Generator Room
Generator Room
(Estimate based on Schedule of rate of Megh. PWD(B) for the year 2015-16.)
1/1.1(b) Earthwork in excavation upto a depth of 2m below the existing ground level
for foundation trenches of foundations, footings of column/ walls, retaining
walls, septic tank etc. including bailing out water where necessary and
removal of surplus earth with all lead and lifts as directed and specified for
the following classification of soils
(a) Ordinary soil
Earth work in Foundation-
C1 4 x 1.50 x 1.50 x 1.70 = 15.30 m³
Plinth 2 x 1.50 x 0.40 x 0.50 = 0.60 m³
2 x 2.50 x 0.40 x 0.50 = 1.00 m³
(T) = 16.90 m³
@ ` 179.00 /m³ `
2/4.1 Providing brick soling in foundation and under floor with stone/ best quality
picked jhama brick, sand packed and laid to level and in panel after
preparing the subgrade as directed including all labour and materials and
if necessary dewatering, complete.
© Stone soling of thickness 100mm.
Foundation 4 x 1.50 x ### = 9.00 m2
Room 1 x 4.00 x ### = 12.00 m2
T = 21.00 m2
@ ` 391.00 /m2
3/2.1 Plain cement concrete works with coarse aggregate of sizes 13mm to 32mm
in foundation bed for footing steps, walls, brick works etc. as directed and
specified including dewatering if necessary, and curing complete (shuttering
where necessary shall be measured and paid separately).
(a) In proportion
1:3:6
Footing Column 4 x 1.50 x 1.50 x 0.10 = 0.90 m³
Room 1 x 4.00 x 3.00 x 0.15 = 1.80 m³
T = 2.70 m³
@ ` 6377 /m³ `
4/2.5.1 In Foundation and sub - structure including footing, columns with base, tie and
plinth beam, pile cap, raft slab, base slab, RCC walls, retaining walls, walls of
septic tank, inspection pit and the like and other works not less than 100mm
thick up to Plinth Level.
(Without using admixture, plasticiser)
(b) For M20 Grade concrete or prop 1:1.5:3
Column 4 x 1.50 x 1.50 x 0.20 = 1.80 m³
4 x {( 1.50 x 1.50 ) + ( 0.30 x 0.30 )}x 0.35 = 1.63 m³
2
4 x 1.50 x 0.30 x 0.30 = 0.54 m³
Plinth Beam 2 x 3.70 x 0.25 x 0.30 = 0.56 m³
2 x 2.70 x 0.25 x 0.30 = 0.41 m³
(T) = 4.94 m³
@ ` 8732 /m³ `
5/2.5.3 In Columns, pillars, posts, struts, suspended floor, roof, landing, shelf and
support, balcony, lintel, sill band, beam, girder, bressumer, cantilever, staircase
etc. above plinth level upto 1st floor level.
(Without using admixture, plasticiser)
(b) For M20 Grade concrete or prop 1:1.5:3
Column 4 x 3.30 x 0.30 x 0.30 = 1.19 m³
R.Beam 2 x 3.70 x 0.30 x 0.40 = 0.89 m³
2 x 2.70 x 0.30 x 0.40 = 0.65 m³
Roof slab 1 x 4.90 x 3.90 x 0.12 = 2.29 m³
Lintel 2 x 3.70 x 0.12 x 0.15 = 0.13 m³
2 x 2.70 x 0.12 x 0.15 = 0.10 m³
Display Slab 2 x 1.20 x 1.00 x 0.10 = 0.24 m³
2 x 1.20 x 0.30 x 0.10 = 0.07 m³
(T) = 5.56 m³
@ ` 9273 /m³ `
6/2.10( Providing form work of ordinary timber planking of thickness not less than
a) 25mm and removal of the same for concrete members so as to give a rough
finish including centering, shuttering, strutting and propping etc., for height
of propping and centering of supporting floor to the soffit of the concrete
member not exceeding 4.0M as specified for the following items:
(a) Foundation footing, bases of colum, pile cap, raft and mass concrete
works etc.
