Eyob Sisay
Eyob Sisay
JUNE 2022
JUNE 2022
DECLARATION
I, the undersigned, hereby declare that this project work entitled “Factors Affecting
Construction Project Performance: The Case of Ethiopian Institute of Agricultural
Research” is my original work with the guidance of the research advisor and all sources of
materials used for the project work have been acknowledged as complete reference. I further
confirm that the study has not been submitted in full or partial fulfillment in any other
recognized University/Institution for the purpose of earning any degree.
Signature Date
First and for most, I would like to express my heart-felt gratitude to the almighty God for
listening to my prayers and being on my side whenever I need help.
I would like to thank my advisor, Dr. Teklegiorgis Assefa, as he was generous with his time to
share his knowledge and wisdom from the conception of the project work. His advice, insightful
criticism, and friendly character have been very valuable and helpful.
Secondly, I would like to express my deepest appreciation and gratitude to all organizations and
individuals that have aided and provided the required information, without which this paper
would not have been possible.
In special regards, I would like to thank my best supporters, Planner Berket Aklilu, Instructor
Tewdros Getahun, Instructor Tesfaye Moges, and Engineer Waleligne Tefera, who aided and
provided unreserved support for the realization of this work.
I
Abstract
II
Table of Contents
Acknowledgment ....................................................................................................................... I
Abstract ..................................................................................................................................... II
Table of Contents ..................................................................................................................... III
List of Tables ...........................................................................................................................VI
List of Figures ..........................................................................................................................VI
ACRONYMS ......................................................................................................................... VII
Chapter One ............................................................................................................................... 1
Introduction ................................................................................................................................ 1
1.1 Background of the Research ............................................................................................. 1
1.2 Organizational over view of EIAR .................................................................................... 3
1.3. Statement of the Problem ................................................................................................. 3
1.4. Research Questions .......................................................................................................... 4
1.5. Objectives of the Study .................................................................................................... 5
1.5.1. General Objective ..................................................................................................... 5
1.5.2. Specific Objectives ................................................................................................... 5
1.6. Scope of the Study ........................................................................................................... 5
1.7 Limitations of the Study.................................................................................................... 5
1.8. Significance of the Study ................................................................................................. 5
1.9 Definition of Key Terms ................................................................................................... 6
1.10. Structure of Research ..................................................................................................... 6
CHAPTER TWO ....................................................................................................................... 8
LITERATURE REVIEW ........................................................................................................... 8
2.1. Introduction ..................................................................................................................... 8
2.2 Theoretical review ............................................................................................................ 8
2.2.1. Over view of Project ................................................................................................. 8
2.2.2. Over view Performance ............................................................................................. 9
2.2.3 Performance Measurement Theory ........................................................................... 10
2.2.4 Project Success ........................................................................................................ 11
2.2.5. Construction............................................................................................................ 12
2.2.6 Performance Management in Construction ............................................................... 13
2.3 Empirical Reviews .......................................................................................................... 14
2.3.1 Factors Affecting Performance of Construction Projects .......................................... 14
2.3.2 Factors affecting performance related to project procedures ..................................... 17
III
2.3.3. Factors affecting performance related to the Contractor/ Supplier............................ 19
2.3.4 External and Work Environment Related Factors ................................................... 19
2.3.5 Performance indicators in construction projects........................................................ 21
2.3.6 Conceptual Framework ............................................................................................ 21
2.3.7 Research gaps .......................................................................................................... 22
2.4 Summary of the Chapter ................................................................................................. 22
CHAPTER 3 ............................................................................................................................ 23
RESEARCH METHODOLOGY .............................................................................................. 23
3.1. Introduction ................................................................................................................... 23
3.2. Research Approach ........................................................................................................ 23
3.3. Research Design ............................................................................................................ 23
3.4. Research Methods.......................................................................................................... 23
3.4.1 Target population ..................................................................................................... 23
3.4.2. Sampling method .................................................................................................... 24
3.4.4 Data Source and data collection ............................................................................... 25
3.5 Data Measurement .......................................................................................................... 25
3.6 Research Instruments ...................................................................................................... 25
3.6.1 Reliability of Research Instruments .......................................................................... 26
3.6.2 Validity of research instruments ............................................................................... 26
3.6.3. Ethical considerations ............................................................................................. 27
3.7 Method of Data Analysis ................................................................................................ 27
CHAPTER 4 ............................................................................................................................ 28
RESULTS AND DISCUSSION ............................................................................................... 28
Introduction .............................................................................................................................. 28
4.1 Questionnaire.................................................................................................................. 28
4.2 Background Information of Respondents ........................................................................ 29
4.2.1 Position in the Organization or Company ................................................................. 29
4.2.2 Work Experience in Projects .................................................................................... 29
4.2.3 Educational Background .......................................................................................... 30
4.3 Descriptive Analysis of Factors Affecting the Performance of Construction.................... 32
4.4 Statistical Assumption testing ......................................................................................... 38
4.5.Correlations ................................................................................................................ 39
4.6 Research discussion and Findings ....................................................................................... 45
CHAPTER 5 ............................................................................................................................ 52
CONCLUSION AND RECOMMENDATIONS....................................................................... 52
IV
5.2 Summery of finding ........................................................................................................ 52
5.3. Conclusion..................................................................................................................... 53
5.4. Recommendation ........................................................................................................... 53
5.5 Suggestion for Future Research ................................................................................... 54
References ................................................................................................................................ 55
Questionnaires .......................................................................................................................... 61
Part One: General Information ............................................................................................. 62
Part Two: Factors Affecting the Performance of Construction Projects ..................................... 63
Part Three: Overall performance of Construction Projects Executed in the EIAR ................... 65
Appendix.................................................................................................................................. 66
V
List of Tables
Table 1 List of identified procurement related factors ............................................................... 18
Table 2 List of identified contractor/ supplier related factors .................................................... 19
Table 3 List of identified external and work environment related factors .................................. 20
Table 4 Rating scale for significance level of factors on project performance ........................... 25
Table 5 Reliability Statistics of collected data........................................................................... 26
Table 6 Summary of the response rate of the study ................................................................... 28
Table 7 Experience of respondents ........................................................................................... 30
Table 8 Respondents’ level of education ................................................................................... 30
Table 9 Overall performance of cons. Cross tabulation ............................................................. 31
Table 10 The relative importance index (RII) and rank of factors ............................................ 32
Table 11 Clients related factors ................................................................................................ 33
Table 12 Material related factors .............................................................................................. 33
Table 13 Contractor related factor ............................................................................................ 34
Table 14 Project procedure method .......................................................................................... 35
Table 15 External environment of sites ................................................................................... 35
Table 16 Equipment Related factor ........................................................................................... 36
Table 17 The RII &Top five factors affecting the construction performance ............................. 37
Table 18 : The relative importance index (RII) and rank of major groups ................................. 37
Table 19 . Kolmogorov-Smirnov& Shapiro-Wilk Tests of Normality ..................................... 38
Table 20 Case Processing Summary ......................................................................................... 41
Table 21 Pseudo R-Square........................................................................................................ 43
Table 22 The relative importance index (RII) and rank of factors ............................................ 66
List of Figures
Figure 2Normal Q_Q plot 39
VI
ACRONYMS
PM Project Management
UK United Kingdom
VII
Chapter One
Introduction
Construction project management involves directing and organizing each part of the
project life cycle, from conception to completion. It’s a holistic practice with the goal of
delivering projects on time and under budget. Construction project management is a
complex discipline that requires addressing many important concerns, including cost
control, scheduling, procurement, and risk assessment. Project managers interact with all
team members involved in a construction project, from architects to owners to
contractors.
The term "construction" refers to the entire economic activity of creating, modifying,
repairing, or extending fixed assets, such as buildings, engineering-related land
improvements, and other engineering-related structures .The progress of nations depends
on the construction industry. It is one of the biggest industries and makes up roughly
10% of the GDP in industrialized nations, Navon (2005).
