0 Project Schedule for 1x7.3MW WHRPP 284 days Sat 7/21/12 Tue 4/30/13
1 Chettinad Cement Co. Ltd - 1X7.3MW WHRPP at Kallur works 284 days Sat 7/21/12 Tue 4/30/13
2 Site Execution 284 days Sat 7/21/12 Tue 4/30/13
3 Mechanical Erection 284 days Sat 7/21/12 Tue 4/30/13
4 Clinker Cooler Boiler 172 days Thu 10/25/12 Sun 4/14/13
5 WPH, Eco. and EVP section structure erection 45 days Thu 10/25/12 Sat 12/8/12
6 Deduster section upto 26 Mtr elevation 45 days Thu 12/20/12 Sat 2/2/13
7 Platforms and railing upto 30.8 Mtr elevation 20 days Sat 12/15/12 Thu 1/3/13
8 Platforms and railing upto 44.65 Mtr elevation 20 days Fri 1/4/13 Wed 1/23/13
9 HP Super Heater structure erection 7 days Sun 2/3/13 Sat 2/9/13
10 WPH Pressure parts 10 days Sun 12/30/12 Tue 1/8/13
11 HP Eco. Pressure parts 15 days Fri 1/11/13 Fri 1/25/13
12 HP Evaporator Pressure parts 15 days Mon 1/28/13 Mon 2/11/13
13 HP Super Heater Pressure parts 15 days Thu 2/14/13 Thu 2/28/13
14 Steam Drum Erection 5 days Thu 2/14/13 Mon 2/18/13
15 Internal Piping 15 days Sun 3/3/13 Sun 3/17/13
16 Intermediate Duct 10 days Thu 2/21/13 Sat 3/2/13
17 Inlet duct 10 days Tue 12/4/12 Thu 12/13/12
18 Booster Fan Erection 8 days Thu 12/6/12 Thu 12/13/12
19 Outlet Duct 10 days Fri 12/14/12 Sun 12/23/12
20 Internal Hydro test 10 days Sat 3/23/13 Mon 4/1/13
21 Casing patch up for boiler 15 days Fri 3/8/13 Fri 3/22/13
22 CC Boiler Water Draining and Flushing 1 day Tue 4/2/13 Tue 4/2/13
23 CC Boiler Smoke Test 3 days Sat 3/23/13 Mon 3/25/13
24 CC Boiler Alkali Boil Out Test 2 days Tue 3/26/13 Wed 3/27/13
25 CC Boiler Steam Blowing 5 days Sun 3/31/13 Thu 4/4/13
26 CC Boiler Target Plate Clearance 2 days Wed 4/10/13 Thu 4/11/13
27 CC Boiler Safety Valve Floating 1 day Sat 4/13/13 Sat 4/13/13
Page 1 of 8
ID Task Name Duration Start Finish
Page 2 of 8
ID Task Name Duration Start Finish
Page 3 of 8
ID Task Name Duration Start Finish
84 A Frame assembly erection and alignment 20 days Thu 12/20/12 Tue 1/8/13
85 Tube bundle erection 30 days Wed 1/9/13 Thu 2/7/13
86 Manifold erection 5 days Fri 2/8/13 Tue 2/12/13
87 Windwall Erection 25 days Wed 2/13/13 Sat 3/9/13
88 Manifold Welding and Dished End 25 days Wed 2/13/13 Sat 3/9/13
89 Horizontal duct erection 2 days Fri 2/8/13 Sat 2/9/13
90 Air Sealing Plate 10 days Fri 2/8/13 Sun 2/17/13
91 Duct Riser Erection With Bellow 5 days Tue 3/5/13 Sat 3/9/13
92 Clearance for TG alignment from Customer 5 days Thu 2/21/13 Mon 2/25/13
93 transition piece With Pr. Balancing 20 days Sat 2/23/13 Thu 3/14/13
94 Condensate Header and SS Hose Fixing 20 days Tue 2/26/13 Sun 3/17/13
95 CST and Ejector erection after front Clearance from Customer 2 days Fri 3/15/13 Sat 3/16/13
96 CEP & DP Erection after Front Clearance from Customer 3 days Sun 3/17/13 Tue 3/19/13
97 piping with pipe fitting and Valves 15 days Sun 3/17/13 Sun 3/31/13
98 Cladding Sheet Erection 15 days Fri 3/15/13 Fri 3/29/13
99 Fan Ring and Fan Cylinder Erection 20 days Fri 2/8/13 Wed 2/27/13
100 Fan & Gear box and Tip Clearance adjustment 15 days Thu 2/28/13 Thu 3/14/13
101 motor alignment for all pumps & fans 4 days Fri 3/15/13 Mon 3/18/13
102 instrument erection 10 days Fri 3/15/13 Sun 3/24/13
103 leak test 5 days Tue 3/26/13 Sat 3/30/13
104 Commissioning 6 days Sun 3/31/13 Fri 4/5/13
105 Piping 90 days Wed 12/5/12 Mon 3/4/13
106 Auxiliaries Erection & Commissioning 90 days Wed 12/5/12 Mon 3/4/13
107 Turbine & Generator package Erection & Commissioning 89 days Fri 2/1/13 Tue 4/30/13