Col 4 x 4 x 1.50 x 0.20 = 4.80 m2
. 4 x 4 x ( 0.30 + 1.50 ) x 0.35 = 5.04 m2
2 = 9.84
(T) m2
@ ` 339.00 /m2 `
(b) Sides of tie beams, grade beams etc. at or below ground level requiring
formwork at sides only
Plinth beam 2 x 2 x 3.70 x 0.25 = 3.70 m2
2 x 1 x 3.70 x 0.30 = 2.22 m2
2 x 2 x 2.70 x 0.25 = 2.70 m2
2 x 1 x 2.70 x 0.30 = 1.62 m2
Roof Beams 2 x 1 x 3.70 x 1.10 = 8.14 m2
2 x 1 x 2.70 x 1.10 = 5.94 m2
Lintel 2 x 2 x 3.70 x 0.15 = 2.22 m2
2 x 2 x 2.70 x 0.15 = 1.62 m2
= 28.16 m2
@ ` 432.00 /m2
7/2.10(aProviding form work of ordinary timber planking of thickness not less than
25mm and removal of the same for concrete members so as to give a rough
finish including centering, shuttering, strutting and propping etc., for height
of propping and centering of supporting floor to the soffit of the concrete
member not exceeding 4.0M as specified for the following items:
(c) Columns, Pillars, Posts & Strut
(i) Square, Rectangular, polygonal in plan or any shape like Tee/L etc.
Posthaving plane vertical
= Column 4 facex 4 x 4.80 x 0.30 = 23.04 m2
Display slab 2 x 1 x 1.20 x 1.00 = 2.40 m2
Cutting slab 2 x 1 x 1.20 x 0.30 = 0.72 m2
Roof slab 1 x 4.90 x 3.90 = 19.11 m2
(T) = 45.27 m2
@ ` 582.00 /m2 `
8/2.8(a) Supplying, fitting and fixing in position reinforcement bars upto 1st floor
level, conforming to relevant I.S. Code for R.C.C. work/ R.B. walling including
straightening, cleaning, cutting and bending to proper shapes and length as
per details, supplying and binding with 20G annealed black wire and placing
in position with proper blocks, supports, chairs, spacers etc. complete.
(Rates inclusive of all wastage, lappage, hooks, chairs, anchorage etc. and
no measurements for the same is required)
(a) From primery source like TATA/SAIL/ESSAR/JINDAL/SYAM/RINL
(I) TMT corrosion resistant reinforcement bar
r 2015-16.)
3025.10
8211.00
17217.90
43136.08
51557.88
3335.76
12165.12
26347.14
-69.134
112655.63
14916.14
13965.42
13138.20
43332.92
22455.63
52664.56
32544.11
4320.55
8508.16
3750.69
16342.00
503589.99
15107.70
37769.25
37769.25
5035.90
599272.09
599000.00
Propposed by
Superintendent of Fisheries
Director of Fisheries East Khasi Hills District,Shillong.
Meghalaya,Shillong.
6/2.10(a) Providing form work of ordinary timber planking of thickness not less than 2
as to give a rough finish including centering, shuttering, strutting and propp
supporting
(a) floor to thefootings,
Foundation, soffit of the concrete
bases member
of columns, pilenot exceeding
cap, 4.0M co
raft and mass as
Footing 4 x 4
6 x 4
6 x 4
@ ` 421.00 /m2
s not less than 25mm and removal of the same for concrete members so
utting and propping etc., for height of propping and centering of
xceeding 4.0M concrete
raft and mass as specified for etc.
works the following items:
x 1.50 x 0.10
x 1.50 x 0.30
x 0.35 x 1.30
CONSTRUCTION OF GENERATOR ROOM FOR MAHASEER BROOD STOCK
(Estimate based on Schedule of rate of Megh. PWD(B) for the year 2021 -22.)