1
The building sector has an important contribution to the Ethiopian economy. It involves
substantial financial and human resources and plays a vital role in the national economy
and has a wide range of applications to different major sectors, like health, education,
and agriculture. Agriculture is the backbone of the Ethiopian economy. Since Ethiopia is
endowed with abundant agricultural resources and has diverse ecological zones,
agriculture plays a large role in the country’s economy. The agricultural sector in
Ethiopia contributed about 35%of GDP in 2017-18 (Government of Ethiopia 2019 b) and
65% of employment in 2019 (World Bank 2019a). Although agriculture is one of
Ethiopia’s most promising resources, overgrazing, deforestation, and high population
density have led to massive soil degradation leading to low productivity. Therefore, to
alleviate the mentioned difficulties, the Ethiopian agricultural research institute has made
its vital contribution.
Construction projects' performance, how well, how quickly, and at what cost buildings
and infrastructure can be constructed directly affects the cost of projects and contributes
to the national output, and stimulates the growth of other sectors through a complex
system of linkages. The same is true for the Ethiopian Agricultural Research Institute
(EIAR). Currently, the EIAR is implementing different types of construction projects
(laboratories, administrative offices, green hose, and so on) for the realization of its
goals. Others are under construction to achieve its mission.
The governmental budget allocated during the study time for EIAR is more than 300
million Birr. In most programs, there are small to large construction projects undertaken
as part of their plan. As per the engineering unit of the institute, the total annual budget
of these constructions ranges between 130 and 150 million Birrs. This study focus on
identifying the main construction performance factors for EIAR during this study period.
However, most projects fail to be completed on time, causing cost overruns and, at times,
complete abandonment. This can be seen in the same building projects which stand
unfinished. Even more, there are projects that are finished at a date later than agreed in
the project schedule. Therefore, assessing factors affecting the project performance of
EIAR projects is a current issue and testing how they affect overall performance helps
improve the performance of future construction projects.
2
1.2 Organizational over view of EIAR
The Ethiopian Agricultural Research Institute is a governmental research institute and a
foundation for agricultural growth in Ethiopia. Ethiopian Agricultural Research (EIAR)
is one of the largest agricultural research systems in Africa. It works with the ambition of
conducting research that will provide market competitive agricultural technologies that
will contribute to increased agricultural productivity and nutrition quality, sustainable
food security, economic development, and conservation of the integrity of natural
resources and the environment.
The Ethiopian Agricultural Research System (EARS) has evolved through several stages
since its first initiation in the late 1940s. In 1993, a number of Institute of Agricultural
Research centres were transferred to the regional governments and became independent
research centres. During this time, the Ethiopian Agricultural Research Organization was
established with a new set up in 1997 by Proclamation number 79/1997, and later it was
renamed the Ethiopian Institute of Agricultural Research on 25th October 2005. The
EIAR is now organized into a decentralized structure in which a head office is based in
Addis Ababa and 22 main research centres and lots of sub-centres throughout the
country. Fentahun . (2015)
3
Assessing the factors of performance problems is vital. The study conducted by Memon.
(2012) revealed that 92% of construction projects in Malaysia were facing time overruns
and only 8% of the projects could achieve completion within the contract duration. 89%
of respondents agreed that their projects were facing cost overruns, with an average
overrun of 5-10% of the contract price. The same is true for Nigeria and Kenya. The
research conducted by Auma (2014) is evidence that the performance of construction in
Kenya is poor. The majority of the projects escalated by a magnitude of over 50% and
over 50% of the projects are likely to escalate in cost by a magnitude of over 20%.
For several reasons, construction projects in the EIAR challenge their performance
instead of achieving their planned goals. Most of these challenges are related to what we
call project performance problems. This research focuses on identifying factors affecting
the performance of construction projects in selected EIAR construction projects in order
to assist the institute, consultants, and contractors to overcome performance problems,
and improve the performance of future construction projects
4
1.5. Objectives of the Study
1.5.1. General Objective
To determine the major factors that affects the performance of construction projects in
the EIAR.
5
Hence, it informs the management of EIAR on necessary alleviation strategies to handle
their effects. It also informs the institute of future planning and strategy developments for
existing and newly established agricultural research centers. Finally, the study would be
important in the suggestion of areas requiring further research to build on the topic of
factors affecting performance of projects.
Owner: Organization for whom the construction project is being undertaken. In the case
of EIAR Research centres & sub-centers.
Time overruns: is defined as the extension of time beyond planned completion dates.
Cost overrun: is the difference between the original cost estimate of the project and the
actual construction cost on completion of works.
Chapter one: Introduction: this chapter shows the background of the study, statement of
the problem, research questions, objectives of the research, scope, and limitations,
significance, and Definition of Key Terms.
Chapter two: Literature review: this chapter shows a detailed review of concepts and
definitions to identify the main factors affecting the performance and key performance
indicators in Building construction projects.
6
Chapter three: Research methodology: this chapter shows the methodology used in this
research in order to achieve the required objectives and to answer the research
questions.
Chapter Four: The collected data from the subject of the study are carefully analyzeed
and interpreted.
The fifth chapter presents summary, conclusions and recommendations on the findings
of the study. Reference and appendix which include questionnaire are also part of this
study paper.
7
CHAPTER TWO
LITERATURE REVIEW
2.1. Introduction
This chapter presents a literature review of the research work that was done by various
scholars in the field of performance of construction projects. This includes Theoretical
review, conceptual framework, empirical review, and critique of the existing literature
relevant to the study, summary, and research gaps.
A project can be considered to be any series of activities and tasks that have a specific
objective to be completed within certain specifications, defined start and end dates,
funding limits, consume human and nonhuman resources and is multifunctional (i.e., cut
across several functional lines) Kerzner, (2013). Merna and Al-Thani (2008) also defined
a project as a unique investment of resources to achieve specific objectives, such as the
production of goods or services, in order to make a profit or to provide a service.
8
A project is an irreversible change with a life cycle and defined start and completion
dates. “A project is a temporary endeavor undertaken to create a unique product, service,
or result” PMI, (2013).
Turner and Müller, (2003also states that project is an endeavor in which human, material
and financial resources are organized in a novel way, to undertake a unique scope of
work, of given specification, within constraints of cost and time, so as to achieve
beneficial change defined by quantitative and qualitative objectives.
Performance has been described as the degree of execution of a certain task. It is related
to the prescribed objectives which form the project considerations. Performance can be
considered as an evaluation of how well individuals, groups of individuals, or
organizations have done in pursuit of a specific objective.
Juran McCabe, (1998) defines performance as "the fitness of the project". This is broken
down into four categories: quality of design, quality of conformance, availability and
field service. The quality of design focuses on market research, the product concept and
design specifications. Quality of conformance includes technology, manpower, and
management. Availability focuses on reliability, main ability, and logistical support.
Field service quality comprises promptness, competence, and integrity.
Various literatures have revealed that performance should not be considered only as the
achievement of the project schedule, time and quality. It is a broader concept that can be
assessed using different parameters relating to the objectives of different stakeholders for
a particular project. Customer satisfaction, meeting specifications, health and safety, and
environmental responsiveness are some of the concerns when evaluating successful
achievement of project objectives.
9
From a project management perspective, it is all about meeting stakeholders’ needs and
expectations from a project. It invariably involves placing consideration on three major
project elements, i.e. time, cost, and quality. PMI, (2004).In construction, because of the
numerous participants who contribute towards the achievement of project objectives,
performance has been defined in one sense as a participant’s (client, consultant, or
contractor) contribution to the execution of the task required to complete the project,
Mullins, (1995).
