The document outlines a detailed project schedule for a 1x7.3MW Waste Heat Recovery Power Plant (WHRPP) at Chettinad Cement Co. Ltd, spanning from July 21, 2012, to April 30, 2013. It includes various tasks such as mechanical erection, piping, boiler testing, and commissioning, with specified durations and timelines for each task. The schedule is organized into multiple phases, detailing the execution of different components of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views4 pages

A 2 Sheet

The document outlines a detailed project schedule for a 1x7.3MW Waste Heat Recovery Power Plant (WHRPP) at Chettinad Cement Co. Ltd, spanning from July 21, 2012, to April 30, 2013. It includes various tasks such as mechanical erection, piping, boiler testing, and commissioning, with specified durations and timelines for each task. The schedule is organized into multiple phases, detailing the execution of different components of the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Name Duration Start Finish

0 Project Schedule for 1x7.3MW WHRPP 284 days Sat 7/21/12 Tue 4/30/13
1 Chettinad Cement Co. Ltd - 1X7.3MW WHRPP at Kallur works 284 days Sat 7/21/12 Tue 4/30/13
2 Site Execution 284 days Sat 7/21/12 Tue 4/30/13
3 Mechanical Erection 284 days Sat 7/21/12 Tue 4/30/13
4 Clinker Cooler Boiler 172 days Thu 10/25/12 Sun 4/14/13
5 WPH, Eco. and EVP section structure erection 45 days Thu 10/25/12 Sat 12/8/12
6 Deduster section upto 26 Mtr elevation 45 days Thu 12/20/12 Sat 2/2/13
7 Platforms and railing upto 30.8 Mtr elevation 20 days Sat 12/15/12 Thu 1/3/13
8 Platforms and railing upto 44.65 Mtr elevation 20 days Fri 1/4/13 Wed 1/23/13
9 HP Super Heater structure erection 7 days Sun 2/3/13 Sat 2/9/13
10 WPH Pressure parts 10 days Sun 12/30/12 Tue 1/8/13
11 HP Eco. Pressure parts 15 days Fri 1/11/13 Fri 1/25/13
12 HP Evaporator Pressure parts 15 days Mon 1/28/13 Mon 2/11/13
13 HP Super Heater Pressure parts 15 days Thu 2/14/13 Thu 2/28/13
14 Steam Drum Erection 5 days Thu 2/14/13 Mon 2/18/13
15 Internal Piping 15 days Sun 3/3/13 Sun 3/17/13
16 Intermediate Duct 10 days Thu 2/21/13 Sat 3/2/13
17 Inlet duct 10 days Tue 12/4/12 Thu 12/13/12
18 Booster Fan Erection 8 days Thu 12/6/12 Thu 12/13/12
19 Outlet Duct 10 days Fri 12/14/12 Sun 12/23/12
20 Internal Hydro test 10 days Sat 3/23/13 Mon 4/1/13
21 Casing patch up for boiler 15 days Fri 3/8/13 Fri 3/22/13
22 CC Boiler Water Draining and Flushing 1 day Tue 4/2/13 Tue 4/2/13
23 CC Boiler Smoke Test 3 days Sat 3/23/13 Mon 3/25/13
24 CC Boiler Alkali Boil Out Test 2 days Tue 3/26/13 Wed 3/27/13
25 CC Boiler Steam Blowing 5 days Sun 3/31/13 Thu 4/4/13
26 CC Boiler Target Plate Clearance 2 days Wed 4/10/13 Thu 4/11/13
27 CC Boiler Safety Valve Floating 1 day Sat 4/13/13 Sat 4/13/13

