Reference Contract Abic SW 2018 C 071118
Reference Contract Abic SW 2018 C 071118
O
C
E
C
EN
ABIC SW 2018
R
Contract Price: $
EF
Owner:
Contractor:
R
Site:
R
EF
ER
EN
C
E
C
O
PY
Table of contents
Schedules F The site
F1 Owner to give contractor possession of the *site................ 28
1 Schedule 1 – Contract information .........................................1
2 Schedule 2 – Special conditions...............................................7 F2 Contractor’s obligations in relation to the *site ................... 28
F3 Owner warrants that it has given contractor the
3 Schedule 3 – Order of precedence ..........................................9
4 Schedule 4 – Site information ............................................... 11 *site information .................................................................... 28
5 Schedule 5 – Form of guarantee .......................................... 12 F4 Contractor to examine the *site information ....................... 28
F5 If contractor discovers a *latent condition or
6 Schedule 6 – Provisional sums .............................................. 13
7 Schedule 7 – Prime cost sums .............................................. 14 *valuable item ........................................................................ 29
8 Schedule 8 – Items to be supplied by the owner ................ 15 F6 Architect to instruct in relation to a *latent condition
or *valuable item ................................................................... 29
A Overview F7 Contractor to claim for *latent condition or
*valuable item ........................................................................ 29
A1 Cooperative contracting........................................................ 16
A2 Obligations of the contractor................................................ 16
G Building the works
PY
A3 Warranties by the contractor ............................................... 16
G1 Owner’s obligations ............................................................... 30
A4 Obligations of the owner ...................................................... 17
A5 Warranties by the owner ...................................................... 17 G2 Contractor’s obligations......................................................... 30
A6 Architect to administer contract .......................................... 18 G3 Contractor to appoint representative................................... 30
G4 Subcontracting ....................................................................... 30
A7 Architect’s instruction ........................................................... 18
A8 Disputing architect’s certificate or written decision ........... 18 G5 Contractor to give program to architect............................... 30
A9 Disputing architect’s failure to act........................................ 18 G6 Contractor to give updated program .................................... 30
O
A10 Failure to give certificate, decision or notice ....................... 19 G7 Architect may instruct opening up or testing of *works...... 31
A11 Compensation is sole remedy............................................... 19 G8 Contractor entitled to claim cost of opening up or testing . 31
G9 Contractor entitled to unfixed, demolished materials......... 31
B Documents H Claims to adjust the contract
C
B1 Discrepancies or omissions in documents ........................... 20
H1 Time for making a *claim to adjust the contract.................. 32
B2 Order of precedence of documents ..................................... 20
B3 Contractor and owner must supply copies of H2 Details required for claim ...................................................... 32
*official documents ............................................................... 20 H3 Architect to assess claim........................................................ 32
H4 Architect to give assessment ................................................. 33
C Security
C1 Security provided to owner .................................................. 21
E H5
H6
Sum recoverable for claim for *adjustment of time costs ... 33
Architect may adjust contract in absence of claim .............. 33
C2 Security to owner by cash retention .................................... 21
J Variation to the works
C
C3 Security to owner by *unconditional guarantee ................. 21
C4 Owner’s right to draw on security provided to it ................ 21 J1 Architect may instruct *variation to the *works .................. 34
J2 Contractor to review instruction ........................................... 34
C5 Procedure for owner to draw on security provided
................................................................................................ 21 J3 Architect to instruct whether *variation is to proceed ....... 34
EN
PY
M13 Defects liability period ........................................................... 42
M14 Contractor’s obligations during and after defects S Definitions 54
liability period ......................................................................... 42
O
N2 Owner’s obligation to pay *contract price............................ 43
N3 Progress claims – procedure for contractor ......................... 43
N4 Progress claims – procedure for architect ............................ 43
N5 *Tax invoice ............................................................................ 44
C
N6 Certificates – obligation to pay.............................................. 44
N7 Before making first progress payment.................................. 44
N8 If architect fails to issue certificate ....................................... 44
N9 Contractor entitled to make claim ........................................ 45
N10 Final claim – procedure for contractor ................................. 45
N11
N12
Final certificate – procedure for architect ............................ 45
Final certificate – *tax invoice ............................................... 45
E
N13 Final certificate – obligation to pay ....................................... 46
N14 Effect of final certificate......................................................... 46
C
N15 Interest on overdue amounts................................................ 46
P Dispute resolution
EN
Q Termination of engagement
R
Registration/licence no:
Representative:
PY
Address for notices:
O
Email:
Mobile:
C
Telephone:
Facsimile: E
If the *party is an individual, individual trustee,
partnership or unincorporated association
C
Signed by *party:
EN
Signed by witness:
Name of witness:
Date of signing:
R
(if applicable)
Signed by:
R
Signed by:
Capacity: Officer / Director / Sole Director Officer / Director / Sole Director
Print name:
Date of signing:
Representative:
Address:
PY
Email:
Mobile:
Telephone:
O
Facsimile:
C
Clause A6
Name:
Registration number
Representative:
E
C
Address for notices:
EN
Email:
Mobile:
Telephone:
R
Facsimile:
E
Plus *GST $
*Contract price $
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 2 ABIC SW 2018
Contract information – Schedule 1
Item 5 The *works
Clause A2
Brief description of the *works:
PY
Item 7a Is the contractor to give security to the
Clause C1 owner? Yes No
Strike out whichever doesn’t apply
O
Item 7b Cash Retention
Owner’s nominated type of security:
Clauses C1
Unconditional Guarantee
C
Strike out whichever doesn’t apply. If
neither selected, cash retention is default
Clause E1
Is the owner or the contractor to take out and
EF
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 3 Simple Works Contract
Schedule 1 – Contract information
Item 14 Amount to cover cost of demolition
Clause E4.1 and removal of debris
If nothing stated, 10% of the *contract price
PY
public liability insurance:
If nothing stated, $1,000.00
O
If nothing stated, $1,000.00
C
Clause H2 overheads and profit %
If nothing stated, 15%
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 4 ABIC SW 2018
Contract information – Schedule 1
Item 21 Other allowances for delay having regard to the
Clauses L2, L4 nature of the contract and the *works which do
not entitle *adjustment of time costs
Cause: Allowance (*working days):
PY
Item 22 Date for *practical completion
Clause M1
O
Item 23 Commissioning tests for *practical
Clause M1 completion
C
E
C
EN
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 5 Simple Works Contract
Schedule 1 – Contract information
Item 29 Governing law
Clauses P4, If nothing stated, the State or Territory where
P5, P6 and R8 the *site is located
PY
Item 30b *Official documents required to complete the
*works but to be obtained by the owner:
O
C
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 6 ABIC SW 2018
Special conditions – Schedule 2a
Special conditions
Item 3 of schedule 1
Clause B2
PY
O
C
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 7 Simple Works Contract
Schedule 2b – Owner occupier special conditions
The owner remains in occupation
Item 3 of schedule 1
These special conditions only apply for projects where the owner will remain in occupation
during construction:
Replace the words “ possession of ” with the words “ access to ” in the following
subclauses:
PY
A2.1a
A4.1c
D1.1
D1.4c
O
E1.1
E2.1
E5.1a
C
E6.1a
F1.1
G5.1
L1.1b
E
C
Replace clause D3.1 with the following:
EN
Subject to clause D4, from 4.00pm on the day the architect issues the notice of *practical completion,
the owner bears the risks described in the following clauses.
From 4.00pm on the day the architect issues the notice of *practical completion, the contractor ceases
to have access to the *works except by prior arrangement with the owner.
E
If the owner terminates the engagement of the contractor under clause Q1 or Q2 before *practical
completion, the owner may exclude the contractor from the *site.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 8 ABIC SW 2018
Order of precedence – Schedule 3
The order of precedence of *contract documents is:
Clause B2
PY
O
C
E
5. The drawings listed below:
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 9 Simple Works Contract
Schedule 3 – Order of precedence
PY
O
C
E
C
EN
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 10 ABIC SW 2018
Site information - Schedule 4
The *site information is:
Clause F3
PY
O
C
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 11 Simple Works Contract
Schedule 5 – Form of guarantee
Contractor’s *unconditional guarantee to the owner
Clause C3
[Insert name of owner, and ABN if owner is a company] of [insert address] (owner) has entered into a
written contract dated [insert contract date] with [insert name of contractor and ABN] of [insert address]
(contractor) for the construction of the works described in that contract. The contract states that the
PY
contractor may elect to give security for the performance of the contract in the form of an unconditional
guarantee.
[Insert name of security provider] unconditionally undertakes that if the owner gives it a written notice
stating the basis and extent of its entitlement to draw on the undertaking and the amount to which it is
O
entitled, the security provider will pay the owner the amount which the owner declares is due, up to a
maximum of the combined amount of [insert amount $AUD] (the Amount).
