execution of such part of the Work shall not commence prior to the expiry of
the Review Periods for all the Drawings and Design which are relevant to its
design and execution;
ISSUE
R0
(b) execution of such part of the Work shall be in accordance with the relevant
Drawings and Designs, as Approved by the Engineer-in-Charge. Where any
Work or part of the Work executed by the Contractor is not in conformity with
the Approved Drawings and Designs, the Engineer-in-Charge shall be entitled
to require the Contractor to repair, rectify, dismantle and/or reconstruct such
Work or part of the Work, as the case may be and all costs and expenses for
such rectification, repair, dismantling and/or reconstruction of such Work or
part of the Work shall be borne by the Contractor;
(c) if the Contractor wishes to modify any Drawings and Designs which has
previously been submitted for review, the Contractor shall immediately give
notice to the Engineer-in-Charge. Thereafter, the Contractor shall submit the
revised documents to the Engineer-in-Charge in accordance with the above
procedure.
10.5.1 The Contractor shall prepare, and keep up to date, a complete set of “as-built records”
of the execution of the Works, showing the exact “as-built” locations, sizes and details
of the Works as executed, with cross references to drawings, relevant specifications and
data sheets. These records shall be kept on the Site and shall be used exclusively for the
purposes of this Contract. One original copy, 6 (six) hard copies of such “as built”
records, together with a soft copy of such “as built” records shall be submitted to the
Engineer-in-Charge prior to the commencement of the Tests on Completion.
10.5.2 In addition, the Contractor shall prepare and submit to the Engineer-in-Charge “as-built
drawings” of the Works, showing all Works as executed by the Contractor. The
drawings shall be prepared as the Works proceed, and shall be submitted to the
Engineer-in-Charge for its review and inspection. The Contractor shall obtain the
consent of the Engineer-in-Charge as to their size, the referencing system, and other
pertinent details.
10.5.3 Prior to the issue of the Completion Certificate, the Contractor shall submit to the
Engineer-in-Charge one soft copy, one full-size original copy and six (6) printed copies
of the relevant “as-built drawings”, and any further Contractor's Documents specified in
the Specifications. The Works shall not be considered to be completed and the
Completion Certificate shall not be issued under Clause 17 until the documents referred
above have been submitted to the Engineer-in-Charge in accordance with this Clause
10.5.3.
ISSUE
R0
10.6.1 The Engineer-in-Charge shall have the power, by written notice to the Contractor, at
any time prior to or during the execution of the Works, to alter, amend or modify any
Specification. To the extent that such alteration, amendment or modification requires
any corresponding amendment to the Drawings and Designs or any other Contractor’s
Document, the Contractor shall make such amendments to the Drawings and Designs
or, as the case may be, the relevant Contractor’s Document.
10.6.2 Contractor shall be bound to carry out such altered/extra/new items of work in
accordance with any instruction which may be given to it by the Engineer-In-Charge.
For the avoidance of doubt, it hereby clarified that if the rate(s) of any additional,
altered or substituted item of Work are specified in the Price Schedule, the Contractor
shall be bound to carry on the additional, altered or substituted items of Work at the
same rate(s) as are specified in the Price Schedule.
(a) If it is possible to derive the rate(s) for such additional altered or substituted
items of Work from any of the items of Work covered in the Price Schedule,
the rate(s) for such additional altered or substituted items of Work shall be the
rate(s) arrived at on the basis of such derivation. The opinion of the Engineer-
in-Charge as to whether the rate(s) for the additional altered or substituted
items of Work can be derived from the rate(s) of items already covered in the
Price Schedule shall be final and binding on the Contractor.
(b) If, in the opinion of the Engineer-in-Charge, it is not possible to derive the
rate(s) for the additional altered or substituted items of Work from any of the
items of the Work covered in the Price Schedule, then the rate(s) for such items
ISSUE
R0
(iii) labour cost at rate(s) for labour, if any, specified in the Price Schedule;
(iv) if the additional altered or substituted items of Work involve the use of
any material or labour not covered in the Price Schedule, for the purpose
of determining the rates under sub-paragraph (ii) and/or (iii) above, the
prevailing market rate(s) shall be taken into account for determining the
rate(s) of such materials and/or labour and an additional 15% (fifteen
percent) shall be added to the market rate(s) to cover the Contractor’s,
supervisions, overheads and profits.
10.7.1 The Contractor shall prepare and submit to the Engineer-in-Charge, the Operation
and Maintenance Manuals in accordance with the Specifications and in sufficient
detail for Owner to operate, maintain, dismantle, reassemble, adjust and repair the
Facility. The Contractor shall not be entitled to receive the Completion Certificate
unless the Operation and Maintenance Manuals have been submitted to the Engineer-
in-Charge and received its consent.
10.7.2 The Operation and Maintenance Manuals submitted by the Contractor shall, if
required, be updated by the Contractor during the Defect Liability Period and re-
submitted for review by the Engineer-in-Charge in accordance with Clause 9.13.
11.1. Subject to Clause 11.5 below, the title of domestic supply of Goods and Material and
Plant shall pass to Owner in the manner set out below:
11.1.1 In the event the Contractor is the manufacturer of the domestic Goods and Material
and Plant (including the mandatory spares etc.), the title to such domestic Goods and
Material and Plant shall be transferred to Owner ex-factory, ex works or ex
warehouse basis i.e. upon the dispatch of such goods by the Contractor from its
premises.
ISSUE
R0
11.1.2 In the event the Contractor is not the manufacturer of the domestic Goods and
Material and Plant (including the mandatory spares etc.), and instead procures the
same from a Subcontractor/ vendor / original manufacturer, then the title shall be
transferred in the following manner:
(a) If pursuant to the above arrangement between Owner and the Contractor and
between the Contractor and its Subcontractor/ vendor, the goods move from
outside the state where the Site is located to the Site, the title shall be
transferred by the Contractor to Owner during the transport of such goods
from the Subcontractor/ vendor/ original manufacturer’s premises, as the case
may be, to the Site, by endorsement of documents of title by the Contractor in
favour of Owner.
(b) If pursuant to the above arrangement between Owner and the Contractor and
between the Contractor and its sub-contractor/ vendor, the goods move within
the state where the Site is located, then the title shall be transferred to Owner
upon the dispatch of the goods by the Contractor or its Subcontractor/ vendor
/ original manufacturer, as the case may be, from its premises.
Notwithstanding the transfer of title of the domestic Goods and Material and Plant
(including the mandatory spares etc.), the responsibility for care and custody thereof
together with the risk of loss or damage thereto shall remain with the Contractor until
the issuance of Completion Certificate by Owner. However, the risk for any defect or
shortcoming in such Goods and Materials and Plant shall continue to remain with the
Contractor until issuance of the Final Completion Certificate.
11.2. Subject to Clause 11.5 and 11.6 below, the title of Goods and Material and Plant
imported by the Contractor or its Subcontractor for supply to Owner for the execution
of Works shall be transferred by the Contractor in favour of Owner by effecting
appropriate sales through endorsement of the Bill of Lading or such other documents
of title in relation to such imported Goods and Material and Plant before the same
cross the customs frontiers of India on high sea sale basis or FOB (free on board
basis) at the port of loading of the Goods and Material and Plant, as may be agreed
between the Parties.
The Contractor and its Subcontractor/ vendor shall accordingly execute such
documents as may be necessary for effecting the transfer of title in favour of Owner
in a manner indicated herein above, such that the Contractor has proper title over the
imported Goods and Material and Plant before it transfers the title over such imported
Goods and Material and Plant in favour of Owner.
ISSUE
R0
Material and Plant and for their compliance with the performance guarantees and the
technical specifications until the issuance of the Completion Certificate by Owner.
However, the risk for any defect or shortcoming in such Goods and Materials and
Plant shall continue to remain with the Contractor till issuance of the Final
Completion Certificate.
The Contractor warrants that all imported Goods and Material and Plant supplied by
the Contractor shall be free of any encumbrance or lien.
11.3. The title of the Contractor’s Equipment used by the Contractor or its Subcontractor in
connection with the Contract shall remain with the Contractor or its Subcontractor, as
the case may be.
11.4. Notwithstanding anything to the contrary contained in the foregoing provisions of this
Clause 11, the title of all Consumables, shall only be deemed to be transferred by the
Contractor to Owner, upon Final Completion, subject to the provisions of Clause 0.
For the purposes of the foregoing, “Consumables” shall mean and include all raw
material and consumables, comprised in the Goods and Materials and Plant,
including, without limitation, such as sand, bricks, stones, tiles, cement,
reinforcement steel, structural steel, and civil construction materials, subject to
CENVAT credit for such items, not being available under Applicable Laws in India.
11.5. Further, the Contractor shall ensure that all Goods and Material and Plant procured by
the Contractor from the Subcontractors/ vendor / original manufacturer, or otherwise
supplied by the Contractor are consigned by the Subcontractor/ vendor / original
manufacturer or the Contractor (as applicable) directly to the Site, unless otherwise
agreed between the Parties.
11.6. Notwithstanding anything to the contrary contained in Clause 11.1 and 11.2 above,
but subject to Clause 11.4:
(i) title in respect of any Goods and Materials and/ or Plant, which are
consigned, in breach of the foregoing provisions of Clause 11.5, to any
location other than the Site, shall only be deemed to be transferred to Owner,
in accordance with the provisions of Clause 11.1 or 11.2 above, where the
said Goods and Material and/ or Plant are duly consigned to the Site; and
(iii) Contractor shall, in order to protect Owner's interest in all Goods and
Materials and/or Plant to which title has passed to Owner but which remains
in the possession of the Contractor or any another party, take or cause to be
taken all steps necessary under the Applicable Laws to protect Owner’s title
and to protect Owner against claims by other parties with respect thereto.
ISSUE
R0
Contractor shall fully indemnify Owner in this regard. Further, to the extent
reasonably required, Contractor shall cause such Goods and Materials and/or
Plant to be suitably marked with an identifying mark or symbol indicating
that such Goods and Materials and/or Plant are the property of Owner.
12 CONTRACTOR'S PERSONNEL
12.1. The Contractor shall make arrangements for the engagement of staff and labour for
the execution of the Works at its own Cost. The Contractor shall, if required by the
Engineer-in-Charge, deliver to the Engineer-in-Charge or his assistant, a report in
detail, in such form and at such intervals as the Engineer-in-Charge may prescribe,
showing the number of personnel employed in different categories by the Contractor
on the Site.
12.2. The Contractor shall designate and propose suitable, adequately skilled and qualified
persons as key personnel (“Key Personnel”), whose identities and resumes will be
submitted by the Contractor to Engineer-in-Charge within 30 (thirty) days of the
Effective Date, to supervise the execution of the Works and to liaise with Engineer–
in-Charge or any competent Authority, as appropriate.
Should the Contractor intend to make any change in Key Personnel appointed
pursuant to this Clause 12.2, it shall immediately notify the Engineer-in-Charge of
such intended change and seek Approval for replacement of such Key Personnel.
12.3. The Contractor shall ensure that the Contractor's Personnel shall be sufficient and
competent in number, suitably qualified and experienced for the purpose of execution
of the Works at the Site and that it shall provide such numbers of Contractor's
Personnel at the Site until Completion has been achieved and that the selection of the
Contractor's Personnel shall maximise productivity and prevent slow-downs, work
stoppages or other disruptive concerted actions of the Contractor's Personnel.
12.4. Throughout the execution of the Works, and as long thereafter as is necessary to fulfil
the Contractor's obligations, the Contractor shall provide all necessary
superintendence to plan, arrange, direct, manage, inspect and test the Works.
Superintendence shall be given by a sufficient number of persons with adequate
knowledge of the language for communications and of the operations to be carried
out (including the methods and techniques required, the hazards likely to be
encountered and methods of preventing accidents), for the satisfactory and safe
execution of the Works.
ISSUE
R0
12.6. The Contractor shall make itself aware of all labour regulations and their impact on
the cost and build up the same in the Contract Price. Subject to Clause 25, during the
Contract Validity Period no extra amount in this regard shall be payable to the
Contractor, for any reason whatsoever.
12.7. In the event of default being made in the payment of any money in respect of wages
of any person employed by the Contractor or any of its Subcontractor of any tier in
and for carrying out of the Contract and if a claim thereof is filed in the office of the
labour Authorities and proof thereof is furnished to the satisfaction of the labour
Authorities, Owner may, failing payment of the said money by the Contractor or the
Subcontractor, as the case may be, make payment of such claim on behalf of the
Contractor, to the said labour Authorities and any sums so paid shall be recoverable
by Owner from the Contractor. If the Contractor fails to pay any amount required to
be paid to Owner as aforesaid, within 7 (seven) days of its demand, Owner shall be
entitled to recover the amount from any moneys due or accruing to the Contractor
under the Contract.
12.8. The establishment of the Contractor and its sub-contractors shall be duly registered
under the Employees’ Provident Fund and Miscellaneous Provisions Act, 1952 and
the Employees’ State Insurance Act, 1948 and the Contractor shall duly and timely
pay and ensure payment by its subcontractors of contributions and its/their employees
to the Authorities prescribed under the said Acts and any schemes framed thereunder
in respect of all labour employed by it for the execution of the contract. Copies of
challans/receipt of such payments along with the list showing persons employed
together with emoluments paid for the purpose of provident fund deductions shall be
submitted to Owner before the end of every calendar months. In case the relevant
provident fund Authority’s receipt/challans referred to above are not furnished,
Owner shall deduct 5% (five percent) of the payable amount from the Running Bill
and retain the deducted amount as a security for the contribution to provident fund.
Such retained amounts shall be released to the Contractor only on production of
challan/receipts of the relevant provident fund Authority for the period covered by the
related deduction.
12.9. The Contractor and Subcontractor(s) shall obtain from the Authority(ies) designated
in this regard under any Applicable Law, including but not limited to the Factories
Act, 1948 and Contract Labour (Regulation & Abolition Act, 1970 (in so far as
applicable) any and all such licence(s), consent(s), registration(s) and/or other
authorization(s) as shall from time to time be or become necessary for or relative to
ISSUE
R0
the execution of the Works or any part or portion thereof or the storage or supply of
any material(s) or otherwise in connection with the performance of the Contract and
shall at all times observe and ensure due observance by the Subcontractors, servants
and agents of all terms and conditions of the said license(s), consent(s), regulation(s)
and other authorization(s) and laws, rules and regulations applicable thereto.
12.10. Without prejudice to the responsibility of the Contractor to comply with the
Applicable Laws under the Contract, the Contractor shall, in relation to the execution
of the Works, comply and shall ensure that the Subcontractors comply with all labour
laws, including but not limited to the Factories Act, 1948, the Workmen's
Compensation Act, 1923, the Payment of Wages Act, 1936, the Minimum Wages
Act, 1948, the Industrial Disputes Act, 1947, the Employees’ State Insurance Act
1948, the Weekly Holidays Act, 1942, the Employees State Insurance Act, 1948, the
Employees Provident Funds Scheme, 1952, the Employees Provident Funds and
Miscellaneous Provisions Act, 1952, the Maternity Benefit Act, 1962, the Contract
Labour (Regulation and Abolition) Act, 1970, the Equal Remuneration Act, 1976, the
Inter-State Migrant Workmen (Regulation of Employment and Conditions of Service)
Act, 1979, the Labour Laws (Exemption from Furnishing Returns and Maintaining
Registers by Certain Establishments) Act, 1988 , the Children (Pledging of Labour)
Act, 1933, the Child Labour Prohibition and Regulation Act, 1951, the provisions of
the Income Tax Act, 1961, Environment Protection Act, 1986, Maritime Act, 2008,
Wild life (Protection ) Act, 1972 and any other Applicable Law relating to the
employment of workmen, employees or labour or any subsequent modification or re-
enactment thereof.
12.11. Without prejudice to the generality of the scope of Clause 12.8 above, the Contractor
shall comply with the provisions of the Apprentices Act, 1961 and the Rules and
Orders issued there under from time to time. Any failure to comply with the
Apprentices Act, 1961 shall amount to a breach of the Contract and Owner may, at
his discretion, terminate the Contract. The Contractor shall also be liable for any
pecuniary liability arising on account of any violation of the Apprentices Act, 1961
by him.
12.12. (a) In order to govern welfare and working conditions of labourers engaged in
construction activities, the Building and other Construction Workers’
(Regulation of Employment and Conditions of Service Act, 1996, hereinafter
referred to as the “RE &CS”) came into force. The RE&CS Act is applicable
in respect of building and other construction work. Wherever applicable, the
Contractor shall strictly comply with the provisions pertaining to RE&CS
Act. The Contractor must be registered with the concerned authorities under
the RE&CS Act, or in case of non-registration the Contractor should obtain
registration within one month of the award of the Contract.
(b) The Contractor shall comply with the Building and Other Construction
Workers’ Welfare Cess Act, 1996, the Building and other Construction
Workers’ Rules, 1998 and the Building and Other Construction Workers
Welfare Cess Rules, 1998.
ISSUE
R0
Cess as per the prevailing rate, shall be deducted at source from bills of the
Contractor by the Engineer-in-Charge of the contract and remitted to the
“Secretary, Building and Other Construction Workers Welfare Board” of the
concerned State. The Contractor shall be responsible to submit final
assessment return of the cess amount to the assessing officer after adjusting
the cess deducted at source.
12.13. The Contractor shall and shall cause its Subcontractors to comply with the following:
(b) due regard shall be given to all recognised festivals, days of rest and religious
or other customs prevalent in the location where the Site is situated, in all
dealings with the Contractor's Personnel;
(c) no work shall be carried out on the Site outside the normal working hours,
unless, permitted by Engineer-in-Charge/ Owner or if the work is
unavoidable or necessary for the protection of life or property or for the
safety of the Works, in which case the Contractor shall immediately intimate
Owner/ Engineer-in-Charge;
(d) all reasonable precautions shall at all times be taken to prevent any unlawful,
riotous or disorderly conduct by or amongst the Contractor's Personnel and to
preserve peace at the Site and to ensure the protection of all persons
(including the Contractor's Personnel) and property at or in the
neighbourhood of the Site, against any such disruption. If Owner is required
to maintain special police force/security personnel in consequence of
unlawful, riotous or disorderly conduct by or amongst the Contractor's
Personnel, all costs and damages incurred by Owner in this regard shall be
borne by the Contractor; and
(e) the Contractor shall not employ, for the purposes of Works, any Person below
the age as is statutorily forbidden.
12.14. The Contractor shall keep Owner and TCE and their personnel indemnified from
and against all personal and third party claims whatsoever (inclusive of all costs
incurred between attorney and client) arising out of any act, omission or inter-
omission on part of any Sub-Contractor or agent, sub-agent, consultant or employee
of the Contractor or any Sub-Contractor, whether committed, omitted or arising
ISSUE
R0
12.15. If, the Contractor directly or through petty contractors or Subcontractors supplies any
labour to be used wholly or partly under the direct orders and control of the Engineer-
in-Charge or Owner, whether in connection with any work being executed by the
Contractor or otherwise for the purposes of Owner, such labour shall, for the purpose
of this Clause, be deemed to be persons employed by the Contractor.
12.16. The Parties hereto agree that the employment of the personnel and/or workmen by the
Contractor, Subcontractor in relation to the execution of the Works shall not
constitute any Owner-employee relationship between Owner and such personnel
and/or workmen as employed by the Contractor and the Subcontractor in relation to
the execution of the Works.
12.17. (a) The Contractor shall ensure that local labour, skilled and/or unskilled, to the
extent available shall be employed in this work. In case of non-availability of
suitable labour in any category out of the above persons, labour from outside
may be employed.
(b) The Contractor shall not recruit personnel of any category from among those
who are already employed by the other agencies working at Site.
12.18. All foreign nationals coming to India for execution of the Contract will have to apply
for employment visa only and that grant of employment visa would be subject to
strict adherence of following norms:
(a) Employment visa is granted only for the skilled and qualified professionals or
to a person who is being engaged or appointed by a company, organization,
industry or undertaking etc. in India on contract or employment basis at a
senior level or at a skilled position such as technical expert, senior executive
or in managerial position etc.
(b) Request for employment visa for jobs for which large number of qualified
Indians are available, is not considered.
(c) Under no circumstances an employment visa is granted for routine, ordinary
secretarial/ clerical jobs.
The Contractor must check the latest visa rules from Indian Embassy/ High
Commission in their country in case foreign nationals are required to be deputed to
India during execution of the Contract.
ISSUE
R0
Time is the essence of the Contract. The Parties agree and acknowledge that it is of
paramount importance that the Works are executed strictly in accordance with the
Works Completion Schedule, as may be revised from time to time and completed in
accordance with the Specifications, within the Time for Completion.
13.2.1 If the Contractor fails to complete the Works within the Time for Completion, and/or
if completion of any specific work(s) in respect of which a separate progress schedule
has been established is not achieved by the date of completion thereof specified in the
Works Completion Schedule (each of the said date(s) is hereinafter referred to as the
“starting date for discount calculation) other than due to an event of Force Majeure or
any reason solely attributable to Owner, then the Contract Price shall be reduced by 1
% ( one percent) per week of delay or part thereof subject to a maximum deduction
of 10% (ten percent) of the Contract Price. After any adjustments made to the
Contract Price pursuant to this Clause 13.2.1, if any amount is due to Owner from the
Contractor, then such amount will either be set-off against any amount due or that
becomes due to the Contractor or be recovered by invoking the Contract
Performance Bank Guarantee.
13.2.2 The reduction of Contract Price shall not relieve the Contractor from its obligations to
complete the Works and the Facilities, or from any of its other duties, obligations or
responsibilities under the Contract. The Contractor shall use and continue to use its
best endeavour to avoid or reduce further delay to the Works, or the issue of the
Completion Certificate.
13.2.3 It is specifically acknowledged that the provisions of Clause 13.2 constitute purely a
provision for price adjustment and/or fixation and are not to be understood or
construed as a provision for liquidated damages or penalty under Section 74 of the
Indian Contract Act, 1872 or otherwise.
13.2.4 Application of price reduction under this Clause 13.2 above shall be without
prejudice to any other right of Owner, including the right of termination under Clause
32.2 and associated clauses thereunder.
14 EXTENSION OF TIME
14.1. Without prejudice to, and subject to Clause 14.3 below, to the extent that any of the
following events cause the Contractor to suffer a delay in the critical path progress of
the Works, which in turn prevents the Contractor from completing the Works within
the Time for Completion, the Contractor may apply for an extension of the Time for
Completion of the Works:
ISSUE
R0
(b) There is delay in handing over the possession of the Site (save and except
sequential handing over of Site as per provisions of Clause 8.1.2) to the
Contractor not caused due to default of the Contractor;
(c) Instruction of Owner to suspend the Works and the Contractor not being in
default;
(d) Any order of Court restraining the performance of the Contract in full or in any
part thereof, unless such order is attributable to any default, breach or non-
compliance by the Contractor;
(g) Under Clause 9.29 due to Owner’s failure to supply the Free Issue Materials
(i) Under Clause 17.6 due to taking of possession of the Works or any part thereof
by the Engineer-in-Charge prior to Completion.
14.2. Except as specified in Clause 14.1 above, the Contractor shall not be entitled to any
extension of the Time for Completion for any reason whatsoever. Provided,
notwithstanding anything contained in Clause 14.1 or otherwise, the Contractor shall
not be entitled to any extension of time:
(i) The failure of its Subcontractor, to commence or to carry out the part
of the Works in due time; or
14.3. The Contractor shall, as soon as reasonable practicable and in any event within 7
(seven) days, after the Contractor knew or ought reasonably to have known of its
ISSUE
R0
14.4. Any notice issued pursuant to Clause 14.3 shall include full particulars of:
(a) The nature and extent of each such event which is the subject of any claim for
relief under Clause 14.3 with evidence in support thereof;
(b) The estimated duration and the effect or probable effect which such event is
having or shall have on the Contractor's performance of its obligations under
the Contract;
(c) The measures which the Contractor is taking or proposes to take, to alleviate
the impact of such event; and
The Engineer-in-Charge shall not consider any claim for relief from the Contractor, if
the Contractor fails to comply with the provisions of Clause 14.3 and this Clause
14.4.
(a) the Contractor shall constantly use its reasonable endeavours to prevent
and/or minimise delay in the progress of the Works, howsoever caused, and
to prevent delay in the performance of Works beyond the Works Completion
Schedule and the Contractor shall not be entitled to an extension of the
Works Completion Schedule in respect of any cause of delay nor for any
period of delay which by the exercise of reasonable endeavours could be
avoided or reduced (to the extent that such delay could have been reduced).
The onus of proving that the Contractor has exercised all reasonable
endeavours, and that despite such endeavours, the delay could not be
avoided or reduced, shall in all cases rest with the Contractor;
(b) the Contractor shall not under any circumstances be entitled to an extension
of the Works Completion Schedule where the delay or likely delay is, or
would be, attributable to the default, breach, negligence, improper conduct or
lack of endeavour of the Contractor or any persons for whom it is
contractually or otherwise responsible for and further the Contractor shall not
be entitled to an extension of the Time for Completion where delay arises as a
consequence of the termination of a Sub-contractor's employment by the
Contractor;
(c) if there are two or more concurrent causes of delay and only one of those
concurrent causes is a delay which would entitle the Contractor to an
ISSUE
R0
(e) no relief shall be granted to the Contractor to the extent that any failure or
delay in the performance of the Works by the Contractor, would nevertheless
have been experienced by the Contractor, had an event of Force Majeure or
other relevant event(s) specified in Clause 14.1 entitling the Contractor to
otherwise claim an extension of time, not occurred.
14.6. If the delay in the completion of the Works or a portion thereof, for which an earlier
completion period is stipulated, is due to the Contractor's failure or fault, and the
Engineer-in-Charge is of the view that the remaining Works can be completed by the
Contractor in a reasonable and acceptable short time, then Owner may allow the
Contractor an extension of the Time for Completion at its discretion with or without a
reduction in the Contract Price, as it may decide.
14.7. The extension of time shall be the sole remedy of the Contractor for any cause or
event of delay mentioned in Clause 14.1 or elsewhere in the Contract and other than
as provided in the Contract, the Contractor shall not be entitled to claim any damages
or compensation in addition to or in lieu of such extension of time.
15.1. For the purposes of this Contract, “Mechanical Completion” shall mean the
completion of the following activities in relation to the Facility:
(i) the construction of the Facility has been completed, checklist generated &
punched with minor exceptions, Flushing, chemical cleaning including all
other Pre-commissioning activities, MRT (Mechanical Run Test for
Machine) & final boxup excluding system dry out and catalyst loading;
(ii) all Plant, equipment and machinery are installed and aligned;
(iii) all piping and instrumentation work and loop testing is complete;
(iv) all electrical work is complete, electrical systems are energized and motor no
load runs are complete;
(v) all hydrostatic/pneumatic testing is completed;
(vi) safety valves and pressure relief valves are set and checked;
(vii) speed and direction of rotation of all prime movers are checked; and
(viii) DCS system (if applicable) is complete.
ISSUE
R0
15.2. As soon as the conditions mentioned in Clause 15.1 have been satisfied in the opinion
of the Contractor, the Contractor shall notify Engineer-in-Charge with copy to Owner
in writing that the Facility is mechanically complete.
15.3. The Contractor shall divide the Facility into systems/subsystems as per the
process/pre-commissioning requirement mentioned in the Specifications.
15.4. The Contractor shall issue a certificate in the format set out at Appendix 5 Part A
(“Format-I”) for each system for inspection and verification by the Engineer-in-
Charge with copy to Owner that construction has been completed in accordance with
the Specifications.
15.5. Except for any deviation or modification agreed between Owner, the Engineer-in-
Charge and the Contractor, if the Engineer-in-Charge is not satisfied that the relevant
system/subsystem has achieved Mechanical Completion, it may endorse Format-I
accordingly / issue Format II as set out at Appendix 5 Part B, stating in what way the
system/subsystem has not achieved Mechanical Completion in accordance with the
Contract. The Contractor shall then expeditiously complete or rectify the list of
outstanding items in accordance with the Engineer-in-Charge’s suggestions and issue a
certificate in the format set out at Appendix 6 (“Format-III”), with agreed Punch-list
Items to be attended to later.
15.6. The Contractor shall prepare and submit to the Engineer-in-Charge along with each
Format-III, a preliminary, but as definitive as possible a list containing all the
outstanding Punch-list Items and procedures that require completion or rectification
before the taking over of the Facility by Owner (the “Punch List”).
15.7. Upon the submission of the Punch List by the Contractor pursuant to Clause 15.6, the
Engineer-in-Charge shall either approve such list or require such additions to and/or
amendments of such list as it may reasonably consider necessary.
15.8. When Format-IV for all systems/sub-systems comprising the Facility is issued, the
Facility will be deemed to have achieved Mechanical Completion.
(a) the Punch-list Items are completed before the Facility is taken over by Owner
unless otherwise agreed between the Parties; and
15.10 Pre-Commissioning
15.10.1 For the purposes of this Contract, “Pre-Commissioning” shall mean performance of
those activities, which are required to be performed after acceptance of system on
ISSUE
R0
liquidation of all the punch point to make the Facility ready for commissioning and
includes the completion of the following activities in relation to the Facility:
15.10.2 Contractor will start Pre-Commissioning activities after acceptance of Format -III for
all systems/subsystems comprising the Facility by Owner/ Engineer-in-Charge. The
Contractor shall also be responsible for any fabrication and supply of temporary
facilities such as temporary bypasses, spools, blinds, jump-overs, vents, strainers,
screens etc. which will be required to carry out Pre-Commissioning activities.
15.10.3 The Contractor shall issue a ‘ready for commissioning’ certificate for the Facility to
Engineer-in-Charge for its Approval with a copy to the Owner, in the format set out at
Appendix 7 (“Format-IV”). If the Engineer-in-Charge is not satisfied that the
Facility is ready for commissioning, it may endorse Format-IV accordingly, stating in
what way the Facility is not ready for commissioning in accordance with the
Specifications. The Contractor shall then expeditiously complete or rectify the list of
outstanding items in accordance with the Engineer-in-Charge’s suggestions and once
all such outstanding items are completed to the satisfaction of the Engineer-in-
Charge, the Engineer-in-Charge shall declare the Facility to be ready for
commissioning.
16 TESTS ON COMPLETION
For the purpose of this Contract, ‘Commissioning’ shall mean the successfully
putting in to service the Plant, equipment, vessels, tanks, pipelines, machines,
systems, sub systems, controls, monitoring, shutdown comprising the Facility in
accordance with the procedures set out in the relevant operating manuals and/or as
per the requirement of the process licensor and /or detailed engineering contractor/
Engineer–in-Charge and relevant statutory agencies after successful testing, pre
ISSUE
R0
commissioning and the trial runs and the documentation as per Engineer-in-Charge’s
format system.
(a) all parts of the Facility has been demonstrated to have achieved Mechanical
Completion pursuant to Clause 15 and the Contractor has issued Format-III
relating to all systems/subsystems comprising the Facility in accordance with
the provisions of Clause 15.5;
(b) the Contractor has completed all Pre-Commissioning activities and has issued
Format-IV;
(c) Facility is ready for the conduct of the Trial Operation and Performance Tests
in relation thereto; and
(d) all the services and facilities which are necessary for the conduct of the Trial
Operation and/or Performance Tests are available,
the Contractor shall notify Owner and the Engineer-in-Charge that it is ready to
commence Trial Operation. Such notification must be sent by the Contractor to
Owner and Engineer-in-Charge within 7 (seven) days of the issuance of Format-IV
under Clause 15.10.3. Unless otherwise agreed the Trial Operation shall commence
on such day as the Contractor shall notify to Owner and the Engineer-in-Charge
(which shall not be more than 10 (ten) days after Owner’s/ Engineer-in-Charge’s
receipt of the above-mentioned notice from the Contractor) and shall be conducted in
accordance with the Contractor's Documents relating to the same as Approved by the
Engineer-in-Charge pursuant to Clause 9.13.
16.1.2 The Trial Operation of the Facility shall be carried out for 14 (fourteen) days in
accordance with the Contractor's Documents. During the Trial Operation the Parties
shall arrange for the conduct of Performance Guarantee Test Run (PGTR). The PGTR
shall be conducted only after the Facility has been on stable operation, with all
controls and safety systems in normal operation, for a period of not less than 72
hours. The load at which the Facility is operated during the PGTR shall be
determined by the Engineer-in-Charge at its discretion.
16.1.3 Upon successful completion of the PGTR, to the satisfaction of the Engineer-in-
Charge, the Engineer-in-Charge shall direct Owner to issue a certificate to the
Contractor in the format set out at Appendix 8 (“Format-V”).
16.1.4 The Contractor shall at its own Cost arrange for all tools, equipments, gadgets,
facilities or other things as may be deemed necessary by the Engineer-in-Charge for
carrying out the Tests on Completion.
ISSUE
R0
16.2.1 The Performance Tests shall be conducted within 30 (thirty) days (or as directed by
Engineer-in-Charge) of the successful completion of the Trial Operation of the
Facility or before the expiry of such other period as may be agreed between Owner
and the Contractor, to ascertain whether the Facility is capable of meeting the
Guaranteed Performance Levels and is ready for continuous, safe and stable
commercial operation. The Contractor will give Owner and the Engineer-in-Charge at
least 7 (seven) days advance written notice of the expected date of such Performance
Tests. In the event that there is a delay in carrying out the Performance Tests, the
Contractor shall notify Owner and the Engineer-in-Charge of such delay. If the
Engineer-in-Charge fails to attend at any time or place duly appointed for conducting
any Performance Tests, the Contractor shall be entitled to proceed in its absence and
the relevant Performance Tests shall be deemed to have been made in the presence of
the Engineer-in-Charge. The Contractor shall forward to Owner and the Engineer-in-
Charge duly certified copies of the results of each Performance Test.
16.2.2 After the Performance Tests have been conducted in respect of the Facility, the
Contractor shall furnish the test reports to the Engineer-in-Charge for evaluation.
Within 7 (seven) Working Days of receipt of the test reports, the Engineer-in-Charge
shall, after evaluating the test reports, decide whether the Facility complies with the
Guaranteed Performance Levels.
16.2.3 Upon such evaluation, if the Engineer-in-Charge is of the opinion that the Facility has
not achieved 100% (hundred percent) of the Guaranteed Performance Levels, then:
(a) the Contractor shall at its own risk, Cost and expense be responsible for the
repair or replacement of the Works for the Facility if required by Owner/
Engineer-in-Charge in accordance with the provisions of this Contract, within
3 (three) months of the conduct of such Performance Tests; and
(b) the Contractor shall be required to re-conduct the Performance Tests within
such reasonable period of time as may be required by Engineer-in-Charge.
The period for repairing or replacing the Works or for re-conducting the Performance
Tests shall not amount to an extension of the Works Completion Schedule or be
deemed to entitle the Contractor to an increase in the Contract Price. The re-conduct
of the Performance Tests shall not prejudice any rights or remedies of Owner in
respect of defective Works under the Contract and shall not be construed as a waiver
thereof.
16.2.4 If, despite the repetition of the Performance Tests in accordance with Clause 16.2.3
above, the results of the Performance Tests indicate that 100% (hundred percent) of
the Guaranteed Performance Levels have not been satisfied, then the following
consequences shall follow:
(a) Where the Facility and the Works achieves more than 90% (ninety percent)
of the Guaranteed Performance Levels, Owner shall be entitled to levy the
Performance Compensation in accordance with Clause 20 and Owner may
ISSUE
R0
further require the Contractor to make additional repairs or remedy the Works
within 3 (three) months of the completion of the repeated Performance Tests,
at the Contractor's Cost; or
(b) Where the Facility achieves less than or equal to 90% (ninety percent) of the
Guaranteed Performance Levels, Owner shall have the right (but not an
obligation) to reject the Works by giving notice thereof within 15 (fifteen)
Working Days of the receipt of the results of the Performance Tests.
In the event that Owner does not exercise its right to reject the Works in accordance
with paragraph (b) above, then the consequences at paragraph (a) above shall also
apply to such defective Works. Owner shall be entitled to enforce the Performance
Guarantee for recovering the sums due from the Contractor under Clause 16.2.4 (a).
16.2.5 Upon the issuance of a notice by Owner under Clause 16.2.4(b), a Contractor Event
of Default shall be deemed to have occurred and this Contract shall stand terminated
forthwith. The provisions of Clause 32 shall apply upon such termination.
16.2.6 The acceptance and use by Owner of the Works, or any part thereof, for Trial
Operation shall not absolve the Contractor from the fulfilment of other obligations
under the Contact.
17 COMPLETION
(f) provided to Owner all such documentation and information such as manuals,
systems descriptions, computer programs, access codes etc. that are necessary
to enable Owner to properly test and use any part of the Works in accordance
with Good Industry Practice and in compliance with the laws and regulations
ISSUE
R0
When the Contractor has successfully completed the total Works as per the scope of
Works defined in the Contract and the Specifications and the Facility is ready for
commercial operations, the Contractor shall so notify Owner in writing.
17.3 Owner shall, subject to provisions of Clause 17.1, Clause 17.2 and Clause 17.4,
within 30 (thirty) Working Days of receipt of a notification from the Contractor
pursuant to Clause 17.1 or, as the case may be Clause 17.2, along with all the
documents mentioned in Clause 17.4(b) below:
(a) inspect the Works and if it is satisfied that the Works are complete in all
respects in accordance with the Specifications and free of all Defects, issue a
completion certificate to the Contractor (“Completion Certificate”) and the
Works shall be taken over by Owner on the date of issue of the Completion
Certificate; or
(b) if the Engineer-in-Charge is not satisfied that the Works are complete in all
respects in accordance with the Specifications or discovers any Defects in the
Works, notify the Contractor of the reasons why it considers that the notice
given pursuant to Clause 17.1 or Clause 17.2 was improperly or prematurely
issued and notify the Contractor of:
(i) any items of work which are in Owner's or TCE’s reasonable opinion
required to render the Facility ready for being taken over; or
(ii) any Defects in the Facility which are required to be rectified and
following completion such items or, as the case may be, rectification
of such Defects, the Contractor shall submit a fresh notice to Owner
to which the provisions of this Clause 17.1 shall apply mutatis
mutandis.
17.4 Notwithstanding anything contained in Clause 17.3, Owner shall not issue the
Completion Certificate until:
(a) the Contractor has cleared the Site of all scaffolding, wiring, pipes, surplus
materials, Contractor’s labour, equipment and machinery, demolished,
dismantled and removed all the Contractor’s Site offices and quarters and
other Temporary Works, structures and constructions and other items and
things whatsoever brought upon or erected at the Site and not incorporated in
the Permanent Works, removed all rubbish from the Site, cleared and leveled
the Site to the satisfaction of TCE and put Owner in undisputed custody and
possession of the Site, free & clear of all encumbrances and encroachments;
ISSUE
R0
and
(i) the technical documents according to which the Work was carried
out;
(ii) complete set of “as-built” drawings showing therein corrections and
modifications (if any) made during the course of execution of the
Works, signed by the Engineer-in-Charge;
(iii) Statement of final levels as set for various works, signed by the
Engineer-in-Charge;
(iv) Records of the final test as maintained jointly and signed by the
representative of the Contractor and the Engineer-in-Charge or
Format-III (if Commissioning is not within the Contractor's scope of
Work) and Format -V (if Performance Tests are not within the
Contractor's scope of Work) and Performance Test certificate issued
by the Engineer-in-Charge upon successful completion of the
Performance Tests (if Performance Tests are within the Contractor's
scope of Work).;
(v) Item-wise list of surplus materials including the quantity & estimated
value of each surplus item (out of the Free Issue Materials or
materials brought on the Site by the Contractor) returned to Owner’s
or otherwise disposed of, duly signed by the Engineer-in-Charge;
(vi) Materials-at-site accounting for the Free Issue Materials supplied to
the Contractor under the Contract, signed by the Engineer-in-Charge;
(vii) Discharge in respect of Owner supplied equipment and machinery,
signed by the Engineer-in-Charge; and
(viii) Declaration by the Contractor that it has duly cleared any and all of
the dues payable by it to its labourers, employees, piece rate workers
(PRWs), and other personnel, Subcontractors, suppliers, vendors,
income Tax, sales tax, octroi, entry tax, service tax, excise, customs
duty, provident fund, employees state insurance (ESI) and royalties,
or other amounts payable under any Applicable Law (if any).
17.5 Upon the issuance of the Completion Certificate, Owner shall take over the
possession, care, custody and control thereof from the Contractor.
17.6 Notwithstanding anything to the contrary contained in the Contract, the Engineer-in-
Charge shall have the right to take possession of or use any completed or partially
completed Work or part of the Works. Such possession or use shall not be deemed to
be an acceptance of any Works. If such prior possession or use by the Engineer-in-
Charge delays the progress of Work, equitable adjustment in the Time for Completion
shall be made in accordance with Clause 14.
ISSUE
R0
18.1. The Defect Liability Period shall be a period of 12 (twelve) months from the date of
Completion mentioned in the Completion Certificate.
18.2. The Contractor warrants that during the duration of the Defect Liability Period, the
Works shall be free of all Defects.
18.3. If, during the Defect Liability Period, any Defects are discovered in the Works or any
part thereof; or the Works or any part thereof fails to meet the Guaranteed
Performance Levels, Owner will notify the Contractor of such Defects or failure.
Upon receipt of such notice, the Contractor shall promptly repair or replace such
Work (including any necessary uncovering, covering and recovering) in accordance
with the Contract, Good Industry Practices and Applicable Laws. At Owner's option
and Contractor's expense, Owner shall have the right to provide labour in connection
with such repair or replacement to the extent that such labor can be provided by
Owner's then-current permanent employees working at during normal working hours.
The Contractor shall provide for all additional labor required for such repair or
replacement and shall bear all Costs and expenses associated with repairing or
replacing any Work, including costs incurred by Owner in relation to providing labor,
employees and personnel for any such repairs or replacement. Upon completion of
any repair or replacement work, the Contractor shall, at its own expense, and with
Owner's coordination and Approval, perform such tests as necessary to demonstrate
that pursuant to cure of Defects under this Clause 18.3, the Works meet the
Guaranteed Performance Levels.
18.4. If the Contractor fails to rectify any Defects in the Work during the Defect Liability
Period, Owner (at its sole discretion) may:
(a) Carry out the work itself or by others, in a reasonable manner at the risk and
Cost of the Contractor; In addition to the costs, Owner shall be entitled to claim
15% (fifteen percent) of such costs towards the genuine pre-estimated damages
suffered by Owner; or
(b) If the Defect or damage is such that Owner has been deprived of substantially
the whole of the benefit of the Works or part of the Works, terminate the
Contract in respect of such parts of the Works as cannot be put to the intended
use. Without prejudice to any other rights, under the Contract or otherwise,
Owner shall then be entitled to recover all sums paid for such parts of the Works
together with the cost of dismantling the same, clearing the Site and returning
Goods and Materials to the Contractor and the provisions of Clause 32 shall not
apply.
18.5. If the Defect or damage is such that it cannot be remedied expeditiously on the Site
and if Owner gives consent, the Contractor may, remove from the Site for the purpose
of repair any part of the Works, which is defective or damaged. The consent may
require the Contractor to increase the amount of Contract Performance Bank
ISSUE
R0
Guarantee by the full replacement cost of items which are to be replaced or to provide
other appropriate security acceptable to Owner.
18.6. If the repair or remedy of any Defect or damage is such that it may affect the
performance of the Works, Owner may, within 30 (thirty) Working Days after such
repair or remedy, require that certain tests be repeated as may be necessary to
demonstrate compliance with the Guaranteed Performance Levels.
18.7. If any part of the Works has been replaced, renewed or repaired during the Defect
Liability Period, the Defect Liability Period in respect of such part shall start again
for a period of 12 (twelve) months from the date on which such replacement, renewal
or repair has been completed to the satisfaction of TCE (“Extended Defect Liability
Period”).
Upon the expiry of the Defect Liability Period (or Extended Defect Liability Period,
as applicable), but subject to there being no outstanding obligation of the Contractor
to rectify the defects notified during such period, Owner shall issue the Final
Completion Certificate to the Contractor (“Final Completion Certificate”). The
Contract shall not be considered to have been completed until the Final Completion
Certificate has been signed by Owner and delivered to the Contractor, stating the date
on which the Contractor has completed its obligations under the Contract. Only the
Final Completion Certificate shall be deemed to constitute Approval of the Works by
Owner.
20 COMPENSATION
20.1. If the Works and the Facility, or any part thereof, fails to meet the Guaranteed
Performance Levels, then the Contractor shall pay to Owner Performance
Compensation at the rates specified in the Contract (“Performance Compensation”).
The liability of the Contractor towards Performance Compensation under this Clause
20.1 shall not exceed a sum that is greater than 10% (ten percent) of the Contract
Price. The Parties acknowledge that the Performance Compensation are a genuine
pre-estimate of and reasonable compensation for the losses and damages that will be
suffered by Owner in the event that the Works, or any part thereof, fail to meet the
Guaranteed Performance Levels and the Contractor irrevocably undertakes that it will
not, whether by legal proceedings or otherwise, contend that the amount of the
Performance Compensation are not reasonable.
(a) deduct and retain the amount of the Performance Compensation becoming
due under Clause 20.1 from any sums due or which become due to the
Contractor; or
ISSUE
R0
(c) require the Contractor to pay such amount to Owner within 28 (twenty eight)
days from the date receipt of a written notice for such payment from Owner,
notwithstanding any Dispute between the Parties as to the amount due or the
liability to make payment of the same.
20.3. The payment of the Performance Compensation does not in any way relieve the
Contractor from any of its obligations to perform the Works or from any other
obligations and liabilities of the Contractor under the Contract.
20.4. The Contractor agrees that the payment of Performance Compensation shall not affect
the right of Owner to recover damages resulting from the breach of any other terms of
this Contract, seek specific performance, or terminate the Contract pursuant to any
other provisions hereof.
21 CONTRACT PRICE
In consideration of the full and complete discharge of the Contractor's obligations under the
Contract, Owner shall pay to the Contractor the Contract Price at the time and in the manner
set forth in the Payment Schedule, subject to such deductions and adjustments as may be
permissible under the Contract.
The Contract Price is a fixed lump-sum price inclusive of all Taxes and shall not be subject to
any escalation, variation or alteration whatsoever throughout the Contract Validity Period,
except as provided in the Contract or the Bidding Document; and includes any and all direct,
indirect and ancillary costs, including profits, license, royalty and other fees, cost of all Goods
and Materials, Plant and Contractor's Equipment and all other charges arising out of or in
connection with the execution of the Works. The Contractor acknowledges and agrees that the
lump-sum price and the rates set out in the Price Schedule and the Contract Price shall hold
good till the completion of the Works and shall not be adjusted for any fluctuation in the
market costs of labour or materials.
21.2.1 The Contract Price shall be deemed to include and cover the following:
(a) all costs, expenses, outgoings and liabilities of every nature and description
and all risks whatsoever to be taken or which may occur in relation to the
acquisition, loading, unloading, transporting, storing, fabricating any Plant,
equipment or system or the execution, completion, testing, commissioning
and/or handing over of the Facility to Owner;
(b) cost of all construction, Plant, Goods and Materials and all other items,
materials and things required for incorporation in the Permanent Works or
otherwise in execution of the Works, including cost of procuring Contractor’s
Equipment, supply of water and power, construction of Temporary Works/
ISSUE
R0
Facilities, temporary roads, cost of labour, spares, fuel, stores and supplies to
be provided or arranged in connection with the execution of the Works;
(c) cost of all Drawings and Designs, Contractor’s Documents, plans, models,
studies and other documents required to be prepared and furnished by the
Contractor under the Contract;
(e) cost of all Taxes, other than to the extent provided in Clause 22 below;
(f) cost of all rents, royalties, licenses, permits, permissions and other fees,
duties, penalties, levies and damages payable on the performance of the
Works including, the excavation, removal or transportation of any material or
acquisition or use of any right of way or other rights, permits or privileges in
connection with the performance of the Works;
(h) cost of all inspections, tests and cost of items, instruments and/or tools
required to conduct such inspections or tests;
(i) cost of all escalations including, Taxes, labour costs, cost of materials and
other inputs;
22.1. All the Taxes and levies payable in India whether under Central, State or Local laws
applicable in India as well as those leviable outside India, shall form part of the
Contract Price. The Contractor shall bear all the Taxes, duties, levies on the supply of
Goods and Material and Plant (including customs duties payable on imported Goods
and Materials and Plant) and on performance of the services, under Central, State or
Local laws applicable in India as well as those leviable outside India.
22.2. In respect of Goods and Material and Plant to be supplied by the Contractor from
within India the Ex-factory value of such Goods and Material and Plant and all the
indirect Taxes leviable on the transaction between ‘Owner and Contractor’ shall be
separately indicated in the Price Schedules (as indicated in the Price Schedule) along
ISSUE
R0
22.3. The Contract Price comprises the base price of the Goods and Material, Plant and
services and the Taxes thereon and therefore the Contractor is mandatorily required to
indicate the Taxes in the format prescribed under Price Schedules.
22.4. The customs duty shall be to the account of the Contractor and the Contractor shall be
responsible for the timely payment of the custom duties to the relevant Government
Authorities. Owner shall assist in provision of all necessary documents required by
the Contractor to clear the Goods and Material and Plant on availing the benefit of
any concessional rate of customs duty available.
The Contractor shall be responsible for and shall exercise due diligence in properly
classifying the Goods and Material and Plant, undertaking the payment of customs
duties, and/ or otherwise complying with all Applicable Laws with respect to any
import of the Goods and Material and Plant. In case Owner is exposed to any penal
action (interest and/ or penalties) by the customs Authorities for incorrect declaration
and/ or valuation of the Goods and Material and Plant by the Contractor, or otherwise
on account of any breach of Applicable Laws in the course of the import of the Goods
and Material and Plant, the Contractor shall indemnify and hold harmless, Owner for
any and all costs, expenses or losses suffered or incurred by Owner in this regard.
22.5. Owner shall issue in accordance with relevant legislation, the requisite sales tax
declaration forms (including but not limited to Form C for materials other than raw
materials/consumables as defined elsewhere in the contract) to the Contractor in order
to get the benefit of any concession in the rate of VAT/ CST, as the case may be. The
Contractor shall provide relevant statutory declaration forms to Owner in accordance
with relevant legislation, within the period specified under the relevant sales tax
legislation.
22.6. Unless otherwise provided for in the Contract, the Contractor shall be solely liable for
payment of the following amounts:
(a) all Taxes imposed and assessments made in relation to the Contractor's
Equipment and the Works (including any Taxes applicable to the Works
performed by the Subcontractors) which are payable in India;
(b) all contributions payable under Applicable Laws, awards or pursuant to any
contract with an industrial or trade union or other association of employees;
or otherwise with respect to or ascertained by reference to the wages, salaries
or other compensation paid to the employees of the Contractor or any
Subcontractor in respect of the Works, including Taxes or contributions for
workers' compensation, unemployment or sickness benefit, old age benefit,
welfare funds, pensions and disability insurance;
(c) all harbour dues, pilotage fees, port fees, wharf fees, unloading costs incurred
in India in respect of any imported Contractor's Equipment;
ISSUE
R0
(d) all direct Taxes, including income tax, profession tax and wealth tax for
which the Contractor is the responsible party.
22.7. The Contractor and its Subcontractor/ vendor/ original manufacturer shall issue
proper invoice, as stipulated under the customs, excise, VAT/CST, service tax and
other Applicable Laws, and other necessary documents as may be relevant from time
to time to enable Owner or any person designated by Owner to avail the credit of such
Taxes, wherever applicable, paid by the Contractor or any Subcontractor/ vendor/
original manufacturer within the time period specified under the applicable legislation
in this regard.
If Owner is not able to avail the credit (as indicated in the Price Schedule, unless
otherwise mentioned in this Contract), partially or entirely because the Contractor or
any Subcontractor/ vendor/ original manufacturer issued a defective invoice or failed
to produce the requisite documents, then the Contractor shall immediately indemnify
Owner for such loss of Tax credit which would be otherwise available to Owner.
Owner, in such case, may, in its sole discretion, decide to recover such loss by way of
deduction from payment due to the Contractor or invoking the Contract Performance
Bank Guarantee.
22.8. The benefit of any Tax exemption, concessions, rebate or any other incentives
available when the Contractor or its Subcontractors/ vendor are performing their
obligations under the Contract, shall be passed on to Owner.
22.9. Contractor agrees for withholding from wages and salaries of its agents, servants or
employees all sums, required to be withheld by the laws of the Republic of India or
any other agency having jurisdiction over the area where Contractor is conducting
operations, and to pay the same promptly and directly when due to the proper
authority. Contractor further agrees to comply with all accounting and reporting
requirements of any Nation having jurisdiction over the subject matter hereof and to
confirm to such laws and regulations and to pay the cost of such compliance. If
requested by Owner/TCE, Contractor will furnish Owner/TCE the evidence of
payment of applicable Taxes, in the country (ies) of the Contractor's and his sub-
Contractor(s) and expatriate employees.
22.10. The Contractor shall be solely responsible for all procedural compliances related to
the payment of Taxes under the Contract and it shall protect, indemnify and hold
harmless Owner, from any and all cost, penalty, claims or liability:
(a) to pay any Taxes assessed or levied by any competent Authority on the
Contractor or its Subcontractors/ vendor / original manufacturer or on Owner
for or on account of any act or omission on the part of the Contractor or its
Subcontractors/ vendor/ original manufacturer; or
ISSUE
R0
(d) arising from any proceedings initiated against Owner by any competent
Authority in respect of any non-compliance, non-payment, short-payment of
Taxes.
22.11. In case the Contractor is a foreign entity, it is mandatory to furnish the Contractor’s
Permanent Account Number (PAN), as per the Indian Income Tax requirements,
failing which the Contractor shall be responsible for any additional Tax deduction at
source as per the provisions of the Indian Income Tax Act/Rules. The PAN shall be
furnished before release of any payment or within one month of award of work,
whichever is earlier.
23 TERMS OF PAYMENT
23.1.1 Contractor may ((if specified by it in its Bid and accepted by Owner) be provided a
recoverable interest bearing Mobilization Advance up to a maximum of 10% (ten
percent) of the awarded Contract Price towards Mobilisation and execution of the
Works. Mobilization advance shall carry an interest rate as defined in the Contract.
23.1.2 Mobilisation Advance shall be paid to the Contractor in two instalments subject to the
fulfilment of the following conditions:
ISSUE
R0
The Mobilisation Advance together with the interest accrued, thereon, shall be
recovered from each Running Bill @ 12% (twelve percent) of gross amount of each
Running Bill in such a manner that the total Mobilization Advance and interest
accrued thereon is recovered by the time approximately 85% (eighty five percent) of
the Contract Price is paid to the Contractor. Balance amount, if any, shall be deducted
in full from the pre-final Bill. Mobilization advance Bank Guarantee will be reduced
accordingly on quarterly basis against the request of the Contractor.
23.1.4 If the Mobilization Advance has not been fully adjusted against the Running Bills
within 30 (thirty) days of the expiration of the Time for Completion or pre-final bill
whichever is earlier or immediately prior to termination under Clause 32, the whole
of the balance of the Mobilization Advance then outstanding shall immediately
become due and payable by the Contractor to Owner and Owner shall be entitled to
call upon the Mobilization Advance Guarantee.
23.2.1 Owner may provide a Secured Advance to the Contractor for non-perishable, non-
fragile and non-combustible Goods and Materials brought on the Site for execution of
the Works, in the following manner:
(a) in the case of steel, 75% of the value of the Goods and Materials on
ISSUE
R0
receipt of the Goods and Materials at the Site or 75% of the quoted value of
corresponding SOR item in which the Goods and Materials are to be
incorporated, whichever is lower, and Approval of the Goods and Materials
by Owner/TCE. For cement, the Secured Advance will be released only when
the Contractor has established proper storage and handling facility at the Site;
(b) in the case of non-perishable Goods and Materials other than steel, 75% of
the landed cost on receipt of the Goods and Materials at the Site or 75% of
the quoted value of corresponding SOR item in which the Goods and
Materials are to be incorporated, whichever is lower, and Approval of the
Goods and Materials by Owner/TCE(as per the list for Category B Items
provided in SCC in the Bidding Document),
23.2.3 The Secured Advance will be recovered from the Running Bills proportionate to the
extent that the Goods and Materials in respect of which the Secured Advance was
provided are incorporated in the Permanent Work. The balance amount if any will be
recovered completely on the earlier of:
(a) 90% of the Contract Price being paid to the Contractor; and
ISSUE
R0
23.2.4 No interest shall be levied on the Secured Advance, provided that the Goods and
Materials for which the Secured Advance is provided are incorporated in the
Permanent Work within the agreed Works Completion Schedule. If there is any
inordinate and inexcusable delay in incorporation of the Goods and Materials for
which the Secured Advance is provided in the Permanent Work, Owner may levy
interest at the rate as defined in the contract on the value of the unutilised Goods and
Materials from the date on which such Goods and Materials were scheduled to be
incorporated in the Permanent Work as per the Works Completion Schedule till the
date on which the Goods and Materials are incorporated in the Permanent Work.
The Contractor shall submit to Owner, within 30 (thirty) days of the Effective
Date, the Billing Schedule, which shall be taken into account by Owner when
releasing payment of Running Bills.
Within 30 (thirty) Working Days of the receipt of such Billing Schedule, the
Parties shall mutually agree upon the same. In the event that the Parties are
not able to reach an agreement, Owner's decision regarding the Billing
Schedule shall be final and binding on the Parties. Such Billing Schedule
shall be deemed to be a Contractor’s Document and shall form the basis of
progressive payments of the Contract Price as stated in the payment terms, in
accordance with this Clause 23.3.
(i) The Contractor may raise Running Bills, as specified below, every
alternate month and if an ad hoc payment is made by Owner in
respect of the intervening month, for the amount certified by the
Engineer-in-Charge on the basis of a summary assessment made by
the Engineer-in-Charge of the value of the Works performed by the
Contractor during the intervening month, such ad hoc payment(s)
shall be deducted from the amount(s) certified by the Engineer-in-
Charge as payable on the next Running Bill raised by the Contractor.
23.3.2 (a) Within 7 (seven) days after completion of a Payment Milestone (in case of a
ISSUE
R0
(i) the estimated value of the Works executed by the Contractor and the
Contractor's Documents produced until the date of the Running Bill
(including Variations);
(iv) any other additions or deductions which may have become due under
the Contract or otherwise, including those under Dispute; and
(v) the deduction of amounts certified in all previous Running Bills and
paid by Owner to the Contractor in accordance with Clause 23.
(b) Each Running Bill must contain the Contractor's certification with supporting
documentation:
(ii) that it has reviewed all financial and budget data contained in the
Running Bill and the same is true and complete;
(iii) that the quality of all completed Works is in accordance with the
Specifications;
(iv) that each obligation, item of cost or expense has not been the basis of
any previous payment (unless the amount of the payment was
subsequently reimbursed to Owner); and
(c) Within 30 (thirty) Business Days after receipt of a Running Bill submitted in
full compliance with Clause 23.3.2 and not more than once a month, Owner
ISSUE
R0
Owner may withhold from any payment due to the Contractor amount Owner deems
reasonably necessary or appropriate because of any one or more of the following
reasons:
(a) Defects and deficiencies in any Works, whether or not payment has been
made in relation to that part of the Works;
(c) reasonable evidence that completion of the Works will not occur within the
Time for Completion;
(d) failure, in any material respect, to perform the Works or any of the
Contractor's other obligations under the Contract;
(g) a dispute exists as to the accuracy or completeness of any Running Bill (but
only with respect to the amount then in dispute);
(h) amount of Taxes which Owner may have to pay if conditions of Clause 22
are not fulfilled; and
(i) any amount expected to be paid by Owner to any person, on behalf of the
Contractor or its affiliates under any agreement or any Applicable Laws for
the time being in force or any court order or any other reason or purpose.
(j) Any amount otherwise specified under the Contract, as being deductible from
the payments to be made by Owner to the Contractor.
ISSUE
R0
23.5.1 Within 15 (fifteen) days after receipt of the Completion Certificate, the Contractor
must submit a payment claim and endorse it as the “Final Bill”. The Contractor must
include in that claim:
(a) statements for the Contract Price, summarising and reconciling all previous
payments made by Owner and adjustments in the Contract Price; and
(b) any further sums which the Contractor considers to be due to it under the
Contract.
23.5.2 Except as provided in Clause 23.5.4, within 90 (ninety) Business Days after the
receipt of the Final Bill complete in all respects in accordance with the Contract,
Owner must pay to the Contractor the amount mentioned in the Final Bill and
certified by the Engineer-in-Charge, less any disputed amounts, subject to Owner's
right under Clause 23.3 to set off against amounts due from the Contractor. If the
amount that the Contractor owes to Owner under Clause 23.3 is greater than the
amount mentioned in the Final Bill and certified by the Engineer-in-Charge, then the
Contractor must pay the excess amount which is a debt due and payable to Owner
within 90 (ninety) days after Owner's receipt of the Final Bill.
23.5.3 After the expiry of the 15 (fifteen) days period referred to in Clause 23.5.1, a claim
which the Contractor was entitled to make, but has not made in the Final Bill, is
barred and the Contractor waives any right to bring such a claim.