Performance measurement has two main aims: to connect company goals and objectives
to improvements and to set targets for improvement activity. Grunberg, 2004). Outputs
are measured to determine whether they help to accomplish objectives (effectiveness)
and resources are measured to determine whether a minimum amount of resources are
used in the production of outputs (efficiency).
The assembly of building materials and/or components on-site; the materials and
components are supplied by a variety of industries in the manufacturing sector; they are
delivered to the site by the transportation and trade sectors; the assembly proceeds in
accordance with plans, designs, and management procedures supplied mainly by the
business services industry in the service sector; most of the funds required for
construction are supplied by the financial services industry in the service sector, and a
significant part of the output supplied by the construction sector delivered to the real
estate industry in the service sector" Bon (1992)
The construction process consists of construction inputs, construction processing, and
construction outputs. Construction inputs are defined as all resources and parties
involved in the construction process. Abdel-Razeq, (2001). It is the execution process,
which can be defined as activating construction inputs for executing construction
activities. The construction output is the construction facility.Construction projects, have
a predetermined duration with a beginning and an end. The life cycle of a typical
construction project can be broadly divided into three phases: the formulation phase,
mobilization phase, and the construction phase.
The formulation phase includes the conception of the project idea, feasibility studies,
investment appraisal, and project definition. The mobilization phase covers the
preparation of the project preliminary plan, designs and drawings, contracts, resource
mobilization, and earmarking funds. The construction phase includes planning and
controlling execution, inducting resources, construction and commissioning, and finally,
handing over to the client. Chitkara, (1998).
12
Despite this complexity, the construction industry plays a major role in the development
and achievement of goals in society. The pace of the economic growth of any nation can
be measured by the development of physical infrastructure such as buildings, roads, and
bridges. Takin and Akintoye, (2004).Construction contributes to the economic
development of any country by satisfying some of the basic objectives of development,
including output generation, employment creation, and income generation and
redistribution. It also plays a major role in satisfying basic physical and social needs,
including the production of shelter, infrastructure, and consumer goods. Moavenzdadeh
F. (1976). The same is true for the least developed countries, like Ethiopia.
Project success is almost the ultimate goal for every project. The success of construction
projects depends mainly on the success of performance. Many previous researches have
been studied on the performance of construction projects. Dissanayaka and
Kumaraswamy (1999) remarked that one of the principal reasons for the construction
industry's poor performance has been attributed to the inappropriateness of the chosen
procurement system. Thomas (2002) identified the main performance criteria of
construction projects as financial stability, progress of work, standard of quality, health
and safety, resources, relationships with clients, relationships with consultants,
management capabilities, claim and contractual disputes, relationships with
subcontractors, reputation and amount of subcontracting.
13
Construction performance affects the outcomes of national efforts to renew existing
infrastructure systems; to build new infrastructure for power from renewable resources;
and to remain competitive in the global market. Changes in building design, construction
and renovation, building materials and materials recycling are essential to the success of
national efforts. NSTC (2008).
Cheung et al (2004) identified project performance categories such as people, cost, time,
quality, safety and health, the environment, client satisfaction, and communication. It is
found by Navon (2005) that a control system is an important element for identifying
factors affecting construction project effort. For each of the project goals, one or more
Project Performance Indicators (PPI) are needed. Cheung et al (2004) found that human
factors played an important role in determining the performance of a project. Ugwu and
Haupt (2007) remarked that both early contractor involvement (ECI) and early supplier
involvement (ESI) would minimize constructability-related performance problems,
including costs associated with delays, claims, wastages, and rework, etc.The most
important practices relating to scope management are controlling the quality of the
contract document, quality of response to perceived variations, and extent of changes to
the contract.
14
It has been stressed that in today’s highly competitive and uncertain business
environment, clients are demanding better value for their investment. They want their
project to be completed on time, within the estimated cost, and with the right quality.
Padang (2006).
Owusu Tawiah, (1999) identified two main factors affecting contractor performance. The
two factors were the financial and managerial capacities of the firm. Under the financial
factors, the contractors’ financial stability in terms of access to credit was questionable
and that has gone a long way to affecting their performance over the years. Managerial
capacities, site management practices, lack of technical expertise, among others, as
factors influencing contractor performance in Ghana.
Ankrah N.A. (2007) classifies the factors that influence project performance into
uncontrollable and controllable. From a project perspective, uncontrollable factors
include external constraints and industry factors. These are beyond the control of project
participants and hence may be difficult, if not impossible, to influence at a project level
in trying to improve performance, whereas the controllable factors include project and
organization-related factors. The controllable factors include procurement route,
contracts, variations, project complexity, project duration and cost, design time, plant and
equipment, personnel, the interaction between project participants, some process-related
issues, skills and capability, health and safety, quality, and specific company
programmers.
The performance of the project team members can be assessed by their technical and
managerial skills, working relationships and attitudes, and support from their parent
companies. Chua. (1999) found that project performance is influenced by four main
project aspects, namely, project characteristics, contractual arrangements, project
participants, and interactive processes.
According to Enshassi et al. (2009) the most important factors agreed upon by the
owners, consultants, and contractors were: average delay because of closure and
materials shortages, availability of resources as planned throughout the project duration,
leadership skills for the project manager, escalation of material prices, availability of
personnel with high experience and qualifications, and the quality of equipment and raw
materials.
15
Iyer and Jha (2005) did research on factors affecting cost performance evidence from
Indian construction projects and found out that the project manager’s competence and
top management support are found to contribute significantly to enhancing the quality
performance of a construction project. Nyangilo (2012) did an assessment of the
organization structure and leadership effects on construction projects' performance in
Kenya. He found out that lack of appropriate project organization structures, poor
management systems and leadership are the major causes of poor project performance.
Mallawaarachchi & Senaratn (2015) identified factors that affect the quality of the
housing projects, such as a lack of technical and professional expertise and resources to
perform tasks, a lack of employee commitment and understanding, and a lack of
education and training to drive the improvement process. According to Mane & Patil,
(2015), other factors affecting the performance of construction projects include project
managers' competence, poor monitoring and feedback, lack of an on-site project
manager, inadequate project team capability, poor planning and control techniques,
poor/insufficient information and communication channels, lack of early and continual
client/consultant consultation by contractors, and insufficient project manager
experience.
Teena (2014) identified the factors that affect the process quality of construction projects
by collecting data from consultants and contractors through a questionnaire. According
to the study, the most important factors that affect the quality of projects are financial
problems, the quality of raw materials in the project, the availability of personnel with
high qualifications, and conformance to codes and standards.
Adnan & Sherif (2009) identified the factors affecting the performance of local
construction projects and their relative importance. The most important factors agreed by
the owners, consultants, and contractors as the main factors affecting the performance of
construction projects were: material prices, availability of resources as planned through
project duration, average delay because of closures leading to materials shortages,
availability of personnel with high experience and qualifications, quality of equipment
and raw materials in projects, and leadership skills for project managers.
16
According to Ajayi (2010), the choice of the contractor (s) is a critical factor for the
project manager and usually has a significant impact on the success or failure of a
project. The performance of contractors definitely correlates with the performance of the
contract. Several models and methods have been proposed by researchers for the
evaluation of project performance. However, most of these procedures, according to
Ajayi et al. (2010), limit their analysis to selected measures such as cost, schedule, or
labour productivity. Construction performance embraces client satisfaction, time
performance, cost performance, construction quality, and sustainable development.
Puspassari (2005) identified 46 possible factors responsible for the poor performance of
construction contracts. He further categorized these factors into eight groups; factors
caused by clients, factors caused by contractors, factors caused by consultants, factors
related to subcontractors, factors related to materials and labour, contractual relationship
factors, project procedures, and external environmental factors.
18
2.3.3. Factors affecting performance related to the Contractor/ Supplier
When the project enters the construction stage, the main contractor and subcontractors
begin their primary responsibilities. Contractor experience, site management, subcontractor
supervision and involvement, contractor cash flow, and the success of the cost control
system are all factors to consider. Behailu 2018 identified four (4) contractor/supplier
related factors from different works of literature.