C
It is not the responsibility of the security provider to investigate the accuracy or the reasonableness of the
contents of the notice or the declarant’s capacity to give the notice. The security provider will make the
payments without further reference to the contractor, despite any notice by the contractor or any other
E
person to the security provider not to pay the whole or any part of the amount.
C
The security provider’s liability under this undertaking is not affected by any variation of the contract or
by any waiver by the owner of any default by the contractor.
EN
This undertaking remains in force until the first of the following events occurs:
• the owner notifies the security provider in writing that this undertaking is no longer required;
• the security provider pays the Amount to the owner ;
• the owner informs the security provider that the contractor has performed all its obligations and
paid all amounts required to be paid under the contract; or
R
This undertaking creates no rights in anyone except the owner and the owner’s successors and cannot be
E
assigned.
EF
Signed, sealed and delivered on behalf of [insert name of security provider] by its attorney [insert name
R
and address of attorney of security provider] declaring it has no notification of the revocation of the
power of attorney granted to it on [insert date] under which this undertaking is executed.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 12 ABIC SW 2018
Provisional sums - Schedule 6
*Provisional sums
Section K
PY
$
O
$
C
$ E
$
C
EN
$
E R
$
EF
$
R
† Note: If the owner intends on using a particular person to carry out the work for which a *provisional
sum has been allowed the name of that person should be shown above. If the identity of the particular
person is not known at the time that this contract is executed the intention to use a particular person
should be indicated by inserting ‘Yes’ above in the column headed ‘Particular person’.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 13 Simple Works Contract
Schedule 7 - Prime cost sums
*Prime cost sums
Section K
PY
$
O
$
C
$ E
$
C
EN
$
E R
$
EF
$
R
† Note: If the owner intends on using a particular person to carry out the work for which a *prime cost
sum has been allowed the name of that person should be shown above. If the identity of the particular
person is not known at the time that this contract is executed the intention to use a particular person
should be indicated by inserting ‘Yes’ above in the column headed ‘Particular person’.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
Simple Works Contract For definitions, see pages 54 to 56 Page 14 ABIC SW 2018
Items to be supplied by the owner - Schedule 8
Items to be supplied by the owner for incorporation in the *works
Clause N1
Items to be supplied by the owner and installed by the contractor (and only the costs of
installation are included in the *contract price):
PY
O
C
E
C
Items to be supplied and installed by the owner (and no allowance has been included in
EN
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials_________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 15 Simple Works Contract
A Overview
A
A1 Cooperative contracting
.1 Under this contract, the contractor and the owner must:
a act reasonably
b cooperate in all matters
c avoid obstructing the other and
d provide all reasonable assistance and cooperation to the other who is a claimant under
an insurance policy required by this contract.
.2 These obligations do not affect either *party’s rights or responsibilities under this contract.
PY
.1 The contractor must:
a begin the *works within 10 *working days after being given possession of the *site
b diligently carry out all *necessary work and complete the *works to the standard set out
in the *contract documents
O
c keep the *site and any area affected by the *works clean and tidy at all times
d comply with all instructions issued under this contract by the architect
e obtain all *official documents required under this contract to complete the *works, and
C
any shown in item 30a of schedule 1
f comply with all other obligations under this contract
g comply with all *relevant legislation
.2
h
E
bring the *works to *practical completion in accordance with clause M1.
If the contractor’s capacity to complete the *works is altered to the extent that it may be
unable to meet its obligations, it must immediately inform the architect and the owner in
C
writing.
.3 If relevant work health and safety legislation (WH&S legislation) requires it, the contractor:
EN
a acknowledges that the owner has engaged and appointed it under the WH&S
legislation as the principal contractor for the *works and
b will discharge the responsibilities imposed on it as the principal contractor under the
WH&S legislation.
b has the skill and the technological, human and financial resources necessary to
perform its obligations
EF
c is registered or licensed, as the case may be, in accordance with the *relevant legislation
to carry out the *works and the registration or licence number is shown in item 1 of
schedule 1
d has been allocated the Australian Business Number (ABN) shown in item 1 of
schedule 1 for taxation purposes and that it is registered for *GST
R
e will notify the owner *promptly of any change in its ABN, *GST registration, or the
status of its licence or registration to carry out the *works.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 16 ABIC SW 2018
Overview A
A4 Obligations of the owner
.1 The owner must:
a subject to subclause A2.1e, obtain and give to the contractor all *official documents
required to begin the *works and any shown in item 30b of schedule 1
b obtain from neighbouring owners all easements that are required before the *works can
begin
c give possession of the *site in accordance with this contract
d appoint an architect to administer this contract and provide appropriate *contract
documents for the *works, given the nature of the *works
PY
e indemnify the contractor for any liability incurred by the contractor to the extent that
the liability is a result of any default or negligence of the architect or any other
consultant the owner engages in relation to the *works
f issue instructions to the contractor only through the architect
g pay the contractor the *contract price as adjusted in accordance with this contract
O
h comply with all other obligations under this contract.
.2 If the owner’s financial position alters to the extent that it may be unable to meet its
obligations under this contract, it must immediately inform the contractor and the architect
C
in writing.
.3 If the owner does not own the property on which the *works are to be carried out, written
permission from the property owner for the *works to be carried out must be provided by the
owner to the contractor. The contractor is released from any obligations under the contract if
E
the owner fails to provide this written permission.
C
A5 Warranties by the owner
.1 The owner warrants that it has the financial resources necessary to perform its obligations.
EN
.2 If the owner has financed the *works using a lending institution, the owner warrants that the
institution is shown in item 1 of schedule 1.
.3 If the owner has shown an Australian Business Number (ABN) in item 1 of schedule 1, it
warrants that:
a the ABN is correct
R
a appoints the contractor as the principal contractor for the *works as defined in the
WH&S legislation
EF
b authorises the contractor to have management and control of the workplace and to
exercise such authority of the owner as is necessary to enable the contractor to
discharge the responsibilities imposed on the contractor as the principal contractor
under the WH&S legislation.
.5 The owner warrants that all *owner-specified materials comply with the *building code.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 17 Simple Works Contract
A Overview
A6 Architect to administer contract
.1 The architect for the purposes of this contract is shown in item 2 of schedule 1.
.2 The architect is appointed to administer this contract on behalf of the owner and the owner
warrants that the architect has authority to administer this contract.
.3 The architect is the owner’s agent for giving instructions to the contractor. However, in
acting as assessor, valuer or certifier, the architect acts independently and not as the agent of
the owner.
.4 The owner must ensure that the architect, in acting as assessor, valuer or certifier, complies
with this contract and acts fairly and impartially, having regard to the interests of both the
PY
owner and the contractor. The owner must not compromise the architect’s independence in
acting as assessor, valuer or certifier.
.5 The architect is not the owner’s agent for giving or receiving notices under clause A8,
clause A9, section P and section Q.
.6 If the architect resigns, or becomes incapable of acting as architect, or if the owner terminates
O
the engagement of the architect, the owner must immediately nominate another architect and
give written notice of the name and address of the architect to the contractor.
.7 If the contractor has no reasonable objection to the nominated architect, that person will be
C
appointed as the architect for the purposes of this contract.
.8 The newly appointed architect is bound by the written decisions of any previous architect.
A7 Architect’s instruction
E
.1 The architect may issue an instruction at any time during this contract provided that the
C
instruction is given in writing.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 18 ABIC SW 2018
Overview A
A10 Failure to give certificate, written decision or notice is not acceptance
.1 If the architect fails to issue a certificate, notice, written decision or written assessment
required under this contract in respect of a claim, this does not mean that the claim has been
accepted or is valid.
PY
O
C
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 19 Simple Works Contract
B Documents
B
PY
a any special conditions shown in schedule 2a
b any owner occupation special conditions shown in schedule 2b
c the conditions set out in this contract and schedule 1
d the specifications for the *works in the order shown in schedule 3
e the drawings for the *works shown in schedule 3
O
f any other document in the order shown in schedule 3.
.2 Large scale drawings take precedence over small scale drawings.
.3 An instruction from the architect to resolve a discrepancy, an ambiguity, or an omission that
C
is not in accordance with the order of precedence referred to in clause B2, is an instruction
for a *variation.
a any report, notice, order, permit, licence, approval or other document required or
issued by an *authorised person in relation to the *works
b any document listed in item 30 of schedule 1
c any statutory approval
d an approval for provision of *infrastructure services to the *site
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 20 ABIC SW 2018
Security C
C
PY
10% of each progress payment until the value held equates to the percentage shown in item 8
of schedule 1 of the *contract price.
.2 The owner must hold the cash retention, including interest earned on it, less any bank fees or
charges on the account, as trustee for the contractor in a separate bank account.