23.5.4 The amount certified in the Final Bill will not become due under Clause 23.5.2 until
the Contractor submits to Owner:
(a) a certificate of release certifying that the Contractor waives all rights to bring
any claims which the Contractor is entitled to make, but which are not
included in the Final Bill;
(c) a confirmation from the Contractor that there has been no Change of Law that
it has not notified Owner which may result in a reduction in the Contract
Price; and
(d) any and all outstanding documentation required to be given to Owner by the
Contractor.
23.2. No interim payment by Owner constitutes acceptance by Owner of the Works or any
part thereof, or releases the Contractor from any of its obligations or liabilities under
the Contract.
ISSUE
R0
23.3. Payment of the amount mentioned in the Final Bill by Owner shall not mean release
of the Contractor from all of its liabilities under the Contract. The Contractor shall be
liable to fulfill and discharge all his liabilities and responsibilities under the Contract
until the end of the Contract Validity Period and release of the Contract Performance
Bank Guarantee.
23.4. Without limiting Clause 23.4 and 23.5, Owner may at any time deduct from any
moneys which are or may be payable to the Contractor (including security), any sums
which may be or are payable by Owner pursuant to the Contract. Nothing in this
Clause 23.4 affects the right of Owner to recover from the Contractor, the whole of
the debt or any balance that remains owing after any deduction.
23.5. If the Contractor fails to pay a Subcontractor on time such sum as is properly due
under the agreement between the Contractor and such Subcontractor, then Owner
may, on behalf of the Contractor, make the payment direct to the Subcontractor and
the amount so paid will be a debt due and payable from the Contractor to Owner.
23.6.1 Subject to the other provisions of the Contract, if the execution of the Works shall
necessitate the importation into India of materials, plant or equipment or if the Works
or any part thereof are to be executed by labour from outside India, a portion of the
payments to be made under the Contract shall be made in the appropriate foreign
currencies as requested in the Bid and accepted by Owner.
23.7 All payments required to be made by Owner to the Contractor shall be made by wire
transfer to an account or accounts to be designated by the Contractor, which is
maintained by the Contractor: (a) for payments in Indian currency, with a bank or
banks in India; and (b) for payments in foreign currency, with a bank or banks in the
country in which the payment is to be received. Owner’s liability to make payment
shall be deemed to have been discharged when the amount due is deposited in the
accounts or accounts designated by the Contractor for this purpose and subject to all
acts necessary to initiate the relevant wire transfer being completed within the time
stipulated for making payment of the amount due, any delay within the international
or domestic banking system in the transfer of such amount to the Contractor’s
account or accounts shall not give rise to a claim that Owner is in breach of its
payment obligations under the Contract.
23.8 Measurement
23.8.1 All measurements under this Contract shall be in the metric system and except where
expressly indicated to the contrary in the Contract, all measurements shall be taken in
accordance with the procedure set out in the Contract notwithstanding any
provision(s) in the relative standard method of measurement or any other general or
local custom to the contrary.
ISSUE
R0
23.8.3 If the Contractor absents itself for any reason whatsoever on the date appointed for
joint measurements, the measurements shall be taken by the Engineer-in-Charge or its
representative in the absence of the Contractor and such measurements signed by the
Engineer-in-Charge or its representative shall be final and binding upon the
Contractor.
23.8.4 Measurements shall be signed and dated on each page by the Contractor or the
Contractor’s Representative and the Engineer-in-Charge or its representative. If the
Contractor objects to any of the measurements recorded, including the mode of
measurement, such objection shall be noted in the measurement book against the item
objected to and such note shall be signed by the Contractor’s Representative and the
Engineer-in-Charge or its representative. In the absence of any noted objections, the
Contractor shall be deemed to have accepted the relative measurements as entered in
the measurement book and shall be barred from making or recording any objection in
respect of the measurements recorded in the measurement book.
23.8.5 All measurement(s) relative to which any objection(s) have been noted in the
measurement book shall be submitted to the Engineer-in-Charge for its decision and
the decision of Engineer-in-Charge shall be final and binding on the Contractor.
In case the clarity is not available through (a), (b) & (c) above, then it shall be as
prescribed by the Bureau of Indian Standards (“BIS”) and if it does not so prescribed
by BIS, then measurement of works shall be as decided by Engineer-in-Charge,
which shall be final and binding upon the Contractor.
23.8.7 Wherever the unit of items has been indicated as lump sum, the payment shall be
made on lump sum basis on completion as per payment break-up schedule, and no
mode of measurement shall be applicable.
ISSUE
R0
24 VARIATION
24.1. Engineer-in-Charge may at any time during the performance of the Works instruct the
Contractor, by issuing a written notice, to carry out a Variation (“Variation Order”);
and the Contractor must perform and be bound by a Variation. Engineer-in-Charge
shall not propose a Variation which:
(a) will have a material adverse effect upon the Contractor's ability to cause the
Works to meet the Guaranteed Performance Levels upon completion of the
Facility;
24.2. The Contractor may propose to Owner any Variation which the Contractor considers
necessary or desirable to improve the quality, efficiency, reliability, operability,
maintainability or safety of the Facility. Owner may, in its absolute discretion,
Approve or reject any Variation proposed by the Contractor. Any Approval must be
notified to the Contractor.
24.3. Notwithstanding anything contained in Clauses 24.1 and 24.2, a Variation made
necessary due to any act, omission or default of the Contractor in the performance of
its obligations under the Contract will not result in any payment to the Contractor or
an increase in the Contract Price.
24.4. No Variation shall invalidate the Contract. The Contractor agrees that a Variation
may involve the omission of any part or parts of the Works and the Contractor agrees
that Owner may engage others to perform that part or parts of the Works which have
been omitted. The Contractor further acknowledges that any omission or omissions
will not constitute a basis to allege that Owner has repudiated the Contract no matter
the extent or timing of the omission or omissions.
24.5. Within 15 (fifteen) days of receipt of the direction referred to in Clause 24.1, the
Contractor must prepare and submit to the Engineer-in-Charge a statement setting
out:
24.6. Owner may accept the offer given under Clause 24.5 or request the Contractor to
submit revised estimates. If Owner accepts any offer it shall issue an instruction
ISSUE
R0
identifying the offer that is being accepted and requesting the Contractor to proceed
with the Variation.
24.7. If agreement of an estimate is not reached under Clause 24.6, Owner may issue an
instruction to the Contractor to proceed with the Variation and:
24.9. If a Variation results in a reduction of the time required to complete the Works, the
Engineer-in-Charge may determine a reasonable reduction and notify the Contractor
of the revised Time for Completion and other dates as set out in the Works
Completion Schedule.
24.10.1 The quantities set out in the Price Schedule are estimated quantities for the execution
of the Works and such quantities shall not be taken as the actual and correct quantities
required for the execution of the Works. The Contractor shall be paid only for the
actual quantities of Works executed by it on the basis of the rates set out in the Price
Schedule and in accordance with the Payment Schedule and other relevant provisions
of the Contract.1
24.10.2 Notwithstanding anything to the contrary in Clause 21 and this Clause 24.10,
variations in the quantities of the items set out in the Price Schedule shall be paid for
by Owner in the following manner:2
(a) There shall be no variation in the rates of the items specified in the Price
Schedule as a result of any increase in the total Contract Price up to 25%
(twenty five percent);
(b) If the increase in the total Contract Price is likely to be more than the limit
specified in Clause 24.10.2 (a) above, the rates for the additional quantities
1
This Clause is not applicable if the Contract is a lump-sum price contract
2
This Clause is not applicable if the Contract is a lump-sum price contract
ISSUE
R0
shall be mutually agreed between Owner and the Contractor, duly accounting
for savings, if any, that may be available to the Contractor in case of
increased quantities.
24.10.3 The Contractor shall be bound to notify TCE at least 15 (fifteen) Working Days
before the necessity arises for the variation in the quantities of item(s) set out in the
Price Schedule, in excess of the limits of variation specified above. If TCE and the
Contractor are unable to agree on the revised rates on account of variation in
quantities of item(s) in excess of the limits mentioned above, the revised rates of such
varied quantities of item(s) shall be determined in accordance with Clause 35,
pending which the Contractor shall be bound to perform the Works in relation to such
varied quantities in accordance with the Contract.
24.10.4 There shall be no variation in the rates of the items specified in the Price Schedule,
unless specifically, mentioned elsewhere in the Bidding Document as a result of any
decrease in the total Contract Price and the Contractor shall not be entitled to any
compensation in this regard.
24.10.5 Except as provided in Clause 24.10.2 above, the quantities of the Works stated in the
Price Schedule are indicative and as such (in case of item rate tender) do not form
part of the Contract and Owner shall neither be liable for any increase or decrease in
the actual quantities of the Works performed, nor shall such increase or decrease in
the actual quantities of the Works performed form the basis of any alteration of the
rates quoted in the Price Schedule or for any claim for additional compensation,
damages or loss of profits. Notwithstanding the quantities mentioned in the Price
Schedule and the Contract Price mentioned in the Letter of Award, the Contractor
shall only be entitled to payment in respect of actual quantities of the Works
performed by it.
24.10.6 The quantities of the Works and the gross value of the Works actually performed by
the Contractor as valued on finalisation of all dues to the Contractor is the sole
liability of Owner towards the Contractor and the Contractor shall not be entitled to
any compensation in addition to such amounts.
25 CHANGE IN LAW
25.1. In the event that the Contractor reasonably considers that there is a Change in law as a
result of which the Contractor suffers an increase in Cost or reduction in net financial
burden payable with respect to execution of the Works, the Contractor shall give
notice to TCE as soon as is reasonably practicable with:
ISSUE
R0
25.2. If the Change of Law requires a Variation or the Contractor is beneficially affected by
a Change of Law, TCE must within 14 (fourteen) Working Days of receiving the
Contractor's notification under Clause 25.1 provide a direction to either:
25.3. If TCE provides a direction under Clauses 25.2(a) and 25.2(b), such direction will be
treated as a Variation to which the provisions of Clause 24 will apply.
25.4. To the extent that a Change of Law causes the Contractor to incur more Cost or less
Cost than it would otherwise have incurred, the difference shall be compensated by
Owner or the benefit of lower Costs shall be passed on to Owner by the Contractor, as
the case maybe. The Contractor shall produce sufficient proof and estimate of
increase in Costs for Owner's consideration.
26 SUSPENSION
26.1. The Engineer-in-Charge may at any time by issuing a written order (“Suspension
Order”) to the Contractor (with a copy to Owner) suspend the execution of part or all
of the Works including: (a) delivery of Contractor's Equipment which is ready for
delivery to the Site; or (b) the erection of the Plant or part thereof which has been
delivered to the Site; or (c) testing and commissioning of the Works.
26.2. The Suspension Order may be issued by the Engineer-in-Charge under the following
circumstances:
(i) any act, default, omission or breach by the Contractor or for some
default or breach by the Contractor reasonably anticipated by the
Engineer-in-Charge; or
(iii) existence of any emergency on the Site or at any place where the
Works (or any part thereof) are being executed leading to unsafe
conditions; or
ISSUE
R0
(b) For any other reason which the Engineer-in-Charge thinks reasonable.
26.3. Upon issuance of any Suspension Order under Clause 26.1, the Contractor shall
protect, store and secure such part or whole of the Works or any Plant or Contractor's
Equipment to which the Suspension Order relates to, against any deterioration, loss or
damage and shall not remove any goods or equipment (including any Goods and
Materials and Plant) from the Site without the prior written consent of Owner, during
the entire suspension period. The Contractor shall take all steps to minimize cost and
losses to Owner due to suspension and shall meet Owner on a regular basis.
26.4. On issuance of the Suspension Order due to events specified in Clause 26.2(a), the
Contractor shall within 10 (ten) days undertake all necessary steps (including such
steps as instructed by the Engineer-in-Charge) to remedy the circumstances leading to
Suspension Order and immediately inform the Engineer-in-Charge on completion of
such actions. Within 7 (seven) Working Days of receipt of such intimation from the
Contractor, if he Engineer-in-Charge is satisfied that its instructions above have been
fulfilled and complied with, issue a letter instructing the Contractor to resume the
Works or such part of the Works that are subject of a Suspension Order. If the
Engineer-in-Charge is of the view that such instructions have not been complied, the
Engineer-in-Charge shall identify by means of further written notice the additional
action required to be taken by the Contractor before any instruction to resume can be
given.
26.5. The Engineer-in-Charge may at any time instruct the Contractor to resume the Works
or such part of the Works that are subject of a Suspension Order, in which case the
Contractor shall do so as soon as is reasonably practicable and in any event within 5
(five) days of receiving such instructions. The Contractor shall, after notice to the
Engineer-in-Charge, and together with Engineer-in-Charge, examine the Works,
Plant, Goods and Materials affected by the Suspension Order. The Contractor shall
make good any deterioration or Defect in or loss of/ to the Works, Plant, Goods and
Materials, which has occurred during the suspension.
26.6. The Contractor shall under no circumstances be entitled to any extension of the Time
for Completion or claim for any monetary compensation where Suspension Order has
been issued by the Engineer-in-Charge under Clause 26.2(a).
26.7. Notwithstanding anything contained in the Contract, the Contractor shall not be
entitled to any Costs for preserving the Works during the period of suspension caused
due to any Force Majeure event.
ISSUE
R0
27 FORCE MAJEURE
27.1. Neither Party is responsible for any failure to perform its obligations under the
Contract, if it is prevented or delayed in performing those obligations by an event of
Force Majeure.
27.2. An event of Force Majeure is an event or circumstance which is beyond the control
and without the fault or negligence of the party affected (“Affected Party”) and
which by the exercise of reasonable diligence the Affected Party was unable to
prevent and which is not caused or contributed by the Affected Party, provided that
event or circumstance is limited to the following:
For the avoidance of doubt, inclement weather, third party breach, delay in supply of
materials (other than due to a nationwide transporters’ strike) or commercial hardship
shall not constitute a Force Majeure event.
27.3. Where there is an event of Force Majeure, the Affected Party must notify the other
Party in writing as soon as possible and in any event within 10(ten) days of becoming
aware of or the date it ought to have become aware of the occurrence of an event of
Force Majeure giving full particulars of the event of Force Majeure and the reasons
for the event of Force Majeure preventing the Affected Party from, or delaying the
Affected Party in performing its obligations under the Contract. The Affected Party
must use its reasonable efforts to mitigate the effect of the event of Force Majeure
upon its performance of its obligations under the Contract and notify the other party
of the measures being taken to mitigate the effect(s) of the event of Force Majeure.
27.4. Upon completion of the event of Force Majeure the Affected Party must as soon as
reasonably practicable recommends the performance of its obligations under the
Contract. Where the Affected Party is the Contractor, the Contractor must provide an
amended Works Programme rescheduling the Works to minimise the effects of the
ISSUE
R0
27.5. An event of Force Majeure does not relieve a party from liability for an obligation
which arose before the occurrence of that event, nor does that event affect the
obligation to pay money in a timely manner which matured prior to the occurrence of
that event.
27.6. The Contractor has no entitlement and Owner has no liability for:
(a) any costs, losses, expenses, damages or the payment of any part of the
Contract Price during an event of Force Majeure; and
(b) any delay costs in any way incurred by the Contractor due to an event of Force
Majeure.
27.7. If an event of Force Majeure occurs and its effect continues for a period of 180 (one
hundred eighty days or more in a continuous period of 365 (three hundred sixty five)
days after notice has been given under this Clause 27, either Party may terminate the
Contract by issuing a written notice of 30 (thirty) days to the other Party.
27.8. In the event that the Parties are unable to agree in good faith about the existence or
occurrence of a Force Majeure event, such dispute shall be finally settled in
accordance with the dispute resolution mechanism provided herein; provided
however that the burden of proof as to the occurrence or existence of such Force
Majeure event shall be upon the Party claiming relief on account of such Force
Majeure event.
28 INTELLECTUAL PROPERTY
28.1. The Contractor (with full title guarantee) hereby grants to Owner a royalty-free,
irrevocable, non-exclusive licence to use, modify and reproduce the Contractor's
Documents and any Intellectual Property contained in the Facility, the Works and the
Contractor's Documents for any purpose whatsoever connected with the Facility; and
the licence hereby granted shall carry the right to grant sub-licences and shall be
transferable to third parties. This licence does not include a licence to reproduce the
Intellectual Property contained in the Works and the Contractor's Documents for any
other project undertaken by Owner or any third person.
28.2. Owner shall grant or shall grant to the Contractor a royalty-free, exclusive licence to
use the Background Information and any Intellectual Property contained in the
Background Information for the sole purpose of the performance of the Contractor's
obligations under this Contract. The Contractor shall have no right to create any
copies of, reproduce or to disclose the Background Information to any third Persons
without the prior written consent of Owner, except in favour of the Contractor's
Personnel and its Subcontractors (provided that the Contractor's Personnel and its
Subcontractors shall be bound by the terms of the license granted under this Clause
28.2).
ISSUE
R0
(a) it has all rights and licences necessary to grant, assign and transfer to Owner
licences to the Contractor's Documents and any Intellectual Property
contained in the Works and the Contractor's Documents in accordance with
this Contract;
(b) it has no title or ownership to the Background Information and shall make no
claim against or create any encumbrance over the Background Information or
any Intellectual Property therein;
(c) no infringement of any Intellectual Property of any kind of any third Person
will result from the performance of this Contract; and
(d) it has paid all royalty on any and all Intellectual Property licensed by it
28.4. The Contractor acknowledges that the Contractor is the author of the Contractor's
Documents referred to in Clause 28.1 and the Contractor waives any moral rights
which the Contractor might otherwise possess and the Contractor shall obtain a
waiver of all rights that any of its employees, agents or Subcontractors may have
pursuant to Applicable Laws in relation to the Contractor's Documents.
28.5. The Contractor shall, if so requested by Owner, at any time, execute such documents
and perform such acts as may be required fully and effectively to assure to Owner the
rights referred to in this Clause 28.
(a) procure for Owner the right to continue using the Works and the Contractor's
Documents or any portion thereof;
(b) re-perform the Works or part thereof, or replace the Contractor's Documents
or part thereof with a non-infringing plant and equipment or part thereof; or
28.7. The Contractor shall indemnify Owner, TCE and their officers, advisors,
representatives, agents, personnel and employees from and against all claims,
liability, loss, damage costs and expenses (including but not limited to legal costs)
arising out of any claim that any Intellectual Property contained in the Works or the
Contractor's Documents or any use of such Intellectual Property by or on behalf of
Owner infringes the Intellectual Property of a third party.
28.8. The Contractor shall pay all royalties and license fees, if any, for materials, apparatus,
methods, processes, systems, software or other Intellectual Property rights purchased
ISSUE
R0
The Contractor makes the following representations and warranties to Owner each of
which is true and correct during the term of the Contract:
(a) it has been incorporated as a company under the laws of India and is validly
existing under those laws;
(b) it has power to enter into the Contract and comply with its obligations under
it;
(c) the Contract and the transactions under it do not contravene its constituent
documents or any Applicable Law or obligation by which it is bound or to
which any of its assets are subject or cause a limitation of powers or the
powers or its directors to be exceeded;
(d) it has in full force and effect the authorisations necessary for it to enter into
the Contract and the transactions under it;
(e) its obligations under the Contract are valid and binding and are enforceable
against it in accordance with the terms of the Contract;
(h) there are no reasonable grounds to suspect that it is unable to pay its debts as
and when they become due and payable;
(i) it has the necessary skills and experience to perform the Works in accordance
with the Contract;
ISSUE
R0
(j) it owns or has the right to use or provide to Owner all Intellectual Property
necessary to perform its obligations under the Contract; and
(k) it will perform its obligations under the Contract and conduct its business
with a high level of integrity which is reasonably expected of an international
contractor of similar size and profile, conducting a similar line of business,
and will not engage in any corrupt or fraudulent practices.
Without prejudice to any other warranties expressed elsewhere in the Contract, and
despite any inclusion of Engineer-in-Charge’s /Owner's documents in the Contract
(including in the Specifications) or any Approval given or withheld by Owner/
Engineer-in-Charge under the Contract, the Contractor warrants:
(a) the Works will be performed with all the skill and care to be expected of
appropriately qualified and experienced contractors with experience in
performing works and services of a similar size, type, nature and complexity
to the Works and in accordance with Good Industry Practice;
(b) the Works will be performed in accordance with, all the requirements in the
Contract and the Specifications, by properly qualified and accredited
personnel, for the Contract Price and by the Time for Completion;
(c) the Works will be performed with the highest regard for safety and protection
of the environment and so that the Facility is capable of being operated and
utilised in accordance with all Applicable Laws and the Contract;
(d) the Works will be fit for their intended purpose as described in, or reasonably
inferable from, the Contract;
(e) the Works utilise proven technology, being a technology that has operated
commercially at other coal fired power stations of similar net output capacity
and which, as of the date of the Contract, is capable of being insured on a
reasonable commercial basis; and
30 INDEMNITY
30.1. The Contractor shall indemnify and hold harmless Owner, the Engineer-in-Charge,
their officers, advisors, representatives, agents, personnel and employees from and
against all actions, suits, proceedings, claims, damages, losses, expenses and
demands of every nature and description, by reasons of any breach of the provisions
of the Contract by the Contractor or any act or omissions of the Contractor, its
representative or its employees, agents, and sub-contractors in the execution of the
ISSUE
R0
30.2. These indemnification obligations shall include but not be limited to claims,
damages, losses, damage proceedings, charges and expenses which are attributable
to:
(c) Loss, damage or costs arising from the carriage of Goods and Materials and/or
ownership or chartering of marine vessels by the Contractor, or Subcontractor
of any tier.
The Contractor shall also indemnify and hold harmless Owner and TCE from and against all
claims and proceedings on account of infringements of patents rights, design, trademark, etc.,
as detailed out in Clause 28.
30.3. All sums payable by way of compensation under these conditions shall be considered
reasonable compensation payable to Owner with reference to the actual loss or
damage sustained by Owner. The decision of TCE as to compensation claimed shall
be final and binding.
30.4. Notwithstanding anything in the Contract to the contrary, no liabilities owed by the
Contractor to Owner that is covered by insurance obtained by the Contractor or
Owner pursuant to Clause 33 is included in the Contractor's aggregate liability for
the purpose of determining the limit of the Contractor's liability under the Contract.
30.5. Neither Party shall be liable to the other Party for any kind of indirect or
consequential loss or damage including, loss of use, loss of profit, loss of production
or business interruption which is connected with any claim arising under the
Contract.
The Contractor shall take full risk and responsibility for the care of the Works, or any
part thereof, including full risk and responsibility for the care of the Works being
constructed/ installed, or stored off-Site for inclusion in the Works, until the date of
issue of the Completion Certificate, when risk and responsibility shall pass to Owner.
31 LIMITATION OF LIABILITY
31.1 The aggregate total liability of the Contractor to Owner under the Contract shall not
exceed the total Contract Price, except that this Clause 31 shall not limit the liability
of the Contractor for following:
ISSUE
R0
(b) In the event of fraud, willful misconduct or illegal or unlawful acts, or gross
negligence of the Contractor or any person acting on behalf of the Contractor;
or
(c) In the event of acts or omissions of the Contractor which are contrary to the
most elementary rules of diligence which a conscientious Contractor would
have followed in similar circumstances; or
(d) In the event of any claim or loss or damage arising out of infringement of
Intellectual Property; or
(e) For any damage to any third party, including death or injury of any third
party caused by the Contractor or any person or firm acting on behalf of the
Contractor in executing the Works.
31.2 Neither Party shall be liable to the other Party for any kind of indirect or
consequential loss or damage including, loss of use, loss of profit, loss of
production or business interruption which is connected with any claim arising under
the Contract.
32 TERMINATION
Owner shall, in addition to any other right enabling it to terminate the Contract, have
the right to terminate the Contract at any time by giving prior written notice of at least
14 (fourteen) days to the Contractor. Such termination shall be without prejudice to
the rights of the Parties that have accrued on or before the date of termination of the
Contract.
The Contract may be terminated by Owner, at its sole and absolute discretion, upon
the occurrence of any of the following events/acts committed by the Contractor (each
a “Contractor's Event of Default”) by issuing a notice to the Contractor, stating the
intention of Owner to terminate the Contract:
(a) fails to complete Mobilisation within the Time for Mobilisation under Clause
9.3;
(c) abandons or repudiates the Contract or suspends the execution of the Works
during the subsistence of any Dispute under the Contract;
ISSUE
R0
(e) the Contract Price is reduced to the maximum extent specified in Clause 13.2,
yet the delay in respect of which the reduction was made continues to subsist;
(f) a petition for the winding up of the Contractor has been admitted and a
liquidator or provisional liquidator has been appointed or an order of
bankruptcy or an order for the winding up or dissolution of the Contractor has
been made by a Court of competent jurisdiction, except voluntary change in
partnership/ constitution of Contractor’s organisation (if a partnership/
Company) or liquidation for the purpose of amalgamation or reconstruction
subject to Owner’s acceptance to continue the Contract with the re-
constituted firm/ company.
(i) gives any warranty or makes any representation under the Contract which is
found to be false or misleading;
(k) fails to obtain and maintain insurance in accordance with its obligations
under the Contract; or
32.3. If the Contractor fails to remedy or rectify the default stated in the notice issued by
Owner under Clause 32.2 within 30 (thirty) days of receipt of such notice, Owner
shall be entitled to terminate the Contract by issuing a termination notice and may
prevent the Contractor from entering the Site (but without thereby releasing the
Contractor from any of its obligations or liabilities under the Contract, or affecting the
rights and powers conferred on Owner under the Contract up to the date of
termination). However, in case of events specified in Clause 32.2 (c) and (f), Owner
shall be entitled to immediately terminate the Contract without giving any notice to
the Contractor.
ISSUE
R0
(a) Owner may complete the Works and/or arrange for other entities to do so at the
risk and Cost of the Contractor. Owner and its entities may then use the access
roads, the Contractor's Documents and all other facilities made by or on behalf
of the Contractor;
(b) Call upon the whole or such portion of the Contract Performance Bank
Guarantee amount as Owner may consider fit;
(c) Recover from the Contractor the cost of carrying out the balance Works in
excess of the sum which the Contractor would have been paid according to the
Final Bill, if the Works had been carried out and completed by the Contractor
under the terms of the Contract. The amount to be recovered may be deducted
by Owner from any amount due to the Contractor under the Contract. Any
amount outstanding to Owner under this Clause 32.4.1(c) shall be recovered
from the Contractor as a debt due;
(d) Enter upon the Site and debar the Contractor from entering the Site. Further:
Owner may, to the exclusion of any right of the Contractor, take over and use,
without payment to the Contractor, any Contractor’s Equipment, materials,
goods, machinery or other items which are on the Site in connection with the
Works for any reasonable period as Owner considers necessary for the
performance and completion of the Works.
32.4.2 Upon termination of the Contract under Clause 32.3, the Contractor must either
immediately or upon any date as is specified in the notice of termination:
(a) cease all further work, except for any work Owner may specify in the notice
of termination;
(c) deliver to Owner the parts of the Works performed by the Contractor up to
the date of termination;
(d) to the extent legally possible assign or novate to Owner all right, title and
benefit of the Contractor to the Works as at the date of termination, and, as
may be required by Owner, in any subcontracts between the Contractor and
its Subcontractors;
ISSUE
R0
Should the Contractor fail to comply with the provisions of sub-Clause (e) above,
Owner shall have the right, at the sole risk and Cost of the Contractor, to clear the
Site of all rubbish, scaffolding, surplus materials, Contractor’s Equipment,
machinery, dismantle and remove the Contractor’s Site offices and other Temporary
Works and store, sell, dispose of and/or otherwise deal with any of the above and the
Contractor shall forthwith on demand pay Owner the costs and expense incurred by
Owner in this regard with an additional amount equivalent to 15% (fifteen percent) of
such costs and expenses to cover Owner’s overheads. Owner shall have the right to
recover such amounts from: (i) the proceeds of any sale of disposal of the
Contractor’s Equipment, machinery, surplus materials, Temporary Works or other
items removed from the Site; and (ii) any amounts due to the Contractor under the
Contract.
Nothing contained in this Clause or otherwise in the Contract shall constitute Owner
as a trustee or bailee for or in respect of any of the Contractor’s Equipment, surplus
materials, machinery or other items or things removed, cleared, demolished or
dismantled as mentioned above and Owner shall not be bound by any duty of care in
respect thereof.
32.4.3 Notwithstanding anything contained in Clause 32.4.2 above, upon termination of the
Contract, Owner may require the Contractor to:
(b) take such steps as are considered necessary by TCE for properly protecting
and securing the Works already completed by the Contractor.
32.5.1 If the Contract is terminated under Clause 27.7 or 32.1, the Contractor is entitled to be
paid :
(a) the Contract Price attributable to the Works performed as at the date of
termination, or in the case of a termination under Clause 27.7, the
commencement of the relevant event of Force Majeure; and
(b) the costs, if any, necessarily incurred in performing the work (if any)
specified in the notice of termination issued by Owner under Clause 32.1 or
as instructed by Owner pursuant to Clause 32.4.3; and
(c) if the Contract is terminated in accordance with Clause 32.1, additionally (but
without duplication):
ISSUE
R0
less the aggregate of all previous payments allocated to the Works. Any sums
due to Owner from the Contractor accruing prior to the date of termination or
the commencement of the relevant event of Force Majeure (as the case may
be) will be deducted from the amount to be paid to the Contractor under the
Contract. If, as a result of any such deductions, there is a negative amount
payable to the Contractor, then the Contractor must pay an amount equal to
that negative sum to Owner within 15 (fifteen) days of Owner raising an
invoice for that amount.
32.5.2 If the Contract is terminated under Clause 32.3, Owner will not be bound to make any
further payment to the Contractor until the full and final cost of completion of the
Works by Owner or other contractors and all damage, loss or expense suffered or
incurred by Owner as a result of the termination of the Contract have been
ascertained.
32.5.3 Upon all cost, damages, loss and/or expense being ascertained under Clause 32.5.2,
TCE must issue a certificate stating the total amount of the cost of completing the
Works and any damage, loss or expense suffered or incurred by Owner as a result of
the termination of the Contract.
32.5.4 If the Contract Price attributable to the Works performed as at the date of termination
less the aggregate of: (a) all previous payments allocated to the Works which have
been paid to the Contractor; and (b) the amount stated in the certificate under Clause
32.5.3,
(a) is a positive amount payable to the Contractor, then Owner must pay such
amount to the Contractor within 15(fifteen) Business Days of the issuance of
the certificate pursuant to Clause 32.5.3; or
(b) is a negative amount payable to the Contractor, then an amount equal to that
negative sum will be a debt due and payable to Owner by the Contractor and
the Contractor must pay such amount to Owner within 15 (fifteen) days of
Owner raising an invoice for that amount.
ISSUE
R0
33 INSURANCE
33.1. Owner shall at its own Cost, take out and maintain in effect, or cause to be taken out
and maintained in effect, during the execution of the Works, a comprehensive
Erection All Risks Policy (“Owner's Insurance”).
33.2. Without prejudice to Clause 33.1, the Contractor shall be required to take out and
maintain at all times during the subsistence of this Contract, adequate insurance
coverage in respect of:
(b) all Contractor's Equipment brought on to the Site by the Contractor or its
Subcontractors for use in connection with the Works, to the extent of their
full value against all loss or damage from whatever cause arising; and
(c) third party liability for physical loss of or damage to any third party property
or injury to or death of any third party which may arise out of or in
connection with the execution of the Works at the Site by the Contractor or
Owner,
(collectively “Contractor's Insurance”).
33.3. Owner's Insurance and the Contractor's Insurance shall each be composite policies in
the joint names of the Parties, for their respective rights and interests. The terms of
Owner's Insurance and the Contractor's Insurance shall entitle the respective Parties to
maintain the policies in force after termination of the Contract.
33.4. Either Party shall, at the request of the other Party, produce within 7 (seven) days of
request, such evidence as the other may reasonably require and as is obtainable from
insurers that Owner's Insurance or the Contractor's Insurance (as relevant) have been
effected, which evidence may include sight of the insurance policies and confirmation
of the payment of all premiums to keep the policies in force.
If either Party fails upon request to produce to the other satisfactory evidence in
accordance with this Clause 33.4 that there is in force any of Owner's Insurance or the
Contractor's Insurance (as relevant), the other Party may effect and keep in force any
such insurance and the Party failing to evidence insurance shall pay to the other all
reasonable costs incurred by the other for such purpose.
33.5. Each Party shall ensure that it and its personnel, Subcontractors, servants and agents
at all times:
ISSUE
R0
(a) Comply with the terms and conditions of Owner's Insurance or the
Contractor's Insurance, as relevant;
(b) Comply with the procedures for claims notification and administration there
under; and
(c) Do nothing nor omit to do anything which might entitle any insurer to refuse
to pay any claim under, or which might otherwise prejudice any of Owner's
Insurance or the Contractor's Insurance.
33.6. Owner's Insurance as well as the Contractor's Insurance, shall wherever possible,
provide for 30 (thirty) days written notice of any cancellation, non-renewal or
material modification of any such policy to be given by the insurers to the insured
persons. Further, Owner's Insurance and the Contractor's Insurance shall contain a
clause to the effect that the insurers have agreed to waive all rights of subrogation
against the persons assured (including all beneficiaries thereof).
33.7. Regardless of the extent of settlement of claims for insurance proceeds under Owner's
Insurance or under the Contractor's Insurance or the time taken for settlement of such
claims, the Contractor shall promptly make good any loss or damage for which it is
responsible under the terms of this Contract. The Contractor shall be reimbursed to
the extent that any insurance proceeds are received and payable to the Contractor.
34.1 The Contract shall be governed by and construed in accordance with the laws of India
and the courts at Guwahati, Assam shall have exclusive jurisdiction over all Disputes
arising under or in connection with the Contract.
35.1 Claims
35.1.1. If the Contractor intends to claim any additional payment on the occurrence of any
event which entitles the Contractor to claim such additional payment, the Contractor
shall give notice to TCE as soon as possible and in any event within 10 (ten) days of
the Contractor becoming aware of such event.
35.1.2. The Contractor shall keep such contemporary records as may be necessary to
substantiate any claim. Without admitting Owner’s liability, TCE may on receipt of a
notice pursuant to Clause 35.1.1 above, inspect such records and may instruct the
Contractor to produce and maintain further records. The Contractor shall permit TCE
to inspect all such records and shall (if instructed) submit copies to TCE.
35.1.3. Within 30 (thirty) days of issuing a notice pursuant to Clause 35.1.1, the Contractor
ISSUE
R0
shall send to TCE an account, giving detailed particulars of the amount and basis of
the claim.
35.1.4. If the Contractor fails to comply with this Clause 35.1, the Contractor shall not be
entitled to claim any additional payment.
35.1.5. Notwithstanding anything to the contrary in this Contract, Owner shall not be liable
for any claim arising out of or in connection with the Contract or the execution of the
Works, unless the Contractor shall have given notice of such claim within 60 (sixty)
days from the date of issuance of the Completion Certificate.
35.1.6. The Contractor shall be entitled to additional costs as TCE considers due, after taking
Approval from Owner. If the particulars supplied are insufficient to substantiate the
whole of the claim, the Contractor shall be entitled to payment for such part of the
claim as has been substantiated by TCE and agreed to by Owner.
35.2.1. If any disagreement arises out of or in connection with the validity, application or
interpretation of the Contract (the “Dispute”), the Parties shall endeavour in good
faith to resolve the Dispute through negotiation within 7 (seven) days of a written
notice setting out the nature of such Dispute.
35.2.2. In the event that any Dispute is unable to be resolved between the Parties pursuant to
Clause 35.2.1 within 21 (twenty-one) days of receipt of the notice under Clause
35.2.1, then such Dispute shall be referred to arbitration.
35.2.3. The arbitration will be conducted as per the Arbitration Act. The arbitral tribunal shall
comprise of a sole arbitrator whom shall be appointed by Owner. The place of
arbitration for any Disputes and Related Disputes shall be Guwahati, Assam. The
language to be used in the arbitral proceedings shall be English. The arbitral award
shall be final and binding upon both the Parties.
35.2.4. Responsibility of payment for all costs of arbitration, excepting counsel fees, shall be
as per the arbitration award.
35.2.5. While any Dispute under this Contract is pending; and except where this Contract has
been terminated in accordance with the terms of this Contract, the Parties shall
continue to perform all of their respective obligations under this Contract without
prejudice to the final determination in accordance with the provisions under this
Clause 35.
35.2.6. Where, in Owner's absolute discretion, it is beneficial for the completion of the
Facility for any Dispute between Owner and the Contractor, in respect of which an
arbitration notice has been given, to be resolved in the same arbitration proceedings
as a dispute between Owner and any other party or parties engaged in relation to the
ISSUE
R0
(a) if a notice to concur in the appointment of an arbitrator has been served in the
Related Dispute, the Contractor hereby agrees that, at Owner's sole option,
the Dispute between Owner and the Contractor shall be referred to the
arbitrator appointed or to be appointed in respect of the Related Dispute and
be determined at the same time as such Related Dispute;
(b) where an arbitrator has already been appointed in connection with the Related
Dispute, the Contractor hereby agrees that, at Owner's sole option, the
Dispute between Owner and the Contractor shall be referred to and be
determined by the arbitrator so appointed contemporaneously with the
Related Dispute.
ISSUE
R0
36 MISCELLANEOUS
(a) No director, officer or other employee of Owner (or TCE) shall in any
manner be personally bound or liable to the Contractor for acts, commissions
or obligations of Owner under the Contract or otherwise or be personally
answerable to the Contractor for any default or omission in the performance
of any act(s), deed(s) or things to be observed and/or performed by Owner
under the Contract.
(b) The Contractor shall not be entitled to any increase in the rate(s) mentioned
in the Price Schedule or to any other payment by reason of any
representation, explanation or assurance given or alleged to have been given
by TCE or any employee, representative, consultant or agent of Owner.
(d) The Contractor shall not, under any circumstances, pay or advance to any
officer(s), servant(s) or agent(s) of Owner any money on any account without
the prior Approval of Owner and any payment without such Approval shall
be entirely at the risk of the Contractor and Owner shall have no liability in
this regard.
(e) Any money paid to any director, attorney, agent, officer or employee of the
Contractor and any receipt, settlement, acknowledgement of liability or other
arrangement, agreement or document whatsoever signed by any such
director, attorney, agent, officer or employee of the Contractor or erstwhile
director, attorney, agent, officer or employee (without notice of his cessation
of interest) or by any person held to be a director, attorney, agent, officer or
employee of the Contractor authorised to act on behalf of the Contractor
shall, as between the Contractor and Owner, be binding upon the Contractor
and shall constitute a full release and discharge to Owner and/or a valid
settlement, acknowledgement of obligation of the Contractor, as the case may
be.
(f) Any money paid to or dealing had with any partner or member of the
Contractor (if a firm or consortium) and any receipt, settlement,
acknowledgement of liability or other arrangement, agreement or document
whatsoever signed by any one of the partners of the firm or members of the
consortium or erstwhile partner of the firm or member of the consortium
(without notice of the cessation of his interest) or with any person held to be a
partner of the firm or member of the consortium shall be binding on the
ISSUE
R0
Contractor and shall constitute a full release and discharge to Owner and/or a
valid settlement, acknowledgement of obligation of the Contractor, as the
case may be, provided that Owner shall always have the right to call upon all
or any of the partners/members of the Contractor’s firm/consortium to sign
any receipt, settlement, acknowledgement or other document and all or any of
the partners of the firm or members of the consortium shall, when called upon
to do so by Owner, immediately sign the receipt, settlement,
acknowledgement or other document required to be so signed.
36.2 Assignment
The Contractor shall not assign, novate or charge the whole or any part of the
Contract or create any encumbrance over the Facility, without the prior written
consent of Owner. In the event of an assignment or novation by the Contractor, any
stamp duty and all costs and expenses payable in respect of such documents, required
to be signed by Owner, shall be to the account of the Contractor. Owner shall be
entitled to assign and/or transfer its rights and obligations under the Contract to any
party, without requirement of any further consent of the Contractor.
36.3 Partnership
36.4 Severability
The Contract contains all covenants stipulations and provisions agreed by the Parties,
and constitutes the entire Contract between the Parties hereto and supersedes any oral
or written representations, understandings, proposals, or communications heretofore
entered into by or on account of the Parties and may not be changed, modified, or
amended except in writing and signed by the Parties hereto.
ISSUE
R0
In item rate contract where the quoted rates for the items exceed 50% (fifty percent) of the
Owner’s estimated rates, such items will be considered as Abnormally High Rates Items
(AHR) and payment of AHR items beyond the contracted quantities shall be made at the
lower of the following rates:
(a) Rates as per the Schedule of Rates, quoted by the Contractor.
(i) Based on rates of machine and labour as available from the Contract
(which includes Contractor’s supervision, profit, overheads and other
expenses).
(ii) In case rates are not available in the Contract, rates will be calculated
based on prevailing market rates of machine/equipments, material
and labour plus 15% (fifteen percent) to cover Contractor’s
supervision profit, overhead & other expenses.
36.8 Corrupt and Fraudulent Practices
36.8.1 Bidders are required to furnish the complete and correct information/ documents
required for evaluation of their bids. If the information/ documents forming basis of
evaluation is found to be false/ fake/ forged, the same shall be considered adequate
ground for rejection of the bids and forfeiture of earnest money deposit.
36.8.2 Owner requires that the Contractor observes the highest standard of ethics during the
execution of Contract. In pursuance of this policy, Owner defines, for the purposes of
this provision, the terms set forth below as follows:
ISSUE
R0
36.8.4 The Contractor is required to execute the “Integrity Pact” attached in the Bid
Document as a condition precedent to execution of the Contract.
36.8.5 In case, the information/ document furnished by the Contractor forming basis of
evaluation of its Bid is found to be false / fake/ forged after the award of the Contract,
Owner shall have the right to terminate the Contract and get the remaining Works
executed by a third party at the risk & Cost of the Contractor and without any
prejudice to other rights available to Owner under the Contract such as forfeiture of
the Contract Performance Bank Guarantee, withholding of payment etc.
36.8.6 In case, this issue of submission of false/fake documents comes to the notice after
execution of the Works, Owner shall have full right to forfeit any amount due to the
Contractor along with forfeiture of the Contract Performance Bank Guarantee
furnished by the Contractor.
36.8.7 Further, any Contractor which is found guilty of any Corrupt or Fraudulent Practice
or submission of false/fake /forged documents, shall be put on the negative/ holiday
list of Owner debarring them from future business with Owner.
The Integrity Pact forming a part of the Bidding Document, duly signed by the
authorized person(s) of Owner and the Contractor, will form part of the Contract. If the
Contract has been terminated according to provisions of the Integrity Pact, or, if
ISSUE
R0
(a) It is expressly understood that Govt. of India is not a party to this Contract
and has no liability, obligations or rights hereunder. It is expressly understood
that Owner is an independent legal entity with power and authority to enter
into the Contract solely on its behalf under the Applicable Laws and general
principles of contract law.
(b) The Contractor expressly agrees and acknowledges and understands that
Owner and TCE are not an agent, representative or delegatee of Government
of India.
(a) The Running Bills will be prepared by the Contractor on their personal
computers as per the standard formats and codification scheme proposed by
Owner. The Contractor will be provided with data entry software to capture
the relevant billing data for subsequent processing. The Contractor will
submit these data to Owner in an electronic media along with the hard copy
of the bill, necessary enclosures and documents. The Contractor will also
ensure the correctness and consistency of data so entered with the hard copy
of the bill submitted for payment.
(b) Owner will utilize this data for processing and verification of the Running
Bills of the Contractor.
Where the Contractor is a consortium, the lead member of the consortium shall
represent the Contractor in all dealings with Owner and shall do all acts, deeds,
matters and things required to be done by the Contractor under the Contract,
including (but not limited to) exchange of correspondence, raising invoices, drawings,
documents and receiving payments.
(a) All dealings had with and/or all acts, deeds, matters and things and things
done by or payments made to and invoices/documents drawn and/or
negotiated by the lead member shall be binding upon the Contractor and each
member of the consortium, and in so far as Owner shall require a discharge in
respect of any dealing had or act, deed, matter or thing done or payment made
as aforesaid, the same shall constitute a valid discharge to Owner.
ISSUE
R0
(b) Each and every member of the consortium shall be jointly and separately
liable to Owner for and in respect of all liabilities obligations of the
Contractor under the Contract.
The constitution of the Consortium or the relative distribution of the Work(s) and/or
activities amongst the consortium members as approved by Owner shall not be altered
or assigned, as the case may be except with the prior written consent of Owner and
any contrary alteration or re-assignment shall be deemed to be an unauthorized
assignment of the Contract with attendant liabilities including termination of the
Contract.
(a) For all equipment pedestals, pipe racks, other foundation and R.C.C.
Structures, work done up to 300 mm level above finished grade level will be
taken as work in foundations and work above this level will be treated as
work in superstructures and payments would be made accordingly.
(b) For buildings only, all works up to plinth level corresponding to finished
floor level shall be treated as `work in foundation' and all works above the
finished floor level shall be treated as "work in superstructure".
(c) Irrespective of what has been stated above, all pavements, R.C.C. retaining
wall, all pipe sleepers and any similar item would be taken as work done in
foundations irrespective of locations, nomenclature and levels given
anywhere.
(d) Where not specifically pointed out all works in cellars/ sumps, tank pads,
cable trenches, or such similar item would be taken as work in foundation.
The Contractor shall obtain licence from the relevant Authorities for undertaking
blasting work as well as for obtaining and storing the explosive as per Explosive
Rules 2008 (as made under the Explosives Act, 1884), as amended from time to time.
ISSUE
R0
The Contractor shall purchase the explosives, fuses, detonators etc. only from a
licensed dealer and shall be responsible for the safe custody and proper accounting of
the explosive materials. TCE and its authorized representatives shall have access to
check the Contractor's store of explosives and its accounts. In case where the
explosives are required to be transported and stored at Site, relevant clauses of the
Explosives Rules 2008 as amended subsequently shall apply. The Contractor shall be
responsible for any accident to workman, public or property, due to blasting
operations.
Contractor shall arrange for the import of all materials required for permanent
incorporation in the Works as well as construction equipment as per the guidelines
laid down by the Government of India. Owner shall not provide import licence.
36.17 Retired Government or Company Directors
The Contractor agrees and acknowledges that that access to the Site and access routes
thereto, has been granted to the Contractor on a non-exclusive basis, and that Owner,
may at its sole discretion, grant access thereto, to other Persons (“Other
Contractors”) to undertake thereon, any works other than those contemplated under
the Contract. Further, the Contractor shall at all times undertake its works in such
manner, as to not cause minimal disturbance to the Other Contractors, in the
performance of the works allocated to such Other Contractors.3
36.19 Survival
The termination of the Contract shall not relieve the Contractor or Owner of any
obligations hereunder which expressly or by implication survives termination.
Further, except as otherwise provided in any provision of the Contract expressly
limiting the liability of either Party, the termination of the Contract shall not relieve
either Party of any obligations or liabilities for loss or damage to the other Party
arising out of or caused by acts or omission of such Party prior to the effectiveness of
such termination or arising out of such termination.
ISSUE
R0
APPENDIX 1
FORM OF CONTRACT PERFORMANCE BANK GUARANTEE
IN FAVOUR OF:
WHEREAS
A. Owner has entered into an Engineering, Procurement and Construction Contract dated
[............................■] (the "Contract") with [.............................................insert name
of Contractor], a company incorporated under the Indian Companies Act, 1956 and
having its registered office at [............................................................■] (the
"Contractor", which expression shall, unless it be repugnant to the context or
meaning thereof, include its successors-in-title and permitted assigns), for the Project.
C. At the request of Owner and for sufficient consideration, the Guarantor has agreed to
provide an unconditional, irrevocable and on-demand bank guarantee, for the due and
punctual performance/discharge by the Contractor of its obligations under the
Contract during the Contract Validity Period.
1. Capitalised terms used herein but not defined shall have the meaning ascribed to them
in the Contract.
ISSUE
R0
2. The Guarantor hereby irrevocably and unconditionally guarantees and secures (as
primary obligor and not merely as guarantor) to Owner the payment in full of all
amounts at any time that may be due, owing or payable to Owner from the Contractor
for the failure of the Contractor to duly and punctually perform all of its obligations
under the Contract (the "Guarantee"), without any demur, reservation, protest or
recourse, immediately on receipt of a demand from Owner.
The Guarantor agrees that the value of the Guarantee shall at all times be maintained
at the amount of Rs. [................................................insert amount] (the "Guaranteed
Amount").
The Guarantor further agrees that this Guarantee does not limit the number of claims
that may be made by Owner against the Guarantor. Upon a payment being made
under this Guarantee, the amount of the Guarantee shall automatically be replenished
to the full Guaranteed Amount.
Any payment made hereunder shall be made free and clear of and without deduction
for, or on account of, any present or future Taxes, deductions or withholdings of any
nature whatsoever and by whomsoever imposed, and where any withholding on a
payment is required by any Applicable Law, the Guarantor shall comply with such
withholding obligations and shall pay such additional amount in respect of such
payment such that Owner receives the full amount due hereunder as if no such
withholding had occurred.
3. The Guarantor shall, pay to Owner sums not exceeding the Guaranteed Amount,
within 5 (five) Business Days of receipt of a written demand from Owner stating that
the Contractor has failed to meet its performance obligations under the Contract. The
Guarantor shall not be required to go into the veracity of any breach or failure on the
part of the Contractor or validity of demand so made by Owner and shall pay the
amount specified in the demand notwithstanding any direction to the contrary given
or any dispute whatsoever raised by the Contractor or any other Person. The
Guarantor's obligations hereunder shall subsist until all such demands are duly met
and discharged in accordance with the provisions hereof.
4. The obligations of the Guarantor herein are absolute and unconditional, irrespective
of the value, genuineness, validity, regularity or enforceability of the Contract or the
insolvency, bankruptcy, reorganization, dissolution or liquidation of the Contractor or
any change in ownership of the Contractor or any purported assignment by the
Contractor or any other circumstance whatsoever which might otherwise constitute a
discharge or defence of a guarantor or a surety.
Further, this Guarantee is in no way conditional upon any requirement that Owner
first attempt to procure the Guaranteed Amount from the Contractor, or any other
ISSUE
R0
Person, or resort to any other means of obtaining payment of the Guaranteed Amount,
prior to make any recourse to this Guarantee.
5. In order to give effect to this Guarantee, Owner shall be entitled to treat the Guarantor
as the principal debtor. The obligations of the Guarantor under this Guarantee shall
not be affected by any act, omission, matter or thing which, but for this provision,
would reduce, release or prejudice the Guarantor from any of the Guaranteed Amount
or prejudice or diminish the Guaranteed Amount in whole or in part, including
(whether or not known to it, or Owner):
(a) any time or waiver granted to, or composition with, the Contractor or any
other Person;
(b) any incapacity or lack of powers, Owner or legal personality of or
dissolutions, or insolvency, or bankruptcy, or change in the status of the
Contractor or any other Person;
(c) any variation of the Contract so that references to the Contract in this
Guarantee shall include each variation;
(e) the partial or entire release of any Guarantor or other Person primarily or
secondarily liable or responsible for the performance, payment or observance
of any of the Contractor's obligations during the Construction Period; or by
any extension, waiver, or amendment whatsoever which may release a
guarantor or Guarantor (other than performance or indefeasible payment of a
Guaranteed Amount); or
(f) any part performance of the Contract by the Contractor or by any failure by
Owner to timely pay or perform any of its obligations under the Contract.
6. If, and to the extent that, for any reason the Contractor enters or threatens to enter into
any proceedings in bankruptcy or reorganization or otherwise, or if, for any other
reason whatsoever, the performance or payment by the Contractor of the Guaranteed
Amount becomes or may reasonably be expected to become impossible, then the
Guaranteed Amount shall be promptly paid by the Guarantor to Owner on demand.
7. So long as any sum remains owing by the Contractor to Owner, the Guarantor shall
not exercise any right of subrogation or any other rights of a guarantor or enforce any
guarantee or other right or claim against the Contractor (whether in respect of its
liability under this Guarantee or otherwise) or claim in the insolvency or liquidation
of the Contractor or any such other Person in competition with Owner. If the
ISSUE
R0
Guarantor receives any payment or benefit in breach of this Clause 7, it shall hold the
same upon trust for Owner.
8. This Guarantee shall remain in full force and effect from the date hereof until the end
of the Contract Validity Period i.e., up to midnight of {.................... insert date} plus
additional 90 days to enable claims to be made i.e., up to midnight of {....................
insert date}, unless discharged/ released earlier by Owner in accordance with the
provisions of the Contract. No claim made after such date shall be valid against the
Guarantor.
Notwithstanding the foregoing, this Guarantee shall continue in effect until the sums
payable under this Guarantee have been indefeasibly paid in full and the Guarantor
receives written notice thereof from Owner (such notice to be issued promptly upon
such occurrence).
(a) it has the power to execute, deliver and perform the terms and provisions of
this Guarantee and has taken all necessary action to authorize the execution,
delivery and performance by it of this Guarantee;
(b) the Guarantor has duly executed and delivered this Guarantee, and this
Guarantee constitutes its legal, valid and binding obligation enforceable in
accordance with its terms except as the enforceability thereof may be limited
by applicable bankruptcy, insolvency, moratorium or other similar laws
affecting the enforcement of creditors' rights generally and by general
equitable principles;
10. This Guarantee is a continuing one and all liabilities to which it applies or may apply
under the terms hereof shall be conclusively presumed to have been created in
reliance hereon. No failure or delay on the part of Owner in exercising any right,
ISSUE
R0
power or privilege hereunder and no course of dealing between Owner and the
Guarantor, or the Contractor, shall operate as a waiver thereof, nor shall any single or
partial exercise of any right, power or privilege hereunder preclude any other or
further exercise thereof or the exercise of any other right, power or privilege.
11. The rights, powers and remedies expressly provided in this Guarantee are cumulative
and not exclusive of any rights, powers or remedies which Owner would otherwise
have. No notice to or demand on the Guarantor in any case shall entitle the Guarantor
to any other further notice or demand in similar or other circumstances or constitute a
waiver of the rights of Owner to any other or further action in any circumstances
without notice or demand.
12. If any one or more of the provisions contained in this Guarantee are or become
invalid, illegal or unenforceable in any respect, the validity, legality and
enforceability of the remaining provisions shall not in any way be affected or
impaired thereby, and the Guarantor shall enter into good faith negotiations with
Owner to replace the invalid, illegal or unenforceable provision.
13. The Guarantor hereby agrees to execute and deliver all such instruments and take all
such actions as may be necessary to make effective fully the purposes of this
Guarantee.
14. This Guarantee may be executed in one or more duplicate counterparts, and when
executed and delivered by the Guarantor and Owner shall constitute a single binding
agreement.
15. Any notice, request or other communication to be given or made under this Guarantee
shall be in writing addressed to the Guarantor at the location set opposite its signature
hereto and in the manner as set out in respect of notices under the Contract.
16. This Guarantee shall be governed by, and construed in accordance with, the laws of
India. The Guarantor irrevocably agrees that any legal action, suit or proceeding
arising out of or relating to this Guarantee may be brought in the courts in Guwahati,
Assam.
17. Owner may assign or transfer all or any part of its interest herein to any other person
with prior notification to the Guarantor. The Guarantor may not assign or transfer any
of its rights or obligations under this Guarantee.
IN WITNESS WHEREOF the Guarantor has set its hands hereunto on the day, month and
year first hereinabove written.
ISSUE
R0
APPENDIX 2
FORM OF MOBILIZATION ADVANCE GUARANTEE
IN FAVOUR OF
WHEREAS
C. At the request of the Contractor and for sufficient consideration, the Guarantor has
agreed to issue this guarantee in favour of Owner.
1. Capitalised terms used herein but not defined shall have the meaning ascribed to them
in the Contract.
2. The Guarantor shall upon a written demand from Owner informing the Guarantor that
the Mobilization Advance made to the Contractor has not been adequately adjusted,
ISSUE
R0
pay to Owner, within 5 (five) days of receipt of such written demand from Owner,
without further proof or conditions and without contest, recourse, demur or protest
and without any enquiry to Owner or the Contractor, forthwith and in full amount,
without any deductions or set off or counter claims whatsoever, the sum claimed by
Owner in such demand not exceeding an amount equivalent to the Guaranteed
Amount. The Guarantor will pay the amount specified in the demand notwithstanding
any direction to the contrary given or any dispute raised by the Contractor or any
other person.
The Guarantor agrees that this Mobilization Advance Guarantee does not limit the
number of claims that may be made by Owner against the Guarantor provided that
such claims taken together shall not exceed the Guaranteed Amount.
Any payment made hereunder shall be made free and clear of and without deduction
for, or on account of, any present or future Taxes, deductions or withholdings of any
nature whatsoever and by whomsoever imposed, and where any withholding on a
payment is required by any Applicable Law, the Guarantor shall comply with such
withholding obligations and shall pay such additional amount in respect of such
payment such that Owner receives the full amount due hereunder as if no such
withholding had occurred.
4. The obligations of the Guarantor herein are absolute and unconditional, irrespective
of the value, genuineness, validity, regularity or enforceability of the Contract or the
insolvency, bankruptcy, reorganisation, dissolution or liquidation of the Contractor or
any change in ownership of the Contractor or any purported assignment by the
Contractor or any other circumstance whatsoever which might otherwise constitute a
discharge or defence of a guarantor or a surety.
5. The Guarantor shall not be required to go into the veracity of any breach or failure on
the part of the Contractor or validity of demand so made by Owner and shall pay the
amount specified in the demand notwithstanding any direction to the contrary given
or any dispute whatsoever raised by the Contractor or any other Person. The
Guarantor's obligations hereunder shall subsist until all such demands are duly met
and discharged in accordance with the provisions hereof.
6. The Guarantor hereby agrees that its liability under this Mobilization Advance
Guarantee shall not be discharged by virtue of any agreement between the Contractor
ISSUE
R0
7. The Guarantor's obligations under this Mobilization Advance Guarantee for the
Guaranteed Amount is primary, independent and absolute and not by way of surety
only.
8. The obligations of the Guarantor under this Mobilization Advance Guarantee shall
not be affected by any act, omission, matter or thing which, but for this provision,
would prejudice or diminish the Guaranteed Amount in whole or in part, including
(whether or not known to it or Owner):
(a) any time or waiver granted to, or composition with, the Contractor or any
other person;
(b) any incapacity or lack of powers, authority or legal personality of or
dissolutions, or insolvency or bankruptcy, or change in the status of the
Contractor or any other Person;
(c) any variation of the Contract so that references to the Contract in this
Mobilization Advance Guarantee shall include each variation;
(d) any unenforceability, illegality or invalidity of any obligation of any person
under the Contract or any unenforceability, illegality or invalidity of the
obligations of the Guarantor under this Mobilization Advance Guarantee or
the unenforceability, illegality or invalidity of the obligations of any person
under any other document or guarantee, to the extent that each obligation
under this Mobilization Advance Guarantee shall remain in full force as a
separate, continuing and primary obligation, and its obligations be construed
accordingly, as if there were no unenforceability, illegality or invalidity;
(e) any extension, waiver, or amendment whatsoever which may release a
guarantor or the Guarantor (other than performance or indefeasible payment
of a Guaranteed Amount); or
(f) any part performance of the Contract by the Contractor or by any failure by
Owner to timely pay or perform any of its obligations under the Contract.
9. So long as any sum remains owing by the Contractor to Owner, the Guarantor shall
not exercise any right of subrogation or any other rights of a guarantor or enforce any
guarantee or other right or claim against the Contractor (whether in respect of its
liability under this Mobilization Advance Guarantee or otherwise) or claim in the
insolvency or liquidation of the Contractor or any such other person in competition
with Owner. If the Guarantor receives any payment or benefit in breach of this
Clause, it shall hold the same in trust for Owner.
(a) it has the power to execute, deliver and perform the terms and provisions of
this Mobilization Advance Guarantee and has taken all necessary action(s) to
authorize the execution, delivery and performance by it of this Mobilization
Advance Guarantee;
ISSUE
R0
(b) the Guarantor has duly executed and delivered this Mobilization Advance
Guarantee, and this Mobilization Advance Guarantee constitutes its legal,
valid and binding obligation enforceable in accordance with its terms except
as the enforceability thereof may be limited by applicable bankruptcy,
insolvency, moratorium or other similar laws affecting the enforcement of
creditors’ rights generally and by general equitable principles;
(e) this Mobilization Advance Guarantee will be enforceable when presented for
payment to a Scheduled Bank (as defined by the Reserve Bank of India Act,
1934) in [...................................................................Insert name of place].
11. This Mobilization Advance Guarantee is a continuing one and all liabilities to which
it applies or may apply under the terms hereof shall be conclusively presumed to have
been created in reliance hereon. No failure or delay on the part of Owner in
exercising any right, power or privilege hereunder and no course of dealing between
Owner and the Guarantor, or the Contractor, shall operate as a waiver thereof, nor
shall any single or partial exercise of any right, power or privilege hereunder preclude
any other or further exercise thereof or the exercise of any other right, power or
privilege.
12. If any one or more of the provisions contained in this Mobilization Advance
Guarantee are or become invalid, illegal or unenforceable in any respect, the validity,
legality and enforceability of the remaining provisions shall not in any way be
affected or impaired thereby, and the Guarantor shall enter into good faith
negotiations with Owner to replace the invalid, illegal or unenforceable provision.