1/2.1 Earthwork in excavation by manual means up to a depth of 2m below the
existing ground level for foundation trenches of foundations, footings of
column/ walls, retaining walls, septic tank etc. including bailing out water
where necessary and removal of surplus earth with all lead and lifts as
directed and specified for the following classification of soils.
Qty.
(b) In all kinds of soil
Earth work in Foundation-
C1 4 x 1.50 x 1.50 x 1.70 = 15.30 m³
Plinth 2 x 1.50 x 0.40 x 0.50 = 0.60 m³
2 x 2.50 x 0.40 x 0.50 = 1.00 m³
(T) = 16.90 m³
@ Rs 213.00 /m³ ₹ 3,599.70
2/12.5 Providing soling with stone/ best quality picked jhama brick, sand packed
and laid to level and in panel after preparing the subgrade as directed
including all labour and materials and if necessary dewatering, complete.
Steel/Metal Works
Qty as item Above 11/11.2 = 5.40 m2 x 0.66 = 3.56 m2
Qty as item Above 12/11.7 = 8.51 m2 x 2.50 = 21.28 m2
Total = 24.84 m2
@ Rs 116.00 /m2 ₹ 2,881.32
T ###
Say ###
(Estimate based on Schedule of rate of Megh. PWD(B) for the year 2015-16.)
1st Measurement
1/1.1(b) Earthwork in excavation upto a depth of 2m below the existing ground
level for foundation trenches of foundations, footings of column/ walls,
retaining walls, septic tank etc. including bailing out water where necessary
and removal of surplus earth with all lead and lifts as directed and specified
for the following classification of soils
(a) Ordinary soil
Earth work in Foundation-
C1 6 x 1.30 x 1.30 x 1.50 = 15.21 m³
Plinth 7 x 2.25 x 0.30 x 0.30 = 1.42 m³
Verandah 1 x 5.25 x 0.30 x 0.30 = 0.47 m³
2 x 0.90 x 0.30 x 0.30 = 0.16 m³
(T) = 17.26 m³
@ ` 179.00 /m³ ` 3089.54
2/4.1 Providing brick soling in foundation and under floor with stone/ best quality
picked jhama brick, sand packed and laid to level and in panel after
preparing the subgrade as directed including all labour and materials and
if necessary dewatering, complete.
© Stone soling of thickness 100mm.
Foundation 6 x 1.30 x ### = 10.14 m2
@ ` 378.00 /m2 3832.92
3/2.1 Plain cement concrete works with coarse aggregate of sizes 13mm to
32mm in foundation bed for footing steps, walls, brick works etc. as
directed and specified including dewatering if necessary, and curing
complete (shuttering where necessary shall be measured and paid
separately).
(a) In proportion
1:3:6
Footing Column 6 x 1.30 x 1.30 x 0.12 = 1.22 m³
@ ` 6141 /m³ 7492.02
4/2.8(a) Supplying, fitting and fixing in position reinforcement bars upto 1st floor
level, conforming to relevant I.S. Code for R.C.C. work/ R.B. walling
including straightening, cleaning, cutting and bending to proper shapes and
length as per details, supplying and binding with 20G annealed black wire
and placing in position with proper blocks, supports, chairs, spacers etc.