.3 A legal or accounting practice’s trust account will not discharge the owner’s obligations
O
under clause C2.2.
C
.1 If the security provided by the contractor is *unconditional guarantees, the contractor must
within 10 *working days after this contract is executed give to the owner two *unconditional
guarantees each equal in value to the percentage shown in item 9 of schedule 1 of the
*contract price.
E
.2 An *unconditional guarantee is an unconditional undertaking or a performance undertaking
C
from a recognised financial institution approved by the owner. The guarantees must be of an
approved type. The type shown in schedule 5 is approved.
.3 If the owner is registered for *GST and able to claim an *input tax credit, the value of the
EN
*unconditional guarantees which must be provided to the owner is exclusive of the *GST
component of the *contract price.
a a certificate issued by the architect in favour of the owner under any of clause N4,
N11, Q9 or Q17 is not paid by the contractor within the period shown in item 10 of
E
schedule 1
b the contractor has not disputed the relevant certificate under clause A8 and
c the owner has complied with the procedure set out in clause C5.
EF
if the architect has issued a certificate in favour of the owner under clause Q9 or Q17.
.2 If the security is cash retention, the owner may then draw on the cash retention to the extent
of its entitlement.
.3 If the security is by *unconditional guarantees, the owner must first give to the security
provider a written demand for payment stating the amount of its entitlement.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 21 Simple Works Contract
C Security
C6 Owner’s release of security on *practical completion
.1 When the architect issues the notice of *practical completion, the contractor is entitled to the
release of 50% of the amount of the security then held.
.2 If the security is cash retention:
a the architect must give to the contractor a certificate equal to 50% of the amount of the
security then held at the same time that the notice of *practical completion is issued
b the contractor, on receiving the certificate, must prepare a *tax invoice in accordance
with clause N5 and give both documents to the owner for payment
c the amount stated in the certificate must be paid in accordance with clause N6.
PY
.3 If the security is by *unconditional guarantees, the owner must return one of the guarantees to
the contractor within the period shown in item 10 of schedule 1.
O
certificate under clause Q9 or Q17, as the case may be, the owner must release to the
contractor any remaining security for the whole less any amount owing to the owner under
C
the certificate.
.2 If the security is cash retention, the architect must take into account any remaining security
when preparing the final certificate.
.3 If the security is by *unconditional guarantee and:
a
E
the certificate is in favour of the contractor, the owner must give to the contractor the
remaining *unconditional guarantee within the period shown in item 10 of schedule 1
C
b the certificate is in favour of the owner, the certificate is evidence of the basis and
amount of the owner’s entitlement, and the owner may draw on the security under
clause C5 before returning the remaining *unconditional guarantee to the contractor
EN
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 22 ABIC SW 2018
Liability D
D
PY
the *site:
a the *works
b any *necessary work
c any structure on the *site before the time the contractor is given possession of the *site
d on-site materials or equipment intended to be incorporated in the *works, including
O
any item shown in schedule 8 and
e plant, tools and equipment.
C
D2 Indemnity before *practical completion
.1 While the contractor bears the risks described in clause D1, the contractor must indemnify
the owner in respect of any liability arising from negligence or breach of contract or breach of
E
statutory duty by the contractor or any of the contractor’s employees, agents, licensees or
subcontractors.
.2 The amount of the contractor’s indemnity to the owner is reduced to the extent to which the
C
owner or any of its employees or agents is responsible for the personal injury, illness,
disease, death or loss or damage.
EN
contribution or damages.
.1 Subject to clause D4, from 4.00pm on the day the architect issues the notice of *practical
completion, the owner bears the risks described in the following subclauses.
EF
.2 The risk of injury to, or illness, disease or death of any person on or in the immediate vicinity
of the *site.
.3 The risk of loss of, or damage to, the property of any person on or in the immediate vicinity
of the *site.
.4 The risk of loss of, or damage to, any of the following items on or in the immediate vicinity of
R
the *site:
a the *works and
b materials or equipment intended to be incorporated in the *works, including any
item shown in schedule 8.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 23 Simple Works Contract
D Liability
D4 Indemnity after *practical completion
.1 While the owner bears the risks described in clause D3, the owner must indemnify the
contractor in respect of any liability arising from negligence or breach of contract or breach of
statutory duty by the owner or any of the owner’s employees, agents or licensees.
.2 The obligation of the owner to indemnify the contractor is reduced to the extent to which the
contractor or any of its employees, agents or subcontractors is responsible for the personal
injury, illness, disease, death or loss or damage.
.3 Except if expressly provided otherwise in this contract, if the owner is to indemnify,
reimburse, pay a contribution or pay damages to the contractor under this clause or under
PY
any other clause, the amount the owner must pay the contractor is:
a reduced by any *input tax credit directly obtained or obtainable by the contractor and
b increased by *GST the contractor has paid or will pay on that indemnity,
reimbursement, contribution or damages.
O
D5 Reinstatement during period when contractor bears risk
.1 If an event occurs which causes loss or damage during the period when the contractor bears
C
the risk, the contractor must *promptly reinstate, at its own expense, the lost or damaged
items referred to in subclause D1.4.
.2 The owner must indemnify the contractor for the cost of reinstatement under this clause to
the extent to which the owner, its employees, agents or separate contractors was responsible
for the event which caused the loss or damage.
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 24 ABIC SW 2018
Insurance E
E
PY
*necessary work, on or in the immediate vicinity of the *site (except the *works, or
materials or equipment on the *site that are intended to be incorporated in the *works,
or plant, tools and equipment used on the *site).
.2 The policy must contain all terms required by law and the following terms:
a the insurance covers the interests of the owner, the contractor and any other person
O
involved in the *necessary work
b the insurer’s rights of subrogation against any insured are excluded (although this
exclusion may be limited to the right of subrogation against an insured to the extent of
C
that insured’s interest under the policy).
.2 The policy must contain any term required by law and each of the following:
a the insurance covers the interests of the owner and the contractor
b notice of a claim given by any one insured is effective in relation to each of the
insureds
c the insurer’s rights of subrogation against any insured are excluded (although this
R
exclusion may be limited to the right of subrogation against an insured to the extent of
that insured’s interest under the policy).
E
credit on the insurance premium within 20 *working days of the insurance being taken out.
Each *party must indemnify the other for any loss arising out of the *party’s failure to notify
the insurer. On request by a *party, the other *party must provide evidence that it has
complied with this clause.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 25 Simple Works Contract
E Insurance
E4 Insurance cover
.1 The insurance against loss of or damage to the items referred to in clause E2 must cover:
a the full reinstatement or replacement cost of the *works, materials and equipment on
the *site that are intended to be incorporated in the *works, and plant, tools and
equipment used on the *site
b additional consultants’ fees including the architect’s fees, relating to the reinstatement
or replacement for the amount shown in item 13 of schedule 1
c any necessary demolition and removal of debris, for the amount shown in item 14 of
schedule 1 and
PY
d all *GST associated with reinstatement and replacement of the *works.
.2 The insurance against liability for injury, illness, disease or death must be at least for the
amount shown in item 16 of schedule 1.
O
.1 If one of the *parties is required to take out and maintain either of the insurances under
clause E1 or E2, the other may do so if:
C
a the nominated party fails to satisfy the other *party that insurances under clause E1 or
E2, and complying with the required terms, are in place at the time possession of the
*site is given or
b the nominated party fails to comply *promptly with a request from the other *party for
E
either, a statement in writing setting out all the provisions of the insurances, or
insurance documentation to the satisfaction of the other *party or
C
c the nominated party fails to satisfy the other *party that the insurance remains in place.
.2 If the other *party takes out and maintains insurance under this clause and wishes to recover
the cost from the nominated party, it must submit to the architect a claim that sets out
EN
evidence of the premium cost. The architect must take the claim into account in preparing
the next certificate and adjust the *contract price accordingly.
done or not be done, which might affect any insured’s right to recover from the insurer in
respect of damage or liability covered by an insurance.
E
accordance with the statutory scheme that applies under this contract until the final
certificate for the *works is issued under clause N11. If that scheme does not provide for an
indemnity against a common law damages claim by a worker, the contractor must also
maintain insurance against that risk.
R
.2 The contractor must ensure that each of its subcontractors maintains similar insurances.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 26 ABIC SW 2018
Insurance E
E8 Insurance claims
.1 Subject to subclause E8.2, the contractor has the primary responsibility to make any claim
under an insurance policy required by this contract.
.2 The owner must make a claim if the owner, its agents, employees or licensees directly causes
the event giving rise to the loss.
.3 The following are the obligations of either the owner or the contractor when making an
insurance claim for any loss or damage arising from an insured event:
a the insurance claim must be made *promptly
b the *party making the insurance claim must provide all information which is required
PY
under the relevant insurance policy
c the *party making the insurance claim must *promptly notify the architect in writing on
becoming aware of the event giving rise to the insurance claim
d the notice must contain details of the insurance claim
e the *party making the insurance claim must *promptly give the architect any additional
O
information the architect reasonably requests.