13. The Guarantor hereby agrees to execute and deliver all such instruments and take all
such actions as may be necessary to make effective fully the purposes of this
Mobilization Advance Guarantee.
ISSUE
R0
14. This Mobilization Advance Guarantee may be executed in one or more duplicate
counterparts, and when executed and delivered by the Guarantor and Owner shall
constitute a single binding agreement.
15. Any demand, notice, request or other communication to be given or made under this
Mobilization Advance Guarantee shall be deemed to have been duly given or served:
(a) acknowledges that the lenders of the Owner will review this Mobilization
Advance Guarantee and may require changes thereto as a condition of
granting financing and/or providing political risk insurance; and
17. This Mobilization Advance Guarantee shall be governed by, and construed in
accordance with, the laws of India. The Guarantor irrevocably agrees that any legal
action, suit or proceeding arising out of or relating to this Mobilization Advance
Guarantee may be brought in the courts in Guwahati, Assam.
18. Owner may assign or transfer all or any part of its interest herein together with the
Contract to any other person with prior intimation to the Guarantor. The Guarantor
may not assign or transfer any of its rights or obligations under this Mobilization
Advance Guarantee.
IN WITNESS WHEREOF the Guarantor has set its hands hereunto on the day, month and
year first hereinabove written.
Name:
Designation:
ISSUE
R0
APPENDIX 3
SAFETY CODE
1. GENERAL
1.1 The CONTRACTOR shall adhere to safe construction practices and guard against
hazardous and unsafe working conditions and shall comply with Owner’s safety rules
as set forth herein.
1.2 In addition, the CONTRACTOR shall adhere to and be bound by the "Safety
Practices during Construction" (OISD-GDN-192 and OISD-207) formulated by the
Oil Industry Safety Directorate from time to time. A copy of the existing "Safety
Practices During Construction" as presently formulated by the Oil Industry Safety
Directorate is annexed hereto as Appendix 3.
1.3 In the event of any irreconcilable conflict between the “Safety Practices during
Construction” prescribed by the Oil Industry Safety Directorate and the Safety
provisions set out herein, the "Safety Practices during Construction" established by
the Oil Industry Safety Directorate shall prevail to the extent of the irreconcilable
conflict.
1.4 In this Section any reference to the Facility shall wherever applicable include any
existing plant, unit or installation in or adjacent to which the Site or any part thereof
is located.
2.1 The Contractor shall maintain first aid facilities for its employees and those of its sub-
contractors.
2.2 The Contractor shall make outside arrangements for ambulance service and for the
treatment of industrial injuries. Names of those providing these services shall be
furnished to TCE prior to start of construction, and their telephone numbers shall be
prominently posted in Contractor’s field office.
2.3 All critical industrial injuries shall be reported promptly to TCE, and a copy of
Contractor’s report covering each personal injury requiring the attention of a
physician shall be furnished to Owner.
3. GENERAL RULES
Carrying/Striking of matches, lighters within the Site, smoking within the Site, tank,
farm, or dock limits are strictly prohibited. Violators of the "No Smoking" rules shall
be discharged immediately. Within the operation area, no hot work shall be permitted
without valid gas safety/fire permits. The Contractor shall be held liable and
responsible for all lapses of his subcontractors/employees in this regard.
ISSUE
R0
4. CONTRACTOR'S BARRICADES
4.1 The CONTRACTOR shall erect and maintain barricades required in connection with
his operation to guard or protect:
(i) Excavation
(ii) Hoisting areas
(iii) Areas adjudged hazardous by the Contractor’s or Owner’s inspectors.
(iv) Owner’s existing property liable to damage by Contractor's operations, in the
opinion of TCE.
(v) Railroad unloading spots.
4.2 The Contractor’s employees and those of its sub-contractors shall become acquainted
with Owner’s barricading practices and shall respect the provisions thereof.
4.3 Barricades and hazardous areas adjacent to but not located in normal routes of travel
shall be marked by red flasher lanterns at nights.
5. SCAFFOLDING
5.1 Suitable scaffolding shall be provided for workmen for all works that cannot safely be
done from the ground or from solid construction except such short period work as can
be done safely from ladders. When a ladder is used, an extra person shall be engaged
for holding the ladder and if the ladder is used for carrying materials as well, suitable
footholds and handholds shall be provided on the ladder and the ladder shall be given
an inclination not steeper than 1 in 4 (1 horizontal 4 vertical).
5.2 Scaffolding or staging more than 12' (twelve feet) above the ground floor, swung or
suspended from an overhead support or erected with stationary support shall have a
guard rail properly attached, bolted, braced and otherwise rewinded at least 3' high
above the floor or platform of scaffolding or staging and extending along the entire
length of the outside and ends thereof with only such openings as may be necessary
for the delivery of materials. Such scaffolding or staging shall be so fastened as to
prevent it from swaying from the building or structure.
5.3 Working platforms, gangways and stairways should be so constructed that they
should not sag unduly or unequally and if the height of the platform or the gangway
or the stairway is more than 12' above ground level or floor level, they should be
closely boarded, should have adequate width and should be suitably fastened as
described in Clause 5.2 above.
5.4 Every opening in the floor of a building or in a working platform shall be provided
with suitable fencing or railing whose minimum height shall be 3 feet to prevent the
fall of persons or materials by providing.
5.5 Safe means of access shall be provided to all working platforms and other working
places. Every ladder shall be securely fixed. No portable single ladder shall be over
30' in length while the width between the side rails in rung ladder shall in no case be
ISSUE
R0
less than 11.5" for ladder up to and including 10' in length. For longer ladders this
width would be increased by at least ¼'' for each additional foot of length. Uniform
step spacing shall not exceed 12''. Adequate precautions shall be taken to prevent
danger from electrical equipment. No materials on any site of work shall be so
stacked or placed as to cause danger or inconvenience to any person or public. The
Contractor shall also provide all necessary fencing and lights to protect the workers
and staff from accidents, and shall be bound to bear the expenses of defense of every
suit, action or other proceedings, that may be brought by any person for injury
sustained owing to neglect of the above precautions and to pay damages and costs
which may be awarded in any such suit or action or proceedings to such person, or
which may with the consent of the Contractor be paid to compromise any claim by
any person.
6.1 All trenches 4' (Four feet) or more in depth, shall at all times be supplied with at least
one ladder for each 100' length or fraction thereof.
6.2 The Ladder shall be extended from bottom of the trench to at least 3' 3" above the
surface of the ground. The site of the trenches which is 5' (Five feet)or more in depth
shall be stepped back to give suitable slope, or securely held by timber bracing, so as
to avoid the danger of sides to collapse. Cutting shall be done from top to bottom.
Under no circumstances shall undermining or undercutting be done.
7. DEMOLITION
7.1 Before any demolition work is commenced and also during the process of such works
all roads and open areas adjacent to the Site shall either be closed or suitably
protected.
7.2 No electric cable or apparatus which is liable to be a source of danger over a cable or
apparatus used by the operator shall remain electrically charged.
7.3 All practical steps shall be taken to prevent danger to persons employed, from risk of
fire or explosion or flooding. No floor or other part of the building shall be so
overloaded with debris or material as to render it unsafe.
8. SAFETY EQUIPMENT
8.1 All necessary personal safety equipment as considered adequate by TCE should be
made available for the use to the persons employed on the Site and maintained in a
condition suitable for immediate use, and the Contractor should take adequate steps to
ensure proper use of equipment by those concerned.
8.2 Workers employed on mixing asphaltic materials, cement and lime mortars shall be
provided with protective footwear and protective gloves.
ISSUE
R0
8.3 Those engaged in white washing and mixing or stacking of cement bags or any
materials which are injurious to the eyes shall be provided with protective goggles.
8.4 Those engaged in welding and cutting works shall be provided with protective face
and eye- shields, and gloves, etc.
8.5 Stone breakers shall be provided with protective goggles and protective clothing and
seated at sufficiently safe intervals.
8.6 When workers are employed in sewers and manholes, which are in use, the
Contractor shall ensure that the manhole covers are opened and are ventilated at least
for an hour before the workers are allowed to get into the manholes, and the manholes
so opened shall be cordoned off with suitable railing and provided with warning
signals or boards to prevent accident.
8.7 The Contractor shall not employ men below the age of 18 years and women on the
work of painting or products containing lead in any form. Wherever men above the
age of 18 years are employed on the work of lead painting, the following precautions
should be taken:
(a) No paint containing lead product shall be used except in the form of paste or
readymade paint.
(b) Suitable face masks shall be supplied for use by the workers when paint is
applied in the form of spray or if a surface having lead paint dry rubbed and
scrapped.
(c) Overalls shall be supplied by the Contractor to workmen and adequate
facilities shall be provided to enable the working painters to wash during and
on cessation of Work.
9. RISKY PLACES
When the work is done near any place where there is a risk of drowning, all necessary
safety equipments shall be provided and kept ready for use and all necessary steps
taken for prompt rescue of any person in danger and adequate provision should be
made for prompt first aid treatment of all injuries likely to be sustained during the
course of the work.
Use of hoisting machines and tackle including their attachments, anchorage and
supports shall conform to the following standards or conditions:
ISSUE
R0
(c) Every crane driver or hoisting appliance operator shall be properly qualified
and no person under the age of 21years should be in charge of any hoisting
machine including any scaffolding winch or to give signals to the operator.
(d) In case of every hoisting machine and of every chain, ring, hook, shackle,
swivel and pulley block used in hoisting or lowering or as a means of
suspension, the safe working load shall be ascertained by adequate means.
(e) Every hoisting machine and all gear referred to above shall be plainly marked
with the safe working load and the condition under which it is applicable
shall be clearly indicated. No part of any machine or any gear referred to
above in this paragraph shall be loaded beyond the safe working load except
for the purpose of testing.
(f) In case of departmental machines, the safe working load shall be notified by
TCE. As regards Contractor’s machines, the Contractor shall notify the safe
working load of the machine to TCE, whenever he brings any machinery to
Site of work and get it verified by TCE.
All scaffolds, ladders and other safety devices mentioned or described herein shall be
maintained in safe conditions and no scaffold, ladder or equipment shall be altered or
removed while it is in use. Adequate washing facilities should be provided at or near
the place of work.
These safety provisions should be brought to the notice of all concerned by display on
a notice board at a prominent place at the Site. The person responsible for compliance
of the safety code shall be named therein by the CONTRACTOR.
ISSUE
R0
15. NO EXEMPTION
15.1 Notwithstanding anything provided in this Appendix 3, the Contractor shall be bound
by the provisions of any other Act or rules in force in the Republic of India, with a
view that the provisions hereof be in addition thereto and not in lieu thereof.
15.2 The works throughout including any temporary works shall be carried on in such a
manner as not to interfere in any way whatsoever with the traffic on any roads or
footpaths at the Site or in the vicinity thereof or with any existing works whether the
property of Owner or of a third party.
15.3 The Contractor shall also arrange to obtain valid gate passes for his men and
equipment from the concerned Authorities.
15.4 No man/material/equipment not covered by valid passes shall be permitted within the
Site no material/equipment shall be permitted to be taken out of the Site, unless
authorized by the concerned Authorities. The Contractor shall be held fully
responsible for any or all delays/ losses/ damages that may result consequent on any
lapse(s) that may occur on the part of his subcontractors/employees in this regard.
16.1 The CONTRACTOR has to apply for photo Entry Passes for his workers and staff
and the workers and staff of his Sub-Contractors in a prescribed proforma provided
by Owner. The Application shall be accompanied by a Statement and Declaration in
the form prescribed by Owner signed by the employees for whom the Entry Passes
are sought and confirmed by the employer. The photo Entry Passes shall be issued by
Owner for a maximum period of 3 (three) months, which will be extendable upon the
Contractor’s application. As a special case, Temporary Passes may be issued for a
maximum period of 7 (seven) days.
16.3 In case of the loss of an Entry Pass/Identity Card, the Contractor shall immediately
lodge an FIR with the local police station and inform TCE of the loss and shall pay a
charge of Rs.150/- against Entry Pass/Identity Card lost. The Contractor is required to
keep an account and track of all Entry Passes issued and surrendered.
Gate Passes/Identity Cards issued by the Security Section should always be displayed
by the Contractor’s or Sub-contractor’s employees while working inside the Plant.
ISSUE
R0
17.1 To bring materials, equipment, tools and tackle and other things inside the Site for
construction Work, the Contractor has to produce proper documents of title or
authority relative thereto for inspection by Owner’s personnel at the gate. These shall
be checked thoroughly by Owner’s personnel at the Gate and recorded in their
Register before permitting the same to be brought inside within the Site. It is the
Contractor’s responsibility to see that the entry is duly recorded in the Register with
proper Entry Number, date and signature of Owner’s authorized representative and
that the supporting challans/documents are stamped and signed by Owner’s personnel
at the gate at the time of entry.
Those materials which need repairing/ replacement as per Site condition will be
allowed to move beyond Owner’s battery limit only after exchange of good
equivalent material.
18.1 In order to keep Owner informed of the various jobs being undertaken within the Site
and to enable Owner to regulate the same to ensure the observance of safety
regulations relative thereto, when Work is to be carried out in hazardous areas, a Hot
Work Permit is to be obtained by the Contractor from Owner before start of Work on
jobs which are capable of generating a flame, spark or heat e.g., gas cutting, grinding,
welding, use of any electrical, diesel, petrol or battery operated prime mover,
machine, tool or equipment or generator set, mixer machine, drilling machine, pump,
crane, fork lift or hand truck or trailer or chipping or breaking of rocks or concrete or
hacksaw cutting and drilling. Similarly the Contractor shall obtain a Cold Work
Permit from Owner for jobs which do not come under the category of hot work and in
respect of which there is no risk of fire, e.g., transportation, backfilling of ordinary
soil by manual process, pile testing, hydro-testing, shuttering, fixing of reinforcement,
hand mixed concreting, plastering and brickwork.
18.2 Depending on the nature of the Work and the equipments and tools involved, the
Contractor shall apply for Cold/Hot Permit in a prescribed format at least 7(seven)
days before the Work is planned to start. No Work Permit shall be issued by Owner
unless proper arrangement is made by the Contractor to ensure safe performance of
the Work inside the Site limit. Job-wise and area-wise permits shall be issued to the
Contractor and for Work against each permit the Contractor shall post at Site at least
one Construction Supervisor and one Safety Supervisor of required level to ensure the
due observance of all safety requirements.
ISSUE
R0
(i) Vehicle/Equipment shall be in good condition and fitted with spark arrestor.
(ii) Vehicles should carry, wherever applicable, valid Road Tax Certificate and
Fitness Certificate from the competent authority and insurance policy.
(iii) Valid operating/driving license of driver/operator.
(i) Any Hot or Cold Work Permit issued is valid only for 24 hours.
(ii) Thereafter the validity of the Permit must be renewed for each shift (morning
& evening) by the shift in-charge/ shift representative of Owner.
(iii) The permit may be renewed for a maximum period of one month from the
date of issue and if extension is required, the Contractor has to apply for a
fresh permit.
(iv) A permit is not valid for Work on holidays unless special permission of
Owner is obtained for the purpose.
(a) The Work shall be carried out inside the Site to conform to the Owner’s
safety section and in accordance with any instructions of TCE issued from
time to time. Sometimes working hours may be drastically reduced or
increased to satisfy safety requirements and the Contractor shall meet these
requirements without any time and cost implications. No claim for idling of
machinery, plant, manpower or equipment shall be entertained for reason of
delay in the issue of a Work Permit and it shall be the exclusive responsibility
of the Contractor to apply for, pursue and obtain the requisite Work Permit(s)
well in advance of the relative requirement(s).
(b) The Contractor shall abide by all safety regulations of the Plant and ensure
that safety equipment for specific jobs as stipulated in the Factories Act
Safety Handbook is issued to all employees during the execution of Work,
failing which all the works at Site shall be suspended.
(a) When doing hot work inside the plant, the Contractor must ensure that the
fire hose is hooked up with the fire water system and extended to the Site/
suitable alternative fire- fighting arrangements are made to the satisfaction of
the Engineer-in-Charge. In addition, at least one fire extinguisher must be
kept near the working spot. The area around and below the place of hot work
must be adequately protected from sparks and hot metals by a booth made of
ISSUE
R0
(b) Welding & electrical cables should be of approved quality and no jointing or
loose connection shall be permitted.
(c) At the end of the working day the Contractor must inform the electrical
section to switch off power at sub-station end.
(d) The Contractor must provide cotton clothes, safety shoes, safety helmet,
safety belt, and hand gloves of approved quality to his workers to meet the
safety requirement of various jobs to be carried out inside the Plant.
(a) Vehicle must not ply on any road within the Site at a speed exceeding 20
KM/hr.
(b) Mobile cranes, loaded trucks and trailers must not exceed the speed limit of
15 KM/hr. inside the plant.
(c) No crane is allowed to move inside the plant with load.
(d) No vehicle is allowed to be parked inside the plant.
(e) Limited number of vehicles will be permitted inside the battery area due to
security reasons.
22.1 In addition to price reduction and deductions as provided for, Owner shall be entitled
to deduct from any payment due to the Contractor, any amount claimed by Owner
under the Contract and any costs, damages or expenses for which the Contractor is
liable under the Contract.
22.2 In addition to price reduction and deductions as provided for in the Contract, Owner
shall be entitled to deduct from any payment due to the Contractor, for violations of
safety provisions, as per details given below:
(i) Violation of applicable safety, health and environment related norm, a price
reduction of INR 5000/- per occasion
(ii) Violation as above resulting in (a) Any physical injury - a price reduction of
0.5% of the Contract Price (maximum of INR 2,00,000) per injury in addition
to INR 5,000/; or (b) Fatal accident - a price reduction of 1% of the Contract
Price (maximum of INR 10,00,000) per fatality in addition to INR 5,000/-
ISSUE
R0
With a view to ensure the formulation and enforcement of a safety code by the
Contractor, it is stipulated that in the event of any act, omission or accident at the Site
which results in the death of a person, the Contractor shall contribute a sum of INR
5,00,000/- (Rupees five lakh only), or which results in the permanent disablement of a
person, the Contractor shall contribute a sum of INR 3,00,000/- (Rupees three lakh
only) in addition to any other sum(s) required to be paid by the Contractor under any
law or other contract, to a welfare fund to be established by Owner for, inter alia,
such contributions, and until such fund is established, to a charity nominated by
Owner.
ISSUE
R0
APPENDIX 4
INDEMNITY BOND
To
Dear Sirs,
WHEREAS Owner and having its head/registered office at 4th Floor, Orion Place, G S Road,
Guwahati, Assam - 781005, India (hereinafter called “the Indemnified” which expression
shall include its successors and assigns) has awarded to
M/s…………………………………… a Partnership Firm/ Sole Proprietor Business/ a
company having its Registered Office at ……………………………………. (hereinafter
called “the Indemnifier”, which expression shall include its successors and assigns) a contract
for conditions set out, inter-alia, in “the Indemnified” Purchase Order No. …………………
dated……………………….. (hereinafter referred to as “the said Contract”) to “the
Indemnifier”.
AND WHEREAS “the Indemnified” has agreed to supply to “the Indemnifier” raw material/
components to the value of INR……………... (Rupees……………………
…………………… only) for incorporation in fabrication by “the Indemnifier” in terms of
“the said contract”, the components/ raw material to be supplied by “the Indemnified” to “the
Indemnifier” for the said fabrication, (hereinafter, or the sake of brevity, referred to as “the
said material”) and pending fabrication and delivery at job-site of the completed fabricated
work(s) incorporating “the said material” and accounting for “the said material” shall be
under the sole custody and charge of “the Indemnifier” and shall be kept, stored, altered,
worked upon and/ or fabricated at the sole risk and expenses of “the Indemnifier”.
ISSUE
R0
fabricated work(s) incorporating the said material AND jointly and severally undertake to pay
to “the indemnified” forthwith on first demand in writing without protest or demur the value
of “the said material” or item part thereof lost, damaged, destroyed, misused and/or
misappropriated, as the case may be, inclusive of “the Indemnified” ’s cost and expenses
(inclusive but not limited to handling, transportation, cartage, insurance, freight, packing and
inspection costs and/ or expenses) as specified in the said demand.
1. This Indemnity shall remain valid and irrevocable until the settlement of all claims of “the
Indemnified” arising hereunder.
3. “The Indemnified” shall be at liberty without reference to “the Indemnifier” and without
affecting the full liability of “the Indemnifier” hereunder to take any other such security
in respect of “the Indemnifier’s” obligations and/or liabilities under or in connection with
the “said contract” inclusive of “the said material” and to vary the terms vis-a-vis “the
Indemnifier” of “the said contract” or to grant time and/or indulgence to “the
Indemnifier” or to reduce or to increase or otherwise vary the prices or the total contract
value or the quantity, quality, description or value of the said material or to release or to
forbear from endorsement of all or any of the obligations of “the Indemnifier” under the
said contract (inclusive of anything in respect of “the said material”) and/or to remedies
of “the Indemnified” under any other security (ies) now or hereinafter held by “the
Indemnified” and no such dealing(s), variations(s), reduction(s), increase (s) or other
indulgence (s) or arrangement(s) with “the Indemnifier” or release “the Indemnifier” from
their full liability to “the Indemnified” hereunder or of anywise prejudicing rights of “the
Indemnified” against “the Indemnifier” and “the Indemnifier” hereby waive all rights, if
any, at any time, inconsistent with the terms of this Indemnity.
4. This Indemnity shall not be determined or affected by the liquidation or winding up,
dissolution, or change of constitution or bankruptcy or insolvency of “the Indemnifier”
and the obligations of “the Indemnifier” in terms hereof shall not be anywise affected or
suspended by reason of any dispute or disputes having been raised by “the Indemnifier”
(whether now pending before any Arbitrator, Officer, Tribunal or Court) or any denial of
liability by “the Indemnifier” or any other order or communication whatsoever by “the
Indemnifier” or any other order or communication whatsoever by “the Indemnifier”
stopping or preventing or purporting to stop or prevent any payment by “the Indemnifier”
to “the Indemnified” in terms hereof.
ISSUE
R0
5. The mere statement made by or on behalf of “the Indemnified” in any notice or demand
or other writing addressed to “the Indemnifier” as to any of “the said material” or item or
part thereof supplied to “the Indemnifier” having been lost, damaged, destroyed, misused
or misappropriated while in the custody of “the Indemnifier” before or after completion of
the completed fabricated work(s) incorporating “the said material” and delivery at job site
thereof shall as between “the Indemnifier” and “the Indemnified” be conclusive of the
factum of “the said material” or item or part thereof having been supplied to “the
Indemnifier” and/or the loss, damage, destruction, misuse or misappropriation thereof, as
the case may be, while in the custody of “the Indemnifier” and/or prior to the completion
of the completed fabricated work(s) and delivery to job site thereof without necessity on
the part of “the Indemnified” to produce any documentary proof or other evidence
whatsoever in support of this.
6. The amount stated in any notice of demand addressed by “the Indemnified” to “the
Indemnifier” as the value of any of “the said material”, lost, damaged, destroyed or
misused or misappropriated, inclusive relative to the cost and expenses incurred by “the
Indemnified” in connection therewith shall as between “the Indemnifier” and “the
Indemnified” be conclusive of the value of such “said material” and the said costs and
expenses as also of the amount liable to be paid by “the Indemnifier” to “the Indemnified”
in terms and for the purpose of, without necessity for “the Indemnified” to produce any
voucher, bill or other documentation or evidence whatsoever in support thereof.
In witness whereof “the Indemnifier” have hereunto set and subscribed his hand this day and
year first hereinabove written in the presence of witnesses.
Yours faithfully,
1.
2.
3.
WITNESSES:
1.
2.
ISSUE
R0
APPENDIX 5
PART A
FORMAT-I
EXCEPTIONS:
SIGNATURE
DATE
CONTRACTOR’S CONSTRUCTION:
CO-ORDINATOR
ISSUE
R0
PART B
FORMAT-II
CHECKLIST
SIGNATURE DATE
Owner/TCE:
ISSUE
R0
APPENDIX 6
FORMAT-III
READY FOR PRE-COMMISSIONING CERTIFICATE
DESCRIPTION ON PLANT/SECTION/SUB-SECTION
________________________________
SIGNATURE DATE
CONTRACTOR’S CONTRACTION
CO-ORDINATOR:
CONTRACTOR’S COMMISSIONING
CO-ORDINATOR:
ISSUE
R0
APPENDIX 7
FORMAT-IV
READY FOR COMMISSIONING CERTIFICATE
This is to certify that all the necessary pre-commissioning activities for the system/sub-system
as detailed below have been completed and the system/sub-system is ready for
commissioning except for the minor details as given below which will not affect the
commissioning trial runs.
DESCRIPTION ON PLANT/SECTION/SUB-SECTION
________________________________
SIGNATURE
DATE
CONTRACTOR’S COMMISSIONING:
CO-ORDINATOR
SIGNATURE
DATE
Owner/ TCE:
ISSUE
R0
APPENDIX 8
FORMAT-V
This is to certify that the system/sub-system as detailed below has been successfully
commissioned and is under operational control of Client’s Production department. The minor
items, which will not affect the normal operation of the system/sub-system, are given in the
attached list.
DESCRIPTION ON PLANT/SECTION/SUB-SECTION
________________________________
SIGNATURE
DATE
CONTRACTOR’S COMMISSIONING:
CO-ORDINATOR
SIGNATURE
DATE
Owner/ TCE:
ISSUE
R0
1.0 GENERAL
1.2 These Special Conditions of Contract (SCC) shall be read in conjunction with the
General Conditions of Contract (GCC), Schedule of Rates, specifications of work,
drawings and any other document forming part of this Contract wherever the
context so requires.
1.4 In the absence of any Specifications covering any material, design or work(s) the
same shall be performed/ supplied/ executed in accordance with standard
Engineering practice as per the instructions/directions of the Engineer-in-Charge,
which will be binding on the Contractor.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
therefrom as may be made under the Contract and as adjusted
by the actual quantities, if applicable, utilized in the execution of
the Works.
Clause is modified as :
“Engineer–in-Charge” or “TCE” or “PMC” means Tata Consulting
Engineers Limited, a company incorporated under the Companies Act,
1956 with its registered office at Matulya Centre ‘A’,1st Floor, 249,
Senapati Bapat Marg, Lower Parel (West), Mumbai- 400013 and its
1 (44) Corporate Office at Unit no. NB 1502 & SB 1501 15th Floor Empire
Tower, Cloud City Campus, Thane- Belapur Road, Airoli, Navi
Mumbai 400708 acting in its capacity as the Project Management
Consultant (PMC) of the Owner (which expression shall be deemed to
include the successors, and assigns of TCE).
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
9.1.6.1 The CONTRACTOR shall within 15 days from the
effective date, submit to the OWNER a detailed Bill of
quantities specifying the materials, which on preliminary
determination made by the CONTRACTOR, will be
required to be incorporated in the permanent works in order
to establish the Works/ and to operate the Plant/ (to the
extent of the mandatory spares), including construction
materials.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
therein are intended only for the satisfaction of the OWNER
that the priced Bill of Materials, prima-facie covers the
materials required to be supplied by the CONTRACTOR
within the scope of supply.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
within 10 (Ten) days after the Effective Date. The Engineer-in-
Charge shall review the Project Quality Plan/Quality Assurance
Plan and provide any comments to the Contractor within
7(Seven) Working Days after its receipt of such draft. Within 7
(Seven) days after its receipt of the Engineer-in-Charge’s
comments, the Contractor shall implement such comments re-
submit the Project Quality Plan/Quality Assurance Plan to the
Engineer-in-Charge for Approval. This procedure shall be
repeated until the Project Quality Plan/ Quality Assurance Plan is
approved by the Engineer-in-Charge. Any compliance by the
Contractor with the Engineer-in-Charge's comments shall neither
constitute a Variation nor entitle the Contractor to any extension
of the Time for Completion or increase in the Contract Price. No
proposed change to the Project Quality Plan/ Quality Assurance
Plan shall be effective unless the Engineer-in-Charge approves
of such proposed change. Notwithstanding any comments
provided by the Engineer-in-Charge, the Contractor shall remain
fully responsible for the Project Quality Plan/ Quality Assurance
Plan, including rectifying all defects therein.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
varaiations exceeds 25 (twenty five) % of the Contract Price.
Clause shall be read as follows:
Clause is modified as :
Price Reduction due to delay in completion of Phase I and
Phase II
If the Contractor fails to complete the Works within the Time for
Completion, and/or if completion of any specific work(s) in respect of
which a separate progress schedule has been established is not achieved
by the date of completion thereof specified in the Works Completion
Schedule (each of the said date(s) is hereinafter referred to as the
“starting date for discount calculation) other than due to an event of
Force Majeure or any reason solely attributable to Owner, then the
13.2 Contract Price shall be reduced by 1 % ( one percent) per week of
delay or part thereof subject to a maximum deduction of 10% (ten
percent) of the proportionate of Contract Price for Phase I and Phase II
as applicable . After any adjustments made to the Contract Price
pursuant to this Clause 0, if any amount is due to Owner from the
Contractor, then such amount will either be set-off against any amount
due or that becomes due to the Contractor or be recovered by invoking
the Contract Performance Bank Guarantee.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
Completion of Phase I of Works.
Clause 15. 9 (b) is not applicable to this Contract.
Clause 15.10 is not applicable to this Contract.
ISSUE
R0
GCC
CLAUSE SUPPLEMENT DESCRIPTION
NO.
Contractor from within India the DAP (INCO TERMS 2010) Site
value of such Goods and Material and Plant and the GST
leviable on the transaction between ‘Owner and Contractor’ shall
be separately indicated in the Price Schedules (as indicated in
the Price Schedule) along with the rate of Tax so applied in
computing such indirect Taxes.
Clause is modified as:
Owner shall issue in accordance with relevant legislation, the
requisite Goods and Service Tax (GST) declaration forms, as
applicable to the Contractor in order to get the benefit of any
22.5
concession in the rate of Taxes , as the case may be. The
Contractor shall provide relevant statutory declaration forms to
Owner in accordance with relevant legislation, within the period
specified under the relevant GST legislation.
Fisrt para of this Clause is modified as:
The Contractor and its Subcontractor/ vendor/ original
manufacturer shall issue proper invoice, as stipulated under the
customs, Goods and Service Tax (GST) and other Applicable
Laws, and other necessary documents as may be relevant from
22.7
time to time to enable Owner or any person designated by Owner
to avail the credit of such Taxes, wherever applicable, paid by
the Contractor or any Subcontractor/ vendor/ original
manufacturer within the time period specified under the
applicable legislation in this regard.
23.1, 23.2 Please refer Schedule of Payment in Annexure IX of this SCC
and 23.3
First sentence of this clause is modified as under:
ISSUE
R0
3.1 It shall be the duty of the CONTRACTOR to duly observe and perform all
laws, rules, regulations, orders and formalities applicable to GST (IGST /
CGST / SGST / UTGST) and Customs Duty on the supply including import of
any material to OWNER and/or on the services performed by the
CONTRACTOR pursuant hereto. The CONTRACTOR shall keep the
OWNER and the PMC indemnified for and against any and all claims,
demands, prosecutions, penalties, damages, demurrages and/or other levies
whatsoever made or levied by the Court or Customs Authorities with respect
to any alleged breach, evasion or in fraction of such duties, taxes, charges or
levies or any breach or in fraction of such laws, rules, regulations, orders or
formalities concerning the same and from the consequence thereof.
3.2 The award of work under the entire contract shall be on ‘Work Contract
Service’ basis. The contractor shall be responsible for payment of any tax
levied on the transfer of property and goods involved in the “Works contract
Service‟ in accordance with relevant GST act and rules made there under
including amendments, if any. The contractor shall be liable to ensure to have
registered with the respective tax authorities and to submit self -attested copy
of such registration certificate(s) and any taxes/ duties/ levies being charged
by the Contractor would be claimed by issuing proper tax invoice/challan
indicating details/ elements of all taxes charged and necessary requirements
as prescribed under the respective tax laws and also to mention correct and
valid registration number(s) on all tax invoices raised to Owner.
3.3 It shall be mandatory for the Contractor to get Goods and Services Tax
Registration Number (GSTIN) within 1 Months from the award of Order or
prior to release of any payment including advance, whichever is earlier. No
payment shall be released till such time Contractor obtains the GST Number
and submits the same to Owner.
3.4 The Bidders who are already registered with GST authorities shall submit
copy of their registration certificate along with their unpriced Bids. In case
registration certificate is not available at the time of submission of offer, an
undertaking should be furnished by the bidder for submission of registration
certificate in line with clause No. 3.3.
3.6 The Contractor would be liable to reimburse or make it good of any loss/
claim by Owner towards tax credit rejected/ disallowed by any of the tax
authorities due to non-deposit or delayed deposit of taxes or non-compliance
or delayed compliance of tax laws by the Contractor. The Contractor shall be
liable to reimburse Owner, for all such losses and other consequences
related to GST including, but not limited to the tax loss, interest and penalty.
3.7 The contractor will be under obligation for quoting/charging correct rate of tax
ISSUE
R0
as prescribed under the respective Tax Laws. Further, the Contractor shall
avail and pass on benefits of all exemptions/concessions/benefits/waiver or
any other benefits of similar nature or kind available under the Tax Laws. In
no case, differential Tax Claims due to wrong classification of goods and/or
services or understanding of law or rules or regulations or any other reasons
of similar nature shall be entertained by Owner.
3.8 The Contractor has to get registered as per tax law of the State where the
work is to be executed and the Contractor will be responsible for procurement
of material in its own registration (GSTIN) and also to issue its own Road
Permit, E-way Bill, if applicable etc. E- way bills / Transit passes / Road
Permits, if required for materials etc., brought into the project site is to be
arranged by the Contractor only. Delays on account of arranging road-
permits/e-way bills shall not make Contractors eligible for waiver of late
delivering penalties in terms of Contract. The Contractor will be under
obligation for proper utilization for the specific supply and in case of seizure of
goods/ vehicle, the Contractor will be wholly responsible and indemnify
Owner /PMC against any litigation cost.
3.12 The Contractor shall issue proper tax invoice, as stipulated under the
customs, GST and other Applicable Laws, and other necessary documents
as may be relevant from time to time to enable Owner to avail the credit of
such Taxes, wherever applicable, paid by the Contractor within the time
period specified under the applicable legislation in this regard
If Owner is not able to avail the credit (as indicated in the Price Schedule,
unless otherwise mentioned in this Contract), partially or entirely because the
Contractor issued a defective tax invoice or failed to produce the requisite
documents, then the Contractor shall immediately indemnify Owner for such
loss of input tax credit including interest and penalty imposed, if any, which
would be otherwise available to Owner. Owner, in such case, may, in its sole
discretion, decide to recover such loss by way of deduction from payment
due to the Contractor or invoking the Composite Performance Bank
Guarantee or any other measure available with the Owner in addition to the
amount of GST, Owner shall also be entitled to recover interest at the rate
ISSUE
R0
prescribed under GST Act and penalty, in case any penalty is imposed by the
tax authorities on Owner.
3.14 Any changes in statutory rules and regulations under GST regime Shall be
followed by Contractor.
3.15 The payment towards all Indian Taxes and duties (CGST/SGST/IGST)
payable by the OWNER under the Contract will be paid in Indian Rupees at
actuals limited to the amount indicated in their bid except for statutory variation.
3.16 The benefit of any Tax exemption, concessions, rebate or any other incentives
available when the Contractor or its Subcontractors/ vendor are performing their
obligations under the Contract, shall be passed on to the Owner.
3.17 In case of Price Adjustment for delay in Completion applicable appropriate Debit
Note / Credit Note shall be Issued by Owner / Contract as per GST laws.
3.18 Tax element on any Debit Note / Supplementary invoice, raised by the
CONTRACTOR will be reimbursed by Owner as long as the same is within the
permissible time limit as per the respective taxation laws and also permissible
under the Contract terms and conditions. Contractors to ensure that such debit
Notes are uploaded while filing the Statutory returns as may be prescribed from
time to time.
3.19 Contractor to share the monthly information with Owner which would be
uploaded by the CONTRACTOR in its GSTR -1 along with the information of
input tax credit to be claimed by Owner in such month.
3.20 CONTRACTOR shall be liable to comply with all the compliances as may be the
rating prescribed to ensure that compliance rating is not reduced below the
prescribed limit as laid down under GST Act and GST regulations. Contractor
shall be required to submit a self- declaration from time to time that they are not
black-listed on the GST portal. Notwithstanding anything contained in
agreement, in the event of black listing of Contractor i.e. compliance rating
reduced below the prescribed limit, the amount related to tax shall be paid to
CONTRACTOR only on receipt of input tax credit to Owner.
4.0 INTEGRATED GOODS AND SERVICES TAX (IF APPLICABLE) FOR SUPPLIES
(GOODS / SERVICES)
5.0 INTRASTATE SALES (CENTRAL GOODS AND SERVICES TAX (CGST) PLUS
STATE GOODS AND SERVICES TAX (SGST) / UNION TERRITORY GOODS
AND SERVICES TAX (UTGST)) FOR SUPPLIES (GOODS/SERVICES)
ISSUE
R0
5.1 The OWNER shall pay CGST plus SGST levied on and paid by the
CONTRACTOR on such indigenous supplies of goods/services by the
CONTRACTOR to the OWNER under the Contract. CONTRACTOR shall be
obligated to issue a valid tax invoice complying with GST Invoice Rules for
the supply made by him. If any error/discrepancies found in the invoice
issued by contractor, it shall not be accepted by OWNER as a valid invoice
and OWNER shall have the full power to send back such tax invoice for
rectification to the The CONTRACTOR shall be under an obligation for the
rectification of such a tax invoice. In case any error/discrepancy is found at a
later date post acceptance of the invoice, owner shall have the full authority
to make any loss good from any due/security available with the owner.
5.4 The OWNER shall not reimburse GST taxes, if the requirements as specified
above are not fulfilled by the CONTRACTOR.
5.5 Any statutory increase in the amount of GST resulting from an increase in the
rate of GST payable against certain supplies made to the OWNER shall be
reimbursed by the OWNER at actuals. Similarly, any reduction in the amount
of GST resulting from a reduction in the rate of GST or remission or
exemption from GST with respect to supplies made to the OWNER shall be
refundable to the OWNER at actuals with reference to the amount of GST
indicated in the Bill of Materials for such materials.
5.7 In case Owner’s Input Tax Credit (ITC) is rejected on account of wrong levy
of tax i.e. payment of Integrated Tax in place of Central Tax+ State/Union
Territory Tax, the CONTRACTOR is liable to make good the loss suffered by
Owner by issuance of suitable credit note to Owner. In case, contractor does
not issue credit note to Owner, Owner would be constrained to recover the
amount including interest payable along with Statutory levy, if any, payable
on such recovery.
6.1 Tax Invoice to be submitted by the bidder in compliance with the prevailing
tax laws at the time of execution / delivery.
6.2 Contactor is requested to acquaint themselves about GST Law and other tax
ISSUE
R0
6.3 The credit of GST will be factored for Bid evaluation purposes by the Owner,
to the extent the Owner may be eligible Contractor shall be required to issue
tax invoice /debit note/ Credit invoice in accordance with GST Rules so that
input credit can be availed by Owner. In the event that the Contractor fails to
provide the invoice in the form and manner prescribed under the GST Act
read with GST Invoicing Rules thereunder, Owner shall not be liable to make
any payment on account of GST against such invoice.
6.4 The Contractor shall comply with all the provisions of the GST Act / Rules /
requirements like providing of tax invoices, payment of taxes to the
authorities within the due dates, filing of returns within the due dates etc. to
enable Owner to take Input Tax Credit. The Contractor shall always comply
with the requirements of applicable laws and provide necessary documents
as prescribed under the Rules & Regulations, as applicable from time to time.
In particular, if any tax credit, refund or other benefit is denied or delayed to
Owner due to any non-compliance / delayed compliance by the Contractor
under the Goods & Service Tax Act (such as failure to upload the details of
the sale on the GSTN portal, failure to pay GST to the Government) or due to
non-furnishing or furnishing of incorrect or incomplete documents by the
Contractor, the Contractor shall be liable to reimburse Owner for all such
losses and other consequences including, but not limited to the tax loss,
interest and penalty.
7.0 Imports (CUSTOMS DUTY, EC, Social Welfare Surcharge and IGST)
7.1 Contractor shall be responsible for payment of custom duty, EC, Social
Welfare Surcharge and IGST for imports for the purpose of permanent
incorporation in the works, in line with any other applicable Scheme in
force for the project
ISSUE
R0
7.2 The Contractor shall pay the Customs Duties and all other duties/taxes/cess
applicable on the material imported for the purpose of permanent
incorporation in the works. The CONTRACTOR shall be fully responsible for
Port and Customs clearance including stevedoring, handling, unloading,
loading and storage and for satisfying all Port and Customs formalities for the
clearance of the goods, including preparation of the Bill(s) of Entry and other
documents required for import and/or clearance of the goods. The
CONTRACTOR shall also be fully responsible for any delays, penalties,
demurrages, shortages and other charges and losses, if any, in this regard.
7.3 The CONTRACTOR shall provide the OWNER with all necessary documents
like Bill of lading, Bill of Entry, Invoices etc. These document should have
reference that “the material imported is intended for use of “Transshipment
Project”. These documents are only for Insurance purpose and shall not be
linked with any milestone payment.
7.4 The CONTRACTOR shall appoint a Customs House Clearing Agent of good
standing and ensure speedy customs clearance.
7.5 The CONTRACTOR shall be responsible to register the Import License with
Customs Authorities at the Port of Import, and to answer and sort out
technical queries (if any) raised by Customs Authorities in regard to any
import(s).
7.7 The Contractor shall be responsible for, and shall exercise due diligence in
properly classifying the Goods & Material, undertaking the payment of
customs duties, IGST and/or otherwise complying with all Applicable Laws
with respect to any import of the Goods & Materials. In case Owner
/CONSULTANT is exposed to any penal action (interest and / or penalties)
by the customs Authorities for incorrect declaration and/ or valuation of the
Goods or Materials by the Contractor, or otherwise on account of any breach
of Applicable Laws in the course of the import of the Goods and Materials by
Contractor, the Contractor shall indemnify and hold harmless, Owner/PMC
for any and all costs, expenses or losses suffered or incurred by Owner/PMC
in this regard.
7.9 High Sea Sales shall not be applicable for this contract/ Work
8.1 The CONTRACTOR shall be exclusively responsible and liable to pay all
ISSUE
R0
income taxes on any payments arising out of the Contract, whether payable
in India or in any other jurisdiction.
8.2 The CONTRACTOR shall also be responsible for ensuring compliance with
all provisions of the direct tax laws of India including, but not limited to, the
filing of appropriate Returns and shall promptly provide all information
required by the OWNER for discharging any of its responsibilities under such
laws in relation to or arising out of the CONTRACT. For the lapses, if any, on
the part of the CONTRACTOR and consequential penal action taken by the
Income Tax department, the OWNER shall not take any responsibility
whether financial or otherwise.
8.5 The Indian Income Tax Act and rules made there under contains provisions
permitting deduction of tax at a lesser rate if the CONTRACTOR is able to
justify to the Income Tax Authorities such lesser rate of deduction. However,
a deduction once made has to be deposited by the OWNER with the Income
Tax Authorities in India and will not be adjustable by the OWNER. It is
therefore in the interest of the CONTRACTOR that prior to release of any
payment due to the CONTRACTOR under the Contract that the
CONTRACTOR obtains, from the relevant Income Tax Authorities in India,
a certificate specifying the rate of deduction/withholding of Income tax at
source, failing which, payment to the CONTRACTOR shall be made by the
OWNER after Withholding/deduction at the highest rate as may be
applicable to the non-resident contractors as per Provisions of Income Tax
Act, 1961.
ISSUE
R0
10.1 The CONTRACTOR shall bear all personnel taxes levied or imposed on
its personnel, SUB- CONTRACTOR’ s personnel, vendors, consultants etc.
on account of payment received under this CONTRACT. Contactor shall also
bear, within the quoted rates, the Corporate Tax, as applicable, on the
income arising out of this contract.
11.2 Notwithstanding the foregoing, Owner shall not bear any liability in
respect of:
12.0 SEIGNIORAGE FEE & CESSES FOR CIVIL WORKS (If applicable )
13.1 The Contractor will submit a bill in approved proforma in quadruplicate to the
Engineer-in-Charge/Site-in-Charge of the work giving abstract and detailed
measurement for the various items executed during a month, before the expiry of
ISSUE
R0
14.1 Technical loading of offers shall be as per Section D of this ENQUIRY document
ISSUE
R0
ATTACHMENT-I
ISSUE
R0
ATTACHMENT - III
This Agreement made the ----- day of ------------ Between between Assam
Petrochemicals Ltd, a company registered under companies Act,1956 having its
registered office at Orion Place ,G.S.Road, Guwahati (hereinafter called
“Owner/APL”, which expression unless excluded by or repugnant to the context
include its successors and permitted assign ) of the one part,
AND
RECITALS
WHEREAS:
1. The Owner being desirous of having provided and executed works mentioned,
enumerated or referred to in the tender documents (Volume I, VolumeII and
Volume III) including and not limited to General Conditions of Contract, Special
Conditions of Contracts, Specifications, Drawings, Plans, Time Schedule for
Completion of jobs, Agreed Deviations, other documents, has called for Tender.
2. The contractor has inspected the site and surroundings of the works specified in
the tender documents and has satisfied himself by careful examination before
submitting his tender as to the nature of the surface strata, soil, sub-soil and
ground, the form and nature of site and local conditions, the quantities, nature
and magnitude of the work, the availability of labour and material necessary for
the execution of work, the means of access to site, the supply of power and
water thereto and the accommodation he may require and has made local and
independent enquiries and obtained complete information as to the matters and
things referred to, or implied in the tender documents or having any connection
therewith and has considered the nature and extent of all probable and possible
situations, delays, hindrances, or interferences to or with the execution and
ISSUE
R0
completion of the work to be carried out under the Contract and has examined
and considered all other matters, conditions and things and probable and
possible contingencies and generally all matters incidental thereto and ancillary
and thereof effecting the execution and completion of the work and which might
have influenced him in making his tender.
3. The Contractor has represented that it has experience, expertise, capability and
knowhow to ensure that the Road and Drain Facility Works are executed and
completed in accordance with the provisions of the Contract and in a safe and
environmentally responsible manner;
4. Solely relying upon the representation in Recital 2 above, the Owner agrees to
appoint the Contractor to execute the Works and the Contractor agrees to carry
out and complete the Works within the Time for Completion and undertakes to
remedy any defects therein, in accordance with the terms and conditions
contained in this Contract; and
5. The terms of and Conditions of the Contract have been fully negotiated and
agreed upon between the Owner and the Contractor as parties of competent
capacity and equal understanding.
ISSUE
R0
the Specification;
the Drawings;
the Schedules and any other documents forming part of the Contract.
This Contract will be governed by and construed in accordance with the laws of
India. Each Party hereby submits to the jurisdiction as set out in Disputes Resolution
Procedure in the Conditions of the Contract.
Place:__________________ Place:___________________
For and on behalf of “the Owner” in the For and on behalf of “the
presence of CONTRACTOR” in the presence of
Witness: Witness:
Name:____________________ Name:_______________________
Address:__________________ Address:_____________________
Date:________________________ Date:________________________
ISSUE
R0
ATTACHMENT - V
NO DEMAND CERTIFICATE
(On contractor letter head)
CERTIFICATE THAT
1. The recoveries in respect of material issued to the contractor have been made
from RA bills. Balance if any is to be recovered from final bill as per the
statement enclosed.
2. Recovery on account of Water or Electricity are to be made by OWNER.
3. The contractor has made payment to the labour engaged by him and no
complaint has since been received from any of the labour employed by the
contractor in the performance of the above work. A certificate from sub-
contractor to this effect is enclosed.
4. Work has been completed satisfactorily and is according to the specifications
laid down in the contract.
5. None of the heavy equipment were given to the contractor on hire basis and
nothing is recoverable on this account or recoveries in respect of hire charges
of heavy equipment have been made from RA bill. Balance if any is to be
recovered from Final bill as per statement enclosed.
6. Labour hutment has been/has not removed by the sub-contractor and ground
rent is to be recovered as per statement enclosed.
7. The work has been completed within the schedule period.
OR
The completion of the work has been delayed by _______months/days and as
such the recovery of liquidated damages to the extent of
INR.______________________(Rupees __________________may be
made .
Extension for ______months/days has been granted by the competent
authority vide letter No. ________________ dtd. ________________.
8. The requisite obligations as per contract have been fulfilled by the contractor.
ENGINEER-IN-CHARGE ____________________
ACCOUNTS ____________________
ISSUE
R0
DATE ____________________
ATTACHMENT - VI
NO DUE CERTIFICATE
(On Contractors Letterhead)
We certify that we have fully paid and satisfied all claims for the work relating to labors,
materials supplied equipment and any other entitlement whatever touching or affecting
the contract. We undertake to indemnify and keep indemnified the owner from and
against all claims, demands, debts, lines obligations and liabilities whatever arising there
from or relating thereto.
_________________________
SIGNATURE OF CONTRACTOR
NAME: _____________________
ADDRESS: _____________________
_____________________
_____________________
DATE:
ISSUE
R0
ATTACHMENT - VII
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF CONTRACTOR :
NAME OF WORK :
WE HERE BY CERTIFY THAT ALL YOUR MATERIAL, EQUIPMENTS, SITE OFFICE ETC.
HAS BEEN REMOVED FROM THE _____________________ SITE. WE HAVE CLEARED
THE SITE IN ALL RESPECT AND HANDED IT OVER TO OWNER.
_____________________________
SIGNATURE OF CONTRACTOR
NAME:
ADDRESS:
DATE:
ISSUE
R0
ATTACHMENT - VIII
NAME OF CLIENT :
NAME OF CONSULTANT :
NAME OF CONTRACTOR :
NAME OF WORK :
_____________________________
SIGNATURE OF CONTRACTOR
NAME:
ADDRESS:
DATE:
ISSUE
R0
ATTACHMENT - IX
SCHEDULE OF PAYMENT
ISSUE
R0
ISSUE
R0
ii) 44% (Forty Four percent) After issuing good for construction
drawings at site for roads and drains
iii) 4% (four Percent) After issuing as built drawings
iv) 4% (four percent) After completion of construction of road upto and
including WBM till first 2000m length
v) 4% (four percent) After completion of construction of road upto and
including WBM from next 2000m onwards till complete length
3.2 Construction including supply and transportation
i) 80% (Eighty Percent) After completion of all layers below
WBM/DLC, including laying of all underground road crossings as
per scope and tender specifications, in accordance to priority
stipulated in scope of enquiry (Section A). The breakup of 80%
shall be as given below:
a) 20% (Twenty Percent) on completion of 1000m length of road.
b) 20% (Twenty Percent) on completion of next 750m length of
road beyond 1000m length already completed.
c) 20% (Twenty Percent) on completion of next 750m length of
road beyond 1750m length already completed.
d) 20% (Twenty Percent) on completion of balance length of road
beyond 2500m length already completed.
ii) 10% (Ten Percent) After completion WBM layer, as per scope and
tender specifications, in accordance to priority stipulated in scope
of enquiry (Section A).
iii) 10% (Ten Percent) After completion of all road and drain
construction activity as per scope and tender specifications and
handing over the site to OWNER after phase-2
4. Phase 2 of Work
4.1 Design Engineering Services
i) 80% (Eighty Percent) on completion of residual engineering for
roads and drains, pipe culverts, box culvers etc. and submittion of
design calculations along with approval purpose drawing, including
marking of all additional underground road crossings if any and
after obtaining approval under code-1
ii) 5% (Five percent) After issuing good for construction drawings at
site for road and drains.
iii) 5% (Five percent) After issuing as built drawings and after
completion of As built Drawings
iv) 10% (Ten percent) After completion of all road and drain
construction activity as per scope and tender specifications and
handing over the site to OWNER after phase-2,
4.2 Construction including supply and transportation
i) 30% (Thirty percent) after rectifying the defects/damages of the
roads, makring it to correct levels and alignments, including
compaction, completing all bitumen layers, including top
coats/finishing coats/seal coat , construction of shoulders, kerbs,
providing drainpipes for roads and connecting the same to nearest
ISSUE
R0
storm water drain, including painting of kerb walls and Road marking
etc. as per scope and tender specifications, in accordance to
priority stipulated in scope of enquiry (Section A), for the roads
which are constructed up to WBM under phase-1 work. The
breakup of 20% is given below:
a) 7.5% on completion of 1000m length of road.
b) 7.5% on completion of next 750m length of road beyond 1000m
length already completed.
c) 7.5% on completion of next 750m length of road beyond 1750m
length already completed.
d) 7.5% on completion of balance length of road beyond 2500m
length already completed.
ISSUE
R0
ATTACHMENT - X
ISSUE
R0
LUMPSUM PRICE FOR LSTK CONTRACT FOR ROAD AND STORM WATER
DRAIN WORKS AS PER SCOPE OF WORK DETAILED IN SECTION A OF THE
DOCUMENT
SCHEDULE 1
%age
breakup
SR. NO. DESCRIPTION of IGST CGST SGST
lumpsum
price
1a PHASE I of Scope of works
Design engineering & detailing including
issuing IFC drawings, preparing design
i. reports etc. complete till issuance of IFC
drawings in accordance to the scope of
enquiry.
Excavation, dewatering, providing any soil
improvement is required, compacting sub-
ii. grade, preparing sub-grade, including filling
of material, soling etc. complete in
accordance to the scope of enquiry.
Supply and construction of sub-base of
designed thickness including all layers of
iii. sub-base and filter material, including laying
all road crossings in accordance to the
scope of enquiry.
Supply and construction of WBM, including
providing temporary drains along the length
iv.
of the roads etc. in accordance to the scope
of enquiry.
1b PHASE II OF Work
Residual design engineering & detailing
including issuing IFC drawings and
i.
preparing design reports etc. complete till
issuance of IFC drawings
Supply and construction of bituminous roads
after rectifying the defects/damages of the
ii.
roads, makring it to correct levels and
alignments, including compaction,
ISSUE
R0
ISSUE
R0
ATTACHMENT – XI
ISSUE
R0
Applicant:
COMPANY DETAILS
________________________________________________________________________
____________________________________________________________
6. Head office
Address: ____________________________________________________________
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 2 OF 15 OF
(To be furnished by the bidder)
____________________________________________________________
8. List by name the owner and all executive directors of the company; include nationality,
responsibility area, years of experience, years with the company.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 3 OF 15 OF
(To be furnished by the bidder)
Applicant:
Single companies and each member of the Joint venture are required to submit audited
financial statements for the last three years.
A summary of assets and liabilities derived from the audited financial statements and
converted to Indian Rupees (Rs) as shown in the following:
Rs Rs Rs
Financial Standing
Year 2016-17 Year 2017-18 Year 2018-19
Currency Conversion
Rate
Date of Currency
Conversion
a. Current Assets
b. Fixed Assets
c. Other Assets
d. Short-term debts
e. Long-term debts
f. Net worth
g. Working capital
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 4 OF 15 OF
(To be furnished by the bidder)
4. The annual value of works undertaken for each of the above mentioned years is
shown in the following:
Date of Currency
Conversion
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
__________________
Date:
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 5 OF 15 OF
(To be furnished by the bidder)
Applicant:
1. Please provide the name and address of the established Bank or financial institution that is
providing your credit line:
_____________________________________________________________________
_____________________________________________________________________
_____________________________________________________________________
2. Total amount and type of credit line. This must be stated in a clear and unequivocal terms
on regular Bank letterhead and signed by own authorized representative of the Bank.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 6 OF 15 OF
(To be furnished by the bidder)
Applicant:
MANPOWER
List by category, the total number of employees of the company and the employees resident in
India. List by name and complete the biodata as required, including English language
capabilities of the personnel with relevant experience, detailed CV’s of available personnel are
to be included in Form J:
Executive Directors
General Management
Administrative
Technical/Management
Contracts Management
Site Agent
Others
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 7 OF 15 OF
(To be furnished by the bidder)
Relevant
Years with experience
Category Name Qualification
Company Including contract
values
Executive Directors
General
Management
Administrative
Technical /
Management
Permanent
Employee
Contract Employee
Contracts
Management
Semi-skilled /
Skilled personnel
(Civil, M&E)
Site Agent
Site supervisory
staff (Civil, M&E)
Permanently
Established
Groups (eg.
Process/ Plant
Design etc.)
Others
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 8 OF 15 OF
(To be furnished by the bidder)
Applicant :
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-06 INFORMATION ABOUT BIDDER SHEET 9 OF 15 OF
(To be furnished by the bidder)
Applicant :
1. India
a.
b.
c.
d.
e.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 10 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
2. Other
Countri
es
a.
b.
c.
d.
e.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 11 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
Applicant :
The technical qualification and experience of key staff will form an important part of the
evaluation process. A CV should be attached for each of the staff categories.
The resume for each key person available to be assigned to the project should indicate the
following information. The key personnel shall be associated with this project for the entire
project duration. In case, replacement of key personnel is required, the key person of equivalent
capacity shall be made available with prior approval of Owner.
b. Name : ____________________________________________________
d. Nationality : ____________________________________________________
e. Education : ____________________________________________________
(Enclose photocopy of diploma/certification)
f. Language capability: __________________________________________________
g. Years of experience:____________________________________________________
(State speciality)
h. Countries where : ____________________________________________________
Experience obtained
i. Relevant experience: ___________________________________________________
(State value of projects in Indian Rs., duration of works and position(s) held)
j. Employment history : __________________________________________________
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 12 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
The applicant is required to furnish Project Execution Plan (PEP) in the following format. A brief
but clear PEP is required describing planning and programming of the works.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 13 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
Applicant :
1. List of principal
Plant / Equipment
owned by the
contractor
a) Tower Cranes
b) Cranes (Mobile),
c) Trucks,
d) Concrete Mixers,
e) Batching Plants,
f) Pumps,
g) Other (applicant
to list)
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 14 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
2. List of Plant /
equipment
(owned, Leased,
hired) which
contractor
considers
necessary for this
contract
a)
b)
c)
d)
e)
f)
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV- SHEET 15 OF
3000-3005-06 INFORMATION ABOUT BIDDER
(To be furnished by the bidder) 15 OF
Applicant :
ADDITONAL INFORMATION
The applicant is invited to include any other information that may further demonstrate his
competence to perform the said project works.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
R6.docx R6.docx
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-07 PROFORMA DOCUMENTS/SAMPLE FORMS SHEET 1 OF 4
Sub: Enquiry No - TCE.6842A-CV-3000-3005 - Tender for Road and Storm Water Drain
Works
Dear Sir,
With reference to the above invitation by APL we have examined the ITB and related
annexure for the above WORK downloaded from your website. We hereby offer to provide
the services in conformity with the said ITB conditions and related annexure as per
terms and conditions specified in the BID DOCUMENT.
We undertake to carry out the work as per the time schedule in the ITB.
We understand that APL is not bound to accept the lowest of the BIDs received and may
reject all or any BID without assigning any reason thereof.
We hereby agree that unless and until a formal agreement is prepared and executed in
accordance with the conditions of CONTRACT, this ITB together with your written letter of
acceptance thereof (i.e. LETTER OF INTENT) in case our bid is accepted shall constitute
a binding CONTRACT between us.
Yours faithfully,
Signature:
Name:
Company’s name:
Address:
Dated:
Name of Directors/partners of the Company
TO,
The General Manager (Project),
Project Department,
Assam Petrochemicals Limited,
Namrup, P.O. Parbatpur, Dist- Dibrugarh, Pin -786623,
Assam, India.
Contact Person: Mr. Atul Barman
Tel. No.: 0374-2500331
Fax. No.: 0374-2500231
Email: [email protected]
Dear Sir,
We confirm that we shall be bound by all and whatsoever our representative (s) shall
commit.
Yours faithfully,
Signature....................................................
Name & Designation....................................
For & on behalf of........................................
NOTE:
I. This Letter of Authority should be on the letterhead of the bidder and should be
signed by a person competent and having the power of attorney to bind the bidder.
II. You must send this letter 48 hrs in advance to scheduled Pre-Bid Meeting as
mentioned in the ENQUIRY. Non submission of this letter in stipulated time period
will be considered as not willing to attend the Pre-Bid Meeting.
ISSUE
R0
TO,
The General Manager (Project),
Project Department,
Assam Petrochemicals Limited,
Namrup, P.O. Parbatpur, Dist- Dibrugarh, Pin -786623,
Assam, India.
Contact Person: Mr. Atul Barman
Tel. No.: 0374-2500331
Fax. No.: 0374-2500231
Email: [email protected]
Dear Sir,
We confirm that we shall be bound by all and whatsoever our representative (s) shall
commit.
Yours faithfully,
Signature.................................................
Name & Designation................................
For & on behalf of....................................
NOTE:
I. This Letter of Authority should be on the letterhead of the bidder and should be
signed by a person competent and having the power of attorney to bind the bidder.
II. Only One representative will be allowed for attending price bid opening.
III. Bidder’s Representative shall carry this letter and submit it to TCE / CLIENT at the
time of Bid opening.
ISSUE
R0
(Here given particulars of black listing or holiday listing and in absence thereof state "NIL").
(Here given particulars of black listing or holiday listing and in absence thereof state "NIL").