Contractor/
supplier related
success factors Reference Literature
Contractor’s/ supplier’s
1 competence and
commitment
Contractor’s/ supplier’s
4 cash flow/ financial
capabilities
Four (4) contractor/ supplier related factors
2.3.4 External and Work Environment Related Factors
The construction environment, according to R. Youker (1992), is the aggregate of
surrounding things, conditions, or influences. He describes this environment as all
external influence on the construction process. Thus, the environment includes virtually
everything outside the project; its technology, the nature of its products, customers, and
competitors, its geographical setting, and the economic, political, and even metrological
climate in which it must operate. Bennett (1991), in a major review of project
management theory, established that the environment interferes with the planned
progress of construction projects. The less predictable the environment is and the greater
its potential effects, the more it must be taken into account in managing the development
of construction projects.
19
Ankrah N.A. (2007) classifies the factors that influence project performance into
uncontrollable and controllable. From a project perspective, uncontrollable factors
include external constraints and industry factors. These are beyond the control of project
participants and hence may be difficult, if not impossible, to influence at a project level
in trying to improve performance, whereas the controllable factors include project and
organization-related factors.
Belassi and Tukel (1996) classify factors affecting the performance of construction
projects as political environment, economic environment, social environment,
technological environment, nature, client, competitors, and sub-contractors.
Salleh (2009) cited the work of Chan and Kumarswamy (1997) and presented the results
of a survey undertaken to determine and evaluate the relative importance of the
significant factors causing time and cost overruns in Hong Kong construction projects.
The factors were grouped into eight major categories: project-related, client-related,
design-related, contractor-related, materials, labour, equipment, and external factors.
Chan et al. (2004) reviewed seven international journals and summarized and grouped
the factors into five categories: human-related, project-related, project procedures,
project management actions, and external environment. Under each group, there are a
number of identified factors listed that have a direct effect on the success of a project
The various variables affecting the performance of projects are identified from different
works of literature. These factors can be grouped as project characteristics-related
factors, material-related factors, contractors’ related factors, project procedures, external
environment, and equipment related factors. A variable in one group can influence a
variable in the other and vice versa. It is graphically presented as shown below.
21
Conceptual Frame work
Own Survey
Chapter two discusses the literatures relevant to the objectives of the study. Project
characteristics related factors, Type of project (Infrastructure or Building), material
related factors, Contractor related factor, Project procedures, External environment
(Political environment, economic environment, social environment, and physical
environment), and Equipment factors. These are discussed in detail and how they
influence construction project performance which is the dependent variable.
22
CHAPTER 3
RESEARCH METHODOLOGY
3.1. Introduction
This chapter sets out the various stages and phases to complete the study. The
methodology adopted in this research provides the procedures that are necessary for
obtaining the information needed to structure the research questionnaire, collect data,
analyse the collected data, and interpret and present the results. The methodologies
followed in this survey are outlined in the following sections.
23
3.4.2. Sampling method
A two-step process is used in which the population is partitioned into strata as owner
(EIAR) and contractors. The strata are mutually exclusive and collectively exhaustive in
that every population element should be assigned to only one stratum and no population
elements should be omitted. A purposive sampling technique was used to select the staff
among 20 research centres of the Ethiopian Institute of Agricultural Research. Based on
this sampling technique, the researchers used proportional sampling from each of the
research centres.
A sample design is a definite plan for obtaining a sample from the sampling frame
(Kothari, 2004). Different authors tend to give different guidelines concerning the
number of cases required for multiple regressions. Tabachnick and Fidell (2001, p. 117)
give a formula for calculating sample size requirements, taking into account the number
of independent variables that you wish to use:
The target groups in this study are EIAR selected centres construction projects and their
participants are owners (EIAR professional staff who know the concerned construction
projects during the specified time.) and contractors.
The sample size is determined based on the following Slovin’s sampling formula
(Yemane, 1967).
2
n= N / [1+ N*e ] ……………………………….………………. Equation 1
Where:
e = error margin / margin of error, a 95% confidence level is taken and e = 0.05
24
Therefore, 70 of the EIAR professional staff who know the concerned construction
projects during the specified time, and 22 from contractor’s organizations were selected.
In order to be able to select the appropriate method of analysis, the level of measurement
must be understood. In this research, ordinary was used. An ordinal scale is a ranking or
rating data that normally uses integers in ascending or descending order. The numbers
assigned to the agreement or degree of influence (1, 2, 3, 4, 5) do not indicate that the
interval between scales is equal, nor do they indicate absolute quantities. Based on this
scale, the researcher has the following table
Scale 5 4 3 2 1
The questionnaire designed for this study utilizes the information sourced from the
extensive literature review, the global nature of the construction industry, and relevance
to the EIAR construction projects context. The questionnaires are divided into three
sections: Part A, which seeks to establish general details of the respondent, Part B, which
contains factors affecting the performance of construction projects grouped into seven,
includes project characteristics related factors, material related factors, contractor related
factors, project procedures, external environment, and equipment related factors. Part C
contains the respondent’s judgment on the overall performance of the executed
construction projects on the above factors.
25
3.6.1 Reliability of Research Instruments
The statistical measure Cronbach's Coefficient Alpha reliability is used to make sure the
questions are properly reliable in advance of data analysis
Reliability Statistics
0.891 0.902 7
Alpha if item deleted: This represents the Cronbach’s alpha reliability coefficient if the
individual item is discarded from the scale. This value is then compared to the value of
Cronbach’s alpha present above to see if anyone wants to delete the item. A value of 0.7
reliability coefficient or higher is acceptable in the social sciences (Jugdev . 2007). The
result of reliability measure was good α=902 in the study and it were concluded that all
items in the survey were internally consistent and reliable
26
3.6.3. Ethical considerations
By adhering to the following ethical research guidelines, the researcher ensures that the
research is conducted in an ethical manner. (Respondents' anonymity, confidentiality,
and voluntary involvement). Prior to data collection, letters were sent from EIAR's
concerned administrative agencies to a number of research centers and private companies
where important information for the research may be obtained.
The data was analysed using the relative importance index rank method (RII) to identify
the identified performance factors affecting the performance of construction projects.
The relative importance index is computed using the following formula; (Cheung et al,
2004; Iyer and Jha, 2005; Ugwu and Haupt, 2007):
∑ (W)
RII= - - - - - - - - -
AxN
Where;
W is the weight given to each factor by the respondents and ranges from 1 to 5
The RII values have a range of 1 to 5. The higher the RII, the more important the factor
for the performance of construction projects. The RIIs is ranked, and the results are
shown by using tables. In addition to this RII, the analysis used both descriptive and
inferential statistics (correlation and regression) to identify the relationship between
these factors and to assess the extent of the performance of EIAR construction projects.
In addition to the RII, the factors were analysed using ordinal regression analysis.
Ordinal regression is a member of the family of regression analyses. As a predictive
analysis, ordinal regression describes data and explains the relationship between one
dependent variable and two or more independent variables. In ordinal regression
analysis, the dependent variable is ordinal (statistically it is polychromous ordinal) and
the independent variables are ordinal or continuous-level.
27
CHAPTER 4
RESULTS AND DISCUSSION
Introduction
This chapter displays the discussion of the final results and the process through which
the results were obtained. The data was collected through questionnaires from the
contractors and staff of the EIAR who directly participated in the projects, and
discussion about the results. The data was analyzed using both SPSS and Excel
worksheets, after which meaningful results were derived from the percentages arrived
at in this process. The purpose of the data analysis was to determine the factors that
affect construction project performance in the EIAR.
Contractor 22 20 90.9%
Owner 70 60 85.7%
Total 92 80 86.96%
Own Survey, SPSS output
The unsuccessful response rate (13.04%) consisted of those questionnaires that were
not filled out. This response rate was excellent for the analysis.