Page 1 of 8
ID Task Name Duration Start Finish

28 Readyness to Provide Steam 1 day Sun 4/14/13 Sun 4/14/13


29 PH-1 Boiler 181 days Sat 7/21/12 Thu 1/17/13
30 Column erection up to 55mtr elevation 20 days Sat 7/21/12 Thu 8/9/12
31 Staircase, Platforms and railing upto 55 Mtr elevation 15 days Sun 8/5/12 Sun 8/19/12
32 HP Economiser Pressure parts 20 days Mon 8/20/12 Sat 9/8/12
33 Column erection 55 to 64.6 elevation 10 days Sun 9/9/12 Tue 9/18/12
34 Staircase, Platforms and railing upto 55 to 64.6Mtr elevation 7 days Sun 9/16/12 Sat 9/22/12
35 HP Evaporator 2 Pressure part 9 days Thu 9/20/12 Fri 9/28/12
36 Column erection 64.6 to 77.5mtr elevation 10 days Sat 9/29/12 Mon 10/8/12
37 Staircase, Platforms and railing upto 64.6 to 77.5Mtr elevation 10 days Sat 10/6/12 Mon 10/15/12
38 HP Evaporator 1 Pressure part 10 days Tue 10/16/12 Thu 10/25/12
39 HP Steam Drum 6 days Fri 10/26/12 Wed 10/31/12
40 Internal Piping 15 days Tue 11/6/12 Tue 11/20/12
41 Inlet Duct 8 days Thu 11/1/12 Thu 11/8/12
42 Outlet Duct 8 days Thu 11/1/12 Thu 11/8/12
43 Bypass Duct 8 days Tue 10/23/12 Tue 10/30/12
44 Internal Hydro test 8 days Wed 11/21/12 Wed 11/28/12
45 Hammering system erection & trials 10 days Wed 11/21/12 Fri 11/30/12
46 Casing patch up for boiler 15 days Mon 11/19/12 Mon 12/3/12
47 PH-1 Boiler Water Draining and Flushing 1 day Thu 11/29/12 Thu 11/29/12
48 PH-1 Boiler Smoke Test 7 days Tue 12/4/12 Mon 12/10/12
49 PH-1 Boiler Alkali Boil Out Test 6 days Tue 12/4/12 Sun 12/9/12
50 PH-1 Boiler Steam Blowing 7 days Thu 12/13/12 Wed 12/19/12
51 PH-1 Boiler Target Plate Clearance 5 days Thu 12/20/12 Mon 12/24/12
52 Hook-up with CC boiler 15 days Tue 12/25/12 Tue 1/8/13
53 PH-1 Boiler Safety Valve Floating 2 days Wed 1/9/13 Thu 1/10/13
54 Readyness to Provide Steam 7 days Fri 1/11/13 Thu 1/17/13
55 PH-2 Boiler 121 days Sat 11/10/12 Sun 3/10/13