We hereby declared that we have not been placed on any holiday list or black list declared by
Client or TCE, except as indicated below:
(Here given particulars of black listing or holiday listing and in absence thereof state "NIL").
It is understood that if this declaration is found to be false in any particular, Client / TCE ,
shall have the right to reject my / our bid, and, if the bid has resulted in a contract, the
contract is liable to be terminated.
ISSUE
R0
This has the reference to our proposed CONTRACT for Road and Storm Water Drain
Works of APL to be entered into with ASSAM PETROCHEMICALS LIMITED (APL).
For the purpose of section 184/188 of the Companies Act 2013, we certify that to the best of
my/our knowledge:
PLACE:
SIGNATURE OF BIDDER
DATE
Note:
1) The second copy of the certificate duly completed, signed and stamped must be
submitted with Un-priced BID indicating “QUOTED” in proposed contract.
2) The original copy of the certificate duly completed, signed and stamped must be
submitted with Priced BID after filling in the value of the proposed CONTRACT.
ISSUE
R0
This has the reference to our proposed CONTRACT for INR________ for Road and Storm
Water Drain Works of APL to be entered into with ASSAM PETROCHEMICALS
LIMITED (APL)
For the purpose of section 184/188 of the Companies Act 2013, we certify that to the best of
my/our knowledge:
PLACE:
SIGNATURE OF BIDDER
DATE
Note:
3) The second copy of the certificate duly completed, signed and stamped must be
submitted with Un-priced BID indicating “QUOTED” in proposed contract.
4) The original copy of the certificate duly completed, signed and stamped must be
submitted with Priced BID after filling in the value of the proposed CONTRACT.
ISSUE
R0
INTEGRITY PACT
BETWEEN
AND
Preamble
The Principal intends to award, under laid down organizational procedures, Contract/s for
__________________________________________ The Principal values full
compliance with all relevant laws and regulations, and the principles of economic use of
resources, and of fairness and transparency in its relations with its Bidder/s and Contractor/s.
In order to achieve these goals, the Principal will appoint an external independent Monitor
who will monitor the tender process and the execution of the contract for compliance with
the principles mentioned above.
(1) The Principal commits itself to take all measures necessary to prevent corruption and to
observe the following principles: -
a) No employee of the Principal, personally or through family members, will in connection with
the tender for, or the execution of a contract, demand, take a promise for or accept, for
him/herself or third person, any material or immaterial benefit which he/she is not legally entitled
to.
b) The Principal will, during the tender process treat all Bidders- with equity and reason. The
Principal will in particular, before and during the tender process, provide to all Bidders the same
information and will not provide to any Bidder confidential / additional information through which
the Bidder could obtain an advantage in relation to the tender process or the tender execution.
c) The Principal will exclude from the process all known prejudiced persons.
2) If the Principal obtains information on the conduct of any of its employees which is a criminal
offence under the IPC / PC Act, or if there be a substantive suspicion in this regard, the Principal
will inform its Vigilance Office and in addition can initiate disciplinary actions.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-09 SHEET 2 OF 6 OF
INTEGRITY PACT
(1) The Bidder / Contractor commits itself to take all measures necessary to prevent corruption.
He commits himself to observe the following principles during his participation in the tender
process and during the contract execution.
a) The Bidder / Contractor will not, directly or through any other person or firm, offer, promise or
give to any of the Principal's employees involved in the tender process or the execution of the
contract or to any third person any material or immaterial benefit which he / she is not legally
entitled to, in order to obtain in exchange any advantage of any kind whatsoever during the
tender process or during the execution of the contract.
b) The Bidder / Contractor will not enter with other Bidders into any undisclosed
agreement or understanding, whether formal or informal. This applies in particular to
prices, specifications, certifications, subsidiary contracts, submission or non-submission of bids
or any other actions to restrict competitiveness or to introduce cartelization in the bidding
process.
c) The Bidder / Contractor will not commit any offence under the IPC / PC Act; further the Bidder /
Contactor will not use improperly, for purposes of competition or personal gain, or pass on to
others, any information or document provided by the Principal as part of the business
relationship
d) The Bidder / Contractor will, when presenting his bid, disclose any and all payments he has
made, is committed to or intends to make to agents, brokers or any other intermediaries in
connection with the award of the contract.
(2) The Bidder / Contractor will not instigate third persons to commit offences outlined above or
be an accessory to such offences.
Section 3 - Disqualification from tender process and exclusion from future contracts
If the Bidder, before award of contract has committed a transgression through a violation of
Section 2 or in any other form such as to put his reliability or credibility as Bidder into question,
the Principal is entitled to disqualify the Bidder from the tender process or to terminate the
contract, if already signed, for such reason.
(1) If the Bidder / Contractor has committed a transgression through a violation of Section 2 such
as to put his reliability or credibility into question, the Principal is entitled also to exclude the
Bidder / Contractor from future contract award processes. The imposition and duration of the
exclusion will be determined by the severity of the transgression. The severity will be
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-09 SHEET 3 OF 6 OF
INTEGRITY PACT
(2) The Bidder accepts and undertakes to respect and uphold the Principal's absolute right
to resort to and impose such exclusion
(3) Apart from the above, the Principal may take action for banning of business dealings / holiday
listing of the Bidder as deemed fit by the Principal.
(4) If the Bidder / Contractor can prove that he has restored / recouped the damage caused by
him and has installed a suitable corruption prevention system, the Principal may revoke the
exclusion prematurely.
1) Without prejudice to any rights that may be available to the Principal under law or the Contract or
its established policies and laid down procedures, the Principal / Owner shall have the following
rights in case of breach of this Integrity Pact by the Bidder/ Contractors): Forfeiture of EMD /
Security Deposit: If the Principal has disqualified the Bidder(s) from the Tender process prior to the
award of the Contract or terminated the Contract or has accrued the right to terminate the Contract
according to Section 3, the Principal apart from exercising any legal rights that may have accrued
to the Principal, may in its considered opinion forfeit the Earnest Money Deposit / Bid-Security
amount of the Bidder / Contractor.
(2) If the Principal has terminated the contract according to Section 3, or if the Principal is entitled
to terminate the contract according to Section 3, the Principal shall be entitled to demand and
recover from the Contractor liquidated damages equivalent to 5% of the contract value or the
amount equivalent to Security Deposit / Performance Bank Guarantee, whichever is higher.
(3) The bidder agrees and undertakes to pay the said amounts without protest or demur subject
only to condition that if the Bidder / Contractor can prove and establish that the exclusion of the
Bidder from the tender process or the termination of the contract after the contract award has
caused no damage or less damage than the amount of the liquidated damages, the Bidder /
Contractor shall compensate the Principal only to the extent of the damage in the amount proved.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-09 SHEET 4 OF 6 OF
INTEGRITY PACT
(2) If the Bidder makes incorrect statement on this subject, he can be disqualified from the tender
process or the contract, if already awarded, can" be terminated for such reason.
(3) If the Bidder / Contractor can prove that he has resorted / recouped the damage caused by him
and has installed a suitable corruption prevention system, the Principal may, at its own discretion
as per laid down organizational procedures, revoke the exclusion prematurely.
(1) The Bidder / Contractor undertake to demand from all sub contractors a commitment in
conformity with this Integrity Pact. The Bidder / Contractor shall be responsible for any violation(s)
of the principles laid down in this agreement / Pact by any of its Subcontractors / Sub-vendors.
(2) The Principal will enter into agreements with identical conditions as this one with all
Bidders and Contractors.
(3) The Principal will disqualify from the tender process all bidders who do not sign this
pact or violate its provisions.
(1) The Principal appoints competent and credible external independent Monitor
for this Pact. The task of the Monitor is to review independently and objectively, whether and to
what extent the parties comply with the obligations under this agreement.
(2) The Monitor is not subject to instructions by the representatives of the parties and performs
his functions neutrally and independently.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-09 SHEET 5 OF 6 OF
INTEGRITY PACT
(3) The Contractor accepts that the Monitor has the right to access without restriction to all
Project documentation of the Principal including that provided by the Contractor. The Contractor
will also grant the Monitor, upon his request and demonstration of a valid interest,
unrestricted and unconditional access to his project documentation. The same is applicable
to Sub-contractors. The Monitor is under contractual obligation to treat the information and
documents of the Bidder / Contractor / Sub-con tractor with confidentiality.
(4) In case of tenders having an estimated value of INR 100 Crore, the Principal will provide to
the Monitor sufficient information about all meetings among the parties related to the Project
provided such meetings could have an impact on the contractual relations between the
Principal and the Contractor.
(5) As soon as the Monitor notices, or believes to notice, a violation of this agreement, he will so
inform the Management of the Principal and request the Management to discontinue or to
take other relevant action. The Monitor can in this regard submit non-binding
recommendations. Beyond this, the Monitor has no right to demand from the parties that
they act in a specific manner, refrain from action or tolerate action.
(6) The Monitor will submit a written report to the CEO of the Principal within 2 weeks
from the date of reference or intimation to him by the 'Principal' and, should the occasion
arise, submit proposals for correcting problematic situations.
(7) If the Monitor has reported to the CEO of the Principal substantiated suspicion of
an offence under the IPC / PC Act and the CEO has not, within reasonable time, taken visible
action to proceed against such offence or reported it to the Vigilance Office, the Monitor may also
transmit this information directly to the Central Vigilance Commissioner, Government of India,
(8) The word 'Monitor' would include both singular and plural.
This Pact begins when both the parties have legally signed it. It expires for the Bidder / Contractor
12 months after the completion of work under Contract or till the continuation of guarantee period,
whichever is more and for all other bidders, till the contract is awarded.
If any claim is made / lodged during this time, the same shall continue to be valid despite the lapse
of this pact as specified it is discharged / determined by the CEO of the Principal.
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
DOC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: E
TCE.6842A-CV-
3000-3005-09 SHEET 6 OF 6 OF
INTEGRITY PACT
1) This agreement is subject to Indian Law. Place of performance and jurisdiction is the Registered
Office of the Principal, i.e. Guwahati.
2) Changes and supplements as well as termination notices need to be made in writing. Side
agreements have not been made.
3) If the Contractor is a partnership or a consortium, this agreement must be signed by all partners
or consortium members.
4) Should one or several provisions of this agreement turn out to be invalid the remainder of this
agreement remains valid. In this the parties will strive to come to an agreement to their original
intentions.
WITNESS 1
WITNESS 2
Place : _____________________________
Date: ____________________________
ISSUE
R0
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: E
SPEC. NO.
TCE.M4-917
SAFETY CONDITIONS FOR UNDERTAKING SITE WORK SHEET 1 OF 9
1.0 SCOPE
2.1 Each CONTRACTOR at site shall organise a Safety Group headed by a Safety
Officer who shall be responsible for providing, supervising and monitoring safe
working conditions at all times for their workers. The Safety Officer shall be
experienced in maintaining safe conditions for workers at site and shall be
responsible for and shall have authority to enforce safe conditions for the
workers.
2.2 The CONTRACTOR shall have a declared Safety Policy and shall get the same
approved by the PURCHASER/CONSULTANT. The approved Safety Policy
shall be displayed prominently in the CONTRACTOR’s site office.
2.3 The CONTRACTOR shall take active interest and participate in the
development and operation of safety programs at site. His responsibility does
not cease with establishment of Safety Group and approval of its various
activities. He shall demonstrate his involvement by regular participation in safety
meetings, review of safety records and taking corrective action where required,
introduction of safety promoting bulletins, posters, suggestions and awards and
by setting example by strictly observing safety rules.
2.4 The CONTRACTOR shall remove all waste material and debris from and
around the work area and properly clean up the area at the end of each day
before leaving the work site.
2.5 The CONTRACTOR shall take all necessary precautions not only for safe
working of his own workmen but also deploy all precautions to ensure safety of
structures, equipment and workmen of other agencies in and around his work
site.
2.6 The CONTRACTOR shall ensure that his workmen do not trespass into
prohibited areas.
2.7 The PURCHASER/CONSULTANT shall have the right to inspect at any time, all
items of machinery or equipment brought to site by the CONTRACTOR, his
agents or workmen and to prohibit the use on the site of any item, which in the
opinion of the PURCHASER/CONSULTANT is or may be detrimental to the
safety of the site. The exercise of such right or the omission to exercise it in any
particular case shall not absolve the CONTRACTOR or his agents or workmen
of their responsibility of adhering to the safe working practices.
2.8 The CONTRACTOR shall execute the work in a manner causing the least
possible interference with the business of the PURCHASER/CONSULTANT, or
with the work of any other CONTRACTOR who may be engaged on the
premises and shall at all times co-operate with the other CONTRACTORS
working at site.
ISSUE
R2
2.9 The CONTRACTOR shall obtain work permit from the PURCHASER/
CONSULTANT before starting any work at site. The work permits are issued to
prevent the CONTRACTOR from working in unauthorised areas and shall be
valid for specific area for a stipulated period
2.10 The CONTRACTOR shall ensure at all times that his workers do not lie down or
sleep under or around any machine, equipment, vessel or vehicle in his work
area.
(b) Instituting ways to improve existing work methods from safety point of
view.
(d) Provision and use of protective clothing and equipment and use of fire
fighting equipment
(h) Carrying out site surveys to see that only safe work methods are in
operation, health and safety requirements are being observed and
welfare and first aid facilities are adequate and properly maintained.
ISSUE
R2
2.11.2 The Safety Officer shall inspect and ensure the following:
(b) Standard access platforms and ladders are provided for inspection,
operation and maintenance of equipment.
For carrying out work at heights exceeding 2 meters or near openings in floors
and roofs etc. precautions as given in following paras shall be taken.
3.1 Adequate safety precautions like use of safety belts, crawling-ladders, safety
nets etc. shall be taken. The workers shall wear safety belts with hook properly
fastened.
3.2 All workmen engaged on work at heights shall be experienced in such work.
3.5 Staging with toe guards shall be provided with simple safety rails or ropes at
waist height throughout its length on all open sides.
3.6 Staging supports shall be All Purpose Scaffolding (APS) steel tubes scaffolding,
safety secured and supported on firm level footings or slung from overhead
beams. The supports shall be situated at maximum distance of 2.5 metres apart
and the staging shall be secured to each support.
3.7 Wherever it is not possible to put up staging and/or use of safety belts and
safety nets, steel sheets shall be slung beneath the place of work for safety.
3.8 When working over open process vessels or tanks, safety belts and safety nets
shall always be used whether or not staging and scaffolding is provided.
3.9 Safe access to all points of works shall be provided in the form of suitable
ladders and stairways etc.
3.10 Area around the work place shall be barricaded suitably or fenced off to avoid
ISSUE
R2
injuries to personnel passing by. Suitable warning boards and signs shall be put
up.
4.0 EXCAVATION
5.2 These certificates shall be available at site in the CONTRACTOR’s office for
inspection as and when required.
6.1 Pressure and leak testing of equipment shall be carried out hydraulically.
However, in special cases where pneumatic testing is specified, written approval
shall be obtained from the PURCHASER/CONSULTANT before starting work.
Under no circumstance gases other than nitrogen, carbon dioxide, air or steam
shall be used for testing.
6.2 In case nitrogen or carbon dioxide is used for testing, the equipment shall be
adequately ventilated and gas tested to ensure oxygen content of 21% before
permitting a worker to enter the equipment.
7.1 All equipment and associated piping shall be isolated, completely drained,
purged and well ventilated before entry of a worker. The atmosphere inside the
vessel or equipment shall be tested to ensure absence of toxic and flammable
gases.
7.2 Toxic and flammable liquids and gases in the equipment shall be safely
disposed off as per the instructions of the PURCHASER/CONSULTANT.
7.3 Workers carrying out drainage, purging and testing operations shall wear gas
masks and other protective gear appropriate to the material being handled.
7.4 While a worker has entered an equipment or a drainage system, another worker
shall be present outside at all times to assist the worker inside in the event of an
emergency.
8.0 ELECTRICAL
ISSUE
R2
8.1 Portable power tools rated for above 50 V supply and hand lamps rated for
above 24 V supply shall not be used at site.
8.2 An armoured cable with a 3 pin Reyrolle type plug, properly earthed shall be
provided between the CONTRACTOR’s DG set and step down transformer.
8.3 All power supply and distribution boards shall have canopy for protection and all
the distribution boards shall be earthed securely.
8.4 All supply points shall have proper plug and socket.
9.0 WELDING
9.1 Only qualified welders shall be employed at the work site. The CONTRACTOR
shall organise the qualifying test at site for his welders and the PURCHASER/
CONSULTANT shall approve the welders. All welders shall have to undergo
qualifying test and only on passing the test, they shall be allowed to work at site.
9.2 For all welding work at site, generator sets shall be used instead of AC
transformer sets. AC transformer sets are banned for welding jobs inside
vessels (both open and closed top type).
9.3 The CONTRACTOR shall get his welding sets certified by the PURCHASER/
CONSULTANT before starting work. These certificates shall have to be
renewed every two months. A copy of the certificates shall be displayed on
respective welding sets.
9.4 Only cables in good condition and insulated holders shall be used. The length of
supply cable to welding site shall not exceed 8 metres and the welding set body
shall be properly earthed.
9.5 A charged fire extinguisher of CO2 type shall be carried with each welding set.
The CONTRACTOR shall keep Halon or equivalent type fire extinguishers near
hot jobs like cutting oil lines.
9.6 The welder shall not use a building structure, pipeline or railway track etc. as a
return path of the current. Adequately rated circuit breaker shall be provided in
the power circuit for human protection on all power supply points.
10.1 Before starting any hot work like gas cutting, welding and grinding etc., the
CONTRACTOR shall obtain hot work permit from the PURCHASER/
CONSULTANT. The permit shall be renewed on day-to-day basis.
10.2 The CONTRACTOR shall ensure purging of piping and equipment to make it
totally safe before carrying out any hot work
ISSUE
R2
10.4 At permitted locations, cigarette ash or butts shall be disposed off only in ash
trays provided.
10.5 No combustible material shall be stored on or near any source of heat like hot
pipes, welding or gas. Before leaving the place of work or the CONTRACTOR’s
sheds, the CONTRACTOR’s workmen shall ensure that no material or item that
could start a fire is left at site. Special attention shall be paid to collection and
disposal of oil soaked cotton waste or rags. On no account are these to be
dropped into corners, pushed below equipment or left hanging on pipes.
10.6 Gas cylinders shall be used in a safe manner. These shall not be dropped from
heights or dragged on the floor. Trolley with rubber rimmed wheels shall be
used for transporting gas cylinders within the site. Acetylene cylinders shall be
kept in upright position. Oxygen cylinders shall not be kept near inflammable
materials like oil etc.
10.7 Tarpaulins shall not be used in the vicinity of welding and gas cutting jobs.
10.9 The CONTRACTOR shall return the hot work permit after completion of welding
work.
11.1 Workmen shall wear protective clothing, head, leg and eye protection safety
equipment at all times as per the job requirements. These are to be supplied
and provided by the CONTRACTOR.
11.3 Welders shall wear good quality insulated welding gloves, goggles, face shield,
shoes and overalls while at work.
12.0 ACCIDENTS
13.0 INSURANCE
ISSUE
R2
All the CONTRACTOR’s workmen shall be covered under the Employees State
Insurance Scheme, Janata Policy or any other scheme which may be specified
by the Statutory Authorities from time to time.
15.1 Extra care shall be taken for jobs to be carried out after normal working hours
with due revalidated work permit and supervised by the CONTRACTOR’s site-
in-charge. The site-in-charge shall make available his residential address and
telephone number to the PURCHASER/CONSULTANT so that he can be
contacted in case of an emergency.
15.2 Proper lighting shall be ensured at the workplace for any work carried out after
the normal working hours.
The CONTRACTOR shall ensure that conveyance and person with driving
license is available at site at all times of work execution so that in case of an
accident, the victim can be rushed to nearest medical centre.
17.1 Avoid working under un-insulated live conductors or working on freshly painted
steel, which is still wet.
17.2 Stairs and railing shall be in place as long as necessary. Ladders shall be
periodically checked for any defects. Ladders shall be securely fastened to
prevent movement while in use.
17.3 The CONTRACTOR shall advise his workmen to take the following precautions
while using ladders:
(a) While ascending or descending, face the ladder. Use both hands for
holding.
(b) Do not climb higher than the third rung from top on straight or
extension-ladders and second rung from top on set ladders.
(e) Make shift ladders such as clear fastened across a single rail and short
ladders spliced together shall never be used.
ISSUE
R2
(h) Ladders shall not be left un-attended unless these are securely
anchored at top and bottom.
(i) While using ladders, shoes shall not be greasy, muddy or otherwise
slippery.
17.4 Lumber shall be piled out of the work area. Nails shall be removed or bent while
handling lumber to avoid injury to workmen.
17.5 While tearing down plaster or brickwork, dust shall be controlled with water.
17.6 Walls shall not be subjected to lateral pressure or impact from materials stored
or falling materials.
17.7 The safety valves for boilers shall be set by trained personnel and shall be
sealed or padlocked at safe working pressure. Only authorised person shall
change the setting of safety valves. The safety valve relieving pressures shall
be checked as recommended by the manufacturer and applicable codes.
17.8 Blow down valves shall be operated strictly as per instructions. If blow cock is
not marked with an arrow to show open and close position, the same shall be
marked at site.
17.9 Safety slogans and safety instructions shall be prominently displayed in English,
Hindi and local language at strategic locations.
18.1 The CONTRACTOR shall familiarize himself with the emergency procedures,
which apply to plants and areas in which his men are working.
18.2 First Aid Box shall be kept in the CONTRACTOR’s site office. The
CONTRACTOR’s site-in-charge and his key supervisors shall be trained in
administering first aid, preliminary treatment for electrical shocks, fall from
height and burns etc.
18.3 When an emergency condition exists or on hearing the ‘Stop Work Alarm’ every
supervisor shall ensure:
ISSUE
R2
(e) No one shall be permitted to return to work until notification has been
received from a responsible authorised agency that it is safe to do so.
19.1 Understand the company’s policy on maintaining safe working environment and
appreciate the responsibility allocated to each grade of supervision.
19.2 Know the safety requirements and relevant Government Regulations, and
ensure their implementation.
19.3 Ensure that sound, safe working methods and reasonable welfare facilities are
provided for workers.
ISSUE
R2
1.2.2 The CONTRACTOR shall also nominate in writing competent Safety Appointees
(SAs) from various disciplines to assist the SR in implementation of health and
safety measures in their routine contract works. The SR shall have sufficient
authority to direct the CONTRACTOR's or his SUB-CONTRACTOR's personnel
to meet health and safety requirements and to stop performance of work until
such requirements are met.
1.3.1 The CONTRACTOR shall ensure full involvement of all his employees
recognising their right to consultation on health and safety matters. The safety
appointees of the various areas, in conjunction with the SR shall be responsible
for ensuring employees' involvement through routine safety inspections, hazard
and risk assessment in new and changed works and their control. The
CONTRACTOR shall maintain appropriate operating procedures to guide these
requirements.
1.3.2 The CONTRACTOR shall also appoint a Safety Committee (SC) comprising of
the SAs from the various areas under the chairmanship of the SR. The
committee shall meet at periodic intervals to discuss the status and adequacy of
the safety management, and any safety concerns of the employees. The
ISSUE
R1
committee shall also formulate and validate the safety procedures incorporating
controls to prevent or mitigate hazards and risks before submission for approval
by the PURCHASER/CONSULTANT. The minutes of the SC meeting shall be
submitted to the PURCHASER/CONSULTANT. The SR shall maintain the
records of the meetings.
1.4.1 The CONTRACTOR shall submit a monthly written report to the PURCHASER/
CONSULTANT, which shall be due on the fifth workday of every month. The
health and safety of all full time, part-time, permanent, temporary, contract
employees and any outsourced employee undertaking any part of the
CONTRACT works shall be included in the safety report. The report shall
include the total number of working hours for the month, the number of
recordable accidents and the number of lost-time accidents. A cumulative trend
plot of the monthly severity and frequency rate of the reportable accidents shall
be included in the monthly safety report and calculated as:
1.4.2 The CONTRACTOR shall arrange to display the safety statistics and the
cumulative plot of severity and frequency of accidents mentioned above painted
on a board prominently displayed, as a means of encouragement and
assurance to all interested parties and for publicising the safety achievements.
1.5.1 ‘Accident’ for the purpose of this para is defined as ‘Undesired Event Giving
Rise to Death, Ill-health, Injury, Damage or other Loss’ and ‘Incident’ is defined
as ‘Event that gave rise to an Accident or had the Potential to lead to an
Accident’. An accident where no ill health, injury, damage or other loss occurs is
also referred to as ‘Near-Miss’. Incident includes Near-Miss. The
CONTRACTOR shall report orally, to the PURCHASER/CONSULTANT
regardless of their extent, duration and severity, immediately on occurrence of
all accidents resulting in:
ISSUE
R1
(c) Fires
(d) Spills
(e) Near-Misses
1.5.2 The CONTRACTOR shall submit the accident and incident report in writing to
the PURCHASER/CONSULTANT within 24 hours of its happening in the form
as prescribed by the governing statute or in the absence of which, in the form
prescribed by the PURCHASER/CONSULTANT. The CONTRACTOR shall
detail in the ‘Accident/Incident Report’, the particulars of the dangerous
occurrence leading to the accident, lost time of absence due to accident, root
cause analysis and the corrective and preventive actions to prevent such
recurrence. In addition, the CONTRACTOR shall include his estimate of the
impact of accident on project schedule. Incidents shall also be reported in the
same manner identifying root cause/s to eliminate such potential occurrence or
risks.
1.6.1 The CONTRACTOR shall make available first-aiders, first-aid boxes and or first-
aid stations as per statutory requirements. The persons holding current
certificates of competency of recognised institutions in prescribed numbers as
per any governing statute and in the absence of such regulatory requirement a
minimum of two first-aiders for each area of work for every hundred workmen.
First-aiders' names shall be prominently displayed.
1.6.2 The first-aid boxes shall display contents of medical and medicinal articles with
quantity maintained, which shall be in accordance with governing statute.
Nominated first-aider shall replenish stock promptly.
1.6.3 The first-aid refresher training shall be provided at least once in a year and all
employees shall be encouraged to undergo first-aid training. A record shall be
kept of all first aid treatments with particulars of treatment and personnel
providing the treatment.
1.7.1 Where required by the CONTRACT, the CONTRACTOR shall establish and
maintain an Occupational Health Centre where hazardous Processes are
involved such as roof work, steel work, working above or below water,
demolition and confined space. Where the PURCHASER maintains the
Occupational Health Centre facilitating the CONTRACTOR, such a facility shall
meet the requirements laid by the governing statute and this shall be stated in
the CONTRACT. Where the CONTRACTOR out-sources such facility, it shall
meet the statutory requirements and shall be approved by the
PURCHASER/CONSULTANT and the statutory body.
ISSUE
R1
1.7.2 The Occupational Health Centre shall be served by a full time medical officer
holding a medical degree in allopathic medicine with a minimum of five years
experience in Occupational Health/Medicine. A nurse, one dresser/compounder
and one sweeper-cum-ward boy who will all be available during entire
construction operation during the day shall assist the medical officer. One
additional Medical Officer shall be posted for every additional thousand
Construction workmen along with the team of nurse, compounder and ward boy
The PURCHASER shall arrange for an ambulance room and an ambulance van
directly or outsource the facilities meeting the governing statutory needs for
prompt transportation of serious cases accident and or sickness to the hospital.
Such facilities shall be maintained in good repair and equipped with facilities
such as dry powder type extinguishers, flashlights, portable oxygen unit, self-
contained breathing apparatus etc. as prescribed by the governing statute.
1.9.1 The CONTRACTOR shall maintain a procedure for identification of the training
needs and training his employees to create a health and safety conscious work-
force that will comply with the law and safety requirements of the Organisation.
He shall also maintain a procedure for safety induction and initial training as well
as follow-up training on the job safety for new entrants. All employees shall
receive effective training and periodic refresher training on the operation control
procedures specific to their tasks designed to control the job-safety risks. A
booklet of such operation control procedures and safety rules with need based
pictorial illustrations shall be made available to all employees who are to learn
and be familiar with such procedures. All training shall be monitored for
effectiveness as per established procedures. The CONTRACTOR shall maintain
records of all training.
1.9.2 The SR and the SAs shall conduct regular fortnightly or weekly mock-safety
drills for different imaginary accident scenarios, in premeditated work areas to
provide on-job training such as:
ISSUE
R1
(d) First-aid
1.9.3 Participants shall receive training during mock-drills through role-play of their
normal expected tasks during emergencies and fire fighting. The degree of
demonstrated ability in the chosen tasks during such safety drills shall be
recorded as participants' competence level for planning his further training. The
experience gained in mock drills shall be used to update of operational control
procedures and the training needs. The roster of participants and contents for
routine mock-drills shall be appropriately planned to cover all employees in the
training at least once in four months.
Safety posters, banners and slogans displayed for safety promotion shall be
rotated at frequent intervals. The CONTRACTOR is encouraged to have safety
promotion as an item in the SC agenda. The CONTRACTOR is encouraged to
include safety promotion programmes such as: safety bulletins, magazines,
competitions in slogan and poetry writing on safety, screening of safety films,
celebration of national safety and environmental day, safety suggestion
schemes and safety library etc.
1.11.1 The CONTRACTOR shall maintain a procedure for control of his purchases to
ensure that all safety requirements are appropriately vetted by the safety
personnel during all stages of procurement including planning of specifications,
inspection for acceptance and commissioning in order that threats to safety are
not overlooked and appropriate attention is paid to the training of personnel in
the operation of the CONTRACTOR's new or changed machinery and their
operation control procedures, to prevent/control risks.
1.11.2 The CONTRACTOR shall exercise due diligence in appointing his SUB-
CONTRACTORS and outsourcing contract services, that no new health and
safety threats are created. The CONTRACTOR shall ensure personnel of SUB-
CONTRACTORS and outsourced contract services are competent in health and
safety management to meet the POLICY requirements. They shall be made
aware of the safety rules, emergency procedures and any information that will
have a bearing on the safety, health and related contractual obligations
1.12.1 The CONTRACTOR shall ensure that his key personnel and safety personnel
ISSUE
R1
1.12.2 The CONTRACTOR shall maintain a Hazard Identification, Risk Analysis and
Risk Control Manual (HIRARC) pertaining to all his activities duly updated as
detailed above. The HIRARC manual shall be made available to the
PURCHASER/CONSULTANT during regular inspections and audits
1.13.1 The CONTRACTOR shall maintain a work permit procedure to limit the
hazardous processes and high risks tasks to authorised personnel, who shall be
informed of the job safety analysis and the job specific safety precautions, on
issue of a work-permit. The work permit issued under the procedure shall be
valid for a specified period and shall be issued only after all safety precautions
are fulfilled and duly verified by the SR or the SA or specialist who is authorised
for safety certification as a prerequisite for issue of a work permit. The work
permit shall be appropriate for the purpose for which it is issued. Various work-
permits are:
HWP shall be used where hot working, like electric or gas welding, gas
cutting, or burning or any other operation involving heating, open
flames or electric arcs, grinding and electrical works etc. are potentially
dangerous in areas such as inflammable materials storage, plant and
pipe lines handling inflammable and or explosive materials either
presently or in the past, or where new works are undertaken adjoining
such works which in the opinion of the PURCHASER/CONSULTANT
are potential risks. A HWP shall be deemed mandatory in all such
potentially dangerous areas. The CONTRACTOR shall get areas such
as welding shops or maintenance areas approved by the
PURCHASER/CONSULTANT for 'Permit-Free' operation.
CSP is issued for entering and carrying out tasks in confined space.
ISSUE
R1
Confined spaces shall include but not limited to storage tanks, process
vessels, bins, boilers, ventilation or exhaust ducts, sewers,
underground utility vaults, tunnels, pipelines and open top spaces more
than 4 feet in depth such as pits, tubs, vaults and vessels.
1.14.1 The CONTRACTOR shall maintain a procedure for Safety Inspection at routine
intervals to provide assurance that the instituted safety procedures are in place
to prevent deviations from established standards that could lead to a safety
hazard and consequential risk. The CONTRACTOR shall establish appropriate
standardised checklists for systematic job safety verification to ensure
ISSUE
R1
1.14.2 Should the existing operation control procedures prove inadequate and the
residual risks are higher than tolerable levels, the SR shall initiate hazard and
risk assessment and analysis and consultations with the SC to deploy
appropriate remedial measures and improved operation control procedures.
Periodic inspection reports and proposed remedial measures shall be submitted
to the PURCHASER/CONSULTANT. Records of changes change processes;
consultations with the SC and revision of operational controls shall all constitute
objective evidence of the existence of established procedures.
1.15.1 The CONTRACTOR shall undertake periodic safety audits to confirm through
investigative methods the effectiveness of the measures set out in the POLICY.
In order to be effective such safety audit shall be comprehensively covering all
aspects detailed in this specification to ensure effective loss-control/accident
prevention programme. Safety audits shall take into account the safety
inspection records, remedial measures and effectiveness of the safety
programme. Effectiveness of safety programme shall be based on the
CONTRACTOR’s effective hazard identification and risk assessment processes
for design of operation control procedures and on the safety statistics. Audit
reports and preventive actions and safety improvement programmes shall be
submitted to the PURCHASER/CONSULTANT.
2.1.1 The CONTRACTOR shall ensure that all his equipment and machinery are safe
to use while in motion or working. Operators shall have received training or
instruction on operation of the machinery and the regulatory requirements. The
CONTRACTOR shall have adequate procedure to ensure the stability and
securing of his working machinery during operation. He shall restrict repair and
maintenance of the machinery to trained personnel and maintain records of
repairs and maintenance. The equipment shall have appropriately designed
means of isolating from sources of energy and shall have emergency stop
control, which is easily accessible. All controls shall be clearly and uniformly
marked. All operation controls, interlocks, sensing devices and guards on tools
and equipment shall be functional and their status shall be regularly checked
and recorded. The CONTRACTOR shall provide evidence of compliance to
these requirements in any contractual write-ups submitted to the PURCHASER/
CONSULTANT for approval in respect of critical construction/contract works.
2.1.2 The CONTRACTOR shall provide only good quality hand tools and ensure
control of condition, storage, routine inspection and use of such hand-tools.
Unsafe tools such as with cracked or broken handles, mushroomed chisels and
ISSUE
R1
2.1.3 All safety ladders, scaffolding and such access equipment shall meet
requirements of IS 3696 and IS 4014 and such standards as the
PURCHASER/CONSULTANT may stipulate. The safety work permits shall be
issued only after ensuring that all safety requirements of access equipment are
complied with. Access equipment shall be inspected on a routine basis to
prevent injuries caused by falls.
2.1.4 The CONTRACTOR shall ensure safety of all those concerned with lifting and
those who may be affected by material hoisting, lifting and handling using
various mechanical aids. All lifting equipment such as cranes, hoists, lifting
shackles, hooks chains and links shall be designed as per appropriate
International codes of construction. Operators shall have been trained in
operation and maintenance of such equipment besides training on standard
hand signals to be employed during the hoisting and lifting operations. Safe
Working Loads (SWL) shall be marked on equipment prominently. SWL shall be
evidenced to have been established by test procedures in accordance with
acceptable codes of practices.
2.1.5 Riding on construction equipment, forklifts and cranes shall be prohibited unless
such vehicles are provided with passenger seats.
2.1.6 Pressurised gas and air systems shall be maintained safe in good working order
and shall meet the requirements of the Factories Act 1948, The Static and
Mobile Pressure Vessels Rules 1984 and the Gas Cylinder Rules 1934 as
applicable. The safety relief valves, safety appurtenances and isolation systems
shall be compliant with safety code of practices. Any statutory register of
pressure vessel records and the code of practices shall be subject to periodic
auditing by the PURCHASER/CONSULTANT.
2.1.7 The areas of highly dangerous activities like hoisting, lifting and rock blasting,
and radiation, shall be appropriately barricaded to protect personnel and
machinery and guided by work permit discipline. Emergency plans shall cater to
emergencies arising out of such activities.
2.1.8 Signs, barricades, barrier tapes and warning or entry restriction devices or
accessories shall be provided to minimise work related risks of accidents and
injuries. Signage shall meet all regulatory requirements such as under The
Building and other construction workers Act 1996, Factory Act 1948,
Manufacture, Storage, Import of Hazardous Chemicals Rules under
Environmental Protection Act 1986, Indian Explosives Act 1984 and Gas
Cylinder Rules 1981 and Indian Electricity Act 1910 and Rules there of and any
other safety requirements of the PURCHASER/CONSULTANT.
2.2.1 The CONTRACTOR shall provide only such equipment for work that is
electrically safe to work. The CONTRACTOR shall have a procedure to identify
and record all his electrical equipment in a register, with provisions to record his
ISSUE
R1
2.2.2 Approved earth leakage relays or alternative safety devices to relevant IS and
International codes shall be used on all portable electrical hand tools. Where
possible low-voltage electric power supply shall be used for hand tools, earth
leakage units shall protect electrical installations in workshops, kitchens,
cafeterias, first-aid rooms, laboratories and offices. Record of regular checks
shall be maintained. The CONTRACTOR shall comply with ‘Code of Practice for
Earthing’ as per IS 3043.
2.2.4 The CONTRACTOR shall arrange displaying signage under Indian Electricity
Act 1910, such as:
2.2.5 All power cables providing construction power to various construction machinery
and the connectors shall be in safe and sound condition. Cables shall be routed
through cable trays supported on appropriately designed structures, duly
clamped, secured and identified. Road crossing cables shall be laid in conduits
buried at least 600 mm below the surface to prevent damage due to vehicular
traffic. All cables shall be off the floor to avoid damage or tripping hazard.
Cables shall be terminated at the switchgear and sockets in a workman like
manner to prevent loose contacts and flashover. Only safety receptacles shall
be used for providing power connection to hand-tools. All switches and
distribution boards shall be clearly marked. All electrical distribution and panel
wiring diagrams shall be available with the electrical maintenance personnel.
The CONTRACTOR shall maintain a safe electrical isolation/lockout procedure.
2.2.6 The CONTRACTOR shall ensure lighting circuits are not used for hand-tools.
ISSUE
R1
2.4.1 The CONTRACTOR shall prevent all injuries, illnesses and damage to property
or the environment caused by any article or substance, which proves to be
hazardous. The code of practices of construction and operation and
maintenance and control procedures shall meet required statutory and
regulatory requirements. Personnel shall be trained on use, handling, storage,
disposal and emergency spillage procedures.
2.4.2 The CONTRACTOR shall detail and deploy operational controls to reduce
hazardous wastes and their disposal as required by the statute ‘Hazardous
Waste (Management and handling) Rules 2000’. Oil wastes, used oils, soil and
cotton soaked in oil consequent to handling operations, grease and many class
of paints and asbestos sheets and gaskets are typical hazardous wastes.
2.4.3 The CONTRACTOR shall identify, contain and control all sources of radiation.
Appropriate regulatory approvals shall be obtained before commencement of
work involving radiation sources. Radiation protection advisors suitably qualified
and experienced shall be appointed whose names shall be submitted to
PURCHASER/CONSULTANT. Dosimetry and surveillance of personnel
engaged in such work shall be maintained in accordance with regulatory
requirements.
The CONTRACTOR shall provide his employees required PPE meeting the
requirements of the stated IS specifications and guidelines or equivalent
International Standards as may be prescribed by the PURCHASER/
CONSULTANT from time to time. The CONTRACTOR shall have instituted
good working procedures and practices in providing PPE, maintenance, issue
and training on their use. All PPE shall be periodically checked to ensure worn,
damaged equipment are replaced expeditiously.
ISSUE
R1
The CONTRACTOR shall comply with requirements of IS 2925. Hard hats shall
be used and worn where a hazard of falling or flying objects exist. Hard hats
intended for use by visitors shall have replaceable paper lining.
Eye protection shall be worn during all operations by operators and people in
the vicinity, where there is a danger of flying particles of metal such as
generated during use of hand tools such as chisels, grinding, welding and
cutting lathe work on brass and cast iron acid and alkali splash, high pressure
jet cleaning or insulation removal from heights using high pressure jets. The
CONTRACTOR shall meet the requirements of IS 8520 entitled ‘Guide for
Selection of Industrial Safety Equipment for Eye, Face and Ear Protection’.
3.1.4 Footwear
Safety shoes, boots and gumboots fitted with steel toe-caps of approved quality
conforming to prescribed Indian or international standards. Wearing of unsafe
safety shoes such as jogging shoes, tennis shoes, slippers and sandal etc. are
prohibited. The CONTRACTOR shall meet the requirements of IS 10667 entitled
‘Guide for Selection of Industrial Safety Equipment for Protection of Foot and
Leg’.
ISSUE
R1
ISSUE
R1
3.2.1 The CONTRACTOR shall have procedures to identify risks involved in manual
handling operation and tasks. The CONTRACTOR shall ensure appropriate
training to prevent any possible injury. Full use of mechanical aids shall be
made to avoid risks arising out of such manual handling. Employees shall be
adequately trained on such manual tasks and related safety precautions to
reduce the risk of injury to personnel engaged in such work.
4.1.1 Where the PURCHASER maintains the fire protection equipment, the
CONTRACTOR shall comply with the PURCHASER's fire regulations, warning
signals and procedures. The CONTRACTOR shall arrange to train his
personnel meeting the prescribed qualifying competence needs, in requisite
numbers in the operation of such fire protection equipment and systems.
4.1.2 Risk assessments shall be carried out to identify potentially vulnerable areas to
provide sufficient quantities of correct type of extinguishers and ancillary
equipment to deal with various types of fire hazards.
4.1.3 Where required under the CONTRACT the CONTRACTOR shall provide
appropriate type of extinguishers close to areas of fire hazard but not too close
they are cut off from use during a fire. Water based extinguishers shall not be
positioned close to or used on electrical equipment.
ISSUE
R1
4.1.5 The location of fire fighting equipment shall quickly and easily be identifiable
especially in emergencies in a conspicuous manner painted as high as possible
to identify the location of the extinguisher to prevent it from being obscured by
machinery and goods stacked in front and to return the equipment to its location
after emergency use in other locations. In order to ensure this, ‘Keep Clear’ area
shall be demarcated and maintained. Location plans of extinguishers and fire-
fighting equipment shall be prominently displayed when desired by the
PURCHASER/CONSULTANT.
4.1.6 SR and SAs shall be trained on fire fighting techniques who shall co-ordinate
and control fire protection and prevention programmes.
4.1.7 Where required under the CONTRACT, the CONTRACTOR shall maintain
alarm systems powered by mains and by battery for back-up. Where required
under the CONTRACT, emergency lighting shall be provided to aid evacuation
in poor lighting conditions following the alarm. The alarm system shall be made
known to all employees. When the PURCHASER extends these facilities for use
by the CONTRACTOR, he shall provide appropriate training to his personnel in
the use of such emergency facilities and duties
4.1.8 A clear written procedure for action in the event of fire should be produced. Fire
teams and hose teams shall be identified and their responsibilities during
emergencies shall be detailed in writing. Personnel shall be trained on their fire
duties and use of fire-fighting equipment. Regular drills shall be conducted to
test procedures and to validate them. Fire instructions and emergency
procedures shall be displayed throughout the premises. Emergency response
procedures are detailed under para 5.0 below.
4.1.9 A means of escape shall be provided in all work areas and storages and
maintained and kept free from obstruction. All exits shall be clearly marked and
kept unlocked whilst the premises are in use. Escape routes shall be protected
from fire.
4.1.10 When a hot work permit is issued, the CONTRACTOR shall ensure
(b) Determination that flammable vapours and liquids are not present
(d) Determination that sprinkler and hydrant and other installed fire
systems are functional
ISSUE
R1
(g) Workmen performing the task are adequately briefed on job safety
analysis, hazards and risks and the safeguards against risks.
4.2 SECURITY
4.2.1 Where required under the contract, security personnel shall do all that is
reasonably practicable to ensure the safety of employees and property of the
company in the face of accidents by fighting fires and containing losses due to
pilferage, theft, vandalism and industrial espionage both by employees and
external elements. Security personnel shall be appropriately competent and
receive adequate safety training. Security personnel shall routinely report on a
standardised basis on aspects such as violation of fire-protection rules, use of
alcohol and narcotic drugs, condition of security fencing, floodlighting and
storages etc.
4.2.2 Where the project is located where a number of other companies are in
operation, the CONTRACTOR shall plan for mutual assistance programmes in
cases of emergencies, as are practiced in the area in conjunction with the
PURCHASER.
5.1 The CONTRACTOR shall plan to deal with emergencies. An EP/ER specific to
the job site shall be written and communicated to all employees. The EP/ER
shall identify for the potential for and responses to incidents and emergency
situations and for preventing and mitigating the likely illness and injury that may
be associated with them.
5.2 The CONTRACTOR shall review his emergency preparedness and response
plans and procedures in particular after occurrence of incidents or emergency
operations
5.3 The CONTRACTOR shall designate his emergency team with their duties
during emergencies defined, Including those of the hose teams, medical
personnel, first-aiders and security. The CONTRACTOR shall maintain a
procedure as to how his emergency organisation shall liaise with the
PURCHASER's representatives in the EP/ER.
5.4 The CONTRACTOR shall also periodically test such emergency procedures by
conducting mock-drills and use the experience for updating the EP/ER and for
training the employees on the perceived competence needs.
ISSUE
R1
5.5 The EP/ER of the CONTRACTOR shall be under the control of the SR who shall
be able to co-ordinating with the PURCHASER/CONSULTANT for liaising with
government agencies, neighbouring industries and community
5.6 The EP/ER shall be designed to allow people to work under disaster conditions
when normal services such as telephone water, light power, transport and
sanitation are not available and first aid and fire fighting facilities are not able to
cope with sudden demand on services.
The CONTRACTOR shall ensure that workplaces are ventilated with at least
prescribed amount of clean or cleaned fresh air of a suitable temperature,
especially where toxic or irritating substances are present such as welding,
vehicle exhaust fumes, irritating dusts, organic solvents or any other inimical
atmosphere creating health hazards or safety.
ISSUE
R1
6.7.1 The CONTRACTOR shall ensure stacked material is bonded on a stable and
level footing capable of carrying the mass of the stack. Adequate clearances
shall be provided between the sides of the stack and top to facilitate unimpeded
access to service equipment like overhead wiring, cranes, forklifts and fire
fighting equipment, and hoses. Circular items shall be sufficiently choked with
wedges not with odd bits of materials. Free-standing stacks of gunny bags and
sacks such as cement bags shall be stacked to prescribed safe-stack heights
with layers formed for stable bonding, preventing slippage causing accidents.
Stacking against walls shall not be permissible.
6.7.2 The CONTRACTOR shall maintain the premises and surrounding areas in clean
and clear manner with safe access and egress. There shall be sufficient and
adequate storage racks, shelving, bins and pallets and material handling
equipment to stack his construction materials such as pipes structurals and
construction enabling materials. Unwanted materials shall be promptly moved
away for efficient material movement.
6.8.1 Hazardous materials shall be stored on solid bases. Solid bases shall include
compacted earth, pallets, concrete or asphalt platforms or paving. Hazardous
materials shall be stored, stacked and secured to prevent toppling, spillage or
other unintended dislodgement. Aisles and clearances shall be as detailed
under 6.6 above. Hazardous materials shall be stacked in such a manner that
an observer standing in the aisle can read their labels and legend.
6.8.3 Hazardous materials which if brought in contact with each other could react or
pose equal or greater hazard than either material stored alone shall be stored at
a distance not lesser than twenty feet apart.
6.8.4 Warnings shall be posted and maintained in a legible condition at all access
points clearly defining the specific hazardous nature of the stored materials such
as ‘Corrosive’, ‘Flammable’, ‘Explosive’, ‘Oxidising’, ‘Compressed Gas’ or other
hazardous nature.
ISSUE
R1
6.8.6 The CONTRACTOR shall inspect the hazardous storages and installations on a
daily basis and hall undertake any requisite preventive action necessary to
avoid safety risks
6.9.1 The CONTRACTOR shall secure flammable and or explosive materials against
accidental ignition.
6.9.2 Storage facilities for flammable liquids such as petrol, diesel kerosene and
lubricants as well as the quantities stored shall meet the legal and statutory
requirements. These shall be stored in approved fire-resistant rooms with a
sump of sufficient volume to contain any spillage.
6.9.3 The electrical fittings to be flame -proof and on a strict maintenance schedule.
Containers shall be appropriately bonded in receptacles into which low flash
point fuel is decanted.
Compressed gas cylinders shall be stored and secured in the upright position at
safe distances from shielded from welding and cutting operations. Compressed
gas cylinders in storage shall be shut off and torches, hose and manifolds
removed and capped. Cylinders shall be periodically checked for leakages.
Storage shall meet requirements of Gas Cylinder Rules 1981.Compressed gas
storages shall be provided with safety relief valves, Safety valves and rupture
disc to protect them overpressures. appropriately designed to ensure their
continued availability in the face of process changes
The CONTRACTOR shall ensure that he has sufficient waste bins that are
identified for different wastes and maintained in clearly demarcated areas.
Wastes with oily or other ignitable materials such as oily cotton wastes and
hand gloves shall be stored separately with covers to prevent fires and shall be
made of metal. Different wastes shall be segregated and stored separately and
disposed off. These shall be emptied at routine intervals to prevent that they do
not overflow with wastes.
ISSUE
R1
SECTION F
ISSUE
R0
The BIDDER shall indicate below all deviations from the Technical Specifications.
ISSUE
R7
The BIDDER shall indicate below all deviations from the General Conditions.
ISSUE
R1
The BIDDER shall indicate below the equipment and erection machinery he has in his possession and
proposes to bring to the site, in case the work is awarded to him.
NUMBER
SL. TYPE AND DESCRIPTION OF THE EQUIPMENT AND NUMBER IN PROPOSED
NO. ERECTION MACHINERY POSSESSION TO BRING TO
THE SITE
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
The BIDDER hereby confirms that the quantity and type of equipment and erection machinery he will
employ for the site work will not be less than those listed above. The BIDDER also agrees to bring
more equipment and erection machinery, if so warranted, in the opinion of the PURCHASER/
CONSULTANT to meet the construction norms and construction schedule.
COMPANY SEAL SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
ISSUE
R4
The BIDDER shall indicate below the all-inclusive prices of labour assumed for the purpose of this
CONTRACT.
NORMAL TIME
SL. OVER TIME RATE
SUPPLY OF LABOUR RATE FOR 8 HRS
NO. Rs. PER HOUR
Rs. PER DAY
1. Unskilled Labour - Male
2. Unskilled Labour - Female
3. Skilled Labour - Male
4. Mason
5. Carpenter
6. Painter
7. Fitter - Reinforcement
8. Fitter - Structural steel
9. Welder
10. Rigger
11. Welders with Welding Equipment
12. Gas Cutter with all Equipment
13.
14.
15.
16.
17.
18.
19.
20.
21.
The PURCHASER shall have the right to ask the CONTRACTOR to supply labour for any work at the
rates quoted above.
COMPANY SEAL SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
ISSUE
R4
The BIDDER shall indicate below a list of similar jobs executed by him, to whom a reference may be
made by the PURCHASER.
SYSTEM SUPPLIED
(SEE
BRIEF DETAILS OF
SCHEDULED DATE
CONTRACT PRICE
AND E-MAIL ID OF
TEL. NO., FAX NO.
ACTUAL DATE OF
NAME, ADDRESS,
OF COMPLETION
COMPLETION, IF
PROJECT NAME
CONTRACT NO.
COMPLETION
REASON FOR
APPLICABLE
PURCHASER
EQUIPMENT/
CLIENT AND
SCOPE OF
AND DATE
REMARKS
DELAY IN
LEGEND)
ORDER/
SL. NO.
IN Rs.
SERVICES
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
LEGEND: E - ERECTION, S - SUPPLY, SUP - SUPERVISION OF ERECTION, TC - TESTING AND
COMMISSIONING
COMPANY SEAL SIGNATURE
NAME
DESIGNATION
COMPANY
DATE
ISSUE
R5
ENQUIRY No._________________________________________________________________
Email: __________________________________________________________________
1. Duly signed & stamped copies of this “PATC”, with all the clauses duly confirmed/
precisely replied to by the Contractor, shall be enclosed with each and every set of
Contractor's un-priced quotation.
2. All the commercial terms and conditions shall be indicated by Contractor in this format
only and nowhere else in his quotation. However, in case the space for Contractor's
reply is not sufficient against a particular question, the Contractor shall furnish same by
way of separate annexure attached to this “PATC”, indicating cross-reference of
respective clauses.
3. Failure on the part of Contractor in not returning this duly filled-up "PATC” with all the
sets of un-priced quotation and/or submitting incomplete replies may lead to rejection of
Contractor's quotation”.
Sl.
Description of the Terms & conditions Contractor’s offer
No.
Contract shall be awarded to sole bidder
Contract
1. on Overall Lowest basis for entire scope of Confirmed
Terms
ENQUIRY
Security Contractor shall submit Security deposit of
2. Confirmed
Deposit amount and duration as per SCC / GCC
Liquidated Damages shall be applicable as
3. per SCC / GCC. Please confirm your Confirmed
acceptance.
NOTE:
Liquidated
In case of Rate Contracts, the Liquidated damages, accepted above, will
Damages
be levied on the total value of our respective indents.
4.
In case any deviation is taken by you, from our standard LD Clause,
while evaluating your offer, your offer will be loaded to the extent of your
non-acceptance to our LD Clause.
Please specify whether Goods & Service
Goods &
5. Tax is Nil or is included in your quoted rate
Service Tax
or is Extra. (Nil) (Included) (Extra)
Sl.
Description of the Terms & conditions Contractor’s offer
No.
In case Goods & Service Tax is extra,
please specify the rate, in terms of
6. percentage of Basic Price.
This will be loaded while evaluating
your offer.
Rebate Benefit on Goods & Service Tax
7.
that CLIENT can avail
In case of Goods & Service Tax applicable
8. Indicate Goods & Service Tax Registration
No.
Only statutory variations, if any, in the
present rate of Goods & Service Tax, up to
the contractual delivery period shall be to
9. Owner's account subject to documentary Confirmed
evidence to be furnished by the bidder.
Variation in Confirm compliance.
Goods &
Any variation in Goods & Service Tax at
Service
the time of work execution for any reasons,
10. Tax/ other other than statutory, including variations Confirmed
taxes & due to turnover, shall be borne by bidder.
duties Confirm compliance.
Works will be eligible for Input Tax Credit
and Bidder shall furnish all documents as
11. required to avail the same. Confirm Confirmed
compliance.
If Goods & Service Tax indicated by bidder
as nil [or] not applicable at present due to
12. any reason, the same shall be borne by Confirmed
Supplier if it becomes applicable later on.
Confirm compliance.
Any new or additional taxes/ duties and
any increase in the existing taxes/duties
imposed after contractual delivery period
13. shall be to BIDDER’S account whereas Confirmed
any corresponding decrease shall be
passed on to the Owner. Confirm
Compliance
Payment As per SCC / GCC (whichever applicable).
14. Confirmed
Terms Confirm compliance.
Sl.
Description of the Terms & conditions Contractor’s offer
No.
In case of any deviations, from our
standard payment terms (such as
15. Documents through bank, by Demand Confirmed
Draft, etc), all bank charges will be to your
account. Please confirm your acceptance
In case of delayed delivery, invoices shall
be submitted after deducting price
16. reduction towards delayed delivery as Confirmed
mentioned in SCC / GCC. Confirm
Compliance.
Please confirm completion period as per
17. Confirmed
Section A – Scope of Enquiry Document
NOTE:
Completion
(1) The completion period will be reckoned from the date of our LOI /
Period
18. Purchase Order / date of Contract as mentioned in Section A / C
(2) In case of Rate Contracts, the delivery period will be reckoned from
the date of each Indent.
Shall be as per SCC / GCC. Please
19. Guarantee Confirmed
confirm your acceptance.
Please confirm that your offer is valid, for
20. acceptance, for a period as mentioned in Confirmed
Validity of
ITB.
your offer
In case the validity of your offer is shorter, your offer is liable for
21.
rejection.
Firmness of Quoted prices shall remain firm and fixed
22. prices till complete execution of the order. Confirmed
Confirm Compliance.
Please confirm your acceptance to our
Arbitration
23. Arbitration Clause as per SCC / GCC. Confirmed
Clause
Sl.
Description of the Terms & conditions Contractor’s offer
No.
In case you are registered with NSIC,
please confirm that you have not
succeeded in securing orders for the same
26. Confirmed
item, in competition (i.e. without price
preference) with the large scale units,
during the preceding 12 months.
If registered, please enclose a copy of the valid NSIC registration
certificate, applicable for the items offered by you.
27. Price preference shall be considered for units registered with NSIC,
as per the prevailing government guidelines, rules & regulations, as
applicable.
Please confirm that PBG will be submitted
28. PBG by you as per SCC / GCC in OWNER’s Confirmed
prescribed format.
Inspection Shall be as per SCC / GCC
29. Confirmed
Sl.
Description of the Terms & conditions Contractor’s offer
No.
Please confirm you have not been banned
or delisted by any Government or Quasi
Government agencies or PSUs or other
private firms. If you have been banned,
36. then this fact must be clearly stated. This Confirmed
does not necessarily because for
disqualification. However, if this
declaration is not furnished the bid shall
be rejected as non-responsive.
Deviations to Terms & Conditions shall
37. lead to loading of prices as per special
Confirmed
conditions of contract (SCC) / ITB or
rejection of offer. Please confirm.
Any claim arising out of order shall be sent
to Owner in writing with a copy to TCE
within 3 months from the date of last
38. despatch. In case the claim is received Confirmed
after 3 months, the same shall not be
entertained by TCE/ Owner. Confirm
Compliance.
Terms and conditions, if any, appearing in
quotation, shall not be applicable in the
event of order. In case of contradiction
39. between the confirmations given herein
Confirmed
and terms & conditions mentioned
elsewhere in the offer, the confirmation
given herein shall prevail. Confirm
compliance.
Sl.
Description of the Terms & conditions Contractor’s offer
No.
Contractor to quote as per the
requirements and terms and conditions of
the ENQUIRY Document including all the
enclosures and not to stipulate deviations/
exceptions. Once quoted, the Contractor
shall not make any subsequent price
changes, whether resulting or arising out
of any technical/ commercial clarifications
and details sought on any deviations,
exceptions or stipulations mentioned in the
Contractor offer unless any amendment to
40. ENQUIRY Document is issued by Confirmed
OWNER/ TCE. Similarly, no revision in
quoted price shall be allowed should the
deviations stipulated by Contractor are not
accepted by OWNER/TCE and are
required to be withdrawn by Contractor in
favour of meeting the requirements and
complying to the terms and conditions of
the ENQUIRY Document. Any unsolicited
proposed price change by the Contractor
is likely to render the Contractor offer
liable for rejection. Confirm compliance.
TCE.6842C-CV-3000-
SCHEDULE OF PRESENT / SHEET 1 OF 1 OF
3005-11
CONCURRENT COMMITMENTS
ISSUE
R0
FILE NAME: F-329-Rev-R6.doc TCE FORM NO. 120 R3
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: TITLE
TCE.6842A-CV-
TENDER FOR ROAD AND STORM WATER DRAIN
3000-3005 SHEET i OF i
WORKS
FOR
VOLUME II
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information.
R0
SECTION D
ISSUE
R0
1.0 SCOPE
This specification covers the general requirements of earthwork in excavation in
different materials, site grading, filling in areas as shown in drawing, filling back
around foundations and in plinths, conveyance and disposal of surplus soils or
stacking them properly as shown on the drawings and as directed by the
ENGINEER and all operations covered within the intent and purpose of this
specification.
2.0 APPLICABLE CODES
The following Indian Standard Codes, unless otherwise specified herein, shall be
applicable. In all cases, the latest revision of the codes shall be referred to.
1. IS 456: 2000 - Code of practice for plain and reinforced
(Reaffirmed 2005) concrete.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 2 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 3 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 4 OF 14
AND BACKFILLING
other method approved by the ENGINEER for loosening the rock mass,
developing cracks, etc. The loosened material shall be thereafter removed
either by mechanical means or manually. Boulders of rock occurring in such
sizes and not classified under (a) and (b) above shall also be classified as
hard rock. Concrete work both reinforced and unreinforced to be dismantled
will be measured under this item, unless a separate provision is made in the
Schedule of Quantities.
8.0 EXCAVATION
All excavation work shall be carried out by mechanical equipment unless, in the
opinion of the ENGINEER, the work involved and time schedule permit manual
work.
Excavation for permanent work shall be taken out to such widths, lengths, depths
and profiles as are shown on the drawings or such other lines and grades as may
be specified by the ENGINEER. Rough excavation shall be carried out to a depth
150 mm above the final level. The balance shall be excavated with special care.
Soft pockets shall be removed even below the final level and extra excavation filled
up as directed by the ENGINEER. The final excavation if so instructed by the
ENGINEER, should be carried out just prior to laying the mud-mat.
The CONTRACTOR may, for facility of work or similar other reasons excavate, and
also backfill later, if so approved by the ENGINEER, at his own cost outside the
lines shown on the drawings or directed by the ENGINEER. Should any excavation
be taken below the specified elevations, the CONTRACTOR shall fill it up, with
concrete of the same class as in the foundation resting thereon, upto the required
elevation. No extra shall be claimed by the CONTRACTOR on this account.