28
4.2 Background Information of Respondents
Engineer/Designer 5 6.25%
Supervisor 13 16.25%
Planning 2 2.50%
Total 80 100.00%
It was evident that the majority of the respondents were Finance & Procurement staff
(55%) followed by Supervisors (16.25%). This is because the EIAR merged its
engineering & maintenance directorate into finance & recalled its procurement. While
the rest are Program/Center Directors (12.5%), Project Manager (7.5),
Engineer/Designers (6.25%) and Planning (2.5%) as shown in table 10. This shows
that everybody in the construction firm had the opportunity to respond to the
questionnaire.
29
Table 7 Experience of respondents
Frequency Percent
Total 80 100.00%
Accordingly, 39 (48.75%) indicated that they had been working between 10-15 years,
followed by 14 (17.5%) who had been working between 5-10 years, 13 (16.25%) had
been working between 15-20 years, and 7 (8.75%) had been working below 5 years
and 7 (8.75%) had been working above 20 years. This shows that most of the
respondents are capable of providing relevant data on factors affecting construction
performance.
Frequency Percent
Diploma 3 3.75%
Bachelor’s degree 52 65.00%
Masters 19 23.75%
PHD 6 7.50%
Total 80 100.00%
30
As indicated in the above table 11, the majority of the respondents’ 52 (65.0%) had a
bachelor's degree, 19 (23.75%) had a Masters, while 6 (7.0%) of the respondents had
a PHD, and the rest 3 (3.75%) had a Diploma. This shows that the respondents are
capable and reliable of exploring the fundamental issues related to the study.
Generally, the finding regarding the characteristics of respondents confirms that the
respondents are qualified to understand the questions concerning factors affecting
project performance at the EIAR. So, the researcher believes that the response
obtained from them is reliable and trustworthy. That enables the researcher to move
towards the intended research finding.
EIAR 1 8 10 28 13 60
Contractor 1 2 12 3 2 20
As indicated in the above table 12, from 60 EIAR respondents, 13, (21. %), from 20
contractors 2 (10%), from a total of 80 respondents, 15 (18.8%) of them believed
project performance factors extremely affect the overall EIAR executed construction
projects.
31
4.3 Descriptive Analysis of Factors Affecting the Performance of Construction
The results of this part of the study show the rank of all factors affecting the
performance of construction projects in the EIAR that have been investigated in this
research from contractors and the EIAR staff viewpoints. A total of 31 factors which
influence construction performance have been studied and discussed. The rank was
based on the relative importance index of the factors ranking according to the type of
target group.
32
Table 11 Clients related factors
Response Group
Table 14 shows clients' related factors ranked by their combined value of the relative
importance index (RII). The first four most important CLR factors agreed by all
stakeholders are delay in progress payment to contractors, client’s ability to make project
decisions, client’s emphasis on low construction costs, and client’s interference during
construction, with the value of RII of 0.493, 0.41, 0.638 and 0.428 respectively. The
client’s emphasis on low construction costs is the most critical factor for both parties of
the project.
Contractor related factor RII Rank RII Rank RII Rank Rank
Table 16 shows contractor related factors ranked by their combined value of relative
importance index (RII). The five COR factors RII agreed by all stakeholders are
Contractor experience, Shortage of labour force, Site management & supervision,
Competence and commitment, and Contractor cash flow, with the values of 0.62, 0.59,
0.725, 0.598, and 0.585respectively. Site management & supervision is the most critical
factor for both parties of the project.
34
Table 14 Project procedure method
Project procedure method RII Rank RII Rank RII Rank Rank
Table 17 shows project procedure method related factors ranked by their combined
value of relative importance index (RII). The three PPR factors RII agreed by all
stakeholders are procurement method; contract administration and contract close out,
with the value of RII of 0.6125, 0.5325 and 0.53 respectively. The procurement
method is the most critical factor for both parties of the project.
External environment of site RII Rank RII Rank RII Rank Rank
Table 18. External environment related factors ranked by their combined value of
relative importance index (RII). The four EER factors RII agreed by all stakeholders
are the political environment, economic environment, social environment, and
physical environment of sites, with a value of RII of 0.733, 0.77, 0.503, and 0.575
respectively. The economic and political environments are the most critical factors for
both parties of the project with the highest RII.
35
Table 16 Equipment Related factor
Equipment related factors are ranked by their combined value of the relative
importance index (RII). Typically, construction equipment is used to perform
essentially repetitive operations, and can be broadly classified according to two basic
functions: first, operators, such as cranes, graders, etc.
In both cases, the cycle of a piece of equipment is a sequence of tasks which are
repeated to produce a unit of output. For example, install a wall panel.
The five EQR factors RII agreed by all stakeholders are shortage, efficiency, break
down, poor planning, and wrong selections, with a value of 0.567, 0.593, 0.503,
0.575, and 0.485respectively. Efficiency is the most critical factor for both parties of
the project in the EQR factors.
The table below shows the top ten individual factors from all groups that affect the
performance of construction projects in the EIAR
36
Table 17 The RII &Top five factors affecting the construction performance
All
EIAR Contractor
Response
Groups/Factors
Generally, results from the RII indicated that the factor Escalation of material price
has been ranked in the first position by contractors & the EIAR staff with a mean
score of 0.950. This result indicates the high importance of managing the escalation of
material prices to complete the project planned. This agreement of opinions proves
the importance of these factors in completing the project planned.
Table 18 : The relative importance index (RII) and rank of major groups
All
EIAR Contractor
Response
Factors
37
As shown in the table, material-related factors, the external environment of sites, and
contractor-related factors are the top three ranked factor groups that affect the
performance of construction projects in the EIAR.
Kolmogorov-Smirnova Shapiro-Wilk
Overall performance
of Construction
.233 80 .000 .893 80 .000
Projects
38
Figure 1Normal Q_Q plot
Above (fig2) shows that dots are not despersed along with the line. This indicates that
the data is not normally distributed. Having checked the remaining skewness and by
Kolmogorov-Smirnov & Shapiro-Wilk Tests, Visual Kurtosis inspection of their
histogram, normal Q-Q plots and box plots showed that their factor scores were not
normally distributed.
4.5.Correlations
To examine the presence of a relationship among the factors, correlation analysis was
done. Correlation Analysis is used to measure the association or relationship between
two or more variables (Marczyk, Dematteo & Festinger, 2005). The result of the
correlation measures the strength and direction of the relationship. Spearman’s
correlation method was preferred for this study.
39
negative relationship (disagreement). As the relationship gets weaker, the correlation
gets closer to zero.
To examine the presence of a relationship and the level of correlation between the
dependent variable (overall performance of construction projects) and independent
variables (Project characteristics related factors, Clint related factors, material related
factors, and contractor related factors, Project procedures, external environment, and
equipment factors), Spearman correlation was done.
Among the seven factors, the correlation of EER factors to the overall performance of
construction projects is shown below.
Correlations
Overall
EER4 Physical performance of
EER1 Political EER2 Economic EER3 Social environment of Construction
environment environment environment sites Projects
Spear EER1 Political environment Correlation Coefficient 1.000 0.184 0.051 0.210 .259*
man's
Sig. (2-tailed) 0.103 0.654 0.062 0.020
rho
N 80 80 80 80 80
EER2 Economic Correlation Coefficient 0.184 1.000 .409** 0.048 -.621**
environment
Sig. (2-tailed) 0.103 0.000 0.674 0.000
N 80 80 80 80 80
** ** **
EER3 Social environment Correlation Coefficient 0.051 .409 1.000 .356 -.323
Sig. (2-tailed) 0.654 0.000 0.001 0.004
N 80 80 80 80 80
EER4 Physical environment Correlation Coefficient 0.210 0.048 .356** 1.000 0.215
of sites
Sig. (2-tailed) 0.062 0.674 0.001 0.055
N 80 80 80 80 80
Overall performance of Correlation Coefficient .259* -.621** -.323** 0.215 1.000
Construction Projects
Sig. (2-tailed) 0.020 0.000 0.004 0.055
N 80 80 80 80 80
40
As shown in the table above, it is found that, there is very strong significant
correlation between test samples of EER1 (Economic environment) with (p= 0.000
and r=--0.621.So, there is a moderate negative relationship between independent
variables. Among the seven factors, MAR to the overall performance of construction
projects is shown below.