Page 2 of 8
ID Task Name Duration Start Finish

56 Column erection up to 55mtr elevation 15 days Sat 11/10/12 Sat 11/24/12


57 Staircase, Platforms and railing upto 55 Mtr elevation 15 days Tue 11/20/12 Tue 12/4/12
58 HP Economiser Pressure parts 15 days Wed 12/5/12 Wed 12/19/12
59 Column erection 55 to 64.6 elevation 10 days Thu 12/20/12 Sat 12/29/12
60 Staircase, Platforms and railing upto 55 to 64.6Mtr elevation 7 days Tue 12/25/12 Mon 12/31/12
61 HP Evaporator 2 Pressure part 10 days Sat 12/29/12 Mon 1/7/13
62 Column erection 64.6 to 77.5mtr elevation 10 days Tue 1/8/13 Thu 1/17/13
63 Staircase, Platforms and railing upto 64.6 to 77.5Mtr elevation 7 days Tue 1/15/13 Mon 1/21/13
64 HP Evaporator 1 Pressure part 10 days Tue 1/22/13 Thu 1/31/13
65 HP Steam Drum 5 days Fri 2/1/13 Tue 2/5/13
66 Internal Piping 15 days Sat 2/9/13 Sat 2/23/13
67 Inlet Duct 10 days Wed 2/6/13 Fri 2/15/13
68 Outlet Duct 8 days Wed 2/6/13 Wed 2/13/13
69 Bypass Duct 10 days Thu 2/14/13 Sat 2/23/13
70 Internal Hydro test 7 days Sun 2/24/13 Sat 3/2/13
71 Hammering system erection & trials 10 days Wed 2/20/13 Fri 3/1/13
72 Casing patch up for boiler 10 days Thu 2/14/13 Sat 2/23/13
73 PH-2 Boiler Water Draining and Flushing 1 day Sun 3/3/13 Sun 3/3/13
74 PH-2 Boiler Smoke Test 2 days Sun 2/24/13 Mon 2/25/13
75 PH-2 Boiler Alkali Boil Out Test 3 days Sun 2/24/13 Tue 2/26/13
76 PH-2 Boiler Steam Blowing 3 days Fri 3/1/13 Sun 3/3/13
77 PH-2 Boiler Target Plate Clearance 3 days Mon 3/4/13 Wed 3/6/13
78 Hook-up with CC boiler 3 days Thu 3/7/13 Sat 3/9/13
79 PH-2 Boiler Safety Valve Floating 1 day Sun 3/10/13 Sun 3/10/13
80 Readyness to Provide Steam 1 day Sun 3/10/13 Sun 3/10/13
81 Air Cooled Condenser Erection & Commissioning 142 days Thu 11/15/12 Fri 4/5/13
82 site mobilization 7 days Thu 11/15/12 Wed 11/21/12
83 Duct/manifold fabrication 25 days Thu 11/22/12 Sun 12/16/12

Page 3 of 8
ID Task Name Duration Start Finish

84 A Frame assembly erection and alignment 20 days Thu 12/20/12 Tue 1/8/13
85 Tube bundle erection 30 days Wed 1/9/13 Thu 2/7/13
86 Manifold erection 5 days Fri 2/8/13 Tue 2/12/13
87 Windwall Erection 25 days Wed 2/13/13 Sat 3/9/13
88 Manifold Welding and Dished End 25 days Wed 2/13/13 Sat 3/9/13
89 Horizontal duct erection 2 days Fri 2/8/13 Sat 2/9/13
90 Air Sealing Plate 10 days Fri 2/8/13 Sun 2/17/13
91 Duct Riser Erection With Bellow 5 days Tue 3/5/13 Sat 3/9/13
92 Clearance for TG alignment from Customer 5 days Thu 2/21/13 Mon 2/25/13
93 transition piece With Pr. Balancing 20 days Sat 2/23/13 Thu 3/14/13
94 Condensate Header and SS Hose Fixing 20 days Tue 2/26/13 Sun 3/17/13
95 CST and Ejector erection after front Clearance from Customer 2 days Fri 3/15/13 Sat 3/16/13
96 CEP & DP Erection after Front Clearance from Customer 3 days Sun 3/17/13 Tue 3/19/13
97 piping with pipe fitting and Valves 15 days Sun 3/17/13 Sun 3/31/13
98 Cladding Sheet Erection 15 days Fri 3/15/13 Fri 3/29/13
99 Fan Ring and Fan Cylinder Erection 20 days Fri 2/8/13 Wed 2/27/13
100 Fan & Gear box and Tip Clearance adjustment 15 days Thu 2/28/13 Thu 3/14/13
101 motor alignment for all pumps & fans 4 days Fri 3/15/13 Mon 3/18/13
102 instrument erection 10 days Fri 3/15/13 Sun 3/24/13
103 leak test 5 days Tue 3/26/13 Sat 3/30/13
104 Commissioning 6 days Sun 3/31/13 Fri 4/5/13
105 Piping 90 days Wed 12/5/12 Mon 3/4/13
106 Auxiliaries Erection & Commissioning 90 days Wed 12/5/12 Mon 3/4/13
107 Turbine & Generator package Erection & Commissioning 89 days Fri 2/1/13 Tue 4/30/13