E9 Payment of excess
C
.1 The *party making a claim under an insurance policy arranged under clause E1 or E2 must
pay the excess.
.2 The *party paying the excess may recover the excess from the other *party in proportion to
E
the extent to which the personal injury, illness, disease or death or loss or damage is the
result of negligence, or breach of contract or breach of statutory duty by the other *party. The
C
excess paid under clause E9.1 that is to be reimbursed, is the amount shown in item 16 of
schedule 1.
EN
*necessary work or materials or equipment on the *site that were, or were intended to be,
incorporated in the *works, as the case may be, to which the loss or damage occurred.
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 27 Simple Works Contract
F The site
F
PY
obtained by the contractor.
O
reasonable terms to the *site and all other places at which *necessary work is carried out in
relation to the *works by or on behalf of the contractor, after being given reasonable notice.
.2 If access to the site is given for the purposes in clause F2.1, the contractor may exclude from
C
the site, without prior notice, any person on the site who does not comply, or in the
contractor’s reasonable opinion may have not complied, with the contractor’s work health
and safety policies and procedures.
E
F3 Owner warrants that it has given contractor the *site information
C
.1 The owner warrants that it has given the contractor all the *site information in its possession at
least 5 *working days before the closing of tenders.
.2 *site information includes any reports, surveys, test results, plans, specifications, computations
EN
or other information such as foundations data, soils tests or geotechnical tests and any other
information regarding the *site and the physical conditions on and underlying the *site
shown in schedule 4.
.1 Before executing this contract, the contractor must have examined the *site information and
have inspected the *site and its surroundings and, having done so, is entitled to rely on the
E
*site information to the extent that it is reasonable to do so, having regard to the nature of the
*site and its surroundings.
.2 The contractor must indemnify the owner against a claim for any loss, expense or damage
EF
incurred by a subcontractor engaged by the contractor or any other person as a result of the
contractor failing to examine the *site information or inspect the *site.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 28 ABIC SW 2018
The site F
F5 If contractor discovers a *latent condition or *valuable item
.1 The contractor must notify the architect in writing and seek instructions within 5 *working
days if the contractor discovers:
a a *latent condition affecting the *site which the contractor considers may result in it
incurring loss, expense or damage, or may affect its ability to bring the *works to
*practical completion by the date for *practical completion as adjusted or
b a *valuable item on the *site.
.2 A *latent condition is a physical condition on, underlying or adjacent to the *site which a
competent contractor would not have anticipated if the contractor had examined the *site
PY
information and inspected the *site before executing this contract.
.3 A *valuable item includes minerals, money, treasure, fossils, archaeological remains, historic
objects or relics.
.4 Any *valuable item remains the property of the owner and the contractor must take all
necessary steps to avoid removal of, loss of, or damage to, any *valuable item.
O
F6 Architect to instruct in relation to a *latent condition or *valuable item
C
.1 The architect must *promptly give the contractor a written instruction regarding a *latent
condition or *valuable item.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 29 Simple Works Contract
G Building the works
G
G1 Owner’s obligations
.1 The owner must give the contractor the necessary information to allow the contractor to
properly set out the *works including sufficient information to locate a reference set-out
mark.
G2 Contractor’s obligations
.1 The contractor must:
a set out the *works and have the setting out certified by a licensed surveyor
b direct the manner of performance of the *necessary work
PY
c supervise the *necessary work competently
d maintain satisfactory industrial relations in relation to the *works
e maintain compliant work health and safety on the *site.
O
.1 The person named as the contractor’s representative in item 1 of schedule 1 is the
contractor’s representative for the purposes of this contract, particularly for receiving
C
instructions from, and giving information to, the architect. The contractor may change its
representative by giving written notice to the architect.
.2 The contractor must ensure that a contractor’s representative is appointed at all times.
E
G4 Subcontracting
.1 The contractor may subcontract any part of the *works, but not the *works as a whole. The
C
contractor is liable for the *necessary work done by its subcontractors.
.2 The contractor must take responsibility for any acts and omissions of its suppliers and
subcontractors in relation to the *works.
EN
.3 The relevant provisions of this contract must be included in contracts the contractor makes
with its suppliers or subcontractors. The contractor must fully inform all potential suppliers
or subcontractors of the contractor’s relevant obligations under this contract.
.1 The contractor must give the architect a program within 10 *working days after being given
possession of the *site. The program must include each of the following:
E
a the dates of commencement and completion of the major stages of the *works
b the date for *practical completion
EF
.1 The contractor must give the architect an updated program when the date for *practical
completion has been adjusted by 5 *working days or more or such other period as agreed. The
updated program must indicate how the previous program has been affected by any
adjustments of time.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 30 ABIC SW 2018
Building the works G
G7 Architect may instruct opening up or testing of the *works
.1 The architect may at any time give to the contractor a written instruction to open up or carry
out tests on elements of the *works other than as required by the *contract documents. The
contractor must *promptly comply with the instruction.
PY
.2 The requirements for making a *claim to adjust the contract and the procedures to be followed
are stated in section H.
O
.1 The contractor owns and will own the following:
a all demolished materials, and
b all unfixed materials supplied by the contractor, but only until the owner has paid for
C
the materials.
.2 Clause G9.1 applies unless the *contract documents state otherwise.
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 31 Simple Works Contract
H Claims to adjust the contract
H
PY
these purposes, an event is not a consequence of an instruction.
.2 If the claim results from an instruction to proceed with a *variation, the requirements for
submission of the claim are set out in clause H2.
.3 If the claim results from a delay in the progress of the *works, the contractor is not required to
give the first notification required under subclause H1.1, but the detailed claim must be
O
submitted within 20 *working days after the delay ends.
C
.1 A *claim to adjust the contract must contain the following details:
a identification of the architect’s instruction that caused the claim or, if none has been
issued, details of the event and the basis for the claim
b
E
a breakdown, on a trade by trade basis, of any extra costs or savings including
.1 the cost of relevant preliminaries and
.2 the allowance for contractor’s overheads and profit at the rate shown in item 17
C
of schedule 1
c reference to the rates and unit prices in any bill of quantities, if applicable
EN
architect must consider the detailed claim submitted by the contractor and any further
information the architect requests the contractor to supply.
EF
.2 If the architect needs additional information to assess the claim, the architect must issue a
written request to the contractor.
.3 The contractor must *promptly give to the architect any additional information the architect
reasonably requests.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 32 ABIC SW 2018
Claims to adjust the contract H
H4 Architect to give assessment
.1 The architect must, within 20 *working days after receiving the claim, issue to the contractor
and to the owner its written decision specifying any adjustment to the *contract price or any
adjustment to the date for *practical completion, or both.
.2 The contractor may dispute the architect’s decision or a failure to issue a decision issued
under this clause in accordance with clause A8 but, in accordance with clause P1, must
continue to perform its contractual obligations.
PY
.1 If a sum or sums per day is shown in item 18 of schedule 1, a claim by the contractor is
limited to that sum. If no sum or sums per day is shown, the contractor is entitled to an
adjustment to the *contract price equal to the loss, expense or damage it incurs as a result of
the approval of an adjustment by the architect to the date for *practical completion.
O
H6 Architect may adjust contract in absence of claim
.1 If the contractor has not made a *claim to adjust the contract in relation to any change which
C
results from complying with any instruction given under section J for a *variation or from
causes of delay noted in clause L1 or L2, the architect may adjust the contract at any time up
to the issue of the final certificate under clause N11, or a certificate under clauses Q9 or Q17.
E
C
I
I Not used
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 33 Simple Works Contract
J Variation to the works
J
PY
c a detailed quotation for the whole of the cost of the *variation or part of a *variation and
the effect on the date for *practical completion.
.3 The contractor may request an instruction from the architect if it considers that a *variation
may be required. A request by the contractor under this clause must be in writing.
O
.4 A *variation is a change to:
a the scope of the *works as contemplated by the *contract documents and capable of being
executed under this contract
C
b a dimension or level of the *works
c the materials, workmanship or quality of any part of the *works
d a detail of the *works or
e the order of precedence of the *contract documents referred to in clause B2.
.5
E
If the contractor receives an *official document which requires a *variation, the procedures in
clauses J6 to J8 apply.
C
J2 Contractor to review instruction
.1 The contractor must review any written instruction issued by the architect under clause J1.
EN
instruction.
.3 If the instruction will:
a result in an adjustment to the *contract price or
EF
d continue to carry out the *works in accordance with the *contract documents until a
further instruction is received under clause J3.