As exhibited in the table above, there is a moderate negative correlation between test
samples of MAR1 (Shortage of material) and MAR5 (Escalation of material price)
with (p=0.000 and r=-0.474**) and (p= 0.000 and r=-0.402**). So, there is a
moderate negative relationship between independent variables.
41
Table25 Model Fitting Information
Table 25 shows the model fitting information, i.e., it contains the result of the
comparison between the intercept only model (base model) and the final model which
contains all explanatory variables. The significance of the difference between the "-2
Log Likelihood" between the final and intercept only models is tested using a chi-
square test.
The smallest sig. value indicates that the final model gives a better improvement than
the intercept only model. The p-value of less than 0.001 shows that the model is a
very good finding on how well the model fits the data.
The next table in the output is the Goodness-of-Fit. This table contains Pearson's chi-
square statistic for the model (as well as another chi-square statistic based on the
deviance).These statistics are intended to test whether the observed data is consistent
with the fitted model. If we do not reject this hypothesis (i.e. if the p value is large),
then we conclude that the data and the model predictions are similar and that we have
a good model.
Table26 Goodness-of-Fit
Chi-Square df Sig.
The above Table 26 indicates the Pearson chi-square and deviance. It helps to test the
hypothesis H0: the fit is good vs H1: the fit is not good. The large sig. value (P=1)
implies we do not reject H0, which implies that our model fit is good.
42
In linear regression, R 2 (the coefficient of determination) summarizes the proportion
of variance in the outcome that can be accounted for by the explanatory variables,
with larger R 2 values indicating that more of the variation in the outcome can be
explained up to a maximum of 1. For logistic and ordinal regression models, it is not
possible to compute the same R2 statistic as in linear regression, so three
approximations are computed instead.
Pseudo R-Square
Nagelkerke 0.999
McFadden 0.994
The table above contains the values of three pseudo R-square values. High values of
R2 indicate that the model well explains the data. All the pseudo R-square values
considered in this study (Cox and Snell, Nagelkerke, and McFadden) have R 2 values
greater than 0.9. This indicates that the explanatory variables considered in this study
explain most of the variations, or, in other words, the explanatory variables in this
study are a good predictor of the outcome variable.
43
Table 28 Parameter Estimates
95% Confidence
Interval
Threshold [OVAP =
-61.128 95.847 0.407 1 0.524 -248.985 126.729
1]
[OVAP =
-38.459 59.452 0.418 1 0.518 -154.984 78.065
2]
[OVAP =
-19.447 31.323 0.385 1 0.535 -80.838 41.945
3]
[OVAP =
13.869 25.785 0.289 1 0.591 -36.670 64.408
4]
COR
-12.796 19.997 0.409 1 0.522 -51.989 26.396
44
0.013). On the other hand, the result of analysis indicated that CLR scores (p-value =
0.044). PPR scores (p-value = 0.000) and COR scores (p-value = 0.007)
Project procedure related factors are also among the factors that affect the project
performance of the EIAR construction projects with the RII equals 0.613 and 0.533
are procurement method and contract administration respectively. The most important
top two project characteristics related factors that affected project performance of the
EIAR were the shorter completion period given for the contract with RII equals to
0.608 and the nature of the project with RII equals to 0.568.
Equipment factors also affect the performance of the EIAR construction projects.
Their top two influential factors were efficiency (RII equals 0.593) and poor planning
for equipment (RII equals 0.575 respectively. Finally, the clients' related factors that
affected the project performance of the EIAR construction projects were the client’s
emphasis on low construction costs and the delay in progress payment to contractors
with RII equals 0.638 and 0.493 respectively.
The main factors from all listed variables were analysed. Based on this, the top ten
most significant factors affecting construction project performance in the EIAR were
discussed in detail below.
46
The escalation of material prices has been ranked in the first position by contractors &
the EIAR staff with a mean score of 0.950. The result is in line with Enshassi et al
(2009), Wiguna and Scoot (2005). The escalation of material prices was one factor
that contributed and had a significant impact on construction performance. All
construction bids in the EIAR are based on a fixed price. These prices are determined
by material prices which are estimated prior to the beginning of the project. It is not
uncommon for material prices to fluctuate dramatically from the time of bid to the
time of completion. Over the past year, the volatility of construction materials prices
has wreaked havoc on construction budgets and caused many disputes between
contractors and the EIAR.
In addition to this, the shortage of materials and material changes, which ranked (5th)
and 6th, led to difficulty anticipating and managing the cost of materials for the
project and made group material related issues rank as the 1st major factor affecting
project performance of the EIAR? This rank was supported by the ordinal regression
results.
The economic environment has been ranked in the 2nd position by contractors and the
EIAR staff with a mean score of 0.770. Construction is naturally volatile and it is
highly responsive to the fluctuation in both customer and business confidence.
Sustained low economic growth typically leads to a construction recession and high
economic growth leads to a rapid acceleration of construction activity. The result is in
line with (odeh and Battaaineh). A challenging task for any project manager is to
ensure that a project is financially viable in a fluctuating economic environment.
Since the periodic economic cycle significantly affects the performance of
construction, accurate forecasting of economic trends, both local and global, is
important. In an economic downturn, fewer construction jobs mean less business for
suppliers, which could drive prices higher or force suppliers out of business. When
suppliers are out of business, construction companies may be forced to pay more for
suppliers, making it more difficult for them to stay afloat.
The political environment has been ranked 3ed.with a mean score of.733. The
political environment is concerned with government policy and the effect of political
decisions on construction projects.
47
The significant roles played by the government in the construction industry are
regulators of the national economy, and regulators of the construction environment
and construction practices, among many others. In its capacity as regulators of the
construction environment, governments influence the development and building
approval processes and enforce compliance with Acts and Regulations. As observed
by Mansfield (1994), governments may also invoke their powers to initiate or stop
projects on political, social, and environmental grounds. Political stability, national
unity and good political leadership are thus crucial to national development. Uncertain
environment, such as unstable government, unpredictable shifts in the economy, and
unexpected changes in consumer demand.
The main reason associated with this is that in the last two to three years, the country's
unstable political environment has affected the free flow of people and materials as
needed. This result agrees with Saleh Samir Abu Shaban (2008) as this factor affects
the schedule & cost performance of projects. A review of the results of hundreds of
World Bank projects by Youker (1992) indicated that success or failure often depends
on factors in the general environment outside the control of the project manager.
Site management & supervision has been ranked 4th with a mean score of 0.713. This
agrees with Akawak Endale, (2020). Sambasivan and Soon, (2007) identified that site
management and supervision are highly contribute to construction project
performance. Site management & supervision is a key to ensuring project
performance successfully. When there is good supervision, projects are done to the
design specifications and, therefore, work is not repeated due to incorrect installations
which have to be re-done. The gap in managing the project activities is reflected in
either poor quality of work, or unnecessary additional costs to the project. This result
is in agreement with Adnan Enshassi, (2010) that it affects strongly the project
performance.
The client’s emphasis on low construction costs is ranked 6th and the procurement
method is ranked 7th with a mean score of 0.6375 and 0.6125 respectively. Even
though the variables are groped in different groups, they are highly related.
48
Mostly, the preferred biding option of EIAR is the ‘traditional working process',
which always involves the lowest price. This procurement process has been working
for many years, so everyone knows how it works because it has been tried and tested.