complete. (Rates inclusive of all wastage, lappage, hooks, chairs,
anchorage etc. and no measurements for the same is required)
(a) From Primary Sources like TATA/ SAIL/ ESSAR/ JINDAL/ SHYAM/ RINL
(i) TMT Corrosion resistant steel (CRS) reinforcement bar
Foot base 12mm dia dis bar @ 150 mm c/c bothways
6 x 22 x 1.50 x 0.89 = ### kg
Column 4-16 mm dia main bar
6 x 4 x 6.05 x 1.58 = ### kg
Lateral ti6mm dia stirrup @120 mm c/c
6 x 42 x 1.10 x 0.22 = 60.984 kg
Plinth Beam 4-12 mm dia bars
3 x 4 x 3.15 x 0.89 = 33.642 kg
2 x 4 x 5.65 x 0.89 = 40.228 kg
Stirrups: 6mm dia spacing @120 mm c/c
3 x 19 x 1.10 x 0.22 = 13.794 kg
4 x 19 x 1.10 x 0.22 = 18.392 kg
T = ### kg
or 5.727 Qtl
@ ` ### /Qtl ###
5/2.10( Providing form work of ordinary timber planking of thickness not less than
a) 25mm and removal of the same for concrete members so as to give a
rough finish including centering, shuttering, strutting and propping etc., for
height of propping and centering of supporting floor to the soffit of the
concrete member not exceeding 4.0M as specified for the following items:
(b) Sides of tie beams, grade beams etc. at or below ground level
requiring formwork at sides only
Plinth beam 3 x 2 x 2.80 x 0.30 = 5.04 m2
2 x 2 x 5.25 x 0.30 = 6.30 m2
= 11.340 m2
@ ` 421.00 /m2 4774.14
3/2.5 Providing and laying Concrete in Reinforced Cement Concrete Works using
Concrete Mixture Machine with coarse sand & 20mm down graded stone
aggregate including dewatering if necessary, and curing complete but
excluding cost of form work and reinforcement for reinforced cement
concrete work (form work and reinforcement will be measured and paid
separately)
2.5.1 In Foundation and sub - structure including footing, columns with base,
tie and plinth beam, pile cap, raft slab, base slab, RCC walls, retaining
walls, walls of septic tank, inspection pit and the like and other works
not less than 100mm thick up to Plinth Level.
(T) = m2
@ ` 568.00 /m2 `
8/2.8(a) Supplying, fitting and fixing in position reinforcement bars upto 1st floor
level, conforming to relevant I.S. Code for R.C.C. work/ R.B. walling
including straightening, cleaning, cutting and bending to proper shapes and
length as per details, supplying and binding with 20G annealed black wire
and placing in position with proper blocks, supports, chairs, spacers etc.
complete. (Rates inclusive of all wastage, lappage, hooks, chairs,
anchorage etc. and no measurements for the same is required)
(a) From Primary Sources like TATA/ SAIL/ ESSAR/ JINDAL/ SHYAM/ RINL
(i) TMT Corrosion resistant steel (CRS) reinforcement bar
dep
dep
dep
dep
dep
dep
dep
1st. Advance ` 2,10,500.00
Expenditure on Materials
CONSTRUCTION OF A FISH RETAIL OUTLET AT FISH DALE FARM EAST KHASI HILLS
DISTRICT, MEGHALAYA,SHILLONG
Junior - Engineer
Directorate of Fisheries
Meghalaya,Shillong
2nd. Advance
Expenditure on Materials
CONSTRUCTION OF A FISH RETAIL OUTLET AT FISH DALE FARM EAST KHASI HILLS
DISTRICT, MEGHALAYA,SHILLONG
Junior - Engineer
Directorate of Fisheries
Meghalaya,Shillong
40200.00
STATEMENT SHOWING THE UTILISATION REPORT FOR CONSTRUCTION OF A FISH RETAIL
OUTLET AT FISH DALE FARM EAST KHASI HILLS DISTRICT, MEGHALAYA,SHILLONG UNDER
BLUE REVOLUTION FOR THE YEAR 2016-2017
Junior - Engineer
Directorate of Fisheries
Meghalaya,Shillong
0.00
Expenditure on Materials
CONSTRUCTION OF A FISH RETAIL OUTLET AT FISH DALE FARM EAST KHASI HILLS
DISTRICT, MEGHALAYA,SHILLONG
Junior - Engineer
Directorate of Fisheries
Meghalaya,Shillong
STATEMENT SHOWING THE UTILISATION REPORT FOR CONSTRUCTION OF A FISH RETAIL
OUTLET AT FISH DALE FARM EAST KHASI HILLS DISTRICT, MEGHALAYA,SHILLONG UNDER
BLUE REVOLUTION FOR THE YEAR 2016-2017
GENERAL ABSTRACT