.4 If the architect instructs the contractor under subclause J1.2, then within 20 *working days the
contractor must give the architect the information requested.
PY
.1 If the architect instructs the contractor to proceed with the *variation, the contractor must do
so *promptly.
.2 If the instruction to proceed confirms that all or part of the quotation for the *variation is not
accepted, the contractor must:
O
a maintain *detailed records of any cost of carrying out the *variation, except for any part
of the *variation for which a quotation has been confirmed as accepted in accordance
with clause J3
C
b maintain *detailed records of the effect on the date for *practical completion, if any, of the
*necessary work to carry out the *variation not covered by an accepted quotation
c notify the architect in writing after completion of all the *necessary work required to
carry out the *variation
E
d submit the detailed *claim to adjust the contract within 20 *working days after giving the
notice in accordance with subclause J4.2c.
C
.3 The details required for a *claim to adjust the contract are stated in clause H2.
.4 *Detailed records are written records maintained by the contractor of the hours worked and all
EN
other costs incurred by the contractor and subcontractors in carrying out the *variation.
.1 If an *authorised person issues an *official document to the contractor which requires a *variation
to the *works, the contractor must notify the architect in writing *promptly after receiving the
EF
*official document. The notification must request an instruction from the architect and provide
a copy of the *official document to the architect.
.1 If the architect receives an *official document from the contractor under clause J6 the architect
must *promptly issue a written instruction to the contractor regarding the *official document.
.2 The architect’s instruction must be an instruction in accordance with subclause J1.2.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 35 Simple Works Contract
K Adjustment of provisional and prime cost sums
K
PY
for:
a a foreseeable item of material or equipment, the precise identity of which was not
known or had not been specified at the date of the contract or,
b an allowance for payment of a fee or charge to a *relevant authority.
.3 The contractor agrees that it has made adequate allowance in the *cost of building work for the
O
scheduled *provisional sums and *prime cost sums including, but not limited to, its
preliminaries, overhead and profit.
.4 The contractor agrees that the contract period contains an adequate allowance of time for any
C
*necessary work to be performed under any *provisional sum or *prime cost sum to the extent
that the *necessary work was reasonably described in the *contract documents at the time that
the contract was executed. E
K2 Architect may instruct regarding *provisional or *prime cost sum
.1 Subject to subclause K2.6, nothing is to be done for which a *provisional sum or a *prime cost
C
sum has been included in the contract except in accordance with an instruction from the
architect.
EN
.2 The architect may instruct the contractor to provide a written quotation for anything for
which a *provisional sum or a *prime cost sum has been included in the contract.
.3 The quotation must be for:
a the direct cost to the contractor of performing the *necessary work
b connection of an *infrastructure service
R
notify the architect in writing if *GST is not applicable to the fee or charge.
.4 Except in relation to payment of a fee or charge to a *relevant authority, if the architect agrees
EF
with the quotation, the architect must issue an instruction to proceed accepting the
quotation.
.5 Except in relation to payment of a fee or charge to a *relevant authority, if the architect:
a does not agree with the quotation or
b has not instructed the contractor to provide a quotation,
R
the architect may instruct the contractor to proceed, in which case the architect must issue a
decision in accordance with clause H4.
.6 The contractor may pay a fee or charge to a *relevant authority for which a *prime cost sum has
been included in the *cost of building work without first receiving an instruction from the
architect.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 36 ABIC SW 2018
Adjustment of provisional and prime cost sums K
K3 Architect may instruct contractor to use particular person for *provisional or *prime
cost sum
.1 Except for payment of a fee or charge to a *relevant authority, the architect may give an
instruction to the contractor for a person other than the contractor to perform work or to
supply or supply and install an item for which a *provisional sum or *prime cost sum has been
included in the *cost of building work.
.2 The architect may only issue an instruction under this clause if the person is identified in
schedule 6 or schedule 7, or the intention to use a particular person whose identity was not
known at the time the contract was executed is shown in schedule 6 or schedule 7.
PY
K4 Adjustment for *provisional or *prime cost sum
.1 The architect must adjust the *cost of building work to take account of any difference between a
*provisional sum or *prime cost sum and:
O
a the accepted quotation,
b the architect’s assessment of a claim under subclause K2.5,
c the amount of a fee or charge to a *relevant authority,
C
as applicable. The architect must adjust the *cost of building work in the next progress
certificate.
.2 If the assessed cost of performance of the *necessary work, connection of an *infrastructure
service, or supply, or supply and installation is more than the *provisional sum or *prime cost
E
sum, the extra cost will be increased by the percentage shown in item 19 of schedule 1 and
added to the *cost of building work.
C
.3 If the assessed cost of performance of the *necessary work, connection of an *infrastructure
service, or supply, or supply and installation is less than the *provisional sum or *prime cost
sum, the difference will be deducted from the *cost of building work.
EN
.4 In relation to a fee or charge paid to a *relevant authority, the architect must adjust the *cost of
building work by deducting, or adding, the net difference between the *prime cost sum and the
actual fee or charge.
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 37 Simple Works Contract
L Adjustment of time
L
L1 Causes of delay which entitle making a claim for adjustment of time with costs
.1 The contractor may make a claim for an adjustment to the date for *practical completion and
*adjustment of time costs in respect of a delay affecting *working days, caused by:
a loss of or damage to the *works, or materials or equipment on the *site that are
intended to be incorporated in the *works, or plant or equipment used on the *site,
provided that loss or damage was not caused by an act or omission of the contractor
b the owner failing to give possession of the *site in accordance with clause F1
c an architect’s instruction
d *relevant authorities, including a private building surveyor, failing to *promptly give
PY
approval for the *works (except when the delay is caused by an act or omission of the
contractor)
e a dispute with a nearby owner or occupier (except one caused by an act or omission of
the contractor)
f the owner’s consultants failing to *promptly provide necessary information which is
O
properly due to the contractor or which the contractor has specifically requested in
writing
g widespread industrial unrest not limited to the *site or to any other sites on which only
C
the contractor or any of its subcontractors is working
h a suspension of the *necessary work under clause Q12
i a breach of this contract by the owner
j an act of prevention by the owner not otherwise covered by this clause.
.2
E
The contractor must take all reasonable steps to minimise the impact of the delay on the
progress of the *works.
C
.3 A claim to adjust the date for *practical completion with or without *adjustment of time costs is
a *claim to adjust the contract.
.4 The requirements for making a *claim to adjust the contract and the procedures to be followed
EN
L2 Causes of delay which entitle making claim for adjustment of time without costs
.1 The contractor may make a claim for an adjustment to the date for *practical completion but
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 38 ABIC SW 2018
Adjustment of time L
L3 Contractor to notify of delay
.1 When progress of the *works is delayed by any of the causes in clause L1 or L2, the contractor
must, within 2 *working days of becoming aware of the start or end of a delay, as the case may
be, notify the architect in writing:
a that the *works are being delayed, and state when the delay began, give a description
of the cause or causes of the delay and give an estimate of the number of *working days
affected and
b that the delay has ended, and state when the delay ended.
.2 Subject to subclause L3.1, delays of less than 2 *working days may be notified in the same
PY
notice.
O
weather conditions that is reasonable, having regard to the time of the year when the
*necessary work is likely to be carried out, and which will disrupt a *critical construction
C
activity. The contractor’s allowance is shown in item 20 of schedule 1.
.2 A *critical construction activity is an activity which is part of the *necessary work that if delayed
will have a direct effect on subsequent activities such that the contractor’s ability to achieve
*practical completion by the date for *practical completion will be affected.
E
L5 Adjustment of provisional allowance for delays
C
.1 The contractor is not entitled to an adjustment of time for any of the causes under clause L4
until the provisional allowance stated in item 20 and 21 of schedule 1 has been exceeded for
that cause.
EN
L6 Overlapping delays
.1 Subject to clauses L4 and L5, when one or more *critical construction activities are delayed by
more than one cause at the same time, the architect must assess any *claim to adjust the
R
a an adjustment of time equal to the time from the commencement of the first occurring
delay to the end of the last overlapping delay, and
b *adjustment of time costs for that part of any delay due to an event described in
EF
clause L1 that is not simultaneous with a delay due to an event described in clause L2.
.3 If one overlapping cause of delay does not further extend the delay resulting from another
overlapping cause, the contractor is entitled to:
a an adjustment of time equal to the period of time from the first occurring overlapping
R
delay and
b *adjustment of time costs for that part of any delay due to an event described in
clause L1 that is not simultaneous with a delay due to an event described in clause L2.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 39 Simple Works Contract
M Completion of the works
M
M1 *Practical completion
.1 The contractor must bring the *works to *practical completion by the date for *practical
completion shown in item 22 of schedule 1 as adjusted in accordance with this contract. The
*works are at *practical completion when, in the reasonable opinion of the architect:
a they are substantially complete and any incomplete work or *defects remaining in the
*works are of a minor nature and number, the completion or rectification of which is
not practicable at that time and will not unreasonably affect occupation and use
b all commissioning tests in relation to the plant and equipment shown in item 28 of
schedule 1 have been carried out successfully and
PY
c any approvals required for occupation have been obtained from the *relevant
authorities and copies of *official documents evidencing the approvals have been
provided to the architect.