However, this method forces contractors to price work at unrealistically low levels.
As it is impossible to maintain standards and make profits, the quality of work falls
and contractors become more eager to engage in legal battles to recover their ‘losses’.
Additionally, it does not deliver cost savings, but in fact, is more likely to result in
cost and time overruns, leading ultimately to poor value for money and greater whole-
life costs in the maintenance and operation of assets.
The shortest completion period given for the contract has been ranked 8th with a
mean score of 0.6025. This is in line with the study by Long (2004). He identified that
inaccurate time estimating contributes to the causes of delays in construction projects.
Time estimates are important as inputs into other techniques used to manage and
structure all projects. An inaccurate time estimation technique may cause a project
delay. For instance, in some delayed projects, the contractor does not allow time for
some common problems that always happen during the construction stage, such as
breakdown of equipment, missing deliveries of supplies, accidents and emergencies,
and so on. Because of this problem, the actual time run out from the estimated. So, the
whole project performance is affected.
Competence and commitment of the contractor has a mean score of 0.5975. The
presence of competent and experienced project managers ensures the leading of a
process of construction project implementation. This also guarantees a proper
program of work which should be followed by the commitment of contractors. Due to
their close involvement with site activities, supervisors’ management efforts impact
directly on the productivity and final quality of the work they are responsible for.
Their performance is thus of particular importance for achieving a project’s
objectives.
Poor planning for acquiring and using project machinery and equipment has a mean
score of 0.595. The term planning is being used in many ways and different contexts,
but here it is explained as planning for acquiring and using project machinery and
equipment. This is in line with the study of Ogunlana (1998), who mentioned that
frequent breakdowns and poor planning are the most significant factors that contribute
49
to the performance of construction. Once machinery breaks down, the work stops
immediately and cause some work delays. Finally, the whole project performance is
affected.
From the result of ordinary regression case processing summary, the selected factors
are extremely significant for EIAR construction projects (12.5%). A total of 97.5% of
respondents believed that the construction performance of EIAR was affected
negatively by the selected factors.
Additionally, the model fitting information showed a p-value of less than 0.001. This
demonstrated that the model was a very good finding in how well it fits the data
factors considered in this study.
The output is the Goodness-of-Fit These statistics are intended to test whether the
observed data is consistent with the fitted model. Pearson's chi-square statistic for the
model from the result showed that the data and the model predictions were similar and
that we have a good model. The three pseudo high values of R2 indicate that the
model well explained the data. All the pseudo R-square values considered in this
study (Cox and Snell, Nagelkerke, and McFadden) have R2 values greater than 0.9.
This indicates that the explanatory variables considered in this study explain most of
the variations, or, in other words, the explanatory variables in this study were a good
predictor of the outcome variable.
The odds of the overall performance of construction projects being affected increased
by a factor of 3.54, 3.30, 2.47, and 1.05 for MAR, PCR, EER, and EQR, respectively.
For CLR, PPR and COR, the odds decreased by a factor of 0.43, 0.33 and 0.32,
respectively.
50
The negative parameter estimates imply that as sores increase on an independent
variable, there is a decreased probability of falling at a higher level of dependent
variable. This is true for CLR, PPR and COR due to their negative parameters.
The Material Related factor is ranked as the most significant independent variable
with an estimated result of 3.54.. Which means
1 unit of increase in material related factors affects project performance by 3.54 The
same is true for EER and PCR, respectively, due to their positive variable estimates.
51
CHAPTER 5
CONCLUSION AND RECOMMENDATIONS
5.1 Introduction
This chapter explained the discussion of key findings, conclusion drawn from the
findings and recommendation made regarding the study. The conclusions and
recommendations drawn were focused on addressing the objective of the study.
From a literature review under seven independent variables, 31 factors were selected
and distributed to respondents. Based on the perceptions of the respondents, factors
were analysed and ranked using the relative importance index (RII) method to identify
the most influential factors that affect the performance of construction projects. Based
on the overall RII rankings, material related issues are the key factors that affect the
project performance of the EIAR. The external environment of sites and contractor
related factors are other major factors that affect project performance in the EIAR.
These RII ranks were supported by the ordinal regression results.
52
5.3. Conclusion
Conclusion of the study can be made based on the results found, their interpretation
and discussion of the questionnaire and statistical analysis in accordance of the
research question.
In relation to the objective of this research, it was shown that the factor escalation of
material price has been ranked in the first position by contractors and the EIAR staff
with a mean score of 0.950. This result indicates the high importance of managing the
escalation of material prices to complete the project as planned. This agreement of
opinions proves the importance of these factors in completing the project as planned.
In relation to the problem stated in the research, the results showed that the top five
crucial factors influencing the success of the EIAR construction projects are the
following: increasing material prices, the political and economic climate, a shortage
of materials, site management, and supervision. As a result, the escalation in material
prices, which has a RII of 0.95, stands out as one of the material-related factors that
had the greatest impact on the EIAR projects' performance to complete projects on
time and on budget.
5.4. Recommendation
Based on the conclusions reached, the following recommendations are provided to
improve the performance of construction projects in the EIAR. Changes in material
prices pose a significant risk to the parties involved in any construction project. In any
event, the better practice is to specifically address price escalations going forward to
mitigate these risks.
Proactively including cost adjustment for an escalation clause in the EIAR
construction contract agreements is vital. Mitigating the effects of price escalations
should start in the bidding process. During the bidding phase of a project, identifying
materials most susceptible to price volatility and considering possible changes will set
aside contractors from the small risk of escalated material prices. Therefore, it is
better to address price escalations during the bidding process and include for price
escalation adjustments clauses in the construction contracts going forward to mitigate
these risks. Following price adjustment clauses, an adequate contingency allowance`
53
has to be allocated on the EIAR side in order to cover escalation for certain specified
material costs.
A good understanding of the different features and factors within the environment that
can have an effect on the project is essential. Therefore, contractors should need the
most accurate forecasting of economic trends both locally and globally. This is
important in their cost estimation in order to overcome gaps caused by materials
shortages. Due to intertwined security problems that require being resolved, political
decisions and considerations of the ongoing external environment, especially the
political and business environment, are important to improve the performance of the
construction projects.
Further study should be conducted into the factors affecting project performance in
the EIAR construction projects regarding project cost overrun, project schedule
delays, and project quality by the capital & external project funds using inferential
statistics in order to enhance generalizability of factors affecting projects across the
sector. The built environment, in line with continuous site supervision, could improve
the performance of construction projects.
54
References
Abdel-Razek, R.H., El-Dosouky, A.I. and Solaiman, A.M. (2001), “A Proposed Method to
Measure Quality of the Construction Project”, International Exhibition Conference for
Building & Construction, Egypt.
Adnan Enshassi., Sherif Mohamed. & Saleh Abushaban. (2009) “Factors Affecting the
performance of Construction Projects in the Gaza Strip”, journal of civil engineering and
management. 15(3), 269–280.
Africa Development And Resource Research Institute (ADRRI) PISSN: 2343-6662 ISSN-L:
2343-6662 VOL. 5,No.5(2), pp 74-91, February, 2014
Akawak Endale(2020) Assessment factors affect ing project performance: A Case Study of
Bishoftu Town Cobblestone Constructionprojects
Akintola Akintoye, 2000. "Analysis of factors influencing project cost estimating practice
Aoieong, R.T., Tang, S.L. & Ahmed, S.M. (2002) "A Process Approach in Measuring Quality
Costs of Construction Projects: Model Development", Journal of Construction Management
and Economics, Vol.20, No. 2, pp.179-192.
Atkinson, A.A., Waterhouse, J.H. & Wells, R.B. (2007) "A Stakeholder Approach to Strategic
performance measurement", Sloan Management Review, Vol.38, No. 3, pp.25 37.