All excavation shall be done to the minimum dimensions as required for safety and
working facility. Prior approval of the ENGINEER shall be obtained by the
CONTRACTOR in each individual case, for the method he proposes to adopt for
the excavation, including dimensions, side slopes, dewatering, disposal, etc. This
approval, however, shall not in any way relieve the CONTRACTOR of his
responsibility for any consequent loss or damage. The excavation must be carried
out in the most expeditious and efficient manner. Side slopes shall be as steep as
will stand safely for the actual soil conditions encountered. Every precaution shall
be taken to prevent slips. Should slips occur, the slipped material shall be removed
and the slope dressed to a modified stable slope. Removal of the slipped earth will
not be paid for if the slips are due to the negligence of the CONTRACTOR.
Excavation shall be carried out with such tools, tackles and equipment as
described herein before. Blasting or other methods may be resorted to in the case
of hard rock only with the specific permission of the ENGINEER.
9.0 STRIPPING LOOSE ROCK
All loose boulders, semi-detached rocks (along with earthy stuff, which might move
therewith) not directly in the excavation but so close to the area to be excavated as
to be liable, in the opinion of the ENGINEER, to fall or otherwise endanger the
workmen, equipment, or the work, etc., shall be stripped off and removed away
from the area of the excavation. The method used shall be such as not to shatter
or render unstable or unsafe the portion, which was originally sound and safe.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 5 OF 14
AND BACKFILLING
Any material not requiring removal as contemplated in the work, but which, in the
opinion of the ENGINEER, is likely to become loose or unstable later, shall also be
promptly and satisfactorily removed as directed by the ENGINEER. The cost of
such stripping will be paid for at the unit rates accepted for the class of materials in
question.
10.0 EARTHWORK IN EXCAVATION FOR MAJOR EXCAVATION (BASEMENTS/
RETAINING WALLS)
Excavation shall be undertaken to the width of the Basement/ Retaining Wall Raft/
Footing including necessary margins for construction operation as per drawing or
as directed by the ENGINEER. Where the nature of soil or the depth of the trench
and season of the year do not permit vertical sides, the CONTRACTOR shall, at
his own expense, put up the necessary shoring, strutting and planking or cut
slopes with or without steps, to a safer angle or both with due regard to the safety
of personnel and works and to the satisfaction of the ENGINEER. The scheme
proposed by the CONTRACTOR shall take into consideration the presence of
existing buildings/ structures in the vicinity, if any.
All the major excavation shall be carried out by mechanical excavator. No extra
payment shall be made for that.
The CONTRACTOR shall make, at his own cost, all necessary arrangements for
maintaining water level, in the area where works are under execution low enough
so as not to cause any harm to the work. These shall be considered as inclusive of
pumping out or bailing out water, if required, for which no extra payment shall be
made. This will include water coming from any source such as rains, accumulated
rain water, floods, leakages from sewer and water mains, water ingress from
nearby nallah, subsoil water table being high or due to any other cause
whatsoever. The CONTRACTOR shall make necessary provision of pumping,
dredging, bailing out water coming from all above sources and excavation and
other works shall be kept free of water by providing a suitable system approved by
the ENGINEER.
In order to avoid possibility of basement raft of building getting uplifted/ damaged
due to water pressure, the CONTRACTOR shall lower the ground water table
below the proposed foundation level by boring tube wells all around the proposed
building using well point sinking method or any suitable method as approved by the
ENGINEER. Sub soil water table shall be maintained at least 50 cm below the
layer of blinding concrete (Plain Cement Concrete (PCC)) level during laying of
PCC, water proofing treatment, laying of basement raft and beams including filling
of earth/ sand under the basement floor. The water table shall not be allowed to
rise above base of raft level until completion of outer retaining walls including water
proofing of vertical surface of walls and back filling along the walls upto ground
level and until the structure attains such height to counter balance the uplift
pressure. The CONTRACTOR should inspect the site and make his own
assessment about sub-soil water level likely to be encountered at the time of
execution and quote his rates accordingly. Rate of all items are inclusive of
pumping out or bailing out water, if required. Nothing extra on this account
whatsoever shall be paid to him. The CONTRACTOR shall obtain the
ENGINEER’s approval on the sequence of construction.
The CONTRACTOR shall take all necessary measures for the safety of traffic
during construction and provide, erect and maintain such barricades including
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 6 OF 14
AND BACKFILLING
signs, markings, flags, lights and flagman, as necessary at either end of the
excavation/ embankment and at such intermediate points as directed by the
ENGINEER for the proper identification of construction area. He shall be
responsible for all damages and accidents caused due to negligence on his part.
11.0 EXCAVATION IN HARD ROCK
11.1 GENERAL REQUIREMENTS
Unless otherwise stated herein, IS specification “IS: 4081 - Safety Code for
Blasting and related Drilling Operations” shall be followed. After removal of
overburden, if any, excavation shall be continued in rock to such widths, lengths,
depths, and profiles as are shown on the drawings or such other lines and grades
as may be specified by ENGINEER. As far as possible, all blasting shall be
completed prior to commencement of construction. At all stages of excavation,
precautions shall be taken to preserve the rock below and beyond the lines
specified for the excavation, in the soundest possible condition. The quantity and
strength of explosives used shall be such that it will neither damage nor crack the
rock outside the limits of excavation. All precautions, as directed by ENGINEER,
shall be taken during the blasting operations and care shall be taken that no
damage is caused to adjoining buildings or structures as a result of blasting
operations. In case of damage to permanent or temporary structures,
CONTRACTOR shall repair the same to the satisfaction of ENGINEER at his cost.
As excavation approaches its final lines and levels, the depth of the charge holes
and amount of explosives used shall be progressively and suitably reduced.
Specific permission of ENGINEER will have to be taken by CONTRACTOR for
blasting rock and he shall also obtain a valid Blasting License from the authorities
concerned. If permission for blasting is refused by ENGINEER, the rock shall be
removed by wedging, pick, barring, heating and quenching or other approved
means. All loose or loosened rock in the sides shall be removed by barring,
wedging, etc. The unit rates for excavation in hard rock shall include the cost of all
these operations.
CONTRACTOR shall obtain necessary license for storage of explosives, fuses and
detonators issued to him from OWNER’s stores or from supplier arranged by him,
from the authorities dealing with explosives. The fees, if any, required for obtaining
such license, shall be borne by CONTRACTOR. CONTRACTOR shall have to
make necessary storage facilities for the explosives, etc. as per rules of local, State
and Central Government authorities and statutory bodies/ regulations. Explosives
shall be kept dry and shall not be exposed to direct rays of sun or be stored in the
vicinity of fire, stoves, steam pipes or heated metal, etc. No explosives shall be
brought near the work in excess of quantity required for a particular amount of
firing to be done; and surplus leftafter filling the holes shall be removed to the
magazine. The magazine shall be built, as far as possible, from the area to be
blasted. ENGINEER’s prior approval shall be taken for the location proposed for
the magazine.
In no case shall blasting be allowed closer than 30 metres from any structure or at
locations where concrete has just been placed. In the latter case, the concrete
must be at least 7 days old.
11.2 SPECIFIC REQUIREMENTS
For blasting operations, the following points shall be observed.
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 7 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 8 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 9 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 10 OF 14
AND BACKFILLING
the centre line of the pipe shall be done with selected earth by hand compaction or
other approved means in layers not exceeding 15 cm.
In case of excavation of trenches in rock, the filling upto a level 30 cm above the
top of the pipe shall be done with fine materials, such as earth, murrum, etc. The
filling upto the level of the centre line of the pipe shall be done by hand compaction
in layers not exceeding 8 cm whereas the filling above the centre line of the pipe
shall be done by hand compaction or approved means in layers not exceeding 15
cm. The filling from a level 30 cm above the top of the pipe to the top of the trench
shall be done by hand or other approved mechanical methods with broken rock
filling of size not exceeding 15 cm mixed with fine material as available to fill up the
voids.
Filling of the trenches shall be carried simultaneously on both sides of the pipe to
avoid unequal pressure on the pipe.
13.0 GENERAL SITE GRADING
Site grading shall be carried out as indicated in the drawings and as directed by the
ENGINEER. Excavation shall be carried out as specified in the specification. Filling
and compaction shall be carried out as specified under clause 12.0 and elsewhere
unless otherwise indicated below.
If no compaction is called for, the fill may be deposited to the full height in one
operation and levelled. If the fill has to be compacted, it shall be placed in layers
not exceeding 225 mm and levelled uniformly and compacted as indicated in
clause 12.0 before the next layer is deposited.
To ensure that the fill has been compacted as specified, field and laboratory tests
shall be carried out by the CONTRACTOR at his cost.
Field compaction test shall be carried out at each of the different stages of filling
and at frequency of one test in each layer per 2000 sqm areaand also after the fill
to the entire height has been completed. This shall hold good for embankments as
well.
The CONTRACTOR shall protect the earthfill from being washed away by rain or
damaged in any other way. Should any slip occur, the CONTRACTOR shall
remove the affected material and make good the slip at his cost.
The fill shall be carried out to such dimensions and levels as indicated on the
drawings after the stipulated compaction. The fill will be considered as incomplete
if the desired compaction has not been achieved.
If specifically permitted by the ENGINEER, compaction can be achieved by
allowing loaded trucks conveying fill or other material to ply over the fill area. Even
if such a method is permitted, it will be for the CONTRACTOR to demonstrate that
the desired/ specified compaction has been achieved. In order that the fill may be
reasonably uniform throughout, the material should be dumped in place in
approximately uniform layers. Traffic over the fill shall then be so routed to compact
the area uniformly throughout.
If so specified, the rock as obtained from excavation may be used for filling and
levelling to indicated grades without further breaking. In such an event, filling shall
be done in layers not exceeding 50 cm approximately. After rock filling to the
approximate level, indicated above has been carried out, the void in the rocks shall
be filled with finer materials such as earth, broken stone, etc. and the area flooded
so that the finer materials fill up the voids. Care shall be taken to ensure that the
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 11 OF 14
AND BACKFILLING
finer fill material does not get washed out. Over the layer so filled, a 100 mm thick
mixed layer of broken material and earth shall be laid and consolidation carried out
by a 12 tonne roller. No less than twelve passes of the roller shall be accepted
before subsequent similar operations are taken up.
14.0 SITE FILLING
14.1 FILL MATERIAL
14.1.1 General
All fill material whether such material is brought from outside borrow areas or from
excavation from within the site, will be subject to the ENGINEER’s written approval.
Notwithstanding any approval given to the fill material of borrow areas from which
fill material is proposed to be brought, the ENGINEER/ OWNER reserves the right
to reject such material, which in his opinion either does not meet the specification
requirements or is unsuitable for the purpose for which it is intended.
14.1.2 Borrow Areas
It shall be CONTRACTOR’s responsibility to locate suitable borrow areas for
borrowing fill material. Such area will be inspected by the ENGINEER and
approved before the CONTRACTOR makes arrangements to borrow the fill
material. The top soil which may contain vegetation, rubbish, slush, etc. shall not
be used. If demanded by the ENGINEER, the CONTRACTOR shall arrange to
have trial pits of specified dimensions and numbers dug at locations specified, for
the ENGINEER to examine the nature and type of material likely to be obtained
from the borrow area.
14.1.3 Lead, Lift and Transportation
Unless separately provided for, all lead, lift and transportation required for bringing
in the fill material from borrow areas or from excavation from within the site shall be
included in the CONTRACTOR’s quoted unit rates.
14.1.4 Quality
The borrowed soil shall be generally granular, and non-cohesive. It shall consist of
sand, silty sand, murrum, ordinary soil, gravel and shingle. Dredged material shall
also be free from sulphates, salts, organic, foreign and other harmful or
objectionable materials. Any material rejected by the ENGINEER shall be removed
from the site immediately.
14.2 ACCESS ROADS
Roads, whether of temporary or other nature, required to be constructed for access
and for movement of men, materials, equipment, transport vehicles, vehicles
carrying fill material, etc. to or over borrow areas and/ or to or over areas on which
fill has to be deposited shall be constructed by the CONTRACTOR at his cost.
Such costs shall be deemed to have been included in the unit rates quoted by the
CONTRACTOR. Such access roads shall be maintained in good condition during
all seasons to ensure completion of work according to time schedule.
14.3 CLEARING
Site clearing before filling shall be carried out as per clause 5.0 of this specification.
14.4 FILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 12 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 13 OF 14
AND BACKFILLING
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
SPEC. NO.
EARTHWORK IN GRADING, EXCAVATION
TCE.M4-418-01 SHEET 14 OF 14
AND BACKFILLING
Backfilling, plinth filling, etc. with borrowed earth will be paid for at rates quoted.
The quoted rate shall include all operations such as clearing, excavation, lead and
transport, fill, compaction, etc. as specified. Actual quantity of consolidated filling
shall be measured and paid for in cubic metres. The lead, lift, etc. shall be as
indicated in the Schedule of Quantities.
Actual quantity of consolidated sand filling shall be measured and paid in cubic
metres.
Volume of rock excavated shall be calculated on the basis of length, breadth and
depth of excavation dimension as per the foundation drawings.
No payment will be made for excavations/ over-break beyond payment line
specified. Where such measurement is not possible as in the case of strata
intermixed with soil, excavated rock shall be properly stacked as directed by
ENGINEER and the volume of rock calculated on the basis of stack measurements
after making appropriate allowance for voids. The allowance to be made for voids
shall be decided by ENGINEER and this will not be a subject matter of dispute or
appeal.
Measurement for Site Filling will be made on the basis of this specification.
END
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R5
FILE NAME: M4-418-01-Rev-R5.docx TCE FORM NO. 329 R6
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED SECTION: WRITE-UP
TCE.M4-418-03 DEWATERING SHEET 1 OF 1
1.0 SCOPE
This specification covers the general requirements of dewatering excavations
in general.
2.0 DEWATERING
All excavations shall be kept free of water. Grading and surface water
drainage scheme in the vicinity of excavation shall be properly closed to
prevent surface water from draining into excavated areas. CONTRACTOR
shall remove by pumping or other means approved by ENGINEER any water
inclusive of rain water and subsoil water accumulated in excavation and keep
all excavations dewatered until the foundation work is completed and
backfilled. Sumps made for dewatering must be kept clear of the excavations/
trenches required for further work. Method of pumping shall be approved by
ENGINEER; but in any case, the pumping arrangement shall be such that
there shall be no movement of subsoil or blowing in due to differential head of
water during pumping. Pumping arrangements shall be adequate to ensure
no delays in construction.
The CONTRACTOR shall take adequate measures for bailing and/ or
pumping out water from excavations and construct diversion channels, bunds,
sumps, coffer dams, etc. as may be required. Pumping shall be done directly
from the foundation trenches or from a sump outside the excavation in such a
manner as to preclude the possibility of movement of water through any fresh
concrete or masonry and washing away parts of concrete or mortar. During
laying of concrete or masonry and for a period of at least 24 hours thereafter,
pumping shall be done to ensure that the surface below the concrete remains
dry.
Capacity and number of pumps, location at which the pumps are to be
installed, pumping hours, etc. shall be reviewed by the CONTRACTOR from
time to time. The ENGINEER may direct the CONTRACTOR to make
changes in his scheme if the adopted scheme fails to achieve the desired
results.
Pumping shall be done in such a way as not to cause damage to the work or
adjoining property by subsidence, etc. Disposal of water shall not cause
inconvenience or nuisance in the area or cause damage to the property and
structures nearby.
When there is a continuous inflow of water and quantum of water to be
handled is considered in the opinion of ENGINEER as large, well point
system - Single stage or multi stage, shall be adopted. CONTRACTOR shall
submit to ENGINEER his scheme of well point system including the stages,
the spacing, number and diameter of well points, headers, etc. and the
numbers, capacity and location of pumps of approvals. Unless separately
provided for in the Schedule of Prices, the cost of dewatering shall be
included in the item rate for excavation.
3.0 MEASUREMENT
Unless separately provided for in the Schedule of Quantities, dewatering is
deemed to have been included in the unit rates quoted for excavation.
END
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE). ISSUE
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. R2
1.0 SCOPE
1.1 This Specification covers the general requirements for ready mixed concrete
and for concrete using on-site production facilities including requirements with
regard to the quality, handling, storage of ingredients, proportioning, batching,
mixing, transporting, placing, curing, protecting, repairing, finishing and
testing of concrete; formwork; requirements with regard to the quality,
storage, bending and fixing of reinforcement; grouting as well as mode of
measurement and payment for completed works.
1.2 It shall be very clearly understood that the specifications given herein are brief
and do not cover minute details. However, all works shall have to be carried
out in accordance with the relevant standards and codes of practices or in
their absence in accordance with the best accepted current Engineering
practices or as directed by ENGINEER from time to time. The decision of
ENGINEER as regards the specification to be adopted and their interpretation
and the mode of execution of work shall be final and binding on
CONTRACTOR and no claim whatsoever will be entertained on this account.
2.0 APPLICABLE CODES AND SPECIFICATIONS
2.1 The following specifications, standards and codes, including all official
amendments/ revisions and other specifications and codes referred to therein,
should be considered a part of this specification. In all cases the latest issue/
edition/ revision shall apply. In case of discrepancy between this specification
and those referred to herein below or other specifications forming a part of
this bid document, this specification shall govern.
2.2 MATERIALS
IS 9103:1999
(i) Reaffirmed Specification for admixtures for concrete.
2013
IS 2645:2003
(j) Reaffirmed Specification for integral cement waterproofing compounds.
2017
IS 4990:2011
(k) Reaffirmed Specification for plywood for concrete shuttering work.
2017
IS 4926:2003
(l) Reaffirmed Ready Mixed Concrete.
2017
(m) IS 12269:2013 Specification for 53 grade Ordinary Portland Cement.
IS 8041:1990
(n) Reaffirmed Specification for rapid hardening cement.
2014
IS 12600:1989
(o) Reaffirmed Specification for low heat cement.
2014
IS 6909:1990
(p) Reaffirmed Specification for Supersulphated Cement.
2016
IS 12089:1987
(q) Reaffirmed Specification for Granulated Ground Blast Furnace Slag.
2008
2.3 MATERIAL TESTING
IS 4031 Methods of physical tests for hydraulic cement :Part
(Part 1):1996 1Determination of fineness by dry sieving (second
(a)
Reaffirmed revision)
2016
IS 4031 Methods of physical tests for hydraulic cement: Part
(Part 2):1999 2Determination of fineness by specific surface by
(b)
Reaffirmed Blaine air permeability method (second revision)
2013
IS 4031 Methods of physical tests for hydraulic cement:Part 3
(Part 3):1988 Determination of soundness (first revision)
(c)
Reaffirmed
2014
IS 4031 Methods of physical tests for hydraulic cement:Part 4
(Part 4):1988 Determination of consistency of standard cement paste
(d)
Reaffirmed (first revision)
2014
IS 4031 Methods of physical tests for hydraulic cement:Part 5
(Part 5):1988 Determination of initial and final setting times (first
(e) Reaffirmed revision)
2014
ISSUE
R9
DIN EN
(s) 12620:2015- Aggregates for concrete(Refer to Note).
07-DRAFT
IS 2386:1963 Methods of test for aggregates for concrete (Parts 1 to
(t) Reaffirmed 8)
2016
IS 3025 Methods of sampling and test (physical and chemical)
(Part 1):1987 for water and wastewater Part 1 - Sampling
(u)
Reaffirmed
2014
IS 3025 Methods of Sampling and Test (Physical and
(Part 2):2004 Chemical) for Water and Waste Water - Part 2 :
(v)
Reaffirmed Determination of 33 Elements by Inductively Coupled
2014 Plasma Atomic Emission Spectroscopy
IS 3025 Methods of Sampling and Test (Physical and
(Part 3):1987 Chemical) for Water and Wastewater, Part 3: Precision
(w)
Reaffirmed and Accuracy
2014
IS 3025 Methods of Sampling and Test (Physical and
(Part 4):1983 Chemical) for Water and Wastewater, Part 3: Colour
(x)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 5):1983 for water and wastewater : Part 5 Odour
(y)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 6):1983 for water and wastewater : Part 6 Odour threshold
(z)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 7):1984 for water and wastewater : Part 7Taste threshold
(aa)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 8):1984 for water and wastewater : Part 8 Taste rating
(bb)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 9):1984 for water and wastewater : Part 9 Temperature
(cc)
Reaffirmed
2017
IS 3025 Methods of sampling and test (physical and chemical)
(Part 10):1984 for water and wastewater : Part 10 Turbidity
Reaffirmed
(dd) 2017
ISSUE
R9
(a) IS 1199:1959
Reaffirmed Method of sampling and analysis of concrete.
2013
(b) IS 516:1959
Reaffirmed Method of test for strength of concrete.
2013
(c) IS 9013:1978 Method of making, curing and determining
Reaffirmed compressive strength of accelerated cured concrete
2013 test specimens.
(d) IS 8142:1976
Method of test for determining setting time of concrete
Reaffirmed
by penetration resistance.
2016
(e) IS 9284:1979
Reaffirmed Method of test for abrasion resistance of concrete.
2017
(f) IS 2770
(Part 1):1967
Reaffirmed Methods of testing bond in reinforced concrete:Part 1
2017 Pull-out test
ISSUE
R9
IS 4014
(Part 1):1967 Code of practice for steel tubular scaffolding Part 1
(q)
Reaffirmed Definitionsand materials
2016
IS 4014 Code of practice for steel tubular scaffolding: Part 2
(r)
(Part 2):2013 Safetyregulations for scaffolding (first revision)
IS 2571:1970
Code of practice for laying in situ cement concrete
(s) Reaffirmed
flooring
2017
IS 7861
(Part 1):1975 Code of practice for extreme weather concreting: Part
(t)
Reaffirmed 1Recommended practice for hot weather concreting
2016
IS 7861
(Part 2):1981 Code of practice for extreme weather concreting: Part
(u)
Reaffirmed 2Recommended practice for cold weather concreting
2016
ISSUE
R9
Minus - 5 mm
Plus - 10 mm
(f) Footings
i. In a flight of stairs
Rise - 3 mm
Tread - 5 mm
ISSUE
R9
ISSUE
R9
Table-2
Volume of Coarse Aggregate per unit of Volume of Concrete
Grade – A (Maximum Size 40 mm) Grade – B (Maximum Size 20 mm)
Volume of Dry-rodded Coarse Aggregate per Unit Volume of
Maximum Size
Aggregates of Concrete for different Fineness Modulii of sand
FMS = 2.40 FMS = 2.60 FMS = 2.80 FMS = 3.00
10 0.50 0.48 0.46 0.44
12.50 0.59 0.57 0.55 0.53
20 0.66 0.64 0.62 0.60
25 0.71 0.69 0.67 0.65
40 0.76 0.74 0.72 0.70
50 0.78 0.76 0.74 0.72
Notes:
1. Volumes are based on aggregates in dry-rodded condition.
2. These volumes are selected from empirical relationships to produce
concrete with a degree of workability suitable for usual reinforced
construction. When placement is to by pump, they shall be reduced by
about 10 percent.
3. FMS = Fineness Modulus of Sand.
14.8.2 Fine Normal Weight Aggregate
Fine aggregate shall consist of natural sand, manufactured sand or a
combination thereof and shall be graded within the following limits:
Sieve Size Percent passing by Weight
9.50 mm 100
4.75 mm 95 to 100
2.36 mm 80 to 100
1.18 mm 50 to 85
600 microns 25 to 60
300 microns 10 to 30
150 microns 2 to 10
Fine aggregates shall conform to the requirements of IS: 2386. Particular
attention shall be given to those passing through finer screen sizes. For small
line system (less than 150 mm) 15 to 30% shall pass 300 micron sieve and 5
to 10% shall pass 150 micron sieve. Sands, which are deficient in either of
these two sizes shall be blended with selected finer sands or inert material
such as quarry dust to produce these desired percentages.
The fineness modulus of sand meeting the above grading limits will fall
ISSUE
between 2.13 and 3.37 with the median being 2.75. Pumpability of mixes will R9
ISSUE
R9
ISSUE
R9
ISSUE
R9
3. REINFORCEMENT CHECKED
4. COVER TO REINFORCEMENT CHECKED
VERIFIED TEST CERTIFICATE FOR
5. YES/ NO YES/ NO
CEMENT/ STEEL
ADEQUENCY OF MATERIALS/
6. YES/ NO YES/ NO
EQUIPMENT FOR POUR
EMBEDED PARTS CIVIL
CHECKED MECHANICAL
7.
(LOCATION AND
PLUMB) ELECTRICAL
POUR AUTHORISED SITE ENGINEER
SOFFIT(S) AND POUR TOP(T) LEVELS S(B) T(B)
CHECKED BEFORE (B) AND AFTER (A) FORM S(A) T(A)
8. REMOVAL (ONLY OF BEAMS OF OVER 10 M
SPAN AND IMPORTANT STRUCTURES LIKE
TG, ETC.)
CONSTRUCTION JOINT LOCATION AND TIME
9.
(IF NOT AS PER DRAWING)
10. CEMENT CONSUMPTION IN KG
NUMBER OF CUBES AND IDENTIFICATION
11.
MARK
12. TEST CUBE RESULTS (7 DAYS/ 28 DAYS) / / /
VERY GOOD/ GOOD/ FAIR/
13. CONCRETE CONDITION ON FORM REMOVAL
POOR
SITE-IN-CHARGE
NOTES:
1. EACH ITEM TO BE CHECKED AND SIGNED BY THE RESPECTIVE ENGINEERS.
2. ITEMS 8 TO 13 (BOTH INCLUSIVE) TO BE FILLED BY ONLY TCE ENGINEER.
3. EACH POUR TO HAVE SEPARATE CARDS, IN TRIPILCATE ONE EACH FOR CLIENT, TCE
AND SITE OFFICE.
UNDER REMARKS INDICATE DEVIATIONS FROM DRAWINGS AND SPECIFICATIONS,
CONGESTION IN REINFORCEMENT, IF ANY, UNUSUAL OCCURENCES, SUCH AS FAILURE OF
EQUIPMENT, SINKING OF SUPPORTS/ PROPS, HEAVY RAINS AFFECTING CONCRETEING, ISSUE
POOR COMPACTION, IMPROPER CURING, OTHER DEFICIENCIES, OBSERVATIONS, ETC. R9
1 SCOPE
1.1 This specification covers the general requirements for civil and
architectural works comprising of masonry, flooring, skirting, dado,
plastering for wall and ceilings, painting, doors, windows, ventilators,
Builders hardware, ironmongery, Glass and glazing, Partition works,
False ceiling works, toilet cubicles, sanitary fixtures and fittings, water
proofing, Metal sheet cladding, grills and railing works.
1.2 The works under this specification shall consist of furnishing of all
tools, plants, labour, materials, and everything necessary for
execution.
2 MASONRY WORK
2.1 GENERAL
ISSUE
R3
IS:2185 - Specification for concrete masonry units (Parts 1,2 & 3).
2.3.1 MATERIALS
2.3.1.1 Stones for the works shall be of the type specified such as granite,
ISSUE
trap, sandstone, quartzite, etc. and shall be obtained from quarries, R3
2.3.1.4 For preparing cement mortar, the ingredients shall first be mixed
thoroughly in dry condition. Water shall then be added and mixing
continued to give a uniform mix of required consistency. Mixing shall
be done thoroughly in a mechanical mixer, unless hand mixing is
specifically permitted by the ENGINEER. The mortar thus mixed
shall be used as soon as possible, preferably within 30 minutes from
the time water is added to cement. In case, the mortar has stiffened
due to evaporation of water, this may be re-tempered by adding
ISSUE
water as required to restore consistency, but this will be permitted R3
2.3.2 WORKMANSHIP
2.3.2.1 For all works below ground level the masonry shall be random rubble
un-coursed with ordinary quarry dressed stones for the hearting and
selected quarry dressed stones for the facing. Stones having sharp
corners or round surface shall not be used.
2.3.2.2 For all works above ground level and in superstructure the masonry
shall be random rubble un-coursed, well bonded, faced with hammer
dressed stones with squared quoins at corners. The bushings on the
face shall not be more than 40 mm on an exposed face and on the
face to be plastered it shall not project by more than 12 mm nor shall
it have depressions more than 10 mm from the average wall surface.
2.3.2.3 Face stones shall extend back sufficiently and bond well with the
masonry. The depth of stone from the face of the wall inwards shall
not be less than 2/3 the thickness of wall. The length of the stone
shall not exceed three times the height and the breadth on base shall
not be greater than three-fourths the thickness of wall nor less than
150 mm. The height of stone may be upto a maximum of 300 mm.
Hearting stones shall not be less than 150 mm in any direction and
shall be bedded in mortar. Stones shall be laid with its grains
horizontal.
2.3.2.4 Chips and spalls shall be used wherever necessary to avoid thick
mortar joints and to ensure that no hollow spaces are left in the
masonry. The use of chips and spalls in the hearting shall not ISSUE
R3
2.3.2.5 The maximum thickness of joints shall not exceed 20 mm. All joints
shall be completely filled with mortar. When plastering or pointing is
not required to be done, the joints shall be struck flush and finished
as the work proceeds. Otherwise, the joints shall be raked to a
minimum depth of 20 mm by a raking tool during the progress of the
work while the mortar is still green.
brought to the level courses at plinth, window sills, lintel and roof
levels. Levelling shall be done with concrete comprising of one part
of mortar as used for masonry and two parts of graded stone
aggregate of 20mm nominal size. The masonry in structure shall be
carried uniformly. Where the masonry of one part is to be delayed,
the work shall be racked back at an angle not steeper than 45 0.
Height of wall raised in any one day shall not exceed one metre.
2.3.2.10 CONTRACTOR shall note that the unit rates quoted for the masonry
work shall be deemed to include for the installation of miscellaneous
inserts such as pipe sleeves, bolts, steel sections with anchors etc.
and providing pockets, leaving openings, cutting chases etc. in
accordance with the construction drawings. Miscellaneous inserts
shall be either supplied FREE by the OWNER or to be furnished by
the CONTRACTOR. Any of the miscellaneous inserts which are
required to be fabricated and supplied by the CONTRACTOR and
ISSUE
cement concrete to be provided for fixing embedments, hold fasts of R3
2.3.3 MEASUREMENT
2.3.3.2 No deductions shall be made for openings less than 0.1sq.m area or
for embedments upto 0.1 sq.m in section.
2.4.1 MATERIALS
2.4.1.1 The material specification for the work shall be as per clause 2.3.1
2.4.2 WORKMANSHIP
2.4.2.1 Face stones shall be hammer dressed on all beds, and joints so as to
give them approximately rectangular block shape. These shall be
squared on all joints and beds. The bed joint shall be rough chisel
dressed for at least 80 mm back from the face, and side joints for at
least 40 mm such that no portion of the dressed surface is more than
6 mm from a straight edge placed on it. The remaining unexposed
portion of the stone shall not project beyond the surface of bed and
side joint. The bushing on the face shall not project more than 40 mm
as an exposed face and 10 mm on a face to be plastered. The
ISSUE
hammer dressed stone shall also have a rough tooling for minimum R3
width of 25 mm along the four edges of the face of the stone, when
stone work is exposed.
2.4.2.2 All stones shall be wetted before use. The walls shall be carried up
truly plumb or to specified batter. All courses shall not be less laid
truly horizontal and all vertical joints shall be truly vertical. The height
of each course shall not be less than 150mm or more than 300mm
2.4.2.4 The hearting or the interior filling of the wall shall consist of stones
carefully laid on their proper beds in mortar; chips and spalls of stone
being used where necessary to avoid thick beds of joints of mortar
and at the same time ensuring that no hollow spaces are left
anywhere in the masonry. The chips shall not be used bellow the
hearting stone to bring these up to the level of face stones. The use
of chips shall be restricted to the filling of interstices between the
adjacent stones in hearting and these shall not exceed 10% of the
quantity of stone masonry.
2.4.2.6 Bond Stones shall be as specified in 3.1.2.6 except that a bond stone
or a set of bond stones shall be inserted 1.5 to 1.8 meters apart, in
every course.
2.4.2.7 The quoins shall be of the same height as the course in which these
occur. These shall be at least 450 mm long and shall be laid
stretchers and headers alternatively. These shall be laid square on
the beds, which shall be rough-chisel dressed to depth of at least 100 ISSUE
R3
2.4.2.8 All bed joints shall be horizontal and all side joints vertical. All joints
shall be fully packed with mortar, ace joints shall not be more than
one cm thick. When plastering or pointing is not required to be done,
the joints shall be struck flush and finished at the time of laying.
Otherwise, joints shall be raked to a minimum depth of 20 mm by
raking tool during the progress of work, when the mortar is still green.
2.4.3 MEASUREMENT
2.5.1 Bricks used in the works shall conform to the requirements laid down
in IS:1077 /IS:13757. The class of the bricks shall be as specifically
indicated in the respective items of work.
thickness of one brick and half brick walls using non-modular bricks
shall be considered as 230 mm and 115 mm respectively. The
dimensional tolerances of modular and non-modular sized bricks
over the standard sizes shall be as per IS 1077. / IS13757.
2.5.4 Clay Fly ash bricks shall be hand/machine moulded and shall be
made from the admixture of suitable soils and fly ash in optimum
proportioned as per IS2117. Fly ash used for manufacture of bricks
shall conforming to grade 1 or grade 2 as per IS3812. The bricks
shall be free from pores, cracks, flaws and nodules of free lime.
Hand moulded bricks shall be moulded with a frog and those made
by extrusion process may not be provided with a frog. Bricks shall
give a clear ringing sound when struck and shall have a minimum
crushing strength of 5N/sq.mm unless otherwise specified in the
item.
2.5.5 The average water absorption shall not be more than 20 percentages
by weight up to class 12.5 and 15 percentages by weight for higher
classes. Bricks which do not conform to this requirement shall be
rejected. Over or under burnt bricks are not acceptable for use in the
works.
2.5.6 Sample bricks shall be submitted to the ENGINEER for approval and
ISSUE
bricks supplied shall conform to approved samples. If demanded by R3
2.5.7 Mortar for brick masonry shall consist of cement and sand and shall
be prepared as per IS:2250. Mix shall be in the proportion of 1:5 for
all brickworks, unless otherwise specified in the respective items of
work. Sand for masonry mortar shall conform to IS:2116. The sand
shall be free from clay, shale, loam, alkali and organic matter and
shall be of sound, hard, clean and durable particles. Sand shall be
approved by ENGINEER. If so directed by the ENGINEER, sand
shall be screened and washed till it satisfies the limits of deleterious
materials.
2.5.8 For preparing cement mortar, the ingredients shall first be mixed
thoroughly in dry condition. Water shall then be added and mixing
continued to give a uniform mix of required consistency. Mixing shall
be done thoroughly in a mechanical mixer, unless hand mixing is
specifically permitted by the ENGINEER. The mortar thus mixed
shall be used as soon as possible, preferably within 30 minutes from
the time water is added to cement. In case, the mortar has stiffened
due to evaporation of water, this may be re-tempered by adding
water as required to restore consistency, but this will be permitted
only upto 30 minutes from the time of initial mixing of water to
cement. Any mortar which is partially set shall be rejected and shall
be removed forthwith from the site. Droppings of mortar shall not be
re-used under any circumstances.
2.5.10 WORKMANSHIP
2.5.10.1 Workmanship of brick work shall conform to IS: 2212. All bricks shall
be thoroughly soaked in clean water for at least one hour ISSUE
R3
immediately before being laid. The cement mortar for brick masonry
work shall be as specified in the respective item of work. Brick work
200mm/230mm thick and over shall be laid in English Bond unless
otherwise specified. 100mm/115mm thick brickwork shall be laid with
stretchers. For laying bricks, a layer of mortar shall be spread over
the full width of suitable length of the lower course. Each brick shall
be slightly pressed into the mortar and shoved into final position so
as to embed the brick fully in mortar. Only full size bricks shall be
used for the works and cut bricks utilised only to make up required
wall length or for bonding. Bricks shall be laid with frogs uppermost.
2.5.10.2 All brickwork shall be plumb, square and true to dimensions shown.
Vertical joints in alternate courses shall come directly one over the
other and be in line. Horizontal courses shall be levelled. The
thickness of brick courses shall be kept uniform. In case of one brick
thick or half brick thick wall, at least one face should be kept smooth
and plane, even if the other is slightly rough due to variation in size of
bricks. For walls of thickness greater than one brick both faces shall
be kept smooth and plane. All interconnected brickwork shall be
carried out at nearly one level so that there is uniform distribution of
pressure on the supporting structure and no portion of the work shall
be left more than one course lower than the adjacent work. Where
this is not possible, the work shall be raked back according to bond
(and not saw toothed) at an angle not exceeding 45 0. But in no case
the level difference between adjoining walls shall exceed one metre.
Brick-work shall not be raised more than one metre per day.
2.5.10.3 Bricks shall be so laid that all joints are well filled with mortar. The
thickness of joints shall not be less than 6 mm and not more than 10
mm. The face joints shall be raked to a minimum depth of
10mm/15mm by raking tools during the progress of work when the
mortar is still green, so as to provide a proper key for the
plastering/pointing respectively to be done later. When plastering or ISSUE
R3
pointing is not required to be done, the joints shall be uniform in
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 13 of 173
thickness and be struck flush and finished at the time of laying. The
face of brickwork shall be cleaned daily and all mortar droppings
removed. The surface of each course shall be thoroughly cleaned of
all dirt before another course is laid on top.
2.5.10.5 Brickwork shall be kept constantly moist on all the faces for at least
seven days. The arrangement for curing shall be got approved from
the ENGINEER.
2.5.10.8 All brickwork shall be built tightly against columns, floor slabs or other
structural members.
ISSUE
R3
2.5.10.10 The above items shall be measured and paid for separately under
the respective items of work.
2.5.10.11 Bricks for partition walls shall be stacked adjacent to the structural
member to pre-deflect the structural member before the wall is taken
up for execution. Further, the top most course of half or full brick
walls abutting against either a de-shuttered slab or beam shall be
built only after any proposed masonry wall above the structural
member is executed to cater for the deflection of the structural
element.
2.5.10.14 CONTRACTOR shall note that the unit rates quoted for the masonry
work shall be deemed to include for the installation of miscellaneous
inserts such as pipe sleeves, bolts, steel sections with anchors etc.
and providing pockets, leaving openings, cutting chases etc. in
accordance with the construction drawings. Miscellaneous inserts
shall be either supplied FREE by the OWNER or to be furnished by
the CONTRACTOR. Any of the miscellaneous inserts which are
required to be fabricated and supplied by the CONTRACTOR and
cement concrete to be provided for fixing embedments, hold fasts of
door/window frames etc. shall however, be measured and paid
separately under the respective items of work. .
2.5.10.15 Facing bricks of the type specified conforming to IS:2691 shall be laid
in the positions indicated on the drawings and all facing brickwork
shall be well bonded to the backing bricks/RCC surfaces. The level of
execution of the facing brickwork shall at any time be lower by at
least 600 mm below the level of the backing brickwork.
2.5.10.18 Faced works shall be kept clean and free from damage, discoloration
etc., at all times.
2.5.10.19 Cutting of chases in 230 thick wall and above for routing GI pipes, CI
pipes or for any other services shall preferably be in the vertical ISSUE
R3
ISSUE
R3
2.5.11 MEASUREMENT
2.5.11.2 No deductions shall be made for openings less than 0.1sq.m area or
for embedment upto 0.1 sq.m in section.
2.5.11.4 All concrete works shall he measured and paid for separately under
the respective items of work.
2.6.1 MATERIALS
2.6.1.1 Masonry units of hollow and solid concrete blocks shall conform to
the requirements of IS : 2185 (Part 1).
2.6.1.2 Masonry units of hollow and solid light-weight concrete blocks shall
conform to the requirements of IS:2185 (Part 2).
2.6.1.6 The maximum variation in the length of the units shall not be more
than + 5mm and maximum variation in height or width of the units
shall not be more than + 3mm.
2.6.1.7 Concrete blocks shall be either hollow blocks with open or closed
cavities or solid blocks.
2.6.1.9 The concrete mix for the hollow and solid concrete blocks/light weight
concrete blocks shall not be richer than one part of cement to six
parts of combined aggregates by volume i.e. (1:6).
2.6.2 WORKMANSHIP
2.6.2.1 The type of the concrete block, thickness and grade based on the
compressive strength for use in load bearing and/or non-load bearing ISSUE
walls shall be as specified in the respective items of work. The R3
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 19 of 173
2.6.2.5 The thickness of both horizontal and vertical joints shall be 10 mm.
The first course shall he laid with greater care, ensuring that it is
properly aligned, levelled and plumb since this will facilitate in laying
succeeding courses to obtain a straight and truly vertical wall. For
the horizontal (bedding) joint, mortar shall be spread over the entire
top surface of the block including front and rear as well as the edges
to a uniform layer of 10 mm. For vertical joints, the mortar shall be
applied on the vertical edges of the front and rear sides of the blocks.
The mortar may be applied either to the unit already placed on the
wall or on the edges of the succeeding unit when it is standing
vertically and then placing it horizontally, well pressed against the
previously laid unit to produce a compacted vertical joint. To assure
satisfactory bond, mortar shall not be spread too far ahead of actual
laying of the block as the mortar will stiffen and lose its plasticity.
Mortar while hardening shrinks slightly and thus pulls away from the ISSUE
R3
edges of the block. The mortar shall be pressed against the units
with a jointing tool after it has stiffened to effect intimate contact
between the mortar and the unit to obtain a weather tight joint. The
mortar shall be raked to a depth of 10 mm as each course is laid to
ensure good bond for the plaster.
2.6.2.6 Only well dried blocks should be used for the construction. Blocks
with moisture content more than 25% of maximum water absorption
permissible shall not he used. The blocks should not be wetted
before or during laying in the walls. Blocks should be laid dry except
slightly moistening their surface on which mortar is to be applied to
obviate absorption of water from the mortar.
2.6.2.7 For jambs of doors, windows and openings, solid concrete blocks
shall he provided. If hollow units are used, the hollows shall be filled
with concrete of mix 1:3:6. Hold fasts of doors/windows should be
arranged so that they occur at block course level.
2.6.2.8 At intersection of walls, the courses shall laid up at the same time
with a true masonry bond between at least 50% of the concrete
blocks. The sequence for construction of partition walls and
treatment at the top of load bearing walls for the RCC slab shall be
as detailed under clause 3 for the brick work.
2.6.2.9 Curing of the mortar joints shall be carried out for atleast 7 days. The
walls should only be lightly moistened and shall not be allowed to
become excessively wet.
2.6.2.12 Concrete blocks shall be stored at site suitably to avoid any contact
with moisture from the ground and covered to protect against wetting.
2.6.3 MEASUREMENT
ISSUE
R3
3.1 GENERAL
3.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
IS: 383 Coarse and fine aggregates from natural sources for
concrete
IS:456 Plain And Reinforced Concrete - Code Of Practice
ISSUE
R3
3.3.1 MATERIALS
3.3.1.1 Stone used under grade slab for rubble soling on grade, foundations
etc., shall be clean, hard, durable rock free from viens, flaws,
luminations, weathering and other defects. Stones shall generally
conform to the requirements stipulated in IS:1597 (Part-I).
3.3.2 WORKMANSHIP
3.3.2.1 Stones shall be hand packed carefully and laid with their largest base
downwards resting flat on the prepared sub-grade and with their
height equal to the thickness of the packing. Stones shall be laid
breaking joints and in close contact with each other-. All interstices
between the stones shall be wedged-in by small stones of suitable
size, well driven in by crow bars and hammers to ensure tight
packing and complete filling-in of the interstices. The wedging shall
be tarried out simultaneously with the placing in position of rubble
packing and shall not lag behind. After this, any interstices between
the smaller wedged stones shall be in-filled with clean hard sand by
brooming so as to fill the joints completely.
3.3.2.2 The laid rubble packing shall be sprinkled with water and compacted
by using suitable rammers/rollers.
ISSUE
R3
3.3.3 MEASUREMENT
3.4.1 WORKMANSHIP
3.4.1.1 The thickness and grade of concrete shall be as specified in the item
of work.
3.4.1.2 Before placing the blinding concrete, 50/75mm thick as per the item
of work, the sub-base of rubble packing shall be properly wetted and
rammed. Concrete for the base shall then be deposited between the
forms, thoroughly tamped and the surface finished level with the top
edges of the forms. Two or three hours after the concrete has been
laid in position, the surface shall be roughened using steel wire brush
to remove any scum or laitance and swept clean so that the coarse
aggregates are exposed. The surface of the base concrete shall be
left rough to provide adequate bond for the floor finish to be provided
later.
3.4.2 MEASUREMENT
3.5.1 Terrazzo tiles and cement tiles shall generally conform in all respects
to standards stipulated in IS:1237. Tiles shall be of the best quality
manufactured adopting hydraulic pressure of not less than 14N/mm 2.
3.5.2 The type, quality, size, thickness colour etc, of the tiles for
flooring/dado/ skirting shall be as specified in the respective items of ISSUE
R3
work.
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 27 of 173
3.5.3 The aggregates for terrazzo topping shall consist of marble chips
which are hard, sound and dense. Cement to be used shall be either
ordinary Portland cement or white cement with or without colouring
pigment. The binder mix shall be with 3 parts of cement to 1 part of
marble powder by weight. The proportion of cement shall be inclusive
of any pigments. For every one part of cement-marble powder binder
mix, the proportion of aggregates shall be 1.75 parts by volume, if the
chips are between l mm to 6mm and 1.50 parts by volume if the
chips are between 6mm to 25mm.
3.5.4 The minimum thickness of wearing layer of plain cement and plain
coloured tiles for general purpose and terrazzo tiles with chips upto
6mm to 12mm general purpose is 5mm thick tiles. Terrazo tiles with
chips of size up to 20mm for heavy duty and general purpose and
plain cement and plain coloured tiles for heavy duty shall be 6mm
thick tiles. Pigment used in the wearing layer shall not exceed 10
percent of the weight of cement used in the mix.
3.5.5 WORKMANSHIP
3.5.5.2 Tiling work shall be commenced only after the door and window
frames are fixed and plastering of the walls/ ceiling is completed.
Wall plastering shall not be carried out up to about 50mm above the
level of proposed skirting/dado.
3.5.5.5 Neat cement slurry using 4.4 kg of cement per one sq.m of floor area
shall be spread over the hardened mortar bedding over such an area
at a time as would accommodate about 20 tiles. Tiles shall be fixed in
this slurry one after the other, each tile being gently tapped with a
wooden mallet till it is properly bedded and in level with the adjoining
tiles. The joints shall be in straight lines and shall normally be 1.5mm
wide. On completion of laying of the tiles in a room, all the Joints
shall be cleaned and washed fairly deep with a stiff broom/wire brush
to a minimum depth of 5mm. The day after the tiles have been laid,
the joints shall be filled with cement grout of the same shade on the
colour of the matrix of the tile. For this purpose white cement or grey
cement with or without pigments shall be used. The flooring should
be kept moist and left undisturbed for 7 days for the bedding/joints to
set properly. Heavy traffic shall not be allowed on the floor for at least
14 days after fixing of the tiles.
3.5.5.6 About a week after laying the tiles, each and every tile shall be lightly
tapped with a small wooden mallet to find out if it gives a hollow
sound; if it does, such tiles along with any other cracked or broken
tiles shall be removed and replaced with new tiles to proper line and
level. The same procedure shall be followed again after grinding the
tiles and all damaged tiles replaced, properly jointed and finished to
match. For the purpose of ensuring that such replaced tiles match ISSUE
R3
3.5.5.7 Wherever a full tile cannot be provided, tiles shall be cut to size and
fixed. Floor tiles adjoining the wall shall go about 10mm under the
plaster, skirting or dado.
3.5.5.8 Tile skirting and dado work shall be executed only after laying tiles on
the floor. For dado and skirting work, the vertical wall surface shall be
thoroughly cleaned and wetted. Thereafter it shall be evenly and
uniformly covered with 12mm thick backing of 1:4 cement sand
mortar. For this work the tiles as obtained from the factory shall be of
the size required and practically full polished. The back of each tile to
be fixed shall be covered with a thin layer of neat cement paste and
the tile shall then be gently tapped against the wall with a wooden
mallet. Fixing shall be done from the bottom of the wall upwards. The
joints shall be in straight lines and shall normally be 1.5mm wide. Any
difference in the thickness of the tiles shall be evened out in the
backing mortar or cement paste so that the tile faces are in
conformity & truly plumb. Tiles for use at the corners shall be suitably
cut with bevelled edges to obtain a neat and true joint. After the work
has set, hand polishing with carborundum stones shall be done so
that the surface matches with the floor finish.
3.5.5.9 Wall plastering of the strip left out above the level of skirting/dado
shall be taken up after the tiles are fixed.
3.5.5.10 CONTRACTOR shall note that the unit rate quoted for skirting shall
also include for any chipping of the brick work required to be carried
out for this item.
3.5.5.11 Chequered terrazzo tiles for flooring and for stair treads shall be
delivered to site after the first machine grinding.
ISSUE
R3
3.5.5.12 Machine grinding and polishing shall be commenced only after a gap
of 14 days of laying. The sequence and three numbers of machine
grinding operations, usage of the type of carborundum stones, filling
up of pin holes, watering etc. shall be carried out all as specified in
IS:1443.
3.5.5.13 Tiles shall be laid to the levels specified. To ensure this, finished floor
levels should be marked at all door locations and also on the floor at
frequent intervals. Where large areas are to be tiled the level of the
central portion shall be kept l0mm higher than that at the walls
to overcome optical illusion of a depression in the central portion.
Localized deviation of 3mm in any 3m length is acceptable in a
nominally flat floor.
3.5.5.14 All corners shall be in perfect right angle matching up with the
corners of walls. If due to any misalignment during construction, the
corners of wall are not at right angle, adjustment shall be made in the
title portion lying below skirting.
3.5.5.15 Flooring in toilets, kitchen shall be taken up only after fixing water
closet, squatting pans & floor traps.
3.6.1 The aggregates for terrazzo topping shall consist of marble chips
which are hard, sound and dense.
3.6.3 The binder mix shall be with 3 parts of cement to 1 part of marble
powder by weight. The proportion of cement shall be inclusive of any
pigments. For every one part of cement-marble powder binder mix,
the proportion of aggregates shall be 1.75 parts by volume, if the
chips are between l mm to 6mm and 1.50 parts by volume if the
ISSUE
chips are between 6mm to 25mm. R3
3.6.4 WORKMANSHIP
3.6.4.1 Cement shall first be mixed with the marble powder in dry state. The
mix thus obtained shall be mixed with the aggregates in the specified
proportions.
3.6.4.2 Care shall be taken not to get the materials into a heap which results
in the coarsest chips falling to the edges and cement working to the
centre at the bottom.
3.6.4.4 The mix shall be used in the works within 30 minutes of the addition
of water to the cement.
3.6.4.5 The thickness, type, quality, size and colour of chips etc. for the in-
situ terrazzo finish for flooring/dado skirting shall be as specified in
the respective items of work. Laying and finishing of in-situ work shall
conform to the requirements of workmanship stipulated in IS: 2114.
3.6.4.6 In-situ terrazzo finish shall be laid over hardened concrete base. The
finish layer consists of an under layer and terrazzo topping. The
under layer shall be of cement concrete of mix 1:2:4 using l0mm
downgraded coarse aggregates. The combined thickness of under
layer and topping shall not be less than 30 mm for flooring and 20mm
for dado/skirting work.
3.6.4.7 The minimum thickness of topping shall be 6mm if chips used are
between 1mm to 4mm, 9mm if chips are between 4mm to 7mm and
12mm if chips are between 7mm to l0mm. If chips larger than l0mm
size are used, the minimum thickness shall be one and one third the
maximum size of chips. ISSUE
R3
3.6.4.8 Both the under layer and later the topping shall be divided into panels
not exceeding 2 Sq.m. for laying so as to reduce the possibility of
development of cracks. The longer dimension of any panel shall not
exceed 2m. Dividing strips shall be used to separate the panels.
When the dividing strips are not provided, the bays shall be laid
alternately, allowing an interval of at least 24 hours between laying
adjacent bays.
3.6.4.11 Terrazzo topping shall be laid while the under-layer is still plastic and
normally between 18 to 24 hours after the under-layer is laid. Cement
slurry of the same colour as the topping shall be brushed on the
surface immediately before laying is commenced. The terrazzo mix
shall be laid to a uniform thickness and compacted thoroughly by
tamping and with a minimum of trowelling. Straight edge and steel
ISSUE
floats shall be used to bring the surface true to the required level in R3
3.6.4.12 The surface shall be left dry for air-curing for a period of 12 to 18
hours. Thereafter it shall be cured by allowing water to stand in pools
for a period of not less than 4 days.
3.6.4.13 Machine grinding and polishing shall be commenced only after a gap
of 7 days from the time of completion of laying. The sequence and
four numbers of machine grinding operations, usage of the type of
carborundum stones, filling up of pinholes, wet curing, watering etc
shall be carried out all as specified in IS: 2114. Where machine
polishing is not possible, polishing shall be carried out by hand in the
same sequence and procedure as for machine polishing.
3.6.4.14 Where the dampness from ground may find its way to the top of floor,
concrete floor on the ground or basement shall be provided with an
effective damp proof.
3.6.4.15 Flooring in toilet and kitchen shall be taken up after fixing water
closet, squatting pans and floor trap.
3.7.1 The mix proportion for the in-situ concrete floor topping shall be
1:2.5:3.5(one part cement: two and half parts sand : three and half
parts coarse aggregates) by volume unless otherwise specified in the
item of work.
3.7.3 Coarse aggregates shall have high hardness surface texture and
shall consist of crushed rock of granite, basalt, trap or quartzite. The
aggregate crushing value shall not exceed 30 percent. The grading
ISSUE
R3
3.7.4 Grading of the sand shall be within the limits indicated in IS:2571.
3.7.5 WORKMANSHIP
3.7.5.1 The thickness of the floor topping shall be as specified in the item of
work. The minimum thickness of the floor topping shall be 25mm, if it
is laid separately. 15mm thick wearing course of cement concrete 1:2
(1 cement:2 stone) aggregate of size 4.75mm & below) by volume
shall be applied monolithically over floor topping, if called for in the
schedule of item. Wearing course shall be 20mm thick, if it is cast
monolithically over ground floor slab. Laying and finishing of in-situ
topping shall conform to the requirements of IS 2571.
3.7.5.2 The surface shall be rough to provide adequate bond for the topping.
It shall be finished to a level below the finished floor equal to the
thickness of topping and / or wearing courses, if specified.
3.7.5.4 Floor finish shall be laid in suitable panels to reduce the risk of
cracking. No dimension of a panel shall exceed 2 meters and the
length of a panel shall not exceed one and a half times its breadth.
Topping shall be laid in alternate panels, the intermediate panels
being cast after a gap of at least one day. Construction joints shall be
plain vertical butt joints.
3.7.5.5 Screed strips shall be fixed dividing the area into suitable panels.
ISSUE
Immediately before depositing the concrete topping, neat cement R3
3.7.5.9 In severe condition, where dampness from ground may find its way
on the top of the floor, the floor slab shall be cast in two equal halves.
The top surface of bottom half shall be made plane and smooth after
it is cast. A coat of bitumen primer conforming to IS 3384 shall be
applied on the hard surface over which two coats of bitumen
conforming to IS 1580 shall be applied @ 1.5 kg/m2 for each layer.
After the bitumen surface is dry, the top half of floor slab shall be
cast.
3.8.2 The thickness of the floor topping shall be as specified in the item of
work. The minimum thickness of granolithic floor topping on
hardened concrete base shall be 40mm, if laid separately. It shall be
20mm, if the topping is laid monolithically over the floor concrete.
3.9.2 Floor hardener of the metallic or non-metallic type suitable for the
performance of normal/medium/heavy duty function of the floor, the
quantum of ingredients and the thickness of topping shall be as
specified in the respective items of work.
3.9.3 For monolithic application with the floor finish/slab, the thickness of
the layer shall be 15mm. It shall be 20mm if it is laid separately over
floor slab. The topping shall be laid within 2 to 3 hours after concrete
is laid and it is still plastic but stiffened enough for the workmen to
tread over it by placing planks. The surface of the concrete layer ISSUE
R3
shall be kept rough for providing adequate band for the topping.
Laitance shall be removed before placing the topping. The topping
shall be screeded and thoroughly compacted to the finished level.
After the surface has hardened sufficiently, it shall be kept
continuously moist for at least 10 days.
3.9.4 The procedure for mixing the floor hardener topping shall be as per
manufacturer's instructions.
3.9.5 Floor hardener topping shall be prevented from any damages due to
subsequent building operations by covering with 75 mm thick layer of
sand, if it is laid monolithically with the slab.
3.10.1 The epoxy resin and hardener formulation for laying of Pointless
lining work in floors and walls of concrete tanks/trenches, floor
toppings etc shall be as per the requirements of IS:9197. Method of
laying shall be as per the requirements of IS 4631.
3.10.3 Epoxy resin shall be of liquid type of suitable grade and class as
recommended by the manufacturer.
3.10.4 The hardener shall be of the liquid type such as Aliphatic Amine or
an Aliphatic/Aromatic Amine Adduct or a polyamide or amido
polyamine of suitable characteristics. The hardener shall react with
epoxy resin at normal ambient temperature above 5oC.
3.10.6 Accelerator, plasticizer and coal tar may be added for the preparation ISSUE
of epoxy composition, to the proportion as recommended in IS 9197. R3
3.10.8 WORKMANSHIP
3.10.8.2 The epoxy lining shall be of the trowel type to facilitate execution of
the required thickness for satisfactory performance.
3.10.8.3 The concrete surfaces over which epoxy lining is to be provided shall
be thoroughly cleaned of oil or grease by suitable solvents, wire
brushed to remove any dirt/dust and laitance. The surfaces shall then
be washed with dilute hydrochloric acid (10% to 15%) and rinsed
thoroughly with plenty of water or dilute ammonia solution. The
surfaces shall then be allowed to dry. It is essential to ensure that the
surfaces are perfectly dry and even, before the commencement of
epoxy application.
3.10.8.4 Just adequate quantity of epoxy resin which can be applied within the
pot life as specified by the manufacturer shall be prepared at one
time for laying and jointing.
3.10.8.7 For epoxy lining over the inside concrete surfaces of underground
tank or trenches, it should be ensured that they are leak proof
against water by conducting leakage test.
3.11.1 The slabs shall be of approved selected quality, hard, sound, dense
and homogenous in texture, free from cracks, decay, weathering and
flaws. The percentage of water absorption shall not exceed 5 percent
as per test conducted in accordance with IS:1124.
3.11.2 The slabs shall be hand or machine cut to the required thickness.
Tolerance in thickness for dimensions of tile more than 100 mm shall
be ±5mm. This shall be + 2mm on dimensions less than l00mm.
3.11.3 Slabs shall be supplied to the specified size with machine cut edges
or fine chisel dressed to the full depth. All angles and edges of the
slabs shall be true and square, free from any chipping giving a plane
surface. Slabs shall have the top surface machine polished (first
grinding) before being brought to site. The slabs shall be washed
clean before laying.
3.11.4 WORKMANSHIP
3.11.4.1 The type, size, thickness and colour/shade etc. of the slabs for
flooring/dado/ skirting shall be as specified in the respective items of
the work.
3.11.4.2 Concrete base shall be prepared and finished below the finished floor
level equal to the thickness of stone slab and cement mortar below.
3.11.4.3 The thickness of the slabs for dado/skirting work shall not be more
than 25mm. Slabs shall be so placed that the back surface is at a
distance of 12mm from the wall. If necessary, slabs shall be held in
position temporarily by suitable method. After checking for verticality, ISSUE
the gap shall be filled and packed with cement sand mortar of R3
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 40 of 173
proportion 1:3. After the mortar has acquired sufficient strength, the
temporary arrangement holding the slab shall be removed. The
recommended mortar mix for joints and beddings for stone blocks
shall be two parts of white cement and seven parts of stone dust.
The thickness of joints shall be 5 mm. For fixing of stones to the
walls, fixing clamps of non-ferrous metal should be used.
3.11.4.4 Grinding and polishing shall be as per clause 3.6.4.13 except that
first grinding with coarse grade carborundum shall not be done and
cement slurry with or without pigment shall not be applied before
polishing.
3.12.2 Each tile shall bear on its back, permanent and legible trade mark of
the manufacturer. All angles of the tiles shall be right angle, all edges
sharp and true, colour and texture of the wearing face uniform
throughout. Maximum tolerance/allowance for length and breadth
shall be +1 mm and thickness +3mm along the wearing surface of
the tile and the wearing surface shall be planed free from pin-holes
and other blemishes.
3.12.4 The topping shall be uniform and of thickness not less than 6mm.
The quantity of carborundum grit shall be not less than 1.35 kg/sq.m
used with cement with or without pigment. The carborundum grit
shall pass through 1.18mm mesh and shall be retained on
ISSUE
R3
0.60mm mesh. The total thickness of tiles including the topping shall
be not less than 20 mm.
3.12.5 The tile shall be cured at the shop for at least 14 days before delivery
to site. Tiles shall be packed properly to prevent damage during
transit and storage. The tiles must be stored carefully to prevent
staining by damp, rust, oil and grease or other chemicals. Tiles made
in each batch shall be kept and used separately so that the colour of
each area of floor may remain uniform.