.2 Subject to clause M11, the owner takes possession of the *works at 4.00pm on the date the
architect issues the notice of *practical completion.
O
M2 Inspection by the contractor
.1 At least 10 *working days before the date the contractor expects that *practical completion will
C
be reached, the contractor must inspect the *works and prepare a detailed schedule of *defects
and incomplete work and give a copy of the schedule to the architect.
.2 At the same time, the contractor must give the architect a written timetable for the correction
E
of *defects and completion of incomplete work.
incomplete work indicating that each item has been corrected or completed to the
satisfaction of the contractor.
.2 The architect must commence its inspection of the *works *promptly and complete the
inspection within an agreed time or, if none is agreed, within 10 *working days. The architect
must issue a notice or instruction under clause M4, M5 or M6.
R
.3 Within the agreed time for the architect’s inspection, or if none is agreed, within 10 *working
days, the contractor must give the architect any *official documents required for occupation
and evidence that all the commissioning tests shown in item 23 of schedule 1 have been
E
successful.
.1 If the architect decides that the *works have reached *practical completion, the architect must
give written notice of *practical completion to the contractor and to the owner within 5
*working days after completing the inspection. The notice must state the date when *practical
completion was reached.
R
.2 The architect must also notify the owner in writing that security must be released in
accordance with clause C6.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 40 ABIC SW 2018
Completion of the works M
M6 Contractor to bring the *works to *practical completion
.1 If the architect gives notice to the contractor under clause M5, the contractor must *promptly
do whatever is necessary for *practical completion to be reached. The contractor must notify
the architect in writing when it considers the *works have reached *practical completion. The
procedures under clauses M2 to M6 apply until the architect decides that the *works have
reached *practical completion.
PY
notice.
.2 If the architect fails to issue a notice within 5 *working days of the request:
a the contractor may make a *claim to adjust the contract for any loss, expense or damage
that results from the failure of the architect to issue a notice and
O
b the date of *practical completion will be the date identified in the contractor’s notice
made under clause M3 and
c any security must be released in accordance with clauses C6.
C
.3 The requirements for making a *claim to adjust the contract and the procedures to be followed
are stated in section H.
.2 If the owner takes possession of the *works before the architect issues the notice of *practical
completion, the contractor may make a *claim to adjust the contract.
.3 The requirements for making a *claim to adjust the contract and the procedures to be followed
are stated in section H.
R
adjusted, the architect must *promptly notify the contractor and the owner in writing of the
owner’s entitlement to liquidated damages.
EF
.2 Up to 20 *working days after the date of issue of the notice of *practical completion, the owner
may notify the architect in writing whether it will enforce its entitlement to liquidated
damages against the contractor.
.3 The contractor is liable to pay or allow to the owner liquidated damages at the rate shown in
item 24 of schedule 1.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 41 Simple Works Contract
M Completion of the works
M10 Deduction of liquidated damages
.1 If the owner notifies the architect in writing under clause M9, then the architect must:
a notify the contractor of the owner’s decision within one *working day, and
b deduct liquidated damages from the next and subsequent progress certificates, as
applicable.
.2 If, after the architect has issued a certificate in which an allowance for the owner’s
entitlement to liquidated damages has been made, an adjustment is made to the date for
*practical completion, with the result that the owner’s entitlement to liquidated damages is
altered, or the owner has advised that it no longer wishes to enforce its entitlement to
PY
liquidated damages, the architect must make an appropriate adjustment in the next
certificate.
O
after the date of *practical completion, within the agreed time as stated in an instruction or if
no time is stated, within 10 *working days after receiving a written instruction from the
architect to do so.
C
M12 If the contractor fails to correct *defects and finalise work
.1 If the contractor fails to correct a *defect or finalise any incomplete work within the time
E
nominated under clause M11 or fails to show reasonable cause for the failure together with a
timetable for correcting the problem that is acceptable to the architect, the owner may use
another person to correct the problem at the cost of the contractor.
C
.2 If the owner is required to use another person to rectify a problem, the owner is entitled to
make a *claim to adjust the contract in accordance with the procedure stated in clause H2.
EN
.3 If the owner makes a *claim to adjust the contract the architect must *promptly assess the claim
and may issue a certificate under clause N4.
*practical completion of the *works. The owner must give the contractor access to the *site for
the duration of the defects liability period for the purpose of the contractor fulfilling its
obligation under clause M17.
E
.2 The architect may notify the contractor that, in respect of any part of the *works that has
undergone significant correction within the first defects liability period, a further defects
EF
liability period of equal length to the first defects liability period may run for that part. The
notification must be given at the time of acceptance of the corrected work.
instruction from the architect or from the contractor’s own observations of any *defect or
incomplete work during the defects liability period, it must *promptly return to the *site and
correct the *defect or finalise the incomplete work. This obligation continues until the *defect is
corrected or the incomplete work is finalised, and does not come to an end when the defects
liability period is over.
.2 The architect cannot give the first instruction to correct an outstanding *defect or to finalise
any incomplete work after the end of the defects liability period, unless it is for the
N
rectification of a latent *defect and the final certificate has not been issued.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 42 ABIC SW 2018
Payment for the works N
N1 *Contract price
.1 The *contract price, shown in item 4 of schedule 1 is a lump sum and the contractor
represents that the *contract price allows for:
a everything reasonably required in accordance with this contract to complete the *works
b all *provisional sums and *prime cost sums shown in schedule 6 and schedule 7
c installation of any item shown in schedule 8 to be supplied by the owner and installed
by the contractor
d rise and fall
e all statutory taxes and charges applying 5 *working days before the closing of tenders
PY
f import duties and tariffs on imported materials or equipment to be incorporated in or
used in the completion of the *works applying 5 *working days before the closing date
for tenders
g exchange rates applying 5 *working days before the closing date for tenders
h relevant industrial awards and work place agreements, site allowances, building
O
industry superannuation levies and long service leave levies and
i *GST.
.2 The *contract price does not include any item to be supplied and installed by the owner,
C
shown in schedule 8 or specifically identified elsewhere in the *contract documents.
on or after the date in each month shown in item 26 of schedule 1, unless a different date is
agreed in writing between the contractor and the owner. The claim is not a *tax invoice.
.2 The claim must set out the contractor’s valuation of:
a the work completed
b materials and equipment delivered to the *site for incorporation in the *works,
R
.3 The claim must identify any amount of *GST that has been included in the claim. The claim
must be supported by any information shown in item 27 of schedule 1 and a declaration
EF
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 43 Simple Works Contract
N Payment for the works
b the proportion of the *cost of building work claimed, representing the value of the work
completed up to and including the day of the claim, making allowance for the cost of
rectifying *defects, if any
c the proportion of the *cost of building work claimed, representing the value of materials
and equipment delivered to the *site for incorporation in the *works up to and
including the day of the claim, provided title has passed to the contractor
d an allowance for cash retention if clause C2 applies
e any claim by the owner for a set off of monies due under this contract
f the owner’s entitlement to liquidated damages, in accordance with clause M9, since
any previous certificate, calculated up to the date of the certificate
PY
g any other matter to be taken into account in accordance with this contract
h *GST.
.3 The certificate must identify the amount of *GST that has been included and the architect
must give written reasons for any difference between the *cost of building work amount
certified and the (*GST exclusive) amount claimed.
O
.4 If the architect reasonably needs additional information to assess the claim, the architect
must *promptly ask the contractor for it. If that information is needed to assess only part of
the claim, the architect must assess the rest of the claim.
C
N5 *Tax invoice
.1 On receiving a certificate from the architect, the *party to be paid must deliver the certificate
E
to the other *party for payment. If the *party to be paid is registered for *GST, it must, at the
same time, deliver a *tax invoice equal in value to the certificate to the other *party.
C
N6 Certificates – obligation to pay
.1 The amount stated as owing in any certificate must be paid within the period shown in
EN
item 10 of schedule 1 after delivery of the certificate and the *tax invoice (if applicable).
.2 The architect may issue a certificate for payment at any time up until the final certificate is
issued.
.1 Before the owner is obliged to make the first progress payment, the contractor must:
a have in place the security by *unconditional guarantee in accordance with clause C1
b have in place the insurances in accordance with section E unless the owner has taken
E
the certificate within 5 *working days after the date the notice is delivered.
.2 If the architect fails to issue the certificate within 5 *working days after the date the notice is
delivered, the contractor is entitled to payment of the full amount of the progress claim
within 7 calendar days after the date the notice was delivered.