Barrett, P. (2000), “Systems and Relationship for Construction Quality”, International Journal
of Quality & Reliability Management, Vol.17 No. 4/5, PP.377-392.
Barrie, D.S. and Paulson, B.C (1992), “Professional Construction Management”, McGraw-
Hill.
55 | P a g e
Belassi, Walid & Tukel, Oya. (1996). A New framework for determining critical
success/failure factors in projects. International Journal of Project Management. 14.
Carden, L., & Egan, T. (2008). Does our literature support sectors newer to project management? The
search for quality publications relevant to nontraditional industries. Project Management Journal, 39(3),
Chan, A.P. and Tam, C.M. (2000), “Factors Affecting Quality of Building Projects in Hong
Kong”, International Journal of Quality & Reliability Management, Vol.17 No. 4/5, PP.423.
Cresswell, J. W. (1998). Qualitative inquiry and research design: Choosing among five
traditions. Thousand Oaks, CA: Sage Publications.
Davis, K., Ledbetter, W.B., and Burati, J. (1989),”Measuring Design and Construction Quality
Costs” Journal of Construction Engineering and Management, Vol.115, No.3.
Dissanayaka Sunnil M. and Kumaraswamy Mohan M., (1999), Comparing contributors to time
and cost performance in building projects, Building and Environment. In Hong kong building
projects
Fellows, R. and Liu, A. (1997), “Research Methods for Construction”, Blackwell Science Ltd.
56 | P a g e
Hiwot B. Gemeda: Thesis Effect of poor project performance on the quality of
housingconstruction: Case of condominium houses in Addis Ababa Quote from interview with
Mr. Haile, Addis Ababa City Administration
Jha, K.N. & Iyer, K.C. (2005) "Factors affecting cost performance: evidence from Indian
construction projects", International Journal of Project Management, Vol. 23, No. 4, pp.283.
Jugdev, K., Mathur, G., and Fung, T.S. 2007. “Project management assets and their
relationship with the project management capability of the firm”. International Journal of
Project Management,
Juran, J.M and Gyrna, F.M. (1999), “Quality Planning and Analysis”, McGraw-Hill.
Kim, D.Y., Han, S.H., Kim, H. & Park, H. (2008) Structuring the prediction model of project
performance for international construction projects: A comparative analysis, Expert Systems
with Applications, Vol. 36, No. 2, pp. 1961-1971.
Low, S.P. and Peh, K.W. (1996), “A Framework for Implementing TQM in Construction”, The
TQM Magazine, Vol. 8, No.5, PP.39-46.
57 | P a g e
Marczyk, Dematteo & Festinger, (2005). Marczyk, Dematteo, & Festinger. (2005). Essentials
of research design and methodology. Johnwiley and Sons,Inc, Hoboken, Newjersey and
Canada
Mesfin Habtemariam ,(2019). Factors Affecting the construction project s performance In the
Cause of save the children.
Muhammad Saqib, Rizwan U. Farooqui, Sarosh. H. Lodi. 2008. "Assessment of Critical
Success Factors for Construction Projects in Pakistan." Karachi, Pakistan.
Navon, (2005). Bindpobikation,Bidfag till tidsskrift, The Biodiversity library Work.
N.R. Mansfield, O.O. Ugwu, T. Doran. (1994 ), Causes of delay and cost overruns in Nigerian
construction projectsInt. J. Proj. Manag., 12 (4) (p. 25
Nee, P.A. (1996), “ISO 9000 in Construction”, John Willy & Sons, Inc. Olomalaiye, P.,
Jayawardane, A. (1998), “Construction Productivity Management”, Addison Wesley Longman.
Ogunlana (1998) Problems causing delays in major construction projects in Thailand. School
of Engineering, Asian Institute of Technology, Bangkok, Thailand
58 | P a g e
Owusu Tawiah, (1999), Factors affecting the performance of Ghanaian owned construction
firms. Unpublished Msc. Thesis, Dept. of Building Technology, Knust, Kumasi
Koushki, (2005),Dtelay and cost increase in the construction of privet residential projects in
Kuwait
Pyzdek, T. and Berger, R.W (1996), “Quality Engineering Handbook”, Tata McGraw-Hill.
Reichelt Kimberly and Lyneis James, (1999), the dynamic of project performance:
Benchmarking the drivers of cost and schedule overrun, European management journal.
R. Youker , (1992 Nov), Managing the International Project EnvironmentInt. J. Proj. Manag.,
10 (4) Strip pp. 219-226
Sambasivan and Soon, (2007)Causes and effects of delay in Malaysian construction industry
Saleh Samir Abu Shaban (2008) Factores Affecting the performance of construction in the
Gazza
Ugwu O.O. and Haupt T.C., (2007), Key performance indicators and assessment methods for
infrastructure sustainability - a South African construction industry perspective, Building and
Environment, Vol. 42, PP. 665
59 | P a g e
60 | P a g e
Questionnaires
Dear Respondents,
To successfully undertake this research, it is mandatory to look into the issues from different
perspectives by involving professionals who have involvement in the construction projects. In
this respect, you are the one who can give the correct and necessary information. Hence, I
kindly request you to take time and give your honest answers to the questions listed below.
I would like to confirm you that your response designed to gather information on the research
title “Factors Affecting project performance in the case of Ethiopian Agricultural Research
Institute. The study is being carried out for a research project in partial fulfilment of the
requirements for the award of degree will be kept strictly confidential. The result shall be used
for academic purposes and the final recommendation and finding shall be forwarded to the
respective office of EIAR for their preventive measure and actions. Besides, your quick
response is vitally important in order to complete the research timely and I would appreciate if
you return the completed questionnaire within a week of your receipt of the same.
Thank you very much for your time and cooperation and looking forward to receiving your
response.
Yours Sincerely,
Eyob Sisay
Addis Ababa
61 | P a g e
Part One: General Information of the Respondent Please tick ( √) the appropriate box
to indicate your answer.
Male [] Female [ ]
Others []
62 | P a g e
Part Two: Factors Affecting the Performance of Construction Projects
1. There are a number of factors affecting the performance of construction projects. From
your experience, please express your opinion on the importance of the following factors.
To what extent do they affect the performance of construction projects in the EIAR?
63 | P a g e
3.Material related factors
Extremely Very Moderately Slightly Not
Lists of Factors Significant Significant Significant Significant Significant
(5) (4) (3) (2) (1)
Shortage of material
Material change
Low quality material selection
Lack of project material
management system
Escalation of material price
Contractor experience
Shortage of labor force
Site management & supervision
Competence and commitment
Contractor cash flow
Procurement method,
Contract administration
Contract close out
Political environment
(political interference, political
conflicts &instabilities, vandalism etc.
64 | P a g e
Economic environment
exchange rate, inflation, price
escalation etc.
Social environment
Diversity with employees, customs,
norms, values, educational level,
attitude towards social responsibility
etc. of the society within which the
projects undertake
7.Equipment factor
Extremely Very Moderately Slightly Not
Lists of Factors Significant Significant Significant Significant Significant
(5) (4) (3) (2) (1)
Shortage
Efficiency
Break down
Poor planning for acquiring &
using of project equipment
Wrong selection
Perceived Overall
executed construction
project performance
considering the above
factors
65 | P a g e
Appendix
For Project characteristics RII Rank RII Rank RII Rank Rank
related factors
Type of project (Building or infrastructure) 0.57 17 0.41 23 0.53 21 3
N 80 80 80 80 80 80
66 | P a g e
MAR2 Correlation 0.176 1.000 0.063 0.048 -0.008 -0.174
Material Coefficient
change
Sig. (2- 0.118 0.578 0.669 0.942 0.124
tailed)
N 80 80 80 80 80 80
N 80 80 80 80 80 80
N 80 80 80 80 80 80
N 80 80 80 80 80 80
N 80 80 80 80 80 80
67 | P a g e