3.12.6 The manufacturer shall supply along with the tiles the grout mix
containing cement and pigment in exact proportions as used in
topping of tiles. The containers of the grout mix shall be suitably
marked to relate it to the particular type and batch of tiles
3.12.7 The size, thickness, colour and plain or chequered etc. of the tiles for
flooring/skirting shall be as specified in the respective items of work.
The under bed for floors shall be 1 part cement: 2 parts coarse sand:
4 parts stone aggregate by volume mix with sufficient water to form a
stiff workable mass. For skirting and dado, it shall be 1 part cement:
3 parts coarse sand by volume.
3.12.8 The total average thickness shall be minimum 50 mm for floors and
30 mm for walls.
3.12.9 WORKMANSHIP
3.13.1 Tiles shall be of the best quality from an approved manufacturer. The
tiles shall be flat, true to shape and free from flaws such as crazing,
blisters, pinholes, specks or welts. Edges and underside of the tiles
shall be free from glaze and shall have ribs or indentations for a
ISSUE
R3
3.13.2 WORKMANSHIP
3.13.2.1 The size, thickness, colour, with or without designs etc of the tiles for
flooring/dado/skirting shall be as specified in the respective items of
work.
3.13.2.2 The total thickness of glazed tile finish including the bedding mortar
shall be maximum 20 mm in flooring/dado/skirting. The minimum
thickness of bedding mortar shall be 12mm for flooring and l0mm for
dado/skirting work.
3.13.2.4 Tiles shall be soaked in water for about 10 minutes just before laying.
Where full size tiles cannot be fixed, tiles shall be cut to the required
size using special cutting device and the edges rubbed smooth to
ensure straight and true joints.
3.13.2.5 Coloured tiles with or without designs shall be uniform and shall be
preferably procured from the same batch of manufacture to avoid any
differences in the shade.
3.13.2.6 Tiles for the flooring shall be laid over hardened concrete base. The
surface of the concrete base shall be cleaned of all loose materials,
mortar droppings etc well wetted without allowing any water pools on
the surface. The bedding mortar shall then be laid evenly over the
surface, tamped to the desired level and allowed to harden for a day.
The top surface shall be left rough to provide a good band for the
tiles. For skirting and dado work, the brick walls shall be raked to a
ISSUE
depth of 15mm. In case of concrete walls, the surfaces shall be R3
3.13.2.7 Neat cement slurry using 3.3 kg cement per one sq.m of floor area
shall be spread over the hardened mortar bed over such an area as
would accommodate about 20 tiles. Tiles shall be fixed in this slurry
one after the other, each tile being gently tapped with a wooden
mallet till it is properly bedded and in level with the adjoining tiles. For
skirting and dado work, the back of the tiles shall be smeared with
cement slurry for setting on the backing mortar.
3.13.2.8 Fixing of tiles shall be done from the bottom of the wall upwards. The
joints shall be in perfect straight lines and as thin as possible but
shall not be more than l mm wide. Tiles used for corners shall be
suitably beveled to obtain a true and neat joint. The surface shall be
checked frequently to ensure correct level/required slope. Floor tiles
near the walls shall enter skirting/dado to a minimum depth of 10mm.
Tiles shall not sound hollow when tapped.
3.13.2.9 All the joints shall be cleaned of grey cement with wire brush to a
depth of at least 3mm and all dust, loose mortar etc. shall be
removed. White cement with or without pigment shall then be used
for flush pointing the joints. Curing shall then be carried out for a
minimum period of 7 days for the bedding and joints to set properly.
The surface shall then be cleaned using a suitable detergent, fully
washed and wiped dry.
3.14.2 The surface of the sheets/tiles shall be free from any physical defects
such as pores, blisters, cracks etc. which affects the appearance and
serviceability. Tiles/sheets shall meet with the tolerance limits in
dimensions specified in the IS codes. CONTRACTOR shall submit
the test certificates, if so desired by the ENGINEER.
3.14.3 Each tile/sheet shall be legibly and indelibly marked with the name of
the manufacturer or his trade mark, IS certificate mark and batch
number.
3.14.4 The adhesive to be used for laying the PVC/VINYL flooring shall be
rubber based conforming to IS 12830 and of the make as
recommended and approved by the manufacturer of PVC/VINYL
sheets/tiles.
3.14.5 The type, size, thickness, colour, plain or mottled and the pattern
shall be as specified in the respective items of work.
3.14.6 WORKMANSHIP
3.14.6.1 Laying of PVC / VINYL sheets / tiles shall conform IS 5318. PVC /
VINYL floor covering shall be provided over an under bed of cement
concrete floor finish over the base concrete or structural slab. It is
essential that the sub-floor and the under bed are perfectly dry before
laying the PVC / VINYL flooring. This shall be ensured by methods of
testing as stipulated in Appendix-A of IS:5318. Concrete floor on the
ground / basement shall be treated with an effective damp proof
course.
3.14.6.2 The surface of the under bed shall have trowelled finish without any
irregularities which creates poor adhesion. Surface shall be free of oil
ISSUE
R3
or grease and thoroughly cleaned of all dust, dirt and wiped with a
dry cloth.
3.14.6.4 Layout of the PVC / VINYL flooring shall be marked with guidelines
on the under bed and PVC / VINYL tiles/sheets shall be first laid for
trial, without using the adhesive, according to the layout.
3.14.6.6 PVC / VINYL sheet shall be carefully taken and placed in position
from one end onwards slowly so that the air will be completely
squeezed out between the sheet and the background surface and no
air pockets are formed. It shall then be pressed with a suitable roller
to develop proper contact. The next sheet shall be laid edge to edge
with the sheet already laid, so that there is minimum gap between
joints. The alignment shall be checked after each row of sheet is
completed and trimmed if considered necessary.
ISSUE
R3
3.14.6.7 Tiles shall be laid in the same manner as sheets and preferably,
commencing from the centre of the area. Tiles should be lowered in
position and pressed firmly on to the adhesive with minimum gap
between the joints. Tiles shall not be slided on the surface. Tiles shall
be rolled with a light wooden roller of about 5kg to ensure full contact
with the underlay. Work should be constantly checked to ensure that
all four edges of adjacent tiles meet accurately.
3.14.6.9 A minimum period of 24 hours shall be given after laying for the
development of proper bond of the adhesive. When the flooring in
thus completed, it shall be cleaned with a wet cloth soaked in warm
soap solution.
3.14.6.10 Metallic edge strips shall be used to protect the edges of PVC /
VINYL sheets/tiles which are exposed as in doorways/ stair treads.
3.14.6.11 Hot sealing of joints between adjacent PVC / VINYL sheet flooring to
prevent creeping of water through the Joints shall be carried out, if
specified in the item of work, using special equipment as per
manufacturer's instructions.
3.14.6.12 It is desirable that the PVC / VINYL flooring are taken up after
completing all other works in the area so as to avoid any accidental
damage to the flooring.
ISSUE
R3
3.15.1 The ceramic unglazed vitreous acid resisting tiles shall conform to
the requirements of IS: 4457.
3.15.2 The finished tile when fractured shall appear fine grained in texture,
dense and homogeneous. Tile shall be sound, true to shape, flat,
free from flaws and any manufacturing defects affecting their utility.
Tolerance in the dimensions shall be within the limits specified in the
respective IS code.
3.15.3 The tiles shall be bedded and jointed using chemical resistant mortar
prepared from resin type conforming to IS: 4832 (Part II) filter,
accelerator and catalyst mixed in proportion as recommended by
manufacturers. Method of usage shall generally be as per the
requirements of IS: 4443.
3.15.4 WORKMANSHIP
3.15.4.1 The size and thickness of tiles for use in the flooring/skirting/dado
shall be as specified in the respective items of work.
3.15.4.2 The base concrete surface shall be free from dirt and thoroughly
dried. The surface shall be applied with a coat of bitumen primer
conforming to IS: 3384. The primed surface shall then be applied
with a uniform coat of bitumen conforming to IS: 1580. Tiles shall be
laid directly without the application of bitumen, if epoxy or polyester
resin is used for the mortar.
3.15.4.3 Just adequate quantity of mortar which can be applied within the pot
life as specified by the manufacturer shall be prepared at one time for
bedding and jointing. Rigid PVC/Stainless steel/chromium plated
tools shall be used for mixing and laying.
3.15.4.4 For laying the floor 6 to 8 mm thick mortar shall be spread on the
back of the tile. Two adjacent sides of the tile shall be smeared with 4 ISSUE
to 6 mm thick mortar. Tile shall be pressed into the bed and pushed R3
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 48 of 173
against the floor and with the adjacent tile, until the joint in each case
is 2 to 3 mm thick. Excess mortar shall then be trimmed off and
allowed to harden fully. Similar procedure shall be adopted for the
work on walls by pressing the tile/brick against the prepared wall
surfaces and only one course shall be laid at a time until the initial
setting period.
3.15.4.5 The mortar joints shall be cured for a minimum period of 72 hours
with 20 to 25% hydrochloric acid or 30 to 40% sulphuric acid. After
acid curing, the joints shall be washed with water and allowed to
thoroughly dry. The joints shall then be filled with mortar to make
them smooth and plane. Acid curing is not required to be carried out
if epoxy or polyester resin is used for the mortar.
3.15.4.6 Resin mortars are normally self curing. The area tiled shall not be put
to use before 48 hours in case epoxy, polyester and furane type of
resin is used for the mortar. If phenol or cashew nut shell liquid resin
is used for the mortar, the area tiled shall not be put to use for 7 to 28
days respectively, without heat treatment. This period shall be 2 to 6
days respectively if heat treatment is given with infrared lamp.
3.15.4.8 It is necessary that the concrete slab / wall shall be made leak proof
against water, if necessary by pressure grouting etc. before taking up
any titling works. Cost of such works shall be deemed to have
included in the cost of tiling works, whether same is specifically
mentioned or not.
3.16.5.2 The area to receive imprinted concrete shall have the sub-grade
prepared as required as for any concrete slab on grade.Sub grade to
receive stamped concrete paving work must be well drained and
have adequate, uniform load bearing characteristics.
3.16.5.4 Place and spread concrete to completely fill all space inside forms.
Move concrete into place with square-tipped shovels or concrete
rakes. Consolidate concrete by tamping or vibrating to provide a
suitable surface for finishing. Prior to appearance of excess moisture
or bleed water, screed concrete with wood or magnesium straight
edge or mechanical vibrating screed. Continue concrete surface
leveling and consolidation with highway magnesium straight edge ISSUE
and (or) magnesium bull float. Mechanically float concrete surfaces R3
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 50 of 173
3.16.5.7 Sealing
3.16.5.10 Moisture content of concrete is low enough that alkali and other salts
do not become trapped beneath sealer. This will require a minimum
of 28 days subsequent to concrete placement, or longer if required.
3.16.5.12 Seal imprinted concrete with liquid membrane curing and sealing
compounds as recommended by manufacturer. Apply two coats of
specified curing and sealing compound according to manufacturer’s
written instructions.
3.16.6.3 Imprinting tools must be stored flat, textured face up, with no objects
resting on top. Handle products according to manufacturer’s printed
instructions.
ISSUE
R3
3.16.6.4 Care must be taken to ensure that the products are not damaged
while loading / unloading and transporting. Cartons must always be
stored with designated side upwards.
3.16.7 MEASUREMENT
3.16.7.2 This will include the materials, labour, tools, equipment, and
execution.
3.17.3 Sealing compound for filling the joints above the preformed bitumen
filler shall conform to Grade 'B' as per IS:1834.
3.17.4 WORKMANSHIP
3.17.4.2 The concrete/masonry surface shall be cleaned free from dust and
any loose particles. When the surface is dry, one coat of bitumen ISSUE
primer conforming to IS 3384 to be applied over which one coat of R3
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 53 of 173
3.17.5 MEASUREMENT
3.17.5.1 Measurement for the preformed joint filler shal1 be in sq.m correct to
two places of decimal for the specified thickness as per the items of
work. Measurement for applying the bitumen coat to
concrete/masonry surfaces shall be in sq.m correct to two places of
decimal. Measurement for the joint sealing compound shall be in
running metres correct to two places of decimal for the specified
width and thickness as per the items of work. Measurement for the
mild steel corner angle and plate shall be by weight as per the item of ISSUE
R3
work.
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 54 of 173
3.18.1 MATERIAL
3.18.2 WORKMANSHIP
3.18.2.1 For flooring, the base Reinforced cement concrete slab or the grade
slab shall be cleaned of all dirt with water and hard brush. If required
the base surface shall be backed or otherwise roughened to obtain a
good bond. The surface shall be clean, free from grease, oil, dust,
loose particles, etc. and thoroughly soaked with water to prevent
absorption of mixing water from the base course. Before placing the
under bed, any excess standing water shall be mopped out. Before
laying the flooring approval of the Engineer-in-charge shall be
obtained as to the acceptability of the base. No extra payment is
admissible for the preparation of base and the unit rate of flooring
shall be inclusive of preparation of the base. Wherever the level is
down, the contractor may have to fill it up with the base concrete to
achieve the specified top level of the flooring surface. Wherever the
level is higher, the contractor may have to chip/break the concrete to
achieve the specified thickness of the floor topping. The rate quoted
for the floor topping shall be firm for the variation in level of the
existing surface upto ±12mm. No extra rate will be paid for chipping
the specified floor topping thickness. Similarly no extra payment will
be made for the extra concrete to be laid for achieving the top
specified level in flooring.
3.18.2.2 The Indian patent stone floor unless otherwise stated, shall have a
ISSUE
total thickness of 50 mm laid in two layers. The under-bed shall R3
3.18.2.4 The floor shall be cast in panels not exceeding 5 sq.m. in area and
no side more than 2.5 m long. The casting sequence shall be in a
chequered board fashion, no two adjacent panels being cast before
the contraction of the previous one has taken place. The edge of
each panel into which the floor is divided shall be supported by flat
bars of steel or glass strips duly oiled to prevent sticking. The bars
shall be removed before filling in adjoining panels. At least 48 hours
shall elapse before the concreting in the adjacent bay is commenced.
After laying, the underbed shall be leveled, compacted and brought
to proper grade with a screed or float. PVC/Glass floor separator of
approved make shall be used between the panels with the approval
of Engineer. Unit rate quoted shall be inclusive of preparation of
base, cement slurry application, underbed and the topping coat and
the finishing including cost of all labour, tools and materials and the
PVC/GLASS separators between adjacent panels.
3.18.2.5 Final layer of minimum 6 mm thickness shall be laid over the green
underbed and trowelled smooth with a mixture of cement and sand
(1:1 by volume). The underbed and topping shall be completed in
one operation.
ISSUE
R3
3.18.3 MEASUREMENT
3.18.3.1 Measurement shall be for the plan area of flooring and for the
finished work.
3.19.1 The contractor shall submit full details of the system with catalogues
etc. he proposes to adopt for this work. The contractor shall ensure
strict adherence to all the steps given therein to ensure good quality
work. However, it shall be the contractor's entire responsibility to
complete the works to the satisfaction of the Engineer. The
contractor shall mobilize to the site adequate manpower and all the
equipment necessary for this work. Standby arrangement of
equipment and power shall also be made to ensure uninterrupted
work.
3.19.2 WORKMANSHIP
water that is required for the hydration of cement at the end of this
stage.
3.19.2.2 The mat and pump shall then be removed and mechanically
operated power floats shall be rotated on the wet concrete surface.
The process shall be repeated and the surface shall be finally
finished with minimum two passes of power trowel.
3.19.2.3 The finished surface shall then be covered with a polythene sheet the
following day after sprinkling water on the surface. Ponding of water
shall be carried out after 2-3 days and the surface shall be kept wet
continuously for at least 21 days.
3.19.3 MEASUREMENT
ISSUE
R3
4.1 GENERAL
4.1.1 This specification covers the general requirements for finishing the
plastered brick / concrete surfaces with Plaster of Paris and other
related works forming a part of this job, which may be required to be
carried out though not specifically mentioned above. The work under
this specification shall consist of furnishing of all tools, plants, labour,
materials and everything necessary for carrying out the work.
4.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
4.3.1 MATERIALS
4.3.1.1 The plaster of Paris powder shall conform to the requirements of IS:
2333.
4.3.2 WORKMANSHIP
4.3.2.1 The plaster on masonry surface shall be allowed to dry before the
POP punning is applied.
4.3.2.3 The POP shall be laid and rubbed and finally trowelled to a fine
uniform smooth finish. All unevenness shall be rubbed down from top
to bottom in one operation to eliminate joint marks.
4.4.1 MATERIALS
4.4.1.1 Water resistant white cement based putty ideal for use on concrete /
mortar walls (internal and external) and ceiling.
4.4.2 WORKMANSHIP
4.4.2.2 Mixing of putty:Putty shall be mixed with 30-35% clean water slowly
to make a paste. Mixing shall be continued for 10-15 minutes till a
uniform paste is formed. ISSUE
R3
4.4.2.4 Marks if any shall be removed with the help of moist sponge or the
surface shall be rubbed very gently with putty blade. The surface
shall be allowed to dry completely.
4.4.2.5 Only the required quantity of putty shall be prepared at a time and
shall be used within 2-3 hours of mixing of water. The total thickness
of the coats should be limited to maximum 1.5 mm. If required, to
remove unevenness of surface before applying any kind of paint/
distemper, walls / ceiling surface shall be leveled gently with very fine
water proof emery paper of not less than 5900 number to get a
glossy white surface.
4.4.3.1 Material received at site shall be with original packing and labels. It
ISSUE
shall be intact till issued for use of site. R3
4.4.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
4.4.4 MEASUREMENT
4.4.4.1 Measurement for white cement based putty work shall be in sq. m
correct to two places of decimal. Unless a separate item is provided
for grooves, mouldings etc., these works are deemed to be included
in the unit rates quoted for putty work.
4.4.4.2 The quantity of work to be paid for under these items shall be
calculated by taking the projected surface of the areas plastered after
making necessary deductions for openings for doors, windows,
exhaust fan openings etc. The actual plaster work carried out on
jambs/sills of windows, openings, etc. shall be measured for
payment.
4.5.1 The proportions of the cement mortar for plastering shall be 1:4 (one
part of cement to four parts of sand) unless otherwise specified under
the respective item of work. Cement and sand shall be mixed
thoroughly in dry condition and then water added to obtain a
workable consistency. The quality of water and cement shall be as
per relevant IS. The quality and grading of sand for plastering shall
conform to IS:1542. The mixing shall be done thoroughly in a
mechanical mixer unless hand mixing is specifically permitted by the
ENGINEER. If so desired by the ENGINEER sand shall be screened
and washed to meet the specification requirements. The mortar thus
mixed shall be used as soon as possible preferably within 30 minutes
from the time water is added to cement. In case the mortar has
stiffened due to evaporation of water this may be re-tempered by
adding water as required to restore consistency but this will be ISSUE
R3
permitted only upto 30 minutes from the time of initial mixing of water
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
SPEC. NO. TATA CONSULTING ENGINEERS LIMITED
WRITE UP
TCE.M4-419-01
GENERAL BUILDING WORKS SHEET 62 of 173
4.5.2 WORKMANSHIP
4.5.2.3 All joints in masonry shall be raked as the work proceeds to a depth
of l0mm/20mm for brick/stone masonry respectively with a tool made
for the purpose when the mortar is still green. The masonry surface
to be rendered shall be washed with clean-water to remove all dirt,
loose materials, etc., Concrete surfaces to be rendered shall be
roughened suitably by hacking or bush hammering for proper
adhesion of plaster and the surface shall be evenly wetted to provide
the correct suction. The masonry surfaces should not be too wet but
only damp at the time of plastering. The dampness shall be uniform
to get uniform bond between the plaster and the masonry surface.
4.5.3 Interior plain faced plaster - This plaster shall be laid in a single coat
of 13mm thickness. The mortar shall be dashed against the
prepared surface with a trowel. The dashing of the coat shall be
done using a strong whipping motion at right angles to the face of the
wall or it may be applied with a plaster machine. The coat shall be
trowelled hard and tight forcing it to surface depressions to obtain a
permanent bond and finished to smooth surface. Interior plaster
shall be carried out on jambs, lintel and sill faces, etc. as shown in
the drawing and as directed by the ENGINEER. Rate quoted for
ISSUE
R3
4.5.4 Plain Faced Ceiling plaster - This plaster shall be applied in a single
coat of 6mm thickness. The proportion of cement mortar shall be 1:3.
4.5.5 Exterior plain faced plaster - This plaster shall be applied in 2 coats.
The first coat or the rendering coat shall be approximately 14mm
thick. The rendering coat shall be applied as stipulated as
mentioned, except finishing it to a true and even surface and then
lightly roughened by cross scratch lines to provide bond for the
finishing coat. The rendering coat shall be cured for atleast two days
and then allowed to dry. The second coat or finishing coat shall be 6
mm thick with approved water proofing admixture, if so specified in
the item description. Before application of the second coat, the
rendering coat shall be evenly damped. The second coat shall be
applied from top to bottom in one operation without joints and shall
be finished leaving an even and uniform surface. The mortar
proportions for the coats shall be as specified in the respective item
of work. The finished plastering work shall be cured for atleast 7
days.
4.5.6 Interior plain faced plaster 20mm thick if specified for uneven faces of
brick walls or for random/coursed rubble masonry walls shall be
executed in 2 coats.
4.5.7 Exterior Sand Faced Plaster - This plaster shall be applied in 2 coats.
The first coat shall be 14mm thick and the second coat shall be 6mm
thick. However, only approved quality white sand shall be used for
the second coat and for the finishing work. Sand for the finishing
work shall be coarse and of even size and shall be dashed against
the surface and sponged.
4.5.7.1 The mortar proportions for the first and second coats shall be as
specified in the respective items of work. ISSUE
R3
4.5.7.2 Wherever more than 20mm thick plaster has been specified, which
is intended for purposes of providing beading, bands, etc. this work
shall be carried out in two or three coats as directed by the
ENGINEER duly satisfying the requirements of curing each coat
(rendering/floating) for a minimum period of 2 days and curing the
finished work for atleast 7 days.
4.5.7.3 In the case of pebble faced finish plaster, pebbles of approved size
and quality shall be dashed against the final coat while it is still green
to obtain as far as possible a uniform pattern all as directed by the
ENGINEER.
4.5.7.5 Curing of plaster shall be started as soon as the applied plaster has
hardened sufficiently so as not to be damaged when watered.
Curing shall be done by continuously applying water in a fine spray
and shall be carried out for atleast 7 days.
4.5.7.6 When the specification items of work calls for waterproofing plaster
the CONTRACTOR shall provide the waterproofing compound as
specified while preparing the cement mortar. Payment for water-
proofing compound will be made separately if it is not included as a
combined item of work.
4.5.7.7 Where lath plastering is specified, it shall be paid for at the same rate
as for plaster work except that separate payment for metal lath will
be made.
ISSUE
R3
4.5.7.9 The finished plaster surface shall not show any deviation more than
4mm when checked with a straight edge of 2m length placed against
the surface.To overcome the possibility of development of cracks in
the plastering work following measures shall be adapted.
4.5.8 MEASUREMENT
ISSUE
R3
4.6.1 The cement mortar for pointing shall be in the proportion of 1:3 (one
part of cement to three parts of fine sand) unless otherwise specified
in the respective items of work. Sand shall conform to IS:1542 and
shall be free from clay, shale, loam, alkali and organic matter and
shall be of sound, hard, clean and durable particles. Sand shall be
approved by ENGINEER and if so directed it shall be
washed/screened to meet specification requirements.
4.6.2 WORKMANSHIP
4.7 Any dust/dirt in the raked joints shall be brushed out clean and the
joints shall be washed with water. The joints shall be damp at the
time of pointing. Mortar shall be filled into joints and well pressed
with special steel trowels. The joints shall not be disturbed after it
has once begun to set. The joints of the pointed work shall be neat.
The lines shall be regular and uniform in breadth and the joints shall
be raised, flat, sunk or 'V' as may be specified in the respective items
of work. No false joints shall be allowed.
4.7.1.1 The work shall be kept moist for atleast 7 days after the pointing is
completed. Whenever coloured pointing is to be done, the colouring
pigment of the colour required shall be added to cement in such
proportions as recommended by the manufacturer and as approved
by the ENGINEER.
ISSUE
R3
4.7.2 MEASUREMENT
4.7.2.1 The quantity of work to be paid for under this Item shall be measured
in sq.m correct to two places of decimal by taking the projected
surface of the area pointed after making necessary deductions for
openings, etc.
ISSUE
R3
5 PAINTING WORKS
5.1 GENERAL
5.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
5.3.1 MATERIALS
5.3.1.1 All paint products shall have no added lead, mercury, chromium,
arsenic and antimony content.
5.3.1.2 Oil bound distemper shall conform to IS: 428. The primer shall be
alkali resistant primer of the same manufacture as that of the
distemper.
5.3.1.3 Cement paint shall conform to IS: 5410. The primer shall be a
thinned coat of cement paint.
5.3.1.6 Lead free acid, alkali and chlorine resisting paint shall conform to IS:
9862.
5.3.1.7 All paints shall have low VOC with VOC for non flat (gloss finish)
paints shall be 150g/l and VOC for flat (mat finish) paint shall be 50
g/l.
5.3.1.8 White wash shall be made from good quality fat lime conforming to
IS: 712. It shall be slaked at site and mixed with water in the
proportion of 5 litres of water to 1 kg of un-slaked lime stirred well to
make a thin cream. This shall be allowed to stand for a minimum
period of one day and strained through a clean coarse cloth. Four kg
of gum dissolved in hot water shall be added to each cu.m of cream.
1.30 kg of sodium chloride dissolved in hot water shall then be added
per 10 kg of lime used for the white wash to be ready for application.
ISSUE
R3
5.3.1.10 All the materials shall be of the best quality from an approved
manufacturer. CONTRACTOR shall obtain prior approval of the
ENGINEER for the brand of manufacture and the colour/shade. All
materials shall be brought to the site of works in sealed containers.
5.3.2 WORKMANSHIP
5.3.3 WHITE WASH - The prepared surfaces shall be wetted and the finish
applied by brushing. The operation for each coat shall consist of a
stroke of the brush first given horizontally from the right and the other
from the left and similarly, the subsequent stroke from bottom
upwards and the other from top downwards, before the first coat
dries. Each coat shall be allowed to dry before the next coat is
applied. Minimum of 2 coats shall be applied unless otherwise
ISSUE
R3
specified in the item of work. The dry surface shall present a uniform
finish without any brush marks.
5.3.4 COLOUR WASH - Colour wash shall be applied in the same way as
for white wash. A minimum of 2 coats shall be applied unless
otherwise specified in the item of work. The surface shall present a
smooth and uniform finish without any streaks. The finished dry
surface shall not show any signs of peeling/powdery and come off
readily on the hand when rubbed.
5.3.6 OIL BOUND DISTEMPER - The prepared surfaces shall be dry and
provided with one coat of alkali resistant primer by brushing. The
surface shall be finished uniformly without leaving any brush marks
and allowed to dry for at least 48 hours. A minimum of two coats of
oil bound distemper shall be applied unless otherwise specified in the ISSUE
R3
item of work. The first coat shall be of a lighter tint. At least 24 hours
shall be left after the first coat to become completely dry before the
application of the second coat. Broad, stiff, double bristled distemper
brushes shall be used for the work. Paint may also be applied using
rollers.
5.3.7 PLASTIC EMULSION PAINT - The prepared surface shall be dry and
provided with one coat of primer which shall be a thinned coat of
emulsion paint. The quantity of thinner shall be as per manufacturer's
instructions. The paint shall be laid an evenly and smoothly by
means of crossing and laying off. The crossing and laying off
consists of covering the area with paint, brushing the surface hard for
the first time over and then brushing alternately in opposite directions
two or three times and then finally brushing lightly in a direction at
right angles. In this process, no brush marks shall be left after the
laying off is finished. The full process of crossing and laying off
constitutes one coat. The next coat shall be applied only after the first
coat has dried and sufficiently become hard which normally takes
about 2 to 3 hours. A minimum of 2 finishing coats of the same colour
shall be applied unless otherwise specified in the item of work. Paint
may also be applied using rollers. The surface on finishing shall
present a flat velvety smooth finish and uniform in shade without any
patches. Paint may also be applied using rollers.
5.4.1 MATERIALS
5.4.6 All the materials shall be of the best quality from an approved
manufacturer. CONTRACTCOR shall obtain prior approval of the
ENGINEER for the brand of manufacture and the colour/shade. All
materials shall be brought to the site of works in sealed containers.
5.4.7 WORKMANSHIP
5.4.7.1 The type of finish to be provided for woodwork, either for painting or
polishing, the number of coats, etc. shall be as specified in the
respective items of work.
5.4.7.2 Primer and finish paint shall be compatible with each other to avoid,
cracking and wrinkling. Primer and finish paint shall be from the
same manufacturer.
5.4.7.4 All the wood surfaces to be painted shall be thoroughly dry and free
from any foreign matter. Surfaces shall be smoothened with abrasive
paper using it across the grains and dusted off. Wood primer coat
shall then be applied uniformly by brushing. The number of primer
coats shall be as specified in the item of work. Stopping as per IS
426 shall be used to fill up large holes & cracks on the surface. For
small holes or minor cracks, fillers as per IS 110 should be used. Any
slight irregularities of the surface shall then be made up by applying
an optimum coat of filler conforming to IS: 110 and rubbed down with
an abrasive paper for obtaining a smooth surface for the undercoat of
synthetic enamel paint conforming to IS: 2932.
ISSUE
R3
5.4.7.6 All the wood surfaces to be provided with clear finishes shall be
thoroughly dry and free from any foreign matter. Surfaces shall be
smoothened with abrasive paper using it in the direction of the grains
and dusted off.
5.4.7.8 After the surface is dry, a suitable sealer shall be applied to prevent
bleeding of stain and filler into the finish coat. The surface shall be
rubbed down lightly, wiped off and allowed to dry.
5.4.7.9 Over this prepared surface, varnish conforming to IS: 337 shall be
applied by brushing. Varnish should not be retouched once it has
begun to set. Staining if required shall be provided as directed by the
ENGINEER. When two coats of varnish is specified, the first coat
should be a hard-drying undercoat or flatting varnish which shall be
allowed to dry hard before applying the finishing coat. The number of
coats to be applied shall be as per the item of work.
5.4.7.10 For works where clear finish of French polish is specified the
ISSUE
prepared surfaces of wood shall be applied with the polish using a R3
5.4.7.11 Finishing shall be carried out using a fresh clean cloth over the pad,
slight dampening with methylated spirit and rubbing lightly and
quickly in circular motions. The finished surface shall have a uniform
texture and high gloss. The number of coats to be applied shall be as
per the item of work.
5.4.8 MOCK-UP
5.4.8.1 The contractor shall prepare and install mock-up samples as per
approved shop drawings.
5.4.8.2 Mock-up samples shall be of full size and shall be true representation
of actual works to be carried out at site. Mock-ups may be part of
completed work if undisturbed.
5.4.9.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
5.4.9.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
5.4.9.3 Paints shall be kept covered at all times and mixing shall be done in
suitable containers.
5.4.10 MEASUREMENT
5.4.10.2 No deduction shall be made for openings up to 0.5 sq.m. of area nor
any extra to be paid for jambs, sills etc..
5.4.10.3 For openings exceeding 0.5 sq.m. but not exceeding 3.0 sq.m.,
deductions shall be made for half the area of openings and no
additions shall be made for jambs, sills etc.
5.4.10.4 For openings exceeding 3.0 sq.m., deductions shall be made for the
whole area and additions shall be made for jambs, sills, soffits etc.
5.4.10.5 No extra payment shall be made for painting etc. done around
openings, wall features like grooves, projections, cornices etc.
5.4.10.6 Rate quoted shall take into account the provision of necessary
enabling works such as scaffolding, painter's cradle etc.
ISSUE
R3
6.1 GENERAL
6.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
6.3.1 MATERIALS
6.3.1.1 Timber to be used shall be first class Teak wood as per IS: 4021.
Timber shall be of the best quality and well seasoned by a suitable
process before being planed to the required sizes. The maximum
permissible moisture content shall be from 10 to 16 percent for
timber 50mm and above in thickness and 9 to 14 percent of timber
less than 50mm in thickness for different regions of the country as
stipulated In IS: 287. Timber shall be close grained, of uniform colour
and free from decay, fungal growth, boxed heart, pitch pockets or
streaks on the exposed edges, borer holes, splits and cracks.
6.3.1.2 Flush door shutters of the solid core type with plywood face panels
shall conform to IS: 2202 (Part 1) and with particle board/hard board
face panels shall conform to IS: 2202 (Part 2).
6.3.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
6.3.2 WORKMANSHIP
6.3.2.2 All works shall be executed as per the detailed drawings and/or as
directed by the ENGINEER.
6.3.2.3 All members of the door, window, and ventilator shall be straight
ISSUE
without any warp or bow and shall have smooth well planed faces. R3
The right angle shall be checked from the inside surfaces of the
respective members of the frame.
6.3.2.4 Frames shall have mortise and tenon joints which shall be treated
with an approved adhesive and provided with metal or wood pins.
The vertical members of the door frame shall project 50 mm below
the finished floor level with a spacer bar. The finished dimension of
frames shall be rebated on the solid for keying with the plaster and
for receiving the shutters. The depth of rebate for housing the shutter
shall be 15 mm. The size of the frames shall be as specified in the
respective items of work. The workmanship shall generally conform
to the requirements specified in IS: 4021.
6.3.2.5 The face of the frames abutting the masonry or concrete shall be
provided with a coat of coal tar.
6.3.2.7 Timber panelled shutters for doors, windows and ventilators shall be
constructed in the form of framework of stiles and rails with panel
insertion. The panels shall be fixed by either providing grooves in the
stiles and rails or by beading. Glazing bars shall be as detailed in the
drawings. The stiles and rails shall be joined by mortise and tenon
joints at right angles. All members of the shutter shall be straight
without any warp or bow and shall have smooth, well planed faces at
right angles to each other. The right angle for the shutter shall be
checked by measuring the diagonals and the difference shall not be
more than + 3 mm. Timber panels made from more than one piece
shall be jointed with a continuous tongued and grooved joint, glued ISSUE
R3
6.3.2.8 Details of the wooden flush door shutters, solid core type with
specific requirement of the thickness, core, face panels, viewing
glazed panel, Venetian louver opening, teak wood lipping etc. shall
be as indicated in the respective items of work. Panels of shutter
shall be of marine plywood conforming to IS: 710, if so specified in
the item of work. Flush door shutters shall be from reputed
manufacturers and CONTRACTOR shall submit test results as per
IS: 4020, if so desired by the ENGINEER.
6.3.2.9 The material of the fittings and fixtures either of chromium plated
steel, cast brass, copper oxidized or anodized aluminum shall be as
specified in the item of work. The number, size and type of the fittings
and fixtures shall be as indicated in the drawings/item of work.
6.3.2.10 Wood work shall not be provided with the finishes of painting,
galvanizing etc. unless it has been approved by the ENGINEER. The
type of finish and the number of coats shall be as stipulated in the
respective items of work. Preparation of the wood surface and
application of the finishes shall be as per Painting and Polishing of
wood works.
6.4.1 MATERIALS
6.4.1.1 Hot rolled steel sections for the fabrication of steel doors, windows
and ventilators shall conform to IS: 7452, which are suitable for
single glazing.
6.4.1.2 Pressed steel door frames for steel flush doors shall be out of 1.25
mm thick mild steel sheets of profiles as per IS:4351.
6.4.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
6.4.2 WORKMANSHIP
6.4.2.1 All steel doors, windows and ventilators shall be of the type as
specified in the respective items of work and of sizes as indicated in
the drawings. Steel doors, windows and ventilators shall conform to
the requirements as stipulated in IS: 1038. Steel windows shall
conform to IS: 1361, if so specified.
6.4.2.4 For windows with fly proof mesh as per the item of work, rotor
operator arrangement, for the operation of the glazed shutters from
the inside shall be provided.
6.4.2.5 Pressed steel door frames shall be provided with fixing lugs at each
jamb, hinges, lock-strike plate, mortar guards, angle threshold,
shock-absorbers of rubber or similar material as per the requirements
of IS:4351. Pressed steel door frames shall be fixed as 'built-in', as
the masonry work proceeds. After placing it plumb at the specified
location, masonry walls shall be built up solid on either side or each
course grouted with mortar to ensure solid contact with the door
frame, without leaving any voids. Temporary struts across the width
shall be fixed, during erection to prevent bow/sag of the frame.
6.4.2.7 Doors, windows and ventilators shall be fixed into the prepared
openings. They shall not be 'built-in' as the masonry work proceeds,
to avoid distortion and damage of the units. The dimensions of the
masonry opening shall have l0mm clearance all-round the overall ISSUE
R3
6.4.2.8 Glazing of the units shall be either with flat transparent glass or
wired/figured glass of the thickness as specified in the item of work.
All glass panels shall have properly squared corner and straight
edges. Glazing shall be provided on the outside of the frames.
6.4.2.9 Fixing of the glazing shall be either with spring glazing clips and putty
conforming to IS: 419 or with metal beads. Pre-formed PVC / VINYL
or rubber gasket shall be provided for fixing the beads with
concealed screws. The type of fixing the glazing shall be as indicated
in the item of work and/or in drawings.
6.4.2.10 Steel doors, windows and ventilators shall be provided with finish of
either painting as specified or shall be hot dip galvanized with
thickness of zinc coating as stipulated all as described in the
respective items of work.
6.4.2.12 Installation of the units with fixing lugs, screws, mastic caulking
compound at the specified locations shall generally conform to the
requirements of IS:1081. Necessary holes etc required for fixing shall
be made by the CONTRACTOR and made good after installation.
Workmanship expected is of a high order for efficient and smooth
operation of the units.
ISSUE
R3
6.5.1 MATERIALS
6.5.1.1 Aluminum alloy used in the manufacture of extruded sections for the
fabrication of doors, windows, ventilators shall conform to
designation 63400 WP of IS:733.
6.5.1.3 Builder's hardware of fittings & fixtures shall be of the best quality
from approved manufacturers.
6.5.2 WORKMANSHIP
6.5.2.1 All aluminum doors, windows, and ventilators shall be of the type as
specified in the respective items of work and of sizes as indicated in
the drawings. The doors, windows, ventilators shall conform to the
requirements of IS: 1948. Aluminum windows, shall conform to IS:
1949, if so specified.
indicates generally the arrangement along with the overall size of the
various components and weight per running meter of the extruded
sections to be adopted.
6.5.2.6 The framework of the partitions with mullions and transoms shall be
with anodized/powder coated aluminum box sections of dimensions
as per the item of work. Anodized/powder coated Aluminum box
sections shall be in-filled with timber of class 3 (silver oak or any
other equivalent) as per IS:4021. Panels of double/single
glazing/plywood shall be fixed as per details indicated in the drawing.
Partitions shall be fixed rigidly between the floor and the structural
columns/beams including provision of necessary shims for wedging
etc. Finished work shall be of rigid construction, erected truly plumb
to the lines and levels, at locations as per the construction drawings.
6.6.1 MATERIALS
6.6.1.2 The type viz. self coiling type (manual) for clear areas up to 12 sq.m,
gear operated type (mechanical) for clear areas up to 35 sq.m and
electrically operated type for areas up to 50 sq.m shall be as
specified in the IS Code 6248. Mechanical type shall be suitable for
operation from both inside and outside with the crank handle or chain
gear operating mechanism duly considering the size of wall/column.
Electrical type shall also be provided with a facility for emergency
mechanical operation.
6.6.2 WORKMANSHIP
6.6.2.1 Rolling shutters / grill shall be supplied duly considering the type,
specified clear width/height of the opening and the location of fixing
as indicated in the drawings.
6.6.2.3 Fabrication and assembly of rolling grill curtain shall have the type of
links and other additional requirements as specified in the item of
works.
6.6.2.4 The guide channels out of mild steel sheets of thickness not less
than 3.15 mm shall be of either rolled, pressed or built up
ISSUE
R3
6.6.2.5 Hood covers shall be of mild steel sheets not less than 0.90mm thick
and of approved shape.
6.6.2.6 Rolling shutters / grill shall be provided with a central hasp and staple
safety device in addition to one pair of lever locks and sliding locks at
the ends.
6.6.2.7 Where a rolling shutter is combined with rolling grill, height of rolling
grill shall be 500mm maximum.
6.6.2.9 Where galvanizing is called for, the curtain sections, guides, lock
plate, bracket plates, suspension shaft and the hood cover shall be
hot dip galvanized with a zinc coating containing not less than 97.5
percent pure zinc. The weight of the zinc coating per sq.m shall be as
specified in the item of work.
ISSUE
R3
6.7.1.3 Size of the frame and material for frames will be decided as per
project requirement.
6.7.1.5 The module should be provided with short circuit proof power supply
unit for power rating of 220/240 V, 50/60 Hz. A power point will be
made available at a suitable location by electrical contractor.
6.7.1.6 The door shall have facilities for activation by infrared movement
detector on both sides.
6.7.1.10 Both the fixed and sliding panels shall be made of 12 mm thick
toughened glass with or without etching. It should be provided with all
required fittings and fixtures, digital entry – exit function on the top
and electro- mechanical locking system.
ISSUE
R3
6.8.1 MATERIALS
6.8.1.1 The UPVC windows shall be made of high quality UPVC profile
section and GI/Aluminum reinforcement.
6.8.1.2 Generally, the UPVC windows shall comprise of main profiles for
outer frames and shutters, beads, coupling mullions, bays and
reinforcement.
6.8.1.3 The windows shall be non combustible, non corrosive, shall have
good sound and heat insulation properties, shall withstand harsh
weather conditions and desert conditions and shall not form stains,
blisters or corrosion in salty conditions.
6.8.2 WORKMANSHIP
6.8.2.4 Drainage slots shall be provided in the outer chamber of the profile.
All horizontal members, except heads of the outer frame, shall have
drainage slots of min 5mm wide and 30mm long.
6.8.2.6 Friction stays shall be of high quality stainless steel and nylon ISSUE
component for improved durability. R3
6.8.2.11 Contractor shall provide warranty for installed hand railing system for
the period described herein, starting from date of completion of
installation work. When notified in writing from Owner,
contractor/installer shall promptly correct the said deficiencies,
without inconvenience and extra cost to owner.
6.8.3 MOCK-UP
6.8.3.1 The contractor shall prepare and install mock-up samples as per
approved shop drawings.
6.8.3.2 Mock-up samples shall be of full size and shall be true representation
of actual works to be carried out at site. Mock-ups may be part of
completed work if undisturbed.
ISSUE
R3
6.8.4.3 Finished shop work shall not be installed in any room or space where
concrete, masonry, or plaster work is not completed and dry.
6.8.4.4 Contractor shall use all means necessary to protect doors, windows
and associated fittings from damage prior to, during, and after
installation. All damaged items shall be repaired or replaced by the
contractor at no cost to the owner.
6.8.5 MEASUREMENT
6.8.5.3 Rate quoted shall be for all the works including glazing, painting,
builder's hardware of fittings and fixtures as specifically described in
the respective items of work.
ISSUE
R3
7.1 GENERAL
7.1.1 This specification covers the general requirements for hardware such
as hinges, locks, stays, stoppers, handles etc. for doors, windows,
and ventilators and other related works forming a part of this job,
which may be required to be carried out though not specifically
mentioned above. The work under this specification shall consist of
furnishing of all tools, labour, materials and everything necessary for
carrying out the work.
7.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
7.3.1 All ironmongery shall be of first quality and shall be obtained from an
approved manufacturer. Butt hinges shall be aluminum alloy,
stainless steel or brass as specified with double stainless steel
washers.
7.3.2 The size, materials, finishes, type and quality of ironmongery shall be
as described in the schedule of ironmongery.
7.3.4 Proper sockets shall be provided for all bolts to fix flush in floors, cills
and door/window/ventilator frames. Each lock shall be provided with
minimum two keys and no two locks shall have identical keys, unless
specifically required.
7.3.5 The use of nails for fixing ironmongery will not be permitted. The
Contractor shall hand over all work in a finished state and to the
satisfaction of owner.
7.4 MOCK-UP
7.4.1 Contractor shall prepare full size mock-up after sample approval for
typical Doors and Windows and install at location approved by owner
for final approval at no extra cost as specified in the Special
Conditions of the Contract. ISSUE
R3
7.6 IRONMONGERY
7.7.1 The contractor shall set up the locks for a system of master- keying.
Two change keys shall be furnished for each lockset.
ISSUE
R3
8.1 GENERAL
8.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
8.3 MATERIALS
8.3.1 All glass and glazing shall have uniform reflective index and free form
flaws, specs and bubbles.
8.3.2 The glass shall be brought to site in the original packing from the
manufacturer and cut to size at site. The cut edges shall be straight
and free from hips, spells or any other damages.
8.3.3 Clear glass shall be float glass and shall be of thickness as specified
in the schedule of items. Properties of float glass shall generally meet
the requirements of IS: 14900.
8.3.4 Wired glass shall be thick rolled glass with centrally embedded wire
mesh of Georgian type conforming to IS: 5437
8.3.5 Composite double glazing shall be made of two 6mm thick clear float
glass on either sides and separated by 12mm air gap. The trapped
air shall be kept dry by means of suitable desiccant. The glass shall
be hermetically sealed. The composite double glazing shall be
procured as finished product.
8.3.6 The curtain glazing shall consist of minimum 8mm thick heat
strengthened glass fixed with framework made of aluminum sections
designed as per structural requirements.
8.3.7 The silicone sealant shall be of best quality and shall be brought to
site in manufacturer's original packing.
8.4 WORKMANSHIP
8.4.1 All glazing clips, putty, mastic etc. shall be provided as required.
8.4.3 After completing the glazing work, contractor shall remove all dirt,
stains, excess sealants and clean the glass panes and leave the
work in perfectly acceptable condition. All broken, cracked or
damaged glass shall be replaced by new ones without any extra cost
to the owner.
8.4.4 The glass must be protected during installation period so that they
will not be damaged by splashing of cement, welding, grinding etc.
8.4.5 Labels, tapes, adhesives, writing with chalk or any other tool shall
never be done on the coating of glazing.
8.4.7 When assembling and installing the glazing, the coating shall be
positioned as indicated in the drawing.
8.4.8 Glazing shall be carefully done to avoid the contact with metal
frames.
8.5 MOCK-UP
8.5.1 The contractor shall prepare and install mock-up samples as per
approved shop drawings.
8.5.2 Mock-up samples shall be of full size and shall be true representation
of actual works to be carried out at site. Mock-ups may be part of
completed work if undisturbed.
ISSUE
R3
8.5.3.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
8.5.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
8.5.3.3 All items shall be protected from dampness both during and after
delivery to site.
8.5.3.4 Partition shall not be installed in any room or space where concrete,
masonry, or plaster work is not completed and dry.
8.5.3.5 Care must be taken to ensure that the frames and panels of partition
works are not damaged while transporting/erection.
8.5.4 MEASUREMENT
ISSUE
R3
9 PARTITION WORKS
9.1 GENERAL
9.1.1 This specification covers the general requirements for fabrication and
erection of wooden / aluminum / gypsum board partitions and other
related works forming a part of this job, which may be required to be
carried out though not specifically mentioned above. The work under
this specification shall consist of furnishing of all tools, labour,
materials and everything necessary for carrying out the work.
9.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
IS: 287 Permissible moisture content for timber used for different
purposes.
IS: 303 Plywood for general purpose
IS: 710 Marine plywood
IS: 733 Wrought aluminum and aluminum alloys, bars, rods
and sections for general engineering purposes.
IS: 848 Synthetic resin adhesive for plywood
IS: 1200 Method of measurement of building and civil
engineering works.
IS: 1328 Veneered decorative plywood
IS: 1868 Anodic coating on aluminum and its alloys.
IS: 1948 Aluminum doors, windows and ventilators
IS: 1949 Aluminum windows for industrial buildings
IS: 2095 Gypsum plaster boards ISSUE
R3
ISSUE
R3
9.3.1 MATERIALS
9.3.1.1 Timber to be used shall be first class Teak wood as per IS: 4021.
Timber shall be of the best quality and well seasoned by a suitable
process before being planed to the required sizes. The maximum
permissible moisture content shall be from 10 to 16 percent for
timber 50mm and above in thickness and 9 to 14 percent for timber
less than 50mm in thickness for different regions of the country as
stipulated In IS: 287.
9.3.1.2 Timber shall be close grained, of uniform colour and free from decay,
fungal growth, boxed heart, pitch pockets or streaks on the exposed
edges, borer holes, splits and cracks.
9.3.1.4 Builder's hardware of fittings and fixtures shall be of the best quality
from approved manufacturers.
9.3.2 WORKMANSHIP
9.3.2.2 All works shall be executed as per the detailed drawings and/or as
directed by the ENGINEER.
9.3.2.3 The framework of the partitions with mullions and transoms shall be
with the sections of dimensions as per the item at work. Panels of
double/single glazing/ plywood shall be fixed as per details indicated
ISSUE
in the drawings. R3
9.3.2.4 Partitions shall be fixed rigidly between the floor and structural
columns/beams including provision of necessary shims for wedging
etc. Finished work shall be of rigid construction, erected truly plumb
to the lines and levels, at locations as per the construction drawings.
9.3.2.5 The face of the frames abutting the masonry or concrete shall be
provided with a coat of coal tar.
9.3.2.6 Glazing of partitions shall be with either flat transparent sheet glass
or figured glass. Transparent sheet glass shall be of 'B' quality as per
IS: 2835. The thickness and type of glazing to be provided shall be
as specified in the item of work.
9.3.2.7 The material of the fittings and fixtures either of chromium plated
steel, cast brass, copper oxidized or anodized aluminum shall be as
specified in the item of work. The number, size and type of the fittings
and fixtures shall be as indicated in the drawings/item of work.
9.3.2.8 Wood work shall not be provided with the finishes of painting,
galvanizing etc. unless it has been approved by the ENGINEER. The
type of finish and the number of coats shall be as stipulated in the
respective items of work.
9.4.1 MATERIALS
9.4.1.1 Aluminum alloy used in the manufacture of extruded sections for the
fabrication of doors, windows, ventilators shall conform to
designation 63400 WP of IS:733. ISSUE
R3
9.4.1.3 Builder's hardware of fittings & fixtures shall be of the best quality
from approved manufacturers.
9.4.2 WORKMANSHIP
9.4.2.4 IS:1948 and IS:1949 are referred to incorporate the sizes, shapes,
thicknesses and weight per running meter of extruded sections for
the various components of the units. However, new sizes, shapes,
thicknesses with modifications to suit snap-fit glazing clips etc. are
continuously being added by various leading manufacturers of
extruded sections, which are available in the market. As such, the
sections of the various components of the unit proposed by the
CONTRACTOR, will be reviewed by the ENGINEER and will be
accepted only if they are equal to or marginally more than that
specified in the codes/ item of works.
9.4.2.5 The framework of the partitions with mullions and transoms shall be
with anodized/powder coated aluminum extruded sections of
dimensions as per the item of work. Anodized/powder coated
Aluminum extruded sections shall be in-filled with timber of class 3
ISSUE
(silver oak or any other equivalent) as per IS:4021. Panels of R3
9.5.1 MATERIALS
9.5.1.2 GI frame shall include 48mm studs (0.55mm thick having one flange
of 34mm and another flange of 36mm made of GI steel) placed at
610mm c/c vertically, in 50mm thick floor and ceiling channel
(0.55m,m thick having equal flanges of 32mm made of GI steel).
9.5.1.3 Glass wool of density 24Kg/cum shall comply with BS: 476 Part 4,
1970.
9.5.2 WORKMANSHIP
9.5.2.1 Single Skin Partition shall consist of 13mm thick plaster board
screw fixed with 25mm dry wall screw at 300mm c/c to either side of
stud framework. Necessary cut-outs shall be provided in the partition ISSUE
R3
to receive cable raceways, electrical/HVAC fittings and fixtures,
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 109 of
GENERAL BUILDING WORKS
173
which shall be neatly finished after fixing the fixtures thereby leaving
no gaps. Square and tapered edges of the boards shall be jointed
and finished to have a flushed look including filling and finishing with
jointing compound, joint paper tape and two coats of drywall top coat
suitable for gypsum board. Glass wool shall be rot proof and
odourless. The moisture content shall be less than 2% in accordance
with BS: 2972. The water absorption shall be less than 2% in
accordance with BS: 2972. The gypsum board shall be continued up
to true ceiling or shall be stopped 100mm above false ceiling. The
partition shall be finished to take on wall paper / paint directly by
applying suitable base coats, prime coats etc. complete.
9.5.2.2 Double Skin Partition shall include first skin consist of 13mm thick
tapered edge plaster board screw fixed with 25mm dry wall screw at
300mm c/c to either side of stud framework. Necessary cut-outs shall
be provided in the partition to receive cable raceways,
electrical/HVAC fittings and fixtures, which shall be neatly finished
after fixing the fixtures thereby leaving no gaps. The layer shall be
finished to take on second skin in gypsum board/Plywood/ MDF
directly. The first skin of the partition shall be continued up to true
ceiling. Second skin shall consist of 13mm thick tapered edge plaster
board screw fixed with 35mm dry wall screw at 300mm c/c to existing
first skin of partition. Care shall be taken that the joints are staggered
to avoid leakage. Finally square and tapered edges of the boards
shall be joined and finished to have a flush look including filling and
finishing with jointing compound, joint paper tape and two coats of
drywall top coat suitable for gypsum board. The second skin of
partition shall be stopped 100mm above false ceiling. Necessary cut-
outs shall be provided in the partition to receive cable raceways,
electrical/HVAC fittings and fixtures, which shall be neatly finished
after fixing the fixtures thereby leaving no gaps. The partition shall be
finished to take on wall paper / paint directly by applying suitable ISSUE
R3
9.5.3.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
9.5.3.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
9.5.3.3 All items shall be protected from dampness both during and after
delivery to site.
9.5.3.4 Partition shall not be installed in any room or space where concrete,
masonry, or plaster work is not completed and dry.
9.5.3.5 Care must be taken to ensure that the frames and panels of partition
works are not damaged while transporting/erection.
9.5.4 MASUREMENT
9.5.4.2 Measurement shall be from out to out of the frames. Rate quoted
shall be for all the works including glazing, painting, builder's
hardware of fittings and fixtures as specifically described in the
respective items of work.
ISSUE
R3
10.1 GENERAL
10.1.1 This specification covers the general requirements for fabrication and
erection of aluminum / gypsum board false ceilings and other related
works forming a part of this job, which may be required to be carried
out though not specifically mentioned above. The work under this
specification shall consist of furnishing of all tools, labour, materials
and everything necessary for carrying out the work.
10.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
10.3.1 MATERIALS
10.3.1.3 The fiber boards shall be fire resistant, termite and insect resistant,
weather resistant, acoustically satisfactory, dimensionally stable,
warp-free, easily workable, treated with anti-fungus chemicals, heat
insulated and of adequate structural strength and should have good
surface finish as approved by the Owner.
10.3.1.4 The size of fiber board ceiling tile shall generally be 600 x 600 x 12
mm thick. All types of boards and ceiling tiles shall be stored flat
under cover at a clean dry place on firm ground. The Contractor
should ensure that boards are not stacked on termite infected, wet or
loose ground. The boards should be always carried on edges.
10.3.1.5 The metal frame work shall be interlocking type and made of sections
of light metal, such as extruded anodized aluminum. The shape and
cross section shall be such as to facilitate proper suspension and
proper fixing of the ceiling boards covering them and shall be
structurally sound and rigid.
10.3.2 WORKMANSHIP
10.3.2.1 The Contractor shall ensure that the frame to support the ceiling is
designed for its structural strength to withstand the weight of ceiling
boards to be fixed, live load of 75 kg/m2, and other loads such as
that of air- conditioning ducts, grills, electrical wiring and lighting
fixtures, thermal insulation, etc. as shown on the drawings. The
Contractor shall also submit a detailed drawing to show the grid
work, sizes of grid members, method of suspension, position of
openings for air-conditioning and lighting, access doors, etc.
10.3.2.2 The metal frame work of extruded anodized aluminum false ceiling
grid system shall consist of aluminum main members of special T- ISSUE
R3
profile of 32 mm x 32 mm interlocking with each other and run both
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 114 of
GENERAL BUILDING WORKS
173
10.3.2.3 In the case of aluminum grid system, boards are just placed into the
frames formed by the main `T' members and the cross members
fitted with the clips for locking the boards. Contractor should take
utmost care so as not to force the boards in position, and a very little
gap is preferable to a tight joint. Fixing fiber boards by adhesives
shall not be permitted unless approved by the Owner. The fiber
boards should be cut with a fine toothed saw, if required.
10.3.2.4 The hard boards shall be conditioned by wetting the screen surface
with clean water by a sponge or brush. The damp boards should be
stacked back to back on flat surface at site for 48 hours and then
fixed immediately. Conditioning if required shall be done as per the
manufacturer's specifications.
10.3.2.5 As the work of false ceiling may be interconnected with the work of
air-conditioning ducts and lighting, the Contractor shall fully
cooperate with other agencies entrusted with the above works and
who may be working simultaneously. The Contractor shall provide
necessary openings, in the false ceiling work for air- conditioning,
lighting and other fixtures. Additional framing, if required, for the
above openings shall also be provided at no extra cost to the Owner.
Removable or hinged type inspection or access trap doors shall be
provided at locations specified by the Owner.
10.4.1.1 Thermal Insulation material consisting of boards slabs and rolls of ISSUE
R3
approved manufacturer, shall be of approved thermal conductivity for
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 115 of
GENERAL BUILDING WORKS
173
10.4.1.2 The quoted rate shall include supply, delivery, cutting and fixing of all
materials for covering the roof with thermal insulation material,
including wood pegs, slotted angle, G.I rawl plugs, wood/coach
screws, lacing wire, G.I washers, wire mesh, any covering as
stipulated in schedule of prices and quantities, finishing at all levels
and elevation etc., complete.
10.4.2.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site.
10.4.2.2 Material shall be stored at properly covered dry location and shall be
safe from damage.
10.4.2.3 Care must be taken to ensure that the floor tiles are not damaged
while loading / unloading and transporting. Tile packages shall not be
stacked higher than 2m.
10.4.3 MEASUREMENT
10.4.3.1 The superficial area of false ceiling shall be measured and paid for at
the unit rate less deductions, if any. Openings in false ceiling which
are less than 0.4 sq. m in area shall not be deducted for the purpose
of payment.
10.4.3.2 The quoted rates shall include supply, delivery and erection of all
materials for covering the ceiling, frame work suspenders or hangers,
ISSUE
anti-termite treatment making openings in false ceiling, extra frame R3
10.4.3.4 Where fire barriers are specified, they shall be as per details shown
in drawings and as directed and shall be measured in square meters
and paid for separately.
ISSUE
R3
11 TOILET CUBICLES
11.1 GENERAL
11.1.1 Specification applies to steel toilet partitions / cubicles with doors and
hardware for fixing and mounting of the panels as per architect's
design, plans and schedules. The scope of work includes design,
supply, installation and handling except civil works.
11.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
11.3 MATERIALS
11.3.1 All clamps, fittings, accessories should be made out of first grade
quality galvanized steel conforming to IS 316. All products should be
made out of 0.6mm (24g) galvanized sheet.
11.3.4 The panels and doors should be constructed out of 12mm thick
merino laminate or any other optional material as specified by the
architect.
11.3.5 All panels should have a built in feature to be totally sight proof on all
four corners for better privacy. Standard gap of 150mm on sides and
on moving element has to be provided unless otherwise specified or
scheduled in the drawing or layout.
11.3.6 Cubicles should have a provision for mounting of the toilet hardware
like handrails, hinges, locks with indicator, coat hooks, tissue holders
and taps as per scheduled and specified. All panels should be fully
protected with the self adhesive film and to be removed at the
handing over of the cubicles
11.4 MEASUREMENT
ISSUE
R3
12.1 GENERAL
12.1.1 The scope of this section consists of but is not necessarily limited to
installation, testing and commissioning of Sanitary appliances and
fixtures for toilets, Steel, Chromium plated, brass fittings, Stainless
steel sinks, Accessories e.g. towel rods, toilet paper holders, soap
dish, towel rails, coat hooks, hand dryers, mirrors, liquid soap
dispensers etc.
12.1.2 Whether specifically mentioned or not the Contractor shall provide for
all appliances and fixtures, all fixing devices, nuts, bolts, screws,
hangers as required.
12.1.3 All exposed pipes within toilets and near appliances/fixtures shall be
of chromium plated brass or copper unless otherwise specified.
12.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
ISSUE
R3
12.3 MATERIALS
12.3.1.1 Water Closet shall be wash down or symphonic wash down type floor
or wall mounted set, as shown in the drawings, designed for low
volume flushing from 2-6 liters of water to be flushed by means of a
porcelain flushing cistern or an exposed or concealed type (as
detailed in the drawings or as directed by the Owner’s Site
Representative) 32 mm size CP, brass flush valve with regulator
valve.
12.3.1.4 Each WC set shall be provided with approved quality of seat, rubber
buffers and chromium plated hinges. Seat shall be so fixed that it
remains absolutely stationary in vertical position without falling down
on the WC.
12.3.1.5 Each WC shall be provided with 110 mm dia (OD) PVC Pan
Connector connecting the ceramic outlet of WC to CI pipe.