.3 If the owner then fails to pay the full amount of the progress claim in accordance with
subclause N8.2, the contractor may immediately suspend the *necessary work in accordance
with clause Q12.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 44 ABIC SW 2018
Payment for the works N
N9 Contractor entitled to make claim
.1 The contractor is entitled to make a *claim to adjust the contract for any loss, damage or
expense that results from the suspension of the *necessary work under clause Q12.
.2 The requirements for making a *claim to adjust the contract and the procedures to be followed
are stated in section H.
PY
b the contractor has rectified all *defects and finalised all incomplete work it became
aware of by instruction from the architect or from the contractor’s own observations
during the defects liability period and
c the *works have been completed in accordance with this contract.
O
.2 The claim must be supported by any information shown in item 28 of schedule 1 and a
declaration made by the contractor that:
a the contractor has performed its obligations under this contract
C
b all monies due to subcontractors at the date of the declaration have been paid.
.3 The contractor’s final claim must identify any *GST included in the claim.
.4 The contractor must submit a final claim within 20 *working days after receiving a written
request to do so from the architect.
.5
E
If the contractor fails to comply with a written request made under subclause N10.4 the
architect may determine the final claim.
C
.6 After a final claim has been made under subclause N10.1 or is treated as having been made
under subclause N10.5, the contractor is not entitled to make any further claims under this
contract.
EN
architect must, within a reasonable time (not exceeding 10 *business days) after receiving the
final claim (or the additional information if requested) issue to the contractor and to the
E
owner a final certificate setting out the amount due for payment.
.2 The certificate must:
a identify the amount of *GST that has been included
EF
b give written reasons for any difference between the (*GST exclusive) amount certified
and the (*GST exclusive) amount claimed and
c notify the owner of its obligation to release any remaining security under clause C7.
.3 If the contractor fails to give the architect any additional information the architect asks for
R
within a reasonable time, the architect must *promptly assess the claim on the basis of the
information the architect has.
.4 If the engagement of the contractor is terminated under clause Q1, Q2, Q13 or Q14 a
certificate will be issued in accordance with clause Q9 or Q17, as applicable.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 45 Simple Works Contract
N Payment for the works
N13 Final certificate – obligation to pay
.1 The amount stated as owing in the final certificate must be paid within the period shown in
item 10 of schedule 1 after delivery of the certificate and the *tax invoice (if applicable).
PY
N15 Interest on overdue amounts
.1 Each *party must pay interest on any money that it owes the other but fails to pay on time. In
the case of the owner, this includes any delay caused by the failure of the architect to issue a
progress certificate on time.
O
.2 The interest rate is shown in item 28 of schedule 1.
.3 The interest is calculated daily, from the date the money should have been paid. The interest
must be paid on the last day of each month. If interest due on the last day of a month is not
C
paid, it is immediately capitalised and added to the money outstanding.
O
E
O Not used
C
EN
E R
EF
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 46 ABIC SW 2018
Dispute resolution P
P
P2 Compulsory conference
.1 If a dispute or difference between the *parties arises out of or in relation to this contract:
a either *party may deliver a written dispute notice to the other which states what the
dispute is and requires the representatives of the *parties to meet within 5 *working days
after the dispute notice is delivered to make a bona fide attempt to resolve the dispute
PY
or difference.
b if the dispute or difference is not resolved within 5 *working days after the dispute
notice is delivered, representatives of the owner and the contractor with authority to
settle a dispute must meet within 10 *working days after the dispute notice is delivered
and make a bona fide attempt to resolve the dispute or difference.
O
.2 The operation of this clause is not affected by one *party receiving a proposal under clause P3
from the other within 10 *working days after the dispute notice is delivered.
C
P3 Mediation
.1 If the dispute or difference is not resolved within 10 *working days after the dispute notice is
delivered, representatives of the owner and the contractor with authority to settle a dispute
E
may agree, subject to subclause P3.2, to resolve their dispute by mediation.
.2 Mediation is only available if the *parties agree in writing to mediation within 20 *working
C
days after a dispute notice is delivered.
.3 If the *parties fail to comply with subclause P3.2, either *party may begin any legal
proceedings available to it.
EN
.4 After written agreement under clause P3.2 to mediate the dispute or difference, and within
25 *working days after a dispute notice is delivered, representatives of the owner and the
contractor with authority to settle a dispute must agree in writing on the identity of the
mediator or, if not, the *party that issued the dispute notice must request in writing, copied to
the other *party, that the chairperson of the Chapter of the Resolution Institute in the State or
R
the mediator under subclause P3.4, unless the *parties agree in writing to a longer period.
.7 If the mediation has failed to resolve the dispute or difference when the mediator confirms
the mediation is concluded, either *party may begin any legal proceedings available to it.
P4 Legal rights
R
.1 Nothing in this section prevents either *party from taking action at any time to enforce
payment due under a certificate issued in accordance with this contract or to seek urgent
court relief to prevent the detrimental action of the other *party.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 47 Simple Works Contract
Q Termination of engagement
Q
PY
given to the architect.
O
written notice of termination.
.2 The notice of termination must state that it is given under this clause and a copy must be
given to the architect.
C
Q3 Owner may take possession of the *site
.1 If the owner terminates the engagement of the contractor under clause Q1 or Q2 before the
architect has issued the notice of *practical completion:
E
a clause D3 applies as if the architect had issued the notice of *practical completion on the
C
day the owner terminates the engagement of the contractor, and clauses E1 and E2
apply, except that the owner must take out the insurance and
b the owner may take possession of the *site and exclude the contractor from it.
EN
.2 The owner may take possession of any documents, plant, tools, unused materials and
equipment on the *site belonging to the contractor, and may use them in completing the
*works. The owner must make available for collection by the contractor, the items of which it
has taken possession, as soon as it receives the certificate issued under clause Q9. The owner
is not liable for fair wear and tear of anything of which the owner has taken possession.
R
.3 At any time after termination of the contractor’s engagement, the architect may instruct the
contractor to remove all or some of its property from the *site. The contractor must comply
within 10 *working days, failing which the owner may remove the property identified in the
E
architect’s instruction, and dispose of it. The owner must give notice in writing to the
contractor and the architect of the amount the property is disposed for. The owner must pay
EF
the contractor the amount the property is disposed for, less the costs of removal and
disposal.
.1 If the engagement of the contractor has been terminated under clause Q1 or Q2, the
contractor must assign to the owner all of its rights under any subcontract relating to the
supply of labour, services, materials or equipment for the *works if directed to do so by the
architect.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 48 ABIC SW 2018
Termination of engagement Q
Q6 Owner not bound to make any further payment to contractor
.1 If the engagement of the contractor has been terminated under clause Q1 or Q2 the owner
will not be bound to make any further payment to the contractor unless an obligation to pay
arises under clause Q9.
PY
subcontractor or supplier is to be taken into account by the architect in preparing its
certificate under clause Q9, provided the owner has not already paid the contractor for the
same *necessary work, materials or equipment.
O
.1 If the engagement of the contractor has been terminated under clause Q1 or Q2, the architect
must *promptly make a written assessment of the cost to the owner of completing the *works
C
and issue to the contractor and to the owner a copy of that assessment. For this purpose, the
cost to the owner of completing the *works excludes any amount paid by the owner under
clause Q7. That assessment is to be reflected in the certificate made under clause Q9.
E
Q9 Architect to give certificate of amount payable to contractor or owner
.1 If the engagement of the contractor has been terminated under clause Q1 or Q2, and the
C
assessment required under clause Q8 has been made, the architect must *promptly prepare a
certificate as to the amount payable, including *GST, by one *party to the other and issue it to
the contractor and to the owner. That certificate is to be calculated using the following
EN
procedure.
.2 The architect is to determine the amount of the *contract price as adjusted at the date of
termination of the engagement of the contractor.
.3 The architect is to determine the total of:
a the value of building work completed, including *GST, assessed in the last certificate
R
PY
Q11 Contractor may require owner to remedy default
.1 If the owner defaults by:
a failing to make a progress payment on time or
b failing to meet any other substantial obligation under this contract
O
then the contractor may give the owner a written notice stating that:
c it is given under this clause
C
d the owner must rectify the default within 10 *working days after receipt
e if the default is not so rectified, the contractor will be entitled to proceed under
clause Q12 to suspend the *necessary work or subsequently under clause Q13 to
terminate its engagement.
.2
E
The contractor must give a copy of the notice to the architect.
b the owner fails to show reasonable cause why the default cannot be remedied within
time or
c subclause N8.3 applies,
the contractor may immediately suspend the *necessary work by giving the owner written
notice.
R
.2 The notice must state that it is given under this clause. A copy of the notice must be given to
the architect.
