Topic 10 – OLD COLLECTIONS
1) The size of the letter means the ___ of the letter.
a) thickness
b) height
c) length
d) width
2)
The Aspect ratio (a proportional relationship between width and height)
of Letter and Number is
a) 1:1 Both
b) 1:2 and 1:3 respectively
c) 1:3 and 1:2 respectively
d) 1:4 both
Er. Laxman Baral 2
Topic 10 – OLD COLLECTIONS
3) What is the inclination of inclined lettering?
a) 75 degree
b) 65 degree
c) 45 degree
d) 85 degree
6) The width of the standard A-series drawing paper such as A4, A3, A2... is
a) 1/3 times the length of the paper
b) 1/√2 times the length of the paper
c) 1/2 times the length of the paper
d) 1/√3 times the length of the paper
8) Which of the following lines are used to show that the object is cut and
then viewed?
a) Hidden lines
b) Leader lines
c) Centre lines
d) Hatching Lines
Er. Laxman Baral 5
Topic 10 – OLD COLLECTIONS
9) The hidden line are drawn as
a) dashed narrow lines
b) dashed wide lines
c) long-dashed dotted wide line
d) long-dashed double dotted wide line
20) An ant starts from top rim of the cylinder section of pipe and reaches a
point directly below its starting point after making three complete
revolutions around the pipe. The path traced by ant viewed from top is
a) Helical
b) spiral
c) Circular
d) Straight line
32) A debenture:
a) is a long-term loan
b) Does not require security
c) Is a short-term loan
d) Receives dividend payments
Er. Laxman Baral 17
Topic 10 – OLD COLLECTIONS
33) What is the expression for the sinking fund factor?
a) i / [(1+i)^n - 1]
b) i / [(1+i)^n + 1]
c) 1 / [(1+i)^n - 1]
d) 1 / [(1+i)^n + 1]
36) If ‘a’ is the base amount expenditure, ‘b’ is the increase in the operation
cost each year over a period of’ 'n’ years, the total cost of maintenance is:
a) a + (n + 1) b
b) a + (n - 1) b
c) a × (n - 1) b
d) a - (n - 1) b
Er. Laxman Baral 19
Topic 10 – OLD COLLECTIONS
37) The rate which is used to make future sum in present value is
a) Discount rate
b) Nominal rate
c) Ordinate rate
d) Compound rate
38) What do you call the sum of principle is added to the future worth with
an increasing i% interest rate?
a) simple interest
b) compound interest
c) Effective interest
d) Continuous interest
Er. Laxman Baral 20
Topic 10 – OLD COLLECTIONS
39) SPI (schedule performance index) is the ratio of
a) BCWP/BCWS
b) BCWS/BCWP
c) BCWP/ACWP
d) BCWP-BCWS
40) A property fetches Rs. 9000/- deduction all outgoings. If the rate of
interest is 8% per annum the capitalized value of the property is______
a) Rs. 1,22,500
b) Rs. 1,32,500
c) Rs. 1,34,500
d) Rs. 1,12,500
Er. Laxman Baral 21
Topic 10 – OLD COLLECTIONS
41) The formula of effective annual interest rate "I" is ..... ["r" is the nominal annual
interest rate, and "m" is the number of compounding periods per year]
a) [1-(r/m)]^m + 1
b) [1-(r/m)]^m - 1
c) [1+(r/m)]^m + 1
d) [1+(r/m)]^m - 1
42) What term refers to the actual cost incurred for the work performed by a
company in a project?
a) Earned Value Analysis
b) Planning
c) Cost
d) Actual Cost of Work Performed (ACWP)
Er. Laxman Baral 22
Topic 10 – OLD COLLECTIONS
43) in Resource levelling which of the following is constraint?
a) Time
b) money
c) resources
d) both time and money
48) In PERT analysis, the time estimates of activities and probability of their
occurrence follow
a) Normal distribution curve
b) Poisson's distribution curve
c) Beta distribution curve
d) None of the above
Er. Laxman Baral 25
Topic 10 – OLD COLLECTIONS
49) What is a critical path?
a) It is a path that operates from the starting node to the end node.
b) It is a mixture of all the paths
c) It is the longest path
d) It is the shortest path
52) The technique for establishing and maintaining priorities among the
various jobs of a project, is known
a) Event flow scheduling technique
b) Critical ratio scheduling
c) Slotting technique for scheduling
d) Short interval scheduling
76) There is provision for price adjustment for the project with duration
a) less than 6 months
b) more than 12 months
c) more than 18 months
d) more than 24 months
78) The assessment done by the implementing agency to check the eligibility
of the firm to carry out the contract.
a) Pre-qualification
b) Tender-assessment
c) Post-Qualification
d) Contract assessment
80) What process is often utilized to analyze the potential social effects of a
new infrastructure project?
a) Impact analysis
b) Expert evaluation
c) Preliminary assessment
d) Social impact assessment
Er. Laxman Baral 41
Topic 10 – OLD COLLECTIONS
81) The pessimistic time and optimistic time of completion of an activity are
given as 10 days and 4 days respectively, the standard deviation of the
activity will be
a) 1
b) 6
c) 12
d) 18
90) As per labor law, workers are not allowed to work continuously for more
than .....
a) 3 hours
b) 5 hours
c) 8 hours
d) 12 hours
Er. Laxman Baral 46
Topic 10 – OLD COLLECTIONS
91) What is the punishment for infringement of Copyright for the first time?
a) Imprisonment upto 3 months and fine of Rs.10,000/- to Rs. 1 lacs or both
b) Imprisonment upto 6 months and fine of Rs.10,000/- to Rs. 1 lacs or both
c) Imprisonment upto 6 months and fine of Rs.20,000/- to Rs. 2 lacs or both
d) Imprisonment upto 12 months and fine of Rs.20,000/- to Rs. 2 lacs or both
118)If an engineer violates sub-section 3(b) of NEC act 2055, the punishment
is
a) NRs 2000 fine
b) NRs 3000 fine
c) NRs 10000 fine
d) NRs 25000 fine
Er. Laxman Baral 60
Topic 10 – OLD COLLECTIONS
119) The Minimum time period allocated by GoN for formation of new
council after the dissolution of current NEC like is
a) 3 month
b) 6 month
c) 9 month
d) 1 year