12.3.3.1 Wash basins shall be white /coloured glazed vitreous china of size,
shape and type specified in the Schedule of Quantities.
12.3.3.3 Each basin shall be provided with 32mm dia CP waste with overflow,
pop-up waste or rubber plug and CP brass chain as specified in the
Schedule of Quantities.
12.3.3.4 Each basin shall be provided with hot and cold water mixing fitting or
as specified in the Schedule of Quantities. Wash Faucets shall be
sensor controlled and shall have an added aerator to reduce flow to
2.0 LPM.
12.3.3.5 Flow Rate = 2 Liters per minute @ 58 PSI, all others except private
applications. (as per LEED requirement)
12.3.4 Sinks
12.3.4.1 Sinks shall be stainless steel or any other material as specified in the
Schedule of Quantities.
12.3.4.2 Each sink shall be provided with painted MS or CI brackets and clips
and securely fixed. Counter top sinks shall be fixed with suitable
painted angle iron brackets or clips as recommended by the
manufacturer. Each sink shall be provided with 40mm dia CP waste ISSUE
R3
12.3.4.3 Sanitary fittings for sinks shall be deck mounted or wall mounted CP
swivel faucets with or without hot and cold water mixing fittings as
specified in the Schedule of Quantities. Installation of fittings shall be
measured and paid for separately.
12.3.4.4 Flow Rate = 2 Liters per minute @ 58 PSI, all others except private
applications. (as per LEED requirement)
12.3.5.1 Janitor's sink shall be stainless steel, single bowl type of size as
called for in the Schedule of Quantities, provided with painted R.S. or
CI brackets and clips and securely fixed. Each sink shall be provided
with 40mm dia CP waste. Fixing shall be as directed by the Owner’s
Site Representative. The supply fittings for Janitor's sink shall be wall
mounted type of size as mentioned in Schedule of Quantities.
12.3.6.1 Drinking water fountain shall be wall mounting type made of vitreous
china, stainless steel or any other material as given in the Schedule
of Quantities. The drinking water fountain shall be with anti-squirt
bubble less, self closing valve type with automatic volume regulator.
The drinking water fountain shall be provided with an anti-splash
back and integral strainer with 32mm or 40mm cast brass trap.
ISSUE
R3
12.3.8.1 The hand drier shall be no touch operating type with solid state time
delay to allow user to keep hand in any position. The hand drier shall
be fully hygienic, rated for continuous repeat use (CRU). The rating
of hand drier shall be such that time required to dry a pair of hands
up to wrists is approximately 30 seconds. The hand drier shall be of
wall mounting type suitable for 230 V, single phase, 50 Hz, AC power
supply.
12.3.9.1 Shower set shall comprise of two CP brass concealed stop cocks,
four/five way auto-diverter, adjustable type over-head shower with
CP shower arm, all with CP wall flanges of approved quality all as
specified in the Schedule of Quantities. Bath spout, hand showers
and pop up wastes shall also be provided wherever, specified. Wall
flanges shall be kept clear off the finished wall. Wall flanges
embedded in the finishing shall not be accepted.
12.3.9.2 Flow Rate = < 6.1 Liters per minute @ 58 PSI (as per LEED
requirement)
12.3.9.4 Approved / rated flow control fitment in brass body, chrome outer
cover, rated for flow / discharge of the fixture.
12.3.10.1 Toilet paper holder shall be white glazed vitreous china or chrome
plated of size, shape and type specified in the Schedule of
Quantities.
12.3.10.2 Porcelain toilet paper holder shall be fixed in walls and set in cement
mortar 1:2 (1 cement: 2 coarse sand) and fixed in relation to the tiling
work.
12.3.11.2 Towel rail shall be fixed with screws/capping having finish similar to
the towel rail in wall with rawl plugs or nylon sleeves and shall
include cutting and making good as required or directed by the
Owner’s Site Representative.
12.3.12 Urinals
12.3.12.1 Urinals shall be lipped type half stall with glazed vitreous China of
size as called for in the Bill of Quantities.
12.3.12.2 Half stall urinals shall be provided with 15mm dia CP spreader, ISSUE
R3
32mm dia CP domical waste and CP cast brass bottle trap with pipe
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 128 of
GENERAL BUILDING WORKS
173
and wall flange and shall be fixed to wall by CI brackets, CI wall clips
and CP brass screws as recommended by manufacturer complete as
directed by the Owner’s Site Representative.
12.3.12.4 Flush pipes shall be GI pipes concealed in wall chase but with
chromium plated bends at inlet and outlet.
12.3.12.5 Flow Rate = 4.0 Litres per Flush. 8.5 Liters per minute @ 4 Bar 58
PSI, private applications only (as per LEED requirement)
12.3.13.2 The contractor shall provide all the necessary supporting and fixing
devices to install the sanitary fixtures and fittings securely in position.
The fixing devices shall be rigidly anchored into the building
structure. The devices shall be rust resistant and shall be so fixed
that they do not present an unsightly appearance in the final
assembly. Where the location demands, the Architect may instruct
the contractor to provide chromium plated or other similarly finished
fixing devices. In such circumstances the contractor shall arrange to ISSUE
R3
12.4.1 All appliances, fixtures and fittings shall be provided with all such
accessories as are required to complete the item in working condition
whether specifically mentioned or not in the Schedule of Quantities,
specifications, and drawings. Accessories shall include proper fixing
arrangements, brackets, nuts, bolts, washers, screws and required
connection pieces.
12.4.2 The sanitary fixtures and fittings shall be installed at the correct
assigned position as shown on the drawings and as directed by the
Architect / Owner’s Site Representative and shall fully meet with the
aesthetic and symmetrical requirements as demanded by the
Architect / Interior Designer
12.4.3 All fixtures and accessories shall be fixed in accordance with a set
pattern matching the tiles or interior finish as per Architect
requirements. Wherever necessary, the fittings shall be centered to
dimensions and pattern as called for.
12.4.4 Fixing screws shall be half round head chromium plated (CP) brass
screws, with CP brass washers unless otherwise specified.
shall be made good by the Contractor at his own cost. Fixtures shall
be mounted rigid, plumb and true to alignment.
12.4.8 Wall flanges shall be provided on all walls, floors, columns etc.
wherever supply and disposal pipes pierce through them. These wall
caps shall be or chromium plated brass fittings and the receiving
pipes and shall be large enough to cover the punctures properly.
12.4.12 The appliance shall be fixed in a manner such that it will facilitate
subsequent removal if necessary.
12.4.15 Pipe connections shall be made with demountable unions. Pipe work
shall not be fixed in a manner that it supports or partially supports
and appliance.
12.4.18 The contractor shall fix all plumbing fittings such as water faucets,
shower fittings, mixing valves etc. in accordance with manufacturer’s
instructions and connect to piping system. The contractor shall
supply all fixing materials such as screws, rawl plugs, unions, collars,
compression fittings etc., as required.
12.4.19 Joints / gaps between all sanitary appliances / fixtures and the floor /
walls shall be caulked with an approved mildew resistant sealant,
having antifungal properties, of colour and shade to match that of the
appliances / fixture and the floor / wall to the extent possible.
12.4.20 The contractor shall install all sanitary fixtures and fittings in their final
position in accordance with approved trial assemblies and as shown
on drawings. The installation shall be complete with all supply and
waste connections. The connection between building and piping
system and the sanitary fixtures shall be through proper unions and
flanges to facilitate removal/replacement of sanitary fixtures without
disturbing the built in piping system. All unions and flanges shall
match in appearance with other exposed fittings. ISSUE
R3
12.4.21 Fixtures shall be mounted rigid, plumb and to alignment. The outlets
of water closet pans and similar appliances shall be examined to
ensure that outlet ends are butting on the receiving pipes before
making the joints. It shall be ensured that the receiving pipes are
clear of obstruction. When fixtures are being mounted, attention shall
be paid to the possibility of movement and settlement by other
causes. Overflows shall be made to ensure that necessary anchoring
devices have been provided for supporting water closets, wash
basins, sinks and other appliances.
12.5.1 The contractor shall provide all the necessary supporting and fixing
devices to install the sanitary fixtures and fittings securely in position.
The fixing devices shall be rigidly anchored into the building
structure. The devices shall be rust resistant and shall be so fixed
that they do not present an unsightly appearance in the final
assembly. Where the location demands, the Architect may instruct
the contractor to provide chromium plated or other similarly finished
fixing devices. In such circumstances the contractor shall arrange to
supply the fixing devices and shall be installed complete with
appropriate vibration isolating pads, washers and gaskets.
FINAL INSTALLATION
12.5.2 The contractor shall install all sanitary fixtures and fittings in their final
position in accordance with approved trial assemblies and as shown
on drawings. The installation shall be complete with all supply and
waste connections. The connection between building and piping
system and the sanitary fixtures shall be through proper unions and
flanges to facilitate removal/replacement of sanitary fixtures without
disturbing the built in piping system. All unions and flanges shall
match in appearance with other exposed fittings.
ISSUE
R3
12.5.3 Fixtures shall be mounted rigid, plumb and to alignment. The outlets
of water closet pans and similar appliances shall be examined to
ensure that outlet ends are butting on the receiving pipes before
making the joints. It shall be ensured that the receiving pipes are
clear of obstruction. When fixtures are being mounted, attention shall
be paid to the possibility of movement and settlement by other
causes. Overflows shall be made to ensure that necessary anchoring
devices have been provided for supporting water closets, wash
basins, sinks and other appliance.
12.6.1 Material received at site shall be with original packing and labels. It
shall be intact till issued for use of site. Material shall be stored at
properly covered dry location and shall be safe from damage.
12.6.2 Care must be taken to ensure that the sanitary fixtures are not
damaged while loading / unloading and transporting. Cartons must
always be stored with designated side upwards.
12.6.3 The contractor shall take every precaution to protect all sanitary
fixtures against damage, misuse, cracking, staining, breakage and
pilferage by providing proper wrapping and locking arrangement till
the completion of the installation.
12.6.4 At the time of handing over, the contractor shall clean, disinfect and
polish all the fixtures and fittings. Any fixtures and fittings found
damaged, cracked chipped stained or scratched shall be removed
and new fixtures and fittings free from defects shall be installed at his
own cost to complete the work.
12.7 MEASUREMENTS
12.7.1 Rate for fixing only of sanitary fixtures accessories, CP fittings shall
etc. include all items, and operations stated in the respective ISSUE
R3
specifications and bill of quantities and nothing extra is payable.
FILE NAME: F-329-Rev-R6.docx TCE FORM NO. 329 R6
SECTION:
TATA CONSULTING ENGINEERS LIMITED
SPEC. NO. WRITE UP
TCE.M4-419-01 SHEET 134 of
GENERAL BUILDING WORKS
173
12.7.2 Rates for all items shall be inclusive of cutting holes and chases and
making good the same, CP screws, nuts, bolts and any fixing
arrangements required and recommended by manufacturers, testing
and commissioning and making good to the satisfaction of the
Owner’s Site Representative.
ISSUE
R3
13.1 GENERAL
13.3.1.1 Where specified, all the walls in a building shall be provided with
damp-proof course to prevent water from rising up the wall. The
damp-proof course shall run without a break throughout the length of
the wall, even under the door or other openings. Damp-proof course
shall consist of 50 mm thick cement concrete of 1:2:4 nominal mix
with approved water-proofing compound admixture conforming to IS:
2645 in proportion as directed by the manufacturer. Concrete shall
be with 10 mm downgraded coarse aggregates.
13.3.1.3 Damp-proof course shall be cured properly for at least seven days
after which it shall be allowed to dry for taking up further work.
13.3.2 MEASUREMENT
ISSUE
R3
13.4.1 MATERIALS
13.4.1.1 Material shall be High solids content Polyurethene based cold liquid
applied coatings as per ASTM C836-89 and shall comprise of
urethane pre-polymers extended with flexible material which cure by
reaction with atmospheric moisture and that can be applied with a
brush on concrete surfaces to form a permanent, flexible, seamless
membrane coating after it is cured.
13.4.1.2 The material shall not be diluted. The coating shall have physical
features like high viscosity, minimum 80% solids, high resistance to
impact, abrasion and cracking, superior tensile strength, 500%
elongation and forming a perfectly smooth permanently flexible
seamless membrane which should have good adhesion to roof
surface. It should also be resistant to acid (mild concentrated), alkalis
and have a very low water absorption rate (0.5% max) at ambient
temperature after 7 days. The material shall not be older than 9
months.
13.4.2 WORKMANSHIP
13.4.2.1 The roof shall be sloped with mortar or concrete (M20 grade with
12mm down size agregates) screed to achieve the specified slope as
per drawing and shall be properly cured before taking up water-
proofing treatment.
13.4.2.2 The roof surface shall be cleaned of all foreign matters by wire
brushing, dusting etc. and shall be made thoroughly dry. All cracks
and voids on the surface shall be filled with mastic sealant, if
required. A V-groove shall be made along the crack line and shall be
filled with mastic sealant. ISSUE
R3
13.4.2.5 After the first coat is touched dry, second coat @ 0.50 kg/sq.mm and
minimum average thickness of 0.50mm shall be applied. After the
second coat is dry, third coat shall be applied to result in an overall
thickness of 1.5mm.
13.4.2.8 Water proofing treatment shall be taken on the brick masonry wall /
parapet / column projection by a minimum of 150 mm along its
height. Groove 75mm wide and 65mm deep in masonry shall be left
for tucking the water proofing treatment. The groove shall be filled
with 1:4 cement mortar for securing the water proofing treatment
firmly.
13.4.3 All completed works shall be cleaned to remove any spillage from
chemicals.
13.4.4 For finishing on top, machine made burnt clay flat terracing tiles
conforming to IS 2690 (Part-1) or cement concrete flooring tiles
conforming to IS 1237 shall be used and shall be of the size and
ISSUE
thickness as specified in the item of work. Tiles shall be soaked in R3
water for at least one hour before laying. Bedding for the tiles shall
be 12mm thick in cement mortar 1:3. Tiles shall be laid, open jointed
with 4 to 6 mm wide joints, flat on the mortar and lightly pressed and
set to plane surface true to slope, using a trowel and wooden straight
edge. They shall be laid with their longitudinal lines of joints truly
parallel and generally at right angles to the direction of run-off
gradient. Transverse joints in alternate rows shall come directly in
line with each other. Transverse joints in adjacent courses shall
break joints by atleast 50 mm. The joints shall be completely filled
and flush pointed with cement mortar l:2 mixed with water proofing
compound as per manufacturer's instructions. Curing shall be
carried out for a minimum period of seven days.
13.4.4.1 After completing all the water proofing works over the roof surface
and curing, the works shall be tested against any leakage / soaking
of water below the roof. For this, arrangement shall be made by
Contractor to store minimum 50mm height of water over the roof
surface and shall be maintained for a period of 7 days. If any wet
patch is observed on the ceiling, rectification of water proofing works
should be attended immediately by the contractor. The test should be
repeated till the leakage / soaking through the ceiling completely
stops.
13.4.4.2 The contractor shall give guarantee for a minimum period of 10 years
against any leakage / soaking through the ceiling, for the quality of
materials supplied and for the good workmanship carried out. The
guarantee should be in writing on a format prepared by owner. In
case of any defect found in the above during guarantee period, it
should be attended to and rectified immediately by the contractor at
his own cost
ISSUE
R3
13.4.5 MEASUREMENT
13.4.5.1 Measurement shall be for the plan area of treatment and for the
finished work. No separate payment shall be made for the fillets and
work as specified on the vertical faces. Cement concrete tiling works
or machine pressed clay tile works shall be paid separately, unless
they are specifically included in the item of works.
13.5.1 MATERIAL
13.5.2 WORKMANSHIP
13.5.2.1 Base slab or raft shall be provided over the lean concrete/PCC. The
membrane shall be applied in the similar manner as mentioned in
clause 14.2.2. The top surface of elastomeric memberane shall be
protected by providing 20mm thick mortar ratio 1:4. Protective
coating shall be cured for 3days.
13.5.2.2 The elastomeric membrane for the vertical wall shall be provided on
the outer face exposed to water pressure/earth pressure. The
membrane shall be applied as explained in clause 14.2.2. There
shall be proper continuation of membrane provided below the base
slab /raft and over the outer face of wall. The exposed membrane
shall be protected by providing extruded high density dimpled
polyurethane board.
13.5.3 MEASUREMENT
13.5.3.1 Measurement shall be for the plan area of treatment and for the
finished work. No separate payment shall be made for providing and
ISSUE
R3
13.6.1 MATERIAL
13.6.2 WORKMANSHIP
13.6.2.1 After casting the concrete slab, the surface shall be cured for
required period.
13.6.2.2 The inner surface shall be prepared and memberane coating shall be
applied as described above clause 14.2.2. Provisions of IS13182
shall be adopted for making the wet areas watertight.
13.6.2.3 The prepared surface shall be plastered with cement mortar 1:3 – 15
mm thick admixed with – Normal Setting Integral Waterproofing
Compound conforming to IS: 2645, or approved equivalent at 2% by
weight of cement. Surface shall be cured for minimum 7 days.
13.7 WATERSTOPS
13.7.1 MATERIAL
13.7.1.1 The material for the PVC waterstops shall be a plastic compound
with the basic resin of polyvinyl chloride and additional resins,
plasticizers, inhibitors, which satisfies the performance
characteristics specified below as per IS:15058. Testing shall be in
accordance with IS:8543 (Part 4/sec1), IS 13360 (Part 5/sec11) and
IS 9766..
Tensile strength : 13.8 MPa minimum
ISSUE
Ultimate elongation : 285% minimum R3
Accelerated extraction
ISSUE
R3
13.7.1.2 PVC water stops shall be either of the bar type, serrated with centre
bulb and end grips for use within the concrete elements or of the
surface (kicker) type for external use. The width, type, minimum
thickness and safe hydraulic head requirements shall be as specified
in the individual items of work.
13.7.1.3 PVC water stops shall be of approved manufacture. Samples and the
test certificate shall be got approved by the ENGINEER before
procurement for incorporation in the works.
13.7.2 WORKMANSHIP
13.7.3 MEASUREMENT
13.8.1 MATERIAL
13.8.2 WORKMANSHIP
13.8.2.1 Construction joint surface shall be cleaned and swellable water bar
shall be placed in the grove or fixed with adhesive and cured as per
the manufacturer instruction/specification. before placement of next
layer of concrete.
13.8.3 MEASUREMENT
ISSUE
R3
14.1 GENERAL
IS:901
Code Of - Practice For Use Of Cold-Formed Light Gauge Steel
Structural Members In General Building Construction
ISSUE
R3
14.3 MATERIAL
14.3.2 Troughed permanently colour coated metal sheet for roofing, side
cladding, ridges, hips, flashings, trimmings, closure for vertical &
horizontal joints,capping etc., shall be
14.3.3 With sheet having minimum 0.6mm (bare metal thickness) thickness
galvanised to grade 275 as per IS277, of minimum yeild strength of
250Mpa of drawing grade as per IS513.
14.3.4 With sheet having minimum 0.5mm (bare metal thickness) thickness
coated with zinc aluminium alloy at 150gm/m2 of minimum yield
strength of 350 as per AS1397.
14.3.5 Steel sheet shall be colour coated as per clause 15.2.1 and shall be
of approved profile, sectional properties, colour and shade.
14.4.1 For metal decking the sectional properties shall be calculated as per
IS801 for satisfying deflection and strength requirements. Deflection
shall be limited to span/250 under critical load combinations.
ISSUE
R3
14.4.4 Sealant used for cladding shall be butyl based, two parts poly
sulphide or equivanlent approved, non stainless material and be
flexible enough not to interface with fit of the sheets.
14.4.5 Filler blocks as a trough filler shall be used to seal cavities formed
between the profiled sheet and the support or flashing . Filler block
shall be manufacturered from black synthetic rubber or any other
material approved by ENGINEER.
14.4.8 Percentatge elongation of the mild steel sheet having minimum yield
strength of 250Mpa shall be 23% as per IS :2062.
14.5 WORKMANSHIP
14.5.1 The sheeting shall be fixed as per the working drawings. Sheets shall
be supplied in required sizes (based on the secondary beams
spacing/ purlins) according to the cutting schedule. Generally cutting
ISSUE
of sheets to lengths shall shall be used for cutting. Cutting and R3
14.5.3 Side and end laps of the sheets shall be made weather proof by
securing them with the fasterners not less than 4mm dis with 2mm
thick neoprene washer. Maximum spacing of the fasterners not to
exceed 500mm.
14.5.4 Length of the sheet shall be such as to cover minimum 3 span purlin
spacings. The roof decking sheets shall be fixed to the purlins with
the help of self drilling and tapping type fasteners and neoprene
washers.
14.5.5 Sheets shall be laid over the supporting purlins with a minimum
bearing of 50mm and end projection of 75mm at lap joints. End and
side laps between the sheets shall be sufficiently large to ensure the
weather tightness. In no case, the end laps shall be less than 150mm
and side laps less than one trough length with proper weather tight
arrangement.
14.5.6 Cladding erection for each elevation shall commence at the bottom
and proceed towards the top, in order to ensure tight fittings laps.
14.5.7 In case double skin cladding, inner sheet and outer sheet can be
directly fixed to the opposite faces of the sheeting runner totally
concealing the supporting steel structure.
ISSUE
R3
ISSUE
R3
15.1 GENERAL
15.2.1 Work shall be carried out as per latest edition of Indian Standards
and Code of Practices. List given here shall not be considered as
conclusive and is for reference and guidance only. Any
discrepancies/ conflict noticed shall be brought to the notice of
Architect/Engineer in charge for direction / approval. However, as a
general rule more stringent specification shall take precedence.
INDIAN STANDARDS:
NBC 2005 Bureau of Indian Standards, the National Building
Code of India,
IS: 806 Code of Practice for Use of Steel Tubes in
General Building Construction.
IS: 2835 Specification for flat transparent sheet glass(third
revision)
ISSUE
R3
BRITISH STANDARDS
CP 3012: Code of Practice for Cleaning and
Preparation of Metal Surfaces
IBC 2407: Glass in Handrails and Guards
BS EN 14179-2: Glass in building. Heat-soaked thermally-
toughened soda lime silicate safety glass
Evaluation of conformity/product standard
BS EN 1096-1: Glass in building. Coated glass Definitions
and classification ISSUE
R3
15.3.1 MATERIALS
15.3.1.2 All rails and other horizontal / inclined tubular components shall be
constructed using the following:
15.3.1.3 Surface to be 320 grain/grit finish/ polish / matte/ bead blasted Tubes
1-1/2” (38mm) outside diameter by 5/64” (2 mm) wall thickness.All
posts and other vertical components shall be constructed using the
following:
15.3.1.7 Stainless steel grade AISI type 316, surface to be 320 grain/grit
finish/ polish / matte/ bead blasted for component fittings including
handrail attachment support and post attachment components
Stainless Perforated, Woven Or Welded Metal Infill Panels: As per
Custom pattern as specified herein.
15.3.1.8 Fasteners:
15.3.1.9 Anchors & Fastening bolts to be stainless steel or other high strength
material as determined by engineering requirements with capability
to sustain, without failure, load imposed within a safety factor of 4, as
determined by testing per ASTM E488.
15.3.2.5 When two stainless steel items are joined it is absolutely necessary
to use elements of stainless steel or of other materials with an
equivalent resistance to corrosion.
15.3.2.6 When stainless steel items are joined to carbon steel structural
elements the carbon steel element must be well protected by suitable
painting.
15.3.2.7 Stainless steel rivets, screws and bolts must be used and the carbon
steel element must be suitably insulated from the stainless steel
element using EPDM/ neoprene/Teflon
15.3.3 WORKMANSHIP
15.3.3.1 Installation work shall not be carried out until substrates have been
properly prepared.
15.3.3.3 All works shown or inferred from the Specifications and Drawings are
intended to be the design criteria for the subcontract work. The
detailed design development shall be submitted by the Contractor for
Acceptance and Endorsement.
15.3.3.5 The Contractor shall allow for any additional supports on framework
where required so as to ensure the stability and capability of the
installation to withstand all specified loads under normal usage
encountered during the service life of the works.
15.3.3.6 Field measurements: Where handrails and railings are indicated to fit
to other construction, check actual dimensions of other construction
by accurate field measurements before fabrication; show recorded
measurements on final shop drawings.
15.3.3.15 Stainless steel tubing cuts shall be square, without burrs and where
exposed, rounded to produce smooth rigid and hairline joints
15.3.3.18 Perform cutting, drilling and fitting required for installation. Set
accurately in location, alignment and elevation, plumb, level and true,
measured from established lines and levels.
15.3.3.26 Maximum offset from true alignment for every 50-foot of railing shall
be 1/4", non-accumulative.
15.3.4.6 Upon delivery railing will have protective wrapping over cap only.
Immediately upon completion of installation of railing, remove cap
cover and clean all work for inspection and approval.
15.3.4.7 When cleaning surfaces use plain water containing a mild soap or
detergent. No abrasive agents or harsh chemicals shall be used.
15.3.5 WARRANTY
15.3.5.1 Finish Warranty: Manufacturer shall warranty installed system for the
periods described herein, starting from Date of Substantial
Completion. When notified in writing from Owner, manufacturer /
installer shall, promptly and without inconvenience and cost to
Owner, correct said deficiencies.
15.3.6 MEASUREMENT
15.3.6.1 Horizontal plan length of top rail only will be measured as handrail
length in Running Unit. Verticals will not be measured. Rate shall
include all labour and materials including balustrades (vertical pipes)
all necessary infill details (as shown in drawing), welding (if
necessary), tools, plants & buffing charges fixing arrangements etc
complete as directed.
15.3.6.3 All the specifications mentioned above are the general standardised
ones. Architectural layout plans & the detail drawings should be
ISSUE
followed / referred for all the specified design & details & the R3
15.4.1 MATERIALS
15.4.1.1 Guardrails And Handrail System - All rails and other horizontal /
inclined tubular components shall be constructed using the following:
15.4.1.3 All posts and other vertical components shall be constructed using
the following:
15.4.1.7 Provide 1.0mm radius at all corners with ‘v-cut’ where necessary.
15.4.1.9 Stainless steel grade AISI type 316, surface to be 320 grain/grit
finish/ polish / matte/ bead blasted for component fittings including
handrail attachment support and post attachment components
15.4.1.13 Tinted glass: Class 2 (tinted heat absorbing and light reducing).
Manufacturer’s standard tint color or custom color as indicated
below:
15.4.1.16 Glass shall be Fully Tempered and 100% Heat Soak Tested to EN
14179 part 1.
15.4.1.18 Opacifier coatings and films are required to be suitable for the
proposed temperature and exposure conditions and are required to
function without bubbling, blistering or colour shift for the design life
of the Building.
15.4.1.20 Anchors & Fastening bolts to be stainless steel or other high strength
material as determined by engineering requirements with capability
to sustain, without failure, load imposed within a safety factor of 4, as
determined by testing per ASTM E488.
15.4.1.22 Glass for laminating is to be cut into individual panels prior to the
laminating process.
15.4.1.24 Heat treated glass is to be orientated so that warp, bow and roller
wave between successive panels are matched. Two stage
convection empering ovens are to be used to ensure glass
distortions are minimized. Edge clamping of glass is forbidden.
15.4.1.27 When two stainless steel items are joined it is absolutely necessary
to use elements of stainless steel or of other materials with an
equivalent resistance to corrosion.
15.4.1.28 When stainless steel items are joined to carbon steel structural
elements the carbon steel element must be well protected by suitable
painting. Stainless steel rivets, screws and bolts must be used and
ISSUE
R3
15.4.1.30 All laminated glass shall have clean cut edges, or polished edges if
required to eliminate thermal stress breakage risk. Laminated glass
units shall be fabricated with autoclaved edges on all four sides.
15.4.1.32 All exposed laminated glass edges shall be protected from blushing
by hot rolling the interlayer back into the glass edge, or by use of an
approved edge seal material.
15.4.1.35 Perform cutting, drilling and fitting required for installation. Set
accurately in location, alignment and elevation, plumb, level and true,
measured from established lines and levels.
15.4.1.42 Maximum offset from true alignment for every 50-foot of railing shall
be 1/4", non-accumulative.
15.4.3 WORKMANSHIP
15.4.3.3 All works shown or inferred from the Specifications and Drawings are
intended to be the design criteria for the subcontract work. The
detailed design development shall be submitted by the Contractor for
Acceptance and Endorsement.
15.4.3.5 The Contractor shall allow for any additional supports on framework
where required so as to ensure the stability and capability of the
installation to withstand all specified loads under normal usage
encountered during the service life of the works.
15.4.3.6 Field measurements: Where handrails and railings are indicated to fit
to other construction, check actual dimensions of other construction
by accurate field measurements before fabrication; show recorded
measurements on final shop drawings.
ISSUE
R3
15.4.3.15 Stainless steel tubing cuts shall be square, without burrs and where
exposed, rounded to produce smooth rigid and hairline joints
15.4.4.1 Submit (within the One month of the award of contract) the
Comprehensive, detailed and dimensioned shop drawings to indicate
all set-out and construction/ installation details to include and not ISSUE
R3
15.4.6.5 Defective works log to be kept up to date for the duration of the
warranty period outlining each defect type location and corrective
action to rectify each defect.
15.4.8 Glass
15.4.8.2 Bow Distortion: ‘bow’ and ‘warp’ shall have the same meaning.
Overall bow across the shorter glass dimension (‘the gauge length’)
shall not exceed 0.00342 times gauge length for gauge length less
than 900mm, and 0.00258 times gauge length for gauge length
greater than 900mm.
15.4.8.3 100% heat soak testing will be required for all glass with edge stress
exceeding 50mpA (7500 psi). Submit Heat Soak method,
temperature, and duration for review and Acceptance, prior to
commencement.
15.4.9 MOCK-UP
ISSUE
R3
15.4.9.1 Contractor shall install a full scale mock up for a length of 7.5m of
typical detailing treatment at locations to be confirmed by the
Architect.
15.4.9.2 The visual mock-up for the assembly will be required to be Accepted
and Endorsed by the Architect with respect to appearance of colour.
15.4.10.5 Upon delivery railing will have protective wrapping over cap only.
Immediately upon completion of installation of railing, remove cap
cover and clean all work for inspection and approval.
15.4.10.7 When cleaning surfaces use plain water containing a mild soap or
detergent. No abrasive agents or harsh chemicals shall be used.
ISSUE
R3
15.4.11 WARRANTY
15.4.12 MEASUREMENT
15.4.12.1 The mode of measurement will be length of railing and not length of
individual pipes/bars i.e. Horizontal plan length of top rail only will be
measured as handrail length in Running Unit. Verticals will not be
measured.
15.4.12.2 Rate shall include all labour and materials including balustrades
(vertical pipes) all necessary infill details / Glass Panels (as shown in
drg), welding (if necessary), tools, plants & buffing charges fixing
arrangements etc complete as directed.
15.4.12.4 All the specifications mentioned above are the general standardised
ones. Architectural layout plans & the detail drawings should be
followed / referred for all the specified design & details & the
architectural drawings submitted should be termed as final, in case of
any discrepancies or variations, what-so-ever.
ISSUE
R3
15.5.1 MATERIALS
15.5.1.1 Mild steel tubular sections should be used for hand railing; design
should be as per drawing.
15.5.2 WORKMANSHIP
15.5.2.1 The hand railings will be fitted in staircase and other areas without
tampering the finishing material of the stair/area. The fixing will be
done as per details shown in drawing.
15.5.3 MOCK-UP
15.5.3.1 Contractor shall install a full scale mock up for a length of 7.5m of
typical detailing treatment at locations to be confirmed by the
Architect.
15.5.3.2 The visual mock-up for the assembly will be required to be accepted
and endorsed by the Architect with respect to appearance of colour.
15.5.4 MEASUREMENT
15.5.4.2 Rate shall include all labour and materials including balustrades
(vertical pipes) welding, tools, scaffoldings, buffing charges, fixing
arrangements etc complete as directed.
ISSUE
R3
16 MISCELLANEOUS
16.1 GENERAL
IS:4948 - Specification for welded steel wire fabric for general use.
16.3.1 WORKMANSHIP
16.3.1.1 All the miscellaneous inserts such as bolts, pipes, plate embedments
etc. either supplied FREE by the OWNER or to be furnished by the
CONTRACTOR shall be accurately installed in the building works at
the correct locations and levels, all as detailed in the construction
drawings. CONTRACTOR shall prepare and use templates for this
purpose, if so directed by the ENGINEER. In the event, any of the
inserts are improperly installed, CONTRACTOR shall make
necessary arrangements to remove and re-install at the correct
locations/levels, all as directed by the ENGINEER without any extra
cost to the OWNER.
16.3.1.2 The rate quoted by the Bidder for concrete works shall hold good for
accurately fixing the inserts at the correct levels/alignment and shall
include the cost of any temporary supports/anchors such as bars
including cutting, bending, welding, etc. as required.
16.3.1.4 The Contractor shall ensure proper protection of all bolts, inserts, etc.
from weather by greasing or other approved means such as applying
white lead putty and wrapping them with gunny bags or canvas or by
other means as directed by the Engineer to avoid damage due to
movement of his labourers, materials, equipment, etc. No extra claim
from the Contractor on this account shall be entertained. The
Contractor shall be solely responsible for all damage caused to bolts,
inserts, etc. due to his negligence and in case damage does occur,
they shall be rectified to the satisfaction of the Engineer at the
Contractor's cost.
16.3.1.5 Cut outs, chamfers, pockets, etc. shall be left as indicated in the
drawings and no extra cost shall be payable for providing these at
their correct locations. The Contractor shall take all necessary
precautions to protect the cut outs from accidentally getting filled up
or the edges getting broken.
16.3.2 MEASUREMENT
16.4.1 MATERIALS
16.4.2 WORKMANSHIP
16.4.2.1 The type and details of the steel material to be used for metal lath
plastering work and at the junctions of brick masonry/concrete before
wall plastering shall be as specified in the respective items of work.
16.4.2.2 For metal lath plastering work, the weight of steel material shall be
not less than 1.6 kg/sq m.
16.4.2.3 Steel material for use at the Junction of brick masonry/ concrete shall
have the mesh dimensions not greater than 50 mm.
16.4.3 MEASUREMENT
ISSUE
R3
1.0 SCOPE
This specification covers the general requirements for the materials and
construction of concrete plant roads using pavement quality concrete.
The work shall consist of preparing sub grade , construction of dry lean concrete
as sub base and concrete pavement in accordance with these specifications and
in conformity with the lines, grades and cross sections shown in the drawings or
as directed by the Engineer. The work shall include furnishing of all plants and
equipments, materials and labour and performing all operations, in connection
with the work, as approved by the Engineer.
The design parameters of dry lean concrete as sub base and concrete as road
surface like width, thickness, grade of concrete, details of joints, etc shall be as
stipulated in the drawing.
13) IS 1786: 2008 Specification for high strength deformed steel bars
(Reaffirmed 2013) and wires for concrete reinforcement.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 2 OF 35
18) IS 3812 Part 1: Pulverized Fuel Ash – Part 1 : for use as Pozzolana in
2013 Cement, Cement Mortar and Concrete
19) IS 3812 Part 2: Pulverized Fuel Ash - Part 2 : for use as Admixture in
2013 (Reaffirmed Cement Mortar And Concrete
2017)
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 3 OF 35
11) IS 11993: 1987 Code of practice for use of screed board concrete
(Reaffirmed 2013) vibrators.
13) IS 2722: 1964 Specification for Portable Swing Weigh Batchers for
(Reaffirmed 2016) concrete (single and double bucket type).
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 4 OF 35
2.7 DESIGN
8) IRC: 101 – 1988 Guide line for continuously reinforced concrete with
elastic joint
11) IS 2502: 1963 Code of practice for bending and fixing of bars for
(Reaffirmed 2013) concrete reinforcement.
12) MORTH Specifications for Road and Bridge Works 2013 (5th
Rev)
2.9 MEASUREMENT
3.0 EARTHWORK
3.1 EARTHWORK IN EXCAVATION
In general the excavation shall be in accordance with TCE specification
No.TCE.M4-418-01.
Profiles of road excavation shall be laid at 50 m intervals to conform to the
required alignment, sections, grades and side slopes and the lines of cuts shall be
clearly marked.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 5 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 6 OF 35
and the second time in backward move. Each layer shall be thoroughly
compacted to achieve minimum dry density of 95% as per IS:2720 (Part 8).
To allow for subsequent settlement the finished level of the embankment shall be
kept higher than the specified level by one centimetre for every metre of the
height of the bank.
Embankment shall be finished and dressed smooth and even to conform to the
alignment, levels, cross sections, and dimensions shown on drawings with due
allowance for shrinkage. Any damage caused by rain, or any other reason shall
be made good in the finishing operation.
Table 1
Density requirement of Embankment and Subgrade materials
Sl. Type of Work Max. Dry Unit Weight tested
No. as per IS 2720 (Part 8)
1. Embankment up to 3m height not Not less than 15.2 kN/cum
subjected to excessive flooding
2. Embankment exceeding 3m height or Not less than 16.0 kN/cum
any height subjected to long periods of
inundation
3. Subgrade and earthen shoulders/ Not less than 17.5 kN/cum
verges/ backfill
Table 2
Compaction requirement of Embankment and Subgrade
Sl. Type of Work/ Material Relative compaction as % of
No. max laboratory dry density
as per IS 2720 (Part 8)
1. Subgrade and earthen shoulders Not less than 97%
2. Embankment Not less than 95%
3. Expansive clays
a) Subgrade and 500mm portion below Not allowed
b) Remaining portion of embankment 90% to 95%
3.2.1 MEASUREMENT
Earth embankment/ subgrade construction shall be measured separately by
taking cross sections at intervals before and after work and computing volume of
earthwork in cum by method of average and areas. The measurement of fill
materials from borrow areas shall be the difference between the net quantities of
compacted fill and the net quantities brought from road/ drain excavation. It shall
be assumed that one cum of material brought from excavation is equivalent to one
cum of compacted fill and bulking/ shrinkage shall be ignored. In case the
embankment/ subgrade construction is carried out using earth from stacks
excavated earlier, the volume of stacked material shall be reduced by 30% to
account for voids in the loose fill.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 7 OF 35
5.0 SOLING
Soling shall not be provided on a wet subgrade.
Unless otherwise specified, the width of the soling shall be 230 mm more on either
side than that of the waterbound macadam course and the finished thickness of
the soling course shall be 230 mm.
The soling stones shall be laid with the largest face downwards and in contact
with each other. The stones shall break joints as far as possible. The height of the
soling stone shall be equal to specified thickness of soling.
As the laying of rubble advances the soling shall be hand packed by wedging and
packing with 80 mm and downgraded metal in the joints of the soling and driving
them by hammers in place so as to fill the voids as completely as possible. This
operation of hand packing shall closely follow the rubble laying. The soling shall
be laid and hand packed true to grade and section and these shall be often
checked by boning rods, template boards and fish line etc. The grades, sections
etc. of the soling shall correspond to those of the surfacing coming on it. The
soling thus laid shall be finished by knocking out projecting stones and filling
depressions by chips to come up to the grade and camber.
The quality of the 80 mm and downgraded metal shall be same as specified for
the soling and the longest dimension shall not be more than 100 mm and the
shortest dimension not less than 50 mm.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 8 OF 35
The soling after it is properly laid and hand packed including filling of voids with 80
mm metal shall be rolled dry with 10 - 12T power roller to refusal i.e. till the stones
in the soling course cease to move under the roller and no more compaction can
be achieved. Rolling shall start at the edges and work towards the centre. The
roller shall run over the same surface of rolling for at least 8 times till the soling
course is well consolidated. The surface shall be checked by templates and in
case of unevenness high spots shall be knocked out and depressions filled by
spalls and re-compacted fully. Bunds shall be laid along the edges and
compacted before starting rolling on soling to prevent spreading of stones.
Gravel shall be spread in thin layers over the above prepared soling surface,
swept into the interstices with brooms, watered lightly to assist the filling of voids.
Spreading of gravel, sweeping and watering shall continue till the interstices are
completely filled. At all times only enough water shall be sprinkled to force the
gravel into the voids and never so much as to soften the subgrade. The process
of gravel filling shall be accompanied by dry rolling of soling with a power roller
weighing not less than 10 tonnes starting at edge and working towards the centre.
The roller shall run over the same surface for at least eight times. Each pass of
the roller shall uniformly overlap not less than one third of the track made in the
preceding pass. The surface shall be checked with templates of approved design
(to be provided by Contractor) and high and low spots corrected by removing
soling and repacking.
Where slag from iron making plants is available, it can be used to form the base
course. Crushed slag shall be made from air cooled blast furnace slag. It shall be
of angular shape, reasonably uniform in quality and density and generally free
from thin, elongated and soft pieces, dirt or other deleterious materials. The
weight of crushed slag shall not be less than 11.2kN/m3 and the percentage of
glossy material shall not be more than 20. It should also comply with requirements
below:
Table 3
Requirement of slag (Sub Base / Base Course)
Sl.No. Test Requirements Test Method
1. Chemical stability Comply BS1047 BS 1047
2. Sulphur content 2% (max.)
3. Water absorption 10% (max.)
5.1 MEASUREMENT
Measurements shall be made for the finished work in square metres of the actual
plan area covered with the soling stone. The rate shall cover carrying out works as
specified above and include the cost of all materials, labour, plant and equipment
involved in the works.
6.1.1 CEMENT
Any of the following types of cement may be used with prior approval of the
engineer:
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 9 OF 35
6.1.2 AGGREGATES
Aggregates for lean concrete shall be natural material conforming to IS: 383 but
with Los Angeles Abrasion Test result not more than 35%. The aggregates shall
not be alkali reactive. The limits of deleterious materials shall not exceed the
requirements set out in Table 5. The aggregates shall be free from chert, flint,
chalcedony or other silica in a form that can react with alkalis in the cement. In
addition, the total chlorides content expressed as chloride ion content shall not
exceed 0.06% by weight and the total sulphate content expressed as sulphuric
anhydride (SO3) shall not exceed 0.25% by weight. In case the Engineer
considers that the aggregates are not free from dirt, the same may be washed
and drained for at least 72 hours before batching, as directed by the Engineer.
Coarse Aggregate: Coarse aggregate shall consist of clean, hard, strong, dense,
non-porous and durable pieces of crushed stone or crushed gravel and shall be
devoid of pieces of disintegrated stone, soft, flaky, elongated, very angular or
splintery pieces. The maximum size of the coarse aggregate shall be 31.5 mm. No
aggregate which has water absorption more than 2% shall be used in the
concrete mix. The aggregate shall be tested for soundness in accordance with
IS:2386 (Part 5). After 5 cycles of testing the loss shall not be more than 12% if
sodium sulphate solution is used or 18% if magnesium sulphate solution is used.
Combined flakiness and elongation index of aggregate shall not be more than
35%.
Fine aggregate: The fine aggregate shall consist of clean, natural sand or crushed
stone sand or a combination of the two and shall confirm to IS: 383. Fine
aggregates shall be free from soft particles, clay, shale, loam, cemented particles,
mica, organic and other foreign matter. The fine aggregate shall have a sand
equivalent value of not less than 50 when tested in accordance with IS 2720 Part
37.
Table 4
Aggregate Gradation or Dry Lean Concrete
Sieve Designation Percentage passing the sieve by weight
26.50 mm 100
19.00 mm 75 – 95
9.50 mm 50 – 70
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 10 OF 35
4.75 mm 30 – 55
2.36 mm 17 - 42
600 micron 8 – 22
300 micron 7 – 17
150 micron 2 – 12
75 micron 0 – 10
Table 5
Aggregate Gradation or Dry Lean Concrete
Sl. Deleterious Method of Fine Aggregate %ge Coarse Aggregate
No. Substance Test by weight (max) %ge by weight (max)
Uncrushed Crushed Uncrushed Crushed
(1) (2) (3) (4) (5) (6) (7)
i) Coal and lignite IS 2386 Part 1.0 1.0 1.0 1.0
2: 1963
ii) Clay lumps IS 2386 Part 1.0 1.0 1.0 1.0
2: 1963
iii) Materials finer IS 2386 Part 3.0 8.0 3.0 3.0
than 15 sieve 1: 1963
iv) Soft fragments IS 2386 Part - - 3.0 -
2: 1963
v) Shale IS 2386 Part 1.0 - - -
2: 1963
vi) Total %ge of all deleterious 5.0 2.0 5.0 5.0
materials (except mica) including
Sl. No. (i) to (v) for Col. 4, 6, 7
and Sl No. (i) and (ii) for Col. 5
only
Crushed aggregate at least one face fractured
Note: The presence of mica in the fine aggregate is found to considerably reduce the
durability and compressive strength of concrete considerably. It is advisable
therefore to determine the mica content of fine aggregate and make suitable
allowances for the possible reduction in the strength of concrete and mortar, in
case the stretch of road passes through micacious belt.
6.1.3 WATER
Water used for mixing and curing of concrete shall be clean and free from
injurious amounts of oil, salt, acid, vegetable matter or other substances harmful
to the finished concrete. It shall meet the requirements stipulated in IS: 456.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 11 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 12 OF 35
6.4.2 TRANSPORTING
The mix shall be transported from mixer to job site in tipping trucks covered with
tarpaulin. The lead should be such as to allow finishing of concrete laying in any
transverse section within 90 minutes from mixing when temperature is between
25Oc to 30OC and 120 minutes when temperature is less than 25OC. Each tipping
truck shall be washed with water jet before next loading to prevent old concrete
sticking to it. Segregation of mix shall be controlled by moving dumper back and
forth while placing concrete.
6.4.3 PLACING
Lean concrete shall be placed on drainage layer by a paver with electronic sensor
in one layer for the specified thickness and full width of two lane carriageway. The
paving machine shall have tamping bars for initial compaction of the sub-base.
The sub-base drainage layer shall be given a fine spray of water and rolled with
smooth wheeled roller one day before placing dry lean concrete. The DLC shall
be laid 750mm wider than proposed width on each side to enable the crawler to
move; the cost of extra width shall be included by contractor in his quoted rates.
Work shall not proceed if concrete temperature exceeds 30OC or ambient
temperature exceeds 35OC. Chilled water or ice may be added in mixing to bring
down the temperature.
6.4.4 COMPACTION
Compaction shall start immediately after laying of material and rolling continued till
no further movement under roller is visible. Double drum smooth wheeled
vibratory rollers of 80 – 100 kN static weight are suitable for compaction of DLC,
the number of passes are determined during trial section construction by
measurement of in-situ density. Rolling shall proceed from edges to centre except
in super elevated section where rolling shall be from inner to outer edge. The final
lean concrete surface shall be well closed, free from movement under roller
passes, and free from ridges, low spots, cracks, loose material, pot holes, ruts and
other defects. Minimum dry density shall be 98% of that obtained during trial
length and 96% at 0.5m from edges. Surface shall be inspected immediately after
compaction and checked for regularity with 3m straight edge. For repairing,
concrete with 10mm down aggregates shall be spread and compacted. Strength
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 13 OF 35
tests shall be carried out and if deficiency is found, at least 3 – 100mm diameter
cores per km shall be cut for strength tests. Holes shall be filled with concrete and
compacted.
6.4.5 JOINTS
Construction and longitudinal joints in the lean concrete shall be provided as
shown in drawings. Transverse butt type joints shall be provided at the end of a
day’s work. Where forms are not used, the edge shall be cut back to a vertical
plane of correct thickness. Transverse joints shall be staggered from butt type
construction joint in concrete pavement by 800 – 1000mm; longitudinal joints shall
be staggered from longitudinal joint in concrete pavement by 300 - 400mm.
6.4.6 CURING
Curing shall commence immediately after compaction by one of the following
three methods:
Covering the surface with gunny bags/ hessian kept continuously wet for 7
days by sprinkling water.
Spraying with approved resin based alumnized reflective curing compound
conforming to ASTC-C 309-81 and covering with wet hessian cloth for 3 days.
Applying wax-based white pigmented curing compound conforming to BS
7542 with water retention index > 90% in two stages and covering with wet
hessian cloth for 3 days and second application 24 to 48 hours prior to placing
of concrete pavement.
6.4.7 MEASUREMENT
Dry lean concrete pavement work shall be measured in cubic metre of concrete
placed based on net plan area for accepted thickness. The rate payable shall be
for all materials, equipment, labour, mixing, transport, placing, compacting,
finishing, curing and rectification of defects and incidentals such as trial length.
7.2.1 CEMENT
Any of the following types of cement may be used with prior approval of the
engineer
Ordinary Portland cement 43 grade IS: 8112
Ordinary Portland cement 53 grade IS: 12269
Portland Slag Cement IS: 455
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 14 OF 35
Portland Pozzolana Cement IS: 1489 – Part 1 (with flyash content < 20%)
If the sub grade is found to consist of soluble sulphates in a concentration more
than 0.5 per cent, cement used shall be sulphate resistant and shall confirm to IS:
12330.
Flyash conforming to IS 3812 (Part 1) up to 20% of total cementitious material
(cement + flyash) may be permitted as replacement of OPC 43/ 53 Grade cement.
7.2.2 ADMIXTURES
Admixtures conforming to IS:6925 and IS:9103 shall be permitted to improve
workability of the concrete or extension offsetting time, on satisfactory evidence
that they wil not have any adverse effect on the properties of concrete with
respect to its strength, volume change, durability and have no deleterious effect
on steel bars. The particular of the admixtures and the quantity to be used, must
be furnished to the Engineer in advance to obtain his approval before use.
Satisfactory performance of the admixtures is to be proved both on the laboratory
concrete trial mixes and in trial paving works. If air entraining admixture is used,
the total quantity of air in air entrained concrete as a percentage of the volume of
the mix shall be 5 +/- 1.5 per cent for 31.5 mm nominal size aggregate.
Silica fume complying with IS 15338, IS 456 and IRC 44 may be used as
admixture in proportion 3% to 10% of cement content. Steel fibre conforming to
IRC: SP 46 or polymeric synthetic fibres may be used with approval of Engineer to
reduce cracking.
Effective diameter 10 – 100 micron
Length 6 – 48 mm
Specific gravity More than 1.0
Suggested dosage 0.6-2.0 kg/cum (0.2-0.6% by weight of cement in mix)
Water absorption Less than 0.45%
Melting point of this fibre shall not be less than 160OC
The aspect ratio generally varies from 200 to 2000
These synthetic fibres will have good alkali and UV light resistance
7.2.3 AGGREGATES
Aggregates for lean concrete shall be natural material conforming to IS: 383 but
with Los Angeles Abrasion Test result not more than 35%. The aggregates shall
not be alkali reactive. The limits of deleterious materials shall not exceed the
requirements set out in Table 5. The aggregates shall be free from chert, flint,
chalcedony or other silica in a form that can react with alkalis in the cement. In
addition, the total chlorides content expressed as chloride ion content shall not
exceed 0.06% by weight and the total sulphate content expressed as sulphuric
anhydride (SO3) shall not exceed 0.25% by weight. In case the Engineer
considers that the aggregates are not free from dirt, the same may be washed
and drained for at least 72 hours before batching, as directed by the Engineer.
Coarse Aggregate: Coarse aggregate shall consist of clean, hard, strong, dense,
non-porous and durable pieces of crushed stone or crushed gravel and shall be
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 15 OF 35
7.2.4 WATER
Water used for mixing and curing of concrete shall be clean and free from
injurious amounts of oil, salt, acid, vegetable matter or other substances harmful
to the finished concrete. It shall meet the requirements stipulated in IS: 456.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 16 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 17 OF 35
In order to ensure that minimum strength at 28 days is achieved in 99% of all test
beams, the mix shall be proportioned to give an average strength exceeding
characteristic strength by 2.33 times the standard deviation.
Table 7
Concrete Grades
Grade of Minimum Compressive Characteristic compressive
Concrete Strength at 7 days (N/Sq.mm) strength at 28 days (N/sq.mm)
The ratio between 7 and 28 day strengths shall be established for the mix. During
construction if the average value of any four consecutive 7 day test results falls
below the required 7 day strength, the cement content will be increased by 5% by
weight or as approved by Engineer without additional payment.
The workability of the concrete at the point of placing shall be adequate for the
concrete to be fully compacted and finished without undue flow. The water content
shall be minimum required to provide the agreed workability for full compaction of
concrete to required density and the maximum free water cement ratio shall befor
blended cement 0.45 for OPC and 0.50. A slump value in the range of 25±15mm
is reasonable for pavement construction but may be modified at site with approval
of the Engineer.
7.5 BATCHING & MIXING OF CONCRETE
A systems approach may be adopted for construction of the pavement, and the
method statement for carrying out the work, detailing all the activities including
indication of time cycle, equipment, personal etc., shall be got approved from the
engineer before the commencement of the work. The capacity of paving
equipment, batching plant as well as all the ancillary equipment shall be adequate
for a paving rate of at least 300m in one day.
Proportions of aggregates and cements, as decided by the concrete mix design,
shall be by weight. These proportions shall be maintained during subsequent
concrete batching by means of weigh batchers capable of controlling the weights
within (+/-) one percent for cement and water and (+/-) two percent for aggregates
of the desired value. The type and capacity shall be got approved by the Engineer
before commencement of the trial length.
The design feature of the batching plant should be such that the shifting
operations of the plant will not take very long time when they are to be shifted
from place to place with the progress of the work.
Batching and mixing of the concrete shall be done at a central batching and
mixing plant with automatic controls, located at a suitable place which takes into
account sufficient space for stockpiling of cement, aggregates and stationary
water tanks.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 18 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 19 OF 35
membrane, the sub-base shall be swept clean of all extraneous material using air
compressor Overlap of plastic sheet shall be 300mm minimum and any damaged
sheeting shall be replaced at the contractor’s expense. The separation membrane
may be nailed to the lower layer with concrete nails.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 20 OF 35
held to the minimum necessary for conveying concrete by this method. When
concrete is to be pumped, the concrete mix shall be specially designed to suit
pumping. Care shall be taken to avoid stoppages in work once pumping has
started. While concrete is still plastic, its surface shall be textured by brush or
tines. Surface and edges of slab shall be cured by liquid curing membrane.
Before resuming concreting on a surface which has hardened all laitance and
loose stone shall be thoroughly removed by wire brushing/hacking and surface
washed with high pressure water jet and treated with thin layer of cement slurry
for vertical joints and a 15 mm thick layer of cement sand mortar for horizontal
layers, the ratio of cement and sand being the same as in the concrete mix.
When concreting is to be resumed on a surface which has not fully hardened, all
laitance shall be removed by wire brushing, the surface wetted, free water
removed and a coat of cement slurry applied. On this a layer of concrete not
exceeding 150 mm thickness shall be placed and well rammed against the old
work. Thereafter work shall proceed in the normal way.
8.0 REINFORCEMENT
Reinforcing bars supplied bent or in coils shall be straightened cold without
damage without any extra cost. No bending shall be done when ambient
temperature is below 5°C. Local warming may be permitted if steel is kept below
10°C.
All bars shall be accurately bent gradually and according to the sizes and shapes
shown on the drawings/ schedules or as directed by ENGINEER.
Re-bending or straightening incorrectly bent bars shall not be done without
approval of ENGINEER.
Reinforcement shall be accurately fixed and maintained firmly in the correct
position by the use of blocks, spacers, chairs, binding wire, etc. to prevent
displacement during placing and compaction of concrete. The tied in place
reinforcement shall be approved by ENGINEER prior to concrete placement.
Spacers shall be of such materials and designs as will be durable, not lead to
corrosion of the reinforcement and not cause spalling of the concrete cover.
Binding wire shall be 16 gauge soft annealed wires. Ends of the binding wire shall
be bent away from the concrete surface and in no case encroach into the
concrete cover.
Substitution of reinforcement, laps/splices not shown on drawing shall be subject
to ENGINEER’s approval.
9.0 CURING
Immediately after the surface texturing, the surface and sides of the slab shall be
cured by the application of approved resin-based aluminized reflective curing
compound which hardens into an impervious film or membrane with the help of a
mechanical sprayer.
Curing compounds shall contain sufficient flake aluminum in finely divided
dispersion to produce a complete coverage of the sprayed surface with a metallic
finish. The compound shall become stable and impervious to evaporation of water
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 21 OF 35
from the surface of the concrete within 60 minutes of application and shall be of
approved type.
The curing compound shall not react chemically with the concrete and the film or
membrane shall not crack, peel or disintegrate within three weeks after
application. Immediately prior to use, the curing compound shall be thoroughly
agitated in its containers. The rate of spread shall be in accordance with the
manufacturer’s instructions checked during the construction of the trail length and
subsequently whenever required by the engineer. The mechanical sprayer shall
incorporate an effective mechanical device for continuous agitation and mixing of
the compound during spraying.
In addition to the spraying of curing compound, the fresh concrete surface shall be
protected for at least 3 hours by covering the finished concrete pavement with
tents. After three hours, the pavement shall be covered by moist hessian and the
same shall then be kept damp for a minimum period of 14 days after which time
hessian may be removed. The hessian shall be kept continuously moist.
Curing and protection shall start immediately after the compaction of the concrete
to protect it from:
i. Premature drying out, particularly by solar radiation and wind.
ii. Leaching out by rain and flowing water.
iii. Rapid cooling during the first few days after placing.
iv. High internal thermal gradients.
v. Low temperature or frost.
vi. Vibration and impact which may disrupt the concrete and interfere with its
bond to the reinforcement.
All concrete, unless directed otherwise by ENGINEER, shall be cured by use of
continuous sprays or ponded water or continuously saturated coverings of
sacking, canvas, hessian or other absorbent material for the period of complete
hydration with a minimum of 7 days. The quality of curing water shall be the same
as that used for mixing.
Where a curing membrane is directed to be used by the ENGINEER, the same
shall be of a non-wax base and shall not impair the concrete finish in any manner.
The curing compound to be used shall be got approved from the ENGINEER
before use and shall be applied with spraying equipment capable of a smooth,
even textured coat.
Curing may also be done by covering the surface with an impermeable material
such as polyethylene, which shall be well sealed and fastened.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 22 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 23 OF 35
Tie bars shall be provided at the longitudinal joints as per dimensions and spacing
shown in the drawing.
10.6 DOWEL BARS
Dowel bars shall be mild steel rounds in accordance with details/dimensions as
indicated in the drawing and free from oil, dirt, loose rust or scale. They shall be
straight, free of irregularities and burring restricting slippage in the concrete. The
sliding ends shall be sawn or cropped cleanly with no protrusions outside the
normal diameter of the bar. The dowel bar shall be supported on cradles/ dowel
chairs in pre-fabricated joint assemblies positioned prior to the construction of the
slabs or mechanically inserted with vibration into the plastic concrete by a method
which ensures correct placement of the bars besides full re-compaction of the
concrete around the dowel bars.
Dowel bars shall be positioned at mid-depth of the slab ±20mm and centred
equally about intended lines of joint ±25mm aligned parallel to the carriageway.
The position should be within these tolerances under 110N force applied in
vertical and horizontal direction within following tolerances.
Bars supported on cradles before laying of the slab:
All bars in a joint shall be within ±2mm per 300mm length of bar
2/3rd the number of bars shall be within ±3mm per 500mm length of bar
No bar shall differ in alignment from adjoining bar by more than 3mm per
300mm length of bar in either horizontal or vertical planr
Cradles shall not extend across the line of joint
For bars inserted after laying of slab except when inserted by dowel bar inserter,
the above tolerances may be twice those indicated above.
Dowel bars shall be covered with 0.5mm thick plastic sheath for 2/3rd length in
contraction/ construction joints and 50% of length + 50mm got expansion joints.
The rigidity of fixing of dowel bars in expansion joints shall be as follows:
The deflection of the top edge of the filler board shall not be greater than
13mm under load of 1.3kN applied perpendicular to face of joint filler board
and distributed over a length of 600mm, at mid depth and midway between
individual fixings or 300mm from either end of continuous filler board. Residual
deflection after removal of load shall not be more than ±3mm.
The fixings for joint assembly shall not fail under 1.3kN load. Fixings shall be
deemed to fail when there is displacement of assemblies by more than 3mm
when the load reaches 2.6kN.
For expansion joints, a closely fitting PVC or GI cap 100mm long shall be placed
over the sheathed end of each dowel bar. Expansion space equal to the thickness
of joint filler board (usually 25mm) shall be formed between end of cap and dowel
bar by using compressible sponge. The mouth of sheathing and dowel bar shall
be taped.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 24 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 25 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 26 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 27 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 28 OF 35
Provided, however, that the negative tolerance for wearing course shall not be
permitted in conjunction with the positive tolerance for base course if the thickness
of the former is thereby reduced by more than 5 mm for concrete pavement.
For subgrade and sub-base, the measurements of the surface levels shall be
taken on a grid of points placed at 6.25m longitudinally and 3.5m transversely. For
any 10 consecutive measurements taken longitudinally or transversely, not more
than one measurement shall be permitted to exceed the tolerance above; this one
measurement being not in excess of 5mm beyond the permitted tolerance.
For concrete pavements, the measurements of the surface levels shall be taken
on a grid of points placed at 6.25m along the length and at 0.5m from the edges
and centre of the pavement. For the final road surface the above compliance shall
be satisfied for all points on any length of pavement.
12.4.3 SURFACE REGULARITY
The surface regularity of completed subgrade, sub-base course, base course and
wearing course in the longitudinal and transverse directions shall be within the
tolerances indicated in Table 7.