E
.3 If, after the suspension of the *necessary work, the owner rectifies the default, the contractor is
entitled to make a *claim to adjust the contract for any loss, expense or damage that results
from the suspension of work.
EF
.4 The requirements for making a *claim to adjust the contract and the procedures to be followed
are stated in section H.
.1 After the contractor has given the owner written notice of suspension under clause Q12, the
contractor may terminate its engagement under this contract by giving the owner written
notice of termination.
.2 The notice must state that it is given under this clause. A copy of the notice must be given to
the architect.
PY
Q17 Architect to give certificate
.1 The architect must *promptly assess any claim made by the contractor under clause Q16 and
must *promptly issue to the contractor and to the owner a certificate specifying the amount
for payment to the contractor or the owner, as the case may be.
.2 If a certificate is issued under this clause, it takes the place of a final certificate under
O
clause N11, and clause C7 applies.
C
.1 On receiving the certificate from the architect, the *party to be paid must deliver the
certificate to the other *party for payment. If the *party to be paid is registered for *GST, it
must, at the same time, deliver a *tax invoice equal in value to the certificate to the other
*party.
E
.2 The amount stated as owing must be paid within the period shown in item 10 of schedule 1
after delivery of the certificate and the *tax invoice.
C
Q19 If this contract is frustrated
EN
.1 If this contract is frustrated at law or the *parties agree that the contract is frustrated, the
contractor is entitled to submit a claim for:
a the value of the *works at the date of frustration, less any progress payments that have
already been made
b the value of any security then held by the owner
R
c the non-recoverable costs the contractor has incurred, or entered into an agreement to
incur, to enable the contractor to complete the *works
d the non-recoverable costs the contractor has incurred or will incur in order to cease the
E
.2 The architect must *promptly assess the claim and issue to the contractor and to the owner a
final certificate specifying the amount for payment. If a final certificate is issued under this
clause, it takes the place of a final certificate under clause N11, and clause C7 applies.
.3 A final certificate issued under this clause must be paid in accordance with clause Q18.
R
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 51 Simple Works Contract
R Miscellaneous
R
R1 Transmission of documents
.1 A *party or the architect may only deliver a document under this contract to the other *party
or the architect by:
a delivering it to the *party or the *party’s representative or the architect by hand or mail
at the address shown in item 1 of schedule 1
b faxing it to the *party or the architect at the fax number shown in item 1 of schedule 1
c emailing it to the *party or the architect or attaching an electronic copy to the email, but
only if the receiving *party or the architect has given an email address in item 1 of
schedule 1, or, the *party or the architect has confirmed in writing that email
PY
communication to the *party or the architect is acceptable for use under this contract.
.2 If the fax numbers, or email addresses of the *party and the *party’s representative are
different, the document must be sent to both the *party’s address and the address of the
*party’s representative.
.3 If a *party or the architect has had 5 *working days written notice from another *party or the
O
architect of a change of postal address, email address, or fax number, a document may then
only be delivered to that *party or the architect at the latest address, email address or fax
number.
C
R2 Time document is received
.1 A document that is hand delivered is to be treated as having been received when it is left at
E
the relevant address.
.2 A document that is sent by mail is to be treated as having been received 3 *working days (7
*working days in the case of overseas mail) after posting.
C
.3 A document sent by fax is to be treated as having been received as soon as the sender
receives an error free transmission report from the correct fax number. If a document is
delivered, or an error free transmission report is received after 5.00pm in the time zone of the
EN
*site the document is to be treated as having been delivered at the beginning of the next
*working day.
.4 A document sent by email is to be treated as having been received when the sender receives
a return email, which is an email in reply or from the recipient’s e-mail system confirming
delivery, or that it has been read. If an email is sent after 5.00pm in the time zone of the *site
R
the email is to be treated as having been delivered at the beginning of the next *working day,
whether or not the return email is received on the day of sending.
E
R3 Assignment
EF
.1 Neither of the *parties may assign any rights under this contract, without obtaining the
other’s consent. That consent may not be unreasonably withheld.
R4 Entire contract
.1 This contract contains everything the owner or the architect has agreed with the contractor in
R
relation to the matters it deals with. Neither *party may rely on an earlier contract, or on
anything else said or done by the other *party (or by an officer, agent or employee of the
other *party) before this contract was entered into.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract For definitions, see pages 54 to 56 Page 52 ABIC SW 2018
Miscellaneous R
R6 Severability
.1 If any clause or part of a clause is illegal, unenforceable or invalid, that clause or part of a
clause is to be treated as removed from this contract and the rest of this contract is not
affected. This does not apply if the clause or part of a clause goes to the heart of the
transaction contemplated by this contract.
R7 Waiver
.1 The fact that a *party or the architect fails to do, or delays in doing, something it is entitled to
do under this contract, does not amount to a waiver of that *party’s or the architect’s right to
PY
do it. Any waiver by a *party or the architect must be in writing. A written waiver is only
effective in relation to the particular obligation or breach in respect of which it is given. It is
not to be taken as an implied waiver of any other obligation or breach, or as an implied
waiver of that obligation or breach in relation to any other occasion.
O
R8 Governing law
.1 This contract is governed by the law of the State or Territory shown in item 29 of schedule 1
and the *parties submit to the non-exclusive jurisdiction of its courts.
C
R9 Compliance with law
.1 Both *parties must comply with *relevant legislation or any order, code, ordinance or *official
E
document of a *relevant authority applicable to the *works and this contract.
architect in writing giving details of the effect on the *works. The architect must *promptly
issue an instruction to the contractor.
.2 The contractor must not advertise its relationship with the owner or its involvement in the
*works without the written permission of the owner, which must not be unreasonably
withheld.
.3 The contractor must ensure that its subcontractors are bound by a clause similar to this
R
clause. The owner’s written permission to the contractor applies to the subcontractors, unless
the owner specifically restricts the permission in writing.
Owner’s initials_________________ © 2018 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 For definitions, see pages 54 to 56 Page 53 Simple Works Contract
S Definitions
S
S1 Definitions
adjustment of time costs includes any loss, expense or damage reasonably incurred by the
contractor that results from a delay due to the causes referred to
in clause L1
authorised person a building inspector or certifier or other person authorised under
*relevant legislation having jurisdiction over the *works
building code means Volumes One and Two of the National Construction Code
as in force as at the date of commencement of the *works
PY
business day any day other than a Saturday, Sunday, or statutory public
holiday in the State or Territory shown in item 35 of schedule 1
claim to adjust the contract a claim made to the architect to adjust the *contract price
(including *adjustment of time costs) or the date for *practical
O
completion or both
contract documents any special conditions shown in schedule 2, the conditions of this
contract, the specifications, the drawings and any other
C
documents shown in schedule 3
contract price see clause N1 E
cost of building work the actual net cost of the *works excluding any amounts for *GST
critical construction activity see clause L4
C
defect or defective work work that is:
a in breach of any of the warranties set out in the *contract
EN
documents
b not in accordance with the standard or quality of building
work specified in the *contract documents
detailed records see clause J4
R
GST goods and services tax levied under the *GST Act
GST Act the A New Tax System (Goods and Services Tax) Act 1999
E
infrastructure service a service to the *site for which there is an alternative source of
supplier, or supply, such as gas, electricity, telecommunications,
EF
Owner’s initials_________________ © 2017 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract Page 54 ABIC SW 2018
Definitions S
e a provisional liquidator, liquidator, receiver, receiver and
manager, administrator, scheme administrator, controller
or other such administrator is appointed (whether by a
court, creditor or otherwise) to the person or over the
person’s assets
f a trustee in bankruptcy, interim receiver, controlling
trustee or other such administrator is appointed (whether
by a court, creditor or otherwise) to the person or over the
person’s assets.
latent condition see clause F5
PY
necessary work all work including any temporary work necessary to complete
the *works
non-working days statutory public holidays and rostered days off and recognised
O
industry shut-down periods in the State or Territory shown in
item 29 of schedule 1
official document see clause B3
C
owner-specified materials all items, materials, fixtures and fittings sourced or supplied and
requested by the owner to be incorporated into the *works
party or parties the owner or the contractor or both, as the case may be
E
PPSR the Personal Property Security Register, or equivalent national
register for security interests in personal property from time to
C
time
practical completion see clause M1
EN
Owner’s initials_________________ © 2017 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
ABIC SW 2018 Page 55 Simple Works Contract
S Definitions
working day Monday to Friday excluding *non-working days
works the completed construction set out in the *contract documents
(briefly described in item 5 of schedule 1).
PY
O
C
E
C
EN
E R
EF
R
Owner’s initials_________________ © 2017 Australian Institute of Architects / Master Builders Australia Ltd Contractor’s initials _________________
Simple Works Contract Page 56 ABIC SW 2018