The longitudinal profile shall be checked with a 3 metre long straight edge, at the
middle of each traffic lane along a line parallel to the centre line of the road. The
transverse profile shall be checked with a set of three camber boards at intervals
of 10 metres.
Table 9
Maximum Permitted number of Surface Irregularities
Surfaces of carriageways Surfaces of lay-bys,
and paved shoulders service areas and all
bituminous base courses
Irregularity 4 mm 7 mm 4 mm 7 mm
Length (m) 300 75 300 75 300 75 300 75
National Highways/ 15 9 2 1 40 18 4 2
Expressways (*)
Roads of lower 40 18 4 2 60 27 6 3
category (*)
(*) Category of road shall described in the project contract
The maximum allowable difference between the road surface and underside of a
3m straight edge when placed parallel with or at right angles to centre line of the
road at points decided by the Engineer shall be:
For concrete pavement surface 3mm
For dry lean concrete sub-base course 10mm
12.4.4 RECTIFICATION
Where the surface irregularity of subgrade and the various courses fall outside the
specified tolerances, the Contractor shall be liable to rectify these in the manner
described below and to the satisfaction of the Engineer.
i. Subgrade
Where the surface is high, it shall be trimmed and suitably compacted.
Where the same is low, the deficiency shall be corrected by adding fresh
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 29 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 30 OF 35
b) Compaction control
Control shall be exercised by taking at least one set of ten measurement of
density for each 3000 square metres of compacted area, or closer as
required to yield the minimum number of test results for evaluation of a
day’s work on statistical basis. The determination of density shall be in
accordance with IS 2720 (Part 28). Tests locations shall be chosen only
through random sampling techniques. Control shall not be based on the
result of any one test but on the mean value of a set of 5-10 density
determinations. The number of tests in one set of measurements shall be
doubled for non-destructive tests as long as it is felt that sufficient control
over borrow material and the method of compaction is being exercised. If
considerable variations are observed between individual density results,
the minimum number of tests in one set of measurement shall be
increased. The acceptance of work shall be subject to the condition that
the mean dry density equals or exceeds the specified density plus
[1.65 – 1.65/(No of samples)0.5]*standard deviation.
However, for earthwork in shoulders (earthen) and in the subgrade, at least one
set of ten density measurement shall be taken for every 2000 square metres of
the compacted area. In other respects, the control shall be similar to that
described earlier.
12.5.3 DRY LEAN CONCRETE SUB-BASE
Testing of cubes
Samples for making cubes shall be taken at the rate of 3 samples for each 100
sqm or part laid each day. Test cubes shall be prepared in accordance with
IS:516 except that cubes shall be compacted in moulds by electric or pneumatic
vibratory hammer having area between 7500 to 14000 N/sq.mm Compression
force of 300N to 400N shall be uniformly applied for 60±5 seconds on each of
three layers of the material.
In-situ Density
This shall be measured in three density holes spaced equally on a diagonal that
bisects each 2000 sqm or part laid each day and at random at the edges.
Minimum dry density obtained shall be 97% of that achieved during trial and 95%
at 0.5m from edge.
Thickness
Average thickness of sub-base layer shall be computed by level data of the sub-
grade and sub-base. Thickness at any location shall not be less than 8mm less
than specified thickness.
Frequency of control tests
The frequency of testing is defined in Tables 8 and 9.
12.5.4 PAVEMENT CONCRETE
Testing of beams and cubes
At least two beams and two cubes, one each for 7 day and 28 day strength testing
shall be cast for every 150 cum (or part) of concrete pavement. On each day’s
work, not less than three pairs of beams and cubes shall be made for each type of
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 31 OF 35
mix. Where quality requirements are not satisfied by the sample testing, actual
strength shall be ascertained by tests on 150mm diameter cores cut at the rate of
2 cores every 150 cum of concrete. The average results of crushing strength on
the 2-3 cores shall not be 0.8x0.85 times the characteristic compressive strength
for core height to diameter ratio of two. Correction factor for core height to
diameter ratio n = 1 to 2 is given by
f = 0.11*n + 0.78
An individual strength below specified strength may be disregarded if the average
28 day strength of the failed beam plus the preceding 5 and succeeding 4 beams
exceeds the specified strength by 1.65 time standard deviation.
The equivalent flexural strength shall be estimated from in-situ strength multiplied
by 100 and divided by age-strength relation from Table 10.
Table 10
Age Strength relation of Concrete (related to 100% at 28 days)
Days 0 2 4 6 8
0 - 41.0 60.0 71.0 77.5
10 81.5 85.0 87.5 90.0 92.0
20 94.0 96.0 97.5 98.5 100.0
30 101.0 102.0 103.5 104.5 105.5
40 106.5 107.0 108.0 109.5 110.0
50 110.5 111.0 112.0 112.5 113.0
60 114.0 114.5 115.0 115.5 116.0
70 116.5 117.0 117.5 118.0 118.5
80 119.0 119.5 119.5 120.0 120.5
90 121.0 121.5 122.0 122.0 122.5
100 123.5 123.5 123.5 124.0 124.5
110 125.0 125.0 125.5 125.5 126.0
120 126.0 126.0 127.0 127.0 127.5
130 127.5 128.0 128.5 128.5 129.0
140 129.0 129.5 129.5 130.0 130.0
150 130.5 130.5 131.0 131.0 131.5
160 131.5 131.5 132.0 132.0 132.5
170 132.5 132.5 133.0 133.0 133.5
180 133.5 134.0 134.0 134.5 134.5
190 135.0 135.0 135.0 135.5 135.5
200 135.5 135.5 136.0 136.0 136.5
210 136.5 136.5 137.0 137.0 137.0
220 137.0 137.5 137.5 137.5 138.0
230 138.0 138.5 138.5 138.5 138.5
240 139.0 139.0 139.0 139.5 139.5
250 139.5 140.0 140.0 140.0 140.0
260 140.5 140.5 140.5 140.5 141.0
270 141.0 141.0 141.5 141.5 141.5
280 142.0 142.0 142.0 142.0 142.0
290 142.5 142.5 142.5 142.2 142.5
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 32 OF 35
Table 11
Control Tests and Their Frequencies Paving Quality Concrete
Levels, Alignment and texture
Test Frequency
i. Level tolerance Refer section 13.2.2
ii. Width of pavement and position of Refer section 13.2.1
edges
iii. Pavement thickness Refer section 13.2.2 and 13.3.4
iv. Alignment of joints, widths, depths To be checked at one joint per 400m
of dowel grooves length or a day’s work
v. Surface regularity – transverse and Once a day or one day’s work
longitudinal
vi. Alignment of dowel/ tie bars In trial length as per section 6.3.2 and
once every 2 km
vii. Texture depth Refer section 12.0
Table 12
Control Tests and Their Frequencies Paving Quality Concrete
Quality of Material and Concrete
Sl. Types of Test Frequency
No. Construction
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 33 OF 35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 34 OF 35
Upon the completion of concrete work, all forms, equipment, construction tools,
protective coverings and any debris, scraps of wood, etc. resulting from the work
shall be removed and the premises left clean.
12.6 ACCEPTANCE CRITERIA:
Any concrete work shall satisfy the requirements given below individually and
collectively for it to be acceptable.
i. Properties of constituent materials;
ii. Characteristic compressive strength;
iii. Specified mix proportions;
iv. Minimum cement content;
v. Maximum free-water/cement ratio;
vi. Workability;
vii. Temperature of fresh concrete;
viii. Density of fully compacted concrete;
ix. Cover to embedded steel;
x. Curing;
xi. Tolerances in dimensions;
xii. Tolerances in levels;
xiii. Durability;
xiv. Surface finishes;
xv. Special requirements such as :
xvi. Water tightness
xvii. Resistance to aggressive chemicals
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-02
SPECIFICATION FOR CONCRETE ROADS SHEET 35 OF 35
END
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE.
R1
FILE NAME: M4-422-02-R1 TCE FORM NO. 329 R6
TATA CONSULTING ENGINEERS LIMITED SECTION:WRITEUP
TCE.M4-422-01
SPECIFICATION FOR PLANT ROADS SHEET 1 OF 45
1.0 SCOPE
This specification covers the general requirements for the materials and
construction of soling, water bound macadam course and bituminous surface
treatment of plant roads.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
4.0 MATERIALS
4.1 GENERAL
All materials shall be obtained from local sources and shall be subject to
Engineer's approval prior to use.
4.2 SOLING STONE
It shall be clean, sound, dense, hard tough, durable stone of uniform quality free
from unsound material, cracks, decay and weathering. Water absorption shall not
be more than 5 percent. The stone shall be in the smallest dimension equal to
thickness of the soling course specified with a tolerance of 25 mm. Soling stone
shall be sufficiently flat bedded. The height of the soling stone shall be equal to
the specified thickness of soling. The length and breadth shall not exceed twice
the specified thickness.
4.3 STONE AGGREGATE/METAL
Coarse aggregate and screenings shall consist of natural or crushed stone, clean,
hard, tough, durable and free from excess of flat, elongated, soft and disintegrated
particles, dirt, salt, alkali, vegetable matter, adherent coatings, organic and other
objectionable matter, and shall conform to the physical requirements given in
Tables 1 or 2 hereunder, as applicable. Aggregate for bituminous wearing courses
shall in addition have good hydrophobic properties i.e. capacity of retaining the
film of bituminous material applied to the stone in all weather conditions and
especially in wet conditions. Basalt and dolerite are good in this respect; granite
and quartzite are comparatively poor.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Sand used for blinding the bituminous road surface, shall be coarse, sharp, gritty,
clean, granular material. Only material passing through 4.75 mm sieve and
retained on 75 micron sieve shall be used.
4.9 AGGREGATES FOR WET MIX MACADAM
Coarse aggregates shall be crushed stone. If crushed gravel/ shingle is used, not
less than 90% by weight of the gravel shingle pieces retained on 4.75mm sieve
shall have at least two fractured faces. Aggregates shall conform to physical
requirements in Table 1 and grading requirements given in Table 11.
4.10 BITUMINOUS MATERIALS
Bituminous materials shall conform to IS 73, IS 215, IS 217 or IS 454 as
applicable and be of the grade specified in this specification.
Table 1
Physical Requirements of Coarse Aggregate for Water Bound Macadam &
Wet Mix Macadam (Sub Base / Base Course)
Sl.No. Test Requirements Test Method
1. Los Angles Abrasion Value* 40% (max.) IS 2386 (Part-4)
OR
Aggregate Impact Value* 30% (max.) IS 2386 (Part-4)
OR
IS 5640 ***
2. Combined Flakiness and 35% (max.) IS 2386 (Part-1)
Elongation Indices**
(*) Aggregate may satisfy requirements of either of two tests.
(**) Requirements of flakiness index shall be enforced only in case of crushed/ broken
stone.
(***) Aggregates like brick metal, kankar, laterite etc. which get softened in presence of
water shall be tested for Impact Value under wet conditions in accordance with
IS:5640.
Table 2
Physical Requirements of Aggregate for Granular Sub-Base
Property Test Requirements Test Method
Aggregate 40 maximum IS 2386 (Part 4)
Impact Value of IS 5640
(AIV)
Liquid Limit Maximum 25 IS 2720 (Part 5)
Plasticity Maximum 6 IS 2720 (Part 5)
Index
CBR at 98% Minimum 30 IS 2720 (Part
dry density 31)
(*) Sample tested in soaked condition.
(**) Test to be carried out only if water absorption exceeds 2%.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 3
Requirement of slag (Sub Base / Base Course)
Sl.No. Test Requirements Test Method
1. Chemical stability Comply BS 1047 BS 1047
2. Sulphur content 2% (max.)
3. Water absorption 10% (max.)
Table 4
Physical Requirements Of Aggregates for Bituminous Macadam
Property Test Requirements Test Method
Cleanliness Grain size analysis 5% passing 0.075mm IS 2386 (Part-1)
sieve (max.)
Particle shape Flakiness and 35% (max.) IS 2386 (Part-1)
Elongation Index (combined)
Strength (*) Los Angles Abrasion 40% (max.) IS 2386 (Part-4)
Value OR
Aggregate Impact 30% (max.) IS 2386 (Part-4)
Value
Durability Soundness (Sodium or Magnesium, 5 cycles)
Sodium sulphate 12% (max.) IS 2386 (Part-5)
Magnesium sulphate 18% (max.) IS 2386 (Part-5)
Water Water absorption 2% (max.) IS 2386 (Part-3)
absorption
Stripping Coating and stripping Minimum retained IS 6241
of Bitumen Aggregate coating 95%
mixtures
Water Retained Tensile 80% (min.) AASHTO T283
sensitivity (**) Strength
(*) Aggregate may satisfy requirements of either of two tests.
(**) This test is to be carried out only if the minimum retained coating in stripping test
is less than 95%. Use anti stripping agent if retained tensile strength falls below
80%.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 5
Physical Requirements Of Aggregates for
Dense Graded Bituminous Macadam
Property Test Requirements Test Method
Cleanliness Grain size analysis 5% passing 0.075mm IS 2386 (Part-1)
(dust) sieve (max.)
Particle shape Flakiness and 35% (max.) IS 2386 (Part-1)
Elongation Index (combined)
Strength (*) Los Angles Abrasion 35% (max.) IS 2386 (Part-4)
Value OR
Aggregate Impact 27% (max.) IS 2386 (Part-4)
Value
Durability Soundness
Sodium sulphate 12% (max.) IS 2386 (Part-5)
Magnesium sulphate 18% (max.) IS 2386 (Part-5)
Water Water absorption 2% (max.) IS 2386 (Part-3)
absorption
Stripping Coating and stripping Minimum retained IS 6241
of Bitumen Aggregate coating 95%
mixtures
Water Retained Tensile 80% (min.) AASHTO T283
sensitivity (**) Strength
(*) Aggregate may satisfy requirements of either of two tests.
(**) This test is to be carried out only if the minimum retained coating in stripping test
is less than 95%. Use anti stripping agent if retained tensile strength falls below 80%.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 6
Physical Requirements Of Aggregates for Bituminous Concrete
Property Test Requirements Test Method
Cleanliness Grain size analysis 5% passing 0.075mm IS 2386 (Part-1)
(dust) sieve (max.)
Particle shape Flakiness and 35% (max.) IS 2386 (Part-1)
Elongation Index (combined)
Strength (*) Los Angles Abrasion 30% (max.) IS 2386 (Part-4)
Value OR
Aggregate Impact 24% (max.) IS 2386 (Part-4)
Value
Polishing Polished stone value 55 (min.) BS 812 (Part
114)
Durability Soundness
Sodium sulphate 12% (max.) IS 2386 (Part-5)
Magnesium sulphate 18% (max.) IS 2386 (Part-5)
Water Water absorption 2% (max.) IS 2386 (Part-3)
absorption
Stripping Coating and stripping Minimum retained IS 6241
of Bitumen Aggregate coating 95%
mixtures
Water Retained Tensile 80% (min.) AASHTO T283
sensitivity (**) Strength
(*) Aggregate may satisfy requirements of either of two tests.
(**) This test is to be carried out only if the minimum retained coating in stripping test
is less than 95%. Use anti stripping agent if retained tensile strength falls below 80%.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 7
Grading for Close Graded Granular Sub-base materials
IS sieve designation Percent by weight passing IS sieve
Grading I Grading II Grading V Grading VI
75.0 mm 100 - 100 -
53.0 mm 80-100 100 80-100 100
26.5 mm 55-90 70-100 55-90 75-100
9.50 mm 35-65 50-80 35-65 55-75
4.75 mm 25-55 40-65 25-50 30-55
2.36 mm 20-40 30-50 10-20 10-25
0.85 mm - - 2-10 -
0.425mm 10-15 10-15 0-5 0-8
0.075mm <5 <5 - 0-3
CBR value (min.) 30 30 30 30
Table 8
Grading for Coarse Graded Granular Sub-base materials
IS sieve designation Percent by weight passing IS sieve
Grading III Grading IV
75.0 mm - -
53.0 mm 100 100
26.5 mm 55-75 50-80
9.50 mm - -
4.75 mm 10-30 15-35
2.36 mm - -
0.85 mm - -
0.425mm - -
0.075mm <5 <5
CBR value (min.) 30 30
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 9
Grading Requirements of Coarse Aggregates for Water Bound Macadam
Grading No. Size Range IS Sieve Percent by
Designation Weight Passing
the Sieve
1. 63 mm to 45 mm 75 mm 100
63 mm 90-100
53 mm 25-75
45 mm 0-15
22.4 mm 0-5
2. 53 mm to 22.4 mm 63 mm 100
53 mm 95-100
45 mm 65-90
22.4 mm 0-10
11.2 mm 0-5
Compacted thcikness for a layer shall be 75mm.
Table 10
Gradings for Screenings
Grading Size of IS Sieve Percent by Weight
Classification Screenings Designation Passing the Sieve
A 13.2 mm 13.2 mm 100
11.2 mm 95-100
5.6 mm 15-35
180 micron 0-10
B 11.2 mm 11.2 mm 100
9.5 mm 80-100
5.6 mm 50-70
180 micron 5-25
The use of screening shall be omitted in the case of soft aggregates such as brick
metal, kankar, laterites etc. as they are likely to get crushed to a certain extent
under rollers.
Table 11
Grading Requirements of Coarse Aggregates for Wet Mix Macadam
IS Sieve Designation Percent by Weight Passing the Sieve
53 mm 100
45 mm 95 – 100
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
5.0 EARTHWORK
5.1 EARTHWORK IN EXCAVATION
In general the excavation shall be in accordance with TCE specification
No.TCE.M4-418-01.
Profiles of road excavation shall be laid at 50 m intervals to conform to the
required alignment, sections, grades and side slopes and the lines of cuts shall be
clearly marked.
CONTRACTOR shall not excavate beyond the slopes or below the specified
grade unless so directed by the ENGINEER in writing. If excavation is done below
the specified level or outside the section it shall not be paid for and the
CONTRACTOR shall be required to fill up at his own cost such extra excavation
with approved materials, in layers of 150 to 200 mm, watered and compacted as
specified for the subgrade.
The excavation shall be finished neatly, smoothly and evenly to the correct lines,
grades, sections and side slopes as shown in the drawings or directed by
ENGINEER.
5.2 EARTHWORK IN EMBANKMENT
The embankment shall be formed of earth obtained from approved source/ borrow
areas.
The ground over which embankment is to be formed shall be cleared of all
brushwood, loose stones, vegetation, bushes, stumps, and all other objectionable
matter and materials. Such removed material shall be burnt off or disposed off as
directed by ENGINEER. The cost of this clearing, burning and disposal shall be
included in the unit rates quoted for embankment construction.
Profiles of embankment shall be set up with stout poles to mark the centre and
edges of the formation with the top levels of formation clearly marked by paint or
cut and the slopes with strings and pegs at every 10 metres on straight portions.
Toe line may be marked with pick marks.
Before placing any embankment material the top 150 mm of soil strata receiving it
shall be scarified and watered and compacted with 8-10 tonnes roller so as to
achieve minimum dry density of 95% as per IS 2720 (Part 8).
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 12
Density requirement of Embankment and Subgrade materials
Sl. Type of Work Max. Dry Unit Weight tested
No. as per IS 2720 (Part 8)
1. Embankment up to 3m height not Not less than 15.2 kN/cum
subjected to excessive flooding
2. Embankment exceeding 3m height or Not less than 16.0 kN/cum
any height subjected to long periods of
inundation
3. Subgrade and earthen shoulders/ Not less than 17.5 kN/cum
verges/ backfill
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 13
Compaction requirement of Embankment and Subgrade
Sl. Type of Work/ Material Relative compaction as %ge
No. of max laboratory dry density
as per IS 2720 (Part 8)
1. Subgrade and earthen shoulders Not less than 97%
2. Embankment Not less than 95%
3. Expansive clays
a) Subgrade and 500mm portion below Not allowed
b) Remaining portion of embankment 90% to 95%
5.2.1 MEASUREMENT
Earth embankment/ subgrade construction shall be measured separately by
taking cross sections at intervals before and after work and computing volume of
earthwork in cum by method of average and areas. The measurement of fill
materials from borrow areas shall be the difference between the net quantities of
compacted fill and the net quantities brought from road/ drain excavation. It shall
be assumed that one cum of material brought from excavation is equivalent to one
cum of compacted fill and bulking/ shrinkage shall be ignored. In case the
embankment/ subgrade construction is carried out using earth from stacks
excavated earlier, the volume of stacked material shall be reduced by 30% to
account for voids in the loose fill.
7.0 SOLING
Soling shall not be constructed on a wet subgrade.
Unless otherwise specified, the width of the soling shall be 230 mm more on either
side than that of the waterbound macadam course and the finished thickness of
the soling course shall be 230 mm.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The soling stones shall be laid with the largest face downwards and in contact
with each other. The stones shall be placed to break joints as far as possible. The
height of the soling stone shall be equal to specified thickness of soling.
As the laying of rubble advances the soling shall be hand packed by wedging and
packing with 80 mm metal in the joints of the soling and driving them by hammers
in place so as to fill the voids as completely as possible. This operation of hand
packing shall closely follow the rubble laying. The soling shall be laid and hand
packed true to grade and section and these shall be often checked by boning
rods, template boards and fish line etc. The grades, sections etc. of the soling
shall correspond to those of the surfacing coming on it. The soling thus laid shall
be finished by knocking out projecting stones and filling depressions by chips to
come up to the grade and camber.
The quality of the 80 mm metal shall be same as specified for the soling and the
longest dimension shall not be more than 100 mm and the shortest dimension not
less than 50 mm.
The soling after it is properly laid and hand packed including filling of voids with 80
mm metal shall be rolled dry with 10 - 12T power roller to refusal i.e. till the stones
in the soling course cease to move under the roller and no more compaction can
be achieved. Rolling shall start at the edges and work towards the centre. The
roller shall run over the same surface of rolling for at least 8 times till the soling
course is well consolidated. The surface shall be checked by templates and in
case of unevenness high spots shall be knocked out and depressions filled by
spalls and re-compacted fully. Bunds shall be laid along the edges and
compacted before starting rolling on soling to prevent spreading of stones.
Gravel shall be spread in thin layers over the above prepared soling surface,
swept into the interstices with brooms, watered lightly to assist the filling of voids.
Spreading of gravel, sweeping and watering shall continue till the interstices are
completely filled. Only enough water shall be sprinkled to force the gravel into the
voids at all times and never so much as to soften the subgrade. The process of
gravel filling shall be accompanied by dry rolling of soling with a power roller
weighing not less than 10 tonnes starting at edge and working towards the centre.
The roller shall run over the same surface for at least eight times. Each pass of
the roller shall uniformly overlap not less than one third of the track made in the
preceding pass. The surface shall be checked with templates of approved design
(to be provided by Contractor) and high and low spots corrected by removing
soling and repacking.
7.1 MEASUREMENT
Measurements shall be made for the finished work in square metres of the actual
plan area covered with the soling stone. The rate shall cover carrying out works as
specified in Clauses 6.0 and 7.1 to 7.7 above and include the cost of all materials,
labour, plant and equipment involved in the works.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
and grade. The paver finisher shall be self-propelled having loading hoppers with
distribution mechanism, tamping and vibrating arrangement for initial compaction
to the layer as it is spread without rutting or marring the profile and control
mechanism to ensure that the finished surface is free from blemishes.
The surface of aggregates shall be carefully checked with templates and all high
or low spots remedied by removing or adding aggregate. The layer may be tested
by depth blocks during construction. No segregation of larger and fine particles
should be allowed. The aggregates as spread should be of uniform gradation with
no pockets of fine materials.
10.3 COMPACTION
After the mix has been laid to the required thickness, grade and camber, this shall
be uniformly compacted to full depth with suitable roller. If the thickness of single
compacted layer does not exceed 100mm, a smooth wheeled roller of 80 to 100
kN weight may be used. For compacted single layer up to 200mm, the compaction
shall be done with vibratory roller of 80 to 100 kN static weight. The speed of roller
shall not exceed 5 km per hour.
In portions having unidirectional camber/ super-elevation, rolling shall commence
from the lower edge and progress gradually towards the upper edge. Thereafter,
roller should progress parallel to the centreline of the road, uniformly over-lapping
each preceding track by at least one-third width until the entire surface has been
rolled. Alternate trips of the roller shall be terminated in stops at least 1m away
from any preceding stop.
In portion having camber, rolling should begin at the edge with the roller running
forward and backward until the edges have been firmly compacted. The roller
shall then progress gradually towards the centre parallel to the centre line of the
road uniformly overlapping each of the preceding tracks by at least one-third width
until the entire surface has been rolled.
Any displacement occurring as a result of reversing of the direction of a roller or
from any other cause shall be corrected at once and made good to the
satisfaction of the Engineer.
Along forms, kerbs, walls or other places not accessible to the roller, the mixture
shall be thoroughly compacted with mechanical tampers or a plate compactor.
Skin patching of an area without scarifying the surface to permit proper bonding of
the added material shall not be permitted.
Rolling should not be done when the subgrade is soft or yielding or when it
causes a wave like motion in the sub-base/ base course or subgrade. If
irregularities develop during rolling which exceed 12mm when tested with a 3
metre straight edge, the surface should be loosened and premixed material added
to achieve a uniform surface conforming to the desired grade and camber. In no
case should the use of unmixed material be permitted to make up the
depressions.
Rolling shall be continued till the density achieved is at least 98% of the maximum
dry density for the material as determined according to IS 2720 (Part-8).
After completion, the surface of any finished layer shall be well-closed, free from
movement under compaction equipment or any compaction planes, ridges, cracks
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
and loose material. All loose, segregated or otherwise defective areas shall be
made good to the full thickness of the layer and re-compacted.
10.4 SETTING AND DRYING
After the final compaction of the wet mix macadam course, the same shall be
allowed to dry for 24 hours.
10.5 RECTIFICATION OF SURFACE IRREGULARITY
Where the surface irregularity exceeds acceptable tolerance limits or the course is
defective due to subgrade soil getting mixed with the aggregates, the full
thickness of the layer shall be scarified over the affected area, reshaped with
added premixed material or removed and replaced with fresh premixed material
and re-compacted. The area treated shall not be less than 5 metre long and 2
metre wide. In no case shall depressions be filled up with unmixed or ungraded
material or fines.
10.6 MEASUREMENTS AND RATES
The measurements shall be made for the finished work in position in cubic metres.
The rates shall cover carrying out works as specified above and include the cost
of all materials, labour, plant and equipment involved in the works.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
be coarse aggregate salvaged from the scarification of the existing granular base
course supplemented by fresh aggregate and screenings. Profile corrective
course for correcting existing pavement profile shall be laid in accordance with
drawings as required. The type of material for profile correcting course shall be of
same specification as that of the overlay/ strengthening course. Where the profile
corrective course of bituminous material is to be laid over existing granular
surface, the latter shall be primed with bitumen emulsion complying with IS 8887.
The surface finish of all granular layers on which bituminous works are to be
placed be free from dust, capable of being swept by mechanical broom after
removal of non-integral loose material and without shedding significant quantities
of material and dust removed by air jet or washing.
Where existing bituminous layer is to be removed to specified width, it shall be
without undue disturbance to the underlying layer after removal of loose material,
the underlying layer shall be suitably reworked and compacted to line and level.
After supplementing the base material with suitable fresh stone, the compacted
finished surface shall be primed with bitumen emulsion complying with IS 8887.
11.3 TACK COAT
This comprises of application of a single coat of low viscosity liquid bituminous
material. The binder shall be bitumen emulsion complying with IS 8887.
Bituminous material shall not be applied to wet surface or during a dust storm or
when the weather is foggy, rainy or windy or when shade temperature is less than
10OC. The tack coat distributor shall be a self-propelled or towed bitumen
pressure sprayer, equipped for spraying the material uniformly. Hand held
pressure sprayer shall be used for inaccessible areas or in narrow strips. Rate of
application of tack coat shall be as follows:
Table 15
Rate of Application of Tack Coat
Sl. Type of Surface Quantity of liquid bitumen
No. in kg/sqm
i) Bituminous surfaces 0.20 to 0.30
ii) Granular surfaces treated with primer 0.25 to 0.30
iii) Cement concrete pavement 0.30 to 0.35
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 16
Manufacturing and Rolling Temperatures
Bitumen Bitumen Aggergate Mixed Laying Rolling*
Viscosity Mixing (oC) Mixing (oC) Material (oC) (oC) (oC)
Grade
VG-40 160-170 160-175 160-170 150 min. 100 min.
VG-30 150-165 150-170 150-165 140 min. 90 min.
VG-20 145-165 145-170 145-165 135 min. 85 min.
VG-10 140-160 140-165 140-160 130 min. 80 min.
(*) Rolling must be completed before the mat cools down to these minimum
temperatures
Bituminous materials shall be discharged from the mixer and transported to the
point of use in suitable clean insulated and covered tippler vehicles. Thin coating
of diesel or lubricating oil may be applied to the interior of the vehicle to prevent
sticking and facilitate discharge of material with approval of Engineer.
The surface shall be cleaned of all loose and extraneous matter by means of a
mechanical broom or other approved equipment/ method. The dust and loose
matter shall be removed by use of high pressure air jet.
The hot mix shall be spread by means of a self-propelled mechanical paver with
suitable screeds capable of spreading, tamping and finishing the mix to specified
lines and levels to a thickness sufficient to achieve, after rolling, the specified
thickness. The travel rate of the paver and its method of operations shall be
adjusted to ensure an even and uniform flow of material across the screed, free
from dragging, tearing and segregation of material. Temperature of the mix at the
time of laying shall be in the range given in Table 16. In restricted locations and in
narrow widths where available equipment cannot be operated in the opinion of the
Engineer, he may permit manual laying of the mix using hand tools by
experienced staff.
Longitudinal joints and edges shall be constructed true to the delineating lines
parallel to the centre line of the road. Longitudinal joints shall be offset by at least
150 mm from those in the tack coat. All joints shall be cut vertical to the full
thickness of the previously laid mix and the surface painted with hot bitumen
before placing fresh material. When laying binder course or wearing course
approaching and expansion joint of a structure, machine laying shall stop 300mm
short of the joint and the remaining portion shall be laid manually.
Laying shall be suspended while free-standing water is present on the surface to
be covered, or during rain, fog and dust storms. After rain the surface shall be
blown off with high pressure air jet to remove excess moisture or left to dry before
laying. Laying of bituminous mixtures shall not be carried out when surface
temperature is less than 10oC or when wind speed exceeds 40km/ hour at 2m
height.
11.5 COMPACTION
Immediately after the spreading of mix it shall be thoroughly compacted by rolling
with a set of rollers moving at a speed not more than 5 km per hour. The initial or
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
break down rolling shall be with 8-10 tonnes dead weight smooth-wheeled rollers.
Intermediate rolling shall be done with 8 – 10 tonnes dead weight vibratory roller
or with a pneumatic tired roller of 12 – 15 tonnes weight having nine wheels and
tire pressure of at least 5.6kg/ sqcm. The finish rolling shall be done with 6 - 8
tonnes smooth wheeled tandem rollers.
Rolling shall be done in longitudinal direction with driven rolls nearest the paver.
The roller shall first compact material adjacent to joints and then work from the
lower to the upper side of the layer, overlapping on successive passes by a least
one-third of the width of the rear roll or, in case of pneumatic tired roller a
minimum nominal width of 300mm. Rolling of the longitudinal joints shall be done
immediately behind the paving operation. After this, rolling shall commence at the
edges and progress towards the centre longitudinally. On super-elevated and
unidirectional cambered portions rolling shall progress from the lower to the upper
edge parallel to the centre line of the pavement. Rolling shall continue till mix is
thoroughly compacted and all the roller marks have been removed from the
surface and there is no movement under the roller.
The joints and edges shall be rolled with 8 to 12 ton three wheeled roller. Any high
spots or depressions which become apparent shall be corrected by addition or
removal of mix material. The wheels of the roller shall be moistened with water
from spray to prevent the mix sticking to the wheels while rolling; moisture should
only be sufficient to prevent the mixture adhering to the wheels and water should
not stand on the partially compacted pavement.
11.6 PROTECTION OF THE LAYER
The bituminous macadam shall be covered with the next pavement course or
wearing course within maximum of forty eight hours. In case of delay by
contractor, it shall be covered with seal coat at no additional expense.
11.7 MEASUREMENT
Bituminous macadam shall be measured as finished work in cum or by weight in
metric tonnes where used as regulating course or in sqm at specified thickness as
indicated in the contract or specified in drawings.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
tested for stripping and if found to have poor affinity for bitumen shall be treated
with approved anti-stripping agents without additional payment. Where crushed
gravel is proposed as aggregate, not less than 90% by weight of the crushed
material retained on 4.75mm sieve shall have at least two fractured surfaces.
12.1.3 FINE AGGREGATES
The fine aggregates shall be the fraction passing 2.36 mm sieve and retained on
75 micron sieve consisting of crusher run screenings, natural sand or mixture of
both. These shall be clean, hard, durable, uncoated, dry and free form any
injurious, soft or flaky pieces and organic or deleterious substances. The fine
aggregate shall have a sand equivalent value of not less than 50 when tested in
accordance with the requirement of IS 2720 (Part 37).
12.1.4 FILLER
Filler shall consist of finely divided mineral matter such as rock dust (having a
Plasticity Index not greater than 4), hydrated lime or cement approved by the
Engineer and free from organic impurities. Grading limits of filler shall be as per
Table 18. When the coarse aggregate is gravel, 2% by weight of total aggregate
shall be OPC or hydrated lime and the percentage of fine aggregate reduced
accordingly. For limestone aggregate, cement/ lime is not required. Where the
aggregates fail to meet the requirement of water sensitivity test of Table 5,
hydrated lime at 2% by weight of total aggregate shall be added by the contractor
without additional cost.
12.1.5 AGGREGATE GRADING AND BINDER CONTENT
The combined aggregate grading shall fall within limits shown in Table 17. The
type and quantity of bitumen, and appropriate thickness, are also indicated for
each mixture type.
12.1.6 MIX DESIGN
The aggregates shall be proportioned and blended to produce a uniform mixture
complying with requirement of Table 17. The mix shall in addition meet the
requirements of Table 19. Binder content shall be optimized as described the
Asphalt Institute Manual AS-2 to achieve the requirements of mixture in table 15.
The contractor shall ensure that the job mix formula is based on true
representative sample of the materials actually to be used in the work. Permissible
variations in the actual mix from approved job mix formula are specified in Table
19.
Table 17
Composition of Dense graded Bituminous Macadam pavement layers
Mix designation Grading – 1 Grading – 2
Nominal aggregate size 37.5mm 26.5mm
Layer thickness 75 – 100mm 50 – 75mm
IS Sieve (mm) Cumulative % weight of total aggregate passing
45 100
37.5 95 – 100 100
26.5 63 – 93 90 – 100
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 18
Grading requirements for Mineral Filler
IS Sieve (mm) Cumulative % passing by weight of total aggregate
0.6 100
0.3 95 – 100
0.075 85 – 100
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 19
Requirements for Dense graded Bituminous Macadam
Properties Viscosity Modified bitumen Test Method
Grade Paving
Hot climate Cold climate
Bitumen
Compaction 75 blows on each face of the specimen
level
Minimum 9.0 12.0 10.0 AASHTO
stability (kN at T245
60OC)
Marshall flow 2–4 2.5 – 4 3.5 – 5 AASHTO
(mm) T245
Marshall 2–5 2.5 – 5 MS-2 & ASTM
Quotient D2041
(Stability/Flow)
% air voids 3–5
% Voids Filled 65 – 75
with Bitumen
(VFB)
Coating of 95% minimum IS 6241
aggregate
particle
Tensile 80% minimum AASHTO
strength ratio T283
% Voids in Minimum % Voids in Mineral Aggregate (VMA)
Mineral are set out in Table 20
Aggregate
(VMA)
Table 20
Minimum %voids in Mineral Aggregate (VMA)
(2)
Nominal Max. Min. VMA (%) related to Design Air Voids (%)
Particle Size (mm) (1)
3.0 4.0 5.0
26.5 11.0 12.0 13.0
37.5 10.0 11.0 12.0
(1) Nominal maximum particle size is one size larger than the first sieve to retain
more than 10%
(2) Interpolate VMA for intermediate values of VFB
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 21
Permissible variations from the Job Mix formula
Description Permissible variation
Aggregate passing 19mm or larger ± 8%
Aggregate passing 13.2mm, 9.5mm ± 7%
Aggregate passing 4.75mm ± 6%
Aggregate passing 2.36mm, 1.18mm, 0.6mm ± 5%
Aggregate passing 0.3mm, 0.15mm ± 4%
Aggregate passing 0.075mm ± 2%
Binder content ± 0.3%
Mixing temperature ± 10oC
The primer shall be applied by a self propelled or towed bitumen pressure sprayer
to spray uniformly at specified rates and temperatures. Hand spraying shall be
permitted by the Engineer for small areas inaccessible to the sprayer or in narrow
strips. The road surface shall be carefully swept clean of dust and loose particles
and surface shall be kept slightly moist till application of primer. The primed
surface shall be allowed to cure for at least 24 hours or till such time to allow all
volatiles to evaporate before any subsequent surface treatment is laid. Any
unabsorbed primer shall be blotted with an application of sand.
12.4 TACK COAT
The application of tack coat shall be carried out in similar manner as described in
section 11.3.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 23
Composition of Bituminous Concrete pavement layers
Mix designation Grading – 1 Grading – 2
Nominal aggregate size 19mm 13.2mm
Layer thickness 50 – 65mm 30 – 40mm
IS Sieve (mm) Cumulative % weight of total aggregate passing
45
37.5
26.5 100
19 90 – 100 100
13.2 59 – 79 90 – 100
9.5 52 – 72 70 – 88
4.75 35 – 55 53 – 71
2.36 28 – 44 42 – 58
1.18 20 – 34 34 – 48
0.6 15 – 27 26 – 38
0.3 10 – 20 18 – 28
0.15 5 – 13 12 – 20
0.075 2-8 4 – 10
Bitumen content, % by Min 5.2 (*) Min 5.4 (*)
weight of total mixture
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 24
Permissible Variations in Plant Mix from the Job Mix formulas
Description Permissible variation
Aggregate passing 19mm or larger ± 7%
Aggregate passing 13.2mm, 9.5mm ± 6%
Aggregate passing 4.75mm ± 5%
Aggregate passing 2.36mm, 1.18mm, 0.6mm ± 4%
Aggregate passing 0.3mm, 0.15mm ± 3%
Aggregate passing 0.075mm ± 1.5%
Binder content ± 0.3%
Mixing temperature ± 10oC
13.5 COMPACTION
The procedure for compaction and rolling of the mix placed shall be carried out in
similar manner as described in section 11.5. If required, laying trials shall be
carried out to further adjust the final laying process with approval of the Engineer.
13.6 MEASUREMENT
Bituminous concrete shall be measured as finished work in cum or by weight in
metric tonnes or in sqm at specified thickness as indicated in the contract or
specified in drawings.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 25
Aggregate Gradation for close-graded Premix carpet
IS Sieve (mm) Cumulative % weight of total aggregate passing
Type A Type B
13.2 - 100
11.2 100 88 – 100
5.6 52 – 88 31 – 52
2.8 14 – 38 5 – 25
0.090 0–5 0–5
Table 26
Quantities of materials required for 10 sqm of road surface for 20mm thick Open
graded Premix Surfacing using Penetration Bitumen or Cutback
Aggregates
a) Nominal stone size 13.2mm (passing 22.4mm 0.18 cum
sieve and retained on 11.2mm sieve)
b) Nominal stone size 11.2mm (passing 13.2mm 0.09 cum
sieve and retained on 5.6mm sieve)
Total 0.27 cum
Binder (quantities in terms of straight runs of bitumen)
a) For 0.18 cum of 13.2mm nominal size stone at 9.5 kg
52 kg bitumen per cum
b) For 0.09 cum of 11.2mm nominal size stone at 5.1 kg
56 kg bitumen per cum
Total 14.6 kg
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 27
Requirements of Asphaltic Concrete Mix
Sr.No. Description Requirements
1. Number of compaction blows, each end of Marshall 50
specimen
2. Marshall stability (ASTM Designation-D-1559) 340 kg (min.)
determined on Marshal specimen
3. Marshall flow (mm) 2-4
4. Percent voids in mix 3-5
5. Percent voids in mineral aggregate filled with 75-85
bitumen
6. Binder content percent by weight of mix 5-7.5
The contractor shall intimate to the Engineer in writing, well in advance of the start
of work, the job-mix-formula proposed to be used by him for the work and shall
give following details to the Engineer for his approval:-.
i. Source and location of all materials
ii. Proportions of all materials expressed as follows where each is applicable:
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
disintegrated material shall be removed. The potholes shall then be filled either
with material of the equivalent specification to the original construction. The area
for bituminous construction shall be tacked or primed with cutback or emulsion
depending on whether the lower area is bituminous or granular. The sides are to
be painted with hot tack coat material. The bituminous mixture shall be placed in
layers of loose thickness not more than 100mm. The filling shall be compacted in
layers with roller/ plate compactor/ hand roller, heavy hand rammers or approved
mechanical tampers. While placing the final layer, the mix shall be spread slightly
proud of the surface so that after rolling, the surface shall be flush with the
adjoining surface. The surface shall be thoroughly swept and scraped clean and
free of dust and other foreign matter.
14.5 TACK COAT
The application of tack coat shall be carried out in similar manner as described in
section 11.3.
14.6 PREPARATION OF MIX AND LAYING
Hot mix plant of adequate capacity and capable of producing a proper and
uniform quality mix shall be used for preparing the mix. The hot mix plant shall
have separate dryer arrangement for heating aggregate. The temperature of the
binder at the time of mixing shall be in the range of 150oC to 163oC and that of the
aggregate in the range of 155oC to 163oC. At no time shall the difference in
temperature between the aggregate and binder exceed 14oC. Mixing shall be
thorough to ensure that a homogeneous mixture is obtained in which all particles
of the aggregate are coated uniformly and the discharge temperature of mix shall
be between 130oC to 160oC.
The hot mix shall be immediately transported from the mixer to the point of use in
suitable vehicles or hand barrows. The vehicles employed for transport shall be
clean and the mix being transported covered in transit if so directed by the
Engineer.
The premixed material shall be spread by suitable means to the desired thickness,
grades and camber making any due allowance for any extra quantity required to
fill up depressions, if any. The camber should be checked by means of camber
boards and irregularities levelled out. Excessive use of blades or rakes should be
avoided.
14.7 ROLLING
As soon as sufficient length of bituminous material has been laid, rolling shall
commence with 8 – 10 tonne rollers, smooth wheel tandem type or other
approved equipment. Rolling shall begin at the edge and progress toward the
centre longitudinally, except that on super elevated and uni-directional cambered
portions, it shall progress from the lower to the upper edge parallel to the centre
line of the pavement.
When the roller has passed over the whole area once, any high spots or
depressions, which become apparent, shall be corrected by removing or adding
premixed materials. Rolling shall then be continued until the entire surface has
been rolled and all the roller marks eliminated. In each pass of the roller the
preceding track shall be overlapped uniformly by at least 1/3rd width The roller
wheels shall be kept damp to prevent the premix from adhering to the wheels. In
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
no case shall fuel/ lubricating oil be used for this purpose. Use of excess water for
this purpose shall also be avoided.
Rollers shall not stand on newly laid material. Rolling operations shall be
completed in every respect before the temperature of the mix falls below 100oC.
Joints along and transverse to the surfacing laid and compacted earlier shall be
cut vertically to their full depth so as to expose fresh surface which shall be
painted with a thin coat of appropriate binder before the new mix is placed against
it.
14.8 SEAL COAT
A seal coat conforming to section 15.0 shall be applied to the surface immediately
after laying the surfacing.
14.9 OPENING TO TRAFFIC
No traffic shall be allowed on the road until the seal coat has been laid. After the
seal coat is laid, the road may be opened to traffic according to section 15.4.3.
14.10 MEASUREMENTS AND RATE
The measurements shall be taken for the finished work in sq.m for the area
covered in plan. The rate shall cover carrying out works as specified above and
include the cost of all materials, labour, plant and equipment involved in the
works. .
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
and retained on 2.36 mm sieve. The quantity used for spreading shall be 0.09
cum per 10 sq.m. The chips shall satisfy the quality requirements in Table 4
except that the upper limit for water absorption value shall be 1%.
15.1.3 FINE AGGREGATE FOR TYPE B SEAL COAT
This fine aggregate shall be sand or fine grit and shall consist of clean, hard,
durable, uncoated dry particles and shall be free from dust, soft or flaky material,
organic matter or other deleterious substances. The aggregate shall pass 2.36
mm sieve and be retained on 180 micron sieve. The quantity used for premixing
shall be 0.06 cu.m. per 10 square metre area.
15.2 PREPARATION OF SURFACE
The seal coat shall be applied immediately after laying of bituminous course which
is required to be sealed. Before application of the seal coat, the surface shall be
cleaned free of any dust or other extraneous matter.
15.3 CONSTRUCTION OF TYPE A SEAL COAT
15.3.1 APPLICATION OF BINDER
Binder shall be heated in boilers to 150 C - 163 C, maintained at the temperature
and sprayed on the dry surface in a uniform manner with the help of mechanical
sprayers. Excessive deposits of binder caused by stopping or starting of the
sprayer through leakage or any other reason shall be suitably corrected before the
stone chippings are spread.
15.3.2 APPLICATION OF STONE CHIPPINGS
Immediately after the application of the binder, stone chippings in a dry and clean
state shall be spread uniformly on the complete surface. If necessary, the surface
shall be broomed to ensure uniform spread of chippings. The surface shall be
checked by means of a camber board laid across the road and a 3 metre straight
edge laid parallel to the centre line of the road and undulations if any, shall be
corrected by addition or removal of chippings.
15.3.3 ROLLING
Immediately after the application of the seal coat, the entire surface shall be rolled
with a 8 to 10 tonne smooth wheeled steel roller, 8 to 10 tonne static weight
vibratory roller, or other approved equipment. Rolling shall commence at the
edges and progress towards the centre except in super elevated and
unidirectional cambered portions where it shall proceed from lower to the higher
edge. Each pass of the roller shall uniformly overlap not less than one-third of the
track made in the preceding pass. While rolling is in progress, additional material
shall be spread by hand in whatever quantities required to make up for
irregularities. Rolling shall continue until all material is firmly bedded in the binder
and presents a uniform closed surface. Generally five to six passes shall be made
for thorough compaction of the surface or as directed by Owner/Engineer. Along
kerbs, manholes and at all places not accessible to roller, thorough compaction
shall be secured by means of steel rammers or hand rollers. Traffic shall be
allowed after 24 hours. After a period of seven days, surplus grit shall be swept
and collected and shall be used for binding the spots where bleeding occurs.
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
tolerance above; this one measurement being not in excess of 5mm beyond the
permitted tolerance.
For wearing courses, the measurements of the surface levels shall be taken on a
grid of points placed at 6.25m along the length and at 0.5m from the edges and
centre of the pavement. For the final road surface the above compliance shall be
satisfied for all points on any length of pavement.
16.2.3 SURFACE REGULARITY
The surface regularity of completed subgrade, sub-base course, base course and
wearing course in the longitudinal and transverse directions shall be within the
tolerances indicated in Table 28.
The longitudinal profile shall be checked with a 3 metre long straight edge, at the
middle of each traffic lane along a line parallel to the centre line of the road. The
transverse profile shall be checked with a set of three camber boards at intervals
of 10 metres.
Table 28
Maximum Permitted number of Surface Irregularities
Surfaces of carriageways Surfaces of lay-bys,
and paved shoulders service areas and all
bituminous base courses
Irregularity 4 mm 7 mm 4 mm 7 mm
Length (m) 300 75 300 75 300 75 300 75
National Highways/ 15 9 2 1 40 18 4 2
Expressways (*)
Roads of lower 40 18 4 2 60 27 6 3
category (*)
(*) Category of road shall described in the project contract
The maximum allowable difference between the road surface and underside of a
3m straight edge when placed parallel with or at right angles to centre line of the
road at points decided by the Engineer shall be:
For pavement surface 3mm
For bituminous base courses 6 mm
For granular sub-base/ base courses 8mm
For subgrade 15mm
16.2.4 RECTIFICATION
Where the surface irregularity of subgrade and the various courses fall outside the
specified tolerances, the Contractor shall be liable to rectify these in the manner
described below and to the satisfaction of the Engineer.
i. Subgrade
Where the surface is high, it shall be trimmed and suitably compacted.
Where the same is low, the deficiency shall be corrected by adding fresh
material. The degree of compaction and the type of material to be used
shall conform to the sections 5.0 and 6.0.
ii. Granular sub-base
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The treatment method shall be similar to item (i) above, except that the
degree of compaction and the type of material shall conform to the
requirements in section 8.0.
iii. Water Bound Macadam/ We Mix Macadam
Where the surface is high or low, the top 75 mm shall be scarified,
reshaped with added material as necessary and recompacted as per
section 9.0 or section 10.0. The area treated at a place shall not be less
than 5 metres long and 2 metres wide.
iv. Bituminous Construction
For bituminous construction other than wearing course, where the surface
is low, the deficiency shall be corrected by adding fresh material and
recompacting to specifications. Where the surface is high, the full depth of
the layer shall be removed and replaced with fresh material and
compacted to specifications.
For wearing course, where the surface is high or low, the full depth of the
layer shall be removed and replaced with fresh material and compacted to
specifications. In all cases where the removal and replacement of a
bituminous layer is involved, the area treated shall not be less than 5
metres long and not less than 3.5 m wide.
16.3 TESTS
16.3.1 GENERAL
For ensuring the requisite quality of construction, the materials and works shall be
subjected to quality control tests, as described hereinafter. The testing
frequencies set forth are the desirable minimum and the Engineer shall have the
full authority to increase the frequencies of tests as he may deem necessary to
satisfy himself that the materials and works comply with the appropriate
specifications.
Various quality control tests shall be conducted in accordance with the procedures
indicated in the respective sections of MORTH Specifications. Where no specific
testing procedure is mentioned, the tests shall be carried out as per the prevalent
accepted engineering practice to the directions of the Engineer.
16.3.2 TESTS ON EARTHWORK FOR EMBANKMENT AND SUBGRADE
CONSTRUCTION
a) Borrow material
(i) Sand Content {IS 2720 (Part 4)}: 2 tests per 3000 cu.metres of soil
(ii) Plasticity Test {IS 2720 (Part 5)}: Each type to be tested, 2 tests
per 3000 cu. metres of soil.
(iii) Density Test {IS 2720 (Part 8)}: Each soil type to be tested, 2 tests
per 3000 cubic metres of soil.
(iv) Deleterious Content Test {IS 2720 (Part 27)}: As and when
required by the Engineer.
(v) Moisture Content Test {IS 2720(Part 2)}: Two test for every 250
cubic metres of soil.
(vi) CBR Test on materials to be incorporated in the subgrade on
soaked/unsoaked samples {IS 2720 (Part 16)}: One result (average
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
Table 29
Control Tests and Their Frequencies for Sub-Bases
and Bases (Excluding Bitumen Bound Bases)
SI. Types of Test Frequency
No. Construction
1. Granular i. Gradation One test per 400 m3
ii. Atterbergs limit One test per 400 m3
iii. Moisture content prior to One test per 400 m2
compaction
iv. Density of compacted One test per 1000 m2
layer
v. Deleterious constituents As required
vi. C.B.R. As required
2. Water Bound i. Aggregate Impact Value One test per 1000 m3
Macadam of aggregate
ii. Grading One test per 250 m3 of
aggregate
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
END
The contents of this document are proprietary and confidential to Tata Consulting Engineers Limited (TCE) and the ISSUE
disclosure of the contents to anyone outside TCE is strictly prohibited except with the prior written consent from TCE. R4
1.0 SCOPE
2.1 MATERIALS
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information
and any claim arising thereof, cost and consequence will be on the party misusing the information. ISSUE
R0
IS: 5382 Specification for Rubber Sealing Rings for Gas Mains,
Water mains and Sewers
3.0 GENERAL
Design of RCC pipes, details of reinforcement and the ends of the pipe
shall be in accordance with the relevant clauses of IS: 458. The Class of
the pipe shall be of RCC NP3 conforming to IS 458 unless otherwise
specified in Data Sheet – A.
4.0 MANUFACTURING
4.1 GENERAL
a) The method of manufacture shall be such that the form and the
dimensions of the finished pipes are accurate within the limits specified in
relevant IS: 458. The surfaces and edges of the pipes shall be well defined
and true, and their ends shall be square with the longitudinal axis. The
ends of the pipes shall be further reinforced by an extra ring of
reinforcement to avoid breakage during transportation.
b) The RCC pipes and collars / rubber rings shall be systematically checked
for any manufacturing defects by experienced supervisors so as to
maintain a high standard of quality.
c) Engineer shall at all reasonable times have free access to the places where
the pipes and collars/ rubber rings are manufactured for the purpose of
examining and testing the pipes and rubber rings and of witnessing the test
and manufacturing.
d) All tests specified in Clause 4.6 for Testing of pipes shall be performed
by Supplier / Contractor at his own cost and in presence of Engineer if
ISSUE
R0
desired. For this, sufficient notice before testing of the pipes shall be given
to Engineer.
e) If the test is found unsatisfactory, Engineer may reject any or all pipes of
that lot. The decision of Engineer in this matter shall be final and binding
on Contractor and not subject to any arbitration or appeal.
4.2 MATERIALS
For all materials, Factory’s test result and written guarantee document
with necessary analysis data shall be submitted to obtain the approval of
the Engineer before carrying to sites.
4.2.1 Cement
Ordinary Portland cement/Sulphate Resisting Cement as specified in Data
Sheet –A shall be used for the manufacture of RCC pipes and fittings and
shall conform to relevant IS codes. The use of pozzolana as an admixture
to Portland cement shall not be permitted.
4.2.2 Aggregates
Aggregates used for the manufacture of RCC pipes shall conform to IS:
383. The maximum size of aggregate should be 10mm for pipes of
internal diameter 150 to 250mm but should not exceed one third thickness
of the pipe or 20mm, whichever is smaller, for pipes of internal diameter
above 250mm.
4.2.4 Reinforcement
Reinforcement used for the manufacture of the spigot and socket RCC
pipes shall be mild steel Grade I or medium tensile steel bars conforming
to IS: 432 (Part-1) or hard-drawn steel wire conforming to IS: 432 (part-
2). A reinforcement cage for pipes shall be as per relevant requirement of
IS: 458.
ISSUE
R0
4.2.5 Concrete
Concrete used for the manufacture of spigot and socket RCC pipes shall
conform to IS: 456. The minimum cement content and minimum
compressive strength of concrete shall be as per relevant requirements of
IS: 458. Compressive strength tests shall be conducted on 15cm cubes in
accordance with the relevant requirements of IS: 456 and IS: 516.
4.3 CURING
Pipes manufactured in compliance with IS: 458 shall be either water cured
or steam cured in accordance with the relevant requirements of IS: 458.
a) Pipes shall be straight and free from cracks except that craze cracks may
be permitted. The ends of the pipes shall be square with their longitudinal
axis so that when placed in a straight line in the trench no opening
between ends in contact shall exceed 3mm in pipes upto 600mm diameter
(inclusive), and 6mm in pipes larger than 600mm diameter.
b) The outside and inside surfaces of the pipes shall be smooth, dense and
hard, and shall not be coated with cement wash or other preparation unless
otherwise agreed to between Engineer and the manufacturer or supplier.
c) The pipes shall be free from defects resulting from imperfect grading of
the aggregate, mixing or moulding.
d) The pipes shall be free from local dents or bulges greater than 3.00 mm in
depth and extending over a length in any direction greater than twice the
thickness of barrel.
ISSUE
R0
e) The deviation from straight in any pipes throughout its effective length,
tested by means of a rigid straight edge parallel to the longitudinal axis of
the pipe shall not exceed, for all diameters, 3 mm for every meter run.
4.7 TESTING
a) All pipes for testing purposes shall be selected at random from the stock
of the manufacturer and shall be such as would not otherwise be rejected
under the criteria of tolerances as mentioned in IS: 458.
b) During manufacture, tests on concrete shall be carried out as per IS: 456.
The manufacturer shall supply, when required to do so by Engineer the
results of compressive tests of concrete cylinders or cubes made from the
concrete used for the pipes.
c) The specimen of pipes for the following tests shall be selected in
accordance with Clause 11 of IS: 458 and tested in accordance with the
methods described in IS: 3597.
i. Hydrostatic test
ii. Three edge bearing test or sand bearing test
iii. Absorption test
iv. Visual Examination
Note: Three edge bearing strength to produce 0.25 mm crack shall be as
per IS:458 for diameter and class of pipes as specified in Data Sheet – A .
a) In any consignment, all the pipes of same class and size and manufactured
under similar conditions of production shall be grouped together to
constitute a lot. The conformity of a lot to the requirements of this
Specification shall be ascertained on the basis of tests on pipes selected
from it.
b) The number of pipes to be selected from the lot shall be in accordance
with column 1 and 2 of Table 22 of IS: 458.
c) Pipes shall be selected at random. In order to ensure randomness, all the
pipes in the lot may be arranged in a serial order and starting from any
pipe, every “rth” pipe be selected till the requisite number is obtained, “r”
being the integral part of N/n where “N” is the lot size and “n” is the
sample size.
ISSUE
R0
d) The number of pipes selected for testing shall be in accordance with Table
22 of IS: 458 and tested in accordance with methods described in IS:
3597. These pipes shall be selected from pipes that have satisfied the
requirements mentioned in the above clause. All the pipes shall be
inspected for dimensional requirements, finish and deviation from
straight. A pipe failing to satisfy one or more of these requirements shall
be considered as defective.
e) A lot shall be considered as conforming to the requirements of IS: 458 if
the following conditions are satisfied.
i. The number of defective pipes (those not satisfying one or more of the
requirements for dimensions, finish and deviation from straight) shall not be
more than the permissible number given in Column 3 of Table 22 of IS:
458.
ii. All the pipes tested for various tests as per IS: 3597 shall satisfy
corresponding requirements of the tests.
iii. In case the number of pipes not satisfying requirements of any one or more
tests, one or two further sample of same size shall be selected and tested for
the test or tests in which failure has occurred. All these pipes shall satisfy
the corresponding requirements of the test.
All result of tested data must be prepared by contractor at site so that the
Engineer shall make decision of “fail or pass” at once. All cost for the test
shall be borne by the Contractor.
4.9.1 Transport
Pipes should be loaded at the works for transportation , either by rail or
by road , in such a way that they are secure and that no movement can
take place on the vehicle during transit . The same care is needed if
pipes are to be transferred from one vehicle to another , however, short
the journey be.
4.9.2 Handling
Unloading should be carried out by means of chain block with shear legs
or crane of adequate capacity , using properly designed slings and
spreader beams or specially designed lifting beams . Slings should be
placed around the circumference of pipe and should not be threaded ISSUE
R0
through the pipe bore as the latter method may damage the jointing
surfaces. For the same reasons, hooks located in the end of the pipes
should not be used .
4.9.3 Stacking
Pipes may be placed directly on the ground provided it is reasonably
level and free from rocks and other projections . Stacking in tiers
permissible provided timber bearer are placed between succeeding tiers
.If pipes to be stacked more than two tiers high , reference should be
made to manufacturer for advice before exceeding the two tiers stacking
4.10 STORAGE
Each stack of pipes shall contain only pipes of same class and size, with
consignment or batch number marked on it with particulars of suppliers
wherever possible. Storage shall be done on firm level and clean ground
and wedges shall be provided at the bottom layer to keep the stack stable.
The stack shall be in pyramid shape or the pipes lay lengthways and
crosswise in alternate layers. The pyramid stack shall be made for smaller
diameter pipes for conserving space in storing them. The height of the
stock shall not exceed 1.5 m.
Rubber rings shall be stored in a clean, cool store away from windows,
boiler, electrical equipment and petrol, oils or other chemicals.
4.11 MARKING
ISSUE
R0
5.1 LAYING
ISSUE
R0
5.2 JOINTING
The RCC pipe with the rubber ring accurately positioned on the spigot
shall be pushed well home into the socket of the previously laid pipes.
The manufacturer’s instructions shall be used, and the manufacturer’s
instructions shall be deemed to form a part of these Specifications. The
rubber rings shall be lubricated before making the joint and the lubricant
shall be soft soap water or an approved lubricant supplied by the
manufacturer. The socket of RCC pipes shall face up the gradient.
6.0 MEASUREMENT
All RCC pipes shall be measured according to the work actually done and
no allowance will be made for any waste in cutting to the exact length
required. The measurement for pipes shall be in running meter nearest to a
centimeter of length along the centreline of pipes as actually laid at work
site as per drawings and approved by Engineer.
ISSUE
R0
7.0 PAYMENT
Payment for RCC pipes shall be on running meter basis. The rate quoted
for providing, laying and jointing of RCC pipes shall be deemed to
include the cost of collars/rubber rings, jointing materials, testing and
including cleaning of pipes without excavation.(Excavation will be paid
separately under relevant item).
END
ISSUE
R0
FOR
VOLUME III
Proprietary rights of the information contained herein belong to Tata Consulting Engineers Limited (TCE).
This information is intended to be used for the mentioned purpose/project only. In case of misuse of information ISSUE
and any claim arising thereof, cost and consequence will be on the party misusing the information.
R0